The coal future capital and fuel cycle energy costs of a ... · TABLEAContinued FOOTNOTES:...
Transcript of The coal future capital and fuel cycle energy costs of a ... · TABLEAContinued FOOTNOTES:...
Digitized by the Internet Archive
in 2012 with funding from
University of Illinois Urbana-Champaign
http://archive.org/details/coalfuturecapita163rieb
NOTICE: Return or renew all Library Materialsl The Minimum Fee tor
each Lost Book is $50.00. JIIN 9 7 1Q0QThe person charging this material (s rfe^ffisible for
its return to the library from which it was withdrawn
on or before the Latest Date stamped below.
Theft, mu|mfo^rifcr«i.md of books are reasons for discipli-
nary actio^rgjWaHplulTo renew can Telepnone Center,
sj*l from the University.
UNIVERSITY OF ILLINOIS LIBRARY AT URBANA-CHAMPAIGN
L161—O-1096
INFERENCE ROOM
Appendix B
CAC Document No. 163
Final Report
The Coal Future: Economic and TechnologicalAnalysis of Initiatives and Innovations to
Secure Fuel Supply Independence
by
Michael RieberCenter for Advanced Computation
University of Illinois at Urbana-Champaign
and
Shao Lee SooJames Stukel
College of EngineeringUniversity of Illinois at Urbana-Champaign
AdvisorJack Simon, Chief
Illinois State Geological Survey
Center for Advanced ComputationUniversity of Illinois at Urbana-Champaign
Urbana, Illinois 61801
May 1975
This work was supported by the National Science Foundation(RANN) , NSF Grant No. GI-35821 (A) 1
.
Any opinions, findings, conclusions or recommendations
expressed in this publication are those of the author(s) and do not
necessarily reflect the views of the National Science Foundation.
THE COAL FUTURE
APPENDIX B
Capital and Fuel Cycle Energy Costs
of a 1,000 MWe Nuclear Reactor
Contents
CAC Technical Memorandum No. 50
and
CAC Technical Memorandum No. 51
CAC Technical Memorandum No. 50
INPUT-OUTPUT
CALCULATION OF FUEL CYCLE ENERGY
COSTS FOR THE AVERAGE
NUCLEAR POWER PLANT
by
Peter PennerResearch Assistant
Center for Advanced ComputationUniversity of Illinois at Urbana-Champaign
Urbana, Illinois 61801
April 1975
This work was supported by the National Science Foundation (RANN)
,
NSF Grant GI 35821(A)!.
CAC Technical Memorandum No. 50
INPUT-OUTPUTCALCULATION OF FUEL CYCLE ENERGY
COSTS FOR THE AVERAGENUCLEAR POWER PLANT
I . INTRODUCTION
This memo calculates the energy costs of mining, pre-
paring, reprocessing, and disposing of fuel for an average
1000 MWe nuclear power plant. This model plant is assumed to
average one boiling water reactor (BWR) and two pressurized
water reactors (PWR) . It is assumed that the reactor operates
with the following characteristics:
Average load factor: 65%
Burnup rate (fuel efficiency): 30,000 MW(t)D/MTU
Efficiency (elec. gen.): 33.5%
II. METHODOLOGY - COST COMPONENTS
Fuel cycle costs are calculated in detail in Reference 1
These costs represent annual average expenses per kilowatt-hour
over the thirty-year lifespan of the plant. Certain costs, such
as perpetual storage and diffusion plant tails disposal, are not
included in this accounting. Certain other costs are included in
the economic calculation but are not considered for their energy
costs.
Ill, METHODOLOGY - ENERGY ACCOUNTING
We use Input-Output analysis as an energy accounting
method to find the energy costs associated with economic costs.
The basic document concerning energy Input-Output analysis is
Reference 4. The main result of the analysis is the 1-0 coeffi-
cient, which is the energy cost per dollar spent on any given
good or service. For example, the energy cost of ten dollars'
worth of uranium mining can be calculated as follows:
1. Uranium mining is in 1-0 product category 6.02.
21
. The 1-0 coefficient for category 6.02 is
128,209 British Thermal Units of energy (Btu)
per dollar spent on mining. (1967 basis)
3. The energy cost of this mining is:
($10) x (128,209) (Btu/$) = 1,282,090 Btu
Dollar costs must be expressed at 1967 price levels. In our
calculations we use economic deflators to calculate the proper
dollar amounts.
IV. CALCULATIONS AND CONCLUSIONS
Table A shows the Input-Output calculations based on
the fuel cycle costs found in Reference 1. The table shows that,
on the average, every kilowatt-hour of electricity produced by
this nuclear plant requires a minimum of about 0.14 kilowatt-hours
of processing energy in order to make power generation possible.
It must be understood, however, that this estimate does not
include several cost components in fuel processing, reprocessing,
and the disposal cycle; does not include allocated plant capital^
costs or energy produced but used in-plant. That our figure is
a lower bound is confirmed by calculations furnished in Reference !
where Paul R. Gast, Argonne National Laboratory, cites certain fuel
cycle energy requirements which are slightly higher than our own.
PS «O fafa 5o
OT p4Eh
O 3< u w
h*0) >* uiH O DA fa 55<d faEh 55 0)
fa gfah^oCjo>hoCJrH
t-3 fafa Ofa §
M-l (D
Cn£M «
CD-P-~
<D vd
CU«W\
fa <D 4J
o «
oJh atOHfd\•-» r-
O
o+Jo0)
CO
oIM
x:
XJ «•p\la a0«HOH
cct
-MCQ>
OCU
OCJ
4>00
o
vorHinr^nTrinoiH^•^•CACMCOOOrHCMrHOr-CMOrHOOOooooooooo
^ §<3\ N N N 3 N N H 3OVDV£»vx)4-»VOVOr->4-»
». w •> « « « ^OOrHrHi-HOrHrHCOO(NCOCOOOOCOCOOOrHCMCMCMVOCMCMrHVO
If) o\ <T» a» o cn cn CO o00 cn o> CD vo cn cn 00 voo *r •<* ^ Ok ** ^ CM cnM« in If) in CO m in ** CO
Ol H iH H£ iH iH CO J^oooojoooj• •••H»«»Hvor-r>r*»reCr*r>-co
CM CM CM fa CM CM V0
in cn in o m coo^ o h m o N
rH t"^ CMo o oCMm < rtj
• 55 55
tntn
Cn C oC vo •H cn•H fa c Cu MiH D o Cu cn fdrH •H •H en rH >ix:•H P x: c «d u u2 +» «J CO Cn c •r4 4J Cn
n C Cn O 4J cn CTJ C 4J <d •H •H •H fd Eh c c •HC c a Q) (0 (0 C cu -H TJ cu
<d •H <D cu 3 (0 5-1 «d cn > >i U oCO § M fa a) CU a c C M (d c
Cn U x: fa o > •H M >H 3 <d
c: <D o P cu C cu ft fd Cn >H
•H > •H rH C u p CU H U cu Pc C H Q) a> cu o 10 -H cu *w to
•H o c 3 a Q) cu <d x: 3 fd c:
a CJ fa fa w fa fa £ w fa w H
<u
Cncd
UOPw
rd
-Mcu
arl
CU
CM00CO
cn
OEh
TABLE A Continued
FOOTNOTES
:
a) Assumptions: Load factor .65Burnup = 30,000 MW(T)D/MTUEfficiency = 33,5%
Costs are from [1], Table III-2, p. 54.
b) In 1980 dollars, based on seven percent annual inflationrate, compounded annually.
c) As classified in [2] according to definitions in [3]
.
d) 1-0 category 27.01 is deflated according to the followingformulae
:
1) $1980 = $1971(1. 07)9 = $1971(1.84)
->\ $ 1967 , eopfnr a * - Xa(1967) .' Xa(1971)*> $1971 < secx:or a
' Xa(1958) * Xa(1958)
Where: Xa(19yy) = dollar output of SIC sector a,valued in 19yy dollars [6]
.
Other sectors use equation 1) but use standard Departmentof Commerce deflators in lieu of equation 2) (see [7]).All deflators rounded to four digits at each step ofcalculation.
e) Source: [4] and [5]
.
f) Energy is found by forming the product of dollars (1971)and energy coefficient (Btu/$1971) . Btu converted to Kwheat 3413 Btu/Kwhe. Rounded after calculation.
g) Shipping total includes all shipping except spent fuelshipping
.
h) Energy calculations for shipping costs are treated as follows:
1) Total annual shipping costs ($1971) are dividedby average rail shipping cost in 1971 ($1971/TM)
,
$.016/TM. See [8] p. 9.
2) The resulting total annual ton-miles shipped ismultiplied by the rail energy coefficient,1600 Btu/TM, resulting in total annual shippingenergy (Btu). See [8] p. 9.
3) Total annual shipping energy (Btu) is convertedto Kwhe (see note f) and divided by total annualoutput of plant (Kwhe)
.
REFERENCES
2.
3.
Rieber, M. .-d Halcrow^R.. "Nuclear Power to 1985= possibleJSE^S^S^'ESSI* o^Illinois, Urbana. November
1974.
the Budget, ±yo7.
••a« rr^rcrv Incut-Output Matrix for the United4 -
Ilatef^e!:' U^r'sGuIdeT Center for Advanced Conation
Document""
69, University of Illinois, Urbana, March 1973.
5. Additional tables from Energy Research Group Input-Output 1energy data base.
6. Ibid.
7. National Income and Product Accounts ."Survey of Current
Business," U.S. Department of Commerce, July issue, various
years.
.. Sebald A. ^fr^ae^, 7lllll^ %™Z?*£&-ra?ion^
aCcL°ter
Afor Advanced Confutation Document
university of Illinois, Urbana, September 1974.
r.,„i d rash Director. LMFBR Program Office,'• JSS.^SiSSS LbSSrfTS Bruce « Hannon Center or
Advanced Computation, University of Illinois, June 16, a*
CAC Technical Memorandum No. 51
SUMMARY OF TECHNIQUES USED FOR CALCULATING
THE ENERGY COSTS OF CONSTRUCTING A
COMMERICAL NUCLEAR REACTOR
by
Peter »PennerResearch Assistant
Center for Advanced ComputationUniversity of Illinois at Urbana-Champaign
Urbana, Illinois 61801
April 1975
This work was supported by the National Science Foundation (RANN)NSF Grant GI 35821(A)!.
CAC Technical Memorandum No. 51
SUMMARY OF TECHNIQUES USED FOR CALCULATINGTHE ENERGY COSTS OF CONSTRUCTING A
COMMERCIAL NUCLEAR REACTOR
I . OBJECTIVE
The purpose of this report is to compute the energy cost
of materials needed to construct a boiling water reactor plant,
based on AEC data. Energy cost, measured in British Thermal Unitso
(Btu) , is the sum of all energy which is needed to manufacture the
goods used to construct a nuclear plant.
II. GENERAL METHODOLOGY
The computations employ Input-Output analysis or (1-0)
.
Designed to compute dollar costs, the methodology has been adapted3to measure the energy content of any given dollar amount. This
is accomplished by first dividing the economy into 360 product and
service sectors. For each sector an "energy coefficient" is found
which yields the energy cost-per-dollar for all goods in the sector.
The total energy cost (in Btu's) for any particular item can be
found by multiplying the item's dollar cost by the correct energy
coefficient.
III. EXPLANATION OF CALCULATIONS
The calculations necessary to find energy costs are as
follows. First, it is necessary to express all 1971 dollar costs
of the nuclear plant in 1967 dollars. This is achieved by including
a "deflator" in the cost equation. The usual computation, calle<
Itemized 1-0 , is the product:
Energy Cost (Btu) = Dollar Cost ($1971) x
Deflator $%$ x
Energy Coefficient -rFTgi-i \
Example : Budget account 218C in the reactor Bill of
Materials is an administration building costing $910,500 in 1971
dollars. This belongs in 1-0 category 11.03, public utility con
struction. The corresponding SIC category is 1511, and the propel
deflator is 0.71. The energy coefficient for sector 11.03 is
79,610 Btu/dollar. Therefore, the energy cost of this building is
$910,500 x 0.71 x 79,610 = 51.5 billion Btu
In some cases, the 1-0 sectors did not accurately descri
a particular item. For example, if the administration building
described above was not a normal public utility structure, but
rather had a larger amount of steel in it than the average buildir
described by 11.03, the usual 1-0 product would not yield correct
results. In this cases it is possible to use corrected I-O .
Example : Consider the administration building in the
previous example. Assume that it has $10,500 more steel in it the
the average public utility. Steel is in 1-0 sector, 40.04, SIC
sector 3441, and has deflator 0.835. The energy coefficient for
sector 40.04 is 124,602 Btu/dollar. The corrected 1-0 calculatior
is then:
$900,000 x 0.71 x 79,610 = 50.9 billion Bi
cost of usual deflator energycontents of coefficientbuilding
i
$10,500 x 0.835 x 124,602 = 1.1 billion Btu
cost of steel steel energyexcess steel deflator coefficient
Total Energy Cost = 50.9 + 1.1 = 52 billion Btu
In performing this calculation, only costs for actual contruction
and construction materials were considered. Other costs, such as
services used in construction or interest during construction were
not considered.
V. DATA SOURCES
A. Division of the Economy into Sectors - The U.S.
Bureau of the Budget regularly issues a Standard Industrial Classi-4
fication (SIC) Manual. This divides the economy into 99 major
sections and many subsections. The subsection classifications are
called SIC sectors. The Bureau of Economic Analysis, U.S. Depart-
ment of Commerce, has divided the economy into 368 sectors expressly5for the purpose of Input-Output analysis. Each 1-0 sector commonly
contains one or more SIC sectors.
B. Economic Deflators - The U.S. Bureau of Labor
Statistics issues price deflators classified according to SIC
sector.
C. Input-Output Data - Economic information is published7by the U.S. Department of Commerce. This information is converted
oto energy coefficients.
D. Economic Budget for Nuclear Plant - For the BWR, this
comes entirely from reference 1, which itemizes all material, labor
and installation costs for AEC prototype reactors. For the PWR,9another report had already classified reactor costs and converted
them to 1967 prices, and we used these sums.
VI. RESULTS
The energy cost of constructing a 1,000 MWe boiling
water nuclear plant is:
9.36 trillion Btu, or about
2.74 billion Kwh
The energy cost of constructing a 1,000 MWe pressurized
water reactor is:
9.65 trillion Btu, or about
2.82 billion Kwh
VII. ACCURACY OF RESULTS
Several studies have examined the accuracy of energy
costs computed with I-O.11 ' 12 These results show that most results
are accurate to within approximately 25 percent.
VIII. ADDITIONAL INFORMATION (see following list of references)
A^ For additional information on the theoretical basis
of Input-Output analysis see references 3, 4 and 10, Appendix A.
B. For additional information on the raw data inputs
to this calculation see references 4, 5, 6 and 7. Also see
Appendix A (following) which lists for the BWR all budget account
entires, dollars amounts and the 1-0 sector this amount was placed
in. Corresponding tables for the PWR can be found in reference 9,
page 24.
C^ For additional information on the accuracy of result!
see references 11 and 12.
D^ For a complete list of all 1-0 sectors and accompany-
ing SIC sectors see reference 6.
FOOTNOTES
1. United Engineers and Constructors, Inc., 1000 MWe CentralStation Power Plants Investment Cost Study , Volume II,Boiling Water Reactor Plant. Philadelphia, Pennsylvania,June 1972. Prepared for the U.S. Atomic Energy Commission,Contract No. AT (30-1) -3032.
2. One kilowatt-hour is approximately equal to 3400 Btu.
3. Herendeen, Robert and Bullard, Clark W. , "Energy Cost ofConsumer Goods, 1963-1967," Center for Advanced ComputationDocument No. 140, University of Illinois at Urbana-Champaign,Urbana, November 1974.
4. Office of Statistical Standards, Standard Industrial Classi-fication Manual , Executive Office of the President, Bureauof the Budget, Washington, D.C., 1967.
5. Bureau of Economic Analysis, Input-Output Structure of theU.S. Economy, 1967 , Department of Commerce, Social andEconomic Statistics Administration, Washington, D.C. >',-,•'•
-
:
6. Issued regularly in National Income and Product Accounts,"Survey of Current Business," a periodical issued by theU.S. Department of Commerce.
7. Bureau of Economic Analysis, above.
8. Herendeen and Bullard, above.
9. Just, Parker, Borko, and Ashmore, "Energy Technology Coeffi-cients and Dynamic Energy Models," Vol. II, Appendix D Nuclear,The Mitre Corporation, Virginia, January 1975.
10. Reference 9 also includes, in addition to construction andconstruction materials, installation materials. This is asmall difference, amounting to less than one-half of one per-cent change in costs.
11. Sebald, Anthony V., "An Analysis of the Sensitivity of LargeScale Input-Output Models to Parametric Uncertainties,"Center for Advanced Computation Document No. 122, Universityof Illinois at Urbana-Champaign, Urbana, November 1974.
12. Kirkpatrick, Ken, "Independent Verification of Input-OutputResults," Center for Advanced Computation Technical MemorandumNo. 26, University of Illinois at Urbana-Champaign, Urbana,August 1974.
APPENDIX A
I. Itemized Input-Output
II. Corrected Input-Output
Footnotes to Appendix A
I. ITEMIZED INPUT-OUTPUT
Classification in Budget
INTAKE & PIS. STRUCTURE
214.131 Formwork
214.132 Reinforcing Steel
214.133 Concrete
214.141 Misc. Iron
214.15 Cofferdam
214.16 Rip-rap
214.1602 Steel Piling
214.1611 Formwork
214.1612 Reinforcing Steel
214.1613 Concrete
214.162 Block Walls
214.1631,214.164 Coping & Sprinklers
214.165 Lighting
ADMINISTRATION BUILDING
218C Administration Building 910,500 11.02
YARD WORK
Amount 3I/O Sector
42,000 40.07
40,500 40.09
142,000 36.12
51,000 40.08
972,500 11.03
125,000 36.15
60,000 33.12
3,000 40.07
1,500 40.09
3,000 36.12
5,000 36.10
3,000 42.08
6,000 55.03
211.14 Fence 16,000 34.81
Gate House (labor & mat) 15,000 11.05
211.15 Sewage Facilities (lab & mat) 85,000 11.03
211.16 Drainage Pipes, etc. 38,000 36.05
211.17 Yard Lighting 26,000 55.02
211.34 Bridge Steel 12,000 40.04
Forms 3,000 40.07
Steel 4,500 40.09
Concrete 5,500 36.12
211.43 Railroad Siding 1,165,000 11.05
211.11 General Cut and Fill 280,000 11.05
Classification in Budget
211.12 Roads, Walks, Parking
211.13 Wall Forms
Wall Steel
Wall Concrete
Cribbing
910.
911.
912.
913.
251.11
251.12
251.132
252.1
252.211
252.293
252.221
252.242
252.292
252.31
253.21
Amount I/O Sector
242,000 11.04
10,000 40.07
12,000 40.09
28,000 36.12
25,000 36.11
UNDISTRIBUTED COSTS
Professional Services 23,750,000 73.03
Temporary Facilities 1,260,000 11.02
Construction Equipment 6,435,000 45.01
Construction Services 2,065,000 11.05
Spare Parts 1,000,000 37.01
MISCELLANEOUS PLANT EQUIPMENT
Traveling Crane 170,000 46.03
Reactor Crane 250,000 46.03
Misc. Hoists 25,000 46.03
Air Systems 107,000 40.03
Service Water Pumps 26,000 49.01
Water Strainers 50,000 42.05
252.29 Piping (backfill neglected) 520,000 42.08
City Water Piping 14,000 42.08
Fire Pumps 60,000 49.01
Water Tank 50,000 40.06
Pipes, Valves, etc. 50,500 42.08
Auxiliary Boilers 400,000 40.06
253.1 Communication System 35,000 56.03
Fire Protection System 10,000 56.03
253.25 Noise Monitoring System 5,000
254.23 Chemical Lab. Furn & Fix. 44,500 23.03
254.31 Office Furniture 50,000 23.
254,6 Cafeteria Equipment 125,000 2.
254.41 Locker Room Material 8,000
Classification in Budget
STACKS AND RADWASTE BUILDING
Amount I/O Sector
216.131 Forms 50,000 40.07
216.132 Reinforcing 75,000 40.09
216.133 Concrete 130,000 36.12
216.134 Iron 9,000 42.05
216.1411 Forms 75,000 40.07
216.1412 Reinforcing 90,000 40.09
216.1413 Concrete, Incl. Block 140,000 36.10
216.1414 Embedded Iron 21,000 42.05
216.142 Steel and Iron 33,500 40.08
216.145 Roofing, etc. 14,400 40.07
216.147 Doors 1,800
Steel Doors 2,10040.05
216.149 Paint 10,000 30.00
216.211,216.212 Drains and Pipes 60,000 42.08
216.22 Heating 135,000 40.03
216.23 Fire Protection 15,000 56.03
216.24 Lighting and Wiring 25,000 55.03
219A.2 Foundation 100,000 36.12
219A.3 Stacks, Bricks 125,000 36.10
219A.4 Paint 5,000 30,00
219A.5 Warning Lights
SERVICE BUILDING ANDDIESEL GENERATOR BUILDING
10,000 56.03
218B.131 Forms 2,600 40.07
218B.132 Reinforcing Steel 3,750 40.09
218B.133,218B.135 Concrete 10,500 36.12
218B.134 Anchor Bolts 1,500 41.01
Classification in Budget'
218B.141,218B.142
218B.1411
218B.1412
218B.1413
218B.1415
218B.147
218B.21
218B.22
218B.24
218B.141
Platforms, Stairs, etc.
Forms
Reinforcing Steel
Concrete
Roofing
Doors, Louvers, etc.
Drainage
Heating & Ventilating
Lighting and Wires
Fire Wall
Amount I/O Sector
35,400 40.09
15,000 40.07
27,000 40.09
24,000 36.12
2,250 40.07
12,000 40.05
10,000 42.08
25,000 40.03
6,000 55.03
21,000 36.12/40.09
15,000 36.12
80,000 40.04
24,750 36.11
9,000 40.07
45,000 36.11
37,500 36.14
35,000 30.00
40,000 40.01
10,000 42.08
14,000 42.08
90,000 40.03
5,000 56.03
75,000 55.03
218D.13
218D.142
218D.141
218D.144
218D.143
218D.146
218D.148,218D.146
218D.21
218D.22
218D.23
218D.24
Concrete
Structural Steel & Iron
Floor Slabs
Roof and Roofing
Exterior Walls
Interior Walls
Paint
Fixtures, etc.
Floor and Roof Drains
Misc. Piping & Drainage
Heating, Ventilating, A/C
Fire Protection System
Lighting and Wiring
II. CORRECTED INPUT-OUTPUT
1 '2 3Classification in Budget Amount I/O Sector
REACTOR STRUCTURES & IMPROVEMENTS
212.133,212.1413 Concrete
212.131,212.1411 Formwork
212.132,212.1412 Reinforcing
212.134,212.1414 Structural Iron
212.142 Building Steel & Iron
212.149 Paint
212.371,212.3755 Steel & Iron Cont.Strc.
212.22 Heating System Equipment
212.24 Lighting System Equipment
REACTOR PLANT EQUIPMENT
221. Reactor Equipment
222. Reactor RecirculationSystem Equipment
Reactor RecirculationSystem Piping
223.1 Residual Heat RemovalSystem Equipment
Residual Heat RemovalSystem Piping
223.2 Emergency ShutdownSystem (pipes incl)
223.3 Coolant Injection & coreSpray System Equipment
Coolant Injection & CoreSpray System Piping
895,000 36.12
225,000 40.07
750,000 40.09
129,000 37.01
618,000 40.08
50,000 30.00
1,940,000 40.06
1,250,000 40.03
100,000 55.02
23,435,000 40.06
1,600,000 49.01
900,000 42.08
1,076,000 49.01
1,390,000 42.08
172,000 49.01
580,000 49.01
1,420,000 42.08
1 2Classification in Budget Amount I/O Sectoj
224.1 Liquid waste processingEquipment 808,000 49.01
Liquid waste ProcessingPiping
224.2 Gaseous Waste Processing EQ
Gaseous Waste Processing Pp
224.3 Solid Waste Processing EQ
225.3 Service Platforms
225. Nuclear Fuel Handling andStorage System Equipment
" Piping
226.5 Coolant Purification andTreatment System EQ
Coolant Purification andTreatment System Pp
226.7 Auxiliary Cooling Syst.EQ
" Piping
226.92 Paint
227.1 Nuclear Plant Instrum.
227.2 Computer Equipment
227.5 Instrum. & Control Pp
345,000 42.08
50,000 40.03
205,000 42.08
70,000 46.02
400,000 40.08
225,000 40.03
100,000 48.06
20,000 49.01
500,000 40.08
50,000 57.03
50,000 55.02
285,000 42.08
50,000 49.01
1,150,000 40.06
53,000 42.08
35,000 49.01
90,000 40.06
386,000 42.08
25,000 30.00
2,000,000 53.03
1,500,000 57.02
300,000 42.08
oo
v.
or» G« •H CO
r» (N 4Jvr> CO OO 1 oooooooooooo (0 o o o o o o o 3to- 3 OO 1 oooooooooooo P o o o o o o m 04
rH OO 1 oooooooooooo G o o o o o o CN Gll a 3 ** *. «. .» v •. •• •H •
M OCN "rJ«rHOr-rH004rHCr>OinO O V£) rH CO rH CTv CT> CN •o._
*
3 cn ,-< mo^mo'ouj^ooriin e CD V£) o <tv r- r» vo rH CU
rH CO im cNrHovo HNO\coinH id rH CN vr a\ c\ r^ o rH 4J
03 » I * * * * * * •>. • «.«.«.|
» id -P•H </> rH CN CN <cj> n rH rH •p rH rH r-{ in H CN •HH CN G 1 1 1 1 1 ^r «M g0) id op "s. o(0 •H -P cu
e rHm •HG Hcu id
c3 o«
G o^ co
5-1 rH UIOOChrnWNUJfOHOOOOChO •H in vo r- ^ cm in CU 5-1
OXlid
rH COCTirHdCNlONrHOOCNOCNOfOO CO f* CO O 00 CTV rH 1
1
o. o4J
in rH «3< o cn o o o G rH rH CN CO CN rH1
1
rH •H • <N CU'
<*> PGo
CO
4J-P G •H 3 CO
CO s, p oCO id Xj -H
o rH•
CU
nrH3
id >r-l
-p Cn 04 o • cu cu
c -a rH G CO CO
0) rH M^o^H^cooinotNinHNr^ •P o o o o o o o id •H
1•H
PQ (n^HNH^OHHinoomfSNOG
o o o o o o o o •Hpid
u u04 CU
e x.m rHrH CN f^'«* co in cn cn o o o o o o o Gd n •P o •H rH O -P
& 3 rH 3 U0) dP Xl T3
cu
ug «a
•o N o> . CO id
•H 3c H 3 ofO +jooooooooooooooo M 1 1 1 1 1 1 o cu G O 0)
tr rH ooooooooooooooo 0) 1 1 1 1 1 1 o u •H CU TJC•H
(d
-Pooooooooooooooo >
o1 1 1 1 1 1 o
cu
j-i id
u uO -PU inmcncoinininoorHrHoooo CN
rH o b or^cNrHr^r^vor^ovo^rooinm co 10 XI CO o•H +J 00 <X> rH in rOr~ HhOOlOH o o 3 rH3 </> «. « « •. •» - -^ • ^ -p CO HXI 0) H in cn in o cn i-i rH CN G cu •H id
(A <N rH ** cu M X. -Pu • O o •P CU
O \ r4 rH IH «M u-p \ • 3rH cu <u Go H • 10 •p CJ CO CU X a, X) •H TJn3 04 • CD o tn cu COM • GCU >i G • -H >, id CO H CU G G H+IO Cn rH *! •a id
H X) O 04 a M 04 U 3 CO •H CO £ T3 o o cu•H G -H CTX! O. O -P > • r-\ a rH • rH M CO
rH M P H O CU 3 W .< -P * CO U 73 <D 10 • rH m CU rH03 O CU id H -P tf id O-HO p CU 0) cu co u id p p TJ id
-P -P •H P H flJWt^S • 3 fo -H CO U -P HDP4J Cn CO CO •H WO M 0) <D H C 'O'd fi CO CU a* W n o u cu G cu cu CO CU
-P <d U PS «* 04 Cn-H rH .Q G CT» O p U tJ rt+)2 •H u u G rH'
0) 10 3 CM • >J» dvito G id id O Ort cu H -P rH-PrH-HCU-HGCOOO-H-P O4O u 3 CU •H cu cu ° XJu o OCUC0)CCU+J>O-HO4-P-H4JO G Cn T3 U G O *P • o <d G G gj
2 o Cdioo-HoidcojagHg cn cu •H G O G Cm CSX W g COM •p oxJih-phj-pcuo a-H 3 £ a) -h rH •H O O M o «d -h cu o o MQ UWrHtOfUWKCJWP^CUCOW^W rH Tj £ U M 2hS (X p 4J O •J CO \ Id rH 4J COM •p G-H T3 TJ o oD 3 H O 3 cu cu CU •
n 04 O •HXi TJ -d CO rHc -P CNjr>-rHcjoovonr>4M>corHnfMron +» CO rH CN) o *r crt CO G G rH
oEh
H o
to
rHOOOOOOOOOOOOOO •H CO
13 -HTJX!
O rH O rH o o o 3o o
01
rHrH O<:-pcu voor->oooovooof\jcr>mr*inr^ o vo r^ CO o o rH
D Cn nvm^n^T^TTrrininuim «: -P cm m ro m ^j. ^j> rH< M o2
id
3 r>• •
CN•
CO
II. B.
classification in Budget_
Amount' I/O Sector
218A.131
218A.132
218A.133
218A.134
218A.142
218A.1411
218A.1412
288A.1413
218A.147
218A.1411
218A.1412
218A.1413
218A.143
218A.148
218A.145
218A.212
218A.211
218A.213,218A.214
218A.222
218A.228
218A.24
218A.224
218A.227
236.1
236.4
241.132
241.21
CONTROL ROOM, BUILDING AMD
ELECTRIC PLANT EQUIPMENT
Forms
Reinforcing Steel
Concrete
Misc. Iron
Misc. Iron
Wood Forms
Reinforcing Steel
Concrete
Doors
Forms
Reinforcing Steel
Concrete
Masonry Partitions
Suspended Ceiling
Roofing
Drains
Drains
Piping
Electric Heating
Piping
Wiring
A/C Equipment
Ductwork
Instruments
Pipes
Transformers
Switchgear
4,000 40.07
7,500 40.09
10,000 36.12
1,000 42.05
13,000 42.05
9,000 20.06
42,000 40.09
26,000 36.12
4,000 40.04
20,000 40.07
35,000 40.09
28,000 36.12
10,000
30,000 42.05
5,000 40.07
1,500 42.05
500 42.05
3,500 42.05
16,000 54.05
5,000 42.08
60,000 55.03
35,000 40.03
10,000 40.07
785,000 53.03
175,000 42.08
15,000 53.02
,250,000 53.03
Classification in Budget Amount I/O Sector
241.22 Controls 300,000 53.03
241.24 Controls 50,000 53.03
242.1 Transformers (less supports) 477,000 53.02
242.211 Substations 700,000 55.03
242.3211 Generators 1,000,000 49.05
242.3212 Oil Tank 50,000 40.06
242.332 Inverters 20,000 49.05
243. Switchboards 470,000 53.03
244.11 Wiring 45,000 38.10
244.113 Lighting Masts 15,000 40.04
245.3 Conduit 320,000 55.03
246.1 Generator Bus 435,000 55.03
Generator Bus 60,000 55.03
246.211 Bus Duct 100,000 55.03
246.212 Cable 285,000 38.10
246.221,246.222
•
Cable 210,000 38.10
246.223 Bus 50,000 55.03
246.224 Bus 70,000 55.03
246.3 Wiring 550,000 38.10
246.4 Wiring 400,000 38.10
246.5 Canisters (incl. Instal) 500,000 40.06
CN014J
01 O O O O ooooooooo o o o o o 23 o o o o ooooooooo o o o o o 04iH
5m
o o o o ooooooooo o o o o o•H •
*dcm in co cn Mn^r^HinfOfN^ cn <j\ <y\ CN^
^3 i-i a\ cn ^r OCOrHrHO | ^OrHr- r- co in CN CN rH Q)
W rH 1 1
1
CN-^CNiHin rH 00 <7»
III * 1 -CN CN V£>
l 1 1
CO1
CT> rH 4Jfd -P
</> rH (N CN•H
•HM-l gO\+J 0)
rH CO c n«^» CO Cn fdo O C oo • ^r •H U 01
^ iH r^inoo t ^(NN^OMOHOOO 'O in VD TT r- a) n
inco
rH a\ rH o co r-cncnoocococNCNo rH r^ oo cn o4J
o u4-1 rH •H CN "SJ1 00 rH CN O 3 rH rH «5T CNin .Q • CO 0)
*i a 01
in c»P C o •prH •H •H pj CD</>- \
4J•pfd
o u
II rH• 3
fd >U
CD Cn O • ai a)
3 T) P iH f4 01 01
•H rH in^nvo rHCNrrCTvinCNVOOOr^ C o o o o O fd Hfd
>« MIOCNO ^rHinmmcoiHcoin d)
Oo o o o O
t
o •H
fd
cua)m CO 0\ rH HCOVD o o o o O drH o rH rH Q) o •H rH O 4Jtd 0, rH u oP <A° TJ O
0) 0) rH CT3&H \ cS 01 fd o c**"""
*
3 o •h fd4J
H o o o o ooooooooo u 1 1 1 1 (U G o <u
S rH o o o o ooooooooo <D 1 1 1 1 u •H (U TJ
H fd
-Po in o o ooooomooo > 1 1 1 1
fj) a)
r-l fd
u uO 4Jdi o» T in cr\ •^cTiooinc^oino
H H cn oo cn vDrHincr»cr\^ooincN CO XI 01 oP in rr r- rH oo o o 3 rHo </> •» ^ * «» • +J 01 -Hw rH rH CN rH rH
rH ai
0)
u•h fd
Xi -P^ u -P <1)
5z \ • • U Cn n m U2 u O C <D a) ctH p -p •P •H 04 J3 •H'Od W d) c O CP T3 a
c • -P o 0) c rH •H CO »d cd
cj o a O 03 U to •H • •H O o CD
H •H •H rH 0) 3 (U > V •H 3 • rH U 0)
« •P HH JJ <U -P tP'd > 13 U 0) <D CO CD rH^ cu fd fd D1 o) fd c; o c rH tn •P 0) £ Q) P P fj fd
u •H -P -P W •PrH-HMOfdtJ^M 01 -p Cn 01 01 -H 01
w M <u <u (DWft Hd. n> c o 01 0) 0) w a Q) 0) Ul <Dt-H O a a cn •P -H H -H -P •P 5-1 -P •H M U CJrHw CO c <D • u is Cn *^ fd 3 CU 0) t3 c fd fd O
d) -P • -H M U 0) c • 0) O JH CL M rH •H 0) o O £Q Q 0) O -P TJ U2HCJ-HfJ(D4J(l) C 'O O 0) C! fd £ c: Is2 CD 01 fd C U -ri O U U) CVH a •H C 0) £ oi
<J J2 -H CD O -P O U'ri'ri-ri 5 d) O -P M 0) nW 2 ffi 5 C. lU rH 3: U w H « -P p o •
a \ <d •P COo c TJ t3 ooo ^ 0) a> o •
« •H T3 •d 01 H•P r-» cr> co vo cN^voocoinoocoin •P 00 rH iH CN CO G d •Hu<d
wo o o o iHOOrHOOOOO •H
•0
O rH O O o 3 •HrH< -po o o o vQoooo»ncNCNco<y» o v£> r^ r- rH
£-• ^r tt ^r <n cn*3, '*vmmT*riri*r < CN CO CO CO rH2 o 1
O \ • • •
CJ Hj 1 «H CN CO
II. c.
Classification in Budget
TURBINE ROOM AND HEATER BAY
Amount I/O Sector
213.114 Concrete Fill 25,000 36.12
213.131,213.1411 Forms 215,000 40.07
213.132 Reinforcing 150,000 40.09
213.133 Concrete 240,000 36.12
213.134 Embedded Iron 35,000 42.05
213.1412 Reinforcing 200,000 40.09
213.1413 Concrete Block 320,000 36.10
213.1414 Embedded Iron ' 15,000 42.05
213.1421-213.1425 Steel & Iron 853,500 40.08
213.143 Metal Siding 80,000 40.07
213.144 Roof Deck 21,000 40.07
213.145 Roofing, etc. 45,000 40.07
213.146 Block Walls 10,000 36.10
213.211,213.212 Plumbing 105,000 42.08
213.22 Heating 450,000 40.03
213.24 Lighting
TURBINE PLANT EQUIPMENT
50,000 55.03
231.1 Turbines 29,700,000 43.01
231.2112 Concrete 25,000 36.12
231.2114 Formwork 3,300 40.07
231.2115 Reinforcing Steel 18,000 40.09
231.2116 Concrete 40,000 36.12
231.2119 Misc. Iron 6,000 40.08
231.2124 Formwork 35,000 40. 07
231.2125 Reinforcing Steel 57,000 40.09
classification in Budget
231.2126
231.2129
231.221
231.421
231.422
231.45
231.511
231.512
232.11,232.133
232.161
232.211
232.212
232.213
232.221
232.222
232.223
Concrete
Misc. Iron
Steel Supports
Tank
Piping
Oil
Storage Racks
Pipe & Manifolds
Screens
Sluice Gates
Pumps
Motors
Pipe
Formwork
Reinforcing Steel
Concrete
Pipe
Formwork
Reinforcing Steel
Concrete
Misc. Iron
Sheet Pile
Pumps
Formwork
Reinforcing Steel
Concrete
Misc. Iron
Permanent Piling Frame
Formwork
Reinforcing Steel
Concrete
Misc. Iron, Gates, etc
Amount I/O Sector"
64,000 36.12
30,000 40.08
25,000 40.04
23,500 40.06
50,000 42.08
25,000 31.01
50,000 40.08
17,000 42.08
235,000 42.05
140,000 40.06
677,500 49.01
265,000 53.04
225,000 42.08
12,500 40.07
16,800 40.09
30,000 36.12
54,500 42.08
20,000 40.07
28,000 40.09
44,000 36.12
10,000 40.08
10,000 40.07
15,000 49.01
25,000 40.07
30,000 40.09
90,000 36.12
5,000 40.08
185,000 40.08
6,000 40.07
9,000 40.09
14,000 36.12
18,000 40.08
Classification in Budget"
233.11
233.211
233.212
233.221
233.23
233.251,233.252
233.34
234.11
234.21
234.231
234.31
234.341
234.342
235.11
235.221
235.222
235.251
235.31 .
235.321
235.322
235.33
235.41,235.51
Condensers
Pumps
Motors
Pumps
Motors
Tank
Piping
Foundations
Piping
Heaters
Pumps
Motors
Pumps
Motors
Pipes
Pipes
Pipes & Drains
Pipes
Pipes
Tanks
Tanks
Pipes
Pumps
Tanks
Heat Exchanges
Pipes
Water Treating Plant
Amount I/O Sector
3,000,000 40.06
100,000 49.01
60,000 53.04
125,000 49.01
100,000 53.04
130,000 40.06
940,000 42.08
35,000 40.08
140,000 42.08
1,500,000 40.03
140,000 49.01
700,000 53.04
230,000 49.01
50,000 53.04
775,000 42.08
340,000 42.08
305,000 42.08
1,100,000 42.08
750,000 42.08
11,500 40.06
19,500 40.06
165,000 42.08
45,000 49.01
7,500 40.06
65,000 40.06
310,000 42.08
1,020,000 40.06
oo
-3>
or-
<0
i-l
rd
>
O2:H9HDCQ
O52HH<
T3 WO w3c *•H sPG Qo «u W
55• H• sH DH Eh
(NCQ
rHCU>H
CO
co-
coo
uh
9CQ
Q
fd
PoEH
GO•HpHoco
a)
Q
opua>
co
000 1 00000 1 00000 1 00COOHin r» f-H
vx> rH roI I I
01 inrH inrH <Tv
o oo oo ot-» 00cn 00o <N
in0000 1 000000 1 000000 1 00* •. * •> » *»
^ r> r-» i* r^ or-IOWJO <T> —
I
r~ r-» cn o\ m <r>
I
cncn
mHOONN I o o
o o(N CM «* o o
rHTtfr-tVOinOO**!'-
in
\o vo a\ *f • ^o 00*& f» G> CN I CM CM
OOOOOOOOOOOOOOOOoooooomoo
r»(N H ID
00000000000000IT) O O O O O O
civo<y»mov£>ino vo o o r- m r- or- moHN 01Hcn c\ r» ** m a\
«. «. * * »
If) rH <T» <* rHCN
0)
a)
v<
ucoO CO
•H d)
id <U
p p(U CO
CO
>
0)
a)
pCO
lfl C7
C7»> GG -H
• •H »PO P CO P3 £ <U-HV) CT> Cit tMp -rt «HCO J 04
0*•H3
:1 -P
co cu P& o a)
G G H rH•H -H <D OP 43 rH HIS M-H-Pa; Q)
ffi H CQ (u
CO
10
a)
wo*eou
CO
CO ua. oE pd oP. 2
cNf-CAinooo^rrocorHOOOrHOOOO^DOO<N*-DOOin(NfO'^•^T^l•^|^•»l, ^, ln^^,
CO r-i U> <-4 r-i "STOOOOOO>jnf rr m "f in
cotr>
G•iH
-arH•H
43
10
•-H
G•H
§oUH
PoG
§oua>
04
a)
Go
>O
eno
O4J
CQ
-P
D4c•H
r3
el
•HP•H
000000000ooovoCO O rH(N o nHCIrl
I I I
in •># 10r- cn 00
rH >* r-\
OOo
HI
o(N
ooo
ooo
*3" r-i
in cm<N 00
ko cnI <N
CO
00
000000000
I I I
I I I
I I I
oo
oo
m c ac•-H • S-i •H
> O rH M pn 0) <U (0 nJ
<1) c <U <D to rHin P •rl 3 rH
fl) 0) CO U 3>-f
+J >0 u wcv 0) i^S c u a
-H u a HTl 0) C m
0) G O Cm c ca
p O U^ CO u M S2
EhOEh
COrlHMO O rH O
• • • •
o r~ id r~(N cn cn cn
00cn
CQ
P30Uc
^ H •
cn TJCN rH O<n rH P
fd PCO •rl
•*r MH gO O
P <D
a u •
O rd >iHW CQ P0) M OOi Q)
p Hr- •H
• cn <u T3
CJ CQ
p •T3 *
•Hrj
Q) a)
P t^
ni 45 -HrH fd > rH
d H• (l) a) G
rH C CO CO -rl
<d -HO •HUM a)
P 0. 0) MC fd e 45 rd
•rl rH -P300 CO
«d Pa> rH C T3 GCO fd c: 3p O -H fd
P Rc OJ f0
M •h <u «dm rd >1
««H T3 H U CT>
(U <D OP VI
43 CQ O d)
3 H GP CO -H 0)
c a) -h rd 1
a) n ^p 1
p <i> Gu MH )H
<D a> g •H
ex 43 "rl tJ P0) G3 rH m 'O fd a)
rH tr> O a) Mfd C • h n a vi
CD rH
P +J TJ n) ^-. u(Ji rH CO CO -rl CO dP
C -H <u w <u rH 41
•>H u M C rH ° "SC CQ fd id • P•Htd mh
a) ,GG S ^ 6
<D VIe0)
CO
O rl
rt -p P • rH <«
p ro ° -T3 rrj rj •rl <ti
0) <u <u • tJI (D
T) fC> CQ rH -rl Pn C G rH rH P
• 3 3 ,H ~ tT> 'rl
O rH q grH PS rt < +» ZrH
I rH CN CO
FOOTNOTES TO APPENDIX A
1. Investment Cost Study, 1000 MWe Central Station Power Plant,. United Engineers and Constructors Inc., 1401 Arch Street,Philadelphia, Pennsylvania, 19108, June 1972, Part V. Itemsincluded are all listing above $250,000 (except excavation)and other items both large costs relative to building sizeor type.
2. Expressed in budget to the nearest thousand dollars (1971)
.
In most cases, only primary materials cost is listed. Insome cases, installation materials (always very minute) areincluded. Labor costs are never included. Some budget
. accounts are omitted because they are neglible or toodifficult to classify.
3. See: Bureau of Economic Analysis, Social and Economic Statis-tics Administration, U.S. Department of Commerce: Input-OutputStructure of the U.S. Economy: 1967, Volume 2. Classificationwas done on the basis of 1967 SIC Sector definitions from 1967SIC Manual.