TECHNIQUES AND RESULTS OF EXAMINATION OF FISSION PRODUCT RELEASE FROM VVER FUEL RODS WITH ARTIFICIAL...
-
Upload
pedro-fears -
Category
Documents
-
view
214 -
download
1
Transcript of TECHNIQUES AND RESULTS OF EXAMINATION OF FISSION PRODUCT RELEASE FROM VVER FUEL RODS WITH ARTIFICIAL...
TECHNIQUES TECHNIQUES AND AND RESULTS RESULTS OF OF EXAMINATIONEXAMINATION
OF OF FISSION FISSION PRODUCT PRODUCT RELEASERELEASE FROM FROM VVER FUEL VVER FUEL
RODS WITH RODS WITH ARTIFICIAL ARTIFICIAL DEFECTS DEFECTS AND AND A A BURNUPBURNUP
OF ~60 MWd/kgU OF ~60 MWd/kgU AT AT THE THE MIR MIR LOOPLOOP FACILITY FACILITY
РНЦ КИРНЦ КИ
8th International Conference8th International Conferenceon VVER Fuel Performance, Modelling on VVER Fuel Performance, Modelling
and Experimental Supportand Experimental Support
26 September – 04 October 2009, Helena Resort near Burgas, Bulgaria26 September – 04 October 2009, Helena Resort near Burgas, Bulgaria
А.V. Burukin, А.V. Goryachev, S.А. Ilyenko, A.L. Izhutov, V.V. Konyashov, V.Yu. Shishin, V.N. Shulimov
JSC “SSC RIAR”, DimitrovgradL.M. Luzanova, V.N. Miglo
RRC “Kurchatov Institute”, Moscow, Russian Federation
22
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
CONTENTS
Introduction
1. EQUIPMENT AND TECHNIQUES
1.1 PV-1 loop facility of the MIR reactor, equipment used for
radiation measurements and sampling
1.2 Procedure of fission product sampling and activity measurement
1.3 Irradiation rig and experimental fuel rods
2. RESULTS OF IRRADIATION TESTS
3. MAIN RESULTS OF POST-IRRADIATION EXAMINATION
4. RESULTS AND DISCUSSIONS
Conclusions
33
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
PURPOSE OF EXAMINATION
On the basis of experimental data on radioactive fission product
(RFP) release from the defective high-burnup VVER fuel rods under
conditions simulating typical design-basis operation scenarios of a
power reactor, it is possible to justify radiation safety of NPP taking
into account the effect of burnup level on RFP release from
defective fuel rods into the primary coolant of the operating reactor
and to verify calculation codes for prediction of radiation
environment in the primary circuit of the VVER reactor.
INTRODUCTION
44
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
INTRODUCTION
IRRADIATION TEST TASKIRRADIATION TEST TASK
During the first test, which was conducted at the PV-1 loop facility of the
MIR reactor, release of gaseous and main dose-forming volatile RFP from
an experimental defective re-fabricated fuel rod was measured; this fuel rod
was prepared using a full-size VVER fuel rod operated in the NPP power
reactor. The re-fabricated fuel rod was irradiated under quasi-steady-state
conditions which correspond to operating parameters of the VVER-1000
fuel rods.
That was a methodical test which aimed at testing of new equipment and
techniques in order to assess their appropriateness for the further test run.
55
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
Preparatory stages before testing involved the following activities:
-analysis of technical characteristics of the MIR loop facilities in order to select the most appropriate one taking into account predicted coolant activity and implementation of different design-basis scenarios for fuel operation providing compliance with safety requirements;
-analysis of characteristics of the modern spectrometric equipment in order to assess whether measurements of predicted coolant activities are sufficient taking into account acceptable measurement intervals which allow tracing of activity change kinetics during the test;
-design, manufacture and installation of equipment for irradiation test at the MIR loop facility; the equipment should provide application of required examination techniques;
- development of equipment for application of calibrated artificial through defects on claddings of re-fabricated fuel rods.
1. EQUIPMENT AND TECHNIQUES
66
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
1.1 PV-1 loop facility of the MIR reactor,equipment used for radiation measurements and sampling
1 – loop channels; 2 – circulating pumps; 3 – pressure compensators; 4 – gas tanks;5 – heat exchanger of PVP-1 loop facility; 6 – main heat exchanger; 7 – mechanical filter;
8 – purification heat exchanger; 9 – ion-exchange filterLayout of PV-1 loop facility of the MIR reactor
77
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
1 – ion-exchange filter; 2 – portable sample container; 3 – chamber wall of PV-1 loop facility; 4 – flow-through measuring tank; 5 – collimator; 6 – HPGe detector
Equipping of the PV-1 loop facility primary circuitwith auxiliary radiation measuring instruments
1.1 PV-1 loop facility of the MIR reactor,equipment used for radiation measurements and sampling
6
P rim aryc ircu itou tle t
P rim aryc ircu itin le t
1
To autom aticchem ical
contro lsystem
R ecircu lation c ircu ito f sam p ling system
2
S am plingcabine t
To specia lventila tion
S am pling system foractivity m easurem ent
5
3
4
88
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
1.1 PV-1 loop facility of the MIR reactor,equipment used for radiation measurements and sampling
1 – ion-exchange filter; 2 – portable sample container; 3 – sample syringe;4 – HPGe detector; 5 – buffer gas vessel; 6 – water vessel
Flowsheet of coolant sampling system and sample handling operations
R ecircu la tion c ircu ito f sam p ling system
P hase separa tion
P rim aryc ircu itou tle t
P rim aryc ircu itin le t
1
To specia l sew erageFor phase separa tion and
activity m easurem ent
2
S am plingcabine t
To autom atic chem ica lcontro l system
To specia lventila tion
4
G am m a spectrom etricanalys is
3
2 5 6
99
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
1.1 PV-1 loop facility of the MIR reactor,equipment used for radiation measurements and sampling
1 – gamma ray detector; 2 - radiation (background) shielding of detector; 3 - radiation collimator;4 - shadow shielding of measuring tank; 5 – hole in the shielding of measuring tank;
6 - measuring tank; 7 - cutoff valves of measuring tankGamma spectrometry measurement area
for the coolant samples at PV-1 loop facility
Coolant inlet
Coolant outlet
1
2 3 4 5
7
6
8
PC for control and primary processing
DSPec-jr-2.0 instrument
To MCS of PV-1
1010
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
1.2 Procedure of fission product sampling and activity 1.2 Procedure of fission product sampling and activity measurementmeasurement
Complementary procedure and system for measurement of specific activity of radionuclides can be applied simultaneously during irradiation testing:- on-line measurement system which provides detailed information about short-lived high-activity fission products with a short half-life period (5-10 min);-sampling technique which provides quantitative information about long-lived low-activity fission products.
Sampling:Sampling frequency – every day;Separation of coolant phases – immediately after sampling;Measurement of radiation spectrum of coolant fractions after sampling: - in 20-30 min; - in ~ 1.5 h; - in ~ 1 day; - in ~ 3 days; - in ~ 7 days.«On-line» measurements:Measurement of radiation spectrum of coolant – continuously during irradiation, exposure time - 5-30 min.
1111
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
1.3 Irradiation rig and experimental fuel rods
Irradiation rig and experimental fuel assembly
For testing an irradiation rig was developed and manufactured; it provided thermophysical parameters and a coolant velocity diagram near the experimental fuel rods which are similar to the standard ones in a full-size VVER-1000 fuel assembly. The experimental fuel assembly, which contained seven fuel rods and was similar to the fragment of the VVER-1000 fuel assembly at the cross-section, formed a part of the irradiation rig. The experimental re-fabricated fuel rod was inserted into the central cell and surrounded by six fuel rods with unirradiated fuel.
Fuel rod with an artificial defect
Design of the experimental fuel rod was selected from considerations of its similarity to the full-size VVER-1000 fuel rod as to the active part and gas plenum volume. The active fuel length was ~ 1000 mm; it corresponds to the MIR core height. The artificial defect was applied on the cladding in form of a through hole 1 mm in diameter; it was applied in the active part with the maximum heat release at a height of ~ 240 mm from the fuel rod end plug.
1212
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
2. RESULTS OF IRRADIATION TESTS
Duration of irradiation of the re-fabricated fuel rod for the first test depended on a standard cycle of the MIR reactor and made up ~22 days; it allowed achieving equilibrium activity levels of most of the recorded RFP in the PV-1 primary coolant
Change in maximum fuel temperature, temperature (Тc) and pressure (Рout) of PV-1 primary coolant during testing
Change in maximum (MLHGR) and average (ALHGR) LHGR of the fuel rod with artificial defect during testing
0
200
400
600
800
1000
0 3 6 9 12 15 18 21 24Time, days
Tem
pera
ture
, о С
0
5
10
15
20
25
Pre
ssur
e, M
Pa
TcTf maxPout
0
5
10
15
20
0 3 6 9 12 15 18 21 24
Time, days
LH
GR
, kW
/m
MLHGRALHGR
1313
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
2. RESULTS OF IRRADIATION TESTS
Change in specific activity of iodine radionuclides in the coolant during testing
Change in specific activity of inert radioactive gases in the coolant during testing
1.00E+05
1.00E+06
1.00E+07
1.00E+08
1.00E+09
0 3 6 9 12 15 18 21 24Time, days
Acti
vit
y,
Bq
/kg
Kr-85m Kr-87Kr-88 Kr-89Xe-133 Xe-135Xe-138
1.00E+05
1.00E+06
1.00E+07
1.00E+08
1.00E+09
0 3 6 9 12 15 18 21 24Time, days
Acti
vit
y,
Bq
/kg I-131 I-132 I-133
I-134 I-135
1414
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
3. MAIN PIE RESULTS
Test performed by the above techniques did not reveal any noticeable changes of fuel rod state except for the strained area with a crack in the gas plenum area. Cladding surface of the active part, the artificial defect and the areas near this defect didn’t undergo any noticeable changes.
Non-destructive examination
Inspection and photographing of
fuel rodGamma scanning
Profilometrymeasurements
X-ray radiography
Areas of the fuel rod cladding with the artificial defect after testing:(a) artificial defect, (b) through defect in the gas plenum area
a) b)
1515
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
No RFP redistribution and fuel wash-out through the
artificial defect
No change in fuel rod diameter over the full
active fuel length
No gaps between the fuel pellets;
No damage of pellets
Results of gamma scanning of the experimental fuel rodsin the area of the artificial defect after testing
Inspection and photographing of
fuel rodGamma scanning
Profilometrymeasurements
X-ray radiography
Non-destructive examination
0
100
200
300
400
225 230 235 240 245 250 255Coordinate, mm
Inte
nsi
ty,
pu
lse/s
Cs-137Cs-134ZrNbRu-106
Lower part of fuel rod
Artificialdefect
3. MAIN PIE RESULTS
1616
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
Destructive examination
Metallographic examination Electron probe microanalysis
- fuel is fragmented into 4-6 parts
by radial cracks mainly ;
- diameter of central hole in the
fuel column is 2.3–2.4 mm over
the full length of the experimental
fuel rod;
- rim-layer is ~ 60 μm in width;
- no fuel-cladding gap over the full
length of the experimental fuel
rod;
- fuel-cladding interaction layer is
~ 10 μm in width Fuel microstructure of experimental fuel rod with
artificial defect after testing at different cross-sections:(a) cross-section ~500 mm above end plug,
(b) cross-section near the artificial defect
3. MAIN PIE RESULTS
b)
a)
Boundary with central hole
Center of pellet
Boundary with cladding
1717
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
1. PIE showed that the fuel-cladding gap of the experimental fuel rod
was bridged. A close thermal contact between fuel boundary area and
cladding caused the rim-layer temperature to be within limits specified
for normal operation of an original full-size VVER fuel rod .
This observed effect and absence of fuel surface oxidation, which is
probably caused by a close contact between fuel and cladding, suggest
that only gaseous and volatile fission products, which were
accumulated in the central hole of the fuel column, released into the
primary coolant of the PV-1 loop facility through the cladding defects
(artificial defect and defect formed in the gas plenum area during
testing).
4. RESULTS AND DISCUSSIONS
1818
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
2. Defect in the gas plenum area as a result of cladding strain and rupture was formed in the earliest test stage due to thermal expansion of the coolant if the fuel rod reached a specified LHGR.
Change in MLHGR of fuel rod and activity of PV-1 primary coolantin accordance with sensor readings in the course of bringing reactor to power
4. RESULTS AND DISCUSSIONS
0
100
200
300
400
500
1.25 1.50 1.75 2.00Time, days
Sen
sor
read
ings
of
con
trol
sy
stem
s, r
el. u
nit
s
0
4
8
12
16
20
LH
GR
, kW
/m
CIC systemGAC systemMLHGR
1919
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
4. RESULTS AND DISCUSSIONS
0
5
10
15
20
21 22 23 24 25Time, days
LH
GR
, k
W/m
13.0
13.8
14.5
15.3
16.0
Pre
ssu
re,
MP
a
MLHGR
Pout
1.0E+05
1.0E+06
1.0E+07
1.0E+08
1.0E+09
21 22 23 24 25
Time, days
Act
ivit
y,
Bq
/kg
I-131I-134
Cs-137
Change in MLHGR of fuel rod and Pout before/after test completion in the course of MIR reactor shut-down and decrease of pressure in the PV-1 primary circuit
Change in 131I, 134I and 137Cs activity in the coolant under the above conditions
2020
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
3. Significant size of the defect, which was formed in the gas
plenum area, reduced appreciably (or practically eliminated)
inhibition of volatile and gaseous fission product release from the
free volume of fuel rod into the coolant.
If we compare size and location of the artificial defect and the
through defect formed on the cladding during testing, we can
suppose that iodine from the central hole of the fuel column
released completely and without interruption through the
macrodefect in the gas plenum area.
4. RESULTS AND DISCUSSIONS
2121
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
CONCLUSIONS
1. Complex of equipment and several techniques for examination
of RFP release from defective fuel rods were developed, prepared
and tested at the PV-1 loop facility of the MIR reactor.
2. During the first test, which was conducted at the PV-1 loop
facility and aimed at testing of developed equipment and
techniques, measurement of RFP release from an experimental
re-fabricated fuel rod with a burnup of ~60 MWd/kgU and an
artificial defect was performed under design-basis steady-state
operating conditions of the VVER-1000 reactor.
2222
РНЦ КИРНЦ КИ
26 September – 04 October 2009, Burgas, Bulgaria
3. PIE of all main parameters of the experimental defective fuel rod did not reveal any state peculiarities which could be caused by the artificial defect, i.e. fuel and cladding characteristics in the defect area did not differ from the initial ones (before testing) as well as their characteristics in areas distant from the defect; they are typical for fuel rods with a similar irradiation history in the VVER NPP.The gap in the experimental fuel rod was bridged due to close contact between fuel and cladding at increased fuel burnup; it can appreciable reduce RFP release into the PV-1 primary coolant. This suggestion and quantitative characteristics of effect of gap bridging in a high-burnup fuel rod on RFP release should be investigated during the next tests performed at the PV-1 loop facility.
4. Values of RFP release measured during the first test at the PV-1 loop facility in the MIR reactor will be used for development of an empirical engineering model in order to take into account high burnup effects and their impact on fission product release from fuel and defective fuel rods.
CONCLUSIONS
2323
РНЦ КИРНЦ КИ
THANK YOU FOR ATTENTION!
ACKNOWLEDGMENTSThe authors would like to express profound gratitude to the specialists of JSC TVEL,
especially to Mr. А.I. Sharikov, for his great assistance and active participation
in management of the tests in the MIR reactor