The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20...

26
The Impact of the Internet of Things on our Lives. The Challenge of Legacy Assets Richard Lucas, BSc(Eng) MBA MD of ASH Wireless ASH Wireless is an electronics design consultancy Specialising in wireless and sensors

Transcript of The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20...

Page 1: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

The Impact of the Internet of Things on our Lives.

The Challenge of Legacy Assets

Richard Lucas, BSc(Eng) MBA

MD of ASH Wireless

ASH Wireless is an electronics design consultancy Specialising in wireless and sensors

Page 2: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

2

An Ofgem funded Network Innovation Competition project

Page 3: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

3

The problem

Assets have nominal thermal

rating

Ratings = OC

Ratings K amps

Diverse range of environments

Small changes in environmental

factors can result in very different

actual ratings

HV network

LV network

Assumed thermal ratings can lead to

capacity being under-utilised

or unnecessary risk

Objective is to maximise power

through transformer

Page 4: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

4

Celsius as part of the smart future

Celsius monitoring

Smart meter data

Thermal Ratings Tool

ReinforceRetrofit cooling

Extra capacity

Lower bills for customers

Page 5: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

5

Step 1: Fit thermal monitoring

Internal temperature

Asset

Environmental factors

External temperature

Thermal coefficient

Learning

Thermal Ratings

Tool

Deliverable

More capacity

Benefit

Page 6: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

6

Step 2: Retrofit cooling

Retrofit cooling

Internal temperature

Asset

Environmental factors

External temperature

Full capacity

Benefit

EnhancedThermal Ratings

Tool

Deliverable

Retrofit cooling specifications,

installation methodologies and buy order

Learning

Page 7: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

7

Partners and roles on project

Facilitate customer focus groups

Develop customer communication

materials

Lead the customer survey engagement

Analyse trial data

Develop methodologies to

understand relationship between

asset temperature, load characteristics

and surrounding environment

Determine impact of cooling technologies

Develop tool and spec for low cost

temperature sensor

Recommendations for BAU rollout

Supply complete retrofit monitoring

solution

Provide ongoing support throughout

installation, commissioning and

operation of the retrofit thermal

monitoring workstream

Peer review of the analysis

methodology of the retrofit temperature

sensor part of the project

An investigative study on the impact

of Celsius on the lifetime health of network assets

Work with ASH, Ricardo-AEA and Electricity North West to develop retrofit thermal

monitoring solution

Participate in evaluation and

selection of retrofit cooling techniques

Page 8: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

8

Monitoring site selection and timescales

To enable trials to take place during all seasons and to

trial all cooling techniques

Four year project

Subset of 520 substations –

enough sites to adequately trial all

techniques

100 cooling technique sites

Enough substations to

represent 80% of GB substation

population

520 substations

Page 9: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

9

Celsius

£5.5 million

Investment

Up to £583m across GB by

2050 Financial benefits

Awarded: 9th December 2015

Go live Monitoring installation Mar 2017

Monitoring trial

Mar 2018

Thermal ratings

tool stage 1

Oct 2018

Retrofit cooling

installationJun 2018

Cooling trial

Jun 2019

Thermal ratings

tool stage 2

Jan 2020

ClosedownMar 2020

Page 10: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

So the answer’s simple

1. Gather data on the power throughput & characteristics, asset temperature,

2. Work out the relationships, and how you can change these with retrofitted cooling technology

3. Decide how long you can postpone reinforcing or replacing assets,

4. Save lots of money

But there are some practical problems…………..

Page 11: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

11

Legacy Assets

▪ A significant percentage of electrical substations are more than half a century old

▪ Most are not installed with measurement equipment for voltage, current, power, power quality, temperature of key assets

▪ Critical infrastructure – any work must not intrude on continued operation.

▪ Access to the sites is restricted for safety reasons

Page 12: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

12

?How to fit monitoring sensors when…

▪ No internet connection available

▪ No mains power available

▪ Can’t install wiring, mount equipment, etc without intruding on critical operations

▪ Challenging RF environment for radio connections,, multipath, multiple monitoring points needed

Page 13: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

KeLVN- Design Requirements

▪ Monitoring system can be installed non-invasively;

▪ All equipment magnetic or cable-tie mounting;

▪ All equipment battery powered for duration of data gathering project (3.5 years).

▪ All equipment wireless, only leads are those required to actually take measurements.

▪ Daily reports to back end. 30 minute measurements of V, I, P, Q, THD, Temperature

Page 14: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

Backhaul Choices

• Clusters of sensors over a small area

• Spread over a large part of the country

• Mobile network is clear winner

• LPWAN

• Possible, but patchy network support

• 2.5G GPRS chosen

• Coverage, component cost

Page 15: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

Local Wireless Sensor Network

• Requirement for large substations (30m x 15m), sensors may be in cabinets

• Path loss at 2.4GHz expected less than 90dB

• Avoid stationary nulls by using antenna diversity

• Energy-efficient 802.15.4 transceivers used, no front-end-modules

• Operation needs to allow for more than one hub

• Large coverage

• Check installation from outside the substation

Page 16: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

Local Wireless Sensor Network

• Simple, non-paired network access, minimised energy

• Sensors transmit the last 6 hours of measurements (1 packet) every 30s

• Time-jittered to avoid multiple collisions from time-aligned sensors

• A hub listens for 60s for reports every 6 hours

• Hub transmits a daily report to a back-end database

• Hub operates for 3.5 years on a Lithium D-cell

• Other sensors use AA or D cells for >3.5 year life

Page 17: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

TT TT

Voltage Sensor

Temperature Sensor

GPRSBackhaul

Mobiledata link

Hub 1

Hub 2(optional)

Hex 1PMU

Hex 2 Ind.V,I,T

Low PowerRadioNetwork

Single Temperature Sensors

Back End

KeLVN- Substation Monitoring

Page 18: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

Battery Life

• The Hub is an interesting challenge:

• Lithium D-cell, 10AH

• Over 3.5 years life

• Distribution of where the capacity is used:KeLVN Hub battery usage

Daily GPRS data transfer

Sensor receiver window

Quiescent: ‘off’

Page 19: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

Key learning points

• The installation and environment defines

• Equipment design (e.g. magnetic mounting)

• Protocol (e.g. multiple hubs allowed)

• installation procedure (fast, non-invasive)

• GPRS modem auto-connect modes are not reliable, process needs detailed design

• Alarms

• Not required in Celsius

• Low latency for alarms is managed with a hub software extension, and external power to the hub

Page 20: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

Example of how legacy assets can be made to yield valuable data

Retrofitting monitoring equipment to legacy assets:

• Ease of installation is primary consideration

• Use of a local wireless sensor network eases installation

• Optimise air interface to manage trade off between latency, data rate, battery life

Page 21: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

Additional material

Page 22: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

22

Site selection map

Page 23: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

23

Celsius technology

Hub Wireless sensor

Page 24: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

24

Celsius technology – trial fit

LV board with three sensors

Page 25: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

25

Celsius technology – trial fit

Transformer

Page 26: The Challenge of Legacy Assets - University of Southampton · 2017. 3. 29. · 10 15 20 25 30 35-20 0 20 40 60 80 100 120 140 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016

26

Trial site data

-5

0

5

10

15

20

25

30

35

-20

0

20

40

60

80

100

120

140

30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016 12:00 02/10/2016 00:00 02/10/2016 12:00

Tem

pe

ratu

re D

egr

ee

s C

Re

al P

ow

er

kW p

er

Ph

ase

Magda Rd 750kVA Transformer Load and Temperatures

P1 kW P2 kW P3 kW Top Oil oC Inlet oC Outlet oC Bottom Oil oC