Teresa Guthrie, Robert Hecht, Yogan Pillay , Mark Blecher, Kelsey Case
description
Transcript of Teresa Guthrie, Robert Hecht, Yogan Pillay , Mark Blecher, Kelsey Case
Financial Implications of HIV/AIDS in South Africa – the role of the Business Sector
Findings from aids2031 costing & the efforts of the National AIDS Spending Assessment
7 Apr 2011Teresa Guthrie, CEGAA
Teresa Guthrie, Robert Hecht, Yogan Pillay , Mark Blecher, Kelsey Case
Overview of the Cost Estimates
The aids2031 South African costing project was carried out during 2009-2010, sponsored and guided by a national Steering Committee composed of senior South Africa officials and other leading national figures.
It was part of a larger international project led by R4D which included the estimation of global costs.
It aimed to estimate the long-term costs of various response scenarios till 2031.
2
• Developed epi baseline & 3 scenarios to 2031 – SPECTRUM parameterised to ASSA outputs to 2016
• Collected, reviewed and verified existing costing studies (unit costs) – limited from private sector
• Obtained current coverage rates for every intervention
• Received input from the project Steering Committee on current coverage and target rates
• Agreed on program scale up scenarios with Steering Committee
Methodology
3
Cost and Epi Projections – for each scenario
• Epidemiological impact assessed (incidence, mortality, need for treatment, numbers on ART) using Spectrum with Goals
• Costs estimated using Resource Needs Model (Futures) Resource requirements by program area and intervention For ART & PMTCT incorporated BU-HERO estimates (Meyer
Rath, 09) – note that the ART costs have been further adjusted based on the new Tender prices, which will reduce the cost estimates presented here.
Methodology (continued)
4
The South African Scenarios
1.Narrow NSP by 20112.Expanded NSP by 20213.Hard Choices by 2015
Baseline (maintaining current coverage as comparator)
5
Scenario 1 – Narrow NSP
Political will to achieve universal access is strong
Rapid scaling-up of prevention & treatment
• Achieving key NSP targets by 2011
• ART – old WHO regime and 200 CD4 criteria
• PMTCT single dose till 2009, replaced by dual therapy
• Early paediatric ART from 2009
• No male circumcision
6
Scenario 2 – Expanded NSP
Achievement of all NSP & extra targets by 2021
• ART – new regime & CD4 350 eligibility from 2010, 90% reached by 2015/6
• MC introduced 2010, reaching 90% by 2021
• Expanded workplace programmes, education and behaviour change
• Mobilization and higher coverage for CSW & MSM
• Expanded efforts for youth-out-of-school
• Programs to reduce violence against women
• Expanded mitigation interventions
7
Scenario 3 – Hard Choices Resources are limited, focus on scaling up to high
levels the most effective prevention interventions; some other prevention and social programs reduced; targets achieved by 2015:
• same ART effort as under Narrow NSP
• Increased coverage for Youth in school, condoms, male circumcision, SW & MSMs, STI treatment
• Maintaining current coverage for VCT & FCG
• Reduction below NSP targets for: mass media, youth-out of-school, workplace, HBC, palliative care, food parcels, uniforms
• Mitigation efforts significantly reduced
8
Estimated Epidemiological Impact
9
10
Adult (15+yrs) HIV Prevalence (2000–2031)
12
13
14
Infant HIV-related Deaths (1993 –2031)
Key points from the Epi-projections
1. Only the expanded NSP will halve the new infections, as per the NSP goal, but only by 2020.
2. Compared to Baseline, the expanded NSP will avert nearly 6,000 infections in total by 2031, where as continuing with the current NSP will only avert 3,000 – half!
3. With increasing treatment coverage, HIV prevalence is unlikely to reduce below 10%, best case scenario.
4. Numbers on treatment will continue to grow, up to 3million by 2018, but thereafter will start to decrease with the expanded NSP & the expanded prevention efforts.
5. PMTCT will significantly reduce infant mortality, in all scenarios since same coverage.
16
Estimated Resource Requirements
17
Total HIV/AIDS Costs by Scenario (2009-2031, ZAR Billions)
18DRAFT-do not copy or disseminate
NB. These estimations include all sectors and all sources of funding
Expanded NSP – Total Resources Required and their Distribution (ZAR billions)
20
Expanded NSP – Programme Disaggregation (ZAR billions)
21DRAFT-do not copy or disseminate
Expanded NSP delivery
Cost Implications
1. With Expanded NSP costs will double from 2010 to 2021 (but will be significantly reduced with new tender prices, should allow for all on at 350CD4 – greater prevention effects)
2. But thereafter they start to decrease significantly. Treatment taking 60% by 2020, but thereafter reducing.
3. Largest proportion will be DOH responsibility for the delivery of public ART – therefore important to increase the role of businesses in provision of ART and PMTCT.
4. Workplace programmes are important for other prevention interventions & Private sector important.
5. The role of NGOs could be expanded.
Sustainable Funding Sources?
25
Sources of Financing for HIV/AIDS in SA• No SA NASA yet to ascertain current spending trends of all sectors (public, external & private).
• No comprehensive database of external sources (some from Burlington (2009).
• No database of business sector CSI activities (some from Trilogue)• Budgetary allocations show national spending, conditional grants
to provinces & some provincial voted allocations – limited disaggregation.
• OOPE – unknown.• Development partners appear uneasy to share their longer-term
commitments to HIV/AIDS in SA?• DPs also struggle to provide year-specific expenditures by
province.• Business sector is not willing to share their expenditure for the
NASA process.• Therefore impossible to measure the projected financing gap.
26
SA Public HIV/AIDS Budget Allocations (2006/07-2012/13)
27
Rough Questimate of Total Resource Gap (for all actors, not only public)
28
SA DOH Budget Allocations for HIV/AIDS (ZAR millions)
29
Rough Guestimate of public ART shortfall, assuming 90% coverage by 2015
30
Importance of the National AIDS Spending Assessment (NASA)
31
Objectives of NASA in South Africa
For the years 2007/08, 2008/09 & 2009/10, to identify in each province:
All the sources (public, external and private) of financing for HIV/AIDS and TB
The providers of the HIV/AIDS and TB servicesThe activities services delivered – and their
alignment with the PSP prioritiesThe beneficiaries of the services
In order to make recommendations for the improved targeting of funds and efficiency of spending, according to the provincial priorities.
DRAFT - DO NOT DISSEMINATE.
32
Methodology
• Aimed to include data from all sources, from all agents and from sampled service providers.
• All DOE, DSD, DOH expenditure by activity and service provider – from BAS records.
• Wellness programme spending – included all departments but challenge of coding of HIV-related in BAS records.
• All NGOs receiving DOH/ DSD/ EU/ PEPFAR grants – sampled others (but nothing received).
• Districts & Municipalities – most included• Donors – Most - EU, GF, UN agencies (NB PEPFAR limitations
excl) – pending other donors• Private - Businesses - limited response. Medical aid estimates
incld.• Limited research activities• 90% public, 80% external, 80% NGOs & almost no business
33
Business sector HIV activities in SA
MISSING……. ??
34
Estimating & Securing Resource Requirements1. Using estimates of the future costs of an expanded NSP
2. Comparing current spending per intervention More detailed and accurate financing gaps can be calculated Sustainable resources mobilised
This requires all partners to: • participate more actively in the achievement of the
Expanded NSP• be transparent about their current and future funding
activities
What are the HIV services currently being provided / funded by business?
How could these be expanded?What does government need to do to encourage business
sector involvement?
35
WEBSITE: WWW.CEGAA.ORG
SANAC, PACs, HASTs, etc
UNAIDS
Mark Blecher, National Treasury
Drs Pillay & Mbengashe (NDOH)
aids2031 Steering Committee
Gesine Meyer-Rath & Lawrence Long, BU/HERO
Kelsey Case, Imperial College London
John, Lori & Steve, Futures Institute
Leigh Johnson, UCT
Susan Cleary, UCT
Steve Cohen, SDC
All the DoH departments that provided data
The teams at CEGAA and Results for Development Institute
Acknowledgements
36