The Challenges of an Autonomous Medium Voltage Control ... · PDF file> Standard RTU560 for...
Transcript of The Challenges of an Autonomous Medium Voltage Control ... · PDF file> Standard RTU560 for...
European Utility Week – 4th November 2015
Dr. Lars Jendernalik
Westnetz GmbH, Germany
The Challenges of an Autonomous Medium
Voltage Control System: Lessons Learned
from the GRID4EU German Demo
The German Demo Agenda
Renewable Energy in Germany
Principle idea and concept of the German Demo
Field implementation in Reken, Germany
System integration
Security concept
Simulation results
Conclusion
www.grid4eu.eu 2
The German Demo Renewable Energy in Germany
Renewable Energy
in Germany (figures end of 2014)
Photovoltaic: 38.2 GW
Wind (onshore): 38.1 GW
… and still increasing!
0
10
20
30
40
50
60
70
2000 2003 2006 2009 2012 2015 2018 2021 2024 2027 2030
Wind offshore
Wind onshore
Solar power
GW
+ 21 GW / 10 a
Wind Power
in the Past
+ 33 GW / 10 a
Solar Power
in the Future
The situation today
Massive increase of decentralized generation requires huge grid investments
Power flow becomes less predictable (even reverse power flow becomes reality), grid operation and observation become more complex
www.grid4eu.eu 3
The German Demo Overview
Objectives
Integration of an increasing number of decentralized energy resources (windmills,
solar panels…) in the medium and low voltage networks
Avoiding „classical“ network expansion measures
Achieving higher reliability, shorter recovery times after grid failures
Increasing the surveillance and remote-control level in MV networks to achieve
better overload and failure management
Loss reduction due to optimized switching situation for each scenario
Basic idea
Extension of the automation level of MV networks based on an autonomously
acting multi module system as an industrial solution for network operation
Partners
www.grid4eu.eu 4
The German Demo Boundary conditions
Located in Germany, North-Rhine Westphalia,
area of the municipality of Reken
Semi-urban area with moderate continental
climate conditions
MV grid with approx. 100 secondary substations,
(7 switching modules, 11 measurement modules)
Ratio between maximum load and Decentralized
Generation (DG) almost balanced
Massive increase in DG expected
www.grid4eu.eu 5
The German Demo Principle concept
System acts and optimizes locally!
Switching module
Control Center (CC)
Local communication
Global communication
Concept
Approach is based on autonomously working
modules and a lean control center (located in
primary substation)
Modules communicate amongst each other
and can act on remote-controllable switches
in order to adjust grid topology to current
state of grid
Derivation of decisions based on measured
operating parameters
All relevant information (alarms, grid
topology) is to be sent to the central SCADA-
system
Multi module system can be …
Pre-stage of MV/LV SCADA system
Part of an existing MV/LV SCADA system to
minimize central tasks
www.grid4eu.eu 6
The German Demo Grid implementation
HV/MV substation „Groß Reken“
FIONA (ABB):
> Standard RTU560 for all modules
> Standard GPRS Communication
> Standard Protocol:
> 60870-5-104
> Switching Module Software based on PLC 3 Switching Modules
4 Switching Modules (Cabinet solution)
11 Measuring Modules www.grid4eu.eu 7
The German Demo Hardware implementation in Reken
Option 1:
Full replacement of old secondary
substations with an intelligent
compact substation
Option 2:
Replacement of existing switchgear in
walk-in substation / Implementation of
“intelligence”
Option 3:
Dedicated cabinet solution containing
new switchgear and “intelligence”
added to existing substations
Option 1
Option 2
Option 3
www.grid4eu.eu 8
The German Demo System integration
Signal Description
Dedicated to the substation
FWU War Warning signal to report a missing clock synchronisation
FWU Sto Fault indication, caused by a deficient measuring unit
FWU Komm Sto Indication of communication between substation and front end processor
9
The German Demo Security concept
Security Audit
Process 1: All involved devices are
checked by a penetration test
Port scanner
Vulnerability scanner
Manual checks
Process 2: Auditor check of all
relevant documents (ISO 27001,
Coherence)
Final assessment report
www.grid4eu.eu 10
The German Demo Switching behaviour (I)
0 20 40 60 80 100 1201.02
1.03
1.04
1.05
1.06
1.07
1.08x 10
4
simulation step
volt
ag
e /
V
controlled
static
~ 5 minutes
Considered Scenario
Near-critical voltage increase affected by photovoltaic and
wind generation at two substations is detected
(10.7 kV ≤ V < 10.8 kV)
www.grid4eu.eu 11
The German Demo Switching behaviour (II)
0 20 40 60 80 100 1201.02
1.03
1.04
1.05
1.06
1.07
1.08x 10
4
simulation stepvolt
ag
e /
V
controlled
static
1 2 3 4 5 0 7 6
~ 5 minutes
t
0:00:00*
0:08:00
0:10:00
0:10:30
0:11:30
0:11:40
0:12:50
0:25:00
0. Simulation started
1. ESL1* detected
2. Transition to ESL2
ESL2 treatment activation
3. Optimization started
4. Optimization finished
Switching Program generated
Execution activated
5. Execution started
switching process
6. Execution finished
ESL2 treatment deactivated
7. Simulation stopped
5
* ESL = Endangered State Level
Voltage improvement achieved Reaction time within the expected range Involved modules worked successfully
12
The German Demo Effects on reliability
HV/MV substation „Groß Reken“
3
2
5
6
4
1
Current state
System applied
Situation SAIDI in
min/a
ASIDI in
min/a
Current
state 12,8 14,9
System
applied 6,1 7,5
SAIDI
(System Average Interruption Duration Index)
Based on No of customers
ASIDI
(Average System Interruption Duration Index)
Based on apparent power / rated power of assets www.grid4eu.eu 13
The German Demo Field test phase in 2015
Stepwise operation approach towards operational autonomy
Phase 0 – Recording of measured values and signals
Phase 1 – Semi-automatic switching step 1
Phase 2 – Semi-automatic switching step 2
Phase 3 – Autonomous switching
Set of test cases clustered by
Test phases 0 – 3
Use cases (Threshold violation, FDIR, loss reduction)
Test components (hardware, communication, software modules)
“No switching”
“Switching via SCADA”
“Switching via central RTU in HV/MV substation”
www.grid4eu.eu 14
The German Demo Conclusion
Integrating a higher number of Renewable Energy is a key objective of the German Demo:
The dynamic reconfiguration of the grid topology enables an optimum connection of time-dependent load and feed-in oriented grid sections
Field implementation of the autonomously acting multi module system in Reken successfully finalized
Simulation results show the potential of an autonomous MV operating system
2015: Field test phase started
Dr. Lars Jendernalik
Westnetz GmbH, Germany
www.grid4eu.eu 15