The 2012-2014 Programme and Budget · This Programme and Budget Document outlines Management’s...

77
This Programme and Budget Document outlines Management’s assumptions and projections about the Bank’s Work Programme and resource allocations. It also attempts to reflect the guidance received from the Board during discussion of the Framework Paper and from the Committee of the Whole and the December 2011 formal Board Meeting. The situations and projections contained in this document will, inevitably, be affected by future developments. However, the analysis and estimates are to the best of Management’s judgment as at the time they have been prepared and, unless specifically addressed in a corrigendum or update or revised version, the Bank is under no obligation to change it. AFRICAN DEVELOPMENT BANK GROUP THE 2012-2014 PROGRAMME AND BUDGET

Transcript of The 2012-2014 Programme and Budget · This Programme and Budget Document outlines Management’s...

This Programme and Budget Document outlines Management’s assumptions and projections

about the Bank’s Work Programme and resource allocations. It also attempts to reflect the

guidance received from the Board during discussion of the Framework Paper and from the

Committee of the Whole and the December 2011 formal Board Meeting. The situations and

projections contained in this document will, inevitably, be affected by future developments.

However, the analysis and estimates are to the best of Management’s judgment as at the time

they have been prepared and, unless specifically addressed in a corrigendum or update or

revised version, the Bank is under no obligation to change it.

AFRICAN DEVELOPMENT BANK

GROUP

THE 2012-2014 PROGRAMME

AND BUDGET

This document was prepared by a Bankwide Team coordinated by the Office of the Vice-

President and Chief Operating Officer.

The team is composed of the following members:

Mr. Zondo SAKALA Director, COBS

Mrs Kodeidja DIALLO Director, FFMA

Mr. Massamba DIENE OIC/Manager, ORPC/ORPC.1

Mr. Patrick KEI-BOGUINARD Manager , FFMA.1

Mr. Clement BABALOLA Lead Budget Officer, COBS

Mr. André N’Guessan OKOU Chief Budget Officer, COBS

Mr. Luigi MENNELLA Chief Budget Officer, COBS

Mr. Mohamed OLINDI-APERANO Chief Budget Officer, COBS

Mr. Etienne Yao KOUADIO Chief Budget Officer, COBS

Mr. Marcellin NDONG-NTAH Chief Development Policy Economist, ORPC

Mr. Mateus MAGALA Principal Strategist, STRG

Mr. Samuel KAMARA Principal Budget Officer, COBS

Mr. Karim DEKIOUK Principal Budget Officer, COBS

Mr. Thomas BRIENT Senior Budget Officer, COBS

Mr. Mamadou M’BAYE Budget Officer, COBS

Mrs. Tanta GUEYE Secretary, COBS

And,

The Resources and Budget Management Coordinators in various Complexes: Mr. Georges

BOHOUSSOU, Ms. Lydia KONE, Mr. Laté Zankli LAWSON, Mr. Graeme

MUTANTABOWA, Mr. Vivianus NGONG, Mr. Olivier SHINGIRO and Mr. Alexis

SISSO SOKOUE.

Special mention goes to the COBS Data Processing Team: Mr. Eloi DAHOUET-BOIGNY,

Mr. Gaoussou DIABAGATE, Mr. Christian FAGNIDI, Mr. Brian MUGOVA, Mr.

Mohamed RADHOUANI, Mr. Nawa YEO and Mr. Roland ZOMA.

Table of Contents

ACRONYMS AND ABBREVIATIONS................................................................................................................... I

BUDGET GLOSSARY ........................................................................................................................................... III

EXECUTIVE SUMMARY .................................................................................................................................... VII

INTRODUCTION ...................................................................................................................................................... 1

1 ASSESSING THE BANK’S CAPACITY FOR EFFECTIVE DELIVERY AND RESULTS .................... 2

1.1 EVALUATION OF BANK RESULTS IN 2010 ....................................................................................................... 2

1.2 ACHIEVEMENTS IN 2011 .................................................................................................................................. 4

2 . STRATEGIC FRAMEWORK – FROM MEDIUM TO LONG TERM STRATEGY ............................. 4

2.1 THE LONG TERM STRATEGY ........................................................................................................................... 4

2.2 CHALLENGES AND OPPORTUNITIES FOR THE BANK ........................................................................................ 5

2.3 OPERATIONAL AND INSTITUTIONAL FOCUS .................................................................................................... 5

3 . INDICATIVE OPERATIONAL WORK PROGRAMME (IOP) ............................................................... 6

3.1 BANK GROUP LENDING PROJECTIONS ............................................................................................................. 6

3.1.1 ADB Projections ..................................................................................................................................... 6

3.1.2 ADF Projections ..................................................................................................................................... 6

3.1.3 NTF Projections ...................................................................................................................................... 7

3.1.4 2012-2014 Financing Targets................................................................................................................. 7

3.2 OPERATIONAL AREAS OF FOCUS ..................................................................................................................... 7

3.3 PROPOSED OPERATIONAL PROGRAMME .......................................................................................................... 8

3.3.1 Indicative Lending Programme .............................................................................................................. 8

3.3.2 Non-Financing Activities ...................................................................................................................... 10

4 . INDICATIVE NON-OPERATIONAL WORK PROGRAMME (INOP) ................................................ 12

4.1 INSTITUTIONAL GOVERNANCE AND COORDINATION .................................................................................... 12

4.2 HUMAN RESOURCES MANAGEMENT ............................................................................................................. 12

4.3 DECENTRALIZATION ...................................................................................................................................... 12

4.4 RISK MANAGEMENT AND FIDUCIARY ........................................................................................................... 13

4.5 INFORMATION TECHNOLOGY AND BUSINESS CONTINUITY .......................................................................... 14

4.6 INFORMATION DISCLOSURE AND COMMUNICATION ..................................................................................... 14

5 . RESOURCE IMPLICATIONS .................................................................................................................... 15

5.1 THE BUDGET FRAMEWORK FOR 2012-2014 .................................................................................................. 15

5.2 THE 2012 BASELINE AND ESTIMATES ........................................................................................................... 16

5.3 MAJOR COST DRIVERS .................................................................................................................................. 16

5.3.1 Decentralization Implementation Enhancement ................................................................................... 17

5.3.2 Human Resources ................................................................................................................................. 17

5.3.3 Business Continuity ............................................................................................................................... 17

5.3.4 Operations Improvement, Enhanced Safeguards and Policy Advocacy ............................................... 18

5.3.5 Corporate Governance ......................................................................................................................... 19

5.4 SUMMARY OF THE 2012 ADMINISTRATIVE BUDGET ..................................................................................... 19

5.4.1 Operation and Non-Operation Complexes ........................................................................................... 19

5.4.2 Board and Units Reporting to the Board of Directors.......................................................................... 20

5.4.3 Special Appropriation ........................................................................................................................... 20

6 . PERFORMANCE REVIEW AND MONITORING FRAMEWORK ...................................................... 20

6.1 2012-2014 MONITORING FRAMEWORK ......................................................................................................... 20

6.2 PRODUCTIVITY, EFFICIENCY GAINS AND COST SAVINGS ............................................................................. 21

7 . RESOURCE ESTIMATES ........................................................................................................................... 22

7.1 INTERNALLY GENERATED RESOURCES ......................................................................................................... 22

7.2 TRUST FUNDS AND CO-FINANCING ............................................................................................................... 23

8 . 2012-2014 CAPITAL BUDGET ................................................................................................................... 23

8.1 CIVIL AND OUTFITTING WORKS .................................................................................................................... 24

8.2 IT INVESTMENTS ............................................................................................................................................ 24

8.3 SECURITY INVESTMENTS ............................................................................................................................... 25

9 . CONCLUSION AND RECOMMENDATIONS ......................................................................................... 25

ANNEXES ................................................................................................................................................................. 26

i

Acronyms and Abbreviations

ADB African Development Bank

ADF African Development Fund

ADF-12 Twelfth Replenishment of the ADF

ADOA Additionality and Development Outcome Assessment

AFP African Financing Partnerships

ATRS Activity Time Recording System

BCP Business Continuity Plan

BTS Business Technology Strategy

CAS Cost Accounting System

CGSP General Services and Procurement Department

CHRM Human Resources Management Department

CIMM Information Management and Methods Department

CIPSC Capital Investment Programme Steering Committee

COBS Programming and Budget Department

COO Chief Operating Officer

CSP Country Strategy Paper

CSVP Corporate Services Vice-Presidency

CWP Country Work Programme

EPSA Enhanced Private Sector Assistance

ERCU External Relations and Communication Unit

ERM Enterprise-wide Risk Management

EROs External Representation Offices

ESW Economic and Sector Work

FCR Fixed Cost Ratio

FFMA Financial Management Department

FNVP Finance Vice-Presidency

FOs Field Offices

FSF Fragile States Facility

GCI General Capital Increase

GCI-VI Sixth General Capital Increase of the ADB

HEST Higher Education, Science and Technology

HQ Headquarters

HR Human Resources

IACD Integrity and Anti-Corruption Department

IATI International Aid Transparency Initiative

ICT Information and Communication Technologies

IFIs International Financial Institutions

INOP Indicative Non-Operational Programme

IOP Indicative Operational Programme

ISSC Information Systems Steering Committee

IT Information Technology

KPIs Key Performance Indicators

LICs Low Income Countries

LMDP Leadership and Management Development Programme

LTS Long Term Strategy

MDRI Multilateral Debt Relief Initiative

ii

MICs Middle Income Countries

MTS Medium Term Strategy

NPO National Programme Office

NTF Nigeria Trust Fund

PBD Programme and Budget Document

PBO Policy Based Operations

PCRs Project Completion Reports

PIT Productivity Incentive Tax

PMG Performance Monitoring Group

PPP Public-Private Partnership

PSOs Private Sector Operations

RECs Regional Economic Communities

RISPs Regional Integration Strategy Papers

RMCs Regional Member Countries

ROs Regional Operations

RRCs Regional Resource Centres

SAP Systems, Applications and Products for data processing

SECU Security Unit

SMCC Senior Management Coordination Committee

SMEs Small and Medium Enterprises

SRP Staff Retirement Plan

STS Short Term Staff

TA Technical Assistance

TRA Temporary Relocation Agency

UA Units of Account

USD United States Dollar

VPU Vice-Presidency Unit

WBS Work Breakdown Structure

YPP Young Professionals Programme

ZAFO South Africa Field Office

iii

Budget Glossary

Term Definition

Activity Time Recording

System (ATRS)

Is a tool that allows staff to record time spent on an activity against specific

deliverables (using WBS codes).

Actual Expenditures Actual expenditures are expenses incurred and recorded in the General Ledger

Accounts of the Bank.

Adjusted Budget The Approved Budget plus/minus all the transfers between the different budget

lines of the Cost Centres and to/from other Cost Centres in the Bank, plus

eventual supplementary Budgets approved by the Board during the year. In

addition, it also reflects changes due to staff movements, organizational

restructuring, salary adjustments, in-situ promotions, etc.

Also: snapshot of the Budget, at a given time, reflecting any adjustment made to

the Approved Budget.

Approved Budget The budget envelope approved by the Board of Directors for the fiscal year

beginning the 1st January and ending the 31

st December.

Assigned Budget This budget refers to the sum of the Actual Expenditures (as defined above) and

the Committed Budget (as defined below).

Business Continuity Plan Plan of actions that are triggered when an emergency occurs that could or does

have the potential to adversely impact business operations. Having a Plan helps

Organisations / Business Units manage their operations under adverse

conditions. Business Continuity Plans are usually updated on a quarterly basis

and tested annually.

Capital Budget It refers to a multi-year investment plan for office equipment, ICT, civil works

and other projects.

Carryover (or Carried

Forward) Budget

This is a budget carried forward to cater for previous year outstanding

obligations covering contracts overlapping two budget years and which remain

valid for payment up to 30th June of the current year.

Centrally Managed Budget Is a budget managed by a specific Cost Centre on behalf of the whole Bank. For

example, office rent is centrally managed by the General Services and

Procurement Department (CGSP).

Commitment or Committed

Budget

A budget committed item is earmarked or set aside in response to a Purchase

Order (legally binding obligation) before converting into an actual expenditure.

Cost Accounting System

(CAS)

Is a Management Accounting System that helps record and report the cost of

deliverables to enable Managers and the Bank to understand the cost of running

the business.

Cost Effectiveness A measure of the balance between the effectiveness and cost of a service,

process or activity. A cost effective process is one which achieves its objectives

at minimum cost.

Directly Managed Budget Is a budget managed by a specific Cost Centre in order to finance its own Work

Programme. Currently, these consist of Salaries, Consultancy Services,

Missions, Short Term Staff (STS), Entertainment – Non Employees, and

Hospitality Bank Staff.

Efficiency (Continual Service Improvement) - A measure of whether the right amount of

resources has been used to deliver a process, service or activity. An efficient

process achieves its objectives with the minimum amount of time, money,

people or other resources.

External Offices Bank Representational Offices in Non-Regional Member Countries.

iv

Term Definition

Fair Value It is an accounting/financial term which refers to the amount at which a willing

buyer or seller will be prepared to exchange an asset or a liability in a free

market environment. It can either be a quoted market value or an amount

determined using acceptable valuation techniques, of an asset or a liability in a

current transaction, other than liquidation.

Field Offices Bank Regional Resource Centres, Regional Offices, Country Offices and

National Programme Offices in Regional Member Countries (RMCs).

Financing Target A Financing Target is the level of yearly total approvals per window that the

Bank Group intends to achieve. It takes into account available resources for the

window, the level of demand from the RMCs and a realistic pipeline of projects

and programmes.

Fixed Cost Ratio (FCR) Fixed Cost Ratio (FCR) is the proportion of salaries + benefits and overhead to

total budget (i.e. salaries, benefits, overhead, consultancy services, missions,

representation* and STS).

Formula is:

FCR = B/C

B (numerator) = Salaries + Benefits + Overhead

C (denominator) = (Salaries + Benefits + Overhead) + (Missions + Consultancy

Services + Representation + STS)

* Representation = Hospitality + Entertainment

Benefits = 66% of Salary

Overhead = 45% of Salary

NB: 66% and 45% are the calculated Bank-wide averages at present.

Fungibility This describes the possibility of transferability of budgets between expense line

items. Three types of fungibility are observed: (i) fungibility, which refers to

budget movements between expense items grouped under “Directly Managed”

(e.g. transfers from/to missions, salaries, consultancy services, representation,

STS); (ii) fungibility under “Centrally Managed” (e.g. transfers from benefits to

external training); and (iii) Across-fungibility, i.e. budget transfers executed

from one expense item in one budget grouping (e.g. benefits classified under

Centrally Managed Budget) to another expense item belonging to the other

grouping (e.g. salaries classified under Directly Managed Budget).

Indicative Lending

Programme (ILP)

Indicative List of Operations (Programmes and Projects) the Bank intends to

process for funding within a period of time (a year for instance). In developing

the ILP, the Bank ensures that the financial sum of operations for a given

country is within reasonable margin of its lending allocation target for the

period.

Indicative Non-Operational

Programme (INOP)

It specifies the detailed planned Work Programme of the Non-Operational

(Support) Complexes – CSVP, FNVP (excl FFMA.2, FTRY.4, FFCO.3&4),

some Units in UPRST (SAPR, PRST0, STRG, SEGL, GECL3&4, OMBU,

SECU, ERCU, OAGL, IACD), COO (COO.0, COBS, COEO), and URBD

(TRIB).

Indicative Operational

Programme (IOP)

It specifies the detailed planned Work Programme of the Operational (direct

RMC related) Complexes – ORVP, ECON, OIVP, OSVP and some Divisions in

v

Term Definition

FNVP (FFMA.2, FTRY.4, FFCO.3&4), URBD (OPEV, CRMU), UPRST

(GECL.1&2), and COO (ORQR, OPSC). It is the sum of the Indicative

Financing (or lending) and non-financing operational work programme of the

Bank.

Indicative Work Programme It specifies the planned Work Programme of the Bank as a whole, i.e. of both

Non-Operational and Operational Complexes and the Boards.

Key Performance Indicators

(KPIs)

Is a set of quantifiable measures used to gauge or compare performance in terms

of meeting strategic and operational targets.

Net Income This is a measure of the Bank’s profitability and efficiency from direct and

indirect operations. It is Operational Income (as defined below), less each

entity’s (ADB, ADF & NFT) share of Administrative Expenses and after

adjusting for gains/losses on market operations and impairment provisions. For

the Bank, income distribution approved by the Board of Governors is also taken

into consideration in determining net income.

Operational Income This is a measure of the Bank’s profitability from direct operations. It consists of

loan income and income on investments, less finance charges (including

borrowing costs) and loan loss provisions.

Price Increase/Adjustment This is the increase/adjustment in the cost of the expenditure while the volume

remains the same, e.g. the salary base for the same number of staff changes in

response to movements of compensation packages (such as a salary increase).

Ring-Fenced Budget Sequestrated funds that are subject to stringent transfer rules specified in Board

Resolution approving these budgets.

Slippage Factor Additional Operational Work Programme activities included to provide for

expected withdrawal or non-realisation of other activities in the same category

due to changed political situation, policy or priorities in the RMCs. Allowing for

a slippage factor helps ensure that the Bank will be able to deliver on its annual

Financing Target.

or

Factor aimed at managing efficiently the processing of the Indicative Lending

Programme (ILP) toward achieving the Financing Target by allowing the

replacement of operations that may drop out during the implementation of the

ILP due to a number of reasons such as priority changes at country level, delays

in carrying out project cycle activities, inadequate resources allocation, etc.

Special Appropriation or

Mandatory Spending

Is spending controlled by laws other than Appropriation Acts.

Staff Planning Is the set of activities that a Vice-Presidency Unit (VPU) undertakes to

determine its staffing needs and the actions required to meet these needs. Staff

planning is the principal tool for managing staff costs under UA Budgeting, as

position control is no longer used.

Supplementary Budget It is a supplementary funding enacted subsequent to a regular annual approval of

the Budget by the Boards.

Sustainable Lending Limit

(SLL)

Annual lending volume that the Bank can commit to without breaking its

prudential ratios, i.e. RCUR (Risk Capital Utilization Ratio), leverage ratio and

gearing ratio.

UA Budgeting Is a set of budget reforms with expanded flexibility and responsibilities to

Managers that aim to improve the efficiency and effectiveness of linking

resource allocations to Work Programme planning and implementation. It

emphasizes the importance of well-defined and realistic Work Programmes as

the basis of budget and staffing proposals and allocations. The starting point of

vi

Term Definition

the Work Programmes is the Bank Strategy, to which they must be aligned.

WBS (Work Breakdown

Structure) code

Is a code in SAP to identify deliverables related to Work Programme activities.

This code is used to book expenses and to link them to Deliverables.

vii

EXECUTIVE SUMMARY

The 2012-2014 Programme and Budget Document has been prepared in a uniquely challenging

African and global context. There is a deepening international financial crisis which is

threatening the economies of several of our Member Countries and Participant States, and

difficult choices have to be made, including in their responses to Africa’s development needs.

Consequently, there is increasing pressure for the Bank to rely more on its balance sheet – to

demonstrate greater efficiency and cost savings, and to build its reserves. In this regard, the

recently approved Income Model is expected to help assure an optimal balance between the use

of the Bank’s resources and its long term financial sustainability.

The assessment of the economic outlook in 2011 shows that Africa continues to demonstrate

resilience, in terms of maintaining positive growth, despite the global economic turbulences and

the recent political and economic developments in North Africa. In fact, the North African region

has registered a considerable decline in economic growth rate in 2011. Nonetheless, these events

are expected, in the long term, to have a positive impact in terms of opening space for inclusion

through more economic and social participation of the majority of the population. The forecast

average GDP growth for the continent for 2012 is 4.9%1. Thus, while the environment is likely to

remain challenging, the 2012-2014 Work Programme of the Bank is expected to be implemented

within a context of increased effective demand from both the low and middle income member

countries (LICs and MICs).

The mid-term review of the Medium Term Strategy (MTS) 2008-2012 has confirmed the

continuing relevance of the Bank’s strategic priorities. Accordingly, the MTS shall continue to

guide the Bank’s operations and its 2012-2014 Work Programmes. However, the manner of

execution of the strategic priorities will be substantially influenced by the urgent objective of

inclusive growth. This will be realised through, among other interventions, the promotion of

entrepreneurship and job creation, and faster economic integration. This will require flexibility,

innovation and increased responsiveness on the part of the Bank.

Internally, the Bank’s efforts towards improved capacity, results and better measurement of

impact should continue to focus on the following main areas: (i) streamlined business processes

and practices – and efficient information and communication technology services to provide the

necessary delivery platform; (ii) strengthened field presence and regional capacity; (iii) quality at

entry and managing for results; (iv) human resources management; (v) deepening programming

and budget reforms and discipline; (vi) enhanced risk management; and (vii) effective

governance, controls and safeguards.

A recent assessment of the Bank’s capacity for effective delivery and results published in the

maiden "Annual Development Effectiveness Review 2011", as well as the 2011 Mid-year

Performance and Budget Review, have revealed that there are a few areas for improvement in the

planning and management of the Bank’s operations, human resources and budget. As a result,

Management has taken proactive and appropriate measures that will better position the Bank to

meet the demand from LICs and MICs during the 2012-2014 Programme and Budget cycle.

1 Source: Statistics Department, African Development Bank. Forecast as of October 2011.

viii

The aggregate 2012-2014 financing target is estimated at around UA 16,875 million, of which

UA 5,725 million will be in 2012, UA 5,625 million in 2013 and UA 5,525 million in 2014. It is

in the same range as that of the previous programming period (2011-2013), thus confirming the

sustainable lending capacity of the Bank.

Analysis of the submissions for the 2012 Work Programme indicates that the major cost drivers

are: (i) operations improvement; (ii) decentralization; (iii) business continuity; (iv) human

resources development and management; and (v) corporate governance.

Management strongly believes that this is a time for prudence; a time for the Bank to leverage its

internal capacity in order to maintain strong balance sheets and preserve its AAA rating. To this

end, a zero budget framework is proposed for the 2012 Budget in demonstration of

Management’s commitment to contain administrative spending by doing more and better with

less. It is a budget which optimises ongoing efforts to generate cost savings and internal

efficiencies.

To meet the resource needs for what is still an ambitious Work Programme, the proposed budget

for 2012 has been built using a base budget corresponding to 95% of the “adjusted”2 2011

Approved Budget as per the Budget execution KPI target, and then adjusting it to reflect the

budgetary resources that VPUs estimated for enhancements to ongoing core priorities, new

initiatives and also factoring in cost savings and efficiency gains. The proposed Administrative

Budget amounts to UA 292.55 million, showing an increase of UA 3.41 million (nominal 1.18%)

compared to the 2011 Approved Budget or UA 6.08 million (+2.12%) over the “Adjusted” 2011

Approved Budget.

Under capital investments, the total Capital Budget requested for the period amounts to UA 46.05

million of which UA 20.59 million is planned for 2012, UA 22.25 million for 2013 and UA 3.21

million for 2014. The 2012 Capital investment programme includes UA 9.86 million for office

equipment and furniture acquisition, civil and outfitting works, and vehicles replacement and/or

acquisition; UA 10.43 million for IT projects; and UA 300,000 to acquire additional non-IT

security systems and equipments.

Considering the proposed Administrative Budget, ADB Group will report a profit which is

projected to increase during the period, mainly due to expected increases in ADB operational

income. ADF is projected to report annual deficits, primarily because of the depressed interest

rate environment and the impact of the amortization of the discount on accelerated encashment

notes. Management will shortly submit, for Board consideration, measures to protect the long

term viability of the Fund.

2 2011 Approved Budget less provision for Aniaman Building in Abidjan and two External Representation Offices

(EROs) – USA and Europe.

1

INTRODUCTION

1. The High Level Panel Report entitled “Investing in Africa’s Future – The ADB in the

21st Century” recommended that the Bank positions itself as the preferred partner in Africa, as

the “economic motor” providing well-focused development assistance and high-impact

solutions in support of the agenda for growth and economic integration.

2. In 2008, the Board of Governors endorsed Management’s recommendations on the

future growth of the Bank and one of the subsequent follow up developments was the GCI-

VI, which tripled the Bank’s capital base in 20103. A growing Bank has also meant

implementing profound structural and operational changes. This has led to the creation or

strengthening of new specialised Units; nearly doubling its size in terms of staffing; more than

double the growth in financing operations in general, and a dramatic rise in private sector

operations; and significant increases in the Administrative Budget at a time when growth in

other IFIs was generally flat or very modest.

3. We are now at the cross-roads. Early in the year we witnessed remarkable events in

some North African countries. This has been followed by an ever deepening global financial

crisis. Bank shareholders and clients are facing mounting resource challenges and difficult

choices have to be made. Specifically, it is expected that the 2012-2014 Programmes and

Budgets will be implemented in a context likely to be characterized by further abrupt social,

political, economic and democratic changes.

4. The socio-political changes witnessed in 2011 represent both threats and opportunities

to the economic outlook of the continent. While the average growth is expected to increase to

4.9% in 2012, with sub-Saharan Africa growing at 5.8%4, the combination of the above-noted

factors and the uncertainties of the international environment, as well as the longstanding

structural challenges, put African countries in a vulnerable situation. The key structural

challenges include vast infrastructure gaps, a nascent and not sufficiently inclusive private

sector, fragmented and shallow markets, demographic pressure and pervasive poverty

including food shortages, environmental degradation, and paucity of skills for a competitive

economy.

5. This landscape will impact on the Bank’s operations. The emerging demand will

require the Bank to continue demonstrating swiftness and flexibility. The Bank will need to

preserve its operations and ensure business continuity under difficult conditions. It will also

need to protect its investment while remaining relevant to all its RMCs. To this end, the Bank

will: (i) endeavour to maintain its financial solidity and long term sustainability; (ii) promote

inclusive growth while staying focused on its core priorities as spelt out in the Medium Term

Strategy (MTS), and thus resisting strategic drift; and (iii) improve the quality of its dialogue

and operations in the Regional Member States. Due consideration will be given to identifying

clear complementarity and partnerships with other development agencies in the Bank’s

priority areas.

6. Building on the results of the recent review of the 2008-2012 MTS, the 2012-2014

PBD will serve as the basis for continuing to improve execution and delivery. The

commitments made during the GCI-VI and the ADF-12 negotiations serve the same purpose

and aim to strengthen the operational focus and institutional effectiveness of the Bank.

3 Ref. ADB/BD/WP/2008/165/Rev.2 - ADF/BD/WP/2008/116/Rev.2

4 Source: Statistics Department, African Development Bank. Forecast as of October 2011.

2

7. In the light of the state of the global economic environment, and despite the fact that

currently the Bank is reasonably strong financially, Management has decided on a zero budget

framework. However, this is built on an optimistic baseline to enable the Bank to support

some key front-line programmes and preserve its capacity gains and footprint.

8. This PBD is articulated around eight chapters. Further to this introduction, Chapter 1

elaborates on the assessment of the Bank’s capacity for effective delivery and results. Chapter

2 deals with the Strategic Framework and outlines the transition from Medium to Long Term

Strategy. Chapter 3 discuss the Indicative Operational Programme while Chapter 4 presents

the Indicative Non-Operational Work Programme. The Resources Implications and the

Performance Review and Monitoring Framework are discussed in Chapters 5 and 6

respectively. Chapter 7 focuses on Resources Estimates and Chapter 8 on Capital Budget.

These chapters are followed by the Conclusion and Recommendations and the Annexes.

1 ASSESSING THE BANK’S CAPACITY FOR EFFECTIVE DELIVERY AND

RESULTS

9. To assess the Bank’s readiness to deliver its Work Programme and demonstrate results

during the 2012-2014 PBD period, a review of the Bank’s institutional and operational

framework is necessary.

1.1 Evaluation of Bank Results in 2010

10. The Bank recently published the 2011 “Annual Development Effectiveness Review”

report which evaluates, among other things, the Bank’s performance in managing its

operations and indicates how efficient the Bank is as an organisation. The efforts undertaken

by the Bank to strengthen its operational and corporate capacities to deliver are highlighted

hereunder.

How well the Bank manages its operations

11. The Bank must manage its operations effectively to maximize the support provided to

its clients. To do so, it has introduced new Quality-at-Entry measures to ensure that its

operations are well designed and appropriate to the needs of beneficiaries. The majority of its

operations are now supervised twice a year, allowing timely identification of emerging

problems and quick response to resolve them.

12. The Bank has also made concerted efforts to cancel under-performing operations to

free resources for more effective uses. It has improved the quality and timeliness of project

completion reports, thus ensuring that the knowledge arising from its operations is captured

when most relevant and can be used in developing other programmes in the future.

13. In recent years, the Bank has been transferring resources to the RMCs more effectively

and has reduced the period from approval to first disbursement from just over 25 months in

2006 to 12 months.

The Bank’s efficiency as an organisation

14. At the urging of Regional Member Countries, the Bank launched an ambitious process

of decentralization of its operations. Presently, there are 28 operational offices. The

decentralization is reinforcing the Bank’s presence in the field, thus making the Bank more

effective and responsive. In order to support the decentralization effort, the Bank has invested

3

intensively in information technology by providing high quality voice, data and video

conferencing services to almost all the Field Offices.

15. In the area of human resources management, the Bank has made efforts to improve its

ability to attract and retain highly qualified personnel and to ensure that employees

continuously build their knowledge and expertise. Furthermore, the Bank is developing

structures which are more conducive to career development, creating new opportunities to

gain experience in management, and rewarding the dedication and excellence of staff. The

Bank has also established an accelerated recruitment programme to bring down the vacancy

rate.

16. Finally, the Bank has undertaken a series of reforms in its business processes and

practices, such as the adoption of new accounting practices. It is also introducing new

practices designed to increase accountability and transparency to its member countries,

stakeholders and partners5.

Budget availability

17. To enhance efficiencies in the utilisation of the Budget, Management has identified

areas for improvement and has initiated actions to, on one hand, improve the programming

and budgeting process while, on the other, step up the Work Programme and Budget

execution rates.

18. Key issues receiving close attention from Senior Management involve strengthening

the level of diligence in the planning and arbitration of Work Programmes and the staffing

requirements at the VPU levels. Management is, therefore, taking necessary steps to enforce

rigour throughout this process. This will, in turn, ensure that the Work Programmes are

realistic and deliverable, and resource envelopes are close to actual needs and capacity to

absorb them.

19. Management recognizes that UA Budgeting and the flexibility it has brought should

help improve the timeliness of Managers’ responses to developments affecting their Work

Programmes and, consequently, budget execution rates. Further efforts are being made to

strengthen budget management capacity in, and across, the Complexes. A review of

experience to date with Budget Reforms introduced in 2008 has started and a report will be

ready for discussion with the Board by end of first quarter 2012.

Staff recruitment

20. In the area of staff recruitment, achievements include the successful hiring of 1,009

new staff between 2007 and 2010, representing an annual average intake of 252 staff, or 16%

of total staff at post6.

5 In November 2011, Publish What You Fund (The Global Campaign for Aid Transparency) released a new aid

transparency index of 58 Aid Agencies. The report ranks the African Development Bank third highest in this

index after the World Bank and the Global Fund to fight AIDS, Malaria and Tuberculosis. 6 Refer to Annex 1 for details of recruitment achievements between 2007 and October 2011.

4

1.2 Achievements in 20117

21. The Budget and Performance Report as at 30 November 2011 gives updates on

operational and non-operational Bank performance and the associated utilization of approved

financial resources.

22. The Work Programme delivery is on track (Annex 2): (i) Economic Knowledge

Products already exceeded yearly targets; (ii) portfolio quality is under control; (iii)

Decentralization is making steady progress; (iv) Lending Operations achieved 66% of yearly

targets; (v) Operational Strategy Papers (RISPs, CSP and related documents) are on track to

meet year-end targets; (vi) Recruitment process for vacant positions is being accelerated to

reduce the vacancy ratio for Professional staff to the adjusted target of 8% by year end; and

(vii) 2011 Administrative and Capital Budgets actual execution is 72% and 66% respectively.

The yearly budget execution targets are 95% and 33% respectively.

23. In measuring the process efficiency of the portfolio, the average lapse of time between

approval and first disbursement dates during the period under review stood at 12.86 months,

which is above the target set at 11 months. Performance by end 2010 had reached an

impressive 9.7 months. Coordination effort is underway with borrowers to improve

performance. Meanwhile, sustained and proactive monitoring on portfolio quality delivery has

ensured timely PCR coverage which has already reached 93% and surpassed the yearly target

of 85%.

24. It should also be noted that the implementation of GCI-VI and ADF-12 commitments

is progressing well, with 50% and 100% already delivered respectively.

25. From the above, it can be seen that Management is taking actions and measures aimed

at allowing the Bank to achieve its planned 2012-2014 Work Programmes.

2. STRATEGIC FRAMEWORK – FROM MEDIUM TO LONG TERM

STRATEGY

2.1 The Long Term Strategy

26. The Bank’s current Medium Term Strategy (MTS) 2008-2012 will expire in 2012. In

this regard, Management has proposed, in the Mid-Term Review of the MTS 2008-2012

which was approved by the Boards of Directors in May 2011, that the Bank should transit

from a short term to a long term planning horizon. The work on the Long Term Strategy

(LTS) has started. A newly constituted team is in place and an approach paper will soon be

submitted for discussion with the Board. The LTS will be operationalized through the Bank’s

three-year rolling PBDs – thus, the MTS will no longer be required under its current form8.

27. The preparation of the LTS will include extensive consultations with Bank Group

Member Countries, the Board, various categories of Stakeholders and Senior Management

and Staff. These inclusive consultations will be supported by in-depth analytical work, with a

view to reaching a broadly shared consensus on what should be the strategic direction and

operational focus of the Bank to best fulfil its mission in the longer time frame.

7 Budget & Performance Report as at 30 November 2011.

8 The Asian Development Bank used a similar process when it introduced its Long Term Strategy 2020. They

concluded that a Medium-Term Strategy was no longer required and was replaced by a three-year rolling plan

(Work Program and Budget Framework) to operationalize and implement the Strategy 2020.

5

2.2 Challenges and Opportunities for the Bank

28. The Bank will operate in the environment described in the introduction and which

will, without doubt, have and impact not only on the RMCs but also on its operations. There

will be consequences for the Bank’s location, its decentralization programme, its regional

integration strategy, its risk-taking capacity and its net income projections. The greatest

challenge will be to preserve the Bank’s operations and ensure business continuity under any

unforeseen adverse developments. The Bank will need to protect its investment while

remaining relevant to RMCs. With the challenges, there will also be opportunities, principally

for the Bank to increase assistance to RMCs – for instance by helping them to build resilience

to political and social shocks through promotion of good governance, participation, inclusion,

transparency and accountability.

29. There will also be challenges at the institutional and operational levels. The recent

review of the Bank’s Medium Term Strategy confirms that the strategy is pertinent and

relevant, but that there are a few gaps in the implementation of the strategy that need to be

closed. Hence, in the 2012-2014 programme and budget period, the Bank will be required to

provide a solid platform to continue work to improve execution and delivery.

30. While intervening factors are likely to explain the Bank’s moderate performance in

2010, adjustments to both the pipeline and capacity to deliver must be made so that the Bank

fulfils its GCI-VI commitments. For the remainder of the MTS, the Bank should take the

necessary steps to ensure that there are no slippages and the GCI-VI commitments are met

within the timeframe established in the GCI Matrix.

31. Overall, the Bank will need to maintain financial solidity and long term sustainability,

while responding appropriately to shocks and emerging issues – and doing so in a proactive

and flexible manner and thus remain relevant to its Member Countries. The recent approval of

a comprehensive income model will contribute to strengthening the Bank’s financial

management. Finally, the Bank will reinforce coordination and complementarity with other

development agencies through creative partnerships in order to be part of a coherent

framework of support to the RMCs.

2.3 Operational and Institutional Focus

Operational focus

32. The Bank will continue to promote operations through the private sector window, and

ensure that our non-sovereign portfolio is benefitting the Low Income Countries (LICs), while

maintaining the Bank’s financial soundness. More importantly, however, premium will be

placed on the private sector development activities which go beyond catalytic transactions and

focus on creating the enabling environment, the required soft (e.g. governance and

regulations) and hard economic infrastructure and productive enterprise as the key drivers for

inclusive development. Governance and public sector management will remain major areas of

focus for the Bank, while support for higher education, vocational training, science and

technology will be significantly scaled up, with special attention to national and regional

centres of excellence, and linkages between human development and production.

33. Non-lending activities, especially Economic and Sector Work, portfolio management,

policy development and dialogue will continue to complement the Bank’s financing

operations in the RMCs. Particular emphasis will be put on improving the quality of the

portfolio and on leveraging the resources to develop and disseminate policy and operationally

relevant knowledge.

6

Corporate focus

34. Institutional governance efforts in 2012 will be targeted at supporting the

decentralization programme as outlined in the recently approved Roadmap; enhancing the

Bank’s delivery capacity through better management of its staff and reinforced coordination

and synergies across Complexes; and rolling out an Enterprise Risk Management Framework.

35. With respect to Human Resources, Management is going to carry out an assessment of

the ongoing implementation of current HR Strategy, which was approved in 2008. An

external firm has been recruited and will start work in January 2012.

3. INDICATIVE OPERATIONAL WORK PROGRAMME (IOP)

36. The assessment of the economic outlook in 2011 shows that Africa continues to

demonstrate resilience in terms of maintaining positive growth despite the challenging years

during and in the aftermath of the global economic crisis, and the recent political and

economic changes in the northern African countries. The 2012-2014 Work Programme of the

Bank, therefore, is going to be implemented within a context of increased effective demand

from both LICs and MICs. The Bank is presently strong financially and strategically well

positioned to respond to the expected surge in demand. However, Management is acutely

aware that this will come under increasing threat due to the difficult global environment.

3.1 Bank Group Lending Projections

37. The levels of lending that the Bank Group plans to achieve during the period 2012-

2014 will be underpinned by the headroom of non-concessional lending allowed by the 6th

GCI, the remaining volume of concessional resources available under the ADF-12

Replenishment, the projected concessional resources expected from the ADF-13

Replenishment, and the demand from borrowing countries, Regional Economic Communities

and private operators. As much as possible, the Bank Group will leverage a larger resource

base through co-financing with other partner donors, so as to have more development impact

at country/REC level.

3.1.1 ADB Projections

38. The GCI-6 will continue to sustain an annual commitment capacity at around UA 3.6

billion for the period 2011-2020. Consequently, during the period 2012-2014, the Bank will

be able to commit headroom of UA 3.6 billion without breaching the prudential ratios. Out of

this amount, a significant and increasing portion (35% to 39%) is earmarked for non-

sovereign operations, reflecting the Bank’s intention to scale up its private sector operations

in both MICs and LICs. In order to ensure progressive and prudent expansion of Bank support

to PSOs, particularly in LICs which were underserved due to the high risk associated with the

countries, the Bank recently approved a proposal that defined the Bank risk appetite, which

led to an increase in the allocation of risk capital to PSOs.

3.1.2 ADF Projections

39. The ADF lending projections used to develop the 2012-2014 IOP are based on (i) the

outcome of the 12th Replenishment for the years 2012 and 2013, and (ii) the assumption

made for the 13th Replenishment. In fact, the estimated overall volume of the 12th

Replenishment is about UA 6 billion, with UA 2 billion per year on average. In view of the

current global international economic and financial situation, a flat scenario is retained for the

ADF-13 Replenishment. However, Management recognizes that there is a likelihood of a

7

decline in the ADF replenishment. Hence, these projections will be subject to further

adjustment.

3.1.3 NTF Projections

40. Nigeria Trust Fund (NTF) lending projections remain driven by the provision that the

Fund should be financially viable and self-sustaining. A lending projection of UA 25 million

per year is scheduled for the period 2012-2014, based on the Fund’s commitment capacity.

3.1.4 2012-2014 Financing Targets

41. The financing targets derived from the above projections are summarized in Table 1.

Table 1: 2012-2014 Financing Targets

(in UA million)

2011 2012 2013 2014 2012-2014

ADB 3,600 3,600 3,600 3,600 10,800

ADB Public 2,490 2,324 2,260 2,193 6,777

ADB Private 1,110 1,276 1,340 1,407 4,023

ADF 1,900 2,100 2,000 1,900 6,000

NTF 20 25 25 25 75

Bank Group 5,520 5,725 5,625 5,525 16,875

42. The aggregate 2012-2014 financing target is estimated at around UA 16,875 million,

of which UA 5,725 million will be in 2012, UA 5,625 million in 2013 and UA 5,525 million

in 2014. It is in the same range as that of the previous programming period (2011-2013), thus

confirming the sustainable lending capacity of the Bank.

3.2 Operational Areas of Focus

43. The Bank Group’s investments in infrastructure will aim at enhancing RMCs’ capacity

to foster sustained economic growth and poverty reduction, including through broader access

to modern energy services, transport, ICT, and safe drinking water and adequate sanitation.

This will contribute to filling the infrastructure gap in these areas and to significantly increase

access to essential public goods and services, which are critical for sustainable and equitable

socio-economic development.

44. The Bank will continue to support agriculture through: (i) the provision of agricultural

infrastructure, including rural and community roads, markets and storage infrastructure, and

(ii) renewable natural resource management, including land, water and forestry management.

These interventions are aimed at improving food security and increasing agricultural

productivity in RMCs.

45. In line with its commitments, the Bank will promote private sector development at

RMC level, using both its public and private sector windows, while also ensuring that its non-

sovereign portfolio is benefitting the Low Income Countries (LICs). With regard to

governance, the Bank will pay particular attention to the promotion of transparency and

accountability in the management of public resources, as well as reforms for enhanced

productivity. This will be achieved through the use of general and sector budget support.

8

46. The Bank will scale up the support to higher education, science and technology, with

special attention to infrastructure for this sector, national and regional centres of excellence,

and linkages between human development and production. By increasing its support to the

development of telecommunications infrastructure and networks, the Bank will foster greater

access to information and to knowledge. The Bank will also continue to expand its regional

integration portfolio to promote economic integration, which is imperative to build regional

markets and new opportunities for growth, job creation and improved living standards.

47. Greater consideration will be given to climate change. Thus, the Bank will promote

stand-alone climate change and environment projects, in addition to systematically

mainstreaming these issues in its investment and policy-based operations. The Bank’s

interventions will be mainly channelled through its traditional financing tools, including

project lending and Policy Based Operations.

3.3 Proposed Operational Programme

48. The operational programme described below builds systematically on the programme

activities as discussed and agreed in the Country Strategy Papers (CSPs) and the Regional

Integration Strategy Papers (RISPs) with governments of RMCs. The strategies are fully

aligned with the MTS 2008-2012 priority areas. For the post-2012 work programme, it is

envisaged that the current MTS priority areas are by and large expected to remain important.

The programme is also sufficiently flexible to accommodate the changing needs of RMCs in

response to the fast changing realities on the ground. Furthermore, the operational programme

is conceived in adherence to the engagement principle where dialogue with the RMCs is

going to be strengthened considerably in order to promote and support inclusive growth. To

this effect, more attention will be given to selective flagship Economic and Sector Works

(ESWs) which will inform the planning of Bank Group operations.

3.3.1 Indicative Lending Programme

Indicative Lending Programme versus Financing Targets

49. The 2012 indicative lending programme amounts to UA 6.784 billion. This comprises

UA 4.791 billion for public operations (ADB public, ADF including FSF, and NTF), UA

1.875 billion for private sector operations, and about 0.118 billion for other trust funds (see

the list of operations in Annex 3). The 2012 indicative lending programme accounts for about

116% of the financing target (including NTF but excluding other trust funds), reflecting an

over-programming rate of 16% which is within the suggested margin of about 20%. This

global rate hides, however, some disparities among financing windows. Due to the high

volatility of its pipeline, the ADB private window records a high over-programming rate of

about 147%, while both the ADB public and the ADF windows register individually a

reasonable over-programming rate of about 107%. The NTF recorded an over-programming

rate of 43%, which is acceptable in view of the volume of the available resources.

Distribution by financing instrument

50. As highlighted in Figure 1 below, investment operations will remain the main

financing instrument in 2012, representing about 73.1% of the financing volume. The

proportion of policy-based operations mostly composed of general and sector budget supports

represent 13.8% of the financing volume, a decrease of about 4 percentage points from the

level programmed in the 2011 IOP. This is largely explained by the drop of about UA 404

million under the ADF financing window. The ADB window, however, records an increase of

PBOs of about UA 136 million over its 2011 level. The decline in the 2012 planned PBOs

under ADF is mainly due to the fact that most of the planned ADF-12 PBOs were

9

programmed in 2011. At 11.1%, the proportion of lines of credit, equity participations and

loan guarantees processed by the Private Sector Department is expected to be almost equal to

their 2011 level (about 11.3%). Technical Assistance (TA) operations remain a meagre

portion of the volume of financing with about 1.9%. Therefore, there is still a need to explore

how to optimize the use of TA possibilities offered by the Bank, in particular how to harness

the available TA resources for helping the RMCs prepare multi-year investment programmes

and building a robust pipeline of projects for the Bank.

Figure 1: Distribution of the 2012 IOP by Financing Instruments

LLC, EQY, GTE

11.1%

Investment

Operations

73.1%

Technical

Assistance

1.9%

Policy Based

Operations

13.8%

LLC = Lines of Credit

EQY = Equity Participations

GTE = Loan Guarantees

Distribution by sector

51. In terms of sector distribution (see Figure 2 below), infrastructure will continue to be

the main beneficiary sector in 2012 with about 55.1% of the work programme, followed by

multi-sector operations mainly comprised of policy-based operations in support of policy

reforms and good governance (12.8%). The agriculture operations are expected to rise from

8.1% to 10.2%, reflecting the Bank’s continuing efforts to assist RMCs in addressing food

crisis, notably through support of the agricultural infrastructure and management of the

renewable natural resources. It is worth noting that a significant portion of agriculture

operations are devoted to agricultural infrastructure.

52. The social sector, including higher education, accounts for about 7.8% of the work

programme, a rise of about 2 percentage points over its 2011 level, due to a significant

increase in the volume of HEST and vocational training operations, which represent, at UA

274 million, about half of the social portfolio. This translates efforts made to scale up the

Bank’s interventions in the higher education sector as one of the core operational priorities of

the MTS. The share of finance operations is slightly reduced compared to 2011 and represents

8.3%. With a share of 5.7%, industry, mining and quarrying operations are expected to

increase compared to 2011.

53. The sector distribution of the 2012 indicative lending programme is broadly consistent

with the MTS operational priorities. Greater consideration has also been given to inclusive

10

growth oriented operations which account for about 35% of the work programme. These areas

will now place more emphasis on how the Bank can better contribute to assisting the RMCs

achieve strong and sustainable inclusive growth. The operations aim at, among other things:

(i) supporting well-targeted infrastructure development such as rural electrification projects,

construction of rural feeder roads, water supply and sanitation in both rural and peri-urban

areas, etc.; (ii) promoting greater transparency and accountability by national governments in

the management of public resources and implementation of public policy; (iii) boosting

investment in higher education and vocational training and improving the quality of such

operations and their relevance to the economy; and (iv) promoting small and medium

enterprises to generate employment, enhance entrepreneurship and lay the basis for industrial

development.

54. During the programming exercise, efforts have also been made to foster climate

change mitigation and environmental sustainability both through policy-based and investment

operations. This is the case for a number of energy operations where clean solutions and

renewable energy schemes have been proposed to reduce carbon emissions. In addition, a

modest 0.1% of the 2012 Work Programme is allocated to stand-alone climate change /

environment projects, in addition to the mainstreaming of these critical issues in investment

and policy-based operations.

Figure 2: Distribution of the 2012 IOP by Sector

Multi-Sector

12.8%

Agriculture and

Rural Development

10.2%

Finance

8.3%

Industry, Mining &

Quarrying

5.7%

Infrastructure

55.1%

Social, incl. higher

education

7.8%

Climate change /

Environment

0.1%

3.3.2 Non-Financing Activities

55. In addition to the operational programme outlined above, the Bank will continue to

undertake non-financing activities to enhance its responsiveness, efficiency and effectiveness

with special emphasis on improving the focus and delivery of the Bank Group’s financing

operations. The non-financing activities mainly cover the areas of Economic and Sector Work

(ESWs), policy development, programming and pipeline development and portfolio

management. The non-financing activities of the Bank Group for 2012 are outlined below.

11

Programming and pipeline development activities

56. With the aim of enhancing the quality and efficiency of Bank Group Operations, the

Bank will focus on preparing high quality Country Strategic Papers (CSPs) and Regional

Integration Strategic Papers (RISPs). The Bank’s operations will be anchored on these

documents and improve project and programme design by taking a long term perspective in

the identification and preparation of high impact operations. This will enable the Bank to

develop a robust pipeline which will reduce the volatility of the work programme.

57. The focus will remain on preparing and implementing new CSPs to replace completed

ones, and finalizing the Regional Integration Strategy Papers (RISPs) under preparation. In

2012, Management will also pay attention to the implementation of the RISPs recently

approved. It is noted that during 2011, Management significantly improved the planning of

the CSP preparation process, so as to minimise delays in the processing of projects that might

be due to the absence of approved CSPs.

Economic and sector work

58. Building upon the continuous improvement in the planning and quality of its ESW

products, the Bank will sustain the momentum of the ESWs in 2012 by ensuring the delivery

of high quality products. To this end, 40 ESWs have been programmed, of which seven

reports are carryovers from 2011. In 2012, six flagship reports at regional and country level

will be produced to guide Bank Group engagement and operations. The planned ESWs cover

a range of strategic areas of engagement including: (i) inclusive growth and employment

generation; (ii) Private Sector Development (PSD) and Public-Private Partnership (PPP)

study; (iii) domestic resource mobilization; (iv) energy sector development; and (v) post-war

reconstruction.

Portfolio management

59. The Bank will intensify efforts to improve its portfolio management through a

comprehensive approach which includes improving the quality of CSP/RISPs, project design,

implementation and overall portfolio management. Particular emphasis will be put on

progressively transferring the leadership of portfolio management to the Field Offices. As part

of the implementation of the Action Plan on Quality and Results, the Bank will also finetune

and roll out the use of Quality at Entry (QaE) tools in 2012 and strengthen capacity to manage

portfolio both at Headquarters and Field Office and Regional Resource Centre (RRCs) levels.

60. Sector Operations Departments will continue to enhance their supervision to ensure

that the annual target of 50% of projects to be supervised twice a year is met and that there is

timely reporting and follow up actions.

Policy development

61. Within the framework of the implementation of GCI-VI and ADF-12 matrices,

Management has taken steps to revamp Bank operational policies. The Urban Development

Strategy, the Guidelines on Cancellation of Loans, Grants and Guarantees, and the

Presidential Directives on De Facto Governments have been approved in 2011. Work is at an

advanced stage for the following operational policies: (i) Disclosure of Information Policy;

(ii) Policy-Based Operations (PBOs) Policy; (iii) Energy Sector Policy and Private Sector

Development Policies; (iv) Board Approval Procedures for Private Sector Operations; and (v)

Review of Bank Group ICT Operations Strategy.

12

62. The Bank will finalize the above-mentioned policy papers in 2012 after intensive

external consultation processes which have already been launched. Furthermore, guidelines to

these policies will be prepared to assist Bank staff during the implementation phases.

4. INDICATIVE NON-OPERATIONAL WORK PROGRAMME (INOP)

63. The Indicative Non-Operational Work Programmes (INOP) are designed to continue

building an institution that can deliver results. The key reforms under implementation include

those which are in response to the GCI-VI and ADF-12 commitments. In all, the planned

activities are focused on strengthening institutional governance and coordination, human

resources management, decentralization, risk management and fiduciary services, IT and

business continuity, information disclosure and communication.

4.1 Institutional Governance and Coordination

64. Whenever necessary, Management has taken steps in a timely manner to finetune the

institution to strengthen the governance framework and thus provide coherent strategic

direction and ensure that programmes are implemented and objectives are achieved9. The next

major move is to develop a Long Term Strategy (LTS), and thus establish a clearer

perspective of the Bank’s priorities.

4.2 Human Resources Management

65. The focus in this area is on four issues that came out of the 2010 Staff Survey. These

are: (i) creating an environment of openness and trust to support a high performing

organization; (ii) improving rewards and recognition; (iii) facilitating and improving upward

communication; and (iv) improving staff retention. Programmes under preparation to address

these issues include efforts from HR Department, Office of the Ombudsman, Ethics Office,

and Tribunal.

66. Other key areas under the four pillars of the HR Strategic Framework 2008-2012

which are receiving due attention include: (i) performance management system review; (ii)

new total compensation framework for international and locally recruited staff; (iii) Diversity

Report; (iv) talent management and succession planning programme; and (v) mutually agreed

staff separation policy and case management programme – all of which will be discussed with

the Board during Q4, 2011.

67. The Leadership and Management Development Programme (LMDP) will be

reinforced so as to promote the creation of an enabling work environment that will facilitate

staff retention. There is also a need to fully align the workforce with the Bank’s strategic

priority areas and the Human Resources Strategic Framework. In this regard, external

consultants will work with HR and Senior Management to assess HR systems and processes,

conduct an organizational skills audit, and assist in the development of the next HR strategic

framework in line with the Bank’s priorities as outlined in the MTS and proposed LTS.

4.3 Decentralization

68. Management remains committed to advancing the decentralization programme, with

the aim to improve dialogue and portfolio performance in Regional Member Countries, as

9 Recently, this has included the creation of two committees – Climate Change Coordination Committee (CCCC)

and Permanent Committee on Decentralization (PECOD) – and the transfer of the Quality and Results

Department (ORQR) to the Office of the Chief Operating Officer (COO).

13

well as reinforce coordination and tactical partnerships with other Development Partners. The

recently approved Decentralisation Roadmap articulates the plans Management will

implement in the next few years.

4.4 Risk Management and Fiduciary

69. This covers a range of business areas including financial, security, audit, anti-

corruption and resource management. The additional activities designed are to help further

strengthen the Bank’s capacity to address potential risks associated with the growth in private

sector operations, new lending instruments and the implementation of the new

decentralization paradigm.

Financial risk management

70. Delivery of the GCI-VI commitments under this theme is well on track, including the

recently approved Income Model to strengthen the Bank’s long term financial sustainability.

Going forward, the Bank will gradually move to an economic Capital Risk Management

Framework to enhance the resilience of the institution to unforeseen events.

Security

71. Activities will continue to focus on ensuring full protection of the Bank’s four security

pillars – people, property, information and reputation – by implementing focused activities for

the Field Offices while maintaining improvements at the TRA and preparing the security

environment for a return to Headquarters in Abidjan. In support of the implementation of the

decentralization process, priority will focus on technical and human security enhancements in

the Field Offices and tightening data controls.

Audit and anti-corruption

72. The Office of the Auditor General will be strengthened to enable it to effectively and

efficiently tackle issues on audit, safeguards, governance and control in TRA and also on a

strategic and comprehensive programme of auditing Field Offices.

73. The anti-corruption work will aim to sustain attention on the initiatives recently

launched to help fight fraud and corruption on Bank projects. These initiatives include

ramping up the Bank’s internal investigatory resources, publicizing successful investigations

and sanctions to deter misconduct, fostering partnerships with counterparts in other MDBs

and law enforcement agencies to facilitate information flow, and exploring the use of

technology in monitoring operations. In addition, Management has identified projects to pilot

integrating anti-fraud and anti-corruption measures into the Banks’ operations. Furthermore,

new instruments such as electronic and social media to complement whistle-blowing will be

deployed.

Resource management

74. In line with the Budget Reforms10

, Management has made progress in improving work

programme planning and budgeting, strengthening oversight, raising awareness of cost

savings and efficiencies and streamlining processes. For example, approving budget transfers

is now simpler and faster, and there have been significant improvements in redeploying

resources to meet emerging priorities. In addition, Management has been undertaking

initiatives to build capacity, especially of Resource and Budget Management Coordinators, to

support the devolution of resource management functions to Complexes. These efforts

notwithstanding, experience to date reveals the need for continuous awareness building

10

See Annex 4.

14

among Managers, as well as reinforcing work programme planning and budgeting processes;

fine-tuning processes, guidelines, policies and tools in order to improve efficiencies and cost

savings; and strengthening the performance monitoring framework.

75. On performance monitoring, the introduction of the KPI Dashboard has made high-

level data and information available in an integrated and timely manner, capable of helping

Managers better understand past performance and make informed decisions for sustainability

and/or improvements. Building on this success, Management intends to broaden the scope of

the Dashboard to incorporate other aspects of the Results Measurements Framework.

Additional plans include the introduction of advanced analytical tools to equip VPUs with

techniques on designing and monitoring Key Performance Indicators.

76. Engagements with VPUs have increased the awareness of the need for better planning

and evidence of generated savings and cost cuts. Nevertheless, Management will continue to

press for more improvements in these areas. Specifically, it will continue to reinforce its

coordination among Complexes on these issues, while simultaneously accelerating ongoing

efforts to ensure the success of the newly introduced Activity Time Recording System

(ATRS) as a major input to the implementation of the Cost Accounting System (CAS), which

will further sharpen planning and budgeting. Management is still committed to the

introduction of a Productivity Incentive Tax (PIT) to reward line Managers’ efforts for cost

savings and efficiencies. Finally, there are concerted efforts to streamline the use of some

centrally managed budgets, such as training and Field Office recruitments, in order to improve

the efficiency in the use of these resources.

4.5 Information Technology and Business Continuity

77. Management is working on a new Business Technology Strategy (BTS) that will guide

future developments in the Bank’s information systems and infrastructure. A fast and reliable

IT platform is the bedrock for delivery in a decentralised environment. Under the strategy,

therefore, predominance will be given to strengthening connectivity, advancing automation of

business processes, and transforming the ICT infrastructure to support the institution’s agenda

on “Greener Bank” and knowledge work.

78. In light of the events in North Africa since the start of 2011, Management will do

more to further strengthen the Business Continuity Plan (BCP). Activities already planned

include deploying advanced back-up tools and systems; conducting routine technical and

functional tests to assess the effectiveness of its backup site in cases of emergencies; and

undertaking regular crisis management simulation exercises for staff in TRA and FOs.

Furthermore, there are plans to integrate IT and BCP requirements in the renovation of the

HQ building in Abidjan and in the pilot RRCs, and also in the acquisitions/construction of

FOs as the Decentralization Roadmap is rolled out.

4.6 Information Disclosure and Communication

79. Management is currently revising the Disclosure Policy, and it is scheduled for

consideration by the Board by early 2012 The aim going forward is to develop a framework to

ensure compliance, and monitor and report on its implementation. Furthermore, the Bank has

also signed on to the International Aid Transparency Initiative (IATI).

80. Priorities in the core communication functions are on rebranding the Bank’s image,

monitoring and evaluating the efficacy of messages and communication channels, and re-

positioning communications to meet the needs of the Bank’s Decentralization Roadmap.

15

5. RESOURCE IMPLICATIONS

81. In response to increasing demands, the Bank has grown and, in the process, has

regularly fine-tuned its structure and changed its business model. As already discussed,

Management has decided to adopt a conservative approach in determining the 2012 resource

envelope. However, Management is also acutely aware that, within the zero real growth

framework, there is a need to maintain an acceptable budget level in support of the activities

planned to face the upcoming challenges on the African continent, e.g. implementing the

Decentralization Roadmap; responding to the recent developments in North Africa, South

Sudan, Somali and Cote d’Ivoire; and also to protect its gains by providing for activities to

safeguard the Bank’s ability to deliver. The key activities include strengthening support to

Fragile States, a Business Continuity Plan, and a more robust Enterprise Risk Management

Framework.

5.1 The Budget Framework for 2012-2014

82. In deciding on a plausible budget framework for funding the 2012-2014 work

programmes, two considerations were predominant. The first relates to the need to promote

efficiencies and cost effectiveness to contain the growth in administrative spending within

sustainable levels. The second is that the Bank will do more in 2012 and beyond.

83. To support effective delivery in its priority areas, the Bank would need to deploy

additional budgetary resources to the concerned Cost Centres. For decentralization in

particular, significant investments are required to help roll out the Roadmap as discussed in

paragraph 68.

84. In order to establish a realistic baseline for the 2012-2014 budgets, Management has

taken into consideration a number of key issues involving staffing, leveraging trust funds, cost

savings, and improved efficiency in business processes and resource management.

85. Staffing: 2012 will be a year of consolidation and rationalization. The objective is to

improve HR management, boost the recruitment rate and, most importantly, to optimize the

deployment of the Bank’s staff and existing vacancies. Useful lessons have been drawn from

the results of the two last Staff Surveys, while the high levels of vacancies have been a major

contributing factor to the underutilization of the budget (unspent provisions for recruitment

costs, settlement, benefits and overheads).

86. To address the vacancy issue and optimisation in the use of available competences,

Management has decided that, within the requested 2012 total budget envelope, the Bank will

not have provision or headroom for the creation of new staff positions. Instead, Management

will redeploy 2011 vacancies, which will be carried into 2012, across the Bank to meet needs

in priority areas. The Bank will not request provision or headroom for the creation of new

headcount under future Budgets until Management has taken stock of the outcome of the

review of the implementation of UA Budgeting, including the impact of the removal of the

headcount control. The 2011 staff allocation by Complex as at end of October is given in

Annex 5.

87. Leveraging funding from trust funds: As part of ongoing efforts to mainstream trust

funds into the Administrative Budget planning process, Management will undertake a

comprehensive review of the sourcing, purpose and management of existing trust funds to

ensure that they are demand-driven and in alignment with the Bank’s business needs.

16

5.2 The 2012 Baseline and Estimates

88. The proposed budget for 2012 reflects a concerted effort to address the conflicting

demands of an ambitious and adequately resourced Work Programme in a fiscally constrained

environment. It has been built using a base budget corresponding to 95% of the 2011

“Adjusted Budget” 11

as per the Budget execution KPI target, and then adjusting it to reflect

the budgetary resources that VPUs estimated for enhancements in priority areas and new

initiatives. It also factors in cost savings and efficiency gains.

89. From the foregoing, the base budget for 2012 is projected at UA 272.16 million, to

which Management proposes to add a total of (i) UA 17.27 million to fund the planned

enhancements in the key ongoing activities; (ii) UA 4.09 million representing the projected

adjustment to staff compensation12; and (iii) UA 4.37 million to cater for the impact of

inflation13

. It is worth noting that Management has decided to absorb part of the new

requirements (i.e. UA 5.32 million) through trade-offs, cost savings and efficiency gains

efforts14

.

90. The proposed resource envelope for 2012 amounts to UA 292.55 million. It represents

an increase of UA 3.41 million (nominal + 1.18%) compared to the 2011 Approved Budget

and UA 6.08 million (nominal + 2.12%) compared to the 2011 “adjusted budget”.

91. The 2.12% increase in the 2012 Administrative Budget is composed of a: (i) 1.52%

price adjustment; (ii) 1.43% provision for salary adjustment; and (iii) -0.83% volume factor.

92. The 2013 and 2014 Indicative Work Programmes will require projected

Administrative Budgets of UA 301.17 million in 2013 and UA 305.78 million in 2014,

showing increases of UA 8.62 million (2.95%) and UA 4.60 million (1.53%) respectively.

5.3 Major Cost Drivers

93. The 2012 Budget envelope is mostly driven by enhancements made to the key

activities in the Bank’s current Work Programme, new initiatives and Staff Compensation

Adjustment. The enhancements and new initiatives are articulated around the: (i) enhanced

Decentralization Programme to reinforce presence on the ground; (ii) improvements in the

management of the Bank’s Human Resources; (iii) Business Continuity Programme in

response to the need for robust preparedness to deal with unforeseen emergencies; (iv)

improvement of the Bank’s Operations through better services and assistance, and reinforced

policy advocacy role through knowledge sharing and dialogue; and (v) strengthening

Corporate Governance.

11

The 2011 Budget used as the basis for projections excludes the UA 2.05 million budgeted for the obligations

on the Aniaman Building in Abidjan – for which an accounting provision was made in the 2010 Financial

Statement – and UA 0.61 million from the ringfenced UA 1.47 million allocated for the opening of External

Representation Offices in 2011. As recently agreed with the Board (Document ADB/BD/WP/2011/103), only the

Tokyo Office will be opened in 2011. 12

Proposal for 2012 salary increases and changes in Salary and Benefits Policies; ADB/BD/WP/2011/163/Rev.2. 13

A 4.4% inflation rate has been applied to all expenditures, excluding salaries and benefits. Annex 6 discusses

the inflation rate calculation method and the factors of 2012 Budget increase. 14

See Annex 7 for additional efforts towards cost savings and efficiency gains.

17

5.3.1 Decentralization Implementation Enhancement15

94. Information & Communications Technology improvement (UA 2.64 million): ICT

being a critical platform for the success of the Bank’s Decentralization Programme, the

proposed allocation is to fund the planned strengthening of the ICT infrastructure, the

improvement of its connectivity and to cater for software licenses, database hosting and

satellite fees.

95. Regional Resource Centres (UA 4.43 million): The proposed allocation comprises the

costs of resettlement/relocation of staff to the two pilot centres, for upgrading the Kenya

Office, and for satellite access fee for both Regional Resource Centres.

96. Decentralization Roadmap and field presence (UA 0.79 million): The allocation is to

support: (i) strengthening fiduciary function in existing FOs; (ii) opening a Field Office in

South Sudan and establishing a presence in Mauritius; and (iii) general activities to be

undertaken by the Bank in implementing the Decentralisation Roadmap. With the Bank’s

increased presence in Fragile States, Management plans to strengthen donor coordination,

provide capacity building support, and provide training to Bank staff in these countries to

develop their expertise in conflict and inclusive growth analysis.

5.3.2 Human Resources

97. Staff Compensation Adjustment and additional benefits to support decentralization

(UA 4.09 million)16

: This is, firstly, to support decentralization and to improve diversity and

recruitment of local staff; and secondly, to enhance the Bank’s competitiveness and improve

the positioning of the grades that are below our current benchmarks vis à vis the reference

market, while taking into account the global economic environment and budgetary

constraints.

98. Improve work conditions (UA 0.27 million): To improve the staff work conditions and

environment, the Bank intends to rent a new building in Tunis and also open a fitness centre

for staff. The allocation will fund the rent and the new building security expenses.

99. Human resources management (UA 0.21 million): In the framework of the

improvement of HR Management, the budget will be used to strengthen the Zahrabed Medical

Centre, which was opened and became operational this year.

5.3.3 Business Continuity

100. Business Continuity Plan – BCP (UA 1.9 million): The budget is to cater for the costs

of planned overhead expenses. These costs are related to BCP site rental and maintenance,

electricity, water, IT connectivity, and office security.

101. Additional risk insurance (UA 1.00 million annual premium): This is a special

coverage whose main objectives are to: (i) update the existing Political Risks Policy,

including the coverage of expenses related to activation of the BCP – concept of "forced

abandonment"; (ii) update the costs and capital to be ensured (from the current coverage of

EUR 3 million to EUR 30 million) to cover the maximum of the expenses related to a

possible trigger of the Business Continuity Plan; and (iii) introduce "monetized" franchises in

place of current franchises which are expressed in days.

15

The cost of the Bank’s Decentralization Programme from 2009 to 2012 is given in Annex 8 16

Refer to Document ADB/BD/WP/2011/263/Rev.2

18

5.3.4 Operations Improvement, Enhanced Safeguards and Policy Advocacy

102. Special Country Initiatives (UA 0.90 million): The proposed allocation is to help

sustain the momentum of Bank work in the light of the specific developments which have

been taking place in some of the Bank’s client countries.

103. Governance (UA 0.54 million): The proposed allocation is to fund scaling-up of

knowledge work on governance in the continent and strengthening regional governance

initiatives and partnerships.

104. Food security (UA 0.51 million): There is a global action, addressing the food crisis in

the greater Horn of Africa. The Bank’s contribution is to assist the countries concerned

develop appropriate policies to meet the local conditions and provide sustainable solutions to

the food crisis caused by recurrent drought and floods.

105. High Education, Science & Technology – HEST (UA 0.39 million): Work on this

area has started taking shape, and the focus in 2012 and beyond will be on youth employment,

and the broader programme includes analytical work on the employment policies and

matching training and skills requirements.

106. Fiduciary safeguards (UA 0.35 million): The budget provision is for reviewing

existing fiduciary safeguard frameworks, strengthening independent ex-post reviews, and

training staff in FOs in monitoring and supervising procurement and disbursement activities

in Bank-financed projects.

107. Operations evaluation (UA 0.35 million): The requested envelope is to finance the

new initiatives related to the review of the evaluation function; the Thematic and Quality at

Entry evaluations; and the private sector projects evaluations.

108. Knowledge and analytical work (UA 0.28 million): The funds are earmarked for

requests from RMC governments, in implementing country infrastructure actions plans, and

support to recovery programmes and monetary policies.

109. Fragile States (UA 0.24 million): This is to scale-up work in supporting fragile states

to move out of fragility. In order to do this, there will be an increase in the country-by-country

conflict analysis and inclusive growth studies.

110. Policy outreach and public consultations (UA 0.20 million): The Bank will conduct

outreach and public consultations for a number of policies, namely (i) Disclosure and Access

to Information Policy; (ii) Program-Based Operations Policy (PBOs); (iii) the Energy Sector

Policy; and (iv) the Private Sector Development Policy. These consultations will ensure that

the Bank Group’s operational policies reflect stakeholders’ expectations, are well harmonized

with those of our partner institutions, are fully owned by key internal and external

stakeholders, and comply with international best practices.

111. Climate Change competences (UA 0.17 million): The targeted Climate Change work

is aimed at building the Bank’s subject matter expertise and developing tools to support the

development and transfer of knowledge and learning to countries.

112. Gender (UA 0.10 million): The proposed envelope is to support the strengthening of

the Bank’s knowledge and advocacy work, including planned activities during the 2012

Annual Meetings.

19

5.3.5 Corporate Governance

113. External Representation Offices – EROs (UA 1.56 million): Following Board

decision on the establishment of the EROs, the Bank is going to start light this year with the

Tokyo office, but with the expectation that full scale operations will gain momentum in 2012.

This is also the year in which the Office in Washington DC is slated to be opened and start

operations. Thus, the budget provision is based on full year operation of both offices.

114. Information disclosure (UA 0.19 million): The planned activities that the allocation

will fund are the preparation of an Information Disclosure Handbook, monitoring the

implementation of Information Disclosure Policy (IDP), and training of staff at TRA and the

Field Offices.

5.4 Summary of the 2012 Administrative Budget

5.4.1 Operation and Non-Operation Complexes

115. Budget plans are revised continually during the planning and budgeting exercise to

reflect Bank priorities and adjustments in response to the changing environment. Consistent

with budget principles and preceding discussions, the proposed allocations for Complexes go

largely to meet the operational demands in support of the post-crisis transitions in North

Africa, strengthening our engagements in Sudan and South Sudan, and increasing our

presence in RMCs, especially in Fragile States.

116. While capitalizing on the gains of the budget reforms in terms of alignment of the

Work Programme and allocation of resources with the strategic priorities, difficult arbitrations

and choices still had to be made in the final distribution of the proposed envelope among the

various Complexes. Particular attention was given to recent growth patterns and demonstrated

efficiency and prudence in the use of resources.

117. Detailed budget proposals by Complexes and category of expenses are provided in

Annex 9. Below are the changes in budget allocation by Complex groupings.

Funding for Operational Complexes is projected at UA 143.12 million,

corresponding to an increase of UA 2.83 million (2.02%) over the 2011 adjusted

budget. Among the Operational Complexes, ORVP receives UA 54.81 million, i.e.

3.95% increase, primarily to support its involvement in the deepened decentralization

programme. OSVP’s allocation is UA 32.48 million (-0.62%). Funding to OIVP is UA

41.20 million representing an increase of 3.21% compared to its 2011 adjusted budget.

The Complex has increased its focus on climate change; yet major operational work in

this area is not expected to kick in until 2013. ECON’s budget of UA 14.63 million

decreases by 2.21%.

CSVP: Funding to CSVP is projected at UA 30.00 million (-4.64%). The decrease of

CSVP budget is due to the decrease of its Workload (i.e. Missions, Consultancy,

Representation and STS) budget.

FNVP: The Complex budget will decrease slightly (UA 22.36 million in funding, i.e.

0.79% decrease). However, the Complex will receive a minor increase in its overhead

budget to enable the implementation of activities related to risk management.

Units Reporting to the Presidency (UPRST): An increase of 5.27% (UA 2.13

million) is projected for this very diverse Complex. The key drivers are the expanded

20

work on climate change, strengthening the security and fiduciary safeguard functions,

and establishing External Representation Offices (EROs). As a result, the respective

budget allocations for ORQR, SECU, OAGL, IACD, GECL, and COO (EROs) have

increased. The funding for the EROs took into account the full year funding for the

Tokyo Office and the opening of a new one in Washington, DC.

5.4.2 Board and Units Reporting to the Board of Directors

118. Overall projected allocation for the Board of Governors and Executive Directors,

OPEV, TRIB and CRMU is UA 23.08 million. This is 1.22% lower than the 2011 adjusted

budget. Funding for OPEV amounts to UA 5.08 million, which is 4.26% higher than its 2011

adjusted budget.

5.4.3 Special Appropriation

119. Staff Retirement Plan (SRP): Contributions to the Retired Benefit Plans are projected

to increase to UA 20.28 million in 2012, from UA 19.61 million in 2011 (3.43%). The Bank’s

contribution to the Staff Retirement Plan represents 18% of the Bank’s total staff salary

envelope. In 2012, the positions previously budgeted for nine months (2010 carried-over

vacancies) and seven months (2011 new positions) have been annualized, thus impacting on

the Bank’s contribution to the SRP.

120. Young Professionals Programme (YYP): The policy17

of the programme was reviewed

and discussed with the Board of Directors on 9 February 2011. The objective was to agree on

solutions to problems resulting from the management of the programme. One of the

recommendations of the review was the creation of a pool of positions to be allocated to the

programme and facilitate/accelerate the absorption of YPs across the Bank. The reduction

(UA 1.72 million) observed in the 2012 budget envelope of the programme is the result of

that rationalization. However, it is important to note that the minimum annual intake of YPs

remains the same, i.e. 20 YPs per year as per the initial policy document18

. Management has a

high regard for the YPP, which was reintroduced in 2007.

6. PERFORMANCE REVIEW AND MONITORING FRAMEWORK

6.1 2012-2014 Monitoring Framework

121. On the results monitoring side, the Bank will identify growth drivers and assist in

steadily eliminating growth bottlenecks and other infrastructure impediments (transport,

connectivity and energy deficit) that stand in the way of faster economic integration and

inclusive growth.

122. During the 2012-2014 period, the Bank will leverage on its IT infrastructure and will

also continue to intensify efforts towards instilling a robust culture of performance monitoring

within the institution. The Bank has been engaged for several years in a process of continuous

improvement of its monitoring framework.

123. In 2011, an action plan to achieve this objective was developed around the following

activities: (i) improving the Key Performance Indicators to better respond to expectations; (ii)

enhancing the work on Quality Indicators to close the gap between performance monitoring

and results monitoring; (iii) developing specific reports on the outputs/outcomes of the

projects financed by the Bank in RMCs; (iv) taking advantage of new analytical tools (WBS

17

Ref. ADB/BD/WP/2010/167/Rev.1 18

Ref. ADB/BD/WP/2008/29/Rev.1

21

and ATRS) that have been implemented as part of the introduction of a Cost Accounting

System; (v) improving communication, facilitating access to information and developing staff

capacity; and (vi) strengthening the collaboration and dialogue with other International

Financial Institutions (IFIs).

124. The implementation of this plan will continue throughout the 2012-2014 period.

However, it is worth noting that the first results are expected by the end of 2011.

125. Annex 10 gives the list of Institutional KPIs and the 2012-2014 yearly targets.

6.2 Productivity, Efficiency Gains and Cost Savings

126. There is continuous evidence that the Bank is making worthy progress in the efficient

use of resources. Bank Group productivity indicators confirm that core operational processes

are being implemented in a more cost-effective manner since 2006. An analysis of the three-

year rolling average shows that administrative expenses for every UA million lent will decline

from UA 73,130 during 2006-2008 to UA 53,330 in 2012-2014. Also, for every UA million

disbursed, there will be a decline from UA 124,450 for 2006-2008 to UA 84,270 during 2012-

2014 (see Figure 3 below).

127. Management is determined to leverage internal processes improvement for maximum

efficiency to contain budget growth, and deliver more and better with less. Evidence of past

achievements in this area is the Bank Group’s excellent ranking (for the second consecutive

year) on maximizing efficiency19

. Management will continue to strengthen its monitoring and

controlling activities to retain top rating and, above all, contribute to producing results on the

ground.

128. Through various measures, UA 8.97 million was identified as expected efficiencies

and savings in the planned Administrative Expenses for 2012 (see Annex 7). This amount was

factored in to reduce the total proposed budget envelope.

19

In its 2nd

edition report titled “Measuring the Quality of Aid”, published in November 2011, the Center for

Global Development ranked the African Development Fund (AfDF) “Number 1” out of 31 Development

Partners on “Maximizing efficiency”, with “Low administrative unit costs” as one of the criteria. AfDF was

ranked Number 2 in the October 2010 edition.

22

Figure 3: Productivity Indicators (3-year rolling average 2006-2014)

(in UA ’000)

7. RESOURCE ESTIMATES

7.1 Internally Generated Resources

129. The main revenue and expense components that make up net income are loan income

and investment income on the revenue side, and financial charges, net administrative

expenses and loan loss provisions on the expenses side. The estimates of these various

components are made on the basis of certain underlying assumptions essentially related to the

lending programmes, market interest rates and the cost sharing formula. These assumptions

and the allocation of administrative expenses for 2012 are summarized in Annex 11A.

130. Based on these assumptions the total operational income of the Bank Group will vary

between UA 436.33 million and UA 558.26 million over the next three years as summarized

in Annex 11B. After providing for administrative expenditures, estimated net income before

distribution approved by the Board of Governors for the Bank Group is projected at UA

109.70 million in 2012 and expected to reach UA 217.80 million in 2014. The chart in Annex

11B presents the Bank Group Operational Budget and Net Income Estimates for 2012.

131. In 2011, ADB is projected to report a net income before distribution approved by the

Board of Governors of UA 164.39 million, and an allocable income of UA 167.57 million

after excluding the impact of non-cash elements such as provisions for impairment, unrealized

gains or losses on fair value items and translation gains or losses. For 2012, 2013 and 2014,

the projected allocable income of UA 168.99 million, UA 207.57 million and UA 245.21

23

million respectively should enable the Bank to continue to strengthen its risk bearing capacity,

while transferring a portion of the net income to mandatory developmental initiatives.

132. ADF is projected to report deficits20

of UA 86.26 million and UA 62.03 million

respectively in 2011 and 2012. These are mainly due to the current low interest rate

environment and the impact of the amortization of the discount on accelerated encashment

notes. The return of the benchmark for the ADF Operational portfolio, which reflects three

month LIBOR rates21

, decreased significantly from 5.32% in 2007 to 3.84% in 2008, 0.93%

in 2009, 0.45% in 2010 and 0.33% in 2011 (August YTD). This deficit is structural22

and will

be discussed in more detail with the Board during the presentation on the Long Term

Financial Sustainability Framework of the Fund that is scheduled for mid-January 2012.

133. NTF net income is expected to range between UA 2.74 million and UA 2.82 million

during the PBD period.

7.2 Trust Funds and Co-Financing

134. In the face of continued economic uncertainties and emerging development challenges

in RMCs, mobilization of complementary resources has become more important. As at end

July 2011, UA 68.1 million has been mobilized for bilateral and thematic funds. From

January to July 2011, UA 46 million has been approved for 41 trust fund projects. Some 294

trust fund operations totalling UA 256 million are being implemented in support of the Bank’s

knowledge and analytical work, project preparation and capacity building in RMCs.

135. Management continues to encourage donors to pool resources into multi-donor

thematic funds. In 2011, Sweden joined the Multi-Donor Governance Trust Fund. Brazil

established a Trust Fund to promote South-South Cooperation, which is intended to become a

multi-donor fund upon confirmation of other donors’ contributions. The Danish-supported

Sustainable Energy Fund for Africa, approved by the Board in July 2011, is also intended to

be converted into a multi-donor fund.

136. In 2011, the Gates Foundation joined the African Water Facility. The proposed Aid for

Trade Fund initiated by Canada will be launched as a multi-donor fund as soon as the second

donor is confirmed. Other newly proposed thematic funds include those in Higher Education,

Science and Technology; Fund for Agricultural Statistical Capacity Building; and the Africa

Green Fund.

137. Co-financing is increasingly crucial to leverage the Bank’s resources. More structured

co-financing arrangements will be pursued with partners, while existing co-financing

arrangements with Korea (USD 400 million), the Islamic Development Bank (USD 500

million) and through the African Financing Partnerships will be fully tapped. The second

phase of the Enhanced Private Sector Assistance (EPSA) will be launched with Japan in 2011.

8. 2012-2014 CAPITAL BUDGET

138. The proposed Capital Expenditure Budget for the 2012-2014 period is expected to

amount to UA 46.05 million – UA 20.59 million in 2012, UA 22.25 million in 2013 and UA

3.21 million in 2014 (see Annex 12).

20

Projections are based on the best available information at the time they are generated and are subject to

change. 21

The benchmark reflects LIBOR rates primarily in USD and EURO which represent more than 90% of the

portfolio. 22

As ADF loan charges are fixed, ADF will only report a profit when short term market interest rates increase.

24

139. Out of the requested 2012 Capital Budget, UA 9.86 million is planned for office

equipment and office furniture acquisition, civil and outfitting works, and vehicles

replacement/acquisition; UA 10.43 million is for IT projects; and UA 300,000 is for the

enhancement of the Bank’s security systems and equipment.

8.1 Civil and Outfitting Works

140. The 2012 Investment Programme submitted to CIPSC for approval amounts to UA

9.86 million. It is strongly oriented towards the support of the Bank’s decentralization policy

and it supports the Bank’s commitment to build capacity to continue to deliver on its mandate

despite potential crisis situations that may arise in the various countries where the Bank is

present.

141. Temporary Relocation Agency (TRA), Tunis: UA 1.40 million – As part of the

outfitting works of a new building, an amount of UA 1.00 million is requested in 2012 for the

acquisition of office furniture. Also, as part of the building works and acquisition of

miscellaneous equipment, UA 400,000 is required for various outfitting works, air

conditioning strengthening, and Simultaneous Interpretation Equipment acquisition.

142. Field Offices (FOs): UA 8.46 million – An amount of UA 4.95 million will be used to

set up the Regional Resource Centres (RRCs) in Kenya and South Africa. The capacity in the

RRCs takes into account the BCP component. The requested budget includes outfitting works,

office furniture and office equipment acquisition for the office operations.

143. To give logistical support to FOs, an envelope of UA 1.50 million will be for the

renewal of office furniture and office equipment and the replacement of vehicles in some

offices. There are also plans for outfitting works to meet additional space requirements

resulting from changes in staffing in some offices. In a number of countries, the buildings

occupied by the Bank do not offer the possibility of extension and/or had seen their security

environment declining in recent times. Following the recommendations of the Bank’s

Security Unit, there are plans to relocate the concerned offices. Under the proposed expansion

of existing offices, an amount of UA 1.20 million is budgeted for 2012.

144. An amount of UA 510,000 is planned for the upgrading of the Bank’s presence in Juba

to a full-fledged Office for South Sudan. In accordance with the commitment made by

Management to the Boards, a study will be undertaken, at a total cost of UA 300,000, to: (i)

update the previous study on the acquisition of office space in the existing FOs; and (ii) on

office space in the recently opened offices.

145. Headquarters, Abidjan: No allocation is requested in 2012. It will be recalled that a

total of UA 47 million was approved in June 2009 (Resolution B/BD/2009/14) for the

renovation of the Headquarters Building. However, progress has been seriously limited,

largely due to the crisis in Cote d’Ivoire. Currently, UA 41 million is available and it is

considered more than sufficient to cover the anticipated expenses during 2012. The remaining

balance will be included in the 2013 Budget.

8.2 IT Investments

146. In the area of IT investments, the 2012-2014 portfolios are grouped in two key

categories: the ongoing projects and the new projects. The total 2012 budget envelope

submitted to ISSC for approval amounts to UA 10.43 million.

25

Ongoing projects: UA 6.12 million – The key projects in this category relate to those

in the IT Action Plan approved by the Board in 2009. The Action Plan is a remedial

roadmap to address burning issues and recommendations raised in recent audits and

studies. Major projects are directed at ensuring connectivity to the FOs and improving

resilience and stability of both the local and wide area networks; replacement of

obsolete IT equipment; supporting the Bank’s decentralization roadmap; improving

business processes to make them more agile, efficient and responsive to the needs of

the Bank and the RMCs (including SAP System upgrade); enhancing IT systems that

support fiduciary services, human resources, financial and risk management activities

of the Bank; and enhancing systems that promote institutional knowledge collection

and dissemination, and management of knowledge as an institutional asset.

New Projects: UA 4.31 million – The key projects planned in the 2012-2014 period

include Financial Risk and Treasury Systems, Knowledge and Enterprise Information

Management, and IT security and Private Sector Equity Funds Management.

8.3 Security Investments

147. An amount of UA 300,000 is required to purchase non-IT systems and equipment to

strengthen the security of the Bank’s property and personnel at ATR and in the FOs, including

South Sudan Office.

9. CONCLUSION AND RECOMMENDATIONS

148. The 2012-2014 Programme and Budget has been prepared in a particularly

challenging fiscal context. It will probably be implemented in an environment marked by

sustained economic turbulence – in Africa and internationally. The Bank is required to

demonstrate prudence, while being credibly responsive to the expected high demands from its

shareholders and clients. Building on the results of the recent review of the 2008-2012 MTS,

the 2012-2014 Programme and Budget will serve as the basis for continuing to improve

execution and results, ensure business continuity in the case of unforeseen upheavals, protect

the Bank’s investment, and maintain its financial solidity and long term sustainability.

149. The Bank Group’s projected operational income amounts to UA 436.33 million, UA

487.64 million and UA 558.26 million for 2012, 2013 and 2014 respectively. Taking into

account the proposed 2012 Budget request and the projected Bank Group’s annual operational

income for the same year, the projected Allocable Income amounts to UA 168.99 million in

2012, UA 207.57 million in 2013 and UA 245.21 million in 2014.

150. Table 2 below indicates the proposed Administrative Budget, its derived Contingency

Budget and the Capital Budget envelopes for 2012, 2013 and 2014.

Table 2: 2012 Budgets and Projections for 2013 and 2014 (in UA million)

2012 2013 2014

Administrative budget 292.55 301.17 305.78

Contingency budget 2.92 3.01 3.05

Capital budget 20.59 22.25 3.21

151. Management invites the Board of Directors to consider the proposed 2012-2014 Work

Programmes, approve the 2012 Administrative, Contingency and Capital Budgets, and take

note of the budget projections for 2013 and 2014.

26

ANNEXES

27

List of Annexes

Annex 1 Achievement in Staff Recruitment

Annex 2 Bank Group Performance as at 30th November 2011

Annex 3 2012 Indicative Operational Programme

Annex 4 Update on Budget Reforms

Annex 5

Annex 5A

Annex 5B

Staff Allocation by Complex

- 2011 Staff Distribution by Complex

- Historicall Staffing Data by Complex

Annex 6 Note on Inflation Rate used in the 2012-2014 Programme and Budget

Document and Factors of 2012 Budget Increase

Annex 7 2012 – Planned Efficiencies and Measures with Expected Savings in

Administrative Expenses

Annex 8 Costs of Decentralization from 2009 to 2012

Annex 9

Annex 9A

Annex 9B

2012-2014 Budget Proposals by Complexes and Category of

Expenses

- 2012-2014 Budget Proposals by Complexes

- 2012-2014 Budget Proposals by Category of Expenses

Annex 10 List of Institutional KPIs and 2012-2014 Yearly Targets

Annex 11

Annex 11A

Annex 11B

Assumptions & Allocation of Administrative Expenses and Detailed

Operational & Net Income Estimates 2011-2014

- Assumptions and Allocation of Administrative Expenses

- Detailed Operational and Net Income Estimates 2011-2014

Annex 12

Annex 12A

Annex 12B

2012-2014 Proposed Capital Budget

- Proposed Budget by Type of Investment

- Detailed 2012-2014 Proposed Investment Programme

Annex 1

Achievement in Staff Recruitment

1/1

Between 2007 and 2010, a total of 1,009 staff have been recruited, representing an annual

average intake of 252 new staff (or an annual average of 16% of total staff at post). In 2011, a

total of 131 new staff have joined the Bank as at 31st October, representing 7% of the total

Bank staffing at post. In addition, 60 candidates have been given job offers and are awaiting

assumption of duty.

Between January and 31st October 2011, a total of 147 staff have been promoted through a

competitive interview process.

Management has proposed that, within the requested 2012 total budget envelope, the Bank

will not have provision or headroom for the creation of new staff positions. Instead, the focus

will be on filling the approximately 200 vacant positions projected to be carried over from

2011 to 2012. Management will redeploy vacancies to priority areas. A skills assessment will

also be conducted in 2012 as part of efforts to align resources with strategic priorities.

Recruitment Efforts: 2007 to 2011

2007

2008

2009

2010

2011

(as at 31 Oct)

Staff at Post

EL/PL 783 846 989 1,064 1,105

GS 531 595 631 688 689

Total 1,314 1, 441 1, 620 1, 752 1, 794

New Hires

EL/PL 145 137 198 143 94

GS 111 93 81 101 37

Total 256 230 279 244 131

% of New Hires 19% 16% 17% 14%

7%

Promotions

221 152 147

% of total staff

14% 9% 8%

Annex 2

Bank Group Performance as at 30th November 2011

1/2

Key Performance Indicators (KPIs) Unit Achievement

Nov. 2010

2011

Target

Achievement

Nov. 2011

Implementation

Rate Nov. 2011

I - Development Financing Operations

Total Bank Group Financing (1) UA million 2,627.50 5,520 3,617.15 66%

ADB Public Lending UA million 604.36 2,490 1,609.53 65%

ADB Private Lending UA million 1,120.45 1,110 839.61 76%

ADF Financing UA million 902.69 1,900 1,158.01 61%

NTF Financing UA million N/A 20 10 50%

Bank Group Financing Leverage Capacity

ADB Private Sector Arranged Financing UA million N/A 400 373 93%

PS Co-financing Project Investments UA million N/A 6,720 6,940 103%

ADB Private Sector engagement with LIC (2) % N/A 30% 71%

II – Operational Strategy Papers

RISPs Number N/A 1 1 100%

CSPs and Related Documents (3) Number 18 31 29 94%

CPPRs Number 1 5 3 60%

CPPRs prepared by FOs % N/A 25% 66%

ESWs and Related Papers Number 46 44 43 98%

III – Economic Knowledge Products

Publication (Books, WPs, Briefs, Flagships, Bank Annual Report

Number N/A 130 130 100%

Support for Results Measurement and Development

Effectiveness in Bank Operations (ADOA, Statistical Support)

Number N/A 54 64 119%

Capacity Development and Knowledge Sharing

(Training, Statistical Capacity Building, Conferences, Seminars, Eminent Speakers)

Number N/A 268 275 103%

IV - Disbursements

Bank Group Amount UA million 2,212 3,553 2,689 76%

ADB Public Amount UA million 839 1,322 1,245 94%

ADB Private Amount* UA million 344 730 377 52%

ADF Amount (4) UA million 1,024 1,497 1,059 71%

NTF Amount (4) UA million 5 4.3 9 199%

Bank Group Ratio (Investment only) % 18% 30% 16%

ADB Public Disbursement Ratio % 18% 20% 14%

ADB Private Disbursement Ratio % 33% 50% 33%

ADF Disbursement Ratio % 16% 20% 15%

V- Portfolio Management

Projects at Risk % 36% 40% 31%

Operations Supervised Twice a Year % 49% 50% 74%

Projects Managed by Field Offices % 19% 20% 20%

Supervisions Led by Field Offices % N/A 20% 32%

New Projects with Core Sector Indicators (CSIs) % N/A 75% 100%

Impaired Loan Ratio (Non-Sovereign only) % 0.79% <5% 1.45%

VI - Process Efficiency

Lapse of Time between Approval and First

Disbursement Months 11.08 11 12.86

Lapse of Time for Procurement (Goods and Works) Months N/A 8 9.2

Lapse of Time for Procurement (Services) Months N/A 10 9.8

Timely PCR Coverage % 96% 85% 93%

VII - Cross-cutting Areas

Gender Mainstreaming in Operations (5) % 100% 100% 97%

Projects accessing Climate Finance (6) Number N/A 3 1 33%

VIII - Human Resources (PL)

Field Based (7) % 26% 30% 29%

Gender Balance % 27% 27% 28%

Staff Age Diversity (8) % 44% 40% 44%

Staff Premature Attrition Rate (9) % 33% 11% 31%

Staff Attrition Rate (10) % N/A 1.6% 2%

IX - Budget and Expenses

Administrative Budget Implementation % 73% 95% 72%

Field Offices Expenses % 12% 17% 13%

Operations (11) Expenses % 50% 60% 51%

Fixed Staff Costs % 62% 87% 67%

New untied trust funds (bilateral/multilateral) UA Million 11.3 100 68.6 69%

% of Bank Operational consultancy committed by

Trust Funds % N/A 55% 46%

Capital Budget Implementation % 58% 33% 66%

X - Implementation of Institutional Commitments (12)

Annex 2

Bank Group Performance as at 30th November 2011

2/2

Key Performance Indicators (KPIs) Unit Achievement

Nov. 2010

2011

Target

Achievement

Nov. 2011

Implementation

Rate Nov. 2011

GCI-VI Commitments Number N/A 18 9 50%

ADF-XII Commitments Number N/A 15 15 100%

*Private Sector Disbursement Amount include Equity participations –Net Disbursements (UA Million 55.22)

(1) Excluding HIPC and ADB special assistance SRF, NTF and other grants.

(2) Expressed as percentage of ADB PS Total Lending.

(3) CSPs and related documents are RBCSPs, Joint Assessment Strategy Papers, Interim Country Strategy Papers, Mid-Term Review

CSPs, Updated CSPs and Completion Reports.

(4) ADF and NTF disbursement targets are extracted from the Financial Projections Report 3Q2011 - ALCO.

(5) % of new projects and new RBCSPs which identify at least one gender equality outcome indicator in the logframe.

(6) Number of newly approved projects accessing Climate Finance Instruments (like CDM, Green Development Fund, etc.).

(7) Considered as % of Operational PL staff (PL staff in the three Operations Complexes, ECON PL staff and PL staff in 100%

Operational Units outside Operations Complexes (ADB/BD/IF/99/330)).

(8) % of PL staff less than 45 years of age (excluding Board Officers).

(9) % of PL leaving the Bank within the first three years of contract in comparison to total PL leaving the Bank in the same period.

(10) PL staff resignations in the first contract in comparison to total PL staff at post (excl. Elected Staff).

(11) Operations defined as ORVP, OIVP, OSVP, ECON, and 100% Operational Units outside Operations Complexes (OPEV, GECL.1,

GECL.2, OPSC, CRMU, FFMA.2, FTRY.4, FFCO.3, CCCC, PECOD and ORQR).

(12) Commitments agreed during GCI and ADF negotiation process. COO will oversee implementation.

Annex 3

2012 Indicative Operational Programme

(in UA million)

1/8

I - PUBLIC SECTOR OPERATIONS - Countries

Item Country

Name Sector Dept Regional Dept Project Title

Sector

Code

Sector

Description

ADB

Public

ADB

Private MIC SRF

ADF

Loan

ADF

Grant FSF

Total

ADF NTF

Co-

Finan-

cing

Other

Trust

Funds

Total

Cost

Fin.

Instru-

ments

1 Algeria ORNB ORNB Etude sur la croissance inclusive et

l'emploi K00 Multi-Sector 1.00 0.00 1.00 GGS

2 Angola OITC ORSB Economic Infrastructure

Maintenance D00 Transport 10.00 10.00 10.00 LLP

3 Angola OSAN ORSB Sustainable Land Management and

Mangroves Conservation (GEF) C00 Environment 0.00 4.00 4.00 GLP

4 Angola OITC ORSB Etude du chemin de fer Angola

Zambia D00 Transport 0.70 0.00 0.70 GGS

5 Angola OSAN ORSB Integrated Support to Market-

Oriented Fisheries Project AAF Agriculture 36.00 36.00 36.00 LSI

6 Benin OSGE ORWA General Budget Support K00 Multi-Sector 20.00 20.00 20.00 LGBS

7 Botswana OSAN ORSA Water Recycling and Harvesting for

Irrigation AA0 Agriculture 10.00 0.00 10.00 LLP

8 Botswana OSAN ORSA Pandamatenga Agriculture

Infrastructure PhaseII AA0

Agriculture

Infrastructure 40.00 0.00 40.00 LLP

9 Botswana OSHD ORSA

Sector Budget Support/

Strengthening of School of Medicie

- University of Botswana

IAD Higher Education 45.00 0.00 45.00 LSBS

10 Burkina

Faso OITC ORWA

Projet de Construction et de

bitumage des routes Dedougou-

Tougan (RN10) et Kongoussi-Djibo

(RN22)

D00 Transport 75.00 75.00 75.00 GLP

11 Burundi OITC OREA Route Makebeko Ruyigi D00 Transport 9.00 4.00 13.00 13.00 GLP

12 Cameroon OITC ORCE Projet d'Aménagement de la Route

Kumba-Mamfe D00 Transport 30.00 30.00 30.00 LLP

13 Cameroon OWAS ORCE Projet d'Assainissement de Yaoundé

(PADY 2) E00

Water Supply and

Sanitation 14.24 14.24 14.24 LLP

14 Cape Verde OWAS ORWB Distribution System /RWSSI E00 Water Supply and

Sanitation 5.00 5.00 5.00 LGS

15 Cape Verde OITC ORWB Projet Extension Aéroport de Praia D00 Transport 30.00 0.00 30.00 LLP

16 Centrafrique OSHD ORCE

Projet d'appui au développement

des services financiers en milieu

rural

K00 Multi-Sector 2.50 2.50 5.00 5.00 LGI

/GGI

17 Centrafrique OWAS ORCE Premier sous programme d'AEPA

en milieu rural E00

Water Supply and

Sanitation 1.04 10.43 11.47 11.47 GLP

18 Centrafrique OSAN ORCE

Projet de Réhabilitation des

Infrastructures de Production

Agricole (PRIPA)

AA0 Agriculture 4.50 4.50 9.00 9.00 LLP /

GLP

19 Chad OWAS ORCE Projet d'eau et Assainissement en

milieu rural E00

Water Supply and

Sanitation 10.06 10.06 20.12 20.12

LLP /

GLP

20 Comoros OSAN OREB Support to Fishery Project AA0 Agriculture 3.60 10.00 13.60 13.60 GLP

21 Congo ONEC ORCE Projet d'électricité en milieu rural FA0 Power Supply -

Electricity 10.00 10.00 10.00 LLP

22 Cote d'Ivoire OSAN ORWA Appu infrastructures Moyen Comoè A00 Agriculture

infrastructure 20.00 20.00 20.00 GSI

23 Dem Rep

Congo OITC ORCE

Projet de Réhabilitation de la route

Batshamba-Tshipaka Lot 2 D00 Transport 53.56 53.56 53.56 GLP

24 Dem Rep

Congo OWAS ORCE RWSSI II E00

Water Supply and

Sanitation 46.67 46.67 46.67 GLP

Annex 3

2012 Indicative Operational Programme

(in UA million)

2/8

I - PUBLIC SECTOR OPERATIONS - Countries

Item Country

Name Sector Dept Regional Dept Project Title

Sector

Code

Sector

Description

ADB

Public

ADB

Private MIC SRF

ADF

Loan

ADF

Grant FSF

Total

ADF NTF

Co-

Finan-

cing

Other

Trust

Funds

Total

Cost

Fin.

Instru-

ments

25 Djibouti OWAS OREB

Development of water resources for

multiple use (domestic, agriculture,

and …)

E00 Water Supply and

Sanitation 3.00 3.00 3.00 GLP

26 Djibouti OWAS OREB Projet d'AEPA en milieu rural et

semi urbain E00

Water Supply and

Sanitation 3.32 3.32 3.32 GLP

27 Egypt ONEC ORNA Egypt Kom Mobo CSP Project FA0 Power Supply -

Electricity 113.33 0.00 113.33 LLP

28 Egypt ONEC ORNA Climate Change Budget Support

Program FA0

Power Supply -

Electricity 155.00 0.00 155.00 LSBS

29 Egypt OSAN ORNA Farm Level Irrigation

Modernization Project AAC

Irrigation and

Drainage 70.00 0.00 70.00 LLP

30 Egypt OSHD ORNA Health Insurance Reform IB0 Health 50.00 0.00 50.00 LLP

31 Egypt OWAS ORNA Water and Sanitation Project E00 Water Supply and

Sanitation 125.00 0.00 125.00 LLP

32 Ethiopia OSHD/OSGE OREB GBS: Protection for basic services

Program III K00 Multi-Sector 120.00 120.00 120.00 LGBS

33 Ethiopia ONEC OREB GHEBBA Hydropower Project FA0 Power Supply -

Electricity 62.47 62.47 62.47 LLP

34 Gabon ONEC ORCE Projet de Ligne de Transmission FA0 Power Supply -

Electricity 130.00 0.00 130.00 LLP

35 Gabon OSGE ORCE Projet d'appui aux réformes et

d'amélioration du climat des affaires K00 Multi-Sector 10.00 0.00 10.00 LGI

36 Gabon OSHD ORCE Projet d'amélioration de la

productivité du travail et de l'emploi IB0 Social 10.00 0.00 10.00 LLP

37 Gambia OSAN ORWB Global Agriculture and Food

Security Program ( GAFSP) AA0 Agriculture 0.00 30.00 30.00 GSI

38 Gambia OSGE ORWB General Budget Support K00 Multi-Sector 3.50 3.50 3.50 GGBS

39 Gambia OWAS ORWB RWSSI II E00 Water Supply and

Sanitation 1.10 1.10 3.58 4.68 GLP

40 Ghana OSAN ORWA Rural Enterprises Project A00

Agriculture and

Rural

Development

50.00 50.00 50.00 LLP

41 Ghana OSGE ORWA Institutional Support Project K00 Multi-Sector 10.00 10.00 10.00 LGI

42 Ghana OSHD ORWA Skills Development for Industry

(HEST) IAD Higher Education 50.00 50.00 50.00 LLP

43 Guinea OSAN ORWB Projet GASFP AAO Agriculture 0.00 30.00 30.00 LLP

44 Guinea-

Bissau OITC ORWB Route Buba catio D00 Transport 4.00 4.00 8.00 8.00 GLP

45 Kenya OSHD OREA HEST I00 Higher Education 23.00 23.00 23.00 LLP

46 Kenya OWAS OREA Thwake Water and Sanitation

Program E00

Water Supply and

Sanitation 70.00 70.00 70.00 LLP

47 Lesotho OSGE ORSA Budget Support K00 Multi-Sector 9.50 7.60 17.10 17.10 LGBS

48 Liberia OSGE ORWB Institutional Support Project K00 Multi-Sector 3.00 3.00 3.00 LGI

49 Liberia OWAS ORWB Water - Study for Rural Water

Supply and Sanitation Program E00

Water Supply and

Sanitation 0.00 1.00 1.00 GGS

50 Liberia OSAN ORWB

Smallholder Agricultural

Productivity Enhancement and

Commercialization (SAPEC)

project

E00

Agriculture and

Rural

Development

4.00 4.00 29.08 33.08 LLP

Annex 3

2012 Indicative Operational Programme

(in UA million)

3/8

I - PUBLIC SECTOR OPERATIONS - Countries

Item Country

Name Sector Dept Regional Dept Project Title

Sector

Code

Sector

Description

ADB

Public

ADB

Private MIC SRF

ADF

Loan

ADF

Grant FSF

Total

ADF NTF

Co-

Finan-

cing

Other

Trust

Funds

Total

Cost

Fin.

Instru-

ments

51 Libya OSGE ORNA Technical Assistance Program for

Econ and Financial Management KA0

Public Sector

Management 0.50 0.00 0.50 GGI

52 Madagascar OITC ORSB Projet de reconstruction de la RN9 -

Phase I D00 Transport 25.00 25.00 25.00 LLP

53 Madagascar OSGE ORSB Appui Institutionnel - PRIBG II K00 Multi-Sector 10.00 10.00 10.00 LGI

54 Madagascar OSHD ORSB Projet formation professionnelle IA0

Technical and

Vocational

Training

10.00 10.00 10.00 LSI

55 Malawi OSHD ORSB Support to Higher Education

Science and Technology I00 Higher Education 13.00 7.00 20.00 6.00 26.00 LSI

56 Malawi OSGE ORSB Support to PFM / General Budget

Support K00 Multi-Sector 30.00 30.00 30.00 GBLG

57 Malawi ONEC ORSB Hydropower Feasibility Study FAD Power Supply -

Electricity 3.00 3.00 3.00 GGS

58 Malawi OSHD ORSB Support to Technical and

Vocational training I00 Higher Education 10.00 10.00 20.00 20.00

LLP /

GLP

59 Mali OITC ORWB Route Sevare-Gao D00 Transport 9.70 9.70 9.70 LLP

60 Mali OWAS ORWB Projet d'alimentation en eau potable EA0 Water Supply 20.00 20.00 20.00 LLP

61 Mali ONEC ORWB Electrification Rurale + SREP

MALI FA0

Power Supply -

Electricity 17.00 17.00 6.25 23.25 LLP

62 Mauritania OSAN ORNB

Adapting Agriculture and Agro-

industry Investment, and

Reinforcing Resilience of agro-

ecosystems to Climate Change

(GEF)

C00 Environment 0.00 4.00 4.00 GSI

63 Mauritania OWAS/OSAN ORNB Programme intégré d'alimentation

en eau dans les zones rurales EA0 Water Supply 2.60 2.90 5.50 5.50 LLP

64 Mauritania ORNB/OSHD ORNB Etude sur la croissance et l'emploi I00 Social 0.00 0.30 0.30 GGS

65 Mauritius OSGE ORSB MIC Grant Project Supporting

Economic Reform K00 Multi-Sector 0.30 0.00 0.30 GGS

66 Mauritius OWAS ORSB Water and Sewerage Program EA0 Water Supply 60.00 0.00 60.00 LLP

67 Mauritius ORSB ORSB MIC GRANT Public Sector

Efficiency K01 Multi-Sector 0.70 0.00 0.70 GGS

68 Morocco OSHD ORNB 2ème phase Programme d’urgence de

l’éducation nationale et d’emploi I00 Education 100.00 0.00 100.00 LLP

69 Morocco ONEC ORNB Projet du plan solaire d'Ouarzazate F00 Energy 168.00 0.00 168.00 LLP

70 Morocco OITC ORNB Projet de Réparation des Ouvrages

de 7 ports D00 Transport 90.00 0.00 90.00 LLP

71 Morocco OWAS ORNB Projet d'AEP de la région de

Marrakech EA0 Water Supply 180.00 0.00 180.00 LLP

72 Morocco OSAN ORNB Programme d'appui au Plan Maroc

Vert A00

Agriculture /

Environment 90.00 0.00 90.00 LSBS

73 Morocco OSAN ORNB

2ème phase du Projet d'appui au

Programme National d'Economie

d'Eau d'Irrigation (PAPNEEI 2)

AE0 Agriculture 72.00 0.00 72.00 LLP

74 Morocco OSGE ORNB

Programme d'appui à la réforme de

l'administration publique (2ème

génération)

K00 Multi-Sector 100.00 0.00 100.00 LGBS

Annex 3

2012 Indicative Operational Programme

(in UA million)

4/8

I - PUBLIC SECTOR OPERATIONS - Countries

Item Country

Name Sector Dept Regional Dept Project Title

Sector

Code

Sector

Description

ADB

Public

ADB

Private MIC SRF

ADF

Loan

ADF

Grant FSF

Total

ADF NTF

Co-

Finan-

cing

Other

Trust

Funds

Total

Cost

Fin.

Instru-

ments

75 Morocco OSAN ORNB MIC Programme de Dev des Oasis

du Sud du Maroc AAC

Irrigation and

Drainage 1.00 0.00 1.00 GGS

76 Morocco ORNB/OSHD ORNB Etude sur la croissance inclusive et

l'emploi I00 Social 0.70 0.00 0.70 GGS

77 Mozambique OSAN ORSB Sustainable Land & Water

Resources Management Project C00 Environment 0.00 12.50 12.50 LSI

78 Mozambique OSAN ORSB

Enhancing Climate Resilience

Agricultural Production and Food

Security Project

AE0 Agriculture 0.00 12.50 12.50 LSI

79 Mozambique OSAN ORSB Irrigation Development Project AAC Irrigation and

Drainage 16.50 16.50 16.50 LSI

80 Niger OSAN ORWA Projet de Dvpt de l'Information et

de la Perspective Climatique AE0 Agriculture 0.00 10.00 10.00 GLP

81 Niger OSAN ORWA

Projet de Mobilisation et de

Valorisation des Ressources en Eau

GAFSP

AA0 Agriculture 0.00 9.60 21.00 30.60 LSI

82 Niger ONEC ORWA Projet d'Amenagement

Hydroélectrique de KANDADJI FA0

Power Supply -

Electricity 40.00 40.00 40.00 LLP

83 Niger OSGE ORWA Appui Institutionnel K00 Multi-Sector 10.00 10.00 10.00 LGI

84 Nigeria OITC ORWA National Urban Road Project D00 Transport 80.00 80.00 80.00 LLP

85 Rwanda OSGE OREA General Budget Support V K00 Multi-Sector 15.00 15.00 15.00 GGBS

86 Sao Tome &

Principe OSGE ORWB

Institutional Support Project -

Capacity Building K00 Multi-Sector 5.00 5.00 5.00 GGI

87 Senegal OITC ORWB Projet Routier Diourbel-Thies D00 Transport 30.00 30.00 30.00 LLP

88 Seychelles OWAS OREA Water Supply & Sanitation Project E00 Water Supply and

Sanitation 10.00 0.00 10.00 LLP

89 Sierra Leone OITC ORWB Upgrading - Matotoka-Sefadu Road D00 Transport 3.20 6.80 10.00 10.00 LLP /

GLP

90 Sierra Leone OWAS ORWB RWSSI E00 Water Supply and

Sanitation 5.67 5.67 5.67 LLP

91 South Africa ONEC ORSA Power Project I FA0 Power Supply -

Electricity 100.00 0.00 100.00 LLP

92 Sudan OSHD OREB Capacity Building Project II I00 Social 3.50 3.50 3.50 GGI

93 Swaziland OSGE ORSA Economic Competitiveness and

Adjustment Programme (ECAP) K00 Multi-Sector 93.00 0.00 93.00 LSL

94 Swaziland OSHD ORSA Youth Development Employment I00 Social 15.00 0.00 15.00 LLP

95 Swaziland OSHD ORSA Social Safety Net program IB0 Health 20.00 0.00 20.00 LLP

96 Tanzania OITC OREA Road Sector Support II D00 Transport 140.00 140.00 140.00 LLP

97 Tanzania OWAS OREA Improvement to Zanzibar Water

Supply E00

Water Supply and

Sanitation 14.00 14.00 14.00 LLP

98 Tunisia OITC ORNA Projet Ligne desserte et

electrification Chemin de Fer D00 Transport 200.00 0.00 200.00 LLP

99 Tunisia OSAN ORNA PISEAU III AAC Irrigation And

Drainage 18.00 0.00 18.00 LLP

100 Tunisia OSAN ORNA PDAI II AA0 Agriculture 15.00 0.00 15.00 LLP

101 Tunisia OSGE ORNA Projet de Renforcement du

Commerce avec Af. Sub K00 Multi-Sector 75.00 0.00 75.00 LLP

102 Tunisia OSGE ORNA Programme d'appui à l'integration II

(PAI II) K00 Multi-Sector 250.00 0.00 250.00 LSL

103 Tunisia OSHD ORNA Multisectorial project K00 Multi-Sector 50.00 0.00 50.00 LLP

Annex 3

2012 Indicative Operational Programme

(in UA million)

5/8

I - PUBLIC SECTOR OPERATIONS - Countries

Item Country

Name Sector Dept Regional Dept Project Title

Sector

Code

Sector

Description

ADB

Public

ADB

Private MIC SRF

ADF

Loan

ADF

Grant FSF

Total

ADF NTF

Co-

Finan-

cing

Other

Trust

Funds

Total

Cost

Fin.

Instru-

ments

104 Uganda OSHD OREA Support project to HEST I00 Higher Education 70.00 70.00 70.00 LLP

105 Uganda OITC OREA Road Sector Support Project 4 D00 Transport 113.00 113.00 113.00 LLP

106 Zambia OSAN ORSB Enhancing Climate Resilient

Agriculture Project C00 Environment 0.00 28.12 28.12 LLP

SUB-TOTAL I 2,494.3 0.0 4.9 0.0 1,183.9 331.7 28.4 1,544.0 6.0 83.0 119.0 4,251.2

II - PUBLIC SECTOR OPERATIONS - Multinational

Item Country

Name

Sector

Dept Regional Dept Project Title

Sector

Code Sector Description

ADB

Public

ADB

Private MIC SRF

ADF

Loan

ADF

Grant FSF

Total

ADF NTF

Co-

Finan-

cing

Other

Trust

Funds

Total

Cost

Fin.

Instru-

ments

1 Multinational -

ORCE OSGE Multinational

Appui à la rationalisation des

CER en Afrique centrale et

renforcement des capacités de la

CEEAC

K00 Multi-Sector 7.00 7.00 GSI

2 Multinational ONRI Multinational

Capacity Building in

Infrastructure Programming for

AUC/NPCA

K00 Multi-Sector 5.00 5.00 GGI

3 Multinational ONRI Multinational Capacity Building for Tripartite

(COMESA, SADC and EAC K00 Multi-Sector 5.00 5.00 GGI

4 Multinational ESTA Multinational Statistical Capacity Building

Program K00 Multi-Sector 20.00 20.00 GGI

5 Multinational OSHD Multinational Pan African University I00 Higher Education 30.00 30.00 GGI

6 Multinational -

West ONEC Multinational

Cote D'Ivoire, Liberia, Sierra

Leone Guinea Interconnection FA0

Power Supply -

Electricity 118.00 6.25 124.25 LLP

7 Multinational -

ORCE OITC Multinational Central Africa Backbone (CAB) GD0

Information and

Communication

Technologies

32.00 32.00 LLP

8 Multinational -

ORCE ONEC Multinational Chad -Cameroon interconnection FA0

Power Supply -

Electricity 51.00 6.25 57.25 LLP

9 Multinational -

East ONEC Multinational

Ethiopia and Kenya Power

Interconnection Project FA0

Power Supply -

Electricity 200.00 200.00 LLP

10 Multinational -

OREA OITC Multinational

Arusha-Holili/Taveta-Voi Road

Development Project D00 Transport 155.00 155.00 LLP

11 Multinational -

ORSB ONEC Multinational

CESUL Mozambique Backbone

transmission line FA0

Power Supply -

Electricity 75.00 75.00 LLP

12 Multinational -

ORWB OITC Multinational

Gambia River Bridge (additional

allocation) D00 Transport 14.00 14.00 LLP

SUB-TOTAL II 0.0 0.0 0.0 0.0 0.0 0.0 0.0 712.0 12.5 0.0 0.0 724.5

III - PRIVATE SECTOR OPERATIONS

Item Country Name Sector Dept Regional Dept Project Title Sector

Code

Sector

Description

ADB

Public

ADB

Private MIC SRF

ADF

Loan

ADF

Grant FSF

Total

ADF NTF

Co-

Finan-

cing

Other

Trust

Funds

Total Cost

Fin.

Instru-

ments

1 Multinational -

ORNA OPSM ORNA

Industries and Services N°

2012 / 1 B00

Industry, Mining

& Quarrying 59.06 59.06 LLP

2 Multinational -

ORNB OPSM ORNB

Industries and Services N°

2012 / 2 A00

Agriculture and

Rural

Development

59.06 59.06 LLP

3 Multinational -

OREA OPSM OREA

Industries and Services N°

2012 / 3 A00

Agriculture and

Rural 59.06 59.06 LLP

Annex 3

2012 Indicative Operational Programme

(in UA million)

6/8

III - PRIVATE SECTOR OPERATIONS

Item Country Name Sector Dept Regional Dept Project Title Sector

Code

Sector

Description

ADB

Public

ADB

Private MIC SRF

ADF

Loan

ADF

Grant FSF

Total

ADF NTF

Co-

Finan-

cing

Other

Trust

Funds

Total Cost

Fin.

Instru-

ments

Development

4 Multinational -

OREB OPSM OREB

Industries and Services N°

2012 / 4 B00

Industry, Mining

& Quarrying 29.53 29.53 LLP

5 Multinational -

ORWA OPSM ORWA

Industries and Services N°

2012 / 5 B00

Industry, Mining

& Quarrying 44.30 44.30 LLP

6 Multinational -

ORWA OPSM ORWA

Industries and Services N°

2012 / 6 B00

Industry, Mining

& Quarrying 44.30 44.30 LLP

7 Multinational -

ORWB OPSM ORWB

Industries and Services N°

2012 / 7 I00

Social 29.53 29.53 LLP

8 Multinational -

ORCE OPSM ORCE

Industries and Services N°

2012 / 8 IA0

Education 29.53 29.53 LLP

9 Multinational -

ORSA OPSM ORSA

Industries and Services N°

2012 / 9 B00

Industry, Mining

& Quarrying 44.30 44.30 LLP

10 Multinational -

ORSA OPSM ORSA

Industries and Services N°

2012 / 10 B00

Industry, Mining

& Quarrying 44.30 44.30 LLP

11 Multinational -

ORSB OPSM ORSB

Industries and Services N°

2012 / 11 B00

Industry, Mining

& Quarrying 29.53 29.53 LLP

12 Multinational OPSM Multinational Industries and Services N°

2012 / 12 B00

Industry, Mining

& Quarrying 46.88 46.88 EQY

13 Multinational OPSM Multinational Industries and Services N°

2012 / 13 B00

Industry, Mining

& Quarrying 37.50 37.50 EQY

14 Multinational OPSM Multinational Industries and Services N°

2012 / 14 B00

Industry, Mining

& Quarrying 0.94 0.94 GGA

15 Multinational OPSM Multinational Industries and Services N°

2012 / 15 B00

Industry, Mining

& Quarrying 0.94 0.94 GGA

16 Multinational OPSM Multinational Industries and Services N°

2012 / 16 B00

Industry, Mining

& Quarrying 0.94 0.94 GGA

17 Multinational OPSM Multinational Industries and Services N°

2012 / 17 B00

Industry, Mining

& Quarrying 0.94 0.94 GGA

18 Multinational OPSM Multinational Industries and Services N°

2012 / 18 B00

Industry, Mining

& Quarrying 0.94 0.94 GGA

19 Multinational OPSM Multinational Industries and Services N°

2012 / 19 B00

Industry, Mining

& Quarrying 0.94 0.94 GGA

20 Multinational -

ORNA OPSM ORNA Infrastructure N° 2012 / 1 FA0

Power Supply -

Electricity 39.38 39.38 LLP

21 Multinational -

ORNA OPSM ORNA Infrastructure N° 2012 / 2 FA0

Power Supply -

Electricity 39.38 39.38 LLP

22 Multinational -

ORNB OPSM ORNB Infrastructure N° 2012 / 3 FA0

Power Supply -

Electricity 39.38 39.38 LLP

23 Multinational -

ORNB OPSM ORNB Infrastructure N° 2012 / 4 FA0

Power Supply -

Electricity 39.38 39.38 LLP

24 Multinational -

OREA OPSM OREA Infrastructure N° 2012 / 5 G00

Communications 78.75 78.75 LLP

25 Multinational -

OREB OPSM OREB Infrastructure N° 2012 / 6 FA0

Water Supply

and Sanitation 39.38 5.00 44.38 LLP

Annex 3

2012 Indicative Operational Programme

(in UA million)

7/8

III - PRIVATE SECTOR OPERATIONS

Item Country Name Sector Dept Regional Dept Project Title Sector

Code

Sector

Description

ADB

Public

ADB

Private MIC SRF

ADF

Loan

ADF

Grant FSF

Total

ADF NTF

Co-

Finan-

cing

Other

Trust

Funds

Total Cost

Fin.

Instru-

ments

26 Multinational -

ORWA OPSM ORWA Infrastructure N° 2012 / 7 FA0

Power Supply -

Electricity 59.06 6.00 65.06 LLP

27 Multinational -

ORWA OPSM ORWA Infrastructure N° 2012 / 8 D00

Transport 59.06 59.06 LLP

28 Multinational -

ORWB OPSM ORWB Infrastructure N° 2012 / 9 FA0

Power Supply -

Electricity 39.38 39.38 LLP

29 Multinational -

ORCE OPSM ORCE Infrastructure N° 2012 / 10 FA0

Water Supply

and Sanitation 39.38 6.25 45.63 LLP

30 Multinational -

ORSA OPSM ORSA Infrastructure N° 2012 / 11 D00

Transport 59.06 59.06 LLP

31 Multinational -

ORSA OPSM ORSA Infrastructure N° 2012 / 12 D00

Transport 59.06 59.06 LLP

32 Multinational -

ORSB OPSM ORSB Infrastructure N° 2012 / 13 FA0

Power Supply -

Electricity 39.38 39.38 LLP

33 Multinational OPSM Multinational Infrastructure N° 2012 / 14 E00 Water Supply

and Sanitation 56.25 56.25 EQY

34 Multinational OPSM Multinational Infrastructure N° 2012 / 15 D00 Transport 56.25 56.25 EQY

35 Multinational OPSM Multinational Infrastructure N° 2012 / 16 D00 Transport 0.94 0.94 GGA

36 Multinational OPSM Multinational Infrastructure N° 2012 / 17 D00 Transport 0.94 0.94 GGA

37 Multinational OPSM Multinational Infrastructure N° 2012 / 18 D00 Transport 0.94 0.94 GGA

38 Multinational OPSM Multinational Infrastructure N° 2012 / 19 D00 Transport 0.94 0.94 GGA

39 Multinational OPSM Multinational Infrastructure N° 2012 / 20 D00 Transport 0.94 0.94 GGA

40 Multinational OPSM Multinational Infrastructure N° 2012 / 21 D00 Transport 0.94 0.94 GGA

41 Multinational OPSM Multinational Infrastructure N° 2012 / 22 D00 Transport 0.94 0.94 GGA

42 Multinational OPSM Multinational Infrastructure N° 2012 / 23 D00 Transport 0.94 0.94 GGA

43 Multinational -

ORNA OPSM ORNA

Financial Intermediate N°

2012 / 1 H00

Finance 29.53 29.53 LLC

44 Multinational -

ORNA OPSM ORNA

Financial Intermediate N°

2012 / 2 H00

Finance 29.53 29.53 LLC

45 Multinational -

ORNB OPSM ORNB

Financial Intermediate N°

2012 / 3 H00

Finance 29.53 29.53 LLC

46 Multinational -

ORNB OPSM ORNB

Financial Intermediate N°

2012 / 4 H00

Finance 29.53 29.53 LLC

47 Multinational -

OREA OPSM OREA

Financial Intermediate N°

2012 / 5 H00

Finance 29.53 29.53 LLC

48 Multinational -

OREA OPSM OREA

Financial Intermediate N°

2012 / 6 H00

Finance 29.53 29.53 LLC

49 Multinational -

OREB OPSM OREB

Financial Intermediate N°

2012 / 7 H00

Finance 29.53 29.53 LLC

50 Multinational -

ORWA OPSM ORWA

Financial Intermediate N°

2012 / 8 H00

Finance 44.30 44.30 LLC

51 Multinational -

ORWA OPSM ORWA

Financial Intermediate N°

2012 / 9 H00

Finance 44.30 44.30 LLC

52 Multinational -

ORWB OPSM ORWB

Financial Intermediate N°

2012 / 10 H00

Finance 29.53 29.53 LLC

53 Multinational -

ORCE OPSM ORCE

Financial Intermediate N°

2012 / 11 H00

Finance 29.53 29.53 LLC

Annex 3

2012 Indicative Operational Programme

(in UA million)

8/8

III - PRIVATE SECTOR OPERATIONS

Item Country Name Sector Dept Regional Dept Project Title Sector

Code

Sector

Description

ADB

Public

ADB

Private MIC SRF

ADF

Loan

ADF

Grant FSF

Total

ADF NTF

Co-

Finan-

cing

Other

Trust

Funds

Total Cost

Fin.

Instru-

ments

54 Multinational -

ORSA OPSM ORSA

Financial Intermediate N°

2012 / 12 H00

Finance 44.30 44.30 LLC

55 Multinational -

ORSA OPSM ORSA

Financial Intermediate N°

2012 / 13 H00

Finance 44.30 44.30 GTE

56 Multinational -

ORSB OPSM ORSB

Financial Intermediate N°

2012 / 14 H00

Finance 29.53 29.53 LLC

57 Multinational OPSM Multinational Financial Intermediate N°

2012 / 15 H00

Finance 42.19 42.19 EQY

58 Multinational OPSM Multinational Financial Intermediate N°

2012 / 16 H00

Finance 21.09 21.09 EQY

59 Multinational OPSM Multinational Financial Intermediate N°

2012 / 17 H00

Finance 21.09 21.09 EQY

60 Multinational OPSM Multinational Financial Intermediate N°

2012 / 18 H00

Finance 1.41 1.41 GGA

61 Multinational OPSM Multinational Financial Intermediate N°

2012 / 19 H00

Finance 1.41 1.41 GGA

62 Multinational OPSM Multinational Financial Intermediate N°

2012 / 20 H00

Finance 1.41 1.41 GGA

63 Multinational OPSM Multinational Financial Intermediate N°

2012 / 21 H00

Finance 1.41 1.41 GGA

SUB-TOTAL III 0.0 1,875.0 0.0 0.0 0.0 0.0 0.0 0.0 17.3 0.0 0.0 1,892.3

GRAND TOTAL 2,494.3 1,875.0 4.9 0.0 1,183.9 331.7 28.4 2,256.0 35.8 83.0 119.0 6,867.9

GRAND TOTAL WITHOUT CO-FINANCING 2,494.3 1,875.0 4.9 0.0 1,183.9 331.7 28.4 2,256.0 35.8 6,785.0

Annex 4

Update on Budget Reforms

1/3

On 15 June 200723

, the Board of Directors approved a set of Budget Reforms, to address

issues relating to: (i) lack of alignment between the Bank’s Strategy, Work Programmes and

resource allocation; (ii) highly centralized budget authority (approximately 85% of the budget

was centrally managed); (iii) staff headcount control; and (iv) poor accountability. In addition

to these, resources could not be easily deployed in response to changes in Work Programmes

and deliverables, while all budget transfers required the approval of the President.

The Reforms are being implemented in three phases.

Phase 1, which was implemented in 2008, has: (i) strengthened the link between

institutional priorities and resource allocation; (ii) enhanced institutional budget flexibility

through increased fungibility and devolved resource management authority to VPUs; (iii)

moved to a Multi-Year Programme and Budget framework (the first being the 2009-2011

Programme and Budget Document – PBD); and (iv) established a new accountability and

performance monitoring framework by linking deliverables to Key Performance Indicators

(KPIs).

Phase 2, which is currently underway - 2009 to 2012 - has: (i) expanded budget fungibility

(salaries included) through the implementation of Unit of Account (UA) Budgeting; (ii)

removed the Headcount Control and introduced Staff Planning and the Fixed Cost Ratio

(FCR) as compensatory measures; and (iii) now ensures that the use of resources is recorded

against output/activity codes (WBS elements) to link expenditures to deliverables. Finally, it

will improve monitoring and reporting and the credibility of data through the introduction of

the Activity Time Recording System (ATRS) and the launching of the Cost Accounting

Framework.

Phase 3 is scheduled for implementation from 2012 to 2015 and will include: (i) partial

decentralization of staff benefits; (ii) charge-back of some overhead expenses; (iii) country

budget management; and (iv) productivity incentive tax.

The end objective of these reforms is the transition to expanded budget fungibility and a

decentralized resource management framework through a strategy-driven Unit of Account

(UA) budgeting system, to underpin the achievement of results on the ground.

Following the implementation of the UA Budgeting system in January 2010, COBS is shifting

towards greater attention on monitoring efficiency and cost effectiveness of resource

utilization. Staff planning has been reinforced through the creation of a Staff Planning Focal

Group, which consolidates the projected staffing needs of VPUs to SMCC for validation.

To strengthen budget management capacity across Complexes, Budget and Resource

Management Coordinators are now in place in VPUs, while Management continues to review

its structure to ensure greater effectiveness. As the second phase of the Reforms is nearing

completion, Management has launched an internal mid-term review process to highlight the

benefits and challenges to date. The Review Report will be presented to the Board of

Directors at the end of the first quarter of 2012.

Activity Time Recording System (ATRS): The Activity Time Recording System, which was

reintroduced in May 2010, is currently being tested within limited organization units to

23

Ref. ADB/BD/WP/2006/129/Rev.1/add.2 – ADF/BD/WP/2006/150/Rev.1/add.2

Annex 4

Update on Budget Reforms

2/3

address identified bottlenecks. It will be ready for final deployment across the Bank during

the second half of 2012. As the ATRS is the most important input to the Cost Accounting

System (CAS), a number of interfaces with the System Applications and Products (SAP)

system were developed during 2011 to enable data transfer between both systems. To this

end, a web portal for all staff concerned is being finalized, focusing on data interface with

SAP Enterprise Resource Planning (ERP). This interface aims to centralize all information in

a unified and secured manner to allow automatic transfer of leave, public holidays and

missions from one system to another. A special supervisory profile is also being developed to

enable designated Focal Points in each Complex to monitor and ensure that staff record their

activities in ATRS within a reasonable time.

Cost Accounting System (CAS): The CAS will support UA Budgeting in determining the

overall costs of the Bank’s products and services, and subsequently providing a more reliable

basis for the Bank Group’s Cost Sharing Formula. Functional and technical specifications of

CAS are now completed and COBS is working with CIMM to design the cost allocation

process in SAP with the objective to make the Cost Accounting System Framework go live in

2012.

Expansion of Budget Fungibility

Decentralize benefits – Management is still reviewing the possibility of decentralizing, in the

future, part of staff benefits to the VPUs. Prior to this, Management will ensure that there is

strong evidence of: (i) discipline in staff planning and recruitment procedures, including strict

adherence to HR policies; and (ii) VPU work programmes and resource management

capacity.

Charge Back System – This system will decentralize the budget for some centrally managed

expenses to VPUs. This will require: (i) further cost-benefit analysis; and (ii) a more robust

information management system. This is also subject to ongoing review by Management.

Country Budget Management

Under this arrangement, Country Work Programme related resources will be managed by the

Regional Departments. This is conditional to: (i) further changes to the business processes;

(ii) significant restructuring of the delegation of authority matrix; (iii) better coordination

across Operations Complexes; and (iv) strong work programming and resource management

capacity Bank-wide.

Productivity Incentive Tax

The tax is intended to encourage Complexes to examine ways of improving efficiencies and

cutting costs. The mechanism will be an efficient method for capturing, at the corporate level,

productivity gains accruing at unit level, which would otherwise be difficult to identify.

As an effective performance management tool, the Productivity Incentive Tax will:

encourage internal benchmarking: to reward performance and encourage policy

compliance;

Annex 4

Update on Budget Reforms

3/3

be actionable: by focusing on expense line items (as performance indicators) where

Managers’ actions can ensure cost savings and/or efficiencies. When rolled out, it will

use the following indicators: Budget Implementation Rate, End of Year Cumulative

Expenses, Consultancy Expenses, Mission Related Expenses, STS Expenses,

Managers and Leads/PL Staff, and Carryovers;

be simple: use fewer measures that are simple to calculate; and

be relevant: will reflect current corporate priorities or initiatives.

A Concept Paper is under preparation. It will be reviewed by all Complexes before being

tabled to the SMCC for consideration. The paper will discuss the detailed calculation of the

Incentive Tax and the selected Efficiency Indicators.

Once the PIT will be operational, Complexes will be informed, at the start of the budgeting

period, of the Incentive Tax that will be deducted from their budgets. This will be

accompanied by necessary background data and modelling employed in calculating the

Incentive Tax.

Annex 5

Staff Allocation by Complex

1/4

Annex 5A: 2011 Staff Distribution by Complex

2011 Staffing*

(As at 17 November 2011)

HQ FO Grand

Total

PL GS Total PL GS Total

Boards of Directors 60 20 80 - - - 80

Operations Evaluation 20 12 32 - - - 32

Sub-Total Special Appropriations 80 32 112 - - - 112

Regional & Country Programs 114 39 153 164 176 340 493

Regional Departments 80 29 109 109 176 285 394

Policy and Compliance 10 3 13 - - - 13

Procurement and Fiduciary Services 24 7 31 55 - 55 86

Sector Operations 137 42 179 66 - 66 245

Infrastructure, PS & Regional Integration 204 42 246 70 - 70 316

Sub-Total Operations 455 123 578 300 176 476 1,054

Knowledge Management & Research 63 29 92 - - - 92

Sub-Total Operations and Office of Chief Economist 518 152 670 300 176 476 1,146

Financial Management 105 93 198 4 21 25 223

Corporate Services 148 149 297 - 29 29 326

Institutional Governance & Corporate Management 213 117 330 6 3 9 339

Presidency** 9 7 16 - - - 16

Communication Unit 15 8 23 - - - 23

Legal & Advisory Services 38 16 54 - - - 54

Other Units Reporting to PRST & the Board*** 151 86 237 6 3 9 246

Sub-Total Complexes Staffing 466 359 825 10 53 63 888

Young Professionals Programme (YPP) 70

70 - - - 70

Others (SCOU, CBKHQ, CHRMSL) 2 3 5 - - - 5

Total 1,136 546 1,682 310 229 539 2,221

* Within the requested 2012 total budget envelope, the Bank will not have provision or headroom for the creation of new

positions in 2012. Current staff distribution will change in 2012 due to reallocation in priority areas.

** PRST0 & SAPR

*** Office of the COO, COEO, COBS, CCCC, CRMU, IACD, OAGL, OMBU, OPSC, ORQR, PECOD, SECU, SEGL, STRG,

TRIB, JPRO, USRO & RO in Europe

Annex 5

Staff Allocation by Complex

2/4

Annex 5B: Historical Staffing Data by Complex

2007 Staffing*

2008 Staffing

2009 Staffing

2010 Staffing

2011 Staffing

(as at 17 November 2011)

HQ FO

HQ FO

HQ FO

HQ FO

HQ FO

PL GS PL GS Total PL GS PL GS Total PL GS PL GS Total PL GS PL GS Total PL GS PL GS Total

Boards of Directors 53 18 - - 71 53 17 - - 70 54 18 - - 72 60 20 - - 80 60 20 - - 80

Operations Evaluation 15 4 - - 19 15 4 - - 19 17 9 - - 26 19 10 - - 29 20 12 - - 32

Sub-Total Special Appropriations 68 22 - - 90 68 21 - - 89 71 27 - - 98 79 30 - - 109 80 32 - - 112

Regional & Country Programs 121 36 123 198 478 107 37 92 170 406 103 34 104 174 415 115 39 111 174 439 114 39 164 176 493

Regional Departments 72 27 123 198 420 65 26 79 149 319 66 26 84 153 329 81 29 87 153 350 80 29 109 176 394

Policy and Compliance** 32 5 - - 37 25 6 - - 31 15 3 - - 18 11 3 - - 14 10 3 - - 13

Procurement and Fiduciary Services 17 4 - - 21 17 5 13 21 56 22 5 20 21 68 23 7 24 21 75 24 7 55 - 86

Sector Operations 131 28 - - 159 142 28 43 - 213 149 40 45 - 234 142 43 51 - 236 137 42 66 - 245

Infrastructure, PS & Regional Integration 145 30 - - 175 157 28 49 - 234 167 32 49 - 248 185 40 50 - 275 204 42 70 - 316

Sub-Total Operations 397 94 123 198 812 406 93 184 170 853 419 106 198 174 897 442 122 212 174 950 455 123 300 176 1,054

Knowledge Management & Research 40 26 - - 66 47 26 - - 73 52 27 - - 79 56 27 - - 83 63 29 - - 92

Sub-Total Operations and Office of Chief

Economist 437 120 123 198 878 453 119 184 170 926 471 133 198 174 976 498 149 212 174 1,033 518 152 300 176 1,146

Financial Management 89 93 - - 182 80 86 3 19 188 88 85 5 21 199 96 93 5 20 214 105 93 4 21 223

Corporate Services 135 161 - - 296 137 148 - 24 309 136 146 - 25 307 139 152 - 25 316 148 149 - 29 326

Institutional Governance & Corporate

Management 87 77 - - 164 110 96 - - 206 147 106 - - 253 179 115 - - 294 213 117 6 3 339

Presidency** 5 6 - - 11 6 8 - - 14 9 9 - - 18 8 9 - - 17 9 7 - - 16

Communication Unit 7 7 - - 14 7 7 - - 14 10 8 - - 18 12 8 - - 20 15 8 - - 23

Legal & Advisory Services 24 12 - - 36 32 12 - - 44 34 12 - - 46 38 13 - - 51 38 16 - - 54

Other Units Reporting to PRST & the

Board*** 51 52 - - 103 65 69 - - 134 94 77 - - 171 121 85 - - 206 151 86 6 3 246

Sub-Total Complexes staffing 311 331 - - 642 327 330 3 43 703 371 337 5 46 759 414 360 5 45 824 466 359 10 53 888

Young Professionals Programme

(YPP)**** 28 - - - 28 48 - - - 48 69 - - - 69 88 - - - 88 70 - - - 70

Others (SCOU, CBKHQ, CHRMSL) 1 2 - - 3 3 7 - - 10 2 9 - 1 12 3 3 - - 6 2 3 - - 5

Total 845 475 123 198 1,641 899 477 187 213 1,776 984 506 203 221 1,914 1,082 542 217 219 2,060 1,136 546 310 229 2,221

* In 2007 the mapping of positions to their original Department did not exist.

** PRST0 & SAPR

*** Office of the COO, COEO, COBS, CCCC, CRMU, IACD, OAGL, OMBU, OPSC, PECOD, ORQR, SECU, SEGL, STRG, TRIB, JPRO, USRO & RO in Europe

**** Annual intake of YPP does not change and is 20 per year as per the programme policy (ADB/BD/WP/2008/29/Rev.1)

Annex 6

Explanatory Note on Inflation Rates used in the

2012-2014 Programme and Budget Document (PBD)

and Factors of 2012 Budget Increase

1/4

This Annex is a note of explanation on the mechanism for calculating the inflation rate, and

how it is distributed on the Bank's Budget. It also provides more detailed information about

the terms "price increase” and “volume increase" used in the Programme and Budget

Document (PBD).

I. The Context of Inflation

The Consumer Price Index (CPI) is a measure of the average change over time in the prices

paid by consumers for a market basket of consumer goods and services. It measures the rates

of change in prices rather than price levels. The CPI is used both as an official measure of

price changes in the economy and is used by government, private sector and individuals to

facilitate economic decision making. It is also used as a proxy of the cost of living index for

purposes of adjusting income levels by businesses and labour. The index is computed on the

basis of a basket of goods and services which is representative of the consumption of a given

target population24

.

International standards classify the individual consumption expenditure items by households

into the following 12 major broad categories of goods and services:

G1. Food and Non-Alcoholic beverage

G2. Alcoholic beverage, Tobacco and Narcotics

G3. Clothing and Footwear

G4. Housing (housing, construction, rent, maintenance), water, gas, electricity and

other fuels

G5. Furniture, household appliances and goods for routine maintenance

G6. Health and Health services

G7. Transport

G8. Communication

G9. Recreation and Culture

G10. Education

G11. Restaurants and Hotels

G12. Miscellaneous Goods and Services

The number of expenditure items in the 12 broad categories for which prices are collected

monthly by RMC National Statistical Offices varies between 400 and 1,000 from one country

to another25

.

24

Some countries exclude diplomats, expatriates, and any other category of consumers whose consumption

habits or life styles are temporary in comparison to the target population. 25

Detailed data on prices of goods and services were collected from the following 26 RMCs with Field Offices:

Algeria, Angola, Burkina Faso, Cameroon, Chad, Congo DRC, Egypt, Ethiopia, Gabon, Ghana, Guinea, Kenya,

Madagascar, Malawi, Mali, Morocco, Mozambique, Nigeria, Senegal, Sierra Leone, Sudan, Tanzania, Uganda

and Zambia.

Annex 6

Explanatory Note on Inflation Rates used in the

2012-2014 Programme and Budget Document (PBD)

and Factors of 2012 Budget Increase

2/4

II. The Inflation Rate used in the PBD

The inflation rate for the PBD was computed on the basis of expenditure categories G3 to

G12 and the methodology is discussed below. The underlying number of expenditure items

used in the computation varies from a few hundred up to 1,000 in some countries.

1. Methodology for Computing the Correction Factor of Non-Institutional

Expenditure Component of Budget

Steps Used to Calculate the Inflation Rates

1. Determine an inflation rate for Temporary Relocation Agency (I_TRA) on the

basis of a list of expenditure categories provided for the Budget.

2. Determine, in the same way, an inflation rate for all Field Offices (I_FO).

3. Compute the global inflation rate as a weighted average of the two.

The Formula

Let B_FO and B_TRA respectively represent the budgets for Field Offices and the Temporary

Relocation Agency (Tunis). Côte d’Ivoire is included in Field Offices. Let I_Global be the

overall inflation rate. Then the global inflation rate is calculated as:

TRABFOB

TRATRAxIBFOFOxIBGlobalI

__

_____

(1)

Calculation of the Rate for Temporary Relocation Agency (I_TRA)

This inflation is calculated using monthly consumer price indices for expenditure items in the

CPI for Tunisia. A geometric mean of the indices is then calculated to determine the annual

global index.

For example, if IT2010 and IT2011 are the annual indices for 2010 and 2011 at TRA, then I_TRA

is calculated as:

2010

20102011_T

TT

I

IITRAI

(2)

The computation gives a rate of inflation of 4.0% for the budget at TRA (Tunisia).

Calculation of the Rate for Field Offices (I_FO)

The same methodology in section 3 is used to obtain the inflation rate for Field Offices.

Individual expenditure category indices are extracted from CPIs of each RMC where there is

an ADB Field Office. Then, an overall index for each expenditure item is obtained by

computing the arithmetic mean of the monthly indices for the expenditure item from each of

the RMCs. Having obtained the mean expenditure values for each budget item, annual indices

for 2010 and 2011 are computed as geometric means of the mean expenditure item indices.

Then the global rate of inflation for Field Offices is given by:

2010

20102011_FO

FOFO

I

IIFOI

(3)

Annex 6

Explanatory Note on Inflation Rates used in the

2012-2014 Programme and Budget Document (PBD)

and Factors of 2012 Budget Increase

3/4

The computation using effective expenditures (without institutional expenditures) gives a rate

of inflation of 7.84% for the Field Offices.

Calculation of the Bank’s Consolidated Budget Inflation

Given B_FO = UA 13.15 million and B_TRA = UA 100.58 million and by applying Formula

(1), we get an overall inflation rate of 4.4% for the Bank’s consolidated budget.

2. Distribution of inflation on the Bank’s budget

For the preparation of the 2012-14 PBD, the calculation of inflation was estimated at UA 4.37

million. Table 6.1 below shows the distribution of inflation on the Bank's budget.

Table 6.1: Distribution of inflation on the Bank's budget

Sections

Inflation

(in UA)

Section 01 - Salaries -

Section 02 - Benefits -

Section 03 - Other Employee Expenses 530,811

Section 04 - Short Term Staff 66,582

Section 05 - Consultants 855,784

Section 06 - Staff Training 179,330

Section 07 - Official Missions 779,433

Section 08 - Accommodation / Office Occupancy 542,324

Section 09 - Equipment Rental, Repairs & Maintenance 327,908

Section 10 - Communication Expenses 348,413

Section 11 - Printing, Publishing & Reproduction 63,858

Section 12 - Office Supplies & Stationery 35,090

Section 13 - Library 27,297

Section 14 - Other Miscellaneous Expenses 610,768

Grand Total 4,367,596

III. The Impact of the Price and Volume Increase on the Budget

The concepts of "price increase" and "volume increase" are factors to increase the budget and,

according to our guiding principles, are defined respectively as follows:

1. Price increase: All factor that increase the cost of the expenditure while the volume

remains the same; for example, the salary base for the same number of staff changes

with different compensation packages (salary increase).

2. Volume increase: All increases due to an incremented number of elements; for

example, the opening of new Field Offices.

All increases in the proposed 2012 budget have been classified (see Table 2 below) under one

of the two above-mentioned clusters.

Annex 6

Explanatory Note on Inflation Rates used in the

2012-2014 Programme and Budget Document (PBD)

and Factors of 2012 Budget Increase

4/4

N.B: To obtain the inflation amount of UA 4.37 million, the inflation rate of 4.4% has been

applied to all the items in the budget except salaries and benefits.

Table 6.2: Factors of the 2012 Budget Increase

(in UA ‘000)

Cost items 2012 Proposed

budget*

% of Adjusted

2011 Approved

budget

“Adjusted” 2011 Approved Budget 286,479

2011 Baseline Budget (95% of 2011 Adjusted Budget) 272,155 -5.00%

Price Increase 8,461 2.95%

Inflation - on all other expenditures except salaries and benefits 4,368 1.52%

New Compensation Framework 4,093 1.43%

Volume Increase 17,266 6.03%

BCP 4,505

ICT Improvement 2,637

RRC 1,834

ERO 1,565

Political Risk Insurance 1,000

Special Country Initiatives (North Africa, Somalia, Sudan,

South Sudan, Zimbabwe)

900

Decentralization 791

Governance 537

Food Security 507

HEST 390

Operations Evaluation 354

Fiduciary Safeguard 350

Knowledge and Analytical Work 277

Improve work conditions 266

Fragile States 238

Improve Management of HR 212

Policy Outreach and Public Consultations 200

Information Disclosure 186

Climate Change 172

Gender 100

MTS 86

Risk Management 47

ADF/GCI commitment 41

ADOA 31

Quality Control of Boards & Institutional Support Activities 20

African Economic Outlook 18

Less Efficiency Gains (5,323) -1.86%

Grand Total 292,552 2.12%

* Figures may not add due to rounding

Annex 7

2012 – Planned Efficiencies and Measures with

Expected Savings in Administrative Expenses

1/1

Description

Savings

(in UA

’000)

Management's decision to keep the Global Budget envelope submitted to the Board

in the Framework Paper and to absorb the new requirements through trade-offs, cost

savings and efficiency gains efforts.

5,323

Consultants: (i) reduction in the use of consultants following recent increases in

regular staff; (ii) putting in place a monitoring system to limit consultants’ contracts

duration; and (iii) effective negotiations to offer reduced rates to consultants.

685

Operations: (i) closing aged and non-performing operations; (ii) move from task

fragmentation to consolidation; (iii) mobilize additional resources from trust funds;

(iv) using more sector budget support; (v) reduced work on agriculture; and (vi)

reduced project completion reports due to reduction in backlog.

.

830

Decentralization: Increasing delegation of lending and non-lending activities

(preparation, supervision, completion, ESWs, dialogue, conferences, etc.) to field

based staff including those in the pilot Regional Resource Centres.

234

Leveraging on IT, and Communications: (i) reduction in annual leased line fees

following the migration of Leased Lines (LL) to Multi-Protocol Label Switching

(MPLS); (ii) online subscriptions for publications and suspension as much as

possible of physical resources spending (books, newspapers and magazines); (iii)

internal design and editing of brochures and publications; (iv) deployment and

upgrade of Taleo as online recruitment system; and (v) telephone costs reduction as

a result of deploying GSM gateway telephoning facilities to make calls to mobile

phones in Tunisia.

463

Missions: (i) on-time booking of missions and combining trips to multiple

destinations; (ii) reduced ticket costs as a result of better negotiations with airlines;

and (iii) reduction in waivers for more expensive routes.

1,018

Public Relations and Promotional Items: (i) publicity spots to be replaced by

winning partnerships with cost sharing; (ii) cancellation of wall calendars; (iii)

replacement of paper greeting cards with electronic version; (iv) reduction in the

quantity of diaries; (v) creation of database for photographs of Bank events and

projects to reduce photographs and albums production; and (vi) reduction in the

number of media to invite and reinforced selection criteria for newsmen to invite.

300

Meetings and Conferences: (i) prioritization of attendance at meetings and

conferences; (ii) implementation of the Bank Events Management centralization; and

(iii) streamlined management of Annual Meetings Invitations and Events.

115

Total 8,968

Annex 8

Costs of Decentralization from 2009 to 2012

1/1

Original Budget (in UA million)

Item 2009 2010 2011 20121

Workload 2.42 2.54 2.69 2.10

Missions 2.18 1.84 2.00 1.72

Consultancy 0.24 0.69 0.68 0.38

STS - 0.01 0.02 -

General Expenses 9.95 10.82 10.66 16.59

o/w

Staff Training 1.28 1.18 0.72 0.60

Accommodation & Office Occupancy 3.86 4.11 4.32 5.04

Equipment Rental, Repairs & Maintenance 0.67 0.76 0.91 0.60

Communication Expenses (including

Satellite costs) 1.52 1.28 1.78 2.12

Salaries & Benefits 26.51 24.82 28.64 33.84

FO based Staff2 26.51 24.82 26.31 31.55

TRA based Staff3 - - 2.33 2.29

Total Administrative Budget 38.89 38.18 42.00 52.53

Share of total ADB Administrative Budget 15.37% 14.46% 14.53% 17.96%

Share of total Operations Budget4 24.40% 23.56% 23.60% 28.44%

Capital Investment Budget5

Section 16 - Office Equipment 0.18 - - 0.93

Section 17 - Office Furniture 0.42 - 0.53 2.12

Section 19 - IT & Communication 1.76 0.21 2.06 3.39

Section 20 - Buildings & Civil Works 2.82 8.05 9.76 4.91

Section 23 - Other Projects 0.77 0.64 1.75 0.70

Total Capital Budget 5.95 8.90 14.10 12.05

Share of total ADB Capital Budget 32.08% 30.91% 35.22% 58.50%

1 BCP related costs for South Africa Field Office - ZAFO (UA 1.9 million) are not included – ringfenced subject to later Board

approval (possibly in February 2012). 2 FO based staff include staff and positions in the two Regional Departments (OREA and ORSA) being relocated, from

January 1st, to Nairobi and Pretoria. Budget for staff from Sector and General Services yet to be identified, and will be moved

and added later. 3 TRA-based Staff ► twenty-six staff whose work programmes include specific Field Offices' related work, e.g. HR FO

Compensation Officer, FO Security Coordinator, FO Audit Coordinator, etc. 4 Operations defined as ORVP, OIVP, OSVP, ECON, and 100% Operational Units outside Operations Complexes

(OPEV, GECL1, GECL2, OPSC, CRMU, FFMA2, FTRY4, FFCO3 and ORQR). 5 Capital investment figures represent the annual approvals.

Annex 9

Annex 9A: 2012-2014 Budget Proposals by Complexes (in UA million)

1/4

2011 Adjusted 2012 Proposed Budget

Staff Costs Workload Overhead Total Staff Costs Workload Overhead Total

Increase in

amount

Increase

%

COMPLEXES BUDGET

Regional & Country Programs (ORVP)

29,18 5,59 17,96 52,72

31,00 4,92 18,88 54,80 2,08 3,94%

Regional Departments

16,33 1,79 3,37 21,49

17,65 2,08 3,38 23,11 1,62 7,55%

Field Offices

3,99 2,73 11,45 18,17

4,10 1,79 12,06 17,96 (0,21) -1,15%

Resource Mobilization (ORMU)

1,25 0,13 0,22 1,60

1,23 0,20 0,24 1,67 0,06 3,97%

Partnerships Unit (ORRU)

1,03 0,15 1,38 2,56

1,00 0,15 1,44 2,59 0,03 1,32%

Policy & Compliance (ORPC)

1,23 0,24 0,24 1,72

1,19 0,13 0,42 1,73 0,02 0,95%

Procurement & Fiduciary Services (ORPF) 5,34 0,54 1,30 7,18

5,82 0,58 1,33 7,73 0,55 7,66%

Sector Operations (OSVP)

19,98 7,79 4,91 32,69

19,96 7,02 5,50 32,48 (0,21) -0,64%

Infrastructure, PS & Regional Integration (OIVP) 25,22 8,70 6,01 39,92

25,77 9,12 6,30 41,19 1,27 3,19%

Knowledge Management & Research (ECON) 7,49 2,53 4,94 14,96

7,45 1,96 5,22 14,63 (0,33) -2,22%

Financial Management (FNVP)

14,76 1,77 6,01 22,53

14,57 1,57 6,21 22,35 (0,18) -0,80%

Corporate Services (CSVP)

21,11 4,82 5,53 31,46

21,04 3,02 5,96 30,02 (1,44) -4,59%

Institutional Governance & Corporate Management (UPRST) 25,11 6,24 8,99 40,34

26,48 6,47 9,61 42,56 2,22 5,51%

Presidency & SAPR

1,72 0,59 0,65 2,97

1,67 0,58 0,62 2,88 (0,09) -3,18%

Comminication Unit (ERCU)

1,64 0,65 0,62 2,91

1,75 0,46 0,61 2,82 (0,10) -3,32%

Security Unit (SECU)

1,41 0,32 0,46 2,19

1,40 0,51 0,47 2,38 0,19 8,82%

Integrity & Anti-Corruption (IACD) 1,47 0,23 0,37 2,06

1,60 0,17 0,39 2,16 0,10 4,82%

Strategy Unit (STRG)

0,49 0,04 0,13 0,66

0,52 0,03 0,13 0,68 0,02 2,99%

Chief Operating Officer (COO*)

8,12 2,81 3,80 14,73

8,84 3,00 4,11 15,94 1,21 8,21%

Legal & Advisory Services (GECL) 4,21 0,73 1,15 6,09

4,48 0,87 1,31 6,67 0,58 9,56%

Office of the Auditor General (OAGL) 1,85 0,29 0,45 2,58

1,79 0,23 0,48 2,49 (0,09) -3,47%

General Secretariat (SEGL)

3,83 0,50 1,30 5,63

4,09 0,53 1,35 5,96 0,33 5,82%

Ombu (OMBU)

0,35 0,09 0,06 0,51

0,35 0,09 0,14 0,58 0,07 13,92%

Special Appropriation

25,87 - 2,61 28,48

29,33 - 2,11 31,45 2,97 10,41%

YP programme

6,26 - 2,61 8,87

4,95 - 2,11 7,07 (1,80) -20,30%

New compensation framework

- - - -

4,09 - - 4,09 4,09 -

Staff Retirement Plan

19,61 - - 19,61

20,28 - - 20,28 0,67 3,43%

Total Complexes Budget 168,72 37,43 56,96 263,11

175,60 34,09 59,78 269,48 6,37 2,42%

BOARDS and URBD

Boards of Governors

- - 3,40 3,40

- - 3,38 3,38 (0,02) -0,69%

Boards of Directors

10,00 1,54 1,59 13,13

9,77 1,55 1,38 12,70 (0,43) -3,29%

Operation Evaluation (OPEV)

2,64 1,53 0,70 4,87

2,54 1,83 0,71 5,08 0,21 4,25%

Compliance Review & Mediation (CRMU) 0,56 0,19 0,62 1,36

0,54 0,19 0,62 1,34 (0,02) -1,55%

Tribunal

0,26 0,25 0,08 0,59

0,25 0,23 0,09 0,57 (0,02) -3,48%

Total BOARDS and URBD 13,45 3,52 6,39 23,36

13,10 3,81 6,17 23,07 (0,29) -1,25%

GRAND TOTAL 182,17 40,95 63,35 286,47

188,70 37,90 65,95 292,55 6,08 2,12%

Provision for Aniaman and two EROs

2,66

2011 Approved Budget

289,14

3,41 1,18% (*) Includes COO Directorate, OPSC, COBS, COEO, ORQR, CCCC, PECOD, JPRO, USRO & ERO in Europe

Annex 9

Annex 9A: 2012-2014 Budget Proposals by Complexes (in UA million)

2/4

2012 Proposed Budget

2013 Proposed Budget

Staff Costs Workload Overhead Total

Increase in

amount Staff Costs Workload Overhead Total

Increase in

amount

Increase

%

COMPLEXES BUDGET

Regional & Country Programs (ORVP)

31,00 4,92 18,88 54,80 2,08

31,47 5,31 20,34 57,12 2,32 4,23%

Regional Departments

17,65 2,08 3,38 23,11 1,62

17,92 2,22 3,50 23,64 0,53 2,30%

Field Offices

4,10 1,79 12,06 17,96 (0,21)

4,17 1,94 13,24 19,34 1,38 7,69%

Resource Mobilization (ORMU)

1,23 0,20 0,24 1,67 0,06

1,25 0,21 0,25 1,71 0,04 2,68%

Partnerships Unit (ORRU)

1,00 0,15 1,44 2,59 0,03

1,02 0,16 1,50 2,68 0,09 3,48%

Policy & Compliance (ORPC)

1,19 0,13 0,42 1,73 0,02

1,20 0,14 0,44 1,78 0,05 2,62%

Procurement & Fiduciary Services (ORPF) 5,82 0,58 1,33 7,73 0,55

5,91 0,63 1,42 7,96 0,22 2,90%

Sector Operations (OSVP)

19,96 7,02 5,50 32,48 (0,21)

20,27 7,02 5,79 33,07 0,59 1,83%

Infrastructure, PS & Regional Integration (OIVP) 25,77 9,12 6,30 41,19 1,27

26,69 9,78 6,52 42,99 1,79 4,35%

Knowledge Management & Research (ECON) 7,45 1,96 5,22 14,63 (0,33)

7,56 2,42 5,40 15,39 0,76 5,16%

Financial Management (FNVP)

14,57 1,57 6,21 22,35 (0,18)

14,79 1,59 6,48 22,86 0,51 2,29%

Corporate Services (CSVP)

21,04 3,02 5,96 30,02 (1,44)

21,36 3,19 5,72 30,26 0,24 0,81%

Institutional Governance & Corporate Management (UPRST) 26,48 6,47 9,61 42,56 2,22

27,30 6,66 10,12 44,09 1,53 3,58%

Presidency & SAPR

1,67 0,58 0,62 2,88 (0,09)

1,70 0,61 0,65 2,95 0,08 2,65%

Comminication Unit (ERCU)

1,75 0,46 0,61 2,82 (0,10)

1,78 0,48 0,59 2,85 0,03 1,16%

Security Unit (SECU)

1,40 0,51 0,47 2,38 0,19

1,42 0,53 0,49 2,44 0,06 2,60%

Integrity & Anti-Corruption (IACD) 1,60 0,17 0,39 2,16 0,10

1,62 0,18 0,41 2,21 0,05 2,16%

Strategy Unit (STRG)

0,52 0,03 0,13 0,68 0,02

0,52 0,04 0,14 0,70 0,01 2,07%

Chief Operating Officer (COO*)

8,84 3,00 4,11 15,94 1,21

9,39 3,04 4,38 16,81 0,87 5,43%

Legal & Advisory Services (GECL) 4,48 0,87 1,31 6,67 0,58

4,55 0,91 1,42 6,88 0,21 3,15%

Office of the Auditor General (OAGL) 1,79 0,23 0,48 2,49 (0,09)

1,81 0,24 0,61 2,66 0,17 6,62%

General Secretariat (SEGL)

4,09 0,53 1,35 5,96 0,33

4,15 0,55 1,37 6,07 0,11 1,90%

Ombu (OMBU)

0,35 0,09 0,14 0,58 0,07

0,36 0,10 0,07 0,52 (0,06) -10,27%

Special Appropriation

29,33 - 2,11 31,45 2,97

29,51 - 2,19 31,70 0,26 0,81%

YP programme

4,95 - 2,11 7,07 (1,80)

5,03 - 2,19 7,22 0,16 2,22%

New compensation framework

4,09 - - 4,09 4,09

4,09 - - 4,09 - 0,00%

Staff Retirement Plan

20,28 - - 20,28 0,67

20,38 - - 20,38 0,10 0,49%

Total Complexes Budget 175,60 34,09 59,78 269,48 6,37

178,95 35,96 62,57 277,48 8,00 2,97%

BOARDS and URBD

Boards of Governors

- - 3,38 3,38 (0,02)

- - 3,53 3,53 0,15 4,40%

Boards of Directors

9,77 1,55 1,38 12,70 (0,43)

9,92 1,62 1,44 12,97 0,27 2,16%

Operation Evaluation (OPEV)

2,54 1,83 0,71 5,08 0,21

2,58 1,91 0,72 5,21 0,13 2,54%

Compliance Review & Mediation (CRMU) 0,54 0,19 0,62 1,34 (0,02)

0,55 0,20 0,66 1,40 0,06 4,24%

Tribunal

0,25 0,23 0,09 0,57 (0,02)

0,26 0,25 0,09 0,59 0,02 3,05%

Total BOARDS and URBD 13,10 3,81 6,17 23,07 (0,29)

13,29 3,98 6,43 23,70 0,63 2,71%

GRAND TOTAL 188,70 37,90 65,95 292,55 6,08

192,24 39,94 68,99 301,17 8,62 2,95%

(*) Includes COO Directorate, OPSC, COBS, COEO, ORQR, CCCC, PECOD, JPRO, USRO & ERO in Europe

Annex 9

Annex 9A: 2012-2014 Budget Proposals by Complexes (in UA million)

3/4

2013 Proposed Budget

2014 Proposed Budget

Staff Costs Workload Overhead Total

Increase in

amount Staff Costs Workload Overhead Total

Increase in

amount

Increase

%

COMPLEXES BUDGET

Regional & Country Programs (ORVP)

31,47 5,31 20,34 57,12 2,32

31,47 5,60 21,40 58,47 1,35 2,4%

Regional Departments

17,92 2,22 3,50 23,64 0,53

17,92 2,34 3,65 23,91 0,27 1,2%

Field Offices

4,17 1,94 13,24 19,34 1,38

4,17 2,05 13,89 20,11 0,76 4,0%

Resource Mobilization (ORMU)

1,25 0,21 0,25 1,71 0,04

1,25 0,22 0,26 1,74 0,02 1,4%

Partnerships Unit (ORRU)

1,02 0,16 1,50 2,68 0,09

1,02 0,17 1,66 2,85 0,17 6,3%

Policy & Compliance (ORPC)

1,20 0,14 0,44 1,78 0,05

1,20 0,14 0,46 1,81 0,03 1,5%

Procurement & Fiduciary Services (ORPF)

5,91 0,63 1,42 7,96 0,22

5,91 0,66 1,48 8,05 0,10 1,2%

Sector Operations (OSVP)

20,27 7,02 5,79 33,07 0,59

20,27 7,02 6,01 33,30 0,23 0,7%

Infrastructure, PS & Regional Integration (OIVP)

26,69 9,78 6,52 42,99 1,79

26,69 10,43 6,75 43,87 0,89 2,1%

Knowledge Management & Research (ECON)

7,56 2,42 5,40 15,39 0,76

7,56 2,41 5,64 15,62 0,23 1,5%

Financial Management (FNVP)

14,79 1,59 6,48 22,86 0,51

14,79 1,64 6,78 23,21 0,35 1,5%

Corporate Services (CSVP)

21,36 3,19 5,72 30,26 0,24

21,36 3,31 5,97 30,64 0,38 1,3%

Institutional Governance & Corporate Management (UPRST)

27,30 6,66 10,12 44,09 1,53

27,32 6,96 10,40 44,67 0,59 1,3%

Presidency & SAPR

1,70 0,61 0,65 2,95 0,08

1,70 0,63 0,67 3,01 0,06 1,9%

Comminication Unit (ERCU)

1,78 0,48 0,59 2,85 0,03

1,78 0,50 0,62 2,90 0,05 1,7%

Security Unit (SECU)

1,42 0,53 0,49 2,44 0,06

1,42 0,56 0,51 2,49 0,05 1,8%

Integrity & Anti-Corruption (IACD)

1,62 0,18 0,41 2,21 0,05

1,62 0,19 0,42 2,23 0,03 1,2%

Strategy Unit (STRG)

0,52 0,04 0,14 0,70 0,01

0,52 0,04 0,14 0,70 0,01 1,1%

Chief Operating Officer (COO*)

9,39 3,04 4,38 16,81 0,87

9,41 3,17 4,54 17,12 0,31 1,9%

Legal & Advisory Services (GECL)

4,55 0,91 1,42 6,88 0,21

4,55 0,95 1,35 6,85 (0,03) -0,4%

Office of the Auditor General (OAGL)

1,81 0,24 0,61 2,66 0,17

1,81 0,25 0,63 2,69 0,03 1,2%

General Secretariat (SEGL)

4,15 0,55 1,37 6,07 0,11

4,15 0,57 1,43 6,16 0,08 1,4%

Ombu (OMBU)

0,36 0,10 0,07 0,52 (0,06)

0,36 0,10 0,07 0,53 0,01 1,4%

Special Appropriation

29,51 - 2,19 31,70 0,26

29,51 - 2,29 31,79 0,09 0,3%

YP programme

5,03 - 2,19 7,22 0,16

5,03 - 2,29 7,32 0,09 1,3%

New compensation framework

4,09 - - 4,09 -

4,09 - - 4,09 - 0,0%

Staff Retirement Plan

20,38 - - 20,38 0,10

20,38 - - 20,38 - 0,0%

0,0%

Total Complexes Budget

178,95 35,96 62,57 277,48 8,00

178,96 37,37 65,24 281,58 4,10 1,5%

BOARDS and URBD

Boards of Governors

- - 3,53 3,53 0,15

- - 3,68 3,68 0,16 4,4%

Boards of Directors

9,92 1,62 1,44 12,97 0,27

9,92 1,69 1,50 13,11 0,13 1,0%

Operation Evaluation (OPEV)

2,58 1,91 0,72 5,21 0,13

2,58 2,00 0,78 5,35 0,14 2,8%

Compliance Review & Mediation (CRMU)

0,55 0,20 0,66 1,40 0,06

0,55 0,21 0,70 1,45 0,05 3,8%

Tribunal

0,26 0,25 0,09 0,59 0,02

0,26 0,26 0,09 0,61 0,01 2,5%

0,0%

Total BOARDS and URBD

13,29 3,98 6,43 23,70 0,63

13,29 4,15 6,76 24,20 0,50 2,1%

GRAND TOTAL

192,24 39,94 68,99 301,17 8,62

192,26 41,52 72,00 305,78 4,60 1,5% (*) Includes COO Directorate, OPSC, COBS, COEO, ORQR, CCCC, PECOD, JPRO, USRO & ERO in Europe

Annex 9

Annex 9B: 2012-2014 Budget Proposals by Category of Expenses (in UA million)

4/4

Major Components

2011

Adjusted* Budget

2012

Budget

Increase

over

Baseline

Increase

%

Contribution

to the

Increase

2013

Budget

Increase

over 2012

Increase

%

Contribution

to the

Increase

2014

Budget

Increase

over 2013

Increase

%

Contribution

to the

Increase

(a) (b) (c=b-a) (d=c/a) (e=c/∑a)

(f) (g=f-b) (h=g/b) (i=g/∑b)

(j) (k=j-f) (l=k/f) (m=k/∑f)

Direct Operating Expenses 226.98

229.21 2.22 0.98% 0.78%

235.07 5.87 2.56% 2.01%

236.85 1.78 0.76% 0.59%

Staff Related Cost of which 182.78

189.17 6.39 3.49% 2.23%

192.73 3.56 1.88% 1.22%

192.76 0.04 0.02% 0.01%

Salaries 108.96 112.92 3.96 3.64%

113.48 0.56 0.49% 113.49 0.01 0.01%

Benefits 73.82 76.24 2.42 3.28%

79.25 3.01 3.94% 79.28 0.03 0.03%

Workload 44.20

40.04 (4.16) -9.42% -1.45%

42.34 2.30 5.76% 0.79%

44.09 1.74 4.12% 0.58%

Consultants 21.13 17.44 (3.69) -17.45%

17.95 0.51 2.94% 18.62 0.66 3.70%

Short Term Staff 1.69 0.78 (0.90) -53.43%

0.82 0.03 4.40% 0.86 0.04 4.40%

Business Travel 19.95 20.92 0.97 4.84%

22.47 1.55 7.39% 23.41 0.94 4.19%

Other Direct Expenses 1.44 0.89 (0.54) -37.68%

1.11 0.21 23.52% 1.21 0.10 9.23%

Support Cost 46.27

49.74 3.47 7.49% 1.21%

52.01 2.28 4.58% 0.78%

54.22 2.20 4.23% 0.73%

Human Resource Management 15.96 13.32 (2.65) -16.59%

13.90 0.58 4.38% 14.51 0.61 4.38%

Facility Management 19.54 23.93 4.40 22.51%

25.26 1.32 5.53% 26.28 1.03 4.07%

IT & Treasury Information System Mgt. 7.90 9.73 1.83 23.16%

10.05 0.32 3.32% 10.49 0.44 4.38%

Other Overhead (Publishing,

Reproduction, etc) 2.87 2.76 (0.11) -3.86%

2.81 0.05 1.68% 2.93 0.12 4.40%

Other Institutional General Expenses 13.22

13.61 0.39 2.96% 0.14%

14.09 0.48 3.52% 0.16%

14.71 0.62 4.40% 0.21%

Meeting Bank Business 6.31 7.02 0.71 11.30%

7.26 0.25 3.49% 7.58 0.32 4.40%

Audit, Legal & Advisory Service Fees 0.97 0.77 (0.20) -20.64%

0.81 0.03 4.40% 0.84 0.04 4.40%

Indirect Borrowing Expenses & Hedging

Premium 0.96 0.88 (0.09) -8.97%

0.91 0.04 4.40% 0.95 0.04 4.40%

RMC Training & Other Institutional

Expenses 4.97 4.94 (0.03) -0.70%

5.10 0.16 3.26% 5.33 0.22 4.40%

TOTAL REFERENCE BUDGET 286.47

292.55 6.08 2.12% 2.12%

301.17 8.62 2.95% 2.95%

305.78 4.60 1.53% 1.53%

(*) 2011 Approved Budget (UA 289.14 million) = 2011 Adjusted (UA 286.47 million) + Provision for Aniaman (UA 2.05 million) + Provision for two EROs (UA 0.61 million)

Annex 10

List of Institutional KPIs and 2012-2014 Yearly Targets

1/3

Indicators Unit Baseline

Targets 2012-2014

2012 2013 2014

I - Development Financing Operations

Total Bank Group Financing (1) UA million 5,520 5,725 5,625 5,525

ADB Public Lending UA million 2,490 2,324 2,260 2,193

ADB Private Lending UA million 1,110 1,276 1,340 1,407

ADF Financing UA million 1,900 2,100 2,000 1,900

NTF Financing UA million 20 25 25 25

Bank Group Financing Leverage

Capacity

ADB Private Sector Arranged

Financing (Syndication) UA million 400 250 375 625

ADB Private Sector Engagement with

LIC (2)

% 30% 30% 30% 30%

PS Co-financing Project Investments UA million 6,700 6,700 7,000 7,200

ADB Private Sector Trade Financing UA million 125 375 700

II - Operational Strategy Papers

RISPs Number 1 1 0 0

CSPs and Related Documents (3) Number 31 27 21 9

CPPRs Number 5 9 12 15

ESWs and Related Papers Number 44 40 42 47

CPPRs prepared by FOs % 25% 40% 50% 60%

Policies papers Number 4 4 3 3

III - Economic Knowledge Products

Publication (Books, WPs, Briefs,

Flagships, Bank Annual Report)

Number

130 142 149 157

Support for Results Measurement and

Development Effectiveness in Bank

Operations (ADOA, Statistical

Support)

Number

54 167 175 184

Capacity Development and Knowledge

Sharing (Training, Statistical Capacity

Building, Conferences, Seminars,

Eminent Speakers)

Number

268 229 240 252

IV - Disbursements

Bank Group Amount UA million 3,397 3,048 3,637 4,131

ADB Public Amount UA million 1,322 1,224 1,661 2,150

ADB Private Amount UA million 574 640 720 750

ADF Amount (4) UA million 1,497 1,175 1,245 1,216

NTF Amount (4) UA million 4.3 9 11 15

Bank Group Ratio (Investment only) % 30% 30% 30% 30%

ADB Public Disbursement Ratio % 20% 20% 20% 20%

ADB Private Disbursement Ratio % 50% 50% 50% 50%

ADF Disbursement Ratio % 20% 20% 20% 20%

V - Portfolio Management

Projects at Risk % 40% 35% 35% 30%

Operations Supervised Twice a Year % 50% 60% 60% 65%

Supervisions Led by Field Offices % 20% 35% 35% 40%

Projects Managed by Field Offices % 20% 25% 25% 30%

New Projects with Core Sector

Indicators (CSIs) % 75% 75% 75% 75%

Impaired Loan Ratio (Non-Sovereign

only) % <5% <5% <5% <5%

Annex 10

List of Institutional KPIs and 2012-2014 Yearly Targets

2/3

Indicators Unit Baseline

Targets 2012-2014

2012 2013 2014

VI - Process Efficiency

Lapse of Time between Approval and

First Disbursement Months 11 11 11 11

Lapse of Time for Procurement (Goods

and Works) Months 8 8 8 8

Lapse of Time for Procurement

(Services)

Months 10 10 10 10

Timely PCR Coverage % 85% 90% 90% 90%

Efficiency in disclosing information on

the website

Days

4 4 4 4

Efficiency Ratio (Cost to Income) –

ADB only (5)

%

30%

30% 30% 30%

VII - Cross-cutting Areas

Gender Mainstreaming in Operations

(6) % 100% 100% 100% 100%

Projects accessing Climate Finance (7) Number 3 9 9 9

VIII - Human Resources (PL)

Field Based (8) % 30% 32% 35% 37%

Gender Balance % 27% 29% 30% 31%

Staff Age Diversity (9) % 40% 48% 49% 50%

Staff Premature Attrition Rate (10) % 11% 1.50% 1.40% 1.30%

Staff Attrition Rate (11) % 1.60% 5% 5.50% 6%

Vacancy Rate - PL at post and offers

made and positions committed % 18%

8%

10%

10%

Vacancy Rate - staff at post % 13% 10% 12% 13%

IX - Budget and Expenses

Administrative Budget Implementation % 95% 95% 95% 95%

Field Offices Expenses % 17% 18% 20% 20%

Operations (12) Expenses % 60% 60% 60% 60%

Fixed Costs Ratio % 87% 87% 87% 87%

New untied trust funds

(bilateral/multilateral) UA million 100 80 90 100

% of Bank Operational Consultancy

committed by Trust Funds % 55% 55% 55% 55%

Capital Budget Implementation % 33% 33% 33% 33%

X - Implementation of Institutional

Commitments (13)

GCI-VI Commitments Number N/A 5 NA NA

ADF-XII Commitments Number N/A 11 NA NA

(1) Excluding HIPC and ADB special assistance SRF, NTF & Other Grants.

(2) Expressed as percentage of ADB PS Total Lending.

(3) CSPs and related documents are RBCSPs, Joint Assessment Strategy Papers, Interim Review Strategy Papers, Mid-

Term Review CSPs, Updated CSPs and Completion Reports.

(4) ADF and NTF disbursement targets are extracted from the Financial Projections Report 3Q2011 - ALCO.

(5) % of operating costs over total revenues where operating costs = Employees expenses (salaries & benefits) + General

Administrative expenses + Amortisation of fixed assets and total revenues = Net interest income + Net fees and

commissions + Market related revenues.

(6) % of new projects and new RBCSPs which identify at least one gender equality outcome indicator in the logframe.

(7) Number of newly approved projects accessing Climate Finance Instruments (like CDM, Green Development Fund,

etc.).

Annex 10

List of Institutional KPIs and 2012-2014 Yearly Targets

3/3

(8) Considered as % of Operational PL staff (PL staff in the three Operations Complexes + ECON PL staff + PL staff in

100% Operational Units outside Operations Complexes (ADB/BD/IF/99/330)).

(9) % of PL staff less than 45 years of age (excluding Board Officers).

(10) % of PL Staff resignations in the first three years of contract in comparison to total PL Staff at post during the same

period.

(11) PL staff leaving the Bank in comparison to total PL staff at post (excl. Elected Staff) during the same period.

(12) Operations defined as ORVP, OIVP, OSVP, ECON, and 100% Operational Units outside Operations Complexes

(OPEV, GECL.1, GECL.2, OPSC, CRMU, FFMA.2, FTRY.4 , FFCO.3, FFCO.4, CCCC, PECOD and ORQR).

(13) Commitments agreed during GCI and ADF negotiation process. COO will oversee implementation.

Annex 11

Assumptions & Allocation of Administrative Expenses and

Detailed Operational & Net Income Estimates 2011-2014

1/4

Annex 11A: Assumptions and Allocation of Administrative Expenses

The underlying assumptions of the Bank Group’s net income estimates for 2011-2014 are

summarised as follows:

Lending Programme:

The lending assumptions are summarized in Table 11A-1 and are consistent with the Bank’s

Medium Term Strategy. ADB approvals for 2012 are projected to be around UA 3.60 billion,

while ADF and NTF are UA 2.01 billion and UA 25.00 million respectively.

Table 11A-1: Projected Bank Group Lending

(in UA million)

2011 2012 2013 2014

ADB

Public Sector 2,490 2,324 2,260 2,193

Private Sector 1,110 1,276 1,340 1,407

Total 3,600 3,600 3,600 3,600

ADF 1,900 2,100 2,000 1,900

NTF 20 25 25 25

Disbursements:

Disbursement forecasts are based on historical disbursement profiles for new commitments

and specific schedules for existing signed loans adjusted to take into account information on

the execution of projects.

Rates of Return:

The rate of return on ADB and ADF investments for each year is the weighted average return

on the held-to-maturity investment portfolio and the trading investment portfolio. For 2011,

net income projections take into account valuation gains/losses on the investment portfolio,

impairment on the HTM portfolio, as well as unrealized gains/losses related to the fair

valuation of borrowings and derivatives as of 30 September 2011, and are assumed to remain

unchanged until the year end.

The financial projections for ADF incorporate the estimated foregone income effect of the

Multilateral Debt Relief Initiative (MDRI), debt cancellation initiative, but assume continued

special purpose reporting. The share of grants in ADF operations is assumed to remain at 35%

through the period.

Financial Charges:

Financial charges include projected charges on existing borrowings, computed on the basis of

outstanding balances and contractual borrowing rates, as well as projected charges on new

borrowings. The average cost of new borrowings is assumed to remain constant at LIBOR

flat.

Annex 11

Assumptions & Allocation of Administrative Expenses and

Detailed Operational & Net Income Estimates 2011-2014

2/4

Provisioning:

Provisioning for loan losses for ADB and NTF shall be calculated according to the revised

IAS 39 implemented in 2005. ADF presents special purpose financial statements and is not

subject to provisioning. Provisions estimates for ADB assume that borrowers in default status

as at 31 August 2011 will remain in that status throughout the period 2012-2014.

Cost Sharing:

Based on projections of each institution’s operational activities and relative size, the cost-

sharing formula for joint expenditures is contained in Table 11A-2 below. The cost sharing of

expenses between the institutions of the Bank Group is based on the revised cost sharing

approved by the Board of Directors on 9 November 201026

.

Table 11A-2: Bank Group Cost Sharing Formula

2011 2012 2013 2014

ADB 28.00% 28.28% 28.11% 28.07%

ADF 70.45% 70.18% 70.34% 70.38%

NTF 1.55% 1.54% 1.55% 1.55%

Allocation of Administrative Expenses for 2011:

The Bank Group’s budgeted Administrative Expenses amount to UA 289.14 million, UA

292.55 million, UA 301.17 million and UA 305.78 million for 2011, 2012, 2013 and 2014

respectively. In 2012, UA 193.45 million shall be classified as operational expenses, UA

83.20 million as non-operational expenses and UA 15.91 million as direct expenses.27

Using the cost-sharing formula approved in 2010, these expenses are shared among the three

institutions as indicated above. The allocation of the 2011 Bank Group Administrative

Expenses by institution is provided in Table 11A-3 hereunder.

Table 11A-3: Allocation of Bank Group Administrative Expenses for 2012

(UA million)

BUDGET PART Total

Budget ADB ADF NTF(*)

Total Bank Group Administrative Expenses Budget 292.55

Less Direct Administrative Expenses 16.06

Sub-Total 276.49 78.19 194.03 4.27

Shared Depreciation 4.68 1.32 3.29 0.07

Total Shareable Expenses 281.17 79.51 197.32 4.34

Plus Direct Expenses:

Direct Administrative Expenses 15.96 15.81 0.15 0.00

Non-Shareable Depreciation (ADB only) 0.10 0.10 0.00 0.00

Total Administrative Expenses 297.23 95.42 197.47 4.34

(*) In the event that the share of actual Bank Group Administrative Expenditure attributable to NTF exceeds 20% of NTF gross income, the

excess is borne by ADB.

26

ADB/BD/WP/2010/62/Rev.3/Add.1 27

These are expenses relating to: (i) borrowing (UA 1.00 million), depreciation of building (UA 0.10 million),

trust funds management fees (UA 0.93 million) and private sector expenses (UA 13.88 million) that are charged

directly to the ADB.

Annex 11

Assumptions & Allocation of Administrative Expenses and

Detailed Operational & Net Income Estimates 2011-2014

3/4

Annex 11B: Detailed Operational and Net Income Estimates 2011-2014

(in UA million)

2011 2012 2013 2014

ADB ADF NTF Total ADB ADF NTF Total ADB ADF NTF Total ADB ADF NTF Total

Loan Income 301.32 60.00 1.80 363.12 327.06 74.11 3.03 404.20 361.76 80.47 3.07 445.30 401.29 88.55 3.12 492.97

Interest Income on Investments 162.21 79.52 0.46 242.19 183.86 90.68 0.45 274.99 202.18 94.67 0.45 297.31 223.78 118.05 0.42 342.25

Other Income 23.80 23.80 23.84 23.84 23.84 23.84 23.84 23.84

Total Income 487.33 139.52 2.26 629.11 534.76 164.79 3.48 703.03 587.79 175.15 3.52 766.45 648.91 206.60 3.55 859.06

Financial Charges 205.04 0.02 205.05 253.66 0.02 253.68 265.78 0.02 265.80 287.78 0.02 287.80

Provision for Loan Losses 13.00 0.01 13.01 13.00 0.02 13.02 13.00 0.01 13.01 13.00

13.00

Total Operational Expenses 218.04 0.03 218.06 266.66 0.04 266.70 278.78 0.03 278.81 300.78 0.02 300.80

Operational Income 269.29 139.52 2.23 411.05 268.10 164.79 3.44 436.33 309.01 175.15 3.49 487.64 348.13 206.60 3.53 558.26

Share of Administrative Expenses 92.31 196.38 0.45 289.14 94.43 197.42 0.70 292.55 96.76 203.71 0.70 301.17 98.24 206.83 0.71 305.78

Depreciation 4.68 4.68 4.68 4.68 4.68 4.68 4.68 4.68

Total Admin. Expenditures 96.99 196.38 0.45 293.82 99.11 197.42 0.70 297.23 101.44 203.71 0.70 305.85 102.92 206.83 0.71 310.46

Sundry (gain) expenses (2.66) (2.66)

Provisions for impairment on treasury investments 3.13 3.13

Unrealized gain (loss) on fair-valued borrowings and related derivatives 1.59 1.59

Unrealized gain (loss) on derivatives on non fair-valued borrowings and others 16.80 16.80

Unrealised gain (loss) on macro-hedge swaps 6.81 6.81

Net realized and unrealized losses on investments (5.20) (5.20)

Translation gains/(losses) (28.38) (28.38)

ADF discount on accelerated encashment (29.40) (29.40) (29.40) (29.40) (32.20) (32.20) (30.00) (30.00)

Total Non-Operational Gains/(Losses) (7.91) (29.40) (37.31) (29.40) (29.40) (32.20) (32.20) (30.00) (30.00)

Net Income / (Deficit) 164.39 (86.26) 1.78 79.92 168.99 (62.03) 2.74 109.70 207.57 (60.76) 2.79 149.59 245.21 (30.23) 2.82 217.80

Allocable Income 167.57 168.99 207.57

245.21

Annex 11

Assumptions & Allocation of Administrative Expenses and

Detailed Operational & Net Income Estimates 2011-2014

4/4

Chart 11B: Bank Group 2012 Operational Budget

and Net Income Estimates

99.11

197.42

0.70

297.23

268.10

164.79

3.44

436.33

168.99

(62.03)

2.74

109.70

-100

-

100

200

300

400

500

ADB ADF NTF Total

UA

Mill

ion

Operational Income Total Admin. Expenditures Net Income

Note: ADF and Total Net Income includes a loss made on discount on accelerated encashment of UA 29.4 Million

Annex 12

2012-2014 Proposed Capital Budget

1/5

Annex 12A: Proposed Budget by Type of Investment

(in UA thousand)

Investment Type

2011 Budget Proposed Budgets Total Proposed

Budget

2012 Proposed Budget by location

Approved Revised 2012 2013 2014 2012-2014 TRA HQ FO ERO IT

(a) (b) (c) (d) (e) (f)=(c)+(d)+(e) (g) (h) (i) (j) (k)

Section 16 - Office Equipment 400 400 1,080 350 50 1,480 400 1,080

Section 17 - Office Furniture 1,027 1,027 3,120 850 500 4,470 1,000 3,370 100

Section 19 - IT & Communications Equipment 8,626 8,626 10,431 3,400 1,655 15,486 15,486

Section 20 - Buildings & Civil Works 28,714 28,714 5,210 17,300 500 23,010 300 9,000 13,410 300

Section 23 - Other Projects 1,250 1,250 750 400 500 1,650 50 1,600

Total 40,016 40,016 20,591 22,300 3,205 46,096 1,750 9,000 19,460 400 15,486

Percentages 4% 20% 42% 1% 34%

Annex 12

2012-2014 Proposed Capital Budget

2/5

Annex 12B: Detailed 2012-2014 Proposed Investment Programme

(in UA)

Projects

Location

2011

Approved

Budget

Overall

Budget

Proposed 3-Years Rolling Budget

2012 Proposal

2013

Proposal

2014

Proposal

Total

proposed

(2012-

2014)

budget HQ TRA FO

E.R.O

. IT

TOTAL

2012

Section 16 - Office Equipment

400,000 1,580,000

150,000 930,000

1,080,000 350,000 50,000 1,480,000

100835-CGSP1-TRA Photocopy & reproduction machine TRA 900,000

100915-CGSP1-FO Office Equipment FO 150,000

100919-CGSP1-FO Office Equipment B 5 FO 30,000

100921-CGSP1-TRA Office Equipment TRA 150,000 250,000

101121-CGSP1-TRA UPS & Accessories

100,000 100,000 100,000

100,000

101122-CGSP1-TRA Simultaneous Interpretation equipment TRA 150,000 150,000 150,000 150,000 150,000 300,000

1N0097-CGSP1-FO Technical Equipment RRCs FO 800,000 800,000

800,000

1N0102-CGSP1-FO Office equipment FO 100,000 100,000 100,000 50,000 250,000

1N0115-CGSP1-FO Office Equipment SSFO FO 30,000 30,000 30,000

Section 17 - Office Furniture

1,026,658 2,246,658 1,000,000 2,120,000 3,120,000 850,000 500,000 4,470,000

100914-CGSP1-FO Office Furniture FO

270,000

100916-CGSP1-TRA Office Furniture TRA 500,000 1,300,000

100923-CGSP1-FO Office Furniture B 5 FO

150,000

101091-CGSP1-E.R.O. Furniture (Ext Rep Office) E.R.O 176,658 176,658 100,000

100,000

101092-CGSP1-FO Office furniture FO 350,000 350,000 800,000 800,000 750,000 500,000 2,050,000

1N0096-CGSP1-FO Furniture RRCs FO 1,200,000 1,200,000 1,200,000

1N0114-CGSP1-FO Furniture SSFO FO 120,000 120,000 120,000

1N0117-CGSP1-TRA Office furniture TRA

1,000,000

1,000,000 1,000,000

Section 19 - IT & Communications Equipment

8,625,870 22,580,987 10,431,000 10,431,000 3,350,000 1,655,000 15,436,000

100611-CIMM0 - TRA Software and Training IT

448,306

100928-SAP Functional Upgrade IT 1,500,000 4,900,000 500,000 500,000 500,000

100929-Surveillance &Verification Software-OAGL IT 25,000 126,282

100931-Internet/Intranet IT 60,000 269,103 50,000 50,000 50,000

100932-CIMM0 - Enhancement of E-Recruitment & NPO IT 50,000 299,108 50,000 50,000 50,000

100933-General Bank Software IT

40,000 64,000 64,000 64,000

100934-Security Enhancement IT 50,000 500,000

100936-CIMM0 - Loan Disbursement & Portfolio Mngmt IT

105,177

Annex 12

2012-2014 Proposed Capital Budget

3/5

Projects

Location

2011

Approved

Budget

Overall

Budget

Proposed 3-Years Rolling Budget

2012 Proposal

2013

Proposal

2014

Proposal

Total

proposed

(2012-

2014)

budget HQ TRA FO

E.R.O

. IT

TOTAL

2012

100939-Telecom (PABX & VSAT) Enhancement IT

1,214,634

100940-Special Depts Hardware & Software acq IT 150,000 366,561 150,000 150,000 - - 150,000

100941-Broadband Integrated Telecommunications IT 823,640

100942-ADB Corporate Conference Services IT 130,682

100944-Deployment of IT Equipment IT 700,000 2,383,656 800,000 800,000 800,000 800,000 2,400,000

100945-P8 FILENET Plateform DARMS Migration IT 50,000 135,000 50,000 50,000 50,000

100946-Server Consolidation Project IT 420,000 920,755 580,000 580,000 580,000

100947-ADB Client Desktop Automatic Backup IT 30,000 277,113

100948-CAD system IT 700,000

101031-SAP Functional Upgrade - UA budgeting IT 300,000

101052-Information Security Protection Program IT 200,000

101058-Implementation of Outsourcing IT 250,000

101059-Storage Area Networking IT 1,000,000

101060-Infrastructure Improvements IT 150,000 950,000

101071-Network Resilience & Security Enhancement IT

800,101 660,000 660,000 660,000

101093-FFMA2- Project Risk & Rating Assessment phase 2 IT 200,000 200,000

101094-Broadband Integrat Comm Bits Phase II IT 300,000 300,000 450,000 450,000 450,000

101095-IT IP PBX Installation & Enhancement IT 650,000 650,000 400,000 400,000 400,000

101096-Video Conference Equipment Enhancement IT 360,000 360,000 350,000 350,000 350,000

101097-Collaboration Tool - Sharepoint IT 600,000 600,000 500,000

500,000

101098-Business Process Management IT 100,000 100,000 70,000 70,000 70,000

101099-ICT Provisioning for New Building in Tunis IT 440,000 440,000 50,000

50,000

101100-Information Security Projects IT 470,000 470,000

101101-BCP System & Automatic Alert Notification IT 300,000 300,000

101102-ICT Provisioning Field Office Expansion IT 414,150 414,150 1,845,000 1,845,000 485,000 200,000 2,530,000

101103-Enhancing Corporate Procurement Process IT 200,000 200,000

101104-Portfolio & Project Management System IT 100,000 100,000 50,000 50,000 50,000

101105-African Economic Outlook IT 250,000 250,000 130,000

130,000

101106-Summit Risk Modules IT 182,212 182,212

101107-Misys Learning Suite IT 90,000 90,000

101108-E-Learning For Staff & RMCs IT 100,000 100,000

101109-Medigate Project IT 70,000 70,000 50,000 50,000 50,000

101110-Hardware Risk Dashboard IT 300,000 300,000

Annex 12

2012-2014 Proposed Capital Budget

4/5

Projects

Location

2011

Approved

Budget

Overall

Budget

Proposed 3-Years Rolling Budget

2012 Proposal

2013

Proposal

2014

Proposal

Total

proposed

(2012-

2014)

budget HQ TRA FO

E.R.O

. IT

TOTAL

2012

101111-Development Results & Management System IT 150,000 150,000 150,000

150,000

101112-CIMM0-E.R.O. - IT equipments IT 164,508 164,508

1N0026-101060 Infrastructure Improvement IT 250,000 250,000 250,000

1N0072-Risk Reporting Tools IT 160,000 160,000 100,000 40,000 300,000

1N0078-NumeriX Credit Valuation Adjustment (CVA) IT 150,000 150,000 150,000 100,000 400,000

1N0079-NumeriX Market Risk Module IT 210,000 210,000 100,000 90,000 400,000

1N0080-Upgrade of Risk Analysis Tools IT 400,000 400,000 140,000 80,000 620,000

1N0081-Night batch scheduler tool IT 50,000 50,000 20,000 20,000 90,000

1N0082-Integrated Risk Assessment Platform IT 180,000 180,000 60,000 60,000 300,000

1N0083-Portfolio Risk Monitoring Tools IT 35,000 35,000 35,000 35,000 105,000

1N0084-Financial Analyzer System IT 40,000 40,000 40,000 40,000 120,000

1N0085-Sector Dataming System IT 60,000 60,000 40,000 40,000 140,000

1N0104-CIMM2 - Web Centre Services IT 250,000 250,000 250,000

1N0105-Entreprise Information Management IT 1,150,000 1,150,000 300,000 150,000 1,600,000

1N0111-FTRY- Back-Office & Cash Mgt Reconciliation IT 297,000 297,000 297,000

1N0122-Equity Funds Management IT 450,000 450,000 50,000

500,000

1N0123-Operational Risk Management Tool IT 160,000 160,000 160,000

1N0131-Two-Factor Authentication Project -Phase 2 IT 150,000 150,000 150,000

1N0133-Risk Management and Compliance IT 120,000 120,000 120,000

1N0134-Endpoint Security & Data Loss Prevention IT 200,000 200,000 200,000

400,000

Section 20 - Building and Civil Works

28,713,669 69,876,669

300,000 4,910,000

5,210,000 17,300,000 500,000 23,010,000

100911-CGSP1-FO Office Building Outfitting FO 568,000

100913-CGSP1-TRA Electrical Works and Cabling TRA 250,000

100917-CGSP1-TRA Building Fire Security TRA 140,000

100918-CGSP1-TRA Office Building Outfitting TRA 200,000 600,000 100,000 100,000 100,000

100920-CGSP1-TRA Heating and AC systems TRA 320,000 150,000 150,000 150,000

100922-CGSP1-Outfitting New Field offices/ NPO FO 300,000

100925-CGSP1- Construction of NGFO office FO 4,575,000

100959-SECU0-FO Security equipment Batch 5 FO 360,000 585,000 200,000 200,000 200,000

100991-CGSP1 - PRISA (Projet de Rénovation de Siège

Abidjan l HQ 15,000,000 41,000,000

6,000,000 6,000,000

101051-SECU0 ATR Security Equipment TRA 100,000 285,000 50,000 50,000

50,000

101055-HQ-Rehabilitation Villas and Cité BAD HQ 300,000 500,000

3,000,000 3,000,000

Annex 12

2012-2014 Proposed Capital Budget

5/5

Projects

Location

2011

Approved

Budget

Overall

Budget

Proposed 3-Years Rolling Budget

2012 Proposal

2013

Proposal

2014

Proposal

Total

proposed

(2012-

2014)

budget HQ TRA FO

E.R.O

. IT

TOTAL

2012

101056-CGSP1- Construction of AOFO office FO

8,000,000

101113-CGSP1-TRA Office space expansion TRA 2,360,000 2,360,000

101114-CGSP1-FO Outfitting expansion FO 750,000 750,000 1,200,000 1,200,000 500,000 1,700,000

101115-CGSP1-FO Construction of ZMFO FO 4,000,000 4,000,000

101116-CGSP1-FO Construction of SN, MG and GAFO FO 3,900,000 3,900,000

101117-Fragile States FO 750,000 750,000

101118-CGSP1-E.R.O. Outfitting & Installation E.R.O 358,669 358,669 300,000

300,000

101119-Services for CHRM TRA 190,000 190,000

101123-CGSP1-Electrical and AC enhancements HQ 60,000 60,000

101124-SECU0 - Security Equip. External Offices E.R.O 140,000 140,000

101125-SECU0- Security Equip. FOs in Fragile States FO 140,000 140,000

101126-SECU0- Security Equip. Enhancement in EROs FO 105,000 105,000

1N0027-FO-Building Construction - Phase1 FO 8,000,000

8,000,000

1N0075-CGSP1-FO Outfitting RRCs FO 2,950,000 2,950,000 2,950,000

1N0113-CGSP1-FO Outfitting South Sudan Office FO 260,000 260,000 260,000

1N0118-CGSP1-FO Study Acquisition of premises FO 300,000 300,000 300,000

Section 23 - Other Projects

1,250,000 1,976,000

50,000 700,000 750,000 400,000 500,000 1,650,000

100912-CGSP1-FO Vehicles FO 500,000 936,000

100924-CGSP1-Vehicles for New FO and NPO FO

80,000

100958-SECU0-Security Warden/Cores System TRA 210,000 420,000 50,000 50,000

50,000

101120-CGSP3-TRA Acquisition of vehicles TRA 40,000 40,000

101127-Generators for Inter PL FO 500,000 500,000

1N0076-CGSP1-FO Vehicles FO 600,000 600,000 400,000 500,000 1,500,000

1N0116-CGSP1-FO Vehicles SSFO FO 100,000 100,000 100,000

Grand Total

40,016,197 98,260,314 1,500,000 8,660,000

10,431,000 20,591,000 22,250,000 3,205,000 46,046,000