TEL INTEGRATED MULTIPURPOSE PROJECT, ODISHA...Tel Integrated Multipurpose Project Feasibility Report...

283
TEL INTEGRATED MULTIPURPOSE PROJECT, ODISHA GOVERNMENT OF ODISHA WATER RESOURCES DEPARTMENT WAPCOS LIMITED (International Consultant in water Resources Power and Infrastructure, Development) 76-C, Sector 18, Institutional Area, Gurgaon, Haryana, India, Tele-fax : + 91-124-2399427 E-mail: [email protected] Feasibility Report

Transcript of TEL INTEGRATED MULTIPURPOSE PROJECT, ODISHA...Tel Integrated Multipurpose Project Feasibility Report...

  • TEL INTEGRATEDMULTIPURPOSE PROJECT,

    ODISHA

    GOVERNMENT OF ODISHAWATER RESOURCES DEPARTMENT

    WAPCOS LIMITED(International Consultant in water Resources

    Power and Infrastructure, Development)76-C, Sector – 18, Institutional Area, Gurgaon,Haryana, India, Tele-fax : + 91-124-2399427

    E-mail: [email protected]

    Feasibility Report

  • CONTENTS

  • TEL INTEGRATED MULTIPURPOSE PROJECTCONTENTS

    Brief Summary

    Salient Features

    Chapter- 1 Introduction

    Chapter- 2 Physical Features

    Chapter- 3 Interstate Aspects

    Chapter- 4 Survey & Investigations

    Chapter- 5 Project Hydrology

    Chapter- 6 Design Features

    Chapter- 7 Irrigation Planning

    Chapter- 8 Command Area

    Chapter- 9 Hydrogeology

    Chapter- 10 Reservoir Simulation Studies

    Chapter- 11 Power Potential Studies

    Chapter- 12 Environment, Ecology & Forest Aspects

    Chapter- 13 Cost Estimate

    Chapter- 14 Economic Benefits & Justification

  • 1

    Brief Summary of Tel Integrated Multipurpose project

    The proposed project is envisaged to create irrigation and Hydro-power development. It is

    proposed to construct a dam across river Tel, a tributary of Mahanadi at a location with

    longitude 82019’32’’ E and latitude 19049’24’’N and about 2 Km upstream (along the course of

    river) of the interstate border of Orissa with Chhattisgarh. The FRL of the dam is proposed at

    RL 500m with maximum height of dam is proposed to be 87m to have water spread area of

    1330 ha. The generation of hydro-power at two power stations located on the right side of the

    Tel River near village Phatki in Orissa territory will be done by connecting a Head Race Tunnel

    (diameter 2.5 m and 270 m long) from Tel dam. The barrage at Phatki of length 79m and

    height 5.4 m with Full Pond Level 325.1 m across Phatki Nallah, a tributary of Tel River. A

    main canal of length 23.395 km will take off from the Barrage at Phatki with FSL 324.5 m and

    it will cross over the Banjari Nallah through an aqueduct. The CCA of the project is 4025.329

    ha beyond Banjari Nallah, and 5878.132 ha between Phatki and Banjari Nallah . Thus, a total

    command area of 9903 ha will be served by Tel irrigation Project. Apart from this,

    stabilization of 2000 ha command area of Phuljhari weir across Banjari Nallah will also be

    done through this irrigation scheme. In addition, 18 MW of power will also be generated. The

    total land required for acquisition is 1636.6 ha, of which private land is 150.0 ha , forest land

    is 637.6 ha and 849.0 ha of Govt Land. The total estimated cost of the project including

    direct and indirect changes is Rs. 1749.20 crores.

  • SALIENT FEATURES

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon -i-Haryana –122015

    TEL INTEGRATED MULTIPURPOSE PROJECT

    SALIENT FEATURES

    1 – TEL DAM1.1 LOCATION

    (a) State Orissa

    (b) District Nabarangpur

    (c) (i) Latitude 19° 49' 24”

    (d) (ii) Longitude 82° 19' 32”

    (e) River Tel

    (f) LocationDam Site Near Village Karlaparah inNabarangpur District

    (g) Topsheet 65-I/5, 65-I/9

    1.2 HYDROLOGY

    (a) Catchment Area(Sq Km) 480

    (b) Maximum Annual Rainfall(mm) 2021

    (c) Minimum Annual Rainfall(mm) 924

    (d) Mean Annual Rainfall(mm) 1461

    (e) 75% Dependable Rainfall of

    (i) Catchment (mm) 1277

    (ii) Ayacut (mm) 1457.2

    (f)Maximum Design Flood Discharge(Cumecs)

    5000

    1.3 RESERVOIR

    (a) Dead Storage Capacity (MCM.) 20

    (b) Gross Storage Capacity (MCM.) 238.76

    (c) Dead Storage Level(DSL)(m) 465

    (d) Full Reservoir Level(FRL)(m) 500

    1.4 RUNOFF AT THE DAM SITE

    (a) At 50% dependability( MCM) 199

    (b) At 75% dependability( MCM) 131

    (c) At 90% dependability( MCM) 81

    1.5 HEAD WORKS

    A. Main Dam

    Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon -i-Haryana –122015

    TEL INTEGRATED MULTIPURPOSE PROJECT

    SALIENT FEATURES

    1 – TEL DAM1.1 LOCATION

    (a) State Orissa

    (b) District Nabarangpur

    (c) (i) Latitude 19° 49' 24”

    (d) (ii) Longitude 82° 19' 32”

    (e) River Tel

    (f) LocationDam Site Near Village Karlaparah inNabarangpur District

    (g) Topsheet 65-I/5, 65-I/9

    1.2 HYDROLOGY

    (a) Catchment Area(Sq Km) 480

    (b) Maximum Annual Rainfall(mm) 2021

    (c) Minimum Annual Rainfall(mm) 924

    (d) Mean Annual Rainfall(mm) 1461

    (e) 75% Dependable Rainfall of

    (i) Catchment (mm) 1277

    (ii) Ayacut (mm) 1457.2

    (f)Maximum Design Flood Discharge(Cumecs)

    5000

    1.3 RESERVOIR

    (a) Dead Storage Capacity (MCM.) 20

    (b) Gross Storage Capacity (MCM.) 238.76

    (c) Dead Storage Level(DSL)(m) 465

    (d) Full Reservoir Level(FRL)(m) 500

    1.4 RUNOFF AT THE DAM SITE

    (a) At 50% dependability( MCM) 199

    (b) At 75% dependability( MCM) 131

    (c) At 90% dependability( MCM) 81

    1.5 HEAD WORKS

    A. Main Dam

    Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon -i-Haryana –122015

    TEL INTEGRATED MULTIPURPOSE PROJECT

    SALIENT FEATURES

    1 – TEL DAM1.1 LOCATION

    (a) State Orissa

    (b) District Nabarangpur

    (c) (i) Latitude 19° 49' 24”

    (d) (ii) Longitude 82° 19' 32”

    (e) River Tel

    (f) LocationDam Site Near Village Karlaparah inNabarangpur District

    (g) Topsheet 65-I/5, 65-I/9

    1.2 HYDROLOGY

    (a) Catchment Area(Sq Km) 480

    (b) Maximum Annual Rainfall(mm) 2021

    (c) Minimum Annual Rainfall(mm) 924

    (d) Mean Annual Rainfall(mm) 1461

    (e) 75% Dependable Rainfall of

    (i) Catchment (mm) 1277

    (ii) Ayacut (mm) 1457.2

    (f)Maximum Design Flood Discharge(Cumecs)

    5000

    1.3 RESERVOIR

    (a) Dead Storage Capacity (MCM.) 20

    (b) Gross Storage Capacity (MCM.) 238.76

    (c) Dead Storage Level(DSL)(m) 465

    (d) Full Reservoir Level(FRL)(m) 500

    1.4 RUNOFF AT THE DAM SITE

    (a) At 50% dependability( MCM) 199

    (b) At 75% dependability( MCM) 131

    (c) At 90% dependability( MCM) 81

    1.5 HEAD WORKS

    A. Main Dam

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon -ii-Haryana –122015

    (a) Type Rockfill Dam

    (b) Average Height of Dam (m) 87

    (c) Top Width of Dam(m) 10

    (d) Slope

    U/s 2.5:1 to 3:1

    D/s 2:1 to 2.75:1

    (e) Length of Rockfill Dam(m) 3810

    (f) Top Bank Level (TBL) (m) 505

    B. Spillway

    (a) Type Ogee spillway

    (b) Length of Spillway(m) 132

    (c) Average height of spillway(m) 47

    (d) Crest level of Spillway(m) 492

    PH - I

    (a) No. & Size of units to be installed 2 x 4 MW

    (b) Design Discharge 13.6 cumecs

    (c) Type of turbine Francis

    (d) Installed capacity 8 MW

    (e) Design Head (m) 66

    (f)Energy Generation in 50% dependableyear

    20.85 MU

    PH - II

    (a) No. & Size of units to be installed 2 x 5 MW

    (b) Design Discharge 10.8 cumecs

    (c) Type of turbine Francis

    (d) Installed capacity 10 MW

    (e) Design Head (m) 82.8

    (f)Energy Generation in 50% dependableyear

    21.66 MU

    2- BARRAGE AT PHATKI

    2.1 LOCATION

    (a) State Orissa

    (b) District Nabarangpur

    (c) (i) Latitude 19° 51' 41”

    Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon -ii-Haryana –122015

    (a) Type Rockfill Dam

    (b) Average Height of Dam (m) 87

    (c) Top Width of Dam(m) 10

    (d) Slope

    U/s 2.5:1 to 3:1

    D/s 2:1 to 2.75:1

    (e) Length of Rockfill Dam(m) 3810

    (f) Top Bank Level (TBL) (m) 505

    B. Spillway

    (a) Type Ogee spillway

    (b) Length of Spillway(m) 132

    (c) Average height of spillway(m) 47

    (d) Crest level of Spillway(m) 492

    PH - I

    (a) No. & Size of units to be installed 2 x 4 MW

    (b) Design Discharge 13.6 cumecs

    (c) Type of turbine Francis

    (d) Installed capacity 8 MW

    (e) Design Head (m) 66

    (f)Energy Generation in 50% dependableyear

    20.85 MU

    PH - II

    (a) No. & Size of units to be installed 2 x 5 MW

    (b) Design Discharge 10.8 cumecs

    (c) Type of turbine Francis

    (d) Installed capacity 10 MW

    (e) Design Head (m) 82.8

    (f)Energy Generation in 50% dependableyear

    21.66 MU

    2- BARRAGE AT PHATKI

    2.1 LOCATION

    (a) State Orissa

    (b) District Nabarangpur

    (c) (i) Latitude 19° 51' 41”

    Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon -ii-Haryana –122015

    (a) Type Rockfill Dam

    (b) Average Height of Dam (m) 87

    (c) Top Width of Dam(m) 10

    (d) Slope

    U/s 2.5:1 to 3:1

    D/s 2:1 to 2.75:1

    (e) Length of Rockfill Dam(m) 3810

    (f) Top Bank Level (TBL) (m) 505

    B. Spillway

    (a) Type Ogee spillway

    (b) Length of Spillway(m) 132

    (c) Average height of spillway(m) 47

    (d) Crest level of Spillway(m) 492

    PH - I

    (a) No. & Size of units to be installed 2 x 4 MW

    (b) Design Discharge 13.6 cumecs

    (c) Type of turbine Francis

    (d) Installed capacity 8 MW

    (e) Design Head (m) 66

    (f)Energy Generation in 50% dependableyear

    20.85 MU

    PH - II

    (a) No. & Size of units to be installed 2 x 5 MW

    (b) Design Discharge 10.8 cumecs

    (c) Type of turbine Francis

    (d) Installed capacity 10 MW

    (e) Design Head (m) 82.8

    (f)Energy Generation in 50% dependableyear

    21.66 MU

    2- BARRAGE AT PHATKI

    2.1 LOCATION

    (a) State Orissa

    (b) District Nabarangpur

    (c) (i) Latitude 19° 51' 41”

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon -iii-Haryana –122015

    (d) (ii) Longitude 82° 22' 39”

    (e) River Pipaljore Nallah

    (f) LocationAt Phatki Village in NabarangpurDistrict

    (g) Topsheet 65-I/5, 65-I/9

    2.2 HYDROLOGY

    (a) Catchment Area(Sq Km) 20

    (b) Maximum Monsoon Rainfall(mm) 1798

    (c) Minimum Annual Rainfall(mm) 85

    (d) Mean Annual Rainfall(mm) 1387

    (e) Maximum Design Flood Discharge 166

    2.3 RUNOFF AT THE SITE

    (a) At 50% dependability( MCM) 8.3

    (b) At 75% dependability( MCM) 5.5

    (c) At 90% dependability( MCM) 3.4

    2.4 HEAD WORKS

    (a) Length of Barrage (m) 79

    (b) Height of Barrage (m) 5.4

    (c) Full Pond Level (m) 325.1

    (d) Maximum Water Level (m) 328.1

    (e)Maximum height of crest above deepest

    foundation (m)2.5

    (f)Type of Energy dissipation arrangement Discharge being very small, no

    specific dissipation device required

    (g) Guide bunds/ afflux bunds

    (g.1) Length 95

    (g.2) Top Level 329.1

    (h) Head Regulator (ONE)

    (h.1) Total Length (m) 49.45

    (h.2) Height above deepest foundation (m) 8.4

    (h.3) Length of Bay (m) 5

    (h.4) Sill Level (m) 324.2

    (h.5) No. of Gates One

    Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon -iii-Haryana –122015

    (d) (ii) Longitude 82° 22' 39”

    (e) River Pipaljore Nallah

    (f) LocationAt Phatki Village in NabarangpurDistrict

    (g) Topsheet 65-I/5, 65-I/9

    2.2 HYDROLOGY

    (a) Catchment Area(Sq Km) 20

    (b) Maximum Monsoon Rainfall(mm) 1798

    (c) Minimum Annual Rainfall(mm) 85

    (d) Mean Annual Rainfall(mm) 1387

    (e) Maximum Design Flood Discharge 166

    2.3 RUNOFF AT THE SITE

    (a) At 50% dependability( MCM) 8.3

    (b) At 75% dependability( MCM) 5.5

    (c) At 90% dependability( MCM) 3.4

    2.4 HEAD WORKS

    (a) Length of Barrage (m) 79

    (b) Height of Barrage (m) 5.4

    (c) Full Pond Level (m) 325.1

    (d) Maximum Water Level (m) 328.1

    (e)Maximum height of crest above deepest

    foundation (m)2.5

    (f)Type of Energy dissipation arrangement Discharge being very small, no

    specific dissipation device required

    (g) Guide bunds/ afflux bunds

    (g.1) Length 95

    (g.2) Top Level 329.1

    (h) Head Regulator (ONE)

    (h.1) Total Length (m) 49.45

    (h.2) Height above deepest foundation (m) 8.4

    (h.3) Length of Bay (m) 5

    (h.4) Sill Level (m) 324.2

    (h.5) No. of Gates One

    Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon -iii-Haryana –122015

    (d) (ii) Longitude 82° 22' 39”

    (e) River Pipaljore Nallah

    (f) LocationAt Phatki Village in NabarangpurDistrict

    (g) Topsheet 65-I/5, 65-I/9

    2.2 HYDROLOGY

    (a) Catchment Area(Sq Km) 20

    (b) Maximum Monsoon Rainfall(mm) 1798

    (c) Minimum Annual Rainfall(mm) 85

    (d) Mean Annual Rainfall(mm) 1387

    (e) Maximum Design Flood Discharge 166

    2.3 RUNOFF AT THE SITE

    (a) At 50% dependability( MCM) 8.3

    (b) At 75% dependability( MCM) 5.5

    (c) At 90% dependability( MCM) 3.4

    2.4 HEAD WORKS

    (a) Length of Barrage (m) 79

    (b) Height of Barrage (m) 5.4

    (c) Full Pond Level (m) 325.1

    (d) Maximum Water Level (m) 328.1

    (e)Maximum height of crest above deepest

    foundation (m)2.5

    (f)Type of Energy dissipation arrangement Discharge being very small, no

    specific dissipation device required

    (g) Guide bunds/ afflux bunds

    (g.1) Length 95

    (g.2) Top Level 329.1

    (h) Head Regulator (ONE)

    (h.1) Total Length (m) 49.45

    (h.2) Height above deepest foundation (m) 8.4

    (h.3) Length of Bay (m) 5

    (h.4) Sill Level (m) 324.2

    (h.5) No. of Gates One

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon -iv-Haryana –122015

    (h.6) Types of Gates Vertical

    (h.7) Size of Gates 5.4 m x 1.4 m

    2.5 DISTRIBUTION

    (a) Gross Commandable Area (GCA) (Ha.) 15474.157

    (b) Culturable Command Area (CCA) (Ha.) 9903.46

    (c) Percentage of GCA to CCA (%) 64%

    (d) Intensity of Irrigation (Kharif) (%) 86.2%

    (e) Intensity of Irrigation (Rabi) (%) 60.1%

    (f) Area irrigated during Kharif (Ha.) 7680

    (g) Area irrigated during Rabi (Ha.) 5360

    (f) Annual Irrigation (Ha.) 13040

    7. ESTIMATE OF COST

    Unit I – Civil Works(a) Direct Charges 1555.55 Crores

    (b) Indirect Charges 14.89 Crores

    (c) Total Civil Works 1570.45 Crores

    Unit – II Main Canal, Branch & Distribution System(a) Direct Charges 132.41 Crores

    (b) Indirect Charges 1.32 Crores

    (c) Total Civil Works 133.73 Crores

    Unit – III Electro-Mechanical Works(a) TOTAL COST 45 Crores

    TOTAL COST OF THE PROJECT 1749.20 CroresB/C Ratio 1.14

    FIRR 9.18%

    EIRR 10.88%

    Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon -iv-Haryana –122015

    (h.6) Types of Gates Vertical

    (h.7) Size of Gates 5.4 m x 1.4 m

    2.5 DISTRIBUTION

    (a) Gross Commandable Area (GCA) (Ha.) 15474.157

    (b) Culturable Command Area (CCA) (Ha.) 9903.46

    (c) Percentage of GCA to CCA (%) 64%

    (d) Intensity of Irrigation (Kharif) (%) 86.2%

    (e) Intensity of Irrigation (Rabi) (%) 60.1%

    (f) Area irrigated during Kharif (Ha.) 7680

    (g) Area irrigated during Rabi (Ha.) 5360

    (f) Annual Irrigation (Ha.) 13040

    7. ESTIMATE OF COST

    Unit I – Civil Works(a) Direct Charges 1555.55 Crores

    (b) Indirect Charges 14.89 Crores

    (c) Total Civil Works 1570.45 Crores

    Unit – II Main Canal, Branch & Distribution System(a) Direct Charges 132.41 Crores

    (b) Indirect Charges 1.32 Crores

    (c) Total Civil Works 133.73 Crores

    Unit – III Electro-Mechanical Works(a) TOTAL COST 45 Crores

    TOTAL COST OF THE PROJECT 1749.20 CroresB/C Ratio 1.14

    FIRR 9.18%

    EIRR 10.88%

    Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon -iv-Haryana –122015

    (h.6) Types of Gates Vertical

    (h.7) Size of Gates 5.4 m x 1.4 m

    2.5 DISTRIBUTION

    (a) Gross Commandable Area (GCA) (Ha.) 15474.157

    (b) Culturable Command Area (CCA) (Ha.) 9903.46

    (c) Percentage of GCA to CCA (%) 64%

    (d) Intensity of Irrigation (Kharif) (%) 86.2%

    (e) Intensity of Irrigation (Rabi) (%) 60.1%

    (f) Area irrigated during Kharif (Ha.) 7680

    (g) Area irrigated during Rabi (Ha.) 5360

    (f) Annual Irrigation (Ha.) 13040

    7. ESTIMATE OF COST

    Unit I – Civil Works(a) Direct Charges 1555.55 Crores

    (b) Indirect Charges 14.89 Crores

    (c) Total Civil Works 1570.45 Crores

    Unit – II Main Canal, Branch & Distribution System(a) Direct Charges 132.41 Crores

    (b) Indirect Charges 1.32 Crores

    (c) Total Civil Works 133.73 Crores

    Unit – III Electro-Mechanical Works(a) TOTAL COST 45 Crores

    TOTAL COST OF THE PROJECT 1749.20 CroresB/C Ratio 1.14

    FIRR 9.18%

    EIRR 10.88%

  • CHAPTER-1

    Introduction

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 1 - 1Haryana –122015

    CHAPTER - 1

    INTRODUCTION

    1.1 INTRODUCTION

    Odisha is situated in the east coastal region of the country. Its geographical area is

    almost 4.74% of India and its population is 36.7 million (2001census), about 3.57 per

    cent of India’s population. Agriculture remains the backbone of the economy as more

    than 80 per cent of the workforce is engaged here. Development of irrigated

    agriculture has played a major role in the economic growth and poverty alleviation

    through successive plan periods.

    Agro-climatic conditions have a great deal of diversity. The standard classification of

    the state in terms of agro-climatic zones is four-fold: (i) Coastal Plains; (ii) Central

    Table Land; iii) Northern Plateau and iv) The Eastern Ghats. Regional geographers,

    however, simplify this further and speak in terms of two agro-climatic regions: Odisha

    Coastal region (part of the upper Eastern Coastal Plains) and Odisha Highland

    Region.

    The catchment area falls in Odisha Highland Region, which is rugged, and having

    undulating topography and the aboriginal races (Bhuinyas and the Gonds were the

    main inhabitants of this forest-clad region).

    As the catchment region is delineated by features (as explained briefly in above paras)

    responsible in formulation of Tel Integrated Project, the state government of Odisha

    has undertaken through WAPCOS, the preparation of Feasibility cum Detailed Project

    Report for Irrigation and Hydro-power development.

    Since, Irrigation is considered the basic means for improvement in agriculture the

    implementation of this project leads to improvement in rural economy and the quality

    of life of the people including tribal population.

    1.2 AIM AND OBJECTIVES

    Tel Integrated Project is aimed to construct/generate

    a) Dam of length 3682 m across Tel River, a tributary of river Mahanadi at a location

    of 2 Km upstream of interstate border of Chhattisgarh and Odisha with a catchment

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 1 - 2Haryana –122015

    area of 480 Sq. Km. The FRL of the dam is 500 m with Maximum height of the

    dam to be 87 m to have water spread area of 1330 ha.

    b) Generation of Hydro-power at power station located on the right side of the Tel

    river near village Phatki in Odisha territory by connecting an HRT of length about

    1.35 Km from Tel dam.

    c) Barrage at Phatki of length 79 m and height 5.4 m with FSL 325 m across Phatki

    Nallah, a tributary of Tel River.

    d) A main canal of length 23.395 Km will take off from the Barrage at Phatki with

    FSL 324.5 m and it will cross over the Banjari Nallah through an aqueduct.

    e) A feeder canal is proposed to take off from the main canal before crossing the

    Banjari Nallah to augment the flow of Phuljhari diversion weir across Banjari

    Nallah so as to serve the command of existing Phuljhari minor irrigation project.

    The main canal after crossing Banjari Nallah through an aqueduct is also proposed

    to irrigate the command area lying on the right hand side of Banjari Nallah. Apart

    from this, the main canal, in the reach between Phatki barrage and Banjari Nallah,

    will also irrigate the command area lying between these two nallah (i.e., Phatki and

    Banjari Nallah).

    f) The breakup of command area which is proposed to be covered by proposed Tel

    irrigation project is as under.

    i. CCA of 4025.329 ha beyond Banjari Nallah

    ii. CCA of 5878.132 ha between Phatki and Banjari Nallah

    Apart from this, stabilization of 2000 ha command area of Phuljhari weir across

    Banjari Nallah will also be done through this irrigation scheme. As such, a total

    command area of 9903 ha will be served by Tel irrigation project apart from

    generating power of 18 MW (Design Energy 27.42 MU).

    1.3 HISTORY AND BACKGROUND

    The state is blessed with abundant water resources & extensive network of rivers &

    streams. For effective utilization & management of water resources, river basin plans

    for all the eleven river basins of the state have been prepared and steps are being taken

    to set up River Basin Organization.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 1 - 3Haryana –122015

    Irrigation is the main input of Agriculture without which Agriculture cannot sustain its

    full growth. Irrigation Development not only correlates to Agriculture but also to

    other Socio-Economic aspects like industry, navigation, hydropower, pisciculture,

    water supply etc. With this objective, top priority has all along been given in Five-

    Year Plans for irrigation development. During pre-plan period, 1.83 lakh hectare of

    irrigation potential was created. Attempts have been made to achieve irrigation

    development in planned manner by implementing different schemes such as AIBP,

    RIDE, BKVY, RR&R, Bharat Nirman & RLTAP etc. By the end of March-2006,

    21.59lakh hectare of irrigation potential has been created using surface & ground

    water.

    1. Irrigation potential created is about 1.45 lakh ha with 61,799 PLIPs.

    1.3.1 Water Resources at a Glance

    1. Net irrigation potential 2603.06 thousand ha (44.12% of total irrigable area)

    2. Ground water resources 2101128 hectare.mtr

    3. Utilized 14.79%

    4. Major/ medium flow irrigation 122071thou.ha

    5. Lift irrigation (minor) 347.39thou. ha

    6. Flow irrigation (Minor) 454.49 thou.ha

    7. Others 570.47 thou.ha

    1.3.2 Initiatives by Govt. of Odisha

    a) Biju Krushka Vikash Yojana (BKVY)

    The scheme was launched by the State Government in the year 2001 with an objective

    to revive derelict projects and construction of new minor & irrigation projects through

    people’s participation. As per the scheme, the beneficiaries will contribute 10% of the

    capital cost of the project in schedule area & 20% of the capital cost in non- schedule

    areas. After completion of the project, the operation & maintenance will be entirely

    controlled by the beneficiaries and are exempted from payment of water tax to

    Government.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 1 - 4Haryana –122015

    b) Pani Panchayat

    Adopting reform measures in irrigation sectors, participatory irrigation management

    (Pani Panchayat) programme has been taken up in mission mode approach and

    extended to all command area under major, medium and minor (Flow & lift) irrigation

    sector. Legal status has been provided to Pani Panchayat by enacting Pani Panchayat

    Act, 2002 & Pani Panchayat Rule, 2003.

    Keeping in view such schemes (as mentioned above), the Govt. of Odisha has

    undertaken to construct a Dam across Tel river and Four Bay Diversion Dam/Barrage

    across its tributaries which facilitates Irrigation and Power Generation thereby

    improving the living standards of the people (especially farmers) surviving in and

    around the project area.

    1.4 LOCATION AND ACCESSIBILITY

    Location:

    Sl.

    No.

    Name of

    Project

    Latitude Longitude

    1. Tel Dam 19049’24”N 82019’32”E

    2. Banjari Barrage 19049’0”N 82029’0”E

    Accessibility:

    The project is well connected by road, rail and air. Jeypore is the nearest railway

    station which is about 95 Km from the location of the project.

    1.5 CLIMATE

    1.5.1 Rainfall

    The project catchment lies in the western side of Eastern Ghat and has a highly rugged

    topography bounded by ridges kondhan hills whose elevation varies from 90 to 1350

    meters with highest peak named Galigonda at about 1630 meters. The catchment is

    affected by south west monsoon from June to October when it receives the maximum

    rainfall. Mean annual/monsoon rainfall charts for Odisha based on available data

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 1 - 5Haryana –122015

    shows that the annual catchment rainfall varies between 1400 and 1500mm. The four

    months (June to September) of monsoon is about 1200mm.

    1.5.2 Temperature

    The mean annual maximum and minimum temperature of the catchment area,

    represented by nearby climatological station namely Bhawanipatna, is 33.4° C and

    21.1° C respectively. As such the mean annual temperature of the project area is

    27.25° C. The recorded maximum and minimum temperature in the project area is

    44.9° C (in May) and 8.3° C (in January) respectively.

    1.5.3 Humidity

    It is seen that relative humidity is maximum in the month of August and minimum in

    the month of March. The relative humidity in the basin varies from 88% to 93%

    during July to September.

    1.5.4 Cloudiness

    During South-West monsoon sky is generally overcast. In other months sky is

    generally clear and lightly clouded. The maximum cloud cover is observed in the

    month of June and July and minimum cloud cover is in December and January.

    1.5.5 Winds

    The main wind direction in the basin is between Southwest and Northwest during the

    first half of the monsoon seasons. In the second half of the monsoon season, the wind

    direction is between West and Northwest. The wind velocity varies from about 0.5 km

    /hr to 3.2 km/ hr on normal days

    1.6 TOPOGRAPHY AND SOILS

    The region lying in the catchment is having a rocky and uneven wavy surface and

    having an interesting complex of denuded hills, plateaus, sharp ridges and mature

    valleys. Physically, the region may be broadly divided into three distinct units, each

    with a different physical character: (i) northern upland; (ii) the erosional plains of

    Mahanadi valley, and (iii) southern hilly region of Eastern Ghats.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 1 - 6Haryana –122015

    There is a considerable extent of natural vegetation in this region. Besides the

    abundant growth of bamboo along the Eastern Ghat tracts and other low-lying areas,

    Sal forest also occurs extensively throughout this region. The forests yield a variety of

    products like kendu leaves, tusser cocoons, lac, myrobalans, cane, arrow-roots, mahua

    flowers, broom grass, sabai grass, gums, resin, khair and sunari bark which provide

    livelihood support to the original inhabitants of this region.

    The soil depth in the command area is primarily shallow-deep to moderate-deep as

    can be seen in the Figure 1.1. The soil depth suggests the volume of soil which the

    plant root can exploit for obtaining their nutrient and water for growth. As indicated

    the figure, the data shows that the maximum command area is moderately deep and

    the cultivation of Millets, Pigeonpea, Moong, Black Gram and forest crops in selected

    areas are suggested for soil having shallow to medium depth during Kharif season,

    while rice and wheat can be cultivated under irrigated condition during Ravi season.

    As far as soil texture is concerned, it acts as a guide to many soil characteristics

    directly or indirectly related to plant growth. The data about the soil structure in the

    command area is shown in the Figure 1.2, which indicates that the majority of the soil

    covering the command area is loamy and clayey. As soil texture is moderately fine,

    therefore, the supply of water to plant is greater in this type of soil than that of coarse

    texture. Under similar conditions, the availability of nutrients to plants usually

    increases as soil texture becomes finer. As such, the both soil depth and soil texture of

    the command area is well suited for irrigated cultivation.

    1.7 POPULATION AND SOCIOECONOMIC CONDITION

    As per 2001 census, there are 4,733 males and 9673 females who are marginal

    workers and 12,598 males and 18154 females who are non-workers residing in 19,043

    households in 87 inhabitated villages under Chandahandi Block. The total population

    of the Chandahandi Block is 61,076 (30,350 male and 30,726 female), the SC/ST

    population is 6,479 and 20,276 respectively. About 77% of villages are electrified.

    There are about 59 primary schools, 21 middle schools, 9 secondary schools in the

    block. There is one college with 160 students functioning at Chandahandi Block. The

    literacy rate is 57.77% for male and 20.72% for female. There are 5 public health

    center and one mobile health unit maternity care center existing in the Chandahandi

    Block with six doctors and 10 beds.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 1 - 7Haryana –122015

    The inhabitants in the command area are mostly tribals. They mostly depend on

    cultivation and forest products. Some speak Oriya in a corrupt form, which is an

    admixture of several words and phrases from aboriginal dialects. Regions near

    boarder have a heavy dose of Chattishgarhi language. The religion of this area is

    composite. There are Hindus, Christians and Muslims. The tribals living here are

    namely Bhumias, Dombs. The latter are wide spread through the region. They are

    weavers and drummers by profession. The dombs are also engaged in cattle trade.

    Most of them earn their livelihood by cultivation and weaving. In the upper rank of

    the social scale we come across Sankharies, who deal with lac and who make basket,

    chains and dolls out of it. They are good artists, artisans and traders. Malis originally

    grow and collect flowers for temple worship. They now switched over to cultivation

    of Sugarcane, tobacco etc. on the banks of Indravati river. Sundhis are famous for

    distillation and selling of liquor. They are usually rich and wealthy in status.

  • Kachharparha

    Dandamunda

    Dharipani

    Jharbahal

    Pujaharigurha

    Shardapur

    Malgan

    Dumerparha

    Dhepgurha

    Luhaballi

    B

    O

    R

    I

    N

    Phalshaparha

    Matigan

    Bhojpur

    Sargibahal

    Khairbari

    Khaparadihi

    T

    E

    L

    R

    I

    V

    E

    R

    T

    E

    L

    R

    I

    V

    E

    R

    Gamarigurha

    Jharigan 4 km

    Kotradongri

    Malparha

    Photamunda

    Telumal

    Dhupaot

    Kharkhari

    Kodabhata

    Jhulenbar

    Koilimunda

    T

    E

    L

    R

    I

    V

    E

    R

    Jorabandh

    Kendugurha

    Ghantigurha

    Onkaberha

    Nawaparha

    Chandagiri

    Ambagurha

    Sanamunda

    Salebiri

    Babariya

    T

    E

    L

    R

    I

    V

    E

    RG

    u

    m

    a

    m

    i

    h

    a

    r

    i

    N

    SalebiriT

    E

    L

    R

    I

    V

    E

    R

    Beheramunda

    Jhaliaparha

    Babariya

    T

    E

    L

    R

    I

    V

    E

    R

    Kotradongri

    D

    A

    M

    A

    X

    I

    S

    Kathberha

    Khatberha

    T

    E

    L

    R

    I

    V

    E

    R

    N

    A

    G

    A

    R

    S

    H

    I

    L

    J

    H

    O

    R

    Mundagurha

    Lambidara

    Dudana

    Dongar

    TELNADI R.F

    Kadaligaba

    Dobadhara

    TEL RIVER

    Nahardig

    Kataldig

    Hirabar

    Amamunda

    Kendugurha

    Gabagurha

    Balipada

    P

    E

    T

    P

    H

    U

    L

    A

    N

    A

    D

    I

    Petphula

    B

    A

    R

    L

    A

    M

    J

    H

    O

    R

    Kandashor

    Khairapet

    Petphula

    Jogidongar

    Keupani

    Akarshi

    Jogidongar

    BEHEDA RESERVED FOREST

    Khelapadar

    Khelapadar

    Nagarshil

    B

    H

    A

    T

    A

    J

    H

    O

    R

    Telnadigan

    Telnadigan

    Karlaparha

    P

    R

    E

    S

    S

    U

    R

    E

    C

    O

    N

    D

    U

    I

    T

    Mainapadar

    Hatibarhi

    Hatibarhi

    P

    A

    D

    A

    M

    J

    H

    O

    R

    Kendughat

    BEHEDA RESERVED FOREST

    F R L 500m

    DEEPEST BED LEVEL 417m

    T

    E

    L

    R

    I

    V

    E

    R

    19' 52'30"

    INDAGAON PROTECTED FOREST

    T

    A

    I

    L

    R

    A

    C

    E

    C

    H

    A

    N

    N

    E

    L

    H R

    T C

    UM

    OP

    EN

    CH

    AN

    NE

    L

    T

    E

    L

    R

    IV

    E

    R

    B

    A

    N

    J

    A

    R

    I

    N

    A

    D

    I

    Bilijharan

    Kadibhandar

    Potkhalia

    Badalpani

    Buddhi Dongar

    Bandhkona

    Chiligan

    Bendradora

    J

    H

    A

    R

    IP

    A

    N

    I N

    K

    E

    B

    A

    R

    I

    J

    H

    A

    R

    I

    N

    B

    A

    N

    J

    A

    R

    I N

    A

    D

    I

    Gauriharia

    JHARIGAN RESERVED FOREST

    Rajkot

    Kurlapara

    Baidparha

    Potkhalia

    PA

    TA

    N N

    AD

    I

    Bharjori

    Dalbera

    Dalbera

    Baragurha

    KH

    AR

    IP

    AN

    I N

    Bhatiparha

    Bhatiparha

    Potkhalia

    Khutgurha

    Bhatiparha

    Mehlimunda

    Darliparha

    Dulkiparha

    K

    O

    R

    A

    K

    H

    A

    I

    N

    A

    D

    I

    Bhaludongri

    Haldikhaliaparha

    Dhuruwaparha

    BELPATIJOR NADI

    Langparha

    Langparha

    Dhorakot

    Sinaparha

    Semalaparha

    Bhattajor

    Deobandh

    Pipalparha

    Kondiora

    Kondiora

    Jamadarparha

    Haldi

    Tetaliparha

    Junapani

    Salebiri

    Sanadhurwaparha

    Chandahandi

    Ladhuaparha

    Dhupkot

    ChakamalKharkhari

    Malbhata

    Barigurha

    Mohara

    Phalsaparha

    Baramunda

    19' 52'30"

    INDEX MAP

    TEL INTEGRATED PROJECT

    ODISHA

    SYMBOL

    4-

    SCALE

    9.

    6-

    8.

    7.

    5-

    S/N

    3-

    2-

    1-

    DESCRIPTION

    LEGEND

    O D I S H A

    C H H A T I S G A R H

    O D I S H A

    C H H A T I S G A R H

    PANNABERA R.F

    Nuagan

    CCA - 5878 Ha

    E

    X

    I

    S

    T

    I

    N

    G

    L

    E

    F

    T

    C

    A

    N

    A

    L

    FEEDER

    CANAL

    PHULJHA

    RI MIP

    CCA - 2000 Ha

    CCA - 4025 Ha

    SAHAJKHOL P.F.

    S

    A

    H

    A

    J

    K

    H

    O

    L

    R

    .

    F

    .

    10.

    Jamugurha

    Gutipadar

    Bhalujharan

    Gudipadar

    P

    I

    P

    A

    L

    J

    O

    R

    E

    DU

    MA

    JO

    RI N

    J

    I

    G

    A

    N

    S

    H

    I

    N

    Phataki

    T

    H

    I

    P

    A

    N

    A

    D

    I

    K

    O

    R

    A

    K

    H

    A

    I

    N

    A

    D

    I

    540

    500

    5

    0

    0

    530

    500

    350

    450

    400

    481

    4

    5

    0

    4

    0

    0

    4

    0

    0

    4

    5

    0

    568

    512

    4

    5

    0

    4

    0

    0

    360

    380

    450

    450

    494

    400

    350

    481

    350

    500

    4

    0

    0

    3

    9

    0

    Boulder

    5

    0

    0

    450

    400

    450

    530

    520

    5

    0

    0

    538

    492

    B

    H

    A

    T

    I

    L

    P

    A

    R

    H

    A

    M

    C

    H

    I

    L

    I

    G

    A

    N

    S

    /

    M

    S

    A

    L

    E

    B

    I

    R

    I

    D

    I

    S

    T

    Y

    .

    F

    E

    E

    D

    E

    R

    C

    H

    A

    N

    E

    L

    LO

    DH

    UA

    PA

    RH

    A M

    M

    A

    I

    N

    C

    A

    N

    A

    L

    D

    A

    N

    D

    A

    M

    U

    N

    D

    A

    M

    P

    H

    A

    T

    A

    M

    U

    N

    D

    A

    M

    M

    A

    T

    I

    G

    A

    N

    M

    B

    H

    E

    N

    D

    IA

    M

    K

    O

    I

    L

    I

    M

    U

    N

    D

    A

    M

    O

    N

    K

    A

    B

    E

    R

    H

    A

    D

    I

    S

    T

    Y

    .

    H

    A

    R

    A

    D

    A

    P

    A

    R

    H

    A

    S

    /

    M

    400

    360

    Boulders

    500

    Boulders

    4

    5

    0

    5

    0

    0

    5

    0

    0

    5

    0

    0

    Stone quarry from Dam site in Village

    1. Chikili 24.000km

    2. Sandasa 29.750km

    3. Near Deobandh on Deo Dongar hill 9.750 km

    PH 1

    PH 2

    WAPCOS LIMITED

    Pin -122015

    (A GOVERNMENT OF INDIA UNDER TAKING)76 - C, Institutional Area, Sector- 18 Gurgaon (Haryana)

    DRG. No.- WAP/WRD/DPR/TIP/INDEX MAP/2017

    K

    O

    N

    D

    I

    O

    R

    A

    S

    U

    B

    M

    I

    N

    O

    R

    T

    E

    T

    A

    L

    I

    P

    A

    R

    H

    A

    M

    I

    N

    O

    R

    J

    A

    M

    A

    D

    A

    R

    P

    A

    R

    H

    A

    S

    /

    M

    SHEET No 1/2

    TETALIPA

    RHA SUB

    MINOR

    K

    A

    P

    H

    A

    R

    A

    D

    H

    I

    D

    I

    S

    T

    Y

  • CHAPTER-2

    Physical Features

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 2 - 1Haryana –122015

    CHAPTER – 2PHYSICAL FEATURES

    2.1 GENERAL

    The project area falls in Nabarangpur district of Odisha having its geographical area

    as 5294.5 Sq Km. The district extends in the West up to Bastar district of

    Chhattisgarh, in the East up to Kalahandi district, in the North up to Raipur district of

    Chhattisgarh and in the South to Koraput district. Nabarangpur district is situated at

    19014' Latitude and 82032' Longitude at an Elevation of 1876 m from Sea level. The

    district's demographic profile makes it clear that it is a predominantly tribal and

    backward district with 55.58% tribal and 73% of the rural families below poverty line

    (BPL).

    The region is characterized by high temperature in most parts of the year and medium

    to high annual rainfall. There is a considerable extent of natural vegetation in this

    region. The hydrographical features also reflect these effects. The chapter describes

    the general topographical and physical features of the Tel basin and the project

    command area.

    2.2 GEOGRAPHICAL DISPOSITION

    River Tel which rises in the north of Nabarangpur district forms a sort of its

    geographical boundary with Kalahandi district and finally unites with a bigger

    Mahanadi river in Sonepur town. It is not perennial and dries up during the

    summer, as the flow in the river remains virtually nil during the period starting from

    mid March to mid June, except for few years when the good monsoon occurs and the

    base flow continues even during this period.

    Physiographically, the catchment area may be broadly divided into two different

    natural divisions, the hilly tracts and the plain areas. The former chiefly comprises of

    the ranges of hills which ran from the north-east to the south-west of the district and

    the later constitutes the river valleys of Tel and its tributaries.

    The asymmetric pattern and the characteristics of the drainage system strongly reflect

    the character of relief and the climate differences.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 2 - 2Haryana –122015

    The Tel, which form tributary of Mahanadi may be mentioned among the principal

    rivers of Nabarangpur. The scenery along the banks of the course through the hills on

    the Tel, is exceedingly fine and varies from wild raging torrents sweeping over bare

    rocks, to placid stretches of deep pools with the stream swirling in the eddies between

    rich meadow land, verdant with grass and banks overhung with willows.

    2.3 TOPOGRAPHY OF TEL BASIN AND COMMAND AREA

    2.3.1 Topography

    The region lying in the catchment is having a rocky and uneven wavy surface and

    having an interesting complex of denuded hills, plateaus, sharp ridges and mature

    valleys. Physically, the region may be broadly divided into three distinct units, each

    with a different physical character: (i) northern upland; (ii) the erosion plains of

    Mahanadi valley, and (iii) southern hilly region of Eastern Ghats.

    2.3.2 River System

    The River Tel originates from the hilly range near Nabarangpur district in Odisha at

    an elevation of 66m. During its course of 296 Km it drains an area of 1496 Sq.Km

    before its outfall into river Mahanadi on the right about a kilometer downstream of

    Sonepur town in Odisha. The river Tel nearly intercepts 16.3% of the drainage area of

    river Mahanadi which is 32.43% of the drainage area of Mahanadi Odisha and it is

    encompassed between 820 09’ 48” to 840 17’ 53” of east longitude and 190 15’ 08” to

    200 53’ 13” of North latitude. The major tributaries of river Tel are Banjari, Sagada,

    Hate, Rel, Udanti, Indra Lanth, Raul, Khagado, and Suktel.

    The catchment area of Tel basin is 480 Sq.Km. The Banjari Barrage catches an area

    of 230 Sq.Km across Banjari nallah as the area for studies in this project. Similarly

    the catchment area for Four Bay Diversion Dam across Pipaljarah Nallah comes out

    to be 20 Sq.Km.

    2.3.3 Command Area

    The water from reservoir will be carried through Power House - 1 & 2 located at

    lower altitude on the right side of Tel River near village Phatki in Odisha. The water

    finally released from power house will be picked up by proposed Barrage with FRL

    325 m and from there a canal of length about 23.395 Km will take off from this

    Barrage and will feed water to the existing Banjari Barrage for additional irrigation of

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 2 - 3Haryana –122015

    2000 ha through Banjari Barrage and thereafter remaining water will cross Banjari

    nallah through an aqueduct to provide irrigation of 4025 ha, further it is also

    envisaged to irrigate a command area of 5878 ha by this main canal in its way from

    Phatki Barrage to Banjari Barrage. Thus the total water to be carried by the canal is

    for a command area 9903 ha.

    2.3.4 Geology

    The Dam site (height 87m and length 3.8 km) was examined by WAPCOS experts

    and studies revealed that the pink to grey granite gneisses are exposed at the proposed

    site with secondary veins of pink quartz near proposed spillway location. Geological

    study was also carried out at the proposed dam site as well as spillway. After

    accomplishing Geo-Technical Investigations, it is revealed that the rock conditions

    are considered suitable for water conductor system as well as Dam and power house.

    The complete details of Geo-Technical Investigations can be viewed from Chapter-

    4.

    Apart from the above strata, the catchment area has a treasure of many ores like iron,

    chlorite, mica, quartz, hematite, limonite, large deposit of granites and rock beds

    covering layered of coarse white quartz.

  • CHAPTER-3

    Interstate Aspects

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 3 - 1Haryana –122015

    CHAPTER 3

    INTERSTATE ASPECTS

    3.1 INTERSTATE ASPECT

    The Tel Integrated project proposed on Tel River, a tributary of river Mahanadi is

    entirely lying in the state of Odisha and therefore there is no interstate aspect as far as

    the project is concerned. Further there is no interstate tribunal award for sharing

    Mahanadi basin waters among the party states (Chhattisgarh, Madhya Pradesh,

    Maharashtra, Jharkhand and Odisha). However, agreements reached at Chief Minister

    level between Odisha and undivided Madhya Pradesh in 1983 at Bhubaneswar with

    regard to some projects in the Mahanadi basin to be taken up jointly by Odisha and

    the then Madhya Pradesh are reproduced below project wise.

    3.1.1 Ib Project (Odisha Project)

    Madhya Pradesh agrees to spare 25 percent run-off from the catchment area drained

    by Ib River and lying in its territory under the proposed Ib dam project (approximate

    latitude 230 12’ N, longitude 840 06’ E). Odisha agrees to fix full reservoir level of Ib

    dam at R.L. 272.50 m. The land in Madhya Pradesh would however, be acquired up to

    R.L. 273.00 meters to allow for back water impact. In exceptional cases, if areas lying

    above R.L. 273.00 meters in the foreshore area of the reservoir in Madhya Pradesh are

    damaged due to floods, the damage being solely attributable to the construction of Ib

    dam, liable compensation will be paid by Odisha. Madhya Pradesh may generate

    hydro-power at the head works of Ib project entirely at its own cost without paying

    for the cost of storage, but bearing the full cost of all additional civil and electrical

    works required for generation of hydro-power. Madhya Pradesh will make its own

    arrangement for operation and transmission of power generated. Project report for

    power part will be prepared by Madhya Pradesh for which Odisha will extend

    necessary co-operation. However, the regulation of the Ib reservoir shall be done by

    Odisha as per operational and irrigation requirements.

    3.1.2 Sapanai Project (Madhya Pradesh Project)

    Odisha agrees to spare 70 percent of run-off from its catchments area for use in

    Madhya Pradesh at Sapanai dam (approximate lat. 210 53’ 45” N. Long. 830 30’

    05”E). Madhya Pradesh may formulate Sapanai Project leaving an upstream reserve

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 3 - 2Haryana –122015

    to the extent of 30 percent of run-off from Odisha. Catchment for use in Odisha State,

    Submergence due to project is limited to Madhya Pradesh territory only.

    3.1.3 Kurunala a Project (Joint Project)

    Madhya Pradesh and Odisha agree to implement the Kurunala Project as a joint

    irrigation schemes, where the catchment area of Kurunala is about 45 sq. miles

    (Approximate Lat. 210 55’ N, Long. 830 33’ E) to irrigate in about 3000 acres in

    Madhya Pradesh and about 9000 acres in Odisha. The cost of head works of the

    project shall be shared in proportion of the ultimate irrigation benefits derived by each

    State.

    3.1.4 Upper Jonk Project (Odisha Project)

    Odisha agrees to supply water through the left bank canal of Upper Jonk Project at

    Odisha - Madhya Pradesh border to support irrigation in an area of 2000 acres in

    Madhya Pradesh territory on charges to be determined. The requirement of rest of the

    areas in Madhya Pradesh may be met by Madhya Pradesh by utilizing the waters of

    the tributaries of Jonk river upstream of lower Jonk Project (Odisha) draining that

    area subproject to a maximum utilization of 40 square miles of catchment Odisha

    agrees to consider request by Madhya Pradesh for submerging Odisha land for the

    above project (s) if any.

    3.1.5 Lower Jonk Project (Joint Project)

    Odisha and Madhya Pradesh agree that a dam across Jonk river near Girnia

    (Approximate Lat. 210 10’ N and Long. 820 37’ 30” E) should be constructed as a joint

    project and share the cost of dam, reservoir and available run off in the ratio of 30

    percent (Odisha) and 70 percent (Madhya Pradesh). The cost of head regulators and

    canal system will be borne by the respective beneficiary States). The surveys and

    investigation of Girnia Dam will be carried out by Madhya Pradesh.

    3.1.6 Ong Project (Odisha Project)

    Madhya Pradesh agrees to spare 20 percent of run-off from its catchment area lying in

    Ong sub-basin for use by Odisha at the proposed dam site across Ong river near its

    confluence with Surangi River (approximate lat. 210 65’ 29” Long. 830 03’ 06”).

    Odisha agrees to fix the full reservoir level of Ong reservoir at R.L. 219.0 meters.

    Odisha may however fix the full reservoir level at R.L. 220 meters provided the

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 3 - 3Haryana –122015

    reservoir does not submerge existing irrigated areas in Madhya Pradesh for which

    necessary field verification will be carried out jointly.

    3.1.7 Jira Project (Odisha Project)

    Madhya Pradesh agrees to spare run-off from 14.25 sq. km les of is catchment lying in

    Jira sub-basin for use by Odisha proposed Jira dam project (approximate Lat. 210 23’

    N. Long. 830 26’ E) with full reservoir level fixed at R.L. 697.5 ft.

    3.1.8 Sahajhahal Project (Joint Project)

    Odisha and Madhya Pradesh agree to implement Sahajhahal Project as a joint

    irrigation scheme where the catchment area of the river is about 22 sq. miles

    (approximate Lat. 210 21’ 15” N, Long 830 21’ 15” E) in Madhya Pradesh. The cost

    of joint works and irrigation benefit shall be shared in the ratio of 70 percent (Madhya

    Pradesh) and 30 percent (Odisha). Surveys and investigations of this joint project will

    be carried by Madhya Pradesh.

    3.1.9 Lower Kolab Project (Joint Project)

    Odisha and Madhya Pradesh agree to re-investigate the lower Kolab Project with

    alternative possibilities of irrigation and hydro-power generation. It found feasible,

    the project shall be taken up as a joint project. Survey and investigation will be carried

    out by Odisha in consultation with Madhya Pradesh and the first preliminary report

    will be finalized by June, 1984.

    3.1.10 Back Water Studies for Hirakud Dam

    Both the States agree to carry out fresh back water studies for the Hirakud reservoir

    with a view to ascertaining the extent of submergence caused in Raigarh district of

    Madhya Pradesh during high floods. The Central Water & Power Research Station,

    Pune may, if necessary, be associated with these studies.

    3.1.11 Establishment of Joint Control Board

    Madhya Pradesh and Odisha agree to establish a Joint control Board to review the

    progress, from time to time of survey, investigation, planning execution and operation

    of joint Inter-State Irrigation and/or Power Project(s) and to discuss and resolve any

    issues.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 3 - 4Haryana –122015

    3.1.12 Supply of Power

    It is agreed that supply of 5 MW Power which was committed by the Government of

    Odisha previously will be resumed.

    As the M.P. State Electricity Board is keen to have power from Hirakud, this will be

    supplied at Hirakud Bus Bars. The cost of power will be the cost of generation at

    Hirakud Power House. The cost would be reviewed annually by the representatives of

    the two Boards.

    The question of payment of Electricity Duty by M.P. Electricity Board for future

    supply by Odisha State Electricity Board of 5 MW. Power would be referred to the

    Department of Power, Government of India for their guidelines.

    Meeting held on 27.04.1983 at Bhubaneswar

    List of officers present

    Madhya Pradesh Odisha

    1 Shri N.R. Krishna, I.A.S. Secretary,

    Energy & Secretary to Chief Minister

    1 Shri Gian Chand, I.A.S. Chief

    Secretary

    2 Shri V.M. Chitale,

    Secretary, Irrigation

    2 Shri P.C. Hota, I.A.S Commissioner-

    cum-Secretary, Irrigation & Power

    Deptt.

    3 Shri Matin Ahmad, Chief Engineer &

    Special Secretary to Chief Minister

    3 Shri S.B. Mishra, I.A.S. Secretary to

    Chief Minister

    4 Shri S. Dhagat, Chief Engineer

    Irrigation, Mahanadi Basin

    4 Shri S.C. Tripathy, Consultant.

    5 Shri N.C. Sohani, Superintending

    Engineer

    5 Shri K.T. Subudhi, Engineer-in-

    Chief, Irrigation

    6 Shri U.B. Singh, Superintending

    Engineer.

    6 Shri A. Panda, Chairman, Odisha

    State Electricity Board

    7 Shri. K.C. Mohapatra, Deputy

    Secretary, Irrigation & power

    8 Shri. R.K. Mishra, Deputy

    Secretary, Irrigation & power

    9 Shri. M.L. Lath, Superintending

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 3 - 5Haryana –122015

    Madhya Pradesh Odisha

    Engineer, Technical Unit.

    10 Shri. J.C. Pati, Executive Engineer,

    Planning.

    11 Shri. S.N.Mishra, Executive

    Engineer, Sundergarh Irr. Division.

    12 Shri. C.R. Mohapatra, Executive

    division

    13 Shri. S.N.Mohanty, Executive

    Engineer, Kalahandi Irrigation

    Division

    14 Shri. A.R.Satpathy, Asstt. to

    Engineer in chief, irrigation , Odisha

  • CHAPTER-4

    Survey & Investigations

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 4 - 1Haryana –122015

    CHAPTER 4

    SURVEY AND INVESTIGATIONS

    4.1 GENERAL

    The survey and other field investigation as required for preparation of feasibility for

    the Tel Integrated Multipurpose Project have been executed as per CWC guidelines

    2000. The field survey requirements were identified based on toposheet study and

    reconnaissance surveys and the same were carried out as per the conceptual planning

    of the various components of the scheme.

    The project was initially conceptualized and was taken up by the water resources

    department, Government of Odisha for preparation of feasibility report. After

    reconnaissance survey of various sites in Lower Mahanadi river basin, followed by

    detailed study and investigations involving geology, topography and hydrology, soil

    survey etc the site has been selected for the proposed Tel Integrated Multipurpose

    Project. The following field surveys and investigations were taken up for forming up

    selection of the project site.

    4.2 RECONNAISSANCE SURVEY

    Based on Toposheet identification, some tentative sites in upper reaches of the Lower

    Mahanadi river basin were visited. Areas upstream and downstream of the sites were

    traversed and physiographical and other relevant features noted for further

    examination.

    4.3 TOPOGRAPHICAL SURVEYS

    Experts of Water Resource Dept, Govt. of Odisha and WAPCOS visited the tentative

    proposed dam, barrage and power house sites in the basin area. After geological

    reconnaissance and detailed appraisal of the geological features of the project area, the

    proposed site has been found to be geologically safe and suitable for construction of

    headwork structures and it was found that there are no mineral deposits in the reservoir

    area carried out by the Geologist of Directorate of Geology and the same is appended

    as Annexure-4.1 at the end of this chapter. Following Topographical Survey work

    have been carried out as per requirement of Terms of Reference and as per

    specifications of CWC guideline August 2000.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 4 - 2Haryana –122015

    a) Topographical Survey at Dam axis

    The survey has been carried out at the dam axis on the River Tel. Cross section has

    been developed by taking readings at every 50 m interval along the length. Drawing

    pertaining to Strip Survey has been represented in a local Northing and Easting co-

    ordinate system. Topographical contour plan for strip survey of the dam axis have

    been developed with contour interval of 5 m appended in drawing no.

    WAP/WRD/TIP/FIG No. 1.

    b) Submergence Survey

    Topographical survey of the submergence area upstream of the proposed dam axis

    was carried out with the consideration of Full reservoir level (FRL) fixed at 500.0 m,

    so as to determine submergence area, dead storage and live storage capacities of the

    reservoir. The submergence area map is appended as drawing no.

    WAP/WRD/TIP/FIG No. 2.

    c) Dam Base Survey

    Cross sections of Tel River at 200 m interval were taken in a length along the river

    flow upto 3200 m upstream and 1800 m downstream of the proposed dam axis. The

    corresponding cross sections at dam axis, upstream sections and downstream sections

    are shown in drawing nos. WAP/WRD/TIP/FIG No. 3, 4 and 5 respectively. These

    sections are prepared at 1:100V and 1:1000H scale.

    d) Longitudinal Section

    To know the topography and river bed levels of the Tel and Banjari rivers of the Tel

    integrated project, topographical survey was carried out along the Tel River and

    Banjari River and corresponding longitudinal sections have been prepared along the

    reaches. Longitudinal section along Tel River has been appended as drawing no.

    WAP/WRD/TIP/FIG No. 6 and along River Banjari is appended as drawing no.

    WAP/WRD/TIP/FIG No. 7.

    e) Water Conductor System

    Hydrographic surveys / River surveys was carried out for establishing design flood /

    tail water levels at site of proposed structure. Thus, Grid contour topographical survey

    was carried out at the entire area of water conductor system i.e. from Dam on Tel

    River to Phatki Barrage through various civil structures i.e. Intake Tunnel, Head Race

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 4 - 3Haryana –122015

    Tunnel, Penstocks, Open Channel and Tail Race Tunnel. Beyond Phatki barrage,

    storage water will be off takes through Right Main Canal for the multipurpose uses.

    Based on this topographical survey, L-sections have been prepared along the Right

    Main Canal and is appended as drawing no. WAP/WRD/TIP/FIG No. 8.

    f) Command Area Survey

    Command area survey has been carried out following the standard survey practices.

    The command area of the proposed project lies on single sides of the River Tel. The

    survey of the command area has been carried out following the standard methods of

    surveying and a contour map of the area with 1 m contour interval has been prepared,

    and enclosed in drawing no. WAP/WRD/TIP/FIG No. 9.

    For micro canalization of the command area, a detailed topographic survey of a pilot

    area equal to 10 % of the total area with contour at 1 m interval on village maps are

    being carried out. For this purpose the survey party has collected the village maps;

    khasra map of land, details of each land like area, details of land owners etc and

    develop digitized version of the maps incorporating all the collected details.

    Topographical plan of each cultivation land are being prepared developing contour at

    1 m intervals taking levels at suitable intervals and at each corner of the plot as well as

    at centre point of each plot. A Pilot area equal to 10% of the total area is being

    surveyed. Detailed village wise command area survey plan is appended as drawing no.

    WAP/WRD/TIP/FIG No. 10.

    g) Power House Area Survey

    Grid topographical survey of the power house area was carried out. From the surveyed

    data contours has been developed at a contour interval of 1 m. The contour map of the

    power house area – I & II are prepared on 1:1000 scale and appended as drawing no.

    WAP/WRD/TIP/FIG No. 11 & 12 respectively.

    h) Phatki Barrage Area Survey

    Topographic survey of the Patki submergence area upstream of the existing Phatki

    Barrage was carried out, so as to determine submergence area, dead storage and live

    storage capacities in the storage.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 4 - 4Haryana –122015

    i) Establishing Bench Marks

    Bench Marks has been established with existing GTS. The new BMs have been

    connected to the nearest GTS or permanent Bench Mark of SOI by double leveling.

    The words ‘B.M.’ and the RL values have been painted clearly on every location. A

    list of established Bench Marks is given as under:

    B.M / GTS R.L. VALUE (m) LOCATION

    SOI PBM 622.500 RHS of Bitumen Road from Umer Kote toRaigarh near village Chikalpadar on a stonerock

    W-4 609.188 Hanuman Temple at Umerkote9/335 608.800 Culvert Road Umerkote to Jhorigaon. 9.335

    km from UmerkoteW-10 618.498 On culvert – village TaramariW-13 617.942 Police Station Jhorigam Main Gate PillarW-14 622.795 Junction of road Jhorigam to BorigudaW-18 566.609 On rock opposite hut at Hathi Badi bus

    stop. 50 m RHS road JHG-CNDW-19 562.863 On rock opposite Karlapada bus stopW-22 399.287 Jhorigam Chandahandi block boundary

    pillar near GhatiW-24 378.028 Small stone at junction

    Katcha rasta to Bitumen RoadW-28 403.144 On right bank of Tel river Kutcha road

    joining the river

    j) Fixing of Center Line Stones

    The alignment of the water conductor system has been fixed accurately. For centerline

    marking R.C.C. blocks has been fixed and at point of intersections and also along

    tangent and apex point of curves along the alignment of the system.

    k) Preparation of Land Acquisition Plan

    i) Width of land required for canal acquisition has been worked out basedon the cross sections of the canal.

    ii) Width of land required for irrigation sources (new/old)/canal/pipelineacquisition has been worked out based on the cross sections of the canal@ 50 m intervals all along the length and area arrived at for canal.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 4 - 5Haryana –122015

    iii) Demarcation stones along the boundaries of land acquisition have beenfixed on both the sides.

    iv) The alignment along with land widths as worked out above has beenmarked on the village plan to assess survey number wise area of land tobe acquired for execution.

    v) Thus, land plan schedules in the prescribed proforma covering surveynumbers, particulars of land and land holders, survey number wise areahas been acquired along with classification of land etc. has been prepared.

    vi) Statements of structures, trees, wells or any other private, public or Govt.property to be acquired also has been furnished while preparing LandAcquisition Plan.

    l) Accuracies

    All the survey instruments have been maintained in good condition to achieve higher

    accuracies but in no case there shall exceed those given below:

    Theodolite/Total Station, EDM Traversing

    Allowable error of closure - 1/3000Allowable error of distance - 1/5000Allowable error of closure - 4√k mm(Where k is the total distance in km)

    4.4 GEOTECHNICAL INVESTIGATIONS

    The complete Geotechnical investigations carried out in the project area is appended as

    Annexure 4.2 at the end of the chapter.

  • CHAPTER-5

    Project Hydrology

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 1Haryana –122015

    CHAPTER – 5PROJECT HYDROLOGY

    5.1 INTRODUCTION

    The Tel integrated Project is likely to have following components.

    1. A Storage Dam on Tel, about 3 Km upstream of the place where river passes

    from Odisha and starts forming the boundary between Odisha and Chhattisgarh

    and there is likely to be a comparatively large reservoir, possibly with a carry

    over storage. The Dam would have a catchment area of about 480 km².

    2. A 1.35 Km long pipeline leading to a powerhouse near Phatki village. While the

    FRL and MDDL of the reservoir is 500m and 480m, the tail water level after the

    Power House 1st and 2nd would be 418 m and 328 m respectively.

    3. A barrage to be constructed on Phatki nallah - a tributary of Tel, slightly up

    stream of its confluence with Tel. The purpose of this barrage is to act as a

    diversion structure for diverting flow of both Phatki nallah as well as water

    coming from Tel dam through power houses for irrigation command area lying

    between Phatki nallah and Banjari River.

    4. A 23.40 Km long canal from Phatki barrage which crosses Banjari Nallah

    through an aqueduct. The river Banjari is also a tributary of Tel. The catchment

    area of the Barrage would be about 230 km².

    5. An Irrigation distribution system from this canal between Phatki barrage and

    Banjari Nallah having a G.C.A. of 9184.6 ha and another irrigation distribution

    system beyond Banjari nallah having a G.C.A. of 6289.6 ha.

    6. A 7.0 Km long left canal (Exixting) from Banjari Barrage, with an irrigation

    distribution system, which is proposed to serve a G.C.A. of 2500 ha.

    5.2 HYDROLOGIC INPUTS REQUIREMENTS FOR PLANNING THE

    PROJECT

    The Tel Integrated Multipurpose Project system involves a large storage (dam), a

    diversion structure, two new irrigation command areas and a command area for

    stabilization. The simulation of the system has been carried out on monthly basis, for

    the period 1971-72 to 2007-08. Following data were used in the simulation study.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 2Haryana –122015

    i. Data requirement for the simulation studies

    a. Monthly in flow series for each of the dam sites and Barrage sites

    b. Monthly rainfall and effective rainfall information for the command areas

    c. Elevation-Area-Capacity curve for the reservoir

    d. Evaporation data from water surface

    ii. Data required for flood related safety of the structures

    a. The probable maximum flood for the main storage dam

    b. The standard project flood and frequency (100 year flood), as the case may be,

    for the pondages, Barrages or Weirs.

    5.3 AVAILABILITY OF HYDROLOGICAL DATA

    a) Rainfall data

    Rainfall data in the vicinity is available for five stations. The daily data has been

    collected and has been compiled as 10-daily and monthly data. The availability is as

    indicated below. As the rainfall data is not available on a continuos basis for a longer

    period for the stations mentioned below, it has been decided to utilize the flow data

    available (for more than 30 years) in the Tel River basin at kantamal, Kesinga &

    Sukma G&D Sites for assessing the water availability for Tel Integrated Project. The

    data processing and development of flow series are discussed subsequently.

    Station Name Latitude LongitudeData Availability Appendix No.

    Showing the10 daily dataFrom To

    Belpara 20° 35’ 82° 59’ Jan-1970 Dec-1992 Appendix-I(Hyd)

    Jashpurnagar 22° 53’ 84° 08’ Jan-1966 May-1999 Appendix-II(Hyd)

    Jharsuguda 21° 51’ 84° 02’ Jan-1943 Dec-1992 Appendix-III(Hyd)

    Khaparakhol 20° 40’ 82° 50’ Jan-1952 Dec-1992 Appendix-IV(Hyd)

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 3Haryana –122015

    Station Name Latitude LongitudeData Availability Appendix No.

    Showing the10 daily dataFrom To

    Nawapara 20° 50’ 82° 33’ Jan-1947 Dec-1996 Appendix-V(Hyd)

    Sundargarh 22° 07’ 84° 02’ Jan-1979 Nov-2005 Appendix-VI(Hyd)

    b) River flow data

    In the vicinity of the project, river flow data is available for three sites maintained by

    Central Water Commission. The daily discharges have been collected from the

    Central Water Commission. The ten daily compilations of daily data have also been

    made. The details in regard to the availability of this data is shown below and also the

    annual flow data for Kantamal, Kesinga and Sukma for the same years can be viewed

    in Annexure No. 5.1, 5.2 & 5.3.

    Flow data availability

    Site

    NameRiver Basin

    Catchment

    area(Sq.

    km)

    Data availabilityAppendix No.

    showing 10 daily dataFrom To

    Kantamal Tel Mahanadi 196001971-

    72

    2007-

    08Appendix VII (Hyd)

    Sukma Suktel Mahanadi 13651989-

    90

    2001-

    02Appendix VIII (Hyd)

    Kesinga Tel Mahanadi 119601978-

    79

    2007-

    08Appendix IX (Hyd)

    5.4 PAN EVAPORATION DATA

    The observed pan evaporation data is important both for estimating the likely

    reservoir evaporation and for estimating the likely evapo-transpiration from irrigated

    areas. From reservoir, water is lost due to evaporation and loss of water due to

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 4Haryana –122015

    evaporation should be considered while carrying out simulation studies. Evaporation

    rates are important for preparation of reservoir operation tables. It has a very

    significant role to play during a delayed monsoon season when the reservoir storage is

    under maximum stress and demand for irrigation, water supply and hydropower

    increases manifold. Evaporation rates are generally highest in the summer months

    before the advent of monsoon; these may further increase during the delayed monsoon

    period owing to rising temperature resulting in severe depletion of the reservoir.

    Observed evaporation data is not available for any station in the region. The

    evaporation value have, therefore been interpolated from Evaporation Tables

    published by IMD. Evaporation depths are measured by using American Class-A Pan

    Evaporimeter. Factors prescribed by IMD to convert the observed meshed covered

    pan data to open pan and then into the lake or reservoir evaporation depths are

    discussed in this chapter under the section on reservoir evaporation.

    5.4.1 Climatological Data

    In order to decide the crop water requirements and irrigation water requirements.The

    data Bhawanipatnam station has been used the position with regard to this data is

    given under.

    StationName

    Latitude Longitude

    Data Availability AppendixNo.

    Showingthe 10 daily

    data

    From To

    BhawaniPatna

    19° 55' N 83° 11' E 1971 1990Appendix X

    (Hyd)

    5.5 PROCESSING OF FLOW DATA AS REQUIRED FOR SIMULATION

    As already stated, the simulation would be on 10-daily basis since the system has both

    reservoir and diversion structures. Thus, the processing 10 daily data is important.

    The processing of the flow data normally consists of:

    i) Internal consistency checks such as between river stage and river discharge.

    ii) External consistency checks such as:

    Between simultaneous flow of one station and another

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 5Haryana –122015

    Comparison of the shape of the cumulative probability functions (flow

    duration curves) of the various stations

    Comparison of general statistical properties of the various flow series

    Consistency between flow and rainfall

    We have not been able to conduct the internal consistency as the water storage data

    was not readily available from the Central Water Commission. Hopefully, they would

    have already carried out such checks.

    The flows of any site would be affected by various factors, but the size of the

    catchment and rainfall regime would be the prime factors. To remove the effect of the

    catchment size, we have converted all 10 daily volumes, in million cubic meters, into

    specific flows in lit./s/sq. Km. We have used these specific flows in all data

    processing.

    The average flow regime of the three sites as 10 daily specific flows is shown below

    with the relevant tables and graphs:

    10-Daily Average Specific Flows in Lit/s/Sq.Km

    Month Sukma Site Kantamal Site Kesinga Site

    jun-I 0.36 1.97 3.49

    jun-II 43.34 11.73 21.72

    jun-III 5.16 14.48 25.14

    jul-I 36.93 33.55 44.81

    jul-II 41.8 43.02 48.4

    jul-III 63.87 48.67 60.77

    Aug-I 49.82 62.72 82.57

    Aug-II 83.44 68.72 79.15

    Aug-III 65.18 75.14 78.83

    Sep-I 52.66 54.66 62.25

    Sep-II 55.38 60.96 57.89

    Sep-III 29.46 31.72 29.25

    Oct-I 22.18 24.55 35.54

    Oct-II 13.08 13.38 13.92

    Oct-III 4.96 10.03 7.96

    Nov-I 10.6 8.33 8.79

    Nov-II 6.98 7.11 7.92

    Nov-III 3.6 6.01 7.05

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 6Haryana –122015

    Dec-I 1.45 4.40 5.72

    Dec-II 1.73 3.34 4.52

    Dec-III 1.02 2.66 3.21

    Jan-I 1.19 2.26 2.69

    Jan-II 1.18 1.99 2.07

    Jan-III 2.2 1.71 2.15

    Feb-I 1.73 1.57 2.35

    Feb-II 0.85 1.45 2.1

    Feb-III 0.54 1.45 2.69

    Mar-I 0.13 1.22 1.88

    Mar-II 0.19 1.16 2.01

    Mar-III 0 1.08 1.71

    Apr-I 0 1.13 1.88

    Apr-II 0 1.09 1.96

    Apr-III 0 1.16 2.37

    May-I 0 1.20 2.6

    May-II 0 2.17 3.95

    May-III 4.01 1.67 2.91

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 7Haryana –122015

    A comparison of these would show that the general flow regime of the three sites is

    very similar. The flows are very low in the spring-summer session of January to May,

    and at the Sukma site where the catchment area is comparatively small (1365 sq.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 8Haryana –122015

    kms.) the river seems to be ephemeral with no flow. Perhaps the catchment geology

    also may be responsible for this. At the larger site on Tel, a small specific flow of

    around 1 lit/s/sq. km is available during this season. The flow increases suddenly in

    the first or second 10 day period of June and is maximum in the month of August,

    during the autumn – winter season of Oct. to May, the flow decreases, but the flows in

    Sukma seem to be lower than those at the other two sites.

    The Sukma Site has no flow in the the first 10 days of June. The average for the

    second 10 day period is much larger than that for the third 10 day period of June.

    The variability of the 10 daily specific flows form year to year is depicted by the

    standard deviation of the 10 daily array are by the coefficient of variation. The regime

    of the coefficient of variation at the three sites is shown below.

    Kantamal Sukma Kesinga Kantamal Sukma Kesinga

    Jun-I 1.618 2.224 1.5 Dec-I 0.598 0.694 0.883Jun-II 2.613 0.659 2.271 Dec-II 0.806 1.171 1.264Jun-III 1.44 1.973 1.198 Dec-III 1.002 1.004 1.255Jul-I 1.715 1.307 2.066 Jan-I 1.124 0.889 1.346Jul-II 1.008 1.331 0.89 Jan-II 1.033 1.773 1.209Jul-III 0.939 1.027 0.917 Jan-III 1.142 NA 1.528Aug-I 0.727 1.182 0.74 Feb-I 1.33 NA 1.547Aug-II 0.907 0.939 0.731 Feb-II 1.294 NA 1.491Aug-III 0.921 1.082 0.934 Feb-III 1.35 NA 1.52Sep-I 0.774 1.246 0.825 Mar-I 1.496 NA 1.657Sep-II 1.056 1.409 1.183 Mar-II 1.65 NA 1.966Sep-III 0.908 2.178 0.791 Mar-III 1.651 NA 1.76Oct-I 1.552 1.98 2.072 Apr-I 1.71 NA 1.67Oct-II 1.158 0.766 1.175 Apr-II 1.45 NA 1.455Oct-III 1.214 1.497 0.998 Apr-III 1.704 NA 1.63Nov-I 1.331 0.873 1.158 May-I 1.538 NA 1.45Nov-II 0.891 0.615 0.791 May-II 1.842 NA 1.317Nov-III 0.593 0.685 0.759 May-III 1.412 NA 1.404

    MonthsCo-efficient of Variation

    MonthsCo-efficient of Variation

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 9Haryana –122015

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 10Haryana –122015

    A Comparison of these three figures also shows some similarity. The coefficient of

    variation is very high in June and October in view of the uncertainty about the start

    and withdrawal of the Indian summer monsoon. The variability is less during the rest

    of the monsoon. The variability is very considerable during the Dec to May period,

    and this is somewhat unexpected. Obviously, some effect of the North East monsoon,

    and some pre-monsoon showers are causing such sudden variations in flow .This is

    illustrated below for a few years for the Kantamal site.

    A few Years showing some what unusual flow variation at Kantamal on Tel.

    All Figures in Million Cubic Meters

    Year---> 1985 1987 1994 1999Nov-I 1569.456 234.567 523.39 1106.307Nov-II 1946.34 222.40 2472.35 438.40Nov-III 900.20 536.77 1382.68 248.15Dec-I 1698.62 460.55 1019.32 371.81Dec-II 1224.21 192.70 593.30 708.54Dec-III 222.89 307.46 1654.01 737.16Jan-I 418.02 363.57 323.83 366.68Jan-II 157.82 608.28 476.93 355.09Jan-III 338.79 335.80 338.32 177.21Feb-I 177.25 96.39 223.06 148.63Feb-II 66.16 50.13 371.80 269.40Feb-III 73.55 36.40 229.12 142.93Mar-I 74.12 37.79 513.06 156.12Mar-II 61.27 41.82 159.98 145.74Mar-III 42.22 36.59 109.80 128.69Apr-I 28.27 16.13 71.88 104.60

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 11Haryana –122015

    Apr-II 25.22 60.09 94.88Apr-III 14.06 4.85 42.56 82.10May-I 28.38 2.95 42.93 77.41May-II 11.92 2.29 31.05 82.27May-III 7.10 1.12 21.47 76.14

    The 10 daily river flows have a large auto correlation, due to the valley storage of

    surface water, bank storage of ground water etc. This is an important property which

    should be maintained in the series to be prepared for simulations. This auto

    correlation between one ten day period and the next was investigated for all the three

    sites. The results are shown below.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 12Haryana –122015

    A comparision of this information about auto correlation shows that the auto

    correlation is generaly low during the monsoon but is very high during the non

    monsoon period, making the low flows in the Feb to Apr period almost deterministic,

    dependent on the earlier flows .For the Sukma site, there are hardly any flows beyond

    January, and also the data period is short. Perhaps due to these reasons, the auto

    correlation for Sukma are some what erratic and do not fit with the other sites.

    5.6 THE FLOW DURATION ANALYSIS AND INTER COMPARISION OF

    FLOW AT THE THREE SITES

    In general there are two ways in which the flow duration analysis can be done.

    a) The flows or the specific flows for a period like a month, a season, or a year can

    be added or clubed together and the flow duration analysis can be made for these

    clubed values. For example, if the monsoon consists of 12 ten daily periods, and

    20 years data is available, in this method the flow duration would be based on the

    twenty clubed values.

    b) In the second approach, each of the 10 daily figures would be used in constructing

    the flow duration curve. Continue with example given in a) above, in this method,

    the flow duration curve would use all the 240 values.

    c) Apart from this difference in approach, another decision is about the period to be

    used in preparing the flow duration. One has to decide if a separate curve is to be

    prepared for each 10 day period, each month, each season or for the whole year.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 13Haryana –122015

    In general, the approach at a) would be more relevant for storage project where the

    storage is an element which clubs to gather the water receive.

    The approach at b) would be more relevant for the diversion structure. We have used

    both the approaches. Also, we have used the flow duration curves for comparing the

    behavior of the three sites.

    The flow data availability is already tabulated above. The data for all the three sites

    are available for the period 1989-2002.

    A plot showing the comparison of the specific flow for this period is shown below:

    This Graph Seems to indicate that in the monsoon period ,the flows of the three sites

    are some what similar. However, the flows in nonmonsoon are so low that graphical

    comparision is becoming difficult.To over come this we have ploted same graph in

    semilog format .For allowing the semilog plot, the Sukma values, where these are

    zeros, have been replaced by 0.01 lit/s/sq.km. This is shown below.

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 14Haryana –122015

    Following the approach a) more relevant to storages, the seasonal comparison of

    specific flows of the three sites are shown below:

    percentilein specificflow(lit/s/s

    q.km)

    June to Sep Oct to Jan Feb to May

    Kantamal Sukma Kesinga Kantamal Sukma Kesinga Kantamal Sukma Kesinga

    0.1 77.94 87.47 84.87 15.68 4.19 19.49 4.03 0 7.360.2 70.14 58.21 76.89 11.34 3.87 10.24 3.3 0 5.640.3 58.97 50.08 64.11 8.71 3.26 7.9 1.2 0 2.540.4 51.55 43.21 51.63 6.99 2.93 6.76 0.46 0 0.480.5 42.81 35.05 43.36 5.55 2.4 5.12 0.3 0 0.350.6 34.51 31.79 36.6 4.56 2.29 3.77 0.3 0 0.240.7 27.92 23.48 30.49 3.77 1.66 3.41 0.21 0 0.190.8 25.25 18.75 25.86 3.41 0.63 2.68 0.19 0 0.10.9 17.61 8.91 16.89 2.03 0.13 1.66 0.13 0 0.07

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 15Haryana –122015

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 16Haryana –122015

    percentile in specificflow(lit/s/sq.km)

    Annual Flow(June to May)

    Kantamal Sukma Kesinga

    0.1 34.795 30.485 38.112

    0.2 27.251 24.477 28.317

    0.3 23.188 19.769 23.394

    0.4 19.401 15.490 18.877

    0.5 17.117 12.716 15.840

    0.6 13.438 11.895 14.380

    0.7 11.696 8.746 12.866

    0.8 10.650 7.063 9.254

    0.9 6.892 3.162 7.064

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 17Haryana –122015

    These figures clearly shows that the monsoon and annual specific flows of three sites

    have very similar probabilities of exceedance, with the Sukma site showing slighty

    lowers flows. The Sukma sites has a smaller catchment area, more comparbale with

    the proposed dam catchment as compared to the other two sites.However, the Sukma

    site is on another river Suktel, while Kantamal and Kesinga are on the same river on

    which dam is proposed. On the overall, the use of Kantamal specific flows for

    building up of the monsoon in flows at the dam site appeares to be a better

    methodology.

    The comparision of the exceedance probabilities for the Autumn winter season of Oct

    to Jan tells a different story. While the specific flows of Kantamal and Kesinga are

    comparable, the specific flows for Sukma are very much lower. These values, in

    general, are ½ to 1/3 of the values for Kantamal and Kesinga.If this is due to the

    Geology of the Sukma catchment, these properties may not be very relavant for the

    proposed dam on Tel river. However if these reduction are due to smallness of the

    catchment and the consequent absensce of the “in bank” storage in the alluviam,

    these would be relavant to Tel dam. To get a better inside into these, we make

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 18Haryana –122015

    monthly comparision of the exceedance probabilities at these three sites, using the

    methdology at “b)” described earlier. These are shown below.

    10 Daily flow duration curve for Oct - Comparison between the three sites

    Probability of Excedence Kantamal Sukma Kesinga

    0.05 67.501 43.671 67.901

    0.1 31.597 20.190 27.420

    0.15 24.233 12.605 25.560

    0.2 20.751 10.683 19.637

    0.25 19.902 8.291 17.341

    0.3 17.301 7.767 15.934

    0.35 15.336 7.655 13.022

    0.4 13.732 7.604 11.169

    0.45 12.637 7.200 9.434

    0.5 11.497 6.492 8.735

    0.55 9.817 5.583 7.723

    0.6 8.777 5.030 6.572

    0.65 8.018 4.609 5.070

    0.7 6.245 2.988 4.601

    0.75 5.426 2.278 4.072

    0.8 4.348 1.861 3.524

    0.85 3.684 1.680 2.849

    0.9 2.933 1.135 2.217

    0.95 2.561 0.832 1.910

  • Tel Integrated Multipurpose Project Feasibility Report

    WAPCOS Limited76-C, Sector-18, Gurgaon 5 - 19Haryana –122015

    10Daily flow duration curve for Nov - Comparison between the three sites

    Probability ofExcedence

    Kantamal Sukma Kesinga

    0.05 20.110 17.753 20.1720.1 14.573 12.242 17.2100.15 13.520 7.876 14.6870.2 12.121 7.650 12.6050.25 10.237 7.505 11.4740.3 9.447 6.608 10.1760.35 8.563 6.049 8.1760.4 7.721 4.417 6.2740.45 7.02