The Design of an Independent Calibration Facility and its Commissioning … · 2016-04-11 · The...
Transcript of The Design of an Independent Calibration Facility and its Commissioning … · 2016-04-11 · The...
The Design of an Independent Calibration Facility and its
Commissioning Using a Multi-path USM
Tom Ballard GE
T. Cousins CEESI
Introduction
• Introduction: Discussion about the need for good calibration for liquid meters.
• Description of calibration facility
• Description of operation of GE 4 path meter
• Calibration of the Turbine Master meters and USM
• Discussion of things that can go wrong and did with the calibration laboratory –valves, software etc.
• Show how we used the third party meter to help detect the issues, got some great graphs showing the issues.
• Conclusions
Is Measurement Less Important at $30/barrel?
• In absolute terms the losses are of less value!!
• But look at the effect on profit!!!
Price/barrel $ Production Cos/Barrelt $ Margin $
0.2% Uncertainty
on Basic
Volume/barrel
Error in
Margin %
100 20 80 0.2 0.25
30 20 10 0.06 0.6
Reynolds Number
• Many manufacturers calibrate their meters on water. • Water is a much easier process fluid to produce calibration facilities resulting
in cheaper calibration of meters.
• Very little thought has been given to the fact that many meters are not linear over their operational range: • Particularly with regard to Reynolds number
• Water calibrations do not represent the true nature of the meter performance on site, particularly if the fluid is oil.
• Constructing and operating oil facilities that can really simulate the Reynolds number operation on site is expensive.
• Note all meters are controlled by Reynolds Number!!
Reynolds Number-Water Vs Oil Calibration
Effect of Incorrectly Calibrated Meters
• The major results of not calibrating meters correctly • Are potentially large, in terms of uncertainty, errors in installed meters.
• Even with on site proving the results can be confusing and wrong.
• Water calibration can lead to corrections using extrapolation.
• It has taken many years to understand that many Coriolis meter designs are effected by Reynolds number, largely due to the lack of appropriate independent calibration
Linearisation/Data Fitting
• Meters that are often assumed to be linear throughout their range because a theory shows them to be independent of any issues: • it is only when independent testing is carried out that eventually this is often
found not to be true.
• The “black box” concept is used to hide the extent of the non-linearity.
• Both can lead to the customer/user, having a false view of the meter performance, • At the extreme incurring large uncertainties that he is not including in his
overall uncertainty budget: • Hence affecting his metering balances. • And even profitability.
Flowrate (Velocity) Vs Reynolds Number Calibration-Coriolis Meter
Calibration Difference using Low viscosity Fluid to calibrate and Fitting with a Polynomial Equation
Actual Calibration
4th Power Polynomial based on low viscosity fluid calibration.
Flow meter for Commissioning Facility
• Why do we need a “Check meter” for Commissioning? • It is needed so be able to determine the viability of operation of the facility. • It is needed to confirm the reproducibility of all the facility operations
• The proving • Master metering of all variations
• It is needed as a consistent standard for calibration.
• What are the attributes needed? • Large flow range • Consistent operation • Reproducible calibration (trustworthy)
• We chose a USM because: • We new the expected performance. • Low pressure drop. • Large Flow range • Free!!!
Design of USM
• The standard 4 path method is to use the Gaussian distribution.
• The different solutions give a non-linear calibration curve that has to be corrected.
• The GE design uses a combination of: • A theoretical solution using basic aerodynamics.
• Optimized by experiment.
Optimized Chord Locations
• Optimizations were made in the design to overcome limitations of Gaussian quadrature methods
• Development approach using symmetrical simulation methods of flow profiles • Reduced dependence on Reynolds through profile variations
Single K Factor Equation:
Modeled by Chord Location vs. Reynolds:
USM Design
Focus on factors for Linearity
• 4 Path Configuration
• Chord Placement – GE uses optimized locations (patented)
• Chord Weight Factors – empirical test
• Reproducible Cast Body – no welds
• Small Port sizes = less port effects
• Slight Taper Bore
• Simplified, Stable Electronics
Oil Calibration Facilioty Design
CEESI Multi-Viscosity calibration facility
Heat Exchanger
Specification • It uses known and proven measurement methods-9 months from design to first accreditation.
• ISO 17025
• Sealed System with pressure stabilization.
• Size range – 1”-12” Full flow – Two Systems.
• Base calibration – 20” Bi Directional Prover/1300Cum/h capacity SVP/Master meters.
• Master Meters – 3 Helical bladed turbine meters used: • Single meter mode. • Two meter mode • Three meter mode
• Flow Rate – 2-3000 Cum/h.
• Viscosity Range – 1.5-200cS (API 25-45).
• Reynolds Number Range – 300 – 1,200,000.
• Uncertainty range: 0.015%-0.05% depending on base calibration method.
• Temperature stability – 0.2 Deg. C.
Commissioning
• The facility has to be checked in all its modes: • Over the full viscosity range.
• Against the prover
• Against a single master meter ( all three meters)
• Multiple Master meters.
• Repeatability with Prover
• Repeatability with master meters
Calibration of the Master meters
Calibration of the MUT (USM)
Valves (Bloody valves!!!)
• One of the biggest issues during the commissioning was valve leakage: • New Double Block and Bleed Valves leaking.
• Valve damage by swarf.
• 4 Way Prover valve not set up correctly
Leaking MUT Valve
Original calibration curve
Leaking 4 way valve calibration curve
Leaking 4 Way Prover Valves
Software (Bloody Software!!)
The original software initial tests showed good agreement with the prover tests – then some software changes and the calibration changed. It turned out to be MF calculation used flowrate before corrected for MM Reynolds number.
Master Meter Tests after Software Correction
Conclusions
• There is a need to calibrate meters with linearity issues with Reynolds number over as close a range to that in operation
• CEESI have built a multi-viscosity to try to achieve this goal for many oil applications.
• A GE 10” USM was used as a commissioning tool to help setup the flow laboratory. • The wide range and low pressure drop made it a good choice for commissioning. • It worked efficiently as a check meter • It showed clearly when the system had leaks • It allowed us to check the full prover and master meter performance. • It allowed us to confirm the master meter operation, particularly for improved
repeatability when calibrating less repeatable meters.