The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014

Transcript of The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street...

Page 1: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

City of North BendPavement Management Plan

&Street Utility Fee Analysis

February 11, 2014

Page 2: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Pavement Management PlanObjectives

• Review and Reassess Street Surface Conditions Previously Rated as “Good” or “Below” for Asphalt Streets and added Assessments for Concrete Streets

• Total Length of 29 Miles• Update Cost Estimates for Repair; 166 Asphalt

Street Segments, 45 Concrete Street Segments, and Added 4.05 Miles of Gravel Streets

• Develop 5 Year Capital Improvement Plan (CIP)• Provide Report & Electronic Data (Cost

Spreadsheet) to Supplement City’s current Pavement Management Plan.

Page 3: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Roadway Assessment

Page 4: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Repair Methods

• Crack Sealing – Tar or Epoxy Based, Normally associated with other repair methods, may be used on Asphalt & Concrete Streets in “Very Good” & “Excellent” Condition. Life Expectancy is up to 3 Years.

• Slurry Seal – Fine Aggregate, Asphalt Emulsion, Water, Mineral Filler. Used to prevent Raveling, Seal Minor Cracks and improve Surface Friction. Life Expectancy is 3 to 5 years.

• Chip Seal – Asphalt Base with Aggregate cover. Used to Water Proof Surface, Minor Crack Sealing and Surface Friction. Life Expectancy is 3 to 6 Years.

Page 5: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Repair Methods (Continued)

• Overlay – Heated Mixture Mineral Aggregate and Asphalt Cement, Enhance Smoothness, Profile Roadway, Increase Surface Friction. Life Expectancy is 10 to 12 Years.

• Reconstruction – Removal of Pavement Surface and Subgrade. New Gravel Base and Asphalt Cement. Provides New Street Condition. Life Expectancy is 20 to 25 Years.

Note: Life Expectancy may Vary due to Traffic Volumes, Type of Vehicles, and Existing Pavement Conditions

Page 6: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Typical Pavement Repair Locations

• Crack Seal – Streets rated “Very Good” to “Excellent” (Not Reviewed). Used with all other Repair Methods except Reconstruction

• Slurry Seal – Low Volume Residential Streets with Minimal Cracking or Higher Volume Streets with no Cracks

• Chip Seal – Low and Medium Volume Streets with Increased Cracking. Higher Volume Roads with Less Cracking

• Overlays – Medium to High Volume Roads with Medium to Severe Cracking.

• Reconstruction – Failed Pavement for all Street Classifications

Page 7: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Sample Street Repair - Crack Seal/Overlay

Sheridan Street (Ohio to Maryland)

Page 8: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Sample Street Repair - Slurry Seal

13th Street (Marion to Everett)

Page 9: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Sample Street Repair - Chip Seal

State Street (Chester to Brussels)

Page 10: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Sample Street Repair - Overlay

Marion Street (13th to 14th)

Page 11: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Sample Street Repair - Reconstruction

Connecticut Street (Grant to Hayes)

Page 12: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Street Condition Map

Page 13: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Capital Improvement Costs

• Cost Include Construction Costs Contingency (10%) Engineering (18%) Legal/Admin (1.5%). Other Required Utility work not Included.

Page 14: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Capital Improvement Costs (Continued)

• Asphalt Streets - $10,900,700

• Concrete Streets - $2,891,700

• Gravel Streets - $2,707,600

• Total Costs - $ 16,500,00

Page 15: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

5 Year Capital Improvement Plan

• Priority for Street Repairs should be Based on Volume and Condition

• 2015 through 2019 - $3,300,00/Year

Page 16: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Questions / Comments

Page 17: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Street Utility Fee Analysis

Page 18: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Purpose & Terms

• Eligible Maintenance Expenses (EME), defined as the following activities within the City’s easements and right-of-ways: patching, crack sealing, seal coating, overlaying, curb repair/replacement, and related activities in order that local streets and facilities be properly maintained

• Maintenance funded under this program shall exclude storm drainage improvements and maintenance: street lighting power costs, and landscape enhancements

• Determination of Transportation Equivalent Dwelling Units (EDUs) via Institute of Transportation Engineers (ITE)

Page 19: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Projected North Bend Transportation EDUs

Class of Current 2014 2015 2016 2017 % of

Transportation Generator EDUs EDUs EDUs EDUs EDUs 2017

Residential 3880 3899 3919 938 3958 23%

Commercial 10692 10735 10778 10821 10864 63%

Institutional 2462 2467 2472 2477 2482 14%

Total Non-Residential 13154 13202 13250 13298 13346 77%

Total EDUs 17034 17101 17168 17236 17304 100%

Page 20: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Projected Project Costs & Payment Requirements

Annual Payments Required for 20 and 30 year Funding

PrincipalPeriod

Yrs.Interest

% Annual Payment

$16,500,000 20 3.5 $1,160,958

$16,500,000 30 3.5 $897,127

Page 21: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Funding Options

• Urban Renewal Funds (URF)

• State Turnback Program (STP)

• Street Utility Fee (SUF) Note: Gas Tax not considered for this Analysis

Page 22: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Annual Revenue Required From SUF Program

Revenue Required from Street Utility Fee Program

Costs 20 YR Value 30 YR Value

Annual Local Street Maintenance Cost $928,766 $717,702

Annual Collector Street Maintenance Cost $150,925 $116,627

Annual Arterial Road Maintenance Cost $81,267 $62,799

Total Projected Annual Costs $1,160,958 $897,127

Revenue Source    

STEP Revenue Sharing $100,000 $100,000

Urban Renewal $230,000 $230,000

Total Projected Revenues $330,000 $330,000

Gap Which May be Collected by SUF $830,958 $567,127

Page 23: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Alternative Fee Methods

• Uniform Assessment

• Residential/Non-Residential Ratio Funding of Local/Collector/Arterial Streets Assessment

• Flat Fee Assessment

Page 24: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

SUF Funding Alternatives – 20 Year Funding

    Revenue Number of   Mon Rates per EDU for

Alt No. Method Required Res. EDUs Non Res EDUs Res. Non-Res.

1 Uniform Assessment $830,958 3,958 13,346 $4.00 $4.00

2 Residential/Non-Res Assessment          

  Local Streets $664,766 3,958   $14.00 $0.00

  For Res. 50% Collector Streets $54,012 3,958 $1.14 $0.00

  For Non-Res. 50% Coll. Streets $54,012   13,346 $0.00 $0.34

  Arterial Streets $58,167   13,346 $0.00 $0.36

  Totals $830,958     $15.13 $0.70

3 Flat Fee Assessment $830,958 3,958 314 $16.21 $16.21

Page 25: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

SUF Funding Alternatives – 30 Year Funding

    Revenue Number of   Mon Rates per EDU for

Alt No. Method Required Res. EDUs Non Res EDUs Res. Non-Res.

1 Uniform Assessment $567,127 3,958 13,346 $2.73 $2.73

2 Residential/Non-Res Assessment          

  Local Streets $453,702 3,958   $9.55 $0.00

  For Res. 50% Collector Streets $36,863 3,958 $0.78 $0.00

  For Non-Res. 50% Coll. Streets $36,863   13,346 $0.00 $0.23

  Arterial Streets $39,699   13,346 $0.00 $0.25

  Totals $567,127     $10.33 $0.48

3 Flat Fee Assessment $567,127 3,958 314 $11.06 $11.06

Page 26: The Dyer Partnership Engineers and Planners City of North Bend Pavement Management Plan & Street Utility Fee Analysis February 11, 2014.

The Dyer Partnership Engineers and Planners

Questions/Comments