Texas 05 2016

24
By Irwin Rapoport CEG CORRESPONDENT Crews from the Hensel Phelps Construction Co. are hard at work build- ing the $240 million expansion of the terminal at the Austin-Bergstrom International Airport (ABIA), a project that was designed by Gensler. The Austin airport has been the site of sever- al construction projects that were recently completed and more are being planned as passenger traffic increases. The expanded terminal will accom- modate approximately four million additional passengers per year for a total of 15 million annual passengers — an increase of 36 percent. “Austin airport passenger growth has spurred the expansion of the airport’s terminal and surrounding aircraft park- ing area,” said Jim Halbrook, ABIA’s spokesman. “The terminal concourse level has reached its service capacity of 11 million passengers annually. Currently, ABIA has 24 contact gates which have boarding bridges that serv- ice airplanes parked at each gate. The terminal concourse level consists of approximately 300,000 square feet. “In keeping with the recommenda- tions in both the 2003 and 2008 master plan and master plan phasing projects,” he added, “respectively, the new termi- nal space will be added to the eastern end of the existing terminal facility with completion anticipated in 2018. This ABI Undergoes $240M Expansion TEXAS STATE EDITION A Supplement to: Your Texas Connection • Dale Agnew, Carrollton, TX • 1-877-877-4997 “The Nation’s Best Read Construction Newspaper… Founded in 1957.” The expanded terminal will accommodate approximately four million additional passengers per year for a total of 15 million annual passangers — an increase of 36 percent. March 6 2016 Vol. I• No. 5 By Chuck Harvey CEG CORRESPONDENT Work began this January on a $6.5 million U.S. Army Corps of Engineers project to repair flood damage at Lewisville Lake Dam near Dallas. Rising water levels during last year’s floods caused a 161-ft. (49 m)-long embankment slide of the 6.2-mi. (10 km) lake. Repairs to the earthen-rolled dam had been sched- uled for right after Thanksgiving, but heavy rain in the area delayed the process. An earthen-rolled dam is a type of embankment dam made of compacted earth. Although the landslide was considered significant, Army Corps of Engineers and Dallas-area lawmak- ers in December ensured Dallas residents that flood waters would not flow from the dam into the city. Following the initial flooding, strong winds shred- ded the tarp covering the damage at Lewisville Lake Dam. Slide repair contractor Bristol General Contractors LLC, based in Anchorage with an office in Dallas, is on site and is constructing haul roads on government property next to the dam. Notice to proceed on the project was granted on Nov. 29 and repair work is scheduled for completion in late spring or early sum- mer. “Due to high lake levels, this may slip into sum- mer,” said Clayton Church, spokesman of the U.S. Army Corps of Engineers’ Fort Worth district office. “It will be evaluated as work progresses.” Mike Kingston of the U.S. Army Corps of Engineers is project manager. The project does not include subcontractors. Kingston reported that the reconstructed embank- ment will be protected by stone riprap on the upstream side and Bermuda grass sod on the down- stream side. The project also requires removal and replacement of a portion of the asphalt roadway and sub-grade layers along the embankment crest. Dam Repair on Lewisville Lake Well Under Way see DAM page 14 Hensel Phelps expects to remove 103,000 cu. yds. (78,749 cu m) of earth, and 56,000 sq. yds. (42,815 cu m) of existing apron paving. see AIRPORT page 18

description

Texas 05 2016

Transcript of Texas 05 2016

Page 1: Texas 05 2016

By Irwin RapoportCEG CORRESPONDENT

Crews from the Hensel PhelpsConstruction Co. are hard at work build-ing the $240 million expansion of theterminal at the Austin-Bergstrom

International Airport (ABIA), a projectthat was designed by Gensler. TheAustin airport has been the site of sever-al construction projects that wererecently completed and more are beingplanned as passenger traffic increases.The expanded terminal will accom-

modate approximately four millionadditional passengers per year for a totalof 15 million annual passengers — anincrease of 36 percent.“Austin airport passenger growth has

spurred the expansion of the airport’sterminal and surrounding aircraft park-ing area,” said Jim Halbrook, ABIA’sspokesman. “The terminal concourselevel has reached its service capacity of11 million passengers annually.Currently, ABIA has 24 contact gateswhich have boarding bridges that serv-ice airplanes parked at each gate. Theterminal concourse level consists ofapproximately 300,000 square feet.“In keeping with the recommenda-

tions in both the 2003 and 2008 masterplan and master plan phasing projects,”he added, “respectively, the new termi-nal space will be added to the easternend of the existing terminal facility withcompletion anticipated in 2018. This

ABI Undergoes $240M Expansion

TEXAS STATE EDITION A Supplement to:

Your Texas Connection • Dale Agnew, Carrollton, TX • 1-877-877-4997

“The Nation’s Best Read Construction Newspaper… Founded in 1957.”

The expanded terminal will accommodate approximately four million additional passengers per year for a totalof 15 million annual passangers — an increase of 36 percent.

March 62016

Vol. I• No. 5

By Chuck HarveyCEG CORRESPONDENT

Work began this January on a $6.5 million U.S.Army Corps of Engineers project to repair flooddamage at Lewisville Lake Dam near Dallas.Rising water levels during last year’s floods

caused a 161-ft. (49 m)-long embankment slide ofthe 6.2-mi. (10 km) lake.Repairs to the earthen-rolled dam had been sched-

uled for right after Thanksgiving, but heavy rain in thearea delayed the process. An earthen-rolled dam is atype of embankment dam made of compacted earth.Although the landslide was considered significant,

Army Corps of Engineers and Dallas-area lawmak-ers in December ensured Dallas residents that floodwaters would not flow from the dam into the city.Following the initial flooding, strong winds shred-

ded the tarp covering the damage at Lewisville LakeDam.Slide repair contractor Bristol General Contractors

LLC, based in Anchorage with an office in Dallas, ison site and is constructing haul roads on governmentproperty next to the dam. Notice to proceed on theproject was granted on Nov. 29 and repair work isscheduled for completion in late spring or early sum-mer.“Due to high lake levels, this may slip into sum-

mer,” said Clayton Church, spokesman of the U.S.Army Corps of Engineers’ Fort Worth district office.“It will be evaluated as work progresses.”Mike Kingston of the U.S. Army Corps of

Engineers is project manager. The project does notinclude subcontractors.Kingston reported that the reconstructed embank-

ment will be protected by stone riprap on theupstream side and Bermuda grass sod on the down-stream side. The project also requires removal andreplacement of a portion of the asphalt roadway andsub-grade layers along the embankment crest.

Dam Repair onLewisville LakeWell Under Way

see DAM page 14Hensel Phelps expects to remove 103,000 cu. yds. (78,749 cu m) of earth,and 56,000 sq. yds. (42,815 cu m) of existing apron paving. see AIRPORT page 18

Page 2: Texas 05 2016

www.romco.com

TEXAS

Austin512.388.2529

Buffalo903.322.5602

Carmine979.278.3570

Dallas214.819.4100

Ft. Worth817.626.2288

Houston713.937.3005

Longview903.758.5576

Rio Grande Valley956.565.0100

San Antonio210.648.4600

Three Rivers361.254.2317

When strength and versatility are key, look no further than your local Volvo dealer, ROMCO Equipment Co. Engineered for success, Volvo Construction Equipment provides exceptional productivity while maintaining a high standard of durability and performance.

Fuel efficiency provided.Power guaranteed.

smart works.

Sales - Rentals - Parts - Service

Providing Design, Installation and Service for your Crushing, Screening, Drilling and Washing Needs

MOBILE & STATIONARY EQUIPMENT

214-819-4101 / 800-227-6626www.romco.com

214-819-4100 / 800-227-6626www.romco.com

Sales - Rentals - Parts - Service

PAVING TEXAS Concrete & Asphalt Paving Equipment

GOMACO - VOLVO - LEEBOY - BLAW KNOX - BEARCAT

SOLID PERFORMANCESTARTS AT $99,500

LG938L: 2.5 yd 3 / 160 hp

$99,500*LG948L: 3.0 yd 3 / 173 hp

$118,500*LG958L: 4.0 yd 3 / 224 hp

$137,500*LG959: 4.0 yd 3 / 224 hp

$147,500*LG938L: 2.5 yd 3 / 160 hp3

$99,500* / 160 hp LG948L: 3.0 yd 3 / 173 hp

$118,500* / 173 hp LG958L:LG958L: 4.0 yd 3 / 224 hp

$137,500*$137,500*LG958L: / 224 hp LG959: 4.0 yd 3 / 224 hp3

$147,500*

When price and reliability are deciding factors, SDLG is youranswer. We offer four wheel loader models at industry-leadingprices — they’re simple to operate, easy to maintain and aperfect fi t for your day-to-day jobs.

Plus, our loaders are sold through an experienced, top-tier dealer network that's ready to support you any time you need them.Make the simple choice at sdlgna.com.

*Prices are subject to change without notice. Visit sdlgna.com for details.

Austin512.388.2529

Dallas/Ft. Worth817.626.2288

800.865.6998www.romco.com

San Antonio210.648.4600

Houston713.937.3005

Page 2 • March 6, 2016 • www.constructionequipmentguide.com • Texas State Supplement • Construction Equipment Guide

Page 3: Texas 05 2016

Construction Equipment Guide • Texas State Supplement • www.constructionequipmentguide.com • March 6, 2016 • Page 3

Houston TX 800-234-5007Dallas TX 866-270-1700Lake Charles LA 866-222-0053Williston ND 701-577-7014

Page 4: Texas 05 2016

Page 4 • March 6, 2016 • www.constructionequipmentguide.com • Texas State Supplement • Construction Equipment Guide

WPI Hosts Three-Day Event to Introduce iMC Equipment

Customers had the opportunityto see and operate Komatsu intelli-gent Machine Control (iMC) doz-ers and the PC210LCi-10 excava-tor — the world’s first iMC exca-vator — during a three-day eventat WPI’s Austin, Texas, branch.The dozer lineup included modelsranging in size from the 21,848-lb.(9,910 kg) D39PXi-23 to the90,610-lb. (41,100 kg) D155AXi-8.Komatsu iMC dozers feature

fully automatic blade control fromrough-cut to finish grade. As theytravel around a job site, the dozersmeasure actual elevations, whichprovide accurate surface data. Themachine-control system sensesexcess blade load during rough-cutand raises the blade to minimizetrack slip, as needed, to maintainmomentum. It also automaticallylowers the blade to push as much

material as possible until the gradeis reached, maximizing productionin all situations.“Komatsu’s intelligent Machine

Control technology can signifi-cantly increase production andefficiency, and at the same timedramatically reduce operatingcosts,” said Dan Galor, customersupport manager, who along withWPI’s technology solutionsexperts (TSE), was on hand to pro-vide information and answer ques-tions.“Once a model of a job site is

built, it can be uploaded into theiMC system and the grade controlcan be utilized from rough cut tothe finish pass. Conventional after-market systems are typicallyturned on when the operator getsclose to grade. The blade is con-trolled manually until approach-

Komatsu’s PC210LCi-10 was of particular interest to many who wanted to see the excavator’s exclu-sive control function, which goes beyond simple guidance to semi-automatically limit overexcava-tion and trace a target surface.

Customers had the opportunity to see and operate Komatsu intelligent Machine Control (iMC) doz-ers and the PC210LCi-10 excavator — the world’s first iMC excavator — during a three-day event atWPI’s Austin, Texas, branch.

WPI personnel presented information about the GPS technologyand proceeded to the rovers and base stations for a short com-munication and localization demonstration.

Andrew Lopez (top), Cory Webb (L) and Gabriel Saenz are WPI technical solution experts.

see WPI page 10

Page 5: Texas 05 2016

Construction Equipment Guide • Texas State Supplement • www.constructionequipmentguide.com • March 6, 2016 • Page 5

AlamoAmarilloCorpus ChristiCypress (Houston)

Denham SpringsIrving (Dallas/Fort Worth)KilgoreLubbock

Midland/OdessaRoss (Waco)Round Rock (Austin)Selma (San Antonio)

1-866-898-3763 | vermeertexas.com

EQUIPMENTTHAT STANDS UP.SERVICE THATSTANDS OUT.

Page 6: Texas 05 2016

Page 6 • March 6, 2016 • www.constructionequipmentguide.com • Texas State Supplement • Construction Equipment Guide

Experts Look at Buildings, Codes After Texas Tornadoes By Steve ThompsonTHE DALLAS MORNING NEWS

ROWLETT, Texas (AP) Before the wallsshook, before the two-by-fours twisted andthe roof began tearing off, Amanda Bosesaw news about the tornado on television.

“Everybody in the bathroom — rightnow!’’ the woman told her 5-year-old and15-year-old. There was almost no time towonder, she said, whether the home wouldprotect them — or collapse around them.

The Dallas Morning News reported simi-lar scenes played out in homes across NorthTexas during the Dec. 26 storm, whichdestroyed 159 houses and did major damageto 311 in Rowlett alone. Damage from thestorm will reach $1.2 billion, the InsuranceCouncil of Texas estimates.

As populations grow denser throughoutthe “tornado alley’’ that stretches from NorthTexas through South Dakota, many expertssay communities should consider designingbuildings to withstand twisters just as coastalcommunities build to survive hurricanes.

“Tornado-resilient designs of houses, orof any structure, is a thing within our grasp,’’said University of Florida engineering pro-fessor David Prevatt, who surveyed thedamage in North Texas. “It’s something wecan do, and we ought to do it.’’

The tornado that hit Rowlett was rated anEF3 as it moved over Bose’s neighborhood.That means the National Weather Serviceestimated its peak winds there could havebeen as high as 165 mph, a speed at whicheven well-built homes are in trouble.

But most homes in a tornado’s path don’texperience its top winds, Prevatt and otherexperts say. So while improving buildingstandards might not save every home in astorm, it could save many.

Two weeks after the storm, Prevattwalked Bose’s street with a team of his stu-dents. They were joined by employees of

Simpson Strong-Tie, a California-basedcompany that makes products for wind-resistant building. He pointed to Bose’shome as one of many vulnerable to damagebecause of weak construction.

Building codes have improved sinceBose’s home was built in 1984, as engineersand researchers analyze what worked andwhat didn’t after disasters.

In the 1980s, codes in North Texas and inmost places required design against only 70mph winds. That threshold rose to 90 mphabout 15 years ago, in accordance with stan-dards set by the International Code Council.

Cities typically adopt the ICC’s codes,sometimes adding their own small amend-ments. But adopting changes that substan-tially increase costs can threaten a city’scompetitiveness in the real estate market ifsurrounding cities don’t do likewise, somelocal officials say.

Still, Rowlett’s mayor, Todd Gottel, saidthe city should consider adopting a more tor-nado-resilient building code. Costlyupgrades shouldn’t be imposed on thosehomeowners trying to rebuild, he said. Butfor new construction afterward, he contin-ued, “We should look at alternative buildingstandards or codes, to see if it makes sense.’’

In the meantime, the code is only a mini-mum, said Selso Mata, president of theBuilding Officials Association of Texas anddirector of building inspections in Plano.

“It is not the maximum standard,’’ Matasaid. “A lot of people build better than that.’’

Builders tend to spend money on thingsthat buyers can see. Bricks and stone makenice-looking façades, but add little strength.The two-by-four studs behind the bricks arewhat make a structure sturdy.

Homebuyers should consider asking for— and be prepared to pay more for — struc-tural features that exceed the code, Mata said.

Small improvements can dramaticallyincrease a home’s defenses, experts say. Like

using metal straps, rather than only nails, tosecure walls to roof rafters. And using bolts,rather than nails, to anchor walls to a foun-dation. Neither is required in North Texas bythe building code.

Adding a skin of plywood or wood parti-cle board to the studs of a wall structurestrengthens it a lot, experts say. The walls inBose’s neighborhood are sheathed insteadwith a material called Thermo-Ply, whichcritics compare to cardboard. The companythat makes it defends the product and notesthat it is widely used in Texas.

Tornadoes don’t destroy homes instantly.Instead, they find weak points and progres-sively tear homes apart from there, saidChris Ramseyer, an engineering professor atthe University of Oklahoma who specializesin structural design.

“It finds the corner that’s weak, pulls itapart, and then it works on what’s left,’’ hesaid. Reinforcing that one weak corner, oftenthe home’s garage, can save the entire struc-ture.

“The costs that you’re looking at are gen-erally less than the cost of the granite coun-tertop that the homeowner wants in thekitchen,’’ Ramseyer said.

Moore, Okla., was the first city in thenation to adopt a building code to fend offtornado damage, requiring designs to with-stand 135 mph winds. The city adopted theenhanced code after a 2013 tornado killed 24and caused $2 billion in damage.

When the changes were proposed, Moorecity officials braced for a political fight frombuilders.

“Their automatic first response is, ‘Wedon’t want to do that; we’ll price ourselvesout of business,’’’ said Moore’s assistant citymanager, Stan Drake.

But builders ended up endorsing thechanges in Moore, and Drake said he does-n’t think the added costs have made thecity’s housing market less attractive to buy-

ers. Officials in Moore predicted the new rules

would cost an extra dollar per square foot. Inreality, those costs have been higher, accord-ing to builders, who estimate the increases at$1.50 to $2.50 for every square foot underthe roof, plus about $400 to beef up eachgarage door.

Still, builders like the changes, said TomPollard, last year’s president of the MooreHome Builders Association.

“I don’t know if the people are even real-izing it’s costing that much,’’ he said.“They’re concerned obviously about theirhouse staying together.’’

Adopting the same code throughoutOklahoma would pay off in the long term bymitigating disaster costs, according to a cost-benefit analysis by a team led by KevinSimmons, a professor of economics atAustin College in Sherman.

“We could tell the builders to build a fort,but then no one could’’ afford it, Simmonssaid. “So where is the sweet spot? I thinkwhat Moore did came pretty close.’’

The tornado in Rowlett tore past Bose’sneighborhood and out over Lake RayHubbard. Her bathroom, battered and roof-less and flooded, still mostly stood. But thefamily had to crawl out through the rest ofthe house, where it looked as if a bomb hadexploded.

Not far from the bathroom, exterior wallshad been wrenched loose from the rooflineand the concrete slab foundation. Bricks hadtumbled onto the lawn.

Bose’s father, a carpenter, came to helpthe family salvage what they could from thehouse they rented.

“He just thought it was poorly put togeth-er,’’ Bose said. “It could have killed some-body, the way it just fell apart.’’

(This story also can be found on

Construction Equipment Guide’s Web site at

www.constructionequipmentguide.com.)

ROMCO Opens New Division: ROMCO Power SystemsROMCO Equipment Co. announced the opening of a new

division called ROMCO Power Systems. ROMCO PowerSystems provides sales and service of new/rebuilt engines,generators and industrial pumps.

In addition to selling, servicing and rebuilding thenew/rebuilt engines, generators and industrial pumps,ROMCO Power Systems provides rental options for cus-tomers.

“Our goal is to establish ROMCO Power Systems as thepremier generator and power source solutions dealer withinthe Texas market.” said Gable Sprague, product supportsales manager.

ROMCO Power Systems has the ability to provide powergeneration and industrial pump solutions from the following

engine manufacturers: Volvo Penta, John Deere, Kohler andKubota. The alternator portion of our generators is manufac-tured by Marathon and the pump ends by Cornell. From anengine rebuild aspect, RPS will refurbish any make/model ofthe diesel engine. When approaching general service workand preventative maintenance, ROMCO Power Systems isopen to any opportunity that relates to our business.

ROMCO Equipment Co. is a heavy equipment distributorin the state of Texas. ROMCO carries the full line of VolvoConstruction Equipment, Hitachi Construction & MiningEquipment and the SDLG line of wheel loaders. ROMCO’spaving division represents the full line of GOMACO con-crete paving equipment, Volvo, BearCat, Blaw-Knox and

LeeBoy asphalt paving products and the FINN line ofHydroseeders, Bark and Straw Blowers. ROMCO’s MPSdivision (Material Processing Systems) specializes in theaggregate and material processing industries including newplant sales, design, fabrication, project management, mainte-nance and maintenance supervision. ROMCO has tenbranches: Dallas, Ft Worth, Longview, Buffalo, Houston,Mercedes, Austin, San Antonio and Carmine. There also isan additional ROL remote oilfield location in Three Rivers,Texas.

For more information, visit http://www.romco.com/.(This story also can be found on Construction

Equipment Guide’s Web site at www.constructionequip-mentguide.com.)

Page 7: Texas 05 2016

Construction Equipment Guide • Texas State Supplement • www.constructionequipmentguide.com • March 6, 2016 • Page 7

We offer a cost-effective alternative to the purchase of new equipment. Our high quality used equipment has been inspected,repaired if needed and brought back to new equipment

specifications by our factory trained technicians. We specialize in the Rental and Sale of loaders, dozers, excavators,graders, haul trucks with a special emphasis on water equipment.

RENTALS SALES

Page 8: Texas 05 2016

www.wpi.com

Houston 713-551-0506 Tomball 281-351-9016Beaumont 409-721-5305 Buffalo 903-322-7150Kilgore 903-984-2011 Austin 512-251-0013San Antonio 210-648-4444 Corpus Christi 361-884-8275Edinburg 956-386-0107

Trusted Brands at an Affordable Price

Rentals / Rental with Purchase Options / Lease / Low Interest Financing / New or Used

9 Full Service Centers Across Texas

Fu 9

Houston

ull Servic

713-551-0506 ouston

Full Service Centers Across Texas

713-551-0506

Full Service Centers Across Texas

281-351-9016omball T Tomball

s Texas

281-351-9016

entals / Rental with Purchase Options / Lease / Low Interest Financing / New or UsedR

entals / Rental with Purchase Options / Lease / Low Interest Financing / New or Used

HBeaumont

ouston

Kilgore Antonio San

Edinburg

entals / Rental with Purchase Options / Lease / Low Interest Financing / New or Used

409-721-5305 Beaumont 713-551-0506 ouston

903-984-201Kilgore 210-648-4444 Antonio 956-386-0107 Edinburg

entals / Rental with Purchase Options / Lease / Low Interest Financing / New or Used

409-721-5305 713-551-0506

1 903-984-201210-648-4444 956-386-0107

ffalo

entals / Rental with Purchase Options / Lease / Low Interest Financing / New or Used

www.wpi.com

903-322-7150falo Buf 281-351-9016omball T Tomball

512-251-0013Austin 361-884-8275Christi Corpus

entals / Rental with Purchase Options / Lease / Low Interest Financing / New or Used

www.wpi.com

903-322-7150 281-351-9016

512-251-0013361-884-8275

Page 8 • March 6, 2016 • www.constructionequipmentguide.com • Texas State Supplement • Construction Equipment Guide

Page 9: Texas 05 2016

Construction Equipment Guide • Texas State Supplement • www.constructionequipmentguide.com • March 6, 2016 • Page 9

SALES • RENTALS • PARTS • SERVICE

Finance & Lease RatesStarting as Low as 0% APR!

North Texas / North Louisiana3401 E. Park Row Dr.Arlington, TX 76010

817-522-0729

South Texas / South Louisiana2210 McAllister Rd.Houston, TX 77093

713-681-9221

Massachusetts / New England States115 Wood Rd.

Braintree, MA 02184781-884-0284

Page 10: Texas 05 2016

Page 10 • March 6, 2016 • www.constructionequipmentguide.com • Texas State Supplement • Construction Equipment Guide

Komatsu iMC Excavators, Dozers on Display at WPI Eventing the target grade.WPI personnel presented information

about the GPS technology, and proceeded tothe rovers and base stations for a short com-munication and localization demonstration.Attendees could then “test drive” equipment,using a model built by WPI that simulatedgrade control in actual working conditions.A complex roadway, a pond, blue top padsites and a trench for utilities were designedto show the machine’s speed and accuracy.“We wanted customers to experience the

full capabilities of the machines so theycould see the benefits to their business, aswell as address any questions or concernsthey had,” said TSE Andrew Lopez. “Thesystem is highly accurate and eliminates theneed for grade staking thus reducing survey-

ing costs. Because the technology is facto-ry-integrated, there are no cables or mastslike those required with the after-marketGPS grading systems. By having the systemintegrated, there is no need to climb on themachine to mount/remove sensors andwires. This increases jobsite production andsafety.”

PC210LCi-10 LimitsOverexcavation

Komatsu’s PC210LCi-10 was of particu-lar interest to many who wanted to see theexcavator’s exclusive control function,which goes beyond simple guidance tosemi-automatically limit overexcavation andtrace a target surface.As with the dozers, the PC210LCi-10’s

iMC system improves efficiency and accu-racy. When target grade is achieved themachine control will not allow excavationbeyond the designed surface. Minimizingoverexcavation reduces wasted time andcosts associated with removing and replac-ing material.

“Users will be able to dig a trench to theexact depth, precisely build a pond with allthe contours and slopes, or any other aspectof a project faster and without the worry ofremoving too much material,” said Galor.“A large monitor shows the operator real-time and as-built status. They can set audioguidance alerts with different tones that indi-cate how close they are to the final grade”Advanced functions contribute to the

excavator’s ability to effectively reach targetelevation without overexcavating, includingauto grade assist. As the operator moves thearm, the boom adjusts the bucket heightautomatically, tracing the target surface andminimizing digging too deep. This allowsthe operator to rough-dig without worryingabout exceeding the design elevation, aswell as fine-dig by operating the arm leveronly.Another new function is auto stop control.

During operation, the work equipment stopsautomatically when the bucket edge reachesthe design surface.The PC210 also has minimum distance

control, which automatically selects thepoint on the bucket closest to the target sur-face. If the machine is not facing a slopedsurface at a right angle, it will still follow thetarget surface and minimize digging below it“The feedback we received from this

event, as well as from customers who own orhave demonstrated an intelligent MachineControl dozer or excavator, has all been verypositive,” said Bruce Truesdale, vice presi-dent of operations. “Once they see how typ-ical project times can be cut by days, weeks,even months, they clearly understand thebenefits and return on investment that iMCmachines provide.”

(This story also can be found onConstruction Equipment Guide’s Web siteat www.constructionequipmentguide.com.)Komatsu iMC dozers feature fully automatic blade control from rough-cut to finish grade.

The PC210 also has minimum distance control, which automatically selects thepoint on the bucket closest to the target surface.

Attendees could then “test drive” equipment, using a model built by WPI that simu-lated grade control in actual working conditions.

WPI from page 4

Page 11: Texas 05 2016

Construction Equipment Guide • Texas State Supplement • www.constructionequipmentguide.com • March 6, 2016 • Page 11

Page 12: Texas 05 2016

Page 12 • March 6, 2016 • www.constructionequipmentguide.com • Texas State Supplement • Construction Equipment Guide

Page 13: Texas 05 2016

Construction Equipment Guide • Texas State Supplement • www.constructionequipmentguide.com • March 6, 2016 • Page 13

©2016 The Charles Machine Works, Inc.

ditchwitchtexas.com

CONTACT YOUR LOCAL DEALER

WHEREVER YOU NEED IT.

WE’RE IN THIS TOGETHER.

ACT YCONT

AL DEALEROUR LOCACT Y

AL DEALER

Ditch Witch of Houston // Ditch Witch South Texas // Witch Equipment Co.

Ditch Witch East Texas // Ditch Witch of Central Texas // Ditch Witch Southwest

Ditch Witch UnderCon // Ditch Witch Sales & Service El Paso

Page 14: Texas 05 2016

Page 14 • March 6, 2016 • www.constructionequipmentguide.com • Texas State Supplement • Construction Equipment Guide

Army Corps of Engineers Repairs Lewisville Lake DamStatus of Project

As of early February, workerswere building a pad for an excava-tor and constructing roads for haultrucks on the embankment. “They will shortly begin remov-

ing embankment debris, crest roadmaterial and embankment materialto elevation of 550 [feet],” Churchsaid. “Top of the dam is 560.”Workers will bring in 20,000 cu.

yds. (15,291 cu m) of dirt to repairthe embankment slide. Riprap willbe used to protect the embank-ment.Other materials being used for

the project include bedding,geomembrane, filter fabric, turfand road construction material forthe crest road. Geomembranes arerelatively thin sheets of flexiblepolymeric materials that are bynature impermeable, thus provid-ing a barrier to movement of waterand fluids.Filter fabric is a tough fabric that

screens out soil while allowing thepassage of water.

Currently, about 13 workers areat the job site each day, Churchsaid. They are using a small exca-vator, a roller-compactor, haultrucks and an articulated dumptruck, also referred to as a dumphauler.

Challenges of Repairingthe Dam

The undersized bridge that pro-vides access to the site for heavyequipment will need to be rein-forced, Church said. Also highwater levels and rain delayed startof the project by several months.

No Impact onSurrounding Area

Church reported that the projectis not affecting any camping or res-idents in the surround area. “Only roads inaccessible to the

public have been impacted,” hesaid.

Damage Quickly NoticedThe slide was quickly discov-

ered by Lewisville Lake personnelduring flooding that occurred in

late June. The personnel weremonitoring the dam around theclock because of high water levels.Officials described the type of

slide that occurred as typical onearthen-rolled dams. But the dam-age requires action to ensure con-tinued integrity of the dam struc-ture.The Army Corps of Engineers

reported that despite the damage,the dam is not currently at risk offailure. Flood water from heavyrains in December is currentlybeing released through the dam’soutlets.“Life safety is our main priority

within the Army Corps ofEngineers,” said Col. CalvinHudson II, commander, ForthWorth District, in a release.He added that dams are

designed and built to reduce floodrisk, but they cannot eliminate allrisk.

(This story also can be foundon Construction EquipmentGuide’s Web site at www.con-structionequipmentguide.com.)CEG

Workers will bring in 20,000 cu. yds. (15,291 cu m) ofdirt to repair the embankment slide.

DAM from page 1

Ridge Development, the industrial development arm ofTranswestern Development Co., announced it has beenselected as the master developer for 55.89 acres of Port ofHouston Authority land near the Bayport ContainerTerminal, located at 12619 Port Road in Pasadena, Texas.As part of the development arrangement, Ridge plans to

construct a large, build-to-suit facility on 38.38 acres it con-trols via a ground lease with the Port of Houston Authority.Ridge has proposed two building options: a 449,280-sq.-ft.(41,739 sq m), cross-dock building or a 450,684-sq.-ft.(41,870 sq m), rail-served facility. Both scenarios include199 trailer storage spaces, making it one of the most func-tional distribution centers in the southeast Houston submar-ket. In the current design, the rail-served alternative includesthe ability to store 280 railcars on-site. “This project will meet the critical demand in the port area

for rail-served industrial buildings,” said Kent Newsom,executive vice president of Ridge. “We are in talks with sev-eral potential tenants that have shown significant interest inthe flexibility and capacity that this site holds.”Ridge also will oversee development of a 300,000-sq.-ft.

(27,871 sq m) cold storage facility for AGRO MerchantsGroup on 17.51 acres. AGRO, which specializes in third-party cold storage, warehousing and value-added services,has retained Ridge to oversee site due diligence and providedevelopment consulting services for its new facility. The development site is located less than 1 mi. (1.6 km)

from the Bayport Container Terminal. The Port of Houstonhas plans to construct a new heavy haul road, called FreightStation Road, to provide access from the northeast corner of

the site from Port Drive, which is a unique benefit for heavyport users.“The site represents a rare opportunity to develop a much-

needed industrial project within a mile of a world-class con-tainer terminal,” said Ben Newell, senior vice president atRidge. “The location’s logistical advantage provides futuretenants considerable benefits in terms of drayage costs andsupply chain velocity.”According to the Greater Houston Partnership, the Port of

Houston ranks as the largest port in the United States by for-eign tonnage for the 19th consecutive year. In terms of con-tainer traffic, the Port of Houston is the nation’s sixth-busiest,handling 67 percent of the container traffic along the Gulf ofMexico. Houston’s industrial market has remained resilientdespite a drop in crude prices. At 476 million sq. ft.

(44,221,847 sq m), Houston’s industrial market is quicklygaining ground on Detroit, the fifth-largest industrial marketin the country. During second-quarter 2015, with 2.8 millionsq. ft. (260,128.5 sq m) in deliveries, Houston’s overallvacancy rate only increased 10 basis points to 4.4 percent. The Port’s Real Estate Department, under the direction of

Ricky W. Kunz, chief commercial officer, handled the leasenegotiations on behalf of the Port of Houston. RD Tanner,senior real estate director, was the lead negotiating executivefor the Port. KKNJ Properties LLC, owned by CurtisSpencer, will handle the leasing of the site for RidgeDevelopment.

About Ridge DevelopmentRidge Development is the industrial development arm of

Transwestern Development Co., a diversified real estatedeveloper with expertise in all commercial property types.Ridge is managed by the former principals of Ridge PropertyTrust. Ridge Development specializes in industrial develop-ment and investment in modern warehouse, distribution andmanufacturing facilities throughout the United States andMexico. Ridge serves North American clients from five U.S.offices and one office in Monterrey, Mexico. TheTranswestern Development and Ridge Development teamshave developed, constructed and managed more than 138million sq. ft. (12,820,620 sq m) of industrial and distributionspace.

(This story also can be found on ConstructionEquipment Guide’s Web site at www.constructionequip-mentguide.com.)

“The site represents a rare opportunityto develop a much-needed

industrial project within a mile of a world-class container terminal.”

Ben NewellRidge Development

Ridge to Develop Parcel Near Bayport Container Terminal

Page 15: Texas 05 2016

Construction Equipment Guide • Texas State Supplement • www.constructionequipmentguide.com • March 6, 2016 • Page 15

>> EagerBeaverTrailers.comFor a quote on any model, please call 800-257-8163

50 GSL/PT

50 GSL/BR

55 GSL

50 GSL

LOA D E RLOA D E R

707070th

ANNIVERSARY

1946-2016

Other Standard Features of this series:Only “Name Brand Tires”, currently Sumitomo

EagerBeaverTrailers.com

Page 16: Texas 05 2016

Page 16 • March 6, 2016 • www.constructionequipmentguide.com • Texas State Supplement • Construction Equipment Guide

Page 17: Texas 05 2016

Construction Equipment Guide • Texas State Supplement • www.constructionequipmentguide.com • March 6, 2016 • Page 17

Page 18: Texas 05 2016

Page 18 • March 6, 2016 • www.constructionequipmentguide.com • Texas State Supplement • Construction Equipment Guide

Austin-Bergstrom International Airport Expands Terminal$240 million expansion will ‘bal-ance’ the terminal and providemuch needed space for the expand-ing passenger and aircraft opera-tional numbers.”When completed, the east termi-

nal gate expansion will add 70,000sq. ft. (6,502 sq m) — a 23 percentincrease — of new hold roomspace, concessions, restroom facil-ities, and concourse circulationspace. This expansion should servethe terminal through the year 2025.“It also provides the added con-

course footprint that will accom-modate seven to eight additionalaircraft parking spaces on theapron for both domestic and inter-national airline operations,” saidHalbrook. “This near-term expan-sion will provide an approximate30 percent increase in aircraft oper-ational capacity.”On the apron level, the expan-

sion includes baggage conveyors,inbound baggage systems, officespace, signage, airport supportspace, security systems, restroomsand storage. A key issue for the ABIA is

maintaining existing operationswhile the construction proceeds.There will be a lot of night work tofast-track the construction.“Multiple weekly meetings are

held for design and construction,”Holbrook said. “By regular, fre-quent meetings we can formulateplans to address issues that mayarise. Representatives from airfieldto terminal, construction anddesign attend these meetings.Current passenger trends suggestthat we will have 15 million pas-sengers annually in 2025. Theexpansion takes our capacity from11 million to 15 million passengersannually.”“During the preliminary design

phase of the project,” said BartonDrake, Gensler senior project man-ager, “members of the design teamand aviation/city staff visited SanJose International Airport, as wellas San Francisco InternationalAirport. “These facilities, especially

boarding area E, were the basis ofthe design of the terminal expan-sion at ABIA,” he said. Hensel Phelps crews arrived on

site on Nov. 16, immediately set-ting up a silt fence to provide swiftand storm water pollution protec-

tion. On Nov. 30, LindamoodDemolition, was brought to startwork on the demolition of a hang-er on the old U.S. Air Force base.The hanger will be replaced with astorm water/de-icing collectionfacility.Joe Sanders, LEED AP, Hensel

Phelps project manager, is ready todeal with the multi-year, multi-phase project.“We started with the work at

area A — the de-icing facility —and then we’ll move into the mul-tiple phases for the apron paving,”he said. “Next fall we’ll start on theactual terminal expansion itselfand the renovations of the existingterminal.”The biggest challenge for

Sanders will be to minimize theimpact on day-to-day operations.“Making sure that at all times

that they are minimally interruptedbecause the loss of a gate or delay-ing of a plane has a financialimpact on them,” said Sanders, “sowe meet on a weekly basis everyTuesday — design in the morningand construction in the afternoon.We go through planning, witheveryone looking six, nine and 12months ahead on the plans andhow can mitigate any impact onthe airport.”This planning is essential, par-

ticularly for the delivery of con-struction materials. For the termi-nal renovations, it will be more ofan on-time delivery and for theexpansion and apron work,Sanders has plenty of room to storematerials and prepare areas closeto the work site.Hensel Phelps expects to

remove 103,000 cu. yds. (78,749cu m) of earth, and 56,000 sq.yds.(42,815 cu m) of existing apronpaving. Materials that will bebrought in should include 57,000cu. yds. (43,579 cu m) of concreteand 171,000 cu. yds. (130,738 cum) of imported soil.The plan is to recycle as much of

the material as possible on site,with the remainder going to recy-cling centers for processing.“Recycling and creating a sus-

tainable structure is extremelyimportant,” said Sanders. “Wework with our subcontractors toensure that material can be divert-ed from landfills and taken to recy-cling centers.When the work fully develops,

there will be between 400 and 500construction workers on site. Themajor subcontractors include:Champion Site Prep for earthwork;WPM Construction Services forSite Utilities; Hayward Baker –Olden for shoring; DynamicSystems Inc. formechanical/plumbing; Berg elec-tric for electrical; and ChascoConstructors for paving. “We will be coordinating the

expansion,” said Sanders. “Wehave a plan to segregate the expan-sion area. We’ll fence it off andmake sure we have our own area towork in where we can work with-out any impediments. The renova-tion area will require a lot of coor-dination as there will be a lot ofwork associated with it. The apronpaving/concrete work is out on thetaxi lane and there will be a lot ofnight placement and pullbackoperations there.“Night work in the existing air-

port is almost always preferred,”he added. “We’ll really get startedafter the last flight and we’ll becleaned up and out of the way bythe time the passengers arrivearound 4 or 5 a.m. the next day.”Sanders is looking at completing

the terminal work in the fall of2018. The de-icing facility shouldbe operational in December2016/January 2017. “ABIA has been very good to

work with,” he said. “They arevery helpful and open to differentideas and plans and we’ve beenable to make adjustments as we goalong, be it through design or earlybuyouts and phasing. We’ll be ableto tackle any issues as they arise.”Hensel Phelps will rent the

equipment for this project. Theplan is to have two tower cranesand a mobile crane at the terminalsite, two 90-ton (81.64 t) cranes atthe de-icing facility, along withbulldozers, excavators, backhoes,dump trucks, rollers, pavers, andboom lifts.The equipment will be rented

from dealers such as Sunbelt,United Rentals and Ahern.Although the equipment is

being rented, operators will be per-forming daily visuals and fluidchecks — everything that isrequired from the manufacturersand the dealerships, with the infor-mation passed on to the foremenand superintendents. Good communications is the

key to managing a work force ofclose to 500 people. Sanders andhis team hold weekly meetingswith subcontractors and superin-tendents speak with the subcon-tractors daily. “It’s communications from all

levels,” he said. “The work will bedone over a large area within theexisting terminal. We communi-

cate through cell phones andradios, but a lot of it is face-to-face.In addition to our project superin-tendent, we’ll have area specificsuperintendents and engineers. It’sall about getting the informationfrom the field back to us and theweekly meetings is an importantaspect in the flow of information.”Monthly safety meetings are

held, which bring together allHensel Phelps and subcontractoremployees. This bolsters the week-ly safety meetings at specific sites.“We’re pretty early along here,”

he said, “but on all projects, if youdon’t have a good team attitude,then you’re destined for failure.Morale is a big thing and if youhave low morale on a job, it affectsit from the top down, so building ateam effort is crucial. Making sureeveryone understands that what webuild today is going to be in placefor the next 50 years.“If the employees have pride in

their work,” he added, “you’regoing to have a good quality joband that’s what we try to instill ineverybody.”Isaac Johnson, project superin-

tendent, will play “a critical role,”says Sanders. Johnson, who hasbeen with Hensel Phelps for 16years, is keen to take on the chal-lenge.“My key role on this project is

pre-planning and developing theroadmap to allow the project toflow smoothly,” he said. “Alongwith Joe, I spend the majority ofmy time developing the plan andeffectively communicating it to theteam. I have spent the past threeyears on aviation projects and lookforward to starting what will betrue landmark project for the cityof Austin.“Hensel Phelps has a long histo-

ry of success on airport and avia-tion projects,” he added. “With thishistory comes a wealth of knowl-edge that we can draw from aroundthe country if we come acrosssomething we have not encoun-tered before. This is a very excit-ing project to be a part of and I lookforward to showing our client whatwe can do.”

(This story also can be foundon Construction EquipmentGuide’s Web site at www.con-structionequipmentguide.com.)CEG

On Nov. 30, Lindamood Demolition, was brought to start work onthe demolition of a hanger on the old U.S. Air Force base. Thehanger will be replaced with a storm water/de-icing collectionfacility.

AIRPORT from page 1

Page 19: Texas 05 2016

Construction Equipment Guide • Texas State Supplement • www.constructionequipmentguide.com • March 6, 2016 • Page 19

The Pit Boss CommandAir30 ventilationblower is designed to accommodate themost non-hazardous confined space ventilation requirements. The CommandAiris fully capable of handling the toughestjobs and deliver the maximum airflow fora controlled, com-fortable and safework environment!

• Ventilates Pits and Tunnels Up to 30,000 cfm Free• Adjustable from 12” to 24”• Compact and Trailer Mounted• Outriggers for Maximum Stability

• PitGuard Handrails…Choose from 8’, 10’ and 12’ Lengths

• PitBridge… Available In 8’,10’ and 12’ Lengths• PitBridge Rear Mounted Wheels or Skids For Mobility• Engineered In Accordance With OSHA Standards

U.S. Shoring & Equipment Co. ANNOUNCES The All New PitBoss CommandAir30!

U.S. Shoring & Equipment Co.PitBoss CommandAir30 and the Pit Guard

The PitGuard & PitBridge are Product Lines of PitBoss And Boast New Aspects of Pit Protection

(3) 10054 Skytraks for Sale2007, 3306 Hrss/n 160031826

$53,900

2007, 3947 Hrss/n 160031923

$53,900

2008, 3188 Hrss/n 160034184

$53,900

Sales • Rentals • Service

Page 20: Texas 05 2016

Page 20 • March 6, 2016 • www.constructionequipmentguide.com • Texas State Supplement • Construction Equipment Guide

800.392.2686CALL - VISIT -

YOUR SOURCE FORSALES AND RENTALS

CRAWLER TRUCKS, STUMP CUTTERS AND FORESTRY MULCHERS

Page 21: Texas 05 2016

Construction Equipment Guide • Texas State Supplement • www.constructionequipmentguide.com • March 6, 2016 • Page 21

Cooper Equipment Company17474 Judson Rd • San Antonio, TX

210.657.5151Cooperequip.com

Readyy. Set. Save onKubota’

compact track loader

. Set. Save oyy. Set. Save ons SVL SeriesKubota’

compact track loader

. Set. Save ons SVL Series

s.compact track loader

compact track loader

compact track loader

s.compact track loader

$0 owD

now 0% nanFi

ngicnan 4

48 nthsoM

nths*

$0 owD

fe Offfer ends 3/31/16.

now ,0% nanFi.R.A.PP.

fer ends 3/31/16.

ngicnan for 4

48 nthsoM

nths*

ractor CorporaTTractor Corporaubota © K

2016tion,ractor Corpora

kubota.com

4011 East I-30Grand Prairie, TX 75050

972-314-2500Fax: 972-314-2549

8741 Main St.Frisco, TX 75304972-335-2731

Six & Mango Equipmentwww.sixandmango.com

800.528.3113 fecon.com

FROM OUR SIGNATURE BULL HOG®, TO TRACKED CARRIERS, TO FORESTRY ATTACHMENTS, WE HAVE A

RUGGED, DURABLE PRODUCT FOR EVERY APPLICATION. BUILT BRUTALLY TOUGH AND OPERATOR-FRIENDLY, SO YOU CAN CLEAR

THE WAY TO A JOB WELL DONE.

CLEAR THE W

CLEAR THE W

YAAY W WA

FROM OUR SIGNA

, TO TRACKED ®TURE BULL HOG GNA ATURE BULL HOG

, TO TRACKED

800.528.3113

THE WY TOUGH AND ALLLY TOUGH AND OPERABRUTTALL

RUGGED, DURABLE PRODUCT FOR EVERCARRIERS, TO FORESTR

FROM OUR SIGNA

Y TO A JOB WELL DOAAY TO A JOB WELL DONE. W WA, YY, SO YOU CAN CLEAR TOR-FRIENDLLY D OPERA ATOR-FRIENDL

Y APPLICARUGGED, DURABLE PRODUCT FOR EVERACHMENT TTTACHMENTS, WE HAY A ATTCARRIERS, TO FORESTR

, TO TRACKED TURE BULL HOG GNA ATURE BULL HOG

fecon.com

Y TO A JOB WELL DONE., SO YOU CAN CLEAR

TTION. BUIL LT PPLICA ATION. BUILVE A TS, WE HA AVE A

, TO TRACKED

Page 22: Texas 05 2016

Page 22 • March 6, 2016 • www.constructionequipmentguide.com • Texas State Supplement • Construction Equipment Guide

ADVERTISER INDEX

The Advertisers Index is printed as a free editorial service to our advertisers and readership. Construction Equipment Guide is not responsible for errors or omissions.

BANE MACHINERY ..............................................................24

BAYONET-RECS ..................................................................23

BLUELINE CONST EQUIP & SERVICES ..............................9

CONSTRUCTION EQUIPMENT GUIDE

TEXAS STATE PROMO ................................................22

COOPER EQUIPMENT/BAGELA ........................................21

DITCH WITCH WEST ..........................................................13

EAGER BEAVER TRAILERS ................................................15

FECON ..................................................................................21

FLEMING MANUFACTURING LLC ......................................17

FOUR SEASONS EQUIPMENT INC ......................................3

H H FABRICATION ................................................................16

INTERSTATE TRAILERS ......................................................11

KIRBY-SMITH MACHINERY INC ............................................8

KLEIN PRODUCTS OF TEXAS ............................................12

KUBOTA SVL ........................................................................21

MIDCO SLING AND CABLE ................................................20

RAYCO MFG ........................................................................20

ROMCO EQUIPMENT CO ......................................................2

TROPHY TRACTOR ................................................................7

US SHORING & EQUIPMENT CO ......................................19

VERMEER OF TEXAS-LOUISIANA ......................................5

WAUKESHA-PEARCE INDUSTRIES INC ............................8

To read articles about these CEG advertisers, visit www.constructionequipmentguide.com

Page 23: Texas 05 2016

Construction Equipment Guide • Texas State Supplement • www.constructionequipmentguide.com • March 6, 2016 • Page 23

Introducing theSS800 Skid Steer Bayonet Breaker

SS800

The only bucket and hammer combination.Another Great Idea From Texas...For Texans and Made in Texas!

For more information on the Bayonet Breaker, contact:

1-800-427-7368www.bayonetbreaker.com

• 800lb Class Hammer

• Folds Up & Down

• Go from Bucket toBreaker in 5 Seconds

Page 24: Texas 05 2016

Page 24 • March 6, 2016 • www.constructionequipmentguide.com • Texas State Supplement • Construction Equipment Guide

At Bane Machinery, we offer Liebherr machines that are custom-engineered to perform effi ciently. And we stand behind them with full service. Count on us for original parts, factory-trained technicians, and an extensive inventory of machines for your toughest jobs. We can also service your equipment to OEM standards in the shop or the fi eld. We haven’t compromised on anything; why should you?

True Power.

www.banemachinery.com

DALLAS2449 Manana Dr.Dallas, TX 75220 Ph: (214) 734-2361

FORT WORTH10505 North FreewayFort Worth, TX 76177 Ph: (817) 847-5894

TYLER3402 N. NE Loop 323 Tyler, TX 75712 Ph: (903) 597-6641