Terry Chapman, WestConnex Stage 1
Project Director
WestConnex
Planning context
2
WestConnex
indicative alignment
3
Delivery Timeline
Stage 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
Stage
1
M4 Widening
Bu
sin
es
s C
as
e
M4 East
Stage
2
New M5
New M5 King
Georges Road
Interchange
Upgrade
Stage
3
M4-M5 Link
Pre-construction (Environmental assessments, community consultation and planning approval, land acquisition, contract procurement)
Detailed design and construction approval, land acquisition, contract procurement
Route options development
4
5
M4 Widening overview
6
M4 Widening update
Pile
foundation
construction,
Duck River
Gantry
cranes in
precast yard
Lime stabilisation of subgrade
Contract awarded to Rizzani Leighton in
December 2014.
7
M4 East preferred design
M4 East milestones
Leighton Samsung John Holland announced as
preferred contractor in June 2015.
M4 East EIS
on public
exhibition for
community
comment
September –
November
2015
8
9
Western connection to the
widened M4, Homebush
10
Western connection to the
widened M4, Homebush
11
Western entry/exit point to
M4 East tunnels, Homebush
12
Western entry/exit point to
M4 East tunnels, Homebush
13
Concord Interchange
14
Concord Interchange
15
Construction mid-point at
Cintra Park
St Lukes sporting facilities
16
17
City West Link Interchange,
Haberfield
18
City West Link Interchange,
Haberfield
19
Parramatta Road
Interchange, Ashfield
20
Parramatta Road
Interchange, Ashfield
Tunnel cross-section
21
Key construction facts
• Tunnel Length - 5.5km twin tube (3 lanes)
• Tunnel construction sites (shaft and declines) - 4
• Civil construction sites - 4
• Roadheaders - 18
• Drill and blast bench excavation, cross passages
• Total Spoil generate - 1,687,000 (bcm)
• Large cavern spans of 28 M
22
Mechanical and electrical
fast facts
• Largest axial fan = 3.6m diameter
• Number of jet fans = approx 190
• Number of tunnel substations = 8
• Predicted annual energy consumption during operation
= approx 30,000 MWh per year
• High voltage Power Supply – 33kV dual redundant, from
Ausgrid Homebush STS
• Lighting – LED / High Pressure Sodium
23
24
Improving air quality
Projected Particulate
Matter 2.5 along
Parramatta Road
without and with the
M4 East tunnels
User Pays Tolling Principles
• Distance based– Consistent with the M7
– Longer trips provide greater benefits
• Tolling capped– Ensuring equity for people travelling longer distances each day;
consistent with the M7
• Cars pay less than heavy vehicles– Cars pay one third of the heavy truck toll
– Consistent with the M2 and M5
25
Benefits
• More than 4000 full time direct jobs generated across
the project.
• Average travel time savings of six to eight minutes in
2021 on strategic routes.
• More than 50% reduction of traffic volume on
Parramatta Road by 2021.
• Enable the future provision of rapid public transport
services along Parramatta Road.
26
Stage 2 New M5
27
What’s happening right now
• Work underway on M4 Widening.
• Work underway on King Georges Road Interchange Upgrade.
• Work underway on St Lukes sporting field.
• Alexandria landfill site clean up.
• M4 East EIS on public exhibition for community comment until
November 2.
• New M5 EIS being prepared.
• Stage 3 Business Case peer reviewed
• Updated WestConnex Business Case to be released soon.
• $1.5 billion debt raising
28
Community engagement
More than
500,000
touch points
with the
community,
including:
• 6400+ 1300
info line calls
• 9300+
notifications /
doors knocked
• 31,700+ kiosk
visits
29