The Contemporary Language of Risk Analysis AFC Theme 2 Risk Technology Workshops.
-
Upload
shanon-kelley -
Category
Documents
-
view
215 -
download
0
Transcript of The Contemporary Language of Risk Analysis AFC Theme 2 Risk Technology Workshops.
The Contemporary Language of Risk Analysis
AFC Theme 2Risk Technology Workshops
AFC Theme 2Risk Technology Workshops
• We have been doing risk assessment for flood for a long time– EAD is a risk assessment metric
• Major rehab program requiring reliability analysis developed in 1992
• These focused on economic risks and expected values and deemphasize uncertainty
Risk is not new to Corps
What is New?
• Risk analysis as comprehensive approach
• Risk management is not just projects
• Risk is more than economics and expected values
• Uncertainty explicitly recognized in analysis and decisions
• Collaborative risk management may mean the Corps is not in charge
Risk Language
• Risk terms tend to be redefined by each discipline to meet their narrow usage
• If we are to communicate risk to stakeholders and the public we need to be able to communicate among ourselves
• The Corps needs to standardize its risk terminology
Language is Important
• When federal officials repeatedly refer to "100 year" floods and levees designed to protect against them, they mislead people into thinking that such storms are once-in-a-lifetime events. Whatever statistical validity these terms ever had, they no longer serve the public, and the government would do better to drop them. USA Today, 8 July
Risk
• The likelihood and severity of adverse outcomes
Risk of 1 or More Damaging Floods in 75 Years
1.00
0.53
0.14
0.00-
0.20
0.40
0.60
0.80
1.00
1.20
No Protection 100-yr 500-yr Permanent Evacuation
Protection Level10-Year Flood Plain
Pro
abil
ity
Speculative Risk
• A category of risk that, when undertaken, results in an uncertain degree of gain or loss
Distribution of Net Benefits
MeanNBA
Plan A
0 MeanNBB
Net Benefits
Plan B
How to Characterize A and B
• Plan A has lower expected benefits but greater certainty than Plan B
• Plan A has much smaller chance of economic failure than Plan B
• Plan B has much larger chance of big economic payoffs than Plan A
Risk-cost Tradeoffwith Uncertainty
0 100 200 300 400 5000
50
100
150
Habitat Units Restored
Res
tora
tion
Co
sts
Uncertainty
• When there exists a constant or knowable fact unknown by us.– lack of knowledge regarding the true value of a
quantity
Risk Analysis
• Risk analysis is a decision-making framework that comprises three tasks: risk assessment, risk management, and risk communication.
Risk Management
• Policy and preference based
Risk Assessment
• Analytically based
Risk Communication
•Interactive exchange of information, opinions, and preferences concerning risks
Residual Risk
• Risk remaining after a risk management measure has been implemented.
We do not do a good job of communicating residual risk.
Safety
Safety is a subjective concept, whereas risk is more objectively assessed. It is impossible to achieve complete safety.
“Texas Chicken”
Tolerable RiskIn
crea
sing
Ind
ivid
ual r
isks
and
soc
ieta
l con
cern
s
UnacceptableRegion
TolerableRegion
Broadly acceptableRegion
Risk cannot be justifiedexcept in extraordinary
circumstances
People and society are prepared to accept risk in
order to secure benefits
Risk regarded as insignificant, further effort
to reduce risk not required
To learn more about Actions for Change visit us on the web at
https://maps.crrel.usace.army.mil/AFC/
Questions?