TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE...

69
TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE WORKS AT ALTERNATIVE PREMISES OF SBI DWARKA 12B BRANCH DWARKA, DELHI CLIENT: ARCHITECT: SBI INFRA MGMT. SOL. PVT. LTD. M/s VASTU SADAN PVT. LTD.

Transcript of TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE...

Page 1: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

TENDER DOCUMENT

FOR

INTERIOR FURNISHING &

FURNITURE WORKS

AT

ALTERNATIVE PREMISES

OF

SBI DWARKA 12B BRANCH

DWARKA, DELHI

CLIENT: ARCHITECT:

SBI INFRA MGMT. SOL. PVT. LTD. M/s VASTU SADAN PVT. LTD.

Page 2: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

5THFLOOR, D- BLOCK, 122 A /12, GROUND FLOOR, 11, PARLIAMENT STREET, GAUTAM NAGAR, NEW DELHI-

110049.

NEW DELHI-110001 TEL. NO. - 011- 41643626, FAX. NO. – 011-41643426

INDEX

S. NO. DESCRIPTION PAGE NOS.

1. INDEX OF TENDER DOCUMENT 2

2. NOTICE INVITING TENDER 3 – 5

3. INSTRUCTIONS TO THE TENDERERS

6 – 8

4. FORM OF TENDER 9– 10

5. AGREEMENT 11 – 14

6. GENERAL CONDITIONS OF CONTRACT 15 – 32

7. SPECIAL CONDITIONS OF CONTRACT 33 – 36

8. SPECIFICATIONS (INTERIORS) 37 – 41

9. SPECIFICATIONS (SERVICES) 41 - 42

10. TESTING OF MATERIAL &THEIR FREQUENCY 44 – 53

11. SAFETY CODE 54-54

12 STANDARD PROFORMAS

55 - 55

13 LIST OF APPROVED MAKES / BRANDS 56 - 62

14 BILL OF QUANTITIES 63 –64

15 TENDER DRAWINGS 65-65

Page 3: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

SBI INFRA MANAGEMENT SOLUTIONS PVT. LTD. (SBIIMS), NEW DLEHI

Notice Inviting Tender

Tender No- SBIIMS/DAO-III/SS/2018-19/009 Date : 25/01/2019

SBI Infra Management Solutions Pvt. Ltd. on behalf of State Bank of India invites online

Tenders from the Contractors for the Interior & Furniture, Works at alternate

premises of State Bank of India, Dwarka Sector -12B, Dwarka, New Delhi. Details of tenders are as under:

1. Name of Work : Interior &Furniture, Works atalternate

premises of State Bank of India, Dwarka

Sector -12 B, Dwarka, New Delhi.

2. Time allowed for completion : 25 Days from date of handing over of the

site.

3. Earnest Money Deposit

(1% of Estimated cost)

: Rs.20,000/- (Rupees Twenty

thousandonly)by crossed Bank Draft /

Banker’s Cheque drawn in favour of State

Bank of India, New Delhi. (To

To be enclosed in sealed envelope as a

part of Technical Bid).

4. Initial Security Deposit : 2% of the total value of the contract

including Earnest Money.

5. Tender Processing Fees (To Be

Paid online)

: A non-refundable amount of Rs.2000/-

(Rupees Two Thousand only)

Amount to be paid only through SB Collect

payment portal available in SBI site

https://www.onlinesbi.comfrom 28/01/2019

to 04/02/2019

(TENDER ID : DEL201901002)

Upon successful payment of fee, a receipt

with unique reference no. will be generated.

The same is to be printed and to be enclosed

in sealed envelope as a part of technical bid.

It is also to be uploaded online on e-

tendering service provider site.

Page 4: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

6. Pre- Bid Meeting N/A

7. Last date and time of receipt

of Tenders

: 04.02.2019 up to 3.00 p.m.

8. Address at which the Tenders

are to be submitted

: Technical Bid:SBI INFRA MANAGEMENT

SOLUTIONS PVT. LTD.

5thFloor, D- Block, 11, Parliament Street,

New Delhi- 110001.

Price Bid:Price bid to be uploaded

online.

www.tenderwizard.com/SBIETENDER

9. Date and time of opening of

Tenders

: 04.02.2019 at 3.30 p.m.

10. Place of opening Tenders : SBI INFRA MANAGEMENT SOLUTIONS

PVT. LTD.

5thFloor, D- Block, 11, Parliament Street,

New Delhi- 110001.

11. Defects Liability Period : 12 months from the date of handing over of

the project to the satisfaction of Bank.

12. Validity of Offer

: 90 days from the date of opening the

Tenders.

13. Liquidated Damages : At the rate of 0.5% of the Contract Value per

week which subject to a maximum of 5% of

the accepted Contract Value.

14 Online submission of tender : Vendors are required to upload price bid separately

duly signed and stampedalong with soft copy of

requisite EMD and tender cost on the SBI e-tender

portal.

www.tenderwizard.com/SBITENDER

Page 5: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

15 CORRIGENDUM(IF ANY) : will be published on SBI e-tender portal

www.tenderwizard.com/SBITENDER

16 Availablity of tender Documents : Tender ocuments to be downloaded from the SBI e-

tender portal

www.tenderwizard.com/SBITENDERAND

ww.sbi.co.in under procurement news from

28.01.19 to 04.02.2019

17 Contact Person for Any Queries : Shri Shiv Suman, Manager (Civil), mob:9101315866

at SBI A.O. Shankar Road, Rajender Nagar, New

Delhi-110060

email:[email protected]

18 Note : If the vendor is found to have delayed the

running/in hand project beyound the prescribed

time limit specified in related tender document,

the vendor will not to be issued the new tender

until completion of the previous delayed work

19 Performance Guarantee : If the L-1 price quoted is more than 10% below the

estimated cost the vendor has to submit the

additional security deposit as performance

guarantee of the amount of total % value less than

the estimated value. the performance guarantee

will be released after successful completion of the

work

Mode of Submission of Tender: The tender shall be submitted in both physical and

online in two cover system in accordance with the procedure detailed herein below.

Specified documents shall be sealed in envelopes of appropriate size each of which shall

be sealed.

• First Envelope marked Cover 1 shall contain Earnest Money Deposit along

with Covering Letter and Cost of Tender Document.

• Envelope marked Cover 2 shall be of adequate size and shall contain

envelopes marked Covers 1 & Undertaking as in Annexure- I and shall be

properly sealed. This envelope shall be endorsed on the outside face as

under:

“INTERIOR FURNISHING & FURNITURE WORK at Alternative Premises of SBI

Page 6: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

DWARKA BRANCH , SECTOR-12B, DWARKA, NEW DELHI.”

The envelope marked Cover 2 containing the tender documents as per instructions

mentioned above shall be submitted in the office of VICE PRESIDENT (CIVIL), SBI

INFRA MANAGEMENT SOLUTIONS PVT. LTD., 5THFLOOR, D-BLOCK, 11, SANSAD

MARG, NEW DELHI 110001 ON OR BEFORE 3.00 p.m. on 04/02/2019.

Envelope marked Cover 1 containing Earnest Money Deposit along with Covering Letter

and Cost of Tender Document, will be opened if the Earnest Money Deposit or Cost of

Tender Document is not found as prescribed, the tender shall be rejected.

In case the date of opening of tenders is declared as a holiday, the tenders will be

opened on the next working day at the same time.

State Bank of India has the right to accept / reject any or all tenders without assigning

any reasons.

For E-Tender related queries: Service provider: M/s Antares Systems Limited,

Registered Office at: - #24, Sudha Complex, 3rd Stage, 4th Block, Bangalore – 560079.

Ph: - 080-49352000 / 40482000 Fax: - 080-49352034

Help Desk: Contact Person: Mr. Pushpraj/Mr. Tousik Ghosh / Mr. Kushal Bose Mobile no.

7503347659/ 09674758724/ 07686913157 (On working days-9 hours–18 hours) E-mail:

[email protected]/[email protected]/kushal.b@antaressystems

.com

For any other queries the vendors may contact Shri Shiv Suman, Manager (Civil) Mb:

9101315866 at office of Vice President SBIIMS, Delhi Circle, 5th Floor LHO, State Bank of

India, 11, Parliament Street, New Delhi110001

SBI Infra Management Solutions Pvt. Ltd.

(SBIIMS)

SIGNATURE OF THE TENDERER WITH SEAL & DATE

INSTRUCTIONS TO THE TENDERERS

• Scope of Work

• Sealed tenders are invited by M/s VASTU SADAN PVT. LTD., 122A/12,

Ground floor, Gautam Nagar, New Delhi-49. Phone – 011-41643426,

41643626 for and on behalf of State Bank of India for the Interior & Furniture

Works at State Bank of India, Dwarka Branch, sector-12B, Dwarka, New

Delhi.

Page 7: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

• Site and its Location

• The proposed work is to be carried out at alternate premises of State

Bank of India, Dwarka Branch Sector-12B, Dwarka, New Delhi.

• Tender Documents

2.1 The work has to be carried out strictly according to the conditions stipulated in

the tender consisting the following documents and the most workmen like

manner.

Instructions to Tenderers

General Conditions of Contract

Special Conditions of Contract

Additional Specifications

Drawings

Price Bid

• The above documents shall be taken as complementary and mutually explanatory

of one another but in case of ambiguities or discrepancies, shall take precedence in the

order given below:

• Price Bid

• Additional Specifications

• Technical Specifications

• Drawings

• Special Conditions of Contract

• General Condition of Contract

• Instruction to Tenderers

• Complete set of tender documents including relative drawings can be obtained by

downloading from the bank's webiste:https://ww.sbi.co.in under procurement news.

• The tender documents are not transferable.

• Site Visit

3.1 The tenderer must obtain himself on his own responsibility and his own expenses

all information and data which may be required for the purpose of filling this

tender document and enter into a contract for the satisfactory performance of the

work. The tenderer is requested satisfy himself regarding the availability of water,

power, transport and communication facilities, the character quality and quantity

of the materials, labour, the law and order situation, climatic conditions, liaison

requirements with local authorities/ authorities maintaining the campus,

security agencies guarding the campus, traffic regulations in and around

the site etc;

The tenderer will be fully responsible for considering the financial effect of any or

all the factors while submitting his tender.

• Earnest Money

4.1 The tenderers are requested to submit the Earnest Money of Rs. 20000/-

(Rupees Twenty Thousand) in the form of Demand Draft or Bankers’ Cheque

in favour of State Bank of India drawn on any Bank in India.

EMD in any other form other than as specified above will not be

accepted. Tender not accompanied by the EMD in accordance with clause

4.1 above shall be rejected.

Page 8: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

• No interest will be paid on the EMD.

• EMD of unsuccessful tenderers will be refunded/ returned within 30 days of award

of Contract.

• EMD of successful tenderer will be retained as a part of security deposit.

• Initial Security Deposit

The successful tenderer will have to submit a sum equivalent to 2% of contract

value less EMD, by means of Demand Draft drawn in favour of State Bank of India

payable at New Delhi within a period of 7 days of acceptance of tender.

• Security Deposit

6.1 Total security deposit shall be 5% of contract value. Out of this 2% of contract

value is in the form of initial security deposit, which includes the EMD. Balance

3% shall be deducted from the running account bill of the work at the rate of

10% of the respective running account bills i.e., deduction from each running bill

account will be 10% till total 3% of contract value is reached. 50% of the total

security shall be paid to the contractors on the basis of architect’s certifying the

virtual completion. The balance 50% would be paid to the contractors after the

defects liability period as specified in the contract provided he has carried out all

the work and attended to all the defects in accordance with the condition of the

contract and clearance, if any, of the observations of the CTE of CVC.

• No interest shall be paid to the amount retained by the Bank as Security Deposit.

• Signing of Contract Documents

The successful tenderer shall be bound to implement the contract by signing an

agreement and conditions of contract attached herewith within 7 days from the

receipt of intimation of acceptance of his tender by the Bank. However, the

written acceptance of the tender by the Bank will constitute a binding agreement

between the Bank and successful tenderer whether such formal agreement is

subsequently entered into or not.

• Completion Period

Time is essence of the contract. The work should be completed in all respects in

accordance with the terms of contract within a period of 25 Days from the date

of handing over of the site.

• Validity of Tender Tenders shall remain valid and open for acceptance for a period of ninety days

from the date of opening price bid. If the tenderer withdraws his/her offer during

the validity period or makes modifications in his/her original offer which are not

acceptable to the Bank without prejudice to any other right or remedy the Bank

shall be at liberty to forfeit the EMD.

10.0 Liquidated Damages

The liquidated damages shall be 0.5% per week subject to a maximum of 5% of

the accepted Contract Value.

• Rate and Prices:

11.1 The tenderers shall quote their rates for individual items both in words and

figures. In case of discrepancy between the rate quoted in words and figures the

unit rate quoted in words will prevail. If no rate is quoted for a particular item

the contractor shall not be paid for that item when it is executed.

The amount of each item shall be calculated and the requisite total is given. In

case of discrepancy between the unit rate and the total amount calculated from

multiplication of unit rate and the quantity the unit rate quoted will govern and

Page 9: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

the total amount will be corrected.

• The tenderers need not quote their rates for which no quantities have been given. In

case the tenderers quote their rates for such items those rates will be ignored and will not

be considered during execution.

• The tenderers should not change the units as specified in the tender. If

any unit is changed the tenders would be evaluated as per the original unit and the

contractor would be paid accordingly.

11.3 The tenderer should not change or modify or delete the description of the item. If

any discrepancy is observed he should immediately bring to the knowledge of the

Architect/Bank.

11.4 Each page of the BOQ shall be signed by the authorized person and cutting or

over writing shall be duly attested by him.

• Each page shall be totaled and the grand total shall be given.

• The rate quoted shall be firm and shall include all costs, allowances, taxes, levies

etc. and deduction at source for Income Tax, Work Contract Tax etc. will be made as per

statutory rules.

• The contractor shall be required to conduct necessary tests of the water brought from

tube well or any other outside source, from approved laboratory.

• The contractor is required to comply with all act of the Government relating to

labour and the rules and regulations made there under from time to time and to submit at

the proper times all particulars and statements required to be furnished to the appropriate

authorities.

• Nominated Contractor for Allied work, if any.

The contractor shall get allied works executed only through Contractors already in

SBI’s Panel, for different categories of works.

13.0 Vendor has to submit in Hard copy the tender document along with all

terms & Conditions, Specifications and subsequent annexure and

corrigendum’s duly signed and stamped by authorized representative/

signatory on becoming L1. However we accept all the terms and

conditions along with the specifications, Drawings, Layouts etc defined in

the tender documents.

Annexure-I

UNDERTAKING (To be submitted along with the technical Bid)

To

VICE PRESIDENT (CIVIL),

Page 10: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

SBI INFRA MANAGEMENT SOLUTIONS PVT LTD,

5TH FLOOR, D-BLOCK,

11, PARLIAMENT STREET,

NEW DELHI 110001.

Dear Sir,

• Reg.: Interior & Furniture Works at alternate premises of State Bank of

India, Dwarka Branch sector-12B, Dwarka, New Delhi.

I / We refer to the tender notice issued by you for Electrical works and allied works in

connection with the above.

• I undertake to submit in Hard copy the tender document along with all

terms & Conditions, Specifications and subsequent annexure and corrigendum’s

duly signed and stamped by authorized representative/ signatory on becoming L1.

However we accept all the terms and conditions along with the specifications,

Drawings, Layouts etc defined in the tender documents.

• I / We hereby offer to perform, provide, execute, complete and maintain the works in

conformity with the drawings, designs, conditions of contracts, specifications, schedule of

quantities relating to the works

• I / We have satisfied myself / ourselves as to the site conditions, examined the drawings

and all aspects of the tender conditions, subject to above, I / We do hereby agree, should

this tender be accepted in whole or in part, to:

a. Abide by and full fill all the terms and provisions of the said conditions annexed

here to,

• Complete the works within 25 Days as per the work programme enclosed with the

tender in two or three shifts if considered necessary by the Employer / Architects at

no extra cost to the Employer.

• I / We have deposited the earnest money of Rs. 20, 000/- (Rupees Twenty

Thousand only) in the form of Demand Draft / Banker’s Cheque drawn in favour of

SBIIMS payable at New Delhi and State Bank of India payable at New Delhi,

respectively which, I / We note, will not bear any interest and is liable for forfeiture.

I. If our offer is withdrawn within the validity period of acceptance by the

Employer.

Or

• If the contract agreement is not executed by us within 7 days from the date of

Page 11: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

receipt of the letter of acceptance.

Or

• If we fail to pay the initial security deposit as stipulated.

Or

• If the work is not commenced within 3 days after issue of work order.

• I / We understand that you are not bound to accept the lowest or any tender you

receive.

The names of DIRECTORS of our Firm are:

• ________________________________

• ________________________________

• ________________________________

• ________________________________

Yours faithfully,

Signature ……………………………..

Designation …………………………..

Name of Partner / Director of the Firm, authorized

to sign or name of person having power of attorney

to sign the contract. (Certified true copy of power

of attorney should be attached)

Signature and address of witnesses: a. Signature

……………………………………

Name ………………………………………………..

Address ……………………………………………..

Page 12: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

b.

Signature………………………………………

Name ……………………………………………….

Address …………………………………………….

AGREEMENT

This agreement made on the __________day of ____________Two Thousand _____

BETWEEN State Bank of India a corporation constructed under the State Bank of India

Act, 1955 and having its Local Head Office at New Delhi and many other places,

(hereinafter called “the Employer”) of the one part and M/s

__________________________ through its ______________ having its registered

office at _______________________________________ (hereinafter called “the

Contractor”) of the other part.

WHEREAS the Employer is desirous of executing Certain Works to be carried out at

alternate premises of State Bank of India, Dwarka 12BBranch,Dwarka, New

Delhi. as per Schedule-I, to this agreement and has caused Drawings, Bills of Quantities

and Specification describing the work to be done, prepared by M/s VASTU SADAN

PVT. LTD., 122A/12, Ground floor, Gautam Nagar, New Delhi-49, (hereinafter

called “the Architects”).

AND WHEREAS the said Drawings, the Bills of Quantities marked pages _____ to ____

(inclusive) and the Specifications as stated have been signed by or on behalf of the

parties hereto:

AND WHEREAS the Contractor has agreed to execute the work upon the Conditions of

Tender and the Conditions of Contract and further subject to the Special Conditions set

forth in Schedule-II hereto attached (hereinafter collectively referred to as “the said

Conditions”) as per the said Drawings and as described in the said Specification and

included in the said Bills of Quantities for the sum of Rupees _____________________

NOW IT IS HEREBY AGREED AS FOLLOWS:

• In consideration of the sum of Rupees

________________________________________ to be paid at the time and in the

manner set forth in the said Conditions, the Contractor shall upon and subject to the

said Drawings and described in the said Specification and Bills of Quantities.

2. The Employer shall pay to the Contractor the said sum of

Page 13: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

Rs._______________________________

_________________________________________________________________

_______________ or such other sum as shall become payable hereunder at the

3. The term “The Architects” in the said conditions shall mean M/s VASTU SADAN

PVT. LTD., 122A/12, Ground floor, Gautam Nagar, New Delhi-49, or in the

event of their ceasing to be Architects for the purposes of this Contract, such

other persons as shall be nominated for that purpose by the Employer, not being

a person to whom the contractor shall object for reasons considered to be

sufficient by the Employer mentioned in the said Conditions. Provided always

that no persons subsequently appointed to be Architects under this Contract shall

be entitled to disregard or overrule any decision or approval or direction given or

expressed by the Architects for the time being.

4. The said Conditions, Specifications and Priced Bills of Quantities shall be read and

construed as forming part of this agreement, and the parties hereto shall

respectively abide by and submit themselves to the conditions and stipulations

and perform the agreement on their parts respectively in such Conditions,

Specifications and Priced Bills of Quantities contained.

• This agreement is subject to jurisdiction of courts in Delhi only.

• Vice President (Civil), SBI INFRA MANAGEMENT SOLUTIONS PVT. LTD. 5th Floor, D-

Block, 11, Parliament Street, New Delhi- 110001. shall exercise powers on behalf of

the said Employer for the purpose of the Contract Agreement.

• Whereas both the parties agree to sign the following annexure Annexed to this

Agreement in token of their acceptance.

• Agreement

• General Conditions of contract.

• Special Condition of Contract.

• Safety Codes.

• Specifications.

• Material Testing & Their Frequency.

• List of Approved Makes/ Brands

• Priced Bill of Quantities.

• Drawings.

• The Bank shall pay the contractor such sum as shall become payable hereunder at

the times and in the manner specified in the said Conditions mentioned in the

General Conditions of Contract.

• Whereas the Contractor hereby undertakes and agrees to carry out and complete the

works within 25 Days from the date of handing over site or 15 days from the date of

issue of letter of acceptances, whichever is later. The Contractor agrees and has

deposited the sum of Rs. _________ by way of Initial Security Deposit for due

fulfillment of this Contract for the Works. It is agreed that the Security Deposit shall

be deducted from each running bills and refunded to the contractor as per clause 2 of

the General Conditions of the Contract Annexed herewith.

• Whereas it is agreed that the earnest money amounting to Rs. 20, 000/- (Rupees

Twenty Thousand only) deposited by the Contractor in the form of Demand Draft

along with the tender shall be forfeited in full in case the Contractor does not remit

Page 14: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

the Initial Security Deposit within the stipulated period of the start of the works by

the stipulated date mentioned in the award letter.

• Whereas Shri __________________ is the accredited representative(s) of the

Contractor who would be responsible for taking instructions from the Employer in

relation to the Works. The Contractor agrees to pay Sales Tax or any other Tax on

material or finished works like Works Contract Tax, Turnover Tax etc. including

Income Tax in respect of this Contract of the Works and the Employer will not

entertain any claim whatsoever in this report nor the Employer shall be responsible

to pay any Tax as mentioned above. If due to non – payment of any of the aforesaid

Tax or other Taxes connected with the Works, the Contractor suffers any loss or

damages occurred to the Contractor and the Employer will be entitled to claim

damages from the contractor for non completion of the Work within 12 calendar

months stipulated in Para 9, above.

• Whereas the Contractor hereby declares the list of all the relative working with the

Employer which is annexed herewith.

OR

Whereas the Contractor declares that none of his relative is working with the

Employer.

OR

Whereas the Contractor declares that he has associated himself with the agencies

of the appropriate classes of person for Sanitary and Water Supply Installation

etc. or any other specialized job to complete the works.

• The Plans, Drawings, Specifications, Contract Documents and the Documents above

mentioned shall form basis of this Contract and the decision of Vice President (Civil),

SBI INFRA MANAGEMENT SOLUTIONS PVT. LTD. 5th Floor, D- Block, 11, Parliament

Street, New Delhi- 110001. for the time being as mentioned in the Conditions of

Contract in reference to all matters of dispute as to material, workmanship or

account and as to the intended interpretation of the clauses of the Agreement or any

of the document attached hereto shall be final and binding on both parties and may

be made rule of the court.

• The work comprises of the “Interior, Furnishing & Furniture Works for State

Bank of India, Dwarka Branch, Sector-12B, New Delhi.” as mentioned above

and all subsidiary and other works connected therewith on the same site as may be

ordered to be done from time to time by Vice President (Civil), SBI INFRA

MANAGEMENT SOLUTIONS PVT. LTD. 5th Floor, D- Block, 11, Parliament

Street, New Delhi- 110001. for the time being even though such works may not

have been shown on the , Plans or described in the said Specifications or Schedule of

Quantities of various classes of Work to be done.

• The Employer through the Vice President (Civil),SBI INFRA MANAGEMENT

SOLUTIONS PVT. LTD. 5th Floor, D- Block, 11, Parliament Street, New Delhi-

110001. reserves himself the right of altering the Plans, Drawings and nature of

Work of adding to or omitting any items of work or having portions of the same

carried out departmentally or otherwise and such alterations or variations shall be

carried out without prejudice to this Contract.

• All disputes arising out of or in any way connected with this agreement shall be

deemed to have arisen in Delhi and only the courts of Delhi shall have jurisdiction to

determine the same.

• The several parts of this Contract have been read to us and fully understood by us.

In Witness whereof the parties above named have executed these presents today

and year first hereinabove written.

Page 15: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

Signed, Sealed and Delivered by:

Authorised Representative of Employer Authorised Representative of Contractor

SCHEDULE I

Interior Furnishing & Furniture Works State Bank of India, Dwarka sector -12,

New Delhi. all as described in Tender and Drawings inclusive hereto as Specifications.

SCHEDULE II

The following Letters/ Correspondence form a part of Agreement:

1.

Page 16: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

2.

3.

As witness our hands the day and year first written above,

In presence of

Signature: Signature by the said Employer

Name: Name:

Occupation: Designation:

Address: Address:

In presence of

Signature: Signature by the said Contractor

Name: Name:

Occupation: Designation:

Address: Address:

GENERAL CONDITIONS OF CONTRACT

• Definitions:

“Contract means the documents forming the tender and the acceptance thereof

Page 17: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

and the formal agreement executed between State Bank of India (client) and the

contractor, together with the documents referred therein including these

conditions, the specifications, designs, drawings and instructions issued from time

to time by the architects / Bank and all these documents taken together shall be

deemed to form one contract and shall be complementary to one another.

1.1 In the contract the following expressions shall, unless the context otherwise

requires, have the meaning hereby respectively assigned to them.

1.1.1 ‘SBI’ shall mean State Bank of India (client) having its Corporate Centre at State

Bank Bhavan, Madame Cama Road, Mumbai-400 021 and includes the client’s

representatives, successors and assigns.

‘Architects/Consultants’ shall mean M/s VASTU SADAN PVT. LTD., 122A/12,

Ground Floor, Gautam Nagar, New Delhi - 49. ‘Site Engineer’ shall mean an

Engineer appointed by the Bank as their representative to give instructions to the

contractors.

• ‘The Contractor’ shall mean the individual or firm or company whether

incorporated or not, undertaking the works and shall include legal personal representative of

such individual or the composing the firm or company and the permitted assignees of such

individual or firms of company.

The expression ‘works’ or ‘work’ shall mean the permanent or temporary work

described in the “Scope of work” and / or to be executed in accordance with the

contract and includes materials, apparatus, equipment, temporary supports,

fittings and things of all kinds to be provided, the obligations of the contractor

hereunder and work to be done by the contractor under the contract.

• ‘Engineer’ shall mean the representative of the Architect/Consultant.

• ‘Drawings’ shall mean the drawings prepared by the Architects and issued by the

Engineer and referred to in the specifications and any modifications of such drawings as may

be issued by the Engineer from time to time. ‘Contract Value’ shall mean the value of the

entire work as stipulated in the letter of acceptance of tender subject to such additions

thereto or deductions there from as may be under the deductions there from as may be

made under the provision herein after contained.

• ‘Specifications’ shall mean the specifications referred to in the tender and any

modifications thereof as may time to time be furnished or approved by the architect /

consultant “Month” means calendar month.

• “Week” means seven consecutive days.

• “Day” means a calendar day beginning and ending at 00 Hrs. and 24 Hrs.

respectively.

• Total Security Deposit

Total Security Deposit comprise of

Earnest Money Deposit

Initial Security Deposit

Retention Money

• Earnest Money Deposit:

The tenderer shall furnish EMD of Rs. 20,000/- (Rupees Twenty Thousand

only) in the form of Demand Draft drawn in favour of State Bank of India payable

at New Delhi on any Scheduled Bank. No tender shall be considered unless the

EMD is so deposited in the required form. No interest shall be paid on this EMD.

The EMD of the unsuccessful tenderer shall be refunded after the decision to

award the contract is taken without interest. The EMD shall stand absolutely

forfeited if the tenderer revokes his tender at any time the period when he is

required to keep his tender open acceptance by the SBI or after it is accepted by

the SBI the contractor fails to enter into a formal agreement or fails to pay the

Page 18: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

initial security deposit as stipulated or fails to commence the work within the

stipulated time.

• Initial Security Deposit (ISD)

The amount of ISD shall be 2% of accepted value of tender including the EMD in

the form of D/D drawn on any scheduled Bank and shall be deposited within 7

days from the date of acceptance of tender.

• Retention Money:

Besides the ISD as deposited by the contractor in the above said manner the

retention money shall be deducted from the running account bill at the rate of

10% of the gross value of work done by the contractor and claimed in each bill

provided the total security deposit i.e. the ISD plus Retention Money shall both

together not exceed 5% of the contract value. 50% of the total security deposit

shall be refunded to the contractor without any interest on issue of Virtual

Completion certificate by the Architect / consultant. The balance 50% of the total

security deposit shall be refunded to the contractors without interest within fifteen

days after the end of defects liability period provided the contractor has

satisfactorily attended to all defects in accordance with the conditions of contract

including site clearance.

• Language

The language in which the contract documents shall be drawn shall be in English.

3.0 Errors, Omissions and Discrepancies

In case of errors, omissions and / or disagreement between written and scaled

dimensions on the drawings or between the drawings and specifications etc., the following order shall apply.

i) Between scaled and written dimension (or description) on a drawing, the latter shall be adopted.

• Between the written or shown description or dimensions in the drawings and the

correspondence one in the specification the former shall be taken as correct.

• Between written description of the item in the specifications and descriptions in bills

of quantities of the same item, the former shall be adopted.

• In case of difference between rates written in figures and words, the rate in words

shall prevail.

• Between the duplicate / subsequent copies of the tender, the original tender shall be taken as correct.

4.0 Scope of Work:

The contractor shall carryout complete and maintain the said work in every

respect in strictly accordance with this contract and with the directions of and to

the satisfaction of the Bank/ SBIIMS to be communicated through the architect /

consultant. The architect / consultant at the directions of the Bank from time to

time issue further drawings and / or written instructions, details directions and

explanations which are hereafter collectively referred to as Architect’s /

Consultant’s instructions in regard to the variation or modification of the design,

quality or quantity of work or the addition or omission or substitution of any work.

Any discrepancy in the drawings or between the BOQ and / or specifications. The

removal from the site of any material brought thereon by the contractor and any

substitution of any other materials therefore the removal and / or re-execution of

any work executed by him. The dismissal from the work of any person employed

/ engaged thereupon.

• i) Letter of Acceptance:

Within the validity period of the tender the Bank shall issue a letter of acceptance

either directly or through the architect by registered post or otherwise depositing

Page 19: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

at the address of the contractor as given in the tender to enter into a Contract for

the execution of the work as per the terms of the tender. The letter of

acceptance shall constitute a binding contract between the SBI and the

contractor.

ii) Contract Agreement:

On receipt of intimation of the acceptance of tender from the SBI / Architect the

successful tenderer shall be bound to implement the contract and within fifteen

days thereof he shall sign an agreement in a non-judicial stamp paper of

appropriate value.

• Ownership of Drawings:

All drawings, specifications and copies thereof furnished by the SBI/ SBIIMS

through its architects / consultants are the properties of the SBI. They are not to

be used on other work.

• Detailed Drawings and Instructions:

The SBI/ SBIIMS through its architects / consultants shall furnish with reasonable

promptness additional instructions by means of drawings or otherwise necessary

for the proper execution of work. All such drawings and instructions shall be

consistent with the contract documents, true developments thereof and reasonably inferable there from.

The work shall be executed in conformity therewith and the contractor prepare a

detailed programme schedule indicating therein the date of start and completion

of various activities on receipt of the wok order and submit the same to the SBI

through the architect / consultant.

• Copies of Agreement

Two copies of agreement duly signed by both the parties with the drawings shall

be handed over to the contractors.

• Liquidated Damages:

If the contractor fails to maintain the required progress in terms of clause 30 of

GCC or to complete the work and clear the site including vacating their office on

or before the contracted or extended date or completion without justification in

support of the cause of delay, he may be called upon without prejudice to any

other right of remedy available under the law to the SBI on account of such

breach to pay a liquidated damages at the rate of 0.5% of the contract value per

week which is subject to a maximum of 5% of the contract value.

• Materials, Appliances and Employees

Unless or otherwise specified the contractor shall provide and pay for all

materials, labour, water, power, tools, equipment transportation and any other

facilities that are required for the satisfactory execution and completion of the

work. Unless or otherwise specified all materials shall be new and both

workmanship and materials shall be of best quality. The contractor shall at all

times enforce strict discipline and good order among his employees and shall not

employ on the work any unfit person or anyone not skilled in the work assigned

to him. Workman whose work or behavior is found to be unsatisfactory by the

SBI / SBIIMS/ Architect/ Consultant he shall be removed from the site

immediately.

• Permits, Laws and Regulations:

Permits and licenses required for the execution of the work shall be obtained by

the contractor at his own expenses. The contractor shall give notices and comply

with regulations, laws, and ordinances rules, applicable to the contract. If the

contractor observes any discrepancy between the drawings and specifications, he

Page 20: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

shall promptly notify the SBI/ SBIIMS in writing under intimation of the Architect

/ Consultant. If the contractor performs any act which is against the law, rules

and regulations he shall meet all the costs arising there from and shall indemnify

the SBI any legal actions arising there from.

12.0 Setting out Work:

The contractor shall set out the work and shall be responsible for the true and

perfect setting out of the same and for the correctness of the positions, levels,

dimensions, and alignment of all parts thereof and get it approved by the

architect/ consultant before proceeding with the work. If at any time any error in

this respect shall appear during the progress of the works, irrespective of the fact

that the layout had been approved by the architect / consultant the contractor

shall be responsible for the same and shall at his own expenses rectify such error,

if so, required to satisfaction of the SBI/ SBIIMS.

13.0 Protection of Works and Property:

The contractor shall continuously maintain adequate protection of all his work

from damage and shall protect the SBI’s properties from injury or loss arising in

connection with contract. He shall make good any such damage, injury, loss,

except due to causes beyond his control and due to his fault or negligence.

He shall take adequate care and steps for protection of the adjacent properties.

The contractor shall take all precautions for safety and protections of his

employees on the works and shall comply with all applicable provisions of Govt.

and local bodies safety laws and building codes to prevent accidents, or injuries to

persons or property on, about or adjacent to his place of work. The contractor

shall take insurance covers as per clause 26.0 at his own cost. The policy may

take in joint names of the contractor and the SBI and the original policy may be

lodged with the SBI.

• Inspection of Work:

The SBI /SBIIMS/ Architect / Consultant or their representatives shall at all

reasonable times have free access to the work site and/ or to the workshop,

factories, or other places where materials are lying or from where they are

obtained and the contractor shall give every facility to the SBI/ SBIIMS, Architect

/ consultant and their representatives necessary for inspection and examination

and test of the materials and workmanship. No person unless authorised by the

SBI/ Architect / Consultant except the representative of Public authorities shall be

allowed on the work at any time. The proposed work either during its

construction stage or its completion can also be inspected by the Chief Technical

Examiner’s organisation a wing of Central Vigilance Commission.

• Assignment and Subletting

The whole of work included in the contact shall be executed the contractor and he

shall not directly entrust and engage or indirectly transfer, assign or underlet the

contract or any part or share thereof or interest therein without the written

consent of the SBI/ SBIIMS through the architect and no undertaking shall relieve

the contractor from the responsibility of the contractor from active

superintendence of the work during its progress.

16.0 Quality of Materials, Workmanship & Test

All materials and workmanship shall be best of the respective kinds described in

the contract and in accordance with Architect / Consultant instructions and shall

be subject from time to time to such tests as the architect / consultant may direct

at the place of manufacture or fabrication or on the site or an approved testing

laboratory. The contractor shall provide such assistance, instruments, machinery,

labour, and materials as are normally required or examining measuring sampling

Page 21: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

and testing any material or part of work before incorporation in the work before

incorporation in the work or testing as may be selected and required by the

Architect / Consultant.

• Samples

All samples of adequate numbers, size, shades and pattern as per specifications

shall be supplied by the contractor with out any extra charges. If certain items

proposed to be used are of such nature that samples cannot be presented or

prepared at the site detailed literature / test certificate of the same shall be

provided to the satisfaction of the Architect / Consultant. Before submitting the

sample / literature the contractor shall satisfy himself that the material /

equipment for which he is submitting the sample / literature meet with the

requirement of tender specification. Only when the samples are approved in

writing by the architect / consultant the contractor shall proceed with the

procurement and installation of the particular material / equipment. The

approved samples shall be signed by the Architect / Consultant for identification

and shall be kept on record at site office until the completion of the work for

inspection / comparison at any time. The Architect / Consultant shall take

reasonable time to approve the sample. Any delay that might occur in approving

the samples for reasons of its not meeting the specifications or other

discrepancies inadequacy in furnishing samples of best qualities from various

manufacturers and such other aspects causing delay on the approval of the

materials / equipment etc. shall be to the account of the contractor.

iii) Cost of Tests

The cost / expenditure required for the tests shall be borne by the contractor if

such test is intended by or provided for in the specification or BOQ.

iv) Costs of Tests not provided for

If any test is ordered by the Architect / Consultant which is either

If so intended by or provided for or (in the cases above mentioned) is not so

particularized, or though so intended or provided for but ordered by the Architect

/ Consultant to be carried out by an independent person at any place other than

the site or the place of manufacture or fabrication of the materials tested or any

Government / approved laboratory, then the cost of such test shall be borne by

the contractor.

17.0 Obtaining Information Related to Execution of Work

No claim by the contractor for additional payment shall be entertained which is

consequent upon failure on his part to obtain correct information as to any matter

affecting the execution of the work nor any misunderstanding or the obtaining

incorrect information or the failure to obtain correct information relieve him form

nay risks or from the entire responsibility for the fulfillment of contract.

18.0 Contractor’s Superintendence

The contractor shall give necessary personal superintendence during the

execution of the works and as long, thereafter, as the Architect / consultant may

consider necessary until the expiry of the defects liability period stated hereto.

• Quantities

• The Bill of Quantities (BOQ) unless or otherwise stated shall be deemed to have

been prepared in accordance with the Indian Standard Method of Measurements and

quantities. The rate quoted shall remain valid for variation of quantity against individual item

to any extent subject to maximum variation of the contract value by 25%. The entire

amount paid under Clause 20, 21 hereof as well as amounts of prime cost and provisional

sums, if any, shall be excluded.

Page 22: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

Variation exceeding 25%: The items of work executed in relation to variation

exceeding 25% shall be paid on the basis of provisions of clause 22 (e) hereof.

20.0 Works to be measured

The Architect / Consultant may from time to time intimate to the contractor that

he required the work to be measured and the contractor shall forthwith attend or

send a qualified representative to assist the Architect in taking such

measurements and calculations and to furnish all particulars or to give all

assistance required by any of them. Such measurements shall be taken in

accordance with the Mode of measurements detailed in the specifications. The

representative of the Architect / Consultant shall take joint measurements with

the contractor’s representative and the measurements shall be entered in the

measurement book. The contractor or his authorised representative shall sign all

the pages of the measurement book in which the measurements have been

recorded in token of his acceptance. All the corrections shall be duly attested by

both representatives. No over writings shall be made in the M book should the

contractor not attend or neglect or omit to depute his representative to take

measurements then the measurements recorded by the representative of the

Architect / consultant shall be final. All authorised extra work, omissions and all

variations made shall be included in such measurement.

21.0 Variations

No alteration, omission or variation ordered in writing by the Architect /

consultant shall vitiate the contract. In case the SBI / SBIIMS/ Architect /

Consultant thinks proper at any time during the progress of works to make any

alteration in, or additions to or omissions from the works or any alteration in the

kind or quality of the materials to be used therein, the Architect / Consultant shall

give notice thereof in writing to the contractor or shall confirm in writing within

seven days of giving such oral instructions the contractor shall alter to, add to, or

omit from as the case may be in accordance with such notice, but the contractor

shall not do any work extra to or make any alterations or additions to or

omissions from the works or any deviation from any of the provisions of the

contract, stipulations, specifications or contract drawings without previous

consent in writing of the Architect / Consultant and the value of such extras,

alterations, additions or omissions shall in all cases be determined by the

Architect / Consultant and the same shall be added to or deducted from the

contract value, as the case may be.

• Valuation of Variations

No claim for an extra shall be allowed unless it shall have been executed under

the authority of the Architect / Consultant with the concurrence of the SBI as

herein mentioned. Any such extra is herein referred to as authorised extra and shall be made in accordance with the following provisions.

a) i) The net rates or prices in the contract shall determine the valuation of he

extra work where such extra work is of similar character and executed under similar conditions as the work priced herein.

• Rates for all items, wherever possible should be derived out of the rates given in the

priced BOQ.

b) The net prices of the original tender shall determine the value of the items

omitted, provided if omissions do not vary the conditions under which any

remaining items of works are carried out, otherwise the prices for the same shall be valued under sub-clause (c) hereunder.

c) Where the extra works are not of similar character and /or executed under similar

conditions as aforesaid or where the omissions vary the conditions under which

any remaining items or works are carried out, then the contractor shall within 7

days of he receipt of the letter of acceptance inform the Architect / consultant of

Page 23: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

the rate which he intends to charge for such items of work, duly supported by

analysis of the rate or rates claimed and the Architect / Consultant shall fix such

rate or prices as in the circumstances in his opinion reasonable and proper, based on the market, rate.

d) Where extra work cannot be properly measured or valued the contractor shall be

allowed day work prices at the net rates stated in the tender of the BOQ or, if not,

so stated then in accordance with the local day work rates and wages for the

district; provided that in either case, vouchers specifying the daily time (and if

required by the Architect / Consultant) the workman’s name and materials

employed be delivered for verifications to the Architect / consultant at or before the end of the week following that in which the work has been executed.

e) It is further clarified that for all such authorised extra items where rates cannot

be derived from the tender, the Contractor shall submit rates duly supported by

rate analysis worked on the market rate basis” for material, labour, hire / running

charges of equipment and wastage etc. plus 15% towards establishment charges, contractor’s overheads and profit. Such items shall not be eligible for escalation.

• Final Measurement

The final measurement, valuation and payment in respect of the contract shall be

completed within six months of the virtual completion of the work.

• Virtual Completion Certificate (VCC)

On successful completion of entire woks covered by the contract to the full

satisfaction of the Architects / SBI/ SBIIMS, the contractor shall ensure that the

following works have been completed to the satisfaction of the Architects / SBI/

SBIIMS.

• Clear the site of all scaffolding, wiring, pipes, surplus materials, contractor’s labour,

equipment and machinery.

• Demolish, dismantle and remove the contractor’s site office, temporary works,

structures including labour sheds/camps and constructions and other items and

things whatsoever brought upon or erected at the site or any land allotted to the

contractor by the SBI and not incorporated in the permanent works.

• Remove all rubbish, debris etc. from the site and the land allotted to the contractor

by the SBI and shall clear, level and dress, compact the site as required by the SBI.

• Shall put the SBI in undisputed custody and possession of the site and all land

allotted by the SBI.

• Shall hand over the work in a peaceful manner to the SBI.

• All defects / imperfections have been attended and rectified as pointed out by the

SBI/ SBIIMS to the full satisfaction of SBI/ SBIIMS.

Upon the satisfactory fulfillment by the contractor as stated above, the contractor

shall be entitled to apply to the Architect / consultant is satisfied of the

completion of the work. Relative to which the completion certificate has been

sought, the Architect / consultant shall within fourteen (14) days of the receipt of

the application for virtual completion certificate, issue a VCC in respect of the

work for which the VCC has been applied.

This issuance of a VCC shall be without prejudice to the SBI’s rights and

contractor’s liabilities under the contract including the contractor’s liability for

defects liability period nor shall the issuance of VCC in respect of the works or

work at any site be construed as a waiver of any right or claim of the SBI against

the contractor in respect of works or work at the site and in respect of which the

VCC has been issued.

• Work by other Agencies The SBI / Architect / Consultant reserves the rights to use premises and any

portion of the site for execution of any work not included in the scope of this

Page 24: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

contract which it may desire to have carried out by other persons simultaneously

and the contractor shall not only allow but also extend reasonable facilities for the

execution of such work, the contractor, however, shall not be required to provided

any plant or material for the execution of such work except by special

arrangement with the SBI/ SBIIMS. Such work shall be carried out in such

manner as not to impede the progress of the works included in the contract.

• Insurance of Works

26.1 Without limiting his obligations and responsibilities under the contract, the

contractor shall insure in the joint names of the SBI and the contractor against all

loss of damages from whatever cause arising other than the excepted risks, for

which he is responsible under the terms of contract and in such a manner that

the SBI and contractor are covered for the period stipulated in clause 28 of GCC

and are also covered during the period of maintenance for loss or damage arising

from a cause, occurring prior to the period of maintenance for loss or damage

arising from a cause, occurring prior to the commencement of the period of

maintenance and for any loss or damage occasioned by the contractor in the

course of any operations carried out by him for the purpose of complying with his

obligations under clause.

a) The works for the time being executed to the estimated current Contract value

thereof, or such additional sum as may be specified together with the materials

for incorporation in the works at their replacement value.

b) The constructional plant and other things brought on to the site by the contractor

to the replacement value of such constructional plant and other things.

c) Such insurance shall be effected with an insurer and in terms approved by the SBI

which approval shall not be unreasonably withheld and the contractor shall

whenever required produce to the Architect / consultant the policy if insurance

and the receipts for payment of the current premiums.

26.2 Damage to Persons and Property

The contractor shall, except if and so far as the contract provides otherwise

indemnify the SBI/ SBIIMS against all losses and claims in respect of injuries or

damages to any person or material or physical damage to any property

whatsoever which may arise out of or in consequence of the execution and

maintenance of he works and against all claims proceedings, damages, costs,

charges and expenses whatsoever in respect of or in relation thereto except any compensation of damages for or with respect to:

• The permanent use or occupation of land by or any part thereof.

• The right of SBI/ SBIIMS to execute the works or any part thereof on, over, under, in

or through any lands.

• Injuries or damages to persons or properties which are unavoidable result of the

execution or maintenance of the works in accordance with the contract.

• Injuries or damage to persons or property resulting from any act or neglect of the

SBI their agents, employees or other contractors not being employed by the

contractor or for or in respect of any claims, proceedings, damages, costs, charges

and expenses in respect thereof or in relation thereto or where the injury or damage

was contributed to by the contractor, his servants or agents such part of the

compensation as may be just and equitable having regard to the extent of the

responsibility of the SBI/ SBIIMS, their employees, or agents or other employees, or agents or other contractors for the damage or injury.

26.3 Contractor to Indemnify SBI

The contractor shall indemify the SBI/ SBIIMS against all claims, proceedings,

damages, costs, charges and expenses in respect of the matters referred to in the

matters referred to in the provision sub-clause 26.2 of this clause.

Page 25: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

• Contractor’s Superintendence

The contractor shall fully indemnify and keep indemnified the SBI/ SBIIMS

against any action, claim, or proceeding relating to infringement or use of any

patent or design or any alleged patent or design rights and shall pay any royalties

which may be payable in respect of any article or part thereof included in the

contract. In the event of any claim made under or action brought against SBI/

SBIIMS in respect of such matters as aforesaid the contractor shall be

immediately notified thereof and the contractor shall be at liberty, at his own

expenses to settle any dispute or to conduct any litigation that may arise there

from, provided that the contractor shall not be liable to indemnify the SBI/

SBIIMS if the infringement of the patent or design or any alleged patent or design

right is the direct result of an order passed by the Architect / Consultant in this

behalf.

• Third Party Insurance

• Before commencing the execution of the work the contractor but without limiting his

obligations and responsibilities under clause 26.0 of GCC shall insure against his

liability for any material or physical damage, loss or injury which may occur to any

property including that of SBI/ SBIIMS, or to any person, including any employee of

the SBI/ SBIIMS, by or arising out of the execution of the works or in the carrying

out of the contract, otherwise than due to the mattes referred to in the provision to

clause 26.0 thereof.

• Minimum amount of Third Party Insurance

Such insurance shall be affected with an insurer and in terms approved by the

SBI/ SBIIMS which approval shall not be reasonably withheld and for at least the

amount stated below. The contractor shall, whenever required. Produce of the

Architect / consultant the policy or policies of insurance cover and receipts for

payment of the current premiums.

• The minimum insurance cover for physical property, injury, and death is Rs. 5 lacs

per occurrence with the number of occurrences limited to four. After each occurrence

contractor will pay additional premium necessary to make insurance valid for four

occurrences always.

• Accident or Injury to Workman

The SBI / SBIIMS shall not be liable for or in respect of any damages or

compensation payable at law in respect or in consequence of any accident or

injury to any workmen or other person in the employment of the contractor or

any sub-contractor, save and except an accident or injury resulting from any act

or default of the SBI / SBIIMS or their agents, or employees. The contractor shall

indemnify and keep indemnified SBI / SBIIMS against all such damages and

compensation, save and except as aforesaid, and against all claims, proceedings,

costs, charges and expenses whatsoever in respect thereof or in relation thereto.

• Insurance against Accidents etc. to Workmen

The contractor shall insure against such liability with an insurer approved by the

SBI/ SBIIMS during the whole of the time that any persons are employed by him

on the works and shall, when required, produce to the architect / consultant such

policy of insurance and receipt for payment of the current premium. Provided

always a that, in respect of any persons employed by any sub-contractor the

contractor’s obligation to insure as aforesaid under this sub-clause shall be

satisfied if the sub contractor shall be insured against the liability in respect of

such persons in such manner that SBI/ SBIIMS in indemnified under the policy

but the contractor shall require such sub-contractor to produce to the Architect /

Consultant when such policy of insurance and the receipt for the payment of the

current premium.

Page 26: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

• Remedy on Contractor’s failure to Insure: If the contractor fails to effect and keep in force the insurance referred to above

or any other insurance which he may be required to effect under the terms of

contract, then and in any such case the SBI/ SBIIMS may effect and keep in force

any such insurance and pay such premium or premiums as may be necessary for

that purpose and from time to time deduct the amount so paid by the SBI as

aforesaid from any amount due or which may become due to the contractor, or

recover the same as debt from the contractor.

Without prejudice to the others rights of the SBI/ SBIIMS against contractors. In

respect of such default, the employer shall be entitled to deduct from any sums

payable to the contractor the amount of any damages costs, charges, and other

expenses paid by the SBI/ SBIIMS and which are payable by the contractors

under this clause. The contractor shall upon settlement by the insurer of any

claim made against the insurer pursuant to a policy taken under this clause,

proceed with due diligence to rebuild or repair the works destroyed or damaged.

In this event all the monies received from the insurer in respect of such damage

shall be paid to the contractor and the contractor shall not be entitled to any

further payment in respect of the expenditure incurred for rebuilding or repairing

of the materials or goods destroyed or damaged.

• Commencement of Works:

The date of commencement of the work will be reckoned as the date of handing

over site or three days from the date of issue of letter of acceptance of the tender

by the SBI which ever is later.

• Time for Completion

Time is essence of the contract and shall be strictly observed by the contractor.

The entire work shall be completed within a period of 25 Days from the date of

commencement. If required in the contract or as directed by the Architect /

Consultant. The contractor shall complete certain portions of work before

completion of the entire work. However the completion date shall be reckoned as

the date by which the whole work is completed as per the terms of the contract.

• Extension of Time

If, in the opinion of the Architect/consultant, the work be delayed for reasons

beyond the control of the contractor, the Architect/consultant may submit a

recommendation to the SBI/ SBIIMS to grant a fair and reasonable extension of

time for completion of work as per the terms of contract. If the contractor needs

an extension of time for the completion of work or if the completion of work is

likely to be delayed for any reasons beyond the due date of completion as

stipulated in the contract, the contractor shall apply to the SBI/ SBIIMS through

the Architect / Consultant in writing in detail and his justification if any, for the

delays. The Architect/Consultant shall submit their recommendations to the SBI

in the prescribed format for granting extension of time. While granting extension

of time the contractor shall be informed the period-extended time which will

qualify for levy of liquidated damages. For he balance period in excess of original

stipulated period and duly sanctioned extension of time by the SBI/ SBIIMS the

provision of liquidated damages as stated under clause10.0 of Instructions to the

Tenderers shall become applicable. Further the contract shall remain in force even

for the period beyond the due date of completion irrespective whether the

extension is granted or not.

• Rate of Progress

Whole of the materials, plant and labour to be provided by the contractor and the

mode, manner and speed of execution and maintenance of the works are to be of

a kind and conducted in a manner to the satisfaction of the Architect / Consultant

should the rate of progress of the work or any part thereof be at any time be in

Page 27: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

the opinion of the Architect / consultant too slow to ensure the completion of the

whole of the work by the prescribed time or extended time for completion the

Architect / Consultant to expedite progress so as to complete the works by the

prescribed time or extended time. Such communications from the Architect /

Consultant neither shall relieve the contractor from fulfilling obligations under the

contract nor will he be entitled to raise any claims arising out of such directions.

• Work during Nights and Holidays

Subject to any provision to the contrary contained in the contract no permanent

work shall save as herein provided be carried on during the night or on holidays

without the permission in writing of the Architect / Consultant, save when the

work is unavoidable or absolutely necessary for the saving of life or property or

for the safety of the work in which case the contractor shall immediately advise

the Architect / consultant. However the provisions of the clause shall not be

applicable in the case of any work which becomes essential to carry by rotary or

double shifts in order to achieve the progress and quality of the part of the works

being technically required / continued with the prior approval of the Architect /

Consultant at no extra cost to the SBI/ SBIIMS.

All work at night after obtaining approval from competent authorities shall be

carried out without unreasonable noise and disturbance.

• No Compensation or Restriction of Work.

If at any time after acceptance of the SBI/ SBIIMS shall decide to abandon or

reduce the scope of work for any reason whatsoever and hence not required the

whole or any part of the work to be carried out. The Architect / Consultant shall

give notice in writing to that effect to the contractor and the contractor shall act

accordingly. In the matter. The contractor shall have no claim to any payment of

compensation or otherwise whatsoever, on account of any profit or advantage

which he might have derived from the execution of the work fully but which he

did not derive in consequence of the foreclosure of the whole or part of the work.

Provided that the contractor shall be paid the charges on the cartage only of

materials actually and bonafide brought to the site of the work by the contractor

and rendered surplus

as a result of the abandonment, curtailment of the work or any portion thereof

and then taken back by the contractor, provided however that the Architect /

consultant shall have in such cases the option of taking over all or any such

materials at their purchase price or a local current rate whichever is less.

“In case of such stores having been issued for SBI/ SBIIMS stores and returned

by the contractor to stores, credit shall be given to him at the rates not exceeding

those at which were originally issued to the contractor after taking into

consideration and deduction for claims on account of any deterioration or damage

while in the custody of the contractor and in this respect the decision of Architect

/ consultant shall be final.

• Suspension of Work

• The contractor shall, on receipt of the order in writing of the Architect / consultant

(whose decision shall be final and binding on the contractor) suspend the progress of

works or any part thereof for such time and in such manner as Architect / consultant

may consider necessary so as not to cause any damage or injury to the work already

done or endanger the safety thereof for any of following reasons.

a) One account any default on the part of the contractor, or

• for proper execution of the works or part thereof for reasons other then the default of

the contractor, or for safety of the works or part thereof.

Page 28: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

• The contractor shall, during such suspension, properly protect and secure the works

to the extent necessary and carry out the instructions given in that behalf by the

Architect / consultant.

ii) If the suspension is ordered for reasons (b) and (c) sub-para (i) above: the

contractor shall be entitled to an extension of time equal to the period of every

such suspension. No compensation whatsoever shall be paid on this account.

34.0 Action when the whole Security Deposit is forfeited

In any case in which under any clause or clauses of this contract, the Contractor

shall have rendered himself liable to pay compensation amounting to the whole of

his security deposit the Architect / consultant shall have the power to adopt any

of the following course as they may deem best suited to the interest of the SBI/

SBIIMS.

a) To rescind the contract (of which rescission notice in writing to the contractor by

the Architect / consultant shall be conclusive evidence) and in which case the

security deposit of the contractor shall be forfeited and be absolutely at the

disposal of SBI/ SBIIMS.

b) To employ labour paid by the SBI and to supply materials to carry out the work,

or any part of the work, debiting the contractor with the cost of the labour and

materials (the cost of such labour and materials as worked out by the Architect

/Consultant shall be final and conclusive against the contractor) and crediting him

with the value of the work done, in all respects in the same manner and at the

same manner and at the same rates as if it had been carried out by the

contractor under the terms of this contract the certificate of Architect / Consultant

as to the value of work done shall be final and conclusive against the contractor.

c) To measure up the work of the contractor, and to take such part thereof as shall

be unexecuted, out of his hands, to give it to another contractor to complete in

which case any expenses which may be incurred in excess of the sum which

would have been paid to the original contractor, if the whole work had been

executed by him (of the amount of which excess the certificates in writing of the

Architects / Consultant shall be final and conclusive) shall be borne by original

contractor and may be deducted from any money due to him by SBI/SBIIMS

under the contract or otherwise, or from his security deposit or the proceeds of

safe thereof, or sufficient part thereof. In the event of any of above courses being

adopted by the SBI/ SBIIMS the contractor shall have no claim to compensation

for any loss sustained by him by reasons of his having purchased or procured any

material or entered into any engagements or make any advances on account of,

or with a view to the execution of the work or the

performance of the contract and in case the contract shall be rescind under the

provision aforesaid, the contractor shall not be entitled to recover or to be paid

any sum or any work thereto for actually performed under this contract, unless,

and until the Architect / consultant will have certified in writing the performance

of such work and the value payable in respect thereof, and he shall only be

entitled to be paid the value so certified.

35.0 Owner’s Right to Terminate the Contract

If the contractor being an individual or a firm commit any ‘Act of Insolvency’ or

shall be adjusted an insolvent or being an incorporated company shall have an

order for compulsory winding up voluntarily or subject to the supervision of Govt.

and of the Official Assignee of the liquidator in such acts of insolvency or winding

up shall be unable within seven days after notice to him to do so, to show to the

reasonable satisfaction of the Architect / Consultant the at he is able to carry out

and fulfil the contract, and to give security therefore if so required by the

Architect / consultant.

Page 29: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

Or if the contractor (whether an individual firm or incorporated Company) shall

suffer execution to be issued or shall suffer any payment under this contract to be

attached by or on behalf of any of the creditors of the contractor.

Or shall assign or sublet this contract without the consent in writing of the SBI/

SBIIMS through the Architect / consultant or shall charge or encumber this

contract or any payment due to which may become due to the contractor

thereunder:

a) Has abandoned the contract; or

• Has failed to commence the works, or has without any lawful excuse under these

conditions suspended the progress of the works for days after receiving from the SBI

through the Architect / Consultant written notice to proceed, or

• Has failed to proceed with the works with such diligence and failed to make such due

progress as would enable the works to be completed with in the time agreed upon, or

has failed to remove the materials from the site or to pull down and replace work

within seven days after written notice from the SBI/ SBIIMS through the Architect/

Consultant that the said materials were condemned and rejected by the Architect/

Consultant under these conditions; or has neglected or failed persistently to observe

and perform all or any the acts, matters or things by this contract to be observed and

performed by the contractor for seven days after written notice shall have been given

to the contractor to observe or perform the same or has to he determent of good

workmanship or indefiance of the SBI’s or Architect’s/ Consultant’s instructions to the

contrary subject any part of the contract. Then and in any of said cases the SBI/

SBIIMS and or the Architect / Consultant, may not withstanding any previous waiver,

after giving seven days notice in writing to the contractor, determine the contract,

but without thereby affecting the powers of the SBI or the Architect / Consultant or

the obligation and liabilities of the contractor the whole of which shall continue in

force as fully as if the contract had not been so determined and as if the works

subsequently had been executed by or on behalf of the contractor. And further the

SBI/ SBIIMS through the Architect / consultant their agents or employees may enter

upon and take possession of he work and all plants, tools, scaffoldings, materials,

sheds, machineries lying upon the premises or on he adjoining lands or roads use the

same by means of their own employees or workmen in carrying on and completing

the work or by engaging any other contractors or persons to complete the work and

the contractor shall not in any was interrupt or do any act, matter or thing to prevent

or hinder such other contractor or other persons employed for completing and

finishing or using the materials and plant for the works.

When the works shall be completed or as soon thereafter as convenient the SBI

or the architect / consultant shall give a notice in writing to the contractor to

remove his surplus materials and plants and should the contractor fail to do so

within 14 days after receipt thereof by him the SBI/ SBIIMS sell the same by

public auction after due publication, and shall adjust the amount realised by such

auction. The contractor shall have no right to question any of the act of the SBI/

SBIIMS incidental to the sale of the materials etc.

• Certificate of Payment

The contractor shall be entitle under the certificates to be issued by the Architect

/ Consultant to the contractor within 14 working days from the date of certificate

to the payment from SBI/ SBIIMS from time to time. The SBI/ SBIIMS shall

recover the statutory recoveries towards Income tax, Work contract tax as per

the prevailing bye laws and other dues including the retention amount from the certificate of payment.

Provided always that the issue of any certificate by the Architect/ Consultant

during he progress of works or completion shall not have effect as certificate of

satisfaction or relieve the contractor from his liability under clause.

Page 30: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

The Architect/ Consultant shall have power to with hold the certificate if the work or any part thereof is not carried out to their satisfaction.

The Architect/ Consultant may by any certificate make any corrections required in previous certificate.

The SBI/ SBIIMS shall modify the certificate of payment as issued by the

Architect/ Consultant from time to time while making the payment.

The contractor shall submit interim bills only after taking actual measurements and property recorded in the measurement books

The contractor shall not submit interim bills when the approximate value of work

done by him is less than Rs.12 lacs and the minimum interval between two such bills shall be 15 days.

The final bill may be submitted by contractor within a period of one month from

the date of virtual completion and Architect/ Consultant shall issue the certificate

of payment within a period of two months. The SBI shall pay the amount within a

period of three months from the date of issue of certificate provided there is no dispute in respect of rates and quantities.

The contractor shall submit the interim bills in the prescribed format with all

details.

37.0 Settlement of Disputes and Arbitration

Except where otherwise provided in the contract all questions and disputes

relating to the meaning of the specifications, design, drawings and instructions

herein before mentioned and as to the quality of workmanship or materials used

on the work or as to any other question, claim, right, matter or thing whatsoever

in any way arising out of or relating to the contract, designs, drawings,

specifications, estimates, instructions, orders or those conditions or otherwise

concerning the work or the execution or failure to execute the same whether

arising during the progress of the work or after the cancellation, termination, completion or abandonment thereof shall be dealt with as mentioned hereinafter.

• If the contractor considers that he is entitled to any extra payment or compensation

in respect of the works over and above the amounts admitted as payable by the

Architect or in case the contractor wants to dispute the validity of any deductions or

recoveries made or proposed to be made from the contract or raise any dispute, the

contractor shall forthwith give notice in writing of his claim, or dispute to the Vice

President (Civil), SBI Infra Management Solutions Pvt. Ltd., 5th Floor, D-

Block, 11, Parliament Street, New Delhi- 110001 and endorse a copy of the

same to the Architect, within 30 days from the date of disallowance thereof or the

date of deduction or recovery. The said notice shall give full particulars of the claim,

grounds on which it is based and detailed calculations of the amount claimed and the

contractor shall not be entitled to raise any claim nor shall the Bank be in any way

liable in respect of any claim by the contractor unless notice of such claim shall have

been given by the contractor to the Vice President (Civil), SBI Infra

Management Solutions Pvt. Ltd., 5th Floor, D- Block, 11, Parliament Street,

New Delhi- 110001 in the manner and within the time as aforesaid. The contractor

shall be deemed to have waived and extinguished all his rights in respect of any

claim not notified to the Vice President (Civil), SBI Infra Management

Solutions Pvt. Ltd., 5th Floor, D- Block, 11, Parliament Street, New Delhi- 110001 in writing in the manner and within the time aforesaid.

• Vice President (Civil), SBI Infra Management Solutions Pvt. Ltd., 5th Floor,

D- Block, 11, Parliament Street, New Delhi- 110001 shall give his decision in

writing on the claims notified by the contractor. The contractor may within 30 days

of the receipt of the decision of the Vice President (Civil), SBI Infra

Management Solutions Pvt. Ltd., 5th Floor, D- Block, 11, Parliament Street,

New Delhi- 110001 submit his claims to the conciliating authority namely the

Page 31: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

Circle Development Officer, SBI, New Delhi for conciliation along with all details and copies of correspondence exchanged between him and the Regional Manager.

• If the conciliation proceedings are terminated without settlement of the disputes,

the contractor shall, within a period of 30 days of termination thereof shall give a

notice to the concerned Chief General Manager of the Bank for appointment of

an arbitrator to adjudicate the notified claims failing which the claims of the contractor shall be deemed to have been considered absolutely barred and walved.

• Except where the decision has become final, binding and conclusive in terms of the

contract, all disputes or differences arising out of the notified claims of the

differences arising out of the notified claims of the contractor as aforesaid and all

claims of the Bank shall be referred for adjudication through arbitration by the Sole

Arbitrator appointed by the Chief General Manager of the Bank, It will also be

the objection to any such appointment that the Arbitrator so appointed is a Bank

Officer and that he had to deal with the matters to which the Contract relates in the

course of his duties as Bank Officer. If the arbitrator so appointed is unable or

unwilling to act or resigns his appointment or vacates his office due to any reason

whatsoever another sole arbitrator shall be appointed in the manner aforesaid by

the Chief General Manager of the Bank, Such person shall be entitled to proceed with the reference from the stage at which it was left by his predecessor.

It is a term of this contract that the party invoking arbitration shall give a list of

disputes with amounts claimed in respect of each dispute alongwith the notice

for appointment of arbitrator.

It is also a term of this contract that no person other than a person appointed by

Chief General Manager of the Bank, as aforesaid should act as arbitrator.

The conciliation and arbitration shall be conducted in accordance with the

provisions of the Arbitration & Conciliation Act 1996 or any statutory modification

or re-enactment thereof and the rules made there under.

It is also a term of the contract that if any fees are payable to the arbitrator

these shall be paid equally by both the parties. However, no fees will be payable

to the arbitrator if he is a Bank Officer.

It is also a term of the contract that the arbitrator shall be deemed to have

entered on the reference on the date he issues notice to both the parties calling

them to submit their statement of claims and counter statement of claims. The

venue of the arbitration shall be such place as may be fixed by the arbitrator in

his sole discretion. The fees, if any, of the arbitrator shall, if required to be paid

before the award is made and published, be paid half and half by each of the

parties. The cost of the reference and of the award (including the fees, if any of

the arbitrator) shall be in the discretion of the arbitrator who may direct to any

by whom and in what manner, such costs or any part thereof, shall be paid and fix or settle the amount of costs to be so paid.

38.0 Water Supply

The contractor shall make his own arrangements for water required for the work

and nothing extra will be paid for the same. This will be subject to the following conditions.

That the water used by the contractor shall be fit for construction purposes to the satisfaction of the Architect / Consultant.

The contractor shall make alternative arrangements for the supply of water if the

arrangement made by the contractor for procurement of water in the opinion of the Architect/ Consultant is unsatisfactory.

The contractor shall construct temporary well / tube well in SBI land for taking

water for construction purposes only after obtaining permission in writing from

the SBI. The contractor has to make his own arrangement for drawing and

Page 32: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

distributing the water at his own cost. He has to make necessary arrangements.

To avoid any accidents or damages caused due to construction and subsequent

maintenance of the wells. He has to obtain necessary approvals from local

authorities, if required, at his own cost. He shall restore the ground to its original

conditions after wells are dismantled on completion of work or hand over the well

to the SBI without any compensation as directed by the SBIIMS/ Architect/

Consultant.

39.0 Power Supply

The contractor shall make his own arrangements for power and supply /

distribution system for driving plant or machinery for the work and for lighting

purpose at his own cost. The cost of running and maintenance of the plants are to

included in his tender prices. He shall pay all fees and charges required for the

power supply and include the same in his tendered rates and hold the owner free

from all such costs. He has to obtain necessary approval from the appropriate

authorities, if required.

40.0 Treasure Trove etc.

Any treasure trove, coin or object antique which may be found on the site shall be

the property of SBI and shall be handed over to Bank immediately.

41.0 Method of Measurement

Unless otherwise mentioned in the schedule of quantities or in mode of

measurement, the measurement will be on the net quantities or work produced in

accordance with up to date. Rules laid down by the Bureau of Indian Standards.

In the event any dispute / disagreement the decision of the Architect / consultant

shall be final and binding on the contractor.

42.0 Maintenance of Registers

The contractor shall maintain the following registers as per the enclosed Performa

at site of work and should produce the same for inspection of SBI/ SBIIMS/

Architect/ Consultant whenever desired by them. The contractor shall also

maintain the records / registers as required by the local authorities / Govt. form

time to time.

i) Register for Cement / Paint / Lead / Specific Materials

ii) Register for Steel

iii) Register for Secured Advance

iv) Register for Bulkage of Sand

v) Register for Silt Test

vi) Register for Sieve Analysis for Fine Aggregate

vii) Register for Sieve Analysis for Course Aggregate

viii) Register for Slump Test.

ix) Register for Concrete Cube Test.

x) Register for Hindrance to Work.

xi) Register for Consumption of Cement

xii) Register for Running Account Bill

xiii) Register for Labour

43.0 Force Majeure

43.1 Neither contractor nor SBI/ SBIIMS shall be considered in default in performance

of their obligations if such performance is prevented or delayed by event such as

but not to war, hostilities revolution, riots, civil commotion, strikes, lockout,

conflagrations, epidemics, accidents, fire, storms, floods, droughts, earthquakes

or ordinances or any act of god or for any other cause beyond the reasonable

control of the party affected or prevented or delayed. However a notice is

required to be given within 30 days from the happening of the even with

Page 33: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

complete details, to the other party to the contract, if it is not possible to serve a

notice, within the shortest possible period without delay.

43.2 As soon as the cause of force majeure has been removed the party whose ability

to perform its obligations has been affected, shall notify the other such cessation

and the actual delay incurred in such affected activity adducing necessary

evidence in support thereof.

43.3 From the date of occurrence of a case of force majeure obligations of the party

affected shall be suspended during the continuance of any inability so caused.

With the cause itself and inability resulting there from having been removed, the

agreed time of completion of the respective obligations under this agreement

shall stand extended by a period equal to the period of delay occasioned by such

events.

• Should one or both parties be prevented from fulfilling the contractual obligations by

a state of force majeure lasting to a period of 6 months or more the two parties

shall each other to decide regarding the future execution of this Agreement.

44.0 Local Laws, Acts, Regulations:

The contractor shall strictly adhere to all prevailing labour laws inclusive of

contract labour (regulation and abolition act of 1970) and other safety

regulations. the contractor shall comply with the provision of all labour legislation

including the latest requirements of all the Acts, laws, any other regulations that

are applicable to the execution of the project.

• Minimum wages Act 1948 (Amended)

• Payment of wages Act 1936 (Amended)

• Workmen’s compensation Act 1923 (Amended)

• Contact labour regulation and abolition act 1970 and central rules 1971 (Amended)

• Apprentice act 1961 (Amended)

• Industrial employed (standing order) Act 1946 (Amended)

• Personal injuries (Compensation insurance) act 1963 and any other modifications

• Employees’ provided fund and miscellaneous provisions Act 1952 and amendment

thereof.

• Shop and establishment act

• Any other act or enactment relating thereto and rules framed there under from time

to time.

45.0 Accidents

The contractor shall immediately on occurrence of any accident at or about the

site or in connection with the execution of the work report such accident to the

Architect / consultant. The contractor shall also such report immediately to the

competent authority whenever such report is required to be lodged by the law

and take appropriate actions thereof.

Signature of Contractor & Seal

SPECIAL CONDITIONS OF CONTRACT

Page 34: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

• Scope of Work

The scope of work is to carry out Interior Furnishing & Furniture Works at

State Bank of India, Dwarka Branch, Sector-12 B, Dwarka,New Delhi.

• Address of Site

The site is located at State Bank of India, Dwarka Branch, Sector-12 B,

Dwarka, New Delhi.

• Dimension and Levels

All dimensions and levels shown on the drawing shall be verified by the contractor

on the site and he will be held responsible for the accuracy and maintenance of

the entire dimension and the levels. Figured dimensions are in all cases to be

accepted and no dimension shall be scaled. Large-scale details shall take

precedence over small – scale drawing. In case of discrepancy the contractor shall

ask for clarification from the Architect / Consultant before proceeding with the

work.

• Notice of Operation

The contractor shall not carryout any important operation without the consent in

writing from the Architect / Consultant.

• Construction Records

The contractor shall keep and provide to the Architect / Consultant full and

accurate records of the dimension and positions of all new work and any other

information necessary to prepare complete drawings recording details of the work

as constructed.

• Safety of adjacent Structures and Trees

The contractor shall provide and erect to the approval of the Architect /

Consultant such supports as may be required to protect effectively all structures

and protective guards to trees which may be endangered by the execution of the

works or otherwise take such permanent measures as may be required by the

Architect to protect the trees and structures.

• Temporary Works

Before any temporary works are commenced, the contractor shall submit at least

7 days in advance to the architect / consultant for approval complete drawings of

all temporary works he may require for the execution of the works. The

contractor shall carry out the modifications relating to strength, if required by the

Architect/ Consultant may require in accordance with the conditions of contract at

his own cost. The contractor shall be solely responsible for the stability and

safety of all temporary works an unfinished works and for the quality of the

permanent works resulting from the arrangement eventually adopted for their

execution.

• Temporary Roads

The contractor shall provide access roads to the site from the nearest main road

at no extra cost and as directed by the Architect/ Consultant. The contractor

shall also responsible for proper maintenance of this access road and would take

all care to see that existing services, if any, are maintained in working order at

his own cost. The laying and maintaining the temporary roads within the site

area shall be the contractor’s responsibility and the contractor shall take such

measures that are necessary and as directed by the Architect/ Consultant.

• Water, Power and Other Facilities

• The rate quoted by the contractor shall include all expenses that are

Page 35: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

required for providing all the water required for the work and the contractor shall

make his own arrangements for the supply of good quality water suitable for the

construction and good quality drinking water for their workers. If necessary, the

contractor has to sink a tube well / open well and bring water by means of tankers at

his own cost for the purpose. The SBI/ SBIIMS will not be liable to pay any charges in

connection with the above.

The rate quoted in the tender shall include the expenses for obtaining and

maintaining power connections and shall pay for the consumption charges.

The contractors for other trades directly appointed by the SBI/ SBIIMS shall be

entitled to take power and water connections from the temporary water and power

supply obtained by the contractor. However, the concerned contractor shall make

their own arrangements to draw the supply and pay directly the actual

consumption charges at mutually agreed rates between them. All municipal

charges for drainage and water connection for construction purposes shall be

borne by the contractor and charges payable for permanent connections, if any,

shall be initially paid by the contractor and the SBI will reimburse the amount on

production of receipts.

• The SBI/ SBIIMS as well as the Architect / Consultant shall give all possible

assistance to the contractors to obtain the requisite.

• Permission from the various authorities, but the responsibility for obtaining the

same in time shall be of the contractor.

• Office Accommodation

• The contractor shall provide and maintain all necessary offices, workshops, stores,

shelters, sanitary facilities, canteens and other temporary structures for themselves in connection

with the work at the site own cost after getting the approval from the architect / consultant.

• All temporary buildings and facilities as mentioned above shall be removed on

completion of the work or at any other earlier date as directed by the architect / consultant.

All the expenses for obtaining statutory approvals and maintenance of the above

facilities as well as running expense shall be borne by the contractor at no extra

cost. It is also the responsibility of the contractor to obtain statuary approvals for

providing the above facilities.

• Facilities for Contractors’ Employees

The contractor shall make his own arrangement for the housing and welfare of his

staff and workmen including adequate drinking water facilities. The contractor

shall also make his arrangements at his own cost for transport where necessary

for his staff and workmen to and from site of work at his own cost.

• Lighting of Works

The contractor shall at all times provide adequate and approved lighting as

required for the proper execution and supervision and inspection of works.

• Fire Fighting Arrangements

• The contractor shall at all times provide suitable arrangements for the fighting at

his own cost. For this purpose he shall provide requisite number of fire extinguishers and

adequate number of buckets, some of which are of be always kept filed with sand and some

with water. These equipments shall be provided at suitable prominent and easily accessible

places and shall be properly maintained.

• Any deficiency in the fire safety or unsafe conditions shall be corrected by the

contractor at his own cost and to the approval of the relevant authorities. The contractor

shall make the following arrangements at his own cost but not limited to the following :

• Proper handling, storage and disposal of combustible materials and waste.

Page 36: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

• Worked operations which can create fire hazards.

• Access for the fire fighting equipments.

• Types, number and location of containers for the removal of surplus materials and

rubbish.

• Type size, number and location of fire extinguishers or other fire fighting

equipment.

• General house keeping.

• Site Order Book.

A site order book shall be maintained at site for the purpose of quick

communication between the Architect/ Consultant. Any communication relating to

the works may be conveyed through Records in the site order book. Such a

communication from one party to the other shall be deemed to have been

adequately served in terms of contract. Each site order book shall have machine

numbered pages in triplicate and shall carefully maintained and preserved by the

contractor and shall be made available to the Architect/ Consultant as and when

demanded. Any instruction which the Architect/ Consultant may like to issue to

the contractor or the contractor may like to bring the Architect/ Consultant may

like to issue to the Contractor or the Contractor may like to bring to the Architect/

Consultant two copies of such instructions shall be taken from the site order book

and one copy will be handed over to the party against proper acknowledgment

and the second copy will be retained for their record.

• Site Meetings

Site meetings will be held to review the progress and quality evaluation. The

contractors shall depute a senior representative alongwith the site representative

staff of approved sub-contractors and suppliers as required to the site meetings

and ensure all follow up actions. Any additional review meetings shall be held if

required by the Architect/ Consultant.

• Disposal of Refuse

The contractor shall cart away all debris, refuse etc. arising from the work from

the site and deposit the same as directed by the Architect/ Consultant at his own

cost. It is the responsibility of the contractor to obtain from the locate authorities

concerned to the effect that all rubbish arising out of contractor’s activities at the

construction site or any other off-site activities borrow pits has been properly

disposed off.

• Contractor to Verify Site Measurement

The contractor shall check and verify all site measurements whenever requested

by other specialists contractors of other sub contractors to enable them to

prepare their own shop drawings and pass on the information with sufficient

promptness as will not in any way delay the works.

• Displaying the Name of the Work

The contractor shall put up a name board of suitable size as directed by the

Architect/ Consultant indicating therein the name of the project and other details

as given by the Architect/ Consultant at his own cost remove the same on

completion of work.

• Bar Bending Schedule

The contractor shall prepare a detailed bar bending schedule for all reinforced

concrete works and got them approved by the Architect/ Consultant well in

advance.

• As Built Drawings

• For the drawing issued to the contractor by the Architect/Consultant. The

Architect / Consultant will issue two sets of drawings to the contractor for the item for which

Page 37: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

some changes have been made. From the approved drawings as instructed by the SBI /

SBIIMS/ Architect / Consultant. The Contractor will make the changes made on these copies

and return these copies to the Architect/ Consultant for their approval. In case any revision

is required or the corrections are not properly marked the Architect/ Consultant will point

out the discrepancies to the contractor. The contractor will have to incorporate these

corrections and /or attend to discrepancies either on the copies as directed by the Architect/

Consultant and resubmit to him for approval. The Architect / Consultant will return one copy

duly approved by him.

• For the drawings prepared by the Contractor, the Contractor will modify the

drawing prepared by him wherever the changes are made by the SBI/ SBIIMS Architect/

Consultant. And submit two copies of such modified drawings to the Architect/ Consultant

for approval. The Architect/ Consultant will return one copy of the approved drawing to the

Contractor.

• Approved Make

The Contractor shall provide all materials form the list of approved makes at his

own cost. The Architect/ Consultant may approve any make / agency within the

approved list as given in the tender after inspection of the sample / mock up.

• Procurement of Materials

The Contractor shall make his own arrangements to procure all the required

materials for the work. All wastage’s and losses in weight shall be to the

contractors account.

• Excise Duty, Taxes, Levies etc.

The contractors shall pay and be responsible for payment of all taxes except GST,

duties, levies, royalties, fees cess, or charges in respect of the works including

but not limited to sales tax, tax on works contract excise duty, and octroi, payable

in respect of materials, equipments plant and other things required for the

contact. All of the aforesaid taxes except GST, duties, levies, fees and charges

shall be to the contractors account and the SBI shall not be required to pay any

additional or extra amount on this account. Variation of taxes, duty fees, levies

etc if any, till completion of work shall be deemed to be included in the quoted in

the quoted rates and no extra amount on this account. Variation of taxes, duties,

fees, levies, etc if any till completion of work shall be deemed to be included in

the quoted rates and no extra claim on this account will in any case be

entertained. If a new tax or duty or levy or cess or royalty or octroi is imposed

under as statue or law during the currency of contract the same shall be borne by

the contractor.

• Acceptance of Tender

The SBI/ SBIIMS shall have the right to reject any or all tenders without

assigning any reason. They are not to bound to accept the lowest or any tender

and the tenderer shall have no right to question the acts of the SBI/ SBIIMS.

However, the adequate transparency would be maintained by the SBI/ SBIIMS.

SPECIFICATIONS OF INTERIOR & FURNISHING WORKS

1. General:

• Without forgoing the requirements of the Conditions of Tender and the Conditions of

Contract the works in general shall confirm to the “Latest Specifications” published by

CPWD, New Delhi and the “Specifications for Works” stated in this tender. In case of

items not covered by the General Specifications referred above, reference shall be

made to the appropriate I.S. Code. If there is any difference in the particular

specifications of individual item of work and the description of item as given in the

Schedule of Quantity, the latter shall prevail. In case of any work for which there is

no specification in I.S. Specifications or in the specifications forming part of tender

Page 38: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

documents or in case there is any variation, such work shall be carried out in all

respects in accordance with the instructions to be issued by the Architects. The term

Department shall mean the Employer. Any reference to ISI shall also mean reference

to its successor Bureau of Indian Standards. All corrections to “Latest Specifications”

or revisions of I. S. shall be deemed to apply to this contract.

• Materials bearing ISI certification mark shall be given highest preference for use in

the works.

• Where the Contractor is required to do, perform, execute (etc.) any work or service

or the like, it shall be deemed to be at his own cost. Absence of terms providing

supplying, installing, fixing, etc. shall not even remotely entitle the Contractor to any

additional payment thereof.

• The rates accepted in the Schedule of Quantities apply to all floors, heights, depths,

leads, lifts, spans, sizes, shapes, locations, etc. unless a distinction has been included

in the very Schedule.

• The Specifications and the Schedules may have been divided into various sub-heads

for convenience only. This does not limit applicability of one to the other nor it

absolves the Contractor of his responsibility to complete any trade/item of work as

reasonably inferred from one or more of such sub-heads.

• The Schedule of Quantities is not necessarily based on “Schedule of Rates – Delhi

2003 or any of its later/earlier versions. Hence the Schedule of Quantities shall be

read and construed according to explanations given herein and intentions gathered

therefrom. A mere parallel drawn from the said Schedule of Rates shall therefore not

form a basis for a variation and, or additional payment.

• All work under this contract is deemed to be performed above subsoil water level.

However, removal of water collected from rains and the like shall be treated as part

of contractual risk/obligation.

• Screws, bolts, nuts, washers, hold fasts, lugs, anchors, clamps, plugs, suspenders,

brackets, straps and fasteners of the like are deemed to be included in the rates of

various items unless the Schedule of Quantities expressed a different intention.

• Resetting any displacements, making good holes/chases and such other incidental jobs are included in rates of respective items for which these are required.

• Concrete Work (Plain or Reinforced):

• Centering, shuttering, staging, form work, strutting, propping (their provision and

removal) shall not be paid for separately unless exclusion thereof is specifically

described in the item.

• The rates of concrete work do not include rendering or plastering but hacking and preparing surface for receiving the finishes shall be done as early as possible.

• Any chamfers, grooves, drips, etc. which are generally and customarily required shall

be provided in the concrete work integrally or otherwise without extra charges as directed by the Architect.

• Steel Work:

3.1 The measurement of railing shall be the length of top wood/steel section as per situation along the centre line.

3.2 Painting in relation to steel work shall be two or more coats of approved synthetic

enamel plus a coat or primer including preparation of surfaces, fillers etc. The

priming coat shall be measured & paid separately in the relevant item.

3.3 Circular work, bends, stepping are not payable extra.

3.4 The steel work in single sections of R.S. Joists, flats, Tees Angles fixed independently with or without connecting plate, is described in these clauses.

(a) Fabrication

The steel section as specified shall be straightened and cut square to correct

lengths and measured with a steel tape. The cut ends exposed to view shall be

finished smooth. No two pieces shall be welded or otherwise jointed to make up

Page 39: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

the required length of a member.

All straightening and shaping to form, shall be done by pressure. Bending or

cutting shall be carried out in such a manner as not to impair the strength of the metal.

(b) Painting

All surfaces which are to be painted, oiled or otherwise treated shall be dry and

thoroughly cleaned to remove all loose rust. Surfaces not in contact but

inaccessible after shop assembly, shall receive the full specified protective

treatment before assembly. This does not apply to the interior of sealed hollow

sections. Part to be encased in concrete shall not be painted or oiled. A priming

coat of approved steel primer i.e. Red Oxide Zinc chrome primer conforming to

IS: 2074 shall be applied before any member of steel structure are placed in position or taken out of workshop.

(c) Welding

Welding shall generally be done by electric arc process as per IS: 816 and IS:

823. The electric arc method is usually adopted and is economical. Where

electricity for public is not available generators shall be arranged by the

contractor at his own cost unless otherwise specified. Gas welding shall only be

resorted to using oxyacetylene flame with specifiic approval of the Engineer-in-

charge. Gas welding shall not be permitted for structural steel work. Gas

welding requires heating of the members to be welded along with the welding rod

and is likely to create temperature stresses in the welded members. Precautions

shall therefore be taken to avoid distortion of the members due to these

temperatures stresses.

The work shall be done as shown in the shop drawings which should clearly

indicate various details of the joints to be welded, type of welds, shop and site

welds as well as the types of electrodes to be used. Symbol for welding on plane and shops drawings shall be according to IS: 813.

As far as possible every efforts shall be made to limit the welding that must be

done after the structure is erected so as to avoid the improper welding that is

likely to be done due to heights and difficult positions on scaffolding etc. apart

from the aspect of economy. The maximum dia of electrodes for welding any

work shall be as per IS: 814 and appendix B' of IS: 823. Joint surfaces which are

to be welded together shall be free from loose mill scale, rust, paint, grease or other foreign matter, which adversely affect the quality of weld and workmanship.

• Flooring:

4.1 The rates of cement concrete flooring and marble chips flooring are exclusive of

dividing strips for formation of panels.

4.2 Borders, margins, bands, nosings, etc. are not payable extra. Treads shall be

measured as floors, risers as skirtings. However, areas of returns (finished thickness), nosing shall be added respective items.

4.3 No extra shall be paid for cutting of glazed tiles or for wastage thereof.

4.4 Marble/Kota stone slabs shall be of selected quality, hard & sound and shall be

approved by the Architects. The thickness of the slabs shall be as specified in the

description of the item. Tolerance of 2mm shall be allowed for the thickness. In

respect of length & breadth of slabs (Where flooring to be laid) a tolerance of

5mm shall be allowed. Every slab shall be cut to the required size and shape, top

waviness shall be removed, the sides (edges) shall be removed, the sides (edges)

shall be table rubbed with coarse sand or machine rubbed before paving. All

angles of the tiles shall be true equal and free from chipping and the surface shall

be true and plane.

4.5 Marble slab/kota slab shall be cleaned, wetted and mopped before laying.

4.6 Polishing shall be done by machine in four different courses. Ist course shall be

of rubbing with carborundum stone No. 60, the second with No. 120, and the

Page 40: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

third with No. 320 to get even and smooth surface with out pinholes. Where ever

use of machine is not feasible to work, polishing shall be done by hand with No.

60, No. 80 and with No. 120 carborundum stone respectively. Lastly oxalic acid

shall be dusted over the surface @ 33 gm per square meter sprinkled with water

and rubbed hard with namdah block (pad of wooden rags).

4.7 Marble chips, kota stone, marble (all floors, skirting, risers, dado, counter tops,

treads) shall finally be polished with approved floor wax polish as directed at no

extra cost.

4.8 Marble (counter tops) shall be of full width and in single piece upto length of

1.5m. Granite for name-plate shall be in one single piece.

• Finishing:

• Items of plastering apply to all locations including rough sides of walls, curved

surfaces, all heights, etc. without limiting generally of para 1.4.

• Preparation of surfaces including raking out joints, hacking, brushing, watering, etc.

is included.

• Drip mouldings shall not be payable extra.

• Grooves shall be provided in plaster as directed by Architect at corners of ceiling

slabs around the columns & beams at no extra cost.

• Strips of G.I. chicken mesh 250mm wide shall be provided in plaster at all junctions

(which are flush) between masonary/columns, masonary/beams.

• Wood Work:

6.1 The areas of doors & windows shutters shall be measured to the nearest cm in

closed position covering the rebates of the frame but excluding the gap between

the shutter and the frame. Over lap of two shutters shall not be measured. All

work shall be measured for finished dimensions. No allowance shall be made for

dimensions supplied beyond those specified. Length of each piece shall be

measured overall nearest to 1 cm, so as to include projections for tenons, scraves

or mitres, width and thickness shall be measured to the nearest mm.

6.2 Where painting, polishing has been included in the item the same shall be

executed as per Architect’s directions. Painting shall be two or more coats of

approved synthetic enamel plus a coat of fire resistant primer to wood work as

approved by Architect and shall conform to BS-476 part 7 for class I surface

spread of flame. Preparations of surfaces, fillars, etc. are included. This primer

shall also be applied before polishing (i.e. French Spirit Polish). The fire resistant

primer shall be measured & paid separately in the relevant item.

6.3 All flush door shutters shall have teak lipping on all edges as directed with extra

thickness of lipping of meeting edges of double shutter doors.

Glasses 5.5mm thick or 4mm thick shall respectively weigh not less than 13.75

Kg/sqm. Or 10 Kg/sqm.

Bends, stepping and circular shapes in railings are integral part of the rate.

The widths of various rails & styles shall be as described in the items or shown in

the drawing. All aluminum section & fittings used shall be ISI marked. All screws for fixing of fittings/fixtures shall be of matching finish.

In case of composite units (M.S. frame + teak wood shutter) the hold fasts shall

be added or fixed with counter sunk machine screws. Also the M.S. frames shall have necessary holes and other arrangement for receiving/fixing of fittings

• Plaster of Paris Punning (P. O. P.)

If the plaster surface is to be finished with plaster of paris punning, the surface

shall be combed slightly with the wire brushes or nails before it is completely set

to form key for plaster of Paris punning. The surface shall be thoroughly cleaned

Page 41: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

of dust then only damped but not soaked before the application of plaster of paris

punning. The Gypsum for preparing punning shall be approved quality. It shall

be dry and free from lumps and shall be suitably packed in watertight bags or

containers. Paste shall be prepared by adding required quantum of water and it

shall be used before it sets. No dropping paste shall be used in the work.

Punning shall be applied to the prepared surface with steel trowel to a thickness

required to make the surface produce perfectly smooth and even surface working

from top to bottom. It shall then be sand papered to give a smooth and even

surface. Any unevenness shall be made good by applying putty, made of plaster

of paris mixed with water, then sand papering the same after it is dry. Pilling in

plaster shall be made good with plaster of paris mixed with colour to be used.

The surface shall then be rubbed down again with a fine grade sand paper and

made smooth. The surface shall be allowed to dry thoroughly before the regular

coat of paint is applied. The measurement shall be in square metre.

• Plastic Emulsion Paint:

Plastic emulsion paint shall be of approved manufacturer and shall generally confirm to IS-5411 (Part-I)-1969.

The colour and shade of the emulsion shall be got approved by the Architect.

Double scaffolding shall be used, ladden if used shall be tied with old gunny bags

at top to prevent damage or scratches to the walls. The instructions of the

manufacturer shall be followed, in application of priming and finishing coats. Turpentine or any other solvent shall not be used for thinning the paint.

Minimum 3 coats of paint shall be applied inclusive of primer coat. If a proper

and even surface is not obtained to the satisfaction of the Architects in 3 coats,

Contract shall carry out additional coats of painting to approval at his expenses.

Care shall be taken that dust or other foreign material does not settle or disfigure the various coats. The measurement shall be in square metre.

• Miscellaneous:

The work of cupboard/cabinets shall be done as per drawings. The depth of

cupboards shall be as shown in drawings. The work includes holdfasts and other

accessories usually required for complete installation. All inner surfaces shall be

painted & outer face polished as per Architects approval.

All exposed cut ends of boards shall be provided with hardwood lippings.

Kail wood to be used shall be of the best available quality.

The joints in cement concrete pavements/roads shall be formed as per design and

pattern. The joints shall be cleaned and neatly filled with ‘A’ grade sealing

compound. Side kerbs shall be made in situ to design and volume paid for in the same item. Required side forms shall not be paid separately.

For whitewashing, colour washing, distempering on sand faced plaster or on

rough cast plaster with stone aggregate upto 10mm, only flat single surface will

be measured and paid.

In the case of R.C.C. Jallies upto 50mm thick only single flat surface will be

considered for each side of painting.

SPECIFICATIONS FOR SERVICES

• General

1.1 The drawings for services are diagrammatic but shall be followed as closely as

actual construction permits. Any deviations from the drawings shall be in

conformity with architectural and structural drawings. The dimensions designated

by the manufacturers shall take precedence over the drawings.

• At completion of work the Contractor shall submit one set of tracings and two sets

of prints of “As-Built-Drawings”. These drawings shall, among others, include invert levels,

Page 42: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

pipe runs, diameters, location of valves, access panels, layout of equipment, piping

connections and such other information for maintenance & future extensions. Guarantees

given by manufacturers shall be assigned to the Employer along with names & addresses of

manufacturers, suppliers and information about spare parts.

• All site test shall be carried out with prior intimation to the Bank Engineer /

Architect. All defects shall be rectified and tests conducted again to the satisfaction of the

Bank Engineer / Architect. In addition to the test required by the specifications, the

Contractor shall also conduct tests required by the Architect and by the Municipal or other

Authorities.

• All work shall be executed by competent and licensed persons. The contractor

shall maintain liaison with Municipal and other controlling Authorities. He shall obtain their

approvals and certificates as required by the bye – laws at appropriate stages.

• No cutting / chasing shall be done in load bearing structural members without

prior approval of the Asstt. Engineer. Sleeves and openings shall be provided during the

progress of construction in preference to cutting at later date.

• The Architect may require typical mock up(s) to be installed in advance for

approval. Undamaged materials from the mock up shall be allowed to be reused in the work.

• Unless otherwise described in the item CI / SCI pipes and fittings shall be a spigot

and socket type.

• G.I. pipe spouts shall be paid as per item of G.I. pipes (internal work). Cutting

and making good is included. The free ends may be skew-cut.

• Wherever use of G.I. pipes is called for the same shall be medium class (class –

B)

• Materials :

2.1 The materials shall conform to the specifications and in absence thereof to Indian

Standards. The products should bear the ISI Mark.

2.2 The makes of materials for use in this work are broadly approved as per list given

below. The Contractor shall, however, get particular makes and samples approved

before ordering:

2.3 Notwithstanding any interim or final approval the Contractor remains responsible

for satisfactory performance of all fittings & fixtures. The liability of the Contractor

is not limited by any approval of the make of materials.

2.4 The item rate of mirror includes extra packing piece of AC plain sheet, where

required due to off set between plaster & glazed tiles surface.

• Testing

• The sand cast iron soil, waste and vent pipes and fittings including joints shall be

tested by pumping smoke into the pipe at the lowest end.

• All G.I pipes and fittings including joints shall be tested to hydraulic pressure of 6 kg

/ cm2 (60 meters) avoiding water hammer. The test pump having been stopped the

test pressure should maintain without loss for at least half an hour. The pipes and

fittings shall be tested in sections as the work of laying proceeds keeping the joints

exposed for inspection during the testing.

• All stone ware pipes shall be tested with water pressure of 1.5m head of water at the

highest point of the section under test.

Page 43: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

TIMBER As per IS 1708-1969

----------------------------------------------------------------------------------------------------

------------------------------------------- Test Required & Procedure Frequency

Acceptance Criteria ----------------------------------------------------------------------------------------------------

-------------------------------------------- 1 2

3 ---------------------------------------------------------------------------------------------------

Page 44: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

---------------------------------------------- 1. Moisture Content and Specific Gravity Test preparation and procedure:

• Measurement and weight: Prior to each test, the dimensions of each test

specimen shall be measured correct to 0.01 cm and the specimen shall be weighed correct

to 0.001 gm.

• Control of moisture content: Before the preparation of the test specimens for

testing in the seasoned condition, the material shall be brought practically to constant

weight by storage under controlled conditions at 27o C + 2o C temperature and 65 + 5%

relative humidity. This is expected to bring the moisture content at 12% but if it is not

exactly 12% it is permitted to test in the neighbourhood of 12% and results shall be

adjusted to 12% moisture content. The test shall be made under such conditions that large

changes in moisture content do not occur.

• Control of temperature: To avoid significant changes in strength properties all test

specimen shall be tested within the temperature range of 27o + 2o C. The temperature

at the time of test shall be recorded.

For every Ten cum or part thereof.

The loss in weight expressed as a percentage of the oven dry weight shall be taken as

the moisture content of the specimen. The formula for calculation shall be as given

below:

Page 45: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

Percentage moisture = WI – WO X 100 content = WO

Wl = Weight of sample at test in gms. WO = Oven dry wt. of sample in gms.

Moisture content shall not exceed following values

• Timber for frames = 14%

• Timber for planking shutters etc. = 12%

----------------------------------------------------------------------------------------------------

------------------------------------------- Test Required & Procedure Frequency

Acceptance Criteria ----------------------------------------------------------------------------------------------------

-------------------------------------------- 1 2

3 ---------------------------------------------------------------------------------------------------

--------------------------------------------- d) Rate of loading: The rate of loading of the rest machine used shall not vary by more

than + 20% from the specified speed for a given test. The load shall be applied

continuously without interruption at the required speed throughout the test. The

approximate percentage of sapwood if any, by volume, is estimated for all the test

specimens and recorded. The number of the growth rings for 3 cm length shall be

counted in the radial direction on each of the cross-section of such piece and the average

shall be recorded as number of rings/cms for each specimen tested.

Immediately after each mechanical test, disc approx. 2.5 cm in length and of full section

as the test piece, shall be taken normally at the place of failure, failing which, at the

central portion of the test specimen. In the case of shear test, the detached portion of

the section approximately 5x5 cm shall be taken for determination of moisture content.

The sample shall be weighed and then dried in an oven at a temperature of 103 + 20 oC.

The weight shall be recorded at regular intervals. The drying shall be considered to be

complete when the variation between last two weighing shall

Page 46: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

VASTU SADAN PVT LTD. Page of 59

Signature & Stamp Of Tenderer WOODEN PANEL DOOR SHUTTERS

Conforming to IS 2202 (Part I) 1983 ----------------------------------------------------------------------------------------------------

------------------------------------------- Test Required & Procedure Frequency

Acceptance Criteria ----------------------------------------------------------------------------------------------------

-------------------------------------------- 1 2

3 ---------------------------------------------------------------------------------------------------

--------------------------------------------- 1. Physical Test

Physical Verification-

Page 47: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

i) Name of the manufacturer or trade mark.

ii) Thickness of door shutter.

iii) Whether ISI Certification Mark exists.

2. Glue Adhesion Test -

Procedure- Two square sections, 150 mm X 150 mm shall be cut from the corners of

the door. These corner sections as out from the door, shall be immersed in boiling water

at 100o C for four hours, then dried at a temperature of 270o + 20o C and relative

humidity of 65 + 5% for 24 hours. At the end of the drying period the samples shall be

examined for de-lamination. Glue lines in all the four exposed edges of the plywood on

both faces of a specimen and the glue lines between the plywood faces and the stile and

rail shall be examined for de-lamination.

One from each lot.

A specimen shall be considered to have passed the test if no de-lamination has occurred

in the glue lines in the plywood and if no single de-lamination. More then 50 mm in

Page 48: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

length and more than 3 mm in depth has occurred in the assembly glue lines between

the plywood faces and the stile and rail.

VASTU SADAN PVT LTD. Page 3 of 59

Signature & Stamp Of Tenderer

READY MIXED PAINTS

----------------------------------------------------------------------------------------------------

------------------------------------------- Test Required & Procedure Frequency

Acceptance Criteria ----------------------------------------------------------------------------------------------------

-------------------------------------------- 1 2

3 ---------------------------------------------------------------------------------------------------

---------------------------------------------

1. Drive Time

Procedure: The material shall be brushed or sprayed as required on a 150 x 150 mm

mild steel panel prepared and allowed to air dry or stored under specified drying

conditions.

The material shall be examined after specified intervals, for the following conditions: i) Surface dry ii) Hard dry iii) Tack free: The procedure of test on the dried film of the panel after specified period

as follows:

Place the panel in one pan of a suitable balance and counterpoise it with weights. Place a

further weight of 2.25 kg and press on the dried film surface of the panel with the thumb

till the two pans are balanced. Hold for one minute and then slowly release. No sign of

stickiness to the thumb shall be apparent and the thumb impression, if produced, shall

be such as can be wiped away with dry cotton wool.

Page 49: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

On test each lot, (All containers of same size and same batch of manufacture constitute a lot)

No sign of stickiness to the thumb shall be apparent.

VASTU SADAN PVT LTD. Page 4 of 59

Signature & Stamp Of Tenderer

Page 50: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

----------------------------------------------------------------------------------------------------

----------------------------------------- Test Required & Procedure Frequency

Acceptance Criteria ----------------------------------------------------------------------------------------------------

-------------------------------------------- 1 2

3 ---------------------------------------------------------------------------------------------------

-------------------------------------------- 2. Consistency- Procedure: Insert a clean metal rod or palette knife into the original container and

examine the nature of the setting.

3. Finish- Procedure: The material, when applied on an mild steel panel by brushing or spraying,

which ever is specified to give a dry film weight commensurate with the weight per 10

litres of the material and allowed to dry in a vertical position under specified conditions,

shall dry to hard, firmly adherent, flexible and smooth film, free from sagging and

wrinkling with a matt, semi-glossy or glossy surface in accordance with the requirement

of the material specification.

4. Residue on Sieve-

Outline: The material is mixed with a suitable solvent and passed through a 63 micron

lS sieve. Not less than 20 gms. of the material taken from under the top skin shall be

tested.

Procedure: Accurately weigh the required quantity of the material and transfer to a 250

ml beaker

using either 20 ml of petroleum hydrocarbon solvent 145/205 (100 aromatic).

Page 51: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

The material shall not be cake hard inside the container and shall be in such a condition

that stirring easily produces a smooth uniform paint suitable for application.

The film produced shall be of normal capacity and in no way inferior to a film prepared in

the same manner and at the same time from the approved sample, when examined not

earlier than 48 hours and not later than 100 hours after application. In case of failure,

the test shall be repeated by keeping the painted panel under standard atmospheric

condition.

VASTU SADAN PVT LTD. Page of 59 Signature & Stamp Of Tenderer

----------------------------------------------------------------------------------------------------

----------------------------------------- Test Required & Procedure Frequency

Acceptance Criteria ----------------------------------------------------------------------------------------------------

-------------------------------------------- 1 2

3 ---------------------------------------------------------------------------------------------------

-------------------------------------------- (Conforming to IS: 1745-1961) or 20 ml of a mixture containing equal parts by volume

of petroleum hydrocarbon solvent and benzene. Wet a 63 micron IS sieve on both sides

with the solvent. Mix the material and the solvent in the beaker thoroughly, breaking up

all lumps without grinding action, with the flattened end of a stirring rod. Transfer the

contents of the beaker to the sieve using awash bottle containing the solvent. Remove

with the camel-hair brush any small particles of pigment that may be retained on the

stirring rod or the walls of the beaker. Wash the residue left on the sieve with the solvent

and gently brush with a camel-hair brush unit the solvent passing through the sieve is

clear and free from solid particles. When the washing is complete, dry the sieve for one

hour at 100 + 2o C. Cool and transfer the residue with the help of the camel-hair brush

to a weighed watch glass and determine the weight of residue.

5. Water Content

Outline of the method: The material is heated under reflex with an organic solvent

which is immiscible with water. The carrier liquid distils into a graduated receiver

carrying with it water which then separates to from the lower layer,

Page 52: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises
Page 53: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

VASTU SADAN PVT LTD. Page 6 of 59

Signature & Stamp Of Tenderer ----------------------------------------------------------------------------------------------------

----------------------------------------- Test Required & Procedure Frequency

Acceptance Criteria ----------------------------------------------------------------------------------------------------

-------------------------------------------- 1 2

3 ---------------------------------------------------------------------------------------------------

-------------------------------------------- the excess carrier liquid overflowing from the trap and returning to the still.

Procedure: Weigh 100 g. of the material in the flask, add 100 ml of dry petroleum

hydrocarbon solvent (boiling point 75 to 85o C) and IMI of dry ethyacetate (conforming

to IS:229-1964) or acetate (conforming to IS:231-1957) and thoroughly mix the

contents of the flask. Pour petroleum hydrocarbon solvent into the receiver upto the

level of the side tube. Attach the flask to Dean and stark condensing and collecting

system and heat the flask at such a rate that the condensate falls from the end of the

condenser at a rate of two to five drops per second. Continue the distillation unit

condensed water is no longer visible in any part of the apparatus except at the bottom of

the graduated tube and until the volume of water collected remains constant. Remove

the persistent ring of condensed water in the rate of distillation by a few drops per

second.

6. Weight per Litre

Outline of the method: The calibrated cylinder or CNP is filled with the material and

weighed.

Page 54: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

VASTU SADAN PVT LTD. Page 47 of 59

Signature & Stamp Of Tenderer ----------------------------------------------------------------------------------------------------

---------------------------------------- Test Required & Procedure Frequency

Acceptance Criteria ----------------------------------------------------------------------------------------------------

-------------------------------------------- 1 2

Page 55: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

3 ---------------------------------------------------------------------------------------------------

-------------------------------------------- Procedure: Weight the cylinder or cup when empty and then fill to the brim with the

material Assuming that the volume of the contents is 50 ml or 100 ml, calculate and

express as kg per 10 litres.

7. Lead Restriction

Outline of the method: Determination of lead in lead restricted paints is carried out by

precipitating the lead as sulphide from the separated pigment, which is finally oxidized to

lead monoxide.

Procedure: Shake about one gram of the ground pigment obtained, accurately weighed,

continuously for one hour at room temperature with 1000 times its weight of an aqueous

solution of hydrochloric acid containing 0.25 percent by weight of hydrogen chloride.

Allow the mixture to stand for one hour and then filter. Precipitate the lead salt contained

in the clear filtrate as lead sulphide, filter, that the lead sulphide in air to convert it into

lead sulphate, weigh calculate as lead monoxide (PbO) and express the result as

percentage on the dry weight of the material taken for test.

Page 56: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

VASTU SADAN PVT LTD. Page 48 of 59

Signature & Stamp Of Tenderer PARTICLE BOARD

----------------------------------------------------------------------------------------------------

----------------------------------------- Test Required & Procedure Frequency

Acceptance Criteria ----------------------------------------------------------------------------------------------------

-------------------------------------------- 1 2

---------------------------------------------------------------------------------------------------

----------------------------------------- Identification (Physical Verification)

Each particle board shall be legibly marked near any of its edge with the following.

1. Name of the manufacturer or trade mark.

2. Designation of particle board.

3. Thickness and date of manufacture.

4. Whether I.S.I. Certification marks exists.

5. Dimensional Tolerace

Page 57: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

a) Length ± 8 mm b) Width ± 8 mm c) Thickness

i) Boards upto and including 25mm thick ± 5.0%]

ii) Boards above 25mm thick ± 2.5%.

Edges of the board shall be straight with a tolerance of 3 mm. the persistent ring of

condensed water in the rate of distillation by a few drops per second.

VASTU SADAN PVT LTD.

One from each lot

Page 49 of

Density – The density of each sample shall not

vary from the mean density by more than + 10%.

Moisture content : The average value of the moisture content shall be between 7 to

16%.

Water absorption : The value of water absorption shall not exceed 25% for two hrs,

soaking and 50% for 20 hrs. soaking.

Page 58: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

Exterior grade (I) : These particle boards shall not delaminate after 3 hrs. boiling in

water at 100'C.

Interior Grade (Gr.II) : These particle boards shall not disintegrate and / or shall not

detaminate after 24 hrs. immersion in water at 27% ± 2’C.

Swelling water : Swelling in thickness in % of original thickness for 2 hrs. immersion

shall be determined and the same shall not be more than 5%. The Swelling in thickness due to surface absorption in two hours shall not be more than

5%.

Signature & Stamp Of Tenderer

SAFETY CODE

• First aid appliances including adequate supply of sterlised dressing and cotton

wool shall be kept in a readily accessible place.

• An injured person shall be taken to a public hospital without loss of time, in cases

where the injury necessitates hospitalization.

• Suitable and strong scaffolds should be provided for workmen for all works that

cannot safely be done from the ground.

• No portable single ladder shall be over 8 meters in length. The width between the

side rails shall not be less than 30 cm (Clear) and the distance between two adjacent rungs

shall not be more than 30 cm. When a ladder is used an extra mazdoor shall be engaged for

holding ladder.

• Every opening in the floor of a building or in a working platform be provided with

suitable means to prevent to fall of persons or materials by providing suitable fencing or

railing whose minimum height shall be one meter.

• No floor, roof or other part of the structure shall be so overloaded with debris or

materials as to render it unsafe.

• Workers employed on mixing and handling material such as asphalt, cement

mortar or concrete and lime mortar shall be provided with protective footwear and rubber

hand-gloves.

• Those engaged in welding works shall be provided with welder’s protective eye-

shields and gloves.

• I) No paint containing leads or lead products shall be used except in the

form of paste or readymade paint.

ii) The workers should supply suitable facemasks for use when the paint is

applied in the form of spray or surface having lead paint dry rubbed and

scrapped.

• Overalls shall be supplied by the contractor to the painters and adequate facilities

shall be provided to enable the working painters to wash during the periods of cessation of

work.

• Hoisting machines and tackle used in the works, including their attachments,

anchorage and supports shall be in perfect condition.

• The ropes used in hoisting or lowering material or as a means of suspension shall

be of durable quality and adequate strength and free from defects.

Page 59: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

PROFORMA FOR RUNNING ACCOUNT BILLS

C E R T I F I C A T E

The measurements on the basis of which the above entries for the Running

Bill_________________

were made have been taken jointly on _________ and are recorded atpages

_________________of

Measurement

BookNo.__________________________________________________________

___.

Date & Signature of Date & Signature of Date &

Signature

Contractor. Architect’s Representative of Site

Engineer

(Seal).

Page 60: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

The work recorded in the above mentioned measurements has been done at the site

satisfactorily as per tender drawings, conditions and specifications.

ARCHITECT SITE ENGINEER / BANK’s

ENGINEER

RUNNING A/C BILL

Name of Contractor/Agency: ________________________ Name of Work: ________________________ Sr. No. of this Bill: ________________________ No. and Date of Previous Bill. ________________________ Reference to Agreement No. ________________________ Date of Written Order to Commence.____________________ Date of Completion as per Agreement.___________________

Sr. No.

Item

descrip

tion

Unit

Rate (Rs.)

As per

Tender

Upto

Previo

us R/A

Bill

Upto

Date

(Gross

)

Presen

t Bill

Remar

ks

Qty. Amt.

(Rs.)

Qty. Amt.

(Rs.)

Qty. Amt.

(Rs.)

Page 61: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

1. 2. 3. 4. 5. 6. 7. 8. 9.

Note: 1. If Part Rate is allowed for any Item, it should be

Net value since Indicated with reasons for allowing such a Rate.

Previous Bill. 2. If Adhoc Payment is made, it should be mentioned specifically.

Date & Signature of Contractor.

PERFORMA OF HINDERANCE REGISTER

Name of Work : Date of State of Work :

Name of Contractor : Period of Completion :

Agreement No : Date of Completion :

Page 62: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

Sr

No

Nature of

Hindrance

Date of

occurrence of

Hindrance

Date of

which Hindrance

was

removed

Period of

Hindrance

Signature

SE / PE

Remarks

1 2 3 4 5 6 7

Page 63: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

SE = Site Engineer

PE = Project Engineer

ACCOUNT OF SECURED ADVANCE, IF ADMISSIBLE ON

MATERIALS HELD AT SITE BY THE CONTRACTOR

Page 64: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

No. Item Quantity Unit Amount Remarks

1 2 3 4 5 6

Total Value of Materials at Site

Secured Advance @………………………% of above Value B

CERTIFIED (I) That the materials mentioned above have actually been brought by the

contractor to the site of the work and no advance on any quantity of any of this item is

outstanding on their security, (ii) that the materials are of imperishable nature and are all

required by the contractor for use in the work in connection with the items for which rates of finished work have been agreed upon.

Dated Signature of

Site Engineer

preparing the Bill

Designation________

Dated Signature of

Bank’s Architects

(Name of the Architects)

___________________________

Dated signature of Contractor

Page 65: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

LIST OF APPROVED BRANDS / MAKES

One of the following make of the material shall be used. The contractor will have to get

the sample approved from the Architect/ Bank’s Engineer whose decision shall be binding

on the contractor. The condition is also applicable for any material, not mentioned in the

specification or schedule of work. No deviations are allowed in these even during/ after

Tender.

1 Vitrified Tiles Kajaria/ Somany/ H.R.Johnson/ NITCO/ Orient Bell

2 Ceramic wall Tiles Kajaria/ Somany/ H.R.Johnson/ NITCO/ Orient Bell

3 Ceramic floor Tiles

(antiskid) Kajaria/ Somany/ H.R.Johnson/ NITCO/ Orient Bell

4 False Flooring Unifloor/ Flexi Access Floor/ Armstrong

5 Wooden Laminated

Flooring Pergo/ Xylos/ Armstrong/ Vista / Green

6 Aluminum Fittings Jindal/ Hindalco/ MAAN

7 Aluminum Extrusion

Sections Jindal/ Hindalco/ MAAN

8 Commercial Plywood Century/ Greenply / Archidply / Alpro- Premium

9 Laminates (1.00mm thk.) Greenlam / Century/ Aica/ Sonear/ Archid

10 Veneer Century / Durian/ Sonear/ Archid/ Green

11 Drawer Sliding/ Patch

Fittings Earl Bihari (EBCO)/ Godrej/ Hettich/ Dorma

12 Floor Spring / Door Closer Godrej / Hardwyn / Hyper/ Dorma/ Haffele

13 Triple Computer Monitor

Mount/ Stand Arm

Vivo/ Dell/ HP

14 Flush Door Century/ Archid/ Sonear/Alpro

15 Texture Interior Paint Sandtex Matt/ Dulux/ Berger/ Okios/ Asian

16 Readymade Computer

Drawer EBCO/ Hettich/ Blum

17 Paints Asian/ Nerolac/ Berger/ Dulux

a) Cement paint

Snowcem/ Surfacem/ Durocem

b) Synthetic Enamel Paint Asian/ Nerolac/ Berger/ Dulux

c) Acrylic Emulsion Paint

(Interior and Exterior) Asian/ Nerolac/ Berger/ Dulux

18 Glazing Modi Tuff Glass/ Triveni Glass Ltd./ Indo Asahi Glass Co.

Ltd./ Saint Gobain

19 Cement Grade 43/53 of L&T/ A.C.C./ Ambuja/ Ultratech

20 Mineral Fibre False Ceiling

Armstrong/ Indian Gypsum Board/ Gypro

21 ACP Panels/ Sheets

Alubond/ ALU Decor/ Alstrong/ Alstone

22 Acrylic Sheets Sanmati Acrylics/Acrylic Sheet India/ Acry Plus

23 Vertical/Roller blinds Vista/ MAC/ DACK

Page 66: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

24 Corian Corian/ LG/ AVONITE / Merino

25 PU Paint Asian/ Berger/ ICI

26 Wall Paper Elemento/ Marshel

NOTE: Above makes of equipment are approved subject to their meeting the

specifications. The contractor however shall seek approval of specific make from

Consultant/ Bank's Engineer before commencing the work. The decision of Consultant/

Bank's Engineer shall & binding on the contractor in this respect.

BILL OF QUANTITY

PREAMBLE:

Page 67: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

TO BE READ ALONG WITH DRAWINGS.

• RATES TO BE QUOTED BOTH IN FIGURES AND WORDS.

• ALL PAGES TO BE SIGNED AND STAMPED BY THE TENDERER.

• THE RATE OF THE ITEMS SHALL BE APPLICABLE FOR ANY FLOOR LEVEL/ ANY NUMBER

OF FLOORS, OR ANY QUANTITY.

• THE SPECIFICATION OF THE ITEMS SHALL BE AS PER LATEST INDIAN STANDARD

CODES UNLESS OTHERWISE SPECIFIED.

• ALL MATERIALS SHALL BE AS PER APPROVED LIST AND SHOULD BE OF Ist QUALITY

UNLESS OTHERWISE SPECIFIED.

• THE RATES ARE INCLUSIVE OF ALL DUTIES AND TAXES (EXCEPT GST) OF ALL

GOVERNMENT, MUNICIPAL OR ANY OTHER STATUTORY BODY APPLICABLE FROM TIME

TO TIME.

• RATES SHALL BE FOR ITEMS COMPLETE IN ALL RESPECTS AS PER DRAWING,

INSTRUCTIONS AND APPROVAL OF THE ARCHITECT/ BANK’S ENGINEER.

• THE QUANTITIES ARE APPROXIMATE AND TENTATIVE WHICH MAY VARY DURING

COURSE OF EXECUTION. THE RATES QUOTED AGAINST PARTICULAR ITEM SHALL

NOT BE CHANGED WITH VARIATION IN QUANTITIES.

• MAKING OF ANY CUTOUT / OPENING FOR ELECTRICAL / AIR – CONDITIONING

WIRING / FITTING IN ANY OF THE ITEM OF FALSE CEILING, PARTITIONS, PANELING

MASONRY WORK ETC. AND FINISHING EDGES JAMBS / CILLS / SOFFITS OF THE

OPENING SHALL NOT BE PAID EXTRA.

• THE TENDERER SHALL VISIT THE SITE AND SHALL SATISFY HIMSELF AS TO

CONDITIONS UNDER WHICH THE WORK IS TO BE PERFORMED. HE SHALL ALSO

CHECK, ASCERTAIN THE LOCATIONS OF ANY EXISTING STRUCTURES OR EQUIPMENT

OR ANY OTHER SITUATION WHICH MAY AFFECT THE WORK. NO EXTRA CLAIM AS A

CONSEQUENCE OF IGNORANCE OR ON GROUND OF INSUFFICIENT DESCRIPTION

WILL BE ALLOWED AT A LATER DATE.

• THE QUOTED PRICE FOR ITEMS SHALL INCLUDE ALL ACCESSORIES, CONSUMMABLES

ETC. AS REQUIRED TO MAKE THE ITEM COMPLETE IN ALL RESPECTS, COMPATIBLE

WITH OTHER RELATED / ASSOCIATED ITEMS AND FULLY FUNCTIONAL.

• CONTRACTOR SHALL BE FULLY RESPONSIBLE FOR ANY ERROR, DIFFICULTY IN

EXECUTION / DAMAGES INCURRED OWING TO DISCREPANCY IN DRAWINGS WHICH

HAS BEEN OVERLOOKED BY HIM AND HAS NOT BEEN BROUGHT TO THE NOTICE OF

THE ARCHITECT.

• THERE ARE NUMBER OF ITEMS GIVEN IN THE TENDER WHERE IN BASIC RATES

INCLUDING ALL TAXES EXPECTED HAS BEEN MENTIONED IN THE TENDER. THESE

ITEMS SHALL BE PURCHASED BY THE CONTRACTOR FROM THE MARKET ONLY AFTER

THE APPROVAL OF QUALITY AND RATES BY THE ARCHITECT.

• ALL HIDDEN SURFACES OF BOARD / PLY / WOOD WORK TO BE PAINTED WITH ANTI

BACTERIAL PAINT FROM NAV AIR INTERNATIONAL FR 881 (VIPER) (WHITE COLOUR

AS PER MANUFACTURER’S SPECIFICATIONS ON WOOD / BOARD).

• CONTRACTOR SHALL APPOINT TECHNICALLY QUALIFIED FULL TIME SITE

SUPERVISOR TO MONITORING THE DAY TO DAY PROGRESS OF WORK AT SITE ON

THEIR OWN COST.

Page 68: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

(Refer annexed file/section in e-tender portal for detailed Bill of Quantities)

PLEASE NOTE THAT THIS IS A COMPOSIT TENDER i.e. THE WORKS INCLUDE

INTERIOR FURNISHING, CIVIL, AIR-CONDITIONING, ELECTRICAL & ALLIED

WORKS.

SO, A) THE INTERIOR FURNISHING AND CIVIL WORKS ARE TO BE GOT

EXECUTED THROUGH BANK’S EMPANELLED INTERIOR FURNISHING VENDOR

ONLY.

B) SIMILARLY, THE AIR-CONDITIONING WORK IS TO BE GOT EXECUTED

THROUGH BANK’S EMPANELLED AIR-CONDITIONING VENDOR ONLY

C) THE ELECTRICAL & ALLIED WORK IS TO BE GOT EXECUTED THROUGH

BANK’S EMPANELLED ELECTRICAL VENDOR ONLY

FOR DIFFERENT COTAGORIES OF WORKS, SEPARATE BILL TO BE SUBMITTED BY

THE VENDOR CATEGORY WISE.

AGREED AND ACCEPTED ALL THE TERMS & CONDITIONS.

SIGNATURE OF CONTRACTOR

DATE: SEAL:

Page 69: TENDER DOCUMENT FOR INTERIOR FURNISHING & FURNITURE …sbi.co.in/webfiles/uploads/files/0102191848-TENDERNOTICE009__1_… · interior furnishing & furniture works at alternative premises

TENDER DRAWINGS

(Refer annexed file/section in e-tender portal for Tender Drawings)