Bid Evaluation Procedure and Criteria
1. Evaluation Procedure
Bids will be evaluated through the following four steps:
Step-1: General Evaluation
Step-2: Technical Evaluation
Step-3: Financial and Commercial Evaluation
Step-4: Ranking of Bids
The Step-1: General Evaluation will consist in checking the bids to confirm their
compliance with the requirements of the Bid Documents in the following aspects:
a) Eligibility of Bidders;
b) Eligibility of proposed equipment, goods and services;
c) Completeness and responsiveness of bids; andThe above-mentioned factors will be evaluated on a Pass or Fail basis. Any bids that fail
to meet any of the requirements detailed in Sub-sections 3.1 to 3.4 will be eliminated from
further evaluation.
In Step-2, the technical appropriateness and viability of the bids will be evaluated based on
the following 5 major criteria, using a scoring system as detailed in Sub-sections 4.1 to 4.4:
1. Survey and Design Requirements
2. Equipment and Materials Supply Requirements
3. Construction and Installation Requirements
4. Organization and Staffing Requirements
5. Maintenance RequirementsIn Step-3, the financial and commercial aspects of bids will be examined as detailed in
Sub-sections 5.1 to 5.3 to ascertain the reasonability, balance and correct calculation of bid
prices.
Finally in Step-4, all the bids that pass the above evaluation steps will be ranked in order of
the evaluated bid amount, and recommended for contract award.
2. CLARIFICATION OF BIDS
In the course of bid evaluation, the Employer or the Employers Representative may request
the Bidders to clarify the contents of their bid including unbalance in currencies in pricing.
The clarification of bid shall only be made between the Employer and the Bidder with bid to
be clarified, either directly (the Employer will invite the Bidder to a face-to-face meeting, in
which the questions and answers shall be in writing) or indirectly (the Employer will send awritten request for clarification and the Bidder shall answer in writing). The deadline for the
Bidders clarification will be stated in the written request for clarification. The contents of
bid clarification in writing will be kept by the Employer as a part of the bid. After the
deadline for clarification, if the Bidder fails to reply or the Employer does not receive the
written clarification, or if the Bidder has submitted the clarification in writing but it fails to
meet the request of the Employer, the Employer will consider and handle in accordance with
the current provisions of law.
The clarification of bid shall not change the essential contents of the submitted bid and the
bid price.
3. GENERAL EVALUATION
3.1 Eligibility of BiddersAll bids will be checked first to make sure that:
-
7/30/2019 Technical Evaluation UG-F(1)
2/15
i) all the partners of the Bidders are those who have been prequalified or satisfied the
conditions described in Article 4 of Section I Instructions to Bidders;
ii) all the partners and subcontractors of the Bidders have not been directly engaged in, or
associated/affiliated with firms who have been engaged in the consulting services for
the Project, and do not provide personnel to firms who are engaged in the said services.
Any bids that fail to satisfy any of the above-mentioned conditions will be rejected.3.2 Eligibility of Equipment, Goods and Services
Bids will be checked to ensure that the cost of the equipment, goods and services proposed
to be procured from Japan for the Project is not less than 36% of the total cost of such
equipment, goods and services.
Any bids in which the total cost of the equipment, goods and services proposed to be
procured from countries other than Japan exceeds 64% shall be rejected.
3.3 Completeness and Responsiveness of Bids
Completeness and responsiveness of bids will be assessed according to the following major
criteria, and any bids that do not conform to any of the said criteria may be considered as
non responsive, and eliminated from further evaluation.
No. Evaluation Criteria
1. The bid is valid and submitted in the required number of originals and copies
2. All the Bid Forms and Documents are completely filled and valid
3. All pages of the Bid Forms are signed by the Bidders authorized representative
4. Bid validity period is 180 days
5. Joint Venture Agreement with valid powers of attorney from the respective partners is
provided
6. Bid Guarantee conforming to the requirements on validity period, value and
appropriateness is provided
7. Completely priced Cost Centres for the whole of the Works are provided
8. Updated information since prequalification as required by the Bid Documents is provided.
The information shall show the way the Bidder complies with the condition on personnel
replacement as instructed in the GCs letter of notification of prequalification results
9. The Bidders name is included in the list of purchasers of Bid Documents or meet the
requirements specified in Clause 2, Article 28 of Decree 85/2009/N-CP
10. The Bidder meets the eligibility requirement as an organization or an individual as
stipulated in Articles 7 and 8 of the Law on Biding (No.61/2005/QH11)
11. The total bid price is fixed and without conditions
12. The Bidder does not participate in 2 or more bids as prime contractor
13. The Bidder satisfies the capability requirement as stipulated in Article 7 of the Law on
Construction (No.16-2003-QH11)
14. The Bidder does not violate one of the prohibited acts on biding as defined in Article 12 of
the Law on Biding
-
7/30/2019 Technical Evaluation UG-F(1)
3/15
4. TECHNICAL EVALUATION
4.1 Procedure for Technical Evaluation
The technical evaluation will be made based on 5 major evaluation criteria with their
corresponding score on a scale of 1,000 points as summarized below:
Evaluation Criteria Full Mark
1 Survey and Design Requirements 250
2 Equipment and Materials Supply Requirements 150
3 Construction and Installation Requirements 250
4 Organization and Staffing Requirements 200
5 Training 100
6 Maintenance Support Requirements 50
Total 1,000
Points will be given in accordance with the scoring system detailed in Sub-section 4.2. The
bids which get a total score of at least 800 points and a minimum of 70% of the full mark
assigned for each of the above 6 major evaluation criteria will be accepted from the
technical viewpoint and brought to the next step of evaluation.
4.2 Detailed Scoring System
Each of the 6 major evaluation criteria will be divided into several items and each item will
be further divided into several sub-items to ensure in-depth and accurate assessment of the
conditions pertaining to each criteria.
Points will be given to each sub-item according to a predetermined score as shown in the
table below and based on the level of its responsiveness in percentage to the corresponding
requirements.
No. Evaluation ItemsMin/Max
Score
Maximum Score
Stations TunnelsM&E
Works
1Survey and Design Requirements and Design
Programme175/250
1.1 Design Work Programme /125.0 70.0 37.0 18.0
-Contents of Design WorkProgramme: covering all survey and
design works
/20.0 11.0 6.0 3.0
-
Adequacy of Design Programme
components including technical
issues on survey, design, analysis,
evaluation of options, measures of
coordination and risk prevention,
interfacing with adjacent contractors
/30.0 17.0 9.0 4.0
- Quality Assurance Plan for Design /30.0 17.0 9.0 4.0
- Design period of each majorcomponent
/20.0 11.0 6.0 3.0
-
7/30/2019 Technical Evaluation UG-F(1)
4/15
No. Evaluation ItemsMin/Max
Score
Maximum Score
Stations TunnelsM&E
Works
- Design sequence and correlationamong design work items including
design interface
/25.0 14.0 7.0 4.0
1.2 Technical solutions proposed in the design /125.0 58.0 32.0 35.0
1.2.1
Proposed technological solution:
state-of-the-art, Conformity with
technical requirements of the
system
/62.5 /30.0 /16.0 /16.5
-
Conformity with technical design
requirements of the Employer's
Requirements
/12.5 7.0 4.0 1.5
-Conformity with design Standards
and design Specifications/12.5 7.0 4.0 1.5
-
The design is proven to be adequate
in countries with weather and
climatic conditions similar to
Vietnam,
/10.0 6.0 3.0 1.0
- Backup capacity of the system, if any /10.0 10.0
- Uniqueness of the design solutions /10.0 6.0 3.0 1.0
- Having a plan to transfer technicalstandards to be applied to the Project
/7.5 4.0 2.0 1.5
1.2.2 Design Quality and Safety /62.5 /28.0 /16.0 /18.5
-
Appropriateness of studies, analyses
and data to support the selected
configuration
/12.5 7.0 4.0 1.5
- Reliability and Durability /12.5 7.0 4.0 1.5
- Safety Standards and Regulations /12.5 7.0 4.0 1.5
-Proper arrangement of equipment in
subsystems and the entire system,/12.5 12.5
-Design Conditions for Fire detection
system and Evacuation Plan/12.5 7.0 4.0 1.5
2 Equipment and Materials Supply Requirements 105/150
2.1 Scope of supply: /15.0 15.0
-
Meeting the quality and capacity as
per requirements in the Bid
Documents
/3.0 3.0
-Meeting the backup materials and
equipment as per Bid Documents
/6.0 6.0
-
7/30/2019 Technical Evaluation UG-F(1)
5/15
No. Evaluation ItemsMin/Max
Score
Maximum Score
Stations TunnelsM&E
Works
- Meeting the requirements formaintenance facilities, equipment and
tools
/6.0 6.0
2.2
Meeting technical requirements (nature,
specification parameters, standards of
production) by the Bid Documents
/15.0 15.0
- Reliability and safety of product /3.0 3.0
-Meeting standards of power supply
and electrical insulation/6.0 6.0
-
Complying with compulsory
requirements for environment,mechanic, material components,
yard, safety of office etc. as stated in
the Specifications of Bid Documents
/6.0 6.0
2.3 Local Conditions /15.0 15.0
-
The proposed equipment is proven to
be adequate in countries with weather
and climatic conditions similar to
Vietnam,
/15.0 15.0
2.4. Product Quality /30.0 30.0
-Clear origin to meet theRequirements in Bid Documents
/6.0 6.0
-Approvals/certificates of equipment
of the system/12.0 12.0
- Recognized technical standards /6.0 6.0
-Not violating intellectual property,
industrial property/6.0 6.0
2.5.Organization method of supplying
products/30.0 30.0
- Detailed options and logical supplyplan
/12.0 12.0
-
Organization method of supplying
(including yard preparation,
checking, inspection and custom
clearance plan, etc.): evaluation based
on the following criteria: logic,
convenience, sufficiency and
progress assurance.
/12.0 12.0
-
Logic and possibility of shipping
method, storage arrangement and
delivery
/6.0 6.0
-
7/30/2019 Technical Evaluation UG-F(1)
6/15
No. Evaluation ItemsMin/Max
Score
Maximum Score
Stations TunnelsM&E
Works
2.6.Requirements for technical documentsand manuals of use with plan of
transferring materials as requested by Bid
Document
/30.0 30.0
-Technical specifications of materials,
equipment and system/12.0 12.0
-Drawings, layout, manuals for
operation and maintenance process/12.0 12.0
- Hardware and software development /6.0 6.0
2.7Requirements for standby equipment and
materials/7.5 7.5
-List of standby materials and
equipment as per Bid Documents/4.5 4.5
-
Available supply of standby material
and equipment after maintenance
period.
/3.0 3.0
2.8.
Requirements for Inspection and Testing
with inspection and testing plan for
material, equipment and system
/7.5 7.5
- At manufacture location /4.5 4.5
- On site /3.0 3.0
3 Construction and Installation Requirements 175/250
3.1. Construction Programme /25.0 13.0 8.0 4.0
-Presentation of Construction
Programme/6.0 3.0 2.0 1.0
-Construction period of each Work
item: appropriateness/7.0 4.0 2.0 1.0
-Construction Sequence and
correlation among work items
/6.0 3.0 2.0 1.0
-Identification of Critical Path
Activities/4.0 2.0 1.0 1.0
-Conformity with Contractual Key
Dates/2.0 1.0 1.0 0.0
3.2.
Appropriateness of construction
techniques and construction methods for
each component
/50.0 30.0 14.0 6.0
-Detailed construction techniques for
each component/20.0 12.0 6.0 2.0
- Feasibility and flexibility of
construction methods & installation
/19.0 12.0 5.0 2.0
-
7/30/2019 Technical Evaluation UG-F(1)
7/15
No. Evaluation ItemsMin/Max
Score
Maximum Score
Stations TunnelsM&E
Works
techniques
-Compliance with the requirements
for the Construction Specifications/11.0 6.0 3.0 2.0
3.3.Adequacy of Environmental and Safety
Plans/25.0
- Adequacy of Environmental Plan /15.0
- Adequacy of Safety Plan /10.0
3.4. Construction Equipment and Plants /50.0 29.0 14.0 7.0
- Type of Equipment /15.0 9.0 4.0 2.0
- Number of Equipment /10.0 6.0 2.0 2.0
- Capacity of Equipment /5.0 2.0 2.0 1.0
- Age of Equipment /20.0 12.0 6.0 2.0
3.5
Traffic Management and Temporary
Facilities including Land Utilization
during Construction
/50.0 30.0 14.0 6.0
- Traffic Management Plan /30.0 18.0 8.0 4.0
-Temporary Facilities including Land
Utilization
/20.0 12.0 6.0 2.0
3.6.Quality Assurance Plan during
Construction/50.0 29.0 14.0 7.0
4. Organization and Staffing 140/200
4.1 Organization during Design Stage /30.0 17.0 9.0 4.0
4.2 Organization during Construction Stage /30.0 17.0 9.0 4.0
4.3Evaluation of manpower and manpower
mobilization plan/20.0 11.0 6.0 3.0
-
Personnel and labour for construction
and installation works /20.0 11.0 6.0 3.0
4.4Compliance with key personnel
requirements/120.0
- Project Manager /42.0
- Tunnel Manager /13.0
- Senior E&M Manager /13.0
- Tunnel Foreman
- Tunnel Shaft Manager
- Design Manager
-
7/30/2019 Technical Evaluation UG-F(1)
8/15
No. Evaluation ItemsMin/Max
Score
Maximum Score
Stations TunnelsM&E
Works
- Superintendent /13.05 Training 70/100
5.1Plan, organisation and methodology for
training50 5.0 5.0 40.0
5.2Number of technical staff available for the
services20 2.0 2.0 16.0
5.3
Plan to supply equipments, spare parts
and consumable parts to be necessary for
training work
30 3.0 3.0 24.0
6 Maintenance Support Requirements 35/ 50
Proposed Maintenance Plan 50 6.5 6.5 37.0
-
Proposed approach to 2-year
maintenance for TVF and ECS in
stations and provision of Supervisory
team for 5 years
/23.5 2.5 2.5 18.5
-Number of technical staff available
for the services/10.5 1.5 1.5 7.5
-
Major facilities available for the
services /5.5 1.0 1.0 3.5
-Spare parts arrangement (available
stock, delivery time, etc.)/10.5 1.5 1.5 7.5
1) Training and Transfer of Knowledge/Skills for the Environmental Control System for
Underground Stations and Tunnel categorizes as Type-A
The Contractor shall perform all necessary training and transfer knowledge/skills to the personnel
OMC maintenance team prior to the date for completion of the Works. Please refer to
Section 2.4 above.
2) Training and Transfer of Knowledge/Skills for Other Structures, Equipment and Plant
categorized as Type-B
The Contractor shall perform all necessary training and transfer knowledge/skills to the OMC
personnel and/or maintenance team prior to the date for completion of the Works
4.3 Levels of Responsiveness Applied for Point Allocation
Points will be allocated to each evaluation sub-item in accordance with the level of
responsiveness in percentage as mentioned below:
Evaluation Items Point
Allocation
1. Survey and Design Requirements and Design Programme
-
7/30/2019 Technical Evaluation UG-F(1)
9/15
Evaluation Items Point
Allocation
1.1 Design Work Programme
- Good 100%
- Fairly Good 80%
- Acceptable 70%
- Not acceptable 0%
1.2. Technical solutions proposed in the design
1.2.1 Proposed technological solution: state-of-the-art, Conformity with
technical requirements of the system
- Excellent 100%
- Acceptable 80%
- Not acceptable 0%
1.2.2 Design Quality and Safety
- Excellent 100%
- Acceptable 80%
- Not acceptable 0%
2. Equipment and Materials Supply Requirements
2.1 Scope of supply
- Excellent 100%
- Acceptable 80%
- Not acceptable 0%
2.2 Meeting technical requirements (nature, specification parameters,
standards of production) by the Bid Documents
- Excellent 100%
- Acceptable 80%
- Not acceptable 0%
2.3 Local Conditions
- Excellent 100%
- Acceptable 80%
- Not acceptable 0%
2.4 Product Quality
- Good 100%
- Fairly Good 80%
- Acceptable 70%
- Not acceptable 0%
2.5 Organization method of supplying products
-
7/30/2019 Technical Evaluation UG-F(1)
10/15
Evaluation Items Point
Allocation
- Good 100%
- Fairly Good 80%
- Acceptable 70%
- Not acceptable 0%
2.6 Requirements for technical documents and manuals of use with
plan of transferring materials as requested by Bid Document
- Excellent 100%
- Acceptable 80%
- Not acceptable 0%
2.7 Requirements for standby equipment and materials
- Excellent 100%
- Acceptable 80%
- Not acceptable 0%
2.8 Requirements for Inspection and Testing with inspection and
testing plan for material, equipment and system
- Excellent 100%
- Acceptable 80%
- Not acceptable 0%
3. Construction and Installation Requirements
3.1 Construction Programme
- Good 100%
- Fairly Good 80%
- Acceptable 70%
- Not acceptable 0%
3.2 Appropriateness of construction techniques and construction
methods for each component
- Excellent 100%
- Acceptable 80%
- Not acceptable 0%
3.3 Adequacy of Environmental and Safety Plans
- Excellent 100%
- Acceptable 80%
- Not acceptable 0%
3.4 Construction Equipment and Plants
- Type, number and capacity of equipment
-
7/30/2019 Technical Evaluation UG-F(1)
11/15
Evaluation Items Point
Allocation
- Good 100%
- Fairly Good 80%
- Acceptable 70%
- Not acceptable 0%
- Age of equipment
- Less than 3 years 100%
- 3 - < 6 years 80%
- 6 -
-
7/30/2019 Technical Evaluation UG-F(1)
12/15
Evaluation Items Point
Allocation
Tunnel Foreman, Tunnel Shaft Manager
- Qualification which designates the specialty of each position,
and- Qualification of Civil Engineer with University Degree
100%
- Qualification of Civil Engineer with University Degree 70%
- No indication 0%
b) Design Manager and Superintendent:
- Qualification which designates the specialty of each position,
and
- Qualification of Architect or Civil Engineer with University
Degree
100%
- Qualification of Architect or Civil Engineer withUniversity Degree
70%
- No indication 0%
- Experience (70% of Score)
a) Project Manager
- Total years of experience: 15 years or more, and 100%
- Experience in similar works: 10 years or more, and
- Insufficiency in any of above 2 items 0%
a) Tunnel Manager, Senior E&M Manager, Tunnel Foreman,
Tunnel Shaft Manager
- Total years of experience: 12 years or more, and 100%
- Experience in similar works: 7 years or more, and
- Insufficiency in any of above 2 items 0%
b) Deputy Project Manager, Tunnel Manager, M&E Manager
- Total years of experience: 10 years or more, and 100%- Experience in similar works: 7 years or more, and
- Insufficiency in any of above 2 items 0%
5. Training
5.1 Plan, organisation and methodology for training
- Good 100%
- Fairly Good 80%
- Acceptable 70%
-
7/30/2019 Technical Evaluation UG-F(1)
13/15
Evaluation Items Point
Allocation
- Not acceptable 0%
5.2 Number of technical staff available for the service
- Good 100%
- Fairly Good 80%
- Acceptable 70%
- Not acceptable 0%
5.3 Plan to supply equipments, spare parts and consumable parts to be
necessary for training work
- Good 100%
- Fairly Good 80%
- Acceptable 70%
- Not acceptable 0%
6. Maintenance Support Requirements
Proposed Maintenance Plan
- Good 100%
- Fairly Good 80%
- Acceptable 70%
- Not acceptable 0%
4.4 Evaluation Process
The bid evaluation process will be conducted by the General Consultants Bid Evaluation
Committee. Although the scoring system and levels of responsiveness have been
established, there may be discrepancies in the individually scored results. Thus, in order to
ensure best evaluation accuracy and fairness, the scores given by each evaluator will be
cross-checked by another evaluators under the guidance of the Bid Evaluation Committee.
5. FINANCIAL AND COMMERCIAL EVALUATION
Financial and commercial evaluation will be made for the bids which have been retained
through the evaluation of completeness and validity, and technical evaluation in Steps 1and 2 above. The evaluation will be based on the following elements:
5.1 Correction of Errors and Adjustment of Differences
The priced Cost Centres will be checked to find any arithmetical errors in computation and
summation or differences in pricing.
The international unit system, where , (comma) is put before hundreds and thousands
and . (period) before decimals, will be used in checking the amounts in figures, and the
errors shall be corrected appropriately.
If no price is entered for any Milestone Item of a Cost Centre proposed by the Bidders, the
price of that Milestone Item will be deemed as included in the total amount of the
corresponding Cost Centre. Likewise, if any Milestone Item is omitted, it will be deemed
as included in other Milestone Items.
If there is discrepancy between the contents of the Technical Proposal and the Financial
-
7/30/2019 Technical Evaluation UG-F(1)
14/15
Proposal, the contents of the Technical Proposal will prevail.
The errors and/or differences will be corrected and adjusted in the following manner:
a) Where there is a discrepancy between the amounts in figures and in words, the amount
in words will govern; and
b) Where there is a discrepancy between the total amount of a Cost Centre and the actual
sum of all the milestone items in that Cost Centre, the amounts of the milestone itemswill prevail and the total amount of that Cost Centre will be corrected accordingly.
Where there is a discrepancy between the fixed lump sum price entered in the Bid
Total of the Letter of Bid and the actual sum of amounts of all the Cost Centres, the
amounts of the Cost Centres will prevail and the fixed lump sum price will be
corrected accordingly.
The Employer will inform in writing the Bidder of the correction of errors in his Bid in
accordance with the above-mentioned method, and the Bidder shall inform in writing the
Employer of his acceptance of such correction. If the Bidder doest not accept the
correction, his bid will be rejected and his Bid Security will be forfeited in accordance with
Item C20.5 of the Instructions to Bidders.
5.2 Conversion to Single Currency for Comparison of BidsBids will be compared in Japanese Yen only. This will be achieved by converting the Local
Currency portion into Japanese Yen at the Selling Rate of Exchange prevailing on the date
28 days prior to the date of bid submission (Base Date), as published by Gazette of
Ministry of Finance, and then adding the same to the Japanese Yen portion of the Bid.
5.3 Evaluated Bid Price
The evaluated bid price will be determined after correction of errors, adjustment of
differences, conversion of the bid price to a common currency to create an equal basis for
evaluation.
The procedure and factors to be considered in determining the evaluated bid price are as
summarized in the following table:
No. Content Determination Basis
1. Proposed Bid Price Letter of Bid
2. Correction of errors and adjustment of
differences
According to Item 5.1 above
3. Bid Price after Correction & Adjustment Value after Item 5.1
4. Conversion to a single currency According to Item 5.2
5. Evaluation bid price Value of bid price determined
after the above steps
In the case where exceptional situations occur in the biding process, such situations shall be
settled in accordance with the provisions of Article 70 of Decree No.85/2009/ND-CP of
October 15, 2009 or any amendment thereto.
6. RANKING OF BIDS
Based on the results of evaluation and analysis through the successive Step 1: General
Evaluation; Step 2: Technical Evaluation; and Step 3: Financial and Commercial
Evaluation described above, the bids will be ranked in order of evaluated bid amount with
the following details:
-
7/30/2019 Technical Evaluation UG-F(1)
15/15
Ranking Bidders Name Evaluated Bid Amount
1st (1st Lowest)
2nd (2nd Lowest)
3rd (3rd Lowest)
The bid which has the lowest evaluated bid price (1st Ranking) will be recommended to be
the successful bid.