Thaiflex Thailand Project
Radiator steel structure installation instructions manual
1. purpose:
We draft the work in structure to ensure the radiator of Thaiflex Thailand
project can be installed in site smoothly.
2. The basis:
Reference drawing no.: 40-0435-0000 Rev.1.
3. The scope of application:
It is applicable for installation on site for Thaiflex Thailand project.
4. Safety Precautions:
4.1 Installation, operation and maintenance should carry out by qualified
engineer, also has good understanding of all rules and conditions of this
instruction. Make sure that process will follow the instruction. DO NOT
take any operation under unprofessional people.
4.2 If any difference was discovered according to this instruction and
accessories kit instruction please notify supplier in writing (email or fax).
Inform our After-Sales Service department formally.
4.3 Any failure of follow instruction which caused by modification without
consulting KELVION in writing approve, KELVION will not be responsible
for such problem.
4.4 The cooling system is closed circulation, water (oil) should be clean and
free from foreign matters or else the pipelines may be blocked.
4.5 The cooling air must be clean and free from corrosive foreign matters
such as acid and alkali. Air inlet surface air distribution should evenly.
4.6 When radiator out of use in winter time MUST drain fluid out completely
or add some antifreeze (glycol) into system; long out of using for other
season MUST drain fluid completely.
Thaiflex Thailand Project
Radiator steel structure installation instructions manual
5. Installation:
5.1 Requirements:
5.1.1 Installation engineer should have appropriate professional
qualifications and experience.
5.1.2 Please follow principle below to select installation location for
radiator:
5.1.2.1 Must install radiator outdoors.
5.1.2.2 There should be no walls around radiator, which will
affect air ventilation and hot air exhaust. The additional
air resistance of environment to radiator is not
considered in fan design.
5.1.2.3 To choose installation location, please avoid smog
source and contamination to air-ventilation causes by
other equipment nearby radiator, also over heated air at
inlet. Besides, pay attention the impact of monsoon wind
blow-direction, which may blow contaminated or heated
air back to inlet that will result in hot air circulation or
passage contamination.
5.1.2.4 Any vertical obstacles (if there is any) must be away at
least 2m from radiator. The air inlet and air outlet should
have enough clear distance, and no obstacles with in
1.5m distance. The larger vent area, the larger
necessary clearance distance will request.
5.1.2.5 Extension devises (including legs and retaining plates)
must be installed at an integral plane of solid foundation.
The load design must base on total weight of radiator
Thaiflex Thailand Project
Radiator steel structure installation instructions manual
containing liquid and additional loads such as wind, snow
and earthquake. If foundation bolts (prepared by
customers) used for fixing, should also consider factors
above.
5.1.2.6 If several equipments installed at one place running at
same time, it is recommended to arrange them in parallel
way. In this circumstance, must to increase radiator
installation heights satisfy air in taken surface request.
Please contact GEA sales engineers for specific
requirements.
5.1.2.7 When a radiator is installed horizontally, it must be
convenient to exhaust the residual air in it completely.
5.2 Preparations:
Before installation, first remove fin protective-plate, and covering items
of air inlet & outlet side, water (oil) tube connecting flange. Wash off
preservers from sealing surfaces of air side and water (oil) side by using
proper detergent. Taking care painted surfaces during such process.
5.3 Lifting:
5.3.1 Select proper lifting equipment according to radiator weight.
5.3.2 Use crane lift radiator, following suspension angles must be
ensured:
� In the length direction: α≤90°
� In the width direction: β≤50°~70°
Use lifting beam when necessary. See Fig.
Thaiflex Thailand Project
Radiator steel structure installation instructions manual
Warning: forbid use forklift ascension radiator, it will damage the
radiator frame and aluminum fin.
5.3.3 It is not allowed that standing at radiator, carry or move it through
any fixed accessories (expansion tank, electrical junction box etc)
and coil as lifting point.
5.4 Assembly and connection:
5.4.1 First of all, ensure radiator installation level horizontally. If
necessary, some cushion blocks of different thicknesses may be
used to make the radiator level during installation.
Lifting lugs
Thaiflex Thailand Project
Radiator steel structure installation instructions manual
5.4.2 Must consider equipment load as a whole during civil and
foundation construction, such as volume of cooling liquid; weight
of steel structure, expansion tank (water or oil) etc. Please see
equipment general drawing and relevant literature for total loads
details.
5.4.3 Under normal circumstances, the core assembly of the radiator
has been assembled. However, for sake of safe transportation,
the supporting steel members and other parts might be
disassembled before transportation. In this case, the stability of
the equipment must be ensured when it is reassembled. Put the
equipment on the installation foundation, level up, straighten and
fix it, and finally connect the pipelines.
5.4.4 Steel structure installation:
First review steel structure drawings, Lifting and positioning
support column anchor position (below) :
Step 1
1
3
2
4
Thaiflex Thailand Project
Radiator steel structure installation instructions manual
Step 2 Step 3
Step 4 Step 5
Step 6 Step 7
1
2
1
4
2
3
3
4
4
2
5
6
4
6
Thaiflex Thailand Project
Radiator steel structure installation instructions manual
Step 8 Step 9
Step 10 Step 11
Step 12
If the radiator are more, according
to the above methods, and so on
3 5 5
6
7
8
9
7
8
9
9
8
7
Thaiflex Thailand Project
Radiator steel structure installation instructions manual
5.4.5 Radiator installation:
- According to the general arrangement drawing will be the first radiator
lifting and use bolts on the steel structure support, Check the verticality and
levelness of radiator.
- Lifting the second radiator and fixed on the steel structure support, check
the two radiators in and out of the distance between the flanges. The
dimensions must be the same with general arrangement drawing. If not, must
make the adjustment.
Thaiflex Thailand Project
Radiator steel structure installation instructions manual
- According to the above methods, install the third radiator.
5.4.6 All joint faces should parallel to each other and meet seal
requirement; no joint face should bear additional loads. Flexible
connection is recommended.
5.4.7 Wiring of motors: normally, connecting terminals and cable
sheaths are provided at external surface of radiator, wiring operation
can be done by users directly, but lead-in cable should be prepared by
users. Earth terminal is on the connecting ends. For specific operations,
please see relevant drawings.
5.5 Attention:
NEVER use adapter tube of radiator as negative grounding electrode!
During electric welding it may be perforated by electric sparks.
Manufacturer will not responsible for the consequences hereby caused.