The 14th Meeting of the Housing and Infrastructure ...
Transcript of The 14th Meeting of the Housing and Infrastructure ...
The 14th Meeting of
the Housing and Infrastructure Committee
of Kowloon City District Council
Date: 15 March 2018 (Thursday)
Time: 2:30 p.m.
Venue: Conference Room, Kowloon City District Office
Present:
Chairman: Mr HO Hin-ming, BBS, MH
Vice-chairman: Mr NG Fan-kam, Tony
Members: Mr PUN Kwok-wah, JP
Mr KWAN Ho-yeung, Roger
Mr YUE Chee-wing, Admond (Arrived at 2:46 p.m.)
Mr YANG Wing-kit
Mr YEUNG Chun-yu
Mr HE Huahan
Mr NG Po-keung (Arrived at 2:46 p.m.)
(Left at 5:22 p.m.)
Mr LUK King-kwong (Arrived at 2:39 p.m.)
(Left at 4:25 p.m.)
Mr LAM Tak-shing
Ir Dr CHENG Lee-ming
Mr CHO Wui-hung
Mr SIU Tin-hung, Terence (Arrived at 2:40 p.m.)
Mr LAI Kwong-wai (Left at 5:58 p.m.)
Mr SIU Leong-sing
Mr LO Chiu-kit (Arrived at 3:02 p.m.)
Ir CHEUNG Yan-hong, MH
Mr LAM Pok, Jimmy (Left at 5:20 p.m.)
Secretary: Mr IP Wai-kong, Eddie Executive Officer I (District
Council), Kowloon City District
Office
Absent:
The Hon LEE Wai-king, Starry, SBS, JP
Mr TING Kin-wa
Ms LEUNG Yuen-ting
2
In Attendance:
Miss SO Yi-ching, Venus Assistant District Officer (Kowloon
City), Kowloon City District Office
Mr WONG Kam-keung,
Eric
Senior Liaison Officer (Building
Management), Kowloon City District
Office
Ms CHENG Wan-ying,
Johanna
Senior Town Planner/Kowloon 2,
Planning Department
Mr YIP Wing-ping, Ronny Property Service Manager / Property
Service (Kowloon West and Sai
Kung)3, Housing Department
Ms Alisa TSE Senior Building Surveyor / E3,
Buildings Department
Attendance by Invitation:
Item 2 Miss NG Hoi-yan Project Manager (School Building)2,
Education Bureau
Mr WONG Wai-leung,
Dominic
Assistant Project Manager (School
Building) 21, Education Bureau
Mr WONG Kui-hung Supervisor, Munsang College
Ms Kuby CHAN Principal, Munsang College
Mr Louis LUI Deputy Principal, Munsang College
Mr CHAN Bing-hung Member, School Construction
Committee, Munsang College
Mr LAU Tak-cheung,
Vetus
Director, Percy Thomas Partnership
(HK) Limited
Mr LAU Wai-hung Deputy Construction Director, Percy
Thomas Partnership (HK) Limited
Ms YEUNG Yim-yu Senior Architect, Percy Thomas
Partnership (HK) Limited
Item 3 Mr YEUNG
Chung-cheung, Tony
Senior Engineer / Consultants
Management 5, Drainage Services
Department
Mr LEI Kuok-kun Engineer / Consultants Management
2, Drainage Services Department
Environmental Protection Officer
3
Mr LEE Sing-tim, Wallace (Sewerage Infrastructure) 43,
Environmental Protection
Department
Mr FOK Chun-sing,
Dennis
Associate Project Manager, Atkins
China Limited
Mr LEE Wing-kin Project Engineer, Atkins China
Limited
Ms KWAN Yuen-ting Senior Transport Engineer, Atkins
China Limited
Item 4 Ms YAN Sin-wah Senior Manager, Community
Development, Urban Renewal
Authority
Mr Daniel LEE Senior Manager, Building
Rehabilitation, Urban Renewal
Authority
Item 5 Ms YAN Sin-wah Senior Manager, Community
Development, Urban Renewal
Authority
Items 6-7 Ms KONG Pui-heung, Ada Housing Manager / Kowloon West
and Sai Kung 1, Housing Department
Mr LAM Yam-fung Assistant Housing Manager /Tenancy
(Kowloon West and Sai Kung 1) 1,
Housing Department
Item 8 Ms KONG Pui-heung, Ada Housing Manager / Kowloon West
and Sai Kung 1, Housing Department
Mr LAM Yam-fung Assistant Housing Manager /Tenancy
(Kowloon West and Sai Kung 1) 1,
Housing Department
Ms YUNG Suk-ching Chief Health Inspector 1, Food and
Environmental Hygiene Department
Mr YEUNG Chi-yuen,
Ivan
Health Inspector (Pest Control), Food
and Environmental Hygiene
Department
4
Mr Myron NG Assistant General Manager (Public
Affairs), Link Asset Management
Limited
Mr YIU Hon-sang Community Relations Manager, Link
Asset Management Limited
✽ ✽ ✽
Opening Remarks
The Chairman of the Housing and Infrastructure Committee welcomed
all Members, representatives of government departments and the persons in
attendance to the meeting. The Secretariat was informed before the meeting that
The Hon Starry LEE and Mr TING Kin-wa were unable to attend the meeting. Also,
Mr YIP Wing-ping, Ronny, Property Services Manager/S (KWS)3 of the Housing
Department (HD), would attend the meeting on behalf of Mr LAU Ching-kwong,
Wallace Senior Property Services Manager (KWS) of HD who had another official
commitment.
Prior to discussion of the agenda items, the Chairman reminded Members
of their obligation to declare interests. The system of declaring interests was
stipulated in the “Kowloon City District Council Standing Orders” (Standing Orders).
If Members’ personal interests in respect of property ownership, occupation or
investment etc. involved conflict of interest with the items under discussion later, they
should make declaration before the discussion for consideration to be made whether
the members concerned should withdraw from the discussion or voting. In addition,
according to the Standing Orders, the quorum of committee meetings was half the
number of members. As there were 22 members in the Housing and Infrastructure
Committee (HIC), once there were less than 11 members present at the meeting, he
would terminate the discussion immediately.
Confirmation of the Minutes of Last Meeting
2. The Chairman declared that the minutes of the 13th meeting were
confirmed unanimously without amendments by the Committee.
The Proposal of Constructing an Assembly Hall in Munsang College at No. 8
Dumbarton Road in Kowloon City
(Paper No. 12/18)
5
3. Miss NG Hoi-yan, Project Manager (SB)2 of the Education Bureau
(EB), Mr. LUI Hang-sum, Deputy Principal of Munsang College and Mr LAU
Wai-hung, Deputy Construction Director of Percy Thomas Partnership (HK) Ltd.
introduced the paper.
4. Ir Dr CHENG Lee-ming stated that full support was given to the plan of
constructing an assembly hall in Munseng College (Assembly Hall Plan) and he
pointed out that Munsang College had been making contribution to education for over
a century and had nurtured many outstanding students. It was hoped that a funding
application to the Legislative Council (the Legco) would be made by the Education
Bureau (EB) as soon as possible for the provision of modern facilities for the students
to further enhance the teaching quality of the college.
5. Mr CHO Wui-hung stated that an assembly hall was a basic facility for a
secondary school and, in addition to that, the school had promised to share the school
facility with the community. Thus he supported the “Assembly Hall Plan”.
6. Mr LUK King-kwong extended support to the “Assembly Hall Plan” but he
was worried that its works might affect traffic as there was considerable traffic flow in
the vicinity of the school before and after school hours.
7. Mr YANG Wing-kit said he supported the “Assembly Hall Plan”. In
addition, he pointed out that Kowloon Tong School (Secondary Section) also faced
the same problem of lacking an assembly hall. It was hoped that the relevant
departments would treat all schools equally and accelerate improvements to other
schools in the district.
8. Ir CHEUNG Yan-hong, MH said Munsang College had nurtured many
outstanding alumni and he gave full support to the “Assembly Hall Plan”.
According to the papers submitted by EB, a funding application would be made to the
Finance Committee (FC) of the Legco in the third quarter of 2018 and it was expected
that construction works would commence at the end of 2018 if approval was given by
FC. He hoped that EB would provide the relevant building plans. However, in
view of the frequent filibustering in the Legco in recent years, he enquired whether
EB could accord priority to the funding application of the plan to the Legco.
9. Mr Admond YUE expressed strong support for the “Assembly Hall Plan”
and he hoped that a funding application would be made to the Legco by EB as soon as
possible. In addition, he hoped that the school would open the facilities of the
6
assembly hall for use by the community and invite local district councillors to discuss
about the public use of the hall so as to benefit the community.
10. Mr Jimmy LAM said that he supported the “Assembly Hall Plan” and
opined that every school should have a complete set of supporting facilities. He also
hoped that the hall facilities of schools would be open for public use to benefit the
community. Besides, he was also concerned about the impact of the works on the
surrounding environment and he hoped that the school or the relevant departments
would provide the detailed works plan and progress to the owners’ corporations of the
nearby buildings and local district councillors. In addition, as many schools in the
district also needed hall facilities, it was thus hoped that the relevant departments
would assist those schools to improve their facilities step by step and provide the
relevant timetable.
11. Mr Tony NG voiced his support for the “Assembly Hall Plan” and he hoped
that the hall would be open for use very soon. He also suggested that the assembly
hall be open to community organisations for activities on Saturdays, Sundays and
public holidays.
12. The Chairman enquired whether the facilities of Munsang College
(Kowloon) could be lent to Munsang College (Hong Kong Island) for use in case the
latter had insufficient facilities and whether there would be similar expansion plan in
Munsang College (Hong Kong Island). In addition, it was asked whether the present
building height restriction of the District would be fully utilised in the construction of
the proposed assembly hall for future expansion of the school premises.
13. Miss NG Hoi-yan of EB made a response, the main points of which were as
follow:
- EB planned to submit its funding application to FC of the Legco for
the works in the third quarter of 2018 in accordance with normal
procedures and if approved, it was expected that the construction
works would commence at the end of 2018 and be completed in the
first quarter of 2021. However, filibustering was beyond the control
of the Bureau;
- as for the problem of “sub-standard school premises”, EB had been
trying all means to upgrade the facilities of the schools including
improvement works to the schools from 1994 to 2006 as well as the
yearly major revamp works/urgent repairs for schools etc. to ensure
7
the safety of the school premises and to upgrade the school facilities
to improve the school environment; and
- as for in-situ redevelopment of schools, the Bureau would consider
the applications of all eligible public secondary and primary schools
in the territory and assist the schools to upgrade their facilities
according to a series of factors for consideration.
14. Mr LAU Wai-hung of Percy Thomas Partnership (HK) Ltd. made a
response and the main points of her response were as follow:
- during the works period, arrangements on the separation of pedestrian
and vehicular flow would be made. As the entrance for students of
Munsang College was at Dumbarton Road, all construction vehicles
would use the entrance at Junction Road for entry to and exit from the
site and strict supervision on the vehicles entering and leaving the site
would be carried out by the works contractors and sufficient safety
measures would be adopted. Also, the vehicle entrance and exit at
Block E of the school premises where works were being conducted
would be used by the works vehicles involved in the above plan. As
the scale of the proposed works was relatively small, negative impact
on the traffic in the surrounding areas would not be posed during the
construction period;
- mitigating measures would be provided in accordance with the
provisions of the Noise Control Ordinance (Cap 400) and the Air
Pollution Control Ordinance (Cap 311) to control noise and dust
nuisance for ensuring compliance with the established standards and
criteria. In addition, it was estimated that piling works would take
about 8 months and H-type steel piles would be used after boring.
As there would be no percussion on the H-type steel piles, there
would be relatively little noise pollution;
- provisions would be set out in the contract requiring the contractors to
take environmental mitigating measures, strictly control noise
pollution and dust and water drainage during the works so as to
comply with the standards and criteria set by the Environmental
Protection Department (EPD). There would be no negative impact
on the surrounding environment during the works. In addition, the
8
contractors would regularly spray water at the site, control the speed
of vehicles and wash the tyres of construction vehicles to minimise
the amount of dust;
- the design of the assembly hall included: (i) adopting the set-back
design to leave space between it and the nearby buildings to avoid
blocking the day light exposure of adjacent buildings and the
assembly hall so that natural day light would illuminate the hall and
ventilation effect be enhanced; (ii) the adjacent multi-function room
would be connected with the assembly hall to encourage students to
take part in diversified activities; (iii) the wide corridor design would
enhance the flow of people and provide space for teachers and
students to get together; (iv) to tie in with the environmental concept,
the assembly hall building would provide a green rooftop garden and
small green corners for enhancing students’ knowledge on
environment. They would also be used by students as activity
platforms; and (v) on the whole, the school would adopt a barrier-free
design to enhance the quality and uses of the facilities, which could
help achieve harmony between the abled and disabled; and
- the height of the proposed assembly hall was about 30 metres which
was comparable with the height of its surrounding buildings.
15. Mr LAU Wai-hung of Percy Thomas Partnership (HK) Ltd.
supplemented that all the plans of the assembly hall were submitted to the Buildings
Department and the general plan was approved. The plans for the foundation and
structural works were expected to be approved progressively in the near future. The
progress was satisfactory and preparations for calling tender were being made.
16. Ms Kuby CHAN, Principal of Munsang College, in response, said the
school believed that EB understood the needs of all schools in the territory.
Munsang College sought financial assistance for building hall facilities for its
secondary section in 2009 and approval for carrying out the preliminary feasibility
study was given by EB in 2012 while approval for detailed works design was granted
in 2014. The school had followed the established procedures to lodge an application
for building the assembly hall facilities, carrying out all the work related to the works
plan and listening to the views of different stakeholders and local people.
Considerable procedures and time were involved in the plan and the whole process of
application was no faster than that of other schools.
9
17. Mr WONG Kui-hung, Supervisor of Munsang College stated that
Munsang College was located at Kowloon City District and since the plan of building
an assembly hall was hatched, the school had considered sharing the facilities with the
community and the hall would be open to the District Council, educational
organisations, community groups and social welfare organisations so long as the
school operation would not be affected. Munsang College (Hong Kong Island) was
a standard school and it had no expansion plan for the time being. However,
because of geographical factors, except for student exchange activities, there was
little chance that it would use the facilities of Munsang College (Kowloon). Also,
Munsang College (Hong Kong Island) and Munsang College (Kowloon) were two
independent administration units and the Munsang College (SSB) Limited, as a
school sponsoring body, would only be responsible for policy and financial resources
coordination.
18. Mr LUI Hang-sum, Deputy Principal of Munsang College supplemented
that the design plan and progress of the proposed assembly hall were uploaded onto
the website of the school and visits to the school by Members were welcome so that
the design of the assembly hall could be explained more detailedly to them by the
school.
19. Mr YANG Wing-kit stressed that he was expecting the soonest completion
of the assembly hall of Munsang College but it was hoped that EB would not neglect
the needs of the other schools in the district and relevant facilities should be provided
to the schools in the district as soon as possible.
20. Mr LO Chiu-kit declared that his two children were studying at the
Munsang Primary School and stressed that he supported the above plan in the
capacity of a parent.
21. The Chairman concluded that all Members who had spoken on the
“assembly hall plan” well supported the plan. He hoped that EB would submit the
funding application to the Legco before October this year.
Public Works Programme Item No. 4344DS: Upgrading of Central and East
Kowloon Sewerage – Phase 3
(Paper No. 13/18)
22. Mr YEUNG Chung-Cheung, Tony, Senior Engineer/Consultants
Management 5 of the Drainage Services Department (DSD) and Mr LEE
Wing-kin, Project Engineer of Atkins China Ltd. introduced the paper.
10
23. Mr YANG Wing-kit stated that he supported the above works and raised the
following views/enquiries: (i) the drainage works in one section of Maidstone Lane
was near parking spaces and he asked whether the excavation works would affect the
number of parking spaces; (ii) it was worried that the drainage works would affect the
operation of the car companies in that section and he hoped the Department would
handle it with care and maintain adequate communication with the shop operators
there; (iii) there were some food establishments, shops, parking spaces and residential
dwellings in the Chi Kiang Street area and it was worried that the works might have
impact on pedestrian walkway and shop operators; (iv) the section at Tin Kwong
Road and the rear lane of Maidstone Lane was the entrance/exit of another building
and the works should avoid impact on its residents; and (v) the works were mainly
carried out at the side lanes and the shop operators there would definitely be impacted.
Thus he enquired whether there was any compensation mechanism for the affected
shop operators and suggested that the claim procedures should be simplified.
24. Mr Roger KWAN stated that there was always bursting of pipelines in the
district in recent years and it was hoped that the Department would replace the
pipelines as soon as possible. Also, Ha Heung Road and Lok Shan Road were the
main access of the old district and were frequently used by large vehicles. Thus an
enquiry on the ways the works were carried out and then impact on the residents and
pedestrians was made.
25. Ir Dr CHENG Lee-ming opined that the above works were carried out on a
piece-meal and scattered basis and he was worried that the stability and structure of
the whole sewerage system would be affected. An enquiry was made on the reasons
for just replacing part of the pipeline at isolated locations but not the whole pipeline.
26. Mr Jimmy LAM stated that strong support was given to the above works
and he raised the following views/enquiries: (i) whether the rear lane from Chatham
Road North to the Ko Shan Road area would be closed for the works and the
measures to be taken to reduce its impact on rear lane users; (ii) Chatham Road North
was a trunk road and in what way the works would be carried out by the Department
in order to avoid impact on traffic; (iii) because of the overflowing of sewage, he had
made an inspection on the pedestrian lane off Sin Hua Mansion at No. 89-93 Ma Tau
Wai Road with the representatives of DSD and EPD and enquired about the reasons
for not including the problematic pipelines at that location into the improvement
works; (iv) the District was infested with mosquitoes in recent years and as the works
area was close to the residential dwellings, what measures the Department would take
to prevent mosquito nuisance arising from the works, (v) there were dump trucks
11
frequenting the area and debris dropping off onto the roads from some of the trucks
going up the slanting roads. He asked if the relevant department and the contractor
would help clear the debris on the roads; (vi) he enquired about the actual time works
would be undertaken during off peak hours at Chatham Road North and the road
closure arrangements and whether all the traffic lanes could remain in use during peak
hours; and (vii) there were several major redevelopment projects in the To Kwa Wan
area and it was suggested that the Department should replace the pipelines in the Ma
Tau Wai area to make preparations for the double increase in the population projected
in the area.
27. Mr Terence SIU stated that he supported the above works in principle and
raised the following views/enquiries: (i) works would be carried out in the rear lane of
Tam Kung Road, Shing Tak Street and Ma Tau Chung Road and it was hoped that
certain space would be reserved for use by pedestrians during the works period; (ii)
stocks were placed in the rear lanes by food establishments and shops, and the
Department should have adequate communication with the relevant shops beforehand;
(iii) works were carried out on the traffic lanes of Sung Wong Toi Road and Argyle
Street where traffic flow was heavy and it was hoped that the works would be
completed in a short time; and (iv) if there were residents opposing to the trench
method, it was hoped that the more expensive trenchless method would be adopted by
the Department.
28. Mr Jimmy LAM raised the following views/enquiries: (i) he was concerned
about the exact location of the works in the Hung Hom area and he hoped that
detailed relevant information would be provided by DSD; (ii) he would like to know
if the above-mentioned works in the district would be conducted at the same time and
the details about the relevant manpower arrangements; (iii) traffic was very busy in
the Hung Hom area and traffic would be seriously impacted if the works were carried
out on the traffic lanes and what measures the Department would take to minimise the
impact on traffic; (iv) he requested the Department to post up notices on the works
and the timetable to notify the residents in the surrounding areas about this in advance;
and (v) he was concerned about the time of the works and the noise nuisance to be
caused.
29. Ir CHEUNG Yan-hong, MH stated that he was concerned about the
improvement works in Tak Man Street and Dockyard Street in Whampoa District and
opined that the works would definitely lead to traffic diversion as traffic was busy
there from 9 a.m. to 9 p.m., and thus he raised the following views/enquiries: (i) he
enquired about the time the night-shift works would be conducted in Tak Man Street
and it was hoped that the consultancy company, based on common understanding,
12
would avoid conducting the works after 10 p.m. when scheduling the works to avoid
impact on the residents ; (ii) no night-shift works were carried out by the MTR
Corporation Ltd. (MTRCL) when building the Whampoa Station as efficiency was
low at night and he suggested that reference be made to the practice of MTRCL to
conduct the pipeline works during day time to avoid causing nuisance to the residents;
(iii) he asked if arrangements could be made by the Department to maintain two-lane
traffic on both sides during the works period; (iv) he hoped that the Department
would be concerned about the noise nuisance caused by the iron plates temporarily
covering the trenches when traffic was resumed; (v) the residents of the Whampoa
area were greatly disturbed by the construction of the MTR Whampoa Station and
were worried about any new projects in the area. It was hoped that the Department
would maintain good communication with the residents to minimise impact on them.
A community relation officer should be assigned to answer the phone calls and handle
the complaints by residents.
30. Mr Ronald YEUNG showed support for the above works. He pointed out
that the works had entered its third phase and he believed that DSD and the
consultancy company had accumulated sufficient experience. He reminded the
relevant departments to maintain sufficient communication with the stakeholders and
provide contact information to them. He paid special concern to the exact location
of the works at Sung Wong Toi Road and Mok Cheong Street. As illegal parking
was serious on Mok Cheong Street, there would be certain impact on traffic no matter
the works were carried out on the walkway or the carriageway. There was quite
heavy traffic on Sung Wong Toi Road and in case of any traffic problem there, it was
worried that the drivers might not be able to get the relevant information. In
addition, he enquired about the role played by the community liaison officers and
their working hours.
31. Mr Admond YUE expressed strong support for the above works. He
pointed out that recently there were on average two incidents of pipeline bursting
yearly at the junction of Hok Yuen Street and Ma Tau Wai Road and that of Man Lok
Street and Ma Tau Wai Road. During repairs, the engineer involved explained that
these happened due to ageing pipelines and major replacement works would be
conducted in the district. As such, he asked why the replacement works of pipelines
at Ma Tau Wai Road were not included into the above works.
32. Mr LAI Kwong-wai stated that he basically supported the above works and
he raised the following views/enquiries: (i) he believed that the above works would be
conducted in different phases and it was hoped that the Department would provide the
time table of the works scheduled at different locations, (ii) in view of the heavy
13
traffic flow at Ma Tau Kok Road, he enquired about the traffic diversion measures to
be adopted and the Department was requested to have adequate communication with
the residents on traffic diversion before the commencement of the works; (iii) he
hoped to know whether different measures would be taken in respect of works on the
roads and the rear lanes; (iv) paragraph 5.2 of the Department’s paper mentioned that
an automatic detection system would be used to control the change of traffic signals
to ensure smooth traffic flow on the closed roads. He wished to have a better
understanding of the operation mode of the automatic detection system; (v) in what
ways the Department would consult the affected residents before the works were
conducted and whether relevant works information would be provided and discussion
on the works arrangements with the residents would be held; and (vi) DSD had set up
a works liaison group. He asked whether the public would be allowed to attend its
meetings and participate in the discussions or the group would just reflect the views
of the public or serve as a channel for answering public enquiries about the works.
Furthermore, he reminded that part of the above improvement works overlapped with
the works of the Central Kowloon Route (CKR) and the contractors should try the
best to avoid the occurrence of accidents.
33. Mr LUK King-kwong hoped that the Department would provide the time
table of the works scheduled at different locations so that early preparations could be
made by those affected. Also, he pointed out that a 900-1050 mm sewer was
planned to be built between Prince Edward Road East and Olympic Avenue to cope
with the population increase in the Kai Tak Development Area. However, the sewer
in the Shatin to Central Link (SCL) area was mainly 300 mm in diameter. As there
were many redevelopment projects in that area, he was worried that the sewer might
not be able to cope with the population increase after redevelopment.
34. Mr LO Chiu-kit raised the following enquiries: (i) it was stated in the paper
that the discharge capacity of the current sewers in the district was not adequate and
he hoped that the Department would explain the specific impact caused by the
insufficient discharge capacity and the ways the above works would improve the
effectiveness of the sewers in the district; (ii) the cost footed by the Kowloon City
District in the above works; (iii) the Ka Wai Estate and Hung Hom Estate areas were
prone to serious flooding. However, the Department opted to use the 375-450 mm
sewers and conduct improvement works on piece-meal basis at different locations in
the district. He asked if the decision was made owing to financial restraints and
whether the above project was forward-looking and able to cope with the sewage
discharge volume of the District after 2024; and (iv) there was serious traffic
congestion in the Wuhu Street and Station Lane area. He questioned if DSD would
conduct a traffic impact assessment for the above works.
14
35. Mr SIU Leong-sing was concerned about the ways the works liaison group
making close contact with the public and he opined that follow-up actions to the cases
reported via the 1823 hotline system were slow. He suggested that the mobile phone
number of the project officer be provided to the front-line police staff and local
district councillors to ensure immediate settlement of the problems. In addition, he
was worried that the above improvement works might have impact on the existing
metered parking spaces and asked for the reprovision of the affected metered parking
spaces.
36. Mr LEE Wing-kin of the Atkins China Ltd. made a response, the main
points of which were as follows:
- enquiries made by the public to the hotline set up during the works
period were answered by dedicated staff round the clock;
- at present, the works at Maidstone Lane would be conducted at the
side of the carriageway by phases; trench method would be used for
the works in Ha Heung Road while trenchless method be used in Lok
Shan Road. Also, such works would not occupy more than one
traffic lane in order to reduce impact on traffic; and
- the drainage services works at the rear lanes and on the roads would
be conducted by phases. For works on roads, traffic would be
segregated by water-filled barriers and for works at the rear lane,
pedestrian flow would be segregated by plastic barriers. Also, there
would be appropriate diversion signs at the works sites.
37. Ms KWAN Yuen-ting, Senior Traffic Engineer of Atkins China Ltd.
made a response, the main points of which were as follows:
- the consultancy company had conducted a preliminary assessment on
traffic at Chatham Road North and Ha Heung Road and it was
suggested that works be carried out during non-peak hours and road
closure be done by stages and it was scheduled temporarily that the
works hours would be from 10 a.m to 4 p.m. on Monday to Saturday
and from 6 a.m. to 6 p.m. on Sunday. The number of traffic lanes
for use would be maintained during peak hours. The consultancy
and the contractors would remain in close contact with the Transport
Department (TD) to fine-tune the arrangements and time for the
15
works. In addition, the contractors would again conduct a traffic
impact assessment before the commencement of the works to reduce
impact on traffic;
- the traffic liaison group, comprising of representatives of DSD, TD
and the Hong Kong Police (the Police), traffic consultants hired by
the contractors and the site engineers, aimed at making regular
reviews and assessing the temporary traffic measure options;
- as traffic on Tak Man Street, Sung Wong Toi Road and Ma Tau Wai
Road was relatively busy, the improvement works would be
conducted during night time and the number of traffic lanes for use
would remain the same during peak hours and day time;
- the mitigating measures under the traffic impact assessment would
reduce the impact on traffic to the minimum and should be adequate
to cope with the traffic flow. Also, it was understood that the section
of the new lane from Kai Tak Development Area to Kowloon East
would be completed in mid-2018, which would further relieve the
pressure on traffic in the district; and
- the automatic detection system was subject to approval by the traffic
liaison group and it would exercise control on the change of the
traffic signs in response to the request by TD and the Police according
to the prevailing traffic conditions at the scene.
38. Mr Dennis FOK, Deputy Project Manager of Atkins China Ltd. made a
response, the main points of which were as follows:
- a series of measures against mosquito nuisance included: (i) avoid
water accumulation at source. The site staff would conduct site
inspection every day and if water stagnation (mainly after the rain)
was found, immediate request to clear it would be made to the
contractors; (ii) during the mosquito nuisance peak season such as
summer, mosquito larvicidal oil would be sprayed in the sites at least
thrice a week to prevent the growth of mosquito/insect nuisance; (iii)
the staff of the Food and Environmental Hygiene Department (FEHD)
would conduct inspections to check if there was water stagnation in
the sites. They would collect information on water accumulation
16
and mosquito nuisance; and (iv) if there was mosquito nuisance near
the sites, immediate follow-up actions would be taken;
- part of the above improvement works did overlap with the works for
CKR and preliminary assessment showed that excavation would not
be done repeatedly at any location and deep excavation quite far away
from the pipelines was performed on CKR. In addition, TD would
review the traffic diversion measures proposed for various works and
thus Members did not need to worry about it;
- generally, as the diameter of the pipes in the rear lanes were relatively
smaller and the pipes were located near the surface, the trench method
would be employed. As for the pipes of roads, they had a greater
diameter and were usually situated deeper underground, thus
consideration on either the trench method or the trenchless method
would be made depending on the condition of the scene. Therefore,
the segregation devices for the works on roads would be of a larger
scale than those for the works at the rear lanes.
39. Mr YEUNG Chung-cheung of the Drainage Services Department made a
response, the main points of which were as follows:
- the above improvement works aimed at coping with the sewage
discharge produced by the projected population in 2041. The
Department had used the computerised hydraulic model to calculate
the sewage discharge in 2041 and the findings indicated that many
pipes had insufficient discharge capacity and their locations were
rather scattered. The current project would use pipes with greater
discharge capacity that would be able to cope with the sewage
discharge in 2041 and the sewers with defects would be replaced and
improved;
- the above works aimed at improving the sewerage system. However,
DSD attached great importance to the flooding problem and a
separate project was carried out to study the whole rainwater
discharge plan and consultation would be conducted on the plan in
due course;
- the current works aimed at laying sewers with greater diameters to
replace the present sewers with insufficient discharge capacity. As
17
for the leakage problem, the Department’s maintenance section would
undertake routine inspections and if leakage was found, urgent repairs
and replacement would be arranged by the Department. In addition,
DSD had launched another project with plans for inspecting,
rehabilitating and carrying out overall and large-scale replacement of
ageing underground sewers and stormwater drains in the district.
The project was now under consultation;
- the Department had completed an overall impact assessment on traffic
by the works and submitted different proposals to TD and the Police.
As the above improvement works needed to be carried out in phases,
works on some road sections might commence one or two years later.
Thus the contractor would re-assess the traffic conditions before the
commencement of the works and when required, new temporary
traffic management options would be submitted. During the period,
close contact with the relevant stakeholders, residents and district
councillors would be maintained by the Department, site engineers,
front-line staff and the contractors. In response to the views of
various parties, slight adjustments on works arrangements and
temporary road diversion would be made under feasible
circumstances and the option would be implemented after trial so as
to reduce the impact of the works to its minimum;
- the consultation of the first phase of the above improvement works
was to collect the views of the District Council and to fine-tune the
design plan. The Department noted the views of Members on works
at the rear lanes and a works liaison group comprising the
Department’s site engineers, front-line staff and staff of the
contractors would be set up when the works started. The works
liaison group would proactively contact the management office of the
nearby buildings, resident representatives and local district
councillors for consultation and distribution of relevant information
including the works time table, temporary traffic road diversion
measures, contact means etc. A hotline would also be set up during
the works period for collecting residents’ views on the improvement
works and answering residents’ enquiries by site community liaison
officers. Members of the public could also call 1823 for enquiries;
- as for noise nuisance, all works including the works being carried out
at night had to comply with the relevant environmental protection
18
ordinance and noise barrier proposals had to be submitted to EPD for
approval and issuance of the construction noise permit before the
commencement of the works. Furthermore, works inspections
would be conducted by the site engineers and the front-line staff and
orders to stop work would be made once the noise level exceeded the
limit. Thus Members did not have to worry about the noise nuisance
problem;
- at present, there was no regulation and policy under which
compensation could be claimed by shop operators affected by
government works. However, close communication would be
maintained with the relevant shop operators by the Department to
reduce the impact of the works to its minimum;
- as the whole project would last for four and half years, it thus had to
be carried out by phases to reduce impact on the residents.
Consultation on the works locations and time tables with the relevant
district councillors and stakeholders would be made by the
Department and the options would be revised before the
commencement of the works in response to their views. In addition,
the Department explained that the pipelines going to be replaced were
no-pressure sewers and the water flowing downward mode would be
applied in sewage treatment. The rear lane sewers were at upstream
locations (shallow locations) while the road sewers were at
downstream locations (deeper locations) in the whole sewerage
system;
- the Department noted the concern and views of Members on noise
nuisance produced by iron plates, road diversion in the Whampoa
District, community liaison, provision of the mobile numbers of the
project action officers and night works. Consideration on detailed
works design would be made on common understanding and
communication with local district councillors would be made again
later;
- works debris would not accumulate in the work sites for a long time
and would as far as possible be removed on the same day by dump
trucks and supervision would be carried out by site engineers. The
wheels of dump trucks would be washed before they left the site in
19
order not to pollute the nearby streets. The Department would pay
heed to the concerns of Members;
- as for the conduct of improvement works in the redevelopment areas,
the Department would consult the Urban Renewal Authority (URA)
on the works design;
- as for the impact on the metered parking spaces, the Department
would discuss the options submitted by the contractor with the
relevant district councillors; and
- the works liaison group would not function on a regular public
engagement platform basis and, if required, the Department would
inspect the sites and hold discussions with the relevant residents and
district councillors and he opined that such communication would be
more effective.
40. The Chairman concluded that he supported the improvement works in
principle. He hoped that community communication and distribution of information
would be improved by the relevant departments and suggested that sufficient
consultation and communication on detailed works design with the local district
councillors and stakeholders by way of group meetings be conducted.
Effective Use of the Smart Tender Scheme to Rehabilitate Private Buildings
(Paper No. 14/18)
41. Ir CHEUNG Yan-hong, MH introduction Paper No. 14/18. He hoped that
URA would attend all the meetings of private buildings held to discuss building
rehabilitation and introduce the “Smart Tender” Building Rehabilitation Facilitating
Services (Smart Tender Scheme) at the meetings to enhance owners’ understanding on
the scheme so that they could make a decision on whether to join the scheme.
42. Ir Dr CHENG Lee-ming stated that the Smart Tender Scheme could
effectively reduce bid rigging incidents and was greatly welcome by the residents.
However, different bid rigging ways were employed by the works contractors
including hindering owners to understand the services provided under the Smart
Tender Scheme. Thus, to achieve the best effect of the scheme, it was suggested that
the relevant departments should amend the law to require owners’ corporations to
invite URA staff to present the Smart Tender Scheme and then decide on whether to
join the scheme or not at the meetings for discussing rehabilitation works.
20
43. Mr SIU Leong-sing showed support for the Smart Tender Scheme but
opined that amendments to the law should hinge on whether the scheme would be
adopted on a continual basis.
44. Mr LAM Tak-shing stated that the number of residents in the District who
knew about the services under the Smart Tender Scheme was on the increase. He
also enquired about the number of buildings which had joined the Smart Tender
Scheme, the number of successful applications and the number of buildings which
had completed the tender procedure. In addition, he hoped that URA would
continue to improve the services under the Smart Tender Scheme and exempt its fees.
Furthermore, he hoped that URA would enhance publicity on the Smart Tender
Scheme for promote the understanding of the public on its services.
45. Mr Daniel LEE, Senior Manager / Building Rehabilitation of URA
thanked Members for affirming the services under the Smart Tender Scheme and
made a response to the questions by Members, the main point of which were as
follows:
- the suggestion for amending the law to require owners’
corporations to invite URA staff to introduce the Smart Tender
Scheme and decide to join the scheme or not at the meetings for
discussing rehabilitation works involved the Building Management
Ordinance (Cap 344) and this was outside the purview of URA. He
suggested Members to explore the matter with the relevant
government departments and the law enforcement agencies;
- as for the continuous implementation of the Smart Tender Scheme, no
time limit was set on it by URA for the time being. Also, the
Government was expected to launch the Operation Building Bright
2.0 and the Fire Safety Improvement Subsidy Scheme in mid-2018.
As the new schemes would operate for years, it was believed that the
services of the Smart Tender Scheme would not be terminated in the
near future;
- publicity on the Smart Tender Scheme was conducted through
different channels by URA including the use of exhibition vehicles,
letters to the district councils and visits to over 200 housing estates
and buildings and several talks on it were conducted too; and
21
- up to the end of February 2018, URA had received 400 Smart Tender
Scheme applications, five of which were calling for tender from
contractors through the e-tendering system and bid opening
procedures for three of them was completed. In addition, the Smart
Tender Scheme was supported by the industry and bidding by
contractors was active and some bid offers were within the estimation
by URA, which manifested that more options were provided to the
owners.
46. Ir CHEUNG Yan-hong, MH hoped that URA would reflect Members’
proposal for amending the law to require owners’ corporations to invite URA staff to
introduce the Smart Tender Scheme when discussing on building rehabilitation by the
owners’ corporations to the Civil Service Bureau (CSB). Also, he requested the
Assistant District Officer or the Senior Liaison Officer to convey Members’ views to
CSB.
47. Mr NG Po-keung stated the Smart Tender Scheme aimed at enhancing
transparency of tendering procedures and providing more options for owners but it
was very important that stricter penalty on bid rigging be imposed. He enquired if
URA would impose penalty on the works contractors taking part in the tender under
different company names and refer the cases to the law enforcement departments for
follow-up actions.
48. The Chairman believed that URA could not respond to the issues on law
enforcement and a record of the views would be made.
49. Mr Eric WONG, Senior Liaison Officer (Building Management) of the
Kowloon City District Office made a response, the main point of which were as
follows:
- consideration should be made on whether the current mechanism
could handle the relevant issues before proceeding to amend the law.
The Smart Tender Scheme drew favourable comments soon after its
implementation. It was believed that the owners’ corporation would
join the scheme without the need to amend the law after its credits
were recognised;
- individual owners who wanted to apply for the Smart Tender Scheme
could reflect their wish to the management committee. With no less
than 5% of the owners making such request, the chairman of the
22
management committee needed to convene a meeting of the owners’
corporation on the matters prescribed by the owners. He viewed that
the above mechanism could handle the matter;
- the Government played the role of a facilitator in building
management and would not have any direct involvement in the
decision of owners’ corporations in the choice of service providers.
Under the common law principle, it would not compel any
organisation to choose service providers or consider any service
providers because other organisations or markets could also provide
service similar to the Smart Tender Scheme. However, the
Government strongly encouraged the buildings to join the Smart
Tender Scheme to prevent bid rigging; and
- The District Office noted Members’ views and would file them.
50. The Chairman stated that Hong Kong’s law offices or solicitor firms could
also provide service similar to that of the Smart Tender Scheme.
51. Mr Jimmy LAM said that owners’ corporations had the final say on whether
to join the Smart Tender Scheme and the suggestions in the paper only aimed at
enhancing understanding of the service of the Smart Tender Scheme by owners’
corporations. He enquired about the reasons why buildings taking part in the
Operation Building Bright 2.0 and the Fire Safety Improvement Subsidy Scheme had
to join the Smart Tender Scheme at the same time. Also, he again requested the
service of the Smart Tender Scheme be extended to cover the inspections made after
the completion of building rehabilitation.
52. Ir Dr CHENG Lee-ming stated that as the District Office, URA and district
councillors were not invited to the meetings by some of the owners’ corporations and
the decision on arrangements on building rehabilitation and even the signing of
agreement with contractors were made by a small number of owners, which might
compel other owners to accept bid rigging leading and cause them losses. Thus the
paper did not ask for law amendments to force owners’ corporations to adopt the
Smart Tender Scheme but to mandate them to allow intervention by the Government
to protect the owners’ right to information. Also, he pointed out that the Mandatory
Building Inspection Scheme (MBIS) was a bad policy by the Government and thus
additional resources should be provided by the Government to improve the service of
the Smart Tender Scheme and to assist owners to prevent the incidence of bid rigging.
On the other hand, those who took part in bid rigging earlier went scot-free. Unless
23
heavier penalty was imposed on bid rigging, otherwise there would be bid rigging in
different forms in the future.
53. Ir CHEUNG Yan-hong, MH stated that the suggestions in the paper were
based on good will and good intention. As most of the owners of the old districts
were elders, they might lack full understanding of the policy of and measures taken
by the Government and assistance to the relevant owners by the Government to
prevent bid rigging was needed in order to turn MBIS into a good policy. In
addition, he opined that the Government should allocate resources to subsidise the
Smart Tender Scheme continuously to alleviate the problems faced by old buildings.
Also, the expenditures on the Smart Tender Scheme would certainly be far less than
the loss caused by bid rigging and so it was worth the Government’s allocation of
resources to it. On the other hand, he hoped that the District Office would not just
note Members’ views. The Committee should reflect the views to the relevant
government departments and law enforcement agencies.
54. Mr SIU Leong-sing hoped that URA and the District Office should further
enhance publicity on the Smart Tender Scheme as short-term measures for promoting
owners’ awareness on the service of the Smart Tender Scheme. In addition, as the
Treasury had large amount of surplus, it was hoped that the Government would
provide more subsidy to the Smart Tender Scheme so as to enhance its effectiveness.
55. The Chairman hoped that URA would pay heed to the coordination on the
project division approach by district against the Smart Tender Scheme adopted by
contractors and suggested that URA should consider resorting to mechanism to
disqualify contractors who just responded to tenders for rehabilitation projects in
some districts to avoid conspiracy by contractors to set bidding prices by district.
56. Mr Eric WONG of the Kowloon City District Office, in response, stated
that the District Office had taken note of Members’ views and would also reflect their
views to the Headquarters. The owners’ corporations would generally invite the
District Office to their building rehabilitation meetings and the District Office would
make use of those opportunities to encourage owners’ corporations to apply for the
Smart Tender Scheme. The District Office would also provide the contact details of
URA and when required, would ask URA to introduce the Smart Tender Scheme to
owners’ corporations directly. In addition, district-wide briefings on the Smart
Tender Scheme would be organised regularly by URA and he suggested that the next
Building Management Certificate Course and relevant seminars should include
introduction on the Smart Tender Scheme.
24
Appeal to Urban Renewal Authority to Immediately Resume the Old Buildings
around Sheung Heung Road, Wing Yiu Street and Hung Kwong Street by Taking
the Opportunity Created by the Construction of CKR
(Paper No. 15/18)
57. Mr LAI Kwong-wai introduced Paper No. 15/18.
58. Mr Roger KWAN stated that the Kowloon City District Urban Renewal
Forum (DURF) made proposals years ago to include the old buildings around Sheung
Heung Road, Wing Yiu Street and Hung Kwong Street into the urban renewal priority
project areas and the conditions of the buildings there met the requirements for
resumption by URA. Thus it was hoped that URA would consider resuming the old
buildings there as soon as possible.
59. The Chairman suggested URA to explain to Members its role and the
purpose of its establishment.
60. Ms YAN Sin-wah, Senior Manager, Community Development of URA
made a response, the main points of which were as follows:
- URA was not a developer and its main role was to undertake,
encourage, promote and facilitate urban renewal in Hong Kong to
cope with the problems of the ageing urban area and to improve the
living environment of the residents of the old districts. The two core
businesses of URA were redevelopment and rehabilitation as well as
heritage conservation and revitalisation for creating a sustainable and
quality living for the people of Hong Kong;
- as CKR was outside the ambit of URA, it was not in a position to
respond to the impact caused by its works on the structure of the
buildings in the surrounding areas; and
- URA understood the expectations of Members and residents on the
redevelopment of the buildings in the above area. Before the
commencement of any redevelopment project, different factors would
be taken into consideration by URA including the conditions of the
buildings, living environment, URA’s resources etc. and a pragmatic
approach to conduct urban renewal step by step would be taken.
However, under its secrecy obligation, URA could not disclose the
25
project information and redevelopment time table before the projects
were gazetted.
61. Mr Ronald YEUNG stated that the 13 streets of To Kwan Wan fully met
URA’s criteria for redevelopment and he hoped that active consideration of
redevelopment would be made.
62. Mr LAI Kwong-wai stated that he understood URA’s secrecy obligation
under which it was unable to provide the redevelopment time table of the above area.
In addition, he pointed out that in the Executive Summary of the Planning Study on
Urban Renewal Plan for Kowloon City (Renewal Plan) published by DURF in 2014,
it was mentioned that there was a mixture of old and new buildings in the above area
and some of them were in dilapidated conditions and long term disturbance was
caused to the residents by noise nuisance and exhaust problems of CKR. The
Renewal Plan was positioned to bring renewal to the sub-district riding on the
extension of the railway service. It would strive to solve the incompatible land use
problem and at the same time introduce diversified development leading to the
transformation of the sub-district into a multifunctional district centre. The residents
had strong expectations on the Renewal Plan but there were no further news up to the
present. In view of the commissioning of the To Kwa Wan Station of SCL in 2019
and the construction of CKR, it was hoped that URA would take the opportunity to
redevelop the old buildings in the above area as soon as possible.
63. Ms YAN Sin-wah of URA responded that reference had been made by URA
to the Renewal Plan published in 2014 when undertaking requisition and
redevelopment in the district. URA had started 14 projects in Kowloon City, six of
which were commenced in recent years, and it would continue with the work in the
future. However, because of its secrecy obligation, it was unable to provide the
information and time table of individual projects.
Strong Request to Oi Man Estate for Replacing the Rubbish Bins on Each Floor
or Increasing the Number of Bins
(Paper No. 16/18)
64. Mr CHO Wui-hung introduced the paper and in respect of the written reply
by HD that new rubbish bins of 660 and 240 litres would be purchased in due course,
he enquired about the time table the new rubbish bins would be provided for the
residents. He supplemented that there were more than 30 households on each floor
of Oi Man Estate and the small rubbish bins were not suitable for them but would
26
only lead to rodent infestation. Thus it was hoped that the Department would use
rubbish bins of medium and big sizes.
65. Mr Tony NG raised the following views/enquires in respect of the written
reply by HD: (i) he hoped that staff of HD would continue their inspection on each
floor to ensure cleanliness and to check whether the bins were damaged and repairs
and replacement should be made as soon as possible; (ii) notices should be posted
near the bins calling for the residents to place their rubbish properly into the rubbish
bins to maintain environmental hygiene; and (iii) whether points would be deducted
for cases of littering by the residents.
66. Ms Ada KONG, Housing Manager (Kowloon West and Sai Kung 1) of
HD made a response, the main points of which were as follows:
- every year the Department ordered about 60 rubbish bins of 660 litres
and 40 bins of 240 litres for Oi Man Estate to cater to the needs and
20 bins of 240 litres were delivered and the Oi Man Estate Office
would make arrangements for repairs or replacement depending on
the damage of the bins on each floor;
- the Department’s staff would conduct regular inspections on the
cleanliness of each floor and would make arrangements for repairs or
replacement depending on the damage of the bins, and when required,
the number of bins on each floor would be increased or decreased;
- posters and notices were put up at the trash room of each floor and the
lobby to call for the reduction of household waste by the residents and
proper disposal of their rubbish in response to the environmental
policy and call for hygiene improvement by the Government; and
- the Department would conduct inspections every month and points
would be deducted for cases of littering by the residents.
Strong Request to Housing Department for Facing the Problem of Wild Bird
Feeding in Housing Estates Squarely
(Paper No. 17/18)
67. Mr. CHO Wui-hung introduced the paper and stated that though no wild
bird feeding was spotted in the sitting-out areas next to Chung Man House and Chiu
Man House after complaints were made to HD, bread scraps and rice were still found
27
on the ground, showing that some people did feed wild birds there. It was hoped
that HD would strengthen inspection and enforcement actions and he suggested
deducting five points from households feeding birds or imposing on them a fine
$1,500.
68. The Chairman enquired whether HD had the right to impose fines on the
residents feeding the wild birds.
69. Mr Tong NG suggested HD should conduct covert surveillance on the time
wild birds were fed and said that he had provided information on wild bird feeding to
the Department and the relevant persons were caught red-handed. Also, he hoped
that the Department would provide information on whether there was incidence that
points were deducted from offenders and also provide a list of such offenders. He
also suggested that home visits be conducted by HD to call for the residents not to
feed wild birds.
70. Mr Terence SIU stated that there was illegal feeding of wild birds near his
district too. Though cleansing was enhanced by FEHD but no one was prosecuted
and the problem remained unresolved. He asked HD about the ways to disperse
wild birds.
71. Ms Ada KONG of HD made a response, the main points of which were as
follows:
- inspection on the public places in Oi Man Estate was enhanced and
several persons were found feeding wild birds there. The situation
had improved after they were advised not to do so and dispersed and
the incidence of wild-bird feeding had decreased recently. For the
time being, no one was caught feeding wild birds, the Department
thus did not have a list of the offenders and it called for Members and
residents to report the cases of wild-bird feeding to the Department
for investigation and follow-up actions. If required, reference to
social workers for follow-up actions would be made by the
Department;
- close attention was paid to the gathering of wild birds in Oi Man
Estate to prevent the estate from becoming a wild bird black spot.
However, it was found that there were no wild birds gathering on the
trees of Oi Man Estate. Thus inspection and cleanliness would be
28
strengthened on the rooftop of buildings to prevent gathering of wild
birds;
- publicity and education was enhanced by the Department to explain
to the residents the environmental pollution problem brought about by
feeding wild birds and to educate them not to do so;
- apart from deducting 5 points from the residents for feeding wild
birds and soiling the public places in the estate in accordance with the
demerit points system, summons would be served on the offenders
and a fine of $1,500 would be imposed; and
- Members might reflect the gathering of wild birds in other public
housing estates to the relevant public housing authorities while
problems outside the estate areas would be dealt with by FEHD. If
the exact locations where wild birds gathered were provided by Mr
Terence SIU, the Department would help referring the case to FEHD
for follow-up actions.
Strong Request to Oi Man Estate for Strengthening Anti-rodent Measures
(Paper No. 18/18)
72. Mr CHO Wui-hung introduced the paper and showed pictures of rodents
causing nuisance to residents at their homes. Though rodent guards were installed
on the lower floors of buildings, the result was not satisfactory. The mouse traps and
rodent sticky plates distributed by the Department were not sufficient to meet the
demand, resulting in rodents climbing onto the upper floor units. There were signs
that the rodent infestation problem was becoming serious and he requested HD to
assist the annoyed households to get rid of rodents and install rodent guards.
73. Mr Tony NG also showed a video on rodent infestation in Oi Man Estate
and pointed out that the District Officer, Kowloon City also realised the seriousness of
the rodent infestation problem during his inspection in the estate. He pointed out
that though rodent guards were installed and rodent sticky plates were distributed to
every building by HD, propagation of large number of rodents in the estate was
ignored and thus he hoped that there would be more effective rodent control measures
in place. In addition, he also hoped that the Department would set up a rodent
control team in the near future to take immediate rodent elimination actions once
complaints were received from residents.
29
74. Ir Dr CHENG Lee-ming stated that apart from Oi Man Estate, rodent
infestation in Ho Man Tin Hill had become serious recently and he suspected that the
rodents came from Oi Man Estate. Thus he hoped that HD would take the rodent
infestation problem in Oi Man Estate seriously and eliminate the problem to prevent
the nuisance spreading to other areas and lead to territory-wide hygiene problems.
75. Mr Admond YUE stated that there was serious rodent infestation problem in
the district and he was worried that there would be plague outbreak if no effective
rodent elimination measures were identified by HD. He suggested hiring pest
control experts or seeking assistance from FEHD. Also, he hoped that solutions to
solve the problem would be sought by HD, Link Asset Management Ltd (Link) and
FEHD.
76. Mr HE Huahan stated that the Department did not accord due importance to
the rodent infestation problem in Oi Man Estate. The estate should be kept clean
and sufficient mouse traps and rodent sticky plates should be provided to the residents.
Furthermore, he stated that after the installation of the rodent guards on all floors, the
rodent problem in Kai Ching Estate and Tak Long Estate had improved. Thus it was
suggested that the Department should consider applying the measures to Oi Man
Estate.
77. Mr LO Chiu-kit stated that there was serious rodent infestation in Hung
Hom Estate previously and improvements were seen after investigation and provision
of rodent control measures by FEHD. He thus praised the efforts made by FEHD
and hoped that HD would pay heed to the rodent infestation problem in old housing
estates and closely cooperate with FEHD to eliminate rodents. He enquired about
the methods taken by the relevant departments in eliminating rodent infestation in
buildings and opined that assistance to households in need of removing rodents in
their units should be provided by HD.
78. Ms Ada KONG of HD made a response, the main points of which were as
follows:
- on receipt of complaints on rodent nuisance, the Department had
immediately invited FEHD’s staff and experts of its pest control
section to inspect the estate and requested for the provision of pest
control advice. The Department had taken their advice and installed
more rodent guards in Oi Man Estate;
30
- active measures would be taken by the Department to handle the
cases reflected by individual households and those referred by
Members, including having active liaison with the relevant
households and providing rodent sticky plates;
- the Department would inspect individual units and offer advice and
mouse trap equipment according to individual household’s hygiene
needs and would also assist the annoyed households to clear away
sundry articles inside their units. Also, in accordance with the
demerit points system, households deliberately depositing sundry
articles would have their points deducted and once all the points were
deducted, the Department would serve a notice of evacuation on the
household terminating the tenancy agreement and recovering the unit;
- the Department had instructed the staff of the estate cleansing
contractor to wash the floors of the buildings and the public places
diligently;
- joint cleansing and publicity education was conducted by HD and
Link for a cleaner environment in the estate and more raticide was
placed in the vicinity of the estate. The number of dead rodents in
the estate would increase when the raticide began to take effect;
- rodent guards were placed at appropriate locations in the estate and
when required, the Department would pay visits to individual
households for the provision of rodent control advices to them; and
- Oi Man Estate Office would exchange information on rodent control
and elimination with the staff of Kai Ching Estate and Tak Long
Estate. As Oi Man Estate was an old housing estate with open
design, the actual locations for the installation of rodent guards, their
numbers and design might not be exactly the same as those of other
estates.
79. Mr CHO Wui-hung affirmed the efforts made by HD, FEHD and Link but
there were still no significant improvements in rodent control in Oi Man Estate. He
played a short video on the food establishments under Link showing that no adequate
hygiene measures were taken by some of them which became food sources for
rodents. Thus he requested for more cleansing joint actions. In addition, the
rodent control and elimination measures of the relevant department were not targeting
31
at the core problems such as rodents climbing onto the upper floors along the LP gas
pipes outside the buildings, veranda and windows. Effective measures preventing
rodents climbing into the buildings must be taken.
80. Mr Tony NG stated that there was room for improvement by HD in rodent
control and elimination. In view of the less effective rodent control and elimination
measures previously taken, study on new measures to be taken and reference to the
measures of other housing estates should be made so as to actively improve the
control on rodent infestation in Oi Man Estate. In addition, he stated that the estate
office must report cases in which residents were bitten by rodents to the senior staff of
HD.
81. Mr YIU Hon-sang, Community Relations Manager of Link Asset
Management Ltd. made a response, the main points of which were as follows:
- according to FEHD’s information, the territory-wide rodent
infestation rate for 2017 was 3.5%, that of Kowloon City was 2.3%
ranking 14 in the 18 districts;
- Link, in the capacity of the owner of a private company, took joint
actions against rodent infestation within its business areas together
with its clients. At present, Link employed two rodent elimination
consultants and the advice on rodent control and elimination were
provided regularly included the locations for depositing raticide. In
order to prevent rodent infestation, Link had changed the nullah
covers as advised by FEHD;
- on the education issue, Link would try all means to advise shop
operators to maintain environmental hygiene and issue notices on the
proper handling of food, refuse and food remnants to the market and
operators of cooked food stalls in accordance with FEHD’s advice.
Pamphlets on rodent infestation prevention by FEHD were also
distributed to shop operators;
- the rodent infestation problem could not be solved solely by the
owner’ efforts. The cooperation from the shop operators was also
required. As such, consideration was being made by Link to include
hygiene clauses into its tenancy agreements in the future but study on
this had to be carried out by the legal section; and
32
- Link had stepped up the work of cleaning markets, cooked food stalls
and food premises and large-scale cleaning operations were rolled out
together with HD with a view to effectively reducing rodent
harbourages. It was hoped that the joint efforts of various parties
and Members’ supervision could help mitigate rodent infestation in
the estate.
82. Ms YUNG Suk-ching, Chief Health Inspector 1 of FEHD, in reply, said
that the Department was paying close concern to rodent infestation control in Oi Man
Estate and regular inspections were carried out by its staff. Also, advices on rodent
infestation control in the estate were provided to the relevant persons-in-charge and
rodent infestation control was carried out in the public places in Oi Man Estate and its
nearby areas. On receipt of the paper, an inspection by the Department’s staff was
conducted in Oi Man Estate and its surrounding areas including those managed by
Link. Later, an inspection by pest control experts would again be conducted in Oi
Man Estate to follow up the implementation of the pest control measures suggested
earlier by the Department and provide further advices.
83. The Chairman then dealt with the motion stated in Paper No. 18/18 which
was: “Strong Request to HD, Link and Food and Environmental Hygiene Department
for Strengthening Anti-rodent and Rodent Elimination Measures and Facing the
Rodent Infestation Problem at Oi Man Estate Squarely”. The motion was proposed
by Mr CHO Wui-hung and seconded by Mr Tony Ng. The Chairman declared that
the motion was effective.
84. The Chairman asked whether there was any proposed amendment to the
motion by Members. Before the meeting, The Hon Starry Lee in her written notice
appointed Mr Roger KWAN to vote on her behalf. As there were no amendments to
the motion, the Chairman suggested voting on the motion by secret ballot by show of
hands and the result of the voting was as follows:
Support:14
Objection:0
Abstention:0
85. The Chairman declared that the motion was passed.
33
Date of Next Meeting
86. The Chairman announced that the meeting was adjourned at 6:17 p.m.
The date of the next meeting was 10 May 2018 and the deadline for the submission of
papers would be 24 April 2018.
The minutes of this meeting were confirmed on 10 May 2018.
Chairman
Secretary
Kowloon City District Council Secretariat
May 2018