Binninger M., Dlouhy J., and Haghsheno S. (2017). “Technical Takt Planning and Takt Control in Construction.” In: LC3 2017 Volume II – Proceedings of the 25th Annual Conference of the International Group for Lean Construction (IGLC), Walsh, K., Sacks, R., Brilakis, I. (eds.), Heraklion, Greece, pp. 605– 612. DOI: https://doi.org/10.24928/2017/0297 TECHNICAL TAKT PLANNING AND TAKT CONTROL IN CONSTRUCTION Marco Binninger 1 , Janosch Dlouhy 2 and Shervin Haghsheno 3 Abstract: This paper is the counterpart to the paper Collaborative Takt Time Planning of Non-Repetitive Work of Iris Tommelein. Both paper describe Takt approaches in two different geographical and project contexts. A follow up paper is planned and will compare the described approaches and assesses their applicability and success. This Paper describes the German Takt approach, called Technical Takt Planning and Takt Control. The authors used this method in on several projects in construction. It describes the historically development of Takt in construction in German and leads to the current state of the theoretical method used at the Karlsruhe Institute of Technology (KIT). The third part of the paper gives a practical example of the KIT approach. The contribution of this paper is that it offers a characterization of the Takt approach that is used in Germany in several construction projects. The researchers try to give with the KIT Method an overview in science for the German Takt Planning and Takt Control approach. The method is for Takt integration in make to order production. Keywords: Lean Construction, Production System, Takt Planning and Takt Control. 1 I NTRODUCTION Takt time is increasingly being used to structure construction work and thus "shape" project schedules. In the companion papers (Tommelein 2017) we refer to previous uses of Takt in production and offer a framework for characterization of Takt methods currently used in construction. In German the word "Takt" means "beat" (Haghsheno et al. 2016) or the regularity with which something gets done. When the word is used in a Lean context, it is a concept interlinked with standardization, predictability, and many other Lean concepts. Takt refers to the heartbeat of assembly lines in the Toyota Production System (Haghsheno et al. 2016). Once a beat is set, every line can move in sync with others in a continuous flow process. Whether at Toyota, more generally in product development and manufacturing, or in construction, Takt defines the unit of time within which a unit of production must be produced (supply rate) in order to match the rate at which that product is needed by the customer (demand rate). Takt Time is a design parameter used in a production setting, be it manufacturing, construction, or other any other setting. The approaches used in different parts of the world and conceptualizations of Takt Time — even when applied in the same geographic region — appear to differ from one another. The aim of our ongoing study is to create conceptual clarity and highlight distinctions between approaches in the methods they use and contexts in which they apply. 1 Research Fellow, Karlsruher Institute of Technology, Germany, [email protected] 2 Research Fellow, Karlsruher Institute of Technology, Germany, [email protected] 3 Professor, Karlsruher Institute of Technology, Germany, [email protected] 605 | Proceedings IGLC | July 2017 | Heraklion, Greece

Transcript of TECHNICAL TAKT PLANNING AND TAKT CONTROL IN CONSTRUCTION · PDF fileTechnical Takt Planning...

Page 1: TECHNICAL TAKT PLANNING AND TAKT CONTROL IN CONSTRUCTION · PDF fileTechnical Takt Planning and Takt Control in Construction ... Planning with the Location-based Management System

Binninger M., Dlouhy J., and Haghsheno S. (2017). “Technical Takt Planning and Takt Control in Construction.” In: LC3 2017 Volume II – Proceedings of the 25th Annual Conference of the International Group for Lean Construction (IGLC), Walsh, K., Sacks, R., Brilakis, I. (eds.), Heraklion, Greece, pp. 605–612. DOI: https://doi.org/10.24928/2017/0297

TECHNICAL TAKT PLANNING AND TAKT CONTROL IN CONSTRUCTION

Marco Binninger1, Janosch Dlouhy2 and Shervin Haghsheno3

Abstract: This paper is the counterpart to the paper Collaborative Takt Time Planning of Non-Repetitive Work of Iris Tommelein. Both paper describe Takt approaches in two different geographical and project contexts. A follow up paper is planned and will compare the described approaches and assesses their applicability and success.

This Paper describes the German Takt approach, called Technical Takt Planning and Takt Control. The authors used this method in on several projects in construction. It describes the historically development of Takt in construction in German and leads to the current state of the theoretical method used at the Karlsruhe Institute of Technology (KIT). The third part of the paper gives a practical example of the KIT approach.

The contribution of this paper is that it offers a characterization of the Takt approach that is used in Germany in several construction projects. The researchers try to give with the KIT Method an overview in science for the German Takt Planning and Takt Control approach. The method is for Takt integration in make to order production.

Keywords: Lean Construction, Production System, Takt Planning and Takt Control.

1 INTRODUCTION Takt time is increasingly being used to structure construction work and thus "shape" project schedules. In the companion papers (Tommelein 2017) we refer to previous uses of Takt in production and offer a framework for characterization of Takt methods currently used in construction.

In German the word "Takt" means "beat" (Haghsheno et al. 2016) or the regularity with which something gets done. When the word is used in a Lean context, it is a concept interlinked with standardization, predictability, and many other Lean concepts. Takt refers to the heartbeat of assembly lines in the Toyota Production System (Haghsheno et al. 2016). Once a beat is set, every line can move in sync with others in a continuous flow process.

Whether at Toyota, more generally in product development and manufacturing, or in construction, Takt defines the unit of time within which a unit of production must be produced (supply rate) in order to match the rate at which that product is needed by the customer (demand rate). Takt Time is a design parameter used in a production setting, be it manufacturing, construction, or other any other setting.

The approaches used in different parts of the world and conceptualizations of Takt Time — even when applied in the same geographic region — appear to differ from one another. The aim of our ongoing study is to create conceptual clarity and highlight distinctions between approaches in the methods they use and contexts in which they apply.

1 Research Fellow, Karlsruher Institute of Technology, Germany, [email protected] 2 Research Fellow, Karlsruher Institute of Technology, Germany, [email protected] 3 Professor, Karlsruher Institute of Technology, Germany, [email protected]

605 | Proceedings IGLC | July 2017 | Heraklion, Greece

Page 2: TECHNICAL TAKT PLANNING AND TAKT CONTROL IN CONSTRUCTION · PDF fileTechnical Takt Planning and Takt Control in Construction ... Planning with the Location-based Management System

Technical Takt Planning and Takt Control in Construction

Along this line, Frandson et al. (2015) already compared and contrasted Takt Time Planning with the Location-based Management System (LBMS).

In this paper, we detail the approach for collaborative Takt Time Planning of non-repetitive work which we developed and piloted in the course of delivering a small project.

2 HISTORY OF DESCRIBED APPROACH

Using the principle of Takt is not new in the German construction industry. Takt was used in incremental launching in the 1970s (Gaillard 1974). Takt Planning was also mentioned in a context of concrete construction by Adolf Schub (1970) in his dissertation "Problems of Takt Planning in Construction Production". These approaches however, only used Takt for the purposes of planning.

The German Lean movement was started by Professor Fritz Gehbauer (2007). The main points of the method are contractual models and cooperative approaches such as the Last Planner System. Further methods and approaches, which are heavily used by consulting companies, were developed based on this. One such approach originates from a project consulted by Porsche Consulting in 2005 and is described in detail in Kaiser’s dissertation (Kaiser 2013, p. 68). Kaiser’s approach is based on a takted system for operational execution and includes the method Takt Planning and Takt Control. This approach is also mentioned in Friedrich et al. (2013).

The idea of takting work as part of Lean Construction and thereby seeks to create value-creating activities across the entire process chain of equal duration. This idea in combination with a short cycle control of the processes has only been implemented in Germany in the last 10 years. Since then some companies have placed a strong focus on this approach. An example of this is a medium sized enterprise described by Haghsheno et al. (2015). This approach was further developed at KIT (Dlouhy et al. 2016).

3 GEOGRAPHICAL AND PROJECT CONTEXT The Takt approach described here was developed for building projects with clearly identifiable replicable elements such as hotel construction, and later applied to other types of construction. In the meantime, this approach is applied to all types of buildings from office to residential construction.

The example project in this paper describes the new construction of the fire department of an automobile production plant. In this case takt was used only in the fit-out stage.

The scope of the project has a gross floor area of approx. 500 m2 for a German automobile producer. To minimize disruption to the fire brigade’s state of readiness, the goal was to complete construction as quickly as possible to allow normal operations to resume. Therefore, the original construction sequence with a timeline of 90.5 days (or approx. 18 weeks) was takted.

4 THEORETICAL FORMULATION OF TAKT PLANNING AND TAKT

CONTROL IN CONSTRUCTION

4.1 Takt Time in Manufacturing vs Takt Time in Construction

The idea of the Lean Construction methods of Takt Planning and Takt Control is to bring the processes necessary for creating value into a uniform flow. As uniformity and 100%

606 | Proceedings IGLC | July 2017 | Heraklion, Greece

Page 3: TECHNICAL TAKT PLANNING AND TAKT CONTROL IN CONSTRUCTION · PDF fileTechnical Takt Planning and Takt Control in Construction ... Planning with the Location-based Management System

Marco Binninger, Janosch Dlouhy and Shervin Haghsheno

consistency can never be achieved in practice, the system is adjusted to the uniform Takt ‘beats’ given. The more fine-grained a Takt selected, the higher the level of uniformity, and therefore the higher the level of control over the system. For the level of effort needed to control the system the reverse is true. Takt in manufacturing is normally defined in seconds or minutes (Haghsheno et al. 2016)

Kaiser recommends a weekly Takt for the construction sector and justifies this by stating that a Takt under two days in length is very difficult to implement in practice (Kaiser 2013, p. 113). The selected Takt is noticeably dependent on the variability/stability of the system and product, but is not constrained by these. From a Lean perspective, the goal is to reduce the batch size and reduce throughput time.

In practice a weekly Takt is often selected due to the instability of construction processes. Individual examples (Heinonen and Seppänen 2016) of hourly and daily Takt show that the Takt time to be used cannot be seen as a fixed number for all projects. For every project there could be a different takt time.

4.2 The technical Takt Planning and Takt Control method

Takt Planning

The method developed at KIT is based on Kaiser’s approach with various points developed in further detail. The Takt Schedule was developed collaboratively by the project team in 12 steps. The steps are shown in figure 1.

In the first step the project was divided into functional working areas. These are sections and areas of a construction which will be carried out using various process sequences. In the second step the priority of different areas was determined from the perspective of the client, and afterwards sorted into the individual areas according to priority. For the selected area (step 3) the Standard Space Unit (SSU) was defined. The SSU is the smallest repetive part in a project. During a workshop the project team planned works to the level of working steps in reverse order.

Step 6 is the most important piece of the method. Quantities were determined for the SSUs and multiplied by a performance factor. In step 7 the working steps were bundled into work packages. This bundling is strongly influenced by the traditional division of works. Step 8 organises the SSUs into practical Takt Areas and allocates the Takt Time. The Takt Time is often determined beforehand according to the needs of the client. The Takt Area is determined according to a calculation. Haghsheno et al. (2016) lists guidelines for the sizing of areas. Harmonization is completed in connection to this. This process levels the work load and is described explicitly by Binninger et al. (2016). The first result in Step 10 is a train of works. Work packages can be bundeled together in one waggon if there is a no collision. Steps 4-10 are then repeated for all Takt Areas. In Step 12 the results are shown in a Takt Plan.

607 | Proceedings IGLC | July 2017 | Heraklion, Greece

Page 4: TECHNICAL TAKT PLANNING AND TAKT CONTROL IN CONSTRUCTION · PDF fileTechnical Takt Planning and Takt Control in Construction ... Planning with the Location-based Management System

Technical Takt Planning and Takt Control in Construction

2) Define prioritiesWare-house

Office

ShopOther functional areas:Front, Roof, etc.….

Office

12

31) Define functional areas

3) Pick one functional area

11) Do steps 3 to 6 for all functional areas

12) Prepare the takt schedule and determine milestones in order to costumer priority

S1 S2 S3 A1 A2 A3 A4 A5 A6 C

S1 S2 S3 A1 A2 A3 C

S1 S2 S3 A1 A2 A3 A4 C Available for customer

Available for customer

Available

S1 S2 S3 A1 A2 A3 A4 A5 A6 C

A1 A2 A3 A4 A5 A6Container

Paint 1HVAC DC2 ELT 2Paint 2 fFlooringELT1 HVAC2Screed ffloorDC1 Doors

4) Define SSU(s) for one functional area SSU Office

Annotation: Office with several levels.

5) Define work packages for every SSU.

Paint 1HVAC DC2 ELT 2Paint 2 fFlooringELT1 HVAC2Screed ffloorDC1 Doors

6) Do the calculation of the amount of work for every step.

7) Allocate detailed works steps to work packages. Doors- Preperation wall- Door fraiming- Door blade

8) Determine Takt time and Takt area.Takt areae.g. 1 week

9) Takt levelling:- shifting variable work steps - Variation of manpower- Duplication of wagons- Buffer - …

Takt

Tim

e

1 2 3 4 5 6 time-

rela

ted

divi

sion

of w

ork

10) Combine the work packages best for determined Takt time and Takt area

DC 1ELT 1 Paint 1 Screed

floor DryingDC 2 Paint 2

FloorJoinerHVAC1

HVAC 2 ELT 2

Page 5: TECHNICAL TAKT PLANNING AND TAKT CONTROL IN CONSTRUCTION · PDF fileTechnical Takt Planning and Takt Control in Construction ... Planning with the Location-based Management System

Marco Binninger, Janosch Dlouhy and Shervin Haghsheno

Figure 1: 12 steps of Takt Planning

Takt Control

Takt Control, also known as "managing the gemba" or "shopfloor management", has the goal of placing control at the place of value creation. Short-cycled (daily) meetings on-site are considered particularly important (Peters 2009). The meetings are moderated by the construction manager, and all persons responsible for execution take part. The site is managed through Takt Control Boards (shopfloor boards). These boards are also standardized, and serve as a medium for visualization to achieve transparency. The key to motivating employees to take part in the meetings is to integrate them in the problem-solving process. The following key points are recorded:

• Number of workers per trade • Number of machines • Rate of compliance with the Takt Plan • Defects in quality • Safety figures, number of accidents, violations of safety rules • Number of disruptions to work • Information on cleanness and tidiness

The key figures and effort values determined according to the Takt Control, can be utilized in the Takt Planning of future projects with little effort.

4.3 Practical example – Firestation, Dingolfing Bavaria

During functional analysis (1) the first (Corridor) and ground floors (GF) were defined as separate areas. This is shown in Figure 2. The first floor was prioritized (2).

Figure 2: Takt Areas

For the first floor (3) the corridor, bedrooms and ground floor were defined as SSUs (4) before process steps were prepared by the team (5). The works and quantities were

2) Define prioritiesWare-house

Office

ShopOther functional areas:Front, Roof, etc.….

Office

12

31) Define functional areas

3) Pick one functional area

11) Do steps 3 to 6 for all functional areas

12) Prepare the takt schedule and determine milestones in order to costumer priority

S1 S2 S3 A1 A2 A3 A4 A5 A6 C

S1 S2 S3 A1 A2 A3 C

S1 S2 S3 A1 A2 A3 A4 C Available for customer

Available for customer

Available

S1 S2 S3 A1 A2 A3 A4 A5 A6 C

A1 A2 A3 A4 A5 A6Container

Paint 1HVAC DC2 ELT 2Paint 2 fFlooringELT1 HVAC2Screed ffloorDC1 Doors

4) Define SSU(s) for one functional area SSU Office

Annotation: Office with several levels.

5) Define work packages for every SSU.

Paint 1HVAC DC2 ELT 2Paint 2 fFlooringELT1 HVAC2Screed ffloorDC1 Doors

6) Do the calculation of the amount of work for every step.

7) Allocate detailed works steps to work packages. Doors- Preperation wall- Door fraiming- Door blade

8) Determine Takt time and Takt area.Takt areae.g. 1 week

9) Takt levelling:- shifting variable work steps - Variation of manpower- Duplication of wagons- Buffer - …

Takt

Tim

e

1 2 3 4 5 6 time-

rela

ted

divi

sion

of w

ork

10) Combine the work packages best for determined Takt time and Takt area

DC 1ELT 1 Paint 1 Screed

floor DryingDC 2 Paint 2

FloorJoinerHVAC1

HVAC 2 ELT 2

Page 6: TECHNICAL TAKT PLANNING AND TAKT CONTROL IN CONSTRUCTION · PDF fileTechnical Takt Planning and Takt Control in Construction ... Planning with the Location-based Management System

Technical Takt Planning and Takt Control in Construction

calculated and multiplied by an effort value (6). An extract of the calculation can be seen below.

Reference Trade Work Content Quantity Unit Waggons

Room (15 m²) DC I Place framework, single-sided duplex planking

25 m² W1

Room (15 m²) ELT I Installation System 3 m

W2

Run cables 30 m

Room (15 m²) Heater I

Pipe installation 12 m

Prepare heater connection 1 Stk

Insulation 12 m

Room (15 m²) HVAC I Ventilation duct 7 m

Figure 3: Calculation of the work contend

The tasks were assembled into work packages (7). The following figure 4 shows the work packages for the corridor.

Figure 4: Work packages

After determining the Takt Time and length of the Takt (8) and harmonisation (9) the sequence of the trains was determined (10). In the next step the approach (11) was repeated for the ground floor. In this case study five Takt Areas (3x bedrooms, 1 x corridor, 1 x ground floor) were used. On the first floor a Takt Time of 2.5 days was implemented, while five days was used on the ground floor. Finally, the production timeline was prepared (12) as shown in Figure 5. The result is demonstrated in Figure 6 and 7.

Figure 5: Making a Takt schedule

HOW TO DO - BMW LEAN CONSTRUCTIONTAKTBEREICHE DEFINIEREN UND ERSTELLEN.

SSU singleRoom

Standard Space Unit (SSU) = 1 Room

Raum (15 m²) TB I S tänder stellen, einseitig zweifach beplanken 25 m²Trassenbau/Verlegesystem 3 mKabelverlegung inkl. S chalter/Dosen 30 mRohrleitungen verlegen 12 mHeizkörperanschlüsse vorbereiten 1 S tkDämmung 12 m

Raum (15 m²) Lüftung I Lüftungsleitungen 7 mKlimageräte 1 S tkRohrleitungen verlegen 12 mDämmung 12 mWände zweifach schließen 25 m²Zargen einbauen 1 S tkS pachteln Q3 50 m²Trocknung 1 S tkS chleifen, S pachteln Q3 50 m²Trocknung 1 S tkS chleifen 50 m²

ELT I

Heizung I

Klima I

Raum (15 m²)

Raum (15 m²)

Raum (15 m²)

TB III

TB II

Raum (15 m²)

Raum (15 m²)

Calculation of work contentin relation to the SSU Making a Taktschedule

Taktarea 3 Rooms (3xSSU)

Definition Taktarea in Relation to the definedTakttimeTakterea: 3 roomsTakttime: 2,5 days

1 2 3 4 5 6 7 8 9 10

W1PRELIMARESW1EARTHWORKSW2EARTHWORKSW1CONCRETOW2CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ACABADOSW2ACABADOSW3ACABADOSW4ACABADOSCIMENTACIONESCIMENTACIONESTRINCHERASYPITSINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITSFIRMES

W1 ROOF W2 ROOF W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIAW5ACABADOS

W1PANELLWALLW2PANELLWALL W5 ESTRUCTURAMETALICA/MEZANINW6 ESTRUCTURAMETALICA/MEZANIN

W1PRELIMARESW1EARTHWORKSW2EARTHWORKS W1CONCRETOW2CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ACABADOSW2ACABADOSW3ACABADOSCIMENTACIONESCIMENTACIONESTRINCHERASYPITSINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITSFIRMES

W1 ROOF W2 ROOF W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIA

W1PANELLWALLW2PANELLWALL W5 ESTRUCTURAMETALICA/MEZANINEW6 ESTRUCTURAMETALICA/MEZANINE

W1PRELIMARESW1EARTHWORKSW2EARTHWORKSW1CONCRETOW2CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ACABADOSW2ACABADOSW3ACABADOSCIMENTACIONESCIMENTACIONESTRINCHERASYPITSINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITSFIRMES

W1 ROOF W2 ROOF W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIA

W1PANELLWALLW2PANELLWALL W5 ESTRUCTURAMETALICA/MEZANINEW6 ESTRUCTURAMETALICA/MEZANINE

W1PRELIMARESW1EARTHWORKSW2EARTHWORKS W1CONCRETOW2CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ACABADOSW2ACABADOSW3ACABADOSW4ACABADOSCIMENTACIONESCIMENTACIONESTRINCHERASYPITSINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITSFIRMES

W1 ROOF W2 ROOF W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIA

W1PANELLWALLW2PANELLWALL W5 ESTRUCTURAMETALICA/MEZANINEW6 ESTRUCTURAMETALICA/MEZANINE

W1PRELIMARESW1EARTHWORKSW2EARTHWORKSW1CONCRETOW2CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ACABADOSW2ACABADOSW3ACABADOSCIMENTACIONESCIMENTACIONESTRINCHERASYPITSINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITSFIRMES

W1 ROOF W2 ROOF W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIA

W1PANELLWALLW2PANELLWALL W5 ESTRUCTURAMETALICA/MEZANINEW6 ESTRUCTURAMETALICA/MEZANINE

W1PRELIMARESW1EARTHWORKSW2EARTHWORKS W1CONCRETOW2CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ACABADOSW2ACABADOSW3ACABADOSCIMENTACIONESCIMENTACIONESTRINCHERASYPITSINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITSFIRMES

W1 ROOF W2 ROOF W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIA

W1PANELLWALLW2PANELLWALL W5 ESTRUCTURAMETALICA/MEZANINEW6 ESTRUCTURAMETALICA/MEZANINE

W1PRELIMARESW1EARTHWORKSW2EARTHWORKSW1CONCRETOW2CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ACABADOSW2ACABADOSW3ACABADOSCIMENTACIONESCIMENTACIONESTRINCHERASYPITSINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITS FIRMES

W1 ROOF W2 ROOF W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIA

W1PANELLWALLW2PANELLWALL W5 ESTRUCTURAMETALICA/MEZANINEW6 ESTRUCTURAMETALICA/MEZANINE

W1PRELIMARESW1EARTHWORKSW2EARTHWORKS W1CONCRETOW2CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ACABADOSW2ACABADOSW3ACABADOSW4ACABADOSCIMENTACIONESCIMENTACIONESTRINCHERASYPITSINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITSFIRMES

W1 ROOF W2 ROOF W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIA

W1PANELLWALLW2PANELLWALL W5 ESTRUCTURAMETALICA/MEZANINEW6 ESTRUCTURAMETALICA/MEZANINE

W1PRELIMARESW1EARTHWORKSW2EARTHWORKSW1CONCRETOW2CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ACABADOSW2ACABADOSW3ACABADOSCIMENTACIONESCIMENTACIONESTRINCHERASYPITSINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITSFIRMES

W1 ROOF W2 ROOF W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIA

W1PANELLWALLW2PANELLWALL W5 ESTRUCTURAMETALICA/MEZANINEW6 ESTRUCTURAMETALICA/MEZANINE

W1PRELIMARESW1EARTHWORKSW2EARTHWORKS W1CONCRETOW2CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ACABADOSW2ACABADOSW3ACABADOSCIMENTACIONESCIMENTACIONESTRINCHERASYPITSINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITSFIRMES

W1 ROOF W2 ROOF W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIA

W1PANELLWALLW2PANELLWALL W5 ESTRUCTURAMETALICA/MEZANINEW6 ESTRUCTURAMETALICA/MEZANINE

W1PRELIMARESW1EARTHWORKSW2EARTHWORKSW1CONCRETOW2CONCRETOW3CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ALBAÑILERIAW1ACABADOSW3ACABADOSCIMENTACIONESCIMENTACIONESCIMENTACIONESESPECIALESFIRMESYBASEHIDRAULICAINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITSFIRMES

W1 ROOF W2 ROOF W7 MEP W8 MEP W2ACABADOS

W1PANELLWALLW2PANELLWALL W5ACABADOSW6ACABADOS

W1PRELIMARESW1EARTHWORKSW2EARTHWORKSW1CONCRETOW2CONCRETOW3CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ALBAÑILERIAW1ACABADOSW3ACABADOSCIMENTACIONESCIMENTACIONESCIMENTACIONESESPECIALESFIRMESYBASEHIDRAULICAINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITSFIRMES

W1 ROOF W2 ROOF W7 MEP W8 MEP W2ACABADOS

W1PANELLWALLW2PANELLWALL W5ACABADOS

W1PRELIMARESW1EARTHWORKSW2EARTHWORKSW1CONCRETOW2CONCRETOW3CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ALBAÑILERIAW1ACABADOSW3ACABADOSCIMENTACIONESCIMENTACIONESCIMENTACIONESESPECIALESFIRMESYBASEHIDRAULICAINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITSFIRMES

W1 ROOF W2 ROOF W7 MEP W8 MEP W2ACABADOS

W1PANELLWALLW2PANELLWALL W5ACABADOS

W1PRELIMARESW1EARTHWORKSW2EARTHWORKSW1CONCRETOW2CONCRETOW3CONCRETOW1CONCRETOW1 MEP W1STRUCTURALSTEELW2STRUCTURALSTEELW3STRUCTURALSTEELW4STRUCTURALSTEEL W2CONCRETOW3CONCRETOW4CONCRETOW2 MEP W3 MEP W4 MEP W5 MEP W6 MEP W1ALBAÑILERIAW1ACABADOSW3ACABADOSCIMENTACIONESCIMENTACIONESCIMENTACIONESESPECIALESFIRMESYBASEHIDRAULICAINSTSANITYSISTTIERRAS TRINCHERASYPITSTRINCHERASYPITSFIRMES

W1 ROOF W2 ROOF W7 MEP W8 MEP W2ACABADOS

W1PANELLWALLW2PANELLWALL

W1PRELIMARESW1EARTHWORKSW2EARTHWORKSW1CONCRETOW2CONCRETO W1CONCRETOW1 MEP W1STRUCTURALSTEELW3STRUCTURALSTEELW2PANELLWALL W2CONCRETOW4CONCRETOW2 MEP W4 MEP W6 MEP W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIA W1ACABADOSW2ACABADOSW3ACABADOSW4ACABADOSCIMENTACIONESCIMENTACIONESFIRMESYBASEHIDRAULICAINSTSANITYSISTTIERRAS TRINCHERASYPITSFIRMES

W2STRUCTURALSTEELW4STRUCTURALSTEELW1 ROOF W2 ROOF W3CONCRETO W3 MEP W5 MEPTRINCHERASYPITS

W1PANELLWALL

W1PRELIMARESW1EARTHWORKSW2EARTHWORKSW1CONCRETOW2CONCRETO W1CONCRETOW1 MEP W1STRUCTURALSTEELW4STRUCTURALSTEELW2PANELLWALL W2CONCRETOW4CONCRETOW2 MEP W4 MEP W6 MEP W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIA W1ACABADOSCIMENTACIONESCIMENTACIONES FIRMESYBASEHIDRAULICAINSTSANITYSISTTIERRAS TRINCHERASYPITSFIRMES

W2STRUCTURALSTEELW1PANELLWALLW2 ROOF W3CONCRETO W3 MEP W5 MEPTRINCHERASYPITS

W3STRUCTURALSTEELW1 ROOF

W1STRUCTURALSTEELW5STRUCTURALSTEELW6STRUCTURALSTEEL W2 MEP W4 MEP W6 MEP W1ALBAÑILERIAW2ALBAÑILERIA W1ACABADOS

W2STRUCTURALSTEEL W3 MEP W5 MEP

W3STRUCTURALSTEEL

W1PRELIMARESW1EARTHWORKSW2EARTHWORKSW1CONCRETOW2CONCRETO W1CONCRETOW1 MEP W1STRUCTURALSTEELW3STRUCTURALSTEELW1PANELLWALLW2PANELLWALL W4CONCRETO W2 MEP W4 MEP W6 MEP W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIAW4ALBAÑILERIAW1ACABADOSW2ACABADOSCIMENTACIONESCIMENTACIONES FIRMESYBASEHIDRAULICAINSTSANITYSISTTIERRAS FIRMES

W2STRUCTURALSTEELW4STRUCTURALSTEELW1 ROOF W2 ROOF W3 MEP W5 MEP W5ACABADOS

W1PRELIMARESW1EARTHWORKSW2EARTHWORKSW1CONCRETOW2CONCRETO W1CONCRETOW1 MEP W1STRUCTURALSTEELW3STRUCTURALSTEELW1PANELLWALLW2PANELLWALL W4CONCRETO W2 MEP W4 MEP W6 MEP W1ALBAÑILERIAW2ALBAÑILERIACIMENTACIONESCIMENTACIONESFIRMESYBASEHIDRAULICAINSTSANITYSISTTIERRAS FIRMES

W2STRUCTURALSTEELW4STRUCTURALSTEELW1 ROOF W2 ROOF W3 MEP W5 MEP

W5 ESTRUCTURAMETALICA/MEZANINEW6 ESTRUCTURAMETALICA/MEZANINEW4CONCRETOW2 MEP W4 MEP W6 MEP W1ALBAÑILERIAW2ALBAÑILERIAW3ALBAÑILERIAW1ACABADOSW2ACABADOSW4ACABADOSFIRMES

W3 MEP W5 MEP W3ACABADOS

48 49 50 51 5242 43 44 45 46 4736 37 38 39 40 4130 31 32 33 34 3524 25 26 27 28 2918 19 20 21 22 2312 13 14 15 16 176 7 8 9 10 11

17.06.17 24.06.17 01.07.17

4 5

06.05.17 13.05.17 20.05.17 27.05.17 03.06.17 10.06.1725.03.17 01.04.17 08.04.17 15.04.17 22.04.17 29.04.1711.02.17 18.02.17 25.02.17 04.03.17 11.03.17 18.03.1731.12.16 07.01.17 14.01.17 21.01.17 28.01.17 04.02.1719.11.16 26.11.16 03.12.16 10.12.16 17.12.16 24.12.1608.10.16 15.10.16 22.10.16 29.10.16 05.11.16 12.11.1627.08.16 03.09.16 10.09.16 17.09.16 24.09.16 01.10.1626.06.17

30.07.16 06.08.16 13.08.16 20.08.1615.05.17 22.05.17 29.05.17 05.06.17 12.06.17 19.06.1703.04.17 10.04.17 17.04.17 24.04.17 01.05.17 08.05.1720.02.17 27.02.17 06.03.17 13.03.17 20.03.17 27.03.1709.01.17 16.01.17 23.01.17 30.01.17 06.02.17 13.02.1728.11.16 05.12.16 12.12.16 19.12.16 26.12.16 02.01.1717.10.16 24.10.16 31.10.16 07.11.16 14.11.16 21.11.1605.09.16 12.09.16 19.09.16 26.09.16 03.10.16 10.10.1625.07.16 01.08.16 08.08.16 15.08.16 22.08.16 29.08.16

CW30 CW31 CW32 CW33 CW34 CW35 CW36 CW37 CW38 CW39 CW40 CW41 CW42 CW43 CW44 CW45 CW46 CW47 CW48 CW49 CW50 CW51 CW52 CW53 CW54 CW55 CW56 CW57 CW58 CW59 CW60 CW61 CW62 CW63 CW64 CW65 CW66 CW67 CW68 CW69 CW70 CW71 CW72 CW73 CW74 CW75 CW76 CW77 CW78

Page 7: TECHNICAL TAKT PLANNING AND TAKT CONTROL IN CONSTRUCTION · PDF fileTechnical Takt Planning and Takt Control in Construction ... Planning with the Location-based Management System

Marco Binninger, Janosch Dlouhy and Shervin Haghsheno

Figure 6: Takt schedule DGF Fire Station (Authored by the Project Team)

Figure 7: Takt schedule with trains

Takt Time Planning augments the Last Planner System

The three different layers of a Lean approach to construction are stated in Haghsheno et al. (2015) as follows:

• Production Systems

• Collaborative Systems

• Contract Systems The authors conclude that a holistic Lean approach must comprise of all three layers.

Technical systems such as Takt Systems support transparency and stability by using objective data in a holistic Lean system. Furthermore, the borders of collaborative working could be expanded by using data in democratic production systems. Finally, the focus of technical Takt planning and Takt control is value for the customer while the relationship between Takt Time and Takt Areas define the speed of a project's execution.

5 ACKNOWLEDGMENTS The research as described in this paper was completed as part of the PhD studies of Marco Binninger and Janosch Dlouhy at the Karlsruhe Institute of Technology (KIT). By

Train ofTrades

W3 W6 W7W4W1 W2 W5 W8 W9

Dry

Cons

tuct

ion

I

Elec

troI

Heat

ing

IA

erat

ion

I

AC

IDr

y Co

nstr.

II

Dry

Cons

tuct

ion

III

Heat

ing

IIFl

oor S

cree

d

Win

dow

Benc

hPa

inte

rI

Dry

Cons

tr. IV

Elec

troII

(fin

e)HV

AC

(fin

e)

Floo

rer

Pain

ter

II

Door

Leav

esBa

se B

oard

Fine

Cle

anin

g

W3 W6 W7W4W1 W2 W5 W8 W9

Dry

Cons

truct

ion

I

Dry

Cons

tr. III

Floo

rer

Pain

ter

II

W3 W6 W7W4W1 W2 W5 W8 W9

W4 W5W1 W2 W3 W6 W7

Aer

atio

nI

AC

I

Floo

r Scr

eed

Win

dow

Benc

hPa

inte

rI

Dry

Cons

tr. IV

Pain

ter

IIBa

se B

oard

W2 W4 W5W1 W1 W3 W6 W6

Elec

troI

Elec

troI

Heat

ing

IA

erat

ion

I

Heat

ing

IA

erat

ion

IFl

oor S

cree

dLi

nen

Pain

ter

I

Elec

troI

Heat

ing

I

W7 W7Fl

oore

r

Floo

rer

Pain

ter

IIBa

se B

oard

W4 W5

Elec

troII

(fin

e)

W3

Heat

ing

IA

erat

ion

I

Heat

ing

IA

erat

ion

I

Pain

ter

I

Elec

troII

(fin

e)

Elec

troII

(fin

e)

Elec

troII

(fin

e)

W2

Mittermaier / PA-223 Stand 23.09.2014

W3 W6WDW1 W2 W5 W8 W9

Dry

Cons

tr. II

Dry

Cons

tr. III

Pain

erI

Dry

Cons

tr. IV

Pain

ter

II

Door

Leav

es

Showers WD

Sani

tary

WDPa

ver

WD

Sani

tary

(fin

e)

Week 41/1 41/2 42/1 42/2 43/1 43/2 44/1 44/2 45/1 45/2 46/1 46/2 47/1 47/2 48/1 48/2 49/1 49/2 50/1Upper FloorTakt Area 1

RelaxationRooms

Takt Area 2Relaxation Rooms

Takt Area 3Relaxation Rooms

Upper FloorHall

Ground Level

Fine

Cle

anin

gFi

ne C

lean

ing

Fine

Cle

anin

gFi

ne C

lean

ing

Fine

Cle

anin

g

Dry

Cons

tuct

ion

I

Sani

tary

Heat

ing

IIFl

oor S

cree

dHe

atin

gII

Floo

r Scr

eed

Heat

ing

IIFl

oor S

cree

d

Elec

troII

(fin

e)HV

AC

(fin

e)

Elec

troII

(fin

e)HV

AC

(fin

e)

Elec

troII

(fin

e)HV

AC

(fin

e)

Win

dow

Benc

hPa

inte

rI

Dry

Cons

tr. IV

Win

dow

Benc

hPa

inte

rI

Dry

Cons

tr. IV

Dry

Cons

truct

ion

I

Elec

troI

Heat

ing

IA

erat

ion

I

Elec

troI

Heat

ing

IA

erat

ion

I

Elec

troI

Heat

ing

IA

erat

ion

IA

C I

Dry

Cons

tr. II

AC

IDr

y Co

nstr.

II

Dry

Cons

truct

ion

III

Door

Leav

esBa

se B

oard

Floo

rer

Pain

ter

II

Door

Leav

esBa

se B

oard

Elec

troII

(fin

e)HV

AC

(fin

e)

Floo

rer

Page 8: TECHNICAL TAKT PLANNING AND TAKT CONTROL IN CONSTRUCTION · PDF fileTechnical Takt Planning and Takt Control in Construction ... Planning with the Location-based Management System

Technical Takt Planning and Takt Control in Construction

integrating the authors in their Takt projects, the companies weisenburger bau GmbH and BMW AG made collecting the required data possible.

6 REFERENCES

Binninger, M., Dlouhy, J., Oprach, S. and Haghsheno S. (2016): Methods for Production Leveling – Transfer from Lean Production to Lean Contruction. In: Proc. 24th Ann. Conf. of the Int’l. Group for Lean Construction, Boston, MA, USA, sect.6 pp. 53–62.

Dlouhy, J., Binninger, M., Oprach, S. and Haghsheno, S. (2016): Three-level Method of Takt Planning and Takt Control – A New Approach For Designing Production System in Construction. In: Proc. 24th Ann. Conf. of the Int’l. Group for Lean Construction, Boston, MA, USA, sect.2 pp. 13–22.

Frandson, A.G., Seppänen, O., and Tommelein, I.D., (2015): Comparison between location based management and Takt Time Planning. In: Proc. 23rd Ann. Conf. of the Int’l. Group for Lean Construction, 28-31 July, Perth, Australia, pp. 3-12

Friedrich, T.; Meijnen, P.; Schriewersmann, F. (2013): Lean Construction – die Übertragung der Erfolgsmodelle aus der Automobilindustrie (Transformation of successful approaches of the automotive sector). 1. Aufl. Hg. v. Porsche Consulting GmbH: Ernst & Sohn GmbH & Co. KG.

Gaillard, H. (1974): Das Takt-Schiebe-Verfahren. TIEFBAU BERUFSGENOSSENSCHAFT, 86(8).

Gehbauer, F. (2007): Was bedeutet Lean Construction? Lean Praxis Tag, 23.01.2007. Haghsheno, S.; Binninger, M.; Dlouhy, J.; (2015): Wertschöpfungsorientierte Planung und

Realisierung von Bauvorhaben durch Lean Construction. Jahresausgabe 2015/1016. III - 13. Hg. v. VDI - Bautechnik.

Haghsheno, S.; Binninger, M.; Dlouhy, J.; Oprach, S. (2016): History and theoretical Foundations of Takt Planning and Takt Control. In: 24th Annual Conference of the International Group for Lean Construction. Boston, USA, 20-22 Jul 2016.

Heinonen, A., and Seppänen, O. (2016): Takt Time Planning: Lessons for Construction Industry from a Cruise Ship Cabin Refurbishment Case Study. In: Proc. 24th Ann. Conf. of the Int’l. Group for Lean Construction, Boston, MA, USA, sect.2 pp. 23–32.

Kaiser, J. & Zikas, T. (2009): Lean Management im Straßen-und Tiefbau. BauPortal, 121(5). Kaiser, J. (2013): Lean Process Management in der operativen Bauabwicklung. p. 68 Peters, R. (2009): Shopfloor Management – Führen am Ort der Wertschöpfung (leadership

on the shopfloor) LOG_X Verlag, Stuttgart. ISBN 978-3-932298-39-4, S. 27; S.41 Schub, A. (1970): Probleme der Taktplanung in der Bauproduktion (problems of takt

planning in construction). Bauverlag Tommelein, I.D. (2017): Collaborative Takt Time Planning of Non-Repetitive Work. In: