Techno-Economic Feasibility Study Report...Integrated Steel Plant of JSW Steel Limited (JSWSL) Draft...
Transcript of Techno-Economic Feasibility Study Report...Integrated Steel Plant of JSW Steel Limited (JSWSL) Draft...
JSW Infrastructures Ltd.
August 2018
SJSP
Development of Multi-Cargo Captive Jetty(ies) in River Jatadhari for Integrated Steel Plant of JSW Steel Limited (JSWSL)
Techno-Economic Feasibility Study Report
Final Report
Techno-Economic Feasibility Report
Development of Multi-Cargo Captive
Jetty(ies) Port on River Jatadhari, for the
Integrated Steel Plant of JSW Steel Limited
(JSWSL)
Draft Techno-Feasibility Study Report
August 2018
JSW Centre, Bandra Kurla Complex, Bandra (E). Mumbai - 400051 India Tel: +91 42865006 e-mail: rashmiranjan.patra@ jsw.in
Project Development of Multi-Cargo Captive Jetty(ies) in River
Jatadhari, for the Integrated Steel Plant of JSW Steel
Limited (JSWSL)
Project No
P 08172018
Authors Various
Date:
August 2018
Approved by:
Internal
4 Final Report - Rev 08 06.08.2018
3 Final Report - Rev 07 28.06.2018
2 Draft Final Report 09.03.2018
1 Draft Final report 04.09.2017
0 Draft Report 28.08.2017
Revision Description By Checked Approved Date
Key words Lagoon Bay of Bengal Breakwater Dredging Reclamation
Classification
Open
Internal
Proprietary
Distribution No of copies
JSWSL: JSWIL:
1+PDF
Techno-Economic Feasibility Report
CONTENTS
1 Introduction ................................................................................................................................................... 1 1.1 Background ................................................................................................................................................... 1 1.2 Need and Justification of the Project............................................................................................................. 4 1.3 Objective of the Report ................................................................................................................................. 6 1.4 Scope of the Report ...................................................................................................................................... 7 1.5 Developer Credential .................................................................................................................................... 8 1.6 Outline of the report .................................................................................................................................... 10
2 Site Condition .............................................................................................................................................. 11 2.1 Geographical Location ................................................................................................................................ 11 2.2 Jatadhari Coastline ..................................................................................................................................... 11 2.3 Tides and Tidal Currents ............................................................................................................................. 12 2.3.1 Tidal Levels ................................................................................................................................................. 12 2.3.2 Tidal Currents ............................................................................................................................................. 13 2.4 Climate ........................................................................................................................................................ 13 2.4.1 General ....................................................................................................................................................... 13 2.4.2 Rainfall ........................................................................................................................................................ 14 2.4.3 Temperature ............................................................................................................................................... 14 2.4.4 Relative Humidity ........................................................................................................................................ 14 2.4.5 Visibility ....................................................................................................................................................... 14 2.5 Wind and Wave conditions ......................................................................................................................... 14 2.5.1 Wind conditions ........................................................................................................................................... 14 2.5.2 Offshore wave conditions ............................................................................................................................ 15 2.6 Storms and Cyclones .................................................................................................................................. 17 2.6.1 General ....................................................................................................................................................... 17
3 Site Investigations ....................................................................................................................................... 18 3.1 General ....................................................................................................................................................... 18 3.2 Data Analysis .............................................................................................................................................. 18 3.2.1 Tidal Level................................................................................................................................................... 18 3.2.2 Current ........................................................................................................................................................ 19 3.2.3 Wave measurements .................................................................................................................................. 20 3.2.4 Water Sample ............................................................................................................................................. 21 3.2.5 Grain size distribution ................................................................................................................................. 22
4 Wind and wave Conditions ......................................................................................................................... 23 4.1 General ....................................................................................................................................................... 23 4.2 Normal Wave conditions - Offshore ............................................................................................................ 23 4.2.1 Analysis of Ship Observed Data (IMD) ....................................................................................................... 23 4.2.2 Analysis of UKMO Data .............................................................................................................................. 25 4.2.3 Exceedance Probability Tables ................................................................................................................... 32 4.3 Normal Conditions – Near shore ................................................................................................................. 46 4.4 Extreme Conditions ..................................................................................................................................... 48 4.4.1 Hindcasting of cyclonic storm waves .......................................................................................................... 48 4.4.2 Extreme Value Analysis .............................................................................................................................. 53 4.5 Breakwater Design Parameters .................................................................................................................. 55
5 Traffic Projections ....................................................................................................................................... 56 5.1 General ....................................................................................................................................................... 56 5.2 Requirements of Raw Material (Project Report of ISP) ............................................................................... 56 5.3 Outward Cargo Movement from the Captive Jetty(ies) ............................................................................... 58
Techno-Economic Feasibility Report
Development of all-weather green Field Jetty(ies) at
Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
iii
5.3.1 IBRM ........................................................................................................................................................... 58 5.3.2 Steel Products ............................................................................................................................................. 58 5.3.3 Clinker and Cement .................................................................................................................................... 58 5.3.4 Alternate Fuel for Steel Plant ...................................................................................................................... 58 5.4 Total Traffic at the Captive Jetty(ies) .......................................................................................................... 59
6 Captive Jetty(ies) Planning ......................................................................................................................... 60 6.1 General ....................................................................................................................................................... 60 6.2 Identifying location for the Captive Jetty(ies) .............................................................................................. 60 6.2.1 General Comments on the 3 Sites ............................................................................................................. 61 6.2.2 Depths......................................................................................................................................................... 62 6.2.3 Sedimentation ............................................................................................................................................. 62 6.2.4 Protection from Wave action ....................................................................................................................... 62 6.2.5 Subsoil Conditions ...................................................................................................................................... 63 6.2.6 Backup Land ............................................................................................................................................... 63 6.2.7 Connectivity ................................................................................................................................................ 64 6.2.8 Environmental Concerns ............................................................................................................................. 69 6.2.9 Capital and Maintennace cost ..................................................................................................................... 69 6.2.10 Multi-criteria Analysis and Selection of Site ................................................................................................ 69 6.3 Functional Planning of Captive Jetty(ies) Facilities ..................................................................................... 70 6.3.1 Conceptual Planning ................................................................................................................................... 70 6.3.2 Ships Sizes Expected at the Captive Jetty(ies) ........................................................................................... 71 6.3.3 Number of Ship Calls .................................................................................................................................. 74 6.3.4 Handling Capacity and Number of Berths ................................................................................................... 75 6.3.5 Channel Alignment and Dimensions ........................................................................................................... 78 6.3.6 Land Area Requirements ............................................................................................................................ 83 6.3.7 Storage Requirements ................................................................................................................................ 85 6.3.8 Buildings ..................................................................................................................................................... 92 6.3.9 Ships’ Operational Areas ............................................................................................................................ 93 6.4 Design of Berths and Breakwater ............................................................................................................... 94 6.4.1 General ....................................................................................................................................................... 94 6.4.2 Breakwaters ................................................................................................................................................ 94 6.4.3 Structure for Berthing Face ......................................................................................................................... 97 6.4.4 Design Basis for the Berths and estate level ............................................................................................ 101 6.5 Captive Jetty(ies) Layout Options ............................................................................................................. 102
7 Material Handling Systems & Equipment .................................................................................................. 103 7.1 General ..................................................................................................................................................... 103 7.2 Concepts ................................................................................................................................................... 103 7.3 Coal Handling ........................................................................................................................................... 104 7.3.1 In - Captive Jetty(ies) Storage for Cargo Handling ................................................................................... 104 7.3.2 Handling System ....................................................................................................................................... 105 7.3.3 Unloading of coal ...................................................................................................................................... 107 7.3.4 Conveying ................................................................................................................................................. 107 7.3.5 Stacking .................................................................................................................................................... 108 7.3.6 Coal Stack Yard ........................................................................................................................................ 109 7.3.7 Stockpile Dust Control .............................................................................................................................. 109 7.3.8 Continuous belt weighing .......................................................................................................................... 110 7.3.9 Sampling ................................................................................................................................................... 110 7.3.10 Reclaiming ................................................................................................................................................ 110 7.3.11 Supplying to the Daily Bins of the Plants .................................................................................................. 110 7.3.12 Control System for Coal Handling ............................................................................................................. 110 7.4 Lime Stone ................................................................................................................................................ 112
Techno-Economic Feasibility Report
Development of all-weather green Field Jetty(ies) at
Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
iv
7.4.1 Storage ..................................................................................................................................................... 112 7.4.2 Handling System ....................................................................................................................................... 112 7.4.3 Unloading of Limestone ............................................................................................................................ 112 7.4.4 Conveying ................................................................................................................................................. 112 7.4.5 Reclaiming ................................................................................................................................................ 113 7.5 Finished Steel Product .............................................................................................................................. 113 7.5.1 Storage ..................................................................................................................................................... 113 7.5.2 Handling System ....................................................................................................................................... 113 7.5.3 Conveying ................................................................................................................................................. 113 7.6 LNG .......................................................................................................................................................... 114 7.6.1 General ..................................................................................................................................................... 114 7.6.2 Safety Distances ....................................................................................................................................... 115 7.6.3 Process Flow Optimization ....................................................................................................................... 117 7.6.4 Accessibility .............................................................................................................................................. 118 7.6.5 Marine Facilities ........................................................................................................................................ 119 7.6.6 Storage Area ............................................................................................................................................. 119 7.7 Equipment Requirements for the Jatadhari Captive Jetty(ies) .................................................................. 120
8 Infrastructure Facilities .............................................................................................................................. 121 8.1 Background Discussions ........................................................................................................................... 121 8.1.1 General ..................................................................................................................................................... 121 8.1.2 Navigational Aids ...................................................................................................................................... 121 8.1.3 Harbour Crafts/ Togs ................................................................................................................................ 122 8.1.4 Potable water supply ................................................................................................................................. 123 8.1.5 Fire Fighting System ................................................................................................................................. 124 8.1.6 Drainage / Sewage System ...................................................................................................................... 124 8.1.7 Sewage System ........................................................................................................................................ 125 8.1.8 Bunkering System ..................................................................................................................................... 125 8.1.9 Electrical Systems ..................................................................................................................................... 125 8.2 Miscellaneous Services ............................................................................................................................ 128 8.2.1 EDI Facilities ............................................................................................................................................. 128
9 Cost Estimates & Financial Analysis ......................................................................................................... 130 9.1 General ..................................................................................................................................................... 130 9.2 Construction Schedule .............................................................................................................................. 130 9.3 Basis of Cost Estimates ............................................................................................................................ 131 9.4 Financial Evaluation .................................................................................................................................. 132 9.4.1 Assumptions ............................................................................................................................................. 132 9.4.2 Internal Rate of Return .............................................................................................................................. 133 9.4.3 Internal Rate of Return .............................................................................................................................. 133 9.5 Calculation of Tariff Scenarios at Paradip Port – Bulk Handling ............................................................... 133
10 Benefits of the development ..................................................................................................................... 134
11 Conclusions and Recommendations......................................................................................................... 135 11.1 Conclusions .............................................................................................................................................. 135 11.2 Recommendations .................................................................................................................................... 135 11.2.1 Studies to be undertaken .......................................................................................................................... 135
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhar
Muhan, Jagatsinghpur
JSW Infrastructures Limited
xvi
Tables
Table 2-1: Tidal variation during the month of September 2008 relative to Chart Datum (Source: Cmap) ......................... 13
Table 3-1: Total suspended solids (TSS) and chloride (Cl) concentration in the streams joining Mahanadi ...................... 22
Table 3-2: Grain size distribution for material collected from the isolated waterfront near the proposed site ..................... 22
Table 4-1: Estimated significant wave heights for sea, Hm0,sea (m) at –20m CD return periods corresponding to
6hr/week, 6hr/ year and 6hr/10 year. ......................................................................................................................................... 25
Table 4-2: Estimated significant wave heights for sea, Hm0, sea (m) according to the specified return periods for some
significant directions for UKMO data .......................................................................................................................................... 31
Table 4-3: Estimated significant wave heights for swell, Hm0, swell (m) according to the specified return periods for
significant directions for UKMO data .......................................................................................................................................... 31
Table 4-4: Estimated Resultant wave height, Hm0 (m) according to the specified return periods for some significant
directions for UKMO data ........................................................................................................................................................... 32
Table 4-5: Exceedance probability of the sea waves near Paradip .................................................................................... 33
Table 4-6: Exceedance probability of the swell waves near Paradip .................................................................................. 33
Table 4-7: Exceedance probability of the Resultant wave near Paradip ............................................................................. 33
Table 4-8: Meteorological Data for the 1999 Cyclone ......................................................................................................... 50
Table 4-9: Hind-casting of Waves ....................................................................................................................................... 51
Table 5-1: Annual Raw material (net and dry basis) Requirements (in million tonnes per year) ........................................ 57
Table 5-2: Annual Raw material Requirements to be met by the Proposed Captive Jetty(ies) (in million tonnes per year)57
Table 5-3: Projected Traffic for the Captive Jetty(ies) facility (in million tonnes) ................................................................. 59
Table 6-1: Transporation preference for the Projected Traffic for the Captive Jetty(ies) facility ......................................... 68
Table 6-2: Multi-Criteria Analsis for the Captive Jetty(ies) facility ....................................................................................... 70
Table 6-3: Total Traffic (in Million tonnes) ........................................................................................................................... 72
Table 6-4: Assumed ship sizes for various products ........................................................................................................... 73
Table 6-5: Ship calls for the current Cargo ......................................................................................................................... 74
Table 6-6: Average ship size and number of ship trips (Based on Table 6.5) .................................................................... 77
Table 6-7: Number of berths and unloading rate cosidered for the commodities. .............................................................. 78
Table 6-8: Width calculations for approach channel ........................................................................................................... 80
Table 6-9: Stack Volume Quantity Basis ............................................................................................................................. 84
Table 6-10: Stack Volume Quantity Basis ........................................................................................................................ 84
Table 6-11: Berth Length and Back up Area (Berth area) ................................................................................................ 85
Table 6.12: Determination of the Stockyard Area for Coal............................................................................................... 87
Table 6.13: Determination of the Stack yard Area for IBRM ............................................................................................ 88
Table 6.14: Determination of the Stack yard Area for Cement ........................................................................................ 89
Table 6.15: Determination of the Stack yard Area for Lime Stone ................................................................................... 90
Table 6.16: Summary of Area Requirements ................................................................................................................... 91
Table 6.17: Captive Jetty(ies) Buildings Area Requirements in Square Meters .............................................................. 93
Table 7.1: Heat radiation from Flare Stack ....................................................................................................................... 117
Table 7-2: Equipment requirements .................................................................................................................................. 120
Table 8-1: Buoy requirements at the proposed Jetty(ies) ................................................................................................. 122
Table 8-2: Estimated electricity load for the proposed Captive Jetty(ies) ......................................................................... 126
Table 9-1: Cost Estimate for the Project ........................................................................................................................... 131
Table 9-2: Sensitivity analysis ........................................................................................................................................... 133
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhar
Muhan, Jagatsinghpur
JSW Infrastructures Limited
xvii
Figures
Figure 1-1: Location of the planned steel plant and the Captive Jetty on the East Coast of India .................................... 2
Figure 1-2: Location of the Proposed development vis-à-vis the Paradip Port ................................................................. 3
Figure 1-3: Location of the Proposed development vis-à-vis the Paradip Port ................................................................. 3
Figure 1-4: Location of the Proposed development vis-à-vis the IOC & Paradip Port ....................................................... 5
Figure 2-1: Geographical Location of the Proposed development & the Paradip Port .................................................... 11
Figure 2-2: Coastline near the proposed site .................................................................................................................. 12
Figure 2-3: Tidal variation near the Paradip Port............................................................................................................. 13
Figure 2-4: Wind rose diagram (source: IMD, Data 1973 – 2015)................................................................................... 15
Figure 2-5: Resultant Wave Height rose diagram (source: IMD, Data 1973 – 2015) ...................................................... 16
Figure 2-6: Resultant Wave Period rose diagram (source: IMD, Data 1973 – 2015) ...................................................... 16
Figure 3-1: Location of the field measurements .............................................................................................................. 18
Figure 3-2: Water levels at the site near Paradip ............................................................................................................ 19
Figure 3-3: Current speed and direction at offshore location during 12th to 19th December, (top) and 21th to 28th
December, (bottom) ................................................................................................................................................................... 19
Figure 3-4: Variation of predominant wave direction near site at offshore ...................................................................... 20
Figure 3-5: Variation of predominant wave direction near site at offshore ...................................................................... 20
Figure 3-6: Variation of maximum wave height near site at offshore .............................................................................. 20
Figure 3-7: Variation of zero crossing wave period near site at offshore ........................................................................ 21
Figure 3-8: Salinity and temperature at an offshore location ........................................................................................... 22
Figure 4-1: Exceedence probability curves for the near shore significant wave height (Hm0) at –20m CD offshore of the
proposed facility (Top: All, NE, ENE & Bottom: SE,SW, SSW ................................................................................................... 24
Figure 4-2: Time series of the three Hm0–parameters. Top: Significant wave height for resultant wave condition (Hm0,
sea). Middle: Significant wave height for sea only (Hm0, swell) Bottom: Significant wave height for swell wave (Hm0, res);
(source: UKMO, Data set: 1999 – 2008) .................................................................................................................................... 26
Figure 4-3: Wave rose for resultant wave height (source: UKMO, 1999 – 2008) ............................................................ 27
Figure 4-4: Resultant wave period (source: UKMO, Data set: 1999 – 2008) .................................................................. 27
Figure 4-5: Wave rose for sea wave height (source: UKMO, 1999 – 2008) .................................................................... 28
Figure 4-6: Sea wave period (bottom) (source: UKMO, Data set: 1999 – 2008) ............................................................. 28
Figure 4-7: Wave rose for swell wave height (source: UKMO, 1999 – 2008).................................................................. 29
Figure 4-8: Swell wave period (source: UKMO, Data set: 1999 – 2008) ......................................................................... 29
Figure 4-9: Scatter plots of the offshore UKMO wave data. The significant wave height (Hm0) and the mean zero-
crossing period (T02) versus the wave direction (in radians). Top: Resultant only. Middle: Sea only, Bottom: Swell waves;
(source: UKMO, Data set: 1999 – 2008) .................................................................................................................................... 30
Figure 4-10: Exceedence probability curves for the significant sea wave height (Hm0) (source: UKMO, 1999 – 2008) .. 31
Figure 4-11: Exceedance probability curves for the significant swell wave height (Hm0) (source: UKMO, Data set: 1999
– 2008) 32
Figure 4-12: Exceedance probability curves for the Resultant wave height (Hm0) (Source: UKMO, Data Set: 1999 –
2008) 32
Figure 4-13: Bathymetry used for SW module .................................................................................................................. 46
Figure 4-14: Resultant Wave Height at 5 m depth near proposed Jetty............................................................................ 47
Figure 4-15: Resultant Wave Period at 5 m depth near proposed Jetty(ies)..................................................................... 47
Figure 4-16: Resultant Wave Height at 10 m depth near proposed Jetty(ies)................................................................... 47
Figure 4-17: Resultant Wave Period at 10 m depth near proposed Jetty(ies)................................................................... 48
Figure 4-18: Model bathymetry for the Bay of Bengal for Mike 21 SW Input .................................................................... 49
Figure 4-19: Storm tracks of 1999 applied for the simulation of the SW Model ................................................................ 49
Figure 4-20: Computed surface elevation/ storm surge over the Bay of Bengal ............................................................... 51
Figure 4-21: Surface elevation plots for the 1999 cyclone ................................................................................................ 51
Figure 4-22: Frequency plot for the Cyclonic data indicating Log normal distribution matches the best with the data ..... 54
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhar
Muhan, Jagatsinghpur
JSW Infrastructures Limited
xviii
Figure 4-23: Maximum probable wave heights in the fetch with Log-Normal distribution ................................................. 55
Figure 5-1: The slurry pipe line connecting the 3 prespective mines in the Joda-Barbil area and the Captive Jetty(ies)
facility 56
Figure 6-1: Location of the Proposed Captive Jetty(ies) ................................................................................................. 61
Figure 6-2: Location of the Captive Jetty(ies) water area and fore shore facilities at Site 3............................................ 64
Figure 6-3: Railway Map of State of Odisha (East Coast Railway) ................................................................................. 65
Photograph 6-4: Trunk line from Paradip to Cuttack ...................................................................................................... 65
Photograph 6-5: Double line from Paradip to Cuttack in opertaion ................................................................................ 66
Figure 6-6: Proposed Haridaspur-Paradip Rail Link ........................................................................................................ 67
Figure 6-7: Existing road network near the Captive Jetty(ies) ......................................................................................... 68
Figure 6-8: Provisonal Channel Allignment ..................................................................................................................... 79
Figure 6-9: Channel depth components .......................................................................................................................... 82
Figure 6.10: Planning Chart for Dry Bulk Cargo ................................................................................................................ 86
Figure 6-11: Typical section of the breakwater at – 2.0 m Contour CD............................................................................. 97
Figure 6-12: Typical plan and section of the bulk berth ................................................................................................... 101
Figure 6-13: Suggeted Preliminary Layout of the Porposed Captive Jetty(ies) ............................................................... 102
Figure 7-1: Typical unloader working at the ship ........................................................................................................... 107
Figure 7-2: Typical unloader and stacker-reclaimers in the cargo flow chain................................................................ 109
Figure 7-3: Typical mobile harbour crane to be used for steel products ....................................................................... 113
Figure 7-4: LNG Supply Chain ...................................................................................................................................... 114
Figure 9-1: Construction schedule for the proposed Captive Jetty(ies)......................................................................... 131
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhar
Muhan, Jagatsinghpur
JSW Infrastructures Limited
xix
SYMBOLS AND ABBREVIATIONS
Symbols and abbreviations used are generally in accordance with the following list.
1 Proper names and organisations - India
BIS .......... Bureau of Indian Standards
IAPH.................The International Association of Ports and Harbours
OCZMA ....... Odisha Coastal Zone Management Authority
IDCOL ........ Industrial Development Corporation of Odisha Limited
IPICOL..............Industrial Promostion and Investment Corporation of Odisha
Limited
MLDB ......... Main Lighting Distribution Board
OSEB…………….Odisha State Electricity Board
MoEF&CC ...... Ministry of Environment, Forests & Climate Change
MoS .......... Ministry of Shipping
OSPCB ........ Odisha State Pollution Control Board
CESU ......... Central Electrical Supply Utility of Odisha
NHO .......... National Hydro graphic Office, Dehra Dun
OCIMF..............The Oil Companies International Marine Forum
PIANC ........ Permanent International Association of Navigation Congress
SIGTTO.............Society of International Gas Tankers & Terminal Operators Ltd.
SoI………………Survey of India
2 Proper names and organisations – Other
BA ........... British Admiralty
BS ........... British Standard
IMO .......... International Maritime Organization
IMD....................Indian Metereological Department
ISPS ......... International Ship and Port facility Security code
UTM .......... Universal Transverse Mercator (map projection)
WGS .......... World Geodetic System (ellipsoid for map projection)
UKMO................United Kingdom Meteorological Office
3 Other abbreviations
Approx. ...... approximately
cif .......... cost, insurance, freight
dia .......... diameter
feu .......... forty foot equivalent unit (container)
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhar
Muhan, Jagatsinghpur
JSW Infrastructures Limited
xx
fob .......... free on board
max .......... maximum
min .......... minimum
No ........... number (order) as in No 6
nr ........... number (units) as in 6 nr
Panamax ...... ship of max permissible beam of 32.2m for transiting the Panama
Canal
Cape..................ship of maximum carrying capacity of 180,000 T
ppt .......... parts per thousand
teu .......... twenty-foot equivalent unit (container)
BOOT ......... Build – Own - Operate – Transfer
CCTV ......... Closed Circuit Television
CD ........... Chart DatumCSR Corporate Social Responsibility
CBRM………….Coal bearing raw material
DPR .......... Detailed Project Report
EIA .......... Environmental Impact Assessment
HAT .......... Highest Astronomical Tide
ICD .......... Inland Container Depot
IBRM…………..Iron bearing raw material
IT ........... Information Technology
LAT .......... Lowest Astronomical Tide
LOA .......... Length overall (of a ship)
LCL .......... Less Than Container Load / Consolidation Containers
M ............ “mega” or one million (106)
MHWS ......... Mean High Water Spring tides
MHS……………Material Handling System
MLWS ......... Mean Low Water Spring tides
MSL .......... Mean Sea Level
MoU .......... Memorandum of Understanding
MVA……………Mega volt ampere
SEZ .......... Special Economic Zone
ToR .......... Terms of Reference
VTMS ......... Vessel Traffic Management System
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhar
Muhan, Jagatsinghpur
JSW Infrastructures Limited
xxi
4 Units of measurement
Length, area and volume
mm ........... millimetre(s)
m ............ metre(s)
km ........... kilometre(s)
n. mile ...... nautical mile(s)
mm2 .......... square millimetre(s)
m2 ........... square metre(s)
km2 .......... square kilometre(s)
ha ........... hectare(s)
m3 ........... cubic metre(s)
Time and time derived units
s ............ second(s)
min .......... minute(s)
h ............ hour(s)
d ............ day(s)
wk ........... week(s)
mth .......... month(s)
yr ........... year(s)
mm/s ......... millimetres per second
km/h ......... kilometres per hour
m/s .......... metres per second
knot ......... nautical mile per hour
Mass, force and derived units
kg ........... kilogram(s)
g ............ gram = kg x 10-3
t ............ tonne = kg x 103
displacement . the total mass of the vessel and its contents. (This is equal to
the volume of water displaced by the vessel multiplied by the
density of the water.)
DWT .......... Dead Weight Tonne, the total mass of cargo, stores, fuels, crew and
reserves with which a vessel is laden when submerged to the summer
loading line. (Although this represents the load carrying capacity
of the vessel it is not an exact measure of the cargo load).
Mt ........... million tonnes = t x 106
TPD...................Tonnes per day
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhar
Muhan, Jagatsinghpur
JSW Infrastructures Limited
xxii
TPH/tph.............Tonnes per hour
Other units
°C .......... degrees Celsius (temperature)
Mtpa ......... million tonnes per annum
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
1 JSW Infrastructures Limited
1 Introduction
1.1 Background
JSW Steel Limited (JSWSL), one of the leading Industrial houses of India, with interests in Steel,
Power, Cement, Infrastructure, Paint and IT. The High Level Clearance Authority (HLCA),
Government of Odisha (GoO) has in-principle approved in its meeting dated 02.06.2017 held
under Chairmanship of Hon’ble Chief Minister for setting up a 13.2 Million Tonne Per Annum
(MTPA) Integrated Steel Plant (ISP) along with 900 MW Captive Power Plant (CPP) and Captive
Jetty(ies) in the Jagatsinghpur District of Odisha with an investment of ₹71,259 Crores. The Steel
Plant, Power Plant and the Captive Jetty(ies) are proposed to be located at the mouth of the
Jatadhari Muhan River in Jagatsinghpur District. It has been proposed that JSWSL would not only
put up an Integrated steel plant, for which coking coal, limestone and other fluxes would be
brought in by sea, and iron ore concentrate, Pallets and Steel products would be sent out by sea
to various consumption centres along the east and west coastlines of India and abroad. It is
propounding to construct a deep water direct berthing Jetty(ies) on the riverfront of Jatadhari
Muhan River fronting the steel plant in order to facilitate the movement of raw material and
finished products at the least cost. The steel plant along with the Captive Jetty(ies) would form
an integrated system and would entail savings in the cost of production and overall boost to the
industrialisation efforts of the national as well as the Government of Odisha.
The facility is being planned with a contemplated investment of ₹71,259 Crores, by JSWSL, would
result in production of 13.2 MTPA steel and a Captive Jetty(ies) facility that would have equipped
to handle about 52 MTPA. The construction of the steel plant is on the aegis of the JSWSL and
the Captive Jetty(ies) facility by the Infrastructure arm of the JSW Group, M/s JSW Infrastructures
Limited (JSWIL). To initiate the process of permissions and licences to develop and construct
the Captive Jetty(ies), the current techno-economic feasibility report (TEFR) is prepared using
the in house expertise of JSWIL. There are two clear objectives of the present TEFR. The first
objective is to present the facility requirement and the developmental philosophy of the Captive
Jetty(ies) facility in the Jatadhari Muhan Estuary, and secure approval of the Government of
Odisha (GoO). Secondly, the report would form the basis for the Terms of Reference (ToR) for
preparation of Environmental Impact assessment (EIA)/ Environmental Management Plan (EMP)
for the Captive Jetty(ies), to be prepared by a duly accredited consultant, leading to obtaining
Coastal Regulatory Zone (CRZ) & Environmental Clearance (EC) from Ministry of Environment,
Forest and Climate Change (MoEF&CC), Government of India (GoI).
The broad scope of the report is to deal with the feasibility design of the harbour facilities, along
with the likely impacts of the development on the river morphology by comparing the existing
conditions with the simulated conditions of the future. In addition, the report would set the tone
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
2 JSW Infrastructures Limited
of the development, by stipulating the handling parameters, the depth in the navigation channel
and the Jetty(ies) area and other parameters of defining importance. Later a more detailed Detail
Project Report shall be prepared for actually indicating the design confines and the sizing of tools
and equipment. The proposed Jatadhari Captive Jetty is approximately at 200 11.85’- 200 12.94’
N and 860 32.66’-860 34.84’ E shown in Figures 1.1 and 1.2 below. The geographical coordinates
of the Jetty approach are about 12 km to the south of the Port of Paradip, there are two small
rivers between the Mahanadi and the Devi, called the Patakund and the Jatadhari. These two
small streams between the larger rivers to the north and the south cater to their small basins. The
Jatadhari discharges in to a lagoon, separated from the sea by a 12 km long sand spit. The
proposed Jatadhari Captive Jetty(ies) is located in this lagoon.
Figure 1-1: Location of the planned steel plant and the Captive Jetty on the East Coast of India
Figure 1.2 indicates the location of the proposed Captive facility vis-à-vis the Paradip Port
located about 12.8 km (7 nautical miles) north, near the confluence of the Jatadhari River with
the sea.
Clearly, the location is influenced by the South-west and Northeast monsoon winds, with the SW
monsoon being more predominant. Average wind velocities of 20 knots and 10 knots are quite
common during SW and NW monsoons respectively.
The pre-monsoon winds of May-June and the inter-monsoon period of October often times are
associated with Cyclonic winds.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
3 JSW Infrastructures Limited
Figure 1-2: Location of the Proposed development vis-à-vis the Paradip Port
Water depths of about 20 m can be found at a distance of about 10000 m from the shoreline
(Figure 1.3).
Figure 1-3: Location of the Proposed development vis-à-vis the Paradip Port
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
4 JSW Infrastructures Limited
There are marked seasonal variations in the origin, tracks and attainment of intensities of
cyclones. The upper air circulations in the northern hemisphere are from east to west and hence
cyclones affect primarily the Bay of Bengal coast, though a few veer northward after crossing
the peninsula and affect the Arabian Sea coastline. The occurrence of cyclones is dominant in
the months of May to December, whereas in the winter months from January to March, the
frequency of occurrence is small. The Inter Tropical Convergence Zone (ITCZ) governs the area
of generation of cyclones, the cyclones being restricted to the north of the ITCZ. The ITCZ moves
northward from December to May/June, when it occupies the northern part of the Bay in May and
gradually moves southwards until December, when it reaches the southern tip of India. The path
of the cyclones is generally from east to west as mentioned earlier, the Coriolis force giving a
tendency to curve northwards. Thus, the cyclonic period along the Odisha coast is generally June
and August to November. The life span of a severe cyclonic storm in the Indian seas averages
about 4 days from the time it forms until the time it crosses the land.
There are three elements associated with a cyclone, which cause destruction:
i. Cyclones are associated with high-pressure gradients and consequent strong winds.
These, in turn, generate storm surges. A storm surge is an abnormal rise of sea level
near the coast caused by a severe tropical cyclone; as a result, seawater inundates
low-lying areas of coastal regions, drowning human beings and livestock, eroding
beaches and embankments, destroying vegetation and reducing soil fertility.
ii. Wave action is severe, causing damage to shore structures.
iii. Very strong winds may damage coastal installations, dwellings, communication
systems, trees, resulting in loss of life and property.
iv. Heavy and prolonged rains due to cyclones may cause river floods and submergence
of low-lying areas causing loss of life and property. Floods and coastal inundation
due to storm surges pollute drinking water sources causing outbreak of epidemics.
The most destructive element associated with an intense cyclone is storm surge. History indicates
that loss of life is significant when surge magnitude is 3 meters or more. The Port of Paradip had
witnessed a storm of this nature in the year 1999.
1.2 Need and Justification of the Project
High Level Clearance Authority (HLCA), Government of Odisha (GoO) has in-principle approved
in its meeting dated 02.06.2017 held under Chairmanship of Hon’ble Chief Minister for setting up
a 13.2 Million Tonne Per Annum (MTPA) along with 900 MW Captive Power Plant (CPP) & Captive
Jetty(ies) under Dist. Jagatsinghpur in Odisha with an investment of ₹71,259 Crores. The
proposed steel Plant is located near the Gadkujang, Nuagaon, Dhinkia Mouzas under the
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
5 JSW Infrastructures Limited
Jagatsinghpur district was identified maximizing use of Government land and minimizing use of
private land resulting in the minimal or no resettlement and rehabilitation issues. The site is
located to the immediate south of the Indian Oil Refinery Installations along the bank of Jatadhari
Muhan River as shown in Figure 1.4.
Figure 1-4: Location of the Proposed development vis-à-vis the IOC & Paradip Port
The proposed Steel Plant Project envisages installation of an Integrated Steel Plant (ISP) of 13.2
MTPA capacity. In addition, as indicated above the project includes a 900 MW Captive Power
Plant, dual fuel based waste gasses from the ISP and Coal. However, around 300-600 MW of
the same may have the provision of using imported thermal coal.
The integrated steel plant will be equipped with sinter plant, pellet plant, coke oven complex,
blast furnace, DR plant, steel making and casting facility, rolling mills, cement plant and captive
power plant along with captive Jetty.
The Integrated steel plant is envisaged to be established with an annual capacity of 13.2 MTPA
with a provision for expansion in future. The raw material requirement for the ISP as per the
Project report, June, 2018 is as under. It is however to be remembered that the following table
only lists the probable cargo requiring movement through sea mode in addition to the other
modes;
i. Coal bearing Raw Material (CBRM): 16.50 MTPA
ii. Flux (lime stone, quartzite etc.): 3.13 MTPA
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
6 JSW Infrastructures Limited
iii. Clinker: 5.3 MTPA
-----------------
24.93 MTPA
*1: at the 13.2 MTPA stage when the IBRM from slurry pipeline source in excess supply to be supplied to other
JSW group Companies.
In addition, the finished products from the ISP namely steel (in pellet form or in any other form)
and cement shall be shipped using the Captive Jetty. As per the initial estimates about 6 MTPA
of steel material, 6 MTPA cement and 15 MTPA of Pellets/Iron Ore Concentrate will use this mode.
Hence the total initial estimates traffic pending detailed discussions in the Chapter 5 are;
1. Inward Traffic: 24.93 MTPA
2. Outward Traffic 27.00 MTPA
-------------------
51.93 MTPA
The traffic volumes described above requires meticulous logistical planning and easy
connectivity. Parallel efforts are on to connect the ISP with road and rail network. However, the
rail network is already heavily booked and the road is in no better state. Though, a small portion
of the total raw material from the states of Jharkhand and Chhattisgarh or may be Madhya
Pradesh, all land locked states as they are, could be rail bound, majority of the requirements
would have to be met through the least congested water transport.
This justifies the tagging of the captive Jetty(ies) on the waterfront of Jatadhari Muhan River to
handle the raw material and the finished product from the plant.
1.3 Objective of the Report
The objective of the present Techno-Economic Feasibility Report is to serve two clear purposes.
A. The first purpose is to appraise the Jetty(ies) proposal from the Government of Odisha
and to initiate the process of Concession Agreement and carryout the following;
1. To draw the broad outline of the Captive Jetty(ies) indicating the operational
parameters, developmental philosophy and impact on the coastal morphology.
2. Develop the layout of the Captive Jetty(ies) for operating efficiently by integrating all
the modal connectives.
3. Devise an integrated raw material handling system (RMHS) in the coastal zone area,
for serving the need of the transit storage of the Jetty(ies) as well as supplying to the
daily bins of the production centers.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
7 JSW Infrastructures Limited
4. Design the Jetty(ies) components, namely the breakwater for tranquility if any,
approach channel, inner and outer turning circle, the berth length and storage areas
for the traffic to be handled at the Captive Jetty(ies).
5. Material handling systems and the extent of mechanisation required for the indicated
traffic.
6. Block cost estimates and financial evaluation
B. The second objective is to use the report for applying to the MoEF&CC for obtaining ToR
for the EIA & EMP report required for obtaining the clearance from Odisha State Pollution
Control Board (OSPCB), recommendation from Odisha Coastal Zone Management
Authority (OCZMA) leading to final clearance form Infrastructure and CRZ committee of
the MoEF&CC of Government of India.
1.4 Scope of the Report
The broad scope of the present report is to design an equitable system for handling of the raw
material, unitised cargo and other products through a Jetty(ies) facility, of variable depth to
handle a range of vessels on the waterfront of River Jatadhari near its confluence with the sea.
The broad scope of work includes the following;
Collection and Collation of data from secondary sources
Define Wave Climate and site conditions vis-à-vis the Jetty(ies) proposed for design
conditions for structures and normal operating conditions for the harbour.
Detailed Jetty planning, both for the water side and for the land side, in accordance with
the best international practices, duly taking in to account rail and road connectivity.
Basic Engineering: design and drawings have to be produced in order to assess the cost
of the Project to Feasibility level.
Material handling systems
Other Infrastructure and Logistics
Identify and compute the expected traffic for the Jetty(ies)
Analyze the vessel population in the world and determine the design vessel size for the
project
The facilities required in the Jetty(ies) for handling the projected traffic in the most
efficient way
The infrastructure requirements for the Captive Jetty(ies)
Material handling systems and cargo logistics
Construction schedule.
The cost estimates based on the computed time schedule for construction.
Conclusion & Recommendation.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
8 JSW Infrastructures Limited
The report would deal with the sizing of the Jetty(ies) elements and determine the feasibility of
establishment including the basic engineering for the same
1.5 Developer Credential
The JSW Group is amongst the leading conglomerates in India, with presence across the vital
sectors of the Indian economy. We are a $11 billion conglomerate, with presence across India,
USA, South America & Africa, the JSW group is a part of the O.P. Jindal Group with strong
footprints across viz. Steel, Energy, Infrastructure, Cement, Ventures and Sports.
JSW has diverse workforce of over 40,000 individuals, is known to be the “strategic first mover”
to venture away from status quo, have the conviction to make fundamental changes and drive
operational excellence. Built on a strong foundation of core values i.e. Transparency, Excellence,
Dynamism and Passion for Learning, in a short span, JSW group has grown multifold.
Technological innovations, a strong focus on sustainability and a philosophy to give back to the
communities at large set each JSW Company apart.
JSW Steel is India’s leading private sector steel producer and amongst the world’s most illustrious
steel companies with an installed capacity of 18 MTPA. JSW Steel boasts of one of the largest
blast furnace with a capacity of 3.3 MTPA, taking JSW’s overall capacity to 12 MTPA at
Vijayanagar, Karnataka, and its flagship steel plant. With its plants located across six strategic
locations in South and West India, JSW Steel will continue to raise the bar with its high quality &
diverse product range.
JSW Energy is one of the earliest private entrants into the power sector positioned strongly as a
full-spectrum integrated power company with a presence across the power sector value chain.
With 4531 MW operational capacity, it remains one of the most efficient Power Company in the
country with one of the country's largest open cast mining operation by volume and one of the
largest private sector Hydro Operator in India.
JSW Cement is currently upgrading production capacity from 6 MTPA to 20 MTPA by the year
2020. Its plants at Vijayanagar in Karnataka, Nandyal in Andhra Pradesh and Dolvi in Maharashtra
utilise slag from the JSW Steel plants to produce Green cement, which is engineered for strength
and durability. By converting industrial by-product into a useful product, it has reduced the
carbon footprint of the Group. It is currently executing expansion projects in Vijayanagar plant
(South) and Salboni (West Bengal) and gearing up to set up a plant in Jajpur (Orissa).
JSW Foundation is the social development division of the JSW Group. It works with corporate
social responsibility (CSR) teams of Group companies in addressing the critical issues relevant
to the communities, involving suitable partners (selected through a rigorous screening process)
to enable the planning and effective execution. The objective is to serve the most vulnerable
groups within communities with rightful interventions. JSW Foundation today works in 16
locations across India, in the Direct Influence Zone of JSW's plant locations and beyond.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
9 JSW Infrastructures Limited
JSW Infrastructure (JSWIL), is the infrastructure arm of the JSW Group, in its first 14 years of its
inception, has grown to become one of India’s leading Infrastructure development companies.
Its ports and terminals in Maharashtra and Goa currently have an operational capacity of 60
MTPA. Within the next three years, this is going to increase more than three-fold to reach 200
MTPA through Greenfield and brownfield expansions. This capacity is underpinned by the
assurance that comes from JSW Infrastructure’s excellent record of accomplishment of
successful operations benchmarked to international standards. Apart from port, JSWIL is also
developing rail, road, pipeline and inland water connectivity projects. Recently it has
accomplished development of a 42 km road and taken up a 35 km rail connectivity project
consisting of 18 km of tunnels. A slurry pipeline project of 250 km on the east coast of India is
being taken up to transport Iron Ore in slurry form, which can bring down the land transport cost
by 50%. In the near future JSWIL is likely to redefine a new era in the inland waterway transport
by carrying out dredging in the River and shifting from a 2000 T open barge to 8000 T Mini-bulk
carriers, which can also carry steel coils and containers.
JSWIL, is into development of ports, rail/road and inland water connectivity, development of port
based SEZ and other related infrastructure developments works along with terminal handling
operations and port management. JSWIL currently operates Jaigarh Port at Ratnagiri, Dharamtar
Facility of Jetties at Dolvi, both located in Maharashtra and Berths 5A and 6A in Mormugao Port
Trust (MPT); Goa. Having built and operate Green field ports and brown field installations, JSWIL
has experience in the all spheres of development namely, Design- Build-Finance-Operate-
Transfer (DBFOT) of Port and allied Infrastructures.
JSW Jaigarh Port Limited, a subsidiary of JSW Infrastructure Ltd., has developed an all-weather
multi-commodity Greenfield port, capable of handling vessels up to 1,80,000 DWT. The Port is
now equipped to service two vessels simultaneously with 600 m quay length and 18.5 m draft.
Another berth for capable of handling Valemax vessels of capacity up to 400,000 DWT is nearing
completion.
JSW Dharamtar Port Limited, another subsidiary of JSWIL, operates a 331.5 m Jetty, since 2011.
The Jetty is under revamp and being expanded to a total length of 1750 m with new top side
equipment. This is a riverine facility to service mini-bulk carriers of 8000 DWT. The ultimate
capacity of the Jetty would be of the order of 45 million tons per annum.
South West Ports Limited, a company owing its allegiance to JSWIL, operates berth 5A and 6A
inside the MPT. Having handled more than 60 million tons of cargo since its inception in 2004, it
has serviced 17000 rakes. The berths at SWPL facility are equipped to handle bulk and unitized
cargo using mobile equipment and back up storage and dispatch system. The in-motion wagon
loading system operational along with the wagon loaders, can handle up to 12 rakes a day.
JSWIL recently took over the operation and maintenance of the dry bulk terminal (Berth 5 and 6)
of Port of Fujairah. The aim is to improve the operation efficiency and increase the productivity
of the port from the present 15 million tons per annum (MTPA) to 24 MTPA.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
10 JSW Infrastructures Limited
JSW Paradip Terminal Private Limited, another SPV under the JSWIL, is developing an Iron Ore
export terminal inside the Paradip Port. The Terminal is expected to go in to operation in March,
2018. This facility, developed on a BOOT basis, would consist of a 370 m berth and when
developed would be capable of handling up to Cape Size vessels.
Yet another SPV, East Quay Coal Terminal Limited, is developing a 680 m long Coal export terminal
inside the Paradip Port, with an annual capacity of 30 MTPA.
With the above background and expertise, JSWIL is very well equipped to develop port,
associated infrastructures, and are entrusted by the group to carry out the facility development
for the port.
1.6 Outline of the report
The current feasibility study report would describe the various facets of Captive Jetty(ies)
development, in the following chapters;
Chapter 1 Introduction
Chapter 2 Site Conditions
Chapter 3 Site Investigations
Chapter 4 Wind and Wave Conditions
Chapter 5 Traffic Projections
Chapter 6 Planning of the Jetty(ies)
Chapter 7 Material handling Systems & Equipment
Chapter 8 Infrastructure facilities
Chapter 9 Cost Estimates and Financial Evaluation
Chapter 10 Benefits from the Project
Chapter 11 Conclusion and Recommendations
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
11 JSW Infrastructures Limited
2 Site Condition
2.1 Geographical Location
The state of Odisha one of the richest states in the country with regard to the minerals and natural
resources. Bestowed with immense minerals and water resources, the state has been not lived
up to its complete potential. The proposed Captive Jetty(ies) facility to be set up as a part of the
integrated steel plant project approved in principle by Government of Odisha, for handling its
own cargo. Located about 12 km south of the Paradip Port, on the riverfront of the Jathadhari
River, very close to its confluence with the Bay of Bengal. The location on the map of Odisha
and the blow up indicating the proposed Captive Jetty(ies) location vis-à-vis the Paradip port
can be seen from the Figure 2.1. The approximate location of the Captive Jetty(ies) is
approximately at 200 11.85’- 200 12.94’ N and 860 32.66’-860 34.84’ E.
Figure 2-1: Geographical Location of the Proposed development & the Paradip Port
2.2 Jatadhari Coastline
The coastline on the eastern coast of India in the Bay of Bengal has mildly sloping sandy areas
as shown below in Figure 2.2. The shoreline near Paradip is pierced by many rivers and river lets
as the area falls under the so-called Mahanadi Delta. The proposed location is about 12-13 km
from the Paradip Port.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
12 JSW Infrastructures Limited
Figure 2-2: Coastline near the proposed site
The depths are better on the south than the north, with the 10 m contour at a distance of about
4 km from the coastline and 20 m contour about 10 -12 kilometres. The location of the Jetty(ies)
and the approach channel is outside the notified boundaries of the Paradip Port.
River Mahanadi is the largest river of Orissa with its origin in the hills of Madhya Pradesh. It has
a maximum discharge of 6352 m3/s and a minimum discharge of 759 m3/s. The average annual
discharge of about 1900 m3/s is reported. In comparison, the Jatadhari river discharges are low
and minuscule.
The inner estuary of Jatadhar River is sandy and marked by high banks, except at places where
there are plain beaches. The estuary is bereft of any waves and only affected by tidal flows.
2.3 Tides and Tidal Currents
2.3.1 Tidal Levels
The information on tidal levels for Paradip Port as per Naval Hydrographic Chart 3010, with
reference to the datum of soundings, is as given below in Table 2.1. The tide is semidiurnal with
a spring neap variation. An example of the tidal variation for the month of September 2016 for
Paradip Port is shown in Figure 2.3.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
13 JSW Infrastructures Limited
Table 2-1: Tidal variation during the month of September 2008 relative to Chart Datum (Source: Cmap)
Sl. No. Description Tidal Height
1 Mean High Water Springs 2.58 m
2 Mean High Water Neaps 2.02 m
3 Mean Sea Level 1.66 m
4 Mean Low Water Neaps 1.32 m
5 Mean Low Water Springs 0.71 m
Figure 2-3: Tidal variation near the Paradip Port
2.3.2 Tidal Currents
Currents are mostly tidal in nature though near shore currents do get modified by the high
discharges from the River Mahanadi. Density currents are also noticed due to fresh water
discharges in the lower estuary. Maximum currents of 2 knots have been observed.
2.4 Climate
2.4.1 General
The climate of this region is governed by its location in the tropics and by the monsoon. Annually
recurring monsoons divide the year in to three seasons as follows:
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
14 JSW Infrastructures Limited
i. The pre monsoon period (spring) from March to May, a time of the year having hot
climate, with the month of May being the hottest
ii. The south-west monsoon prevailing from June to September with mainly south-westerly
winds and
iii. The post monsoon period (autumn) from October to February with north-westerly winds.
Information on general climatic condition is available is the Bay of Bengal Pilot for the Cuttack
City which is about 60 km from the location and is considered to be applicable.
2.4.2 Rainfall
The annual average rainfall in the area is approximately 1480 mm. Rain fall in the month of January
and February is about 48.62 mm, March to September: 1209.04 mm & October to December:
169.32 mm.
91% of which occurs in the months of June, July, August and September.
2.4.3 Temperature
January is the coldest month with lowest temperature of 110 C. Similarly, the month of May is the
hottest month with temperatures up to 370 C.
2.4.4 Relative Humidity
The average humidity ranges from nearly 84% in August to about 71% in December.
2.4.5 Visibility
The general visibility in the area is good. Visibility in the monsoon normally deteriorates during
rains and occasional squalls.
2.5 Wind and Wave conditions
Indian Meteorological Department (IMD), reports visually observed data reported by ships (VOS
data), is available for the area. The data consist of magnitude and direction of wind and wave
for a grid of 20 Latitude x 20 Longitude cantering the site. In the following paragraphs an analysis
of these data is given.
2.5.1 Wind conditions
Figure 2.4 shows that the offshore wind climate is dominated by South-westerly monsoon winds,
essentially meaning that the monsoon wind dictates the predominant wind directions.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
15 JSW Infrastructures Limited
Similar wind pattern can be seen for the NW monsoon when the wind directions are in the N-
NNE quadrant. The average wind speeds during SW monsoon are about 12 - 16 m/s and during
the NW monsoon, it is around 8 to 10 m/s.
Figure 2-4: Wind rose diagram (source: IMD, Data 1973 – 2015)
2.5.2 Offshore wave conditions
The offshore wave data from the IMD were analysed and given as Figure 2.5 and 2.6.
Figure 2.5 shows the significant wave heights (Hm0) for the waves. It could be seen that, the
maximum Hm0 for the wave condition is about 4.5 m. This is probably due to the mixing of
cyclonic data, which might have been reported by the ships. In the monsoon wave heights up to
3.0 m is quite common. In the non-monsoon time however, much lower wave heights are
experienced.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
16 JSW Infrastructures Limited
Figure 2-5: Resultant Wave Height rose diagram (source: IMD, Data 1973 – 2015)
Similarly, as far as the wave periods are concerned, the maximum waves conform to the 10 to
12 seconds band. Longer period waves up to 16 seconds are also found. The annual distribution
of wave period in the form of a rose diagram is shown as Figure 2.6.
Figure 2-6: Resultant Wave Period rose diagram (source: IMD, Data 1973 – 2015)
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
17 JSW Infrastructures Limited
2.6 Storms and Cyclones
2.6.1 General
There are marked seasonal variations in the origin, tracks and attainment of intensities of
cyclones. The upper air circulations in the northern hemisphere are from east to west and hence
cyclones affect primarily the Bay of Bengal coast, though a few veer northward after crossing
the peninsula and affect the Arabian Sea coastline. The area of generation of cyclones is
governed by the Inter Tropical Convergence Zone (ITCZ), the cyclones being restricted to the
north of the ITCZ. The ITCZ moves northward from December to May/June, when it occupies the
northern part of the Bay in May and gradually moves southwards until December, when it reaches
the southern tip of India. The path of the cyclones is generally from east to west as mentioned
earlier, the Coriolis force giving a tendency to curve northwards. Thus the cyclonic period along
the Bengal coast is generally June and August to November. The life span of a severe cyclonic
storm in the Indian seas averages about 4 days from the time it forms until the time it crosses
the land.
There are three elements associated with a cyclone, which cause destruction:
Cyclones are associated with high-pressure gradients and consequent strong winds.
These, in turn, generate storm surges. A storm surge is an abnormal rise of sea level near
the coast caused by a severe tropical cyclone; as a result, seawater inundates low lying
areas of coastal regions, drowning human beings and live-stock, eroding beaches and
embankments, destroying vegetation and reducing soil fertility.
Wave action is severe, causing damage to shore structures.
Very strong winds may damage coastal installations, dwellings, communication systems,
trees, resulting in loss of life and property.
The severity of the cyclone-generated waves depends heavily on the track of the cyclone, as
well as the development of the low central pressure and the wind speed in the cyclone.
The wave heights in the Fetch (that is within the body of the storm) as well as near shore were
determined by the hind casting of the cyclonic data. The waves generated in the storm fetch
receive a continuous input of energy from the high cyclonic winds, the magnitude of which is
determined by the radial pressure gradients, duly modified by the Coriolis Effect. These waves
have a large spectral width, encompassing a range of wave periods. When the storm is located
offshore of the point of interest, the travel time to the shore is least for the higher wave periods
and most for the shorter wave periods.
IMD has reported more than 49 severe cyclones in the region starting from 1932. The same have
been analysed and reported in the next section.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
18 JSW Infrastructures Limited
3 Site Investigations
3.1 General
A field investigation campaign data with respect to a different project was carried out by JSWIL
to assess the conditions of the area for one month between 13th November and 26th December.
Measurements were carried out for tide, current speed and current direction, and wave, at the
locations shown in Figure 3.1. The locations of the samples for total suspended solids, bed
samples and salinity were selected to represent the entire domain of interest.
Figure 3-1: Location of the field measurements
3.2 Data Analysis
This section presents the analysis of the tide, current, discharge data and wave data collected
at the site.
3.2.1 Tidal Level
The tidal range was recorded at the jetty little inside the river during the data campaign and was
connected to the datum marked on the Jetty. The water level elevations at the jetty are presented
in Figure 3.2. The collected data presents both neap and spring conditions over 1 month. During
neap water levels were found to vary from 1.1 to 2.2 m and tidal range of alternate tides is limited
to about 1 m. Tidal range during spring was observed to be as high as 2.2 m.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
19 JSW Infrastructures Limited
Figure 3-2: Water levels at the site near Paradip
3.2.2 Current
Figure 3.3 presents the measured current speed and direction at an offshore location. The
maximum current speed at the location was 0.8 m/s and minimum was 0.05 m/s. The current
direction is generally varying between 220 to 265 degrees.
Figure 3-3: Current speed and direction at offshore location during 12th to 19th December, (top) and 21th to 28th
December, (bottom)
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
20 JSW Infrastructures Limited
3.2.3 Wave measurements
Wave parameters are presented in Figure 3.6 to 3.9, which were measured at an offshore
location. Prominent wave direction was observed to be SSE to SSW for most of the time except
a small window where direction varied between NE to E. Significant wave height during NE and
E direction waves was found to be higher in the order of 0.3 to 0.6 m with time period of 3s.
Figure 3-4: Variation of predominant wave direction near site at offshore
Figure 3-5: Variation of predominant wave direction near site at offshore
Figure 3-6: Variation of maximum wave height near site at offshore
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
21 JSW Infrastructures Limited
Figure 3-7: Variation of zero crossing wave period near site at offshore
3.2.4 Water Sample
The salinity and temperature recorded at the offshore location were about 25 PSU and 26 0C,
respectively. Water samples were also collected at location marked in Figure 3.1 and are
presented in Table 3.1.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
22 JSW Infrastructures Limited
Figure 3-8: Salinity and temperature at an offshore location
Table 3-1: Total suspended solids (TSS) and chloride (Cl) concentration in the streams joining Mahanadi
Sl. No Transect Date of sampling Cl In mg/l TSS In mg/l
1 Estuary 27/11/15 2760 441
2 Estuary 21/11/15 3940 462
3 At offshore location 27/11/15 11350 818
3.2.5 Grain size distribution
Few samples of the material from the site were collected, which suggested the predominance of
sand (Table 3.2).
Table 3-2: Grain size distribution for material collected from the isolated waterfront near the proposed site
Sl. No.
Gravel, %
(> 2mm)
Coarse sand, %
(2-0.5mm)
Medium sand, %
(0.5-0.25mm)
Fine sand, %
(0.25-0.125 mm)
Silt, %
(62.5-3.9µ)
CLAY %
(<3.9 µ)
1. 0 38.42 23.65 23.48 2.32 12.13
2. 0 42.56 18.27 24.74 13.38 1.05
3. 0 32.74 24.56 36.28 3.54 2.88
4. 0 41.82 21.76 32.54 1.96 1.92
5. 0 40.94 22.54 33.92 1.56 1.04
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
23 JSW Infrastructures Limited
4 Wind and wave Conditions
4.1 General
The normal wave conditions at the proposed Captive Jetty(Ies) are governed by waves generated
by the local wind and by swell waves approaching from offshore.
The wave conditions near a harbour can be divided into two parts namely, normal operating
waves and extreme waves. The normal operating waves are those waves which are experienced
near a site in the normal weather including the monsoon. The data on normal wave conditions
are available from many sources. However, in general two data sources have been found to be
reliable and generally used. The first source from the India Meteorological Department (IMD),
which, supplies visually observed and reported data from the ships and the other one is extracted
from the global wind and wave model of the UK Meteorological office. The analysis of both the
data sets is presented below.
The IMD archival data covering the period between 1973 and 2007, also known as VOS data, are
derived from the Daily Weather Reports, in which the data observed by ships sailing in the Bay
of Bengal and Arabian Sea are reported. The VOS data reported by ships form a very useful data
set, particularly for design of the harbour layout, wherein a design down time is to be estimated.
These data were collated for a 20 x 20 square grid. The UKMO is a 6 hurly data set at a particular
location between 1999 and 2008.
Extreme waves are experienced during cyclonic conditions. The normal waves are used for
designing the alignment of the breakwater so that reasonably tranquil conditions are experienced
inside the harbour to enable ships to carry out cargo loading and unloading operations.
The extreme weather waves on the other hand are used for structural design of the breakwater.
Accordingly, the design of a Captive Jetty(ies) would largely depend on the existing wave
conditions in an area. In the following paragraphs of this section, the normal as well as the
extreme waves shall be discussed and design parameters for the breakwater shall be evolved.
4.2 Normal Wave conditions - Offshore
4.2.1 Analysis of Ship Observed Data (IMD)
The IMD archival data covering the period between 1973 and 2007, also known as VOS data, are
derived from the Daily Weather Reports, in which the data observed by ships sailing in the Bay
of Bengal and Arabian Sea are reported. The VOS data reported by ships form a very useful data
set, particularly for design of the harbour layout, wherein a design down time is to be estimated.
These data were collated for a 20 x 20 square grid. Wave roses presented as Figure 2.4 and 2.5
are based on IMD data.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
24 JSW Infrastructures Limited
Same data is presented as exceedance probability curve in Figure 4.1. The near shore Hm0 for
combined sea and swell can be estimated for various return periods indicated by coloured
(Yellow, Blue and Red) horizontal lines in Figure 4.1.
Figure 4-1: Exceedence probability curves for the near shore significant wave height (Hm0) at –20m CD
offshore of the proposed facility (Top: All, NE, ENE & Bottom: SE,SW, SSW
The estimated wave conditions for sea waves for return periods corresponding to 6hr/week, 6hr/
month and 6hr/1 year are given in Table 4.1. The estimates are based on the exceedance curves
of Figure 4.1.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
25 JSW Infrastructures Limited
Table 4-1: Estimated significant wave heights for sea, Hm0,sea (m) at –20m CD return periods corresponding to 6hr/week, 6hr/ year and 6hr/10 year.
Return
period
Exceedance
probability (-)
All
directio
ns
NE
ENE
SE
SW
SSW
6hr / week 0.035714 ~2.6 ~1.04 - ~0.6 ~1.9 ~2.0
6hr / month 0.008333 ~3.3 ~1.8 ~0.8 ~1.6. ~2.7 ~2.6
6hr / Year 0.000685
~4.6 ~3.8 ~4.2 ~3.3 ~3.6 ~4.2
4.2.2 Analysis of UKMO Data
The VOS data reported by ships are reported at 8:00 hrs in the morning by IMD and is given as
a single value per day. Hence the variations during the day are never reported.
Accordingly, the data can be treated as approximate. On the other hand, the UKMO data is
extracted and is available with a frequency of 6 hours. In addition, whereas the IMD data is
reported over a very large area, the UKMO data is available right near the location of interest and
hence serves as a very useful alternative source with better accuracy.
The offshore wave data from the UKMO are composed of the following wave components:
Sea waves
Swell waves
Resulting wave condition (i.e. combined sea and swell)
Figure 4.2 gives the time series plot for the three wave components described above. It could
be seen from Figure 4.2 that, the majority of the heights for the three types of waves are as
follows
Resultant wave 0.50 – 3.0 m
Sea wave 0.25 – 2.0 m
Swell wave 0.50 – 2.0 m
Figure 4.3 to 4.8 show wave roses derived from the offshore UKMO wave data, i.e., significant
wave height and period observed for sea (Hm0,sea), swell (Hm0,swl) and the resulting/combined
waves (Hm0,res). It could be seen that, the sea waves generally conforms to the local weather
patterns of the area. The region has a prominent SW monsoon period starting 15th of May till the
mid of September. The maximum reported sea wave height is about 4.0 m. The resultant and the
swell wave heights follows similar directional pattern as the predominant directions are from the
SE and SSE. The maximum swell height is about 2.75 m and resultant wave height is 4.75 m.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
26 JSW Infrastructures Limited
Figure 4-2: Time series of the three Hm0–parameters. Top: Significant wave height for resultant wave
condition (Hm0, sea). Middle: Significant wave height for sea only (Hm0, swell) Bottom: Significant
wave height for swell wave (Hm0, res); (source: UKMO, Data set: 1999 – 2008)
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
27 JSW Infrastructures Limited
Figure 4-3: Wave rose for resultant wave height (source: UKMO, 1999 – 2008)
Figure 4-4: Resultant wave period (source: UKMO, Data set: 1999 – 2008)
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
28 JSW Infrastructures Limited
Figure 4-5: Wave rose for sea wave height (source: UKMO, 1999 – 2008)
Figure 4-6: Sea wave period (bottom) (source: UKMO, Data set: 1999 – 2008)
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
29 JSW Infrastructures Limited
Figure 4-7: Wave rose for swell wave height (source: UKMO, 1999 – 2008)
Figure 4-8: Swell wave period (source: UKMO, Data set: 1999 – 2008)
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
30 JSW Infrastructures Limited
The scatter plot for the wave data shown in Figure 4.9 indicate that the short period sea waves
covers a wider band, however the swell waves are restricted to S and SSE direction. The resulting
waves also conform to sea wave band.
Figure 4-9: Scatter plots of the offshore UKMO wave data. The significant wave height (Hm0) and the mean zero-
crossing period (T02) versus the wave direction (in radians). Top: Resultant only. Middle: Sea only,
Bottom: Swell waves; (source: UKMO, Data set: 1999 – 2008)
An exceedance probability analysis for the sea, swell and resulting waves was carried out and is
presented in Figure 4.10 to 4.12 respectively. These curves provide wave conditions for the
waves for return periods corresponding to 6 hr/week, 6 hr/month and 6hr/year for all directions
as well as a break-up in various dominant directions. Table 4.2, 4.3 and 4.4 provide the estimated
values of the wave heights for some of the prominent directions.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
31 JSW Infrastructures Limited
Figure 4-10: Exceedence probability curves for the significant sea wave height (Hm0) (source: UKMO, 1999 –
2008)
Table 4-2: Estimated significant wave heights for sea, Hm0, sea (m) according to the specified return periods for some significant directions for UKMO data
Return
Period
All
directions SSW E SE SSE S SW
6hr / week 2.2 2.2 0.9 0.9 0.7 0.5 0.4
6hr / Month 3.0 2.6 2.0 1.2 1.1 0.9 0.8
6hr / 1 year 5.0 3.4 4.5 2.3 4.5 1.4 1.3
Table 4-3: Estimated significant wave heights for swell, Hm0, swell (m) according to the specified return periods
for significant directions for UKMO data
Return
Period
All
directions E SE SSE
6hr / week 1.9 0.8 0.8 1.9
6hr / Month 2.3 1.1 1.0 2.2
6hr/ Year
6hr / 1 year
3.1 1.6 1.2 2.8
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
32 JSW Infrastructures Limited
Figure 4-11: Exceedance probability curves for the significant swell wave height (Hm0) (source: UKMO, Data
set: 1999 – 2008)
Figure 4-12: Exceedance probability curves for the Resultant wave height (Hm0) (Source: UKMO, Data Set:
1999 – 2008)
Table 4-4: Estimated Resultant wave height, Hm0 (m) according to the specified return periods for some
significant directions for UKMO data
Return
Period
All
directions E SE SSE
6hr / week 2.6 1.1 1.0 2.2
6hr / Month 3.3 1.4 1.2 2.8
6hr/ Year
6hr / 1 year
5.1 2.2 1.5 4.4
4.2.3 Exceedance Probability Tables
The exceedance probability tables from different directions are given as Table 4.5, 4.6 and 4.7.
Techno-Economic Feasibility Report
Development of Captive Jetty(ies) at Jatadhari
Muhan, Jagatsinghpur
33 JSW Infrastructures Limited
Table 4-5: Exceedance probability of the sea waves near Paradip
Table 4-6: Exceedance probability of the swell waves near Paradip
Table 4-7: Exceedance probability of the Resultant wave near Paradip WAVE HEIGHT N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL
0 - 0.5 0.00 0.00 0.00 0.00 0.01 0.00 0.02 0.74 0.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.87
0.5 - 1 0.02 0.27 0.19 0.01 0.01 0.01 0.06 18.80 2.21 0.27 0.01 0.00 0.01 0.00 0.00 0.01 21.88
1 - 1.5 0.00 0.20 0.14 0.08 0.04 0.10 0.24 29.09 2.47 2.25 0.28 0.06 0.02 0.01 0.01 0.01 35.02
1.5 - 2 0.00 0.04 0.05 0.04 0.07 0.14 0.22 18.22 1.28 4.26 0.73 0.11 0.02 0.01 0.01 0.00 25.20
2 - 2.5 0.00 0.00 0.01 0.02 0.04 0.10 0.26 6.12 0.79 3.45 0.59 0.07 0.01 0.00 0.00 0.00 11.47
2.5 - 3 0.00 0.01 0.01 0.03 0.01 0.06 0.08 1.72 0.49 1.27 0.27 0.01 0.00 0.00 0.00 0.01 3.96
3 - 3.5 0.00 0.01 0.00 0.00 0.02 0.01 0.04 0.23 0.25 0.34 0.04 0.00 0.00 0.00 0.00 0.00 0.94
3.5 - 4 0.00 0.00 0.00 0.01 0.01 0.02 0.04 0.02 0.13 0.07 0.00 0.00 0.00 0.00 0.00 0.00 0.30
4 - 4.5 0.00 0.00 0.00 0.00 0.01 0.01 0.03 0.03 0.12 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.22
4.5 - 5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.02 0.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08
TOTAL 0.02 0.53 0.40 0.20 0.24 0.46 0.99 74.99 7.89 11.93 1.91 0.26 0.06 0.02 0.01 0.03 99.94
WAVE HEIGHT N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL
0 - 0.5 2.44 4.92 4.99 2.78 2.26 1.49 1.55 1.69 2.44 3.58 4.06 2.44 1.42 0.88 0.64 0.79 38.37
0.5 - 1 0.49 3.68 2.56 0.59 0.62 0.61 0.59 0.85 2.55 7.54 5.11 1.16 0.40 0.15 0.09 0.05 27.04
1 - 1.5 0.02 0.59 0.43 0.21 0.16 0.20 0.16 0.28 1.17 8.88 3.38 0.69 0.24 0.03 0.05 0.03 16.53
1.5 - 2 0.00 0.04 0.09 0.05 0.12 0.12 0.07 0.08 0.58 7.03 1.99 0.29 0.02 0.01 0.01 0.00 10.49
2 - 2.5 0.00 0.00 0.02 0.01 0.05 0.06 0.06 0.11 0.34 3.53 0.77 0.11 0.01 0.00 0.00 0.01 5.06
2.5 - 3 0.00 0.02 0.00 0.02 0.02 0.07 0.07 0.06 0.22 1.01 0.20 0.00 0.00 0.00 0.00 0.00 1.69
3 - 3.5 0.00 0.01 0.01 0.01 0.02 0.04 0.00 0.02 0.16 0.17 0.02 0.00 0.00 0.00 0.00 0.00 0.45
3.5 - 4 0.00 0.00 0.00 0.00 0.00 0.02 0.04 0.01 0.13 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.22
4 - 4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.02 0.02 0.04 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.09
4.5 - 5 0.00 0.00 0.00 0.00 0.01 0.00 0.00 0.02 0.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.09
TOTAL 2.96 9.24 8.09 3.68 3.25 2.62 2.57 3.14 7.68 31.78 15.53 4.68 2.09 1.07 0.78 0.88 100.02
WAVE HEIGHT N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL
0 - 0.5 0.00 0.00 0.02 0.00 0.02 0.00 0.07 4.80 0.64 0.06 0.01 0.00 0.01 0.00 0.00 0.00 5.64
0.5 - 1 0.01 0.04 0.07 0.01 0.03 0.04 0.31 36.30 4.42 1.79 0.09 0.00 0.00 0.00 0.01 0.00 43.11
1 - 1.5 0.00 0.00 0.00 0.00 0.01 0.11 0.30 31.96 2.64 2.41 0.03 0.01 0.00 0.00 0.00 0.00 37.47
1.5 - 2 0.00 0.00 0.00 0.01 0.00 0.04 0.25 9.61 0.90 0.72 0.01 0.00 0.00 0.00 0.00 0.00 11.54
2 - 2.5 0.00 0.00 0.01 0.00 0.01 0.01 0.09 1.54 0.25 0.09 0.01 0.00 0.00 0.00 0.00 0.00 2.00
2.5 - 3 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.16 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.22
3 - 3.5 0.00 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04
3.5 - 4 0.00 0.00 0.00 0.00 0.00 0.01 0.00 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.01
TOTAL 0.01 0.04 0.10 0.02 0.08 0.24 1.03 84.39 8.88 5.08 0.15 0.01 0.01 0.00 0.01 0.00 100.04
Techno-Economic Feasibility Report
46
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
4.3 Normal Conditions – Near shore
The existing wind and wave conditions of IMD and UKMO data sets analysed and reported in the
previous section were at offshore locations. However, it is recognised that as waves travel form
deep waters to the shallow zones, the waves get modified due to various factors, such as shoaling,
refraction, and diffraction etc. In order to derive the wave climate near the proposed Jetty(ies)
location that governs the working environment, the deep water waves were transformed to the near
shore using state of the art spectral wave model MIKE 21 SW. This will help the Jetty(ies) planners
to design the orientation of the protection works like breakwaters.
MIKE 21 SW is a new 3rd generation spectral wind-wave model that simulates the growth, decay
and transformation of wind-generated waves and swells in offshore and coastal areas. The model
includes wave growth by action of wind, non-linear wave-wave interaction, dissipation by white-
capping, dissipation by wave breaking, dissipation due to bottom friction, refraction due to depth
variations, and wave-current interaction. Transformation of the offshore wave conditions to near
shore are carried out using this model.
The bathymetry used in the SW module is presented in Figure 4.13.
Figure 4-13: Bathymetry used for SW module
The UKMO data was applied as boundary conditions so that the real time wave transformation is
possible. The tidal effect in the model domain is taken care of by applying boundary conditions,
which is extracted from DHI’s global water surface model. Since, this water surface boundary would
generate actual tidal flow conditions, the calculated wave heights are very close to the actual site
observations.
Model was executed for a complete year in order to arrive at annual wave climate of the proposed
location. The results are extracted at 5 and 10 m contours and are presented in the Figures 4.14
to 4.17.
Techno-Economic Feasibility Report
47
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Predominant wave direction near the coast is SSE. At 5 m contour 75 % of the time wave height is
less than 1.5 m. Wave period is also less than 10 s for 73 % of the time in a year. At 10 m contour
SSE, S and SE are observed for 60, 20 and 10 % of the time. Wave heights of 3 m are also
encountered at 10 m depth but for a very short duration in SW monsoon. Wave period is less than
10 s all the time in a year.
Figure 4-14: Resultant Wave Height at 5 m depth near proposed Jetty
Figure 4-15: Resultant Wave Period at 5 m depth near proposed Jetty(ies)
Figure 4-16: Resultant Wave Height at 10 m depth near proposed Jetty(ies)
Techno-Economic Feasibility Report
48
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Figure 4-17: Resultant Wave Period at 10 m depth near proposed Jetty(ies)
4.4 Extreme Conditions
4.4.1 Hindcasting of cyclonic storm waves
Extreme wave conditions at the proposed Jetty(ies) are caused by cyclones traveling westwards
across the Bay of Bengal and crossing the east coast of India, in the vicinity of the Captive
Jetty(ies). The severity of the cyclone-generated waves depends heavily on the track of the cyclone
with respect to the proposed Captive Jetty(ies), as well as the development of the low central
pressure and the wind speed in the cyclone. Hindcasting analysis for storm waves was carried out
only for the severe storms, which were selected as relevant to the Captive Jetty(ies) site, from the
data of storm tracks published by IMD from 1929 onwards. Since the period covered is more than
75 years, the data range was considered adequate for statistical analysis.
Techno-Economic Feasibility Report
49
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
The methodology adopted in the analysis is illustrated using the 1999 storm as an example, since
it gave the maximum values for the chosen location. The bathymetry of the Bay of Bengal, as
shown in Figure 4.18, was utilised in the MIKE 21 SW model, in which the pressure field and
available wind velocity values were fed. The storm track of the 1999 cyclone is shown in Figure
4.19. It may be seen that the cyclone which was first noticed south of the Irrawaddy River mouth
on October 26, 1999, gradually intensified and moved towards the Orissa coast in 60 hours and
remained stationary thereafter virtually, over the project site, over the next three days. This resulted
in a very high storm wave and also in a rise of the water level above the astronomical tide, called
storm surge, as obtained from MIKE SW.
Figure 4-18: Model bathymetry for the Bay of Bengal for Mike 21 SW Input
Figure 4-19: Storm tracks of 1999 applied for the simulation of the SW Model
The meteorological data fed in to the SW model is reproduced in Table 4.8 below.
Techno-Economic Feasibility Report
50
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Table 4-8: Meteorological Data for the 1999 Cyclone
Date YY mm dd
Time hr
Long Lat Radius (km)
Max wind speed (m/s)
Central pressure
Neutral pressure
1999102612 0 93.9 15 30 23.13 991 1004
1999102618 6 93.1 15.6 30 25.69 987 1004
1999102700 12 92.3 16 30 33.40 976 1004
1999102706 18 91.5 16.4 30 38.54 958 1004
1999102712 24 90.9 16.7 30 46.25 944 1004
1999102718 30 90.2 17 30 48.82 954 1004
1999102800 36 89.1 17.6 30 51.39 949 1004
1999102806 42 88.3 18.1 30 59.10 927 1004
1999102812 48 87.7 18.6 30 69.38 924 1004
1999102818 54 87.2 19.1 30 71.94 920 1004
1999102900 60 86.7 19.6 30 71.94 920 1004
1999102906 66 86.3 20 30 69.38 924 1004
1999102912 72 86 20.4 30 59.10 927 1004
1999102918 78 86 20.6 30 51.39 949 1004
1999103000 84 85.9 20.6 30 41.11 958 1004
1999103006 90 85.8 20.5 30 28.26 984 1004
1999103012 96 85.8 20.3 30 23.13 991 1004
1999103018 102 85.9 20.2 30 23.13 991 1004
1999103100 108 85.9 19.9 30 20.56 994 1004
1999103106 114 85.9 19.6 30 20.56 994 1004
1999103112 120 85.8 19.2 30 17.99 997 1004
1999103118 126 85.6 19 30 17.99 997 1004
1999110100 132 85.5 18.9 30 15.42 1000 1004
1999110106 138 85.3 18.6 30 12.85 1002 1004
1999110112 144 85.1 17.9 30 12.85 1002 1004
1999110118 150 84.9 17 30 12.85 1002 1004
1999110200 156 84.8 16.1 30 12.85 1002 1004
1999110206 162 84.7 15.9 30 10.28 1004 1004
1999110212 168 84.5 15.8 30 7.71 1004 1004
1999110218 174 84.1 15.7 30 7.71 1004 1004
1999110300 180 83.7 15.8 30 7.71 1004 1004
1999110306 186 83.3 16 30 7.71 1004 1004
The computed wind field and storm surge over the Bay of Bengal are extracted from the model and
plotted in Figure 4.20.
Techno-Economic Feasibility Report
51
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Figure 4-20: Computed surface elevation/ storm surge over the Bay of Bengal
The wave height growth near the area of interest is shown in Figure 4.21.
Figure 4-21: Surface elevation plots for the 1999 cyclone
The results of the hind casting analysis of waves over a period of 70 years are presented in Table
4.9. It may be noted that very low values are shown for the earlier years that is prior to 1948. This
is primarily due to the limitations of the data, in the earlier period when only daily isobaric patterns
were available. It may be emphasised here that the wave height near shore do not take into account
the effects of shoaling and refraction, which take place when the wave enters shallow water, and
accounted only for the decay distance, and thus represent the wave conditions say at the 20 m
contour, at which point the refraction effects would be minimal for the wave periods under
consideration.
Table 4-9: Hind-casting of Waves
Sl. No Year Wave Height in Fetch Area (m) Wave Height at site (20 m
Water depth)
1 1929 1.68 0.61
2 1930 2.87 1.89
Techno-Economic Feasibility Report
52
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Sl. No Year Wave Height in Fetch Area (m) Wave Height at site (20 m
Water depth)
3 1931 2.96 1.98
4 1932 2.83 1.67
5 1933 2.44 1.71
6 1934 2.59 1.51
7 1935 2.07 0.82
8 1936 2.32 1.19
9 1937 1.37 1.01
13 1941 1.77 0.43
14 1942 2.9 1.95
15 1943 1.07 0.67
16 1944 2.13 2.13
17 1945 1.04 0.46
18 1946 1.58 0.37
19 1947 1.71 0.49
20 1948 4.3 2.68
21 1949 2.77 1.31
22 1950 4.88 2.1
23 1951 5.49 5.49
24 1952 7.01 2.6
25 1953 3.66 1.55
26 1954 4.94 1.92
27 1955 5.94 1.83
28 1956 4.42 2.04
29 1957 3.35 1.48
30 1958 4.57 2.24
31 1959 3.05 3.05
32 1960 7.92 3.57
33 1961 3.66 1.21
34 1962 4.88 4.88
35 1963 3.2 0.93
36 1964 0.91 0.91
37 1965 7.32 3.29
38 1966 2.9 2.9
40 1968 7.01 3.08
Techno-Economic Feasibility Report
53
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Sl. No Year Wave Height in Fetch Area (m) Wave Height at site (20 m
Water depth)
41 1969 2.44 2.44
42 1970 8.23 4.94
43 1971 5.33 5.33
44 1972 9.45 8
45 1973 6.86 3.08
46 1974 2.74 1.07
47 1975 1.88 1.88
48 1976 1.16 1.16
49 1977 3.05 1.01
50 1978 2.23 0.58
51 1979 0.73 0.73
53 1981 2.9 2.9
54 1982 6.7 3.82
56 1984 3.2 1.37
58 1986 1.31 0.56
59 1987 2.74 1.21
60 1999 9.00 9.00
4.4.2 Extreme Value Analysis
In this section, the wave heights of the individual storms are taken and plotted in various statistical
formats to arrive at the design wave height for various periods of recurrence. For this purpose, it
was considered necessary to remove the bias due to lower values, so that emphasis is placed on
the waves generated by severe cyclonic storms. It may be recognised that normal monsoon waves
are of the order of 2 to 3 m, and accordingly for extreme value analysis values only the data with
more than 3 m wave height are considered.
In order to determine the wave heights for design of structures it is necessary to determine the
maximum probable wave heights for different return periods. For predicting the maximum wave
heights for different return periods, based on the hind cast data, statistical analysis was carried
out to predict long-term return period values. This would enable the designer to carry out the
necessary design with required level of safety.
Out of the three methods followed in such determination, the first methods assumes a simple log
normal distribution, while the second and third are more versatile methods and include other
statistical distributions such as Truncated Gumbel and Weibull. These are modules of the MIKE
series of software and goes by the name EVA (Extreme Value Analysis). The hind cast waves given
in Table 4.9 were subjected to this analysis. Figure 4.22 show the frequency plot of the cyclonic
data for various statistical distributions. It could be seen that the Log-Normal distribution fits the
Techno-Economic Feasibility Report
54
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
best hence the Probability for this has been followed for finding wave heights for different return
periods in the fetch (Figure 4.23).
It may be seen that the 100 year return period wave height is about 11.7 m in the fetch. For 50
years return value calculated wave height is 10.7 m for cyclonic conditions. These return period
waves are used for design of the protections in the form of Breakwater/Groynes.
The waves will largely attenuate as they travel inside the river and the wave heights inside the
river/creek and the computations for these wave heights require mathematical models and would
be carried out at the stage of DPR.
Figure 4-22: Frequency plot for the Cyclonic data indicating Log normal distribution matches the best with the
data
Techno-Economic Feasibility Report
55
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Figure 4-23: Maximum probable wave heights in the fetch with Log-Normal distribution
4.5 Breakwater Design Parameters
On the basis of the analysis presented in the sections above, following are the points to be
considered at the time of for breakwater design, which would again depend on the field studies
and mathematical modelling. The following are the main criteria’s for the breakwater design:
Most prominent wave direction near the shore is SSE.
Waves with height 3 m and wave period of 10 s are encountered at the 5 m contour during
normal conditions.
Maximum wave height of 9 m was calculated in the fetch for the super cyclone in the region.
Under extreme cyclonic events, for 100 year return maximum wave height of 11.6 m is
calculated in the fetch.
Clearly these factors indicated above are approximate and based on the available data on the
shoreline from the secondary data sources. Therefore, design of the length and the type of
protections required would be designed after exhaustive model studies both mathematical and
physical.
For the present the length of the breakwater/ groynes are as follows;
1. South Breakwater: 1850 m
2. North Breakwater: 2700 m
Techno-Economic Feasibility Report
56
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
5 Traffic Projections
5.1 General
The objective of the Captive Jetty(ies) on the waterfront of the Jatadhari River is to cater to the
logistical demand of the raw material and the finished product of the integrated steel plant,
including the cement and power plant. The broad logistics proposed for the majority of the cargo
movement is shown in Figure 5.1 below. There will be two slurry pipelines laid from the Iron Ore
mines to the ISP. One slurry pipeline will be activated in the 13.2 MTPA stage and shall bring in 30
MTPA of Iron ore concentrate, out of which 12 MTPA may be sent to JSW group companies and
the rest would be used in the ISP locally. In the subsequent phases based on requirements, the
second slurry pipeline will be activated, and 30 MTPA more Iron Ore concentrate shall be received
at the Jatadhari ISP. While the 30 MTPA of iron ore concentrate would be used in the ISP locally,
30 MTPA received from the 2nd pipeline would be sent to JSW steel plants elsewhere through
coastal shipping.
Figure 5-1: The slurry pipe line connecting the 3 prespective mines in the Joda-Barbil area and the Captive
Jetty(ies) facility
5.2 Requirements of Raw Material (Project Report of ISP)
Requirement of raw material as per the project report of the 13.2 MTPA ISP, 900 MW captive power
plant and 10 MTPA cement plant is as given in Table 5.1. The net and dry requirement of the various
raw materials and sources are given in the table identifying the modes they are likely to use.
Techno-Economic Feasibility Report
57
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
In addition, there will be future provision for receipt, storage and transport of LNG as an alternate
fuel inland in a pipeline laid in the same corridor as the rail/road/slurry pipeline and water line. In
the second phase provision for 4 MTPA LNG shall be made which would be doubled (8 MTPA) in
the subsequent phases.
Table 5-1: Annual Raw material (net and dry basis) Requirements (in million tonnes per year)
Sl. no Raw Material Source Quantity Likely Modes
1 Iron Ore Concentrated (for Pellet Plant) Odisha 30.00 RMHS
2 Iron Ore Fines (for Sinter plant) Odisha/Jharkhand/Chhattisgarh 6.16 Rail
3 Iron Ore Lumps Odisha 1.05 Rail/Road
4 Lime Stone (BF Grade) MP/Jharkhand/Dubai/Oman*1 4.64 Rail/Ship/Road
5 Dolomite (BF Grade) MP/Jharkhand/Dubai/Oman/Thailand*1 2.56 Rail/Ship/Road
6 Quartzite Odisha 0.27 Road/Rail/Ship
7 Lime Stone (SMS Grade) Dubai/Oman 1.711 Ship
8 Dolomite (SMS Grade) Dubai/Thailand 2.57 Rail/Ship/Road
9 Coking Coal Australia/Canada/USA/Mozambique 8.40 Ship
10 Non Coking Coal PCI - Gross Australia/Canada/USA/Mozambique 2.70 Ship
11 Thermal Coal SA/Indonesia/Odisha*2 2.60 Rail
12 Anthracite Coal Australia/Canada/USA/Mozambique 0.30 Ship
13 Bentonite Gujarat 0.26 Ship
14 Ferro Alloy Odisha 0.20 Rail
15 Clinker International market/India 5.00 Ship
16 Gypsum Domestic 0.40 Road/Rail
The raw material expected to be handled at Captive Jetty(ies) from table 5.1 are listed in Table 5.2.
Table 5-2: Annual Raw material Requirements to be met by the Proposed Captive Jetty(ies) (in MT per year)
Sl. no Raw Material Source Quantity Likely Modes
1 Dolomite (SMS Grade) Dubai/Thailand 0.40 Ship
2 Lime Stone (SMS Grade) Dubai/Oman 2.40 Ship
3 Clinker International market/India 5.30 Ship
4 Coking Coal Australia/Canada/USA/Mozambique 8.84 Ship
5 Non Coking Coal PCI - Gross Australia/Canada/USA/Mozambique 2.84 Ship
6 Thermal Coal SA/Indonesia/Odisha*2 4.50 Rail/Ship
7 Anthracite Coal Australia/Canada/USA/Mozambique 0.32 Ship
8 Bentonite Gujarat 0.30 Ship
9 Quartzite International market/India 0.03 Ship
Total Traffic 24.93 Ship
*1&2: Water transport being cheaper given precedence
Techno-Economic Feasibility Report
58
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
5.3 Outward Cargo Movement from the Captive Jetty(ies)
Para 5.2 supra describes the raw material requirements of the ISP (table 5.1) as well as the raw
material movement (inward) expected through the Captive Jetty(ies) (Table 5.2). With the inward
movement more or less determined, it is imperative to understand the out ward volumes as well for
determining the Captive Jetty(ies) capacity in different phases.
Time lines for the development of the ISP is also important in order to determine the traffic for the
Captive Jetty(ies) (both inward and outward) in different time horizons. However, for the purpose
of this report, the Captive Jetty(ies) would be considered as a standalone project with cargo inputs
from the ISP and other means.
5.3.1 IBRM
Iron Bearing Raw Material (IBRM) would include Iron Ore, Iron Ore concentrate and Pellets. Total
Iron Ore amounting to 30 MTPA would be transported by slurry pipelines, to the plant storage.
These iron ore cakes, is used in plants for Iron Ore extraction and pallet formation. After filtration
of 30 MTPA of slurry iron ore, initially about 12 MTPA would be shipped to JSW Group companies.
The rest will be either used by the Odisha steel plant locally. In future, based on global scenario,
one or more pallet plants may be planned for the Odisha project, hence the movement of the
material as export would constitute of a mixture of Iron Ore concentrate and Pallet (as and when it
happens) and they would thus be used interchangeably in the report.
5.3.2 Steel Products
The steel plant capacity proposed is 13.2 MTPA with a provision to upgrade to 20 MTPA in future.
Though the 13.2 MTPA will be achieved in 3 sub-phases with commissioning of 3 blast furnaces
in sequence, 50 % of the product for the purpose of this report is considered for either coastal or
international shipping.
5.3.3 Clinker and Cement
Slag is a by-product of the steel industry and often times requires ingenuity in disposal.
However, slag can be gainfully deployed by grinding the same with clinker in appropriate
proportions to produce what is known as Slag Cement. Hence, keeping pace with the steel plant
capacity, the cement grinding units shall be installed. For the 13.2 MTPA scenario, 10 MTPA cement
plant is proposed.
5.3.4 Alternate Fuel for Steel Plant
In the present case, the Coking, thermal and other type of coal is envisaged to be imported from
countries like Australia, Mozambique, South Africa, Canada, USA and Indonesia. In future in the
case LNG becomes affordable, the ISP may opt for LNG as the alternate fuel for the steel and the
other manufacturing units. Accordingly, provision for LNG receipt, storage and transportation, of
LNG shall be made in the same corridor earmarked for Slurry pipe line/rail/road/water line. In the
second phase 4 MTPA and subsequent phase 8 MTPA of LNG shall be considered. It is however,
Techno-Economic Feasibility Report
59
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
must be made clear that the import of LNG shall be based on market dynamics and the fate of
Coal as a fuel in near future for the sake of Environment.
5.4 Total Traffic at the Captive Jetty(ies)
Based on the above discussions the cumulative traffic to be handled at the Jetty(ies) facility is
given in table 5.3.
Table 5-3: Projected Traffic for the Captive Jetty(ies) facility (in million tonnes)
Commodity
Orissa Project
Phase I
Mode of transport (13.2 MTPA)
Import Cargo
Coking Coal 8.84 Ship
Anthracite 0.32 Ship
PCI Coal 2.84 Ship
Thermal Coal 4.50 Ship
Lime stone (SMS) 2.40 Ship
Dolomite (SMS) 0.40 Ship
Bentonite 0.30 Ship
Clinker 5.30 Ship
Quartzite 0.03 Ship
TOTAL 24.93 Ship
Export Cargo
Finished Steel*1 6.00 Ship
Pallet/Iron Ore Concentrate 15.00 Vijaynagar/Dolvi
Cement*1 6.00 Ship
TOTAL 27.00 Ship
GRAND TOTAL 51.93 Ship
*1: 50 % of the steel is considered as coastal cargo
*2: 60% of the Cement is considered as coastal cargo. 40% for local market
Techno-Economic Feasibility Report
60
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
6 Captive Jetty(ies) Planning
6.1 General
Planning of Captive Jetty(ies) facilities largely is a techno-economic process. Though a Captive
Jetty(ies) can be constructed virtually anywhere at some cost, but planning looks for a cost
effective solution, without sacrificing efficiency.
Planning involves first of all selecting a site considering the depth, connectivity, land availability
etc. Then detailed assessment is taken up to firm up ship size, ship calls, number of berths, land
area requirement and water front details.
This chapter deals with site selection and functional planning of the Captive Jetty(ies). Each of the
above considerations in itself is dependent on a number of factors, some of which are outside the
control of port planners or operators. The above parameters are discussed in the following
paragraphs to enable evolving the layout of the Captive Jetty(ies).
6.2 Identifying location for the Captive Jetty(ies)
The most important consideration for choosing a site for a Captive Jetty(ies) is its proximity to the
proposed Industry and the connectivity it offers to make the logistical in terms of road, rail or any
other mode. As already mentioned earlier, the Captive Jetty(ies) is primarily being developed for
handling of the Captive cargo of the ISP including the 900 MW power plant and the cement-
grinding unit. With 52 MTPA cargo for the 13.2 MTPA steel plant. The ISP is approved in principle
by the GoO, between the coordinates of 200 11.85’ – 200 12.94’ N and 860 32.66’- 860 34.84’ E
along the Jatadhari Muhan River.
Hence, it is prudent to imagine that a Captive Jetty(ies) along the bank of Jatadhari Muhan River
would be ideal, with relation to the material logistics and duplication of storage space. However,
other options including one on the sea front was considered before discarding the same, in favour
of the riverfront as described in this paragraph.
In this section, the three alternative locations are evaluated based on the following criteria in order
ending with a multi-criteria matrix.
Depths Available
Sedimentation
Protection from extreme conditions
Subsoil Condition
Back up land
Connectivity (Hinterland)
Environmental concerns
Cost
Techno-Economic Feasibility Report
61
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Figure 6-1: Location of the Proposed Captive Jetty(ies)
6.2.1 General Comments on the 3 Sites
Three alternative sites were considered and compared before arriving at the final location of the
Captive Jetty(ies). The parameters are listed above. The sites are selected based their proximity to
the proposed steel plant.
In the selection of the Captive Jetty(ies) sites, 2 sites are on the sea front and one inside the creek
as depicted in Figure 6.1.
Captive Jetty(ies) Site 1
The Site 1is located south of the Paradip Port by about 7 km. The area is fronted with a nice and
well-developed beach.
Captive Jetty(ies) Site 2
Captive Jetty(ies) site is located on the seaward side if the Jatadhari Muhan River. The location is
on a stable sand spit that has been created under the combined effects of the littoral movement
and flows in the Jatadhari Muhan River.
Captive Jetty(ies) Site 3
The Captive Jetty(ies) site 3 is located inside the Jatadhari Muhan creek, along the riverfront, just
adjacent to the proposed steel plant.
Based on the above locations the claim of each of the site compared based on the above-
predefined parameters would be discussed and listed in a multi-criteria matrix. The highest score
in the matrix will determine the actual location of the Captive Jetty(ies).
Techno-Economic Feasibility Report
62
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
6.2.2 Depths
A large portion of the capital cost for any Captive Jetty(ies) development goes into capital as well
as maintenance dredging for developing a new approach channel from the Captive Jetty(ies) to
the required depths. Figure 6.2 below indicates the existing depths near the shoreline. It could be
seen that depths of 10 m and 20 m are available at about 4 km and 10 km from the sand line
respectively.
Since substantial amount of traffic would move through long distances, viz. South Africa, Australia,
Mozambique, larger parcel size will bring in economy of scale, hence Cape Size vessels would be
considered as the designed vessel for large volume bulk movements. Accordingly, even with the
soft bed soils at the proposed sea front, a 20 m deep approach channel would be necessary. The
approach channel length would be about 12 km length.
Since the depth contours are shore parallel, the length of the approach channel is similar for all
the options. Except for the Site no 3 where the length would be longer by 2 km or so.
6.2.3 Sedimentation
The east coast has a prominent littoral movement, due to the monsoon waves. About 1.1 million
m3 of sediment moves along the east coast from south to north. Hence, any protrusions along the
shoreline and/or navigation channel deeper than the regular seabed levels would bring large
quantities of sediment blockage. Since sediment is taken out of the energetic alongshore
movement forces, with large carrying capacity, upstream erosions ensues.
Hence, the breakwaters of the Captive Jetty(ies) at site 1 and 2 would have large-scale sediment
accumulation on the southern side and erosion on the northern side of the coast, the same may
not be case for the inner harbour at Site 3.
Channels however, would have similar accumulation of sediments in all the sites. Maximum
sedimentation is expected to be in the monsoon period between July and August based on the
actual environmental conditions. The siltation in the channel would be computed in the detailed
engineering stage using mathematical model.
6.2.4 Protection from Wave action
For the Site 1 and Site 2, the land would have to be created through reclamation using the dredging
material obtained from channel and Captive Jetty(ies) area dredging and protected by adequate
breakwater of suitable size and configuration.
The Captive Jetty(ies) is located inside the Jatadhari Muhan estuary, Site 3, is largely protected
from direct wave attack caused by monsoon and other regular cyclonic events. However, the wave
surges wand water level increase due to cyclonic surges would definitely affect the Captive
Jetty(ies) design.
Wave data presented in Chapter 4 indicated that the most prominent resultant waves up to 4.75 m
height occur under normal monsoon conditions from SSE. This shore is also prone to cyclones;
Techno-Economic Feasibility Report
63
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
with maximum wave height reaching 9 m (refer table 3.9 and 3.10) during super cyclone of year
1999. However, unique location of the berths would prevent it from being directly influenced by the
waves, except for the surges. Therefore, breakwater protection may not be required except for
providing tranquility near the entrance of the Captive Jetty(ies).
The length of breakwater will mainly dictated by the stopping distance it is likely to provide for the
ships to safely stop in the turning circle. This is in contrast to the length and size of the breakwater
required for providing similar facilities including the number of berths on the sea front at the site
1 and 2.
6.2.5 Subsoil Conditions
The subsoil condition is very important as far as the development cost of the Captive Jetty(ies) is
concerned. This affects the Captive Jetty(ies) in two ways and a correct balance is desirable. The
first is the cost of dredging, which constitutes the major portion of port development. It must be
recognized that, the cost of sand dredging differs from the cost of rock dredging by a factor of
10. Hence, if rock is encountered in the dredging of channels and Captive Jetty(ies) area including
the Turning basin, the cost of Captive Jetty(ies) development could be appreciably more than, if
only sand dredging is involved. Secondly, construction of a breakwater requires good quality
seabed and sub-bottom material for the stability of its foundation.
The subsoil profiles from the nearby locations indicate that the soil is mostly sandy. It would be
relatively simple to dredge and use the dredged sand for reclamation of the plant area. The seabed
soil is not likely to pose problems for supporting the breakwater,
6.2.6 Backup Land
As indicated above, for the site 1 and 2, the land would be created by reclamation between the
breakwater protections. As far as the site 3 is concerned, it is located fronting on an existing land
mass designated for locating the ISP. Creation of vast reclaimed land on the shoreline would entail
longer breakwaters, which would further worsen the coastal flow conditions,
JSWSL has requested for allocation of total 5082 acres of land for Steel plant and other facilities
as detailed in the Page No. 5-2 of Project Report for the ISP, Aug-2017.
Land use pattern is quite diverse with thick shrubs in the area. The selected location was particularly
favored as it is fallow land with sparse vegetation patches and no water body. JSW has requested
to IPICOL for assessment of requirement on land, water and power for its ISP and other facilities.
Presently, this is under active consideration with GoO.
The land is low lying and needs to be raised by around 3 m in order to take care of the flooding in
the vent of cyclonic surges.
Prime facie about 30 million m3 of dredged material may be obtained from the dredging of the
Captive Jetty(ies) area and the approaches. This material is of good quality, the same could be
used for reclamation purposes, reducing the cost of disposal in the deep sea.
Techno-Economic Feasibility Report
64
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
From preliminary assessment of the archival data, it was observed that bed and beach material is
generally fine to medium sand with D50 varying between 0.17 to 0.22 mm, which is considered as
a good material for reclamation. The total land area for the Captive Jetty(ies) and the steel plant
would require about 27 million m3 of dredged material.
A detailed geotechnical survey is desirable at DPR stage to observe the suitability of the material
for reclamation.
Figure 6-2: Location of the Captive Jetty(ies) water area and fore shore facilities at Site 3
6.2.7 Connectivity
No Captive Jetty(ies) can survive in isolation. It needs to be connected to the rest of the world
through a well-planned and well-connected road and rail network. As indicated earlier, this Captive
Jetty(ies) is basically envisaged to handle captive cargo required for the Steel and Cement plant
on the foreshore. It is also discussed that the IBRM would be brought from the hinterland mines
through slurry pipe lines and the other raw materials such as, CBRM and Flux for the steel plant
and Clinker for the cement plant would be brought through the Captive Jetty(ies). Hence, the use
of road and rail network are very limited however, a brief description may not be out of place, for
use in the posterity.
6.2.7.1 Rail
The existing rail network in the State of Odisha is shown in Figure 6.3.
A bridge across the Mahanadi is being constructed by the Hindustan Construction Company. At
present no rail connection exists to the proposed site, however the distance from the nearest
railway station (Siju/Badabandh) to the site is barely about 12 km, hence a rail corridor could be
built easily to provide connection to the coastal trunk line. The nearest existing railway station from
Techno-Economic Feasibility Report
65
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
the proposed site is at Paradip. A double line section, through the Paradip-Cuttack rail link,
connects the Howrah-Chennai Trunk line (See Photographs 6.4 and 6.5).
Figure 6-3: Railway Map of State of Odisha (East Coast Railway)
Photograph 6-4: Trunk line from Paradip to Cuttack
Techno-Economic Feasibility Report
66
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Photograph 6-5: Double line from Paradip to Cuttack in opertaion
Haridaspur-Paradip Rail Link
There is a new rail link under construction from the main trunk line to Paradip, in order to meet the
demand of traffic to and from the Paradip Port. This 78 km line under construction (shown in Figure
6.7) will link the Paradip Port with iron ore mines and for supply of imported coal to various steel
plants as a dedicated corridor. The estimated cost of the project is Rs. 441 crores and is to be
executed by Rail Vikas Nigam Limited (RVNL) through an SPV comprising RVNL, Paradip Port Trust
(PPT), Govt. of Orissa, Essar Limited, and others (source: Report of the Committee of Secretaries
Road Rail Connectivity of Major Ports. The Secretariat for the Committee on Infrastructure Planning
Commission, Government of India, Yojana Bhawan, Parliament Street, New Delhi). Around 80-90
% of the work of the rail is already over except for patches where work is going on at a good pace.
It must however be recognised that the rail and road network would be very sparsely used. The
Iron ore from the Barabil and/or other nearby mines will be grounded and would be sent through
slurry pipe lines as described in the next section and would be retrieved by removing the water
from the slurry on the plant side through beneficiation process.
As far as the rail linkage is concerned, the Site 3 is the best equipped and then the Site 1. Site 2
linkage would require a high level bridge over the Jatadhari River.
Techno-Economic Feasibility Report
67
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Figure 6-6: Proposed Haridaspur-Paradip Rail Link
6.2.7.2 Road
Paradip is connected to the State Capital, Bhubaneswar, and the commercial capital, Cuttack City,
by two prominent roads. It is connected to the steel mines near Daitari through Express Highway
No 5A. The road network of the area is shown in Figure 6.7.
At present Paradip is linked to NH-5 through a 2-lane road at Chandikhol about 77 km away. This
connection is through NH 5A and at Cuttack through SH 12. Four laning of Chandikhol-Paradip
Road NH-5A is under progress. The project is being implemented by NHAI at an estimated cost of
Rs.428 core. Construction of 4-lane Cuttack-Paradip Road SH-12 an all concrete road is
completed. This 82 km stretch provides the quickest connection to Cuttack. Various stake holders
including PPT and Govt. of Orissa are to fund the project which would facilitate traffic related to
IOC Refinery, Port Expansion and Regular Passengers. The NH 55 is about 5 km away from the
proposed site.
Another 4-Laning of Keonjhar-Panikoili Road (NH-215) is also under progress. This 269 km stretch
connects the port to the iron ore mines. The estimated cost of the project is Rs.1076 crores. NHAI
is preparing the DPR for the project to be taken up on BOT basis.
Techno-Economic Feasibility Report
68
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Figure 6-7: Existing road network near the Captive Jetty(ies)
The road linkage to the alternative sites are much similar to the rail linkage, for which the site 3 will
score over others.
6.2.7.3 Preferred Transport Option
Neither Railways nor the Road mode is expected to be in use for this facility. Instead, the cargo
logistics are planned using alternative modes. The raw material for the steel plant and their logistical
preference is given below;
Table 6-1: Transporation preference for the Projected Traffic for the Captive Jetty(ies) facility
Sl. No. Raw Material Form of Transfer Mode
1 Iron Ore Slurry Form Pipe Line
2. Coke and Coal Solid Ship (Import)
3. Lime Stone (Flux) Solid Ship (import)
4. Clinker Solid Ship/Rail (import)
5. Cement Solid Ship (export)
6. Iron ore concentrate & Pallet Solid Ship (Export)
7. Finished Products Solid Ship (Export)
Techno-Economic Feasibility Report
69
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
It is therefore evident that the all other cargo barring the Iron Ore is being transported through slurry
pipeline. The right of way for the slurry pipeline shall be acquired along the existing highways
and/or state highways for which the necessary permissions are under active progress.
6.2.8 Environmental Concerns
The environment concerns were also taken into account while deciding the suitability of the site. A
good distance of 15 Km was kept from the existing Gahirmatha Marine sanctuary from the northern
port limit. No habitation, vegetation and agriculture were seen in the identified area. There are no
rehabilitation issues,
The Site 1 and 2 will have greater impact on the environment due to changes in coastal morphology
because of erosion and accretion on account of littoral sand.
Further, a detailed Environmental Impact Assessment (EIA) Report will be prepared on the
environmental and social status of the region.
6.2.9 Capital and Maintennace cost
The last but not the least criteria is to select the site hinges on the cost of the project, both because
of the Capital Investments and through maintenance costs. As already explained above, the Site 1
and 2 would require identical cost in dredging and breakwater, where Site 3 requires no large-
scale breakwater for tranquility. In addition, the breakwater for the former two sites will require
breakwater for creating reclaimed land in addition to the harbour tranquility. On the other hand, the
Site 3 is located inside the estuary and well protected and has large back up government owned
land, which has been applied to the GoO.
6.2.10 Multi-criteria Analysis and Selection of Site
The alternative Captive Jetty(ies) 3 locations were subjected to multi-criteria analysis based on the
above criteria and were considered on a scale of 5, with the following nomenclature. The individual
sites will be graded on the criteria described above and the site with the highest score will qualify
as the selected location of the proposed Captive Jetty(ies);
5: Excellent
4: Very Good
3: Good
2: Average
1: Poor
Table 6.2 gives the details of the grading based on the various criteria described above in order to
determine the best location.
Techno-Economic Feasibility Report
70
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Table 6-2: Multi-Criteria Analsis for the Captive Jetty(ies) facility
Sl. No Criteria for Comparison Site 1 Site 2 Site 3
1 Depths available 4 4 3
2 Sedimentation 2 2 3
3 Protection from Waves 2 2 5
4 Sub Soil 2 4 4
5 Back up Land 2 2 5
6 Connectivity 3 3 4
7 Environmental Concerns 3 3 4
8 Cost 3 3 5
Total 21 23 33
From above it is clear that the Captive Jetty(ies) at the Jatadhari River bank is the most appropriate
and hence will be considered as the site in the rest of the report.
6.3 Functional Planning of Captive Jetty(ies) Facilities
6.3.1 Conceptual Planning
The high cost of modern ships and shipping economics dictate a rapid turnaround of ships calling
at any port, with minimum pre-berth waiting time, and minimum time for operations at the berth,
including berthing and de-berthing, with a view to maximizing the voyage time of the ships.
However, this requirement has to be balanced against the navigation and maneuvering
requirements in the Captive Jetty(ies) area and ship movement and handling limitations caused by
the need to wait for rise of tide (where natural depth is inadequate), and adverse effects of
excessive currents, velocities, excessive ship motions, mechanical and human factors etc.
Excessive motions of the berthed ships not only impede cargo operations but also cause damage
to ships and Captive Jetty(ies) structures, such as jetties and wharves, as well as the cargo itself.
Adequately tranquil water within the Captive Jetty(ies) is therefore essential, for berthing/de-
berthing and loading/unloading operations. There are stringent requirements types of vessels and
on certain loading /unloading equipment to be used on vessels.
For example, Container Vessels cannot tolerate rolling motions without jamming of the boxes, Bulk
Cargo vessels have similar constraints if continuous unloaders are utilized, and vessels carrying
cryogenic cargo call for isolation of unloading areas and restrictions on other traffic, while
cryogenic liquid carriers or gas carriers are transiting the channel. Though, for the present facility,
only bulk carriers would be using the facility, the discussion reiterates that, planning needs to take
care of the types of cargo to be handled. Thus planning of a Captive Jetty(ies) calls for
consideration of a number of inter-connected factors, such as:
Ships Sizes Expected at the Captive Jetty(ies) based on characteristics and quantum of
cargoes to be handled
Techno-Economic Feasibility Report
71
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Number of Ship Calls
Handling Capacity and Number of Berths
Channel alignment and dimensions
Land Area Requirements
Ships’ operational areas
Each of the above considerations is itself dependent on a number of factors, some of which are
outside the control of port planners or operators. The above parameters are discussed in the
following paragraphs to enable evolving the layout of the present Captive Jetty(ies).
The type and volume of traffic in each commodity has already been discussed in Chapter 5, from
which other planning parameters, such as ship sizes, parcel size etc. can be readily arrived at in
order to provide a cost-efficient Captive Jetty(ies). Similarly, the methodology of loading/unloading
vessels and other landside parameters, such as storage areas, rail and road access can be readily
understood and planned for maximum efficiency. These parameters go into what may be called
port planning. However, the merging of marine environmental parameters into the planning process
of what may be called Harbour Planning is perhaps equally, if not more, important since it
determines the throughput of the facilities. These aspects are first discussed in conceptual terms,
before going in to the overall planning of the facility.
6.3.2 Ships Sizes Expected at the Captive Jetty(ies)
A very important aspect of port planning is to determine the types, sizes and number of ships that
may be expected to call at the Captive Jetty(ies) to carry the forecast traffic. The types of ships
are related to the trade. Specialized ships are used for the carriage of Petroleum products,
Chemicals, Containers, break- bulk and dry bulk cargoes. The size of ships usually depends on
voyage distance and trade related factors. Considerable reduction in freight rates is realizable,
using increasing vessel sizes.
Thus, generally, large bulk carriers are used for long voyages due to cost advantages. For shorter
coastal hauls, smaller vessels are used. Another aspect, which may have a decisive influence on
ship size, is the trade route(s) on which the ships will ply. There are some types of vessels, which
have come to be preferred due to their cost-effectiveness on certain trade routes. Finally, draft
limitations, if any, at the loading and/or destination ports would also govern the size of ships calling
at the Captive Jetty(ies).
In Chapter 5, the traffic expected to be handled at the proposed Captive Jetty(ies) has been
discussed in detail. The traffic projections are reproduced here for ready reference in Table 6.3.
In the initial years, billets and slabs of Iron will be imported for re-rolling, only for the Orissa plant,
which will subsequently be stopped, when the actual production from the Odisha steel plant
commences. Accordingly, the port would be designed for a total traffic of about 52 million tonnes,
expandable to 100 million tonnes with no additional storage requirement.
Techno-Economic Feasibility Report
72
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
The detailed functional planning has been carried out for the first 10-year period for the 52 MTPA
traffic. Since the design will be done in a scalable model, expansions could be accommodated
with ease. In addition, the initial operations shall be carried out at a lower utilisation factor.
Subsequently, the development would adopt a Master Plan approach. This methodology affords
the advantages of utilizing the actual realization of cargo types and throughputs, ship size build-
up, clientele/user pattern and preferences, and revenue realization.
Table 6-3: Total Traffic (in Million tonnes)
Commodity
Odisha Project
(13.2 MTPA) Mode of transport
Import Cargo
Coking Coal 8.84 Ship
Anthracite 0.32 Ship
PCI Coal 2.84 Ship
Thermal Coal 4.50 Ship
Lime stone (SMS) 2.40 Ship
Dolomite (SMS) 0.40 Ship
Bentonite 0.30 Ship
Clinker 5.30 Ship
Quartzite 0.03 Ship
TOTAL 24.93 Ship
Export Cargo
Finished Steel*1 6.00 Ship
Pallet/Iron Ore Concentrate 15.00 Vijaynagar/Dolvi
Cement*1 6.00 Ship
TOTAL 27.00 Ship
GRAND TOTAL 51.93 Ship
The facilities at a Captive Jetty(ies) to a large extent depend on the size of the vessels that use the
Captive Jetty(ies) facility. The channel dimensions, the depths at the berths, the length of the
berths, the capacities of the equipment all depend on the type and the size of the ships using the
facility. In addition, before deciding on the ship sizes, it must be remembered that, it is more of a
techno-economic process and various scenarios are required to be studied, before arriving at the
final ship size. The bigger the ship the deeper would be the approach channel, the longer would
be the berths and so is the capacity of the handling equipment. On the other hand, the bigger the
ships, the lesser are the transportation costs. Hence the process is iterative and the capital cost
estimates are weighed against the savings in transportation, in order to arrive at the required ship
size.
Techno-Economic Feasibility Report
73
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Further, the premise on which the Captive Jetty(ies) is developed is as follows: ‘this Jetties will be
planned as a Captive Jetty(ies) for handling around 100 million tons ultimately. No further expansion
of the facility is envisaged beyond that phase. Hence the ship size, the channel dimension and the
foreshore area should be sized accordingly’. This Captive Jetty(ies) therefore, is essentially built to
cater to the demands of the ISP consisting of the steel plant (13.2 MTPA), 900 MW power plant
using dual fuel and the cement grinding units in the immediate vicinity of 10 MTPA. It must also be
recognized that, there are basically 3 types of cargo to be handled at the Captive Jetty(ies). The
first type is coal, which is an imported cargo to be brought in from Indonesia or South
Africa/Australia. The second type, limestone, is to be brought from an Indian and/or Middle East
locations and hence would be more or less coastal shipping. That brings us to the export cargo
comprising of steel products, which again would be transported through coastal shipping.
Accordingly, end of initial stage, which is defined as the planning phase, the volume of the various
types of cargo to be transported are; coal – 16.5 million tonnes, Lime Stone – 3.13 million tonnes
Cement clinker 5.40 million tonnes and steel products 6.0 million tonnes. Out of the above, coal
would be handled in a mix of Panamax and cape size vessels, the limestone would be handled in
Panamax and Handymax mix vessel and the steel products in handymax vessel of 45000 DWT, and
probably with a shipping population falling between 20,000 to 30,000 DWT. Coking Coal is today
being brought in Panamax vessels to the east coast ports of Paradip, Visakhapatnam and Chennai.
Recently Paradip Port has reported of handling bigger parcels up to 275 m length and 45 m beam
with 14.5 m loaded draught.
However, it is very economically advantageous to consider deploying more and more Cape Size
vessels to bring in greater savings in the transportation costs; necessitating greater channel depth.
Since, it is well understood that the channel depth vis-à-vis the vessel size is a techno-economic
process, the ship sizes together with their main dimensions considered for planning purposes for
this report is given in Table 6.4.
Table 6-4: Assumed ship sizes for various products
Cargo Vessel Design vessel Dimensions (m)
Size (DWT) Length Beam Draft
Coal 180,000 290 45 17.5
Lime Stone 75,000/45,000 230/212 33.0/32.5 13.5/12.0
IBRM 180,000 290 45 17.5
Steel Products 45000 212 32.5 12.0
Lime Stone 45,000 212 28.2 11.5
Coastal Shipping (Cement) 10000-25000 165 24.2 8.5
LNG - Qmax 267,000 m3 345 55 13.60
LNG 89,880 m3 239 40 11.00
Techno-Economic Feasibility Report
74
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
6.3.3 Number of Ship Calls
With the volume of cargo and ship sizes having been set out in the earlier paragraphs, the number
of ship-calls may now be calculated. For doing so, it is envisaged that full shiploads would be the
average shipment for all commodities. The distribution of ship sizes is to be considered to assess
the number of ship calls that would occur for each commodity, between the possible maximum
size governing the Ocean trade and the minimum size of vessel likely to be utilised.
As such, the throughput of each commodity will be handled by a total number of ships under a
particular distribution of ship size. In this case the pattern of distribution is taken as normal, as
evidenced by observations of the ocean trade. Accordingly, an attempt has been made to arrive at
the number of ships based on an assumed distribution indicating vessel size and numbers for
meeting the throughput in each commodity.
The number of ship calls, for each type of ship, for the facility, corresponding to the development
of the ISP, is worked out and given in Table 6.5. Total ship calls therefore would be 50 for Panamax
and 54 for the Cape size carriers. This is possible to handle in one berth. LNG will come in variety
of sizes and hence only average size is mentioned in the computations.
Table 6-5: Ship calls for the current Cargo
Total throughput (MTPA)
Distributed throughput Assumed Vessel size
(DWT)
No. of Ships calls
Total throughput achieved % Throughput (MTPA)
COAL
16.5 75 12.38 180.000 69 12375000
25 4.12 80,000 52 4152000
121 16500000
LIME STONE, DOLOMITE & QUARTZITE
2.83 60 1.7 75000 23 1698000
40 1.13 45000 26 1132000
49 2830000
IBRM
15.00 75 11.25 180000 63 11340000
25 3.75 80000 47 3760000
110 15100000
STEEL PRODUCTS
6.0 50 3.00 45000 67 3015000
50 3.00 25000 120 3000000
187 6015000
BENTONITE
0.3 50 0.15 75000 2 150000
50 0.15 45000 4 180000
6 330000
CEMENT
6.0 50 3.00 45000 67 3015000
Techno-Economic Feasibility Report
75
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Total throughput (MTPA)
Distributed throughput Assumed Vessel size
(DWT)
No. of Ships calls
Total throughput achieved % Throughput (MTPA)
50 3.00 25000 120 3000000
187 6015000
CLINKER
5.3 50 2.65 45000 59 2655000
50 2.65 45000 106 265000
165 5305000
Total Ship Calls per Year = 825
6.3.4 Handling Capacity and Number of Berths
The arrival of ships at the berth is usually stochastic in nature and the determination of the adequacy
of the berth is generally dictated by the berth occupancy ratio, which is defined as the number of
hours the berth is occupied by a vessel per year divided by the total number of hours available
each year for potential berthing. If higher berth utilisation is contemplated, to keep the number of
berths to minimum, queuing of ships may take place resulting in a longer waiting time and higher
demurrage. If more berths are provided to reduce the occupancy and the demurrage, the project
becomes capital cost increases. Therefore, a balance between the two is required so that both
capital cost and demurrage are kept at a minimum.
Berth occupancy is considered in relation to acceptable waiting time and such provision covers
the following occurrences:
Expected pattern of arrival - whether random, scheduled or some other pattern
Occurrence of reduced depth of water at berth – caused by tidal restrictions and other
berthing restrictions.
Cargo handling restrictions at berth
Cargo handling rates achievable and ship’s time at berth.
Incidence of weather conditions which delay ship berthing and departure.
Downtime of handling equipment due to wind conditions/mechanical failures.
Reduction in number of hours of work per day and incident holidays
Handling equipment reliability factors
Berth occupancy is usually considered acceptable for a single berth when this figure lies between
45% and 60%. In support of this stipulation, a calculation is made for various cargoes proposed
to be handled at this Captive Jetty(ies). A major consideration to validate this calculation would
have to be the ship arrivals, i.e. whether it is right to regard arrivals as purely random (most unlikely)
or whether it can be considered fully planned and programmed (also most unlikely if ships are
coming from afar) or whether some intermediate condition could be said to apply.
Assuming that ship arrivals are scheduled, but, within this scheduling there creeps a degree of
error due to delays at loading ports, bad weather and other mishaps etc. which requires an arrival
Techno-Economic Feasibility Report
76
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
date tolerance of + 3 days, it is estimated that on a 50 % berth utilisation, about 40% of the ships
would be delayed in obtaining berths and that the average waiting time would be of the order of 7
to 8 hours; which is considered to be an acceptable condition.
The equation used with Poisson arrivals and Erlangian service time distribution taking TW/TS = 1
for bulk and TW/TS = 0.5 for containers ensures the time at port does not exceed twice the service
time for bulk and 1.5 times the service times for container vessels. This is an accepted norm and
equipment capacity arrived at covers these conditions. The rated ship unloading capacity arrived
at thus with 60% handling efficiency ensures meeting with the above requirements. The primary
assumption in the above calculation is that all operations including navigation, maneuvering,
berthing and de-berthing are proposed to be carried out 24 hours per day. The principles of shore
side planning discussed above have been considered and provided for in the calculations for
evaluating the number of berths, rated ship handling capacity and related material handling
requirements and stockyard/storage requirement. Accordingly, the equations developed account
for the following system properties:
Ship Arrival pattern: Poisson
Ship service pattern: Erlangian K2
Waiting time to service time ratio w
s
T1
T for bulk ships
Berth Occupancy for bulk cargo: 1 berth : 50%
2 berths : 71%
3 berths : 80 %
4 berths : 88%
5 berths and above : 95%
The typical equation applied is cited below:
sT = berth + de-berth time + hatch move time + shipload/unload ………………… (1)
Where,
sT = Service time/ship
Shipload/ unload time = DWT
0.6xr
Hatch move time = 30 % (Berthing and de-berthing time)
DWT = Average Ship Size
Berthing + De-berthing time = 4 hr (Assumed)
r = rated ship handling capacity/h accounts for the following variations
10% dwt for trimming at 20% Capacity. A factor of efficiency of 0.6
provided above covers these
variations occurring during
Cargo handling
Techno-Economic Feasibility Report
77
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
20% dwt to be handled at 30% Capacity.
70% dwt to be handled at 90% Capacity.
sT x No. of ships = Total annual time = 330 x 20 x n x P berth hr …………. (2)
Where, n = number of berths; P = occupancy factor
Combining the expressions 1 and 2, the following generalized equation emerges covering the
parameters.
DWT4+30%(4hr)+ x(No.of Ships) = 6600Pn
0.6xr
or
1.666DWT5.2+ x(No.of Ships)= 6600 Pn
r
Above expression is applied to each of the annual throughputs, with the respective average ship
size calculated by weightage average method, in order to arrive at the rated ship handling capacity
and number of berths. Table 6.7 computes the lists the weighted average ship size and the number
of ship trips and the number of ship trips.
Some types of cargoes require an exclusive berth due to their very nature e.g. petroleum products,
chemicals, or cryogenic cargo, while some cargoes could be handled at a common multi-purpose
berth. Thus, a decision on the number of berths and their utilisation is a complex optimization
exercise.
Table 6-6: Average ship size and number of ship trips (Based on Table 6.5)
Commodity Average Ship Size* DWT
(13.2 MTPA)
Throughput Million tonnes/yr.
13.2 MTPA
Coking Coal 136,500 16.5 (121)
Lime Stone 57,000 2.83 (49)
IBRM 155,000 15.10 (110)
Steel Products 35,000 6.01 (187)
Bentonite 38,000 0.33 (6)
Cement 35,000 6.01 (187)
Clinker 26,000 5.30 (165)
Note: Average ship size has been taken as the weighted average based on the cargo handled
and the ship distribution.
In the present case, the dry bulk commodities like Coal, and Limestone could conceivably be
handled at the same berth. Coal traffic initially would require one separate berth from the beginning
as will the limestone and out bound IBRM. There will be 2 cape size berths corresponding to
Techno-Economic Feasibility Report
78
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
average ship size of 150,000 DWT or more. 2 Panamax berths for handling Bentonite and Gypsum
and Limestone. The other berths for Steel products, Cement and other cargos with an average
vessel size around 30-35000 DWT will be handled in berths designated for handymax vessels.
6.3.4.1 Number of Berths and Handling capacity
Using the above expression, the rated capacity of unloading and number of berths for each
commodity namely Coal, Lime stone, IBRM, Steel Products, Bentonite, Cement and Clinker for the
52 million tons per year capacity scenario is given in Table 6.7.
Table 6-7: Number of berths and unloading rate cosidered for the commodities.
Berth/De-berth
Hatch movement
Average Parcel Size
Annual Throughput
No of Ship trips
Efficiency Factor
Rated capacity
Occupancy Factor
Number of Berths
3 0.9 136,500 16.5 121 0.60 5000.00 0.65 1.2
3 0.9 57,000 2.83 49 0.60 5000.00 0.36 1
3 0.9 155,000 15.10 110 0.60 6500.00 0.51 1
3 0.9 35,000 6.01 187 0.60 1200.00 0.43 2
3 0.9 38,000 0.33 6 0.60 4000.00 0.04 1
3 0.9 35,000 6.01 187 0.60 1200.00 0.57 2
3 0.9 26,000 5.30 165 0.60 2000.00 0.54 1
Total Ship Calls per annum 825 Total no of Berths 10.00
Table 6.7 gives the calculations for the various products to be handled in the initial operations. The
first item coal, with an annual throughput of 16.5 million tonnes, would be transported in either
Panamax or Cape Size vessels. The calculations assume the 330 days working in a year with 20
hours per day working. For the coal and Lime Stone 2 unloaders with a 2500 TPH rates capacity
would be deployed on each berth. For the IBRM berth, 2 unloaders of 3250 TPH rated capacity
would be required. For the steel products and Cements, special handling is doctrine with mobile
harbour cranes and pneumatic loaders respectively. Additional berths for the port crafts also could
be accounted in the later years of the first development, so that the optimization of the capital
expenses are achieves. Considering an average berth length of 340 m, a total berth length of 3400
m for the cargo handling and additional 3 berths for the port crafts shall be made provisioned.
Hence, for this report a berth length of 3400 m would be considered.
6.3.5 Channel Alignment and Dimensions
6.3.5.1 General
The next aspect to be considered is whether the approach channel provides a comfortable entry,
requiring wind, wave and current forces to be on the bow or stern, rather than broadside. The
alignment of the approach channel should generally be such that the entry and exit of vessels to
and from the Jetty(ies) are possible with the maximum possible ease. This requires that the
approach channel should be aligned to the most frequent direction of waves, so that rolling and
yawing of the vessel, while transiting the channel, are a minimum.
Techno-Economic Feasibility Report
79
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
However, as already mentioned, the proposed Jetty(ies) has limited option for the alignment of the
channels, keeping the same outside Paradip Port limits. A perusal of Figure 6.7 shows that there
are very limited options for alignment of the approach channel, which necessarily has to be heading
the about 3000 N for obvious reasons of keeping the entrance of SW monsoon waves in to the
estuary.
The channel after about 5300 m would turn to be parallel with the Paradip Port boundary. A bearing
further north would enter or come very close to the Paradip Port waters. Interestingly, this bearing
is very close to the bearing of the Paradip Port Approach Channel, which is 1200. It is also
supported by the most prominent wave direction, i.e., SSE or 1570. The length of the channel is
about 6 km to the 15 m contour, and about 11 km to the 20 m contour. The alignment of the
channel is given in Figure 6.8 avoiding the Paradip port limits. A suggested layout of the
navigational channel is shown in Figure 6.8 below.
Figure 6-8: Provisonal Channel Allignment
Techno-Economic Feasibility Report
80
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
6.3.5.2 Width of Channel
The required width of any channel, measured at bed level, is expressed in terms of the beam of
the Design Vessel. In accordance with BIS Code IS: 4651 (Part V) – 1980, the channel width should
be 3.3 to 5.0 times the beam of the Design Vessel for one-way traffic. For two-way traffic, BIS
recommends the channel width to be 6.1 to 8.0 times the beam of the Design Vessel. These
numbers are the mandatory minimums to be adopted. However, the Consultant is free to refer to
other standards and recommend the channel width, which should not be less than the statutory
minimum specified by BIS.
The Permanent International Association of Navigation Congresses (PIANC) and the International
Association of Ports and Harbours (IAPH) have published a Guide for Design of Approach
Channels, in which the International Maritime Pilots Association has participated. It has been
proposed in this Guide that model studies are desirable. However, a Concept Design method for
Approach Channels has been recommended as given in the Table 6.8.
The values adopted in the case of this Port channel are shown in bold italics.
Table 6-8: Width calculations for approach channel
1. Basic Manoeuvring Lane, WBM Manoeuvrability
- Good 1.3 B
- Moderate 1.5 B
- Poor 1.8 B
2. ADDITIONAL WIDTH Wi Vessel Speed
Outer channel exposed to open
water
Inner channel protected water
(a) Vessel speed (knots)
- fast > 12 0.1 B 0.1 B
- moderate > 8-12 0.0 0.0
- slow 5-8 0.0 0.0
(b) Prevailing cross wind (Knots)
- mild 15 (< Beaufort 4) all 0 0
- moderate > 15-33 fast 0.3 B -
(> Beaufort 4 - Beaufort 7) mod 0.4 B 0.4 B
slow 0.5 B 0.5 B
- severe> 33-48 fast 0.6 B -
(>Beaufort 7 - Beaufort 9) mod 0.8 B 0.8 B
slow 1.0 B 1.0 B
(c) Prevailing cross current (Knots)
- negligible < 0.2 all 0.0 0.0
- low 0.2 - 0.5 fast 0.1 B -
mod 0.2 B 0.1 B
slow 0.3 B 0.2 B
- moderate > 0.5 -1.5 fast 0.5 B -
mod 0.7 B 0.5 B
slow 1.0 B 0.8 B
Techno-Economic Feasibility Report
81
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
- strong > 1.5 - 2.0 fast 0.7 B -
mod 1.0 B -
slow 1.3 B -
(d) Prevailing longitudinal current (knots)
- low < 1.5 all 0.0 0.0
- moderate > 1.5 – 3 fast 0.0 -
mod 0.1 B 0.1 B
slow 0.2 B 0.2 B
- strong > 3 fast 0.1 B -
mod 0.2 B 0.2 B
slow 0.4 B 0.4 B
(e) Significant wave height Hs and length --- (m)
- Hs < 1 < L all 0.0 0.0
fast 2.0 B
- 3>Hs > 1 and = L mod 1.0 B
slow 0.5 B
fast 3.0 B
-Hs > 3 and > L mod 2.2 B
slow 1.5 B
(f) Aids to Navigation
- excellent with shore traffic control 0 0
- good 0.1 B 0.1 B
- moderate with infrequent poor visibility 0.2 B 0.2 B
- moderate with frequent poor visibility > 0.5 B > 0.5 B
(g) Bottom surface
- if depth > 1.5 T 0 0
- smooth and soft 0.1 B 0.1 B
- smooth or sloping and hard 0.1 B 0.1 B
- rough and hard 0.2 B 0.2 B
(h) Depth of waterway
- > 1.5T (>1.5t for Inner Channel) 0 0.0 B
- 1.5T - 1.25T(<1.5T-1.15T for Inner Channel 0.1 B 0.2 B
- < 1.25T (<1.5T for Inner Channel) 0.2 B 0.4 B
(i) Cargo hazard level
- low 0.0 0
- medium 0.5 B - 0.4 B
- high 1.0 B - 0.8 B
3. Width for bank clearance, (WBr or WBg)
Sloping channel edges and shoals
Fast 0.7 B -
Moderate 0.5 B 0.5 B
Slow 0.3 B 0.3 B
Steep and hard embankments, structures
Fast 1.3 B -
Moderate 1.0 B 1.0 B
Slow 0.5 B 0.5 B
4. Width for passing distance, Wp
Vessel Speed Fast 2.0 B -
Moderate 1.6 B 1.4 B
Techno-Economic Feasibility Report
82
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Slow 1.2 B 1.0 B
Encounter traffic density
- light 0 0
- moderate 0.2 B 0.2 B
-heavy 0.5 B 0.4 B
Thus according to PIANC/IAPH, the width of a one-way channel would be 5.1 times the beam of
the Design Vessel. One-way channel is contemplated in the initial operations (where largest vessel
is Cape), that is, 5.1 x 45 = 230 m. For a two-way channel, it is proposed to widen the channel to
6.9 B = 310 m.
6.3.5.3 Depth of Channel
The depth required a ship to navigate any sector of a channel safely and efficiently depends
principally on the maximum draft and the climatic conditions obtaining at the time of navigation. It
is obvious that the depth of water must be adequate to allow for the effects of heave, pitch, roll,
and squat. Other factors such as fresh water draft, errors in charting, or post-charting siltation and
dredging tolerances also need to be taken into account. The additional depth of water required
over and above the ship’s maximum draft due to the combined effect of all these inter-related
factors is termed as Net Under-Keel-Clearance, which is required to be 0.3 m for soft bottoms
and 1.0 m for rocky bottoms. The channel depth components are depicted in Figure 6.9.
Figure 6-9: Channel depth components
CHANNEL DEPTH COMPONENTS
For a given ship and channel sector, squat increases with speed, in accordance with the following
formula:
Squat = 2
2
2
14.2
nh
nh
pp F
F
L
Safety
Clearance
Techno-Economic Feasibility Report
83
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Where, = Volume of displacement = CB Lpp B T
Lpp = Length of ship between perpendiculars
B = Ship beam
T = Ship draught
CB = Block coefficient
Fnh = Froude depth number = ghV /
Where, V = Speed through water in m/s
h = Water depth in m
g = Acceleration due to gravity= 9.81 m/s2
It is envisaged to deploy Cape Size vessels for Coal and IBRM. In fact Cape Size vessel will
commence operation from the very beginning of operation when, the squat would be 0.65 m.
The other parameters which govern the depth of the channel are now examined. Heave is the
vertical up and down motion of the vessel due to wave action. It is assumed here that the design
wave height shall be 3 m. Since the waves in nature are not symmetrical, the trough being only
one-third of the wave height below the mean water level, the heave is taken as 1.0 m.
The pitch of the vessel is taken as 10, from similar studies of ship manoeuvrings on real time, full
bridge models. The vertical motion is therefore 2.0 m.
Thus the depth of water in the channel has to be the draft (17.5 m) plus the squat (0.65 m) plus
heave (1 m) plus pitch (2 m), giving a total of 21.15 m. Deducting 1.0 m for entry restricted to high
water neaps, the dredged depth has to be 20.15 m. Adding a net under keel clearance of 0.3 m
and a dredging allowance of 0.25 m, the capital dredging has to be to 20.70 m below Chart Datum.
The maintained depth could however be reduced to 20 m CD, considering that ships can pass
through mud layers, on the concept of nautical depth. Therefore, a depth of 20 m will be maintained
from the beginning of Captive Jetty(ies) operation.
6.3.6 Land Area Requirements
For purposes of determining the land requirement, it is necessary to look at the present as well as
future projections. In the case of every port developed in the country during the last 40 years, the
earlier projections have been shown to be unduly pessimistic even though the initial take-off was
slow. It is therefore desirable to take a view that possible future land requirements are assessed
liberally.
For the present Captive Jetty(ies) designed as a captive facility, the growth of the cargo would
depend on the demands of the plants as well as their expansions if any. Those details naturally
would not be available now; thus for the present purposes, the requirements of traffic as indicated
in Table 6.1 have been considered. The norms adopted to arrive at the area provisions for storage/
stack pile, rail siding, service and main roads, administrative and other offices / dwellings, safety
systems, green belt etc. are detailed in the following tables (Table 6.9 and 6.10).
Techno-Economic Feasibility Report
84
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Table 6-9: Stack Volume Quantity Basis
Storage area commodities Norm (Whichever is higher)
Solid Bulk :
Coal
Lime Stone
1 month throughput or three ship loads whichever is higher
General Cargo 15 days storage or 8 times parcel size
Table 6-10: Stack Volume Quantity Basis
PROVISION
Rail 4 line main
entry siding with
½ km loop.
4 entering lines : 12m x 500m
4 Exit : 12m x 500m
2 Establishing lines : 6m x 760m
2 Engine escape : 6m x 760m
1 Sick line : 3m x 760m
2 Crossing gap : 10m x 1000 m
2 Washing lines : 6m x 760m
Roads : Main highway approach into 10 km long x 24m
Service Utilities Fire Station.
Staff Building : 50m x 100m
20 no. Tender parking : 24 m x 20m
Water tank, over ground : 350m2
Foam storage : 50m x 20m
Dedicated fire tender exist roads (5 no. x 6m x 500m): 15000m2
Power Sub-
Station
132 KV / 33 KV : 150 m x 150 m
33/11 KV Switch yard and load dispatch : 100 m x 50m
5 unit sub-station (11 KV/3.3KV and 11 KV /415V): 5no. x 50 x 20m
Fenced area and approach : 3 x 4000m
ADM Buildings,
Office complex,
Staff quarters.
4 storey main Captive Jetty(ies) office shipping Cos Stevedores office: 10 cubicles
Customs offices
3 Bank counters
10 Cargo agents offices
Canteen for staff & officers
Staff Quarters for 500; (2 storey units), Park, green belts , car parks at each office units
: 1000m x 500m
Industrial Potable Garden Service
Water Supply Water treatment plant, pump rooms :100 m x 100 m
Green belt In Captive Jetty(ies) : 6 corridors each 7000m x 10m
Out Captive Jetty(ies) : 6 corridors each 2000 m x 5m
Adopting the above norms / basis of provisions the areas required have been worked out. General
uncertainty allocation of 20% is accounted for area evaluation.
6.3.6.1 Water front and Berth Backup area
The length of the waterfront required for developing the berthing facilities depends largely on the
annual throughput, parcel size and the cargo handling rates. An assessment of the number of
berths required for cargo servicing has been presented earlier in the chapter. In total 4500 m of
berth is planned for the facility. The deck width would consist of rail span = 18 m + from the outer
rail to the berth face 3.5 m + conveyors two rows 6.5 m + others including the utility lines= 7.0 m.
Techno-Economic Feasibility Report
85
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
However, when the back of the berth is also used for berthing and cargo handling the requirements
would go up further. A deck width of 35 m adopted for all the berths for the purpose of computing
the area of the berths. Alternative width calculations for the berth is given later in the chapter.
As far as the length of the berths are concerned based on the international guide lines, berth length
=B1.25xL , where,
BL = the length of the Ship
There will be two cape size berths, 5 berths for Panamax vessel handling and three handymax
berths. The other three berths shall be earmarked for the port crafts and other requirements.
For the length calculations the length of the ships considered area;
1. Cape Size Vessel: 290 m
2. Panamax Vessel: 230 m
3. Handymax Vessel: 212 m
Accordingly, the water front area is computed in Table 6.11.
Table 6-11: Berth Length and Back up Area (Berth area)
S .No Berth Number
Length
(m)
Width
(m)
Apron Area
(Sq. m)
1. Berth for 52 MTPA 10+3 3400 35 119,000
6.3.7 Storage Requirements
6.3.7.1 General
The following norms are usually adopted as an international practice and earlier discussed for
calculating storage areas in a Captive Jetty(ies) facility.
Storage area to cater to the higher of the; 15 % of the annual cargo throughput; Or 1.5 times the
maximum parcel size. The above criteria will be followed for the dry bulk cargo to be handled at
the Captive Jetty(ies). However, for some of the cargo, the annual throughput is relatively small
as compared to the parcel sizes and hence the frequency of vessel calls will be low to moderate.
This will, most likely, allow for the clearance of the stored cargo prior to the arrival of the next
shipment. Further, during cargo handling operations at the Cargo berths, part of the cargo is likely
to be directly evacuated without passing through the storage area. Under these circumstances,
the storage areas could be optimized especially for the Coal, which is the most predominant
cargo in the initial stages of development. Other factors to be taken into account in determining
the size of the storage areas are: stowage factor, angle of repose, maximum and average stacking
height, aisle space, reserve capacity factor, peaking factor, etc. The storage area requirements
for each commodity are examined in detail in the following sections. The requirement of the
storage areas in the Captive Jetty(ies) for the Master Plan horizon for the realizable traffic scenario
was assessed.
Techno-Economic Feasibility Report
86
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
6.3.7.2 Dry Bulk Cargo
The stockyard storage volume depends upon the annual throughput and the parcel size. The
general recommendation of UNCTAD is that the storage volume shall be 1.5 times the parcel size
or 1/15 of the annual throughput (i.e. 6.6% of the annual throughput).
UNCTAD also prescribes certain planning charts (Figure 51 UNCTAD applicable for throughput
over 4 MTPA) as shown below in the figure 6.10.
This chart gives average and peak storage volume to be less than 1% on the basis of Monte Carlo
simulation analysis. According to these charts, the peak storage volume is found to be almost
twice the average storage volume. In the case of Jatadhari Captive Jetty(ies), as almost the entire
cargo is for single user and is well planned and chattered, hence, the peak storage volumes are
rather low.
Figure 6.10: Planning Chart for Dry Bulk Cargo
Source: From UNCTAD, 1985: Figure 51
Thermal Coal
Coal will be stacked in the stackyard areas initially before evacuation by Barge/rail/road. Three
separate stockpiles need to be provided to cater for 3 grades of coal. As coal parcels would be
evacuated by a conveyor system directly from the berth side and up to the stackyard, a storage
volume (1/15 x 12,000,000) is recommended.
A stacking height of 10.0 m is recommended for initial phase development and 14 m is
recommended for further phases at this Captive Jetty(ies), that would take care of variations of
peak demand and exigent situations. The width of the stockpile and the berm for movement of
Techno-Economic Feasibility Report
87
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
pay loaders/trucks would be 40 m and 10 m respectively assuming stacking from both sides. The
width of the stockpile can be increased up to 50 m if stacker reclaimer is found to be economical
in the future. The storage area requirement has been worked out based on the following
parameters:
Average bulk density (= 0.8 t/cum)
Stacking height: 10 m for initially, 12 m & 16 m for subsequent phases
Angle of repose (= 37o)
Space for movement of equipment between stockpiles (= 10 m)
Average width of the stockpile (= 50 m)
Table 6.12: Determination of the Stockyard Area for Coal
S.No Item Unit 52 MTPA Stage
A Annual Throughput Million Ton 16.5
B Holding Capacity Required = A/15 Ton 1100000
C Density of Cargo (From UNCTAD) Ton/cum 0.80
D Holding Volume Required : (B/C) cum 1375000
E Stacking Height m 10
F Angle of Repose Degree 37
G Stacking Area Sq. m. 420
H Length of the stockpile = D/G m 3275
I Storage Factor = B/H Ton / m 336
J Width of the Stockpile m 50
K Stockpile Area = H*J in Ha Ha. 16.4
A stockpile area of about 19 ha would be required (20% more) to account for associated facilities
like conveyors, transfer towers, wagon loader systems, buildings, treatment plants, dust
suppression system, surface water collection etc.
IBRM
As Iron ore parcels would be evacuated by a conveyor system directly from the beneficiation area
to the berth, a storage volume (1/15 x 13,000,000) is recommended. The storage area
requirement has been worked out based on the following parameters:
Average bulk density (= 2.4 t/cum)
Stacking height: 8 m initially & 12 m for subsequently
Techno-Economic Feasibility Report
88
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Angle of repose (= 37o)
Space for movement of equipment between stockpiles (= 10 m)
Average width of the stockpile (= 50 m)
Table 6.13: Determination of the Stack yard Area for IBRM
S.No Item Unit 52 MTPA stage
A Annual Throughput Million Ton 15.00
B Holding Capacity Required = A/15 Ton 1000000
C Density of Cargo (From UNCTAD) Ton/cum 2.4
D Holding Volume Required : (B/C) cum 416667
E Stacking Height m 10
F Angle of Repose Degree 37
G Stacking Area Sq. m. 420
H Length of the stockpile = D/G m 992
I Storage Factor = B/H Ton / m 1007
J Width of the Stockpile m 50
K Stackpile Area = H*J Ha. 5.1
A stockpile area of about 5 ha and 12 ha is earmarked for IBRM storage taking the multiplicity of
users and the number of stock piles and consequent space requirements due to separation
distances.
Cement
Based on UNCTAD (1985) recommendations, Figure 51, the storage volume for a throughput of
1.00 MTPA is about 85,000 T.
The storage area requirement has been worked out based on the following parameters:
Stacking Height of 8 m (for bags as well as clinkers)
Aisle Factor covered storage = 1.5
Average Bulk density = 1.0 t/cum,
Angle of repose = 35o and
Closed and open storage in the ratio of 50 : 50 for bagged cement and clinker
Clinker storage width of 20 m and Bagged Cement storage width of 10 m.
Techno-Economic Feasibility Report
89
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Table 6.14: Determination of the Stack yard Area for Cement
S.No Item Unit 52 MTPA
A Annual Throughput Million Ton 6.0
B Holding Capacity Required = A/15 Ton 400000
C Density of Cargo (From UNCTAD) Ton/cum 1.3
D Holding Volume Required : (B/C) cum 307700
E Holding Volume Required for Cement Bags : (D/2) cum 153850
F Holding Volume Required for Clinker : (D/2) cum 153850
G Stacking Height for both cement & Clinker
m 8
H Width of the Stockpile for cement bags m 10
I Stacking Area = G*H Sq. m. 80
J Length of the stockpile = E/I m 1924
K Cement bag Stock pile Area = H*J Ha. 1.94
L Storage Factor for Clinker = E/J Ton/m 80
M Width of the Stockpile for Clinker m 20
N Angle of Repose Degree 35
O Stacking Area Sq. m 115
P Length of the stockpile = F/O m 1338
Q Clinker Stock pile Area = M*P Ha. 2.68
R Total Stack pile Area Required for both cement bags & Clinker = K+Q
Ha. 4.62
As such the total area of 5 ha is estimated for the respective stockpiles. Additional area of 200%
between the stacks for mechanical equipment and Roads has been taken. Altogether, an area of
15.0 ha is considered for handling cement.
Lime Stone
Lime stone is used as Flux in steel extraction process. Storage volume (1/15 x 1,500,000) is
recommended. The storage area requirement has been worked out based on the following
parameters:
Average bulk density (= 1.7 t/cum)
Stacking height: 8 m for initial phase & 12 m subsequently
Angle of repose (= 37o)
Space for movement of equipment between stockpiles (= 10 m)
Techno-Economic Feasibility Report
90
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Average width of the stockpile (= 50 m)
Table 6.15: Determination of the Stack yard Area for Lime Stone
S.No Item Unit 52 MTPA
A Annual Throughput Million Ton 2.80
B Holding Capacity Required = A/15 Ton 186,667
C Density of Cargo (From UNCTAD) Ton/cum 1.7
D Holding Volume Required : (B/C) cum 109804
E Stacking Height m 10
F Angle of Repose Degree 37
G Stacking Area Sq.m. 420
H Length of the stockpile = D/G m 262
I Storage Factor = B/H Ton / m 712
J Width of the Stockpile m 50
K Stockpile Area = H*J Ha. 1.32
A stockpile area of about 4 ha for Limestone storage taking the multiplicity of users and the
number of stockpiles and consequent space requirements due to separation distances in the
different phases.
Iron & Steel Products
Iron and steel products are export products sent in form of Coils, Billets and long products. This
cargo would be placed on hard stands.
The average transit time for the cargo (10 days)
The average stacking height (= 1+1)
Traffic in the current phase = 6.0 MTPA
Storage required for a 10 days dwell time = 6000000*10/330 = 181818 tons
Number of units if the average weight of 32 tons per coil is assumed = 5682
Slots required = 9470/1.5= 3780
The area required = 6320*4 = 15120 m2
About 2.0 ha of land would be reserved for the Iron and steel stacking.
Techno-Economic Feasibility Report
91
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
6.3.7.3 Others
Conveyor Corridor
A conveyor system to evacuate the cargo would run from the berth stockyard and to the plant
feeds. A right of way of 5 m is accordingly considered for the conveyor corridor and an area of 4.0
ha is reserved within the Captive Jetty(ies) area for the same.
Truck Terminals
A truck terminal for the likely tuck traffic along with the associated amenities such as restaurants,
service centre and petrol/diesel filling station would have to be located outside the Captive
Jetty(ies) area. Further, there would be tractors and trailers handling the containers/Iron and steel
products at the berths. In total, an area of 10 ha is considered for accommodating the above.
6.3.7.4 Summary
The land requirements for initial phase of development of the Captive Jetty(ies) is summarized and
presented in the table 6.16 below.
Table 6.16: Summary of Area Requirements
S. No Particulars Area (in. Ha)
52 MTPA stage
1 Waterfront & Berth Back-up Area 1.5
2 Dry Bulk Stockyard Area:
A. Coal Stockyard 19.00
B. IBRM Stockyard 12.00
C. Lime Stone Stockyard 4.00
3 General Cargo (Cement & Clinker) 5.00
4 Iron & Steel Product 2.00
6 Others:
A. Conveyor Corridor 2.00
B. Truck Terminals 5.00
C. Sewage treatment plant 0.50
D. Common user facilities 1.00
E. Misc. Captive Jetty(ies) related activities 3.04
TOTAL 55.40
Green Belt and Others (roads) @33 % 72.80 (180 Acres)
Techno-Economic Feasibility Report
92
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
6.3.8 Buildings
6.3.8.1 Functional Purpose
The buildings proposed to be provided in the Captive Jetty(ies) area and their functional utilities
are described hereunder:
Substation
This building houses the transformers and other electrical equipment. Multiple substations will be
provided as per the load requirements in the different parts of the Captive Jetty(ies) area.
Administrative Building
This building provides space for offices of key personnel engaged in managerial and departmental
activities related to Captive Jetty(ies) operations & management and their support staff. It would
be located on the electrical substation on the first and second floor.
Jetty(ies) Users Building
This would be a three storied building and provide space for the following and would be constructed
at a later date beyond the CRZ line.
Jetty(ies) users, Banks and Canteen on the ground floor
Jetty(ies) Users on the first floor and
Customs Department on the second floor
However, this building would be located on the landward side of the existing road.
Port Operation Building
This building provides space for the operating staff in all the shifts. It would have:
Captive Jetty(ies) control room will be provided at a corner of the building with a suitable
glazing all around. Terminal operations Department and Marine operations staff, pilot rest
room will be accommodated in this building.
The transit light for navigation will also be provided on the roof top of the control room.
This will be located on the 3rd floor of the substation building nearer to the water area.
Canteen
This building provides space for catering staff, messing facilities for all terminal personnel
and for utilities.
Gate House
This building provides space for guardroom, time office and retiring room (for security officer).
Workshop cum central store & Annex
This building consists of two parts, a workshop plus store room, and an annex building.
Techno-Economic Feasibility Report
93
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
The annex provides space for offices of the workshop foremen, mechanics, electricians,
technicians and the storekeepers and rooms for off duty operational personnel and maintenance
labour. The work shop and storeroom are for the regular maintenance activities.
Fire Station
This building houses firefighting equipment, fire tenders, etc.
Dispensary
This would be located near the operational areas and provide minimum facilities required for
the first aid.
Over Head Tank
An Over Head Tank (OHT) is provided to supply potable water to all the buildings or utilities
wherever required in the Captive Jetty(ies) site.
6.3.8.2 Building Areas
The building areas are dictated by the personnel requirement space for offices, storage, machinery,
utilities, etc. Based on the description provided in the previous paragraphs, the estimated building
areas have been worked out and are given in the Table 6.17 below:
Table 6.17: Captive Jetty(ies) Buildings Area Requirements in Square Meters
Building Total Area 52 MTPA stage
Administrative Building 300 150
Jetty Users/ operation/Control room 350 200
Canteen 300 150
Gate House 60 60
Workshop cum central store & Annex 1000
Fire Station 250
Substation 650 500
Dispensary 200
Over Head Tank 300 200
Total 3410 1260
6.3.9 Ships’ Operational Areas
Any Captive Jetty(ies) has to have well laid out operational areas on the land side as well as the
water side.
In this section the water areas required for ship operations and their dimensioning are discussed.
The essential operational area, with brief description of each is provided as follows.
Techno-Economic Feasibility Report
94
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
1. Approach Channel: is that portion of the channel from the landfall point or Pilot Station
leading up to the Port entrance. Where the Port entrance is in deep water an approach
channel may not be required
2. Entrance Channel: is that portion of the channel, which is the transition between the
exposed approach channel and the sheltered Captive Jetty(ies) channel, including the
sector, passing the entrance
3. Port Channel(s): could be one or more channels inside the sheltered port area leading to
one or more port terminals such as docks jetties and other type of berthing facilities,
anchorages or special areas
4. Turning Circle / Manoeuvring Area: This is a special water area usually inside the port
meant for turning ships around or carrying out manoeuvers typically for the purpose of
berthing or un-berthing
5. Berths: jetties, quays, enclosed docks or basins, dock-walls, mooring dolphins or buoys
or other types of arrangements at which ships are berthed and tied up usually for the
purposes of loading or unloading
6. Hauling out space: This is an area immediately adjoining the berth on the waterside, which
the largest ship will occupy at some time or other during berthing or un-berthing.
6.4 Design of Berths and Breakwater
6.4.1 General
For safe manoeuvring and operation of the vessels at the berth and efficient cargo handling,
protective structures are often necessary to create the desired level of tranquillity. Therefore,
depending on the marine environmental conditions, if the port is located on the coast the required
tranquillity can be achieved with provision of breakwater(s) of suitable length. Accordingly, the
main structural components of the alternatives can be summarized as;
Breakwater
Berths
Storage and foreshore facilities
The following paragraphs deal with the structural components of the harbours for enabling smooth
and efficient operations.
6.4.2 Breakwaters
6.4.2.1 Physical factors
The breakwaters are subjected to dynamic forces of waves and need to be safe against the
maximum wave action expected at the site. At the same time the design of the breakwater should
be optimized so as not to become too costly without of course sacrificing safety. In general, the
life of the breakwaters structure is taken as 100 years. In order to make an optimal design the
choice of the design wave height is very important.
Techno-Economic Feasibility Report
95
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
6.4.2.2 Wave climate
The details of wave analysis is given in are given in Chapter 4. It could be seen that the site is
affected by SW and NE monsoons, where SSE is generally predominant and have the maximum
effects. In addition, the Bay of Bengal is affected by about 1½ cyclone per year on an average.
6.4.2.3 Selection of design wave
The near shore wave model carried out with the effects of storm surge; indicate that, the maximum
wave height at a water depth of 10 m is about 7.5 m. The breakwater is located at about 7.0 m of
water. With storm surge of 1.6 m the maximum breaking wave height at MSL is 7.04 m.
Accordingly, the breakwater shall be designed for these breaking waves. For the other portion of
the water, which is located in the shallower portion, lesser wave heights shall be applied.
Depending upon the location of the breakwater it is essential to know whether the depth of water
at the structure is able to sustain the design wave height i.e., whether the wave height at the site
is controlled by water depth. A wave breaking at the structure would exert maximum force on the
structure whereas a non-breaking or broken wave would produce lesser force. Theoretically, a
wave with height H would break in a water depth of 1.3 H. It has been a common practice to design
a structure located in a water depth where d 1.3 H for breaking waves, if 'H' is equal to or less
than the design wave height, assessed for the site.
The Mean High Water Springs at Paradip is +1.3 m and Higher High Water is + 2.58 m C.D. As
already mentioned earlier, the maximum probable wave height, with a recurrence period of one
year, which may reach the Coastal band from SSE, would be 7.5 m. Thus, the minimum water depth
required for sustaining 7.5 m wave would be 1.3 x 7.5 = 9.75 m. In general, statistically all the
worst conditions occurring simultaneously, is rare.
Therefore, it is considered safe enough to assume the design wave conditions at MHWS + 2.58 m
for zero order damage
For Breakwater
i. Breaking wave at MHWS + 2.58 m
ii. No overtopping of waves at HHWL
6.4.2.4 Type of structure
The type of structure to be considered for the breakwater depends upon the construction material
available economically near the site, effect of structural damage and maintenance requirements.
Rubble mound structure is generally favoured because damage to the rubble mound is gradual and
the force due to wave action has to act for a longer period to cause any major damage. Depending
upon the quarries available and the biggest size of stone that could be quarried and the quarry
yield, a rubble mound structure could be designed economically. In case large stones are not
available in sufficient quantities, artificial concrete blocks in the armour could be used.
Techno-Economic Feasibility Report
96
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
6.4.2.5 Preliminary Design of Rubble Mound Breakwater
Many researchers, based on model experiments, have suggested formulae to obtain the weight of
armour unit for the design wave conditions. The parameters generally considered in the formula
are unit weight, wave height at the structure, specific gravity of armour unit, seaward breakwater
slope and a factor, which is indicative of interlocking property of the armour unit. The most
commonly used formula was developed by Hudson and is used here as a guide for preliminary
design. This formula is as under
wr H3
W = ---------------
KD (Sr – 1)3 Cot
Where;
W = Weight of armor unit (tonnes)
wr = Unit weight of armor unit (tonnes/m3)
H = Design wave height (m)
Sr = Specific gravity of rock
= Angle of breakwater slope
KD = Stability coefficient (which varies for different armor blocks)
Presently several other formulas have been suggested in the CEM, developed by Army Corps of
Engineers of US Army, but in essence this formula is still valid and good enough for this design.
The details of the breakwater section are decided on various considerations, such as method of
construction, whether crest level be such that no overtopping of waves would take place, crest
width requirements, necessity for lee side reclamation or otherwise, bedding requirements and
large size stones which could be available from the quarries.
In the earlier days the Tapang quarry used to be used extensively for rocks and other building
material. However, of late the quarries have been exhausted and the quarry of Chandikhol is in use.
These rocks though of lesser specific gravity are good for the construction of breakwater and
berths. The river sand would be used for the fine aggregates. It is assessed that quarries
considered for breakwater would produce stones about 5 ton.
In the rubble mound section, use of stones in the armour layer is always economical. However, the
required size (weight) may be neither easily quarriable nor possible to be transported to the
breakwater site. In such a case artificial concrete blocks need to be cast near the site and used in
the armour layer. There are many types of concrete blocks of different shapes that have been
developed by researchers. Tetrapods have been very extensively used in breakwaters all over the
world. Some new blocks of recent origin like Accropod and Core-loc are being used due to the
specific advantage that these blocks can be used in a single layer instead of in double layer as is
the case with most of the other blocks. Thus the cost of the breakwater could be reduced; however,
these types of blocks need to be placed in a specific manner to achieve the required interlocking
Techno-Economic Feasibility Report
97
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
property which otherwise would not be possible if laid. One more advantage of these new blocks
is that their `KD’ value is higher than that of tetra pods and as such the weight or the concrete
volume required for each block would also be less. Therefore ‘Accropod’ has been considered for
Paradip breakwaters.
For the preliminary design of the breakwater the following conditions were considered.
No overtopping for HHWL
Specific gravity of stones as 2.7 and for concrete 2.4
Stones more than 5 ton are not available economically from the available quarries
KD factor for stones ( is given as 2 in Shore Protection Manual (SPM) Based on our
experience KD = 3 is in order.
Construction level at + 6.5 m or higher.
Based on various considerations mentioned in the earlier paragraphs, breakwater sections for
various reaches for the south, west and north breakwaters have been worked out. The cross-
sections are given in Figure 6.9. It may be noted that armour stones are used for the entire west
and north breakwaters. For the south breakwater, stones are used in the armour up to zero contour
beyond which 6 tonne Accropod are suggested in the trunk portion. For the round heads, 11 tonne
Accropod have been proposed. It may also be noted that wherever there is reclamation on the lee
side of the breakwater no heavier stones are required for protecting the core. However, a geo-
fabric filter would have to be provided between the lee side core slope and the reclamation fill to
avoid leaching of fill material through the voids in the breakwater. The above sections are designed
considering normal wave attack on the breakwater section. It may be noted that the possibility
exists for reducing the armour size after obtaining the directions of waves at various reaches and
carrying out model studies for the stability of the breakwater.
Figure 6-11: Typical section of the breakwater at – 2.0 m Contour CD
6.4.3 Structure for Berthing Face
The type of structure adopted for providing berthing facilities can be broadly divided into the
following two types:
Techno-Economic Feasibility Report
98
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
1 Continuous Wharf Type Structure (Diaphragm wall)
2. Open Berth Structure
However, when more definitive information is available about foundation conditions at the detailed
engineering stage, consideration would be given to other possible forms of construction. These
might include, for example:
Sheet pile bulkhead
Sheet pile cells
Floating caisson
Block-work gravity wall
Also at that stage, the disposition of structural members would be optimised to suit the rail span
of equipment and other applied loads, and the need for a continuous services gallery at the face
of the quay.
The relative merits, demerits, and suitability of the structures are examined in the following
paragraphs:
6.4.3.1 Continuous Wharf Type Structure
This can further be subdivided depending on type of construction and structural types:
a. Diaphragm wall Type
b. Caisson Type
a. Diaphragm Wall Type: This type of construction makes the berth contiguous to the land.
The diaphragm is a continuous concrete wall constructed in-situ on the ground by special
trenching techniques. After construction of the berth, soil in front of the wall is removed to
the required level. The diaphragm wall is designed for earth pressure due to the backfill
earth.
As the berth is designed for the earth pressure, the bollard pull of the ship rather than the
berthing force is critical for the design. Since the berth is contiguous to the land, no
separate approach is required and even heavy vehicles can come directly on to the berth.
Diaphragm wall construction being contiguous to the land provides for efficient handling of
containers or for continuous unloading of bulk cargo. Therefore, where the Captive
Jetty(ies) basin is proposed to be dredged to form a lagoon type harbour, this is a possible
method of construction, since in addition to providing a berthing face, it retains earth fill of
the storage and back up area. The required dredging of the dock basin can be carried out
after construction of diaphragm wall.
Feasibility of such a kind of structure in the proposed layouts warrants discussion of the
inherent disadvantages which are listed below:
The diaphragm wall is costly and involves longer period of construction.
Techno-Economic Feasibility Report
99
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Diaphragm walls do not allow easy dispersal of energy and may create wave reflections.
Therefore, such structures should be invariably associated with energy dissipating
means such as spending beaches.
b. Caisson Type: Similar to the diaphragm wall, the berthing wharf can be constructed of well
foundations by sinking wells side by side. After casting the kerb and part of the steining,
the caissons are sunk to the hard strata by excavating the soil from within the body of
the caisson. The gap between caissons is closed by steel sheet piles, injection piles or
other appropriate methods. The caissons are interconnected by provision of a deck slab at
the water level. A plum concrete wall to the required height is then provided over the slab
for the full length of the wharf to provide an even vertical face for facilitating fixing of
fenders and continuous berthing face.
Before discussing the feasibility of such a structure, the inherent disadvantages of the
construction of such structures are identified and are given as follows;
Construction of caissons located side by side to form a continuous retaining structure
is a time consuming effort.
The sinking of the caissons located side by side could be more difficult due to their
possible tilt or shift during sinking.
The construction cost of caissons is generally higher than that of diaphragm walls.
Reflection of wave energy causes disturbance to the berthed vessel.
6.4.3.2 Open Berth Structure
The open berth structure mainly implies berthing structure on piles. In this type of structure, the
berth is on pile foundations. Since the pile foundations are discrete columns provided at a
designed interval, free flow of water is not hindered. Therefore, these structures are ideal for
locations in deep waters away from the high waterline and on sensitive coasts where wave
reflection may result in resonance due to movement of the vessel at its moorings. Due to their
inherent nature of offering minimum resistance to the existing flow regime and sediment movement,
the piled structures have very little or no impact on the coastal morphology. Accordingly, the piled
jetty is suitable in almost every location except where it is to serve as an earth retaining structure.
However as already discussed, vertical solid berthing faces are not preferred in the proposed
locations, due to the occurrence of wave reflections and standing waves. It is therefore a
requirement by default that all the basins should have pitched slopes because they are not only
economical but are also very good for dissipation of wave energy. The decking of the berth is
provided with reinforced cement concrete structures consisting of beams and top slab. The beams
and slabs together get integrated by design and then constructed as a continuous monolithic plate
for better and even distribution of live and superimposed loads.
Accordingly, for facilities proposed at Paradip, berths are planned on Piles.
Techno-Economic Feasibility Report
100
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
In order to maintain flexibility of operation the berths are proposed to be constructed in a
continuous manner. However, the length requirement for a berth is shown below;
1. Vessel Capacity : 150,000 DWT
2. Overall length and beam : 305 m x 42.5 m
3. Length of Berth : 325 m
4. Width of Berth
Distance between rails : 20.0 m
Forward clearance : 2.5 m
Conveyors : 5.0 m
Footpath and other facilities : 5.0 m
--------
32.5 m say 33m
As per IS:4651 (Part V)-1980, for long continuous wharf for large ocean going vessels, the
recommended length of the berthing area should not be less than the length of the design vessel
plus 10% subject to a minimum of 15 m. However, from the operation point of view, it is always
preferable to have a continuous, wharf, so that, the loading and unloading equipment could be
shared between the berths. Therefore, a continuous wharf would be most ideal. As per the
calculations above, in the first phase 10 berths are required (Refer to Table 6.7). With design
vessels in the ultimate phase being 300 m long, the length of each berth would be around 325 m.
For the present Captive Jetty(ies) all berths are considered to be about 325 m long. However, there
will be a continuous berthing face for accommodating all the vessels. The total length of the berths
are 2 cape berths of 362.5 m long and balance 2 Panamax berths of 290 m long each, and 4
handymax berths of 265 m each, totalling to about 2365 m in phase I.
As already indicated the berthing head for the proposed facilities is a reinforced cement concrete
structure founded on 1200 mm diameter bored cast-in-situ piles. The piles would be bored into
the fresh rock or for the required lengths in to the weathered rock to provide adequate axial and
lateral capacity. The superstructure would be provided on a series of pre-cast beams running in
both the directions. All piles would have a pile muff of 1900 x 1900 mm size and would support the
pre-cast pile cap beams in a direction perpendicular to the berthing face. The pile cap beams are
essentially ‘T’ shaped beams, provided to support the top secondary beams and crane beams.
The secondary beams and the crane beams would have a 200mm top slab in order to provide
integrity and rigidity. The top surface of the slab would be provided with a 75 mm screed to prevent
any wear and tear. The secondary and crane beams would be partially pre-cast in order to reduce
weight for handling. The pre-cast units are designed in such a manner that only minimum side
shuttering would be required. The front row of piles would have lower pile muffs and a cast-in-
situ fender skirt to enable fixing of fenders. The berths would have the required access from the
storage area and back up space on approaches on piles with similar types of superstructure. The
approaches are also planned to carry conveyers, vehicular traffic, pipelines for products etc.
Techno-Economic Feasibility Report
101
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Figs. 6.9 shows pile layouts of the harbour. Figures 6.10 also show the sectional elevation of the
jetty including the fenders and cross beams. The general planning consideration for different
proposals is described here in brief.
Figure 6-12: Typical plan and section of the bulk berth
Plan
Section
6.4.4 Design Basis for the Berths and estate level
The marine environmental data as discussed in Chapter - 2 and 4 indicate a highest high water
level of about 2.58 m including a storm surge of 1.6 m, a water level of 5.10 m has been adopted.
Allowing for locally generated waves due to high wind of 1.3 m and 1 m free board the jetty top
level is assumed at + 6.5 m CD for the coastal Harbour. The top level of berth is therefore kept at
+ 6.5 m CD. The existing ground level is at around + 4.0 m and the dredged bed level is -16.00 m
CD, with a 1: 2 slope for the finished slope of the dock basin up to the dredged levels, the width
of the Jetty head could be calculated as follows:
Top Level of jetty (and estate level) = + 6.5 m
Bottom level of skirt beam of berth = + 5.0 m
& the top level of skirt = + 3.5 m
Bed Level = - 19.50 m
With 1:2 slope up to bed layer
Vertical distance = 19.50 m
Techno-Economic Feasibility Report
102
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Horizontal distance = 39.00 m
So width of the berth = 39.00 m
Accordingly, the width of the berths is decided. It should be noted that as indicated above, from
the handling point of view only a width 33 m is required. Therefore, the greater of the two, would
be adopted in the present case.
6.5 Captive Jetty(ies) Layout Options
Having laid down the parameters for waterside planning in the earlier part of this Chapter, the actual
Captive Jetty(ies) layouts that have been evolved are discussed in this section. As already
indicated, the choices are limited. The proposed Captive Jetty(ies) is located along the Jatadhari
waterfront along the steel plant, which will reduce any large-scale protection for tranquillity.
The only other apprehension of the harbour resonance inside the narrow riverbanks can be taken
care of by providing reverted slope with stone pitching. The other bank of the river/estuary will
remain natural, which would further help in the energy dissipation of trapped wave and tidal energy.
The layout of the Captive Jetty(ies) in the initial phase in the Figure 6.12.
The Captive Jetty(ies) will have two berths for Cape size vessels and other berths will be of smaller
vessels.
The layout attached as JSW/Jetty/LO/001A.
Figure 6-13: Suggeted Preliminary Layout of the Porposed Captive Jetty(ies)
Techno-Economic Feasibility Report
103
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
7 Material Handling Systems & Equipment
7.1 General
A Captive Jetty(ies) can be of maximum benefit to the users, owners and the areas served by it,
only when it is properly laid out, adequately equipped and efficiently operated. The quality of the
service rendered by the Captive Jetty(ies), particularly its promptness and speed, safety and
security of the goods handled and also the total user costs for the services are the basic
requirements for the success of the Captive Jetty(ies) and its future growth. These can be achieved
by a proper layout and well-engineered systems and equipment for (i) import cargoes, including
ship unloading, landside loading and dispatch/delivery to the users, (ii) receipt, unloading and ship
loading of export goods and (iii) in-Captive Jetty(ies) storage and transfer of both.
The cargo handling systems and equipment cannot be evolved in isolation, but should be tailor-
designed to suit the Captive Jetty(ies) layout, which will be influenced by site parameters and
various limitations and considerations of harbour engineering, connecting transport linkages etc.
In turn, the Captive Jetty(ies) layout will also be decided by the cargo handling systems and
equipment. The proposed Captive Jetty(ies) is mainly for import cargo except for steel products.
Keeping this in view, the cargo handling systems and equipment have generally been developed
for the cargo flow from ships to storages and delivery/dispatch to the users via rail and road. The
only exception is the export of steel products where the cargo flow would be in the reverse direction
i.e. unloading and receipt and transfer to storage and ship loading. There will also be some export
of general cargo, but here also the system is generally bi-directional, and capable of handling
flows in both directions.
7.2 Concepts
The broad concepts on which the cargo handling systems have been evolved are:
The Captive Jetty(ies) will work round the clock.
All ships are to be turned around in a maximum of 3 days (72 hours). As a matter of
abundant caution the system capacities will enable the unloading/loading the maximum
size of ships of any particular cargo in about 48 hours’ time.
Uni-flow of cargoes without any backtracking or contra-flow at any stage.
Parallel flows of cargoes so that crossing of flows is avoided. Even if there is any crossing
of flows, there will be a grade separation so that flows do not interrupt each other.
Protection of cargoes from climatic conditions, during receipt, handling, transfer and
storage e.g. cement and coal being conveyed with totally enclosed systems (which has
also the benefit of protecting the environment), covered areas limestone and steel etc.
Provision of facilities for weighing/measuring of cargoes received and cargoes dispatched
like belt scales, flow-meters, weighbridges, etc. for all commercial and accounting
proposes at appropriate stages.
Techno-Economic Feasibility Report
104
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
With loose bulk materials like coal, etc., the in-Captive Jetty(ies) storage capacity to be
adequate for a minimum of 1-month cargo by the trade.
Adequate storage capacity for each cargo so that there is no simultaneous receipt as well
as dispatch of materials from any individual storage area/stack.
Separate access to each storage for cargo evacuation so that the outflow from each area
will be smooth and unhindered.
Easy road access to all the operational areas, storages.
Minimising the rail network in the Captive Jetty(ies) while fully meeting the rail evacuation
requirements.
The systems designed for operation with minimal man power and also with a built-in
suitability for complete automation.
Provide with latest Electronic Data Inter-change (EDI) facilities
Minimising the initial investments with provision for future investments to be made as and
when necessary.
Adequate spaces for future expansion with availability of contiguous areas for each
individual cargo, for meeting any unanticipated growth.
Minimal disruption and hazards to the on-going Captive Jetty(ies) operational activities
during construction at the time of future expansion.
Central Co-ordination Control tower to monitor Captive Jetty(ies) activities and house latest
Meteorological facilities
7.3 Coal Handling
7.3.1 In - Captive Jetty(ies) Storage for Cargo Handling
Material handling would inter-alia include properly located and planned adequate storages. The
storage areas of the Captive Jetty(ies) are generally planned to cater to the unavoidable
mismatches in the rates of cargo receipt/dispatch by sea and hinterland transport system, with
adequate operating space, and retrieval systems.
With an annual throughput of 8.40 million tonnes of coal from foreign destinations ship size of
180,000 DWT, (150,000T cargo), would be aimed at owing to the long term economy of scale. and
accordingly, the storage requirement can be as under:
450,000 t (3 times the maximum shipload)
Or
700,000 t (One-month Storage)
The storage of 450,000 tonnes will be provided in rows. Each row will have 8 stacks of 200 x 50 x
14 m each having a stack capacity of 630,000 t (assuming 0.8 t/m3 bulk density).
Techno-Economic Feasibility Report
105
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
7.3.2 Handling System
There are basically 2 types of unloaders available
Continuous type.
Grab Type
The continuous unloader is an equipment with mechanical devices for digging and conveying the
material. However, it also can have the facility to accept dust control systems, thereby providing
for a cleaner environment in the unloading and all other handling areas. The other real advantage
is that the ship unloading times can be less and the entire transfer and handling systems and
equipment being of a continuous nature, results in higher average handling rates.
On the other hand, Grab type has the advantage of simplicity in operation and has been in use for
decades and users and operators are well conversant with this system. Over the years the basic
feature of unloading has not changed at all but technological improvements have taken place in
materials, increasing the payload/tare weight ratio from 1.0 to 1.2 to 1.6 (the higher figure with
heavier bulk density materials and as such with comparatively smaller benefits for a light commodity
like coal). 4/6 rope grabs have come up with better scooping capabilities. Hydraulically operated
grabs are also being used now-a-days. All these have helped in improving the handling rates.
The grab type suffers from two distinct disadvantages, due to its inherent nature as explained
below:
The digging rates are the best at the start of operations but goes on reducing as the pile
becomes less and is much poorer in the hold near the clean-up stage. The ratio of the
hold digging rate to the cream digging rate can be about 0.5 or even go down to 0.4. Apart
from increasing the ship unloading times this also results in designing of all the subsequent
transfer and handling systems for the cream digging rates, which get over designed and
underutilized most of the time.
The operations viz. grabbing as well as dropping of coal raise considerable amount of dust
and no effective systems are available for controlling the dust emissions.
However, with the advent of dust sensors in the hopper and adaptive Grab design to operate at
lower digging rate, the Grab unloaders are increasingly becoming popular and will be adopted at
the proposed facility.
The coal unloaded from ship using Grab unloaders will be transferred to a completely enclosed
wharf belt conveyor elevated to about 8 m above ground which will enable road traffic to cross
under it at suitable places. This belt conveyor will have diverter arrangements and will discharge to
one of the two inclined conveyors, (fully enclosed) which will raise the height of conveyance to
about 13m-14m and transfer the coal to the stack feed belt-conveyor running alongside the
enclosed coal stackyard. The stack feed conveyor will be provided with a motor driven travelling
tripper arrangement which in turn will feed a stacker also moving longitudinally and parallel to the
belt.
Techno-Economic Feasibility Report
106
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
The stacker which will be travelling on an overhead gantry will have an upper transverse conveyor
and a lower reversible conveyor so that the coal can be dropped in any area precisely. The dropping
will be through a telescopic chute with gap sensing and self-adjusting features so that the height
of open dropping would be kept down to the minimum and dust emissions are minimised.
There will be 5 rows of stacking with each row having 2 stacks of coal (450 m x 50m) longitudinally
in line with each other. The stack height will be 8 m. The longitudinal sides of the stacks will be
walled up, which will increase the capacity of the stack and also give protection to the environment.
In the same gantry (on which the stacker will be travelling), a chain bucket type reclaimer will also
travel longitudinally. This reclaimer will have a transverse reclaiming conveyor, which will deliver
the coal to a longitudinal out loading conveyor running along the stack yard on the side opposite
the stack feed belt conveyor. The out loading conveyor will transfer the coal to a short length cross
conveyor, which in turn will transfer the coal to the loader belt running longitudinally beside the
coal loader gantry. Another tripper, which will move along with gantry type loader and operating on
the longitudinal loader belt, will feed the gantry type loader with a cross belt conveyor. The gantry
will cover 2 rail tracks (inside) and 2 truck lanes (outside). Another telescopic chute (positioned
crosswise) will finally drop the coal into the rail wagon or truck. System operation will be such that
the loader operator will have an overriding control on the reclaimer. The system will thus enable
loading of a full train or road trucks irrespective of the stack from which coal is reclaimed or the
position of the reclaimer or the exact location of the rail wagon or truck.
All transfer points will be totally enclosed while maintaining suction pressure inside to eliminate
dust emission. The coal stacks will have water spray arrangement to suppress dust emission.
In a subsequent expansion (beyond 4 million tonnes of coal traffic per annum) a similar stacking
arrangement will be provided on the other side of the rail wagon/ truck loading area with its own
belt conveyor, tripper, stacker, reclaimer, and conveyor. The diverter arrangement mentioned earlier
will enable feeding the second inclined conveyor for transfer of the unloaded coal to the other
stockyard though a cross running belt conveyor.
At that time a second coal loader can also be provided, operating on the same gantry and the coal
dispatch capacity of the Captive Jetty(ies) would be doubled.
The Captive Jetty(ies) operations in coal handling can be broadly divided into the following
sequential operations.
Unloading from ship and transfer to the wharf belt conveyor.
Transfer through a belt chain to stack feed conveyor
Transfer to the stacker through a tripper
Stacking of coal by the stacker
Reclaiming by the reclaimer and transfer to the out loading conveyor
Transfer to the loader belt through a cross conveyor
Transfer to the loader through a tripper
Techno-Economic Feasibility Report
107
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Transfer of the cargo to the Plant day bins of each plant without any separate storage at
the plant site.
7.3.3 Unloading of coal
The maximum size of coal ships is 180,000 DWT and it is to be unloaded in a period of 48 hours.
On an average, this would require 2500 t/h effective unloading capacity.
Allowing for idle times like shift changes etc. and effective unloading rate being only about 70% of
the rated unloading capacity, a maximum unloading capacity of 3571 t/h will be required. It is
proposed to provide two unloaders with unloading capacity of 2000 t/h each, which will give a
cushion for handling bigger size vessels later.
Two 2500 tph unloader will be provided initially and two more unloaders shall be added in the later
phase. The hold clean-up will not be fully achieved with grab unloader. A good clean up can be
achieved by a bobcat/scraper/pay loader of a suitable capacity operating in the hold.
A typical ship unloader working on the berth is shown in Figure 7.1.
Figure 7-1: Typical unloader working at the ship
7.3.4 Conveying
Considering the conveying rate required being about 2000 t/h (roughly 2500 m3/h) and the
conveying distance of nearly 1450 m in 3 portions (350 m in quay + 100 m (elevating), +700 m
(alongside the stack yard), belt conveyor will be the obvious choice. Steel cord belts would be
appropriate for this purpose with a belt width of 1600-1800 mm and a belt speed of 200-220
m/min.
Techno-Economic Feasibility Report
108
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
The belt conveyor at the quay will be of a closed type, as this will be environmentally safe and
elevated at about 6 m above the ground to enable road traffic to cross underneath it. The extra
gallery costs will be of the order of ₹20,000 – 30,000 per meter length. Good belt scrapers will be
provided for removal of the material clinging on to the belt and avoid its getting dropped en-route.
The elevating conveyor will be at a rising angle of about 4o to 5o to raise the material to a level of
about 13 to 14 m for discharging into the stack feeder belt alongside the stockyard.
There are 4 transfer points in unloading and stacking (i) from unloader to quay belt conveyor, (ii)
from quay belt conveyor to elevating conveyor (iii) from the elevating conveyor to the corresponding
stack feed conveyor and (iv) from the stack feed conveyor to stacks. Dust extraction systems with
filters have to be provided for the transfer points by provision of total enclosure of the transfer
points along with maintenance of suction pressure inside, which will adequately control the dust
egress at these points.
Two overhung electromagnetic separators (cross belt type) are necessary, one immediately after
the ship unloading point in the belt and another at the beginning of the stack feed conveyor to pick
up tramp steel/iron pieces that may be found in the coal.
The out loading conveying will begin with the out loading belt adjacent to the stack yard and running
along its length. The reclaimer will deliver the coal reclaimed from stack on to this conveyor which
in turn will transfer coal to a cross belt conveyor. This conveyor will be able to convey and transfer
the coal on to the loader belt running adjacent to the loader gantry along the whole length. Through
a tripper, the coal will be transferred from the loader belt to the coal loader.
7.3.5 Stacking
The stacker will be fed by the stack feed conveyor through a motor operated travelling tripper. The
stacker will be an overhead travelling type on a built up gantry and will receive the material on an
upper transverse conveyor, which in turn will discharge into a lower reversible conveyor, which
moves in the longitudinal direction.
A telescopic chute with automatic pile position sensor will be provided at the discharge end of the
stacker so that it can be adjusted to suit the prevailing stack height to minimize dust emissions
during dropping, to the maximum extent possible. There will be two stackers cum reclaimers of
5000 TPH, in the initial phase for coal, and one for the Limestone and IBRM respectively. The
stacking will be carried out along the berth in the CRZ zone parallel to the berth. This would allow
optimising the number of equipment and efficiency of operations.
Techno-Economic Feasibility Report
109
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Figure 7-2: Typical unloader and stacker-reclaimers in the cargo flow chain.
7.3.6 Coal Stack Yard
Each row will consist of 4 stacks of 750x 50 m arranged so as to be longitudinally in line and
separated by a distance of 20 m. This could vary depending on the type of coal to be stored in the
facility. The longitudinal sides of the stacks will be walled up as an environmental protection and
also to increase the stack capacity.
With a stacking height of about 10 m in the phase I will be followed, which would go up to 14 m,
in phase II. While one stack is being stacked the other stack would be under reclamation for
dispatch of coal by rail/road. Initially 2 rows will be provided and later, the 2 more rows of coal
stacks can be added. When the throughput exceeds the present levels, a similar arrangement will
be provided on the other side of the coal loading yard i.e., 4 more rows with 2 stacks in each row
with a stacker and reclaimer for each row.
The stack will be provided with multi nozzle water spray system on the sides with water pumps of
adequate capacity for sprinkling water for dust control. Suitable drainage arrangements with traps
and de-silting facilities will be provided and the water will be recycled.
7.3.7 Stockpile Dust Control
Control of stockpile-dust emissions would be achieved by water sprinkling.
Sprays are to be spaced at about every 40 m with a spray rate of about 1.5 m3/hr.
The water sprays replace water lost from the piles through evaporation. As water application is
usually only needed under windy or drying conditions it is proposed to be automatically controlled
by anemometer with manual override for special combination of weather conditions or for dust
suppression such as at pile ends.
Water runoff would have to be arranged and drainage would have to be effective and care taken
of stockpiles during periods of monsoon weather to monitor any potential stockpile slump. The
drain water can be collected in a pond, filtered and recycled.
Techno-Economic Feasibility Report
110
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
7.3.8 Continuous belt weighing
Load cell operated belt scales of 3000 t/h capacity will be provided. There will be 2 belt scales
one after the ship unloading point, and another on the stack feed belt. The system will include
instantaneous and cumulative coal handling volumes at any moment, with digital read outs. The
accuracy of belt scales should be + 0.5%.
7.3.9 Sampling
One Belt (cutter) sampler will be provided at a suitable point to check the quality of coal being
received. The sampling system can be installed in a separate tower, which can be coupled to the
coal transport system by 2 conveyors one conveying the sample to the processing equipment and
the other for returning the extracted material back into the system. Sampling point will also be
totally enclosed to minimize dust escape.
In addition, sample preparation (crushing/grinding equipment) and sample splitting facilities are
needed. Sample analysing equipment is also to be provided.
Spoon sampling will be done for checking the quality of coal being loaded on wagons/road trucks.
7.3.10 Reclaiming
There will be bucket chain reclaimer of matching capacity for each row. Each reclaimer will also
move on the same gantry over the stack but at a lower level than that of the stacker.
The reclaimer and the subsequent belts will be wholly controlled by the rail wagon/truck loader.
7.3.11 Supplying to the Daily Bins of the Plants
The coal from the stack yard shall be supplied to the plant daily bins as required. As the daily
requirements are limited, the reclaiming and the conveyance conveyors are of limited size based
on the plant requirement. There will be an inbuilt control preprogramed in such a manner so that
the reclaiming and supply happens at a particular time of the day.
7.3.12 Control System for Coal Handling
The basic operating features of the coal handling system will be as under:
Semi-automatic operation of unloader i.e. the operation will be started and stopped by the
operator but the rest will be automatic. The operating parameters for the shift will also be
set by the operator at the time of starting. The automatic operation will be arranged through
PLC based control.
Positioning of stacker is manually controlled and initial setting is also done by the operator
along with the operating parameters for the shift. After this initiation, stacker operation will
be automatic.
Techno-Economic Feasibility Report
111
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Positioning of reclaimer will be manually controlled as also the initial setting along with the
operating parameters for the shift. Thereafter it will be controlled by the operator of the
loader which loads coal into railway wagons and road trucks.
Loader will be an overhead type which will be controlled by the operator, using various field
devices and PLC and/or relay based devices.
Conveyor system will be by automatic sequential operation of the conveyor chains with
plant auxiliary equipment. This will be by remote auto operation. A remote manual operation
will be provided as a standby arrangement. In addition, local manual operation without any
interlocks is also provided for test inspection of the system elements. Gates of chutes will
be changed over to meet the selected coal flow line, before sequential start is commenced.
The PLC system will also provide for expert diagnostic systems for trouble shooting as well
as system sensors for equipment protection.
Control panels needed for centralised operation of conveyors will also be installed in the control
house. Necessary control devices, instrumentation and signal lights will be integrated in the control
panels to facilitate remote control requirements and monitoring of the coal handling system. All the
annunciation requirements will also be displayed on the graphic panel in the control house.
The central computer and associated control console will be located on a control tower overlooking
the unloading berths and wharfs, stackyards and loading area. Normal overall plant control and
monitoring will be exercised from the central control room which will be equipped with the console
with colour video displays. Operating conditions of unloaders, conveyors and other auxiliary
equipment will be indicated on a graphic panel in the control house. Colour video displays will
display flow diagrams both as an overview and at the detailed level. Data required from belt scales,
and other sensing devices are integrated into the controller system to present a continuous upward
flow of terminal operating information. All movement of coal in the plant will be initiated by
operators in the ship unloader and coal unloader for dispatch, after prior permission and route
setting by the central control. The individual stacks to which the coal is to be stacked after ship
unloading and from which coal is to be taken out for dispatch by rail/road will be determined by
the central control room operator. The user access system will be at 3 levels. A central terminal
operation is used for continuous monitoring and control of terminal activities and will be located at
the control centre. The second level will comprise equipment operators, wharf foreman, yard
foreman etc. to continuously update and bring the status to the current level and also for
information access. The third level will comprise management, maintenance planners, stores and
other users. Standard video display terminals will be used for data entry and retrieval for all system
users. The control and monitoring function will be supported by a terminal management system.
This will be a computerised data processing system to minimise plant operator’s role. This will
furnish:
i. Inventory control status with recording of receiving and discharging material quantities,
stackwise and coal source/quality wise, stack location, volume of material in stack and
nomination of stacks for receipt of incoming material and dispatch of outgoing material.
Techno-Economic Feasibility Report
112
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
ii. Commercial data with details of dates, carriers, quantities and quality and stacking dates
of coal received on the receipt side and details of date rail wagons (trains)/trucks, stacks
from which coal is dispatched and quality of coal dispatched, on the dispatch side.
iii. Equipment data includes operating hours, breakdowns and their restoration with times and
dates, maintenance status and condition monitoring etc.
iv. All electrical faults and shut downs, device-wise and the date and time of occurrence as
well as their clearance.
v. Report generation plant operation reports, daily, monthly, annually etc. as required will be
generated
7.4 Lime Stone
7.4.1 Storage
Open storage of Limestone is proposed. The storage shall be planned on the similar reasoning as
given under coal storage and a total storage of 400,000 tonnes of lime stone (One-month storage)
will be provided with 4 stacks of 450 x 50 x 10 m each having a stack capacity of 136,000 t
(assuming 0.96 t/m3 bulk density).
The area requirement for the above storage would be roughly 27 ha including the operational areas
around the stacks.
7.4.2 Handling System
The workings of various unloaders have been explained in the previous section. The lime stone
shall be handled as a ‘dry bulk cargo’. As explained above there will be only Grab unloaders
installed at the berths for handling of the lime stone. One fixed unloader of the required capacity
as calculated below shall handle the cargo.
7.4.3 Unloading of Limestone
The maximum size of limestone ships is 80,000 DWT (70,000 ton cargo) and it is to be unloaded
in a period of 48 hours. On an average, this would require 830 t/h effective unloading capacity.
Allowing for idle times like shift changes etc. and effective unloading rate being only about 75% of
the rated unloading capacity, a maximum unloading capacity of 1107 t/h will be required. It is
proposed to provide an unloading capacity of 1200 t/h, which will give a cushion for handling
bigger size vessels later. So in the initial phase, one 1200 TPH unloader will be provided with no
stand by. Each berth will be adequately equipped to handle the products. One Mobile Harbour
Crane (MHC) shall be provided, for any breakdowns at the Lime stone berth.
7.4.4 Conveying
Considering the conveying rate required being about 5000 t/h (roughly 1300 m3/h) and the
conveying to the stockyard.
Techno-Economic Feasibility Report
113
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
7.4.5 Reclaiming
There will be bucket chain reclaimer of 5000 t/h capacity for each row. Each reclaimer will also
move on the same gantry over the stack but at a lower level than that of the stacker.
The reclaimer and the subsequent belts will be wholly controlled for delivery to the day bins of the
plants directly.
7.5 Finished Steel Product
7.5.1 Storage
In the stage 1 of the operation, billets, slabs and wires would be imported for the Orissa plant.
They will be stored in the open; hence levels yards shall be made for this purpose. The storage
area could be used later for storing the steel products which would be cargo of similar nature.
7.5.2 Handling System
The unloading and loading for the loading for the imported billets, slabs and wires as well as the
steel products shall be carried out using Mobile harbour cranes up to the stage two operations.
Keeping pace with the cargo, the MHCs shall be replaced with fixed unloaders/loaders. It should
be clearly understood that, the unloading/loading of this products could use the latest vacuum
technology. A typical harbour crane is shown in Figure 7.3.
Figure 7-3: Typical mobile harbour crane to be used for steel products
7.5.3 Conveying
The Conveying of these materials shall be carried out using the FLT or tractor trailer. The unloaders
will directly unload on to the trailers.
Techno-Economic Feasibility Report
114
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
7.6 LNG
7.6.1 General
LNG is a natural gas is natural gas, primarily composed of methane, which is converted to liquid
form for ease of storage and transport. LNG takes up about 1/600th the volume of natural gas. The
conversion of natural gas to its liquefied form allows for the transport of greater quantities.
Following figure 7.4 depicts the complete LNG Supply Chain. This cargo is presently considered
as an alternative fuel. Only the cargo handling description would be included and no cargo is
included till later stage when the assertion of the quantities has been made.
Figure 7-4: LNG Supply Chain
Liquefaction is the process of cooling natural gas to -162°C (-259°F) until it converts into liquid.
LNG must be converted back into a gas for commercial use and this is done at regasification
plants. This process is known as the LNG Process Chain.
The equipment, flexible hoses, high pressure unloading arms and send out facilities and equipment
such as LNG unloading facilities, LNG storage tanks, boil-off gas handling facilities, LNG HP/LP
pumps, LNG vaporizers, relief devices like flare stack or safety valves, send-out facilities, and also
number of utility facilities, have all been assessed for positioning within the Terminal with due
consideration of the following aspects:
Safety in terms of protection of personnel and property implemented by combination of both
active and passive protection;
Environmental issues (protected natural areas, site conditions, pollution criteria, limitations on
noise levels, seawater quality, etc.)
Techno-Economic Feasibility Report
115
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Optimization regarding the interconnecting piping lengths between units;
Optimization of process flow;
Optimization of hydraulic flow (namely for rain water drainage);
Provision for handling water for ORVs/Modified SCVs
Provision for future expansion, including additional storage tank of 190,000m3, AH-IFV,
associated facilities etc.
Topography and main road access;
Operation flexibility;
Maintenance requirements (access to areas, overhaul space);
General accessibility;
Future development
Compliance with the safety concept;
Construction constraints (especially regarding the construction schedule);
Provision for minimum clearance between hazardous areas;
Provision to minimise hazards in buildings by building pressurization where necessary and
distance to process facilities;
Direct accessibility to valves and equipment;
Spillage collection, including sloped paving in hazardous area.
Consideration to allow inspection and maintenance activities to be performed whilst operations
are continuing undisturbed;
Consideration to reduce the risk that a fire in one area of the plant is spread to another area
(domino effects);
Consideration to reduce the risk that the flammable gas cloud in case of leak and/or gas release
could reach an uncontrolled ignition source;
Consideration to reduce (in case of accidental scenarios) the loadings on buildings and the
risk of a gas cloud reaching buildings;
Consideration to facilitate the emergency action requirements.
7.6.2 Safety Distances
According to the regulations and standards mentioned above, the safe distances between the
equipment in THE TERMINAL shall be complied with the requirements shown below:
Techno-Economic Feasibility Report
116
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
7.6.2.1 LNG Tank Spacing
LNG tanks with capacity more than 265 m3 should be located at minimum distance of 0.7 times the
container diameter from the property line but not less than 30 meters. Minimum distance between
adjacent LNG tanks should be 1/4 of sum of diameters of each tank. This standard does not
consider inter distances between LNG Storage tank below 265m3 capacity. However, any LNG
storage / process equipment of capacity more than 0.5M3 shall not be located in buildings.
7.6.2.2 Vaporiser Spacing;
Vaporizers and their primary heat sources unless the intermediate heat transfer fluid is non-
flammable shall be located at least 15 m from any other source of ignition. In multiple vaporiser
installations, an adjacent vaporiser or primary heat source is not considered a source of ignition.
Integral heated vaporizers shall be located at least 30 m from a property line that may be built upon
and at least 15 m from any impounded LNG, flammable liquid, flammable refrigerant or flammable
gas storage containers or tanks.
Remote heated, ambient and process vaporisers shall be located at least 30 m from a property
line that can be built upon. Remote heated and ambient vapourisers may be located within
impounding area. The inter distances in multiple heated vaporisers a clearance of at least 2 m shall
be maintained.
7.6.2.3 Process Equipment Spacing
For Process equipment spacing Table 2 of OISD-STD-118 as applicable shall be followed. Fired
equipment and other sources of ignition shall be located at least 15 m from any impounding area
or container drainage system.
7.6.2.4 Control Room and Substation
The minimum distance of 60 m shall be maintained between LNG Storage Tank and Substation.
7.6.2.5 Unloading Facility Spacing
A pier or dock used for pipeline transfer of LNG shall be located so that any marine vessel being
loaded or unloaded is at least 30 m from any bridge crossing a navigable waterway. LNG and
flammable refrigerant loading and unloading connections shall be at least 15 m from uncontrolled
sources of ignition, process areas, storage containers, control room and important plant structures.
This does not apply to structures or equipment directly associated with the transfer operation.
7.6.2.6 Gas Dispersion Exclusion Zones
The vaporisation of LNG produces a cold gas cloud initially denser than air, which can progressively
become lighter under the effect of dilution and re-heating by the environment. Gas dispersion
exclusion zones (the required exclusion zones are defined in the safety philosophy) are to be taken
as criteria in the layout development for the following items:
Design of the central control room;
Location and elevation of the flare;
Techno-Economic Feasibility Report
117
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Distance from the tank pressure safety valves (released to the atmosphere) to the property
line and to the flare;
Distance of the jetty to adjacent port infrastructure and implementation of a safety exclusion
zone around the jetty when LNG is being transferred;
The basic criteria used in the determination of the exclusion distances is the envelope of the gas
cloud at which the LNG vaporiser concentration is below the lower flammable limit (LFL) as
recommended by the applicable codes and standards.
The hazardous range of gas dispersion consequent to a scenario of LNG or HP gas line rupture is
delimited by the Lower Flammability Level (LFL). These limits will define restriction on ignition
sources and permanent third party human presence.
7.6.2.7 Heat Radiation
The extent of allowable thermal radiation flux is also a key consideration in establishing the plot
layout. The main equipment for the heat radiation source is the flare stack. Currently the flare
system is sized and located to meet the following radiation intensity criteria. A design wind velocity
of 10 m/s is used for flare radiation calculation.
Table 7.1: Heat radiation from Flare Stack
Emergency Flaring Radiation Level*
kW/m2 Btu/h./sq ft
Maximum at base of flare stack 9.0 2,850
Maximum at edge of sterile area 5.0 1,580
*: By Installation and equipment for liquefied natural gas – design onshore installation. (EN1473, 2007 edition). Solar radiation
is excluded.
In the detail engineering stage, the allowable maximum thermal radiation fluxes for equipment and
buildings both within the fence line and outside the plot boundary shall be computed.
7.6.3 Process Flow Optimization
In the Terminal, LNG is received from a LNG carrier, introduced and stored in the LNG tanks, then
discharged by LP pumps to HP pumps via or bypassing the boil-off gas re-condenser. Finally, the
LNG pressurized by HP pump is converted into gas in the vaporizers and sent out to the pipeline.
There are many other process lines in the terminal for supporting the main stream described above,
along with utility facilities vital for supporting the terminal operation.
It is essential to optimise the positioning of the equipment and systems when establishing the
terminal layout, which will be based on the methodology below:
Equipment distribution along with the process flow
The Terminal is divided into the areas for installation of the equipment based on their task
such as unloading, storage; pumping, vaporizing, etc. Each group of equipment was placed
Techno-Economic Feasibility Report
118
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
along the flow scheme of the process. The LNG storage tanks were placed in the nearest
area next to the jetty trestle, and BOG recovery area was placed next to the LNG storage
tanks, etc.
Minimization of total length of pipes
Based on the distribution of equipment, the piping route was reviewed to minimize its total
length.
Minimization of distance between the facilities
With compliance to the safety exclusion zones, and with reasonable accessibility, the
equipment is placed to have the distances between the relevant equipment as short as
possible.
7.6.4 Accessibility
The Terminal consists of a large variety of components all of which require routine access for
general inspection. The access requirements vary between infrequent use, regular use and
emergency use, therefore the arrangement of walkways and other access routes is carefully
planned to make access effective and efficient.
Particularly, in case of emergency, the accessibility to each area is extremely important to ensure
safe and immediate control. Some of the aspects to be taken into consideration are:
Rapid and unobstructed access to Firefighting facilities such as extinguisher, fire hydrant,
water monitors shall be arranged properly in a strategic location.
Clear and permanent access to site instrument or electrical panels.
Clear and unobstructed permanent access to control and block valves to be operated under
emergency conditions.
Clear escape routes and safe muster points
Piping Layout:
For the piping layout, the following considerations will be taken into account for the design:
Any pocket section where the LNG could be trapped should be avoided in LNG line in order
to prevent the disturbance to smooth flow.
Piping should be grouped in racks and run on sleepers at ground level where practicable.
Expansion loops will be required in LNG lines
LNG lines should be run with a minimum slope or if not practically horizontally to minimize
any potential low points
LNG lines should be always allocated at the bottom of a pipe rack so that impact to the
other piping in case of leakage is reduced.
The height of valve handles should take into account the operability requirements.
Techno-Economic Feasibility Report
119
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
The discharge of safety valve should be located taking into account the heat radiation and
dispersion when activated.
The minimum distance from bottom of the pipe rack beam to top of the road is 5 m.
7.6.5 Marine Facilities
The Jetty head and approach trestle, and LNG carrier berthing components are part of the overall
work scope necessary for the development of the LNG Import Terminal, however, their design and
construction is the responsibility of Jetty(ies).
The jetty shall be designed to accommodate LNG carriers in the size range of 90,000 m3 to 270,000
m3. To accomplish this, the LNG berth will include breasting and mooring dolphins, fender systems,
mooring hooks and mooring line tension monitoring system.
The second objective of the LNG berth is to provide a platform to support the mechanical
equipment required for unloading LNG carriers. The LNG trestle shall provide structural support
from the shore to the LNG unloading platform for the LNG unloading piping, auxiliary mechanical
and utilities, control and electrical systems, and access roadway.
7.6.5.1 Main Marine Facilities
The Jetty and Marine Facilities is placed to north of THE TERMINAL. The jetty is designed to operate
with LNG carriers in the capacity range of 90,000 m3 to 267,000 m3.
The jetty is designed to accommodate:
Four (4) Unloading Arms and One (1) Return Gas Arm
Piping manifold
Jetty K.O. Drum
Jetty superstructure
Nitrogen Buffer Vessel
Shore gangway
Firefighting systems
Jetty Control Room
Other associated facilities
7.6.6 Storage Area
Considering the above a operational area for handling 8 MTPA LNG is about 90 acres which is
equivalent to about 40 ha.
Techno-Economic Feasibility Report
120
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
7.7 Equipment Requirements for the Jatadhari Captive Jetty(ies)
The consolidated requirements of equipment and machineries as described above shall be as
detailed in Table 7.2.
Table 7-2: Equipment requirements
Cargo Equipment 52 MTPA stage
Coal SGU – 2500 TPH 2 (1 + 1)
Lime Stone SGU – 2500 TPH 2
IBRM SGU – 3250 TPH 2
Steel Products MHC – 1200 TPH/ 1
Steel Products FLT + Tractor trailer 10
Coal Stacker - Reclaimers 2 (1+1)
Lime stone Stackers - Reclaimers 1
Rail and road loading Mobile Crane 6
Techno-Economic Feasibility Report
121
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
8 Infrastructure Facilities
8.1 Background Discussions
8.1.1 General
The berthing, cargo handling and transfer facilities created would not be adequate to serve the
overall purpose unless backed by well-planned infrastructure facilities for receipt and dispatch of
projected cargo taking into account the future expansion of the Captive Jetty(ies). The
infrastructure facilities include roads, rail lines and pipelines, and within the Captive Jetty(ies),
water and power supply and distribution, sewage treatment and drainage, bunkering, port craft,
navigation, firefighting systems, safety and control systems, EDI/computerized systems and
communications, office buildings and residential accommodation. The scope of this report does
not cover the off Captive Jetty(ies) infrastructure of rail and road linkages to the main line of existing
rail network and to national/state highways respectively. However, as these infrastructure facilities
are very critical for functioning of the Captive Jetty(ies), the broad requirements of these off-
Captive Jetty(ies) infrastructure facilities are also dealt with in this chapter along with the detailed
requirements of in-Captive Jetty(ies) infrastructure facilities.
8.1.2 Navigational Aids
The terms Aids to Navigation, Nav-aids and Navigational aids used interchangeably, are all meant
to convey marks, including floating marks, such as buoys and beacons, transit and clearing marks
as well as signalling systems, radio aids and communications, electronic systems, radar etc. which
are installed on land or in water for guidance to all ships for safe and regulated navigation in the
channels, anchorages, berths, docks etc. It is envisaged that navigation will be carried out
throughout the year, by day and night except during times of high wind speeds and low visibility,
and inadequate draft etc.
8.1.2.1 Buoyage
The most commonly used navigational aid in any Captive Jetty(ies) is a system of floating markers
known as buoyage system. There are several buoyage systems in vogue at various ports around
the world. However, International organizations have been able to, by and large, standardize these
systems. For this Captive Jetty(ies) and its approaches, the Uniform International Lateral Buoyage
System is envisaged. Starting from seaward, a “Landfall Buoy” may be laid in deep i.e. about 20
m depth of water. This buoy should be large, lighted and provided with radar reflectors or more
advanced fittings to make it visible and/or discernible from a distance of not less than 3 to 5
nautical miles in clear visibility. Ships intending to call at the Captive Jetty(ies) may head for this
buoy. Embarkation of Pilots too may be done off this Landfall Buoy. Buoy requirement at the Captive
Jetty(ies) is worked out as presented in Table 8.1.
Techno-Economic Feasibility Report
122
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Table 8-1: Buoy requirements at the proposed Jetty(ies)
BUOYS (Type) Numbers
Port hand Buoys 7
Starboard Hand Buoys 7
Fairway Buoys 1
Landfall Buoys 1
8.1.2.2 Shore Based Marks
Due to the mobile nature of buoys implicit reliance cannot be placed on them for navigation. In
this respect shore based marks have more reliability and will be used wherever possible either as
supplements to buoyage or by themselves. The following shore marks can be advantageously
deployed to assist navigators.
A pair of Transit Marks may be constructed at suitable points on the land to define the Centreline
of the Approach Channel. The top marks of the back and front marks should both be prominent
but different in shape so as to be distinguishable from one another. The rear of the two marks (as
seen from seaward), i.e. Back Mark should be sufficiently taller than the Front Mark to ensure that
the Back Mark is seen above the top of the Front Mark at any point within the usable part of the
transit line i.e. the Centre line of the channel. The distance between the Front and Back marks
should not be less than one-eighth the distance between the front marks and the most distant
point on the useful part of the transit line, i.e. approach channel. If this distance is reduced, the
sensitivity of the transit will be reduced thereby compromising its usefulness. Both the transit
marks should be lit by lights of suitable colour and characteristics so that the transit is visible and
usable for day and night navigation. In the case of a bent channel one pair of transit marks will
have to be installed for each leg of the navigation channel.
8.1.2.3 Ship-to-Shore Communications
Efficient and reliable ship-to-shore communication is a basic need for smooth port operations. In
the past this was achieved through visual means such as Semaphore and Flags hoisted on ship
and shore signal masts. These systems still cater to dire emergencies and during failures of all
modern systems, which depend on electric power. Accordingly, a Signal Mast complete with yard
and halyards may be erected at a prominent location visible from ships in sight of the Captive
Jetty(ies). Full sets of flags and other types of hoists and visual storm and other signal shapes
should be provided in suitable storages.
8.1.3 Harbour Crafts/ Togs
In the initial Phases all tug services shall be outsourced.
8.1.3.1 Other Minor Port Crafts
A variety of other Port crafts would have to be commissioned with the harbour. These would
include mooring boats, fire tenders, pilot launches and a mooring buoy. Harbour tugs are
sometimes equipped for firefighting as well. However, the important consideration would be
Techno-Economic Feasibility Report
123
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
accessing of all areas by land vis-à-vis by water. With the present location of this Jetty(ies),
access by land will be equally convenient and as such firefighter tugs are not being considered.
8.1.4 Potable water supply
An underground water tank of 2100 cubic metres capacity will be provided to meet an approximate
daily demand of 2.1 million litres. A closed loop grid system with necessary cross connections and
valve stations will be provided inside the Captive Jetty(ies) premises. Water supply will be provided
to all berths by running a pipeline with 600 lpm discharge capacity. Two outlet points at each berth
will be provided for supply of potable water to ships. A pump house will be provided with necessary
pumps and controls to maintain water supply.
In addition, bunkering of potable water to ships will also be provided as per their needs; water
pipelines will be laid to the individual jetties for this purpose.
Besides, fresh water will be required for supply of ballast water requirements.
The ballast water supply requirements have therefore to be based on the likely annual average.
Additional Ballasting water will be required for import cargo only. Assuming that the net average
extra ballasting will be 1/3rd of this the unloaded cargo weight for which compensatory ballast
water has to supplied, the total water requirement will be 0.1 million tonnes. This will correspond
to a water requirement of 0.1 x 106 cubic meter /annum or 275 cubic meter /day. While this need
not be potable this has to be fresh water (and not Sea water) as the ship’s water tanks should not
get corroded in the long run.
Water sprinkling of coal stacks as a dust suppression measure at this Captive Jetty(ies). The stacks
will be covered on top and also on the sides, which automatically reduces the dust ingress into the
ambient and water sprinkling will be correspondingly reduced. Further water sprinkling will not be
required all round the year and sprinkling will be needed only under certain climatic conditions (viz.
windy and drying) with automatic activation through anemometer sensing.
Assuming that there will be 120 nozzles for all stockpiles delivering water at a rate of 1.5 cubic
meter /hr, the total consumption will be 180 cubic meter /hr. Assuming that the sprays will be
operative for 40% of the time the annual water consumption will be 365 x 24 x 0.4 x 180 cubic
meter or the coverage water consumption/day would be 24 x 0.4 x 180 = 1728 or say 1800 cubic
meter. This water also need not be potable but has to be chloride free.
The additional freshwater requirements due to bunkering and coal stack spray will be 275 + 1800
= 2075 cubic meter /day. In addition, there will be a requirement of about 24 cubic meter /day of
portable water for human consumption and use. The total water requirements including potable
water requirements would be 2100 cubic meter /day or 2.1 mld. In summary, the total water
requirements would be as follows.
Water Requirement for Captive Jetty;
S. No Particulars Water Requirement (cubic meter /day)
01 Water sprinkling for dust Suppression 1800
Techno-Economic Feasibility Report
124
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
02 Ballasting 275
03 Drinking & Sanitary 24
Total 2099 (or 2.1 MLD)
8.1.4.1 Sourcing Water
There two water sources near Paradip. One on the right bank of the River Mahanadi, namely
Taladanda Canal, which supplies water to the Paradip Port, and the second one on the Left bank
called Kendrapada Canal, which acts as an irrigation and water supply source for the local
inhabitants. Since the Taladanda Canal is already supplying water to the Paradip city, this source
cannot be completely ruled out. In addition, water from the Kendrapada canal has been considered
as the only water source which can possibly supply water to the proposed Captive Jetty(ies).
As an alternative, the water may be sourced from the Jobra Barrage on river Mahanadi, about
87 km away. The ISP is sourcing the water from this barrage, hence same source may be tapped
for Captive Jetty facilities as well.
8.1.5 Fire Fighting System
8.1.5.1 General firefighting System
Separate firefighting facilities will be provided for all the Captive Jetty(ies) areas and activities,
other than those of LNG viz. for coal, cement, container, oil cakes etc. The system will comprise
a separate water intake to draw water from sea, and a separate pump house with pumps and a
closed loop with hydrants for the needed locations. The system will consist of a closed loop grid
and fire hydrants with single/multiple heads located in such a manner that hose lines can effectively
reach any part of the area. The system will be designed to maintain a pressure of 5 kg/cm2 at the
hydrant outlet for all areas
Sea water will be used for firefighting purpose. Electrical pumps of adequate capacity will be
provided with diesel standbys. A centralized fire station will also be provided for attending to all
calls. This station will house three mobile fire tenders. Further special firefighting equipment such
as foam and carbon dioxide extinguishers will also be provided for chemical and electrical fires.
Fire detection and warning system will be provided, in all vulnerable area of the Captive Jetty(ies).
8.1.6 Drainage / Sewage System
8.1.6.1 Storm Water Drainage
Storm water run-off from the container area is collected using a network of catch basins and inter
connecting pipes. One catch basin is envisaged to cater to around 4000 m2 of area. The runoff
will be led to the waterway behind berths using multiple discharge points. For the bulk handling
facilities area, a system of open drains will be provided to discharge the collected runoff into the
waterway.
Techno-Economic Feasibility Report
125
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
8.1.7 Sewage System
Sewerage system will be designed to integrate with the overall sewage disposal system being
planned for the project. A system of interconnecting sewer lines will be laid both in the Captive
Jetty(ies) so as to be connected to the main sewer lines at suitable locations. The sanitary sewage
discharge from berthed ships will be pumped into the sewer system in the Captive Jetty(ies) area
which would be discharged into the sea after treatment.
8.1.8 Bunkering System
Bunker fuelling facilities will be provided at both the container and bulk cargo berths. Salient
features of the facilities planned are described in the following sections.
8.1.9 Electrical Systems
8.1.9.1 Power supply source and distribution
Power is envisaged to be purchased from OSEB at 66 KV. The supply would be obtained through
overhead lines in duplicate feeders up to the switch yard located within the Captive Jetty(ies)
premises. Voltage would be stepped down from 66 KV to 11 KV using 2 transformers of 5 MVA
capacities in the first phase..
The 11 KV supply system would be the primary distribution voltage of the Captive Jetty(ies). The
11 KV supply from the switch yard would in turn feed five or more sub stations suitably located.
Entire 11 KV supply system would be duplicated at each sub-station providing 100% standby.
The other possibility is to use a ring-main system which is generally not adopted in Captive
Jetty(ies) as there may be only marginal saving in cost. Also the Jetty(ies) tend to be in the form
of narrow strips of berths, one after the other, especially, when the expansions take place in
different phases and in the event of a fault in a sub-station close to the main 66 KV receiving
station, the power is fed through the other substation located at the other end of the Captive
Jetty(ies). Therefore, in the event of one more failure, a large area is likely to be without power.
The proposed double feeder system, however, avoids such difficulties. The cost of the entire
duplication network described above may appear to be high, but it would be only a fractional
addition to the initial cost and will give large benefits compared to the losses in case of power
failure and consequent losses due to idling.
Voltage shall be stepped down to 3.3 KV and 415 Volts at these substations and supplied to utilities.
However, option of operating some of the motors at 6.6 KV and thereby changing the distribution
voltage from 3.3 KV to 6.6 KV with 11 KV/6.6 KV sub-stations would be kept open at this stage.
All distribution within the Captive Jetty(ies) premises would be through underground cables laid in
cable ducts. The unloader, stacker, reclaimer etc. shall be powered by 3.3 KV trailing cable from
3.3 KV junction boxes located at mid-berth locations.
Power factor improvement equipment will be provided not only at the sub-stations but also in major
equipment using large quantities of power.
Techno-Economic Feasibility Report
126
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
All the conveyer drives up to 120 KW are proposed to be supplied at 415 Volts and higher powered
drives will be at 3.3 KV. The bus-bar in the low voltage side would be sectionalised in such a way
as to ensure maximum reliability. Two 100% capacity transformers for distribution at 415 volts from
3.3 KV would ensure reliability.
During construction period, Electrical Power may be obtained at 11 KV with one 500 KVA, 11
KV/440V, 3 phase transformer to start with, followed by installation of similar transformers with
growth in power requirement.
In any continuously working system, uninterrupted power supply is essential. For this purpose,
duplicate feeders from the 66 KV GEB substation to the receiving substation within the Captive
Jetty(ies) using double circuit is to be provided. In the receiving station two power transformers
are envisaged each, capable of taking full load of initial operations. The transformers however can
also run in parallel or in isolation, and can be fed from either of the transmission circuits. The
voltage for distribution within the Captive Jetty(ies) is chosen as 11 KV, so that right from
construction stage, wherever possible, the final designated cable routing in cable ducts can be
carried out, to avoid later duplication of work and wastage.
Power supply at 11 KV to various 11 KV/3.3 KV Captive Jetty(ies) substations is made with double
cables, laid in the same cable ducts from one substation to the next.
8.1.9.2 Design of Electrical System
The equipment selected shall be suitable for the following:
1. Voltage variation + 10%
2. Frequency variation + 5%
3. Combined voltage & frequency variation + 10%
All electrical equipment and cables selected are to be suitable for 50o Celsius ambient temperature
and maximum relative humidity of 90%.
Based on preliminary designs, the magnitude of electrical load is presented in Table 8.3.
Table 8-2: Estimated electricity load for the proposed Captive Jetty(ies)
Start Total Demand
After 10 years Total Demand
1 Lime stone Handling
Travelling type unloader (at the wharf) 360 KW 720 KW
Conveyors 320 KW 640 KW
2. Coal Handling
Unloader (Wharf) 1200 KW 2400 KW
Conveyor (Belt) 600 KW 1200 KW
Stacker 150 KW 300 KW
Reclaimer and Loader 250 KW 500 KW
Techno-Economic Feasibility Report
127
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
3. Steel Products Handling 650 KW 1000 KW
4. Fire Fighting and Water Supply 500 KW 500 KW
5. Lighting, Air-conditioner, Lifts etc. 1000 KW 2500 KW
6. Miscellaneous Loads 2000 KW 1000 KW
Total 6730 KW 12960 KW
The Peak Demand with a diversity factor of 0.7 4920 KW 9500 KW
With a PF if 0.95 5200 KVA 10000 KVA
8.1.9.3 Sub-Station
A 66/11 KV outdoor Main Receiving Station having two feeders parallel incoming is envisaged with
necessary protection, metering equipment and paralleling devices. The Captive Jetty(ies) sub
stations viz. 11/3.3 KV and 11 KV/415 are planned indoors. Adequate margin and spare feeders
are to be inbuilt to meet the future growth. Separate DC System for interlock and protection is
envisaged for sub-station protection. DC Systems would have battery and independent charger
systems.
8.1.9.4 Primary Switch Gear
Breakers would be provided on the 66 KV supply side and isolators on the Captive Jetty(ies) side.
As per the requirements of GEB, breakers would also be provided at the supply side.
11/3.3 KV Switch gear would be SF6/vacuum and SF6/Air circuit breaker having interrupting
capacities of not less than 750 MVA and 250 MVA respectively.
L.T. Switch gear would be drawn out, multi panel type and would have Air Circuit Breakers. All the
Switch gears would be of indoor metal clad type.
8.1.9.5 Lighting
Captive Jetty(ies)s in general work round the clock; therefore, the need for exact illumination for
different areas is required to be identified at a later stage. However, about 120 Lux is desirable in
the control rooms of the Captive Jetty(ies), where readings of the various instruments are to be
recorded. In other areas of the Captive Jetty(ies), provision for about 80 Lux of lighting is proposed,
part of which could be switched off when not under use. In the Captive Jetty(ies) area where night
working is proposed minimum lighting requirement is about 60 Lux; however, in the absence of
night working 15-20 Lux is required for security purposes.
During power failures, supplies would be provided to selective lighting loads, as decided by the
user, through diesel generating sets.
In the main substation, emergency D.C. lighting would be provided for limited use. A set of batteries
with chargers will be provided for this purpose.
8.1.9.6 Backup Power Systems
The loading and unloading operations and emergency lighting would only be using the backup
power. The other operations will be suspended during power failures. Two stand-by diesel
Techno-Economic Feasibility Report
128
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
generating sets having a capacity of 1000 KVA each are envisaged to provide power to the Captive
Jetty(ies), in the case of power failure. These generators would supply at 440 V and would meet
the emergency requirements and lighting load. They are to be started automatically/ manually and
load put on selectively depending on the need. This would amount to a total power demand of
800 KW with the diversity factor of 0.5 and load factor of 0.8. Adequate provision for catering to
the future increase in load requirement is made.
The generator house, switching station etc. will be provided with provision for future expansion of
2 additional sets of 1000 KVA.
8.1.9.7 Codes and Standards
All standards and codes of practice shall be the latest editions including all applicable official
amendments and revisions as on date of implementation.
In the case of conflict between this specification and the standards referred to herein, the former
shall prevail.
8.2 Miscellaneous Services
8.2.1 EDI Facilities
During the last twenty years, since containers have come into widespread use, the productivities
and capacities of the Captive Jetty(ies)s have improved immensely. The competitiveness of
Captive Jetty(ies) operations in general, and container traffic in particular, increases with a shorter
turnaround time due to better availability of quays and high performance equipment together with
involvement of private operators. These changes in Captive Jetty(ies) facilities and the new working
conditions for stevedores substantially increase the Captive Jetty(ies) investments. Matching
productivity increases have to be achieved which requires inter-alia the processing of information
and documentation. It is now widely acknowledged in the Captive Jetty(ies) and maritime industry
that a Captive Jetty(ies)’s productivity and quality of service are also critically dependent on the
speed of documentation, processing and availability of real time information on the location and
status of ships, containers and goods, apart from the state-of-art physical facilities and operations
for reduction of the time spent by ships and goods and all users in the Captive Jetty(ies).
Computerization and EDI systems/operations avoiding highly laborious and time consuming manual
procedures will enable availability of real time information for speedy handling of ships and goods
in Captive Jetty(ies) and interaction with all Captive Jetty(ies) users.
In addition high-speed information/data processing and communications systems are necessary
to provide the infrastructure for EDI systems and improve the competitive edge of the Captive
Jetty(ies), decrease the cycle times, increase the rapidity of calls and shorten the transit-time of
goods in the Captive Jetty(ies) and provide prompt, real time and accurate information to all the
Captive Jetty(ies) users for mutual/joint planning of all activities, for all round optimal performance,
at least cost.
Techno-Economic Feasibility Report
129
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Powerful information/data-processing methods adequately supported by high speed
communication and data links with appropriate inter connections are proposed at this Captive
Jetty(ies) to manage the Captive Jetty(ies) activities in the areas of:
Maritime traffic control, VTS (at a later date)
Scheduling and management of maritime calls and ships
Planning operations for ship unloading, transfer to storages and further handling to the land
side transport
Control of container movements
Management of all storage and container yards and speeding up of cargo-handling
operations in every area
Fast tracking of all goods
Documentary procedures related to transit of goods throughout the Captive Jetty(ies)
In addition, Captive Jetty(ies) equipment and facilities are required to resort more and more
to data processing such as,
Remote control of fixed or mobile equipment – bridges, cranes, video camera networks
etc.
Monitoring and control of the operations of gantry cranes for containers and other cargo
and all major equipment in storage and dispatch/receiving yards
Computer assisted maintenance management including maintenance planning
Inventory requirements of the Captive Jetty(ies)
The information/data processing equipment located at the harbour master’s office, the various
cargo terminals and company head office, along with complementary interactive terminals at the
users’ offices inside and outside the Captive Jetty(ies), viz. various companies and firms, ships
and shipping agents, forwarding agents, hauliers, customs services, etc. form the network for
control, communications, information and data exchanges, decisions and their communication,
and provide the maximum benefit to the Captive Jetty(ies) and all its users and also the inland
infrastructure and services.
The need for extensive communications and exchange of information go together with this facility
development. The codified transactions related to the customs, administrative and commercial
processing of cargo, transmission of data and financial processes and commitments are the basic
elements of such a network.
Techno-Economic Feasibility Report
130
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
9 Cost Estimates & Financial Analysis
9.1 General
A successful project depends on its technical soundness and economic viability. The technical
aspects of the project for handling of the projected traffic have been discussed in the previous
chapters. The present chapter would mainly deal with the cost estimates and financial evaluation
of the project.
The first step leading to any financial evaluation is to determine the capital as well as operation
cost to a reasonable degree of accuracy. Accordingly, cost estimates for various components and
sub-components are required to be determined precisely so that the cost estimates for the
proposed facilities would be accurate and variation if any will be within the permissible and
acceptable limits.
In addition, the cost of money (interest on account of borrowings) is also important. It should be
very well understood that, interest during construction (IDC) is a big component of the total interest
accruals is directly dependent on the construction period. Hence longer the construction period
higher will be the IDC and vice versa. Therefore, before going ahead with the financial evaluation,
it is necessary to make a construction schedule for the project execution.
9.2 Construction Schedule
Detailed construction methodology and scheduling is beyond the scope of this report. However, in
order to carry out the financial analysis of the project the construction methodology and the material
sourcing shall be discussed in brief. It must be remembered that an efficient construction
procedure would lead to shorter period of completion, thereby saving on interest during
construction and furthermore advancing the revenue earning capacity of the Captive Jetty(ies).
The various broad activities envisaged for the realization of the project are outlined below:
i. Approach roads road and railways for Captive Jetty(ies)
ii. Hydraulic dredging and disposal
iii. Reclamation
iv. Construction of waterfront structures
v. Breakwaters
vi. Storage facilities
vii. Access to/from Captive Jetty(ies) by road/rail
viii. Operational/maintenance/service facilities
ix. Operational staff amenities
The construction schedule prepared is enclosed as Figure 9.1.
Techno-Economic Feasibility Report
131
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
Figure 9-1: Construction schedule for the proposed Captive Jetty(ies)
9.3 Basis of Cost Estimates
The item rates for the civil works and cost of various equipment and machinery were arrived at
based on the procurement cost on similar other facilities. The cost of civil construction such as
berths is derived from the current contracts being carried out in the market. The cost of dredging
was taken from the prevailing market price. In case of breakwater actual working out of quantities
was resorted to. Since, the dredging and breakwater constitutes 60% of the cost, care was taken
to calculate them very carefully. The block estimates for the initial phase is given as figure 9.1.
Table 9-1: Cost Estimate for the Project
S.NO. PARTICULARS RATE QUANTITY
AMOUNT (Rs. in Millions)
In Rs. 52 MTPA stage
1 Land Development 100.00
2 Breakwater 1600 783000.00 1252.80
3 Dredging 160 24000000 3840.00
4 Civil works
4.1 Berths 75000 70000.00 5250.00
4.2 Buildings 270.00
4.3 Water supply etc 250.00
4.4 Road (Intrenal) 1000.00
4.6 Foundations for Equipment 200.00
4.7 Jetty for Captive Jetty(ies) Crafts -
Total Civil works 12162.80
4.8 Investigation, consultancy etc. 121.63
Grand Total Civil works 12284.43
5 Mechanical equipment
5.1 Mechnaical Unloader - Coal 550 2 1100.00
5.2 Mechanical unloader - Lime Stone 550 2 1100.00
5.3 Unloader (MHC) 400 2 800.00
5.5 Stacker Reclamier - Coal 450 2 900
5.6 Stacker Reclamier - Lime Stone 250 1 250
5.5 Conveyor for coal 0.2 1050 210
ACTIVITY
YEAR
S.
No.MONTH 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
1 DREDGING (Port area)
(Approach Channel)
2 BERTHS
3 BREAKWATER
4 OTHERS
Time
Techno-Economic Feasibility Report
132
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
S.NO. PARTICULARS RATE QUANTITY
AMOUNT (Rs. in Millions)
In Rs. 52 MTPA stage
5.6 Conveyor for Lime Stone 0.2 1000 200
5.8 Work Shop Equipment LS LS 250
5.10 Tractor Trailor 10 12 120.00
5.11 Dust suprression Etc. 150.00
5.12 Navigation Aids 100.00
5.13 Spares for 2 years 259.00
5.14 Errection and commisioning 11.02% of total cost 599.38
Grand Total Mechanical Equipment
6038.38
6 Miscellaneous
6.1 Electricals 1500.00
6.2 Power backup 500.00
6.3 Installation and comm. (Elct) 220.40
Grand Total Electricals 2220.40
7 Contingencies @ 5% 412.94
8 Consultancy @ 1 % 82.59
TOTAL PROJECT COST 21038.73
9.4 Financial Evaluation
This section discusses the assumptions made to carry out the financial assessment, capital cost
and Interest during Construction (IDC) to calculate total project cost, Internal Rate of Return (IRR)
and finally sensitive analysis considering few scenarios.
9.4.1 Assumptions
In order to carry out the financial evaluation of the alternative the following factors are considered:
Mobilization of investment is considered with a total Debt: Equity ratio of 0.70:0.30.
Interest during construction is considered as 12%.
Capital investment is repayable in 15 equal instalments after the completion of construction
period plus one year on operation. Interest after construction will be considered on reducing
balance.
For the present the project has 2 phases of development as follows:
o Phase I – : 10 berths and associated facilities
o Phase II - : at 100 MTPA stage 14-16 berths
Contingency for other phase is also considered as 5 % of the cost at that particular phase.
Administrative cost including salary and wages is calculated as 2% of the project cost,
increasing at 5% per annum.
Operation and maintenance cost is considered as 2% of the project cost, increasing at 5%
per annum.
Maintenance dredging of 1.5 million m3 per annum is considered at Rs 180/ m3 with annual
increase in price at 1%.
Techno-Economic Feasibility Report
133
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
A straight line depreciation calculation is adopted with the following life periods.
o Civil works : 30 years
o Equipment : 15 years
Annual traffic for each phase is taken as given.
The tariff for first year is Rs 350/ ton, increasing at the rate of 15% every 3 years.
Government royalty in form of wharfage of Rs. 15/- per ton would be levied. The increase
in the wharfage is at a rate of 20% per three years.
9.4.2 Internal Rate of Return
The borrowings at 10 % rate of interest from the nationalized banks are assumed. Accordingly, the
rate of return on the 30 year time period works out to 14.00 % for a tariff of Rs 375/ton.
9.4.3 Internal Rate of Return
Sensitive analysis was carried out changing the tarries alone, since, this Captive Jetty(ies) feeds
the requirements of the in house steel plants. As could be expected the IRR increases with the
tariff which suggests that the returns will be far better than suggested above. Table 9.1 gives the
sensitive analysis for the IRR.
Table 9-2: Sensitivity analysis
Sl. no Tariff in Rs. IRR in %
1 375 14.00
2 400 15.67
3 425 16.75
4 450 18.10
5 475 20.10
9.5 Calculation of Tariff Scenarios at Paradip Port – Bulk Handling
The above analysis is based on a total Jetty(ies) tariff of Rs.350 per ton. However, it was considered
essential to calculate the present total tariff at the nearest Paradip port, so that, the applicability of
Rs. 350/ton is duly verified. Accordingly, based on the notifications of the traffic department dated
November 20th, 2007, the following jetty(ies) tariff is calculated, which is applicable from November
1st 2007. These rates are subjected to escalation based on the year of calculation.
Total tariff at Paradip Port can be summarised as:
i. Ship related charges - Rs. 72.20 + Rs. 30.00 (Demurrage) = Rs. 103
ii. Wharfage - Rs. 71/ton for cargo higher than 7 million tonnes
iii. Handling charges - Rs. 198/ton including unloading and handling
iv. Storage charges - Rs. 15.00/ton for 15 days
Total - Rs. 384/t
Accordingly, it could be seen that, at present the port tariff works out to about Rs.385.00, at the
current prices. The charges are exclusive of the demurrage charges.
Techno-Economic Feasibility Report
134
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
10 Benefits of the development
General benefits of major developments like Captive Jetty(ies) is not only restricted to the financial
benefits to proponent and government but also have several societal benefits. Benefits go beyond
the investment and returns due to the social gains from the project, i.e., improvement in quality of
life, health benefits, environmental benefits, employment generation etc.
The other existing nearby port at Paradip helped in large extent to overall industrial development of
the region through establishment of industries such as Fertilizers (Paradip Phosphates Limited,
IFFCO), Refineries (IOCL) and Seafood processing. Paradip fishing harbour came into being, which
is now considered as one of the largest fish and shrimp landing centres in India and sustain the
livelihood system of thousands of families of the region. The industrial development around the
Paradip port area also helped in establishment of educational institutions, heath care facilities,
transpiration facilities, hotels creating thousands of jobs for local people.
Similarly, new proposed Captive Jetty(ies) will also provide the following opportunities:
• Employment generation for localities
• Development of road and rail connectivity
• Ware housing and other logistics park
• Port company for various cargo handling (stevedoring)
• Port led industrial development or SEZs
Apart from the above mentioned activities, proponent is also willing to contribute towards better
medical and educational facilities and drinking water provisions.
Techno-Economic Feasibility Report
135
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
11 Conclusions and Recommendations
11.1 Conclusions
The current report is preliminary in nature and based on the available secondary data. No data
collection was undertaken for the present study. The main aim of the report is to get the Captive
Jetty(ies) apprised by the Government of Odisha leading to in principle approval and signing of
Concession Agreement. Thereafter, the report would be used for obtaining the Terms of Reference
from the MoEF&CC, for preparation of the EIA/EMP document from a competent and approved
agency leading to CRZ and Environmental clearance.
The report determines the feasibility of establishing the Captive Jetty(ies) facility on the Jatadhari
Muhan River bank, where adequate tranquillity would permit round the year operation without any
extensive breakwater protection. The site was selected after examining 3 alternative locations
including the Jatadhari River bank. The estuary offers tranquil environment and adequate space for
operation and storage. Strategically located fronting the proposed steel plant, the Captive Jetty(ies)
can double up as the RMHS of the steel plant by directly supplying raw material to the plant bins.
Similarly, the products could be stored at the Captive Jetty(ies), so that export of the products are
easy.
10 berths in the first and 14-16 berths in the 100 MTPA phase would be necessary for handling
the captive as well as the commercial cargo that may generate with the operation steel plant and
the ancillary industries that may precede them. The Captive Jetty(ies) would be developed with an
initial outlay of INR 2100 crores, and at the current prevalent tariffs at the Paradip Port, 14% IRR is
computed.
11.2 Recommendations
11.2.1 Studies to be undertaken
As discussed above this is the first report prepared to determine the feasibility of the Captive
Jetty(ies) facility. On approval of the Odisha Government for construction of a Captive Jetty(ies),
the following studies would have to be undertaken, so that statutory approvals and engineering
designs could be carried out. The studies could be broadly divided in to the following;
A. Field Investigation
B. Mathematical Model Studies
C. EIA/EMP study
D. Sustainability study as part of EIA
E. Detailed Project Report and Detailed Engineering
11.2.1.1 Field Studies
Field Studies to determine the following parameters are essential;
1. Hydraulic Parameters of the area consisting of;
Techno-Economic Feasibility Report
136
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
i. Current
ii. Tide
iii. Silt Charge
iv. Bed Material
v. Salinity and Temperature
2. Date collection with respect to wind and wave;
i. Hind cast data on wind and wave for long term data banks such as IMD & UKMO
ii. Local weather data from the regional IMD office
3. Soil Investigation to determine
i. The Dredgeability of the approach channel and Jetty(ies) basin
ii. Safe bearing capacity of the founding soil
iii. Bearing capacity of the stackyard area
4. Environmental Data
Ambient data for determining the likely impact of the development including but limited to air
and water quality modelling. Impact of dredging etc.;
i. Air Quality
ii. Water quality, for surface, marine and ground water
iii. Noise
iv. Terrestrial Ecology
v. Marine ecology
vi. Socio-economic study
vii. Study of historical and heritage locations
11.2.1.2 Mathematical model Studies
The mathematical studies to be undertaken would depend on the design details and the
implementation parameters. In general, for a typical Captive Jetty(ies) location the following model
studies are carried out.
1. Coastal Hydrodynamics and Flow modelling
2. Sedimentation
3. Evolution of shoreline and costal morphology
4. Wave propagation and effect under
a. Fair-weather conditions
b. Extreme weather conditions
5. Tranquility in the harbour and down time estimates
6. Sea water exchange
7. Disposal of dredged material
8. Thermal intake and outfalls
9. Harbour resonance
Techno-Economic Feasibility Report
137
Development of Multi-cargo Captive Jetty(ies)
at Jatadhari Muhan, Jagatsinghpur
JSW Infrastructures Limited
11.2.1.3 EIA and EMP Study
Based on the ambient conditions and developmental plan, an EIA/EMP report shall be prepared
through a competent and accredited consultant.
The report would be prepared based on the standard ToR and the additional ToR issued by the
Environmental Appraisal Committee, Infrastructure and CRZ, MoEF&CC. The Feasibility report and
mathematical model study report will form part of the EIA submittals.
11.2.1.4 Detailed Project Report
After obtaining in principle approval of the Government of Odisha and the Environmental clearance,
the detailed design and developmental plan shall be prepared. This would be submitted to the
appropriate authorities to approve the exact plan of development, leading to execution of the
project.