The 34th Congress of Euroheat & Power
Transcript of The 34th Congress of Euroheat & Power
The 34th Congress ofEuroheat & Power
Varese Risorse – An intelligent way to increasecogeneration and energy savings
Fabio FidanzaDirectorVarese Risorse S.p.a.
25-26 Maggio 2009 Hilton Molino Stucky, Venice
The 34th Congress ofEuroheat & Power
Varese Risorse is the company which manages the district heating of the city of Varese.The company was founded in 1987 by the Municipality together with a private partner;starting from January 2009 Varese Risorse is part of the A2A group which main shareholdersare Milano and Brescia municipalities
INTRODUCTION
25-26 Maggio 2009 Hilton Molino Stucky, Venice
The 34th Congress ofEuroheat & Power
The CHP plant was erected in the last 80s and has been set at work in 1992.The gas turbine has been in operation for more than 70,000 operating hours, generatingmore than 150 GWh of electricity , obtaining more than 38,000 tep of energy savings , 350tons NOx, 170,000 tons CO2
Hilton Molino Stucky, Venice25-26 Maggio 2009
INTRODUCTION
The DH network is extended for more than 20 km in the south east part of the towndistributing hot water to 125 civil, tertiary buildings, hospitals and businesses at atemperature of 90°C cooling down to 60-65°C . More than 20,000 equivalent inhabitantsare reached by the service for a total volume of about 2,000,000 m3.
Plant
Network
The 34th Congress ofEuroheat & Power
25-26 Maggio 2009 Hilton Molino Stucky, Venice
INTRODUCTION
DH Network
The 34th Congress ofEuroheat & Power
The plant , located in Varese, mainly consists of:• Gas turbine (PGT5 Nuovo Pignone) ISO performance 5 MWe• Heat recovery boiler 11 MWt• Post combustor 4 MWt• SCR reactor• 5 auxiliary boiler 37 MWt• 2 hot water storage tanks (430 m3)• Pumping station (8 pumps for a maximum flowrate of 1800 m3/h)
All pumps are provided with VFD
PLANT CONFIGURATION
Hilton Molino Stucky, Venice25-26 Maggio 2009
PLANT CONFIGURATION
The 34th Congress ofEuroheat & Power
AXIAL COMPRESSOR, BARRING ENGINEAND COMBUSTION CHAMBER
The air from the outside iscompressed and sent to thecombustion chamber
In the combustion chamberthe air is mixed with thenatural gas coming from thereduction station andhappens the combustion
HEAT RECOVERY BOILER +POSTCOMBUSTORGAS TURBINE
GENERATOR(Power Unit)
The burned gasexpands
Electricity to thenational grid
Hot water(90°C) to the
district heatingnetwork
CHP SIMPLIFIED FUNCTIONAL SCHEME
25-26 Maggio 2009 Hilton Molino Stucky, Venice
5 MWe
11,5 + 4 MWt
PLANT CONFIGURATION
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
They operate in order to cover the heat peak demands from the end users or in caseof gas turbine malfunction as spare heat generation equipment
AUXILIARY BOILERS
TOTAL POWER37 MWt
Dual Fuel (Natural gasor diesel) Hot water
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
HOT STORAGE WATER TANKS
During the night the tanks are filled with hot water whichis used to cover the heat demand in the earlymorning
Total volume = 430 m3
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
SoftenedwaterstoragetankVolume215 m3
Fire waterstorage tankVolume125 m3
DieselstoragetankVolume50 m3
OTHER TANKS
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
During the year 2008 a SCR system wasinstalled in order to respect the new regionalemission limits; in the picture you can see theflue gas discharge channel, integrated withthe catalytic reactor and the three blue ureastorage tanks.
SCR PLANT
The 34th Congress ofEuroheat & Power
The CHP plant now is operating only in correspondence of what is defined bythe Italian law as the “thermal season” (from October to April).The plant is managed maintaining obviously the priority on cogenerationusing auxiliary boiler and the two hot water storage tanks to satisfy the peakheat demand as determined by the DH network.The plant control system is tuned on the “gas turbine following” mode.So the electric power generated is a by-product with respect to heat.The electric power is supplied to the national grid at a voltage level of 132 kV and is soldat the best possible economic condition in the electricity market thanks to the serviceof a trading company integrated in the A2A group.
Hilton Molino Stucky, Venice25-26 Maggio 2009
OPERATION
The 34th Congress ofEuroheat & Power
In the early 2005 Varese Risorse, after havingprovided a feasibility study then approved bythe general manager of the city hospital,signed a multi-annual agreement for thesupply of:
•Hot water for heating and sanitary usage;•MP steam for sterilization and technologicalusage ;
•Cold water for air conditioning.
Hilton Molino Stucky, Venice25-26 Maggio 2009
The project should be completely integrated with city DH network and should serve mainlythe new hospital that was opened in 2007 together with the old buildings in the hospitalarea. Nowadays new trigeneration plant construction is in progress.
New trigeneration plant
The 34th Congress ofEuroheat & Power
2 plate heat exchangers (total heat power 10 MWt)2 plate heat exchangers for sanitary water (total heat power 4 MWt)
Hilton Molino Stucky, Venice25-26 Maggio 2009
Now the new hospital is already connected with DH network in a provisional asset by meansof:
PROVISIONAL ASSET
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
For summer conditioning hospital need Varese Risorse set in operation a temporarymodular plant:
4 compression chillers with 4 cooling towers (total chilling power 6 MWf)
PROVISIONAL ASSET
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
The new trigeneration plant mainly consists of:
•Three dual fuel MP steam boiler (12 tons per hour each one at 11 barg)•One natural gas engine (GE Jenbacher 1,065 KWe) sized for trigenerationplant electric consumptions able to recover from the exhaust gases 565 kWt forhot water production and 445 kWt for steam generation
•Four absorption chillers (2 single stage using DH hot water and two double stageusing MP steam) for a total chilling power of 9.8 MWf
•Ten cooling tower cells for a total dissipated power of 21 MW•One shell & tube heat exchanger (total power 10 MWt)•Pumps for hot water, cold water and cooling towers•Natural gas reduction station•Diesel storage and pumps•MT electric substation•Demi water plant
NEW ASSET
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
NEW ASSET
New plant under construction
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
THERMALPLANT
• 3 boilers for steam generation (Bono)• 2 plate heat exchangers (Alfa Laval)• 2 plate heat exchangers for sanitary
water (Alfa Laval)
THERMAL COOLING PLANT• 4 absorption chillers (Johnson Controls)•10 cooling tower cells (Scam)
COGENERATIONPLANT
Natural gas engine (GE Jenbacher) :• electric power: 1065 kW• thermic power: 1010 kW
NEW ASSETMain equipment
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
Hot water circuit in the hospital 1) Water supply T = 85 °C2) Water return T = 63 °C
Water to / from district heating 1) Water supply T = 90 °C2) Water return T = 67 °C
Sanitary water circuit 1) Water supply T = 60 °C2) Municipal network T = 15 °C
2 plate heat exchangers
2 plate heat exchangers
NEW ASSET
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
District heating network
Hot water absorption chillers
Steam boilersSteam absorption chillers
Plate heat exchangers
Plate heat exchangers
Heating demand
Sanitary waterdemand
Natural gas engineElectric energy
demand
Cooling demand
Technological steamdemand
Integration/back up exchanger
NEW ASSET
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
Steam boilers satisfy the below reported duties:
Demand1) Back up and peak heating by means of one shell and
tube heat exchanger2) New hospital technological steam3) Old hospital technological steam4) Back up and peak cooling through two absorption
chillers
Equipment3 steam boilers 12 tons/h each
During normal conditions a boiler is completely of reserve because the actual maximum need is 20tons/h.
NEW ASSET
Steam boilers
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
NEW ASSET
Natural gas engine
Electric power
Cogenerated thermic power forhot water production
1065 kW
565 kW
Cogenerated thermic power forsteam generation 445 kW
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
NEW ASSET
Thermal cooling plant2 Hot water absorption chillers
2 Steam absorption chillers
Total chilling power
Total chilling power
6 Cooling tower cellsTotal cooling power
4 Cooling tower cellsTotal cooling power
5 MW
4,8 MW
12,6 MW
8,4 MW
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
NEW ASSET
Winter operation
Hospital heat demand will be covered for 88% by DH, while the remainder will be dividedalmost equally between CHP engine and steam boilers.
The plant electricity demand will be fully covered by the CHP engine.
The modest chilling demand will be met by one of the two double effect chillers.
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
NEW ASSET
Summer operationThe two absorption chillers fed with DH hot water will cover 80% of cooling demand andallow to operate the GE Nuovo Pignone PGT5 also in the summer months using the heatdistributed by the DH network.(Now the GE turbogas is instead not in operation due tothe small heat request coming from users simply satisfied by means of auxiliary boilers).
These equipment will satisfy with priority the base cooling load while the two absorptiondouble effect chillers fed with MP steam (generated by CHP engine and steam boilers) willbe put in operation for the remaining 20% and peak cooling demand or as spareequipment with respect to single effect ones.
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
NEW ASSET EconomicsTotal Investment
11 millions euro
Simple payback period (Worst case)
10 years
Net present value (Worst case)
4 millions euro
Internal rate of return (Worst case)
10%
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
Primary energy savingsNEW ASSET
Estimated primary energy consumption: 11100 TEP / YearConventional plant
Our plantEstimated primary energy consumption: 8900 TEP / Year
Primary energy savings
2200 TEP / Year 20 % savings
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
NEW ASSET Avoided emissionsConventional plant emissions
CO
NOX
SO2
51 tons/year
65 tons/year
72 tons/year
Estimated emissions from our new plant
CO 22 tons/year
NOX 33 tons/year
SO2 3 tons/year
CO2 CO235220 tons/year 28240 tons/year
Estimated emission savings
CO 29 tons/year
NOX 32 tons/year
-56 %
-50 %
SO2 -95 %69 tons/year
CO2 6980 tons/year -20 %
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
Future ChallengesPERSPECTIVE
• Carry out a new trigeneration initiative in the city matching it with the new on-goingurban development plan
• Realize a new district cooling network for Insubria university campus
• Replace the present CHP fossil fuel by making the most of locally based renewableenergy resources (waste, biomass) in order to get lower PRFs
The 34th Congress ofEuroheat & Power
Hilton Molino Stucky, Venice25-26 Maggio 2009
“Science becomes dangerous only when it imagines that it has reached its goal”G.B. Shaw
Thank you for your kind attention!