Tajikistan Documentary Heritage Alla Aslitdinova Academy Library.
THE ACADEMY PROJECT-LIBRARY RENOVATIONS · the academy project library renovations issued for...
Transcript of THE ACADEMY PROJECT-LIBRARY RENOVATIONS · the academy project library renovations issued for...
1809 BARRINGTON St
Suite 1009
Halifax NS B3J 3U8
Canada
Tel: (902) 421-1065
THE ACADEMY PROJECT-LIBRARY RENOVATIONS
CONTRACT# 17-353541B
ISSUED FOR TENDER
JANUARY 15, 2018
INFORMATION
I-002 COVER SHEET
H353541-I-002 REV B
ARCHITECTURAL - *REFER TO ARCHITECTURAL DRAWINGS FOR REVISION NUMBER
A-100 DEMOLITION PLAN & PROPOSED FLOOR PLAN DIMENSION PLAN
H353541-A-100
A-101 PROPOSED FLOOR PLAN & PROPOSED REFLECTED CEILING PLAN
H353541-A-101
A-102 FLOORING PLAN & FINISH SCHEDULE
H353541-A-102
A-103 DETAILS
H353541-A-103
A-104 DETAILS CONT.
H353541-A-104
A-105 MILL WORK
H353541-A-105
A-106 WASHROOMS
H353541-A-106
A-107 SCHEDULES
H353541-A-107
A-108 SPECIFICATIONS
H353541-A-108
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
ISSUED FOR TENDER
ISSUE - REV B
www.hatch.com
MECHANICAL
M-001 BASEMENT PLUMBING FLOOR PLANS, DETAILS & LEGEND
H353541-M-001 REV B
M-002 BASEMENT HEATING FLOOR PLAN, SCHEDULE & LEGEND
H353451-M-002 REV B
M-003 BASEMENT HVAC FLOOR PLAN, SCHEDULES, DETAILS & LEGEND
H353451-M-003 REV B
M-004 BASEMENT FIRE PROTECTION FLOOR PLAN, DETAILS & LEGEND
H353451-M-004 REV B
M-010 MECHANICAL SPECIFICATIONS SHEET 1
H353451-M-010 REV B
M-011 MECHANICAL SPECIFICATIONS SHEET 2
H353451-M-011 REV B
M-012 MECHANICAL SPECIFICATIONS SHEET 3
H353451-M-012 REV B
ELECTRICAL
E-001 EXISTING BASEMENT LIGHTING, POWER, COMMUNICATION, FIRE ALARM PLANS & LEGEND
H353451-E-001 REV B
E-002 NEW BASEMENT LIGHTING, POWER, COMMUNICATION, FIRE ALARM PLANS & LEGEND
H353451-E-002 REV B
E-003 ELECTRICAL DETAILS & SCHEDULES
H353451-E-003 REV B
E-010 ELECTRICAL SPECIFICATIONS SHEET 1
H353451-E-010 REV B
240 ST. GEORGE STREET, BOX 458
ANNAPOLIS ROYAL, NS
P:(902) 532-2395 F:(902) 532-7707
UP UPN
46' -
3 1
/2"
16' - 6" 6' - 0"
19' - 1"
17' -
3"
14' -
0"
14' -
0"
7' -
0"
20' - 1"
11' -
9"
11' -
3"
10' -
8 1
/2"
19' -
0 1
/2"
18' - 7"8' - 0"
58' -
4"
40' - 0"
RAMP UP
REMOVE ALL EXISTING PLUMBING FIXTURES AND ASSOCIATED PLUMBING LINES
REMOVE EXISTING STEEL RAILING
43' - 0"
EXISTING PASS-THRU WINDOWS TO REMAIN
GENERAL NOTES: 1. DASHED LINES INDICATE WALLS & DOORS TO BE REMOVED.2. ALL EXISTING COLUMNS TO REMAIN.3. REMOVE EXISTING FLOORING IN CONTRACT AREA AND PREPARE SUBFLOOR
TO RECEIVE NEW FLOORING.4. REMOVE EXISTING CEILING TILE AND GRID IN CONTRACT AREA.5. PATCH AND REPAIR WALLS TO REMAIN.
SHADED AREA NOT IN CONTRACT
5' - 0"16' - 6"
9' -
0"
REMOVE EXISTING WINDOWS (TO BE BLOCKED UP)
REMOVE INTERIOR SCREENS
MAIN PLUMBING LINE TO REMAIN
RITCHIE ST.
NGR
ANG
E ST
.
KEY PLAN
10' - 0" 20' - 0"
N
326 SF
QUIET ROOM1
1252 SF
STACKS &READING
2
JANITOR
1044 SF
BAND ROOM8
669 SF
FOOD BANK7
399 SF
PROGRAM9
FAM./B.F. WR.
WR.
16' - 6"
WR.
87 SF
STORAGE11
OFFICE
EXISTING RAMP UP
BOILER ROOM
6' - 3" 5' - 0" 14' - 4"
GENERAL NOTES:1. NEW CEILINGS THROUGHOUT CONTRACT AREA, SEE REFLECTED CEILING PLAN.2. NEW EXTERIOR WINDOWS WHERE NOTED. 3. NEW FLOORING THROUGHOUT CONTRACT AREA.4. ALL EXISTING COLUMNS TO RECEIVE INTUMESCENT PAINT AS REQUIRED TO
ACHIEVE 45 MIN FIRE-RATING.5. ALL WALLS ARE W1 TYPE UNLESS OTHERWISE NOTED.
1503 SF
COMMON15
2' - 6" 11' - 0"
379 SF
INNOVATIONCENTRE
12
SHADED AREA NOT IN CONTRACT
7' -
0"
INFI
LL
+/- 7
' - 0
"
INFI
LL
+/- 6
' - 0
"
INFI
LL
+/- 6
' - 0
"
EQU
ALEQ
UAL
6' - 3"
14' - 5"
11' -
5 1
/2"
8' -
6"7'
- 2"
8' -
4"10
' - 1
1"
23' -
0"
EQUAL EQUAL
6' -
0"EQ
EQ
7' - 3"
7' -
1"7'
- 1"
INFI
LL
+/- 9
' - 0
"
6' -
8"3'
- 9"
8' -
2"4'
- 0"
5' -
5"
2' -
8"
2' -
6"
2' -
8"
23' -
4 1
/2"
20' - 7" 8' - 5"
8' - 0"
19' -
0 1
/2"
13' - 10"
18' - 9 1/2"
36' -
0 1
/2"
21' - 6"
23' - 0"
3' -
9"3'
- 0"
2' -
0"
3' -
0"
31' -
8 1
/2"
15' -
10
1/2"
11' -
7 1
/2"
2' - 8" 3' - 1" 2' - 8" 1' - 2"
21' -
0 1
/2"
25' -
8 1
/2"
9' -
0"
EXISTING RISERS TO REMAIN
JOST ARCHITECTS LTD.240 ST. GEORGE STREET, BOX 458
ANNAPOLIS ROYAL, NSP:(902) 532-2395 F:(902) 532-7707
1. CONTRACTOR MUST VERIFY ALL DRAWINGS WITH ON-SITE CONDITIONS, REPORTING ANY DISCREPANCY TO ARCHITECT BEFORE PROCEEDING WITH WORK.2. DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED BY THE ARCHITECT.3. DRAWINGS ARE NOT TO BE SCALED.4. ALL WORK IS TO COMPLY WITH THE 2015 NATIONAL BUILDING CODE AND ALL APPLICABLE CODES.5. CONTRACTOR TO RECEIVE WRITTEN APPROVAL FROM ARCHITECT PRIOR TO INSTALLATION OF ALTERNATE PRODUCTS.
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
HALIFAX, NOVA SCOTIA
- -
-
A ISSUED FOR TENDER 18/01/15
1809 BARRINGTON ST.
H353541-A-000
As indicated
THE ACADEMY PROJECTLIBRARY RENOVATIONS
DEMOLITION PLANPROPOSED FLOOR PLAN - DIMENSION PLAN
LW
1702
HJ
A-100
LW
A-100
HJ HJ
M. BROWN1/8" = 1'-0"1 DEMOLITION PLAN
1/8" = 1'-0"2PROPOSED FLOOR PLAN - DIMENSIONPLAN
DEMOLITION NOTES:
1. SHOULD MATERIAL RESEMBLING SPRAY OR TROWEL-APPLIED ASBESTOS OR OTHER DESIGNATED SUBSTANCE LISTED AS HAZARDOUS BE ENCOUNTERED, STOP WORK, TAKE PREVENTATIVE MEASURES, AND NOTIFY ARCHITECT IMMEDIATELY. DO NOT PROCEED UNTIL WRITTEN INSTRUCTIONS HAVE BEEN RECEIVED FROM ARCHITECT.
2. INSPECT BUILDING SITE WITH ARCHITECT AND VERIFY EXTENT AND LOCATION OF ITEMS DESIGNATED FOR REMOVAL, DISPOSAL, ALTERATIVE DISPOSAL, RECYCLING, SALVAGE AND ITEMS TO REMAIN.3. LOCATE AND PROTECT UTILITIES. PRESERVE ACTIVE UTILITIES TRAVERSING SITE IN OPERATING CONDITION.4. NOTIFY AND OBTAIN APPROVAL OF UTILITY COMPANIES BEFORE STARTING DEMOLITION.5. DISCONNECT, CAP, PLUG OR DIVERT, AS REQUIRED, EXISTING PUBLIC UTILITIES WITHIN THE PROPERTY WHERE THEY INTERFERE WITH THE EXECUTION OF THEWORK, IN CONFORMITY WITH THE
REQUIREMENTS OF THE AUTHORITIES HAVING JURISDICTION. MARK THE LOCATION OF THESE PREVIOUSLY CAPPED OR PLUGGED SERVICES ON THE SITE AND INDICATE LOCATION (HORIZONTAL AND VERTICAL) ON THE RECORD DRAWINGS. SUPPORT, SHORE UP AND MAINTAIN PIPES AND CONDUITS ENCOUNTERED.
6. IMMEDIATELY NOTIFY ARCHITECT AND UTILITY COMPANY CONCERNED IN CASE OF DAMAGE TO ANY UTILITY OR SERVICE, DESIGNATED TO REMAIN IN PLACE.7. IMMEDIATELY NOTIFY THE ENGINEER SHOULD UNCHARTED UTILITY OR SERVICE BE ENCOUNTERED, AND AWAIT INSTRUCTION IN WRITING REGARDING REMEDIAL ACTION.8. PREVENT MOVEMENT, SETTLEMENT, OR DAMAGE TO ADJACENT STRUCTURES, UTILITIES, AND PARTS OF BUILDING TO REMAIN IN PLACE. PROVIDE BRACING AND
SHORING REQUIRED.9. KEEP NOISE, DUST, AND INCONVENIENCE TO OCCUPANTS TO MINIMUM.10. PROTECT BUILDING SYSTEMS, SERVICES AND EQUIPMENT.11. PROVIDE TEMPORARY DUST SCREENS, COVERS, RAILINGS, SUPPORTS, AND OTHER PROTECTION AS REQUIRED.12. REFER TO DEMOLITION DRAWINGS AND SPECIFICATIONS FOR ITEMS TO BE SALVAGED FOR REUSE. REMOVE ITEMS TO BE REUSED, STORE AS DIRECTED BY ARCHITECT, AND RE-INSTALL AS
DIRECTED ON APPROPRIATE DRAWING.13. REMOVE PARTS OF EXISTING BUILDING TO PERMIT NEW CONSTRUCTION. SORT MATERIALS INTO APPROPRIATE PILES FOR REUSE AND RECYCLING.14. DISPOSE OF REMOVED MATERIALS, TO APPROPRIATE RECYCLING FACILITIES & REUSE FACILITIES EXCEPT WHERE SPECIFIED OTHERWISE, IN ACCORDANCE WITH AUTHORITY HAVING JURISDICTION.
H353541-A-10018/01/15
UP
10' - 0" 20' - 0"
N
326 SF
QUIET ROOM1
1252 SF
STACKS &READING
2
30 SF
JANITOR6
1044 SF
BAND ROOM8
NEW WINDOWS WHERE PREVIOUS WINDOWS WERE BLOCKED IN (3)(SIZE TO SUIT)
399 SF
PROGRAM9
FAM./B.F. WR.
WR.
NEW GLASS DOOR & SIDELITE
NEW GLASS DOOR & SIDELITE
EXISTING PASS-THRU WINDOWS & ROLL-UP GRILLES TO REMAIN
WR.
87 SF
STORAGE11
OFFICE
OPEN UP BLOCKED DOORWAY. WIDEN OPENING TO INSTALL NEW DOUBLE DOOR (SEE DOOR SCHEDULE)
EXISTING RAMP UP
243 SF
BOILER ROOM5
NEW INTERIOR WINDOW WITH FIRE-RATED GLASS
GENERAL NOTES:1. NEW CEILINGS THROUGHOUT CONTRACT AREA. SEE REFLECTED CEILING PLAN.2. NEW WINDOWS WHERE NOTED. 3. NEW FLOORING THROUGHOUT CONTRACT AREA.4. ALL EXISTING COLUMNS TO RECEIVE INTUMESCENT PAINT AS REQUIRED TO ACHIEVE 45 MIN FIRE-RATING.5. ALL EXISTING TRIMS TO BE PAINTED6. ALL REMAINING EXISTING WALLS TO BE PATCHED, REPAIRED & PAINTED
NEW INTERIOR GLASS WINDOWS AT FORMER DOOR LOCATION
NEW FIRE-RATED BI-PARTING DOORS.(SEE DOOR SCHEDULE)
1503 SF
COMMON15
NEW INTERIOR WINDOWS WHERE PREVIOUS WINDOWS WERE BLOCKED UP (2)(SIZE TO SUIT)
EXISTING DOORS TO REMAIN
379 SF
INNOVATIONCENTRE
12
BOX AROUND 4" SANITARY LINE DOWN FROM FLOOR ABOVE
SHADED AREA NOT IN CONTRACT
RISERS TO REMAININFILL DOORWAYS TO MATCH ADJACENT WALLS
NEW DOORWAY WHERE PREVIOUS WINDOW WAS BLOCKED UP
NEW MOP SINK; SEE MECH.
W6
W1
A-1064
S1
NEW INTERIOR GLASS WINDOW AT FORMER DOOR LOCATION
INFILL INTERIOR WINDOWS TO MATCH ADJACENT WALLS
ADD ACOUSTIC BATT INSULATION TO INTERIOR PERIMETER WALLS OF BAND ROOM
BUILT-IN COAT/BOOT CUBBIES
NEW VEGETABLE WASH SINK; SEE MECH.
TRIM & FINISH DOOR OPG. WHERE EXISTING INTERIOR LIGHTS WERE REMOVED.
W1 REPLACE EXISTING WINDOWS (SIZE TO SUIT)
REPLACE EXISTING WINDOW
W4
S2
W2
W2
S2 S2
3A-103
2A-103
WOOD
4A-103
1A-103
2A-104
A-105 1
A-105 2
3
A-105
6
8A
2B
2A
3A
1A
9A
9B 10A
13A
14A
12A
12B 11A
5A
6A
7A
7B
12C
CORR.
THE
ACAD
EMY
15A
15B
S3
S3
S3
669 SF
FOOD BANK7
S2
WALL BUILT UP FROM SILL
EXISTING SILL & TRIM TO REMAIN. PATCH, REPAIR & PAINT (COLOR TO BE DETERMINED)
W2
W1
W1
W1
W1
W1
W1
W2W2
W1
W1
W1
W1
W1
W3
W3
W3
REPLACE EXISTING WINDOWS (WINDOWS TO BE PROVIDED BY OWNER)
PATCH, REPAIR & PAINT EXISTING DOORS, WALLS, RISERS, RAILINGS, TRIMS & FINISHES (SEE FLOOR FINISH PLAN FOR FLOORING)
W5
W5
5A-103
FILL OPENING w/ DRYWALL
RITCHIE ST.
NGR
ANG
E ST
.
KEY PLAN
DRYWALL BULKHEAD AT 7'-6" A.F.F.
BULKHEAD AT 7'-6" A.F.F.
BULKHEAD AT 7'-6" A.F.F.
LED STRIP AROUND INNER SIDE OF BULKHEAD3
A-103
3' -
0"
2' -
0"
3' - 0"
3' - 0"
3' -
0"
3' - 0"
2' -
0"
3' - 0"
2' - 0"
2' - 0"
2' -
0"
2A-103
4A-103
RADIANT PANEL
TYP. RADIANT PANEL
1A-103
3' - 0"
2A-104
1A-104
3A-104
LINE OF A.C.T. ABOVE BULKHEAD
LINE OF SLOPED A.C.T. CEILING
N
1' - 0"
2' - 6"
5' - 6 1/2" 1' - 0"
CENTRE TILES
EQ. EQ.
CENTRE TILE IN ROOM
SHADED AREA NOT IN CONTRACT
START w/ FULL A.C.T. @ RADIANT PANEL
START w/ FULL A.C.T. @ RADIANT PANEL
EXPOSED CEILING
REFLECTED CEILING PLAN NOTES:1. ALL CEILINGS @ 8' - 0" A.F.F. EXCEPT WHERE OTHERWISE NOTED.2. SEE MECHANICAL FOR RADIANT PANELS3. A.C.T. 1; 24"x24" ACOUSTIC CEILING TILES TO BE "CIRRUS" BY ARMSTRONG. (SQUARE EDGE) COLOUR TO BE WHITE.4. A.C.T. 2; 24"x24" COFFER CEILING TILES TO BE "METAPHORS" BY ARMSTRONG. COVE ITEM #5727 WITH 18"x18"x0.75" BEVELED TEGULAR ULTIMA INFILL PANEL. COLOUR TO BE WHITE.5. INSTALL NEW CONTINUOUS 3-1/2" INSULATION ABOVE ALL NEW CEILINGS.6. ALL SUSPENDED CEILING GRID TO BE INSTALLED WITH RESILIENT HANGERS.
THE
ACAD
EMY
8' - 11 1/2"
1' - 0"
1' - 0"
PAINT EXISTING CEILINGS
RCP LEGENDRADIANT PANEL (SEE MECH.)
A.C.T. 1 (ACOUSTIC CEILING TILE)
POT LIGHT (SEE MECH.)
PENDANT LIGHT (SEE MECH.)
SUPPLY VENT (SEE MECH.)
RETURN VENT (SEE MECH.)
2 x 2 LIGHTS (SEE MECH.)
A.C.T. 2 (COFFER CEILING TILE)
TRACK LIGHT (SEE MECH.)
WALL TYPESW1 - 5/8" GYPSUM BOARD 2x4 WOOD STUD @ 16" o.c. 5/8" GYPSUM BOARD
W2 - 5/8" GYPSUM BOARD 2x4 WOOD STUD @ 16" o.c. (INFILLED WITH ACOUSTIC BATT INSULATION) 5/8" GYPSUM BOARD
W3 - 2" x 3" WOOD STUD 5/8" GYPSUM BOARD ON ONE SIDE ONLY
JOST ARCHITECTS LTD.240 ST. GEORGE STREET, BOX 458
ANNAPOLIS ROYAL, NSP:(902) 532-2395 F:(902) 532-7707
1. CONTRACTOR MUST VERIFY ALL DRAWINGS WITH ON-SITE CONDITIONS, REPORTING ANY DISCREPANCY TO ARCHITECT BEFORE PROCEEDING WITH WORK.2. DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED BY THE ARCHITECT.3. DRAWINGS ARE NOT TO BE SCALED.4. ALL WORK IS TO COMPLY WITH THE 2015 NATIONAL BUILDING CODE AND ALL APPLICABLE CODES.5. CONTRACTOR TO RECEIVE WRITTEN APPROVAL FROM ARCHITECT PRIOR TO INSTALLATION OF ALTERNATE PRODUCTS.
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
HALIFAX, NOVA SCOTIA
- -
-
A ISSUED FOR TENDER 18/01/15
1809 BARRINGTON ST.
H353541-A-000
As indicated
THE ACADEMY PROJECTLIBRARY RENOVATIONS
PROPOSED FLOOR PLAN & PROPOSEDREFLECTED CEILING PLAN
LW
1702
HJ
A-101
LW
A-101
HJ HJ
M. BROWN
1/8" = 1'-0"1 PROPOSED FLOOR PLAN1/8" = 1'-0"2 PROPOSED REFLECTED CEILING PLAN
18/01/15
RADIUS TO MATCH THAT OF BULKHEAD ABOVE
6' -
9 1/
2"
21' -
0"
24' - 6 1/4"
TRANSITION STRIP
L-2
L-2
TRANSITION STRIP
L-2
L-2
L-2
STAIR NOSING
L-1 L-1
L-1
L-1
L-1
L-2
L-1
3' -
0"
L-2
L-2L-2
L-1
L-1
L-1
L-1
8' - 11" L-1
L-1
L-1 L-1
UNFINISHED FLOOR
QUIET ROOM1
STACKS &READING
2
COMMON15
FOOD BANK7
BAND ROOM8INNOVATION
CENTRE12
PROGRAM9
JANITOR6
CORR.16
WR.14
WR.13
STORAGE11
FAM./B.F. WR.10
BOILER ROOM5
OFFICE3
L-1
L-1L-1
L-2
RE-FINISH EXISTING VCT
INSTALL NEW RUBBER STAIR TREADS TO MATCH EXISTING.
TRANSITION STRIP
5A-103
JOST ARCHITECTS LTD.240 ST. GEORGE STREET, BOX 458
ANNAPOLIS ROYAL, NSP:(902) 532-2395 F:(902) 532-7707
1. CONTRACTOR MUST VERIFY ALL DRAWINGS WITH ON-SITE CONDITIONS, REPORTING ANY DISCREPANCY TO ARCHITECT BEFORE PROCEEDING WITH WORK.2. DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED BY THE ARCHITECT.3. DRAWINGS ARE NOT TO BE SCALED.4. ALL WORK IS TO COMPLY WITH THE 2015 NATIONAL BUILDING CODE AND ALL APPLICABLE CODES.5. CONTRACTOR TO RECEIVE WRITTEN APPROVAL FROM ARCHITECT PRIOR TO INSTALLATION OF ALTERNATE PRODUCTS.
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
HALIFAX, NOVA SCOTIA
- -
-
A ISSUED FOR TENDER 18/01/15
1809 BARRINGTON ST.
H353541-A-000
1/8" = 1'-0"
THE ACADEMY PROJECTLIBRARY RENOVATIONS
FLOORING PLAN & FINISH SCHEDULE
STAFF
1702
HLS
A-102
STAFF
A-102
HLS HJ
M. BROWN
1/8" = 1'-0"1 FLOOR FINISH PLAN
ROOM FINISH SCHEDULE
CODE MATERIAL MANUFACTURER PRODUCT COLOR
L-1 SHEET LINOLEUM : COLOUR 1 FORBO FLOORING SOLUTIONS MARMOLEUM REAL T.B.D.L-2 SHEET LINOLEUM : COLOUR 2 FORBO FLOORING SOLUTIONS MARMOLEUM REAL T.B.D.GB-P GYPSUM BOARD, PAINTED: COLOUR 1 PPG INTERIOR ACRYLIC LATEX T.B.D.ACT-1 ACOUSTIC CEILING TILE ARMSTRONG "CIRRUS" WHITEACT-2 ACOUSTIC CEILING TILE ARMSTRONG "METAPHOR" WHITEWB WOOD BASE N/A N/A T.B.D.
DEFAULT ROOM FINISH SCHEDULE
ROOM NUMBER DESCRIPTION AreaFLOOR
WALL BASECEILING
FINISH COMMENTS FINISH COMMENTS1 QUIET ROOM 326 SF L-1 GB-P WB ACT-1 / ACT-2 SEE RCP2 STACKS & READING 1252 SF L-1 / L-2 SEE FLOOR FINISH PLAN GB-P WB ACT-1 / GB-P SEE RCP3 OFFICE 88 SF L-1 GB-P WB ACT-1 / GB-P SEE RCP4 STORAGE Not
PlacedL-1 GB-P WB ACT-1
5 BOILER ROOM 243 SF N/A GB-P WB EXPOSED6 JANITOR 30 SF L-1 GB-P WB EXPOSED7 FOOD BANK 669 SF L-1 GB-P WB ACT-18 BAND ROOM 1044 SF L-1 / L-2 SEE FLOOR FINISH PLAN GB-P WB ACT-19 PROGRAM 399 SF L-1 GB-P WB ACT-1 / GB-P SEE RCP10 FAM./B.F. WR. 82 SF L-2 GB-P WB ACT-111 STORAGE 87 SF L-1 GB-P WB ACT-112 INNOVATION
CENTRE379 SF L-1 GB-P WB ACT-1 / GB-P SEE RCP
13 WR. 40 SF L-2 GB-P WB ACT-114 WR. 40 SF L-2 GB-P WB ACT-115 COMMON 1503 SF L-1 / L-2 SEE FLOOR FINISH PLAN GB-P WB ACT-1 / GB-P SEE RCP
GENERAL FINISH NOTES:1. WOOD BASE THROUGHOUT TO MATCH EXISTING. COLOUR T.B.D.2. FLOOR PATTERN AS INDICATED ON FLOOR FINISH PLAN.3. SEE REFLECTED CEILING PLAN FOR CEILING FINISH.4. ALL DOORS TO BE PAINTED. COLOUR T.B.D.5. ALL WALLS TO BE P-1 EXCEPT WHERE NOTED OTHERWISE.6. ALL GYPSUM BULKHEADS TO BE PAINTED WHITE UNLESS OTHERWISE NOTED.7. DOOR & WINDOW TRIM TO MATCH EXISTING IN SIZE AND PROFILE. COLOUR T.B.D.
18/01/15
29"
EXISTING HALFWALL TO BE EXTENDED ABOVE NEW CEILING (+/- 8' - 0" A.F.F.)
RADIANT HEAT PANEL
24" X 24" ACT CEILING (8' - 0" A.F.F.)
LINE OF EXISTING BULKHEAD TO BE EXTENDED
EXTENDED BULKHEAD
+/- 1
0' -
0" A
.F.F
.
1' - 6 1/2"0' - 8 1/2"
EXISTING CEILING HEIGHT
0' -
4"
REMOVE EXISTING WOOD SILL / TRIM
20"
LIBRARY BULKHEAD @ 7' - 8" A.F.F.
24" X 24" ACT @ 8' - 0" A.F.F. IN OFFICE
GWB TO 2" ABOVE CEILING
0' -
4"
FASTEN TO EXISTING STRUCTURE2x8
17 3
/4"
0' - 11" 1' - 0 1/2"
RADIANT HEAT PANEL
24" X 24" ACT (8' - 8" A.F.F.)
EXTEND BULKHEAD
LINE OF EXISTING BULKHEAD TO BE EXTENDED
5"
0' -
0 3/
4"
+/-1
0' -
0" A
.F.F
.
8' -
0"
+/- 1
0' -
0" A
.F.F
.
5' -
2"
INTERIOR HALFWALL TO BE EXTENDED UP TO SILL HEIGHT
EXISTING CEILING HEIGHT
NEW BULKHEAD
RADIANT HEAT PANEL
24" X 24" ACT (8' - 0" A.F.F.)
28 3
/4"
5"
1' - 3" 3' - 0"
0' -
4"
NEW WINDOW SILL TO SUITCONDITIONS
1' - 0"
7' -
8"
LINE OF EXTENDED WALL BEYOND
4' -
8"
2' - 0"
2' -
0"
TWO LAYERS 3/4" PLYWOOD w/ BULLNOSE EDGE
2 X 4 WOOD FRAMING
INTERIOR HALFWALL TO BE EXTENDED UP TO SILL HEIGHT
NEW WINDOW SILL TO SUITCONDITIONS
W4
DRYWALL
BASEBOARD
1-1/4" OVERHANG TO ACCOMMODATE DRYWALL & 3/4" ACCENT TRIM UNDER SEAT LIP
OUTLET - SEE ELECT.
JOST ARCHITECTS LTD.240 ST. GEORGE STREET, BOX 458
ANNAPOLIS ROYAL, NSP:(902) 532-2395 F:(902) 532-7707
1. CONTRACTOR MUST VERIFY ALL DRAWINGS WITH ON-SITE CONDITIONS, REPORTING ANY DISCREPANCY TO ARCHITECT BEFORE PROCEEDING WITH WORK.2. DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED BY THE ARCHITECT.3. DRAWINGS ARE NOT TO BE SCALED.4. ALL WORK IS TO COMPLY WITH THE 2015 NATIONAL BUILDING CODE AND ALL APPLICABLE CODES.5. CONTRACTOR TO RECEIVE WRITTEN APPROVAL FROM ARCHITECT PRIOR TO INSTALLATION OF ALTERNATE PRODUCTS.
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
HALIFAX, NOVA SCOTIA
- -
-
A ISSUED FOR TENDER 18/01/15
1809 BARRINGTON ST.
H353541-A-000
1" = 1'-0"
THE ACADEMY PROJECTLIBRARY RENOVATIONS
DETAILS
STAFF
1702
HJ
A-103
STAFF
A-103
HJ HJ
M. BROWN1" = 1'-0"1 BULKHEAD DETAIL - LIBRARY
1" = 1'-0"2 BULKHEAD DETAIL - LIBRARY & OFFICE1" = 1'-0"3BULKHEAD DETAIL - PROG.RM & INNOV.CENTRE
1" = 1'-0"4BULKHEAD DETAIL - LIBRARY ATWINDOW
1" = 1'-0"5 WINDOW SEAT DETAIL
18/01/15
0' -
3"
0' -
11"
2' X 2' A.C.T. @ 8'-0" A.F.F.
NEW GYPSUM BOARD CEILING @ U.S. JOISTS
4' - 0 1/2"
0' - 4"
2x4 WOOD STUD
LIGHT FIXTURE; SEE ELECT.
A-1044
A-1045
3' - 11"
3' - 10 1/2"
1' - 0" 2' - 6"
FASTEN TO EXISTING STRUCTURE ABOVE
WOOD FRAME
STACKS &READING
COMMON
U.S. AT 8'-0"
POT LIGHTS; SEE MECH.
0' - 10"
0' -
6"
TYP. 3/4" QUARTER ROUND
TWO LAYERS 3/4" PLYWOOD w/ BULLNOSE EDGE
1x6 WOOD TRIM
TYP. 3/4" QUARTER ROUND
2x3 WOOD BLOCKING TYP. 3/4" QUARTER ROUND
U/S GYPSUM BULKHEAD
AXIOM FINISH TRIM
FASTEN TO EXISTING STRUCTURE
8' - 0" A.F.F.
MOUNT LED STRIP ON WOOD BLOCKING
0' -
4"
0' - 8"
W1
2x3
TYP. 3/4" QUARTER ROUND
0' -
3"0'
- 1
1/2"
1x3 WOOD TRIM
TWO LAYERS 3/4" PLYWOOD w/ BULLNOSE EDGEPAINTED FINISH (SEE COLOUR SCHEDULE)
W1
2x3 WOOD BLOCKING
INTERIOR SCREEN JAMB DETAIL SIMILAR
0' -
3"
0' - 6 3/4"
TYP. 3/4" QUARTER ROUND
WOOD TRIM TO MATCH EXISTING
0' - 3" 0' - 1 1/2"
TRIM TO MATCH EXISTING COLOUR T.B.D.
SHIM
DOOR FRAME
DOOR HEAD DETAIL SIMILAR
W1
EXTERIOR INTERIOR
METAL FRAME TO LIE FLUSH WITH EXISTING GYPSUM BOARD FINISH
WOOD TRIM TO MATCH EXISTING;OVERLAP METAL FRAME PARTIALLY
NEW GYPSUM BOARD FINISH
WOOD SILL
WOOD TRIM
EXISTING WALL CONST.
EXTERIOR INTERIOR
EXISTING WALL CONST. NEW GYPSUM BOARD FINISH
WOOD TRIM WOOD TRIM TO MATCH EXISTING;OVERLAP METAL FRAME PARTIALLY
METAL FRAME TO LIE FLUSH WITH EXISTING GYPSUM BOARD FINISH
JOST ARCHITECTS LTD.240 ST. GEORGE STREET, BOX 458
ANNAPOLIS ROYAL, NSP:(902) 532-2395 F:(902) 532-7707
1. CONTRACTOR MUST VERIFY ALL DRAWINGS WITH ON-SITE CONDITIONS, REPORTING ANY DISCREPANCY TO ARCHITECT BEFORE PROCEEDING WITH WORK.2. DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED BY THE ARCHITECT.3. DRAWINGS ARE NOT TO BE SCALED.4. ALL WORK IS TO COMPLY WITH THE 2015 NATIONAL BUILDING CODE AND ALL APPLICABLE CODES.5. CONTRACTOR TO RECEIVE WRITTEN APPROVAL FROM ARCHITECT PRIOR TO INSTALLATION OF ALTERNATE PRODUCTS.
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
HALIFAX, NOVA SCOTIA
- -
-
A ISSUED FOR TENDER 18/01/15
1809 BARRINGTON ST.
H353541-A-000
As indicated
THE ACADEMY PROJECTLIBRARY RENOVATIONS
DETAILS CONT.
STAFF
1702
HJ
A-104
STAFF
A-104
HJ HJ
M. BROWN
1 1/2" = 1'-0"1 BULKHEAD DETAIL - SMALL CIRCLES
1 1/2" = 1'-0"2 C/W SECTION3" = 1'-0"4 C/W DETAIL - SILL
3" = 1'-0"5 C/W DETAIL - HEAD
1 1/2" = 1'-0"3BULKHEAD DETAIL - LIBRARY CENTERELEMENT
3" = 1'-0"6 INTERIOR SCREEN SILL DETAIL
3" = 1'-0"7 INTERIOR SCREEN HEAD DETAIL
3" = 1'-0"9 TYPICAL DOOR FRAME JAMB DETAIL3" = 1'-0"8 METAL FRAME - SILL DETAIL
3" = 1'-0"10 METAL FRAME - HEAD DETAIL
18/01/15
3' -
0"
0' -
3"
1' - 3"
4' - 9"
1' - 6" 1' - 6" 1' - 6"
3' -
0"
+/- 5
' - 0
'
2' -
6"
1' - 7 1/2"1' - 7 1/2"
2' -
5"2'
- 5"
1' - 8"
2' -
1"
2' -
0"
7' -
5"
1' - 6" 1' - 6" 1' - 6"
2' -
3"
3' - 6"
0' -
3"
PRINTER
6' - 5"
2' -
3"2'
- 3"
+/- 5
' - 0
"
1' - 6" 1' - 6" 1' - 6" 1' - 6"
1' - 8"
0' -
3"
WINDOW ABOVE
7' - 10"
3' -
0"
LINE OF INT. WALL
1' -
7"2'
- 0"
3' - 3 1/2"
16' - 8"
1' - 9"
3' -
8"0'
- 9"
0' - 8" 0' - 8"0' - 8" 0' - 8" 0' - 8"
0' - 8" 0' - 8" 0' - 8"
0' -
4"4'
- 8"
0' - 8" 0' - 8"
BUILD COAT/BOOTH CUBBIES TO SUIT RAMP SLOPE
3' - 4" 5' - 0" 5' - 0" 3' - 4"
LINE OF INT. WALL
FREE STANDING COMMERICAL SINK
2' -
0"1'
- 7"
3' -
0"
3' -
0"
1' - 4"
WOOD COUNTER w/ PLASTIC-LAMINATE (P-LAM) FINISH
+/- 1
' - 0
"
WOOD SKIRT TO BE AT A HEIGHT SUITABLE TO HIDE FIXTURE PIPING
LAVATORY; SEE MECH.
PROVIDE SUPPORT FOR SKIRTING AS REQUIRED
JOST ARCHITECTS LTD.240 ST. GEORGE STREET, BOX 458
ANNAPOLIS ROYAL, NSP:(902) 532-2395 F:(902) 532-7707
1. CONTRACTOR MUST VERIFY ALL DRAWINGS WITH ON-SITE CONDITIONS, REPORTING ANY DISCREPANCY TO ARCHITECT BEFORE PROCEEDING WITH WORK.2. DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED BY THE ARCHITECT.3. DRAWINGS ARE NOT TO BE SCALED.4. ALL WORK IS TO COMPLY WITH THE 2015 NATIONAL BUILDING CODE AND ALL APPLICABLE CODES.5. CONTRACTOR TO RECEIVE WRITTEN APPROVAL FROM ARCHITECT PRIOR TO INSTALLATION OF ALTERNATE PRODUCTS.
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
HALIFAX, NOVA SCOTIA
- -
-
A ISSUED FOR TENDER 18/01/15
1809 BARRINGTON ST.
H353541-A-000
As indicated
THE ACADEMY PROJECTLIBRARY RENOVATIONS
MILLWORK
STAFF
1702
HJ
A-105
STAFF
A-105
HJ HJ
M. BROWN
1/2" = 1'-0"1MILLWORK ELEVATION - BAND ROOMCOUNTER
1/2" = 1'-0"2MILLWORK ELEVATION - BAND ROOMSTORAGE
1/2" = 1'-0"3MILLWORK ELEVATION - BAND ROOMSTORAGE 2
1/2" = 1'-0"4MILLWORK ELEVATION - PROGRAMKITCHENETTE
1/2" = 1'-0"6MILLWORK ELEVATION - COAT / BOOTSTORAGE
1/2" = 1'-0"5MILLWORK ELEVATION - INNOVATIONCENTRE
1" = 1'-0"7 VANITY DETAIL
18/01/15
0' -
6"3'
- 0"
2' - 0"
WASHROOM 14 SIMILAR
MR
PT
SD
3' -
6"
5' - 0"
7
A-105
Sim
1' -
4" 1' -
8"
WASHROOM 14 SIMILAR
M1
TT
SD
TYP. BASEBOARD (SEE ROOM FINISH SCHEDULE)
3' -
0"
WASHROOM 14 SIMILAR
3' -
11"
1' -
8"
TT
CH
0' - 6"
1' - 0"
1' -
5"
2' - 6"
2' -
6"
0' -
4"
1' -
11 1
/2"
2' -
6"
BC
TT
2' -
6"
SH
CH
3' -
11 1
/4"
2' -
10"
0' -
8"
3' -
11"
0' -
4"
2' -
9"
1' - 6"
3' -
6"
MR
PT
SD
2' - 0"
3' -
0"
MIN.
1' - 6"
3' -
11"
2' -
10"
WALL HUNG LAVATORY
CH
PT
M2
3' -
11"
CH
WASHROOM ACCESSORY SCHEDULESD - SOAP DISPENSER : SURFACE-MOUNTED SOAP DISPENSER "B-2111" CLASSIC SERIES BY BOBRICK OR APPROVED EQUILAVENT - QTY : 3BC - BABY CHANGE TABLE : HORIZONTAL, WALL-MOUNTED BABY CHANGING STATION "KB200-00" BY KOALA KARE PRODUCTS OR APPROVED EQUILAVENT - QTY : 1TT - TOILET PAPER DISPENSER : SURFACE-MOUNTED TWIN JUMBO ROLL TOILET TISSUE DISPENSER "B-2892" CLASSIC SERIES BY BOBRICK OR APPROVED EQUILAVENT - QTY : 3PT - PAPER TOWEL DISPENSER : SURFACE-MOUNTED PAPER TOWEL DISPENSER "B-262" CLASSIC SERIES BY BOBRICK OR APPROVED EQUILAVENT - QTY : 3M1 - CHANNEL FRAME MIRROR "B-165 2436" BY BOBRICK OR APPROVED EQUILAVENT - QTY : 2M2 - FIXED POSITION TILT MIRROR "B-293 2436" BY BOBRICK OR APPROVED EQUILAVENT - QTY : 1GB - GRAB BAR : 1-1/4" DIA. STRAIGHT GRAB BAR "B-5806 x 30" BY BOBRICK OR APPROVED EQUILAVENT - QTY : 3CH - COAT HOOK : HAT & COAT HOOK "B-682" BY BOBRICK OR APPROVED EQUILAVENT - QTY : 6WC - WASTE CHUTE : COUNTERTOP-MOUNTED CIRCULAR WASTE CHUTE "B-529" BY BOBRICK OR APPROVED EQUILAVENT - QTY: 2WR1 - WASTE RECEPTACLE (1) : FLOOR-STANDING WASTE RECEPTACLE w/ OPEN TOP "B-2260" BY BOBRICK OR APPROVED EQUILAVLENT - QTY : 2WR2 - WASTE RECEPTACLE (2) : FLOOR-STANDING LARGE CAPACITY WASTE RECEPTACLE "B-2400" BY BOBRICK OR APPROVED EQUILAVENT - QTY : 1SH - 24" LONG x 8" WIDE STAINLESS STEEL SHELF "B-298x24" BY BOBRICK OR APPROVED EQUILAVENT - QTY : 1
A-105 5
A-105 4
A-106 3
A-106
9
8
7
2
1
3' - 6"
BCTTGB
GB
SD
PTM2
10' - 6"
7' -
10"
6' -
8"8'
- 0"
5' - 0"5' - 0"
1' - 4"1' - 4"
13' - 0"
CH
CH
TT TT
SDSD
PT PT
M1M1
1' - 4" 1' - 4"
CH CH
2' - 0"
MIN
.
1' -
6"
5' -
4 1/
2"5'
- 5"
MIN
.
1' -
6"
CH
CH
SH
WR2
WC
WR1
WC
WR1
0' - 3 3/4"
5' -
0"
5' -
0"
JOST ARCHITECTS LTD.240 ST. GEORGE STREET, BOX 458
ANNAPOLIS ROYAL, NSP:(902) 532-2395 F:(902) 532-7707
1. CONTRACTOR MUST VERIFY ALL DRAWINGS WITH ON-SITE CONDITIONS, REPORTING ANY DISCREPANCY TO ARCHITECT BEFORE PROCEEDING WITH WORK.2. DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED BY THE ARCHITECT.3. DRAWINGS ARE NOT TO BE SCALED.4. ALL WORK IS TO COMPLY WITH THE 2015 NATIONAL BUILDING CODE AND ALL APPLICABLE CODES.5. CONTRACTOR TO RECEIVE WRITTEN APPROVAL FROM ARCHITECT PRIOR TO INSTALLATION OF ALTERNATE PRODUCTS.
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
HALIFAX, NOVA SCOTIA
- -
-
A ISSUED FOR TENDER 18/01/15
1809 BARRINGTON ST.
H353541-A-000
As indicated
THE ACADEMY PROJECTLIBRARY RENOVATIONS
WASHROOMS
STAFF
1702
HJ
A-106
STAFF
A-106
HJ HJ
M. BROWN
3/4" = 1'-0"1 WASHROOM 13 - ELEVATION 1
3/4" = 1'-0"2 WASHROOM 13 - ELEVATION 2
3/4" = 1'-0"3 WASHROOM 13 - ELEVATION 3
3/4" = 1'-0"7 B.F. WASHROOM - ELEVATION 1
3/4" = 1'-0"8 B.F. WASHROOM - ELEVATION 2
3/4" = 1'-0"9 B.F. WASHROOM - ELEVATION 31/2" = 1'-0"4 ENLARGED WASHROOMS
WASHROOM ACCESSORIES:1.0 SUBMITTALS:
1.1 PROVIDE MANUFACTURER'S PRINTED PRODUCT LITERATURE AND DATA SHEETS AND INCLUDE PRODUCT CHARACTERISTICS, PERFORMANCE CRITERIA, PHYSICAL SIZE, FINISH AND LIMITATIONS.
1.2 SUBMIT SHOP DRAWINGS INDICATING SIZE AND DESCRIPTION OF COMPONENTS, BASE MATERIAL, SURFACE FINISH INSIDE AND OUT, HARDWARE AND LOCKS, ATTACHMENT DEVICES, DESCRIPTION OF ROUGH-IN-FRAME, BUILDING-IN DETAILS OF ANCHORS FOR GRAB BARS.
1.3 PROVIDE MAINTENANCE DATA FOR TOILET AND BATH ACCESSORIES FOR INCORPORATION INTO MAINTENANCE MANUAL. 1.4 PROVIDE SPECIAL TOOLS REQUIRED FOR ASSEMBLY, DISASSEMBLY OR REMOVAL FOR TOILET AND BATH ACCESSORIES TO ARCHITECT.
2.0 INSTALLATION: 2.1 DELIVER INSERTS AND ROUGH-IN FRAMES TO JOB SITE AT APPROPRIATE TIME FOR BUILDING-IN. PROVIDE TEMPLATES, DETAILS AND
INSTRUCTIONS FOR BUILDING IN ANCHORS AND INSERTS. 2.2 PROVIDE STEEL ANCHOR PLATES AND COMPONENTS FOR INSTALLATION ON STUDDING AND BUILDING FRAMING. 2.3 VERIFICATION OF CONDITIONS: VERIFY THAT CONDITIONS OF SUBSTRATES AND SURFACES TO RECEIVE TOILET AND BATHROOM ACCESSORIES
PREVIOUSLY INSTALLED UNDER OTHER SECTIONS OR CONTRACTS ARE ACCEPTABLE FOR PRODUCT INSTALLATION IN ACCORDANCE WITH MANUFACTURER'S INSTRUCTIONS PRIOR TO TOILET AND BATHROOM ACCESSORIES INSTALLATION.
2.4 INFORM ARCHITECT OF UNACCEPTABLE CONDITIONS IMMEDIATELY UPON DISCOVERY. 2.5 PROCEED WITH INSTALLATION ONLY AFTER UNACCEPTABLE CONDITIONS HAVE BEEN REMEDIED.2.6 INSTALL AND SECURE ACCESSORIES RIGIDLY IN PLACE. INSTALL STEEL BACK-PLATE TO STUD PRIOR TO DRYWALL FINISH. PROVIDE PLATE WITH
THREADED STUDS OR PLUGS. 2.7 INSTALL GRAB BARS ON BUILT-IN ANCHORS PROVIDED BY BAR MANUFACTURER. 2.8 USE TAMPER PROOF SCREWS/BOLTS FOR FASTENERS. 2.9 FILL UNITS WITH NECESSARY SUPPLIES SHORTLY BEFORE FINAL ACCEPTANCE OF BUILDING. 2.10 INSTALL MIRRORS IN ACCORDANCE WITH GLAZING SPECIFICATION. 2.11 ADJUST TOILET AND BATHROOM ACCESSORIES COMPONENTS AND SYSTEMS FOR CORRECT FUNCTION AND OPERATION IN ACCORDANCE WITH
MANUFACTURER'S WRITTEN INSTRUCTIONS. 2.12 LUBRICATE MOVING PARTS TO OPERATE SMOOTHLY AND FIT ACCURATELY.
3.0 CLEANING:3.1 FINAL CLEANING: UPON COMPLETION REMOVE SURPLUS MATERIALS, RUBBISH, TOOLS AND EQUIPMENT.3.2 WASTE MANAGEMENT: SEPARATE WASTE MATERIALS FOR REUSE AND RECYCLING 3.3 REMOVE RECYCLING CONTAINERS AND BINS FROM SITE AND DISPOSE OF MATERIALS AT APPROPRIATE FACILITY.
4.0 PROTECTION:4.1 PROTECT INSTALLED PRODUCTS AND COMPONENTS FROM DAMAGE DURING CONSTRUCTION. 4.2 REPAIR DAMAGE TO ADJACENT MATERIALS CAUSED BY TOILET AND BATHROOM ACCESSORIES INSTALLATION.
5.0 SCHEDULE: LOCATE ACCESSORIES WHERE INDICATED. EXACT LOCATIONS CONFIRMED BY ARCHITECT PRIOR TO INSTALLATION. SEE WASHROOM ACCESSORY SCHEDULE FOR PRODUCTS.
18/01/15
1. SOLID WOOD 1A:.SOLID WOOD HALF GLASS1B. SOLID WOOD 2 PART GLASS
(1A & 1B SHOWN FOR DIMENSIONS)
3' - 0"3' - 0"
0' -
6"3'
- 0"
2' - 0" 0' - 6"
0' -
8"2'
- 8"
0' -
6"2'
- 8"
0' -
6"
2' - 0" 0' - 6"
FRAME WIDTHS VARY, SEE SCHEDULE
F1. WOODF2. METAL FRAME FOR 45-MINUTE FIRE-RATED DOOR
2. 45 MIN FIRE-RATED STEEL DOOR
7' -
0"
3' - 0"
F3. WOOD
2' - 0" 3' - 0"
3. BAND ROOM
(ACTIVE DOOR)
MATCH EXISTING WOOD FRAMES
-
---
Sim
0' -
10"
9
A-104
Sim
WOOD PANEL
+/- 4
' - 0
"
+/- 6' - 0"
(SU
IT E
XIST
ING
OPE
NIN
G) +/- 3' - 0"
S1 (QTY: 1)- 45 MIN FIRE-RATED (SEE SPEC.)- 45 MIN FIRE-RATED METAL FRAME
S2 (QTY: 2)- WOOD FRAME- TEMPERED GLASS- WIDTH TO SUIT EXISTING OPENING
+/- 4
' - 0
"
+/- 3' - 0"
S3 (QTY: 3)- WOOD FRAME- TEMPERED GLASS
+/- 2
' - 0
"
+/- 2' - 8"
W1 (QTY: 2)- VINYL- OPERATION: AWNING- GRILLES REQ'D- DOUBLE GLAZED, CLEAR GLASS
W2 (QTY: 2)- VINYL- OPERATION: DOUBLE HUNG- GRILLES REQ'D- DOUBLE GLAZED, CLEAR GLASS
W3 (QTY: 1)- VINYL- OPERATION: AWNING- GRILLES REQ'D- DOUBLE GLAZED, CLEAR GLASS
NOTES:1. WINDOW WIDTHS TO SUIT EXISTING OPENINGS. SITE VERIFY.2. ALL EXTERIOR WINDOWS TO BE VINYL, DOUBLE GLAZED, BY PETER KOHLER WINDOWS & ENTRANCE SYSTEMS. OR APPROVED EQUIVALENT.3. MATCH ADJACENT EXISTING WINDOWS IN STYLE.
+/- 2
' - 0
"
+/- 4' - 0"
W4 (QTY: 1)- VINYL- OPERATION: DOUBLE HUNG- GRILLES REQ'D- DOUBLE GLAZED, CLEAR GLASS
+/- 3' - 9"
(SU
IT E
XIST
ING
OPE
NIN
G)
HEA
D H
EIG
HT
7' -
0" T
YP.
HEA
D H
EIG
HT
TO M
ATC
H E
XIST
ING
2' - 8"
2' -
0"
W5 (QTY: 2)- VINYL- WINDOWS SUPPLIED BY OWNER
+/- 2
' - 6
"
4' - 0"
7
A-104
Sim
6
A-104
Sim
JOST ARCHITECTS LTD.240 ST. GEORGE STREET, BOX 458
ANNAPOLIS ROYAL, NSP:(902) 532-2395 F:(902) 532-7707
1. CONTRACTOR MUST VERIFY ALL DRAWINGS WITH ON-SITE CONDITIONS, REPORTING ANY DISCREPANCY TO ARCHITECT BEFORE PROCEEDING WITH WORK.2. DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED BY THE ARCHITECT.3. DRAWINGS ARE NOT TO BE SCALED.4. ALL WORK IS TO COMPLY WITH THE 2015 NATIONAL BUILDING CODE AND ALL APPLICABLE CODES.5. CONTRACTOR TO RECEIVE WRITTEN APPROVAL FROM ARCHITECT PRIOR TO INSTALLATION OF ALTERNATE PRODUCTS.
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
HALIFAX, NOVA SCOTIA
- -
-
A ISSUED FOR TENDER 18/01/15
1809 BARRINGTON ST.
H353541-A-000
As indicated
THE ACADEMY PROJECTLIBRARY RENOVATIONS
SCHEDULES
STAFF
1702
HJ
A-107
STAFF
A-107
HJ HJ
M. BROWN
DOOR SCHEDULE
DOORNUMBER FROM TO
DOOR (SEE NOTE 1) FRAME HARDWARE (SEE NOTE 2)
KEYING REMARKSFIRE
RATING TYPE SWING WIDTH HEIGHT FINISH TYPE MATERIAL LOCKEMERGENCYEXIT DEVICE
PASSAGESET CLOSER STOP
RESTROOM INDICATORDEADBOLT
ACOUSTICWEATHERSTRIP
DOORBOLT
1A STACKS &READING
QUIET ROOM N/A SEE REMARKS 3' - 0" 7' - 0" SEMI-TRANSLUCENT STAIN F1 WOOD
2A COMMON STACKS &READING
1B LH 3' - 0" 7' - 0" SEMI-TRANSLUCENT STAIN F1 WOOD
2B COMMON STACKS &READING
1B RH 3' - 0" 7' - 0" SEMI-TRANSLUCENT STAIN F1 WOOD
3A STACKS &READING
OFFICE 1A RH 3' - 0" 7' - 0" SEMI-TRANSLUCENT STAIN F1 WOOD
5A CORR. BOILER ROOM 45 MIN 2 LH 3' - 0" 7' - 0" PAINT F2 METAL YES YES6A CORR. JANITOR 45 MIN 2 RH 3' - 0" 7' - 0" PAINT F2 METAL YES YES7A COMMON FOOD BANK 1A RH 3' - 0" 7' - 0" SEMI-TRANSLUCENT STAIN F1 WOOD7B FOOD BANK FOOD BANK N/A N/A 6' - 0" 7' - 0" N/A F1 WOOD DOOR OPENING8A COMMON BAND ROOM 3 SEE REMARKS 5' - 0" 7' - 0" SEMI-TRANSLUCENT STAIN F1 WOOD YES YES YES YES ACTIVE LEAF - RHR ; INACTIVE - LHR9A PROGRAM COMMON 3 SEE REMARKS 6' - 0" 7' - 0" SEMI-TRANSLUCENT STAIN F3 WOOD DOUBLE DOOR9B PROGRAM PROGRAM 1 SEE REMARKS 6' - 0" 7' - 0" SEMI-TRANSLUCENT STAIN F1 WOOD YES YES DOUBLE DOOR - KITCHETTE10A COMMON FAM./B.F. WR. 1 LH 3' - 0" 7' - 0" SEMI-TRANSLUCENT STAIN F1 WOOD YES YES YES YES11A PROGRAM STORAGE 1 RHR 2' - 8" 7' - 0" SEMI-TRANSLUCENT STAIN F1 WOOD YES YES12A INNOVATION
CENTRECOMMON 1B 6' - 0" 7' - 0" SEMI-TRANSLUCENT STAIN F3 WOOD
12B INNOVATIONCENTRE
PROGRAM 1A 6' - 0" 7' - 0" SEMI-TRANSLUCENT STAIN F1 WOOD YES YES
12C INNOVATIONCENTRE
INNOVATIONCENTRE
N/A N/A 0' - 0" 7' - 0" N/A F1 WOOD OPENING
13A COMMON WR. 1 RH 3' - 0" 7' - 0" SEMI-TRANSLUCENT STAIN F1 WOOD YES YES YES YES14A COMMON WR. 1 LH 3' - 0" 7' - 0" SEMI-TRANSLUCENT STAIN F1 WOOD YES YES YES YES15A COMMON THE ACADEMY 45 MIN 1 LHR 3' - 0" 7' - 0" PAINT F2 METAL YES YES YES YES DOUBLE EGRESS15B THE ACADEMY COMMON 45 MIN 1 RH 3' - 0" 7' - 0" PAINT F2 METAL YES YES YES YES DOUBLE EGRESS
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YESYES
YESYES
YESYESYES
YES
YES
YESYES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
T.B.D.T.B.D.
T.B.D.T.B.D.
T.B.D.T.B.D.T.B.D.
T.B.D.
T.B.D.
T.B.D.
T.B.D.
T.B.D.
T.B.D.
T.B.D.
YES
YES
NOTES:1. CARRY $5000 DOOR ALLOWANCE. EXISTING DOORS WILL BE RE-USED WHEREVER POSSIBLE. ARCHITECT WILL REVIEW DOORS SALVAGED DURING DEMOLITION TO DETERMINE THOSE SUITEABLE FOR RE-USE. DOORS FOR RE-USE WILL BE RE-FINISHED.2. CARRY $5000 HARDWARE ALLOWANCE. RE-USE EXISTING HARDWARE AS FIRECTED BY ARCHITECT.
YES YES
YESYES
YES YES
T.B.D.
18/01/15
PARTITIONS FOR MINOR WORKS NOTES:
PART 1: GENERAL
1.1 REFERENCES: AMERICAN SOCIETY FOR TESTING AND MATERIALS INTERNATIONAL (ASTM): ASTM C 36/C 36M-01, ASTM C 475-01, ASTM C 645-00, ASTM C 840-01, ASTM C 960/C 960M-01, ASTM C 1002-01, ASTM C 1047-99, ASTM C 1178/C 1178M-01. 1.2 DESIGN REQUIREMENTS: MINIMUM SOUND TRANSMISSION RATING OF INSTALLED PANEL PARTITION TO BE STC 30, TESTED TO ASTM E 90.
PART 2: PRODUCTS
2.1. LUMBER: UNLESS SPECIFIED OTHERISE, SOFTWOOD, S4S, MOISTURE CONTENT 19% (S-DRY) OR LESS IN ACCORDANCE WITH FOLLOWING STANDARDS; CSA O141, NLGA STANDARD GRADING RULES FOR CANADIAN LUMBER, FORESTRY STEWARDSHIP COUNCIL (FSC) CERTIFIED.2.2 GYPSUM BOARD: TO ASTM C 36/C 36M REGULAR, 5/8" THICK AND TYPE X, 5/8" THICK, 4'-0" WIDE x MAXIMUM PRACTICAL LENGTH, ENDS SQUARE CUT, EDGES TAPERED.2.3 GLASS MAT WATER-RESISTANCE GYPSUM BACKING BOARD: TO ASTM C 1178/C 1178M, 5/8" THICK, 4'-0" WIDE x MAXIMUM PRACTICAL LENGTH.2.4 FRAMING AND BOARD LUMBER: IN ACCORDANCE WITH NBC.2.5 FURRING, BLOCKING AND NAILING STRIPS: S2S IS ACCEPTABLE FOR: BOARD SIZES,"STANDARD" OR BETTER GRADE; DIMENSION SIZES, "STANDARD" LIGHT FRAMING OR BETTER GRADE; POST AND TIMBER SIZES, "STANDARD" OR BETTER GRADE.2.6 GENERAL PURPOSE ADHESIVE: TO CSA O112 SERIES. MAXIMUM ALLOWABLE VOC LIMIT 140 g/L.2.7 NAILS, SPIKES AND STAPLES: TO CSA B111.2.8 DRYWALL FURRING CHANNELS" 0.5mm CORE THICKNESS GALVANIZED STEEL CHANNELS FOR SCREW ATTACHMENT OF GYPSUM BOARD.2.9 CASING BEADS, CORNER BEADS, CONTROL JOINTS AND EDGE TRIM: TO ASTM C 1047, ABS PVC ZINC METAL, ZINC-COATED BY HOT-DIP PROCESS ZINC-COATED BY ELECTROLYTIC PROCESS ALUMINUM COATED PHOSPHATIZED, 0.5mm BASE THICKNESS, PERFORATED FLANGES, ONE PIECE LENGTH PER LOCATION.2.10 JOINT COMPOUND: TO ATSM C 475, ASBESTOS-FREE.2.11 ACOUSTICAL INSULATION AND SEALANT: TYPE RECOMMENDED BY MANUFACTURER TO ACHIEVE STC RATING SPECIFIED.
PART 3: EXECUTION
3.1 FRAMING INSTALLATION: COMPLY WITH REQUIREMENTS OF NBC 2005 PART 9 SUPPLEMENTED BY FOLLOWING PARAGRAPHS. .1 INSTALL MEMBERS TRUE TO LINE, LEVELS AND ELEVATIONS, SQUARE AND PLUMB. .2 CONSTRUCT CONTINUOUS MEMBERS FROM PIECES OF LONGEST PRACTICAL LENGTH. .3 INSTALL SPANNING MEMBERS WITH "CROWN-EDGE" UP. .4 SELECT EXPOSED FRAMING FOR APPEARANCE. INSTALL LUMBER AND PANEL MATERIALS SO THAT GRADE-MARKS AND
OTHER DEFACING MARKS ARE CONCEALED OR ARE REMOVED BY SANDING WHERE MATERIALS ARE LEFT EXPOSED. .5 INSTALL FURRING AND BLOCKING AS REQUIRED TO SPACE-OUT AND SUPPORT CASEWORK, CABINETS, WALL AND CEILING
FINISHES, FACINGS, FASCIA, SOFFIT, SIDING ELECTRICAL EQUIPMENT MOUNTING BOARDS, AND OTHER WORK AS REQUIRED. .6 INSTALL ROUGH BUCKS, NAILERS AND LININGS TO ROUGH OPENINGS AS REQUIRED TO PROVIDE BACKING FOR FRAMES
AND OTHER WORK. .7 USE DUST COLLECTORS AND HIGH QUALITY RESPIRATOR MASKS WHEN CUTTING OR SANDING WOOD PANELS. .8 PLACE STUDS VERTICALLY AT 16" ON CENTRE AND NOT MORE THAN 2" FROM ABUTTING WALLS, AND AT EACH SIDE OF
OPENINGS AND CORNERS. .9 PROVIDE TWO STUDS EXTENDING FROM FLOOR TO CEILING AT EACH SIDE OF OPENINGS WIDER THAN STUD CENTRES
SPECIFIED. .10 INSTALL INTERMEDIATE STUDS ABOVE AND BELOW OPENINGS IN SAME MANNER AND SPACING AS WALL STUDS. .11 PROVIDE 2X4 STUD OR FURRING CHANNEL SECURED BETWEEN STUDS FOR ATTACHMENT OF FIXTURES BEHIND LAVATORY
BASINS, TOILET AND BATHROOM ACCESSORIES, AND OTHER FIXTURES INCLUDING GRAB BARS AND TOWEL RAILS, ATTACHED TO STUD PARTITIONS.
.12 EXTEND PARTITIONS TO UNDERSIDE OF STRUCTURE EXCEPT WHERE NOTED OTHERWISE ON DRAWINGS.
.13 MAINTAIN CLEARANCE UNDER BEAMS AND STRUCTURAL SLABS TO AVOID TRANSMISSION OF STRUCTURAL LOADS TO STUDS.
.14 INSTALL CONTINUOUS INSULATING STRIPS TO ISOLATE STUDS FROM UNINSULATED SURFACES.
.15 INSTALL INSULATING STRIP UNDER STUDS AROUND PERIMETER OF SOUND CONTROL PARTITIONS. 3.2 GYPSUM BOARD AND ACCESSORY INSTALLATION:
.1 DO APPLICATION AND FINISHING OF GYPSUM BOARD IN ACCORDANCE WITH ASTM C 840 EXCEPT WHERE SPECIFIED OTHERWISE.
.2 ERECT HANGERS AND RUNNER CHANNELS FOR SUSPENDED GYPSUM BOARD CEILINGS IN ACCORDANCE WITH ASTM C 840 EXCEPT WHERE SPECIFIED OTHERWISE.
.3 SUPPORT LIGHT FIXTURES BY PROVIDING ADDITIONAL CEILING SUSPENSION HANGERS WITHIN 6" OF EACH CORNER AND AT MAXIMUM 24" AROUND PERIMETER OF FIXTURE.
.4 FRAME WITH FURRING CHANNELS, PERIMETER OF OPENINGS FOR ACCESS PANELS, LIGHT FIXTURES, DIFFUSERS, GRILLES,.
.5 INSTALL ACOUSTICAL INSULATION ANDSEALANT IN SOUND RATED PARTITIONS TO CORRESPOND WITH TESTED ASSEMBLY.
.6 INSTALL GYPSUM BOARDS IN DIRECTION THAT WILL MINIMIZE NUMBER OF END-BUTT JOINTS. STAGGER END JOINTS AT LEAST 10".
.7 DO NOT APPLY GYPSUM BOARD UNTIL BUCKS, ANCHORS, BLOCKING, SOUND ATTENUATION, ELECTRICAL AND MECHANICAL WORK ARE APPROVED.
.8 APPLY SINGLE LAYER GYPSUM BOARD TO FURRING OR FRAMING USING SCREW FASTENERS. MAXIMUM SPACING OF SCREWS 12" ON CENTRE.
.9 APPLY WATER-RESISTANT GYPSUM BOARD ADJACENT TO SLOP SINKS IN JANITORS CLOSETS, SINKS IN WASHROOMS, SINK IN PROGRAM ROOM, AND SINK IN INNOVATION CENTRE. APPLY WATER-RESISTANT SEALANT TO EDGES, ENDS, CUT-OUTS WHICH EXPOSE GYPSUM CORE AND TO FASTENER HEADS.
.10 ERECT ACCESSORIES STRAIGHT, PLUMB OR LEVEL, RIGID AND AT PROPER PLANE. USE FULL LENGTH PIECES WHERE PRACTICAL. MAKE JOINTS TIGHT, ACCURATELY ALIGNED AND RIGIDLY SECURED. MITRE AND FIT CORNERS ACCURATELY, FREE FROM ROUGH EDGES. SECURE AT 6" ON CENTRE USING CONTACT ADHESIVE FOR FULL LENGTH.
.11 INSTALL CASING BEADS AROUND PERIMETER OF SUSPENDED CEILINGS.
.12 INSTALL CASING BEADS WHERE GYPSUM BOARD BUTTS AGAINST SURFACES HAVING NO TRIM CONCEALING JUNCTION AND WHERE INDICATED. SEAL JOINTS WITH SEALANT.
.13 FINISH FACE PANEL JOINTS AND INTERNAL ANGLES WITH JOINT SYSTEM CONSISTING OF JOINT COMPOUND, JOINT TAPE AND TAPING COMPOUND INSTALLED ACCORDING TO MANUFACTURER'S DIRECTIONS AND FEATHERED OUT ONTO PANEL FACES.
.14 FINISH CORNER BEADS, CONTROL JOINTS AND TRIM AS REQUIRED WITH TWO COATS OF JOINT COMPOUND AND ONE COAT OF TAPING COMPOUND, FEATHERED OUT ONTO PANEL FACES.
.15 FILL SCREW HEAD DEPRESSIONS WITH JOINT AND TAPING COMPOUNDS TO BRING FLUSH WITH ADJACENT SURFACE OF GYPSUM BOARD SO AS TO BE INVISIBLE AFTER SURFACE FINISH IS COMPLETED.
.16 COMPLETED INSTALLATION TO BE SMOOTH, LEVEL OR PLUMB, FREE FROM WAVES AND OTHER DEFECTS AND READY FOR SURFACE FINISH.
FINISH CARPENTRY:
PART 1: GENERAL
1.1 REFERENCES: .1 AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI): ANSI A208.1-09, ANSI A208.2-09, ANSI/HPVA HP-1-2004..2 ARCHITECTURAL WOODWORK MANUFACTURERS ASSOCIATION OF CANADA (AWMAC) AND ARCHITECTURAL WOODWORK
INSTITUTE (AWI): ARCHITECTURAL WOODWORK QUALITY STANDARDS, 1ST EDITION, 2009. .3 CANADIAN GENERAL STANDARDS BOARD (CGSB): CAN/CGSB-11.3-M87. .4 CSA INTERNATIONAL: CSA B111-74(R2003), CAN/CSA G164-M92(R2003)..5 FOREST STEWARDSHIP COUNCIL (FSC): FSC-STD-01-001-2004, FSC-STD-20-002-2004, FSC ACCREDITED CERTIFIED BODIES. .6 NATIONAL LUMBER GRADES AUTHORITY (NLGA): NLGA STANDARD GRADING RULES FOR CANADIAN LUMBER 2008. .7 UNDERWRITERS LABORATORIES OF CANADA (ULC): CAN4-S104-80(R1985), CAN/ULC-S105-09.
1.2 SUBMITTALS:.1 SUBMIT DRAWINGS INDICATING DETAILS OF CONSTRUCTION, PROFILES, JOINTING, FASTENING AND OTHER RELATED
DETAILS AND INDICATING MATERIALS, THICKNESSES, FINISHES AND HARDWARE. .2 SUBMIT DUPLICATE 12" LONG SAMPLES OF FINISHED WOOD TRIMS AND BASE.
1.3 QUALITY ASSURANCE :.1 LUMBER BY GRADE STAMP OF AGENCY CERTIFIED BY CANADIAN LUMBER STANDARDS ACCREDITATION BOARD (CLSAB). .2 PLYWOOD, PARTICLEBOARD, OSB AND WOOD BASED COMPOSITE PANELS TO CSA AND ANSI STANDARDS. .3 WOOD FIRE RATED FRAMES AND PANELS: LISTED AND LABELLED BY AN ORGANIZATION ACCREDITED BY STANDARDS
COUNCIL OF CANADA TO CAN4-S104 AND CAN/ULC-S105.
PART 2: PRODUCTS
2.1 SOFTWOOD LUMBER: S4S, MOISTURE CONTENT 19% OR LESS IN ACCORDANCE WITH FOLLOWING STANDARDS: .1 CSA O141. .2 NLGA STANDARD GRADING RULES FOR CANADIAN LUMBER..3 AWMAC CUSTOM PREMIUM GRADE, MOISTURE CONTENT AS SPECIFIED..4 MACHINE STRESS-RATED LUMBER IS ACCEPTABLE. .5 HARDWOOD LUMBER:
.1 NATIONAL HARDWOOD LUMBER ASSOCIATION (NHLA).
.2 AWMAC CUSTOM PREMIUM GRADE, MOISTURE CONTENT AS SPECIFIED. 2.2 PANEL MATERIAL: UREA-FORMALDEHYDE FREE; FSC CERTIFIED.
.3 DOUGLAS FIR PLYWOOD (DFP): TO CSA O121, STANDARD CONSTRUCTION.
.4 CANADIAN SOFTWOOD PLYWOOD (CSP): TO CSA O151, STANDARD CONSTRUCTION.
.5 HARDWOOD PLYWOOD: TO ANSI/HPVA HP-1.
.6 POPLAR PLYWOOD (PP): TO CSA O153, STANDARD CONSTRUCTION.
.7 PARTICLEBOARD: TO ANSI A208.1.
.8 HARDBOARD: TO CAN/CGSB-11.3.
.9 MEDIUM DENSITY FIBREBOARD (MDF): TO ANSI A208.2, DENSITY 640-800 KG/M³.
.10 LOW DENSITY FIBREBOARD: TO CSA-A247M.
.11 DECORATIVE OVERLAID COMPOSITE PANELS. .1 DECORATIVE OVERLAY, HEAT AND PRESSURE LAMINATED WITH SUITABLE RESIN TO THICKNESS INDICATED 1/2" (12.7
MM) THICK PARTICLEBOARD MDF UREA-FORMALDEHYDE FREE CORE. .2 OVERLAY BONDED TO BOTH FACES WHERE EXPOSED TWO SIDES, AND WHEN PANEL MATERIAL REQUIRE SURFACE ON
ONE SIDE ONLY, REVERSE SIDE TO BE OVERLAID WITH A PLAIN (BUFF) BALANCING SHEET. .3 FURNITURE FINISH: WOOD GRAIN PATTERN SOLID COLOUR SELECTED BY ARCHITECT. .4 EDGE FINISHING: MATCHING MELAMINE AND POLYESTER OVERLAY EDGE STRIP WITH SELF-ADHESIVE EDGES DADOED
OR SAW KERFED TO TAKE PLASTIC "T" MOULDING IN WIDTH AND COLOUR TO MATCH MELAMINE FINISH EDGE FILLER TO PROVIDE A SMOOTH SURFACE FOR PAINT FINISH.
2.3 NAILS AND STAPLES: TYPE AND SIZE TO SUIT APPLICATION. 2.4 WOOD SCREWS: TYPE AND SIZE TO SUIT APPLICATION. 2.5 SPLINES: METAL. 2.6 ADHESIVE AND SEALANTS: IN ACCORDANCE WITH SECTION 07 92 00 - JOINT SEALANTS. VOC LIMIT 30 70 250 G/L MAXIMUM TO SCAQMD RULE 1168 GS-36.
PART 3: EXECUTION
3.1 VERIFY CONDITIONS OF SUBSTRATES PREVIOUSLY INSTALLED UNDER OTHER SECTIONS OR CONTRACTS ARE ACCEPTABLE FOR INSTALLATION IN ACCORDANCE WITH MANUFACTURER'S WRITTEN INSTRUCTIONS. PROCEED WITH INSTALLATION ONLY AFTER UNACCEPTABLE CONDITIONS HAVE BEEN REMEDIED3.2 DO FINISH CARPENTRY TO QUALITY STANDARDS OF (AWMAC). 3.3 SCRIBE AND CUT AS REQUIRED, FIT TO ABUTTING WALLS, AND SURFACES, FIT PROPERLY INTO RECESSES AND TO ACCOMMODATE PIPING, COLUMNS, FIXTURES, OUTLETS, OR OTHER PROJECTING, INTERSECTING OR PENETRATING OBJECTS. 3.4 FORM JOINTS TO CONCEAL SHRINKAGE. 3.5 FASTENING:
.1 POSITION ITEMS OF FINISHED CARPENTRY WORK ACCURATELY, LEVEL, PLUMB, TRUE AND FASTEN OR ANCHOR SECURELY.
.2 DESIGN AND SELECT FASTENERS TO SUIT SIZE AND NATURE OF COMPONENTS BEING JOINED. USE PROPRIETARY DEVICES AS RECOMMENDED BY MANUFACTURER.
.3 SET FINISHING NAILS TO RECEIVE FILLER. WHERE SCREWS ARE USED TO SECURE MEMBERS, COUNTERSINK SCREW IN ROUND SMOOTH CUT HOLE AND PLUG WITH WOOD PLUG TO MATCH MATERIAL BEING SECURED.
.4 REPLACE ITEMS OF FINISH CARPENTRY WITH DAMAGE TO WOOD SURFACES INCLUDING HAMMER AND OTHER BRUISES. 3.6 STANDING AND RUNNING TRIM: TO BE A SOLID WOOD SPECIES; PROFILE TO MATCH EXISTING
.1 BUTT AND COPE INTERNAL JOINTS OF BASEBOARDS TO MAKE SNUG, TIGHT, JOINT. CUT RIGHT ANGLE JOINTS OF CASING AND BASE WITH MITRED JOINTS.
.2 FIT BACKS OF BASEBOARDS AND CASING SNUGLY TO WALL SURFACES TO ELIMINATE CRACKS AT JUNCTION OF BASE AND CASING WITH WALLS.
.3 MAKE JOINTS IN BASEBOARD, WHERE NECESSARY USING A 45 DEGREES SCARF TYPE JOINT.
.4 INSTALL DOOR AND WINDOW TRIM IN SINGLE LENGTHS WITHOUT SPLICING. 3.7 INTERIOR FRAMES: (TO BE A SOLID WOOD SPECIES)
.1 SET FRAMES WITH PLUMB SIDES AND LEVEL HEADS AND SILLS AND SECURE.
.2 CONSTRUCTION TO MATCH EXISTING EXCEPT WHERE OTHERWISE DETAILED.3.8 PROTECT INSTALLED PRODUCTS AND COMPONENTS FROM DAMAGE DURING CONSTRUCTION. 3.9 REPAIR DAMAGE TO ADJACENT MATERIALS CAUSED BY FINISH CARPENTRY INSTALLATION.
ACOUSTICAL CEILINGS FOR MINOR WORKS:
PART 1: GENERAL
1.1 REFERENCES: .1 AMERICAN SOCIETY FOR TESTING AND MATERIALS INTERNATIONAL (ASTM): ASTM C 636-00, ASTM C 636-96, ASTM E 1477-98a
(2003).2 CANADIAN GENERAL STANDARDS BOARD (CGSB): CAN/CGSB-92.1-M89.3 HEALTH CANADA/WORKPLACE HAZARDOUS MATERIALS INFORMATION SYSTEM (WHMIS): MATERIAL SAFETY DATA SHEETS
(MSDS).4 UNDERWITER'S LABORATORIES OF CANADA (ULC): CAN/ULC-S102-2003
1.2 SUBMITTALS: SUBMIT SHOP DRAWINGS AS FOLLOWS:.1 SUBMIT DUPLICATE FULL-SIZE SAMPLES OF EACH TYPE ACOUSTICAL UNIT..2 SUBMIT REFLECTED CEILING PLANS FOR SPECIAL GRID PATTERNS AS INDICATED. .3 INDICATE LAY-OUT, INSERT AND HANGER SPACING AND FASTENING DETAILS, SPLICING METHOD FOR MAIN AND CROSS
RUNNERS, CHANGE IN LEVEL DETAILS, AND ACOUSTICAL UNIT SUPPORT AT CEILING FIXTURE LATERAL BRACING AND ACCESSORIES.
PART 2: PRODUCTS
2.1 PRODUCTS: SEE RCP LEGEND ON REFLECTED CEILING PLAN FOR PRODUCT SELECTION.2.2 ACOUSTICAL SUSPENSION: SYSTEM, TEE BAR GRID, RESILIENT HANGER WIRE, HANGER INSERTS, CARRYING CHANNELS AND ACCESSORIES AS RECOMMENDED BY MANUFACTURER FOR ACOUSTIC SEPARATION.
PART 3: EXECUTION
3.1 INSTALLATION OF SUSPENSION SYSTEM:.1 INSTALLATION: IN ACCORDANCE WITH ASTM C 636 EXCEPT WHERE SPECIFIED OTHERWISE. .2 DO NOT ERECT CEILING SUSPENSION SYSTEM UNTIL WORK ABOVE CEILING HAS BEEN INSPECTED BY ARCHITECT..3 ALL SUSPENDED CEILING GRID TO BE INSTALLED WITH RESILIENT HANGERS. SECURE HANGERS TO OVERHEAD STRUCTURE
USING ATTACHMENT METHODS AS RECOMMENDED BY MANUFACTURER..4 INSTALL HANGERS SPACED AT MAXIMUM 4'-0" CENTRES AND WITHIN 6" FROM ENDS OF MAIN TEES. .5 LAY OUT CENTRELINE OF CEILING BOTH WAYS, TO PROVIDE BALANCED BORDERS AT ROOM PERIMETER WITH BORDER
UNITS NOT LESS THAN 50% OF STANDARD UNIT WIDTH OF SYSTEM EXCEPT WHERE NOTED OTHERWISE ACCORDING TO REFLECTED CEILING PLAN.
.6 INSTALL WALL MOULDING TO PROVIDE CORRECT CEILING HEIGHT.
.7 COMPLETED SUSPENSION SYSTEM TO SUPPORT SUPER-IMPOSED LOADS, SUCH AS LIGHTING FIXTURES DIFFUSERS GRILLES AND SPEAKERS.
.8 SUPPORT AT LIGHT FIXTURES DIFFUSERS WITH ADDITIONAL CEILING SUSPENSION HANGERS WITHIN 6" OF EACH CORNER AND AT MAXIMUM 24" AROUND PERIMETER OF FIXTURE.
.9 INTERLOCK CROSS MEMBER TO MAIN RUNNER TO PROVIDE RIGID ASSEMBLY.
.10 FINISHED CEILING SYSTEM TO BE SQUARE WITH ADJOINING WALLS AND LEVEL WITHIN 1:1000. INSTALL ACOUSTICAL PANELS AND TILES IN CEILING SUSPENSION SYSTEM.
.11 CO-ORDINATE CEILING WORK TO ACCOMMODATE COMPONENTS OF OTHER SECTIONS, SUCH AS LIGHT FIXTURES, DIFFUSERS, SPEAKERS, SPRINKLER HEADS, TO BE BUILT INTO ACOUSTICAL CEILING COMPONENTS.3.2 INSTALLATION OF ACOUSTIC CEILING TILE: AS PER MANUFACTURER'S RECOMMENDATION.
METAL DOORS AND FRAMES:
PART 1: GENERAL
1.1 REFERENCES: .1 AMERICAN SOCIETY FOR TESTING AND MATERIALS INTERNATIONAL (ASTM): ASTM A 653/A 653M-06A, ASTM B 29-03,
ASTM B 749-03. .2 CANADIAN GENERAL STANDARDS BOARD (CGSB): CAN/CGSB-1.181-99, CGSB 41-GP-19MA-84. .3 CANADIAN STANDARDS ASSOCIATION (CSA INTERNATIONAL): CSA-G40.20-04/G40.21-04, CSA W59-03..4 CANADIAN STEEL DOOR MANUFACTURERS' ASSOCIATION (CSDMA):
.1 CSDMA, RECOMMENDED SPECIFICATIONS FOR COMMERCIAL STEEL DOORS AND FRAMES, 2000.
.2 CSDMA, SELECTION AND USAGE GUIDE FOR COMMERCIAL STEEL DOORS, 1990. .5 NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
.1 NFPA 80-99, STANDARD FOR FIRE DOORS AND FIRE WINDOWS.
.2 NFPA 252-03, STANDARD METHODS OF FIRE TESTS OF DOOR ASSEMBLIES. .6 UNDERWRITERS' LABORATORIES OF CANADA (ULC): CAN4-S104-M80, CAN4-S105-M85.
1.2 STEEL FIRE RATED DOORS AND FRAMES: LABELLED AND LISTED BY AN ORGANIZATION ACCREDITED BY STANDARDS COUNCIL OF CANADA IN CONFORMANCE WITH CAN4-S104 NFPA 252 FOR RATINGS SPECIFIED OR INDICATED. 1.3 PROVIDE FIRE LABELLED FRAMES FOR OPENINGS REQUIRING FIRE PROTECTION RATINGS. TEST PRODUCTS IN CONFORMANCE WITH CAN4-S104, ASTM E 152 OR NFPA 252 AND LISTED BY NATIONALLY RECOGNIZED AGENCY HAVING FACTORY INSPECTION SERVICES. 1.4 PROVIDE SHOP DRAWINGS:
.1 SUBMIT DRAWINGS STAMPED AND SIGNED BY PROFESSIONAL ENGINEER REGISTERED OR LICENSED IN PROVINCE OF NOVA SCOTIA, CANADA.
.2 INDICATE EACH TYPE OF DOOR, MATERIAL, STEEL CORE THICKNESSES, MORTISES, REINFORCEMENTS, LOCATION OF EXPOSED FASTENERS, OPENINGS, GLAZED LOUVRED, ARRANGEMENT OF HARDWARE AND FIRE RATING AND FINISHES.
.3 INDICATE EACH TYPE FRAME MATERIAL, CORE THICKNESS, REINFORCEMENTS, GLAZING STOPS, LOCATION OF ANCHORS AND EXPOSED FASTENINGS AND REINFORCING FIRE RATING FINISHES.
.4 INCLUDE SCHEDULE IDENTIFYING EACH UNIT, WITH DOOR MARKS AND NUMBERS RELATING TO NUMBERING ON DRAWINGS AND DOOR SCHEDULE.
.5 SUBMIT TEST AND ENGINEERING DATA, AND INSTALLATION INSTRUCTIONS.
PART 2: PRODUCTS
2.1 METAL DOORS: 45 MINUTE FIRE-RATED METAL DOORS BY APEX OR APPROVED EQUIVALENT. .1 SWING TYPE, FLUSH, WITH PROVISION FOR GLASS AND/OR LOUVRE OPENINGS AS INDICATED. .2 FABRICATE DOORS WITH LONGITUDINAL EDGES LOCKED SEAM LOCKED SEAMED, ADHESIVE ASSISTED WELDED. SEAMS:
VISIBLE GRIND WELDED JOINTS TO A FLAT PLANE, FILL WITH METALLIC PASTE FILLER AND SAND TO A UNIFORM SMOOTH FINISH. .3 BLANK, REINFORCE, DRILL DOORS AND TAP FOR MORTISED, TEMPLATED HARDWARE AND ELECTRONIC HARDWARE. .4 FACTORY PREPARE HOLES 1/2" DIAMETER AND LARGER EXCEPT MOUNTING AND THROUGH-BOLT HOLES, ON SITE, AT TIME
OF HARDWARE INSTALLATION. .5 REINFORCE DOORS WHERE REQUIRED, FOR SURFACE MOUNTED HARDWARE. PROVIDE INVERTED, RECESSED, SPOT
WELDED CHANNELS TO TOP AND BOTTOM OF INTERIOR DOORS. .6 PROVIDE FACTORY-APPLIED TOUCH-UP PRIMER AT AREAS WHERE ZINC COATING HAS BEEN REMOVED DURING
FABRICATION. .7 PROVIDE FIRE LABELLED DOORS FOR THOSE OPENINGS REQUIRING FIRE PROTECTION RATINGS, AS SCHEDULED. TEST
SUCH PRODUCTS IN CONFORMANCE WITH CAN4-S104 ASTM E 152 NFPA 252 AND LIST BY NATIONALLY RECOGNIZED AGENCY HAVING FACTORY INSPECTION SERVICE AND CONSTRUCT AS DETAILED IN FOLLOW-UP SERVICE PROCEDURES/FACTORY INSPECTION MANUALS ISSUED BY LISTING AGENCY TO INDIVIDUAL MANUFACTURERS.
.8 TOUCH-UP PRIME CAN/CGSB-1.181. MAXIMUM VOC LIMIT 50 G/L TO GC-03.
.9 FIELD PAINT STEEL DOORS AND FRAMES IN ACCORDANCE WITH INTERIOR PAINTING SPECIFICATION.
.10 PROVIDE FINAL FINISH FREE OF SCRATCHES OR OTHER BLEMISHES.
.11 DOOR SILENCERS: SINGLE STUD RUBBER/NEOPRENE TYPE.
.12 FIRE LABELS: METAL RIVITED.
.13 SEALANT: MAXIMUM VOC LIMIT 250 G/L TO SCAQMD RULE 1168.
.14 GLAZING: MAKE PROVISIONS FOR GLAZING AS INDICATED AND PROVIDE NECESSARY GLAZING STOPS. PROVIDE REMOVABLE STAINLESS STEEL GLAZING BEADS FOR USE WITH GLAZING TAPES AND COMPOUNDS AND SECURED WITH COUNTERSUNK STAINLESS STEEL SCREWS DRY GLAZING OF SNAP-ON TYPE. 2.2 METAL FRAMES:
.1 FABRICATE FRAMES IN ACCORDANCE WITH CSDMA SPECIFICATIONS.
.2 FABRICATE FRAMES TO PROFILES AND MAXIMUM FACE SIZES AS INDICATED.
.3 INTERIOR FRAMES: WELDED TYPE CONSTRUCTION. WELDING IN ACCORDANCE WITH CSA W59.
.4 BLANK, REINFORCE, DRILL AND TAP FRAMES FOR MORTISED, TEMPLATED HARDWARE, AND ELECTRONIC HARDWARE USING TEMPLATES PROVIDED BY FINISH HARDWARE SUPPLIER. REINFORCE FRAMES FOR SURFACE MOUNTED HARDWARE.
.5 PROTECT MORTISED CUTOUTS WITH STEEL GUARD BOXES.
.6 PREPARE FRAME FOR DOOR SILENCERS, 3 FOR SINGLE DOOR, 2 AT HEAD FOR DOUBLE DOOR.
.7 CONCEAL FASTENINGS EXCEPT WHERE EXPOSED FASTENINGS ARE INDICATED.
.8 PROVIDE FACTORY-APPLIED TOUCH UP PRIMER AT AREAS WHERE ZINC COATING HAS BEEN REMOVED DURING FABRICATION.
.9 PROVIDE APPROPRIATE ANCHORAGE TO FLOOR AND WALL CONSTRUCTION.
.10 LOCATE EACH WALL ANCHOR IMMEDIATELY ABOVE OR BELOW EACH HINGE REINFORCEMENT ON HINGE JAMB AND DIRECTLY OPPOSITE ON STRIKE JAMB.
.11 PROVIDE 2 ANCHORS FOR REBATE OPENING HEIGHTS UP TO 60" AND 1 ADDITIONAL ANCHOR FOR EACH ADDITIONAL 30" OF HEIGHT OR FRACTION THEREOF.
.12 LOCATE ANCHORS FOR FRAMES IN EXISTING OPENINGS NOT MORE THAN 6" FROM TOP AND BOTTOM OF EACH JAMBS AND INTERMEDIATE AT 26" ON CENTRE MAXIMUM.
PART 3: EXECUTION
3.1 COMPLIANCE: .1 COMPLY WITH MANUFACTURER'S WRITTEN RECOMMENDATIONS OR SPECIFICATIONS, INCLUDING PRODUCT TECHNICAL
BULLETINS, HANDLING, STORAGE AND INSTALLATION INSTRUCTIONS, AND DATASHEETS. .2 INSTALL LABELLED STEEL FIRE RATED DOORS AND FRAMES TO NFPA 80 EXCEPT WHERE SPECIFIED OTHERWISE. .3 INSTALL DOORS AND FRAMES TO CSDMA INSTALLATION GUIDE.
3.2 FRAME INSTALLATION:.1 SET FRAMES PLUMB, SQUARE, LEVEL AND AT CORRECT ELEVATION. .2 SECURE ANCHORAGES AND CONNECTIONS TO ADJACENT CONSTRUCTION. .3 BRACE FRAMES RIGIDLY IN POSITION WHILE BUILDING-IN. INSTALL TEMPORARY HORIZONTAL WOOD SPREADER AT THIRD
POINTS OF DOOR OPENING TO MAINTAIN FRAME WIDTH. PROVIDE VERTICAL SUPPORT AT CENTRE OF HEAD FOR OPENINGS OVER 4' WIDE. REMOVE TEMPORARY SPREADERS AFTER FRAMES ARE BUILT-IN.
.4 MAKE ALLOWANCES FOR DEFLECTION OF STRUCTURE TO ENSURE STRUCTURAL LOADS ARE NOT TRANSMITTED TO FRAMES.
.5 CAULK PERIMETER OF FRAMES BETWEEN FRAME AND ADJACENT MATERIAL. 3.3 DOOR INSTALLATION:
.1 PROVIDE EVEN MARGINS BETWEEN DOORS AND JAMBS AND DOORS AND FINISHED FLOORAND THRESHOLDS AS FOLLOWS. .1 HINGE SIDE: 1/16" .2 LATCHSIDE AND HEAD: 1/16".3 FINISHED FLOOR: 1/2" EXCEPT WHERE NOTED OTHERWISE.
.2 ADJUST OPERABLE PARTS FOR CORRECT FUNCTION.
.3 INSTALL LOUVRES WHERE NOTED.3.4 FINISH AND REPAIRS:
.1 TOUCH UP WITH PRIMER FINISHES DAMAGED DURING INSTALLATION.
.2 FILL EXPOSED FRAME ANCHORS AND SURFACES WITH IMPERFECTIONS WITH METALLIC PASTE FILLER AND SAND TO A UNIFORM SMOOTH FINISH. 3.5 GLAZING: INSTALL GLAZING IN DOORS AND FRAMES AS PER GLAZING SPECIFICATION.
GLAZING:
PART 1: GENERAL
1.1 REFERENCES: .1 AMERICAN SOCIETY FOR TESTING AND MATERIALS INTERNATIONAL (ASTM): ASTM C 542-05, ASTM D 790-07el, ASTM D
1003-07el, ASTM D 1929-96(R2001)el, ASTM D 2240-05, ASTM E 84-10, ASTM E 330-02, ASTM F 1233-08..2 CANADIAN GENERAL STANDARDS BOARD (CGSB): CAN/CGSB-12.1-M90, CAN/CGSB-12.11-M90.
1.2 SUBMITTALS: .1 SUBMIT MANUFACTURER'S INSTRUCTIONS, PRINTED PRODUCT LITERATURE AND DATA SHEETS FOR GLASS, SEALANTS, AND
GLAZING ACCESSORIES AND INCLUDE PRODUCT CHARACTERISTICS, PERFORMANCE CRITERIA, PHYSICAL SIZE, FINISH AND LIMITATIONS.
.2 SUBMIT DRAWINGS STAMPED AND SIGNED BY PROFESSIONAL ENGINEER REGISTERED OR LICENSED IN PROVINCE TERRITORY OF NOVA SCOTIA, CANADA.
.3 SUBMIT PRODUCT CERTIFICATES SIGNED BY MANUFACTURER CERTIFYING MATERIALS COMPLY WITH SPECIFIED PERFORMANCE CHARACTERISTICS AND CRITERIA AND PHYSICAL REQUIREMENTS.
.4 SUBMIT OPERATION AND MAINTENANCE DATA FOR GLAZING FOR INCORPORATION INTO MANUAL.
PART 2: PRODUCTS
2.1 SAFETY GLASS: TO CAN/CGSB-12.1, TEMPERED, TRANSPARENT, 1/2" THICK MIN. EDGE TREATMENT TO SUIT APPLICATION.2.2 FIRE GLASS: FIRELITE®NT AS MANUFACTURED BY NIPPON ELECTRIC GLASS COMPANY, LTD. AND DISTRIBUTED BY TECHNICAL GLASS PRODUCTS, 45-MINUTE FIRE RATING MINIMUM, STANDARD FINISH2.3 ACCESSORIES: AS RECOMMENDED BY MANUFACTURER.
PART 3: EXECUTION
3.1 VERIFICATION OF CONDITIONS: .1 VERIFY CONDITIONS OF SUBSTRATES PREVIOUSLY INSTALLED UNDER OTHER SECTIONS OR CONTRACTS ARE ACCEPTABLE
FOR GLAZING INSTALLATION IN ACCORDANCE WITH MANUFACTURER'S WRITTEN INSTRUCTIONS. .2 VERIFY THAT OPENINGS FOR GLAZING ARE CORRECTLY SIZED AND WITHIN TOLERANCE. .3 VERIFY THAT SURFACES OF GLAZING CHANNELS OR RECESSES ARE CLEAN, FREE OF OBSTRUCTIONS, AND READY TO
RECEIVE GLAZING..4 PROCEED WITH INSTALLATION ONLY AFTER UNACCEPTABLE CONDITIONS HAVE BEEN REMEDIED.
3.2 COMPLY WITH MANUFACTURER'S WRITTEN DATA, INCLUDING PRODUCT TECHNICAL BULLETINS, PRODUCT CATALOGUE INSTALLATION INSTRUCTIONS, PRODUCT CARTON INSTALLATION INSTRUCTIONS, AND DATA SHEETS. 3.3 PERFORM WORK IN ACCORDANCE WITH GANA GLAZING MANUAL AND GANA LAMINATED GLAZING REFERENCE MANUAL FOR GLAZING INSTALLATION METHODS. 3.4 CUT GLAZING TAPE TO LENGTH AND SET AGAINST PERMANENT STOPS, PROJECTING 1/16" ABOVE SIGHT LINE. 3.5 REST GLAZING ON SETTING BLOCKS AND PUSH AGAINST TAPE FOR FULL CONTACT AT PERIMETER OF LIGHT OR UNIT. 3.6 KNIFE TRIM PROTRUDING TAPE. 3.7 PROTECT INSTALLED PRODUCTS AND COMPONENTS FROM DAMAGE DURING CONSTRUCTION. 3.8 REPAIR DAMAGE TO ADJACENT MATERIALS CAUSED BY GLAZING INSTALLATION.
JOST ARCHITECTS LTD.240 ST. GEORGE STREET, BOX 458
ANNAPOLIS ROYAL, NSP:(902) 532-2395 F:(902) 532-7707
1. CONTRACTOR MUST VERIFY ALL DRAWINGS WITH ON-SITE CONDITIONS, REPORTING ANY DISCREPANCY TO ARCHITECT BEFORE PROCEEDING WITH WORK.2. DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED BY THE ARCHITECT.3. DRAWINGS ARE NOT TO BE SCALED.4. ALL WORK IS TO COMPLY WITH THE 2015 NATIONAL BUILDING CODE AND ALL APPLICABLE CODES.5. CONTRACTOR TO RECEIVE WRITTEN APPROVAL FROM ARCHITECT PRIOR TO INSTALLATION OF ALTERNATE PRODUCTS.
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
HALIFAX, NOVA SCOTIA
- -
-
A ISSUED FOR TENDER 18/01/15
1809 BARRINGTON ST.
H353541-A-000
3" = 1'-0"
THE ACADEMY PROJECTLIBRARY RENOVATIONS
SPECIFICATIONS
STAFF
1702
HJ
A-108
STAFF
A-108
HJ HJ
M. BROWN18/01/15
RESILIENT SHEET FLOORING:
PART 1: GENERAL
1.1 REFERENCES: AMERICAN SOCIETY FOR TESTING AND MATERIALS INTERNATIONAL (ASTM): ASTM F 1303-04
1.2 SUBMITTALS.1 SUBMIT DUPLICATE 12" X 12" SAMPLE PIECES OF SHEET MATERIAL AND 12" LONG NOSING AND TRANSITION STRIPS..2 PROVIDE MAINTENANCE DATA FOR RESILIENT FLOORING FOR INCORPORATION INTO MAINTENANCE MANUAL..3 PROVIDE 100 SF OF EXTRA MATERIALS OF OF EACH COLOUR, PATTERN AND TYPE OF RESILIENT SHEET FLOORING AND ADHESIVES. IDENTIFY
EACH ROLL OF SHEET FLOORING AND CONTAINER OF ADHESIVE. DELIVER TO ARCHITECT..4 TURN OVER LARGE SCRAP CUT PIECES OF EACH COLOUR, PATTERN AND TYPE TO ARCHITECT..5 STORE WHERE DIRECTED BY ARCHITECT.
PART 2: PRODUCTS
2.1 MATERIALS :.1 LINOLEUM SHEET FLOORING: SEE ROOM FINISH SCHEDULE LEGEND FOR PRODUCT SELECTION. TWO COLOURS TO BE SELECTED BY
ARCHITECT FROM FULL COLOUR RANGE AFTER CONTRACT AWARD..2 RESILIENT STAIR NOSING: RECESSED VINYL STAIR NOSING, PRODUCT #PVIRCNN-XX-B BY JOHNSONITE OR APPROVED EQUIVALENT. COLOURS
TO BE SELECTED BY ARCHITECT FROM FULL COLOUR RANGE..3 PRIMERS AND ADHESIVES: OF TYPES RECOMMENDED BY RESILIENT FLOORING MANUFACTURER FOR SPECIFIC MATERIAL ON APPLICABLE
SUBSTRATE. .4 SUB-FLOOR FILLER AND LEVELLER: WHITE PREMIX LATEX REQUIRING WATER ONLY TO PRODUCE CEMENTITIOUS PASTE 2 PART LATEX-TYPE
FILLER REQUIRING NO WATER AS RECOMMENDED BY FLOORING MANUFACTURER FOR USE WITH THEIR PRODUCT. .5 TRANSITION STRIPS: ALUMINUM EXTRUDED, SMOOTH, MILL FINISH POLISHED STAINLESS STEEL WITH LIP TO EXTEND UNDER FLOOR FINISH,
SHOULDER FLUSH WITH TOP OF ADJACENT FLOOR FINISH. .6 EXTERNAL CORNER PROTECTORS: STAINLESS STEEL, TYPE RECOMMENDED BY FLOORING MANUFACTURER. .7 EDGING TO FLOOR PENETRATIONS: STAINLESS STEEL ALUMINUM, TYPE RECOMMENDED BY FLOORING MANUFACTURER. .8 CUSTOM WOOD BASE: WOOD BASE TO MATCH EXISTING TRIM.
2.2 MANUFACTURER'S INSTRUCTIONS: COMPLY WITH MANUFACTURER'S WRITTEN RECOMMENDATIONS OR SPECIFICATIONS, INCLUDING PRODUCT TECHNICAL BULLETINS, HANDLING, STORAGE AND INSTALLATION INSTRUCTIONS, AND DATASHEETS.
PART 3: EXECUTION
3.1 PREPARATION:.1 REMOVE EXISTING FLOORING. .2 REMOVE OR TREAT OLD ADHESIVES TO PREVENT RESIDUAL, OLD FLOORING ADHESIVES FROM BLEEDING THROUGH TO NEW FLOORING AND/OR
INTERFERING WITH THE BONDING OF NEW ADHESIVES. .3 CLEAN FLOOR AND APPLY FILLER; TROWEL AND FLOAT TO LEAVE SMOOTH, FLAT HARD SURFACE. PROHIBIT TRAFFIC UNTIL FILLER CURED AND
DRY. .4 REMOVE SUB-FLOOR RIDGES AND BUMPS. FILL LOW SPOTS, CRACKS, JOINTS, HOLES AND OTHER DEFECTS WITH SUB-FLOOR FILLER. .5 PREPARE SUBFLOOR TO RESILIENT FLOORING MANUFACTURER'S PRINTED INSTRUCTIONS.
3.2 APPLICATION: FLOORING.1 PROVIDE HIGH VENTILATION RATE, WITH MAXIMUM OUTSIDE AIR, DURING INSTALLATION, AND FOR 48 TOINSTALL METAL EDGE STRIPS AT
UNPROTECTED OR 72 HOURS AFTER INSTALLATION. IF POSSIBLE, VENT DIRECTLY TO OUTSIDE. DO NOT LET CONTAMINATED AIR RECIRCULATE THROUGH DISTRICT OR WHOLE BUILDING AIR DISTRIBUTION SYSTEM. MAINTAIN EXTRA VENTILATION FOR AT LEAST ONE MONTH FOLLOWING BUILDING OCCUPATION.
.2 APPLY ADHESIVE UNIFORMLY USING RECOMMENDED TROWEL. DO NOT SPREAD MORE ADHESIVE THAN CAN BE COVERED BY FLOORING BEFORE INITIAL SET TAKES PLACE.
.3 LAY FLOORING WITH SEAMS PARALLEL TO BUILDING LINES TO PRODUCE A MINIMUM NUMBER OF SEAMS. BORDER WIDTHS MINIMUM 1/3 WIDTH OF FULL MATERIAL.
.4 RUN SHEETS IN DIRECTION OF TRAFFIC. DOUBLE CUT SHEET JOINTS AND CONTINUOUSLY SEAL HEAT WELD ACCORDING TO MANUFACTURER'S PRINTED INSTRUCTIONS.
.5 HEAT WELD SEAMS OF LINOLEUM SHEET FLOORING IN ACCORDANCE WITH MANUFACTURER'S PRINTED INSTRUCTIONS.
.6 AS INSTALLATION PROGRESSES, AND AFTER INSTALLATION ROLL FLOORING WITH 45 KG MINIMUM ROLLER TO ENSURE FULL ADHESION.
.7 CUT FLOORING AROUND FIXED OBJECTS.
.8 INSTALL FEATURE STRIPS AND FLOOR MARKINGS WHERE INDICATED. FIT JOINTS TIGHTLY.
.9 CONTINUE FLOORING OVER AREAS WHICH WILL BE UNDER BUILT-IN FURNITURE.
.10 CONTINUE FLOORING THROUGH AREAS TO RECEIVE MOVABLE TYPE PARTITIONS WITHOUT INTERRUPTING FLOOR PATTERN.
.11 TERMINATE FLOORING AT CENTRELINE OF DOOR IN OPENINGS WHERE ADJACENT FLOOR FINISH OR COLOUR IS DISSIMILAR.
.12 INSTALL METAL EDGE STRIPS AT UNPROTECTED OR EXPOSED EDGES WHERE FLOORING TERMINATES. 3.3 APPLICATION: RISERS: INSTALL STAIR NOSINGS ONE PIECE FOR FULL WIDTH OF STAIR WHEREVER POSSIBLE. NO PIECE TO BE LESS THAN 24" LONG. ADHERE OVER ENTIRE SURFACE AND FIT ACCURATELY. 3.4 CLEANING:
.1 REMOVE EXCESS ADHESIVE FROM FLOOR, BASE AND WALL SURFACES WITHOUT DAMAGE.
.2 CLEAN TO FLOORING MANUFACTURER'S PRINTED INSTRUCTIONS.
.3 PROHIBIT TRAFFIC ON FLOOR FOR 48 HOURS AFTER INSTALLATION.
.4 USE ONLY WATER-BASED COATING FOR LINOLEUM.
ARCHITECTURAL WOODWORK:
PART 1: GENERAL
1.1 REFERENCES: .1 AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI): ANSI/NPA A208.1-09, ANSI/NPA A208.2-09, ANSI/HPVA HP-1-04..2 ASTM INTERNATIONAL: ASTM E 1333-96(2002), ASTM D 2832-92(R2005), ASTM D 5116-06..3 ARCHITECTURAL WOODWORK MANUFACTURERS ASSOCIATION OF CANADA (AWMAC) AND ARCHITECTURAL WOODWORK INSTITUTE (AWI):
ARCHITECTURAL WOODWORK QUALITY STANDARDS ILLUSTRATED, 8TH EDITION, VERSION 1.0 (2009). .4 CANADIAN GENERAL STANDARDS BOARD (CGSB): CAN/CGSB-71.20-M88..5 CSA INTERNATIONAL: CSA B111-74(R2003), CSA O112.4 SERIES-M1977(R2006), CSA O121-08, CSA O141-05, CSA O151-09, CSA O153-M1980(R2008)..6 FOREST STEWARDSHIP COUNCIL (FSC): FSC-STD-01-001-2004, FSC-STD-20-002-2004..7 GREEN SEAL ENVIRONMENTAL STANDARDS (GS): GS-11-2008, GS-36-00..8 HEALTH CANADA / WORKPLACE HAZARDOUS MATERIALS INFORMATION SYSTEM (WHMIS): MATERIAL SAFETY DATA SHEETS (MSDS). .9 INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO): ISO 14040-2006, ISO 14041-98, .10 NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA): ANSI/NEMA LD-3-05..11 NATIONAL LUMBER GRADES AUTHORITY (NLGA): STANDARD GRADING RULES FOR CANADIAN LUMBER 2003(R2007).
1.2 SUBMITTALS.1 SUBMIT MANUFACTURER'S INSTRUCTIONS, PRINTED PRODUCT LITERATURE AND DATA SHEETS FOR ARCHITECTURAL WOODWORK AND INCLUDE
PRODUCT CHARACTERISTICS, PERFORMANCE CRITERIA, PHYSICAL SIZE, FINISH AND LIMITATIONS. .2 SHOP DRAWINGS:
.1 SUBMIT DRAWINGS INDICATING DETAILS OF CONSTRUCTION, PROFILES, JOINTING, FASTENING AND OTHER RELATED DETAILS. SCALES: PROFILES FULL SIZE, DETAILS HALF SIZE. .2 INDICATE MATERIALS, THICKNESSES, FINISHES AND HARDWARE. .3 INDICATE LOCATIONS OF SERVICE OUTLETS IN CASEWORK, TYPICAL AND SPECIAL INSTALLATION CONDITIONS, AND CONNECTIONS,
ATTACHMENTS, ANCHORAGE AND LOCATION OF EXPOSED FASTENINGS..3 SUBMIT DUPLICATE SAMPLES: SAMPLE SIZE 12" X 12" OR SAMPLE SIZE X 12" LONG. .4 SUBMIT DUPLICATE SAMPLES OF LAMINATED PLASTIC FOR COLOUR SELECTION. .5 SUBMIT DUPLICATE SAMPLES OF LAMINATED PLASTIC JOINTS, EDGING, CUTOUTS AND POSTFORMED PROFILES.
1.3 CERTIFICATIONS: SUBMIT CERTIFICATES SIGNED BY MANUFACTURER CERTIFYING THAT MATERIALS COMPLY WITH SPECIFIED PERFORMANCE CHARACTERISTICS AND PHYSICAL PROPERTIES.
PART 2: PRODUCTS
2.1 CASEWORK (INCLUDING CASE BODIES, BACKS, FRONTS, SHELVING, DRAWERS AND DOORS: BIRCH PLYWOOD: 3/4" THICK, TO AWMAC CUSTOM GRADE, FSC CERTIFIED, PLYWOOD RESIN TO CONTAIN NO ADDED UREA-FORMALDEHYDE.2.2 COUNTERTOPS:
.1 FINISH: FORMICA® BRAND LAMINATE OR APPROVED EQUIVALENT. COLOUR TO BE DETERMINED BY ARCHITECT FROM FULL COLOUR RANGE.
.2 SUBSTRATE: AS RECOMMENDED BY PLASTIC LAMINATE MANUFACTURER.2.3 ACCESSORIES: TO SUIT APPLICATION2.4 HARDWARE:
.1 HINGES: CONCEALED, TYPE TO SUIT APPLICATION, STAINLESS STEEL FINISH
.2 DOOR & DRAWER PULLS: "TRADITIONAL BRASS CUP PULL - 3038" BY RICHELIEU OR APPROVED EQUIVALENT, FINISH TO BE DETERMINED BY ARCHITECT FROM FULL RANGE.
.3 CATCHES: MAGNETIC, TYPE TO SUIT APPLICATION
.4 SHELF RESTS AND STANDARDS: SHELF REST INSTALLED IN HOLES DRILLED, TYPE TO SUIT APPLICATION
.5 DRAWER SLIDES: BOTTOME EDGE MOUNTED, TYPE TO SUIT APPLICATION
.6 CABINET LOCKS: HALF-MORTISED, TYPE TO SUITE APPLICATION, FINISH TO MATCH DOOR & DRAWER PULLS
PART 3: EXECUTION
3.1 DO ARCHITECTURAL WOODWORK TO QUALITY STANDARDS OF AWMAC. 3.2 INSTALL PREFINISHED MILLWORK AT LOCATIONS SHOWN ON DRAWINGS. POSITION ACCURATELY, LEVEL, PLUMB STRAIGHT. 3.3 FASTEN AND ANCHOR MILLWORK SECURELY. SUPPLY AND INSTALL HEAVY DUTY FIXTURE ATTACHMENTS FOR WALL MOUNTED CABINETS. 3.4 USE DRAW BOLTS IN COUNTERTOP JOINTS. 3.5 SCRIBE AND CUT AS REQUIRED TO FIT ABUTTING WALLS AND TO FIT PROPERLY INTO RECESSES AND TO ACCOMMODATE PIPING, COLUMNS, FIXTURES, OUTLETS OR OTHER PROJECTING, INTERSECTING OR PENETRATING OBJECTS. 3.6 AT JUNCTION OF PLASTIC LAMINATE COUNTER AND ADJACENT WALL FINISH, APPLY SMALL BEAD OF SEALANT.3.7 FIT HARDWARE ACCURATELY AND SECURELY IN ACCORDANCE WITH MANUFACTURER'S WRITTEN INSTRUCTIONS. 3.8 APPLY LAMINATED PLASTIC TO UNITS AS INDICATED.
.1 ADHERE LAMINATED PLASTIC OVER ENTIRE SURFACE.
.2 MAKE CORNERS WITH HAIRLINE JOINTS.
.3 USE FULL SIZED LAMINATE SHEETS.
.4 MAKE JOINTS ONLY WHERE INDICATED BY ARCHITECT. 3.9 FOR SITE APPLICATION, OFFSET JOINTS IN PLASTIC LAMINATE FACING FROM JOINTS IN CORE. 3.10 CLEAN MILLWORK AND CABINET WORK INSIDE CUPBOARDS AND DRAWERS AND OUTSIDE SURFACES. REMOVE EXCESS GLUE FROM SURFACES. 3.11 PROTECT MILLWORK AND CABINET WORK FROM DAMAGE UNTIL FINAL INSPECTION. 3.12 PROTECT INSTALLED PRODUCTS AND COMPONENTS FROM DAMAGE DURING CONSTRUCTION. 3.13 REPAIR DAMAGE TO ADJACENT MATERIALS CAUSED BY ARCHITECTURAL WOODWORK INSTALLATION.
INTERIOR PAINTING:
PART 1: GENERAL
1.1 REFERENCES: .1 DEPARTMENT OF JUSTICE CANADA (JUS): CANADIAN ENVIRONMENTAL PROTECTION ACT (CEPA), 1999, C. 33 .2 ENVIRONMENTAL PROTECTION AGENCY (EPA): EPA TEST METHOD FOR MEASURING TOTAL VOLATILE ORGANIC COMPOUND CONTENT OF CONSUMER PRODUCTS, METHOD 24 - 1995, (FOR
SURFACE COATINGS). .3 HEALTH CANADA / WORKPLACE HAZARDOUS MATERIALS INFORMATION SYSTEM (WHMIS): MATERIAL SAFETY DATA SHEETS (MSDS). .4 MASTER PAINTERS INSTITUTE (MPI):MPI ARCHITECTURAL PAINTING SPECIFICATIONS MANUAL, 2004. .5 NATIONAL FIRE CODE OF CANADA - 1995
1.2 QUALITY ASSURANCE:.1 PROVIDE 12" X 12" MOCK-UP. PREPARE AND PAINT DESIGNATED SURFACE, AREA, ROOM OR ITEM (IN EACH COLOUR SCHEME) TO SPECIFIED REQUIREMENTS, WITH SPECIFIED PAINT OR
COATING SHOWING SELECTED COLOURS, GLOSS/SHEEN, TEXTURES..2 MOCK-UP WILL BE USED: TO JUDGE WORKMANSHIP, SUBSTRATE PREPARATION, OPERATION OF EQUIPMENT AND MATERIAL APPLICATION AND WORKMANSHIP TO MPI ARCHITECTURAL
PAINTING SPECIFICATION MANUAL STANDARDS. .3 LOCATE WHERE DIRECTED WHERE INDICATED BY ARCHITECT..4 ALLOW 24 HOURS FOR INSPECTION OF MOCK-UP BEFORE PROCEEDING WITH WORK. .5 WHEN ACCEPTED, MOCK-UP WILL DEMONSTRATE MINIMUM STANDARD OF QUALITY REQUIRED FOR THIS WORK. APPROVED MOCK-UP MAY NOT REMAIN AS PART OF FINISHED WORK.
1.3 SUBMITTALS:.1 SUBMIT PRODUCT DATA AND INSTRUCTIONS FOR EACH PAINT AND COATING PRODUCT TO BE USED. .2 SUBMIT PRODUCT DATA FOR THE USE AND APPLICATION OF PAINT THINNER. .3 SUBMIT TWO COPIES OF WORKPLACE HAZARDOUS MATERIALS INFORMATION SYSTEM (WHMIS) MATERIAL SAFETY DATA SHEETS (MSDS)..4 SUBMIT MAINTENANCE DATA FOR INCORPORATION INTO MANUAL..5 PROVIDE ONE FOUR LITRE CAN OF EACH TYPE AND COLOUR OF PRIMER, STAIN AND FINISH COATING. IDENTIFY COLOUR AND PAINT TYPE IN RELATION TO ESTABLISHED COLOUR SCHEDULE
AND FINISH SYSTEM.1.2 SAMPLES:
.1 SUBMIT FULL RANGE COLOUR SAMPLE CHIPS TO INDICATE WHERE COLOUR AVAILABILITY IS RESTRICTED.
.2 SUBMIT DUPLICATE 8" X 12" SAMPLE PANELS OF EACH PAINT STAIN CLEAR COATING SPECIAL FINISH WITH SPECIFIED PAINT OR COATING IN COLOURS, GLOSS/SHEEN AND TEXTURES REQUIRED TO MPI ARCHITECTURAL PAINTING SPECIFICATION MANUAL STANDARDS SUBMITTED ON FOLLOWING SUBSTRATE MATERIALS:
.1 1/8" PLATE STEEL FOR FINISHES OVER METAL SURFACES.
.2 1/2" BIRCH PLYWOOD FOR FINISHES OVER WOOD SURFACES.
.4 1/2" GYPSUM BOARD FOR FINISHES OVER GYPSUM BOARD AND OTHER SMOOTH SURFACES.
.3 RETAIN REVIEWED SAMPLES ON-SITE TO DEMONSTRATE ACCEPTABLE STANDARD OF QUALITY FOR APPROPRIATE ON- SITE SURFACE.1.3 TEST REPORTS: SUBMIT CERTIFIED TEST REPORTS FOR PAINT FROM APPROVED INDEPENDENT TESTING LABORATORIES, INDICATING COMPLIANCE WITH SPECIFICATIONS FOR SPECIFIED PERFORMANCE CHARACTERISTICS AND PHYSICAL PROPERTIES.
PART 2: PRODUCTS
2.1 INTERIOR ACRYLIC LATEX PAINT: "MANOR HALL" BY PPG PAINTS OR APPROVED EQUIVALENT. 2.2 SEMI-TRANSPARENT STAIN: MINWAX WATERBASED WOOD STAIN OR APPROVED EQUIVALENT.2.3 INTUMESCENT PAINT: SPEEDHIDE® INTERIOR FIRE RETARDANT FLAT LATEX BY PPG PAINTS OR APPROVED EQUIVALENT. APPLIED TO ACHIEVE MINIMUM 45 MINUTE FIRE-RATING.2.4 COLOURS: COLOUR SCHEDULE WILL BE BASED UPON SELECTION OF FIVE BASE COLOURS AND THREE ACCENT COLOURS. NO MORE THAN EIGHT COLOURS WILL BE SELECTED FOR ENTIRE PROJECT AND NO MORE THAN THREE COLOURS WILL BE SELECTED IN EACH AREA. SELECTION OF COLOURS FORM MANUFACTURERS FULL RANGE OF COLOURS.2.5 PERFORM COLOUR TINTING OPERATIONS PRIOR TO DELIVER OF PAINT TO SITE. MIX AND THINK IN ACCORDANCE WITH MANUFACTURER'S WRITTEN INSTRUCTIONS. RE-MIX PAINT IN CONTAINERS PRIOR TO AND DURING APPLICATION TO ENSURE BREAK-UP OF LUMPS, COMPLETE DISPERSION OF SETTLED PIGMENT, AND COLOUR AND GLOSS UNIFORMITY.2.6 PAINT GLOSS IS DEFINED AS SHEEN RATING OF APPLIED PAINT IN ACCORDANCE WITH THE FOLLOWING VALUES:
GLOSS @ 60 SHEEN @ 85 DEGREES DEGREES GLOSS LEVEL 1 MAX. 5 MAX. 10 - MATTE FINISH (FLAT) GLOSS LEVEL 2 MAX.10 10 TO 35 - VELVET-LIKE FINISH GLOSS LEVEL 3 10 TO 25 10 TO 35 - EGGSHELL FINISH GLOSS LEVEL 4 20 TO 35 MIN. 35 - SATIN-LIKE FINISH GLOSS LEVEL 5 35 TO 70 - TRADITIONAL SEMI-GLOSS FINISH GLOSS LEVEL 6 70 TO 85 - TRADITIONAL GLOSS GLOSS LEVEL 7 MORE THAN 85 - HIGH GLOSS FINISH2.7 INTERIOR PAINTING SYSTEMS:
.1 STRUCTURAL STEEL (COLUMNS AND EXPOSED BEAMS): INTUMESCENT PAINT TO ACHIEVE MINIMUM 45 MINUTE FIRE-RATING, SEMI-GLOSS FINISH.
.2 METAL DOOR FRAMES: INTERIOR ACRYLIC LATEX PAINT, SEMI-GLOSS FINISH.
.3 WOOD FRAMES, CASINGS, TRIMS, MOULDINGS AND BASEBOARD: INTERIOR ACRYLIC LATEX PAINT, SEMI-GLOSS FINISH.
.4 CASEWORK: SEMI-TRANSPARENT STAIN, GLOSS FINISH
.5 WOOD DOORS: SEMI-TRANSPARENT STAIN, GLOSS FINISH
.6 METAL DOORS: INTERIOR ACRYLIC LATEX PAINT, GLOSS FINISH
.7 GYPSUM BOARD (HORIZONTAL AND VERTICAL SURFACES): INTERIOR ACRYLIC LATEX PAINT, SATIN FINISH.
.8 WOOD RISERS (BAND ROOM): INTERIOR ACRYLIC LATEX PAINT, GLOSS FINISH.
PART 3: EXECUTION
3.1 COMPLIANCE: COMPLY WITH MANUFACTURER'S WRITTEN RECOMMENDATIONS OR SPECIFICATIONS, INCLUDING PRODUCT TECHNICAL BULLETINS, HANDLING, STORAGE AND INSTALLATION INSTRUCTIONS, AND DATA SHEET. 3.2 PERFORM PREPARATION AND OPERATIONS FOR INTERIOR PAINTING IN ACCORDANCE WITH MPI ARCHITECTURAL PAINTING SPECIFICATIONS MANUAL EXCEPT WHERE SPECIFIED OTHERWISE. 3.3 APPLY PAINT MATERIALS IN ACCORDANCE WITH PAINT MANUFACTURER'S WRITTEN APPLICATION INSTRUCTIONS.3.4 INVESTIGATE EXISTING SUBSTRATES FOR PROBLEMS RELATED TO PROPER AND COMPLETE PREPARATION OF SURFACES TO BE PAINTED. REPORT TO ARCHITECT DAMAGES, DEFECTS, UNSATISFACTORY OR UNFAVOURABLE CONDITIONS BEFORE PROCEEDING WITH WORK. 3.5 PREPARATION:
.1 PROTECTION: .1 PROTECT EXISTING BUILDING SURFACES AND ADJACENT STRUCTURES FROM PAINT SPATTERS, MARKINGS AND OTHER DAMAGE BY SUITABLE NON-STAINING COVERS OR MASKING. IF
DAMAGED, CLEAN AND RESTORE SURFACES AS DIRECTED BY ARCHITECT. .2 PROTECT ITEMS THAT ARE PERMANENTLY ATTACHED SUCH AS FIRE LABELS ON DOORS AND FRAMES. .3 PROTECT FACTORY FINISHED PRODUCTS AND EQUIPMENT. .4 PROTECT PASSING PEDESTRIANS, BUILDING OCCUPANTS AND GENERAL PUBLIC IN AND ABOUT THE BUILDING.
.2 SURFACE PREPARATION: .1 REMOVE ELECTRICAL COVER PLATES, LIGHT FIXTURES, SURFACE HARDWARE ON DOORS, BATH ACCESSORIES AND OTHER SURFACE MOUNTED EQUIPMENT, FITTINGS AND FASTENINGS
PRIOR TO UNDERTAKING PAINTING OPERATIONS. IDENTIFY AND STORE ITEMS IN SECURE LOCATION AND RE-INSTALLED AFTER PAINTING IS COMPLETED. .2 MOVE AND COVER FURNITURE AND PORTABLE EQUIPMENT AS NECESSARY TO CARRY OUT PAINTING OPERATIONS. REPLACE AS PAINTING OPERATIONS PROGRESS. .3 PLACE "WET PAINT" SIGNS IN OCCUPIED AREAS AS PAINTING OPERATIONS PROGRESS.
.3 CLEAN AND PREPARE SURFACES IN ACCORDANCE WITH MPI ARCHITECTURAL PAINTING SPECIFICATION MANUAL REQUIREMENTS.
.4 PREVENT CONTAMINATION OF CLEANED SURFACES BY SALTS, ACIDS, ALKALIS, OTHER CORROSIVE CHEMICALS, GREASE, OIL AND SOLVENTS BEFORE PRIME COAT IS APPLIED AND BETWEEN APPLICATIONS OF REMAINING COATS. APPLY PRIMER, PAINT, OR PRETREATMENT AS SOON AS POSSIBLE AFTER CLEANING AND BEFORE DETERIORATION OCCURS.
.5 WHERE POSSIBLE, PRIME NON-EXPOSED SURFACES OF NEW WOOD SURFACES BEFORE INSTALLATION. USE SAME PRIMERS AS SPECIFIED FOR EXPOSED SURFACES. .1 APPLY VINYL SEALER TO MPI #36 OVER KNOTS, PITCH, SAP AND RESINOUS AREAS. .2 APPLY WOOD FILLER TO NAIL HOLES AND CRACKS. .3 TINT FILLER TO MATCH STAINS FOR STAINED WOODWORK. SAND AND DUST BETWEEN COATS AS REQUIRED TO PROVIDE ADEQUATE ADHESION FOR NEXT COAT AND TO REMOVE DEFECTS
VISIBLE FROM A DISTANCE UP TO 1000 MM. .6 CLEAN METAL SURFACES TO BE PAINTED BY REMOVING RUST, LOOSE MILL SCALE, WELDING SLAG, DIRT, OIL, GREASE AND OTHER FOREIGN SUBSTANCES IN ACCORDANCE WITH MPI
REQUIREMENTS. REMOVE TRACES OF BLAST PRODUCTS FROM SURFACES, POCKETS AND CORNERS TO BE PAINTED BY BRUSHING WITH CLEAN BRUSHES BLOWING WITH CLEAN DRY COMPRESSED AIR OR VACUUM CLEANING.
.7 TOUCH UP OF SHOP PRIMERS WITH PRIMER AS SPECIFIED. 3.6 CONFORM TO MANUFACTURER'S APPLICATION INSTRUCTIONS UNLESS SPECIFIED OTHERWISE. 3.7 APPLICATION:
.1 BRUSH AND ROLLER APPLICATION: .1 APPLY PAINT IN UNIFORM LAYER USING BRUSH AND/OR ROLLER TYPE SUITABLE FOR APPLICATION. .2 WORK PAINT INTO CRACKS, CREVICES AND CORNERS. .3 PAINT SURFACES AND CORNERS NOT ACCESSIBLE TO BRUSH USING SPRAY, DAUBERS AND/OR SHEEPSKINS. PAINT SURFACES AND CORNERS NOT ACCESSIBLE TO ROLLER USING BRUSH,
DAUBERS OR SHEEPSKINS. .4 BRUSH AND/OR ROLL OUT RUNS AND SAGS, AND OVER-LAP MARKS. ROLLED SURFACES FREE OF ROLLER TRACKING AND HEAVY STIPPLE. .5 REMOVE RUNS, SAGS AND BRUSH MARKS FROM FINISHED WORK AND REPAINT.
.2 APPLY COATS OF PAINT CONTINUOUS FILM OF UNIFORM THICKNESS. REPAINT THIN SPOTS OR BARE AREAS BEFORE NEXT COAT OF PAINT IS APPLIED.
.3 ALLOW SURFACES TO DRY AND PROPERLY CURE AFTER CLEANING AND BETWEEN SUBSEQUENT COATS FOR MINIMUM TIME PERIOD AS RECOMMENDED BY MANUFACTURER.
.4 SAND AND DUST BETWEEN COATS TO REMOVE VISIBLE DEFECTS.
.5 FINISH SURFACES BOTH ABOVE AND BELOW SIGHT LINES AS SPECIFIED FOR SURROUNDING SURFACES, INCLUDING SUCH SURFACES AS TOPS OF INTERIOR CUPBOARDS AND CABINETS AND PROJECTING LEDGES.
.6 FINISH INSIDE OF CUPBOARDS AND CABINETS AS SPECIFIED FOR OUTSIDE SURFACES.
.7 FINISH CLOSETS AND ALCOVES AS SPECIFIED FOR ADJOINING ROOMS.
.8 FINISH TOP, BOTTOM, EDGES AND CUTOUTS OF DOORS AFTER FITTING AS SPECIFIED FOR DOOR SURFACES.
.9 PAINT FINISHED AREA EXPOSED CONDUITS, PIPING, HANGERS, DUCTWORK AND OTHER MECHANICAL AND ELECTRICAL EQUIPMENT WITH COLOUR AND FINISH TO MATCH ADJACENT SURFACES, EXCEPT AS INDICATED.
.10 BOILER ROOM, MECHANICAL AND ELECTRICAL ROOMS: PAINT EXPOSED CONDUITS, PIPING, HANGERS, DUCTWORK AND OTHER MECHANICAL AND ELECTRICAL EQUIPMENT.
.11 OTHER UNFINISHED AREAS: LEAVE EXPOSED CONDUITS, PIPING, HANGERS, DUCTWORK AND OTHER MECHANICAL AND ELECTRICAL EQUIPMENT IN ORIGINAL FINISH AND TOUCH UP SCRATCHES AND MARKS.
.12 TOUCH UP SCRATCHES AND MARKS ON FACTORY PAINTED FINISHES AND EQUIPMENT WITH PAINT AS SUPPLIED BY MANUFACTURER OF EQUIPMENT.
.13 DO NOT PAINT OVER NAMEPLATES.
.14 KEEP SPRINKLER HEADS FREE OF PAINT.
.15 PAINT INSIDE OF DUCTWORK WHERE VISIBLE BEHIND GRILLES, REGISTERS AND DIFFUSERS WITH PRIMER AND ONE COAT OF MATT BLACK PAINT.
.16 PAINT FIRE PROTECTION PIPING RED.
.17 PAINT DISCONNECT SWITCHES FOR FIRE ALARM SYSTEM AND EXIT LIGHT SYSTEMS IN RED ENAMEL.
.18 DO NOT PAINT INTERIOR TRANSFORMERS AND SUBSTATION EQUIPMENT. 3.8 FIELD QUALITY CONTROL:
.1 WALLS: NO DEFECTS VISIBLE FROM A DISTANCE OF 1000 MM AT 90 DEGREES TO SURFACE.
.2 CEILINGS: NO DEFECTS VISIBLE FROM FLOOR AT 45 DEGREES TO SURFACE WHEN VIEWED USING FINAL LIGHTING SOURCE.
.3 FINAL COAT TO EXHIBIT UNIFORMITY OF COLOUR AND UNIFORMITY OF SHEEN ACROSS FULL SURFACE AREA.
.4 WHERE "SPECIAL" PAINTING, COATING OR DECORATING SYSTEM APPLICATIONS (I.E. INTUMESCENT PAINT) OR NON-MPI LISTED PRODUCTS OR SYSTEMS ARE TO BE USED, PAINT OR COATING MANUFACTURER SHALL PROVIDE AS PART OF THIS WORK, CERTIFICATION OF SURFACES AND CONDITIONS FOR SPECIFIC PAINT OR COATING SYSTEM APPLICATION AS WELL AS ON SITE SUPERVISION, INSPECTION AND APPROVAL OF THEIR PAINT OR COATING SYSTEM APPLICATION AS REQUIRED AT NO ADDITIONAL COST TO DEPARTMENTAL REPRESENTATIVE DCC REPRESENTATIVE CONSULTANT.3.9 RESTORATION:
.1 CLEAN AND RE-INSTALL HARDWARE ITEMS REMOVED BEFORE UNDERTAKEN PAINTING OPERATIONS.
.2 REMOVE PROTECTIVE COVERINGS AND WARNING SIGNS AS SOON AS PRACTICAL AFTER OPERATIONS CEASE.
.3 REMOVE PAINT SPLASHINGS ON EXPOSED SURFACES THAT WERE NOT PAINTED. REMOVE SMEARS AND SPATTER IMMEDIATELY AS OPERATIONS PROGRESS, USING COMPATIBLE SOLVENT.
.4 PROTECT FRESHLY COMPLETED SURFACES FROM PAINT DROPPINGS AND DUST TO APPROVAL OF ARCHITECT. AVOID SCUFFING NEWLY APPLIED PAINT.
.5 RESTORE AREAS USED FOR STORAGE, CLEANING, MIXING AND HANDLING OF PAINT TO CLEAN CONDITION AS APPROVED BY ARCHITECT.
JOST ARCHITECTS LTD.240 ST. GEORGE STREET, BOX 458
ANNAPOLIS ROYAL, NSP:(902) 532-2395 F:(902) 532-7707
1. CONTRACTOR MUST VERIFY ALL DRAWINGS WITH ON-SITE CONDITIONS, REPORTING ANY DISCREPANCY TO ARCHITECT BEFORE PROCEEDING WITH WORK.2. DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED BY THE ARCHITECT.3. DRAWINGS ARE NOT TO BE SCALED.4. ALL WORK IS TO COMPLY WITH THE 2015 NATIONAL BUILDING CODE AND ALL APPLICABLE CODES.5. CONTRACTOR TO RECEIVE WRITTEN APPROVAL FROM ARCHITECT PRIOR TO INSTALLATION OF ALTERNATE PRODUCTS.
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
HALIFAX, NOVA SCOTIA
- -
-
A ISSUED FOR TENDER 18/01/15
1809 BARRINGTON ST.
H353541-A-000
3" = 1'-0"
THE ACADEMY PROJECTLIBRARY RENOVATIONS
SPECIFICATIONS CONT.
STAFF
1702
HJ
A-109
STAFF
A-109
HJ HJ
M. BROWN18/01/15
SHADED AREA NOT IN CONTRACT
UP
QUIET ROOM
1
STACKS &
READING
2
JANITOR
6
PROGRAM
8
FOOD BANK
7
PROGRAM
9
FAM./B.F. WR.
10
WR.
13
WR.
14
STORAGE
11
OFFICE
3
BOILER ROOM
5
STORAGE
4
COMMON
15
12
1" EXT
2" EXT
4" EXT
3" EXT
3/4" EXT
3/4" EXT
3/4" EXT
3/4" EXT
4"
3/4"
1"
3/4"
5
114
3
2
6
8
9
L-1
WC-1
WC-1
WC-1
L-2L-2
SS-2
SS-1
MSB-1
SS-3
FAM./B.F. WR.
10
WR.
13
WR.
14
STORAGE
11
WHAWHA
WHA
WHA
WHA
L-1
WC-2
WC-1
WC-1
L-2L-2
SS-2
SS-1
1"
3/4"
3/4"
1/2"
1/2"
1/2"
1"
1/2"
CO
CO
4"
4"
4"
4"
4"
4"
10
10
1/2"
1"
1"
JANITOR
6
FOOD BANK
7
BOILER ROOM
5
STORAGE
4
CO
FFD
TP-1
SS-3
MSB-1
3/4" EXT
1 1/4" EXT
2" EXT
3" EXT
3" EXT
3"
1/2"
1/2"
11/2"
13
1
12
88
1/2" EXT
3/4" EXT
3" EXT
BFP-1
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
MECHANICAL
BASEMENT PLUMBING FLOOR PLANS, DETAILS &
LEGEND
H353541-M-001 M-001 B
M. BROWN
17/10/13 17/10/13 18/01/04
18/01/05
H353541
HALIFAX, NOVA SCOTIA
A ISSUED FOR 99% REVIEW MB AS 17/12/19
R. POIRIER A. SRIVASTAVA
M. BROWN
B ISSUED FOR TENDER MB AS 18/01/17
1809 BARRINGTON ST.
BASEMENT PLAN - PLUMBING
SCALE: 1/8"=1'-0"
1
M-001
PLUMBING LEGEND
DOMESTIC COLD WATER PIPING
DOMESTIC HOT WATER PIPING
DOMESTIC HOT WATER RECIRC.
SANITARY PIPING BELOW GROUND
EXISTING DOMESTIC COLD WATER PIPING
EXISTING DOMESTIC HOT WATER PIPING
EXSITING DOMESTIC HOT WATER RECIRC.
EXISTING SANITARY PIPING BELOW GROUND
TRAP PRIMER PIPING
"EXT"PIPE SIZE SUFFIX, INDICATES EXISTING PIPE
CLEAN OUT IN FLOOR
PRESSURE REGULATING VALVE
CHECK VALVE
BALL VALVE
UNION
TRAP PRIMER PASSIVE UNIT
WATER HAMMER ARRESTER
BACKFLOW PREVENTER
FUNNEL FLOOR DRAIN
RECIRCULATION PUMP
FFD
CO
BFP
TP
WHA
1 CONNECT NEW 3" SANITARY TO EXISTING U/S SANITARY.
TRENCH FLOOR AS NECESSARY. REPAIR/PATCH FLOOR.
CONNECT NEW 4" SANITARY TO EXISTING U/S SANITARY.
TRENCH FLOOR AS NECESSARY. REPAIR/PATCH FLOOR.
EXISTING 4" SANITARY STACK FROM GYM LEVEL ABOVE.
REMOVE ALL EXISTING BASEMENT PLUMBING FIXTURES
AND CAP SANITARY STUBS BELOW SLAB. REPAIR/PATCH
SLAB.
CONNECT NEW COLD WATER PIPING TO EXISTING PIPING IN
CEILING SPACE.
CONNECT NEW HOT WATER PIPING TO EXISTING IN CEILING
SPACE.
CAP EXISTING PIPING IN CEILING SPACE .
CONNECT NEW RE-CIRCULATION HOT WATER PIPING TO
EXISTING IN CEILING SPACE.
EXISTING WATER PIPING TO KITCHEN TO REMAIN.
HOT / COLD WATER PIPING DOWN IN WALL. CONNECT TO
BACK TO BACK SINKS.
REMOVE EXISTING WATER PIPING THAT SERVED
DEMOLISHED BASEMENT FIXTURES, CAP AT HOT / COLD
MAINS IN CEILING.
EXISTING HOT / COLD WATER PIPING RUN TO NEW MSB1 &
SS-3 FIXTURES.
NEW PASSIVE TYPE TRAP PRIMER INSTALLED ABOVE MSB1.
CONNECT TO COLD WATER SUPPLY RUN NEW 1/2" COPPER
TP LINE TO FFD IN BOILER ROOM.
4
6
7
8
10
WASHROOM ENLARGEMENT
SCALE: 1/4"=1'-0"
2
M-001
BASEMENT PLAN - PLUMBING
SCALE: 1/4"=1'-0"
3
M-001
3
M-001
2
M-001
GENERAL NOTE:
CONTRACTOR TO INSTALL ALL VENT PIPING IN
ACCORDANCE WITH THE N.P.C. CONTRACTOR TO RE-USE
EXISTING VENT PIPING IN EXISTING WASHROOM AREA
WHERE POSSIBLE.
FOR CONTINUATION
REFER TO FLOOR
PLAN
TRAP PRIMING VALVE
(C/W VACUUM BREAKER PORTS)
DISTRIBUTION UNIT (AS REQUIRED)
UNION CONNECTIONS
SERVICE VALVE
TRAP PRIMER DETAIL
SCALE: NTS
4
M-001
GENERAL NOTE:
PLUMBING CONTRACTOR SHALL COORDINATE
INSTALLATIONS WITH OTHER TRADES TO PREVENT
CONFLICTS IN CEILING SPACE.
GENERAL NOTE:
ALL PIPE PENETRATIONS THROUGH FIRE SEPARATIONS
SHALL BE FIRE-STOPPED.
GENERAL NOTE:
CONTRACTOR SHALL PROVIDE ACCESS DOORS IN
DRYWALL CEILING TO ACCESS PLUMBING COMPONENTS
INSTALLED IN CEILING SPACE
AS INDICATED
TRAP PRIMER SCHEDULE (TP)
TAG MANUFACTURER/MODEL TYPE TP DEVICE LOCATION
ELECTRICS
REMARKS
VOLTS PHASE HERTZ
TP-1
(W) / A200
PASSIVE JANITOR ROOM 6 - - -
PLUMBING FIXTURE SCHEDULE
TAG MANUFACTURER/MODEL
TRIM SERVICES
REMARKS
SUPPLIES TRAP FAUCET DCW
DHW DTW VENT DRAIN
WC-1
FLOOR MOUNT WATER CLOSET
(AS) / 215AA.104.020
(M)
LFH172BV
- - 1/2" - - 2" 4"
TOILET SEAT: (C) / 820STS.001
L-1
WALL HUNG LAVATORY (BF)
(AS) / 0955.001EC / 0059.020 EC
(M)
LFH170BVRB
(M)
8872C
(AS)
7075.100.002
1/2" 1/2" 1/2" 1-1/4" 1-1/4"
P-TRAP SHROUD: (AS) / 0059.020EC.020
MIXING VALVE: (L) / TMM-1070
WALL CARRIER: (AS) / WCA-411-CA-481
L-2
WALL HUNG LAVATORY
(AS) / 9960.001.020
(M)
LFH170BVRB
(M)
8872C
(AS)
7075.100.002
1/2" 1/2" 1/2" 1-1/4" 1-1/4"
MIXING VALVE: (L) / TMM-1070
WALL CARRIER: (AS) / WCA-411-CA-481
MSB-1
MOP SERVICE BASIN
(FT) / MSB2424100
- FIELD BUILT
(AS)
8344.012.002
1/2" 1/2" - 2" 3"
BUMPER GUARD: (FT) / E88AA24000
HOSE AND WALL HOOK: (FT) / 832AA000
BACK SPLASH: (FT) / MSG2424000
SS-1
S.S. COUNTERTOP SINK
(FR) / SL2424-1/2
(M)
LFH170BV
(M)
8912CB
(AS)
7293.152.002
1/2" 1/2" 1/2" 1-1/4" 1-1/2"
MIXING VALVE: (L) / TMM-1070
SS-2
S.S. COUNTERTOP SINK
(K) / QSL2020/8/1
(M)
LFH170BV
(M)
8912CB
(AS)
4175.300.002
1/2" 1/2" 1/2" 1-1/4" 1-1/2"
MIXING VALVE: (L) / TMM-1070
SS-3
S.S. COUNTERTOP SINK
(K) / QSLF2020/12/1
(M)
LFH170BV
(M)
8912CB
(AS)
4175.300.002
1/2" 1/2" 1/2" 1-1/4" 1-1/2"
MIXING VALVE: (L) / TMM-1070
FFD
FUNNEL FLOOR DRAIN
(Z) / ZN415B-IC-P-OF
- - - 1/2" - - - 3"
FUNNEL: (Z) / Z329-7
5
3
2
9
11
12
13
BACK FLOW PREVENTER SCHEDULE (BFP)
TAG MANUFACTURER/MODEL LOCATION POINT OF USE
BFP
SERVICE
HAZARD
SIZE (mm)
BFP-1
(W) / LF800M4QT
JANITOR ROOM 6 BOILER ROOM 5 PVB SEVERE 1/2"
LEGEND:
(W) WATTS (C) CENTICO (FR) FRANKE
(BF) BARRIER FREE (M) MCGUIRE
(L) LAWLER (FT) FIAT
(W) WATTS (K) KINDRED
18.01.17
Fre
eze
rF
re
eze
rF
re
eze
rF
rd
g.
Frd
g.
Frdg.
SHADED AREA NOT IN CONTRACT
UP
TYPE B - 21'-6"
12.9 mbh
TYPE B - 16'-0"
8.2 mbh
TYPE B - 16'-0"
8.2 mbh
HWR
TYPE B - 36'-0"
21.8 mbh
TYPE C - 19'-0"
8.8 mbh
TYPE B - 22'-0"
12.9 mbh
TYPE C - 30'
38.9 mbh
TYPE B - 28'-0"
15.8 mbh
1 1/4" EXT2" EXT
2 1/2" EXT
3/4"
HWR
1"
S1
S1
1 1/4"
1 1/4"
3/4"
S1
S1
S1
S1
S1
1"
TYPE A - 22'-6"
10.4 mbh
HW
RH
WR
HW
R
HWSHWSHWS
HW
RH
WR
HW
R
HW
S
HWS
HW
R
HWS
HW
SH
WS
HW
S
HWS
HW
SH
WS
HW
S
HWR HWR HWR
HWRHWR
HW
R
HW
R
1 1/4" EXT
2" EXT
1" EXT
2 1/2" EXT
1 1/4" EXT
1 1/2" EXT
11/4" EXT
1 1/4" EXT
11/2" EXT
2" EXT 2" EXT
21/2" EXT
1" EXT
S1
S1
HWR HWR
HWS
S1
3/4"
S1
TYPE A - 32'-0"
5.65 mbh
TYPE A - 32'-0"
5.65 mbh
TYPE x - 12'
- mbh
TYPE C - 14'
38.9 mbh
1"
1"
1"
3/4"
1"
HWR
HW
RH
WR
HW
R
HWSHWSHWS
HW
RH
WR
HW
R
HW
S
HWS
HW
R
HWS
HW
SH
WS
HW
S
HW
S
HWS
HW
SH
WS
HW
SH
WS
1 1/4" EXT
1 1/2" EXT
11/4" EXT
HWR HWR HWR
HWRHWR
HW
R
HW
RH
WR
11/4" EXT
11/4" EXT 11/2" EXT
2" EXT 21/2" EXT 2" EXT
21/2" EXT
1" EXT
1 1/4" EXT
2" EXT
1" EXT
S1
S1
S1
S1
S1
S1
S1
S1
S1
S1
S1
S1
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
MECHANICAL
BASEMENT HEATING FLOOR PLAN, SCHEDULE &
LEGEND
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
H353541-M-002 M-002 B
M. BROWN
17/10/13 17/10/13 18/01/04
18/01/05
H3535411/4"=1'0"
HALIFAX, NOVA SCOTIA
A ISSUED FOR 99% REVIEW AS MB 17/12/19
N.VUJIC A. SRIVASTAVA
M. BROWN
B ISSUED FOR TENDER AS MB 18/01/15
1809 BARRINGTON ST.
HEATING LEGEND
NEW HOT WATER SUPPLY PIPING
NEW HOT WATER RETURN PIPING
EXISTING HOT WATER SUPPLY PIPING
EXISTING HOT WATER RETURN PIPING
BALL VALVE
NEW CONTROL VALVE
EXISTING CONTROL VALVE RELOCATED
SENSOR CONTROL WIRING
PIPING TO BE REMOVED
NEW TEMPERATURE SENSORS
EXISTING TEMPERATURE SENSORS
RELOCATED
"EXT"PIPE SIZE SUFFIX, INDICATES EXISTING PIPE
HWS
HWR
HWS
HWR
RADIANT HEATING PANEL SCHEDULE
TAG MANUFACTURER/MODEL LOCATION
CAPACITY
(BTU/H)
SIZE FLUID SIZE
LENGTH WIDTH GPM EWT LWT
A FRENGER / TWA SEE DRAWINGS / LINEAR 463 / FT SEE DWG 2'-0" SEE DWG 190° 170°
B FRENGER / TWA SEE DRAWINGS / LINEAR-MITRED 633 / FT SEE DWG 3'-0" SEE DWG 190° 170°
C FRENGER / TWA LIBRARY / LINEAR 633 / FT SEE DWG 3'-0" SEE DWG 190° 170°
D FRENGER / TWAQUIET ROOM / LINEAR 463 / FT SEE DWG 2'-0" SEE DWG 190° 170°
S1
BASEMENT PLAN - NEW RADIANT HEATING PIPING
SCALE: 1/8"=1'-0"
2
M-002
BASEMENT PLAN - EXISTING RADIANT HEATING PIPING
SCALE: 1/8"=1'-0"
1
M-002
S1
1 CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING
SENSORS / CONTROL VALVES INSTALLED DURING PHASE I -
BOILER CONTRACT TO SUIT NEW RADIANT CEILING
HEATING PANELS.
SENSOR / CONTROL VALVES SHALL BE LOW VOLTAGE (24V).
RADIANT PANELS SHALL BE INSTALLED PER
MANUFACTURERS INSTRUCTIONS. INSULATE ABOVE
PANELS ONCE INSTALLATION IS COMPLETE.
2
3
18.01.17
Fre
eze
rF
re
eze
rF
re
eze
rF
rd
g.
Frd
g.
Frdg.
SHADED AREA NOT IN CONTRACT
UP
B
116
3
EXISTING 36"x6" RET
EXISTING 28"x8" SUP
5
9
EXISTING 24"x8"
EX
IS
TIN
G 2
0"x6
" R
ET
3
2
EXISTING 24"x8" SUP
EXISTING 20"x6" SUP
EXISTING 30"x12" SUP
EX
IS
TIN
G 2
4"x9
" S
UP
EX
IS
TIN
G 2
4"x8
" S
UP
EXISTING 24"x8" SUP
BD
BD
BD
BD
BD
12"x8" EXH
B
116
B
116
B
116
B
116
B
116
A
83
A
83
A
83
8
B
200
B
200
6
7
BD
BD
BD
E
75
E
50
D/G - FD
B
155
B
155
B
155
B
155
B
155
C
-
C
-
4
C
-
B
100
B
100
BDBD
BD BD
BD
FD
BD
BD
BD
BD
B
175
B
175
C
-
C
-
C
-
EXISTING 22"x8"
B
165
B
165
D
75
D/G
D
125
D/G
D
125
D/G
D
125
E
125
E
125
E
125
E
100
D/G
D
100
BD
B
118
B
118
B
118
B
118
B
118
B
118
C
-
8"ø SUP
8"ø SUP
8"ø SUP 8"ø SUP
28"x8" SUP
6"ø SUP
8"ø SUP
6"ø SUP
6"x6" EXH
8"X6" EXH
8"ø SUP
8"ø SUP
8"ø SUP
8"ø SUP
8"ø SUP
5
5
8"ø SUP
8"ø SUP
8"ø SUP
8"ø SUP
8"ø SUP
8"ø SUP
16"x6" SUP
16"x6" SUP
6"x6" EXH
6"x6" EXH
6"x6" EXH
6"x6" EXH
8"ø SUP
8"ø SUP
8"ø SUP
8"ø SUP
55 5
55
5
555
5
5
5
5
1 1
3
3
3
BD
2
3
C
-
FD
BD
BD
BD
BD
BD
BD
BD BD
BD
BD
BD
BD
BD
BD
8"ø SUP
BD
BD
BD
BD BD
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
MECHANICAL
BASEMENT HVAC FLOOR PLAN, SCHEDULES,
DETAILS & LEGEND
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
H353541-M-003 M-003 B
M. BROWN
17/10/17 17/10/17 18/01/04
18/01/05
H3535411/4"=1'0"
HALIFAX, NOVA SCOTIA
A ISSUED FOR 99% REVIEW MB AS 17/12/19
A.SCOTT A. SRIVASTAVA
M. BROWN
B ISSUED FOR TENDER MB AS 18/01/19
1809 BARRINGTON ST.
GRILLE SCHEDULE
TAG MANUFACTURER / MODEL
MODULE SIZE
(in)
FACE SIZE
(in)
NECK SIZE
(in)
AIR FLOW
(CFM)
NC LEVEL CEILING TYPE MOUNTING/TYPE FINISH REMARKS
E.H.PRICE / MODEL SCD 24" x 24" 24" x 24" 6"Ø 0-175 19 T-BAR CEILING DIFFUSER B12
E.H.PRICE / MODEL SCD 24" x 24" 24" x 24" 8"Ø 0-279 19 T-BAR CEILING DIFFUSER B12
E.H.PRICE / MODEL PDR 24" x 24" 24" x 24" 22" x 22" 0-1681 17 T-BAR CEILING RETURN B12
E.H.PRICE / MODEL ATG1 16" x 10" 17 5/8" x 11 5/8" 16" x 10" 0-150 15 - DOOR GRILLE -
C/W FLAT BORDER BOTH SIDES c/w
FD AT BOILER ROOM DOOR
E.H.PRICE / MODEL PDR 12" x 12" 12" x 12" 8" x 8" 0-150 15 T-BAR CEILING EXHUAST B17/B12
C/W EXHAUST PLENUM PAINTED
BLACK INSIDE
BASEMENT PLAN - HVAC
SCALE: 1/8"=1'-0"
1
M-004
GENERAL NOTE:
ALL DUCT PENETRATIONS THROUGH FIRE SEPARATIONS
SHALL BE c/w FIRE DAMPERS.
GENERAL NOTE:
HVAC CONTRACTOR SHALL COORDINATE WITH OTHER
TRADES TO PREVENT CONFLICTS IN CEILING SPACE.
GENERAL NOTE:
HVAC CONTRACTOR SHALL COORDINATE WITH
ARCHITECT'S REFLECTED CEILING PLAN FOR FINAL
GRILLE/DIFFUSER LOCATIONS.
GENERAL NOTE:
HVAC CONTRACTOR SHALL BE RESPONSIBLE FOR ALL
OFFSETS AND FITTINGS NECESSARY TO SUIT SITE
CONDITIONS.
VENTILATION LEGEND
NEW DUCTWORK
EXISTING DUCTWORK & ACCESSORIES TO BE
RETAINED
EXISTING DUCTWORK & ACCESSORIES TO BE
REMOVED
"SUP" SUFFIX. FOR DEFINING SUPPLY DUCT SYSTEM
"RET" SUFFIX. FOR DEFINING RETURN DUCT SYSTEM
"EXH" SUFFIX. FOR DEFINING EXHAUST DUCT SYSTEM
SUPPLY DIFFUSER
RETURN/EXHAUST GRILLE
BALANCING DAMPER
FIRE DAMPER
CROSS-TALK SILENCER
TEMPERATURE SENSOR
DOOR GRILLE
1/2" DOOR UNDER CUT, (U.N.O.)
FLEXIBLE DUCTWORK
U/C
S1
D/G
DUCT
1.6mm FIRE DAMPER SLEEVE
RETAINING ANGLE
FIRE SEPARATION
FUSIBLE LINK
FIRE DAMPER
FIRE DAMPER ACCESS DOOR
BREAKAWAY DUCT CONNECTION
FIRE DAMPER DETAIL
SCALE: NTS
2
M-004
1 EXISTING TRANSFER OPENING TO REMAIN. REMOVE
EXISTING GRILLES, CLEAN AND REINSTALL.
REMOVE EXISTING RETURN DUCTWORK DOWNSTREAM.
RETURN DUCT TO REMAIN OPEN-ENDED IN CEILING SPACE.
REMOVE EXISTING SUPPLY BRANCH DUCTWORK, CAP/SEAL
AT SUPPLY TRUNK.
EXISTING 11" x11" EXHAUST DUCT TO MECHANICAL ROOM
TO REMAIN. REMOVE EXHAUST DUCTWORK IN BASEMENT
LEVEL. INSTALL NEW EXHAUST DUCTWORK AS INDICATED
AND CONNECT TO EXISTING DUCT RISER.
INSTALL SPIN COLLAR AT EXISTING SUPPLY DUCT.
EXISTING SUPPLY DUCT RISER TO REMAIN.
EXISTING RETURN DUCT RISER TO REMAIN.
EXTEND EXISTING SUPPLY DUCT INTO PROGRAM ROOM.
REMOVE EXISTING EXHAUST FAN AND DUCTWORK. PATCH
EXISTING EXTERIOR WALL PENETRATION. MAKE WATER
TIGHT.
2
3
4
5
6
7
8
9
A
-
B
-
C
-
D
-
E
-
BD
FD
18.01.17
Fre
eze
rF
re
eze
rF
re
eze
rF
rd
g.
Frd
g.
Frdg.
SHADED AREA NOT IN CONTRACT
UP
1"
1"
1"
1"
1"
1"
1"
1"
1"1"
1"1"
1"
1" 1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1" 1"
1"
1"
1" 1"
1"
1"
1"
1"
1" 1"
1"
1"
1"
1" 1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
4
2
2
2"
22
2
22
2
2
4
2
2
2
4
2
2
2
2
2
2
2 2
2
2
4
4
2
2
4
2 2
2
2
22
2
2
4
4
4
4
2
2
2
2 2
22
2 2
1"
1"
2
4 4
2
2
4
2
2
2
2 2
1 1/4"
1 1/2"
1"
1" 1" 1 1/4"
1 1/2"
1 1/2" 1 1/4" 1"
1"
2"
1 1/2"
1 1/4" 1"
1"
1"
1" 1" 1 1/4"
1 1/2"
1" 1" 1 1/4"
1 1/2"
1" 1" 1 1/4"
1 1/2"
1" 1" 1 1/4"
1 1/2"
1" 1" 1 1/4"
1 1/2"
1" 1" 1 1/4"
1 1/2"
1"
1"
3" 4" 4" 4"
1 1/4"
1"
1"
1"
1"
1"
1"
1"
1"
1 1/2"
2"
1"1"
1"1"
1"1"
2"
1 1/2" 1 1/4"
1"
1"
1"
1"
1 1/2"
1"
1"
1 1/4"
1"
1 1/4"
1 1/2"
1 1/2"
3"
3"
3"
3"
2 1/2"
2 1/2"
1 1/2"
1 1/2"
1 1/4"
1 1/4" 1" 1"
1"1"
1"
1"
1"
1 1
1
3
3
3
1
1
1
1
1
1
1
3
1
33
3 3 1 3
3 3 1 3
3133
1
1
1
1
3
3
3
1
1 1
3 3 3
113
113 3
3
1
1
1
1
1
3
3
3
1
3
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
MECHANICAL
BASEMENT FIRE PROTECTION PLAN
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
H353541-M-004 M-004 B
M. BROWN
17/12/08 17/12/06 18/01/04
18/01/05
H3535411/4"=1'0"
HALIFAX, NOVA SCOTIA
A ISSUED FOR 99% REVIEW MB AS 17/12/19
R. POIRIER A. SRIVASTAVA
M. BROWN
B ISSUED FOR TENDER MB AS 18/01/15
1809 BARRINGTON ST.
1 EXISTING SPRINKLER HEADS, ALL 1" SUB BRANCH PIPING
AND THE ELBOWS TO BE DEMOLISHED AND REMOVED.
CONTRACTOR TO VERIFY THE EXTENT OF DEMOLITION AND
REUSING OF EXISTING PIPE ON SITE TO SUIT NEW LAYOUT.
CONTRACTOR TO VERIFY SUB BRANCH TAKE OFF WHICH
ARE CONNECTED TO MORE THAN ONE SPRINKLER HEADS
ON SITE AND ALLOW FOR INSTALLATION OF NEW PIPING AS
SHOWN ON NEW PLAN LAYOUT. REMOVAL TO BE DONE IN A
MANNER NOT TO DISRUPT EXISTING SYSTEMS.
SUPPLY AND INSTALL NEW 1" RIGID, FLEX HOSE SPRINKLER
PIPE (AS REQUIRED) & CONCEALED SPRINKLER HEADS
MATERIALS OF RIGID PIPE TO MATCH EXISTING MODIFY
EXISTING SYSTEM ACCOMMODATE NEW PIPE
CONNECTIONS. VERIFY LENGTH FOR NEW PIPING ON SITE.
MAXIMUM LENGTH OF THE FLEXIBLE HOSE TO BE 6' .
EXISTING SPRINKLER HEAD AND ELBOWS TO BE REMOVED
& PIPING TO BE CAPPED.
CONTRACTOR TO INSTALL NEW SPRINKLER BRANCH AND
CONNECT BACK INTO EXISTING PIPING. NEW BRANCH TO
MATCH EXISTING MATERIAL, CONTRACTOR TO INSTALL
REDUCERS & HANGERS AS REQUIRED. SIZE OF NEW PIPING
AS SHOWN ON DRAWINGS.
FIRE PROTECTION LEGEND
EXISTING UPRIGHT SPRINKLER HEAD
EXISTING FIRE PIPING
EXISTING FIRE EXTINGUISHER
EXISTING PENDANT SPRINKLER REMOVED
EXISTING PIPING REMOVED
NEW PENDANT SPRINKLER HEAD
NEW UPRIGHT SPRINKLER HEAD
NEW PENDANT SPRINKLER HEAD c/w FLEX
HOSE CONNECTION
NEW FIRE PIPING
FLEXIBLE HOSE
NEW FIRE EXTINGUISHERFE
FE
BASEMENT PLAN - NEW FIRE PROTECTION PIPING
SCALE: 1/8"=1'-0"
2
M-005
BASEMENT PLAN - EXISTING FIRE PROTECTION PIPING
SCALE: 1/8"=1'-0"
1
M-005
2
3
4
18.01.17
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
MECHANICAL
SPECIFICATION SHEET 1
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
H353541-M-010 M-010 B
M. BROWN
17/12/15 17/12/15 18/01/04
18/01/05
H353541NTS
HALIFAX, NOVA SCOTIA
A ISSUED FOR 99% REVIEW MB AS 17/12/19
R. POIRIER A. SRIVASTAVA
M. BROWN
B ISSUED FOR TENDER MB AS 18/01/15
1809 BARRINGTON ST.
18.01.17
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
MECHANICAL
SPECIFICATION SHEET 2
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
H353541-M-011 M-011 B
M. BROWN
17/12/15 17/12/15 18/01/04
18/01/05
H353541NTS
HALIFAX, NOVA SCOTIA
A ISSUED FOR 99% REVIEW MB AS 17/12/19
R. POIRIER A. SRIVASTAVA
M. BROWN
B ISSUED FOR TENDER MB AS 18/01/15
1809 BARRINGTON ST.
18.01.17
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
MECHANICAL
SPECIFICATION SHEET 3
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
H353541-M-012 M-012 B
M. BROWN
17/12/15 17/12/15 18/01/04
18/01/05
H353541NTS
HALIFAX, NOVA SCOTIA
A ISSUED FOR 99% REVIEW MB AS 17/12/19
R. POIRIER A. SRIVASTAVA
M. BROWN
B ISSUED FOR TENDER MB AS 18/01/15
18.01.17
A-6
RET
A-2
RET
A-1
REM
A-1
RET
A-9
REL
A-4
REM
A-6
RET
A-2
RET
A-7
REL
A-8
RET
A-5
REM
A-1
REM
A-3
RET
A-9
REM
A-7
RET
A-3
REM
A-7
REM
A-2
RET
A-1
REM
A-4
REM
A-5
RET
A-39
REM
B M
B
M
B
REM REM
REMREM
REM
REM
REM
REM
REM
REM
REM
REM
REM
REM
REM
REL
RET
RET
S
S
REM
REM
`A'
REM
S
EXISTING
PANEL `A'
A-10
A-10
A-10
A-10
A-10
A-10
A-13 A-13 A-13 A-13
A-13
A-13A-13A-13A-13A-13
A-15 A-15
A-15
A-15A-15
A-15
A-15A-15
A-17 A-17
A-17
A-17 A-17
A-17
A-17A-17 A-19
A-19
A-19
A-19
A-19
REM REM REM REM REM
REMREMREMREMREM
REM REM REM REM REM
REM
REM
REM
REM
REMREM
REM REM REM REM
REM REM REM REM
REMREM
A-16
REM
A-16
REM
A-16
REM
A-16
REM
A-16
REM
A-16
REM
A-16
REM
A-16
REM
A-16
REM
A-16
REM
A-16
REM
A-18
REM
A-18
REM
C-18
REM
C-18
REM
C-18
REM
C-18
REM
REL
RET
RET
REL
REL
RET
A-21
REM
REM
A-14
REM
REMREM
A-14
A-14A-14
A-21
REM
A-21
REM
A-21
REM
A-21
REM
A-18
REM
REM
A-18
REM
A-18
REM
A-18
REM
A-18
REM
A-18
REM
A-14
REM
A-14
REM
A-14
REM
A-12
REM
A-12
REM
A-12
REM
REM REM
A-18
A-12 A-12
REM
A-12
REM
A-12
REM
A-12
REM
A-12
REM
`A'
EXISTING
PANEL `A'
REM
REM
REM
REM
REM
REM
REM
REM
REM
REM REM
REM
REM
REM
EXISTING 1' x 4' LIGHTING FIXTURE
EXISTING 2' x 4' LIGHTING FIXTURE
EXISTING POT LIGHT LIGHTING FIXTURE
EXISTING SINGLE POLE LIGHT SWITCH
EXISTING 1 POLE LIGHT SWITCHES,
GANGED UNDER COMMON COVER PLATE
EXISTING EXIT SIGNS
EXISTING BATTERY UNIT c/w 2 REMOTE HEADS
EXISTING BATTERY UNIT c/w 1 REMOTE HEAD
B
MEXISTING FIRE ALARM MANUAL PULL STATION
EXISTING FIRE ALARM BELL
EXISTING FIRE ALARM SMOKE DETECTOR
EXISTING INTERCOM SPEAKER
EXISTING RECEPTACLE
EXISTING ELECTRICAL PANEL
S
"RET"
INDICATES ELECTRICAL DEVICE THAT IS TO BE
RETAINED
"REM"
INDICATES ELECTRICAL DEVICE THAT IS TO BE
REMOVED
X
EXISTING MOTOR EQUIPMENT LOCATION
SPECIFIC NOTE
"REL"
INDICATES ELECTRICAL DEVICE THAT IS TO BE
RELOCATED
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
LIBRARY CONCEPT
ANNAPOLIS ROYAL
ELECTRICAL
EXISTING BASEMENT LIGHTING, POWER,
COMMUNICATION, FIRE ALARM PLANS & LEGEND
H353541-E-001 E-001 B
D. KUGLER
17/12/09 17/12/09 18/01/15
18/01/15
H353541
HALIFAX, NOVA SCOTIA
A ISSUED FOR 99% REVIEW MB DK 17/12/18
R. POIRIER D. KUGLER
M. BROWN
B ISSUED FOR TENDER MB DK 18/01/15
1809 BARRINGTON ST.
AS INDICATED
EXISTING LIGHTING ELECTRICAL LAYOUT
SCALE: 1/8"=1'-0"
1
E-001
EXISTING LEGEND
SCALE: NTS
3
E-001
EXISTING POWER, FIRE ALARM & COMMUNICATION ELECTRICAL LAYOUT
SCALE: 1/8"=1'-0"
2
E-001
GENERAL NOTES:
1. ALL DEVICES BEING REMOVED ARE TO BE TURNED OVER TO
OWNER.
2. EXACT LOCATIONS FOR EXISTING EQUIPMENT IS TO BE
CONFIRMED ON-SITE.
18.01.17
SHADED AREA NOT IN CONTRACT
UP
FB
A-6
RET
A-2
RET
A-1
RET
A-6
RET
A-2
RET
A-7
REL
A-8
RET
A-3
RET
A-7
RET
A-2
RET
A-5
RET
B-19
USB
B-25
USB
A-39
USB
B-25
USB
A-39
USB
A-26
USB
B
B
B
B-20
B-18
B-16
B-14
B-12
A-9
REL
B-17
2
B-15
2
B-13
2
B-26
B-28
2
A-44
2
A-60
A-48
2
A-46
2
`B'
B-10
REL
A-4
A-23
B-23
B-21
2
QUIET ROOM
1
STACKS &
READING
2
JAN
6
PROGRAM
8
FOOD BANK
7
PROGRAM 2
9
FAM./B.F.
WR.10
WR.
13
WR.
14
STORAGE
11
OFFICE
3
BOILER
ROOM
5
STORAGE
4
COMMON
15
INNOVATION
CENTRE
12
`A'
A-3
2
A-11
A-3
A-11
2
A-13
2
2
A-4
2
A-13
B-23
B-25
5'AFF
5'AFF
B-19
USB
A-7
USB
A-1
USB
A-7
USB
A-1
USB
A-5
2
WAP
1
B-28
2
B-21
FB
B-27
2
B-27
A-44
USB
A-11
5'A
FF
5'A
FF
2
B-26
2
A-4
4
B-19
B-19
B-22
B-22B-24
B-24
A-4
A-13
A-4
A-15
A-15
A-15
A-15
A-2
TO ELECTRICAL ROOM
1-1/4"
1-1/2"
1-1/4"
1-1/4"
1-1/2"
2 x 2"
1-1/2"
SHADED AREA NOT IN CONTRACT
UP
QUIET ROOM
1
STACKS &
READING
2
JAN
6
PROGRAM
8
FOOD BANK
7
PROGRAM 2
9
FAM./B.F.
WR.10
WR.
13
WR.
14
STORAGE
11
OFFICE
3
BOILER
ROOM
5
COMMON
15
INNOVATION
CENTRE
12
A A AA
A A AA
A A AA
A A AA
A A AA
A A AA
A A A
A A A
A
A
AAA
AAA
AAA
A
A
A A A
A A
A A
A A
A A
A A
A
A
A
A
A
A
A
A
A A
A
A A
A
A A
A
A A
A
A A
A A
A
A
A
A
A
A
A
A
A
A A
A A
A
A
A A
A
A
A
A
B
B
B
B B
B
B
F
B
B
BBB
C
C
C
`A'
A-10
A-10
A-10
A-10
RET
RET
REL
RET
D
A-10
A-10
REL
REL
A A
AA
A
A
a
A-21
A-21
A-21 A-21
A-21
A-21 A-21
A-21
A-21 A-21
A-21
A-21
A-21
A-21
A-21
A-21
A-21
A-21
A-21
A-21
A-21
A-21
A-21
A-21
A-21
A-21
A-21
A-21
A-21 A-21 A-21
A-21
A-21
A-16
A-16
A-16 A-16
A-16
A-16
A-12b A-12b
A-12a A-12a A-12a
A-12a
A-12a
A-12a
A-12bA-12b
A-12a
A-12a
A-12a
A-12a
A-12
A-12
A-12
A-12 A-12
A-16
A-16
A-12
A-12
A-12
A-12c
A-12 A-12
A-12 A-12
A-12A-12
A-12 A-12
A-12A-12
A-12 A-12 A-12
A-12 A-12 A-12
A-12 A-12 A-12
A-12 A-12
A-12
A-12A-12A-12
A-10
A-10
A-10
A-10
A-10
A-10
A-10
A-10
A-10
A-10
A-10
A-16 A-16A-16
A-16 A-16 A-16
A-16A-16
A-16 A-16A-16A-16
A-16 A-16
A-16
A-16
A-16
A-16
A-16
A-16
A-16A-16
A-16 A-16
A-16A-16
A-16 A-16
A-16 A-16 A-16 A-16
A-12b
A-12b
A-12b
A-12b
A-12b
A-12a
A-12b
G
G
G
G
G
G
H
I
I
I
I
A-21
A-21 A-21
A-21 A-21
A-21
A-21
A-21
E
EXISTING EXIT SIGNS
EXISTING BATTERY UNIT c/w 2 REMOTE HEADS
EXISTING UNIT c/w 1 REMOTE HEAD
BEXISTING FIRE ALARM BELL
"REL"
INDICATES ELECTRICAL DEVICE IN RELOCATED
LOCATION
2'x2' LUMINAIRE, REFER TO LUMINAIRE SCHEDULE FOR MORE
DETAILS
1'x2' LUMINAIRE, REFER TO LUMINAIRE SCHEDULE FOR MORE
DETAILS
A
F
120V 15A, SINGLE POLE TOGGLE SWITCH, SPEC GRADE, WHITE IN
COLOR, STAINLESS STEEL COVERPLATE, MOUNTED 48" A.F.F.
UNLESS NOTED OTHERWISE
CEILING MOUNTED LUMINAIRE REFER TO LUMINAIRE SCHEDULE FOR DETAILSC
SAME AS ABOVE EXCEPT A TWO-GANG SWITCH
TRACK LIGHT REFER TO LUMINAIRE SCHEDULE FOR DETAILS
F
1'X3' LUMINAIRE, REFER TO LUMINAIRE SCHEDULE FOR MORE
DETAILS
1'x4' LUMINAIRE, REFER TO LUMINAIRE SCHEDULE FOR MORE
DETAILS
H
G
SAME AS ABOVE EXCEPT 3-WAY OPERATION
120V 15A, 2 POLE OCCUPANCY SENSOR SWITCH, DUAL
TECHNOLOGY, SPEC GRADE, WHITE IN COLOR, STAINLESS STEEL
COVERPLATE, MOUNTED 48" A.F.F. UNLESS NOTED OTHERWISE
SINGLE FACE, CEILING MOUNTED EXIT LIGHT, SELF POWERED RUNNING MAN
STYLE.-
EMERGENCY LIGHT c/w BATTERY PACK WALL MOUNT 120VAC INPUT, 12VDC
OUTPUT
SAME AS ABOVE EXCEPT 4-WAY OPERATION
NEW 120V, 15A DUPLEX RECEPTACLE MTD. 16" A.F.F. OR 6" ABOVE
COUNTER RESPECTIVELY, SPECIFICATION GRADE, WHITE IN
COLOR. - PASS & SEYMOUR# CR15W
NEW 120V, 15A T-SLOT GFCI RECEPTACLE, MTD. 48" A.F.F. OR
ABOVE FINISHED COUNTER, SPECIFICATION GRADE, WHITE IN
COLOR. - PASS & SEYMOUR# 1595W
NEW 120V, 15A DUPLEX RECEPTACLE MTD. 16" A.F.F. OR 6" ABOVE
COUNTER RESPECTIVELY, c/w USB CONNECTION SPECIFICATION
GRADE, WHITE IN COLOR. - PASS & SEYMOUR# TR5262USBW
USB
FB
NEW FLUSH MOUNTED FLOOR BOX TO HAVE 2 DUPLEX
RECEPTACLES, VOICE, AND 2 DATA OUTLETS. CONFIRM EXACT
LOCATION REQUIRED WITH FURNITURE SUPPLIER
WAP
1 WIRELESS ACCESS POINT. PROVIDE SINGLE DATA OUTLET ABOVE
CEILING TILE FOR CONNECTION. WIRELESS ACCESS DEVICE
PROVIDED BY OTHERS.
1
DATA OUTLET, MTD. 16" AFF OR 6" ABOVE COUNTER RESPECTIVELY
(UNO). NUMBER INDICATES QUANTITY OF DATA DROPS AT EACH
LOCATION.
1
COMMUNICATION JUNCTION BOX. SIZED AS REQUIRED.
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
LIBRARY CONCEPT
ANNAPOLIS ROYAL
ELECTRICAL
NEW BASEMENT LIGHTING, POWER,
COMMUNICATION, FIRE ALARM PLANS & LEGEND
H353541-E-002 E-002 B
D. KUGLER
17/12/09 17/12/09 18/01/15
18/01/15
H353541
HALIFAX, NOVA SCOTIA
A ISSUED FOR 99% REVIEW MB DK 17/12/18
R. POIRIER D. KUGLER
M. BROWN
B ISSUED FOR TENDER MB DK 18/01/15
1809 BARRINGTON ST.
AS INDICATED
NEW POWER, FIRE ALARM & COMMUNICATION ELECTRICAL LAYOUT
SCALE: 1/8"=1'-0"
2
E-002
GENERAL NOTES:
1. ALL DATA DROPS THROUGHOUT FLOOR TO TERMINATE IN THE
OFFICE ON SHELF APPROXIMATELY 6' AFF.
NEW LIGHTING ELECTRICAL LAYOUT
SCALE: 1/8"=1'-0"
1
E-001
18.01.17
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
LIBRARY CONCEPT
ANNAPOLIS ROYAL
ELECTRICAL
SCHEDULES & DETAILS
H353541-E-003 E-003 B
D. KUGLER
17/12/09 17/12/09 18/01/15
18/01/15
H353541
HALIFAX, NOVA SCOTIA
A ISSUED FOR 99% REVIEW MB DK 17/12/19
R. POIRIER D. KUGLER
M. BROWN
B ISSUED FOR TENDER MB DK 18/01/15
1809 BARRINGTON ST.
AS INDICATED
PANEL VOLTAGE: 120/208V PANEL TYPE: SQUARE D
PROJECT EXISTING PANEL
PANEL LOCATION: KITCHEN PANEL MAINS: 100A
PANEL SOURCE: PANEL 'DP' PANEL I/C: 10 kA A
PANEL MOUNTING: RECESSED PANEL FEEDER: 4c 3/0 R90 + #2 GND
CCT DESCRIPTION
WATTAGE
BRKR Ø BRKR
WATTAGE
DESCRIPTION CCT
A B C P AMPS ABC AMPS P A B C
1RECPT. 017, 013, 012
- 1 15 A 15 1 -RECPT. 020, 021, 024
2
3RECPT. 017, 013, 012
- 1 15 B 15 1 -RECPT. 019, 020
4
5RECPT. 017, 013, 012
- 1 15 C 15 1 -RECPT. 019, 020
6
7 RECPT. CORRIDOR - 1 15 A 15 1 - RECPT. 024 8
9 RECPT. CORRIDOR - 1 20 B 15 1 - EXIT & EMERG LTS 10
11 LTS. 015 - 1 15 C 15 1 -LTS. 011, 012, 013
12
13 LTS. 017 1 15 A 15 1LTS. 009, 010
14
15 LTS. 017 1 15 B 20 1 LTS. 020 16
17 LTS. 017 1 15 C 15 1LTS. 019, 021
18
19 LTS. 017 1 15 A
70 2
LTS. 020 20
21 LTS. 018 1 15 B
OVEN
22
23 - 1 15 C 15 1 24
25
RANGE 3 70
A 15 1 - 26
27 B
50 2 DISHWASHER
28
29 C 30
31 RECPT. KITCHEN - 1 15 15 1 - RECPT. KITCHEN 32
33 RECPT. COUNTER - 1 15 15 1 - RECPT. COUNTER 34
35 RECPT. KITCHEN STC. - 1 15 15 1 - - 36
37 EF 10 - 1 15 15 1 - EXT. LTS 38
39 WATER COOLER - 1 15 15 1 - EF 12 40
41 CAB HEATER - 1 15 15 1 - RECPT. KITCHEN 42
43 RECPT. COUNTER 108 1 15 15 1 COOLER PLUG ROOM 111 44
45 RECPT. COUNTER 108 1 15 15 1 COOLER PLUG ROOM 111 46
47 RECPT. KITCHEN 1 15 15 1 COOLER PLUG ROOM 109 48
49
HOT WATER TANK 2 20
15 1 COOLER PLUG ROOM 109 50
51
50 2 GYM PANEL 'J'
52
53 SHUNT TRIP 1 15 54
55 RECPT. 108 1 15 15 1 RECPT. 108 56
57 RECPT. 108 1 15 15 1 RECPT. 108 58
59 RECPT. 108 1 15 15 1 - 60
PHASE LOADS ### ### ### ### ### ###
TOTAL PHASE LOADS ### ### ###
TOTAL LOAD ###
TOTAL AMPERAGE # A
PANEL VOLTAGE: 120/208V PANEL TYPE: SQUARE D
PROJECT PHASE 2 PANEL ADDITIONS
PANEL LOCATION: BOILER ROOM PANEL MAINS: 100A
PANEL SOURCE: PANEL 'DP' PANEL I/C: 10 kA B
PANEL MOUNTING: SURFACE PANEL FEEDER: SEE RISER
CCT DESCRIPTION
WATTAGE
BRKR Ø BRKR
WATTAGE
DESCRIPTION CCT
A B C P AMPS ABC AMPS P A B C
1
CP-1 (HEATING LOOP)
250
3 15
A
15 3
190
CP-4 (BOILER LOOP)
2
3 250 B 190 4
5 250 C 190 6
7
CP-2 (HEATING COILS)
125
3 15
A 15 1 500B-1 (HOT WATER)
8
9 125 B 15 1 200
EMERGENCY SHUT-OFF
VALVE
10
11 125 C 15 1 1000
FOOD BANK - COOLER
RECPT.
12
13 LIBRARY COMPUTER RECPT. 500 1 15* A 15 1 1000
FOOD BANK - COOLER
RECPT.
14
15 LIBRARY COMPUTER RECPT. 500 1 15* B 15 1 1000
FOOD BANK - COOLER
RECPT.
16
17 LIBRARY COMPUTER RECPT. 500 1 15* C 15 1 1000
FOOD BANK - COOLER
RECPT.
18
19 LIBRARY RECPT. 750 1 15* A 15* 1 1000
FOOD BANK - COOLER
RECPT.
20
21 LIBRARY - CIRC. DESK 1000 1 20 B 15* 1 500 FOOD BANK RECPT. 22
23 PROGRAM ROOM RECPT. 250 1 15* C 15* 1 500 FOOD BANK RECPT. 24
25 PROGRAM ROOM - T.V. 200 1 15* A 15* 1 1000 LIBRARY OFFICE - IT EQMT. 26
27 LIBRARY - CIRC. DESK 1000 1 20 B 15* 1 1000 LIBRARY OFFICE DESK 28
29 SPARE 1 20 C 15* 1 SPARE 30
PHASE LOADS 1825 2875 1125 3690 2890 2690
TOTAL PHASE LOADS 5515 5765 3815
TOTAL LOAD 15095
TOTAL AMPERAGE 42 A
* - INDICATES NEW BREAKERS IN PANEL
LUMINAIRE SCHEDULE
TYPE MANUFACTURER DESCRIPTION MOUNTING LAMP NOTE
A
METALUX
22CZ-LD5-34-RDP-UNV-L835-CD1-U
2'x2' RECESSED LENS FIXTURE, WHITE IN
COLOR, 0-10V DIMMING. 120V OPERATION
RECESSED IN CEILING
30W LED
3400 LUMENS
3500°K
-
B
PORTFOLIO
HOUSING - LD4B-10-D010
LIGHT ENGINE - EU4B-1020-80-35
TRIM - 4LB-W-0-XX
4" RECESSED LED POT LIGHT, WHITE IN
COLOR, 120V OPERATION, OWNER TO
CONFIRM FINISH TYPE
RECESSED IN CEILING
11W LED
1000 LUMENS
3500°K
-
C
BETACALCO
95-0800-35-S1-Z1
24" PENDANT LIGHT FIXTURE, LIGHT
CHERRY FINISH,120V OPERATION
PENDANT MOUNTED, SUPPORTED
FROM ADJUSTABLE AIR CRAFT
CABLES. 7'-9" AFF.
65W LED
6038 LUMENS
3500°K
-
D
HALO
HU10-24-D-9-30-P
24" UNDER CABINET LUMINAIRE, CLEAR
LENS, 120V OPERATION.
SURFACE TO UNDERSIDE OF CABINET
10.5W LED
615 LUMENS
3000°K
-
E
MAGICLITE
TLP-50-IW
TOKI LED TAPELIGHT FOR COVE ACCENT
LIGHTING, 120V OPERATION
SURFACE MOUNT WITH ADHESIVE
TAPE,
.3W LED
3000°K
-
F
PORTFOLIO
LD8A-S30-1-D010TE-ER8A-S30-8-35-8LW
111-W-WF
8" RECESSED LED POT LIGHT, WHITE IN
COLOR, 120V OPERATION, OWNER TO
CONFIRM FINISH TYPE
RECESSED IN CEILING
35W LED
3000 LUMENS
3500°K
-
G
HALO
L806SMNF8030P
TRACK LIGHT c/w HALO POWER-TRAC
SUPPORT. 2' TRACK LENGTHS WITH
FIXTURE QUANTITIES AS SHOWN ON
DRAWING.
SURFACE MOUNTED
13W LED
934 LUMENS
3000°K
2
H
METALUX
2SWLED-LD4-24HL-LC-UNV-L835-CD-1
1'x2' WALL MOUNTED LED FIXTURE. 120V
OPERATION.
WALL MOUNTED
25W LED
2400 LUMENS
3500°K
-
I
METALUX
4SWLED-LD4-32SL-LC-UNV-L835-CD-1
1'x4' STRIP LED. 120V OPERATION SURFACE MOUNTED. 7'-6" AFF.
30W LED
3200 LUMENS
3500°K
1
EMERGENCY
BATTERY
PACK
LUMACELL RGS-QB SERIES
IMPACT RESISTANT STEEL CENTER
CABINET. 120 VAC INPUT. 12VDC
WALL MOUNTED. 7'-6" AFF LED -
EXIT
LUMACELL
LS-3-W-S
RUNNING MAN EXIT SIGN, STEEL HOUSING,
WHITE IN COLOUR, UNIVERSAL FACES AND
MOUNTING, SELF POWERED FOR 90
MINUTES, 120V OPERATION.
CEILING MOUNTED LED
NOTES:
1. LIGHT TO BE INSTALLED IN FIRE RATED ROOM. ENSURE FIXTURE MOUNTING DOES NOT EFFECT ROOM FIRE RATING.
2. FIXTURE TO BE AIMED AT BOOKSHELVES. COORDINATE AIMING LOCATIONS ON SITE WITH FURNITURE SUPPLIER.
PANEL VOLTAGE: 120/208V PANEL TYPE: SQUARE D
PROJECT EXISTING PANEL
PANEL LOCATION: KITCHEN PANEL MAINS: 100A
PANEL SOURCE: PANEL 'DP' PANEL I/C: 10 kA
A (REVISED)
PANEL MOUNTING: RECESSED PANEL FEEDER: 4c 3/0 R90 + #2 GND
CCT DESCRIPTION
WATTAGE
BRKR Ø BRKR
WATTAGE
DESCRIPTION CCT
A B C P AMPS ABC AMPS P A B C
1
RECPT. QUIET
ROOM/LIBRARY
500 1 15 A 15 1 -RECPT. 020, 021, 024
2
3RECPT. 017, 013, 012
- 1 15 B 15 1 750 RECPT. INNOVATION RM. 4
5RECPT. 017, 013, 012
- 1 15 C 15 1 -RECPT. 019, 020
6
7 RECPT. CORRIDOR/LIBRARY 250 1 15 A 15 1 - RECPT. 024 8
9 RECPT. CORRIDOR - 1 20 B 15 1 - EXIT & EMERG LTS 10
11 RECPT. PROGRAM RM 2 1000 1 15 C 15 1 1410LTS. 011, 012, 013
12
13 RECPT. INNOVATION CENTRE 750 1 15 A 15 1 14
15 GFCI RECPT. WASHROOMS 1000 1 15 B 20 1 1200 LTS. 020 16
17 1 15 C 15 1 18
19 1 15 A 15 1 20
21 LTS. 018 1276 1 15 B
70 2 OVEN
22
23 RECPT. PROGRAM RM. 1000 1 15 C 24
25
RANGE 3 70
A 15 1 250 RECPT. COMMON RM. 26
27 B
50 2 DISHWASHER
28
29 C 30
31 RECPT. KITCHEN - 1 15 A 15 1 - RECPT. KITCHEN 32
33 RECPT. COUNTER - 1 15 B 15 1 -
RECPT. COUNTER
34
35 RECPT. KITCHEN STC. - 1 15 C 15 1 - 36
37 - - 1 15 A 15 1 - EXT. LTS 38
39 RECPT. COMMON AREA 500 1 15 B 15 1 - EF 12 40
41 CAB HEATER - 1 15 C 15 1 - RECPT. KITCHEN 42
43 RECPT. COUNTER 108 1 15 A 15 1 500 RECPT. QUIET RM. 44
45 RECPT. COUNTER 108 1 15 B 15 1 1000 LIBRARY PRINTER 46
47 RECPT. KITCHEN 1 15 C 15 1 1000 LIBRARY PRINTER 48
49
HOT WATER TANK 2 20
A 15 1 50
51 B
50 2 GYM PANEL 'J'
52
53 SHUNT TRIP 1 15 C 54
55 RECPT. 108 1 15 A 15 1 RECPT. 108 56
57 RECPT. 108 1 15 B 15 1 RECPT. 108 58
59 RECPT. 108 1 15 C 15 1 500 FIRE PLACE - QUIET RM. 60
PHASE LOADS 1500 2276 2000 250 1950 1410
TOTAL PHASE LOADS 1750 4226 3410
TOTAL LOAD 9386
TOTAL AMPERAGE 26 A
18.01.17
DRAWING SCALE:
DRAWN BY: CHECKED BY:
HATCH PROJECT No: PROJECT MANAGER:
DESIGNED BY:
DATE: DATE:
DATE:
DATE:
DWG No: SHEET No: REV No:
REV DESCRIPTION CHK APP DATE
REVISIONS
NOTES
LIBRARY CONCEPT
ANNAPOLIS ROYAL
ELECTRICAL
BASEMENT NEW LIGHTING, POWER,
COMMUNICATION & FIRE ALARM PLANS
H353541-E-004 E-004 B
D. KUGLER
17/12/09 17/12/09 18/01/15
18/01/15
H353541
HALIFAX, NOVA SCOTIA
A ISSUED FOR 99% REVIEW MB DK 17/12/19
R. POIRIER D. KUGLER
M. BROWN
B ISSUED FOR TENDER MB DK 18/01/15
1809 BARRINGTON ST.
AS INDICATED
1. General Requirements
.1 General
The following general conditions shall be read in conjunction with the general conditions & special conditions contained in the architectural
specifications in conjunction with related drawings, tender & other contract documents.
.2 Codes & standards
.1 All work shall be done in accordance with the latest edition of the Canadian electrical code.
.2 Do complete installation in accordance with CSA C22.1-2015 except where specified otherwise.
.3 Scope of work
This contractor shall include all labor, materials, equipment & associated services necessary for & incidental to the installation of completely
finished, tested, balanced & properly operating electrical systems as specified hereafter & shown on drawings. The intention is to provide for a
finished piece of work complete in all essentials as called for by the documents & accepted by good practice. the work shall include, but not be
limited to:
.1 Wiring of equipment supplied by others
.2 Branch circuit wiring
.3 Wiring devices
.4 Lighting fixtures & lamps
.5 Emergency lighting & exits
.6 Communication wiring
.4 Permit & by-laws
.1 Submit to electrical inspection department & supply authority necessary number of drawings & specifications for examination & approval prior
to commencement of work.
.2 This contractor shall abide by all codes & by-laws relating to this installation. Provide necessary notices, obtain permits & pay all fees, in order
that work specified may be carried out.
.5 Site visit
Before tendering, this contractor shall visit the site & familiarize him or herself with the existing conditions at the building or site where the work has
to be done. No extra shall be allowed due to failure to take site conditions into consideration.
.6 Coordination of work
.1 This contractor shall coordinate his work with the general contractor & all other sub-contractors.
.2 Schedule & perform all work in existing premises so as not to interfere with normal operations of building occupants. Carry out all work that will
interfere outside operating hours of place of work as approved by owner.
.3 Cooperate with other trades, owner & owner's suppliers forces in carrying out work. Report any deficiencies or defects on other contractor's
work that affect this contract's work to engineer immediately.
.4 Where work is carried out in existing premises, notify owner's local representative at least 48 hours in advance of any necessary interruptions
in services or access.
.7 Guarantee
This contractor shall guarantee all work & new apparatus, installed under this specification,
against any defects of workmanship & material for a period of one year after acceptance of
same by owner. Repair & make good all damage to building incurred as a result of failure of
electrical work.
.8 Drawing
The drawings for the work accompanying these specifications are made as accurately as possible, but, absolute accuracy of dimensions cannot
be guaranteed. They are intended to supplement & simplify the general contract drawings. No claim for extra payment on account of difference of
actual & estimated dimensions shall be allowed. In the case of discrepancy of figure dimensions on the drawings, the matter shall be immediately
submitted to the engineer for his decision. Without the decision, the discrepancy shall not be adjusted by the contractor save at his own risk & in
the settlement of any complications arising from such adjusting, this contractor shall bear all extra expense involved. Interpretation of all
documents shall be left to the engineer. One complete copy of all drawings, specifications & details, including addenda & change orders, shall be
in good order & kept on file by this trade in the temporary office at the site & shall be accessible to the tenant, owner, engineers & other authorized
representatives at any time. This file shall not be removed from the office until the completion & acceptance of the work.
.9 Extra work
No additional money over contract price shall be paid unless contractor receives a signed approval in accordance with the general conditions.
.10 Cutting & patching
This contractor shall locate exact dimensions & positions of openings & holes where cutting may be required in floors &/or walls for the passage of
conduit. Where cutting & patching is necessary, it shall be done by the general contractor.
.11 Site work
All trenching, backfilling & concrete work shall be the responsibility of the general contractor.
.12 Shop drawings
.1 This contractor shall submit, within two weeks after being awarded the contract, a minimum of 1 PDF copy of certified shop drawings for review
by the engineer of all equipment & material specified & shall not proceed with any of this work until the drawings have been returned stamped
& signed. This review does not relieve the contractor of the obligation of checking the drawings himself or furnishing the materials specified.
.2 When submitted, shop drawings/product data must bear contractor's stamp representing that he has determined & verified all field
measurements, field construction criteria, materials, catalog numbers & similar data or will do so & that he has checked & coordinated each
shop drawing with requirements of work & of the drawings & specifications.
.3 Shop drawings required for: luminaires & lamps, control systems, exit lights, emergency lighting batteries & heads, transformers, panelboards,
motor starters, disconnects, switches & power receptacles. information required: manufacturer, model, dimensions, construction details,
accessories, installation details, capacities, performance data, finishes. include wiring single line & schematic diagrams where applicable.
.13 Cleaning up
This contractor shall, at all times, keep the site neat, clean & free from accumulation of waste materials & rubbish which arise out of his or hers
work.
.14 As-built drawings
This contractor shall maintain, at the job site, one set of plans on which he shall clearly note all changes or deviations from the contract
documents, as the job progresses. Contractor shall at the time of final inspection submit to the owners representative, one set of `as-built'
drawings.
.15 Nameplates
Supply & install suitable engraved 4"x1"x1/8" plastic lamacoid nameplates, white face-black core, for every component in the system. This shall
include starters, disconnect switches, panel boards etc. attach with self-tapping screws in conspicuous locations. Wording shall indicate device
name as indicated or a system name, voltage, phases & power source.
.16 Operation & maintenance instructions
This contractor shall instruct the owner in operation & maintenance of all equipment & systems installed. All safety & control features shall be
thoroughly explained. Three copies of operating & maintenance instructions, together with all approved shop drawings & spare parts list fastened
in a binder, shall be submitted to the owner.
.17 Disposals
Advise owner of availability of surplus material. Turn over items requested & dispose of remainder in accordance to all by-laws & local authorities
having jurisdiction.
.18 Demolition
Disconnect & remove all devices, components, equipment & exposed raceways, wires & cables made redundant by this work including those
within in-floor ducts & suspended ceilings. Make safe any remaining live connections. Leave polypropylene cord in each empty conduit. Tag each
conduit at each end with location of the other end.
2. Basic Material & Methods
.1 Equipment & property
.1 Any alternate product proposed shall meet same standards as product specified but shall be considered acceptable only if approved prior to
installation by engineer. Such approval will not be unreasonably withheld.
.2 Specified products provided by this contractor shall be new & capable of proper operation. Unspecified products provided shall be of quality
best suited to their purpose, CSA or local inspection authority & capable of proper operation.
.3 Reuse existing products which meet specifications wherever practicable.
.4 Clean visible portions of all devices & cover plates as recommended by manufacturer to restore factory finish.
.5 Protect work & owner's property from damage that may arise as a result of this contractor's performance of work.Promptly make good any
damages to work & owner's property arising from this contractor's performance of work.
.6 Arrange deliveries & storage with owner & authorities having jurisdiction as appropriate. Protect new & reused materials from abuse, damage
& environmental conditions which they are not intended to withstand. Not withstanding foregoing, follow manufacturer's recommendations.
.2 Wiring methods
.1 Where cables & conduits pass through floors & fire rated walls, partitions & ceilings, seal all voids with ULC approved fire stop compound
conforming to CGSB 19-GP-9MA, caulk or foam as required to maintain barrier rating. Acceptable manufacturers: Dow Dorning, Delson, 3M.
.2 Locate, dimension & make electrical services openings. Provide necessary sleeves, escutcheons & covers.
.3 Drill & provide anchors as required for expansion bolts, hangar rods, brackets & supports.
.4 Relocate existing wiring, raceways, fixtures & devices as required to maintain reasonable accessibility & to facilitate installation of total
projects work.
.3 Testing
.1 Megger circuits up to 350V with a 500V instrument.
.2 Megger circuits between 350V to 600V with a 1000V instrument.
.3 Check resistance to ground before energizing any part of the work.
.4 Test all luminaires, controls, wiring devices, electrical heaters, circuit breakers, disconnect switches & emergency lighting unit equipment for
correct operation & absence of shorts or grounds.
.5 Put equipment & systems in service as may be requested by engineer for trial use provided no hazard or damage will result nor guarantees
voided.
.6 Measure phase voltages at loads & adjust transformer taps to achieve a load voltage or 115-120V.
.7 For power wiring, maintain phase sequence & color coding throughout. Color coding to CSA C22.1.
3. Conduit & Fittings
.1 Conduit: Provide for EMT conduit as noted on drawings.
.2 Electrical metallic tubing (EMT): With couplings, size as indicated. Bush both ends & bond at one end.
.3 Flexible metal conduit: 1/2"(15mm) minimum diameter & a maximum length of 6'(1800mm), with a fish wire.
.4 Conceal all finished areas' wiring in suspended ceiling spaces, walls, partitions, counters, furniture raceways, infloor raceways, shafts, exterior
concrete work & timber.
.5 Run all conduit tight against & securely fastened to supporting surfaces. Support conduit from building structure, independent of ceiling suspension.
Run all exposed conduit, raceways & cables neatly, perpendicular or parallel to building structure lines in service areas or utility rooms only.
.6 AC90 armored cable (BX): With couplings, size as indicated. Cable ends shall be protected with bushing of insulated material or equivalent devices.
BX shall be used for final short connections between junction boxes in ceiling space to ceiling mounted lighting fixtures or to feed outlets receptacles
in the drywall partitions. BX cables are not allowed to run in the open ceiling areas.
.7 All communication wiring to be in a minimum of 21mm conduit.
4. Wire & Cable
.1 Wire & cables: All 600V wiring to be solid copper conductors with thermoplastic insulation, type RW90 rated 600V. Branch wiring shall be #12AWG
minimum. #8AWG & larger shall be stranded conductor. Connectors, Clamps & supports to suit.
.2 Armored cable with thermoplastic jacket(Teck90): For connections to outdoor equipment & as noted on drawings.
.3 AC90 Armoured cable(BX): With couplings, sized as indicated, for all wiring cable ends shall be protected with bushings of insulated material or
equivalent devices. BX shall be used for final short connections between junction boxes in ceiling space to ceiling mounted lighting fixtures or to feed
outlets, receptacles in the drywall partitions. BX cables are not allowed to run in the open ceiling areas.
.4 Provide separate insulated bond conductor, same gauge as phase conductors in raceways or conduits.
5. Outlet, Pull & Junction Boxes
.1 Provide electro-galvanized steel single or multiple gang boxes for flush installation of all devices & communications outlets
as indicated. Boxes shall be code gauge & sized to meet the electrical code requirements. Equip all boxes with extension &
plaster rings as required.
.2 Provide FS or FD utility for outlets connected to surface mounted conduit, boxes shall be sized to meet the electrical code
requirements.
.3 Provide 4"(100mm) square or octagonal outlet boxes for flush lighting fixtures.
.4 Provide welded steel junction/pull boxes with hinged covers for surface mounting as required to facilitate conductor
installation. Generally such boxes will be located so as not to exceed 100'(30.5m) of conduit run & 2-90Ø bends between
pull boxes. Provide additional junction/pull boxes as required. Ensure all junction/pull boxes are accessible when all work is
complete.
.5 Support all boxes independently of connecting conduits.
.6 For flush installations, mount outlets flush with finished wall using tile rings to permit wall finish to come within 1/4"(6mm)
of opening.
.7 Do not install outlets back-to-back in hollow walls; allow minimum 6"(150mm) horizontal distance between boxes located on
opposite sides of the same wall.
6. Wiring Devices
.1 Change location of outlet, including service poles, at no extra cost or credit, providing distance does
not exceed 3m from that indicated, and information is given before installation.
.2 Adjust outlet as required to suit final finishes.
.3 Equipment mounting height is from finished floor to equipment centerline unless specified or
indicated otherwise.
.4 If equipment mounting height is not indicated, verify with engineer before proceeding with installation.
.5 Install electrical equipment at following heights unless indicated otherwise (refer also to architectural drawings).
- Local switches: 1200mm (48") (lights, fans)
- Time switches: 1370mm (54")
- Door release pushbutton: 1000mm (40")
- Power receptacles (wall): 400mm (16")
- Power receptacles (above countertop splashback): 150mm (6")
- Communications outlets: 400mm (16")
- Emergency battery & remote units: 2250mm (90")
- Wall mounted exit lights: 2450mm (98")
- Fire alarm bells: 2100mm (84")
- Fire alarm pull stations: 1200mm (48")
- Fire alarm control panel: 1500mm (60") to top of panel
- Intrusion alarm key pad: 1200mm (48")
- Panelboards: 1375mm (55")
7. Motor & Controls
.1 Magnetic and combination magnetic motor controllers: Solenoid operated FVNR NEMA contactors in EEMAC 1 enclosures. Manually resettable
bi-metalic overload relays and heaters in each phase to suit motor controlled. Unit c/w control transformer, 1 N-O and 1 N-C auxiliary contacts.
H-O-A selector switch and green "run" and red "stopped" pilot lights. Combination types to include disconnect switch and UL class J HRC-I time
delay fuses to suit motor controlled.
.2 Manual motor starter: Manual motor starters of size, type, rating, and enclosure type as indicated,
with components as follows:
.1 Switching mechanism, quick make and break.
.2 Overload heater, manual reset, trip indicating handle.
.3 Toggle switch: Standard labeled as indicated.
.4 Indicating light: Standard red.
.5 Locking tab to permit padlocking in 'on' or 'off' position.
.3 Manual motor switch: Manual motor switch rated at 30A with flush mounted enclosure. Cutler Hammer #B230AN. NEMA-1 aluminum enclosure with
padlock guard for locking in the off or stop position. Cutler Hammer #B230AG.
.4 Acceptable manufacturer: Allen Bradley, Cutler Hammer, Furnas, Square D.
8. Disconnect Switches
.1 Fusible and non-fusible disconnect switches as indicated. Provision for padlocking in 'off' position. Mechanically interlocked door to prevent opening
in 'on' position. Quick-make, quick-break action. 'On-off' indication on cover. Fuses shall be HRC-J.
9. Grounding
.1 The entire electrical system shall be grounded in accordance with the Canadian Electrical Code section 10, and local authority having jurisdiction
over installation.
.2 Make grounding connections in radial configuration only, with connections terminating at single grounding point. Avoid loop connections.
.3 All metal piping such as, but not limited to, water, sewage and gas, shall be bounded with minimum #6 AWG to the main system ground.
10. Panelboards
.1 Panelboards: Shop assembled commercial integrated type, voltage, phase, mains, capacity, circuit breakers and mounting as indicated. Aluminum
or copper bus with neutral of same ampere rating as mains.
.2 Provide circuit breakers for new panelboards. moulded case, bolt-on, Quick make-quick break, thermal-magnetic tripping breakers with 18,000A
(symmetrical) interrupting capacity. Circuit breakers shall be new with full manufacturer's warranty and purchased through authorized distributor.
.3 Provide type written directories in all panels showing type and location of each circuit.
.4 Provide a separate isolated ground bus.
.5 Flush mounted panelboards shall have 2-25mm (1") EMT empty conduits stubbed into ceiling space for future connections, complete with pull rope.
.6 Equip breakers serving exit lights, fire alarm system, intrusion alarm system, CCTV system and all emergency circuits with lock-on devices.
.7 Acceptable Manufacturer: Cutler-Hammer, Federal Pioneer, Siemens, Square D.
11. Mechanical Equipment
Unless otherwise shown on plan, for mechanical equipment provided by the mechanical trade requiring electrical power, the electrical trade shall
provide the following:
.1 The necessary power distribution equipment at the electrical room.
.2 The necessary conduit and wire to the mechanical equipment location.
.3 A terminating disconnect switch, unless provided for by the equipment manufacturer.
.4 Any miscellaneous items necessary to complete the work as shown on the drawing.
.5 The electrical trade shall verify all motor connections for proper phase rotation, where applicable.
12. Lighting
.1 Provide luminaires as indicated on the luminaire schedule and/or as specified under this section. These must and shall be complete with all
necessary plaster frames, hangers, lamps, louvers, diffusers, canopies, supports, brackets, etc.
.2 Contractor shall include in his tender, the luminaire(s) that are being specified. If an alternate manufacturer is named, it is mandatory that the
luminaire be equivalent in all respects, i.e. same lens, equivalent frame, performance, paint finish, ballast, construction quality, etc. Alternate
manufacturers or alternate luminaire types must be offered as an alternative only, to the base bid, with a separate price stated in the tender. Low
bidder will be determined on the basis of the specified items, not on "alternate saving".
.3 Position light as indicated. Adjust locations of luminaires to suit ceiling grid as indicated. Advise engineer if locations shown to change more than
150mm (6").
.4 Support all linear fixtures from building structure. T-bar support not acceptable.
.5 All luminaires which are located in suspended ceilings shall be supported by approved chains. Which shall allow the luminaires to be supported
independent of the ceiling system. A 1'x4' luminaire shall be supported with two (2) chains and a 2'x4' luminaire shall be supported with four (4)
chains to the roof structure or slab above. Anchor chains to joist and bridging where possible. When connecting to steel deck, anchor to side flutes.
.6 This contractor shall remove and dispose of all lighting not being re-used under new scheme whether shown on drawing or not.
13. Exit Lighting
.1 Exit Lights: Universal mounted, extruded aluminum captive mounting face plate, white baked enamel finish, running man style 120V AC.
Lamps: Flush mounted LED's, 10 watts maximum power consumption per face, 25 year minimum life c/w necessary transformers and solid state
components, 120V AC/12V DC.
Acceptable manufacturer: Dualite, Emergi-Lite, Hubbell, Lumacell, Luxnet, Aimlite.
.2 Number of exit light faces, mounting, arrows as indicated.
.3 Connect exit lights to dedicated circuit as indicated on drawings.
14. Emergency Lighting System
.1 Emergency light battery: Sealed lead oxide with 5 year life, complete with 2-12W, 12V, micro quartz lamps, auto test, auto-charger, and low voltage
disconnect. 120V AC input and 12V DC output.
Acceptable manufacturer: Dualite, Emergi-Lite, Lumacell, Luxnet, Aimlite.
.2 Emergency light heads: 2-12W, 12V micro style quartz lamps as indicated.
Acceptable manufacturer: Dualite, Emergi-Lite, Luxnet. Note: select same manufacturers as for battery unit supplying heads.
.3 Emergency light heads: 2-12W, 12V micro style quartz lamps as indicated.
Acceptable manufacturer: Dualite, Emergi-Lite, Luxnet. Note: select same manufacturers as for battery unit supplying heads.
.4 Connect heads to emergency lighting unit batteries with minimum #12 AWG conductors as indicated. Size conductors for minimum 3% voltage drop
as per CEC 2012.
15. Lighting Control System
.1 Locate light switches as indicated. Verify exact locations with owner prior to roughing-in.
18.01.17
SPECIFICATIONS
16. Data/Communication Systems
.1 Provide conduit and tray raceway for systems as indicated on drawings.
.2 Horizontal cabling is to be standard plenum rated CAT5e cable complete with jacks and patch cords. Cabling in trays to be armoured.
.3 Termination of communication wiring is to be completed by others.
.4 Communication devices to be provided by owner.
Communication wiring
285 ST. GEORGE STREET, PO BOX 310,
ANNAPOLIS ROYAL, NS B0S 1A0
TENDER NO. 17-353541B
THE ACADEMY PROJECT LIBRARY RENOVATIONS
590 ST. GEORGE STREET ANNAPOLIS ROYAL, NS
January 2018
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
TABLE OF CONTENTS Section 00 01 10
Page 1
2017-11-30
Section Title Pages
00 01 10 Table of Contents 1
00 10 00 Invitation to Tender 2
00 12 00 Summary Sheet 1
00 14 00 Articles of Agreement 3
00 20 00 ‘A’ Terms of Payment 4
00 30 00 ‘B’ General Conditions 18
00 40 00 ‘C’ Instructions to Tenderers 6
00 65 00 ‘E’ Insurance Schedule 1
00 70 00 ‘F’ Tender Form 4
00 85 00 ‘G’ Plans and Specifications 2
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
INVITATION TO TENDER Section 00 10 00
Page 1
2017-11-30
INVITATION TO TENDER
Sealed tenders will be received by the Town of Annapolis Royal, until 1:00pm on February 13, 2018,
for the following project:
Project Name: Tender No. 17-353541B
The Academy Project
Library Renovations
Annapolis Royal, Annapolis County, Nova Scotia
Tender Close Location: Town of Annapolis Royal
285 St. George Street
Annapolis Royal, NS
B0S 1A0
TENDER DOCUMENTS
Plans, Specifications, Tender documents and other project information, may be obtained from the Town
of Annapolis Royal office in pdf format, free of charge.
Documents: Town of Annapolis Royal
285 St. George Street
Annapolis Royal, NS
B0S 1A0
TENDER DEPOSIT
General Contractor’s tenders must be accompanied by a bid bond or certified cheque in the amount of
10% of the contract tender price.
TENDER SUBMISSION
Tenders shall be made on the forms provided, typewritten or completed in ink and signed by duly
authorized personnel of the submitting organization. One copy shall be submitted in a sealed envelope
and identified as:
Tender No. 17-353541B
The Academy Project
Library Renovations
Annapolis Royal, Annapolis County, Nova Scotia
Closing at 1:00pm, local time, February 13, 2018
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
INVITATION TO TENDER Section 00 10 00
Page 2
2017-11-30
And will be addressed as follows:
Attn: Gregory Barr, CAO
Town of Annapolis Royal
285 St. George Street
Annapolis Royal, NS
B0S 1A0
PROJECT DATES
All works: Contract Award: February 28, 2018
Final Completion: July 20, 2018
TECHNICAL ENQUIRIES
All queries must be submitted in writing prior to February 7, 2018 @ 1:00 pm and addressed to:
Project Manager: Michael Brown
Hatch
Email: [email protected]
Phone: 902-420-6492
BIDDERS SITE VISIT
A bidders site visit is scheduled for January 31, 2018 @ 10:00 am.
The lowest/highest or any tender will not necessarily be accepted.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
SUMMARY SHEET Section 00 12 00
Page 1
2017-11-30
Page 1 of 1
We, the tenderer, have examined the plans and specifications and the site of the Work and hereby agree to
supply all labour, materials, equipment, tools and incidentals to complete the Work for the prices quoted.
TOTAL TENDER PRICE (excluding HST) $
Total Performance of the Work shall be completed no later than July 20, 2018 , provided that project is
awarded no later than February 28, 2018.
Addenda No. to inclusive were carefully examined and taken into
consideration in the preparation of this tender.
Name of Tenderer
Name and Title of Authorized
Representative ( Please Print )
Signature
Address of Tenderer
Telephone # Fax #
Tenderer’s Tax Registration No.
**** End Summary ****
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS
TENDER NO. 17-353541B
ARTICLES OF
AGREEMENT
Section 00 14 00
Page 1
2017-11-30
THESE ARTICLES OF AGREEMENT made in triplicate this...................................day of............ 2018:
BY AND BETWEEN: Town of Annapolis Royal
285 St. George Street
Annapolis Royal, NS
B0S 1A0
(referred to in the documents forming the contract as the "Owner")
AND: .............................................
.............................................
.............................................
(referred to in the documents forming the contract as the “Contractor")
WITNESS that the Owner and the Contractor covenant and agree as follows:
ARTICLE I
The Contractor shall in a careful and workmanlike manner execute the following work; within the time herein
limited:
Tender No. 17-353541B
The Academy Project
Library Renovations
Annapolis Royal, Annapolis County, Nova Scotia
which work is more particularly described in the documents that are attached hereto, entitled "Plans and
Specifications" marked "G" (referred to in the documents forming the contract as the "Plans and Specifications") at
the place and in the manner therein set out, and for which;
Hatch Corporation
Suite 1009, 1809 Barrington Street
Halifax, Nova Scotia, B3J 3K8
Is acting as and is hereinafter referred to as the “Engineer” and/or “Consultant”
ARTICLE II
1 The Owner shall pay to the Contractor as consideration for the execution of the portion of the work to
which the fixed price arrangement is applicable the sum of $__________ (subject to any additions or
deductions provided for in these Articles, the General Conditions, the Terms of Payment or the Labour
Conditions, except any addition or deduction which is expressly stated to be applicable only to a unit price
arrangement), at the times and in the manner set out or referred to in the document that is attached hereto
entitled "Terms of Payment" and marked "A" (referred to in the documents forming the contract as the
"Terms of Payment").
ARTICLE III
1 Subject to sections 2 and 3 of this Article, bound documents (A) and (B) in addition to attached documents
(C), (E), (F) and (G) hereto entitled
(A) "Terms of Payment" and marked "A"
(B) "General Conditions" and marked "B"
(C) "Instructions to Tenderers" and marked "C"
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS
TENDER NO. 17-353541B
ARTICLES OF
AGREEMENT
Section 00 14 00
Page 2
2017-11-30
(E) "Insurance Schedule" and marked "E"
(F) "Tender Form" and marked "F"
(G) "Plans and Specifications" and marked "G"
all form part of the contract between the Owner and the Contractor.
2 Any provision of these Articles, the Terms of Payment and the General Conditions which are expressly
stated to be applicable only to a fixed price arrangement are not applicable to the whole or to the portion of
the work to which the unit price arrangement is applicable.
ARTICLE IV
1 With respect to the execution of the work by the Contractor;
(a) The security deposit having a current market value of $ ......................... that has been deposited
with the Owner by the Contractor for the due fulfilment of the contract shall be dealt with in
accordance with the provisions concerning security deposit in the General Conditions; or
(b) A surety company has furnished or has undertaken to furnish a Performance Bond, (insert details -
name of company, amount, date, etc.)
and a Labour and Material Payment Bond, (insert details - name of company, amount, date, etc.)
which bond or bonds shall operate according to their tenor.
2 Where bonds are provided under paragraph 1(b), the Contractor shall post on the site of the work a notice
that a Labour and Material Payment Bond is in force together with the name and address of the surety
company thereunder, a definition of those persons protected thereunder and an outline of the procedure for
submitting a claim thereunder.
ARTICLE V
For all purposes of or incidental to the contract, the Contractor's address shall be deemed to be:
.......................
ARTICLE VI
Any provision of this Contract prohibited by the applicable law of the Province of Nova Scotia shall be ineffective
to the extent of such prohibition without invalidating the remaining provisions of this Contract.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS
TENDER NO. 17-353541B
ARTICLES OF
AGREEMENT
Section 00 14 00
Page 3
2017-11-30
SIGNED, SEALED AND DELIVERED
In the Presence of:
Witness "The Owner"
......................................................... ..........................................................
......................................................... ..........................................................
......................................................... ..........................................................
Witness "The Contractor"
......................................................... ..........................................................
......................................................... ..........................................................
......................................................... ..........................................................
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS
TENDER NO. 17-353541B
TERMS OF PAYMENT ‘A’ Section 00 20 00
Page 1
2017-11-30
1. TOTAL PAYMENT
Subject to the provisions of the General Conditions, the Owner shall pay to the Contractor at the
times and in the manner hereinafter set out the amount by which the Contractor shall accept the
payment as full consideration for everything furnished and done by him in respect of the work.
2. PROGRESS PAYMENTS
(1) For the purposes of this section "Payment Period" means an interval of thirty days or
such other interval as the Contractor and Engineer-Architect agree upon.
(2) On or after the end of each Payment Period, a progress claim in writing showing the
amount of each class of work performed and materials furnished during such Payment
Period, with the value of work computed, shall be prepared by the Contractor and
submitted to the Engineer-Architect for approval.
(3) The Engineer-Architect shall within ten days endorse his approval or amended approval
on the copies of the progress claim, after making such alterations therein as he may deem
proper, and shall forward one copy to the Owner, return one copy to the Contractor, and
retain one copy in his possession and the progress claim so approved shall be the basis of
the payment by the Owner.
(4) In respect of each progress claim, the contractor shall deliver to the Owner;
(a) a Statutory Declaration deposing, or
(b) if required by the Owner, documentary proof verifying that all his lawful
obligations to subcontractors, workmen and suppliers of material in respect of the
work as at a date not greater than forty-five days prior to the date of the progress
claim have been fully discharged.
(5) The Owner shall, within twenty days after receipt of the approved progress claim from
the Engineer-Architect and receipt of the statutory declaration or proof of payment
required under subsection (4), pay to the Contractor an amount equal;
(a) when a Labour and Material Payment Bond was required of and furnished by
him, to 85% of the amount of the progress claim.
(6) Upon the expiration of 60 days from the date of issuance of an Interim Certificate of
Completion under the General Conditions or 30 days after the Contractor has delivered to
the Owner an invoice approved by the Engineer-Architect, showing the method by which
the amount claimed therein was calculated, whichever is the later date, and if the
Contractor has made and delivered to the Owner his Statutory Declaration deposing or
proof of payment, if required by the Owner, verifying the fact that all his lawful
obligations to subcontractors, workmen and suppliers of material in respect of the work
are fully discharged and that all other lawful claims against him in respect of the work
including Workmen's Compensation assessments, have been satisfied or provided for, the
amount described in section 1 as estimated by the Engineer-Architect less the aggregate
of;
(a) all payments made pursuant to subsection (5);
(b) an amount equal to double the estimated cost to the Owner of completing the
items and doing the things described in the Interim Certificate of Completion,
which in the opinion of the Engineer-Architect, are brought about by defects and
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS
TENDER NO. 17-353541B
TERMS OF PAYMENT ‘A’ Section 00 20 00
Page 2
2017-11-30
faults in the work;
(c) an amount equal to double the cost to the Owner of completing the items and
doing the things described in the Interim Certificate of Completion other than
items or things to which paragraph (b) applies;
(d) all payments made pursuant to section 7; and
(e) all amounts retained pursuant to a maintenance and guarantee provision, Section
8, contained in the contract shall become due and payable by the Owner to the
Contractor.
(7) Upon the expiration of 60 days from the date of issuance of the Final Certificate of
Completion under the General Conditions or 30 days after the Contractor has delivered to
the Owner an invoice approved by the Engineer-Architect, showing the method by which
the amount claimed therein was calculated (whichever is the later date), and if the
Contractor has made and delivered to the Owner his Statutory Declaration or proof of
payment, if required by the Owner, verifying the fact that all his lawful obligations and
lawful claims against him, arising out of the work, have been discharged and satisfied,
the amounts described in section 1 less the aggregate of
(a) all payments made pursuant to subsection (5);
(b) all payments made pursuant to subsection (6);
(c) all payments made pursuant to section 7, and
(d) all amounts retained pursuant to a maintenance and guarantee provision, section
8, contained in the contract,
shall become due and be payable by the Owner to the Contractor.
(8) Where the Contractor does not provide the Owner with a Statutory Declaration or proof
of payment required within the time limited therein, the Owner may withhold payment of
the monies which would otherwise have become due until the Statutory Declaration or
proof of payment is provided by the Contractor to the Owner and the Owner during this
period of time shall not be required to pay interest as provided for in section 6.
3. CLAIM PAYMENT NOT ACCEPTANCE
Neither a Progress Claim nor a payment by the Owner pursuant thereto shall be construed as
evidence that the work, material or any part thereof is complete, is satisfactory or is in accordance
with the contract.
4. OWNERS DELAY IN PAYMENT
Delay by the Owner in making a payment when it becomes due and is payable shall, if the delay
continues for more than fifteen days, entitle the Contractor to interest on the overdue payment and
the Owner shall pay to the Contractor interest thereon from the said fifteenth day until paid at the
rate being charged by the Canadian chartered banks on prime commercial accounts as of the date
from which such interest was payable.
5. OWNERS RIGHT OF SET-OFF
(1) Without restricting any right of set-off given or implied by law, the Owner may set-off
against any amount payable to the Contractor under the contract, any amount payable to
the Owner by the Contractor under this contract or under any current contract and,
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS
TENDER NO. 17-353541B
TERMS OF PAYMENT ‘A’ Section 00 20 00
Page 3
2017-11-30
without restricting the generality of the foregoing, the Owner may when making payment
deduct from the amount payable any amount which is then payable to the Owner or the
Province of Nova Scotia by the Contractor under the contract or which, by virtue of the
right of set-off, may be retained by the Owner.
(2) For the purposes of this section "current contract" means:
(a) a contract between the Owner and the Contractor under which the Contractor has
an undischarged obligation to perform or supply work, labour or materials, or
(b) a contract between the Owner and the Contractor in respect of which the Owner
has since the date on which this contract was entered into, exercised the right to
take the work, the subject of that contract, out of the Contractor's hands.
6. PAYMENT WHEN CONTRACT TERMINATED
In the event that the contract is terminated pursuant to the General Conditions the Owner shall as
soon as is practicable under the circumstances pay to the Contractor the amount, if any, payable
to the Contractor pursuant to that section.
7. INTERIM RELEASE OF HOLDBACK
(1) The Owner may at any time, but not more than twice during the term of the contract, on
the written application of the Contractor and with the approval of the surety, pay to the
Contractor all, or a portion of, the percentage amounts retained up to that time in respect
of payments on Progress Claims.
(2) Subject to the approval of the surety, the making of any such payment, and the amount
thereof, are wholly in the discretion of the Owner.
8. HOLDBACK FOR MAINTENANCE AND GUARANTEE PERIOD
(1) The owner shall retain fifteen percent (15%) of the amount of each progress claim for
maintenance and guarantee.
(2) Sixty (60) days after the date of a Certificate of Substantial Performance of the Work, if
issued, otherwise sixty (60) days after the date stated in the Certificate of Provisional
Acceptance of the Work, pay to the Contractor, the 15% holdback monies less two
hundred percent (200) of the value of any uncorrected deficiencies, provided that the
Contractor has submitted to the Engineer, prior to payment the following:
(a) A current Statutory Declaration verifying that all subcontractors, suppliers,
labout and accounts for services, materials, machinery and equipment and any
other indebtedness which may have been incurred by the Contractor, directly or
indirectly, in the performance of the Work have been fully paid by the contractor
except for holdbacks on subcontracts listed in this Statutory Declaration and that
mentioned herein, for Work done or materials furnished or in respect of anything
done under or by virtue of the Contract;
(b) A letter of clearance or certificate from the Workers Compensation Board
verifying that all assessments due by the Contractor have been fully paid;
(c) A statement verifying that all claims and demands for extra work or otherwise
under or in connection with the contract have been presented to the Engineer;
(d) A letter from the contractor’s surety (if any) approving the release of holdback;
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS
TENDER NO. 17-353541B
TERMS OF PAYMENT ‘A’ Section 00 20 00
Page 4
2017-11-30
(e) All record Documents, showing changes as constructed, Operating and
Maintenance Manuals, guarantees, warranties, certificates, reports, spare parts
and spare materials required by the Contract Documents.
9. LIQUIDATED DAMAGES FOR DELAY
(1) Liquidated Damages shall be payable to the Owner if the Work has not been completed
by the completion date as established with the Owner, or the completion date as
extended.
(2) The Contractor will be expected to complete the Work within the time given in his
Tender Form. It shall be clearly understood by the Contractor, that whereas the diligent
and effective prosecution of the Work and the completion thereof is a material part of the
Agreement, and that the Owner may sustain damage or loss as a result of the Contractor’s
failure to complete the Work within the time agreed upon and any extension of time as
provided herein, the Contractor will pay the Owner liquidated damages and not as a
penalty, for each calendar day the completion of the Work is delayed beyond the
completion date, or the completion date as extended.
(3) Should Liquidated Damages be inapplicable for any reason or should the Contractor
abandon or refuse to do any Work the Owner shall be entitled to such damages for delay
as set out in the Contract herein.
(4) Any extension of time that may be granted the Contractor shall be so granted and
accepted without prejudice to any rights of the Owner whatsoever, under this Contract,
should the Work not be completed on the said completion date or any extension thereof
as provided by the contact hereof the Owner shall have the authority to deduct the
liquidated damages from any payments which become due and payable to the Contractor
under this Contract.
(5) The value of liquidated damages payable to the Owner for the duration of the Period of
Delay is $500 per day.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 1
2017-11-30
1. DEFINITIONS
In this specification, the following words and expressions shall have the meanings hereinafter assigned to
them, except where the context otherwise requires.
.1. The “Town of Annapolis Royal “ or “The Owner” shall mean the Owner/Council of the Town of
Annapolis Royal, Nova Scotia and includes the Owner’s personal representatives or successors.
.2 “The Consultant” shall mean the consulting engineering firm or individual currently licensed to practice
in the Province of Nova Scotia, assigned or approved by the Owner to carry out the various professional
services required to complete the project.
.3 “The Contract” shall mean the Agreement between the Owner and the selected tenderer governing the
execution of the work.
.4 “The Contractor” shall mean the party or parties, person or persons, firm or company, whose tender for
the execution of the work has been accepted by the Owner and includes the contractor’s personal
representatives, successors and permitted assigns.
.5 “The Engineer” shall mean the Project Manager, the Project Engineer representing Town of Annapolis
Royal or any other authorized person as may be appointed to supervise the carrying out of the Contract.
.6 “The Plans” shall mean and include the plans, sections and other delineations which accompany or are
referred to in the specifications and any modification of such plans approved in writing for the contract
and any additional plans prepared by the Engineer to facilitate the work.
.7 “The Site” shall mean the lands and other places, on, under, in or through which the works are to be
executed or carried out.
.8 “The Specifications” shall mean all sections included in this document including the form of tender,
instructions to tenderers, general conditions of contract, plans and technical specifications contained
herein and on the plans and all supplementary specifications issued for the tender.
.9 “Working Day” shall mean Monday to Friday inclusive, from 7:30am to 5:30pm, of any week excluding
statutory holidays.
.10 “The Work” shall mean all the work set out and described in “The Plans” and “The Specifications” to be
executed in accordance with the contract.
.11 “Incidental items” shall be any item of work, material, labour or equipment necessary to complete a
specified item of work in accordance with these specifications, supplementary general or technical
specifications, contract drawings or as otherwise required by either a manufacturer or in accordance with
recognized standard practice and procedures, for which there is no particularly identified or specified
item under any other part of the Owner’s specifications and for which no payment will be made.
2 ADHERENCE TO PLANS AND SPECIFICATIONS
.1 The Contractor shall execute the works strictly in accordance with the plans and specifications, or with
any Supplementary directions, details or Change Orders ordered by the Engineer, as required for the
proper completion of the contract.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 2
2017-11-30
3 DOCUMENTS
.1 The Contractor will be provided without charge, one (1) digital copy of the Project Documents or parts
thereof as are reasonably necessary for the performance of the Work.
.2 It is the responsibility of the Contractor to ensure that they are in possession of drawings “APPROVED
FOR CONSTRUCTION” before commencement of any work.
.3 The Contractor shall keep one copy of current Contract Documents and shop drawings at the Place of the
Work, in good order and available to the Engineer and his representatives. This requirement shall not be
considered to include the executed set of Contract Documents.
.4 Drawings, Specifications, Models and copies thereof furnished by the Engineer are and shall remain his
property except for the signed Contract sets belonging to each party to this Contract. Such documents
and models are to be used only with respect to the Work and are not to be used on other Work. Such
documents and models are not to be copied or revised in any manner without the written authorization of
the Engineer.
4 MEASUREMENTS, PRECEDENCE AND DISCREPANCIES
.1 In interpreting the Plans and Specifications:
(a) Figured dimensions shown on the drawings will take precedence over scaled measurements. The
Contractor will report any discrepancy to the Engineer.
(b) The Specifications are intended to indicate the qualitative aspects of the work and will take
precedence in this respect.
(c) The drawings are intended to show the location and quantitative aspects of the work and will
take precedence in this respect.
5 CONTRACT BINDING
.1 The Contract shall insure to the benefit of and be binding upon the parties hereto and their heirs,
executors, administrators, successors, and assigns.
6 ASSIGNMENT
.1 The Contract may not be assigned without the written consent of the Owner.
7 INDEMNITY BY CONTRACTOR
.1 Except as provided in Section 8, the Contractor shall indemnify and save harmless the Owner from and
against all claims, demands, losses, costs, damage, actions, suits, or proceedings by whomsoever made,
brought or prosecuted in any manner based upon, arising out of, related to, occasioned by or attributable
to the activities of the Contractor in executing the work under the contract or to an infringement or an
alleged infringement by the Contractor of a patent of invention.
.2 For the purposes of subsection .1, "activities" includes an act improperly carried out, an omission to
carry out an act and a delay in carrying out an act.
8 INDEMNITY BY OWNER
.1 The Owner shall indemnify and save harmless the Contractor from and against all claims, demands,
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 3
2017-11-30
losses, costs, damage, actions, suits or proceedings arising out of his activities under the contract which
are directly attributable to
(a) lack of title, a defect in title or an alleged lack of title or defect in title to the site of the work; or
(b) an infringement or an alleged infringement of any patent of invention in executing anything for
the purposes of the contract, the model, plan or design of which was supplied by the Owner to
the Contractor.
9 ELECTED MEMBERS
.1 No member of the Owner's Council or member of the Legislative Assembly of the Province of Nova
Scotia shall be admitted to any share or part of the contract or to any benefit arising therefrom unless
such member of the Council falls within the latest requirements of the Elections Act, Acts of Nova
Scotia.
.2 No member of the Owner's Council shall be admitted to any share or part of the contract or to any benefit
arising therefrom if the Owner's funds are involved, whether directly or indirectly, in the payment for or
financing of such contract.
10 SERVING NOTICES
.1 Notices shall be in writing and shall
(a) be delivered to the Contractor in person, or, if the Contractor is a corporation or partnership, be
delivered to the superintendent or to a senior administrative officer of the corporation or
partnership, or
(b) be sent by mail (including electronic mail) to the Contractor or his superintendent addressed to
the address mentioned in the contract, and if any question arises as to when any such notice was
given to or received by the Contractor it shall be deemed to have been sufficiently given to and
received by him,
(c) if it were delivered pursuant to paragraph (a), on the day it was delivered, or
(d) if it were sent by mail pursuant to paragraph (b), on the day it was received by the Contractor or
on the sixth day after it was mailed, whichever is the earlier.
11 AUTHORITY OF THE ENGINEER
.1 The Engineer will provide administration of this Contract as described in the Contract Documents.
.2 The Engineer, appointed by the owner, will be the Owner's representative during construction and until
completion of any correction of defects under the provisions of warranty, or until the issuance of the
Certificate of Final Performance of the Work, whichever is later. The Owner's instructions to the
Contractor shall be forwarded through the Engineer. The Engineer will have authority to act on behalf of
the Owner only to the extent provided in the Contract Documents, unless otherwise modified by written
agreement.
.3 The Engineer will not be responsible for and will not have control or charge of construction means,
methods, techniques, sequences or procedures required for the Work in accordance with the applicable
Nova Scotia construction practices. The Engineer will not be responsible for or have control or charge
over the acts or omissions of the Contractor, his Subcontractors, or their agents, employees or other
persons performing any of the Work.
.4 The Engineer will have authority to reject work which in his opinion does not conform to the
requirements of the Contract Documents. Whenever he considers it necessary or advisable he will have
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 4
2017-11-30
authority to require special inspection or testing of work whether such work has been fabricated, installed
or completed. However, neither the Engineer's authority to act nor any decision made by him either to
exercise or not to exercise such authority, shall give rise to any duty or responsibility of the Engineer to
the Contractor, his subcontractors, or their agents, employees or other persons performing any of the
Work.
12 NO IMPLIED OBLIGATION
.1 No implied obligation of any kind by or on behalf of the Owner shall arise from anything in the contract,
and the express covenants and agreements herein contained and made by the Owner are and shall be the
only covenants and agreements upon which any rights against the Owner are to be founded; and, without
limiting the generality of the foregoing, the contract supersedes all communications, negotiations and
agreements, either written or oral, relating to the work and made prior to the date of the contract.
.2 Nothing contained in the Contract Documents shall create any contractual relationship between the
Engineer and the Contractor, his Subcontractors, his suppliers, or their agents, employees or other
persons performing any of the Work.
13 DISPUTE & ARBITRATION
.1 Claims, disputes and other matters in question relating to the performance of the Work or the
interpretation of the Contract Documents, shall be referred initially to the Engineer in writing for
decision which he will give in writing within a reasonable time.
.2 Any claim or dispute involving the Owner and the Contractor may, by agreement of the parties, be
submitted to arbitration.
.3 Should the Owner in accordance with this section agree to enter an Agreement to Arbitrate the
Agreement shall be limited to matters contained in the claim submitted by the Contractor and shall
stipulate that the arbitration is not binding on either party.
14 DEFAULT OR REMOVAL OF WORK FROM CONTRACTOR
.1 In any of the following cases, namely,
(a) where the Contractor has made default or delayed in commencing or in diligently executing the
work or any portion thereof to the satisfaction of the Engineer and the Engineer has given notice
thereof to the Contractor and has by such notice required the Contractor to put an end to such
default or delay, and such default or delay continues for six (6) days after such notice was given;
(b) where the Contractor has made default in the completion of the work, or any portion thereof,
within the time limited for such completion by the contract;
(c) where the Contractor has become insolvent;
(d) where the Contractor has committed an act of bankruptcy;
(e) where the Contractor has abandoned the work;
(f) where the Contractor has made an assignment of the Contract without the required consent; or
(g) where the Contractor has otherwise failed to observe or perform any of the provisions of the
Contract the Owner may, without any other authorization, take all or any portion of the work out
of the Contractor's hands and may employ such means as he may see fit to complete the work.
.2 Where the work or any portion thereof has been taken out of the Contractor's hands under subsection .1
the Contractor shall not, except as provided in subsection .3, be entitled to any further payment in respect
of the work so affected including payments then due and payable but not paid, and the obligation of the
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 5
2017-11-30
Owner to make payments in respect thereof as provided for in the Terms of Payment shall be at an end
with respect to that portion of the work taken out of his hands, and the Contractor shall be liable to and
upon demand therefore shall pay to the Owner an amount equal to all loss and damage suffered by the
Owner by reason of the non-completion of the work by the Contractor.
.3 Where the work or any portion thereof has been taken out of the Contractor's hands under subsection .1
and is subsequently completed by the Owner, the Engineer shall thereafter determine the amount, if any,
of holdback and progress claims of the Contractor in respect thereof unpaid at the time of taking the
work out of his hands that in his opinion are not required by the Owner for the purposes of the Contract
and the Engineer shall, if he is of the opinion that no financial prejudice to the Owner will result,
authorize payment of that amount to the Contractor.
15 CONTRACTOR’S CONTINUING OBLIGATION
.1 The taking of the work, or any portion thereof, out of the Contractor's hands pursuant to Section 14 does
not relieve or discharge the Contractor from any obligation under the contract or imposed upon him by
law except the obligation under the contract to complete the physical execution of that portion of the
work so taken out of his hands.
.2 If the work or any portion thereof is taken out of the Contractor's hands pursuant to Section 14, all
materials and the interest of the Contractor in all real property, licenses, powers and privileges acquired,
used or provided by the Contractor for the work shall be the property of the Owner without
compensation to the Contractor.
16 SUSPENSION OF WORK
.1 The Engineer may require the Contractor to suspend execution of the work either for a specified or
unspecified period by giving notice to that effect to the Contractor.
.2 The Contractor upon receiving notice of the Owner's requirement pursuant to subsection .1 shall suspend
all operations except those which, in the Engineer's opinion, are necessary for the care and preservation
of the work, the materials and plant.
.3 During the period of suspension the Contractor shall not remove from the site any part of the work, any
materials or any plant without the consent of the Engineer.
.4 If the period of suspension is 30 days or less, the Contractor, upon the expiration of the period of
suspension, shall resume the execution of the work and except where the suspension order was due to the
Contractor not diligently prosecuting the work or failing to prosecute the work in a good and
workmanlike manner he is entitled to be paid the cost of any plant, labour and material necessarily
involved in complying with the suspension.
.5 If the period of suspension is more than 30 days and if, upon the expiration of the period of suspension,
the Engineer and the Contractor agree that the execution of the work be completed by the Contractor, the
Contractor shall resume operations and complete the execution of the work in accordance with any terms
and conditions agreed upon by the Engineer and the Contractor.
.6 If upon the expiration of a period of suspension of more than 30 days, the Engineer and the Contractor
do not agree that the work will be completed by the Contractor or they are unable to agree upon the terms
and conditions under which the Contractor will complete the work, the notice of suspension shall be
deemed to be a notice of termination.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 6
2017-11-30
17 TERMINATION OF CONTRACT
.1 The Owner may at any time by giving notice to that effect terminate the contract.
.2 The Contractor shall upon receipts of a notice pursuant to subsection .1 cease all operations forthwith.
.3 If the contract is terminated pursuant to subsection .1 the Owner shall pay to the Contractor an amount
equal to the lesser of
(a) the value as agreed upon by the Contractor and the Engineer of all work performed by the
Contractor as at the date of termination or, if the Contractor and the Engineer cannot agree, as
calculated in accordance with the formula set out in the Contract Document less all amounts
already paid to the Contractor by the Owner and less all amounts which the Contractor is liable
to pay to the Owner; and
(b) the amount calculated in accordance with the terms of payment which would have been payable
to the Contractor had he completed the work.
18 SUB-CONTRACTING
.1 Except for the subcontracting proposed by the Contractor in his accepted tender, neither the whole nor
any part of the work may be subcontracted by the Contractor without the consent of the Engineer.
.2 Every Subcontract by the Contractor, whether as proposed in the approved tender or as approved by the
Engineer under subsection .1, shall provide that the subcontractor shall comply with all terms and
conditions of this contract which can reasonably be applied to his undertaking.
.3 The Contractor shall include as part of his Contract, all Subcontracts for such portions of the work not
done by the Contractor's organization.
.4 The Contractor shall not make any changes to the named Subcontractors listed in the tender form unless
written approval of the change is received from the Engineer.
19 INSURANCE
The Contractor shall provide, maintain and pay for the insurance coverage listed in “Insurance Schedule
‘E’”.
20 BONDS
.1 The Contractor shall provide to the Owner a Performance Bond and a Labour and Material Payment
Bond per the requirements set out in the Instructions to Tenderers.
.2 The contractor shall furnish a performance bond covering the faithful performance of the contract,
including the period of maintenance, satisfactory to it as to form and issuer. The performance bond will
be fifty percent (50%) of the awarded contract price. If a performance bond is accepted, the Owner will
return such cheques or bid bond comprising the initial deposit on receipt of the Performance Bond and
approval of same.
.3 The contractor shall furnish a labour and materials payment bond to the owner in the amount of fifty
percent (50%) of the awarded contract price.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 7
2017-11-30
.4 The Performance Bond and a Labour and Material Payment Bond shall be issued by a duly licensed
surety company authorized to do business in the province of Nova Scotia.
.5 The bonds shall remain in effect until issuance of the Certificate of Final Acceptance. The form of the
bond shall be in accordance with the latest edition of the Crown Construction Contracts Act.
21 PERMITS, LICENCES, LAWS AND RULES
.1 The Contractor shall obtain the permits, licenses and certificates and pay the fees required for the
performance of the Work which are in force at the date of tender closing, but this shall not include the
obtaining of permanent easements or right of way.
.2 The Contractor shall apply and pay for Building Permit and all other necessary permits, licenses,
certificates of inspection that may be required by authorities having jurisdiction, required for the
execution and/or approval of the work.
.3 The Work shall comply with local by-laws and ordinances, rules and regulations of the Province
affecting local building requirements. Notify Engineer, in writing, of deviation from such regulations
found in the Contract Documents.
22 CERTIFICATE OF PROVISIONAL ACCEPTANCE
.1 When all works and tests have been satisfactorily completed, the contractor shall then advise the
Engineer in writing. Within ten (10) working days following the receipt of this letter, the Engineer shall
arrange for an inspection of the work with the Owner and the contractor. A list of any noted deficiencies
will be prepared and the Contractor shall then promptly carry out all the works so named. When these
works have been completed and accepted, the Engineer shall issue the “Certificate of Provisional
Acceptance” also known as “Certificate of Substantial Completion”.
23 CERTIFICATE OF FINAL ACCEPTANCE
.1 After the date declared in the Certificate of Provisional Acceptance, the Contractor shall advise in
writing that the works are fully completed and are ready for final inspection. Within ten (10) working
days following receipt of this letter the Engineer shall make arrangement for this final inspection of the
work with the Engineering Department and the Contractor.
.2 The Contractor shall promptly correct all defects, deficiencies, etc. which are identified during the final
inspection.
.3 When this work has been completed, the Engineer shall prepare the “Certificate of Final Acceptance”.
The Contractor shall sign the certificate, affixing the corporate seal thereto declaring that the Contractor
has no further claims against the Town of Annapolis Royal whatsoever with respect to the contract. The
final holdback amount, less any monies owing, shall then be paid to the Contractor.
24 MAINTENANCE PERIOD
.1 Without restricting any warranty or guarantee implied or stipulated by law the Contractor shall at his
own expense rectify and make good any defect or fault or omission that appears in the work for a
minimum of twelve (12) months or within such additional period stipulated in the Specifications
concerning portions of the work from the date of the Engineer's Certificate of Provisional Acceptance
and until issuance of the “Certificate of Final Acceptance”.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 8
2017-11-30
.2 If any defect, fault or omission appears in the work and the Engineer is of the opinion that it is one which
the Contractor, either under subsection .1 or under a warranty or guarantee implied or stipulated by law,
is obliged to remedy and make good the Engineer may direct the Contractor to remedy and make good
the defect, fault or omission by giving notice to the Contractor of the existence of the defect, fault or
omission and the notice shall specify the time within which the defect, fault, or omission is to be rectified
and made good.
.3 Deficiencies of a non-emergency nature must be repaired within one (1) week after receipt of
instructions in writing to do so.
.4 Deficiencies of an urgent or emergency nature must be repaired immediately upon receipt of notification
from the Engineer or from the Town of Annapolis Royal. Every effort possible must be made by the
Contractor to repair such deficiencies immediately. Failure to do so due to lack of equipment, material,
labour or reasons whatsoever will result in the Owner causing the works to be done at the expense of the
Contractor.
.5 If, after issuance of the “Certificate of Provisional Acceptance”, and during the “Maintenance Period”
the works are found to be in an unsatisfactory condition and the Contractor fails to remedy the work, the
Owner may use monies retained as is found necessary to remedy the works. The balance, if any, will be
paid to the Contractor after issuance of the “Certificate of Final Acceptance”.
25 EXTENSION OF TIME AND PENALTY FOR DELAY IN COMPLETION
.1 The Engineer may, on the application of the Contractor if made in accordance with the time limits in
subsection .2 and made before the day fixed by Article I of the Articles of Agreement for Completion of
the work or any specified portion thereof or before any new date for completion previously fixed under
this subsection, if in his opinion it is in the public interest, extend the time for completion of the work or
any specified portion or portions thereof by fixing a new day for such completion.
.2 For the purposes of this section, the work shall be deemed to be completed on the day the Engineer
issued his Certificate of Provisional Acceptance, and "period of delay" means the period commencing on
the day fixed by Article I of the Articles of Agreement for completion of the work or any portion thereof
or such subsequent day, if any, to which the time for completion has been extended under subsection .1
and ending on the day immediately preceding the day on which the work or portion thereof is completed.
.3 If in the opinion of the Engineer the work could have been completed within the authorized time and the
Contractor has failed to meet the completion date, the Owner reserves the right to charge Liquidated
damages:
.1 Liquidated Damages shall be payable to the Owner if the Work has not been completed by
the completion date as established with the Owner, or the completion date as extended as
provided in the contract.
.2 The Contractor will be expected to complete the Work within the time given in his Tender
Form. It shall be clearly understood by the Contractor, that whereas the diligent and effective
prosecution of the Work and the completion thereof is a material part of the Agreement, and
that the Owner may sustain damage or loss as a result of the Contractor’s failure to complete
the Work within the time agreed upon and any extension of time as provided herein, the
Contractor will pay the Owner liquidated damages and not as a penalty, for each calendar
day the completion of the Work is delayed beyond the completion date, or the completion
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 9
2017-11-30
date as extended.
.3 Should Liquidated Damages be inapplicable for any reason or should the Contractor
abandon or refuse to do any Work the Owner shall be entitled to such damages for delay as
set out in the Contract herein.
.4 Any extension of time that may be granted the Contractor shall be so granted and accepted
without prejudice to any rights of the Owner whatsoever, under this Contract, should the
Work not be completed on the said completion date or any extension thereof as provided by
the contact hereof the Owner shall have the authority to deduct the liquidated damages from
any payments which become due and payable to the Contractor under this Contract.
.5 The value of liquidated damages payable to the Owner for the duration of the Period of
Delay is $500 per day.
26 CHANGES IN THE WORK
.1 The Engineer may at any time before he issues the Certificate of Final Acceptance, in writing,
(a) order work or material in addition to that provided for in the Plans and Specifications; and
(b) delete work or change the dimensions, nature, character, quantity, quality, description, location
or position of the whole or any part of the work or material provided for in the Plans and
Specifications or as ordered pursuant to paragraph (a), and the Contractor shall execute the work
in accordance with such orders, deletions, and changes as if the same had appeared in and been
part of the Plans and Specifications.
.2 All contemplated changes in the work shall be issued by the Engineer on a standard "Request for
Estimate and Change Order" form.
.3 Contractor shall, upon receipt of the Request for Estimate and Change Order, submit to the Engineer for
his approval within ten (10) days, an estimate for the changes in work. Estimates for changes shall be
priced in detail giving: actual net material trade prices (not list price); actual labour costs (including
payroll burden); and actual equipment rental.
The price of any change order shall be the aggregate estimated cost to the Contractor for all labour, plant
and material that is required for that change as agreed upon in writing plus an allowance for supervision,
coordination, administration, overhead, margin and the risk of undertaking the work within the stipulated
amount, which allowance shall be equal to:
15% total for the “net” costs of the change when performed by the Contractor’s Own forces. The
“net” cost shall permit a 5% overhead and 10% profit be applied to the net value of changes.
The overhead and profit are to be applied to the net value of a change after applicable credits
have been deducted.
15% total for the “net” costs of the change when performed by the Contractor’s sub-contracted
workforce. The “net” cost shall permit a 5% mark-up by contractor and 10% mark-up by sub-
contractors be applied to the net value of changes. The overhead and profit are to be applied to
the net value of a change after applicable credits have been deducted.
.4 Engineer shall within five (5) days notify the Contractor whether estimates are accepted or further
information required. Acceptance shall be indicated in writing and a signed copy of form returned to
Contractor.
.5 When a request for estimate and change order is issued by the Engineer, work in the areas affected or
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 10
2017-11-30
related thereto shall be immediately suspended and shall not be resumed until Change Order has been
approved or cancelled by the Engineer which shall be the authority for Contractor to commence work on
change. No claim for delays shall be allowed for the temporary work stoppage unless all work on the
project is affected by the contemplated change.
.6 Minor changes in the work shall be as ordered by a letter from the Engineer and the Contractor shall
proceed with work immediately, price such changes and record in the monthly minutes of meetings
under a separate article along with the price.
.7 Minor changes appearing in minutes of meeting shall be reviewed monthly and items agreed upon shall
be grouped and issued under a single change order.
27 VALUATION OF CHANGES IN THE WORK
.1 In the case of Changes in the Work, the form of presentation of costs and methods of measurement shall
be agreed to by the Engineer and Contractor before proceeding with the change. The Contractor shall
keep accurate records, as agreed upon, of quantities or costs and present an account of the cost of the
Change in the Work, together with vouchers where applicable. No claim for compensation will be
considered unless such detailed account has been received. No payment or compensation for the costs of
repairs to equipment or for construction equipment standing idle on the site will be considered.
28 MAINTAIN RECORDS BY CONTRACTOR
.1 The Contractor and each Subcontractor shall maintain
(a) the detail of the compilation of his estimate showing labour, materials, overhead and all other
elements forming his lump sum prices as prepared for tender, and
(b) full records of the actual cost to him of the work together with all proper tender calls, quotations,
contracts, correspondence, invoices, receipts and vouchers relating thereto, and shall make them
available to audit and inspection by the Owner, the Comptroller of the Province of Nova Scotia,
or by persons acting on their behalf. Contractor shall allow them to make copies thereof and to
take extracts therefrom, and shall furnish them with any information which they may require
from time to time in connection with such records.
.2 The records maintained by the Contractor and each subcontractor pursuant to this section shall be kept
intact until the expiration of two years from the date of issuance of the Final Certificate of Completion or
until the expiration of such other period as the Owner may direct.
.3 The Contractor shall require all subcontractors and all firms, corporations, and persons directly or
indirectly controlled by or affiliated with the Contractor and all firms, corporations and persons directly
or indirectly having control of the Contractor to comply with the subsections .1 and .2 as if they were the
Contractor.
29 EXAMINATION OF SITE
.1 It is the responsibility of the Contractor to become familiar with and understand the nature and extent of
the work to be executed, and generally of all matters which can in any way influence the tender, in so far
as possible. Information on any matter derived from the plans and specifications or obtained from the
Engineer or from test pits, etc. shall not in any way relieve the Contractor from risk or from fulfilling the
terms of the Contract.
.2 All details and incidental items not particularly mentioned in the specifications but which, whether in
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 11
2017-11-30
temporary or permanent works, must evidently be required by the nature of the work shall be considered
included in the contract. On submission of the bid, it shall be understood that this has been done and
provision for all risks, incidental items and contingencies are included in the contract price.
30 ADJUSTMENTS DUE TO SITE CONDITIONS, NEGLECT OR DELAY
.1 No payment, in addition to the payment expressly promised by the contract, will be made by the Owner
to the Contractor due to any extra expense, loss or damage incurred or sustained by the Contractor
including a misunderstanding on the part of the Contractor as to any fact, whether or not such
misunderstanding is attributable directly or indirectly to the Owner or any of the Owner's agents or
servants, and whether or not any negligence or fraud on the part of the Owner's agents or servants is
involved unless, in the opinion of the Engineer the extra expense, loss or damage is directly attributable
to:
a) a substantial difference between information relating to site conditions at the site of the work, or
a reasonable assumption of fact based thereon, in the Plans and Specifications or other
documents or material communicated by the Owner to the Contractor for his use in preparing his
tender and the real site conditions encountered at the site of the work by the Contractor when
executing the work, or
(b) neglect or delay occurring after the date of the contract on the part of the Owner in providing
any information or in doing any act which the contract either expressly requires the Owner to do
or which would be done by an Owner, in accordance with the usage of the trade to enable his
Contractor to carry out an undertaking similar to the work being executed under the contract for
the Owner, in which case, if as a condition precedent the Contractor has given to the Engineer
written notice of his claim before the expiration of thirty days from the encountering of the soil
conditions giving rise to the claim or from the day on which the neglect occurs or the delay
commences, as the case may be, the Owner shall pay to the Contractor in respect of the
additional expense, loss or damage incurred or sustained by reason of that difference, neglect or
delay, an amount equal to the cost of the additional plant, labour and materials necessarily
involved.
.2 If, in the opinion of the Engineer, the Contractor has effected a saving of expenditure by reason of the
execution of the work by the Contractor being rendered less difficult, and less costly because the soil
conditions actually encountered by the Contractor at the site of the work when executing the work are
substantially different from soil conditions indicated in information, or a reasonable assumption of fact
based thereon in the Plans and Specifications or other documents or material communicated by the
Owner to the Contractor for his use in preparing his tender, the amount set out in Article II of the
Articles of Agreement shall be reduced by an amount equal to the saving effected by the Contractor.
31 DETERMINATION OF COST – AGREEMENT
.1 The cost of the labour, plant or material shall be the amount agreed upon by the Contractor and the
Engineer.
32 DETERMINATION OF COST - COST PLUS
.1 Where other methods of determination cannot be used and the Engineer and Contractor do not agree, the
Owner and the Contractor may, by an agreement in writing, agree to determine the cost of labour, plant
or material to be equal to the aggregate of
(a) all reasonable and proper amounts expended by or legally payable by the Contractor in respect
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 12
2017-11-30
of the labour, plant or material which fall within any of the classes of expenditure described in
subsection .2 (being costs which are directly attributable to the execution of the work and are not
costs in respect of which the allowance in paragraph (b) is made); and
(b) 15% of the total of the expenditures of the Contractor that meet the test in paragraph (a) (being
an allowance for all other expenditures by the Contractor and for profit and without limiting the
generality of the foregoing, being also an allowance for payments and charges relating to
overhead, head office expenses and general administration costs of the Contractor, including
finance and interest charges).
.2 Classes of expenditure that are allowable are:
(a) payments to subcontractors, agreed to by the Owner;
(b) wages, salaries, and travelling expenses of employees of the Contractor while they are properly
engaged on the work other than wages, salaries, bonuses, living and travelling expenses of
personnel of the Contractor generally employed at the head office or at a general office of the
Contractor unless such personnel is engaged at the site of the work with the approval of the
Engineer;
(c) payments for materials necessary for and incorporated in the work, or necessary for and
consumed in the execution of the work;
(d) payments for consumable tools, other than tools customarily provided by tradesmen, necessary
for and used in the execution of the work;
(e) payments for preparation, inspection, delivery, installation and removal of materials necessary
for the execution of the work;
(f) payments for renting, erecting, maintaining, and removing temporary offices, sheds and similar
structures necessary for and used by the Contractor in executing the work;
(g) assessments in respect to the work payable under any statutory requirement or other agreements
relating to payroll burdens;
(h) payments for renting plant and allowances for plant owned by the Contractor necessary for the
execution of the work if such payments or allowances are reasonable and do not exceed the
equipment rental rate set out in Schedule A, to the Regulations made under the Crown
Construction Contracts Act;
(I) payments for inspection, delivery, installation and removal for the execution of the work; and
(j) other payments made with the approval of the Engineer that are necessary for the execution of
the work.
33 DEFINITION OR DETERMINATION OF COST
.1 For the purposes of sections 31 and 32 and except as in those sections specifically provided plant does
not include tools.
34 COST BREAKDOWN LUMP SUM WORK
.1 The Contractor shall, on contracts which are wholly lump sum, submit a schedule to the Owner showing
the cost breakdown of the lump sum work to assist the Engineer in assessing progress claims.
35 ESCALATION - LABOUR - MATERIALS
.1 Except where the Labour Conditions contain an escalation clause the amount payable to the Contractor
under the contract shall not be increased or decreased due to any increase or decrease in the cost of the
work brought about by an increase or decrease pursuant to the Labour Conditions.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 13
2017-11-30
36 PROCUREMENT
.1 Buying Locally: The Town recognizes the importance of buying locally and using local suppliers as
much as possible. This factor will always be taken into account when considering Best Value.
.2 Environmental Considerations: All environmental impacts should be considered through the entire
procurement process. Environmentally preferable goods and services are those that have a lesser or
reduced impact on the environment over the life cycle of the good or service, when compared with
competing goods or services serving the same purpose.
37 QUALITY OF MATERIALS
.1 All materials employed in the work must be the best of their respective kinds, consistent with what is
herein specified.
38 WORK SCHEDULE
.1 The Contractor will provide immediately following the date of the contract award a schedule showing
the program and timing for construction of the various portions of the project and estimated dates for
completion of each portion.
.2 No progress claims shall be paid by the Owner during the time while the Contractor is in default under
subsection .1.
.3 He will submit a monthly progress report to the Engineer which will show a comparison of work
completed and work as scheduled, and will revise this schedule as necessary during the work.
.4 The Contractor shall notify the Engineer a minimum of seven (7) days in advance of his requirements,
for drawings or approval of shop drawings not scheduled, or where no schedule is prepared.
39 ACCESS TO WORK BY OWNER
.1 The Contractor shall permit the Engineer to have access to the work and to all areas where portions of
the work are being fabricated or manufactured always during the execution of the work. Shall provide
the Engineer with full information concerning what is being done to execute the work and shall give the
Engineer every possible assistance in respect of the performance of his duty to see that the work is
executed in accordance with the contract and in respect of the performance and exercise of the duties and
powers specially imposed or conferred on him by the contract.
40 INSPECTION
.1 The Engineer will have the right to inspect all or any of the materials to be supplied for the works at their
place of origin, manufacture, or storage. The Contractor will arrange for the Engineer to have the right
of access to such parts of any supplier's premises as may be necessary for inspection.
.2 Any work done in the absence of the Engineer shall be opened for thorough examination and must be
rebuilt or replaced as directed, at the Contractor’s expense. No approval by an Engineer shall be taken
as, or construed into, an acceptance of defective or improper work or material, which must, in every case
be removed and properly replaced whenever discovered at any stage of the work.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 14
2017-11-30
41 CONTRACTOR’S SUPERINTENDENT
.1 The Contractor shall, during working hours, until the work has been completed, keep on the site of the
work a competent Superintendent who has authority to receive on behalf of the Contractor any order,
direction or other communication that may be given under the contract.
.2 The Contractor shall, upon the request of the Engineer, remove any Superintendent who, in the opinion
of the Engineer, is incompetent or has been conducting himself improperly and shall replace a
Superintendent so removed with another Superintendent.
42 DELIVERY OF MATERIALS
.1 The Contractor will arrange for early deliveries of materials necessary to the execution of the work and
will have them on hand well in advance of the time they are required.
43 LAYOUT
.1 The Contractor will lay out the work to establish lines, levels, and grades to indicate the location,
alignment and reference elevations for the work. The Contractor will execute the work in accordance
with any indication given by the Engineer.
44 SAFETY
.1 Before starting the work, the Contractor will inform the Workplace Health, Safety and Compensation
Commission of Nova Scotia of his intentions to begin the job. All work will be done in compliance with
the Occupational Health and Safety Act, Province of Nova Scotia, or subsequent provincial safety
legislation.
.2 All work will be performed in a safe and efficient manner to the complete satisfaction of both the
Engineer and the Safety Inspector.
.3 If, in the opinion of the Engineer, the Contractor is not conducting construction of the work with proper
safety precautions for workmen as prescribed by the Occupational Health and Safety Act then the
Engineer may, by giving notice in writing to the Contractor, stop the work.
.4 Where the Engineer has stopped the work the Contractor shall immediately cease his operations until the
Safety Code provisions have been complied with to the satisfaction of the Engineer.
.5 No extension of time or monetary allowances will be made to the Contractor for loss or delay arising
from any stoppages in work under this section.
45 FIRE LOSS
.1 If the work or any portion thereof is lost or destroyed and monies are paid to the Owner in respect of the
loss or damage under a policy of insurance maintained by the Contractor pursuant to Section 19 –
Insurance the monies will be held by the Owner for the purposes of the contract.
.2 The Owner may elect to retain absolutely the monies held under subsection .1 and, in such event, the
monies belong absolutely to the Owner and
(a) the Contractor is liable to the Owner in an amount equal to the amount by which the insurance
monies payable is less than the loss and damages suffered and sustained by the Owner, including
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 15
2017-11-30
costs associated with clearing and cleaning the site of the work, and
(b) there shall be a financial accounting between the Owner and the Contractor in respect of the
portion of the work which was lost or damaged and in respect of which monies have been
retained absolutely by the Owner and there shall be included in the financial accounting all
amounts paid or payable by the Owner under the contract to the Contractor, together with all
amounts paid or payable by the Contractor under the contract to the Owner and the Owner shall
pay to the Contractor any balance.
.3 Upon payment as required by subsection .2 by the Owner or the Contractor as the case may be, the
Owner and the Contractor are discharged from all rights and obligations under the Contract in respect of
the portion of the work which was lost or damaged and in respect of which monies have been retained
absolutely by the Owner as though such portion of the work had been fully completed and executed by
the Contractor in accordance with the contract.
.4 If an election is not made under subsection .2 the Contractor shall restore and replace the portion of the
work lost or damaged and the insurance monies shall be disbursed by the Owner to the Contractor in the
manner and subject to the terms and conditions governing monies payable under the contract to the
Contractor by the Owner, except that for this subsection "100%" shall be substituted in subsection .6 of
Section 4 of the Terms of Payment for "95%" and "85%".
46 CONTRACTOR’S RESPONSIBILITIES
.1 The Contractor shall guard or otherwise protect the work and shall protect the specifications, plans,
drawings, information, material and real property provided by the Owner to the Contractor against loss
or damage from any cause.
.2 The Contractor shall at his own expense do whatever is necessary to ensure that
(a) no person, property, right, easement or privilege is injured, damaged or infringed due to the
Contractor's activities under this contract;
(b) pedestrian and other traffic on any public or private road or waterway is not unduly impeded,
interrupted or endangered by the execution or existence of the work;
(c) fire hazards are eliminated and in the case of a fire in or about the work that it is promptly
extinguished;
(d) the health of all persons employed on the work is not endangered;
(e) adequate medical supervision of all persons employed on the work is maintained;
(f) adequate sanitation measures in respect of the work are taken;
.3 The Engineer may direct the Contractor to do such things and to construct such works which the
Engineer considers reasonable and necessary to ensure compliance with or to remedy a breach of
subsection .2. The Contractor shall at his own expense comply with the directions of the Engineer.
47 INTERPRETATIONS OF CONTRACT DOCUMENTS - CLAIMS ARISING
.1 If at any time before the work has been completed and the Engineer has issued his Final Certificate of
Completion, any question arises as to whether anything has been done as required by the contract or as to
what the Contractor is required by the contract to do, and without limiting the generality of the
foregoing, as to
(a) the meaning of anything in the Plans and Specifications;
(b) the meaning to be given to the Plans and Specifications in case of any error therein, an omission
therefrom, or an obscurity or discrepancy in the wording or intention;
(c) whether the quality or quantity of any material or workmanship meets the requirements of the
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 16
2017-11-30
contract;
(d) whether the plant, materials or workmen provided by the Contractor for executing the work and
carrying out the contract are adequate to ensure that the work will be executed in accordance
with the contract and that the contract will be carried out in accordance with its terms;
(e) what quantity of any kind of work has been completed by the Contractor; or
(f) the timing and scheduling of the various phases of the execution of the work, the question shall
be decided by the Engineer whose decision is final and binding.
.2 In matters arising other than under Section 30 - Adjustments Due to Site Conditions, Neglect or Delay,
the Contractor shall, where he intends to submit a claim for additional time or money arising out of the
construction of the work give written notice of his intention to claim
(a) in the case of changes or alterations of the work ordered by the Engineer, within 14 days of
receipt of the notice of change; and
(b) in the case of a dispute arising out of interpretation of the contract, within 30 days of the first
occurrence of the circumstances giving rise to the dispute.
.3 In matters arising other than under Section 30 - Adjustments Due to Site Conditions, Neglect or Delay,
the Contractor may submit a claim for additional time or money only on those matters covered by the
notice of intention to claim given under subsection .2 and such claim if not submitted within 30 days of
the occurrence of that portion of the work out of which the claim arises shall be barred.
.4 The Engineer shall within 30 days of receipt of notice of claim under this section render his decision in
writing to the Contractor.
.5 The Contractor shall construct the work in accordance with the decisions and directions of the Engineer
given under this section and in accordance with any consequential decisions and directions given by the
Engineer.
48 DEFECTS AND OMISSIONS
.1 Without restricting any warranty or guarantee implied or stipulated by law the Contractor shall at his
own expense rectify and make good any defect or fault or omission that appears in the work within
twelve months or within such additional period of time stipulated in the Specifications concerning
particular portions of the work from the date of the Engineer's Final Certificate of Completion, or where
an Interim Certificate of Completion has been issued, from the date of such Interim Certificate.
.2 If any defect, fault or omission appears in the work and the Engineer is of the opinion that it is one which
the Contractor, either under subsection .1 or under a warranty or guarantee implied or stipulated by law,
is obliged to remedy and make good the Engineer may direct the Contractor to remedy and make good
the defect, fault or omission by giving notice to the Contractor of the existence of the defect, fault or
omission and the notice shall specify the time within which the defect, fault, or omission is to be rectified
and made good.
.3 The Contractor shall rectify and make good the defect, fault or omission described in a notice given
pursuant to subsection .2 within the time specified in the notice.
49 OWNER’S RIGHT TO COMPLETE WORK
.1 Where the Contractor has failed to comply with any decision or direction given by the Engineer, the
Engineer may employ such methods as he may deem expedient to do that which the Contractor failed to
do.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 17
2017-11-30
.2 The Contractor shall on demand pay to the Owner all costs, expenses and damage incurred or sustained
by the Owner due to the Contractor's non-compliance with any decision or direction given by the
Engineer and by the action taken by the Engineer pursuant to sub-section .1.
50 CONTRACTOR RIGHTS ON DISPUTED DECISION
.1 If the Contractor has, within ten days of communication to him by the Engineer of any decision or
direction of the Engineer, given notice to the Engineer in writing disputing such decision or direction and
stating the ground or grounds which form the basis of such dispute, the Owner shall pay to the
Contractor the cost of the additional labour, materials and plant necessarily involved in carrying out the
decision or direction beyond what the Contract, correctly understood and interpreted, would have
required the Contractor to do.
51 CLEAN UP
.1 Waste material and rubbish shall not be allowed to accumulate and shall be removed from site daily or at
regular intervals as agreed upon by the Engineer. Waste material and rubbish shall not be buried on site
and shall be properly disposed of by the Contractor.
.2 Upon completion of the job all surplus construction materials, all tools, equipment, temporary structures,
etc. will be removed from the site by the Contractor to the satisfaction of and in accordance with any
directions of the Engineer. All dirt, rubbish, trash, etc. becomes the property of the Contractor and must
be removed from the site.
.3 The site as much as practicable must be kept in a clean and orderly appearance and free from excess
material always. The Contractor must clean up the site periodically as work progresses to the complete
satisfaction of the Engineer.
52 PUBLIC CONVENIENCE
.1 No material or other obstruction shall be placed within 10 metres of a fire hydrant, which must be always
readily accessible to the Fire Department. During the progress of the work the convenience of the public
and the residents along the street must be provided for as far as practical.
53 RELATIONS WITH OTHER CONTRACTORS
.1 Wherever work being done by the Owner's forces or by other contractors is contiguous to work covered
by this Contract, the respective rights of the various interests involved shall be established by the
Engineer to secure the completion of the various portions of the work in general harmony.
.2 If any part of the Contractor's work depends for proper execution or results upon the work of any other
contractor, the Contractor shall inspect and promptly report to the Engineer any defects in such work that
render it unsuitable for such proper execution and results and his failure to inspect and report shall
constitute an acceptance of the other Contractor's work as fit and proper for the reception of his work
except as to defects which may develop in the other contractor's work after the execution of this work.
.3 To insure the proper execution of his subsequent work, the Contractor shall at once report to the
Engineer any discrepancy between the executed work and the drawings.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
GENERAL CONDITIONS ‘B’ Section 00 30 00
Page 18
2017-11-30
54 CO-OPERATION
.1 It is to be noted that other work may be in progress under various contracts within the working area of
this contract. The Contractor will, to the satisfaction of the Engineer, allow the other contractors
reasonable access to the work and will co-operate with them in the carrying out of their duties and
obligations.
.2 No claim will be entertained for any inconvenience or any slowdown in work due to these other
Contracts.
55 CONTRACTOR'S JOB OFFICE
.1 The Contractor shall provide a temporary weather tight job office for his own use complete with
facilities for filing drawings, specifications, correspondence, purchase orders and such other
appurtenances as are necessary for the proper conduct of the work and shall remove same upon
completion of the work. Job office shall be located in an area approved by the Engineer.
.2 The Owner may permit the Contractor to locate his job office in a designated location within the work
area.
.3 The Contractor shall always during construction of the work maintain in the job office required by
subsection .1 a complete and current set of plans, specifications and change orders for this contract.
56 EXAMINATION OF SITE
.1 It is the responsibility of the Contractor to become familiar with and understand the nature and extent of
the work to be executed, the nature of the soil, surface water drainage, the general form of the surface of
the ground, and generally of all matters which can in any way influence the tender, in so far as possible.
Information on any matter derived from the plans and specifications or obtained from the Engineer or
from test pits, etc. shall not in any way relieve the Contractor from risk or from fulfilling the terms of the
Contract.
.2 All details and incidental items not particularly mentioned in the specifications but which, whether in
temporary or permanent works, must evidently be required by the nature of the work shall be considered
included in the contract. On submission of the bid, it shall be understood that this has been done and
provision for all risks, incidental items and contingencies are included in the contract price.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS TENDER NO. 17-353541B
INSTRUCTIONS TO
TENDERERS ‘C’
Section 00 40 00
Page 1
2017-11-30
1.0 General
1.1 CROWN CONSTRUCTION CONTRACTS ACT
The "Regulations" of the "Crown Construction Contracts Act" of the Province of Nova Scotia
shall apply to this contract.
1.2 DISCRIMINATION and HIRING PRACTICES
In the employment of persons on the project, there shall be no discrimination because of race,
sex, marital status, national origin, colour, religion or political affiliation.
1.3 MATERIAL ORIGIN
Canadian materials shall be used to the full extent it is procedure and consistent with proper
economy and the expeditious performance of the project.
1.4 DEFINITIONS
Unless the context requires otherwise the following definitions shall apply throughout the
documents forming the contract.
1. The "Owner" means: Town of Annapolis Royal
2. The "Engineer-Architect" or “Consultant” means: HATCH
Wherever reference is made in the documents to "the Department," "the Minister of...." or "Her
Majesty the Queen," substitutes: "The Owner."
1.5 UNIT OF MEASUREMENT
The Imperial System of Units will be used.
All materials used shall be manufactured in the imperial measure system unless prior approval of
the Engineer is received. All gauges, scales and equipment nameplates shall be inscribed in
imperial units only.
All imperial equipment, piping or other manufactured products supplied under this contract must
mate with connecting non-metric equipment, piping or other manufactured products, the
Contractor shall assure himself that mating with adjoining materials is feasible and the special
connecting pieces required for such mating shall be provided by the Contractor at his expense.
1.6 DISCREPANCIES
Tenderers finding discrepancies or omissions in the specifications, drawings or other contract
documents or having any doubt as to the meaning or intent of any part thereof will notify the
engineer immediately who will send written instructions or explanations to all tenderers. Neither
the Owner nor the Engineer will be responsible for oral instructions. Addenda, bulletins or
corrections issued during the tender period or time of bidding, will be covered in the tender and
will become a part of the contract documents.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS TENDER NO. 17-353541B
INSTRUCTIONS TO
TENDERERS ‘C’
Section 00 40 00
Page 2
2017-11-30
1.7 CONTRACT FORMAT
It is a condition of the acceptance of the contract whether so expressed in the acceptance or not
that the Contractor will, within fourteen (14) days of notification of acceptance, enter a contract
with the Owner, of the type and format listed in the Articles of Agreement and this Document.
1.8 PROJECT COMMUNICATION
The Contractor is advised that all communication with the media and or public related to this
project shall be coordinated through the Project Manager. The Contractor is not permitted to
speak directly with the media or the public regarding any project details, announcements or other
project related news.
2.0 Project Information
2.1 CONTACTS
Questions shall be directed in writing to the following;
Hatch Corporation
Suite 1009, 1809 Barrington Street
Halifax, Nova Scotia, B3J 3K8
(902) 420-6492
Attn: Michael Brown
Email: [email protected]
2.2 EXAMINATION OF THE SITE
The contractor shall visit the site before submitting his Tender to thoroughly acquaint himself
with all local conditions under which he will be called upon to carry out the work coming under
this Contract.
A bidders site visit is scheduled for January 25, 2018 @ 10:00am.
2.3 APPROVAL OF PRODUCTS
Bidders are advised that it is their responsibility to ensure to their satisfaction that all trades and
suppliers are bidding in conformance with the terms of the contract documents. The successful
bidder will be held to furnish under his tender, all work/products as specified or approved through
the prior approvals process. Requests for prior approvals will be evaluated by the Consultant on
or before February 7, 2018, with a list of acceptable approvals being issued via Addendum.
2.4 CASH ALLOWANCE
1) Not applicable.
3.0 Submission Requirements
3.1 CORPORATE AUTHORITY
The successful bidder, if an incorporated company, must attach to the signed contract an affidavit
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS TENDER NO. 17-353541B
INSTRUCTIONS TO
TENDERERS ‘C’
Section 00 40 00
Page 3
2017-11-30
indicating the authority under which the corporate seal was affixed and the authority under which
the corporate officers signed the contract.
3.2 TENDER SUBMISSION AND INQUIRIES
Sealed Tenders will be received at the time, date and location as stated in the Tender
Advertisement. The Bid Security Deposit will be in the form and amount as stated in the Tender
Advertisement. Tenders must be in accordance with the Crown Construction Contracts Act and
in accordance with the Tender Advertisement.
The tender envelopes will have on the face and clearly marked as to the contents the name of the
contractor submitting the Tender and will be identified as:
Tender For:
Tender No. 17-353541B
The Academy Project
Library Renovations
Annapolis Royal, Annapolis County, Nova Scotia
and will be addressed as follows:
Attn: Gregory Barr, CAO
Town of Annapolis Royal
285 St. George Street
Annapolis Royal, NS
B0S 1A0
All tenders must be submitted on the form supplied for this purpose. No tender or amendment of
a tender will be considered if received at a date or time later than that specified in the tender
letter. Prices must be filled in for each item called for in the Tender Form.
3.3 BID DEPOSIT
It will be a condition of all tenderers that there be deposited with each tender a certified cheque
or bid bond for an amount of 10% of bid price issued by a surety company licensed to do
business in Nova Scotia.
3.4 CONTRACT SECURITY
It is a condition of the acceptance of the contract whether so expressed in the acceptance or not
that the Contractor will, within 8 days from notification of acceptance, and as a guarantee of the
due fulfilment of all provisions of the Contract, furnish the Owner with a labour and material
payment bond and performance bond each in the amount of 50% of the value of the awarded
price. These bonds shall be issued by a surety company licensed to do business in Nova Scotia.
Such bonds shall also be satisfactory to Town of Annapolis Royal as to form and issuer.
3.5 INSURANCE
Referring to the Insurance Schedule "E" bound herein the insurance shall be issued in the joint
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS TENDER NO. 17-353541B
INSTRUCTIONS TO
TENDERERS ‘C’
Section 00 40 00
Page 4
2017-11-30
names of the Owner, Contractor and Engineer.
3.6 PROPERLY SIGNED
All indications to properly sign shall mean the signing, dating and sealing of all documents,
appendices and bonds by authorized company officers.
4.0 Tendering Procedures
4.1 OPENING OF TENDERS
The public opening of tenders will be held immediately following the tender closing. THE
LOWEST/HIGHEST OF ANY TENDER WILL NOT NECESSARILY BE ACCEPTED.
4.2 TENDERING PROCEDURES
The closing time for receipt of tenders will be that stated in the tender advertisement. The tender
advertisement will indicate the initial location of the box for receipt of tenders from which the
box will be removed to the tender opening room 30 minutes prior to closing time. At the time
specified for the opening an announcement will be made that no further tenders will be accepted.
Responsibility for deposit of tenders in the tender box is that of the tenderer. Town of Annapolis
Royal and Hatch accept no responsibility for tenders that have been mailed or left for deposit in
the box. Tenders not in the box will not be considered.
The tender opening committee shall reject tenders for the following reasons:
(a) Absence of, or an insufficient or incorrect, bid bond or security deposit.
(b) Absence of a letter from a Nova Scotia resident agent of an insurance company
licensed to do business in the Province stating that the bid bond, where required,
has been negotiated for, procured from and the premium paid to that agent.
(c) Tender not signed.
(d) Bid price, lump sum, not written in words.
(e) Absence of the words "dollars" and, where applicable, "cents" set out in the
written item bid.
(f) Any form of qualification or unsolicited alternative of the bid.
(g) Does not contain a bid for each item required to be bid.
(h) Bidding an item not included.
(i) Tender envelopes that do not have bidders name and contract identification on
face of envelope.
(j) Absence of a signed copy, in the tender envelope, of any addenda issued for the
contract.
(k) The submission of more than one tender by the same tenderer, in which case all
tenders submitted by that tenderer shall be rejected.
(l) Submission of a tender by a tenderer not listed as having received tender
documents. The onus is on the tenderer to ascertain if he is listed as having
received tender documents.
(m) A change in the written bid on a tender form that has not been initialled by the
bidder.
(n) The absence of any documents or non-compliance with any special provisions of
the specifications.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS TENDER NO. 17-353541B
INSTRUCTIONS TO
TENDERERS ‘C’
Section 00 40 00
Page 5
2017-11-30
(o) Any deviation from accepted tendering practices that constitute sufficient reason
for rejection of the tender.
(p) Submission of a tender in an unsealed envelope.
Explanation
Items 13 (c) and 13 (d)
Tender forms will be arranged so that units making up totals may be written out. The
tenderer must write out in words unit prices or lump sum figures which are used in
making up the total tender price. The total tender price need not be written out. Written
figures will be used in mathematically checking extensions and totals and the
mathematically correct total from the written units and lump sums will be the tender
price.
Item 13 (i)
Tender documents can be obtained from the address given in the tender advertisement on
payment of the specified deposit. Bids will not be accepted from contractors who
obtained tender forms by other than this method.
4.3 TENDERS WILL BE ACCEPTED EVEN IN THE EVENT THE FOLLOWING ERRORS ARE
PRESENT
Conflict between the written bid and the numerical bid. In all cases the total bid is corrected to
reflect the written bid.
4.4 GENERAL TENDERING PROCEDURES
Public tenders will be opened in a room where the public as well as those submitting tenders are
welcome. Tenders will be opened, checked for content and the name and amount of the tender
announced and/or posted on the board. Following this:
(a) The mathematical calculations of all tenders are checked. Corrections in bid
totals are made during the public opening.
(b) Tenders that are rejected as incomplete will be reviewed with the representative
of Town of Annapolis Royal during the period when the mathematics of the other
tenders is being checked. If the presiding officer is shown to be in error, the
tender will be accepted and the bid price announced. However, if a tender is
rejected and a representative of the company is not present at the opening, no
later consideration will be given to accepting the tender.
(c) The procedures outlined in this specification cover tender opening procedures.
The tenders accepted at the public opening in no way commit the Town of
Annapolis Royal to accept the low or any other bid submitted.
4.5 OWNERS RIGHTS
.1 The Owner reserves the right to increase or decrease the extent of the work or to vary in
any way the work herein is contracted for. In that regard the Contractor shall receive no compensation for any work deleted. Payment for the work completed shall be in accordance with the General Conditions.
.2 The Owner reserves the right, if the successful bidder fails to comply with the conditions
as listed, to cancel this contract and award it to another bidder without penalty or action
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS TENDER NO. 17-353541B
INSTRUCTIONS TO
TENDERERS ‘C’
Section 00 40 00
Page 6
2017-11-30
against the Owner. In this event, the Owner shall cash or negotiate the bid deposit and retain a sum equal to the difference between the value of their tender and the value of the next lowest tender and shall return an amount equal to the surplus, if any, to the tenderer whose bid deposit was so forfeited; or notify the surety company where a bid bond was submitted.
.3 The Owner reserves the right to award in its best interest. As such, tenders with the
lowest price, or any tender need not necessarily be accepted. Or, the tender may be awarded in whole or in part with out penalty.
.4 The Owner reserves the right to reject any of the named sub-contractors without penalty.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS TENDER NO. 17-353541B
INSURANCE SCHEDULE ‘E’ Section 00 65 00
Page 1
2017-11-30
1. The Contractor shall at his own expense, procure and maintain insurance policies which shall
protect the Contractor from claims for bodily injury, including death, and from claims for
property damage which may arise from the performance of this contract. Such Insurance shall be
for a minimum amount of $2,000,000 Combined Inclusive Limit to adequately protect the
Contractor from any claim or claims that may arise during the performance of this Contract: and
the Contractor shall, at the request of the Owner, file with the Owner a policy, one certified copy
of such Insurance which shall be for an amount and on a form acceptable to the Owner.
2. The Owner further reserves the right to require the Contractor to insure his property, plant and
equipment, for such amounts as the Owner deems adequate, and to require the Contractor to file
with the Owner evidence of such insurance in a format acceptable to the Owner.
3. The Contractor shall pay for and maintain Builders all Risks Insurance during the term of the
Contract. Such Insurance shall incorporate at least, the following features:
- The Owner, Her Majesty the Queen in the Right of the Province of Nova Scotia, the
Contractor and all sub-contractors as named assured, and incorporating the insurer's
Waiver of Subrogation against any of such names assureds.
- Coverage for the full value of the project.
- A debris removal clause.
- Coverage may exclude cost of making good faulty workmanship, construction or design,
but this exclusion shall not apply to damage resulting from such faulty workmanship,
construction or design.
- Fire Insurance to a total of no less than eighty percent (80%) of the total value of the
work done and material delivered to the site, payable to the Owner and the Contractor as
their respective interests may appear.
- Automatic reinstatement clause.
- Remain in force until the issue by the Engineer of the Final Payment Certificate except
that Completed Operations Liability shall remain in force for the duration of the
Guarantee period.
- A deductible of no more than $1,000. The cost of this deductible shall be borne by the
Contractor.
- Loss payable shall be made to the Owner and the Contractor as their interests may
appear.
4. All insurances required to be provided and maintained by the Contractor shall be negotiated for,
procured from, and the premium paid to a resident agent of an Insurance Company licensed to do
business in the Province of Nova Scotia.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS
TENDER NO. 17-353541B
TENDER FOR ‘F’ Section 00 70 00
Page 1
2017-11-30
TO:
Attn: Gregory Barr, CAO
Town of Annapolis Royal
285 St. George Street
Annapolis Royal, NS
B0S 1A0
Submitted By
Address
Telephone #
TENDER PRICE
I/We the undersigned, hereby offer and agree to furnish all and every kind of labour, tools, implements,
machinery, plant service and materials that may be required to execute and complete all work embraced
in the construction of the above-named project and in accordance with the plans, Tender Form and
Technical Specifications and such revisions, further details and special plans as may be furnished from
time to time during the progress of the work.
I/We have examined the plans, specifications and site and have ascertained all necessary particulars about
the work, and upon acceptance of this tender, are prepared to enter into a contract to construct the said
work or works included in the contract, and every part thereof in strict accordance with the contract
documents for the stipulated lump sum of:
(WRITE OUT IN FULL, AMOUNT EXCLUDING HST)
(FIGURES)______________Dollars___________Cents
I/We include herewith a Bid Bond or certified cheque in the amount of 10% of the total tender price
including HST.
I/We have examined Addenda No.______to No._______inclusive, and our tender price includes all
labour, materials, etc., as called for and/or implied by said addenda.
A signed copy of each Addendum covering letter must be included with Tender submission.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS
TENDER NO. 17-353541B
TENDER FOR ‘F’ Section 00 70 00
Page 2
2017-11-30
SUB-CONTRACTORS
The following is to be submitted by the selected bidder. List of all major sub-trades per discipline
including own forces (where applicable).
TRADE
SUB-CONTRACTOR
TENDER PRICE
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS
TENDER NO. 17-353541B
TENDER FOR ‘F’ Section 00 70 00
Page 3
2017-11-30
REFERENCES OF WORKS OF A SIMILAR NATURE COMPLETED BY THE TENDERER
JOB
YEAR
VALUE
OWNER
FOREMAN/SUPERINTENDENT
It is hereby agreed that the following person(s) will be employed under this contract until completion and
are subject to approval.
IF ONLY ONE PERSON OF AUTHORITY WILL BE RESPONSIBLE FOR THIS CONTRACT THE
NAME MUST BE STATED IN THE APPROPRIATE PLACE
FOREMAN
QUALIFICATIONS & EXPERIENCE
SECURITY DEPOSIT
Tenders must be submitted on this Tender Form and Schedule and each tender must be "Properly Signed"
by the Tenderer and accompanied by Bid Bond in the amount of ten percent (10%) of the tendered price
or a certified cheque in the amount of ten percent (10%) of the tendered price as a guarantee that the
tenderer, if accepted, will execute the Contract, in full as specified.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT LIBRARY RENOVATIONS
TENDER NO. 17-353541B
TENDER FOR ‘F’ Section 00 70 00
Page 4
2017-11-30
OFFER
This offer is irrevocable for sixty (60) working days from the date on which the tenders are opened and if
accepted, I (we) undertake to enter into contract for the execution of the work and to complete the work in
accordance with our submitted project schedule.
The undersigned declares that this tender is made without any connection or collusion with any persons
making any tender or estimate for the same work and no person employed by or holding office under the
Owner has any interest in this tender or contract or in supplies for work to which it relates or in any
portion of the profits thereof.
DATED AT
THIS DAY OF 20 .
NAME OF
FIRM
ADDRESS
SIGNATURE SIGNATURE OF
OF WITNESS
REPRESENTATIVE
NAME NAME
(PRINTED) (PRINTED)
TITLE
(PRINTED)
SIGNATURE OF SIGNATURE OF
WITNESS REPRESENTATIVE
NAME NAME
(PRINTED) (PRINTED
TITLE
(PRINTED)
NOTE
If the Contractor is an incorporated company, the Tenderer will be signed by the President (or other
Officer duly authorized to sign), and the secretary of the company, and the seal affixed. If the Contractor
is not an incorporated company, the tender will be signed by each individual member of the firm and his
address given. There will be a witness to every execution.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
INDEX Section 00 01 10
Page 1
2017-11-30
SPECIFICATION INDEX
Section Title Pages
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 Summary of Work 4
01 14 00 Work Restrictions 1
01 31 19 Project Meetings 2
01 32 16 Construction Schedules 2
01 33 00 Submittal Procedures 3
01 35 29.06 Health and Safety Requirements 3
01 35 35 Fire Safety Requirements 3
01 45 00 Quality Control 2
01 51 00 Temporary Utilities 1
01 61 00 Common Product Requirements 3
01 73 00 Execution 2
01 74 11 Cleaning 2
01 74 21 Construction/Demolition Waste Management and Disposal 2
01 77 00 Closeout Procedures 1
01 78 00 Closeout Submittals 5
DRAWING INDEX
Dwg. # Title
COVER SHEET
I-002 Cover Sheet
ARCHITECTURAL DRAWINGS
A-100 Demolition Plan & Proposed Floor Plan
A-101 Proposed Floor Plan & Reflected Ceiling Plan
A-102 Flooring Plan & Finish Schedule
A-103 Details
A-104 Details Cont.
A-105 Millwork
A-106 Washrooms
A-107 Schedules
A-108 Specifications
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
INDEX Section 00 01 10
Page 2
2017-11-30
MECHANICAL DRAWINGS
M-001 Basement Plumbing Floor Plans, Details & Legend
M-002 Basement Plumbing Schedules
M-003 Basement Heating Floor Plan, Schedules & Details
M-004 Basement HVAC Floor Plan, Schedules, Details & Legend
M-005 Basement Fire Protection Floor Plan, Details & Legend
M-010 Mechanical Specifications – Sheet 1
M-011 Mechanical Specifications – Sheet 2
M-012 Mechanical Specifications – Sheet 3
ELECTRICAL DRAWINGS
E-001 Existing Basement Lighting, Power, Communication, Fire Alarm & Legend
E-002 New Basement Lighting, Power, Communication, Fire Alarm & Legend
E-003 Electrical Details & Schedules
E-010 Electrical Specifications – Sheet 1
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
SUMMARY OF WORK Section 01 11 00
Page 1
2017-11-30
Part 1 General
1.1 WORK COVERED BY CONTRACT DOCUMENTS
.1 Work of this Contract comprises general renovation and construction of the lower level
of the gymnasium wing of the Academy, located at 590 St. George Street, Annapolis
Royal, NS; and further identified as The Academy Project – Library Renovations.
.2 The scope of work includes all work noted in the documents and the following summary;
.1 Total renovation of the lower level of the gymnasium wing of the Academy for
the creation of community based operational spaces.
.2 Reinstatement of the existing Gymnasium wing AHU’s. This includes the
gymnasium AHU, the lower level AHU and the general exhaust unit. With the
removal of the controls compressor during the condominium project, the dampers
on the units no longer operate. This will involve replacement of the damper
actuators and installation of a AHU controller on the lower level and one on the
gymnasium level. The existing control system is Delta, supported by Controls &
Equipment.
1.2 CONTRACT METHOD
.1 Construct Work under stipulated price contract.
1.3 WORK BY OTHERS
.1 Work under this contract may begin prior to completion of the “Boiler Package Contract”
in the basement area. If the basement renovation contract commences prior to completion
of this work, co-operate with other Contractors in carrying out their respective works and
carry out instructions from Consultant.
1.4 WORK SEQUENCE
.1 Construct Work in stages to accommodate Owner's continued use of premises during
construction.
.2 Co-ordinate Progress Schedule and co-ordinate with Owner Occupancy during
construction.
.3 Maintain fire access/control.
1.5 CONTRACTOR USE OF PREMISES
.1 Limit use of premises for Work, for storage, for access, to allow:
.1 Owner occupancy.
.2 Work by other contractors.
.3 Public usage.
.2 Co-ordinate use of premises under direction of Owner.
.3 Obtain and pay for use of additional storage or work areas needed for operations under
this Contract.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
SUMMARY OF WORK Section 01 11 00
Page 2
2017-11-30
.4 Remove or alter existing work to prevent injury or damage to portions of existing work
which remain.
.5 Repair or replace portions of existing work which have been altered during construction
operations to match existing or adjoining work, as directed by Consultant.
.6 At completion of operations condition of existing work: equal to or better than that which
existed before new work started.
1.6 OWNER OCCUPANCY
.1 Owner will occupy premises during entire construction period for execution of normal
operations.
.2 Co-operate with Owner in scheduling operations to minimize conflict and to facilitate
Owner usage.
1.7 OWNER FURNISHED ITEMS (LIBRARY EQUIPMENT)
.1 Owner Responsibilities:
.1 Arrange for delivery of shop drawings, product data, samples, manufacturer's
instructions, and certificates to Contractor.
.2 Deliver supplier's bill of materials to Contractor.
.3 Arrange and pay for delivery to site.
.4 Inspect deliveries jointly with Contractor.
.5 Submit claims for transportation damage.
.6 Arrange for replacement of damaged, defective or missing items.
.2 Contractor Responsibilities:
.1 Designate submittals and delivery date for each product in progress schedule.
.2 Review shop drawings, product data, samples, and other submittals. Submit to
Consultant notification of observed discrepancies or problems anticipated due to
non-conformance with Contract Documents.
.3 Receive and unload products at site.
.4 Inspect deliveries jointly with Owner; record shortages, and damaged or
defective items.
.5 Handle products at site, including uncrating and storage.
.6 Protect products from damage, and from exposure to elements.
.7 Assemble, install, connect, adjust, and finish products.
.8 Repair or replace items damaged by Contractor or subcontractor on site (under
his control).
1.8 ALTERATIONS, ADDITIONS OR REPAIRS TO EXISTING BUILDING
.1 Execute work with least possible interference or disturbance to building operations and
normal use of premises. Arrange with Consultant to facilitate execution of work.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
SUMMARY OF WORK Section 01 11 00
Page 3
2017-11-30
1.9 EXISTING SERVICES
.1 Notify, Consultant and utility companies of intended interruption of services and obtain
required permission.
.2 Where Work involves breaking into or connecting to existing services, give Consultant
48 hours notice for necessary interruption of mechanical or electrical service throughout
course of work. Minimize duration of interruptions. Carry out work at times as directed
by governing authorities with minimum disturbance to operations.
.3 Establish location and extent of service lines in area of work before starting Work.
.4 Submit schedule to and obtain approval from Consultant for any shut-down or closure of
active service or facility including power and communications services. Adhere to
approved schedule and provide notice to affected parties.
.5 Provide temporary services when directed by Consultant to maintain critical building and
tenant systems.
.6 Where unknown services are encountered, immediately advise Consultant and confirm
findings in writing.
.7 Protect, relocate or maintain existing active services. When inactive services are
encountered, cap off in manner approved by authorities having jurisdiction.
.8 Record locations of maintained, re-routed and abandoned service lines.
1.10 DOCUMENTS REQUIRED
.1 Maintain at job site, one copy each document as follows:
.1 Contract Drawings.
.2 Specifications.
.3 Addenda.
.4 Reviewed Shop Drawings.
.5 List of Outstanding Shop Drawings.
.6 Change Orders.
.7 Other Modifications to Contract.
.8 Field Test Reports.
.9 Copy of Approved Work Schedule.
.10 Health and Safety Plan and Other Safety Related Documents.
.11 Other documents as specified.
Part 2 Products
2.1 NOT USED
.1 Not used.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
SUMMARY OF WORK Section 01 11 00
Page 4
2017-11-30
Part 3 Execution
3.1 NOT USED
.1 Not used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
WORK RESTRICTIONS Section 01 14 00
Page 1
2017-11-30
Part 1 General
1.1 ACCESS AND EGRESS
.1 Design, construct and maintain temporary "access to" and "egress from" work areas,
including stairs, runways, ramps or ladders, independent of finished surfaces and in
accordance with relevant municipal, provincial and other regulations.
1.2 USE OF SITE AND FACILITIES
.1 Execute work with least possible interference or disturbance to normal use of premises.
Maintain existing services to building and provide for personnel and vehicle access.
.2 Owner will assign sanitary facilities for use by Contractor's personnel. Keep facilities
clean.
.3 Closures: protect work temporarily until permanent enclosures are completed.
1.3 ALTERATIONS, ADDITIONS OR REPAIRS TO EXISTING BUILDING
.1 Execute work with least possible interference or disturbance to building operations.
1.4 SPECIAL REQUIREMENTS
.1 Ensure Contractor's personnel employed on site become familiar with and obey
regulations including safety, fire, traffic and security regulations.
.2 Keep within limits of work and avenues of ingress and egress.
.3 Ingress and egress of Contractor vehicles at site is limited.
1.5 BUILDING SMOKING ENVIRONMENT
.1 Comply with smoking restrictions. Smoking is not permitted.
Part 2 Products
2.1 NOT USED
.1 Not Used.
Part 3 Execution
3.1 NOT USED
.1 Not Used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
PROJECT MEETINGS Section 01 31 19
Page 1
2017-11-30
Part 1 General
1.1 ADMINISTRATIVE
.1 Schedule and administer bi-weekly project meetings throughout the progress of the work.
.2 Distribute electronic notice of each meeting four days in advance of meeting date to
Owner and Consultant.
.3 Preside at meetings.
.4 Record the meeting minutes. Include significant proceedings and decisions. Identify
actions by parties.
.5 Reproduce and distribute copies of minutes within three days after meetings and transmit
to meeting participants and, affected parties not in attendance.
1.2 PRECONSTRUCTION MEETING
.1 7 days after award of Contract, request a meeting of parties in contract to discuss and
resolve administrative procedures and responsibilities.
.2 Consultant, Contractor, major Subcontractors, and supervisors will be in attendance.
.3 Agenda to include:
.1 Appointment of official representative of participants in the Work.
.2 Schedule of Work.
.3 Schedule of submission of shop drawings.
.4 Proposed changes, change orders, procedures, approvals required, mark-up
percentages permitted, time extensions, overtime, administrative requirements.
.5 Owner provided products.
.6 Monthly progress claims, administrative procedures, photographs, hold backs.
.7 Appointment of inspection and testing agencies or firms.
.8 Insurances, transcript of policies.
1.3 PROGRESS MEETINGS
.1 During course of Work schedule progress meetings bi-weekly.
.2 Contractor, major Subcontractors involved in Work, Consultant and Owner are to be in
attendance.
.3 Record minutes of meetings and circulate to attending parties and affected parties not in
attendance within 3 days after meeting.
.4 Agenda to include the following:
.1 Review, approval of minutes of previous meeting.
.2 Review of Work progress since previous meeting.
.3 Field observations, problems, conflicts.
.4 Problems which impede construction schedule.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
PROJECT MEETINGS Section 01 31 19
Page 2
2017-11-30
.5 Review of off-site fabrication delivery schedules.
.6 Corrective measures and procedures to regain projected schedule.
.7 Revision to construction schedule.
.8 Review submittal schedules: expedite as required.
.9 Maintenance of quality standards.
.10 Review proposed changes for affect on construction schedule and on completion
date.
.11 Other business.
Part 2 Products
2.1 NOT USED
.1 Not Used.
Part 3 Execution
3.1 NOT USED
.1 Not Used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
CONSTRUCTION
SCHEDULE
Section 01 32 16
Page 1
2017-11-30
Part 1 General
1.1 DEFINITIONS
.1 Activity: element of Work performed during course of Project.
.2 Bar Chart: display of schedule-related information. In typical bar chart, activities or
other Project elements are listed down left side of chart, dates are shown across top, and
activity durations are shown as date-placed horizontal bars.
.3 Baseline: original approved plan (for project, work package, or activity), plus or minus
approved scope changes.
.4 Construction Work Week: Monday to Friday inclusive, will provide five-day work week.
.5 Duration: number of work periods (not including holidays or other nonworking periods).
.6 Master Plan: summary-level schedule that identifies major activities and key milestones.
.7 Milestone: significant event in project, usually completion of major deliverable.
.8 Project Schedule: planned dates for performing activities and the planned dates for
meeting milestones.
1.2 REQUIREMENTS
.1 Ensure Schedule is practical and remains within specified Contract duration.
.2 Ensure that it is understood that Award of Contract or time of beginning, rate of progress,
Interim Certificate and Final Certificate as defined times of completion are of essence of
this contract.
1.3 ACTION AND INFORMATIONAL SUBMITTALS
.1 Submit Schedule to Consultant within 5 working days after Award of Contract.
1.4 PROJECT SCHEDULE
.1 Ensure detailed Project Schedule includes as minimum milestone and activity types as
follows:
.1 Award.
.2 Shop Drawings, Samples.
.3 Permits.
.4 Interior Architecture (Walls, Floors and Ceiling).
.5 Plumbing.
.6 Lighting.
.7 Electrical.
.8 Piping.
.9 Controls.
.10 Heating, Ventilating, and Air Conditioning.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
CONSTRUCTION
SCHEDULE
Section 01 32 16
Page 2
2017-11-30
.11 Millwork.
.12 Fire Systems.
.13 Testing and Commissioning.
.14 Supplied equipment long delivery items.
.15 Engineer supplied equipment required dates.
1.5 PROJECT SCHEDULE REPORTING
.1 Update Project Schedule on weekly basis reflecting activity changes and completions, as
well as activities in progress.
1.6 PROJECT MEETINGS
.1 Discuss Project Schedule at regular site meetings, identify activities that are behind
schedule and provide measures to regain slippage.
Part 2 Products
2.1 NOT USED
.1 Not used.
Part 3 Execution
3.1 NOT USED
.1 Not used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
SUBMITTAL PROCEDURES Section 01 33 00
Page 1
2017-11-30
Part 1 General
1.1 ADMINISTRATIVE
.1 Submit to Consultant shop drawings and product data for review. The Architect/Engineer
may review shop drawings and product data with the contractor on site during the
progress meetings to expedite and simplify the process.
.2 Do not proceed with Work affected by submittal until review is complete.
.3 Present shop drawings, product data, in Imperial units.
.4 Verify field measurements and affected adjacent Work are co-ordinated.
.5 Contractor's responsibility for errors and omissions in submission is not relieved by
Consultant review of submittals.
.6 Contractor's responsibility for deviations in submission from requirements of Contract
Documents is not relieved by Consultant review.
.7 Keep one reviewed copy of each submission on site.
1.2 SHOP DRAWINGS AND PRODUCT DATA
.1 The term "shop drawings" means drawings, diagrams, illustrations, schedules,
performance charts, brochures and other data which are to be provided by Contractor to
illustrate details of a portion of Work.
.2 Indicate materials, methods of construction and attachment or anchorage, erection
diagrams, connections, explanatory notes and other information necessary for completion
of Work.
.3 Adjustments made on shop drawings by Consultant are not intended to change Contract
Price. If adjustments affect value of Work, state such in writing to Consultant prior to
proceeding with Work.
.4 Make changes in shop drawings as Consultant may require, consistent with Contract
Documents.
.5 Submissions include:
.1 Date and revision dates.
.2 Project title and number.
.3 Name and address of:
.1 Subcontractor.
.2 Supplier.
.3 Manufacturer.
.4 Contractor's stamp, signed by Contractor's authorized representative certifying
approval of submissions, verification of field measurements and compliance with
Contract Documents.
.5 Details of appropriate portions of Work as applicable:
.1 Fabrication.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
SUBMITTAL PROCEDURES Section 01 33 00
Page 2
2017-11-30
.2 Layout, showing dimensions, including identified field dimensions, and
clearances.
.3 Setting or erection details.
.4 Capacities.
.5 Performance characteristics.
.6 Standards.
.7 Operating weight.
.8 Wiring diagrams.
.9 Single line and schematic diagrams.
.10 Relationship to adjacent work.
.6 Submit electronic copy of shop drawings for each requirement requested in Tender
package and as Consultant may reasonably request.
.7 Submit electronic copies of test reports for requirements requested in specification
Sections and as requested by Consultant.
.8 Submit electronic copies of certificates for requirements requested in specification
Sections and as requested by Consultant.
.9 Submit electronic copies of Manufacturer's Field Reports for requirements requested in
specification Sections and as requested by Consultant.
.10 Submit electronic copies of Operation and Maintenance Data for requirements requested
in specification Sections and as requested by Consultant.
1.3 SAMPLES
.1 Submit for review samples as requested. Label samples with origin and intended use. The
Architect/Engineer may review samples with the contractor on site during the progress
meetings to expedite and simplify the process.
.2 Where colour, pattern or texture is criterion, submit full range of samples.
.3 Adjustments made on samples by Consultant are not intended to change Contract Price. If
adjustments affect value of Work, state such in writing to Consultant prior to proceeding
with Work.
.4 Make changes in samples which Consultant may require, consistent with Contract
Documents.
.5 Reviewed and accepted samples will become standard of workmanship and material
against which installed Work will be verified.
1.4 CERTIFICATES AND TRANSCRIPTS
.1 Immediately after award of Contract, submit Workers' Compensation Board status.
.2 Submit transcription of insurance immediately after award of Contract.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
SUBMITTAL PROCEDURES Section 01 33 00
Page 3
2017-11-30
Part 2 Products
2.1 NOT USED
.1 Not Used.
Part 3 Execution
3.1 NOT USED
.1 Not Used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
HEALTH AND SAFETY
REQUIREMENTS
Section 01 35 29.06
Page 1
2017-11-30
Part 1 General
1.1 REFERENCES
.1 Canada Labour Code, Part 2, Canada Occupational Safety and Health Regulations
.2 Health Canada/Workplace Hazardous Materials Information System (WHMIS)
.1 Material Safety Data Sheets (MSDS).
.3 Province of Nova Scotia
.1 Occupational Health and Safety Act, S.N.S. 1996.
1.2 ACTION AND INFORMATIONAL SUBMITTALS
.1 Submit site-specific Health and Safety Plan: Within 7 days after date of Notice to
Proceed and prior to commencement of Work. Health and Safety Plan must include:
.1 Results of site specific safety hazard assessment.
.2 Results of safety and health risk or hazard analysis for site tasks and operations.
.2 Submit copies of Contractor's authorized representative's work site health and safety
inspection reports to authority having jurisdiction.
.3 Submit copies of incident and accident reports.
.4 Medical Surveillance: where prescribed by legislation, regulation or safety program,
submit certification of medical surveillance for site personnel prior to commencement of
Work, and submit additional certifications for any new site personnel to authority having
jurisdiction.
.5 On-site Contingency and Emergency Response Plan: address standard operating
procedures to be implemented during emergency situations.
1.3 FILING OF NOTICE
.1 File Notice of Project with Provincial authorities prior to beginning of Work.
1.4 SAFETY ASSESSMENT
.1 Perform site specific safety hazard assessment related to project.
1.5 GENERAL REQUIREMENTS
.1 Develop written site-specific Health and Safety Plan based on hazard assessment prior to
beginning site Work and continue to implement, maintain, and enforce plan until final
demobilization from site. Health and Safety Plan must address project specifications.
1.6 RESPONSIBILITY
.1 Be responsible for health and safety of persons on site, safety of property on site and for
protection of persons adjacent to site and environment to extent that they may be affected
by conduct of Work.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
HEALTH AND SAFETY
REQUIREMENTS
Section 01 35 29.06
Page 2
2017-11-30
.2 Comply with and enforce compliance by employees with safety requirements of Contract
Documents, applicable federal, provincial, territorial and local statutes, regulations, and
ordinances, and with site-specific Health and Safety Plan.
1.7 COMPLIANCE REQUIREMENTS
.1 Comply with Occupational Health and Safety Act, Occupational Safety General
Regulations, N.S. Reg.
.2 Comply with Canada Labour Code, Canada Occupational Safety and Health Regulations.
1.8 UNFORSEEN HAZARDS
.1 When unforeseen or peculiar safety-related factor, hazard, or condition occur during
performance of Work, follow procedures in place for Employee's Right to Refuse Work
in accordance with Acts and Regulations of Province having jurisdiction and advise
Consultant verbally and in writing.
1.9 HEALTH AND SAFETY CO-ORDINATOR
.1 Employ and assign to Work, competent and authorized representative as Health and
Safety Co-ordinator. Health and Safety Co-ordinator must:
.1 Have site-related working experience specific to activities.
.2 Have working knowledge of occupational safety and health regulations.
.3 Be responsible for completing Contractor's Health and Safety Training Sessions
and ensuring that personnel not successfully completing required training are not
permitted to enter site to perform Work.
.4 Be responsible for implementing, enforcing daily and monitoring site-specific
Contractor's Health and Safety Plan.
.5 Be on site during execution of Work.
1.10 POSTING OF DOCUMENTS
.1 Ensure applicable items, articles, notices and orders are posted in conspicuous location on
site in accordance with Acts and Regulations of Province having jurisdiction.
1.11 CORRECTION OF NON-COMPLIANCE
.1 Immediately address health and safety non-compliance issues identified by authority
having jurisdiction.
.2 Provide written report of action taken to correct non-compliance of health and safety
issues identified.
.3 Consultant may stop Work if non-compliance of health and safety regulations is not
corrected.
1.12 POWDER ACTUATED DEVICES
.1 Use powder actuated devices only after receipt of written permission from Consultant.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
HEALTH AND SAFETY
REQUIREMENTS
Section 01 35 29.06
Page 3
2017-11-30
1.13 WORK STOPPAGE
.1 Give precedence to safety and health of public and site personnel and protection of
environment over cost and schedule considerations for Work.
Part 2 Products
2.1 NOT USED
.1 Not used.
Part 3 Execution
3.1 NOT USED
.1 Not used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
FIRE SAFETY
REQUIREMENTS
Section 01 35 35
Page 1
2017-11-30
Part 1 General
1.1 REPORTING FIRES
.1 Know location of nearest fire alarm box and telephone, including emergency phone
number.
.2 Report immediately fire incidents to Fire Department as follows:
.1 Activate nearest fire alarm box; or
.2 Telephone 911.
.3 When reporting fire by telephone, give location of fire, name or number of building and
be prepared to verify location.
1.2 INTERIOR AND EXTERIOR FIRE PROTECTION AND ALARM SYSTEMS
.1 Fire protection and alarm system will not be:
.1 Obstructed;
.2 Shut-off; and
.3 Left inactive at end of working day or shift without authorization from Fire
Chief.
.2 Fire hydrants, standpipes and hose systems will not be used for other than fire-fighting
purposes unless authorized by Fire Chief.
1.3 FIRE EXTINGUISHERS
.1 Supply fire extinguishers, as scaled by Fire Chief, necessary to protect work in progress
and contractor's physical plant on site.
1.4 BLOCKAGE OF ROADWAYS
.1 Advise Fire Chief of work that would impede fire apparatus response. This includes
violation of minimum overhead clearance, as prescribed by Fire Chief, erecting of
barricades and digging of trenches.
1.5 SMOKING PRECAUTIONS
.1 Observe smoking regulations.
.2 Smoking is not permitted in Building.
1.6 RUBBISH AND WASTE MATERIALS
.1 Keep rubbish and waste materials at minimum quantities.
.2 Burning of rubbish is prohibited.
.3 Removal:
.1 Remove rubbish from work site at end of work day or shift or as directed.
.4 Storage:
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
FIRE SAFETY
REQUIREMENTS
Section 01 35 35
Page 2
2017-11-30
.1 Store oily waste in approved receptacles to ensure maximum cleanliness and
safety.
.2 Deposit greasy or oily rags and materials subject to spontaneous combustion in
approved receptacles and remove specified.
1.7 FLAMMABLE AND COMBUSTIBLE LIQUIDS
.1 Handling, storage and use of flammable and combustible liquids governed by current
National Fire Code of Canada.
.2 Keep flammable and combustible liquids such as gasoline, kerosene and naphtha for
ready use in quantities not exceeding 45 litres provided they are stored in approved safety
cans bearing Underwriters' Laboratory of Canada or Factory Mutual seal of approval.
Storage of quantities of flammable and combustible liquids exceeding 45 litres for work
purposes requires permission of Fire Chief.
.3 Transfer of flammable and combustible liquids is prohibited within buildings.
.4 Transfer of flammable and combustible liquids will not be carried out in vicinity of open
flames or any type of heat-producing devices.
.5 Do not use flammable liquids having flash point below 38 degrees C such as naphtha or
gasoline as solvents or cleaning agents.
.6 Store flammable and combustible waste liquids, for disposal, in approved containers
located in safe ventilated area. Keep quantities minimum and Fire Department is to be
notified when disposal is required.
1.8 HAZARDOUS SUBSTANCES
.1 Work entailing use of toxic or hazardous materials, chemicals, or otherwise creating
hazard to life, safety or health, in accordance with National Fire Code of Canada.
.2 Obtain from Fire Chief a "Hot Work" permit for work involving welding, burning or use
of blowtorches and salamanders, in buildings or facilities.
.3 When Work is carried out in dangerous or hazardous areas involving use of heat, provide
fire watchers equipped with sufficient fire extinguishers. Determination of dangerous or
hazardous areas along with level of protection necessary for Fire Watch is at discretion of
Fire Chief. Contractors are responsible for providing fire watch service for work on scale
established and in conjunction with Fire Chief at pre-work conference.
.4 Provide ventilation where flammable liquids, such as lacquers or urethanes are used,
eliminate sources of ignition. Inform Fire Chief prior to and at cessation of such work.
1.9 QUESTIONS AND/OR CLARIFICATION
.1 Direct questions or clarification on Fire Safety in addition to above requirements to Fire
Chief.
1.10 FIRE INSPECTION
.1 Co-ordinate site inspections by Fire.
.2 Allow Fire Chief unrestricted access to work site.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
FIRE SAFETY
REQUIREMENTS
Section 01 35 35
Page 3
2017-11-30
.3 Co-operate with Fire Chief during routine fire safety inspection of work site.
.4 Immediately remedy unsafe fire situations observed by Fire Chief.
Part 2 Products
2.1 NOT USED
.1 Not Used.
Part 3 Execution
3.1 NOT USED
.1 Not Used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
QUALITY CONTROL Section 01 45 00
Page 1
2017-11-30
Part 1 General
1.1 INSPECTION
.1 Allow Consultant access to Work. If part of Work is in preparation at locations other than
Place of Work, allow access to such Work whenever it is in progress.
.2 If Contractor covers or permits to be covered Work that has been designated for tests,
inspections or approvals before such is made, uncover such Work, have inspections or
tests satisfactorily completed and make good such Work.
.3 Consultant will order part of Work to be examined if Work is suspected to be not in
accordance with Contract Documents. If, upon examination such work is found not in
accordance with Contract Documents, correct such Work and pay cost of examination
and correction.
1.2 REJECTED WORK
.1 Remove defective Work, whether result of poor workmanship, use of defective products
or damage and whether incorporated in Work or not, which has been rejected by
Consultant as failing to conform to Contract Documents. Replace or re-execute in
accordance with Contract Documents.
.2 Make good other Contractor's work damaged by such removals or replacements
promptly.
.3 If in opinion of Consultant, it is not expedient to correct defective Work or Work not
performed in accordance with Contract Documents, Owner will deduct from Contract
Price difference in value between Work performed and that called for by Contract
Documents, amount of which will be determined by.
1.3 MOCK-UPS
.1 Prepare mock-ups for Work specifically requested in specifications. Include for Work of
Sections required to provide mock-ups.
.2 Prepare mock-ups for Consultant review with reasonable promptness and in orderly
sequence, to not cause delays in Work.
.3 Mock-ups may remain as part of Work.
1.4 EQUIPMENT AND SYSTEMS
.1 Submit adjustment and balancing reports for mechanical systems.
Part 2 Products
2.1 NOT USED
.1 Not Used.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
QUALITY CONTROL Section 01 45 00
Page 2
2017-11-30
Part 3 Execution
3.1 NOT USED
.1 Not Used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
TEMPORARY UTILITIES Section 01 51 00
Page 1
2017-11-30
Part 1 General
1.1 INSTALLATION AND REMOVAL
.1 Provide temporary utilities controls to execute work expeditiously.
.2 Remove from site all such work after use.
1.2 WATER SUPPLY
.1 Continuous supply of potable water for construction use is available within existing
building.
1.3 TEMPORARY HEATING AND VENTILATION
.1 Temporary heating will be provided under the “Boiler Room Package” contract if
permanent heating system is not operational.
.2 Permanent heating system of building, to be used when available. Be responsible for
damage to heating system if use is permitted.
1.4 TEMPORARY POWER AND LIGHT
.1 Power during construction for temporary lighting and operating of power tools, to a
maximum supply of 230 volts 30 amps will be made available within the existing
building.
.2 Provide and maintain temporary lighting throughout project. Ensure level of illumination
on all floors and stairs is not less than 162 lx.
.3 Connect to existing power supply in accordance with Canadian Electrical Code.
1.5 FIRE PROTECTION
.1 Provide and maintain temporary fire protection equipment during performance of Work
required by governing codes, regulations and bylaws.
Part 2 Products
2.1 NOT USED
.1 Not Used.
Part 3 Execution
3.1 NOT USED
.1 Not Used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
COMMON PRODUCT
REQUIREMENTS
Section 01 61 00
Page 1
2017-11-30
Part 1 General
1.1 QUALITY
.1 Products, materials, equipment and articles incorporated in Work shall be new, not
damaged or defective, and of best quality for purpose intended. If requested, furnish
evidence as to type, source and quality of products provided.
.2 Defective products, whenever identified prior to completion of Work, will be rejected,
regardless of previous inspections.
1.2 AVAILABILITY
.1 Immediately upon signing Contract, review product delivery requirements and anticipate
foreseeable supply delays for items. If delays in supply of products are foreseeable, notify
Consultant of such, in order that substitutions or other remedial action may be authorized
in ample time to prevent delay in performance of Work.
1.3 STORAGE, HANDLING AND PROTECTION
.1 Handle and store products in manner to prevent damage, adulteration, deterioration and
soiling and in accordance with manufacturer's instructions when applicable.
.2 Store packaged or bundled products in original and undamaged condition with
manufacturer's seal and labels intact. Do not remove from packaging or bundling until
required in Work.
.3 Store products subject to damage from weather in weatherproof enclosures.
.4 Remove and replace damaged products at own expense and to satisfaction of Consultant.
.5 Touch-up damaged factory finished surfaces to Consultant satisfaction. Use touch-up
materials to match original. Do not paint over name plates.
1.4 TRANSPORTATION
.1 Pay costs of transportation of products required in performance of Work.
1.5 MANUFACTURER'S INSTRUCTIONS
.1 Install or erect products in accordance with manufacturer's instructions. Do not rely on
labels or enclosures provided with products. Obtain written instructions directly from
manufacturers.
.2 Improper installation or erection of products, due to failure in complying with these
requirements, authorizes Consultant to require removal and re-installation at no increase
in Contract Price or Contract Time.
1.6 QUALITY OF WORK
.1 Ensure Quality of Work is of highest standard, executed by workers experienced and
skilled in respective duties for which they are employed. Immediately notify Consultant
if required Work is such as to make it impractical to produce required results.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
COMMON PRODUCT
REQUIREMENTS
Section 01 61 00
Page 2
2017-11-30
.2 Do not employ anyone unskilled in their required duties. Consultant reserves right to
require dismissal from site, workers deemed incompetent or careless.
.3 Decisions as to standard or fitness of Quality of Work in cases of dispute rest solely with
Consultant, whose decision is final.
1.7 CO-ORDINATION
.1 Ensure co-operation of workers in laying out Work. Maintain efficient and continuous
supervision.
.2 Be responsible for coordination and placement of openings, sleeves and accessories.
1.8 CONCEALMENT
.1 In finished areas conceal pipes, ducts and wiring in floors, walls and ceilings, except
where indicated otherwise.
.2 Before installation inform Consultant if there is interference. Install as directed by
Consultant.
1.9 REMEDIAL WORK
.1 Perform remedial work required to repair or replace parts or portions of Work identified
as defective or unacceptable. Co-ordinate adjacent affected Work as required.
.2 Perform remedial work by specialists familiar with materials affected. Perform in a
manner to neither damage nor put at risk any portion of Work.
1.10 FASTENINGS
.1 Provide metal fastenings and accessories in same texture, colour and finish as adjacent
materials, unless indicated otherwise.
.2 Prevent electrolytic action between dissimilar metals and materials.
.3 Use non-corrosive hot dip galvanized steel fasteners and anchors for securing exterior
work, unless stainless steel or other material is specifically requested in affected
specification Section.
.4 Space anchors within individual load limit or shear capacity and ensure they provide
positive permanent anchorage. Wood, or any other organic material plugs are not
acceptable.
.5 Keep exposed fastenings to a minimum, space evenly and install neatly.
.6 Fastenings which cause spalling or cracking of material to which anchorage is made are
not acceptable.
1.11 FASTENINGS - EQUIPMENT
.1 Use fastenings of standard commercial sizes and patterns with material and finish suitable
for service.
.2 Use heavy hexagon heads, semi-finished unless otherwise specified. Use No. 304
stainless steel for exterior areas.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
COMMON PRODUCT
REQUIREMENTS
Section 01 61 00
Page 3
2017-11-30
.3 Bolts may not project more than one diameter beyond nuts.
.4 Use plain type washers on equipment, sheet metal and soft gasket lock type washers
where vibrations occur. Use resilient washers with stainless steel.
1.12 PROTECTION OF WORK IN PROGRESS
.1 Prevent overloading of parts of building. Do not cut, drill or sleeve load bearing structural
member, unless specifically indicated without written approval of Consultant.
1.13 EXISTING UTILITIES
.1 When breaking into or connecting to existing services or utilities, execute Work at times
directed by local governing authorities, with minimum of disturbance to Work, and/or
building occupants.
Part 2 Products
2.1 NOT USED
.1 Not Used.
Part 3 Execution
3.1 NOT USED
.1 Not Used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
EXECUTION Section 01 73 00
Page 1
2017-11-30
Part 1 General
1.1 MATERIALS
.1 Change in Materials: Submit request for substitution in accordance with Section 01 33 00
- Submittal Procedures.
1.2 PREPARATION
.1 Inspect existing conditions, including elements subject to damage or movement during
cutting and patching.
.2 After uncovering, inspect conditions affecting performance of Work.
.3 Beginning of cutting or patching means acceptance of existing conditions.
.4 Provide supports to assure structural integrity of surroundings; provide devices and
methods to protect other portions of project from damage.
.5 Provide protection from elements for areas which are to be exposed by uncovering work;
maintain excavations free of water.
1.3 EXECUTION
.1 Execute cutting, fitting, and patching to complete Work.
.2 Fit parts together, to integrate with other Work.
.3 Remove and replace defective and non-conforming Work.
.4 Provide openings in non-structural elements of Work for penetrations of mechanical and
electrical Work.
.5 Execute Work by methods to avoid damage to other Work, and which will provide proper
surfaces to receive patching and finishing.
.6 Cut rigid materials using masonry saw or core drill. Pneumatic or impact tools not
allowed on masonry work without prior approval.
.7 Restore work with new products in accordance with requirements of Contract
Documents.
.8 Fit Work airtight to pipes, sleeves, conduit, and other penetrations through surfaces.
.9 At penetration of fire rated wall, ceiling, or floor construction, completely seal voids with
firestopping material.
.10 Refinish surfaces to match adjacent finishes: Refinish continuous surfaces to nearest
intersection. Refinish assemblies by refinishing entire unit.
.11 Conceal pipes, ducts and wiring in floor, wall and ceiling construction of finished areas
except where indicated otherwise.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
EXECUTION Section 01 73 00
Page 2
2017-11-30
Part 2 Products
2.1 NOT USED
.1 Not Used.
Part 3 Execution
3.1 NOT USED
.1 Not Used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
CLEANING Section 01 74 11
Page 1
2017-09-30
Part 1 General
1.1 PROJECT CLEANLINESS
.1 Maintain Work in tidy condition, free from accumulation of waste products and debris.
.2 Remove waste materials from site at daily regularly scheduled times or dispose of as
directed by Consultant. Do not burn waste materials on site.
.3 Provide on-site containers for collection of waste materials and debris.
.4 Clean interior areas prior to start of finishing work, and maintain areas free of dust and
other contaminants during finishing operations.
.5 Store volatile waste in covered metal containers, and remove from premises at end of
each working day.
.6 Provide adequate ventilation during use of volatile or noxious substances. Use of building
ventilation systems is not permitted for this purpose.
.7 Use only cleaning materials recommended by manufacturer of surface to be cleaned, and
as recommended by cleaning material manufacturer.
.8 Schedule cleaning operations so that resulting dust, debris and other contaminants will
not fall on wet, newly painted surfaces nor contaminate building systems.
1.2 FINAL CLEANING
.1 When Work is Substantially Performed remove surplus products, tools, construction
machinery and equipment not required for performance of remaining Work.
.2 Remove waste products and debris other than that caused by others, and leave Work
clean and suitable for occupancy.
.3 Prior to final review remove surplus products, tools, construction machinery and
equipment.
.4 Remove waste materials from site at regularly scheduled times or dispose of. Do not burn
waste materials on site.
.5 Make arrangements with and obtain permits from authorities having jurisdiction for
disposal of waste and debris.
.6 Clean and polish glass, mirrors, hardware, wall tile, stainless steel, chrome, porcelain
enamel, baked enamel, plastic laminate, and mechanical and electrical fixtures. Replace
broken, scratched or disfigured glass.
.7 Remove stains, spots, marks and dirt from electrical and mechanical, fixtures, furniture
fitments, walls, floors.
.8 Clean lighting reflectors, lenses, and other lighting surfaces.
.9 Vacuum clean and dust building interiors, behind grilles, louvres and screens.
.10 Wax, seal, shampoo or prepare floor finishes, as recommended by manufacturer.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
CLEANING Section 01 74 11
Page 2
2017-09-30
.11 Inspect finishes, fitments and equipment and ensure specified workmanship and
operation.
.12 Clean equipment and fixtures to sanitary condition; clean or replace filters of mechanical
equipment.
Part 2 Products
2.1 NOT USED
.1 Not Used.
Part 3 Execution
3.1 NOT USED
.1 Not Used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
CONSTRUCTION/DEMOLITION
WASTE MANAGEMENT AND
DISPOSAL
Section 01 74 21
Page 1
2017-11-30
Part 1 General
1.1 WASTE MANAGEMENT GOALS
.1 Accomplish maximum control of solid construction waste.
.2 Preserve environment and prevent pollution and environment damage.
1.2 DEFINITIONS
.1 Class III: non-hazardous waste - construction renovation and demolition waste.
.2 Recyclable: ability of product or material to be recovered at end of its life cycle and re-
manufactured into new product for reuse.
.3 Recycle: process by which waste and recyclable materials are transformed or collected
for purpose of being transferred into new products.
.4 Recycling: process of sorting, cleansing, treating and reconstituting solid waste and other
discarded materials for purpose of using in altered form. Recycling does not include
burning, incinerating, or thermally destroying waste.
.5 Reuse: repeated use of product in same form but not necessarily for same purpose. Reuse
includes:
.1 Salvaging reusable materials from re-modelling projects, before demolition stage,
for resale, reuse on current project or for storage for use on future projects.
.2 Returning reusable items including pallets or unused products to vendors.
.6 Salvage: removal of structural and non-structural materials from
deconstruction/disassembly projects for purpose of reuse or recycling.
1.3 STORAGE, HANDLING AND PROTECTION
.1 Store, materials to be reused, recycled and salvaged.
.2 Unless specified otherwise, materials for removal become Contractor's property.
.3 Separate non-salvageable materials from salvaged items. Transport and deliver non-
salvageable items to licensed disposal facility.
1.4 DISPOSAL OF WASTES
.1 Do not bury rubbish or waste materials.
.2 Do not dispose of waste, volatile materials, mineral spirits, oil, paint thinner into
waterways, storm, or sanitary sewers.
.3 Remove materials from deconstruction as deconstruction/disassembly Work progresses.
1.5 USE OF SITE AND FACILITIES
.1 Execute work with least possible interference or disturbance to normal use of premises.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
CONSTRUCTION/DEMOLITION
WASTE MANAGEMENT AND
DISPOSAL
Section 01 74 21
Page 2
2017-11-30
1.6 SCHEDULING
.1 Co-ordinate Work with other activities at site to ensure timely and orderly progress of
Work.
Part 2 Products
2.1 NOT USED
.1 Not Used.
Part 3 Execution
3.1 NOT USED
.1 Not Used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
CLOSEOUT PROCEDURES Section 01 77 00
Page 1
2017-11-30
Part 1 General
1.1 ADMINISTRATIVE REQUIREMENTS
.1 Acceptance of Work Procedures:
.1 Contractor's Inspection: conduct inspection of Work, identify deficiencies and
defects, and repair as required to conform to Contract Documents.
.1 Request Consultant inspection.
.2 Consultant Inspection:
.1 Consultant and Contractor to inspect Work and identify defects and
deficiencies.
.2 Contractor to correct Work as directed.
.3 Final Inspection:
.1 When completion tasks are done, request final inspection of Work by
Consultant.
.2 When Work incomplete according to Consultant, complete outstanding
items and request re-inspection.
.4 Declaration of Substantial Performance: when Consultant considers deficiencies
and defects corrected and requirements of Contract substantially performed,
make application for Certificate of Substantial Performance.
.5 Commencement of Lien and Warranty Periods: date of Owner's acceptance of
submitted declaration of Substantial Performance to be date for commencement
for warranty period and commencement of lien period unless required otherwise
by lien statute of Place of Work.
.6 Final Payment:
.1 When Consultant considers final deficiencies and defects corrected and
requirements of Contract met, make application for final payment.
.7 Payment of Holdback: after issuance of Certificate of Substantial Performance of
Work, submit application for payment of holdback amount in accordance with
contractual agreement.
Part 2 Products
2.1 NOT USED
.1 Not Used.
Part 3 Execution
3.1 NOT USED
.1 Not Used.
END OF SECTION
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
CLOSEOUT SUBMITTALS Section 01 78 00
Page 1
2017-11-30
Part 1 General
1.1 ACTION AND INFORMATIONAL SUBMITTALS
.1 Provide submittals in accordance with Section 01 33 00 - Submittal Procedures.
.2 Two weeks prior to Substantial Performance of the Work, submit to the Consultant, 3
final copies of operating and maintenance manuals in English.
.3 Provide spare parts, maintenance materials and special tools of same quality and
manufacture as products provided in Work.
.4 Provide evidence, if requested, for type, source and quality of products supplied.
1.2 FORMAT
.1 Organize data as instructional manual.
.2 Binders: vinyl, hard covered, 3 'D' ring, loose leaf 219 x 279 mm with spine and face
pockets.
.3 When multiple binders are used correlate data into related consistent groupings.
.1 Identify contents of each binder on spine.
.4 Cover: identify each binder with type or printed title 'Project Record Documents'; list title
of project and identify subject matter of contents.
.5 Arrange content by systems, under Section numbers and sequence of Table of Contents.
.6 Provide tabbed fly leaf for each separate product and system, with typed description of
product and major component parts of equipment.
.7 Text: manufacturer's printed data, or typewritten data.
.8 Drawings: provide with reinforced punched binder tab.
.1 Bind in with text; fold larger drawings to size of text pages.
1.3 CONTENTS - PROJECT RECORD DOCUMENTS
.1 Table of Contents for Each Volume: provide title of project;
.1 Date of submission; names.
.2 Addresses, and telephone numbers of Consultant and Contractor with name of
responsible parties.
.3 Schedule of products and systems, indexed to content of volume.
.2 For each product or system:
.1 List names, addresses and telephone numbers of subcontractors and suppliers,
including local source of supplies and replacement parts.
.3 Product Data: mark each sheet to identify specific products and component parts, and
data applicable to installation; delete inapplicable information.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
CLOSEOUT SUBMITTALS Section 01 78 00
Page 2
2017-11-30
.4 Drawings: supplement product data to illustrate relations of component parts of
equipment and systems, to show control and flow diagrams.
.5 Typewritten Text: as required to supplement product data.
.1 Provide logical sequence of instructions for each procedure, incorporating
manufacturer's instructions specified in Section 01 45 00 - Quality Control.
.6 Training: refer to Section 01 79 00 - Demonstration and Training.
1.4 AS -BUILT DOCUMENTS
.1 Maintain, at site for Consultant one record copy of:
.1 Contract Drawings.
.2 Specifications.
.3 Addenda.
.4 Change Orders and other modifications to Contract.
.5 Reviewed shop drawings, product data, and samples.
.6 Field test records.
.7 Inspection certificates.
.8 Manufacturer's certificates.
.2 Store record documents in field office apart from documents used for construction.
.3 Label record documents and file in accordance with Section number listings in List of
Contents of this Project Manual.
.1 Label each document "PROJECT RECORD" in neat, large, printed letters.
.4 Maintain record documents in clean, dry and legible condition.
.1 Do not use record documents for construction purposes.
.5 Keep record documents available for inspection by Consultant.
1.5 RECORDING INFORMATION ON PROJECT RECORD DOCUMENTS
.1 Record information on set of black line drawings, and in copy of Project Manual.
.2 Use felt tip marking pens, maintaining separate colours for each major system, for
recording information.
.3 Record information concurrently with construction progress.
.1 Do not conceal Work until required information is recorded.
.4 Contract Drawings and shop drawings: mark each item to record actual construction,
including:
.1 Measured depths of elements of foundation in relation to finish first floor datum.
.2 Measured horizontal and vertical locations of underground utilities and
appurtenances, referenced to permanent surface improvements.
.3 Measured locations of internal utilities and appurtenances, referenced to visible
and accessible features of construction.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
CLOSEOUT SUBMITTALS Section 01 78 00
Page 3
2017-11-30
.4 Field changes of dimension and detail.
.5 Changes made by change orders.
.6 Details not on original Contract Drawings.
.7 References to related shop drawings and modifications.
.5 Specifications: mark each item to record actual construction, including:
.1 Manufacturer, trade name, and catalogue number of each product actually
installed, particularly optional items and substitute items.
.2 Changes made by Addenda and change orders.
.6 Other Documents: maintain manufacturer's certifications, inspection certifications, field
test records, required by individual specifications sections.
.7 Provide digital photos, if requested, for site records.
1.6 EQUIPMENT AND SYSTEMS
.1 For each item of equipment and each system include description of unit or system, and
component parts.
.1 Include manufacturer's printed operation and maintenance instructions.
.2 Include sequence of operation by controls manufacturer.
.3 Provide original manufacturer's parts list, illustrations, assembly drawings, and
diagrams required for maintenance.
.2 Include test and balancing reports.
1.7 MATERIALS AND FINISHES
.1 Building products, applied materials, and finishes: include product data, with catalogue
number, size, composition, and colour and texture designations.
.1 Provide information for re-ordering custom manufactured products.
.2 Instructions for cleaning agents and methods, precautions against detrimental agents and
methods, and recommended schedule for cleaning and maintenance.
1.8 MAINTENANCE MATERIALS
.1 Extra Stock Materials:
.1 Provide maintenance and extra materials, in quantities specified in individual
specification sections.
.2 Provide items of same manufacture and quality as items in Work.
.3 Deliver to site; place and store.
.4 Receive and catalogue items.
.2 Special Tools:
.1 Provide special tools, in quantities specified in individual specification section.
.2 Provide items with tags identifying their associated function and equipment.
.3 Deliver to site; place and store.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
CLOSEOUT SUBMITTALS Section 01 78 00
Page 4
2017-11-30
1.9 DELIVERY, STORAGE AND HANDLING
.1 Store spare parts, maintenance materials, and special tools in manner to prevent damage
or deterioration.
.2 Store in original and undamaged condition with manufacturer's seal and labels intact.
.3 Store components subject to damage from weather in weatherproof enclosures.
.4 Store paints and freezable materials in a heated and ventilated room.
.5 Remove and replace damaged products at own expense and for review by Consultant.
1.10 WARRANTIES AND BONDS
.1 Submit, warranty information made available during construction phase, to Consultant
for approval prior to each monthly pay estimate.
.2 Assemble approved information in binder, submit upon acceptance of work and organize
binder as follows:
.1 Separate each warranty or bond with index tab sheets keyed to Table of Contents
listing.
.2 List subcontractor, supplier, and manufacturer, with name, address, and
telephone number of responsible principal.
.3 Obtain warranties and bonds, executed in duplicate by subcontractors, suppliers,
and manufacturers, within ten days after completion of applicable item of work.
.4 Verify that documents are in proper form, contain full information, and are
notarized.
.5 Co-execute submittals when required.
.6 Retain warranties and bonds until time specified for submittal.
.3 Except for items put into use with Owner's permission, leave date of beginning of time of
warranty until Date of Substantial Performance is determined.
.4 Conduct joint 6 month and 11 month warranty inspection, measured from time of
acceptance, by Consultant.
.5 Include information contained in warranty management plan as follows:
.1 Roles and responsibilities of personnel associated with warranty process,
including points of contact and telephone numbers within the organizations of
Contractors, subcontractors, manufacturers or suppliers involved.
.2 Provide list for each warranted equipment, item, feature of construction or
system indicating:
.1 Name of item.
.2 Model and serial numbers.
.3 Location where installed.
.4 Name and phone numbers of manufacturers or suppliers.
.5 Names, addresses and telephone numbers of sources of spare parts.
TOWN OF ANNAPOLIS ROYAL
THE ACADEMY PROJECT
LIBRARY RENOVATIONS
TENDER NO. 17-353541B
CLOSEOUT SUBMITTALS Section 01 78 00
Page 5
2017-11-30
.6 Warranties and terms of warranty: include one-year overall warranty of
construction. Indicate items that have extended warranties and show
separate warranty expiration dates.
.7 Cross-reference to warranty certificates as applicable.
.8 Starting point and duration of warranty period.
.9 Summary of maintenance procedures required to continue warranty in
force.
.10 Cross-Reference to specific pertinent Operation and Maintenance
manuals.
.11 Organization, names and phone numbers of persons to call for warranty
service.
.12 Typical response time and repair time expected for various warranted
equipment.
.3 Contractor's plans for attendance at 6 and 11 month post-construction warranty
inspections.
.4 Procedure and status of tagging of equipment covered by extended warranties.
.5 Post copies of instructions near selected pieces of equipment where operation is
critical for warranty and/or safety reasons.
.6 Respond in timely manner to oral or written notification of required construction
warranty repair work.
.7 Written verification to follow oral instructions.
.1 Failure to respond will be cause for the Consultant to proceed with action against
Contractor.
Part 2 Products
2.1 NOT USED
.1 Not Used.
Part 3 Execution
3.1 NOT USED
.1 Not Used.
END OF SECTION