Technical Support 2008 1 9/26/08 PHENIX WEEKLY PLANNING 10/2/2008 Don Lynch.
Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.
-
Upload
brenda-winifred-oconnor -
Category
Documents
-
view
214 -
download
2
Transcript of Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.
![Page 1: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/1.jpg)
1
Tech
nica
l Support 2
00
8
9/4/08
PHENIX PHENIX WEEKLY PLANNINGWEEKLY PLANNING
9/4/2008 9/4/2008
Don LynchDon Lynch
![Page 2: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/2.jpg)
2
Tech
nica
l Support 2
00
8
9/4/08
Shutdown ’08 Schedule
RPC Factory: Dark Current test stand in design due 9/30
Mu Trigger FEE upgrade:Rack assembly installed in North by, South by 9/30N&S platforms Fabricate & install install South by 9/30 (Pearson)Rebuild Bridge & Eyebrow DonePrep work for platforms (water/elec) water done, elec. By 9/5FEE Chasis installation N&S sta’s. 1,2&3 Station 1 & 2N Done, Sta 3N
by 9/15,Sta. 1,2 & 3S by 10/31
FEE water and dry air installation Station 2N Done, Station 1N by 9/15, Station 3N by 9/30, Sta. 1,2&3S by
11/15Install Elec cards Starting 9/15: sta 1N by 9/30, sta 2 N
by 10/15, sta 3N by 10/31, S by 11/15Install S rack cooling & electric Oct.after CM moves northRack room electronics, etc. Sep.– Oct.Disassemble station1 scaffold complete by Oct 15 Testing Sep.-Nov. Complete by 11/30
![Page 3: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/3.jpg)
3
Tech
nica
l Support 2
00
8
9/4/08
Shutdown ’08 Schedule
RPC external review Sep. 25RPC proptotype installation: Prep work wait for final installation design
move (7) MuID pipes move gap 5 south cable tray
Rack prep In progress complete by Sep 30RPC prototype gas system In progress complete by Sep 30Move shielding for installation July - Sep [Pearson]RPC prototype cable routing & support Aug - Sep Modify crystal palace & vapor barrier July – Sep [Pearson] RPC prototype install
(RPC2 – PHENIX) Sep. – Oct.(RPC3 – C. Pearson) Sep. - Oct.
Install rack in tunnel south Install by 10/15 Replace tunnel shielding/Vapor Barrier Nov. [Pearson] Connect electronics/gas Sep. – Nov.
MuTr Decapacitations (Sta. 1&2 S) Mike Leitch will be back 9/8/08Decaps to be performed as sched permits
Fan Tray maintenance in progress (on going fill-in)PC1 west work (needs planning) Oct. 15
![Page 4: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/4.jpg)
4
Tech
nica
l Support 2
00
8
9/4/08
Shutdown ’08 Schedule, cont’d
CM Crane Install [postponed indefinitely?]HBD Install Oct. 27?DC East?/West Repairs Nov. 15Remove all inst’n equipment
Sta 1 (from south) Remove by 1/15Sta 2/3 scaffolds Remove by 11/15all other testing equipment Remove by 12/1
Prep for shutdown 2009 Gap 5 N piping and cable tray re-loc. Oct. - DecGap 2 N cable tray & crate re-mounts Oct. – Dec.
Prep for run 9Begin run 9 Prep 12/1/09Install all lampshades Complete by 11/26 Roll in EC 12/22Pink/White/Blue sheets 12/29Close shield wall 12/31
Cryo Start up 1/1/09Flammable Gas/start shifts 1/11/09Start physics 1/18/09End Run 9 6/30/09
![Page 5: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/5.jpg)
5
Tech
nica
l Support 2
00
8
9/4/08
Shutdown ’08 Schedule, cont’d
Other Work
VTX prototype design support Support review 9/11 w/Walt
NCC prototype design support In progress finish in Sep
HBD support as requiredVTX fabrication tooling design Sep – OctVTX installation design Oct - NovFVTX design/engineering support as required
![Page 6: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/6.jpg)
6
Tech
nica
l Support 2
00
8
9/4/08
1) Run Power to new MuTrgr FEE racks on MMN and MMS 2) Install power feeds to RPC north & south tunnel racks from IR power panels.
3) Install new UPS in Gas mixing house. 4) Install power and signal cable tray (ceiling suspended) for new DCM rack row – north
of existing DCM racks.
5) Assist in signal and LV cable installation for MuTr/RPC upgrades as necessary.
6) Upgrade power capacity of Central Magnet power distribution for future bridge rack loads. a) Remove existing 15KVA transformer and install 45KVA unit. b) Install new (larger size) power cable from rack room to Central Magnet distribution breaker panels.
7) Install 120 volt AC power drops into new control room annunciator alarm rack (rack room).
Shutdown ’08 Electrician Work
![Page 7: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/7.jpg)
7
Tech
nica
l Support 2
00
8
9/4/08
New FEE Platforms & Modified Bridge Parts
Eyebrow reinstalledBridge modifications are complete
Need to modify cable tray and water manifolds
![Page 8: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/8.jpg)
8
Tech
nica
l Support 2
00
8
9/4/08
MuTrgr FEESouth Rack
Ready to be installed
![Page 9: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/9.jpg)
9
Tech
nica
l Support 2
00
8
9/4/08
MuTrigger FEE Rack Utilities
![Page 10: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/10.jpg)
10
Tech
nica
l Support 2
00
8
9/4/08
MuTrigger FEE Installation
Station 2 Cooling water and dry air is done
![Page 11: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/11.jpg)
11
Tech
nica
l Support 2
00
8
9/4/08
Station 1N all chasis installed, cooling water and dry air installation is in progress
MuTrigger FEE Installation
![Page 12: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/12.jpg)
2008/9/4 13
Production status of ADTX board• Mass production is ongoing.• First 20 boards arrived at RIKEN
– QA being done– Will be shipped on Sep 11th.– Start installation from the week of Sep 22
• Need total 40 boards to cover whole station 1• Latest mass production schedule:
13
ST1 scaffold removal
All prep and testing has to be finished by then
MuTr FEE upgrade status2008/9/4
![Page 13: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/13.jpg)
2008/9/4 14
Chassis Status• Chassis Mount :
– Completed mounting chassis to Station-1 Bottom Octant (Carter)
– Waiting for balcony to access Station-3 Top Octant.
– All other chassis were mounted.
• Water plumbing :– John T + Mike Lenz + Carter
+ Yuta Sada (support)– Working on station 1– All MuTr.N power locked
out during plumbing work.
14MuTr FEE upgrade status2008/9/4
![Page 14: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/14.jpg)
2008/9/4 15
ADTX-FEE signal cable• Managed to run MuTr
calibration• Started connecting FEE-
ADTX cable and noise measurement
• Completed station 2 octant 7
• Remote assistance from Mike Leitch.
• Plan to try station 3 bottom octant today, and station 1 next.
• Mike will assist us next week.
15MuTr FEE upgrade status2008/9/4
![Page 15: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/15.jpg)
2008/9/4 16
LV status• Working on cut and connect LV cables to the rack
(Frank, Itaru, Yuta)– LV cable length was too short for top three octants
(station 2 and 3) Plan to put extension.• Power supply to the rack (by next Tuesday)• LV distributor’s front panels (next Tuesday)• LV control.• Voltage tuning at the distributors.
16MuTr FEE upgrade status2008/9/4
![Page 16: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/16.jpg)
2008/9/4 17
Optical Cable
• Completed running five more trunk cables from rack room to IR (Paul, Itaru)
• What needs to be done– Signal transmission test for new cables (scheduled next
week )– BCLK distribution chain test (GTM-GFO-GBO-OFO)
17MuTr FEE upgrade status2008/9/4
![Page 17: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/17.jpg)
18
Tech
nica
l Support 2
00
8
9/4/08
MuTrigger FEE upgrades in MMS in support of RPC prototypes
Design effort and material ordering are in progress
![Page 18: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/18.jpg)
19
Tech
nica
l Support 2
00
8
9/4/08
MuTr Decapacitations
MuTr group needs this setup from last year to work on decapacitations in the south magnet
![Page 19: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/19.jpg)
20
Tech
nica
l Support 2
00
8
9/4/08
RPC2 Prototype Installation, cont’d
![Page 20: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/20.jpg)
21
Tech
nica
l Support 2
00
8
9/4/08
RPC Absorber Concept
RFQ placed with CS
![Page 21: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/21.jpg)
22
Tech
nica
l Support 2
00
8
9/4/08
Detector upgrade Rack allotments
New Platform
HBD/RXNP(not shown)
MuTrgrFEE N
MuTrgrFEE S
VTX Power
FVTX NCC N
NCC S
RPC1 S
RPC1 N
New Platform
RPC1 NS
VTX FEM
No Changes
![Page 22: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/22.jpg)
23
Tech
nica
l Support 2
00
8
9/4/08
Rack Room Reorganization
Inventor model in progress
![Page 23: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/23.jpg)
24
Tech
nica
l Support 2
00
8
9/4/08
Safety, Security, etc.
SF6: The dangers of inhaling it
![Page 24: Technical Support 2008 1 9/4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f335503460f94c50340/html5/thumbnails/24.jpg)
25
Tech
nica
l Support 2
00
8
9/4/08
Where To Find PHENIX Engineering
Info
Links for the weekly planning meeting slides, long term planning, pictures, videos and other technical info can be found on the web site:
http://www.phenix.bnl.gov/WWW/INTEGRATION/ME&Integration/DRL_SSint-page.htm
Now that summer is about over, we can get back to what’s important