The Case for Schedule Risk Analysis Final - nflaace.org · The Case for Schedule Risk Analysis...

30
Francisco Cruz, PE, VDC The Case for Schedule Risk Analysis Section Meeting February 19, 2015

Transcript of The Case for Schedule Risk Analysis Final - nflaace.org · The Case for Schedule Risk Analysis...

Francisco Cruz, PE, VDC

The Case for

Schedule Risk Analysis

Section MeetingFebruary 19, 2015

Presentation Outline

• The Case for Project Risk Analysis• Risk Analysis Approach • Tools to Treat Risks• Final Remarks

There are lies, there are damned lies, and then there are deterministic schedules

Attributed to Dr. Vivek Puri, PMA’s resident simulation guru

2

Francisco Cruz - Background

• Senior Associate at PMA Consultants• Based in Tampa, Florida• Registered Professional Engineer (P.E.) in FL and PR• BS in Civil Engineering, M.Eng. in Construction Management• Experience of over 10 years spans pharmaceutical,

infrastructure, airports, municipal, and mixed-used projects. • Performing Cost and Schedule Risk Analysis on projects since

2007 on over 50 projects in 3 continents, ranging in size from less than $5 million to over $1 billion

• AACEi member since 2009

3

Risk Management Planning

Risk Management Planning

Assess(Identify & Analyze)

Assess(Identify & Analyze)

Treat (Plan & Implement)

Treat (Plan & Implement)

Control (Monitor &

Communicate)

Control (Monitor &

Communicate)

The New Normal in Project Management

Terminology:Risk Management –Soup to nuts strategy for identifying and controlling project or program risks.

*TCM Framework (Section 7.6)

4

The Case for Project Risk Analysis

* KPMG 2008 Global Construction Survey

55%

40%

36%

32%

19%

6%

4%

2%

26%

60%Material Price Escalation

Poorly Defined Scope

Contractual Disputes

Time Delay

Design Creep

Achieving Productivities

Lack of Approvals

Weather

Industrial Relations

Others

What are the three most common causes of cost overruns? *

Material Price Escalation

Poorly Defined Scope

Lack of Approvals

Contractual Disputes

Achieving Productivities

Commissioning Process

57%

36%

34%

21%

17%

15%

13%

2%

19%

57%

Design Creep

Weather

Time Delay

Others

What are the three most common causes of delays? *

According to the Bent Flyvbjerg’s Study on Large Projects,

• 9 out of 10 projects have cost overrun;

• Overrun is found across the 20 nations and five continents.

• Overrun is constant for the 70-year period covered by the study; cost estimates have not improved over time.

5

The Case for Project Risk Analysis

Main causes of underperforming projectsDid you have underperforming projects?

* KPMG Global Construction Survey 2013

What is the current performance in the construction industry?

6

Deterministic vs Probabilistic Schedules

Consider the following simple 2-activity schedule:

Start Activity A(12 weeks)

Activity B(10 weeks)

Finish

Deterministic Schedule

7

Start Activity A(12 weeks)

Activity B(10 weeks)

Finish

% critical = 100%

% critical = 0%

Project always to finish in 12 weeks

Deterministic vs Probabilistic Schedules

Deterministic Schedule

8

Start Activity A(12 weeks)

Activity B(10 weeks)

Finish

10 12 16

8 10 18

OPT MOST PESS

OPT MOST PESS

Activity B has much more variability to the

pessimistic side due to inherent risks of its work

Deterministic vs Probabilistic Schedules

Probabilistic Schedule

9

% critical = 63%

% critical = 37%

P10: 11.3 weeksP50: 13.1 weeksP90: 15 weeks

Start Activity A(12 weeks)

Activity B(10 weeks)

Finish

10 12 16

8 10 18

OPT MOST PESS

OPT MOST PESS

Deterministic vs Probabilistic Schedules

Probabilistic Schedule

10

The New Normal in Project Management

►Brings together and aligns stakeholders

►Vets and improves project scope, schedule and estimate

►Promotes recognition and transparency in project challenges

►Risk treatment reduces potential impacts

►Evaluates feasibility of targets

Risk Assessment process through probabilistic modeling is the next step in Project Management

11

How is the Schedule Contingency Typically Determined?

► Similar Project History

► Expert Judgment (a.k.a. Well-reasoned Heuristics)

► Rule-of-Thumb Guidelines

► Parametric Modeling

► Statistical Methods through Probabilistic Simulations

12

PMA’s Risk Assessment Approach

Qualitative Assessment

Review

IdentifyModel

Range

SimulateCritical & “Risk-sensitive” sequencesProject Risks & Uncertainty

Durations of Risks & Critical Activities

Summary Sequences,Probabilistic Branching

OPRA™NetRisk ™

Identify ModelRange

Simulate

Estimate Issues,Possible Risks & Response Plans

Develop Ranges forVariables: Scope, Price, Productivity, & Duration

Cost Breakdown,Variables, & Distributions

@Risk™ or Crystal Ball

Prioritize

Cost

Schedule

Quantitative Assessment

Summarize

* First Introduced at the 2004 AACEi Annual Meeting

13

Risk Register

Sample Risk Register used to prioritize risks and subsequently input in the quantitative model.

14

Risk Thresholds

Project team defines

thresholds to classify risks and reduce subjectivity

Figure 1: Defined Conditions for Probability Scales of a Risk

Very Low Low Medium High Very High

Probability 0% – 10% 11% to 30% 31% to 50% 51% to 70% >70%

  Figure 2: Defined Conditions for Impact Scales of a Risk on Major Project Objectives

Project Objective Very Low Low Medium High Very High

Cost Insignificant Cost Increase

<2% of TPC 2-7% Cost Increase

8-15% Cost Increase

>15% Cost Increase

Time 0-2 Week Time Increase

3-6 Week Time Increase

7-12 Week Time Increase

13-18 Week Time Increase

>18 Week Time increase

Scope

Scope Decrease Barely Noticeable

Minor Areas of Scope Affected

Major Areas of Scope Affected

Scope Reduction Unacceptable to PA

Project Does not Satisfy Original Intent at Completion

Quality

Quality Degradation Barely Noticeable

Only Most Demanding Specs Not Met

Degradation Requires PA Approval

Quality Reduction Unacceptable to PA

Major Re-work Required to Complete Project

 15

Prioritization

VH 5.00 5.00 10.00 15.00 20.00 25.00H 4.00 4.00 8.00 12.00 16.00 20.00M 3.00 3.00 6.00 9.00 12.00 15.00L 2.00 2.00 4.00 6.00 8.00 10.00

VL 1.00 1.00 2.00 3.00 4.00 5.001.00 2.00 3.00 4.00 5.00VL L M H VH

Probability-Impact Score Legend

High = > 9Med = 5 - 9Low = 1 - 4

Probability Threats

Impact

• Probability & Impact Matrix (P/I)

• Tolerance Thresholds

Tolerance is used to define

Risk appetite of the organization

16

Output Example: Cumulative Probability Distribution

The project schedule deterministic date of 16-Sep-14 is in the 24th

percentile of the simulation results distribution (including weather effects).

► Pre-treatment Results

► What about post-treatment analysis?

17

Contemporaneous Method /SRA

Tornado Diagram – Risks

4%

7%

12%

14%

15%

26%

36%

40%

41%

46%RD11 - FHWA Design Exception for substandard geometry not received by Q2, 2013

REN4 - NY Environmental permits not received by Q4'12

RD9 - Cash Collection is required in toll Lanes

RC20 - Restricted Work Hours may delay construction

RD2 - Procurement Process w ill take longer than 8 months therefore D/B contract w ill not ...

RC23 - Modif ied Toll Plaza collection not accepted for Toll Plaza delaying Traff ic

RD3 - Program not fully defined by Q1, 2012

RC14 - Relocation of Know n/Unknow n Utilities may cause cost and schedule overruns

RD1 - Design Package for Design Build w ill not be completed in Q2, 2013

RRW7 - ULURP process w ill affect property acquisition in NY

Duration Sensitivity

18

Risk Impact Analysis

19

Variation:175 Variation:111 Variation:73 Variation:82 Variation:144 Variation:19 Variation:128 Variation:13

Variation:127 Variation:72 Variation:59 Variation:25 Variation:119 Variation:85 Variation:54

Variation:5

22/ 09/ 2017 31/ 12/ 2017 10/ 04/ 2018 19/ 07/ 2018 27/ 10/ 2018 04/ 02/ 2019 15/ 05/ 2019 23/ 08/ 2019 01/ 12/ 2019 10/ 03/ 2020 18/ 06/ 2020 26/ 09/ 2020 04/ 01/ 20210%

20%

40%

60%

80%

100%

Cum

ulat

ive

Prob

abili

ty

Distribution AnalyzerRemoving RD1 - Finish DateRemoving RC14 - Finish Date

Removing RC23 - Finish DateRemoving RD2 - Finish Date

Removing RC20 - Finish DateRemoving REN4 - Finish Date

Removing RD9 - Finish DateRemoving RD11 - Finish Date

All Risks - Finish Date

Helps determine impact of each risk on project schedule

Output Example: End Node Diagram of Criticality

► In lieu of an unhelpful table of activities, a graphical representation of the activities most likely to influence project completion is provided.

20

Which percentile would youuse for your project?

• Most public agencies and private companies use the P80 through P90

• Some practitioners use a combination of two percentiles to set the baseline, schedule margin and management reserve (e.g., P50 and P80)

ID Public Agency / Private Company Confidence Level

Aerospace1 NASA 70%

Consultant

2Hulett and Associates (Project Risk Consultants)

80%

Energy3 NorthWestern (Montana, Nebraska, North Dakota) 95%

4US Energy Information Administration (EIA)

90%

Food, Health & Environmental5 FDA & USDA 95‐99%

6Forest Ecology and Management(Australia)

90%

7 Environmental Protection Agency (EPA) 90 & 95%

8 Environmental and Occupational Health ‐ Private Industry 95‐98%

Government9 US Corps of Engineers (CoE) 80%

10US Government Accountability Office (GAO)

70‐80%

11 USGS 90%Military

12 Air Force 80%Nuclear

13 US Nuclear Regulatory Commission (NRC) 90, 95, 98%Oil & Gas

14 British Petroleum (BP)50% (Adjusted Mean)*, 90%*

15 GeoGlobal Resources 90%16 Marathon 80%

Pharmaceutical17 Johnson & Johnson 75‐90%18 AstraZeneca 80%19 Siemens HealthCare 80%

Software20 Palisade @Risk 85‐90%

Transportation21 DOT 95%22 FRA 95%23 FTA 70 & 90%24 MTA 80%25 Wisconsin DOT 80%

26 FHWAMean, Standard Deviation, 90‐95%

27 PANYNJ 90%28 WSDOT 90%

21

Comparing ResultsWhat Do Pre and Post-Treatment Results have in Common?

22

Tools to Treat Risks

• Value Engineering• Constructability Reviews• Project Delivery Systems• Virtual Design and Construction

23

Risk Transfer Through Project Delivery Systems

* CMAA’s An Owner's Guide to Project Delivery Methods

1. Design/Bid/Build (DBB)a. Multiple-Prime Contracting

2. Design/Build (DB)a. Bridging b. Public Private Partnership (P3 or PPP)

3. Construction Management at Risk (CMAR or CM/GC)4. Integrated Project Delivery

24

Risk Allocation Through Contract Types

* RP-67R-11 Contract Risk Allocation

25

26

* 2014 Mortenson VDC Construction Analysis Report

Risk Monitoring and Control

27

Final Remarks

28

► Any project or contract schedule that is not risked through its life cycle does not conform to scheduling best practices

► Any schedule that does not expressly reserve reasonable schedule margin does not conform to best practices either

► Most deterministic schedules have less than 20% chance of meeting baseline dates; majority have even less than 1% chance.

► Post-treatment analysis is hardly ever performed; both pre and post-treatment analysis should be performed in tandem

► The use of VE, VDC, Constructability and Risk Management greatly increases the probabilities of project success

29

THANK YOU

Francisco Cruz, PE, VDCSenior AssociatePMA Consultants

[email protected]

30