Tendering Estimating Assignment 01[1]

download Tendering Estimating Assignment 01[1]

of 10

description

tendering

Transcript of Tendering Estimating Assignment 01[1]

  • BTEC HND in QS & BE

    Measuring, Tendering and Estimating for Construction International College of Business and Technology

    Program BTEC HND in QS & BE

    Unit / Module Tendering and Estimating

    Assessment Assignment 1 Tender Procedures & Estimating

    Lecturer Ms. S. Kavitha

    Student Name ID HNDQS/MT/26/__

    Date Handed Over 01st November 2013. Date Due To Be Informed

    Initial Submission Date Re-Submission

    Date

    Stu

    den

    t to

    Tic

    k i

    f

    Att

    emp

    ted

    Grading

    Opportunity

    Criteria Met?

    Assessor Feedback Initially On Resubmission

    P1.1

    P1.2

    P1.3

    P2.1

    P2.2

    P2.3

    P2.4

    P3.1

    P3.2

    P3.3

    P3.4

    P4.1

    P4.2

    P4.3

  • BTEC HND in QS & BE

    Measuring, Tendering and Estimating for Construction International College of Business and Technology

    M1

    M2

    M3

    D1

    D2

    D3

    Final Grade Distinction (D) Merit (M) Pass (P)

    Assessed by (name):

    Signature: Date Assessed :

    Student Signature & Comments

  • BTEC HND in QS & BE

    Measuring, Tendering and Estimating for Construction International College of Business and Technology

    Important Information for Students

    The criteria each task relates to are shown against that task where possible.

    Please note that plagiarism is treated as a serious offence and therefore the work you produce

    must be individual and original although may work in groups in some instances (Please refer

    to Student Handbook on Plagiarism & Cheating).

    All sources of information must be referenced using Harvard referencing where a

    reference list/Bibliography should be included at the end of the assignment.

    Please note that the submission date given for this assignment is the final date that you can

    hand over the assignment. A one week grace period maybe extended with prior approval

    from the Program Manager Undergraduate.

    Assignments returned to students for re-working must be re-submitted within 10 days (Please

    refer to Student Handbook on Assignments Re-submission).

    Failure to re-submit the previously marked assignment with the re-submitted assignment will

    mean that results cannot be released for the respective unit.

    Please read, follow and reference both the contents of the unit outline and the grading

    criteria of the assignment before completing this assignment.

  • BTEC HND in QS & BE

    Measuring, Tendering and Estimating for Construction International College of Business and Technology

    Plagiarism:

    While research and discussion are an essential part of an assignment, the deliberate copying of

    someone elses work or unacknowledged copying from printed or electronic sources is NOT

    permitted. You may be subject to disciplinary procedure if you do this. You should sign this sheet

    to show that you comply with these regulations.

    Students Signature: .. Date: .

    Students Comments:

    ..

    ......

    ..

    Internal Verifier

    Name: Mr. Ramzan Rafeeek

    Signature : Approved By: Mr. Ramzan

    Rafeeek Date Verified : 31

    st Oct 2013

  • BTEC HND in QS & BE

    Measuring, Tendering and Estimating for Construction International College of Business and Technology

    Assignment 01

    A private investor is initiating a plan of building a large shopping mall named Buy in Lavania in

    Mount Lavania. He wants to build a 10 storey building and make it a landmark of Mount Lavania,

    adopting more new technology. He is in the process of developing the best design for his

    construction and design will be completed by end of next month.

    Discuss the following issues, regard this project.

    1. Client plays a major role throughout the lifecycle of the project. Specify typical clients for

    which tenders are required. (P1.1)

    2. Once the design is developed, the contractor has to be chosen. The client wishes to go either

    open or selective tendering. Before deciding on the tender type, describe the stages of open and

    selective tendering. (P4.1)

    3. Once the tender type is confirmed, the contract type for this project has to be decided. Select a

    contract type for this project with reasons. (P4.3)

    4. Since the client needs a very quality project, it is decided to go for selective tendering. In

    selective tendering, the bidders will be short listed based on their pre-qualification. Specify the

    factors that are used to create select lists of bidders. (P4.2)

    5. In this tender, BOQ plays a vital role in contractors estimating. Demonstrate how the bill of

    quantities format can be prepared by the consultant and how the contractor can use it to build

    up estimates. (P3.1)

    6. In an estimate buildup of this project, basic rates will be calculated initially and the top

    management will decide on the overhead and profit margin of the project, before applying to

    the tender.

    6.1. The management has decided the profit margin as 8 % for this project. There are critical

    factors used affected this decision. Determine the critical factors. (P3.2)

  • BTEC HND in QS & BE

    Measuring, Tendering and Estimating for Construction International College of Business and Technology

    6.2. Overheads of this project are identified below.

    Item Cost in Rs.

    Site access roads & maintenance 900,250.00

    Accommodation of site labour 500,000.00

    Head office utilities such as lights, telephone, stationery supplies,

    furniture etc. 1,343,570.00

    Salaries of Workshop & Yard store keepers, Drivers, Foreman, Mechanics

    & Workmen 10,320,000.00

    Fencing & protection 210,000.00

    Cleaning Contractor & Consultant Site Offices 450,000.00

    Setting out & measurements 500,000.00

    Preparing samples for testing 650,000.00

    Insurance, Interest and taxes on business 450,000.00

    Insurance of work & workmen's compensation 800,000.00

    6.2.1. Calculate the head office overhead and site overhead separately. (P3.4)

    6.2.2. If the basic cost of the tender is Rs. 321, 315, 300.00. Calculate the head office

    overhead margin and site overhead margin of this project.

    7. Health, safety & welfare are important issues in the construction. Preplanning of these, will

    avoid unwanted big expenditures. Evaluate how the health, safety and welfare plan affects this

    tender (P3.3)

    8. The client, consultant and the contractor might have several limitations when they are going

    for a selective tender. Determine the constraints which may apply to this tender process. (P1.2)

    9. Documentation is very important in the construction contracts. Any dispute arises, will be

    resolved based on the documentation evidence. Describe the scope of contractual

    documentation required to support the tender process (P1.3)

    10. There some items of the shopping mall have been given for you to estimate. Calculate the rate

    including overhead and profit margin. (P2.4)

  • BTEC HND in QS & BE

    Measuring, Tendering and Estimating for Construction International College of Business and Technology

    10.1. Grade 30 reinforced concrete for 225 x 225 mm columns in ground floor.

    10.1.1. Find the rate per m3

    10.1.2. Find the rate per m

    10.2. 150mm block wall, Block of 150mm thick, 200 x 400 mm, on Stretcher Bond on 1:5

    cement: sand mortar. Find the rate per m2.

    10.3. Painting walls with two coats of weather shield paint. Find the rate per m2.

    Note:

    In order to do the each estimate, you have to do the following tasks,

    a) Produce a method statement suitable for compiling unit cost for each. (P2.3)

    b) This construction is based in Colombo. Collect quotations/ bills from suppliers in

    Colombo, for Material, Plant & Labour. Attach them to the document to make it more

    reliable. (P2.1) Use the overhead and profit margin you obtained from Task 6.

    c) While calculating the prices, use NRM for the measurement systems. (P2.2)

    You are allowed to refer BSR (Building Schedule of Rates) published by ICTAD, as guidance

    with a proper reference.

  • BTEC HND in QS & BE

    Measuring, Tendering and Estimating for Construction International College of Business and Technology

    Merit Grade:

    Performance Descriptors Indicative Characteristics Contextualized

    evidence

    In order to achieve a

    Merit the leaner must

    The Learners evidence shows. To achieve the

    grade will need to

    student.

    M1 Identify and apply

    strategies to find

    appropriate solutions

    Effective judgments have been made

    Complex problems with more than one variable

    have been explored

    An effective approach to study and research has

    been applied

    Effective judgments

    have been made on

    deciding the

    contract type in

    Task 03.

    M2 Select/design and

    apply appropriate

    methods/ techniques

    Relevant theories and techniques have been applied

    A range of methods and techniques have been

    applied

    A range of sources of information has been used

    The selection of methods and techniques/sources

    has been justified the design of methods/techniques

    has been justified

    Complex information/data has been synthesized

    and processed appropriate learning

    methods/techniques have been applied

    Calculating the

    overhead margins

    with appropriate

    technique, using the

    data given in Task

    6.2.2.

    M3 Present and

    communicate findings

    The appropriate structure and approach has been

    used

    Coherent, logical development of

    principles/concepts for the intended audience

    A range of methods of presentation have been used

    and technical language has been accurately used

    Communication has taken place in familiar and

    unfamiliar contexts

    The communication is appropriate for familiar and

    unfamiliar audiences and appropriate media have

    been used

    The overall

    document should be

    presented in a

    professional report

    structure.

  • BTEC HND in QS & BE

    Measuring, Tendering and Estimating for Construction International College of Business and Technology

    Distinction Grade:

    Performance Descriptors Indicative Characteristics Contextualized

    evidence

    In order to achieve a

    distinction the leaner

    must

    The Learners evidence shows. To achieve the

    grade will need to

    student.

    D 1 Use critical reflection

    to evaluate own work and

    justify valid conclusions.

    Conclusions have been arrived at through

    synthesis of ideas and have been justified

    The validity of results has been evaluated using

    defined criteria

    Self-criticism of approach has taken place

    Realistic improvements have been proposed

    against defined characteristics for success

    Critically reflect your

    own work and

    evaluate with

    supplementary

    information building

    up rates in Task 10.

    D 2 Take responsibility

    for managing and

    organizing activities

    Autonomy/independence has been demonstrated

    Substantial activities, projects or investigations

    have been planned, managed and organized

    Activities have been managed

    The unforeseen has been accommodated

    The importance of interdependence has been

    recognized and achieved

    Use various methods

    to plan, manage and

    organize activities to

    complete the report

    and submit on time

    with appropriate

    structure.

    D 3 Demonstrate

    convergent/lateral/

    creative thinking

    Ideas have been generated and decisions taken

    Self-evaluation has taken place

    Convergent and lateral thinking have been applied

    Problems have been solved

    Innovation and creative thought have been applied

    Receptiveness to new ideas is evident

    Effective thinking has taken place in unfamiliar

    contexts

    Demonstration of

    effective thinking

    have been done

    throughout the report

    and finding solutions

    for the scenario by

    applying the theory.

  • BTEC HND in QS & BE

    Measuring, Tendering and Estimating for Construction International College of Business and Technology

    Grading Matrix

    Grade code Assignment 1

    P1.1

    P1.2

    P1.3

    P2.1

    P2.2

    P2.3

    P2.4

    P3.1

    P3.2

    P3.3

    P3.4

    P4.1

    P4.2

    P4.3

    M1

    M2

    M3

    D1

    D2

    D3