Technical Assistance Consultant’s Report...enrolled in the school system. This means the safety of...
Transcript of Technical Assistance Consultant’s Report...enrolled in the school system. This means the safety of...
Technical Assistance Consultant’s Report
This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents.
Project Number: 35174-082 April 2017
Nepal: School Sector Program Financed by the TA: 7935
Prepared by:
Naveed Anwar
Bangkok, Thailand
For Ministry of Education Department of Education
Capacity Development for School Sector Program Implementation (TA 7935 NEP)
Government of Nepal, Ministry of Education Department of Education
Executive Summary
Submitted to
Asian Development Bank
Nepal Resident Mission
June 2014
Strategy and Plan for Increasing
Disaster Resilience for
Schools in Nepal
Capacity Development for School Sector
Program Implementation (TA 7935 NEP)
Contract Number: 106698-S79855
Strategy for Increasing Disaster
Resilience for Schools in Nepal
Executive Summary
Submitted to
Asian Development Bank
June 2014
Strategy for Increasing Disaster Resilience for Schools in Nepal
page 3 of 9
Executive Summary
A Disaster Resilient Nepal: The Current Situation
1. Nepal is located within a high hazard zone with high vulnerabilities, leading to
potentially high risk and grave consequences from natural disasters, especially
from earthquakes. The country lies on several active faults where possible
epicenters are located at rather shallow depths, increasing the probability of
Nepal experiencing very strong ground motions.
2. Due to the growing understanding of the importance of disaster resilience (DR) in
Nepal, many programs have been initiated in many sectors, including the
establishment of National Risk Reduction Consortium (NRRC), comprising of five
flagship programs.
3. One such program is the School Safety Program (SSP) which was initiated and is
being funded by the Asian Development Bank (ADB) and the Australian Agency
for International Development under the Flagship 1 of the NRRC. As a Technical
Assistance Program, SSP is being implemented through Nepal’s Department of Education (DOE), under the Ministry of Education (MOE) which is the government
agency responsible also for the school sector. This program targeted about 260
public school buildings in Kathmandu Valley (KV) for retrofitting. SSP also included
capacity building programs for masons, teachers, students, and professionals in the
DOE within a 2-year duration starting from 2012. Many of these activities have been
successfully completed to date.
4. Even though SSP covers less than 0.3% of total scope of schools in the country, and
is only administered in KV, it has helped to identify several challenges, such as the
lack of capacity and resources, need for better technological solutions, quality
assurance, financial management, reconsideration of the role of community, and
coordination amongst various stakeholders. Tackling the disaster risk reduction
(DRR) activities in the entire country with a scale that is 300 times larger, spread
over 75 districts, needs a clear strategy and plan. Streamlining existing processes
and developing innovative ways to increase and sustain DR is the key to
accomplishing scaling up.
5. The School Sector Reform Plan (2009-2015) is another key project of the Ministry of
Education which serves as the basis for most of the improvements and
modifications in the school sector. Reports showed minimal issues in
implementation and that most of the district-level programs were observed to be
satisfactory. The SSRP is considered a potential platform for integration with SSP and
for scaling up the DR initiatives.
Increasing DR in Schools: Overall Strategies and Actions
6. Recognizing and supporting the several ongoing and planned initiatives and
programs related to DRR in Nepal, and to ensure an increased effectiveness and
reduced instances of duplicated efforts and emphasize focus on DR of schools, the
strategies are divided into two categories; Linked and Stand-alone.
Strategy for Increasing Disaster Resilience for Schools in Nepal
page 4 of 9
7. Linked strategies refer to those that have relationships, ownership, and/or
relevance to the National DRR initiatives, but will also impact the DR of the school
sector. These strategies are either based on strengthening and supporting other
ongoing and planned initiatives or needs integration with them. Six (6) strategies
are proposed under this category:
1. Increased DR awareness in various stakeholders, at various levels.
2. Continuous reinforcement of will and commitment to DR at the highest
levels of the government and development partners.
3. Increased institutionalization and coordination to tackle the risks and
consequences of to various disasters.
4. Building overall capability and capacity of different stakeholders for DRR.
5. Facilitate and support local research to aid in providing relevant solutions
for measures leading to DRR.
6. Development and/or amendment of policies, acts, and regulations, and
their enforcement for enabling implementation of various strategies,
actions and measures aimed at DRR of various sectors, including the
schools.
8. Stand-alone strategies are specific strategies that are primarily applicable to the
school sector and can be implemented mostly independently within the defined
frameworks. These consist of the following nine (9) strategies:
1. Building competency-based capability and capacity of the agencies
directly involved in the implementation of the DRR process.
2. Classification, categorization, and standardization of the intervention
solutions for the vast scale of schools and buildings capitalizing on the
geographical, administrative, rural/urban, building materials, and size
variations.
3. Prioritized increase in multi-hazard DR for public schools, based on the
disaster consequences as the primary parameter derived from hazard
levels, vulnerability, and exposure, using a combination of one-time and
incremental safety approaches.
4. Increased DR of private schools through a combination of appropriate
regulations, licensing, certification, technical and administrative support,
and incentives, in close collaboration with private sector.
5. Integration of DR into SSRP and other related development plans for
maximizing the cost and resource effectiveness, and to avoid duplication
and conflicting interventions.
6. Certification of the DRR process and the final outcome, through continuous
quality assurance mechanisms and formal inspections, combined with
voluntary DR rating.
7. Increased community DR through systematic and assured involvement of
the community in awareness, capacity building, intervention
implementation, monitoring the final outcome of increased school DR.
Strategy for Increasing Disaster Resilience for Schools in Nepal
page 5 of 9
8. Integration of various aspects of DR into the academic and professional
curricula, progressively from basic awareness to vocational training and
advanced knowledge and skill sets.
9. Implementation of results-based monitoring and evaluation performance
management plans to ensure the achievement of the outputs and
outcomes.
9. The scale and complexity of the tasks require the engagement of many
stakeholders carefully aligned with appropriate linkages for a strong and flexible
framework that is necessary for the implementation of the DR strategies at a
national level.
Working Together: Ownership, Implementation, and Coordination
10. Institutional arrangements, roles and responsibilities of the key stakeholders, and
coordination framework are largely reinforced by the collective agreement for the
DOE, to take ownership of the entire program as the primary implementing and
coordinating agency, actively supported by the Department of Urban
Development (DUDBC) under the Ministry of Urban Development (MOUD).
11. The primary role of MOE/DOE will be to formulate new or amend the existing
policies, rules, regulations, and guidelines to include DR considerations in the
design, construction and operations of schools, both in the public and private
domain. This may include enforcing a combined certification and licensing system,
similar to that used for the operations of hospitals.
12. For public schools, DOE will carry out all of the planning, execution management,
and coordination of the entire DRR process, closely with DEO and technical
support from DUDBC. The actual execution of various work items will be conducted
by the consultants and contractors, with appropriate involvements and support
from the community, VDC, and INGOS/NGOS based on several factors including
location (urban/rural, mountains/hills/plains), type of construction, size of buildings,
and complexity of tasks.
13. For private schools, the operators and or owners of buildings will be required,
through regulations, to gradually and progressively retrofit, relocate or rebuild the
school premises and facilities to meet the DR and functionality requirements laid
down by MOE/DOE. DUDBC will provide technical support and facilitate the
building owners in this process and will also carry out the required certifications.
The private school operators/owners will be supported by GON and development
partners in this process through financial assistance, soft loans, and other incentives
such as tax breaks.
14. Both, DOE and DUDBC will need to be strengthened to take on these additional
responsibilities, through the establishment of dedicated divisions/sections and
allocation of appropriate, sufficient, and qualified resources, with adequate
budgets, facilities and incentives.
15. Due to the level of community participation that is prevalent in Nepal, it may be
useful to reconsider the roles for community participation in the school DRR
process. The roles can include generating ownership by the community’s inclusion in basic training programs and thereby equipping the community with skills in order
Strategy for Increasing Disaster Resilience for Schools in Nepal
page 6 of 9
to respond to various hazards and disasters. The community may also be involved
in fund raising and generating other in-kind resources and services related to the
process, direct intervention (construction) activities, and monitoring the works
carried out by other parties, in conjunction with the DEO, VDC, and the
consultants.
16. Frequent and smooth coordination with other ministries such as MOHA, MOUD,
MOF, MOFALD, and the Office of the Prime Minister will help ensure that the
objectives of this program are met.
17. A separate, dedicated coordination office is proposed for the coordination of the
entire school DRR process. This office will function as a clearing house and
repository of all information generated and needed to smoothly carry out various
aspects of the overall process, and will coordinate with various government
agencies, development partners, UN agencies, INGOS/ NGOS, private school
operators, technical committees, the media, and other stakeholders.
What is Needed: The Plan
Finances
18. A total of about 55,725 Million NPR (nearly 560 Million USD), may be needed for
completing the DRR of all public schools in the country, in about 8 to 10 years
duration. A summary of the key budgetary requirements and cost components (in
Million NPR and percentage against the total) is provided below:
Direct Intervention Cost 48,150 86.4%
DOE and DEO Resources and Costs 2,350 4.2%
DUDBC Resources and Costs 375 0.7%
Various Types of Consulting 2,900 5.2%
Coordination, Monitoring, and Evaluations 200 0.4%
Awareness and Capacity Building 500 0.9%
Risk Assessments and Related Studies 300 0.5%
Research and Development 350 0.6%
Miscellaneous 600 1.1%
19. The total cost is estimated to be about 8,000 NPR (about 80 USD), per student
enrolled in the school system. This means the safety of nearly all children (enrolled
in schools) from natural disasters can be significantly improved/ensured by
spending about 10 USD, per child, per year for the next 8 years on school DRR. This
is equivalent to less than 1 USD per month per child.
20. Although, the estimate does not include the direct cost of intervention for private
schools, which is to be borne by the private sector or through other mechanisms,
the finances needed by DOE and DUDBC to implement the strategy proposed for
the private schools were already considered.
21. The cost of planning, design, management, certification, and coordination was
calculated to be about 15% of the total cost. A significant portion of this amount is
to be allocated for the detailed assessment of buildings, which could be reduced
through proper hazard and vulnerability studies and standardization.
22. Some of the cost components, such as the cost that may be additionally incurred
by the various ministries in GON, development partners, UN agencies, NGOs,
Strategy for Increasing Disaster Resilience for Schools in Nepal
page 7 of 9
various professional organizations, academic institutes, and committees that
support the overall DRR process were not explicitly included in this estimates. These
incidentals are expected to be covered as part of the commitment of these
organizations to the cause.
Prioritization
23. Considering the large scale of the intervention, it is important to prioritize the tasks
and schools identified for intervention, so that the finances and resources can be
allocated efficiently and utilized effectively. Three levels of prioritization are
considered:
a) Prioritizing the tasks that need be completed first, without which the DRR
process cannot be initiated. This includes generation of detailed school and
building inventory for all schools in the country, formulation of policies,
conducting/obtaining risk assessment studies, development of design criteria
and guidelines, classifications and categorizations, and development of
standardized solutions.
b) A macro-level (district) priority grouping for the implementation of the DRR
process which is primarily based on the anticipated disaster consequences.
This is done by assuming that the vulnerability of the buildings is of similar order
in all districts, and therefore considering the hazard levels, student density per
classroom, population density of the district, and the overall conditions of the
buildings as the main parameters. This prioritization is done with a view to gain
maximum benefit from the intervention.
c) A local-level prioritization of the individual schools and buildings, within the
districts, based on detailed assessments, and considering other relevant
factors. This is to be done at the implementation stage, and is not considered
in the current plan.
24. Four district-level priority groups have been initially planned based on the available
data. This grouping should be re-evaluated once the basic school inventory is
completed for the entire country. The categorized groups, number of districts in
each group, number of students in public schools that will benefit from the
intervention are presented below, together with associated cost:
Group-1 3 Districts of KV 151,385 Students 1,450 m NPR
Group-2 23 Districts 3,055,830 Students 18,750 m NPR
Group-3 21 Districts 1,701,777 Students 14,450 m NPR
Group-4 28 Districts 1,284,020 Students 13,500 m NPR
25. It is very important to note, that for KV, more than 70% of the students are in the
private schools (about 3 times more of those enrolled in public schools). The focus
of priority Group-1 must on private schools, in addition to the ongoing and future
plans for public schools. The cost and corresponding number of students in private
schools is not included in these estimates.
Resources
26. The primary resources needed for implementation are from DOE, DUDBC, DEOs,
consultants, contractors, and coordination office; whereas the supporting
Strategy for Increasing Disaster Resilience for Schools in Nepal
page 8 of 9
resources required are Technical Advisory Committee, Development Partners, UN
Agencies, INGOs, and NGOs.
27. The average number of estimated resources required during the execution and
implementation of the prioritized plan, over a period about 8 to 10 years, for the
main agencies are summarized as follows, together with the approximate number
of available resources for implementing the DRR process shown in parenthesis.
DOE, total staff in head office and 5 regional offices 150 (7)
DEO, total staff in all districts 625 (220)
DUDBC, total staff in head office and all districts 70 (5)
Consultants, all districts 160 (50)
Construction firms of various sizes 450 (200)
28. Based on the summary of resources (above), a significantly large number of staff
was estimated to be needed in DOE, DEO, and DUDBC to implement the DRR
activities. It is important to prepare the needed staff to be well-trained, and
capable of handling various aspects of the DRR process, as provided with
adequate facilities and incentives.
29. It is also clear that not enough consultants and construction firms may be available
to undertake the implementation tasks, especially considering that the same
consultants and contractors will also be needed for other ongoing and planned
development projects. Given their current commitments, the present roster of
consultants and construction firms will not be fully available for the planned school
DRR process. Therefore, the involvement of international firms will be essential to
supplement and support the local capacity.
On New Schools
30. In planning for the constructing new schools, an average of 35 students per
classroom was projected for each district for all schools (public and private).
Results show that by 2021, approximately 45,000 new classrooms must be
constructed to satisfy the projected demand in Nepal. Given that an estimated
20% of the new classrooms will be private, a total of 36,000 new public classrooms
will need to be constructed by 2021 in Nepal.
31. For the hilly and mountainous areas that are sparsely populated, innovative
solutions such as adopting an Education Village concept may prove to increase
occupancy rate in the classrooms by reducing the student’s travel from daily to
weekly, increase mobilization effectiveness, and maximize the utilization of
resources. An Education Village will essentially transform underutilized school
infrastructures, with the possibility to merge with other schools, to provide both
academic and lodging facilities to students.
Capacity Development for School Sector Program Implementation (TA 7935 NEP)
Government of Nepal, Ministry of Education Department of Education
The Plan
Submitted to
Asian Development Bank
Nepal Resident Mission
June 2014
Overall Plan for Increasing
Disaster Resilience of Schools in
Nepal
Capacity Development for School Sector
Program Implementation (TA 7935 NEP)
Contract Number: 106698-S79855
Overall Plan for Increasing Disaster
Resilience for Schools in Nepal
The Plan
Submitted to
Asian Development Bank
June 2014
page 3 of 70
List of Tables ................................................................................................................................................. 5
List of Figures ................................................................................................................................................ 7
List of Abbreviations ...................................................................................................................................... 8
Executive Summary ..................................................................................................................................... 10
The Plan ................................................................................................................................................ 13
Chapter 1 Background ............................................................................................................................. 14
1.1 The Issue ............................................................................................................................................ 14
1.2 In Brief: The Strategy.......................................................................................................................... 15
1.2.1 Increasing DR in Schools: Overall Strategies and Actions .......................................................... 15
1.2.2 Working Together: Ownership, Implementation, and Coordination.............................................. 16
1.3 Nepal’s School Sector ........................................................................................................................ 17
Chapter 2 Strategic Action Plan ............................................................................................................... 19
2.1 Overview ............................................................................................................................................ 19
2.2 Action Plan Matrix............................................................................................................................... 19
Chapter 3 Classification and Categorization ............................................................................................ 25
3.1 Need for Classification and Categorization ......................................................................................... 25
3.2 School and Building Categories ......................................................................................................... 25
3.3 Data Collection and Assimilation ........................................................................................................ 26
3.4 Public and Private Schools ................................................................................................................. 28
3.4.1 Schools in Kathmandu Valley ...................................................................................................... 29
3.4.3 On Private Schools ...................................................................................................................... 31
3.5 Categories of Public Schools for Intervention ..................................................................................... 31
Chapter 4 Parameters Used for Estimation ............................................................................................. 34
4.1 Additional Data Needed For Improved Planning ................................................................................ 36
Chapter 5 Resource Estimation ............................................................................................................... 37
5.1 Procedure for Resource Estimation .................................................................................................... 37
5.2 DOE Resources ................................................................................................................................. 38
5.3 DEO Resources ................................................................................................................................. 42
5.4 DUDBC Resources............................................................................................................................. 44
5.5 Consultants ........................................................................................................................................ 46
5.6 Summary of the Resource Planning ................................................................................................... 48
Chapter 6 Cost Estimation ....................................................................................................................... 49
6.1 Direct Cost of Intervention .................................................................................................................. 49
6.1.1 Kathmandu Valley ........................................................................................................................ 53
6.1.2 Public Schools in Rural Areas...................................................................................................... 53
6.1.3 Public Schools in Urban Areas .................................................................................................... 54
6.2 Summary of Costs .............................................................................................................................. 55
Chapter 7 Prioritization and Work Plan .................................................................................................... 57
Content
page 4 of 70
7.1 Procedure for Prioritization ................................................................................................................. 57
7.2 Efficient Utilization of Resources ........................................................................................................ 58
7.3 Priority for Intervention ....................................................................................................................... 58
7.4 Work Plan ........................................................................................................................................... 62
7.4.1 Overview ...................................................................................................................................... 62
7.4.2 Time Line ..................................................................................................................................... 63
Chapter 8 On New Schools ..................................................................................................................... 65
8.1 Projection and Construction of New Schools ...................................................................................... 65
8.1.1 Education Village Concept ........................................................................................................... 66
8.2 Estimation of New Classroom Construction ....................................................................................... 66
page 5 of 70
List of Tables
Table 2-1: Action Plan Matrix 19
Table 3-1: Building Categorization Basis for the Academic Institutions in Nepal 25
Table 3-2: Building Size Categorization Description 26
Table 3-3: Information in EMIS Database for All Schools in Nepal 27
Table 3-4: Additional Data from MOE Flash Report 27
Table 3-5: Number of Schools in Various Distribution Parameters 28
Table 3-6: School Distribution in Kathmandu Valley (Public vs. Private) 30
Table 3-7: School Building Typology Distribution in Kathmandu Valley 30
Table 3-8: Ecological Belt-wise School Building Size Distribution 32
Table 3-9: Ecological Belt-wise School Building Size Distribution 32
Table 3-10: Administrative Region-wise Building Typology Distribution (Excluding KV) 33
Table 3-11: Administrative Region-wise School Building Numbers for Rebuild, One Time Intervention
and Incremental Intervention (Excluding KV) 33
Table 5-1: DOE Resources and Cost Summary for KV 38
Table 5-2: DOE Required Resources and Cost for Public School Buildings in Rural Areas 39
Table 5-3: DOE Required Resources and Cost for Public School Buildings in Urban Areas 40
Table 5-4: DOE Required Resources and Cost for Total Public School Buildings including KV 41
Table 5-5: DEO Required Resources and Cost for Public School Buildings in KV 42
Table 5-6: DEO Required Resources and Cost for Public School Buildings in Rural Areas 42
Table 5-7: DEO Required Resources and Cost for Public School Buildings in Urban Areas 43
Table 5-8: DEO Required Resources and Cost for Total Public School Buildings including KV 44
Table 5-9: DUDBC Required Resources and Cost for Public School Buildings in KV 45
Table 5-10: DUDBC Required Resources and Cost for Public School Buildings in Rural Areas 45
Table 5-11: DUDBC Required Resources and Cost for Public School Buildings in Urban Areas 45
Table 5-12: DUDBC Required Resources and Cost for Total Public School Buildings including KV 45
Table 5-13: Consultants Required Resources and Cost for Public School Buildings in KV 46
Table 5-14: Consultants Required Resources and Cost for Public School Buildings in Rural Areas 46
Table 5-15: Consultants Required Resources and Cost for Public School Buildings in Urban Areas 47
Table 5-16: Consultants Required Resources and Cost for Total Public School Buildings including KV 47
page 6 of 70
Table 5-17: The Trade-off between Number of Resources and Time 48
Table 6-1: Overall Intervention Cost Summary for Public Schools (Regional) 49
Table 6-2: Overall Intervention Cost Summary for Public Schools (Belt-wise) 49
Table 6-3: Overall Intervention Cost Summary for Public Schools – Districts (East) 50
Table 6-4: Overall Intervention Cost Summary for Public Schools – Districts (Central & West) 51
Table 6-5: Overall Intervention Cost Summary for Public Schools – Districts (Mid West and Far West) 52
Table 6-6: Cost Basis Model for Public School Buildings in KV 53
Table 6-7: Direct Intervention Cost for Public School Buildings in KV 53
Table 6-8: Cost Basis Model for Public School Buildings in Rural Areas 53
Table 6-9: Direct Intervention Cost for Public School Buildings in Rural Areas 54
Table 6-10: Direct Intervention Cost for Public School Buildings in Urban Areas 54
Table 6-11: Summary of Overall Cost for DRR of Public School Buildings in Nepal 55
Table 7-1: Summary of Priority Groups and Cost 59
Table 7-2: Cost Indicators for Priority Groups 59
Table 7-3: Intervention Cost for Public Schools: Priority Group – 1 60
Table 7-4: Intervention Cost for Public Schools: Priority Group – 2 60
Table 7-5: Intervention Cost for Public Schools: Priority Group – 3 61
Table 7-6: Intervention Cost for Public Schools: Priority Group – 4 62
Table 8-1: District-wise Data for the Projection and Construction of New Schools 67
page 7 of 70
List of Figures
Figure 3-1: Distribution of School-related Indicators in the Kathmandu Valley 29
Figure 3-2: Distribution of Various School Indicators in Districts 30
Figure 7-1: Priority Groups Distribution, by District 58
Figure 7-2: Distribution of Various Parameters for Priority Groups 59
Figure 7-3: Distribution of Intervention Cost for Priority Groups 60
Figure 8-1: Comparison of Students per Classrooms and Population Density for 2011 and 2021 65
page 8 of 70
List of Abbreviations
ADB Asian Development Bank
AHA Analytical Hierarchy Approach
AIT Asian Institute of Technology
ASIP Annual Strategic Implementation Plan
AusAID Australian Government Overseas Aid Program
AWPB Annual Work Plan and Budget
BOQ Bill of Quantity
CBO Community-based Organization
CSSP Community School Support Programme
CTEVT Council for Technical Education & Vocational Training
DEO District Education Office
DOE Department of Education
DRM Disaster Risk Management
DR Disaster Resilience
DRR Disaster Risk Reduction
DUDBC Department of Urban Development & Building Construction
EFA Education for All
EMIS Education Management and Information System
FEMA Federal Emergency Management Agency
GON Government of Nepal
HFA Hyogo Framework for Action
INGO International Non-governmental Organization
JICA Japan International Cooperation Agency
KV Kathmandu Valley
KPI Key Performance Indicator
MOE Ministry of Education
MOFLD Ministry of Federal Affairs and Local Development
MOH Ministry of Health
MOHA Ministry of Home Affairs
MOUD Ministry of Urban Development
NGO Non-governmental Organization
NRRC Nepal Risk Reduction Consortium
NSET National Society for Earthquake Technology - Nepal
PHRD Policy and Human Resources Development, World Bank
RC Reinforced Concrete
page 9 of 70
SSP School Safety Program, sometimes referred to as the School Earthquake
Safety Program (SESP)
SMC School Management Committees
SSRP School Sector Reform Program
SSS School Seismic Safety
TAC Technical Advisory Committee
TEP Teacher Education Project
UNDP United Nations Development Programme
UNEP United Nations Environment Programme
UNOCHA United Nations Office for the Coordination of Humanitarian Affairs
URM Unreinforced Brick Masonry
VDCs Village Development Committees
WB World Bank
WHO World Health Organization
page 10 of 70
Executive Summary
1. This Strategic Action Plan was developed in continuation of the detailed strategy 1
that was established for nationwide implementation of disaster resilience (DR)
activities for Nepal and based on the previous successes of several ongoing DR
programs in Nepal such as the School Safety Program (SSP) and the School Sector
Reform Plan (2009-2015), including the formation of National Risk Reduction
Consortium (NRRC), comprising of five flagship programs.
What is Needed: The Plan
Finances
2. A total of about 55,725 Million NPR (nearly 560 Million USD), may be needed for
completing the DRR of all public schools in the country, in about 8 to 10 years
duration. A summary of the key budgetary requirements and cost components (in
Million NPR and percentage against the total) is provided below:
Direct Intervention Cost 48,150 86.4%
DOE and DEO Resources and Costs 2,350 4.2%
DUDBC Resources and Costs 375 0.7%
Various Types of Consulting 2,900 5.2%
Coordination, Monitoring, and Evaluations 200 0.4%
Awareness and Capacity Building 500 0.9%
Risk Assessments and Related Studies 300 0.5%
Research and Development 350 0.6%
Miscellaneous 600 1.1%
3. The total cost is estimated to be about 8,000 NPR (about 80 USD), per student
enrolled in the school system. This means the safety of nearly all children (enrolled
in schools) from natural disasters can be significantly improved/ensured by
spending about 10 USD, per child, per year for the next 8 years on school DRR. This
is equivalent to less than 1 USD per month per child.
4. Although, the estimate does not include the direct cost of intervention for private
schools, which is to be borne by the private sector or through other mechanisms,
the finances needed by DOE and DUDBC to implement the strategy proposed for
the private schools were already considered.
5. The cost of planning, design, management, certification, and coordination was
calculated to be about 15% of the total cost. A significant portion of this amount is
to be allocated for the detailed assessment of buildings, which could be reduced
through proper hazard and vulnerability studies and standardization.
6. Some of the cost components, such as the cost that may be additionally incurred
by the various ministries in GON, development partners, UN agencies, NGOs,
various professional organizations, academic institutes, and committees that
support the overall DRR process were not explicitly included in this estimates. These
incidentals are expected to be covered as part of the commitment of these
organizations to the cause.
1 Strategy for Increasing Disaster Resilience for Schools in Nepal. June 2014.
page 11 of 70
Prioritization
7. Considering the large scale of the intervention, it is important to prioritize the tasks
and schools identified for intervention, so that the finances and resources can be
allocated efficiently and utilized effectively. Three levels of prioritization are
considered:
a) Prioritizing the tasks that need be completed first, without which the DRR
process cannot be initiated. This includes generation of detailed school and
building inventory for all schools in the country, formulation of policies,
conducting/obtaining risk assessment studies, development of design criteria
and guidelines, classifications and categorizations, and development of
standardized solutions.
b) A macro-level (district) priority grouping for the implementation of the DRR
process which is primarily based on the anticipated disaster consequences.
This is done by assuming that the vulnerability of the buildings is of similar order
in all districts, and therefore considering the hazard levels, student density per
classroom, population density of the district, and the overall conditions of the
buildings as the main parameters. This prioritization is done with a view to gain
maximum benefit from the intervention.
c) A local-level prioritization of the individual schools and buildings, within the
districts, based on detailed assessments, and considering other relevant
factors. This is to be done at the implementation stage, and is not considered
in the current plan.
8. Four district-level priority groups have been initially planned based on the available
data. This grouping should be re-evaluated once the basic school inventory is
completed for the entire country. The categorized groups, number of districts in
each group, number of students in public schools that will benefit from the
intervention are presented below, together with associated cost:
Group-1 3 Districts of KV 151,385 Students 1,450 m NPR
Group-2 23 Districts 3,055,830 Students 18,750 m NPR
Group-3 21 Districts 1,701,777 Students 14,450 m NPR
Group-4 28 Districts 1,284,020 Students 13,500 m NPR
9. It is very important to note, that for KV, more than 70% of the students are in the
private schools (about 3 times more of those enrolled in public schools). The focus
of priority Group-1 must on private schools, in addition to the ongoing and future
plans for public schools. The cost and corresponding number of students in private
schools is not included in these estimates.
Resources
10. The primary resources needed for implementation are from DOE, DUDBC, DEOs,
consultants, contractors, and coordination office; whereas the supporting
resources required are Technical Advisory Committee, Development Partners, UN
Agencies, INGOs, and NGOs.
11. The average number of estimated resources required during the execution and
implementation of the prioritized plan, over a period about 8 to 10 years, for the
main agencies are summarized as follows, together with the approximate number
of available resources for implementing the DRR process shown in parenthesis.
page 12 of 70
DOE, total staff in head office and 5 regional offices 150 (7)
DEO, total staff in all districts 625 (220)
DUDBC, total staff in head office and all districts 70 (5)
Consultants, all districts 160 (50)
Construction firms of various sizes 450 (200)
12. Based on the summary of resources (above), a significantly large number of staff
was estimated to be needed in DOE, DEO, and DUDBC to implement the DRR
activities. It is important to prepare the needed staff to be well-trained, and
capable of handling various aspects of the DRR process, as provided with
adequate facilities and incentives.
13. It is also clear that not enough consultants and construction firms may be available
to undertake the implementation tasks, especially considering that the same
consultants and contractors will also be needed for other ongoing and planned
development projects. Given their current commitments, the present roster of
consultants and construction firms will not be fully available for the planned school
DRR process. Therefore, the involvement of international firms will be essential to
supplement and support the local capacity.
On New Schools
14. In planning for the constructing new schools, an average of 35 students per
classroom was projected for each district for all schools (public and private).
Results show that by 2021, approximately 45,000 new classrooms must be
constructed to satisfy the projected demand in Nepal. Given that an estimated
20% of the new classrooms will be private, a total of 36,000 new public classrooms
will need to be constructed by 2021 in Nepal.
15. For the hilly and mountainous areas that are sparsely populated, innovative
solutions such as adopting an Education Village concept may prove to increase
occupancy rate in the classrooms by reducing the student’s travel from daily to weekly, increase mobilization effectiveness, and maximize the utilization of
resources. An Education Village will essentially transform underutilized school
infrastructures, with the possibility to merge with other schools, to provide both
academic and lodging facilities to students.
page 13 of 70
The Plan
page 14 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Chapter 1 Background
1.1 The Issue
16. Natural disasters have claimed the lives of more than 27,000 people between 1971
and 2007, indicating an average loss of more than 2 lives per day due to natural
disasters in Nepal. More people are killed by natural disasters in Nepal than any
other country in South Asia. In addition to high mortality, more than 50,000 people
were reported as injured, 3,000 people missing, and about 5 million people
affected by natural disasters. 2
17. With the increased understanding of disaster resilience (DR) in Nepal, many
programs have been initiated in many sectors to address the country’s vulnerability. This includes the establishment of the National Risk Reduction
Consortium (NRRC), comprising of five flagship programs.
18. One program was selected for large-scale country-wise implementation. The
School Safety Program (SSP), a Technical Assistance Program, was initiated and is
being funded by the Asian Development Bank (ADB) and the Australian Agency
for International Development under the Flagship 1 of the NRRC. SSP is currently
being implemented through Nepal’s Department of Education (DOE), under the Ministry of Education (MOE) which is the government agency responsible also for
the school sector.
19. The program targeted about 260 public school buildings in Kathmandu Valley (KV)
for retrofitting. SSP also included capacity building programs for masons, teachers,
students, and professionals in the DOE within a 2-year duration starting from 2012.
Many of these activities have been successfully completed to date.
20. Even though SSP covers less than 0.3% of total scope of schools in the country, and
is only administered in KV, it has helped to identify several challenges, such as lack
of capacity and resources, need for better technological solutions, quality
assurance, financial management, reconsideration of the role of community, and
coordination amongst various stakeholders. Tackling the DRR activities in the entire
country with a scale that is 300 times larger, spread over 75 districts, needs a clear
strategy and plan. Streamlining existing processes and developing innovative ways
to increase and sustain DR is the key to accomplishing scaling up.
21. The School Sector Reform Plan (2009-2015) is another key project of the Ministry of
Education which serves as the basis for most of the improvements and
modifications in the school sector. Reports showed minimal issues in
implementation and that most of the district-level programs were observed to be
satisfactory. The SSRP is considered a potential platform for integration with SSP and
for scaling up the DR initiatives.
22. This Strategic Action Plan was developed in continuation of the detailed strategy 3
that was developed for the nationwide expansion and implementation of DR
activities.
2 Disaster Risk Reduction in Nepal: Flagship Programmes, The Nepal Risk Reduction Consortium. April 2011.
http://www.un.org.np/sites/default/files/report/2011-04-19-nrrc-doccument-version-april-2011.pdf 3 Strategy for Increasing Disaster Resilience for Schools in Nepal. June 2014.
page 15 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
1.2 In Brief: The Strategy
1.2.1 Increasing DR in Schools: Overall Strategies and Actions
23. Recognizing and supporting the several ongoing and planned initiatives and
programs related to DRR in Nepal. To ensure an increased effectiveness and
reduced instances of duplicated efforts, as well as to emphasize focus on DR of
schools, the strategies are divided into two categories; Linked and Stand-alone.
24. Linked strategies refer to those that have relationships, ownership, and/or
relevance to the National DRR initiatives, but will also impact the DR of the school
sector. These strategies are either based on strengthening and supporting other
ongoing and planned initiatives or needs integration with them. Six (6) strategies
are proposed under this category:
1. Increased DR awareness in various stakeholders, at various levels.
2. Continuous reinforcement of will and commitment to DR at the highest
levels of the government and development partners.
3. Increased institutionalization and coordination to tackle the risks and
consequences of to various disasters.
4. Building overall capability and capacity of different stakeholders for DRR.
5. Facilitate and support local research to aid in providing relevant solutions
for measures leading to DRR.
6. Development and/or amendment of policies, acts, and regulations, and
their enforcement for enabling implementation of various strategies,
actions and measures aimed at DRR of various sectors, including the
schools.
25. Stand-alone strategies are specific strategies that are primarily applicable to the
school sector and can be implemented mostly independently within the defined
frameworks. These consist of the following nine (9) strategies:
7. Building competency-based capability and capacity of the agencies
directly involved in the implementation of the DRR process.
8. Classification, categorization, and standardization of the intervention
solutions for the vast scale of schools and buildings capitalizing on the
geographical, administrative, rural/urban, building materials, and size
variations.
9. Prioritized increase in multi-hazard DR for public schools, based on the
disaster consequences as the primary parameter derived from hazard
levels, vulnerability, and exposure, using a combination of one-time and
incremental safety approaches.
10. Increased DR of private schools through a combination of appropriate
regulations, licensing, certification, technical and administrative support,
and incentives, in close collaboration with private sector.
11. Integration of DR into SSRP and other related development plans for
maximizing the cost and resource effectiveness, and to avoid duplication
and conflicting interventions.
page 16 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
12. Certification of the DRR process and the final outcome, through continuous
quality assurance mechanisms and formal inspections, combined with
voluntary DR rating.
13. Increased community DR through the systematic and assured involvement
of the community in awareness, capacity building, intervention
implementation, monitoring the final outcome of increased school DR.
14. Integration of various aspects of DR into the academic and professional
curricula, progressively from basic awareness to vocational training and
advanced knowledge and skill sets.
15. Implementation of results-based monitoring and evaluation performance
management plans to ensure the achievement of the outputs and
outcomes.
26. The scale and complexity of the tasks require the engagement of many
stakeholders carefully aligned with appropriate linkages for a strong and flexible
framework that is necessary for the implementation of the DR strategies at a
national level.
1.2.2 Working Together: Ownership, Implementation, and Coordination
27. Institutional arrangements, roles and responsibilities of the key stakeholders, and
coordination framework are largely reinforced by the collective agreement for the
DOE, to take ownership of the entire program as the primary implementing and
coordinating agency, actively supported by the Department of Urban
Development (DUDBC) under the Ministry of Urban Development (MOUD).
28. The primary role of MOE/DOE will be to formulate new or amend the existing
policies, rules, regulations, and guidelines to include DR considerations in the
design, construction, and operations of schools, both in the public and private
domain. This may include enforcing a combination of certification and licensing
system, similar to that used for the operations of hospitals.
29. For the public schools, DOE will carry out all of the planning, execution
management, and coordination of the entire DRR process, in close coordination
with DEO and technical support from DUDBC. The actual execution of various work
items will be conducted by the consultants and contractors, with appropriate
involvements and support from the community, VDC, and INGOS/NGOS based on
several factors including location (urban/rural, mountains/hills/plains), type of
construction, size of buildings, and complexity of tasks.
30. For private schools, the operators and or owners of buildings will be required,
through regulations, to gradually and progressively retrofit, relocate, or rebuild the
school premises and facilities to meet the DR and functionality requirements laid
down by MOE/DOE. DUDBC will provide technical support and facilitate the
building owners in this process and will also carry out the required certifications.
The private school operators/owners will be supported by GON and development
partners in this process through financial assistance, soft loans, and other incentives
such as tax breaks.
31. Both, DOE and DUDBC will need to be strengthened to take on these additional
responsibilities, through the establishment of dedicated divisions/sections and
page 17 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
allocation of appropriate, sufficient, and qualified resources, with adequate
budgets, facilities, and incentives.
32. Due to the level of community participation that is prevalent in Nepal, it may be
useful to reconsider the roles for community participation in the school DRR
process. The roles can include generating ownership by the community’s inclusion in basic training programs and thereby equipping the community with skills in order
to respond to various hazards and disasters. The community may also be involved
in fund raising and generating other in-kind resources and services related to the
process, direct intervention (construction) activities, and monitoring the works
carried out by other parties, in conjunction with the DEO, VDC, and the
consultants.
33. Frequent and smooth coordination with other ministries such as MOHA, MOUD,
MOF, MOFALD, and the Office of the Prime Minister will help ensure that the
objectives of this program are met.
34. A separate, dedicated coordination office is proposed for the coordination of the
entire school DRR process. This office will function as a clearing house and
repository of all information generated and needed to smoothly carry out various
aspects of the overall process, and will coordinate with various government
agencies, development partners, UN agencies, INGOS/ NGOS, private school
operators, technical committees, the media, and other stakeholders.
1.3 Nepal’s School Sector
35. Nepal is undergoing two momentous transformations – from a rural to an
urbanizing economy and from a unitary to a federal state. 4 Typical rural areas in
Nepal have a low population density and small settlements. Agricultural areas are
commonly rural. About 17% of the population resides in urban areas. With a
population of 2.5 million people, KV is growing at 4 % per year, one of the fastest-
growing metropolitan areas in South Asia. Several other districts, especially in the
plains, are also expanding at a significant rate.
36. There are primarily two types of schools in the country: public (community-based)
and private. Public schools receive regular government grants depending on their
sub-type, such as community-supported, community-aided, and community un-
aided. The private schools are funded and operated independently by individuals,
companies, or through other non-governmental organizations.
37. Public schools constitute about 84% of the total population of 6.3 million students.
Private schools, with only 16% of the total, have much greater presence in urban
areas. In case of KV, more than 75% of the students attend privately-operated
schools. It is believed, that with increased urbanization and economic growth,
enrolment in private schools is expected to grow at a faster rate than public
schools.
38. The districts in Nepal can be broadly grouped into administrative regions and
geographical/ecological belts based on terrain. Geographical grouping based on
terrain was considered together with the administrative grouping. However, KV has
4 Urban Growth and Spatial Transition in Nepal. 2013. http://issuu.com/world.bank.publications/docs/9780821396599
page 18 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
different characteristics compared to the other parts of the country and was
therefore considered separately.
39. The Ministry of Education (MOE) is the apex body responsible for initiating and
managing education activities in the country. MOE is mainly responsible for policy
development, planning and monitoring, and evaluation regarding different
aspects of education. The implementation of programs is handled by the
Department of Education (DOE).
40. For more details, a comprehensive report on Nepal’s school sector is available in the strategy document. 5
5 Strategy for Increasing Disaster Resilience for Schools in Nepal. June 2014.
page 19 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Chapter 2 Strategic Action Plan
2.1 Overview
41. Following the established fifteen (15) strategies in two categories: Linked and
Stand-alone, a total of fifty-nine (59) actions were subsequently identified. This
chapter will provide details and linkages among agency involvement and
associated cost components, as further described in chapters 5, 6, and 7.
2.2 Action Plan Matrix
42. The Action Plan Matrix presented below lists the required actions for each strategy
to be implemented together with the agencies and stakeholders responsible for
implementing these actions. The matrix also indicates the associated cost
components that cover these actions. To perform resource and cost estimation,
several related and relevant actions have been grouped together.
Table 2-1: Action Plan Matrix
Sr.
No. Strategies Actions
Responsible
Agencies
Associated Cost
Components
A Linked Strategies
1 Increased awareness on the importance of DR
Awareness and
Capacity Building
Cost
1.1
Develop appropriate and focused
messaging material, in coordination with
international forums and guidelines, and
the NRRC communication unit
NRRC
Communication
Unit
1.2 Distribute communication materials to
relevant stakeholders NRRC
1.3
Carry out an extensive awareness
programs through various TV programs,
print and electronic media, and events
MOE/DOE
1.4
Set up special discussion groups and
forums through social media, and
launch a regular electronic newsletter
MOE/DOE
1.5 Engage teacher associations, student
groups, and youth organizations DOE
page 20 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Sr.
No. Strategies Actions
Responsible
Agencies
Associated Cost
Components
(NPR millions)
2 Continuous reinforcement of political will and
commitment
<No direct cost
has been
assigned >
2.1
Develop a presentation and/or the
submission of strategic documents on
this issue to higher management
NRRC/DOE
2.2
Issuance of a policy statement, and
directives, supporting the DRR initiatives
in general, and DR of schools in
particular
DOE
2.3
Declaration from relevant ministries and
departments to own and commit to this
task, in accordance with the proposed
organizational frameworks
Council of Ministers
2.4
Re-affirmed commitment from the
heads of the development partners
and agencies to support this issue
Ministries and DP
2.5
Possibly signing of MOA by all
stakeholders to legitimize will and
commitment
DOE, DUDBC, DP,
UN-Agencies,
PABSON, AIN
2.6 Development and/or amendment of
policies, acts, and regulations MOE
3 Increased institutionalization and better
coordination
3.1
Identify the primary agencies
responsible for carrying out this task and
develop the corresponding
organizational structures
DOE, DUDBC DOE and DUDBC
Resources and
Cost
3.2
Provide institutional frameworks for the
implementation of this program,
considering all relevant stakeholders
DOE, DUDBC, DP,
UN-Agencies,
PABSON, AIN
Coordination,
Monitoring, and
Evaluation Cost
3.3
Create mechanisms within this program
to enable systematic reporting and
coordination for both the activities and
outcome
DOE, DUDBC,
Coordination
Office
Coordination,
Monitoring, and
Evaluation Cost
3.4
Set up a dedicated web portal and
contribute to open-sources networks
(such as OpenDRI) for information
dissemination and sharing
Coordination
Office
Coordination,
Monitoring, and
Evaluation Cost
4 Building Overall Capacity and Capability
Awareness and
Capacity Building
Cost
4.1
Increase awareness about DR and
Environmental Sustainability in basic
school curriculum
MOE/DOE
Awareness and
Capacity Building
Cost
page 21 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Sr.
No. Strategies Actions
Responsible
Agencies
Associated Cost
Components
(NPR millions)
4.2
Focus on techniques and technologies
for retrofitting, constructing safer new
buildings and structures in vocational
trainings curriculum
CTEVT and Other
organizations
involved in
vocational
training and
certification
Awareness and
Capacity Building
Cost
4.3
Incorporate current trends and
developments in the field of DRR through
the universities curricula development in
various professional academic programs
Tribuan University,
Institute of
Engineers, other
Universities
Awareness and
Capacity Building
Cost
4.4
Focus on the proper application of
codes and new techniques through
professional organizations and programs
DUDBC,
Association of
Structural
Engineers
DUDBC Resources
and Cost
5 Facilitate and support local research
Research and
Development
Cost
5.1
Provide opportunity to work on locally
suitable solutions for technical
challenges faced for implementation,
through the allocation of appropriate
budgets and mechanisms
DOE, DUDBC,
Institute of
Engineers, other
Universities
5.2
Provide an opportunity for local
institutions to link with international
research organizations through program
and project network
DP, UN-Agencies,
MOE
5.3
Utilize the services offered by local
research centers for various tests,
verifications, and review
DOE, DUDBC,
Consultants,
Contractors
5.4
Create a database of centers in
universities, semi-public organizations, as
well as centers in private centers, listing
their capabilities and research interests
Coordination
Office
6 Development and/or amendment of policies, acts,
and regulations
Included in DOE
Costs
6.1
Create and maintain legal conditions
that address DR is necessary when
scaling up for country-wise
implementation
MOE
B Stand-alone Strategies
7 Building competency-based capability and capacity
Awareness and
Capacity Building
Cost
7.1 Establish the need for resources for
various tasks within different stakeholders
NRRC, DOE,
DUDBC
7.2
Develop a database of available
experts engaged in the capability and
capacity building
NRRC, DOE,
DUDBC
page 22 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Sr.
No. Strategies Actions
Responsible
Agencies
Associated Cost
Components
(NPR millions)
7.3
Design consistent and integrated
programs and conduct these programs
while targeting the relevant groups
NRRC, DOE,
DUDBC
7.4
Ensure these programs are integrated
with other programs and projects to
avoid duplication of efforts
NRRC
8 Classification, categorization, and standardization
Included in DOE,
DUDBC, and
Consultancy
Costs
8.1
Generate the basic inventory data base
of all public and private schools
buildings, including basic information
about the physical characteristics
DOE, DEO,
Consultants
8.2
Classify and categorize buildings by
operator, by size, by age, material type,
condition, and location
DOE, DUDBC,
Consultants
8.3
Develop standardized intervention
approaches and details for various
categories
DOE, DUDBC,
Consultants
9 Prioritized increase in multi-hazard DR for public
schools
9.1
Standardize guidelines, procedures, and
tools for multi-hazard assessment and
intervention together with consideration
for appropriate structural and non-
structural aspects
DOE, Consultants
DOE and
Consultancy
Cost
9.2 Carry out preliminary data collection
and assessment DOE, Consultants
DOE and
Consultancy
Cost
9.3
Decide to either accept the building “as is” and move to certification process or for go for further review
DOE, Consultants
DOE and
Consultancy
Cost
9.4
Carry out second level evaluation and
decide approach from any of the
options mentioned in strategy document
DOE, Consultants
DOE and
Consultancy
Cost
9.5
Use an approach that combines
classification, categorization, and
standardization for prioritization,
planning, and implementation
DOE, Consultants,
Contractors,
Community, NGOS
Direct
Intervention Cost
10 Increased DRR of private schools
DOE and DUDBC
Resources and
Cost
10.1
Establish clear policies to obtain and
renew licenses for the operation of
private schools.
MOE/DOE, In
consultation with
PABSON and
parents
associations
page 23 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Sr.
No. Strategies Actions
Responsible
Agencies
Associated Cost
Components
(NPR millions)
10.2
Formulate clear procedures, guidelines,
and supporting mechanisms for private
operators, to include the DR and
sustainability requirements
MOE/DOE, DUDBC
10.3
Notification and awareness building
about the new policies amongst all
stakeholders
MOE/DOE, DUDBC
10.4
Set timelines for the gradual
enforcement of the policies, starting with
awarding licenses for new schools,
followed by evaluating existing schools
to obtain and renew licenses
MOE/DOE, DUDBC
10.5
Set up mechanisms for providing
technical support to the operators by
providing guidelines and networking
services for engagement of qualified
professionals, contractors for carrying out
the construction work
MOE/DOE, DUDBC
10.6
Mechanism to provide soft loans, land
lease, and other performance-based
incentives, such as tax breaks for
achieving required levels of DR
MOE/DOE
10.7 Certification through DUDBC and other
municipal authorities
DOE, DUDBC,
Municipal
Authorities,
Consultants
DOE, DUDBC,
and
Consultancy
Cost
11 Integration of DRR into the overall SSRP and other
related plans
DOE and DEO
Resources and
Cost
11.1
Include basic information and
awareness about disaster resilience into
the overall annual teacher training plan
and other capacity building programs.
MOE/DOE
11.2 Infrastructure classroom standards to
include references to safety issues MOE/DOE
12 Certification and sustaining DRR levels
12.1
Identify the agency (or agencies) that
will carry out and award licenses and
certificates and develop appropriate
certification procedures, forms, and
guidelines
DOE, DUDBC, TAC,
and Consultants
DOE, DEO,
DUDBC
Resource and
Consultancy
Cost
12.2
Certify consultants, contractors, and
masons after going through the
capability and capacity building
programs, with possible mechanism for
better incentives
DOE, DUDBC, TAC
DOE, DEO,
DUDBC
Resource and
Consultancy
Cost
12.3
Intermediate review of design and
construction documents, site inspection
reports, photographs, and other QA/QC
records
DOE, DUDBC, TAC,
and Consultants
DOE, DEO,
DUDBC
Resource and
Consultancy
Cost
page 24 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Sr.
No. Strategies Actions
Responsible
Agencies
Associated Cost
Components
(NPR millions)
12.4
Certify newly constructed buildings
including the retrofit of existing buildings
for public schools through qualified
inspectors, standardized procedures and
formats
DOE, DUDBC, TAC,
Consultants
DOE, DEO
DUDBC
Resource and
Consultancy
Cost
12.5
Certify new and retrofitting intervention
of private school buildings in
conformance with codes and standards
and construction quality by DUDBC and
local municipal councils
DUDBC,
Consultants
DUDBC
Resources and
Consultancy
Cost
12.6 Renewal of certification at intervals of 10
years through site inspections MOE/DOE
DOE and DEO
Resources and
Cost
13 Increasing DR of schools as a means for increasing the overall DR of the
community
13.1
Incorporate the declared rights of the
community to use the intervened parts
of school buildings as temporary and
emergency relief centers in case of
disasters
DOE, Consultants,
iNGOs/NGOs,
Community
13.2
Community participation in the
awareness building, preventative
activities, and other training and drills
conducted for school children
DOE, Consultants,
iNGOs/NGOs,
Community
13.3
Community participation in the capacity
development programs conducted as
part of projects undertaken in this plan,
either by the community, NGOs, or
contractors
DOE, Consultants,
iNGOs/NGOs,
Community
13.4
Active participation in the DR
intervention activities implemented
through the community
DOE, Contractors,
iNGOs/NGOs,
Community
13.5
Use of intervention processes as a
demonstration of the techniques for re-
use in other construction in the
community
DOE, Contractors,
iNGOs/NGOs,
Community
Direct
Intervention
Cost
14 Integration of DR into the academic and professional
curricula
Awareness and
Capacity
Building Cost
14.1
Integrate DR in education can be
implemented in four levels: basic
education, vocational, university,
graduate
MOE
15 Implementation of results-based monitoring and evaluation performance
management plans
Coordination,
Monitoring, and
Evaluation
15.1 Develop a comprehensive result based
M&E plan
DOE, DUDBC, DP,
UN-Agencies,
Consultants
15.2 Conduct continuous M&E, reporting, and
feedback
TAC, Coordination
Office, DP
page 25 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Chapter 3 Classification and Categorization
43. This chapter includes details on the classification and categorization process of the
school data in Nepal. Based on various factors, classifying and categorizing
enabled the development of definite forms and structures to facilitate
interpretation in the most systematic and effective manner to estimate costs and
resources.
3.1 Need for Classification and Categorization
44. School building data in Nepal have been grouped into various categories based
on different factors such as the country’s topology, administration types, and
projected population growth. The diversified nature of the country particularly on
geography and the varying development levels greatly affect the building
typology and the way they are being operated. To logical allocate and effectively
and systematically mobilize resources, it is necessary to have a separate plan of
intervention based on these various categories of school buildings.
3.2 School and Building Categories
45. The school buildings all over the country have been classified based on following
categories:
a. Ecological belt wise
b. Region wise
c. District wise
d. Development area wise
e. Ownership
f. Building typology
g. Building size
46. Table 3-1 lists various categories of data and factors identified and used in the
analysis of the data related to the academic institutions. A total of 81 classifications
has been considered for cost and resource planning.
Table 3-1: Building Categorization Basis for the Academic Institutions in Nepal
Categorization Classification/Types
Ecological Belt Location
Terai/plains
Hilly areas
Mountains
Administrative Region
East
West
Central
Mid-west
Far-west
District Location Kathmandu Valley
All other Districts(73)
page 26 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Development Areas Urban
Rural
Ownership Private
Public
Building Typology
RC Frame with infill walls
Un-Reinforced Masonry (URM)
Other types (Stone masonry, mixed systems
etc.)
Building Size
Type –A: Less than 150 sqm, less than 100
students, 4 rooms
Type –B: 151 to 500 sqm, less than 400 students,
10 rooms
Type-C: Larger than 500 sqm
47. The size of the school buildings considered in the framework and planning are
tentatively defined as:
Table 3-2: Building Size Categorization Description
Building Categories Description
Large
(Category A)
Buildings not categorized as small or medium and less
than 150 sqm
Medium
(Category B)
Buildings up to 4 stories, total area less than 1000 sqm
With about 5 to 10 rooms, not more than 300 students
Intervention cost expected to be less than 5.0 M NPR
These buildings may have varying and specific layouts,
but are not expected to be too complex, and some
level of standardization will apply
Small
(Category C)
Building 1 to 2 stories, total area less than 200 sqm
With up to 4 rooms, not more than 100 students
Intervention cost expected to be less than 1.0 M NPR
These are expected to be simple in configuration, for
which standardized details should be possible, similar
to Type Design
48. Based on development areas, schools are classified in to two groups, rural schools
and urban schools. In addition, schools which are located in municipalities and
district headquarters are classified as urban schools while remaining schools are
classified as rural schools.
49. The latest municipality numbers as per the decision made by GON in May, 2014
are considered for this classification purpose.
3.3 Data Collection and Assimilation
50. The estimation of resources, cost, and time was based on the extrapolation of the
limited data based on the additional information from SSP, OpenDRI, feedback
from various sources, and the Consultant’s expert judgment. The following data sources and data set were used as the primary basis:
a. Basic data about all the schools in Nepal from the EMIS database. This contains
the following information:
page 27 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 3-3: Information in EMIS Database for All Schools in Nepal
Sr. No. Category Description of Data
1 School
Number
Under this category, each school is designated with a unique number. The
number is assigned in such a way that first one or two digits are
representing district code; next three digits are for VDC code. Whereas
remaining digits are representing numbers of school.
2 District Code
and Name
The data for schools is enlisted with district code. The district number is also
represented in school number.
3 VDC Code
and Name
In addition to the district code and name, the schools data is summarized
with VDC Code and Name.
4 School
Name
The EMIS data for all over Nepal also provides proper school names with
school level, such as primary, secondary, and higher secondary schools.
5 Location
and Ward
No.
Under these categories, the location of school is mentioned with city or
village name where school is located with ward number.
6 Established
Data
The established date of each school is given under established date
category. The established date is provided in BS, however current BS year
is also given.
7 Number of
Students
This is a very broad category which is summarized with the total number of
students for different grades i.e. Grade 1 to 12 for each school. In addition
to the total number of students, this category also provides the number of
students in each school and grade with respect to the gender i.e. number
of boys and girls in different grades.
8 Availability of
School wise
Physical
Facilities
Under this category, physical information about each school is
summarized under further sub-categories which are listed below;
Number of buildings,
Rigid buildings,
Weak buildings,
Total number of classrooms,
Rigid classrooms,
Weak classrooms,
Classrooms currently under retrofitting, and
Required retrofitting classrooms.
b. Supplemental data from MOE Flagship Report 2012 about schools and students
for various districts. This data set was used to extract, supplement, and estimate
some additional information from the EMIS database.
Table 3-4: Additional Data from MOE Flash Report
Sr. No. Category Description of Data
1 District code and
name
Flash Report data is enlisted with district code, name, and region
code. The district codes are in accordance with the district codes
of EMIS data. Each district is placed into the proper regions and
belt.
2 Total number of
schools
This is very broad category which is enlisted with total number of
schools in each district with respect to the grade (1 to 12) and
level of school such as primary, lower secondary, basic,
secondary, and higher secondary. Further total numbers of
schools in each district are also divided into total community and
institutional schools for each grade and level.
page 28 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
3 Total number of
students
Similar to the number of schools, total number of students in each
districts are also provided in Flash Report data with respect to the
level of school. However, the numbers of students are not
provided for different grades and with respect to the gender.
c. Population, area, and approximate seismic zone levels for all the districts from
various sources.
d. Current organization and location of offices, etc. for all DOE, DEO, and DUDBC,
as well as the information about local government VDCs, NGOs, and other
related organizations.
e. The extended data about the school buildings from the open DRI data for the
three districts in KV.
f. The detailed information obtained from the ongoing SSP about the retrofit
procedures, methodologies, cost, and other resources, for the three districts in
KV.
g. The common building types used for the school buildings in various belts, as
well as the relative cost variation based on the base cost in KV.
3.4 Public and Private Schools
51. In addition to the distinct categorization of public and private schools,
considerations pertaining to the spatial and demographic distribution of various
school-related indicators is important for the estimation of resources and costs. The
following parameters are considered:
a. The three ecological belts: Terai (plains), elevated lands (hills), and
mountains.
b. Five administrative regions: east, central, west, mid-west, and far-west.
c. Seventy-three districts, plus KV comprising three districts.
d. Two development categories: urban and rural.
Table 3-5: Number of Schools in Various Distribution Parameters
Sr. no. Parameters Public Private
Numbers Percentage Numbers Percentage
a
Plains/Terai 9,130 85% 1,630 15%
Hills 17,245 85% 2,953 15%
Mountains 4,065 95% 200 5%
b
East 6,732 88% 958 12%
Central 8,243 79% 2,183 21%
West 6,585 86% 1,062 14%
Mid-west 4,910 93% 345 7%
Far-west 3,970 94% 235 6%
c Kathmandu Valley 642 29% 1,585 71%
All Other Districts(72) 29,798 90% 3,198 10%
d
Urban 3,826 73% 1,393 27%
Rural 25,972 94% 1,805 6%
Kathmandu Valley 642 29% 1,585 71%
page 29 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
3.4.1 Schools in Kathmandu Valley
52. Several studies and programs are focused on the DRR of the valley including a
focus on the schools. The basic data derived from EMIS is shown for the three
districts in the valley. This helps provide a guide/comparison for the data with
respect to the rest of the country.
53. With more data and information available, it is possible to analyze the types of
building structures, number of stories, and the material used for the schools in the
valley. This data set was also used to extrapolate some of the data available from
EMIS. The following information was generated based on what was retrieved from
the OpenDRI data. There seems to be some significant differences between the
EMIS and OpenDRI database for some of the numbers. It is recommended to
reconcile these numbers between the two data sources.
Figure 3-1: Distribution of School-related Indicators in the Kathmandu Valley
page 30 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Figure 3-2: Distribution of Various School Indicators in Districts
55. Table 3-6 shows the school distribution data based on various factors in KV which
comprises of three main districts. The percentage of private schools is higher as
compared to public schools.
Table 3-6: School Distribution in Kathmandu Valley (Public vs. Private)
Sr.
No.
Districts
All Schools Public Private
Students Schools Buildings Classrooms Schools Schools
1 Lalitpur 122,082 770 838 7,374 205 565
2 Bhaktapur 57,519 362 788 5,207 135 227
3 Kathmandu 365,649 1,095 1,048 7,157 302 793
Total KV 545,250 2,227 2,674 19,738 642 1,585
Table 3-7: School Building Typology Distribution in Kathmandu Valley
Sr.
No.Districts
RC URM Others RC URM Others RC URM Others RC URM Others Total
1 Lal i tpur 23 108 9 99 272 19 49 108 5 171 488 33 692
2 Bhaktapur 22 101 9 93 254 18 46 101 4 161 456 31 648
3 Kathmandu 29 134 12 124 340 25 61 134 7 214 608 44 866
Total 74 343 30 316 866 62 156 343 16 546 1,552 108 2,206
Total One Time InterventionRebuild Incremental Intervention
page 31 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
3.4.3 On Private Schools
56. For private schools, the DR process will mostly involve the establishment and
enforcement of the policy and requirements and corresponding certification. The
actual implementation of the DRR options will be entrusted to the owners and
operators of the schools, managed and enforced by DUDBC and other municipal
authorities.
57. Strategy 10 directly addresses private schools wherein increasing DR will be
attributed to solutions using a combination of appropriate regulations, licensing,
certification, support and incentives, and close collaboration among all sectors
involve both in the respective government agencies (MOE/DOE, MOUD/DUDBC,
municipal authorities) and private sectors (PABSON, consultants).
58. The classification or categorization of buildings and subsequent costing for direct
intervention were not carried out for private schools at this time due to limited
access and information on the particulars of private school operations.
59. Based on the discussions and viewpoints shared by the representatives of the
Private and Boarding School Organization of Nepal (PABSON), it seems that their
involvement with the ongoing School DRR program is a great possibility under
somewhat ideal conditions.
60. PABSON representatives expressed that they welcome policies in order to
implement the DR programs in private schools. Since the major hindrance to
retrofitting is that most of the school buildings are currently in rented buildings that
were not particularly designed for use as schools, or a combination of the two,
PABSON has expressed willingness to explore constructing new school facilities
adhering to DR standards if the government can provide unused governmental
land or other areas in the nearby localities. In addition, the president of PABSON
confirmed commitment of the private school owners/operators to carry out
retrofitting school buildings if soft loans can be provided. Rating schools based
vulnerability is not an option PABSON is keen on since it can directly hamper their
business. However, voluntary audits may be acceptable.
3.5 Categories of Public Schools for Intervention
61. Public schools have been further classified into public rural and public urban to
estimate the costs and resources at the appropriate level as specified earlier in
Table 3-2: Building Size Categorization Description. The following tables show the
estimated numbers for various sizes of school buildings in different administrative
and ecological belts.
62. It is clear from these tables that more urban school buildings are located in plains
compared to hills and mountains, and in the eastern, central and western region,
compared to mid and far western regions.
page 32 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 3-8: Ecological Belt-wise School Building Size Distribution
Ecological
Belts
Public Urban Public Rural Total School Buildings
A B C A B C A B C Total
Mountain 483 506 15 3,747 4,775 211 4,230 5,281 226 9,737
Hill 2,451 2,085 77 16,947 21,409 964 19,398 23,494 1,041 43,933
Terai/Plain 3,643 2,113 222 9,464 10,518 1,177 13,107 12,631 1,399 27,137
Total 6,577 4,704 314 30,158 36,702 2,352 36,735 41,406 2,666 80,807
Table 3-9: Ecological Belt-wise School Building Size Distribution
Administrative
Regions
Public Urban Public Rural Total School Buildings
A B C A B C A B C Total
East 1,820 1,222 60 7,602 8,715 588 9,422 9,937 648 20,007
Central 1,497 1,022 83 7,027 8,718 809 8,524 9,740 892 19,156
West 1,772 1,180 58 7,324 7,547 290 9,096 8,727 348 18,171
Mid-west 644 615 25 4,435 6,768 268 5,079 7,383 293 12,755
Far-west 844 665 88 3,770 4,954 397 4,614 5,619 485 10,718
Total 6,577 4,704 314 30,158 36,702 2,352 36,735 41,406 2,666 80,807
63. The number of school buildings was also estimated for various regions based on
the type of material and primary structural system used for construction (Table 3-
10). This information is vital for the cost and resource estimation.
64. Another important classification needed for the cost and resources estimation is
the number of school buildings that may need to be demolished and rebuilt,
intervened by on-time retrofitting or may be suitable for incremental safety
implementation. A summary of these numbers is shown in Table 3-11.
page 33 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 3-10: Administrative Region-wise Building Typology Distribution (Excluding KV)
Table 3-11: Administrative Region-wise School Building Numbers for Rebuild, One Time
Intervention and Incremental Intervention (Excluding KV)
RC URM Others RC URM Others RC URM Others RC URM Others Total
East 93 1,560 2,721 428 3,931 5,470 203 1,560 1,622 724 7,051 9,813 17,588
Plain 74 1,377 94 320 3,454 196 157 1,377 52 551 6,208 342 7,101
Hill 19 176 2,021 101 455 4,056 45 176 1,207 165 807 7,284 8,256
Mountain 0 7 606 7 22 1,218 1 7 363 8 36 2,187 2,231
Central 84 1,493 2,607 406 3,765 5,234 191 1,493 1,554 681 6,751 9,395 16,827
Plain 66 1,321 89 303 3,316 186 145 1,321 49 514 5,958 324 6,796
Hill 18 165 1,884 96 425 3,775 44 165 1,126 158 755 6,785 7,698
Mountain 0 7 634 7 24 1,273 2 7 379 9 38 2,286 2,333
West 67 1,006 3,025 322 2,547 6,070 152 1,006 1,807 541 4,559 10,902 16,002
Plain 39 750 50 174 1,887 107 84 750 30 297 3,387 187 3,871
Hill 28 256 2,918 148 660 5,849 68 256 1,744 244 1,172 10,511 11,927
Mountain 0 0 57 0 0 114 0 0 33 0 0 204 204
Mid west 44 733 2,079 215 1,862 4,179 101 733 1,239 360 3,328 7,497 11,185
Plain 30 591 39 134 1,483 83 64 591 23 228 2,665 145 3,038
Hill 14 141 1,627 80 366 3,264 37 141 971 131 648 5,862 6,641
Mountain 0 1 413 1 13 832 0 1 245 1 15 1,490 1,506
Farwest 40 645 1,723 184 1,627 3,460 87 645 1,028 311 2,917 6,211 9,439
Plain 30 546 38 126 1,365 78 62 546 22 218 2,457 138 2,813
Hill 10 92 1,059 51 240 2,122 23 92 631 84 424 3,812 4,320
Mountain 0 7 626 7 22 1,260 2 7 375 9 36 2,261 2,306
328 5,437 12,155 1,555 13,732 24,413 734 5,437 7,250 2,617 24,606 43,818 71,041
Rebuild Major Retrofit Minor Retrofit Total
Sr.
No.Rebuild
One Time
Intervention
Incremental
Intervention
1 East 4,374 9,829 3,385
2 Central 4,184 9,405 3,238
3 West 4,098 8,939 2,965
4 Mid west 2,856 6,256 2,073
5 Farwest 2,408 5,271 1,760
17,920 39,700 13,421Total
Regions
page 34 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Chapter 4 Parameters Used for Estimation
65. The combined data from a, b, and d, as listed in section 4.3 Data Collection and
Assimilation were used as the primary basis for the cost and resource estimation
purposes, first performed at the district level and then summarized, and
subsequently computed at the region and belt level. Several assumptions and
judgments regarding various aspects follows in the next paragraphs.
66. Approximate distributions (percentages) of building types of RC frame (with in-fill
walls), unreinforced masonry (URM), including both mud and cement mortar and
other types of buildings is determined from the analysis of available data from SSP,
OpenDRI, and discussions with relevant experts. This was broadly based on the
location of the districts in mountain, hill, and plain belts as shown in the following
table.
Regions RC Frame Brick URM Others
KV 30% 65% 5%
Plains 10% 85% 5%
Hills 3% 10% 87%
Mountains 1% 2% 97%
67. The cost was computed by a fairly comprehensive analysis by dividing the
buildings, first into three types of construction/structure type (RC frame with infill
walls, URM, and others mostly including the stone masonry and other materials);
and then into four categories according to the level of intervention for each type.
These are:
a. Buildings that need to be rebuilt, because of high vulnerability, or very old
age, or where retrofit is not practical;
b. Buildings that need major retrofit, and may be carried out by using one-
time, direct intervention;
c. Buildings that may need minor retrofit, and could be accomplished by
using the increment approach, over a longer period of time; and
d. Buildings that may need any intervention, because they have already
been retrofitted, or newly constructed using type designs, or may of very
low vulnerability.
68. The approximate percentages of these categories for the three construction
materials follow.
Intervention Level RC Frame Brick URM Others
May need to Rebuild 5% 15% 20%
May need Major Retrofit, using
one-time retrofit 35% 40% 45%
May need Minor Retrofit, using
Incremental approach 35% 30% 20%
May not need intervention 25% 15% 15%
69. These were estimated based on the study of various relevant documents and the
expert judgment of the Consultant. The entire cost model was linked to these
page 35 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
assumed percentages, and if needed can be revised when improved or alternate
percentages become available through proper surveys and evaluation.
70. The cost was estimated by first estimating the area of buildings in various
categories in each district. The number of classrooms from the EMIS database were
taken as the main indicator. By using an average area of about 50 sqm per
classroom, including margin for the corridors, and staff rooms; the average costs
determined from SSP, with adjustments for various regions and future changes due
to improved technologies, scaling up benefits, contactors cost, and design cost
were then used as the basis.
71. The resources were then estimated based on the size of the typical school
buildings. The building sizes were categorized into small, medium, and large; then
the estimated number of buildings in each category and each district were
estimated based on number of average classrooms per building. These figures for
the typical building units were calculated for resource estimation only and may not
match with the actual number of buildings on ground. This was due to the fact that
the “total no. of classrooms” was given for each school, not per building.
72. The number of engineers in various departments and the number of consultants
and contractors were estimated based on the person-daily input for various tasks,
which were estimated based on the discussions held with officials and through
other sources. These resource estimates were then used to estimate the time
frame, with due consideration to the realistic availability of these resources for the
DRR process.
73. An estimation of the number of school buildings that may be implemented through
the assistance of the community and the NGOs was also assessed based on the
size and type of school buildings in various districts and regions.
74. The base cost was estimated on the basis of the retrofitting works being carried out
for KV under the ongoing SSP, and was further modified for appreciated cost
variation factors for each belt as shown below. The corrected cost was assigned
to all schools buildings in each district to compute the total cost of intervention for
various levels and types.
Regions RC Frame Brick URM Others
KV 1 1 1
Plains 1 0.9 0.9
Hills 1.5 1.5 0.7
Mountains 2 1.7 0.7
page 36 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
4.1 Additional Data Needed For Improved Planning
75. This current planning process was based on several assumptions and
approximations of the basic data.
76. For improved planning, the following additional information is recommended to be
collected through DEO and approved in the EMIS database, as indicated in
strategy action 8.1 in the Strategic Action Plan matrix.
a. Basic information about each building, in all schools in the entire country:
Unique Building Code/ID, including school ID
Primary building construction material
o Concrete frame/walls
o Brick masonry
o Stone masonry
o Other mixed types
Number of stories
Number of classrooms
A few photographs of the building if possible
Year of construction of building
b. Basic price indicators for various districts on the following items:
Main labor components: skilled labor and mason per day
Unskilled labor per day
Main materials:
o Cement
o Bricks
o Sand
o Stone rubble
o Rebars
o Structural steel
o Steel wire mesh
page 37 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Chapter 5 Resource Estimation
77. Given that detailed data and information are not available on the hazard levels,
vulnerability size of buildings, number of stories, and type of construction materials
for the individual buildings for the district.
78. The procedure for the estimate of all costs, priority, resource, and time were based
on the available data, information, and set of assumptions, extrapolations,
indicators, and judgments. Changes in any assumed parameter or the availability
of more accurate or relevant data will result in a different set of estimates.
Therefore, the numbers and figures presented in this plan cannot be considered as
accurate at this stage. However the information presented here was based on
systematic analysis and then cross-checked with prevalent cost indicators and
previous experiences of the Consultant. The figures may be considered reasonable
and reliable for planning purposes up to a (+/-) 15% possible variation.
5.1 Procedure for Resource Estimation
79. It is very important that the DOE & DUDBC are provided appropriate and
adequate resources, facilities, and funds that are in addition to their normal
budget allocation and is specific to the management of the overall school DRR
process to ensure that the work can be carried out effectively. The cost of the
resources should be built into the overall plan.
80. The estimation of the required resources here in various categories has been
estimated using the following procedure:
a. The basic time input (person, days) for carrying out various activities for the staff
of the different departments and organizations were estimated based on the
ongoing SSP and supplemented by other additional information and
references. These resources input were factored to account for the buildings
that need to be rebuilt. The buildings that need major one-time intervention
and those that will be handled through incremental approach. Consideration
was also given to the type of construction/ material, for example, RC Frame,
URM, others, as well as the size of the building (Type A, B, C).
b. The basic resource needs were then multiplied by the appropriate number of
buildings, in each district to estimate the total person-days needed for
completing various tasks by different resources.
c. Those input needs were then summarized for the administrative regions, for the
seismological belts, and finally by the priority groups for intervention.
d. The person-days were then converted to person-months, based on the number
of working days, and finally used to compute the required number of
resources, for completing the task in assumed time-frame. If the number of
required resources seems excessive, then the number of resources was fixed as
appropriate and the required time was estimated.
page 38 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
5.2 DOE Resources
81. As indicated in the Action Plan Matrix, DOE and the DEOs are proposed to be the
primary executing agency for the school DRR process. The resources needed by
the DOE head office, and the DEOs at each district level have been estimated
based on the experience gained from the ongoing SSP and other parameters as
described in Chapter 7. The following tables summarize the estimated resources
(person-months) and the corresponding cost for various tasks for various types of
interventions.
82. The DOE head office is primarily responsible for the overall planning, management,
and coordination of the entire process. Therefore the resources needed for these
two tasks are the major components; detailed work on assessment and design and
implementation will be carried out under the respective DEOs in each district.
83. The resources indicted in following tables may be placed in the proposed new
section in DOE for managing the school physical infrastructure. Approximately 180
persons may be needed to manage the entire process for 6 to 8 years. Some of
these will be in main office and some in the five regional offices.
Table 5-1: DOE Resources and Cost Summary for KV
Task
Rebuild Major Minor All Rebuild Major Minor All
Planning 18 100 52 169 0.54 02.99 01.55 5.07
Design Management 1 12 6 20 0.04 0.45 0.23 0.72
Bidding, Billing 3 7 5 15 0.10 0.22 0.14 0.46
QE/QA/AC 1 5 2 9 0.05 0.18 0.08 0.31
Coordination 18 51 32 101 0.77 2.15 01.33 4.25
Certification 14 38 16 68 0.50 1.38 0.57 2.45
Reporting 2 5 3 10 0.06 0.15 0.10 0.30
Total 58 219 115 392 2.05 7.52 3.99 13.56
Required Resource (Person-Months)Resource Cost
(NPR Mill ions)
page 39 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 5-2: DOE Required Resources and Cost for Public School Buildings in Rural Areas
TaskPriority
Group
Rebuild Major Minor All Rebuild Major Minor All
Planning 2 193 953 453 1,600 5.95 29.30 13.94 49.19
3 217 840 353 1,410 6.67 25.83 10.86 43.36
4 215 829 350 1,394 6.61 25.48 10.77 42.86
Total 625 2,622 1,157 4,403 19.23 80.61 35.57 135.41
Design Management 2 12 119 57 188 0.45 4.40 2.09 6.93
3 14 105 44 163 0.50 3.87 1.63 6.00
4 13 104 44 161 0.50 3.82 1.62 5.93
Total 39 328 145 511 1.44 12.09 5.33 18.87
Bidding, Billing 2 36 71 41 149 1.12 2.20 1.25 4.57
3 41 63 32 135 1.25 1.94 0.98 4.16
4 40 62 32 134 1.24 1.91 0.97 4.12
Total 117 197 104 418 3.61 6.05 3.20 12.85
QE/QA/AC 2 15 48 18 81 0.54 1.77 0.67 2.98
3 16 42 14 73 0.60 1.55 0.52 2.68
4 16 42 14 72 0.60 1.53 0.52 2.65
Total 47 131 46 225 1.74 4.85 1.71 8.30
Coordination 2 194 479 273 946 8.37 20.61 11.76 40.74
3 217 421 212 851 9.36 18.13 9.14 36.63
4 215 415 210 841 9.27 17.87 9.06 36.20
Total 627 1,315 696 2,638 26.99 56.61 29.96 113.57
Certification 2 146 359 137 641 5.38 13.25 5.04 23.67
3 163 316 106 585 6.02 11.65 3.92 21.59
4 162 311 105 578 5.96 11.49 3.88 21.33
Total 470 986 348 1,805 17.35 36.39 12.84 66.59
Reporting 2 19 48 27 95 0.60 1.47 0.84 2.91
3 22 42 21 85 0.67 1.29 0.65 2.62
4 22 42 21 84 0.66 1.28 0.65 2.59
Total 63 131 70 264 1.93 4.04 2.14 8.11
Total 1,989 5,710 2,565 10,264 72.29 200.65 90.76 363.69
Required Resource (Person-Months)Resource Cost
(NPR Mi l l ion)
page 40 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 5-3: DOE Required Resources and Cost for Public School Buildings in Urban Areas
Total Resources (Rural, Urban, KV)
TasksPriority
Group
Rebuild Major Minor All Rebuild Major Minor All
Planning 2 45 233 111 389 01.35 06.99 03.32 011.66
3 25 99 40 164 0.74 02.98 01.19 04.91
4 24 102 37 164 0.72 03.07 01.12 04.91
Total 94 435 188 716 02.81 013.04 05.63 021.48
Design Management 2 3 29 14 46 0.10 01.05 0.50 01.65
3 2 12 5 19 0.06 0.45 0.18 0.68
4 1 13 5 19 0.05 0.46 0.17 0.68
Total 6 54 23 84 0.21 01.96 0.85 03.01
Bidding, Billing 2 8 17 10 36 0.25 0.52 0.30 01.08
3 5 7 4 16 0.14 0.22 0.11 0.47
4 4 8 3 16 0.13 0.23 0.10 0.47
Total 18 33 17 67 0.53 0.98 0.51 02.01
QE/QA/AC 2 3 12 4 20 0.12 0.42 0.16 0.70
3 2 5 2 8 0.07 0.18 0.06 0.30
4 2 5 1 8 0.06 0.18 0.05 0.30
Total 7 22 8 36 0.25 0.78 0.27 01.31
Coordination 2 45 117 67 229 01.89 04.91 02.80 09.60
3 25 50 24 98 01.04 02.09 01.00 04.13
4 24 51 22 98 01.00 02.15 0.94 04.10
Total 94 218 113 424 03.93 09.15 04.74 017.82
Certification 2 34 88 33 155 01.22 03.16 01.20 05.57
3 19 37 12 68 0.67 01.34 0.43 02.44
4 18 38 11 68 0.64 01.38 0.40 02.43
Total 70 163 56 290 02.53 05.88 02.03 010.44
Reporting 2 5 12 7 23 0.14 0.35 0.20 0.69
3 2 5 2 10 0.07 0.15 0.07 0.29
4 2 5 2 10 0.07 0.15 0.07 0.29
Total 9 22 11 42 0.28 0.65 0.34 01.27
Total 297 946 416 1,660 10.54 32.44 14.37 57.35
Required Resource
(Person-Months)
Resource Cost
(NPR Million)
page 41 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 5-4: DOE Required Resources and Cost for Total Public School Buildings including KV
TasksPriority
Group
Rebuild Major Minor All Rebuild Major Minor All
Plannig 1 18 100 52 169 0.54 02.99 01.55 05.07
2 238 1,186 564 1,988 07.30 36.30 17.26 60.85
3 242 939 393 1,574 07.41 28.81 12.05 48.27
4 239 931 388 1,557 07.33 28.55 11.89 47.77
Total 737 3,156 1,396 5,288 22.57 96.64 42.74 161.96
Design Management 1 1 12 6 20 0.04 0.45 0.23 0.72
2 15 148 70 234 0.55 05.44 02.59 08.58
3 15 117 49 182 0.56 04.32 01.81 06.68
4 15 116 48 180 0.55 04.28 01.78 06.62
Total 46 394 174 615 1.69 14.50 6.41 22.60
Bidding, Billing 1 3 7 5 15 0.10 0.22 0.14 0.46
2 45 89 51 184 01.37 02.72 01.55 05.64
3 45 70 35 151 01.39 02.16 01.08 04.63
4 45 70 35 149 01.37 02.14 01.07 04.59
Total 138 237 126 500 04.23 07.25 03.85 15.33
QE/QA/AC 1 1 5 2 9 0.05 0.18 0.08 0.31
2 18 60 23 100 0.66 02.19 0.83 03.68
3 18 47 16 81 0.67 01.73 0.58 02.98
4 18 47 16 80 0.66 01.72 0.57 02.95
Total 55 158 56 270 02.04 05.82 02.06 09.92
Coordination 1 18 51 32 101 0.77 02.15 01.33 04.25
2 239 596 340 1,175 10.26 25.52 14.56 50.34
3 242 471 236 949 10.39 20.22 10.15 40.76
4 239 466 233 938 10.27 20.02 10.00 40.29
Total 739 1,584 841 3,164 31.70 67.90 36.04 135.64
Certification 1 14 38 16 68 0.50 01.38 0.57 02.45
2 180 447 170 796 06.60 16.41 06.24 29.24
3 182 353 118 653 06.68 13.00 04.35 24.03
4 179 350 116 646 06.60 12.87 04.29 23.76
Total 554 1,188 420 2,162 20.38 43.65 15.44 79.47
Reporting 1 2 5 3 10 0.06 0.15 0.10 0.30
2 24 60 34 117 0.73 01.82 01.04 03.60
3 24 47 24 95 0.74 01.44 0.72 02.91
4 24 47 23 94 0.73 01.43 0.71 02.88
Total 74 158 84 316 02.26 04.85 02.57 09.69
Total 2,344 6,876 3,097 12,316 84.87 240.61 109.12 434.60
Required Resource
(Person-Months)
Resource Cost
(NPR Mill ion)
page 42 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
5.3 DEO Resources
84. Most of the work for individual school buildings are expected to be managed
through the DEOs in each district. This includes coordination with head office,
engagement of consultants, assessment and evaluation of the buildings, design
management, execution management and supervision, Q/A, and reporting. The
summary of the resources needed for these tasks and corresponding costs are
summarized in Tables 5-5 to 5-8. The detailed estimates at the district level are
shown in subsequent tables and figures.
85. The costing was based on average salary of DEO staff engaged in various tasks.
Table 5-5: DEO Required Resources and Cost for Public School Buildings in KV
Table 5-6: DEO Required Resources and Cost for Public School Buildings in Rural Areas
Task
Rebuild Major Minor All Rebuild Major Minor All
Assesment 19 53 22 94 0.57 01.59 0.66 02.82
Design Management 1 13 4 18 0.04 0.45 0.14 0.63
Bidding, Billing 7 16 5 28 0.21 0.47 0.15 0.83
Exec Mngt 12 43 13 68 0.35 01.29 0.40 02.04
Exec Supervision 442 1,642 170 2,254 10.60 39.41 4.08 54.08
QE/QA/AC 1 5 2 8 0.04 0.15 0.06 0.25
Reporting 18 50 15 83 0.43 1.19 0.37 01.99
Total 499 1,821 232 2,552 12.23 44.56 5.86 62.66
Required Resource
(Person-Months)
Resource Cost
(NPR Mill ions)
TaskPriority
Group
Rebuild Major Minor All Rebuild Major Minor All
Assesment 2 166 410 156 732 5.10 12.61 4.79 22.50
3 184 358 120 662 5.66 11.00 3.70 20.36
4 176 339 115 630 5.42 10.42 3.54 19.38
Total 526 1,107 391 2,024 16.19 34.03 12.02 62.24
Design Management 2 10 100 28 139 0.37 3.69 1.05 5.11
3 11 86 22 119 0.41 3.18 0.80 4.39
4 11 84 21 117 0.40 3.11 0.79 4.30
Total 32 270 71 374 1.19 9.98 2.64 13.80
Bidding, Billing 2 63 125 36 224 1.94 3.84 1.09 6.88
3 69 108 27 204 2.13 3.31 0.83 6.28
4 68 105 27 200 2.10 3.24 0.82 6.16
Total 201 338 89 628 6.18 10.40 2.75 19.32
Exec Mngt 2 117 386 110 614 3.61 11.87 3.39 18.87
3 131 338 85 554 4.02 10.40 2.62 17.05
4 130 333 84 547 3.98 10.24 2.59 16.82
Total 378 1,057 280 1,715 11.62 32.51 8.60 52.73
Exec Supervision 2 3,868 12,726 1,206 17,800 95.15 313.07 29.66 437.88
3 4,292 11,094 931 16,316 105.59 272.90 22.89 401.38
4 4,132 10,578 895 15,605 101.64 260.23 22.02 383.89
Total 12,292 34,398 3,031 49,722 302.38 846.20 74.57 1,223.15
QE/QA/AC 2 15 48 18 80 0.45 1.47 0.56 2.47
3 16 42 14 72 0.50 1.29 0.43 2.23
4 16 41 14 72 0.50 1.27 0.43 2.20
Total 47 131 46 224 1.44 4.03 1.42 6.90
Reporting 2 193 476 136 806 4.76 11.72 3.34 19.83
3 217 420 106 743 5.33 10.33 2.61 18.27
4 215 414 105 734 5.29 10.19 2.58 18.06
Total 625 1,311 347 2,283 15.38 32.25 8.54 56.16
Total 14,101 38,613 4,256 56,970 354.37 969.39 110.53 1,434.30
Resource Cost
(NPR Mi l l ion)
Required Resource
(Person-Months)
page 43 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 5-7: DEO Required Resources and Cost for Public School Buildings in Urban Areas
TaskPriority
Group
Rebuild Major Minor All Rebuild Major Minor All
Assesment 2 35 91 34 161 01.05 02.74 01.03 04.83
3 19 38 12 70 0.57 01.15 0.36 02.09
4 19 40 12 71 0.56 01.21 0.35 02.13
Total 73 170 58 301 02.19 05.10 01.75 09.04
Design Management 2 2 24 7 33 0.08 0.86 0.25 01.19
3 1 10 2 14 0.04 0.36 0.09 0.49
4 1 10 2 14 0.04 0.37 0.08 0.49
Total 5 44 11 61 0.17 01.60 0.41 02.18
Bidding, Billing 2 14 30 9 53 0.43 0.90 0.26 01.59
3 8 13 3 23 0.23 0.38 0.09 0.70
4 7 13 3 23 0.22 0.39 0.08 0.70
Total 30 55 14 99 0.89 01.66 0.43 02.98
Exec Mngt 2 27 94 27 148 0.81 02.82 0.80 04.44
3 15 40 10 64 0.45 01.20 0.29 01.93
4 14 41 9 64 0.43 01.23 0.27 01.93
Total 56 175 45 276 01.69 05.24 01.36 08.29
Exec Supervision 2 830 2,880 271 3,981 19.92 69.12 6.51 95.55
3 453 1,210 96 1,758 10.86 29.03 2.29 42.19
4 443 1,265 93 1,801 10.63 30.36 2.22 43.22
Total 1,726 5,355 459 7,540 41.41 128.52 11.03 180.96
QE/QA/AC 2 3 12 4 19 0.10 0.35 0.13 0.58
3 2 5 2 8 0.06 0.15 0.05 0.25
4 2 5 1 8 0.05 0.15 0.04 0.25
Total 7 22 8 36 0.21 0.65 0.23 01.09
Reporting 2 45 117 33 195 01.08 02.80 0.80 04.67
3 25 50 12 86 0.59 01.19 0.29 02.07
4 24 51 11 86 0.57 01.23 0.27 02.07
Total 94 217 56 367 02.24 05.22 01.35 08.81
Total 1,990 6,039 653 8,681 48.81 147.99 16.55 213.35
Resource Cost
(NPR Mill ion)
Required Resource
(Person-Months)
page 44 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 5-8: DEO Required Resources and Cost for Total Public School Buildings including KV
5.4 DUDBC Resources
86. Together with DOE and DEOs, the role of DUDBC is of paramount importance in the
overall DRR process. Technical advice, quality assurance, and the certification of
the private school buildings will be provided in some of the areas where specific
resources will be needed. A special school section may need to be added in
DUDBC to handle these tasks. The resources and cost of this input was estimated.
TaskPriority
Group
Rebuild Major Minor All Rebuild Major Minor All
Assesment 1 19 53 22 94 0.57 1.59 .66 2.82
2 201 501 190 892 6.15 15.35 5.82 27.32
3 203 396 132 732 6.24 12.15 4.06 22.44
4 195 379 127 701 5.99 11.63 3.89 21.51
Total 618 1,330 471 2,419 18.94 40.72 14.44 74.09
Design Management 1 1 13 4 18 0.04 0.45 0.14 0.63
2 12 124 35 172 0.46 4.55 1.30 6.30
3 12 96 24 133 0.45 3.54 0.89 4.88
4 12 95 24 130 0.45 3.48 0.87 4.80
Total 38 327 87 452 1.40 12.03 3.19 16.62
Bidding, Billing 1 7 16 5 28 .21 .47 .15 .83
2 78 155 44 277 2.37 4.74 1.35 8.47
3 77 120 30 228 2.37 3.69 .92 6.98
4 76 118 29 224 2.33 3.63 .90 6.86
Total 238 409 109 756 7.28 12.53 3.32 23.14
Exec Mngt 1 12 43 13 68 .35 1.29 .40 2.04
2 145 480 137 761 4.42 14.69 4.19 23.30
3 146 378 95 619 4.47 11.60 2.91 18.97
4 144 374 93 611 4.41 11.47 2.86 18.74
Total 446 1,275 338 2,059 13.65 39.05 10.36 63.07
Exec Supervision 1 442 1,642 170 2,254 10.60 39.41 4.08 54.08
2 4,698 15,606 1,477 21,781 115.07 382.19 36.17 533.43
3 4,745 12,303 1,026 18,074 116.45 301.93 25.18 443.57
4 4,575 11,844 988 17,406 112.28 290.59 24.24 427.11
Total 14,459 41,395 3,661 59,515 354.39 1,014.12 89.67 1,458.19
QE/QA/AC 1 1 5 2 8 .04 .15 .06 .25
2 18 59 23 100 .55 1.81 .69 3.05
3 18 47 16 81 .56 1.44 .48 2.48
4 18 47 16 80 .55 1.43 .48 2.45
Total 55 158 56 269 1.69 4.83 1.71 8.23
Reporting 1 18 50 15 83 .43 1.19 .37 1.99
2 238 593 169 1,001 5.84 14.52 4.14 24.50
3 242 470 118 829 5.93 11.52 2.89 20.34
4 239 465 116 821 5.86 11.42 2.85 20.14
Total 719 1,528 403 2,650 17.63 37.46 9.89 64.98
Total 16,573 46,423 5,125 68,120 414.99 1,160.75 132.58 1,708.32
Required Resource
(Person-Months)
Resource Cost
(NPR Mill ion)
page 45 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 5-9: DUDBC Required Resources and Cost for Public School Buildings in KV
Table 5-10: DUDBC Required Resources and Cost for Public School Buildings in Rural Areas
Table 5-11: DUDBC Required Resources and Cost for Public School Buildings in Urban Areas
Table 5-12: DUDBC Required Resources and Cost for Total Public School Buildings including
KV
Task
Rebuild Major Minor All Rebuild Major Minor All
Technical Advise 14 164 39 212 0.66 7.57 1.80 10.0
Quality Assurance 15 57 15 69 0.69 1.92 0.51 3.12
Total 29 221 54 281 1.35 9.49 2.31 13.16
Resource Cost
(NPR Millions)
DUDBC Required Resource
(Person-Months)
TaskPriority
Group
Rebuild Major Minor All Rebuild Major Minor All
Technical Advise 2 139 1,382 255 1,655 6.94 69.03 12.74 88.71
3 152 1,129 197 1,438 7.59 56.39 9.84 73.83
4 147 1,068 190 1,375 7.34 53.35 9.49 70.18
Total 438 3,579 642 4,659 21.88 178.77 32.07 232.72
Quality Assurance 2 107 496 110 663 3.90 18.08 4.01 25.99
3 128 438 95 596 4.67 15.97 3.46 24.09
4 127 453 95 589 4.63 16.51 3.46 24.60
Total 362 1,387 300 2,049 13.19 50.56 10.94 74.69
Total 800 4,966 942 6,708 35.07 229.33 43.00 307.40
DUDBC Required Resource
(Person-Months)
Resource Cost
(NPR Mill ion)
TaskPriority
Group
Rebuild Major Minor All Rebuild Major Minor All
Technical Advise 2 38 297 85 376 1.83 14.29 4.09 20.20
3 27 127 39 155 1.30 6.11 1.88 9.28
4 27 146 39 160 1.30 7.02 1.88 10.20
Total 92 570 163 825 4.43 27.42 7.84 39.68
Quality Assurance 2 32 117 32 161 1.12 4.09 1.12 6.34
3 22 55 38 70 0.77 1.93 1.33 4.04
4 32 67 27 70 1.12 2.35 0.95 4.42
Total 86 239 97 422 3.02 8.37 3.40 14.79
Total 178 809 260 1,247 7.44 35.79 11.25 54.48
Resource Cost
(NPR Million)
DUDBC Required Resource
(Person-Months)
TaskPriority
Group
Rebuild Major Minor All Rebuild Major Minor All
Technical Advise 1 14.29 163.64 39 212.31 0.66 7.57 1.80 10.03
2 177 1,679 340 2,031 8.77 83.32 16.83 108.91
3 179 1,256 236 1,594 8.89 62.50 11.72 83.11
4 174 1,214 229 1,535 8.64 60.37 11.37 80.38
Total 544 4,313 844 5,372 26.96 213.76 41.71 282.43
Quality Assurance 1 15 57 15 68.785 0.69 1.92 0.51 3.12
2 139 613 142 824 5.02 22.17 5.13 32.32
3 150 493 133 666 5.44 17.90 4.80 28.13
4 159 520 122 660 5.75 18.86 4.41 29.03
Total 463 1,683 412 2,218 16.91 60.85 14.85 92.60
Total 1,007 5,995 1,256 7,590 43.87 274.61 56.56 375.04
DUDBC Required Resource
(Person-Months)
Resource Cost
(NPR Million)
page 46 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
5.5 Consultants
87. Considering the specialized nature of the DRR process and the interventions, the
engagement of the consultants for various tasks will be necessary to support the
DOE and DEO, as well as to ensure for the quality of the work to be carried out.
88. The role of consultants and estimated resources for each task were estimated and
listed in the following table. This indicates the number of various professionals and
staff needed. The actual assignment of the work may be based on lump-sum cost
or cost plus basis. The traditional fee estimation based on the percentage of
construction cost may not be appropriate for retrofit, where the resource input
from engineers and staff is much larger than a corresponding new building. As can
be seen from the table below, the cost of assessment and evaluation is a major
component of the overall resource cost.
Table 5-13: Consultants Required Resources and Cost for Public School Buildings in KV
Table 5-14: Consultants Required Resources and Cost for Public School Buildings in Rural
Areas
Task
Rebuild Major Minor All Rebuild Major Minor All
Assessment Engineers 113 419 130 662 3.71 13.84 4.30 21.86
Assessment Support Staff 279 778 322 1,379 6.14 17.12 7.08 30.34
Design 25 351 147 522 0.87 12.35 5.17 18.39
Supervision 27 302 13 342 1.04 11.63 0.48 13.15
Certification 21 237 98 357 0.70 7.83 3.24 11.78
Total 465 2,087 710 3,262 12.47 62.76 20.29 95.51
Resource and O/H Cost
(NPR Mill ions)
Estimated Resource For Consultants
(Person-Months)
TaskPriority
Group
Rebuild Major Minor All Rebuild Major Minor All
Assessment Engineers 2 1,005 3,309 942 5,256 37.98 125.09 35.60 198.67
3 1,118 2,890 728 4,736 42.25 109.25 27.52 179.03
4 1,073 2,748 699 4,520 40.56 103.89 26.42 170.87
Total 3,196 8,948 2,369 14,513 120.79 338.23 89.55 548.57
Assessment Support Staff 2 2,699 6,654 2,526 11,879 68.03 167.67 63.66 299.35
3 3,013 5,837 1,961 10,811 75.92 147.09 49.42 272.43
4 2,939 5,652 1,912 10,503 74.05 142.43 48.19 264.68
Total 8,651 18,143 6,400 33,193 218.00 457.19 161.27 836.46
Design 2 209 2,596 989 3,793 8.67 107.93 41.11 157.70
3 230 2,236 752 3,218 9.55 92.96 31.28 133.79
4 221 2,127 723 3,071 9.18 88.44 30.06 127.68
Total 659 6,958 2,464 10,081 27.39 289.33 102.44 419.17
Supervision 2 254 2,499 95 2,847 11.18 110.19 4.18 125.56
3 284 2,196 74 2,554 12.50 96.86 3.25 112.62
4 274 2,101 71 2,446 12.06 92.66 3.14 107.86
Total 811 6,796 240 7,847 35.75 299.72 10.57 346.04
Certification 2 221 2,179 828 3,229 8.37 82.37 31.30 122.04
3 249 1,927 648 2,824 9.41 72.85 24.50 106.75
4 243 1,872 634 2,749 9.20 70.76 23.96 103.92
Total 714 5,978 2,110 8,802 26.97 225.97 79.77 332.71
Total 14,029 46,823 13,582 74,435 428.91 1,610.45 443.60 2,482.95
Resource Cost
(NPR Mill ion)
Estimated Resource For Consultants
(Person-Months)
page 47 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 5-15: Consultants Required Resources and Cost for Public School Buildings in Urban
Areas
Table 5-16: Consultants Required Resources and Cost for Total Public School Buildings
including KV
TaskPriority
Group
Rebuild Major Minor All Rebuild Major Minor All
Assessment Engineers 2 214 745 211 1,171 7.07 24.60 6.96 38.63
3 117 313 74 504 3.86 10.32 2.45 16.63
4 115 328 72 515 3.79 10.82 2.38 16.99
Total 446 1,386 357 2,189 14.72 45.74 11.79 72.24
Assessment Support Staff 2 601 1,560 590 2,750 13.21 34.32 12.98 60.51
3 329 660 210 1,199 7.24 14.52 4.62 26.38
4 320 686 201 1,207 7.05 15.10 4.42 26.56
Total 1,250 2,906 1,001 5,157 27.50 63.93 22.02 113.45
Design 2 45 587 222 853 1.57 20.66 7.81 30.04
3 24 243 77 344 0.85 8.55 2.70 12.10
4 24 253 74 351 0.83 8.91 2.61 12.36
Total 92 1,083 373 1,548 3.25 38.12 13.13 54.50
Supervision 2 55 569 21 645 2.11 21.90 0.83 24.84
3 30 241 8 278 1.16 9.26 0.29 10.72
4 30 252 7 289 1.14 9.72 0.28 11.14
Total 114 1,062 36 1,213 4.40 40.89 1.41 46.69
Certification 2 50 514 195 758 1.64 16.96 6.43 25.03
3 27 219 70 316 0.90 7.23 2.30 10.43
4 27 228 67 322 0.88 7.53 2.21 10.62
Total 104 961 331 1,396 3.42 31.72 10.94 46.08
Total 2,006 7,398 2,099 11,503 53.29 220.40 59.27 332.96
Resource and O/H Cost
(NPR Mill ion)
Estimated Resource For Consultants
(Person-Months)
TaskPriority
Group
Rebuild Major Minor All Rebuild Major Minor All
Assessment Engineers 1 113 419 130 662 3.71 13.84 4.30 21.86
2 1,219 4,055 1,153 6,426 45.05 149.69 42.56 237.30
3 1,235 3,203 802 5,240 46.11 119.57 29.97 195.66
4 1,188 3,076 771 5,035 44.35 114.71 28.80 187.86
Total 3,754 10,753 2,857 17,364 139.23 397.81 105.64 642.67
1 279 778 322 1,379 6.14 17.12 7.08 30.34
2 3,300 8,213 3,116 14,630 81.24 201.99 76.64 359.86
3 3,342 6,497 2,171 12,010 83.16 161.61 54.04 298.80
4 3,259 6,338 2,113 11,711 81.10 157.53 52.61 291.24
Total 10,180 21,827 7,722 39,729 251.64 538.24 190.37 980.25
Design 1 25 351 147 522 0.87 12.35 5.17 18.39
2 253 3,183 1,211 4,646 10.24 128.59 48.92 187.75
3 254 2,479 829 3,561 10.40 101.51 33.98 145.89
4 244 2,380 797 3,422 10.01 97.36 32.67 140.04
Total 776 8,392 2,984 12,152 31.51 339.80 120.74 492.06
Supervision 1 27 302 13 342 1.04 11.63 0.48 13.15
2 308 3,068 116 3,492 13.29 132.10 5.01 150.39
3 314 2,437 81 2,832 13.66 106.13 3.55 123.34
4 303 2,354 79 2,735 13.20 102.38 3.42 119.00
Total 952 8,160 289 9,401 41.19 352.23 12.46 405.88
Certification 1 21 237 98 357 0.70 7.83 3.24 11.78
2 271 2,693 1,023 3,987 10.00 99.33 37.73 147.07
3 276 2,146 718 3,140 10.31 80.07 26.81 117.19
4 270 2,100 701 3,071 10.08 78.29 26.17 114.53
Total 838 7,177 2,540 10,555 31.09 265.52 93.95 390.56
Total 16,500 56,309 16,391 89,201 494.67 1,893.61 523.16 2,911.43
Assessment Support
Staff
Estimated Resource For Consultants
(Person-Months)
Resource and O/H Cost
(NPR Mill ion)
page 48 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
5.6 Summary of the Resource Planning
89. Cooperation between MOE/DOE & DUDBC is very important in resource
estimation. In addition, both departments must be provided appropriate and
adequate resources, facilities, and funds in addition to their annual/expected
budget allocation. This additional fund will be utilized specifically for the
management of overall school DRR process to ensure that the work can be carried
out effectively.
90. A work plan is needed for the utilization of the resources and the expenditures to
complete the process in a reasonable timeframe. Balancing the required
resources and funds, against the availability of these, and the target time of
completion is always a challenge and depends on many factors that are often
beyond the bounds of the program and project.
91. Table 5-17 shows various possible scenarios of the resources and time based on
average resource-months during the duration.
Table 5-17: The Trade-off between Number of Resources and Time
92. A program duration of 6 to 8 years is considered to reasonable provided with
manageable resources for each category. This timeframe is used in developing the
work plan. A maximum duration of 8 years was selected for the purpose of
determining the timeline.
93. The overall work plan is shown in Chapter 8. The major work on rebuilding and
direct intervention is proposed to be completed by 2020, whereas the incremental
work, together with monitoring and evaluation tasks, may extend to 2022.
)
page 49 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Chapter 6 Cost Estimation
6.1 Direct Cost of Intervention
94. The following table presents the overall intervention cost summary for public
schools. The details were categorized by regions and the belts. The overall
information for the entire country is provided in the last row. The maximum cost is
indicated for the central region and in the hills; the lowest is at the far west and the
mountains.
Table 6-1: Overall Intervention Cost Summary for Public Schools (Regional)
Table 6-2: Overall Intervention Cost Summary for Public Schools (Belt-wise)
Demolish -
Rebuild
Major Retrofit
(One-Time)
Minor Retrofit
(Incremental
Approach)
Total
A-Regions
1 East 6,732 20,007 2,633,650 4,686 4,241 1,938 10,865
2 Central 8,253 20,023 3,066,896 5,570 4,957 2,219 12,745
3 West 6,581 18,171 2,983,100 5,191 4,490 1,978 11,659
4 Mid West 4,907 12,755 1,847,100 3,217 2,822 1,251 7,290
5 Far West 3,967 10,718 1,442,500 2,482 2,154 953 5,589
B-Belts
1 Plains 9,124 27,137 3,539,500 7,080 7,567 3,895 18,542
2 Hills 17,255 44,800 6,963,996 11,829 9,461 3,842 25,132
3 Mountains 4,061 9,737 1,469,750 2,237 1,636 602 4,475
Total 30,440 81,674 11,973,246 21,146 18,663 8,339 48,148
Cost
(NPR Million)Sr.
NoClassification
Schools
(Nos)
Buildings
(Nos)
Estimated
Building Area
(Sqm)
Demolish -
Rebuild
Major
Retrofit
(One-Time)
Minor Retrofit
(Incremental
Approach)
Total
East 6,732 20,007 2,633,650 4,686 4,241 1,938 10,865
Plains 2,484 8,142 1,001,150 2,010 2,141 1,098 5,249
Hills 3,274 9,345 1,231,200 2,063 1,651 674 4,388
Mountains 974 2,520 401,300 613 449 165 1,228
Central 8,253 20,023 3,066,896 5,570 4,957 2,219 12,745
Plains 3,166 7,826 1,005,050 2,004 2,149 1,107 5,259
Hills 4,004 9,562 1,704,946 3,024 2,413 967 6,404
Mountains 1,083 2,635 356,900 542 395 145 1,082
West 6,581 18,171 2,983,100 5,191 4,490 1,978 11,659
Plains 1,444 4,450 632,950 1,266 1,351 697 3,314
Hills 5,045 13,481 2,295,450 3,842 3,077 1,258 8,178
Mountains 92 240 54,700 83 61 23 167
Mid West 4,907 12,755 1,847,100 3,217 2,822 1,251 7,290
Plains 1,165 3,498 505,600 1,011 1,084 557 2,652
Hills 2,888 7,523 1,087,550 1,821 1,457 590 3,868
Mountains 854 1,734 253,950 385 281 103 769
Far West 3,967 10,718 1,442,500 2,482 2,154 953 5,589
Plains 865 3,221 394,750 789 842 435 2,066
Hills 2,044 4,889 644,850 1,079 863 352 2,294
Mountains 1,058 2,608 402,900 614 449 165 1,228
Entire Country 30,440 81,674 11,973,246 21,146 18,663 8,339 48,148
RegionSchools
(Nos)
Buildings
(Nos)
Estimated
Building Area
(Sqm)
Cost
(NPR Mill ion)
page 50 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
95. The next tables provide breakdowns of the cost summary for public schools
corresponding to sub-regions and the different types of terrain. This provides the
next level of detail for sub-regional planning and budgeting. The maximum cost is
indicated in West-Hills and the lowest is observed in West-Mountains.
96. The cost distribution in various regions and belts are also shown in the following
figures. Further detail on the cost for demolishing/rebuilding and the major or minor
retrofitting entails per region as categorized per district are also provided in these
table.
97. These figures will also be useful for budgeting and planning at the district level
when combined with prioritization plan given in the following sections.
Table 6-3: Overall Intervention Cost Summary for Public Schools – Districts (East)
Demolish -
Rebuild
Major Retrofit
(One-Time)
Minor Retrofit
(Incremental
Approach)
Total
1 Taplejung 323 713 130,800 199 145 54 398
2 Panchthar 393 1,132 157,800 264 211 86 562
3 Ilam 432 1,309 159,600 267 214 87 569
4 Jhapa 433 1,527 206,900 412 442 228 1,081
5 Morang 599 1,925 258,000 516 551 284 1,351
6 Sunsari 505 1,764 232,950 466 498 257 1,221
7 Dhankuta 316 1,227 156,800 263 210 86 559
8 Terhathum 240 834 111,550 187 150 61 398
9 Sankhuwasabha 381 1,023 161,700 249 184 67 500
10 Bhojpur 417 1,114 161,350 270 216 88 574
11 Solukhumbu 270 784 108,800 165 120 44 330
12 Okhaldhunga 338 969 129,450 217 173 71 461
13 Khotang 690 1,344 182,300 305 244 100 648
14 Udayapur 448 1,416 172,350 290 233 95 618
15 Saptari 473 1,474 153,000 315 327 163 805
16 Siraha 474 1,452 150,300 300 323 166 789
Sr.
No
Ea
st
Schools
(Nos)
Buildings
(Nos)
Estimated
Building Area
(Sqm)
Cost
(NPR mi l l ion)
Re
gio
ns
Districts
page 51 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 6-4: Overall Intervention Cost Summary for Public Schools – Districts (Central & West)
Demolish -
Rebuild
Major Retrofit
(One-Time)
Minor Retrofit
(Incremental
Approach)
Total
17 Dhanusha 414 1,281 148,750 297 318 164 780
18 Mahottari 400 1,152 137,000 274 294 151 719
19 Sarlahi 725 1,114 133,550 267 286 147 701
20 Sindhul i 570 1,479 228,650 383 307 125 815
21 Ramechhap 475 1,257 197,400 330 264 108 702
22 Dolakha 395 865 118,850 181 133 49 363
23 Sindhupalchok 584 1,532 192,050 291 212 78 582
24 Kavrepalanchok 616 1,690 281,050 472 378 154 1,004
25 La l i tpur 205 343 151,107 332 261 99 692
26 Bhaktapur 135 295 97,540 214 169 64 446
27 Kathmandu 302 229 78,100 171 135 51 357
28 Nuwakot 531 1,348 187,400 314 251 102 667
29 Rasuwa 104 238 46,000 69 50 18 138
30 Dhading 621 1,391 241,800 405 324 132 861
31 Makwanpur 549 1,530 241,900 406 326 133 865
32 Rautahat 397 1,028 124,400 249 266 137 652
33 Bara 437 1,029 131,750 263 282 145 690
34 Parsa 379 790 91,050 182 195 100 478
35 Chitwan 414 1,432 238,550 472 506 262 1,240
36 Gorkha 534 1,315 224,500 376 300 123 799
37 Lamjung 380 1,095 181,100 303 242 99 644
38 Tanahu 632 1,433 231,700 390 313 127 830
39 Syangja 541 1,712 240,300 404 324 132 860
40 Kaski 444 1,207 291,250 487 386 159 1,033
41 Manang 27 73 12,850 20 14 5 40
42 Mustang 65 167 41,850 64 47 17 128
43 Myagdi 246 639 123,800 209 165 69 442
44 Parbat 317 961 146,100 245 197 80 522
45 Baglung 536 1,480 243,050 406 325 133 864
46 Gulmi 562 1,150 214,100 358 286 117 761
47 Palpa 448 1,444 226,150 380 305 124 809
48 Nawalparas i 566 1,984 294,450 585 629 321 1,534
49 Rupandehi 483 1,387 204,250 408 435 225 1,068
50 Kapi lbastu 395 1,079 134,250 268 288 148 704
51 Arghakhanchi 405 1,045 173,400 291 233 95 620
Estimated
Building Area
(Sqm)
Cost
(NPR mi l l ion)Sr.
No
Re
gio
ns
DistrictsSchools
(Nos)
Buildings
(Nos)
Ce
ntr
al
We
st
page 52 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 6-5: Overall Intervention Cost Summary for Public Schools – Districts (Mid West and
Far West)
98. Tables 6-6 and 6-8 provide a general overview of the cost model basis. Factors
include the base cost, details on material re-use, inflation set to 5% per annum, the
benefits of improved technology, and other factors together with the cumulative
factor over periods required for rebuild, major retrofit, and minor retrofit. The
approximate duration for cost inflation is listed below each level of intervention.
Demolish -
Rebuild
Major Retrofit
(One-Time)
Minor Retrofit
(Incremental
Approach)
Total
52 Pyuthan 354 1,062 146,750 246 197 80 523
53 Rolpa 397 852 148,750 248 198 81 528
54 Rukum 373 951 152,200 254 203 83 540
55 Salyan 324 629 95,550 161 129 51 340
56 Dang 432 1,446 229,500 459 493 253 1,204
57 Banke 377 1,080 150,350 299 322 166 786
58 Bardiya 356 972 125,750 251 270 139 660
59 Surkhet 506 1,509 210,700 352 281 115 748
60 Dai lekh 506 1,513 185,150 311 250 102 663
61 Ja jarkot 428 1,007 148,450 248 198 81 528
62 Dolpa 117 279 50,600 77 56 21 154
63 Jumla 156 15 1,750 3 2 1 5
64 Kal ikot 308 654 99,550 151 110 41 302
65 Mugu 140 438 52,900 80 58 21 160
66 Humla 133 348 49,150 75 54 20 149
67 Bajura 261 615 93,650 142 104 38 284
68 Bajhang 459 1,092 179,500 274 200 74 547
69 Achham 755 1,268 167,750 281 224 92 597
70 Doti 492 1,085 146,650 245 196 80 521
71 Kai la l i 567 2,200 240,500 481 514 265 1,260
72 Kanchanpur 298 1,021 154,250 309 328 170 806
73 Dadeldhura 253 943 113,800 191 153 62 406
74 Baitadi 544 1,593 216,650 362 290 118 770
75 Darchula 338 901 129,750 196 145 53 394
Cost
(NPR mi l l ion)Sr.
No
Re
gio
ns
DistrictsSchools
(Nos)
Buildings
(Nos)
Estimated
Building Area
(Sqm)
Mid
We
st
Fa
r W
est
page 53 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
6.1.1 Kathmandu Valley
Table 6-6: Cost Basis Model for Public School Buildings in KV
Table 6-7: Direct Intervention Cost for Public School Buildings in KV
6.1.2 Public Schools in Rural Areas
Table 6-8: Cost Basis Model for Public School Buildings in Rural Areas
Rebuild
(4 Years)
Major
Retrofit
(6 Years)
Minor
Retrofit
(8 years)
Rebuild
(4 Years)
Major
Retrofit
(6 Years)
Minor
Retrofit
(8 years)
Rebuild
(4 Years)
Major
Retrofit
(6 Years)
Minor
Retrofit
(8 years)
1 Base Cost (NPR/SqM) 22,000 3,800 1,400 19,000 6,300 2,800 16,000 4,000 1,700
2 Material Re-use 0.90 1.00 1.00 0.75 1.00 1.00 0.70 1.00 1.00
3 Inflation (5% per year) 1.10 1.15 1.20 1.10 1.15 1.20 1.10 1.15 1.20
4 Improved Technology Factors 0.95 0.90 0.90 1.00 0.85 0.85 0.90 0.80 0.80
5 Other Factors 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
6 Cumulative Factor 0.94 1.04 1.08 0.83 0.98 1.02 0.69 0.92 0.96
Avg Cost Used (NPR/SqM) 20,691 3,933 1,512 15,675 6,158 2,856 11,088 3,680 1,632
Sr.
No
RC Frame Others (Stone Masonry etc.)URM (Brick Masonry)
Cost and Cost Modification
Factors
Demolish -
Rebuild
Major Retrofit
(One-Time)
Minor Retrofit
(Incremental
Approach)
Total
Nos Nos SqM NPR (m) NPR (m) NPR (m) NPR (m)
1 Lalitpur 205 343 151,107 332 261 99 692
2 Bhaktapur 135 295 97,540 214 169 64 446
3 Kathmandu 302 229 78,100 171 135 51 357
Entire Country 642 867 326,746 717 565 213 1,495
Cost Sr.
NoDistrict
Number of
Schools
Number of
Buildings
Estimated
Building Area
Rebuild
(4 Years)
Major
Retrofit
(6 Years)
Minor
Retrofit
(8 years)
Rebuild
(4 Years)
Major
Retrofit
(6 Years)
Minor
Retrofit
(8 years)
Rebuild
(4 Years)
Major
Retrofit
(6 Years)
Minor
Retrofit
(8 years)
1 Base Cost (NPR/SqM) 22,500 4,000 1,500 19,000 6,500 2,800 15,000 3,500 1,500
2 Material Re-use 0.90 1.00 1.00 0.75 1.00 1.00 0.70 1.00 1.00
3 Inflation (5% per year) 1.10 1.15 1.20 1.10 1.15 1.20 1.10 1.15 1.20
4 Improved Technology Factors 0.95 0.90 0.90 1.00 0.85 0.85 0.90 0.80 0.80
5 Other Factors 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
6 Cumulative Factor 0.94 1.04 1.08 0.83 0.98 1.02 0.69 0.92 0.96
Avg Cost Used (NPR/SqM) 21,161 4,140 1,620 15,675 6,354 2,856 10,395 3,220 1,440
Cost and Cost Modification
Factors
Sr.
No
RC Frame URM (Brick Masonry) Others (Stone Masonry etc.)
page 54 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 6-9: Direct Intervention Cost for Public School Buildings in Rural Areas
6.1.3 Public Schools in Urban Areas
100. The cost basis model for public schools in urban areas is the same as KV, please
refer to Table 6-6: Cost Basis Model for Public School Buildings in KV
Table 6-10: Direct Intervention Cost for Public School Buildings in Urban Areas
Demolish -
Rebuild
Major Retrofit
(One-Time)
Minor Retrofit
(Incremental
Approach)
Total
A-Regions
1 East 5,765 16,905 2,178,550 3,831 3,427 1,547 8,804
2 Central 6,728 16,554 2,329,400 4,083 3,661 1,656 9,400
3 West 5,562 15,161 2,457,550 4,218 3,593 1,562 9,374
4 Mid West 4,474 11,471 1,649,200 2,851 2,484 1,094 6,429
5 Far West 3,443 9,121 1,200,450 2,029 1,720 743 4,492
B-Belts
1 Plains 7,229 21,159 2,613,650 5,226 5,627 2,878 13,730
2 Hills 15,030 39,320 5,882,650 9,791 7,809 3,190 20,790
3 Mountains 3,713 8,733 1,318,850 1,995 1,449 534 3,978
Total 25,972 69,212 9,815,150 17,011 14,885 6,602 38,499
Cost
(NPR Mill ion) Schools
(Nos)
Buildings
(Nos)
Estimated
Building
Area
(Sqm)
Sr.
NoClassification
Demolish
- Rebuild
Major
Retrofit
(One-Time)
Minor Retrofit
(Incremental
Approach)
Total
Nos Nos SqM NPR (m) NPR (m) NPR (m) NPR (m)
A-Regions
1 East 967 3,102 455,100 855 814 391 2,061
2 Central 883 2,602 410,750 769 731 350 1,850
3 West 1,019 3,010 525,550 973 896 416 2,285
4 Mid West 433 1,284 197,900 366 338 157 860
5 Far West 524 1,597 242,050 453 434 209 1,097
B-Belts
1 Plains 1,895 5,978 925,850 1,854 1,940 1,017 4,811
2 Hills 1,583 4,613 754,600 1,320 1,087 439 2,846
3 Mountains 348 1,004 150,900 242 186 68 497
Total 3,826 11,595 1,831,350 3,417 3,213 1,523 8,154
Cost
Sr.
NoClassification
Number of
Schools
Number of
Buildings
Estimated
Building Area
page 55 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
6.2 Summary of Costs
101. A total of about 500 Billion NPR (nearly USD 500 Million), may be needed for
completing the DRR of schools, projected for a duration of 8 to 10 years. The
following table provides a breakdown of important cost components, together
with percentages of the total costs, as indicated for easy comparison.
Table 6-11: Summary of Overall Cost for DRR of Public School Buildings in Nepal
102. It is important to note that in order for DOE and DEOs to able to undertake this
work, about 2.3 Billion NPR should be provided as additional budget, spread over a
period of about 8 years.
Sr.
No
Cost
(M NPR)% of Each % of Total
1 Direct Intervention Cost
1.1 Rebuild 21,146.00 43.9%
1.2 Major, one time intervention 18,663.00 38.8%
1.3 Incremental Intervention 8,339.00 17.3%
1.4 Total 48,148.00 100% 86.4%
2 DOE Resource Cost
2.1 Planning 161.96 33.4%
2.2 Design Mngt. 22.60 4.7%
2.3 Bidding& Billing 15.33 3.2%
2.4 QE/QA/QC 09.92 2.0%
2.5 Coordination & Reporting 145.33 30.0%
2.6 Certification 79.47 16.4%
2.7 Infrastructure, Facilities and Tools 50.00 10.3%
2.8 Total 484.60 100.0% 0.9%
3 DEO Resources
3.1 Assessment 74.09 4.0%
3.2 Design Mngt. 16.62 0.9%
3.3 Bidding & Billing 23.14 1.2%
3.4 Execution Mngt. & Supervision 1,521.25 81.8%
3.5 Q/A & Reporting 75.21 4.0%
3.6 Infrastructure, Facilities & Tools 150.00 8.1%
3.7 Total 1,860.31 100.0% 3.3%
4 DUDBC Resources
4.1 Technical Advise 282.43 76.2%
4.2 QE/QA/QC 92.60 23.8%
4.3 Total 375.04 100.0% 0.7%
5 Consultants
5.1 Assessment 1,622.93 55.8%
5.2 Design 487.50 16.8%
5.3 Supervision & Certification 797.45 27.4%
5.5 Total 2,907.88 100.0% 5.2%
6 Other Costs
6.1 Coordination , Monitoring and Evaluation 200.00 10.3% 0.4%
6.3 Public Awareness and Capacity Building 500.00 25.6% 0.9%
6.4 Risk Assessment and Mapping 300.00 15.4% 0.5%
6.5 Research and Development 350.00 17.9% 0.6%
6.6 Others and Miscellaneous 600.00 30.8% 1.1%
6.7 Total 1,950.00 100.0%
Total Estimated Cost 55,725.82 100.0%
Cost Components
page 56 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
103. As DUDBC is expected to play an important part in supporting the DRR of both
public and private schools, a budget of about 272 Million NPR should be provided
to support related tasks.
104. The total cost of DRR for all public school buildings approximately equates to about
7,500 NPR, per student (less than 80 USD). This means, the safety of nearly all
school-going children in Nepal from natural disasters can be significantly
improved/ensured, by spending less than 10 USD per child, per year (less than 1
USD per month) for the next 8 years on school DRR.
105. The cost of planning, design, management, certification, coordination, and other
related functions was computed to be about 15% of the total cost. However, it
may be possible to reduce this cost through improved processes and
standardization. A significant portion of this cost is allocated for the detailed
assessment of buildings.
106. Some of the cost components, such as the cost of the various ministries in GON,
development partners, UN agencies, NGOs, various professional organizations,
academic institutes, and committees that support the overall DRR process is not
explicitly included in this estimates, and expected to be covered as part of the
commitment of these organizations to this cause.
107. These computations do not include the cost of intervention for private schools,
since activities to increase DR for private schools is covered by Strategy 10 which
includes the creation of regulatory frameworks.
page 57 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Chapter 7 Prioritization and Work Plan
7.1 Procedure for Prioritization
108. As indicated in the strategy for prioritization, in the absence of proper hazard
maps, vulnerability information, and details from the assessments of individual
buildings, it was not possible to prioritize the school buildings for intervention.
109. To address this situation, prioritization based on consequences was proposed, with
the following underlying assumptions:
a. The seismic hazard levels across the entire country are of similar order. The
assumption is reasonable, based on the results from previous hazard
studies, maps from U.S. Geological Survey (USGS), and other sources.
However, for the detailed evaluation of the vulnerabilities, intervention
design, proper hazard maps, and response accelerator, the soil profile
including soil type and so forth must be determined for each district and
ward.
b. The vulnerability of existing buildings is of similar order, with a small
percentage with low vulnerability, mostly with medium to high and some in
very high ranges. It is assumed that this distribution is similar to various
regions and/or districts.
110. These two assumptions lead to a “similar level of risk” for an assumed range of vulnerability. However, the consequences for the realization of the risk could be
very different based on several factors. Therefore, the estimation of the order of
consequences may be used to prioritize the intervention. This consequence-based
approach, together with the attempt to gain maximum benefit from the particular
expense of cost and resources, was used to estimate the level of “urgency” or priority. The following indicators were computed and combined using the
analytical hierarchy approach.
a. Based on EMIS database, the percentage of classrooms that need
retrofitting for each school and pro-rated to each building.
b. Based on EMIS database, the percentage of weak classrooms that need
retrofitting for each school and pro-rated to each building.
c. The seismic zone level for the district the school is located in.
d. The number of students per classroom for each school and pro-rated to
each building.
e. The population density of the district where the school is located.
f. The percentage of the total students in the district.
g. The percentage of the total school buildings in the district.
page 58 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
7.2 Efficient Utilization of Resources
111. The utilization of resources can be made more efficient by prioritizing groups of
districts so that the same resources can be used over a longer time, and at the
same time provide consistency and continuity in the work for different districts in
the country. It also reduces the need for capability and capacity building of a
large number of personnel.
112. The proposed “priority-groups”, resource number, and time, represent just one of several possible options/scenarios. Alternate options may be studied based on
other considerations and input from various stakeholders.
7.3 Priority for Intervention
113. Priority for intervention was based on the overall consequence reduction and
higher benefit approach to identify which districts should be addressed first.
114. The detailed priority plan for each ward, school, and building can only be
determined once the detailed assessment and evaluation of all school buildings in
each district has been carried out.
115. The estimated priority of intervention at the district levels divided into four groups.
KV is placed in Group 1, as this priority has already been established, and
significant work is ongoing in SSP at this time.
116. IMPORTANT: For consistency, the following numbers for all groups (including KV)
were based on EMIS data. For KV, the EMIS data seems to differ from the data
obtained from OpenDRI, and separate analysis could be undertaken for KV based
on OpenDRI data if needed.
Figure 7-1: Priority Groups Distribution, by District
page 59 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 7-1: Summary of Priority Groups and Cost
117. It can be observed from both tables 7-1 and 7-2 that the distribution of various
parameters and costs that Group 2 has the maximum benefit in terms of the
students covered by this intervention. The various cost indicators clearly show the
benefits of the proposed priority (excluding KV which is a pre-selected priority at
this stage). The analysis for this group indicates that even though the average cost
per building is relatively high, due to higher student density in those districts, the risk
is covered for a comparatively higher number of students.
Table 7-2: Cost Indicators for Priority Groups
118. The relative distribution of various indicators for the 4 priority groups are shown in
the following figures and further emphasize the prioritization logic and outcome.
Figure 7-2: Distribution of Various Parameters for Priority Groups
RebuildOne-Time
Retrofit
Incremental
RetrofitTotal
1 Group-1 3 151,385 642 867 717 565 213 1,495
2 Group-2 23 2,916,112 10,724 30,564 7,746 7,970 3,995 19,710
3 Group-3 21 1,596,882 10,017 25,576 6,528 5,306 2,200 14,034
4 Group-4 28 1,197,278 9,057 24,667 6,154 4,822 1,932 12,909
Total 75 5,861,657 30,440 81,674 21,145 18,663 8,340 48,148
Intervention Cost
(NPR Mi l l ion)Students
(Nos)
Schools
(Nos)
Buildings
(Nos)
Districts
(Nos)
Priority
Group
Sr.
No
District (M) School Building Student
1 Group-1 4% 2% 1% 3% 498.45 2,329,212 1,723,971 9,878
2 Group-2 31% 35% 37% 50% 856.96 1,837,945 644,880 6,759
3 Group-3 28% 33% 31% 27% 668.28 1,400,999 548,710 8,788
4 Group-4 37% 30% 30% 20% 461.03 1,425,298 523,328 10,782
All 100% 100% 100% 100% 641.98 1,581,742 589,514 8,214
Sr.
No
Priority
Group
Districts
(%)
Schools
(%)
Buildings
(%)
Students
(%)
Total Cost Indicators (NPR per )
Group-1 Group-2 Group-3 Group-4
Districts Students Schools Buildings
page 60 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Figure 7-3: Distribution of Intervention Cost for Priority Groups
119. The following tables present details on the intervention costs for all priority groups.
Table 7-3: Intervention Cost for Public Schools: Priority Group – 1
Table 7-4: Intervention Cost for Public Schools: Priority Group – 2
Group-1 Group-2 Group-3 Group-4
Rebuild One-Time Intervention Incremental Total Cost
Demolish -
Rebuild
Major Retrofit
(One-Time)
Minor Retrofit
(Incremental
Approach)
Total
1 Lalitpur 205 343 151,107 332 261 99 692
2 Bhaktapur 135 295 97,540 214 169 64 446
3 Kathmandu 302 229 78,100 171 135 51 357
Total KV 642 867 326,746 717 565 213 1,495
Cost (NPR Million)
Sr.
NoDistrict
Number of
Schools
(Nos)
Number of
Buildings
(Nos)
Estimated
Building Area
(SqM)
Rebuild One-Time
Retrofit
Incremental
RetrofitTotal
1 Sarlahi Centra l Pla in 201,625 725 1,114 267 286 147 701
2 Bara Centra l Pla in 157,800 437 1,029 263 282 145 690
3 Rautahat Centra l Pla in 153,384 397 1,028 249 266 137 652
4 Rupandehi West Pla in 153,907 483 1,387 408 435 225 1,068
5 Mahottari Centra l Pla in 164,402 400 1,152 274 294 151 719
6 Dhanusha Centra l Pla in 155,270 414 1,281 297 318 164 780
7 Kai la l i Far west Pla in 185,538 567 2,200 481 514 265 1,260
8 Si raha East Pla in 140,753 474 1,452 300 323 166 789
9 Jhapa East Pla in 126,662 433 1,527 412 442 228 1,081
10 Kapi lbastu West Pla in 109,352 395 1,079 268 288 148 704
11 Saptari East Pla in 137,102 473 1,474 315 327 163 805
12 Nawalparas West Pla in 133,909 566 1,984 585 629 321 1,534
13 Parsa Centra l Pla in 68,221 379 790 182 195 100 478
14 Dang Mid west Pla in 117,901 432 1,446 459 493 253 1,204
15 KanchanpurFar west Pla in 104,434 298 1,021 309 328 170 806
16 Bardiya Mid west Pla in 108,170 356 972 251 270 139 660
17 Darchula Far west Mountain 38,365 338 901 196 145 52 393
18 Dai lekh Mid west Hi l l 103,595 506 1,513 311 250 102 663
19 Banke Mid west Pla in 101,587 377 1,080 299 322 166 786
20 Surkhet Mid west Hi l l 99,603 506 1,509 352 281 115 748
21 Achham Far west Hi l l 97,301 755 1,268 281 224 92 597
22 Chitwan Centra l Pla in 96,664 414 1,432 472 506 262 1,240
23 Morang East Pla in 160,567 599 1,925 516 551 284 1,351
Total Priority Group 2 2,916,112 10,724 30,564 7,746 7,970 3,995 19,710
Sr. No Districts Region BeltBuildings
(Nos)
Intervention Cost (NPR Million)Schools
(Nos)
Students
(Nos)
page 61 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 7-5: Intervention Cost for Public Schools: Priority Group – 3
RebuildOne-Time
Retrofit
Incremental
RetrofitTotal
1 Sindhul i Centra l Hi l l 96,982 570 1,479 383 307 125 815
2 Rukum Mid west Hi l l 83,380 373 951 254 203 83 540
3 Ja jarkot Mid west Hi l l 82,903 428 1,007 248 198 81 528
4 Sa lyan Mid west Hi l l 47,655 324 629 161 129 51 340
5 Sunsari East Pla in 128,632 505 1,764 466 498 257 1,221
6 Kal ikot Mid west Mountain 57,678 308 654 151 110 41 302
7 KavrepalancCentra l Hi l l 86,920 616 1,690 472 378 154 1,004
8 Rolpa Mid west Hi l l 70,212 397 852 248 198 81 528
9 Udayapur East Hi l l 80,511 448 1,416 290 233 95 618
10 Makwanpur Centra l Hi l l 97,473 549 1,530 406 326 133 865
11 Baitadi Far west Hi l l 96,103 544 1,593 362 290 118 770
12 Pyuthan Mid west Hi l l 65,307 354 1,062 246 197 80 523
13 Gulmi West Hi l l 72,966 562 1,150 358 286 117 761
14 Nuwakot Centra l Hi l l 73,833 531 1,348 314 251 102 667
15 Panchthar East Hi l l 54,677 393 1,132 264 211 86 562
16 Bajhang Far west Mountain 76,590 459 1,092 274 200 74 547
17 Baglung West Hi l l 78,519 536 1,480 406 325 133 864
18 Khotang East Hi l l 72,930 690 1,344 305 244 100 648
19 Taplejung East Mountain 40,213 323 713 199 145 54 398
20 Tanahu West Hi l l 70,197 632 1,433 390 313 127 830
21 Ramechhap Centra l Hi l l 63,201 475 1,257 330 264 108 702
Total Priority Group 3 1,596,882 10,017 25,576 6,528 5,306 2,200 14,034
Sr. No Districts Region BeltBuildings
(Nos)
Intervention Cost (NPR Million)Students
(Nos)
Schools
(Nos)
page 62 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 7-6: Intervention Cost for Public Schools: Priority Group – 4
7.4 Work Plan
7.4.1 Overview
120. The work plan was developed to outline the time line and sequence of work in
order to complete the nationwide implementation and expansion of the DR
activities for the school sector of Nepal within 6-8 years and in compliance with a
set budget.
121. The work plan was characterized by the fifteen (15) major actions based on the
strategies previously defined. The priority groups (1-4) were identified per action.
The timeline was divided quarterly.
122. Ten of the major actions are proposed to begin implementation in 2014.
RebuildOne-Time
Retrofit
Incremental
RetrofitTotal
1 SindhupalchCentra l Mountain 77,110 584 1,532 291 212 78 582
2 Syangja West Hi l l 68,059 541 1,712 404 324 132 860
3 Dolakha Centra l Mountain 51,871 395 865 181 133 49 363
4 Palpa West Hi l l 69,906 448 1,444 380 305 124 809
5 Arghakhanch West Hi l l 55,136 405 1,045 291 233 95 620
6 Okhaldhung East Hi l l 45,464 338 969 217 173 71 461
7 Gorkha West Hi l l 71,436 534 1,315 376 300 123 799
8 Doti Far west Hi l l 65,033 492 1,085 245 196 80 521
9 Bhojpur East Hi l l 51,815 417 1,114 270 216 88 574
10 Ilam East Hi l l 49,599 432 1,309 267 214 87 569
11 Jumla Mid west Mountain 35,386 156 15 3 2 1 5
12 DadeldhuraFar west Hi l l 44,673 253 943 191 153 62 406
13 Kaski West Hi l l 72,662 444 1,207 487 386 159 1,033
14 Terhathum East Hi l l 29,378 240 834 187 150 61 398
15 Solukhumbu East Mountain 32,516 270 784 165 120 44 330
16 Sankhuwasa East Mountain 44,304 381 1,023 249 184 67 500
17 Rasuwa Centra l Mountain 12,042 104 238 69 50 18 138
18 Dhankuta East Hi l l 41,739 316 1,227 263 210 86 559
19 Parbat West Hi l l 22,716 317 961 245 197 80 522
20 Dhading Centra l Hi l l 89,039 621 1,391 405 324 132 861
21 Mugu Mid west Mountain 18,448 140 438 80 58 21 160
22 Humla Mid west Mountain 15,744 133 348 75 54 20 149
23 Myagdi West Hi l l 28,082 246 639 209 165 69 442
24 Lamjung West Hi l l 41,058 380 1,095 303 242 99 644
25 Dolpa Mid west Mountain 10,326 117 279 77 56 21 154
26 Bajura Far west Mountain 50,997 261 615 142 104 38 284
27 Mustang West Mountain 2,001 65 167 64 47 17 129
28 Manang West Mountain 738 27 73 20 14 5 40
All 1,197,278 9,057 24,667 6,154 4,822 1,930 12,909
Buildings
(Nos)
Intervention Cost (NPR Million)
Sr. No Districts Region BeltStudents
(Nos)
Schools
(Nos)
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
page 63 of 70
7.4.2 Time Line
The term “Relevant” pertains to the readiness of a priority group to implement or perform a particular major action.
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
page 64 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
page 65 of 70
Chapter 8 On New Schools
8.1 Projection and Construction of New Schools
123. Considering an average of 35 students per class room, the required and excess
number of classrooms in each district by 2021 were marked in the map shown below,
Figure 8-1.
124. Detailed district wise data is shown in Table 8-1. This analysis includes the data of both
public and private schools. Results show that by 2021, approximately 45,000 new
classrooms are required to be constructed in Nepal. Given that an estimated 20% of
the new classrooms will be private, a total of 36,000 new public classrooms will need
to be constructed by 2021 in Nepal.
125. It is important to note that the actual demand will not only be based on the current
data available. The school levels and grades offered in the schools, and the future
utilization of the classrooms and structures, for example, will need to be considered. A
possible change in migration patterns may also occur, thus these situations are in fact
debatable. More studies should be conducted to retrieve reliable data to support this
initiative.
126. The figures presented are estimates which should be regarded as a way to illustrate
the possibilities and in turn provide a starting point to plan the construction of new
schools for ideal student densities.
Figure 8-1: Comparison of Students per Classrooms and Population Density for 2011 and 2021
2011 2021 (Projected)
Cla
ssro
om
s
Po
pu
latio
n D
en
sity
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
page 66 of 70
8.1.1 Education Village Concept
127. As shown in the table, the districts in hilly and mountain belts have excess classrooms.
As per the census data of 2011, some of the districts have population densities as low
as two (2) while in other districts the number of students per classroom is at three (3).
The trend shows that in coming years, these figures will be further reduced.
128. The villages are characterized by low and sparsely distributed population, with
students often travelling great distances to reach their school. This current situation
adds to the low attendance levels, thus innovative options must be explored. One
concept involves the development of Education Villages. An Education Village will
essentially transform underutilized school infrastructures, with the possibility to merge
with other schools, to provide both academic and lodging facilities to students.
129. This concept aims to increase occupancy rate in the classrooms by reducing the
student’s travel from daily to weekly, increase mobilization effectiveness, and maximize the utilization of resources.
8.2 Estimation of New Classroom Construction
130. To estimate the number of classrooms required by 2021, projected number of
population in 2021 was calculated based on the population growth trend in each
district from 2001 to 2011 and the total calculated population was reduced by 5% to
match with the projection as per the prescribed UN growth rate. � � ℎ = � � − � � /� �
� � = � � ℎ ∗ � �
131. The existing data of number of schools, students and classrooms were then used to
calculate the multiplying factor (student per population). � = /� �
132. The projected number of students and the required number of classrooms in 2021 was
calculated as follows. = � ∗ � �
= /35
page 67 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
Table 8-1: District-wise Data for the Projection and Construction of New Schools
Sr.
No. Districts
2011 2021 (Projected)
Population Total
students
Population
density
Student/
population
No. of
classroo
ms
Students/
Classroom Population
Population
density
Total
students
No. of
classrooms
required
(35
students/room)
Additional
classrooms
1 Taplejung 128,547 60065 35 0.47 2807 21 116543 32 54456 1556 -1251
2 Panchthar 198,362 65856 160 0.33 3409 19 184999 149 61419 1755 -1654
3 Ilam 295,824 68628 174 0.23 3834 18 293969 173 68198 1949 -1885
4 Jhapa 810,636 195019 505 0.24 6977 28 907232 565 218258 6236 -741
5 Morang 964,709 200265 520 0.21 5160 39 1048517 565 217663 6219 1059
6 Sunsari 751,125 180427 598 0.24 6356 28 856699 682 205787 5880 -476
7 Dhankuta 164,133 46441 184 0.28 3497 13 153729 173 43497 1243 -2254
8 Terhathum 101,709 31469 150 0.31 2355 13 86884 128 26882 768 -1587
9 Sankhuwasabha 159,649 48951 46 0.31 3516 14 152091 44 46634 1332 -2184
10 Bhojpur 183,918 54864 122 0.30 3227 17 158284 105 47217 1349 -1878
11 Solukhumbu 106,772 36458 32 0.34 2184 17 100572 30 34341 981 -1203
12 Okhaldhunga 148,320 49365 138 0.33 2689 18 133367 124 44388 1268 -1421
13 Khotang 209,130 74814 131 0.36 3661 20 179565 113 64237 1835 -1826
14 Udayapur 321,962 96895 156 0.30 3706 26 342302 166 103016 2943 -763
15 Saptari 646,250 139739 474 0.22 3249 43 695721 510 150436 4298 1049
16 Siraha 643,136 148670 541 0.23 3028 49 686484 578 158690 4534 1506
17 Dhanusha 768,404 175278 651 0.23 2985 59 835497 708 190582 5445 2460
18 Mahottari 646,405 185275 645 0.29 2911 64 717184 716 205562 5873 2962
19 Sarlahi 768,649 217318 611 0.28 2671 81 882931 701 249629 7132 4461
20 Sindhuli 294,621 104466 118 0.35 4720 22 294694 118 104492 2985 -1735
21 Ramechhap 205,312 67347 133 0.33 4104 16 188530 122 61842 1767 -2337
page 68 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
22 Dolakha 188,186 59074 86 0.31 2619 23 164733 75 51712 1477 -1142
23 Sindhupalchok 289,455 88395 114 0.31 4068 22 260236 102 79472 2271 -1797
24 Kavrepalanchok 389,959 113958 279 0.29 7182 16 374579 268 109463 3128 -4054
25 Lalitpur 466,784 122082 1212 0.26 7374 17 612795 1592 160269 4579 -2795
26 Bhaktapur 303,027 57519 2546 0.19 5207 11 386914 3251 73442 2098 -3109
27 Kathmandu 1,740,977 365649 4408 0.21 7157 51 2661611 6738 559005 15972 8815
28 Nuwakot 278,761 79245 249 0.28 3759 21 255903 228 72747 2078 -1681
29 Rasuwa 43,798 13885 28 0.32 1030 13 40740 26 12916 369 -661
30 Dhading 336,250 102899 175 0.31 5137 20 317166 165 97059 2773 -2364
31 Makwanpur 427,494 116940 176 0.27 5694 21 442210 182 120966 3456 -2238
32 Rautahat 696,221 185477 618 0.27 2802 66 844727 750 225040 6430 3628
33 Bara 701,037 210970 589 0.30 2658 79 835004 702 251286 7180 4522
34 Parsa 601,701 142961 445 0.24 1944 74 691731 511 164352 4696 2752
35 Chitwan 566,661 149091 255 0.26 6599 23 646225 291 170025 4858 -1741
36 Gorkha 269,388 82080 75 0.30 4892 17 239269 66 72903 2083 -2809
37 Lamjung 169,104 51868 100 0.31 4245 12 153353 91 47037 1344 -2901
38 Tanahu 330,581 95684 214 0.29 6145 16 329338 213 95324 2724 -3421
39 Syangja 288,040 89122 247 0.31 5845 15 248389 213 76854 2196 -3649
40 Kaski 490,429 139942 243 0.29 9894 14 600469 298 171341 4895 -4999
41 Manang 6,527 891 3 0.14 262 3 4222 2 576 16 -246
42 Mustang 13,799 2488 4 0.18 925 3 12075 3 2177 62 -863
43 Myagdi 113,731 34684 50 0.30 2807 12 107369 47 32744 936 -1871
44 Parbat 147,076 34764 298 0.24 3299 11 130205 264 30776 879 -2420
45 Baglung 270,009 91303 151 0.34 5572 16 257531 144 87084 2488 -3084
46 Gulmi 283,577 84902 247 0.30 4615 18 257523 224 77101 2203 -2412
47 Palpa 269,372 81264 196 0.30 5117 16 256679 187 77435 2212 -2905
48 Nawalparasi 635,793 185926 294 0.29 7936 23 682255 316 199513 5700 -2236
49 Rupandehi 886,706 224912 652 0.25 4427 51 1054369 775 267440 7641 3214
page 69 of 70
Overall Plan for Increasing Disaster Resilience for Schools in Nepal
50 Kapilbastu 570,612 153524 328 0.27 2994 51 641771 369 172669 4933 1939
51 Arghakhanchi 200,446 61522 168 0.31 3808 16 183164 154 56218 1606 -2202
52 Pyuthan 235,165 73966 180 0.31 3235 23 247254 189 77768 2222 -1013
53 Rolpa 227,075 77731 121 0.34 3163 25 233257 124 79847 2281 -882
54 Rukum 210,878 97790 73 0.46 3044 32 224191 78 103963 2970 -74
55 Salyan 243,575 88352 167 0.36 2005 44 263992 181 95758 2736 731
56 Dang 557,852 152277 189 0.27 5050 30 639385 216 174533 4987 -63
57 Banke 493,017 135642 211 0.28 3712 37 598467 256 164654 4704 992
58 Bardiya 426,946 127043 211 0.30 2815 45 452552 223 134663 3848 1033
59 Surkhet 360,104 126714 147 0.35 4218 30 426966 174 150241 4293 75
60 Dailekh 263,835 107697 176 0.41 3815 28 293642 196 119864 3425 -390
61 Jajarkot 172,565 86178 77 0.50 2969 29 209759 94 104752 2993 24
62 Dolpa 36,701 11139 5 0.30 1033 11 43311 5 13145 376 -657
63 Jumla 108,734 35269 43 0.32 1240 28 125599 50 40739 1164 -76
64 Kalikot 141,620 57843 81 0.41 1995 29 180464 104 73708 2106 111
65 Mugu 55,311 19996 16 0.36 1088 18 66148 19 23914 683 -405
66 Humla 51,008 16074 9 0.32 1005 16 60887 11 19187 548 -457
67 Bajura 135,506 52335 62 0.39 1901 28 160357 73 61933 1770 -131
68 Bajhang 196,277 78156 57 0.40 3629 22 219118 64 87251 2493 -1136
69 Achham 258,022 100649 154 0.39 3385 30 273457 163 106670 3048 -337
70 Doti 211,827 67897 105 0.32 2973 23 205863 102 65985 1885 -1088
71 Kailali 770,279 236151 238 0.31 5008 47 914004 283 280214 8006 2998
72 Kanchanpur 444,315 132399 276 0.30 3321 40 496283 308 147885 4225 904
73 Dadeldhura 141,543 47808 92 0.34 2427 20 150859 98 50955 1456 -971
74 Baitadi 252,116 97452 166 0.39 4395 22 257593 170 99569 2845 -1550
75 Darchula 133,464 45204 57 0.34 2940 15 138710 60 46981 1342 -1598
Total 26,620,809 7,542,393 29,590,466 8,296,353
Required Classrooms 45,235
Capacity Development for School Sector Program Implementation (TA 7935 NEP)
Government of Nepal, Ministry of Education Department of Education
The Strategy
Submitted to
Asian Development Bank
Nepal Resident Mission
June 2014
Strategy for Increasing Disaster
Resilience for Schools in Nepal
Capacity Development for School Sector
Program Implementation (TA 7935 NEP)
Contract Number: 106698-S79855
Strategy for Increasing Disaster
Resilience for Schools in Nepal
The Strategy
Submitted to
Asian Development Bank
June 2014
page 3 of 70
List of Tables ................................................................................................................................................. 5
List of Figures ................................................................................................................................................ 6
List of Abbreviations ...................................................................................................................................... 7
Executive Summary ....................................................................................................................................... 9
Strategy ................................................................................................................................................ 13
Chapter 1 Background ............................................................................................................................. 14
1.1 The Issue ............................................................................................................................................ 14
1.2 Nepal’s School Sector ........................................................................................................................ 15
1.3 Disaster Risks and Need for DRR for School Sector .......................................................................... 18
1.3.1 Multi-Hazard Risks in Nepal......................................................................................................... 18
1.3.2 Seismic Risk and Consequences ................................................................................................ 20
1.4 DRR Initiatives Related to School Sector ........................................................................................... 22
1.4.1 School Safety Program (SSP) Action Plan .................................................................................. 23
1.4.2 School Sector Reform Plan (SSRP) and School DRR ................................................................. 25
1.5 Challenges ......................................................................................................................................... 25
1.6 Conclusions ........................................................................................................................................ 27
Chapter 2 Strategies to Increase DR of Schools...................................................................................... 28
2.1 Vision .................................................................................................................................................. 28
2.2 Objectives ........................................................................................................................................... 28
2.3 Overall Strategies ............................................................................................................................... 28
2.4 Linked Strategies ................................................................................................................................ 29
2.4.1 Strategy 1: Increased DR Awareness .......................................................................................... 29
2.4.2 Strategy 2: Continuous Reinforcement of Will and Commitment ................................................. 30
2.4.3 Strategy 3: Increased Institutionalization and Coordination ......................................................... 30
2.4.4 Strategy 4: Building Overall Capability and Capacity ................................................................... 31
2.4.5 Strategy 5: Facilitate and Support Local Research ...................................................................... 31
2.4.6 Strategy 6: Development and/or Amendment of Policies, Acts, and Regulations ........................ 32
2.5 Stand-alone Strategies ....................................................................................................................... 33
2.5.1 Strategy 7: Building Competency-based Capability and Capacity ............................................... 33
2.5.2 Strategy 8: Classification, Categorization, and Standardization................................................... 34
2.5.3 Strategy 9: Prioritized Increase in Multi-Hazard DR for Public Schools ....................................... 35
2.5.4 Strategy 10: Increased DR of Private Schools ............................................................................. 39
2.5.5 Strategy 11: Integration of DR into SSRP and Other Related Plans ............................................ 40
2.5.6 Strategy 12: Certification and Sustaining DR ............................................................................... 40
2.5.7 Strategy 13: Increased Community DR through Increased School DR ........................................ 41
2.5.8 Strategy 14: Integration of DR into the Academic and Professional Curricula ............................. 42
2.5.9 Strategy 15: Implementation of Results-based Monitoring and Evaluation Performance Management Plans ...................................................................................................................... 42
2.6 Summary ............................................................................................................................................ 43
Chapter 3 Framework for Implementation ................................................................................................ 45
3.1 Overview ............................................................................................................................................ 45
Content
page 4 of 70
3.2 Key Stakeholders and Roles .............................................................................................................. 45
3.2.1 Ministries and Departments of Government of Nepal .................................................................. 45
3.2.2 Nepal Risk Reduction Consortium (NRRC) ................................................................................. 47
3.2.3 Development Partners and International Organizations .............................................................. 48
3.2.4 NGOs, CBOs, and Community .................................................................................................... 49
3.2.5 Academic and Professional Organizations .................................................................................. 49
3.2.6 Other Organizations ..................................................................................................................... 51
3.3 Primary Implementing Agencies ......................................................................................................... 51
3.3.1 Overall Framework ...................................................................................................................... 51
3.3.2 DOE and Institutional Development ............................................................................................. 51
3.3.3 The Role of MOE/DOE ................................................................................................................ 53
3.3.4 The Role of MOUD/DUDBC......................................................................................................... 53
3.3.5 Primary Role of DUDBC .............................................................................................................. 55
3.3.6 Collaboration between DOE and DUDBC .................................................................................... 56
3.3.7 Role of Other Ministries ............................................................................................................... 58
3.3.8 Role of Community ...................................................................................................................... 58
3.3.9 Coordination Framework ............................................................................................................. 59
3.4 Summary and Conclusions ................................................................................................................. 60
References ................................................................................................................................................ 62
Appendix A ............................................................................................................................................... 64
Appendix B ............................................................................................................................................... 67
page 5 of 70
List of Tables
Table 1-1: School Distribution (Public vs. Private) 16
Table 1-2: Number of Schools in Various Distribution Parameters 17
Table 1-3: Relative Comparison of Seismic Risks 21
Table 1-4: A Sample Estimate based on the Consultant’s Review of the Available Data 22
page 6 of 70
List of Figures
Figure 1-1: Administrative, Geographical, and Ecological Regions of Nepal 16
Figure 3-1: Proposed Physical Infrastructure Division (PID) in DOE 53
Figure 3-2: Conceptual Framework for Sharing DR Responsibility in Academic Institutions 55
Figure 3-3: Proposed New Sections in DUDBC 56
Figure 3-4: Proposed Roles for DOE and DUDBC 57
Figure 3-5: Proposed Coordination with Other Ministries 57
Figure 3-6: Proposed Organization in Dedicated Coordination Office 60
page 7 of 70
List of Abbreviations
ADB Asian Development Bank
AHA Analytical Hierarchy Approach
AIT Asian Institute of Technology
ASIP Annual Strategic Implementation Plan
AusAID Australian Government Overseas Aid Program
AWPB Annual Work Plan and Budget
BOQ Bill of Quantity
CBO Community-based Organization
CSSP Community School Support Programme
CTEVT Council for Technical Education & Vocational Training
DEO District Education Office
DOE Department of Education
DRM Disaster Risk Management
DR Disaster Resilience
DRR Disaster Risk Reduction
DUDBC Department of Urban Development & Building Construction
EFA Education for All
EMIS Education Management and Information System
FEMA Federal Emergency Management Agency
GFDRR Global Facility for Disaster Reduction and Recovery
GON Government of Nepal
HFA Hyogo Framework for Action
INGO International Non-governmental Organization
JICA Japan International Cooperation Agency
KV Kathmandu Valley
KPI Key Performance Indicator
MOE Ministry of Education
MOFALD Ministry of Federal Affairs and Local Development
MOH Ministry of Health
MOHA Ministry of Home Affairs
MOUD Ministry of Urban Development
NGO Non-governmental Organization
NRRC Nepal Risk Reduction Consortium
NSET National Society for Earthquake Technology - Nepal
PHRD Policy and Human Resources Development, World Bank
RC Reinforced Concrete
page 8 of 70
SSP School Safety Program
SMC School Management Committees
SSRP School Sector Reform Program
SSS School Seismic Safety
TAC Technical Advisory Committee
TEP Teacher Education Project
UNDP United Nations Development Programme
UNEP United Nations Environment Programme
UNOCHA United Nations Office for the Coordination of Humanitarian Affairs
VDCs Village Development Committees
WB World Bank
WHO World Health Organization
page 9 of 70
Executive Summary
A Disaster Resilient Nepal: The Current Situation
1. Nepal is located within a high hazard zone with high vulnerabilities, leading to
potentially high risk and grave consequences from natural disasters, especially
from earthquakes. The country lies on several active faults where possible
epicenters are located at rather shallow depths, increasing the probability of
Nepal experiencing very strong ground motions.
2. Due to the growing understanding of the importance of disaster resilience (DR) in
Nepal, many programs have been initiated in many sectors, including the
establishment of National Risk Reduction Consortium (NRRC), comprising of five
flagship programs.
3. One such program is the School Safety Program (SSP) which was initiated and is
being funded by the Asian Development Bank (ADB) and the Australian Agency
for International Development under the Flagship 1 of the NRRC. As a Technical
Assistance Program, SSP is being implemented through Nepal’s Department of Education (DOE), under the Ministry of Education (MOE) which is the government
agency responsible also for the school sector. This program targeted about 260
public school buildings in Kathmandu Valley (KV) for retrofitting. SSP also included
capacity building programs for masons, teachers, students, and professionals in the
DOE within a 2-year duration starting from 2012. Many of these activities have been
successfully completed to date.
4. Even though SSP covers less than 0.3% of total scope of schools in the country, and
is only administered in KV, it has helped to identify several challenges, such as the
lack of capacity and resources, need for better technological solutions, quality
assurance, financial management, reconsideration of the role of community, and
coordination amongst various stakeholders. Tackling the disaster risk reduction
(DRR) activities in the entire country with a scale that is 300 times larger, spread
over 75 districts, needs a clear strategy and plan. Streamlining existing processes
and developing innovative ways to increase and sustain DR is the key to
accomplishing scaling up.
5. The School Sector Reform Plan (2009-2015) is another key project of the Ministry of
Education which serves as the basis for most of the improvements and
modifications in the school sector. Reports showed minimal issues in
implementation and that most of the district-level programs were observed to be
satisfactory. The SSRP is considered a potential platform for integration with SSP and
for scaling up the DR initiatives.
Increasing DR in Schools: Overall Strategies and Actions
6. Recognizing and supporting the several ongoing and planned initiatives and
programs related to DRR in Nepal, and to ensure an increased effectiveness and
reduced instances of duplicated efforts and emphasize focus on DR of schools, the
strategies are divided into two categories; Linked and Stand-alone.
7. Linked strategies refer to those that have relationships, ownership, and/or
relevance to the national DRR initiatives, but will also impact the DR of the school
page 10 of 70
sector. These strategies are either based on strengthening and supporting other
ongoing and planned initiatives or needs integration with them. Six (6) strategies
are proposed under this category:
1. Increased DR awareness in various stakeholders, at various levels.
2. Continuous reinforcement of will and commitment to DR at the highest
levels of the government and development partners.
3. Increased institutionalization and coordination to tackle the risks and
consequences of to various disasters.
4. Building overall capability and capacity of different stakeholders for DRR.
5. Facilitate and support local research to aid in providing relevant solutions
for measures leading to DRR.
6. Development and/or amendment of policies, acts, and regulations, and
their enforcement for enabling implementation of various strategies,
actions and measures aimed at DRR of various sectors, including the
schools.
8. Stand-alone strategies are specific strategies that are primarily applicable to the
school sector and can be implemented mostly independently within the defined
frameworks. These consist of the following nine (9) strategies:
1. Building competency-based capability and capacity of the agencies
directly involved in the implementation of the DRR process.
2. Classification, categorization, and standardization of the intervention
solutions for the vast scale of schools and buildings capitalizing on the
geographical, administrative, rural/urban, building materials, and size
variations.
3. Prioritized increase in multi-hazard DR for public schools, based on the
disaster consequences as the primary parameter derived from hazard
levels, vulnerability, and exposure, using a combination of one-time and
incremental safety approaches.
4. Increased DR of private schools through a combination of appropriate
regulations, licensing, certification, technical and administrative support,
and incentives, in close collaboration with private sector.
5. Integration of DR into SSRP and other related development plans for
maximizing the cost and resource effectiveness, and to avoid duplication
and conflicting interventions.
6. Certification of the DRR process and the final outcome, through continuous
quality assurance mechanisms and formal inspections, combined with
voluntary DR rating.
7. Increased community DR through systematic and assured involvement of
the community in awareness, capacity building, intervention
implementation, monitoring the final outcome of increased school DR.
8. Integration of various aspects of DR into the academic and professional
curricula, progressively from basic awareness to vocational training and
advanced knowledge and skill sets.
page 11 of 70
9. Implementation of results-based monitoring and evaluation performance
management plans to ensure the achievement of the outputs and
outcomes.
9. The scale and complexity of the tasks require the engagement of many
stakeholders carefully aligned with appropriate linkages for a strong and flexible
framework that is necessary for the implementation of the DR strategies at a
national level.
Working Together: Ownership, Implementation, and Coordination
10. Institutional arrangements, roles and responsibilities of the key stakeholders, and
coordination framework are largely reinforced by the collective agreement for the
DOE, to take ownership of the entire program as the primary implementing and
coordinating agency, actively supported by the Department of Urban
Development (DUDBC) under the Ministry of Urban Development (MOUD).
11. The primary role of MOE/DOE will be to formulate new or amend the existing
policies, rules, regulations, and guidelines to include DR considerations in the
design, construction and operations of schools, both in the public and private
domain. This may include enforcing a combined certification and licensing system,
similar to that used for the operations of hospitals.
12. For public schools, DOE will carry out all of the planning, execution management,
and coordination of the entire DRR process, closely with DEO and technical
support from DUDBC. The actual execution of various work items will be conducted
by the consultants and contractors, with appropriate involvements and support
from the community, VDC, and INGOS/NGOS based on several factors including
location (urban/rural, mountains/hills/plains), type of construction, size of buildings,
and complexity of tasks.
13. For private schools, the operators and or owners of buildings will be required,
through regulations, to gradually and progressively retrofit, relocate or rebuild the
school premises and facilities to meet the DR and functionality requirements laid
down by MOE/DOE. DUDBC will provide technical support and facilitate the
building owners in this process and will also carry out the required certifications.
The private school operators/owners will be supported by GON and development
partners in this process through financial assistance, soft loans, and other incentives
such as tax breaks.
14. Both, DOE and DUDBC will need to be strengthened to take on these additional
responsibilities, through the establishment of dedicated divisions/sections and
allocation of appropriate, sufficient, and qualified resources, with adequate
budgets, facilities and incentives.
15. Due to the level of community participation that is prevalent in Nepal, it may be
useful to reconsider the roles for community participation in the school DRR
process. The roles can include generating ownership by the community’s inclusion in basic training programs and thereby equipping the community with skills in order
to respond to various hazards and disasters. The community may also be involved
in fund raising and generating other in-kind resources and services related to the
process, direct intervention (construction) activities, and monitoring the works
carried out by other parties, in conjunction with the DEO, VDC, and the
consultants.
page 12 of 70
16. Frequent and smooth coordination with other ministries such as MOHA, MOUD,
MOF, MOFALD, and the Office of the Prime Minister will help ensure that the
objectives of this program are met.
17. A separate, dedicated coordination office is proposed for the coordination of the
entire school DRR process. This office will function as a clearing house and
repository of all information generated and needed to smoothly carry out various
aspects of the overall process, and will coordinate with various government
agencies, development partners, UN agencies, INGOS/ NGOS, private school
operators, technical committees, the media, and other stakeholders.
page 13 of 70
Strategy
page 14 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
Chapter 1 Background
1.1 The Issue
18. Nepal is among the most disaster prone countries in the world with a high level of
exposure to multiple hazards, most prominently earthquakes, floods, landslides,
windstorms, hailstorm, fire, glacial lake outburst floods (GLOFs), and avalanches.
Natural disasters have claimed the lives of more than 27,000 people between 1971
and 2007, indicating an average loss of more than 2 lives per day due to natural
disasters. More people are killed by natural disasters in Nepal than any other
country in South Asia. In addition to high mortality, more than 50,000 people were
reported as injured, 3,000 people missing, and about 5 million people affected by
natural disasters.1
19. The risk of an earthquake is of great concern in Nepal. After a major earthquake
struck this region in 1934, urbanization and population growth has increased the
country’s susceptibility to seismic hazard exponentially such that a similar earthquake would have catastrophic consequences today (NSET, 2012). Much of
the urbanization occurred in KV, which sits upon very soft soils that can amplify
shaking and cause liquefaction, which can further increase the potential
consequences of a high magnitude earthquake. The country lies on several active
faults, and possible epicenters, at a rather shallow depth, with a potential of very
strong ground motion.
20. School buildings and premises present particularly high risks due to the large
number of students, in relatively small, inappropriately designed and constructed
buildings. The loss of human, economic, and education facilities after a strong
event will be of enormous scale.
21. Schools need special attention due to the potentially high consequences in case
of disasters. Putting initiatives in place that address Disaster Resilience (DR) and
Environmental Sustainability (ES) can have long-term and far-reaching effects.
22. By carrying out the Disaster Risk Reduction (DRR) or by strengthening the DR of
school buildings, these consequences can be averted or reduced significantly.
These buildings can also serve another purpose by providing the much needed
immediate shelters and short-term relief centers for nearby communities, which are
oftentimes equally or even more vulnerable.
23. School safety is addressed by relevant education policy and practices aligned
with disaster management at national, regional, district, and local school site
levels. Three key pillars were noted in the Comprehensive School Safety document
published in March 2013.2
1. Structures: Facilities and infrastructures that are safe from various risks is the
primary focus of the proposed strategy and plan.
1 Disaster Risk Reduction in Nepal: Flagship Programmes, The Nepal Risk Reduction Consortium. April 2011.
http://www.un.org.np/sites/default/files/report/2011-04-19-nrrc-doccument-version-april-2011.pdf 2 Comprehensive School Safety, March 2013.
http://www.preventionweb.net/files/globalplatform/5194f951dabc99997_STC00792_DRR_CSS_Framework_singles_web.pdf
page 15 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
2. Plan: Disaster management plans that takes care of the consequences of
disasters, should it happen. These aspects are primarily addressed by
Flagship 2 and 4 of NRRC.
3. Education: Risk reduction and resilience education that prepares students,
teachers, and the affected community in the event of such risks and
disasters. This aspect is also addressed in this strategy document.
1.2 Nepal’s School Sector
24. The Ministry of Education is the apex body responsible for initiating and managing
education activities in the country. The Minister of Education, assisted by the
State/Assistant Minister, provides political leadership to the Ministry. The Ministry, as
a part of the government bureaucracy, is headed by the Secretary of Education
and consists of the central office, various functional offices, and offices located at
the regional and district levels. The Central Office or the Ministry is mainly
responsible for policy development, planning and monitoring, and evaluation
regarding different aspects of education.
25. Nepal is undergoing two momentous transformations – from a rural to an
urbanizing economy and from a unitary to a federal state. 3 Typical rural areas in
Nepal have a low population density and small settlements. Agricultural areas are
commonly rural. About 17% of the population resides in urban areas. With a
population of 2.5 million people, KV is growing at 4 % per year, one of the fastest-
growing metropolitan areas in South Asia. Several other districts, especially in the
plains, are also expanding at a significant rate.
26. Education in Nepal is structured as school education and higher education. School
education includes primary level of grades 1–5, lower secondary and secondary
levels of grades 6–8 and 9–10 respectively. Grades 11 and 12 are considered as
higher secondary level. The Higher Secondary Education Board (HSEB) supervises
higher secondary schools that are mostly under private management. Higher
education consists of bachelor, masters, and PhD levels. Depending upon the
stream and subject, bachelor’s level may be of three to five years' duration. This
categorization is currently being reviewed for re-organization. When confirmed,
Nepal may adopt two levels; 1-8 as Basic Education and 9-12 as Secondary
Education.
27. There are primarily two types of schools in the country: public (community-based)
and private. Public schools receive regular government grants depending on their
sub-type, such as community-supported, community-aided, and community un-
aided. The private schools are funded and operated independently by individuals,
companies, or through other non-governmental organizations.
28. For the entire country, the public schools constitute about 84% of the total
population of 6.3 million students. Private schools, with only 16% of the total, have
much greater presence in urban areas. In the case of KV, more than 75% of the
students attend privately-operated schools. It is believed, that with increased
urbanization and economic growth, enrolment in private schools is expected to
grow at a faster rate than public schools. The number of public and private
3 Urban Growth and Spatial Transition in Nepal. 2013.
http://issuu.com/world.bank.publications/docs/9780821396599
page 16 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
schools and estimated number of students, number of buildings, and classrooms
are shown in Table 1-1. These numbers are essential input for the development of
strategies and the preliminary plan.
Table 1-1: School Distribution (Public vs. Private)
Category Number of Schools Estimated Distribution
Students Buildings Classrooms Area (sqm)
Public 29,630 6,344,749 76,543 237,407 11,870,338
Private 5,593 1,197,644 14,448 44,813 2,240,662
Total 35,223 7,542,393 90,991 282,220 14,111,000
29. In addition to the distinction of public and private schools, the consideration to the
spatial and demographic distribution of various school-related indicators is
important for the development of the strategies and plans. The following
parameters
a. Three ecological belts: Terai (plains), elevated lands (hills), and mountains.
b. Five administrative regions: east, central, west, mid-west, and far-west.
c. Seventy-three districts, plus KV comprising three districts.
d. Two development categories: urban and rural.
Figure 1-1: Administrative, Geographical, and Ecological Regions of Nepal
30. Figure 1-2 shows a visual representation of the number of total schools and
students in all the districts, together with the distribution of public and private
schools, indicating wide variations in various districts located in different regions
and belts.
31. An analysis of the school data based on the above categorization shows wide
variations in the number of students, schools, buildings, classrooms, and student
densities.
32. While the overall number of public schools in the country is much higher than the
number of private schools, it is noticeable that private schools are more prevalent
in urban areas. In KV particularly, the students in private schools account for over
75% of the total number of students enrolled in schools (Figure 1-4). The student
proportions in the private schools are expected to increase in the future due to
urbanization, migration patterns, as well as economic affluence.
page 17 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
Figure 1-2: The Administrative, Geographical, and Ecological Regions of Nepal
Table 1-2: Number of Schools in Various Distribution Parameters
Sr. no. Parameters Public Private
Numbers Percentage Numbers Percentage
a
Plains/Terai 9,130 85% 1,630 15%
Hills 17,245 85% 2,953 15%
Mountains 4,065 95% 200 5%
b
East 6,732 88% 958 12%
Central 8,243 79% 2,183 21%
West 6,585 86% 1,062 14%
Mid-west 4,910 93% 345 7%
Far-west 3,970 94% 235 6%
c Kathmandu Valley 642 29% 1,585 71%
All Other Districts(72) 29,798 90% 3,198 10%
d
Urban 3,826 73% 1,393 27%
Rural 25,972 94% 1,805 6%
Kathmandu Valley 642 29% 1,585 71%
page 18 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
Figure 1-3: School Distribution based on Four Categorizations: Ecological Belt,
Administrative Region, District, and Urban/Rural Development
1.3 Disaster Risks and Need for DRR for School Sector
1.3.1 Multi-Hazard Risks in Nepal
33. Nepal is extremely susceptible to many natural disasters due to the location and
landscape. Though earthquakes are considered one of the major hazards
affecting Nepal, some of the other common natural hazards, 4 related to the
schools safety need to be considered in the overall DRR are listed below:
34. Landslides: Both natural and human factors are responsible for these frequent
landslides. Common natural factors encompass steep slopes, fragile geology, and
high intensity of rainfall. Human factors that may also affect the frequency of
landslides, particularly in vulnerable mountain belts, involve improper land use,
encroachment into vulnerable land slopes, and unplanned development activities
such as construction of roads and irrigation canals without proper protection
measures. These occurrences are found around Siwalik, Mahabharat range, mid-
land, and also in the higher Himalayas.
35. Floods: During the monsoon season, waterways fed by the melting of the Koshi,
Narayani, Karnali, and Mahakali rivers swell and cause damage to the villages,
crops lands, people, and livestock situated at the river basins.
4 Nepal Disaster Knowledge Network - Nepal Disaster Knowledge Network (NDKN) has been developed under the portal of SAARC
Disaster Management Centre. The NDKN is a web portal within the South Asian Disaster Knowledge Network that provides a broad
array of resources, knowledge, and services such as knowledge collaboration, map generation, database, and other important
information pertaining to disaster management.
Accessed from: http://www.saarc-sadkn.org/countries/nepal/country_profile.aspx
page 19 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
P
ub
lic -
Ru
ral
Priva
te -
Ru
ral
Figure 1-4: Variations in School and Student Distributions in Schools in Nepal
(Public/Private, Rural/Urban)
School Distribution Student Distribution P
ub
lic -
Urb
an
Priva
te -
Urb
an
page 20 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
36. Glacial Lake Outburst Floods (GLOFs): Glacial lakes in the foothills of the mountain
outburst from the melting of huge glaciers. These occurrences cause great
damage downstream. Currently, 15 glacial lakes are indicated as substantially
dangerous in Nepal.
37. Fire: Most of the houses in the rural areas are constructed in clusters with materials
made of earthen wire, stone, and wood. Thus, these are highly susceptible to
catching and spreading fire during the dry season. Wildfire is another cause of
natural disaster, which usually occurs during the dry season especially in the mid hill
areas.
38. Avalanche: Rapid movement of snow and debris bring massive masses down
through the slope or flanks of mountains. The high mountainous region of Nepal,
having rugged and steep slopes topographically, is susceptible to these
avalanches.
1.3.2 Seismic Risk and Consequences
39. What makes the seismic hazards more difficult and thus very important to consider
compared to other natural hazards are due to the following points:
a. Unlike many other hazards, such as landslides and floods that may affect
some particular regions and areas, earthquake seismic hazards are of high
level for the entire country.
b. Many of the natural disasters are either seasonal, or can be predicted, or
early warning systems can be developed and implemented to take
preventive or evacuative measures.
c. Many hazards can be avoided by temporary relocation such as moving to
higher ground during floods. However, it is not uncommon to find that there
is no such location to seek refuge at or time to relocate due to the lack of
early warning and extremely short event time of earthquakes.
d. In the context of Nepal, the consequence of a “rare” or “extremely strong” earthquake event is expected to be much more devastating, and longer
lasting than other hazards.
40. Based on the review of various documents, discussions with engineers, and visits to
some of the selected buildings, it was noted that many buildings and schools were
built using unsafe construction techniques, and were also currently in poor physical
conditions due to sub-standard material or workmanship, lack of maintenance, or
extreme age. Many buildings have serious maintenance problems, such as
decaying timbers or severely cracked walls that may deteriorate and create
dangerous conditions causing safety hazards even without the onset of an
earthquake.
41. A relative comparison of the seismic hazards, risks, vulnerability, and possible
consequences for some of the countries is shown in Table 1-3. The seismic hazard
levels in Nepal have nearly the same maximum PGA (Peak Ground Acceleration)
as that in Japan and in California, United States. Both of these countries have less
vulnerability compared to Nepal due to their advanced state of awareness and
technological development, together with better quality of construction and
preparedness. They have experienced lower consequences in terms of loss of life
page 21 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
from strong earthquakes. On the other hand, Haiti, which experienced an
earthquake of a much less intensity than those in the United States or in Japan,
resulted in disastrous consequences due to high vulnerability.
Table 1-3: Relative Comparison of Seismic Risks
Country Hazard Vulnerability
Observed/
Anticipated
Consequences
Japan Very High
Max. PGA = About 1.2
Max. EQ = 9.0 M
Very Low
Advanced state of
awareness,
technology, design,
and empowerment
Low
Low/medium for
general buildings
Low level of casualties
observed
United States
(California)
Very High
Max. PGA = About 1.2
Max. EQ = 7.9 M
Low
Advanced state of
awareness,
technology, retrofitting
of many structures
Low
Low/medium for
general buildings
Low level of casualties
observed
Nepal High to Very High
Max. PGA = Estimate
1,0
Max. EQ = 8.29 M
Very High
Poor construction, lack
of awareness,
inadequate design,
High/ Very High
Extensive damage
experienced in the
past with potential for
much greater
consequences
Haiti High
Max PGA = About 1.1
Max EQ = 7.0 M
Very High
Very poor
construction, lack of
awareness,
inadequate design,
Very High
Recent earthquake
caused close over
250,000 casualties
42. In an earlier study conducted by NSET (2011), 5 a rough estimation of damages to
buildings was determined using information about typical construction types found
in KV. Such information on construction types were also collected and analyzed
while developing the Nepal National Building Code, 1994. 6 Results indicated that
as many as 60% of all buildings in KV are likely to be damaged heavily, many
beyond repair, if a future earthquake causes shaking equivalent to intensity 9.
43. A detailed and reliable estimate of causalities, downtime, and cost of
repair/rebuild requires extensive data and studies, together with the use of
standardized methodologies and tools such as HAZUS 7 are necessary. To estimate
the order of consequences, a few scenarios were roughly considered for strong
5 Snapshot Study for School Safety in Nepal - Report on Snapshot Study for School Safety in Nepal, 2011, a government report
prepared by NSET financed by ADB.
6 Nepal National Building Code, NBC 110: 1994. http://www.dudbc.gov.np/pdf/nbc/NBC110.pdf 7 Hazus is a standardized methodology by FEMA that contains models for estimating potential losses from earthquakes,
Floods, and hurricanes. Hazus uses Geographic Information Systems (GIS) technology to estimate physical, economic, and social
impacts of disasters. http://www.fema.gov/hazus
page 22 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
earthquakes that correspond to a national Maximum Considered Earthquake
(MCE) level event affecting about 40% of the overall schools in the country. The
following range of casualties, and school closures were estimated using the
following data and assumptions.
Total Buildings 90,991
Total Students 7,542,393
Percentage of buildings assumed to be effected by scenario
earthquake
40%
44. The table below is an estimate based on the Consultant’s review of the available data, hazard levels, building designs information, overall type and quality of
construction, and discussions with other experts. The figures derived were not
based on any detailed computational or loss-estimation model. The numbers
however are realistic and provide an insight to the order of the consequences.
The CP (Collapse Prevention), LS (Life Safety), and IO (Immediate Occupancy)
refer to the typical performance indicators used to define various states of
structural response after an earthquake.
Table 1-4: A Sample Estimate based on the Consultant’s Review of the Available Data
Scenario
Case
Severely
Damaged/
Collapsed,
(Casualties
25%, Repair
Cost 80%)
Moderately
Damaged,
(Casualties,
2%, Repair
cost 25%)
Not
Damaged
(No
Casualty,
no repair)
Estimated
Repair Cost
USD
(millions)
Estimated
Lost
Student-
Days
(millions)
Estimated
School-
time Event
Casualties
Favorable 10% 30% 60% 100 60 90,000
Moderate 20% 40% 40% 180 110 175,000
Unfavorable 30% 50% 20% 250 150 250,000
1.4 DRR Initiatives Related to School Sector
45. Important research and groundwork has been established by many organizations
containing key data useful analysis relevant to the development of the strategy for
DR efforts for schools in Nepal, including two related documents:
Developing Strategy for Improving School Seismic Safety (SSS) - National
Society for Earthquake Technology-Nepal (NSET), prepared for GFDRR,
2011.
Snapshot Study for School Safety in Nepal - Report on Snapshot Study for
School Safety in Nepal, 2011, a government report prepared by National
Society for Earthquake Technology-Nepal (NSET) financed by ADB.
46. There have been and are several ongoing initiatives by the GON and
development partners, UN agencies, INGOs, NGOs, and other stakeholders related
to DRR in many sectors including those especially targeted at schools. These
include awareness building programs, capacity building programs, preparedness,
as well as the retrofitting school buildings. While all of these initiatives are valuable
in their own right, the need for coordination and consistency to increase their
page 23 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
effectiveness is felt by many stakeholders, and is therefore identified as one of the
primary challenges when implementing DR activities.
47. One of the most significant ongoing initiatives, and relevant to the development of
the present strategy and the plan is the School Safety Program (SSP) or sometimes
referred to as School Earthquake Safety Program (SESP). This program, started as
part of the Flagship 1 of the National Risk Reduction Consortium (NRRC), focusing
on school and hospital safety, led by the Asian Development Bank (ADB), World
Health Organization (WHO), and Nepal’s Ministry of Education (MOE) and Ministry
of Health (MOH).
1.4.1 School Safety Program (SSP) Action Plan
48. School Safety Program (SSP) is funded by the Asian Development Bank (ADB) and
the Australian Agency for International Development. SSP is a Technical Assistance
Program, implemented through Nepal’s Department of Education (DOE), Ministry of Education (MOE). According to the Action Plan, 8 this program was scheduled
for 2012-2014 duration and is targeted and for retrofitting about 260 public school
buildings in the KV. Several other activities have been also included to create a
more inclusive approach for greater impact such as:
Public awareness building programs.
Development of strategic documents.
Capacity building programs for masons, teachers, students, and
professionals in the DOE, by organizing workshops and other events.
Demonstration of structural retrofitting and rehabilitation techniques.
49. The results and experiences from the implementation of the SSP are being used as
the basis for the expansion of the program and for the development of the present
strategy and plan to scale up the process and techniques to address the DRR of all
schools in the entire country.
50. As of date, the following targets have been achieved through the SSP and other
related initiatives by the DOE: 9
Work Status KV Outside KV Total
Completed Rapid Visual Vulnerability Assessment 201 35 236
Completed Design for Retrofitting 197 35 232
Design Reviewed (approved from Technical
Committee)
197 35 232
Ongoing Program for Vulnerability Assessment
and Retrofit Design
84 125 209
Retrofitting Construction Completed 64 64
8 School Earthquake Safety Program (SSP) Action Plan, 2012/2014. 9 Introduction and update on SSP, Senior Divisional Engineer, DOE, April 28, 2014
page 24 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
Agreement completed and ongoing construction
for retrofitting
133 35 168
51. In addition, the following were also accomplished:
128 engineers/ sub-engineers trained (3 sets of basic technical training on
retrofitting and 1 set of engineers training on seismic strengthening
completed)
TOT for 81 RP (54 in KV + 27 Outside KV)
2,580 teachers trained at RC level
Orientation to 12,000 teachers from 1,215 schools from 11 districts
300 masons trained (156 through 5 days intensive training and remaining
through on the job training) on retrofitting
About 243,000 students were provided with 1 day orientation
1.4.1.1 Key Observations on SSP
52. Many activities have been initiated and completed, and the progress on the
software side of the program is very impressive.
53. Although several school buildings have already been retrofitted, and many have
been designed and are in the process of implementation, however, the
implementation of some activities are behind schedule.
54. The entire process of increasing the DR of existing schools is rather new in the
context of Nepal, and especially for DOE. There are therefore several initiation and
teething difficulties in streamlining the existing processes to accommodate these
new demands such as evaluation and selection of buildings, design and design
reviews, costing, billing, construction supervision, approvals, role of community in
execution of works, and financial community contribution.
55. Although capacity building and training of the respective personnel has been
envisaged and conducted as part of the program, it was observed that very
limited resources were allocated to DOE, and within DOE, to carry out the assigned
tasks. Among the available resources, key persons often manage many other
responsibilities in addition to the tasks required for increasing DR of schools.
56. Other challenges identified were insufficient and delayed budget allocation,
difficulty in achieving community participation targets that lead to delayed or
incomplete execution, lack of policy regarding DRR of private schools, no
budgetary allocation for project management, QA/QC, lack of proper
coordination framework and lack of incentive structure for the technical staff, that
were often employed on ad-hoc and/or temporary basis.
57. Upon reviewing the interventions, it was found that there were significant variations
of intervention cost across different building types and sizes, and between the
buildings designed by different consultants. Implementers also expressed difficulty
in using some of the planned contractor-based implementation. There were also
noticeable delays in some design, approval, and construction process.
page 25 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
58. Provided that the current SSP covers less than 0.3% of total scope and is only
administered in Kathmandu Valley, tackling a similar project with a scale that is 300
times larger, spread over 75 districts, needs a clear strategy and plan.
1.4.2 School Sector Reform Plan (SSRP) and School DRR
59. The School Sector Reform Plan (2009-2015), August 2009, Ministry of Education,
Kathmandu forms the basis of most of the improvements and modification that are
ongoing in the school sector. The plan calls for a total budget of about 2.8 billion
USD for a period of five years.
60. Reports showed that except for a few cases, most of the programs implemented in
the districts were observed to be satisfactory. Enthusiasm, commitment, and
creativity have been reflected in the district reports. An increased level of
awareness on educational programs among stakeholders was also reported due
to the basic orientation of the program and the disclosure of information on
educational activities across multiple channels.
61. Areas such as governance and accountability, internal control mechanism,
transparency, monitoring, evaluation, supervision and reporting are some of the
areas that need increased effectiveness in order to make the system more
functional. 10
62. However, despite the broad scope of the SRRP, there seems to a lack of emphasis
in the plan on any aspects of school safety, DR, or DRR for any of the hazards. This
is neither addressed for the existing school facilities, nor for the requirements and
budget allocated for up-gradation, re-furbishing or construction of new classrooms
and schools.
63. It is important to introduce the SSRP as a potential platform for scaling up the DR
initiatives. The potential of SSRP is elaborated in various strategies and
implementation plan.
1.5 Challenges
64. The specific challenges identified through the ongoing SSP are discussed in section
1.4.1.1, and can be summarized as the need to address the shortage of resources,
increased capacity building in various actors, appropriate budget allocation and
financial approval systems, cost-effective retrofitting solutions, and improved focus
on quality assurance, coordination, and management.
65. The overall challenges identified through several interactions and consultations
with other stakeholders are multi-level and complex.
10 School Sector Reform Program (SSRP), Second Higher Education Project (SHEP), Education For All Shishu Vikash Karyakram,
Community School Capacity Development Program, Status Report 2012.
page 26 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
66. These challenges can be summarized as:
Scale and
Complexity
The scale and complexity in terms of the number of schools, their
geographical and regional distribution, and the number of the
stakeholders involved.
Political
Need for reinforcement of will at the top levels, the commitment to this
will, assigning a high priority, making of appropriate policies and
legislations, and continuity until the objectives are achieved.
Governance Strengthening the appropriate frameworks and organizational
structures to handle this task.
Legal Need of sufficient and appropriate legal frameworks based on the
policies and regulations, and corresponding enforcements.
Financial
Need of financial resources for undertaking the scaled up tasks, the
integration of the DRR activities in appropriate budgets, the possible
misuse of funds, and delays in realization of the allocated funds.
Technical
Need for greater ability and capacity to handle planning and design
aspects, lack of intervention technologies, QE/QA/QC issues, and lack
of relevant research.
Management Lack of capacity, frameworks, and mechanisms for all aspects related
to management, coordination, reporting, monitoring, and evaluation.
Social
Not enough public awareness on the significance of DRR, lack of
acceptance of the intervention solutions, low/inadequate community
contributions.
67. The national scale of the school sector, distinctive spatial distribution, administrative
and ecological regions, and large number of stakeholders present major
challenges in developing the appropriate strategies and plans to cover
widespread implementation. Details are described as follows:
page 27 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
Hazards to be considered Earthquakes (for the entire country)
Floods, landslides, fires, on relevant zones
Seismic risk Hazard amongst the highest zones in the world
Vulnerability, very high
Risk and consequences very high
Regions and administrative
units
75 districts
3,912 VDCs
5 regions
3 ecological belts
Kathmandu Valley
School types Public/community and private
KG, primary, secondary, high
Existing schools 35,200 schools
91,000 buildings
282, 200 classrooms
New schools No clear plan for public and private sector
School students 7. 5 Million, nearly 28% of the total population
Stakeholders GON, a number of related ministries
UN Agencies
Development partners
INGOS/NGOs
Extensive Community involvement
1.6 Conclusions
68. Nepal is located within a high hazard zone with high vulnerabilities, leading to
potentially high risk and grave consequences from natural disasters, especially
from earthquakes. The country lies on several active faults where possible
epicenters are located at rather shallow depths, increasing the probability of
Nepal experiencing very strong ground motions.
69. School buildings and the surrounding premises are thus prone to particularly high
risks due to the large number of students studying in relatively small, inappropriately
designed and constructed buildings. Due to Nepal’s susceptibility to natural
disasters, the loss of human, economic, and education facilities after a strong
event will be of an enormous scale. By increasing the DR of schools and its
infrastructure, these consequences can be averted or reduced significantly. These
buildings can also provide the much needed immediate shelters and temporary
relief centers for the surrounding communities, which are equally or even more
vulnerable.
70. Due to the scale of the task and the relationships among multiple stakeholders,
there is a need to develop and adopt a clear strategy and overall plan to scale
up the ongoing initiatives for increasing the DR of the school sector. This strategy
needs to address various challenges that cover the scale and complexity of the
project; political, governance, and legal issues; financial, technical, and
management requirements for implementation; together with carefully addressing
the social implications to the general public. A preliminary plan is also needed to
estimate the requirements of resources, budget, and time and establish the basis
for the prioritized intervention.
page 28 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
Chapter 2 Strategies to Increase DR of Schools
2.1 Vision
“All new school buildings will be constructed with due consideration to risk from
various hazards (and environmental sustainability11), and that all existing schools
will have acceptably high resilience to various disasters by 2025 or earlier.”
71. At the core of this vision lies the recognition of children’s rights to survival and protection as well as to education and participation. Protecting learners and
education workers from death, injury, and harm involve developing safer
structures, a school disaster management plan, and educating all stakeholders. 12
2.2 Objectives
72. The objectives of this initiative include the following:
1. Prevent and/or minimize casualties and serious injuries to the students and
staff as a result of natural disasters.
2. Reduce the damage to the school property and assets in the course of a
disaster.
3. Minimize the disruption to the normal activity of the schools, during and
after a disaster.
4. Increase the resilience of school buildings at a level that can also serve as
shelters for the community.
5. Use disaster reduction process for the schools as a model and means for
enhancing the ability and capacity of the community.
6. Contribute towards the overall national initiatives for DRR and
management.
2.3 Overall Strategies
73. As highlighted in the Chapter 1, there are several ongoing and planned initiatives
and programs related to DRR in Nepal. It is therefore essential that the strategies for
the DR of schools recognize and support these initiatives. The proposed strategies
are divided into two categories:
74. A - Linked Strategies: Linked strategies refer to those that have direct relationships,
ownership, and/or relevance to the national DRR initiatives, and are either based
on strengthening and supporting other ongoing and planned initiatives or needs
integration with them. Detailed actions, plans, and outcomes for these are
dependent upon the other initiatives that are concurrently being run.
11 It is highly recommended that environmental sustainability considerations be added to this vision, although at
present is not explicitly covered by the strategies and the corresponding plans. 12 Comprehensive School Safety, March 2013
http://www.preventionweb.net/files/globalplatform/5194f951dabc99997_STC00792_DRR_CSS_Framework_singles
_web.pdf
page 29 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
75. B - Standalone Strategies: Stand-alone strategies are specific strategies that are
primarily applicable to the school sector and can be implemented mostly
independently within the frameworks described in this document.
2.4 Linked Strategies
76. The following linked strategies are proposed:
1. Increased DR awareness in various stakeholders, at various levels.
2. Continuous reinforcement of will and commitment at the highest levels of
the government and development partners.
3. Increased institutionalization and coordination to tackle the risks and
consequences of to various disasters.
4. Building overall capability and capacity of different stakeholders for
disaster risk reduction.
5. Facilitate and support local research to aid in providing relevant solutions
for measures leading to DRR.
6. Development and/or amendment of policies, acts, and regulations; and
their enforcement for enabling implementation of various strategies,
actions, and measures aimed at DRR of various sectors, including the
schools.
2.4.1 Strategy 1: Increased DR Awareness
77. There appears to be considerable awareness regarding the importance and need
of DRR amongst various sectors in the primary stakeholders. However, there is still a
need to increase the awareness of overall DRR among a wider audience, carrying
messages about the specific awareness about the importance of the DR of
schools. Increasing this awareness is likely to generate greater consensus and
support for the various other aspects of the strategy and plan for increasing the DR
of schools.
78. It is also important to link awareness raising and capacity development program to
execution and not be handled separately from the construction work.
79. Proposed actions include the following:
1. Develop appropriate and focused messaging material, in coordination
with international forums and guidelines, and NRRC’s communication unit
for specific communication tools for the following primary stakeholders:
a. Government ministries and departments.
b. Development partners, UN Agencies, INGOS, NGOs, etc.
c. Academia, professional bodies.
d. Students, parents, and the general public.
2. Distribute communication materials to relevant stakeholders.
3. Carry out an extensive awareness programs through various TV programs,
print and electronic media, and events.
page 30 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
4. Set up special discussion groups and forums through social media, and
launch a regular electronic newsletter under the umbrella of NRRC to
communicate results.
5. Engage teacher associations, student groups, and youth organizations.
2.4.2 Strategy 2: Continuous Reinforcement of Will and Commitment
80. Initiatives like DR that appear to fall outside the regular operation needs, often
have a better chance of success when supported by champions of the cause at
the highest level who can advocate for the issue and have the will and
commitment to carry them through. This requires the DR strategies to be brought to
the agenda of the highest levels of GON and the top levels of other stakeholders
and partners.
81. This can be achieved through:
1. Developing a presentation and/or the submission of strategic documents
on this issue to H.E. the Prime Minister’s office and Council of Ministers as a
matter of national importance.
2. Seeking the issuance of a policy statement, and directives, supporting the
DRR initiatives in general, and the DR of schools in particular.
3. Declaration from relevant ministries and departments to own and commit
to this task, in accordance with the proposed organizational frameworks.
4. Re-affirmed commitment from the heads of the development partners and
agencies to support this issue.
5. Possibly signing of MOA by all stakeholders to legitimize will and
commitment.
6. Development and/or amendment of policies, acts, and regulations.
2.4.3 Strategy 3: Increased Institutionalization and Coordination
82. In the context of this document, the institutionalization of the DRR aspects covers
the following details:
a. There are primary institutions in the country that are specially tasked with,
and are assigned to provide overall responsibility and the corresponding
authority of the disaster management, such as FEMA in USA and NDMA in
Pakistan.
b. There are specialized secondary agencies that are either independent, or
are divisions or sections within other institutions supporting the DRR activities
in various sectors, that support the initiatives.
c. All institutions have awareness mechanisms and focal points for the
coordination of risk reduction and disaster management.
83. While the establishment of a national level institute is essential for the success of
various DRR initiatives, this is considered beyond the scope of this document.
Actions and frameworks proposed in this document aim to facilitate the
involvement of specialized secondary agencies and focal point institutions in the
context of the DR of schools.
page 31 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
84. DR activities, including the concept of retrofitting may be integrated with
maintenance procedures that are already institutionalized or generally planned
and budgeted for annually.
85. Although most of these actions are further expanded in Chapter 3, Framework for
Implementation, some actions may include the following:
1. Identify the primary agencies responsible for carrying out this task and
develop the corresponding organizational structures.
2. Provide institutional frameworks for the implementation of this program,
considering all relevant stakeholders.
3. Create mechanisms within this program to enable systematic reporting and
coordination for both the activities and outcome.
4. Set up a dedicated web portal and contribute to open-sources networks
(such as OpenDRI) for information dissemination and sharing.
2.4.4 Strategy 4: Building Overall Capability and Capacity
86. One of many objectives of national education is also for the students to learn and
to develop their capabilities, while also building sufficient capacity to contribute to
the development and well-being of the nation as a whole. Carrying out the DRR of
schools will provide a first-hand opportunity for building capacity and capability
that will in essence benefit all initiatives, including DR. It is important to engage
teachers, students, and the community and integrate the awareness of the
components and importance of DR and ES, basic response to disasters, and the
need and scope of further studies and skills into the education process.
87. The specific actions are to include:
1. Within basic school curriculum, there must be increased awareness about
DR and Environmental Sustainability through emphasis by MOE and DOE.
2. Within the curriculum of vocational training, increased focus is necessary on
techniques and technologies for retrofitting, constructing safer new
buildings and structures, in related trades. This can be led by CTEVT and
other organizations involved in vocational trainings and certifications.
3. Within various professional academic programs, incorporate current trends
and developments in the field of DRR through the universities curricula
development.
4. Within the professional development programs, focus on the proper
application of codes and new techniques through professional
organizations and programs.
2.4.5 Strategy 5: Facilitate and Support Local Research
88. One of the challenges identified in the implementation of the ongoing SSP is the
lack of enough appropriate, cost-effective techniques and technologies for
constructing new buildings and retrofitting existing that are well adapted to the
local context. There also seems to be a greater need for human resources with in-
depth local knowledge and expertise for various aspects of the DRR process. This
challenge can be addressed by active support for the research and
development. This will not only lead to appropriate solutions, in a cost-effective
page 32 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
manner, but will also help to strengthen the research activities in the academic
institutes, which will turn benefit the overall capability and capacity building.
89. The following actions are proposed to implement this strategy:
1. Provide opportunities to work on locally suitable solutions for technical
challenges faced for implementation, through the allocation of
appropriate budgets and mechanisms for engaging local research centers
and institutes.
2. Provide opportunities for local institutions to link with international research
organizations through program and project network, as well as through
stipulations for prescribed local engagement.
3. Utilize the services offered by these centers for various tests, verifications,
and reviews.
4. Create a database of centers in universities, semi-public organizations, as
well as centers in private centers, listing their capabilities and research
interests for proper engagement.
2.4.6 Strategy 6: Development and/or Amendment of Policies, Acts, and
Regulations
90. Creating and maintaining legal conditions that address DR is necessary when
scaling up for country-wise implementation. While formulating specific policies,
acts and rules to address the DR requirements in schools are needed, it may be
necessary and possibly more effective to integrate the following aspects in the
relevant existing documents.
a. Requiring all new public schools to be built with due consideration to and
certification of the achieving the safety standards needed by relevant
building codes and guidelines.
b. Requiring all new private schools to be housed in buildings with due
consideration to and the certification of achieving the safety standards
needed by relevant building codes and guidelines.
c. Requiring existing private schools to gradually relocate and/or retrofit the
buildings to achieve the required safety and performance standards.
d. Requiring public and private schools to obtain specific approvals for
expansions, extensions, or alterations with due consideration to the safety
standards and guidelines.
91. Several related policies, acts, and regulations were revisited to determine whether
certain necessary mechanisms to enable the well-coordinated implementation of
DR for schools in Nepal are supported by policies and lawful measures.
92. The Education Rules, 2067 (2002), last amended on 2010, discusses infrastructure
requirements in Chapter 2: Provision relating to permission for establishment of
school. The section offers comprehensive procedural and establishment processes
but does not provide rules to address DR for infrastructure.
93. In relation to Rule 4 on the requirements for infrastructures for establishing a school,
Schedule 3 provides a detailed list from A to R. None of the rules refer specifically
page 33 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
to DR though some provide considerations for infrastructure construction for
example, the nominal height of classrooms, minimum floor area per student, and
rental duration. These rules and schedules can be expanded and/or new rules
and schedules can be added that explicitly address the requirements for buildings
and facilities that are safe and resilient to disasters, in addition to being functional.
94. Of the many the policies, acts, and regulations reviewed, a list of acts that may
need to be reviewed, addressed, and included in order to achieve DRR follows:
National Framework of Child Friendly School for Quality Education (2010)
Technical Education and Vocational Training Council Act, 2066 (2010)
Higher Secondary Education Rules, 2052 (1996)
2.5 Stand-alone Strategies
95. These strategies explicitly cover the “Safe Facilities” aspects of the overall school
safety, while also addressing awareness and education aspects:
7. Building competency-based capability and capacity of the agencies
directly involved in the implementation of the DRR process.
8. Classification, categorization, and standardization of the intervention
solutions for the vast scale of schools and buildings capitalizing on the
geographical, administrative, rural/urban, building materials and size
variations.
9. Prioritized increase in multi-hazard DR for public schools, based on the
disaster consequences as the primary measure derived from hazard levels,
vulnerability, and exposure, using a combination of on-time and
incremental approaches.
10. Increased DR of private schools through a combination of appropriate
regulations, licensing, certification, support and incentives, in close
collaboration with private sector.
11. Integration of DR into SSRP and other related development plans for
maximizing the cost and resource effectiveness, and to avoid duplication
and conflicting interventions.
12. Certification of the DRR process and the final outcome, through continuous
quality assurance mechanisms and formal inspections, combined with
voluntary DR rating.
13. Increased community DR through systematic and assured involvement of
the community in awareness, capacity building, intervention
implementation, and monitoring the final outcome of increased school DR.
14. Integration of various aspects of DR into the academic and professional
curricula, progressively from basic awareness to vocational training and
advanced knowledge and skill sets.
15. Implementation of results-based monitoring and evaluation performance
management plans to ensure the achievement of the outputs and
outcomes.
2.5.1 Strategy 7: Building Competency-based Capability and Capacity
96. One of the main challenges that factors into the need for scaling up the ongoing
SSP is the availability of sufficient qualified, trained, and fully equipped
page 34 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
professionals, including local consultants, to undertake various aspects of the DRR
process. This requires the need to enhance the capability of the existing personnel,
increase the number of qualified personnel, and provide required organizational
and resource support.
97. Key actions involve the following four priorities:
1. Establish the need for resources for various tasks within different
stakeholders.
2. Develop a database of available experts engaged in the capability and
capacity building.
3. Design consistent and integrated programs. Conduct these programs
following the objectives and activities of the proposed mission and
objectives. The following relevant groups should be targeted, with specific
competency:
a. DOE/DEO and DUDBC staff for various roles such as planning,
assessment, budgeting, design review, site supervision, quality
assurance, and reporting.
b. Consultants (engineers and architects, managers) for design and
management capabilities.
c. Inspectors for quality assurance and certification.
d. Contractors and their staff for updating construction techniques
and technologies.
e. Masons and other skilled labor for specific construction techniques
and quality.
4. Ensure these programs are integrated with other programs and projects to
avoid duplication of efforts.
2.5.2 Strategy 8: Classification, Categorization, and Standardization
98. Experiences from the ongoing SSP, which is dealing with only 260 buildings within
KV, has shown scaling up activities to include thousands of buildings across the
country will not be possible using the “individual building” approach being used at present. It is important to classify, categorize, and standardize the design and
construction approaches so that a large number of buildings and facilities can be
handled within a reasonable time, using a simplified process, and producing
consistent output. The following actions are proposed, which will be used as the
basis for developing the preliminary prioritized plan:
1. Generate the basic inventory of all public and private schools buildings,
including basic information about the physical characteristic such as size,
number of stories, basic building material/structure type, overall condition,
providing visuals of the buildings’ exterior and interior. This information can
then added or integrated into the current database maintained by EMIS.
Simple information collection forms can be developed and sent to DEO
and school administrative team. All school buildings should be geo-tagged
by the GPS coordinates.
page 35 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
2. Classify and categorize buildings by operator (public, private), by size
(large, medium, small), by age (historic, very old, old, new), material type
(URM, RC, others), condition (very good, good, fair, poor, very poor), and
location (rural, urban, and further by Terai, hills, mountains, KV).
3. Develop standardized intervention approaches and details for various
categories.
2.5.3 Strategy 9: Prioritized Increase in Multi-Hazard DR for Public Schools
99. Implementing and prioritizing schemes to increase DR for public schools is the
primary focus for the intervention strategy. While the main risk may be from
earthquakes and the demands from other hazards, non-structural threats also
need careful consideration during integration into a single intervention plan.
100. Standard and well-established guidelines, procedures, and tools for multi-hazard
assessment and intervention together with consideration for appropriate structural
and non-structural aspects should be adopted into all aspects of the intervention.13
101. The hazards and strategies that are to be considered are:
– The risk of earthquakes to all schools, based on appropriate hazard levels.
– Landslides and avalanches for schools in hills and mountains, and known
hazard zones. This may require a regional level intervention, or relocation as
building level intervention may not be possible in a cost-effective manner.
– Floods in the schools in plains, hills, and other areas with established
flooding hazard. This risk is typically addressed on regional level, rather than
on individual building levels.
– Glacial Lake Outburst Floods (GLOFs), for specific areas where such hazards
have been identified. This may also require a macro level intervention, or
re-location.
– Winds and storms, for all buildings in all zones.
– Fire for all buildings in all zones.
102. Increasing DR involves three streams of actions:
1. For completely new buildings to be built;
2. For adding rooms/expansions to existing buildings; and
3. For existing buildings without expansion.
103. It is recommended to integrate 2 and 3 into a single approach for existing
buildings, and the following approach is prescribed:
1. Determine if the expansion of the building is included in the SSRP within the
next 5 (or 10) years.
If yes, then integrate DR intervention and expansion into a single
design and implementation plan.
13 Tools for the Assessment of School and Hospital Safety, UN HABITAT
http://www.fukuoka.unhabitat.org/info/misc/20130216.html
page 36 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
If no, then plan for intervention on as-is basis, and mark building for
no expansion after intervention without full evaluation and specific
approval.
2. Carry out preliminary data collection and assessment.
3. Decide to either accept the building “as is” and move to certification
process or go for further review.
4. Carry out second level evaluation and decide approach from any of the
following option:
A. Accept the building > Move to certification process.
B. Demolish and rebuild > Use new building process.
C. Demolish and abandon (No need in overall SRRP).
D. Design the retrofit (Both structural and non-structural).
i. Specify implementation as one-time construction
ii. Specify implementation using incremental process
5. Use an approach that combines classification, categorization, and
standardization for prioritization, planning, and implementation, as detailed
in section 2.5.2.
2.5.3.1 Choosing between Rebuild and Retrofit:
104. When deciding whether to retrofit or rebuild, the following strategy and
considerations are important:
All historical, monumental, or national heritage buildings must be
considered as special cases by the Technical Advisory Committee (TAC).
A purely on cost basis following criteria is recommended in order to
consider the overall benefits of the investment. In essence, older vulnerable
buildings should be considered for re-build, as it will not only improve DR
but also the functionality, and possibly land and/or space utilization. Newer
vulnerable buildings should be preferred for retrofit, even at a higher
relative cost.
While computing rebuilding cost, the savings due to possible re-use of
material from existing buildings should be considered.
105. General considerations based on the age and vulnerability of selected buildings
are outlined below:
page 37 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
106. More details about making the choice between re-build and retrofit are given in a
separate document, Retrofitting for DR of Schools in Nepal, 2013 14, which shows
the relative importance of building age, cost of retrofit, vulnerability, allowed
down-time, land-use value, available budget, and other factors.
2.5.3.2 On One-time Construction and Incremental Approach:
107. In the current SSP, a one-time construction approach is being used, which
considers each intervention as a single project, with specified budget, timeframe,
and resources. This approach is generally suitable when financial and other
resources are available and earmarked for the DRR purpose. This is more of a
project-oriented approach, which is similar to the construction of a new building.
This requires as certain time duration for the school building to be shut down for the
to be work carried out, often times lasting approximately 2-6 months, depending
on the size and complexity of the building. For a few buildings, this could be
scheduled during the annual break to minimize disruption.
108. To complete the DRR of schools which aims to address over 90,000 buildings, the
one-time construction approach may not be feasible in all cases, particularly
within a reasonable time frame, unless almost unlimited resources are mobilized.
An alternative is proposed by FEMA15 in its guideline for reducing DR for schools up
to high school level. This involves incremental interventions for disaster risk
reduction, often in conjunction with and integrated with other physical
infrastructure/building maintenance, enhancements, up-gradations, or expansions.
The overall planning and design is carried out at the start of the initiative, but the
implementation is divided into stages and phases.
109. For the DR of schools in Nepal, a mixed approach is recommended, in which some
schools/buildings are intervened using the direct, one-time intervention, and for
others an incremental approach is used. The following are some of the
considerations for choosing between one-time or incremental strategies,
considering the effect of all relevant hazards. Preliminary planning (presented in
accompanying document) has been carried out using these considerations.
a. For buildings that are found to be highly vulnerable, and cannot be
retrofitted and must be replaced/rebuild; one time new construction
should be carried out.
b. For buildings which are vulnerable, and funds are directly available from
the government, community, NGOS, or any other funding sources; one-
time intervention may be used.
c. For buildings which are found to be vulnerable, but are not selected for re-
built (a above), or immediate one-time intervention (b above), a
prioritization and planning should be carried out first, and then direct
14 Retrofitting for DR of Schools in Nepal, 2013. To be published, development is ongoing.
15 FEMA 395 | Incremental Seismic Rehabilitation of School Buildings (K-12): Providing Protection to People and
Buildings (2003) http://www.fema.gov/media-library/assets/documents/5154
page 38 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
intervention may be used for very high priority buildings, subjected to
availability of funds for this purpose.
d. For all other buildings, (not covered by a-c above); an incremental
approach may be used and integrated into the SSRP and other
development plans, not only by the GON but also by development
partners, NGOs, and the community. It is important to note that currently,
annual funds for rehabilitation and maintenance of schools buildings are
already budgeted in the DOE plans and can be integrated with the
incremental approach. A building which has been retrofitted for DR, may
not need extensive maintenance for a few years, and hence, it may be
possible to integrate the financial allocations.
110. The incremental intervention, also referred to as incremental safety, can be
planned and designed on the following basis:
1. By gradually increasing the performance levels from “Life Safety” to “Collapse Prevention”, for different hazard and risk levels. This can be established through risk assessment studies. Retrofitting to achieve this level
can then be planned incrementally for the different members, such as
columns first, and the beams next.
2. By carrying out the intervention in phases for different parts of the buildings,
such as lower floors in one phase, and the upper floors in the second
phase.
3. By creating “Strong Rooms” 16 first in parts of buildings, in case budget and
resources are not readily available for full intervention.
2.5.3.3 Seismic Retrofit Strategies and Techniques for Existing Buildings
111. The lack of sufficient and cost-effective options for retrofitting existing buildings
have been cited as one of the challenges for scaling up the DR process. A
separate document has been prepared as part of this assignment. 17 This
document summarizes various strategies and techniques used for retrofitting
different buildings types and their relevance to various regions of Nepal.
2.5.3.4 Strategy for New Public School Buildings
112. The following procedure is recommended when planning for and constructing
new public school buildings. This is to be used for completely new buildings that do
not exist as well as for demolishing and rebuilding existing buildings.
1. Develop and/or adopt design guidelines for new school buildings, in line
with national codes. This to be done in close collaboration with DUDBC.
16 Strong rooms are proposed as parts of the building that are either found to less vulnerable, or can be
made less vulnerable at with minimal intervention, and can be used as emergency shelters. These could
be typically located near the stairwells and exits, and students should be trained to rush to these rooms
in case of an earthquake or other hazards.
17 Retrofitting for DR of Schools in Nepal, 2013. To be published, development is ongoing.
page 39 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
2. Review the already prepared seven (7) type designs for Terai regions for
conformance to the guidelines.
3. Modify and/or adopt the type designs, and formulate possible construction
modalities (contractor, community/mixed).
4. Develop type design for hilly and mountain areas.
5. Include DR consideration in the process of site selection.
6. Adopt and use the type design for local site conditions.
7. Develop specific designs where type designs are not applicable using the
guidelines, through the proper review and approval process.
8. Construct structures using appropriate construction modality.
9. Complete the certification process.
2.5.4 Strategy 10: Increased DR of Private Schools
113. It has been highlighted in many discussions and consultative workshops that the DR
of privately owned and operated schools must be ensured, together with the
public/community schools. It was observed from various documents and
databases, that the percentage of total students enrolled in private schools is on
the rise, especially in KV and in other urban centers. In KV, more than 75% of the
student body attend public schools. In many other districts, especially in plains, this
ratio is more than 25%. As the unitization continues and the standard of living
improves, the relative enrolment in private schools is also expected to increase. At
present, these schools are often located in residential buildings that were not
specially designed to be used as school facilities. Most of these residential buildings
have little or no attention to DR. Due to these reasons, it is essential that the DR of
private schools is also achieved to provide a safe and sustainable environment for
all children.
114. Increasing the DR of private schools can be achieved through a combination of
policies, regulations, technical and financial support mechanisms, engagement
with private school operators, and the parents of the school children. The following
actions are proposed:
1. Establishment of clear policies for requiring the operators to obtain and
renew licenses for the operation of private schools. This should be done in
consultation with PABSON and parents associations.
2. Formulation of clear procedures, guidelines, and supporting mechanisms
for private operators, to include the DR and sustainability requirements for
the facilities in which schools are operated, in addition to other
requirements.
3. Notification and awareness building about the new policies amongst all
stakeholders.
4. Setting timelines for the gradual enforcement of the policies, starting with
awarding licenses for new schools, followed by evaluating existing schools
to obtain and renew licenses.
page 40 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
5. Setting up mechanisms for providing technical support to the operators by
providing guidelines and networking services for engagement of qualified
professionals, contractors for carrying out the construction work.
6. Mechanism to provide soft loans, land lease, and other performance-
based incentives, such as tax breaks for achieving required levels of DR.
7. Certification through DUDBC and other municipal authorities.
115. It is essential that the DR of public schools must be initiated and achieved to some
degree before enforcing the requirements for private schools. Leading by
example will greatly increase the chances for enforcement and build public
pressure on private school operators.
2.5.5 Strategy 11: Integration of DR into SSRP and Other Related Plans
116. Integrating school DR initiatives into the SSRP will be beneficial to the overall
objective of the cause because of the following reasons:
a. The DR aspects that are currently missing in the SSRP will be highlighted,
creating the awareness in a wider spectrum of stakeholders in the
education sector
b. Planning for projects for expansion, up-gradation, renovation,
maintenance, and the interventions for increasing DR can be integrated
and/or coordinated to minimize duplication and reduce the conflict of
efforts; increase utilization of funds and resources; and reduce the
frequency of disrupting of academic activities.
c. Support mainstreaming DRR in the academic curriculum and related
educational programs, as highlighted in other strategies.
117. An example of integration involves the inclusion of basic information and
awareness about DR into the overall annual teacher training plan and other
capacity building programs.
118. Since the current infrastructure classroom standards do not make any references
to safety issues, addressing this gap should also be prioritized.
2.5.6 Strategy 12: Certification and Sustaining DR
119. Achieving DR requires comprehensive and continued policy-level commitment
particularly in evaluation and monitoring. The two aspects that are closely related
are, (a) certifying achievements when DR is increased, and (b) sustaining
achieved DR. Both of these aspects are considered as integral parts of this
strategy.
120. To ensure that the desired DR levels have been achieved, the entire process first
needs to be quality-centric, continuously evaluated, and incrementally certified.
Next, the completion of the process must lead to a formal and verifiable
certification. Certification ensures the achievement of the outcome and is a
platform for creating awareness, and incentive awarding.
121. To achieve this, the following actions are needed:
page 41 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
1. Identify the agency (or agencies) that will carry out and award licenses
and certificates for various types and levels of certification, and develop
appropriate certification procedures, forms, and guidelines.
2. Certification of consultants, contractors, and masons after going through
the capability and capacity building programs, with possible mechanism
for better incentives in terms of hiring and financial benefits.
3. Intermediate review of design and construction documents, site inspection
reports, photographs, and other QA/QC records.
4. Certification of newly constructed buildings including the retrofit of existing
buildings for public schools through qualified inspectors, standardized
procedures and format. This process includes a review of the documents
generated previously (step 3), site visits, and feedback from the community
and local bodies.
5. Certification of new and retrofitting intervention of private school buildings
in conformance with codes and standards and construction quality by
DUDBC and local municipal councils.
6. Renewal of certification at intervals of 10 years through site inspections.
Inspections will assess the condition of the buildings and verify that no
major alterations have been made without adherence to DR
considerations.
2.5.7 Strategy 13: Increased Community DR through Increased School DR
122. As the benefits of safer schools directly impact the safety of a community, the
overall DR of the community can be increased, by and through the process of
increasing school DR. The presence of “safer schools” in a community is expected to help in raising the sense of well-being and pride in the members of the
community, especially the children and their parents.
123. Some key actions that the community is recommended to be actively part of
include:
1. Incorporation of the declared rights of the community to use the
intervened parts of school buildings as temporary and emergency relief
centers in case of disasters. Provided that the school infrastructure can be
used for multiple purposes, the continuity of education for the students
must be prioritized in such plans. This can be done by using a part of the
space and shifting teaching protocols.
2. Participation of the community in awareness building, preventative
activities, and other training and drills conducted for school children.
3. Participation of community in the capacity development programs
conducted as part of projects undertaken in this plan, either by the
community, NGOs, or contractors.
4. Active participation in the DR intervention activities implemented through
the community, and ensured prescribed participation in the projects
undertaken by the consultants and contractors.
page 42 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
5. Use of intervention processes as a demonstration of the techniques for re-
use in other construction activities in the community.
2.5.8 Strategy 14: Integration of DR into the Academic and Professional Curricula
124. Developing a culture of resilience at an early age draws attention to the
importance that schools and educators play to achieve a disaster resilient society.
Education can be the foundation for awareness building when mainstreaming DR
in schools in Nepal, particularly in primary and secondary education, to achieving
lasting DR.18 Mainstreaming DR education will include curriculum mapping and
needs assessments together with inquiry-based learning approaches to directly
affect learners (students and teachers) at each possible level.19
125. Integrating DR in education can be implemented in four levels:
Basic Education: Basic awareness about disaster and need for DR,
including ES, is highly proposed for inclusion in the school curricula.
Vocational: Emphasis on developing skills aligned with DR activities should
be prioritized in training for specific professions.
University: Specific fields such as engineering and architecture is advised to
incorporate courses on building design and vulnerability analysis to
produce a critical mass of capable professionals.
Graduate: Higher learning programs for engineers, architects, and other
related professionals can include topics on DRR and management.
126. Continuous research and development in infrastructure DR is particularly important
since the rate of population increases in Nepal alongside the country’s development into a more urban society. The academe can support the
development of systematic approaches that can integrate rehabilitation measures
with the overall economic conditions as well as disaster preparedness plan at a
national level. The potential of locally available materials being used for retrofitting
may also be explored. Latest technologies (including skilled personnel and
required machinery) are suggested for further study and inclusion in current R&D
projects with a view for possible implementation in the near future.
2.5.9 Strategy 15: Implementation of Results-based Monitoring and Evaluation
Performance Management Plans
127. One of the challenge, as well as observation on the ongoing SSP, is the need for
proper quality assurance, reporting, monitoring, and evaluation requirements and
systems.
128. The following indicators are recommended to determine the final outcome of
proposed strategies and plans. Explicit measurement, monitoring, and evaluation
of the outputs leading to these outcomes is to be achieved through development
and implementation of a results-based performance management plan:
18 Educating the Educators: Disaster Resilience Resource Mapping Report, July 2013, Revised in January 2014.
19 Disaster resilience starts with the young. Mainstreaming Disaster Risk Reduction in the School Curriculum. 2011.
page 43 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
129. The following indicators are comprised of the following:
1. Awareness about DR is increased.
2. Commitment at various levels is demonstrated.
3. Institutional frameworks are completed.
4. Required capability and capacity is built.
5. DR of public school buildings is increased.
6. DR of private school buildings is increased.
7. DR of community is increased.
8. Mainstreaming of importance and process of DR is increased.
2.6 Summary
130. It is important to recognize and support the several ongoing and planned initiatives
and programs related to DRR in Nepal to ensure increased effectiveness and
reduced duplication of efforts. Proposed strategies must then be divided into two
categories; Linked and Standalone.
131. Linked strategies refer to those that have direct relationships, ownership, and/or
relevance to the national DRR initiatives. These strategies are either based on
strengthening and supporting other ongoing and planned initiatives or needs
integration with them. Six strategies are defined under this category:
1. Increased DR awareness in various stakeholders, at various levels.
2. Continuous reinforcement of will and commitment at the highest levels of
the government and development partners.
3. Increased institutionalization and coordination to tackle the risks and
consequences of to various disasters.
4. Building overall capability and capacity of different stakeholders for DRR.
5. Facilitate and support local research to aid in providing relevant solutions
for measures leading to DRR.
6. Development and/or amendment of policies, acts, and regulations, and
their enforcement for enabling implementation of various strategies,
actions, and measures aimed at DRR of various sectors, including the
schools.
132. Stand-alone strategies are specific strategies that are primarily applicable to the
school sector and can be implemented mostly independently within the defined
frameworks. These consist of the following nine (9) strategies:
1. Building competency-based capability and capacity of the agencies
directly involved in the implementation of the DRR process.
2. Classification, categorization, and standardization of the intervention
solutions for the vast scale of schools and buildings capitalizing on the
geographical, administrative, rural/urban, building materials and size
variations.
page 44 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
3. Prioritized increase in multi-hazard DR for public schools, based on the
disaster consequences as the primary measure derived from hazard levels,
vulnerability, and exposure, using a combination of on-time and
incremental approaches.
4. Increased DR of private schools through a combination of appropriate
regulations, licensing, certification, support and incentives, in close
collaboration with private sector.
5. Integration of DR into SSRP and other related development plans for
maximizing the cost and resource effectiveness, and to avoid duplication
and conflicting interventions.
6. Certification of the DRR process and the final outcome, through continuous
quality assurance mechanisms and formal inspections, combined with
voluntary DR rating.
7. Increased community DR through systematic and assured involvement of
the community in awareness, capacity building, intervention
implementation, and monitoring the final outcome of increased school DR.
8. Integration of various aspects of DR into the academic and professional
curricula, progressively from basic awareness to vocational training and
advanced knowledge and skill sets.
9. Implementation of results-based monitoring and evaluation performance
management plans to ensure the achievement of the outputs and
outcomes.
133. The complex nature of these strategies require an implementation plan that is
inclusive to all stakeholders, whether formal or informal, in order to facilitate a
strong sense of responsibility, transparency, and accountability in all possible levels
when it comes to DR.
page 45 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
Chapter 3 Framework for Implementation
3.1 Overview
134. The scale and complexity of the tasks to be undertaken and the engagement of
many stakeholders require strong and flexible frameworks that can link the
strategies with work plan. This chapter presents the institutional arrangements, roles
and responsibilities of the key stakeholders, and coordination framework necessary
for implementation of the DR strategies at a national level.
135. This institutional framework for disaster risk management was developed to link
various institutions from the cabinet at the highest level down to the district
councils. 20 The presence of a similar national level framework would greatly
facilitate and support the proposed frames in this document for the DR of school
sector.
3.2 Key Stakeholders and Roles
136. Many stakeholders are currently involved in the overall DRM initiatives in Nepal.
Due to the current situation of the initiatives, it is possible that there will be more
opportunities to contribute to the DR of schools in Nepal.
137. A summary of key stakeholders and their envisaged role/s in increasing the DR of
schools, based on the strategies defined in Chapter 2, is presented in the section.
More details on specific roles and engagements to various activities will be
presented separately as The Plan.
3.2.1 Ministries and Departments of Government of Nepal
138. The GON, through its various ministries, departments, and agencies, is undertaking
several efforts to improve the DR of various sectors in the country. Some of the key
agencies and their relevant roles are:
MOHA Ministry of Home Affairs (MOHA) is considered as the focal
point for all of these efforts, and should also be involved in
the integration of the DR of schools with other initiatives
for the scaling up the SSP.
MOHA is also the coordinator of closely related Flagship 2
and Flagship 5 of the NRRC, described in the following
section.
The District Administration Offices (DAO), discussed latter
in this section, are under this ministry, increasing the
engagement of MOHA in the actual implementation at
the district level.
20 Natural Calamity (Relief) Act, 2039 (1982)
page 46 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
MOE MOE, as the primary ministry managing the education
system, has the overall responsibility for ensuring that all
academic institutions (both public and private) have safe
and supportive infrastructure, building environment, and
facilities conducive to the learning process. This must
explicitly include the DR requirements as well. MOE is to
include the allocation of resources and funds needed for
DR into its overall budget and plans, such as SSRP and
strives to generate these from the GON and
development partners.
MOE, also responsible for the making of and amending
the Education Rules and Acts. Most of policy-related
strategies for increasing the DR of schools need to be
addressed at the ministry level
MOFLD Ministry of Federal Affairs and Local Development
(MOFLD) is an important ministry, as it oversees the District
Development Committees (DDC), as well as the Village
Development Committees (VDC) which will be crucial for
the success of the proposed strategies in and for
engagement of the communities.
MOUD Ministry of Urban Development (MOUD) is responsible for
the development of urban areas in the country. MOUD is
comprised of six divisions handling administration;
planning, monitoring, and foreign aid; water supply and
environment; physical planning and urban development;
housing and building; and municipality coordination.
DUDBC, under this ministry is envisaged to be directly
involved in the DRR of schools, discussed in the following
sections.
DOE The DOE has specific and direct responsibilities for public,
as well as overall responsibility for the private/ institutional
schools in the country and thus should be entrusted with
the overall responsibility of increasing the DR in the
schools.
The role of DOE will be discussed in greater detail as the
primary implementing agency, in close collaboration with
DUDBC.
DUDBC The Department of Urban Development and Building
Construction (DUDBC), under MOUD, is the main
department entrusted to manage the urban
development and building construction and is
encouraged to provide full support to the DOE in terms of
technical and human resources for the DR of public
schools and include direct responsibility for the DR of
private schools, in collaboration with DOE.
The role of the DUDBC will be discussed in greater detail in
the following sections.
page 47 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
DEOs The District Education Offices (DEOs) should be the main
unit responsible for the school’s DR at the district levels, in
close coordination with DOE head office and regional
offices, as well as the divisional offices of DUDBC, and the
municipal offices.
The role of DEO is discussed in greater detail in the
following sections as well as in The Plan.
DDC and
VDC
The District Development Committee (DDC) headed by
Local Development Officer (LDO) that is under Ministry of
Federal Affairs and Local Development, with several
Village Development Committees (VDC) and wards need
to be fully engaged in school DRR. This initiative should
be coordinated through the DEOs.
School
Management
Committees
(SMC)
The School Management Committees (SMC) can play an
important role in creating awareness regarding the DR (as
well ES) in the community, and among teachers and
students. The SMC can also be conduit for coordinating
the training and preparedness activities, as well as
increasing engagement with the community and NGOS.
DAO The most important administrative office present in every
district is the District Administration Office (DAO) headed
by Chief District Officer (CDO), under Ministry of Home
Affairs. CDO is the head of all the administrative body in
the district. While DAO plays a major role during any
disasters, the DEOs should work closely with the district
administration level and to coordinate with CDO for DRR
and DRM aspects of the schools, especially to inform
them of the schools where DR has been achieved.
3.2.2 Nepal Risk Reduction Consortium (NRRC)
139. The Nepal Risk Reduction Consortium (NRRC) is a unique arrangement that unites
humanitarian and development partners with financial institutions in partnership
with the GON in order to reduce Nepal's vulnerability to natural disasters. Based on
the Hyogo Framework and Nepal's National Strategy for Disaster Risk
Management, the NRRC has identified 5 flagship priorities for sustainable disaster
risk management.
140. The DR of schools and hospitals has been assigned to Flagship 1 of the consortium
and has already made significant progress through SSP. The role of NRRC is of
paramount importance for the overall DR of in all sectors, including schools as it
provides the platform for keeping the agenda of all of the development partners
and GON. It is important that the various flagship programs are well integrated,
and the efforts and outputs benefit the other programs.
page 48 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
Flagship-1 School and Hospital Safety. Led by the Asian
Development Bank (ADB), World Health Organization
(WHO), and Nepal’s Ministry of Education (MOE) and
Ministry of Health (MOH), it aims to build the earthquake
resilience of schools and hospitals through retrofitting,
training, raising awareness, and safety measures.
Flagship-2 Emergency Preparedness and Response. Led by
UNOCHA and Nepal’s Ministry of Home Affairs (MOHA), it
seeks to enhance the government’s preparedness and response capabilities at the national, regional, and local
level.
Flagship-3 Flood Risk Management in Koshi River Basin. Led by the
World Bank (WB) and Nepal’s Ministry of Irrigation, this
initiative aims to protect the country from flood-related
disasters.
Flagship-4 Community-based Disaster Risk Management. Led by the
International Federation of Red Cross/Red Crescent
Societies and Nepal’s Ministry of Local Development, this
effort aims to prepare 1000 VDCs to become disaster
resilient.
Flagship-5 Policy/Institutional Strengthening. The United Nations
Development Program and Nepal’s Ministry of Home Affairs lead with the aim of enhancing government’s disaster risk management capacity centrally and at the
municipal and local level.
3.2.3 Development Partners and International Organizations
141. Many development partners (DP) and international organizations (IO) in Nepal
have contributed efforts to reduce poverty, increase access to health and
education, increase literacy rates, and enhance agricultural productivity, social
structure, and the overall community development. According to Nepal’s Ministry of Finance, the total commitment is currently 5.3 billion USD provided by 73
international organizations for 742 projects in Nepal. An average project size
funded by these organizations is about 4.2 million USD.
142. Working with DPs and IOs are especially advantageous for policy making and in
aligning funding for the projects.
143. UN agencies can provide the institutional and international support, exchange
technical assistance, sharing of knowledge base, advice, capacity development,
and other organizational support.
144. INGOs provide support to the community for enhancing their capacity, for both
DRR and DRM in general, including specific projects targeted at schools. NGOs
may also be involved in direct intervention for the retrofitting or building of new
schools, in close coordination with the community and DEOs. Working with NGOs
will be beneficial due to their strengths in awareness raising, sensitization, capacity
building, and community mobilization.
page 49 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
3.2.4 NGOs, CBOs, and Community
145. Similarly, NGOs, CBOs, and the community can be very helpful when formulating
policies for the DRR and when seeking support and funding for projects for
implementing DRR at school level.
146. The Association of International NGOs (AIN) was formed by INGOs working in Nepal
in September 1996, to establish an important network in the development sector of
Nepal. About 112 INGOs are registered under this umbrella organization. These
members generally implement people-centered development programs
throughout the hills, mountains, and Terai areas included activities pertaining to
disaster preparedness, disaster management, and emergency relief programs
147. The four macro-level objectives that can be facilitated through the active
engagement of international and local NGOs are:
Multi-hazard resilience of school buildings in Nepal.
Raising awareness about DR of school buildings in the region
Sustainability of the implementation of multi-hazard resilience of school
buildings in Nepal.
Actual implementation of DRR intervention in some the areas, and for
smaller size buildings.
NGOs Local NGOs provide support to the community for
enhancing their capacity, for both DRR and DRM in
general, including specific projects targeted at schools.
NGOs may also be involved in direct intervention for
retrofit or building of new schools, in close coordination
with the community and DEOs. Working with NGOs will be
beneficial due to their strengths in awareness raising,
sensitization, capacity building, and community
mobilization.
CBOs The Community-Based Organizations (CBOs) are small,
informal organizations that provide various services
towards the development of rural communities and can
be used as channels to route DR awareness and
development information rural communities.
Local
Community
The local community is expected to continue to play an
important role in the education sectors especially in the
rural areas. The role of community in the DRR of schools is
expected to be very significant, and is elaborated in
section 3.3.8.
3.2.5 Academic and Professional Organizations
148. Academic institutions will be responsible for updating curriculum to include DR and
contribute to capability and capacity building. These institutions can also conduct
workshops and technical sessions for professionals. Professional associations can
provide resources, expertise, and many essential services to support a community’s resilience to disasters. Forming Technical Advisory Committees (TACs) are very
page 50 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
important when assisting DOE to finalize the designs by local consultants and guide
DOE/DEO staffs and consultants whenever any technical difficulties arises.
Academic
Institutions
The academic institutions are to update curriculum for
architectural and engineering graduates, which should
include greater emphasis in the DR and ES aspects of
design and familiarity with the design codes. Academic
institutions should also conduct technical workshops and
professional development programs on the proper
application of the codes and standards.
Institute of Engineering (IOE), Pulchowk should
play a leading role in developing and updating
curriculums, conducting technical workshops,
and conducting various research works.
CTVET should be responsible for providing trainings
to produce skilled masons. They should provide
trainings to small scale construction firms to
enhance their capabilities.
Professional
Associations
Professional associations can and do play a fundamental
role in supporting a community’s resilience to disasters. They provide resources, expertise, and many essential
services on which the community depends. Working with
professional associations may bring about collaboration
with critical infrastructure providers, which can contribute
to providing more opportunities to understanding risks
and ensuring the potential to continue providing services
during or soon after a disaster.
Consultants Consultants, oftentimes architectural and engineering
experts, are expected to develop their capabilities and
capacities to be able to do proper evaluation of DR
needs and the design of interventions for the existing
school buildings. This also includes the design of new
school buildings using proper tools, techniques, and
methodologies.
Construction
Firms
The contractors and construction firms are expected to
enhance their capability and capacity to carry out DR
intervention, using the right techniques with the right
quality, in a cost-effective manner. They are also
expected to improve the construction quality for new
buildings that incorporates the details necessary for
proper DRR.
Technical
Advisory
Committee
(TAC)
The role of the Technical Advisory Committee is very
important in ensuring that the overall process proceeds in
the proper manner, with proper quality, and with the right
output. TAC may be responsible for assisting DOE to
finalize the designs by local consultants, to guide
DOE/DEO staffs and consultants whenever any technical
difficulties arises.
page 51 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
3.2.6 Other Organizations
149. Strengthening DR is not a detached activity that can be achieved in a set
timeframe, nor can it be achieved without a joint commitment and concerted
effort by all sectors of society. Other parts of society can also play an important
role through their specializations such as those enumerated below.
National
Media
National media should conduct public awareness
through print, TV, and online media to inform the public
about the importance of DR and ES in general and for
schools in particular. MOE and DOE should provide the
material for such programming.
Teachers
and
academic
staff in the
schools
Teachers and academic staff in the schools are
expected to be trained and become aware of the
importance of DRM and the actions to be taken in case
of an emergency and disaster situation.
Students and
Youth
Groups
Student and youth groups can greatly support awareness
building and participate in emergency and disaster
management activities.
3.3 Primary Implementing Agencies
3.3.1 Overall Framework
150. The interest in DR activities is increasing based on the number of stakeholders and
actors currently involved and looking to participate in related programs. This may
prove to be beneficial for a nation where resources to continue and persevere for
an extended period of time may become a critical issue.
151. Due to the varying interests, it is important to designate primary responsibility to key
agencies. Considerable debates and several rounds of discussions rounded off
suitable agencies and arrangements. After careful deliberations, it was agreed
that the responsibility will be shared between MOE/DOE and MOUD/DUDBC. The
organizations charts of MOE and MOUD are available in Appendix B.
3.3.2 DOE and Institutional Development
152. The primary role and responsibility of DOE is to take ownership of the entire
program as the primary implementing and coordinating agency. More
specifically, DOE will be tasked to carry out the following actions related to the
achievement of the overall vision and objectives of this initiative :
a. Take the lead in obtaining the approval, and adoption of the proposed
strategy and the preliminary plan through the relevant channels
b. Carry out inventory of the all public and private schools in the country, in
association with EMIS, and supported by consultants, DEOs, and school
administration.
page 52 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
c. Carry out the detailed planning of the entire program, including the
prioritization for intervention, in line with this strategy, and the
accompanying plan, as supported by DUDBC and consultants.
d. Engagement and management of consultants to develop the guidelines,
type designs, and standardized solutions for typical cases
e. Carry out the intervention implementation for the public schools through
the DEO supported by DUDBC, municipalities, DAO, DDC, VDC, consultants,
contractors, community, NGOs, and other stakeholders.
f. Ensure the quality of the implementation and manage the coordination of
the process, as well as the final interventions through in-house inspectors
and consultants.
g. Support private school operators in terms of awareness, technical advice,
and guidelines identification of relevant resources for achieving DR.
h. Support DUDBC in the process of certification for private schools.
153. Considering the scale of the challenge at hand and based on the experiences
learned from the ongoing SSP, it is very clear that it is essential to elevate and
expand the institutional status of the sections and resources allocated within DOE
to address the physical infrastructure of the school facilities, A separate “Physical Infrastructure Division”, headed by a director is proposed, by merging various related sections, and establishment of dedicated sections for handing the DR
process, as shown in Figure 3-1.
154. It is important to note that the engineering staff of the DEOs, should report to and
coordinate with the head office for matters related to construction of new schools,
intervention for DR, and other building and infrastructure issues.
155. The new division must be given the required resources, as well as authority to
tackle various aspects of the program. This program must include competence-
based capacity building of the existing and newly engaged resources. These
resource needs are estimated in The Plan.
156. The responsibilities of this division will include overall planning, development of
guidelines, program and project management, property management, and
handling the related areas concerning health, nutrition, and safety of children and
teachers. This division will also handle the construction of new schools, retrofitting of
existing schools, and the maintenance and up-gradation of exsiting schools.
157. The new division is expected to work closely and be supported by with the relevant
sections in the Planning and Monitoring Division in DOE, such as the Educational
Management & Information Section (EMIS), Education Mapping, and
Communication and Coordination Section.
page 53 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
Figure 3-1: Proposed Physical Infrastructure Division (PID) in DOE
3.3.3 The Role of MOE/DOE
158. MOE/DOE will assume the prime responsibility for all schools, both public and
private sector, and will be established as the main implementing agency for the
public schools. Specific activities will be supported by DUDBC.
159. This decision was based on the realization that the DR of public schools is closely
tied with the school system management, a close interaction with community, and
the rehabilitation, expansion, maintenance, and up-gradation of the school
facilities. DOE also has a greater presence in all districts and has direct access to
the teachers, administrators, and tools such as databases. DOE is also in a better
position to carry out most of the Linked Strategies, such as awareness and
curriculum development related to DR. By conducting DR initiatives through DOE,
the process will have a wide ranging effects on the students, their parents, and the
community at large.
160. DOE involvement for the retrofitting works may be substantial in the first phase
which could last approximately three years. This three-year period should be used
to prepare all the guidelines, norms, and regulations 21 for the retrofitting of schools.
After these details have been completed, MOE/DOE can transfer the majority of
the responsibility to DUDBC to continue the program to its completion.
3.3.4 The Role of MOUD/DUDBC
161. DUDBC will ensure the DR for private school buildings as supported and guided by
policies and regulations to be developed by the MOE/DOE. In areas where DUDBC
may not have an active presence, this role may be delegated to municipal
bodies.
21 GON has prepared and endorsed guidelines for Disaster Resilient Hospitals & Health Facilities in Nepal. Similar guidelines should
be prepared for school sector.
page 54 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
162. This decision was based on the current overall responsibility and jurisdiction that
DUDBC handles for the development of infrastructure and buildings, including the
buildings where private schools are housed. DUDBC also has the authority to
develop and enforce the building codes and standards. DUDBC is also currently
involved with the current SSP which deals with the DR of both public and private
hospitals and has thus gained considerable experience and developed capability
and capacity to implement the initiative at a larger scale.
163. The strengths of both departments pertaining to their respective roles are
summarized below. This information is used as the basis for the development of
overall framework, not only for schools, but also for other academic institutions.
DOE DUDBC
MOE is primarily responsible for
all schools nationwide.
The department manages all
aspects of education, including
the physical infrastructure and
database of the schools.
DOE is also closely linked with
community.
DOE is also experienced with
intervention strategies through
the SSP.
It will be easier to integrate and
align the project with SRRP and
other future plans and
programs.
Integrating awareness, training,
drills for students, teachers,
community, and DR into the
academic curricula will also be
easier through DOE.
Maintenance, upgradation,
and expansion of buildings will
also be easier to manage due
to DOE direct responsibility.
• MoUD is directly responsible for
buildings and infrastructure
nationwide.
• The ministry is handling increasing
DR of hospitals and other public
buildings.
• DUDBC has greater technical
expertise and capacity.
• MoUD-DUDBC has jurisdiction on all
buildings, including private schools.
• The department is also responsible
for the approval, certification, and
enforcement of building codes
and regulations.
164. On the provisions of funding allocation to DUDBC, currently funding comes through
the ministries directly to DUDBC. It is key to continue to allocate the budget to the
respective agencies and avoid the trend in GON where budgets are passed from
ministry/department secretaries before the amount is received by the
implementing department or unit.
165. Figure 3-2 shows the conceptual framework for sharing the roles and responsibilities
between MOE/DOE and MOUD/DUDBC for increasing the DR of various types of
academic institutions, with focus on public and private schools. This framework
covers almost all types of institutions and operators. This is used as the basis for
development of the organizational structures and other implementation
mechanisms.
page 55 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
Public and Community
Supported
Primary to High Schools
Direct Intervention by
DOE
Vocational Colleges
Universities
Colleges
Direct Policy
Guidelines Certification
by MOE
Private
Self-owned or Rented
Institutional
Policy and Regulation
License Renewal
By MOE
Ministry of Education Ministry of Urban Development
Coordination
Coordination
Technical Support
Regulations
Inspections
Certification
DUDBC
Figure 3-2: Conceptual Framework for Sharing DR Responsibility in Academic Institutions
3.3.5 Primary Role of DUDBC
166. The active engagement of the DUDBC is essential for the overall success of the
program, as highlighted in the overall framework. The specific role of the DUDBC is
envisaged to be:
a. Provide technical support and advice to the DOE for developing guidelines
in line with the evolving building codes and active involvement in the
similar program for hospitals.
b. Develop criteria and procedures for the evaluation and certification of the
existing private buildings currently being used as schools.
c. Develop criteria and procedures for certifying new private buildings which
have been proposed to be used as schools.
d. Carry out necessary reviews, approvals, inspections, and certifications of
buildings that have been identified to be used as schools.
167. As urbanization continues in the country, it is expected that an increase in the
enrolment of students in private schools in urban areas will continue. And as this
trend continues, the role of DUDBC is expected to expand. At present, more than
75% of the students in KV are enrolled in private schools, thus making the role of
DUDBC more significant when compared to DOE in ensuring the safety of children
in schools during disasters.
page 56 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
Figure 3-3: Proposed New Sections in DUDBC
168. To handle this role, it is proposed that two new sections be established within the
Building Division to handle the schools and hospitals separately. These sections may
be developed into full divisions in a few years as the requirements of certification
and number of private schools increases (Figure 3-3). The division offices under
DUDBC will support the DEOs in technical matters and any issues private schools
may encounter within their respective jurisdictions.
3.3.6 Collaboration between DOE and DUDBC
169. Close collaboration and coordination between DOE and DUDBC are essential for
achieving the goals of the program while providing consistency when
implementing DR for public and private schools. Figure 3-4 show the proposed
coordination arrangement, comprising of :
a. A top level committee, jointly chaired by the Director Generals of DOE and
DUDBC to guide and oversee the implementation of the program.
b. A task force jointly chaired by the directors of the Physical Infrastructure
Division (PID) in DOE and the Building Division in DUDBC for the formulation
of the guidelines and the review of ongoing projects.
c. A working group comprised of representatives from the Planning and
Design Section in PID and the Schools Section in DUDBC for coordinating
the implementation of prescribed interventions in public schools and
certifying private schools.
d. Working groups at each district level comprised of representatives from
DEOs and respective divisional offices of DUDBC for coordination, as well as
for technical cooperation and certification.
Could be established as
Division after few years.
page 57 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
Figure 3-4: Proposed Roles for DOE and DUDBC
MOUD
Planning, Monitoring and Foreign Aid Division
Monitoring and Rating Section
Drinking Water & Environment Division
Regional Coordination & Capacity Increment
Section
Department of Drinking Water & Sewage Outlet
DUDBC
International Economic Cooperation Coordination Division
EconomicPolicy
Analysis Division
Budget and
Program Division
Legal and Consultation Division
Monitoring and Evaluation
Division
MOFALD
Disaster Management & Municipal Development
Section
Municipal Management Section
Municipal Management
Division
Department of
Infrastructure Management
Division
Planning & Foreign
Co-ordination Department
Infrastructure & Technology Management
Section
Infrastructure Policy Coordination Section
Standard development
Information, Publication & Archival Section
Planning & Foreign Aid
Coordination Section
Monitoring & Evaluation Section
MOF
Prime Minister &
Council of Minister
Joint Secretary
(Administrative & Manpower Development
Division)
Joint Secretary
(Financial & Infrastructure
Development Division)
Information & Technology Section
Joint Secretary
(Social Development, Planning and
Monitoring Division)
Social DevelopmentSection
Joint Secretary
(Conference of Council of Ministers &
Constitutional Body Division)
Council of Ministers and Constitutional Body
Section
Joint Secretary
(Governing Development Division)
Joint Secretary
(Legislation & Development Division)
Law & Decision Implementation
Section
MOHA
Divisions
Departments
Security Agencies
Disaster Management
Division
Policy Planning &
Program Division
Internal Management
Division
Law & Order
Coordination Division
Human Resource
Management Division
Figure 3-5: Proposed Coordination with Other Ministries
page 58 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
3.3.7 Role of Other Ministries
170. Coordination with other ministries will also prove to be very important. As shown in
Figure 3-5, the MOHA, MOUD, MOF, MOFALD, and the Office of the Prime Minister
will play a crucial role in ensuring that the objectives of this program are met.
Detailed responsibilities will be provided in the action/responsibility matrix with the
accompanying document, The Plan.
3.3.8 Role of Community
171. It is well established that in Nepal, the role of communities and the local
government are very important in various development works, including the
construction and management of schools. This approach is very admirable, and
has been developed and established over several decades.
172. However, during the stage of retrofitting and strengthening the school against the
disasters, quality assurance is of great importance and key to the project’s effectiveness. If the retrofitting work is not of good quality then the whole effort
could be wasted. One of the main causes for vulnerability in buildings is the low
construction quality. If quality is not achieved properly in the retrofitting work or the
reconstruction work, then the safety and/or the DR will not be properly ensured.
173. It may be appropriate to reconsider the roles for community participation. Several
discussions were held on this topic with the department and other stakeholders.
Therefore, for the school DRR process and activities, the following role of the
community is proposed.
a) Be involved in awareness building of importance of DRR activities, and basic
training programs in response to various hazards and disasters. Generate
ownership, pride, confidence and understand benefits of this intervention for
their community as whole and safety of their children.
b) Be involved in the fund raising, and generating other in-kind resources and
services related to the process. However, this fund-raising and financial
contribution should not be tied to the basic financing of the project. The
appropriate funds for the completion of the primary works 22 to make the
building operational, both for new construction and for retrofit must be
provided by the program/project budget. The contribution from the
community should be encouraged, but should earmarked for secondary
works.23
c) Be involved in the direct intervention (construction) activities at various levels
depending on the size and complexity, ranging from full execution of small and
simple buildings, specially using local materials and techniques, to providing
22 The primary works are defined as all works related to structural safety, building enclosure for protection
from the elements, and prevention of various hazards, so that the building has the required resilience
and functionality.
23 The secondary works are defined as any items will improve the functionality and aesthetics of the
building and can be carried out in stages, such as painting, flooring, electrification, and façade
treatment.
page 59 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
material and labor support for simpler medium size building. The actual extent
of involvement will depend on the capability, capacity and willingness of the
community members, and should be agreed upon mutually by the DEO, the
VDC and the local community for each school/ building.
d) Be involved in the monitoring of the works carried out by other parties, in
conjunction with the DEO, VDC, and the consultants, where applicable.
3.3.9 Coordination Framework
174. A separate, dedicated coordination office is proposed for the coordination of the
entire school DRR process (Figure 3-6). It will function as a clearing house and
repository of all information generated and is needed to smoothly carry out various
aspects of the overall process. The coordinator will be assisted by at least four
offices, each coordinating with the various ministries in the GON with various
development partners, UN agencies, NGOs, and with private schools. Information
offices to mainstream databases, reports, and documents while mandated with
the task of properly disseminating both media partners and the public are essential
components of the initiative.
175. The coordination office will also work with the various task forces, technical
committees, with professional bodies, academic institutions and so forth. If one
national level disaster management agency is established, this coordination office
could become the conduit for integrating DR into schools as part of the overall
national framework. The following options are possible for the creation of the
coordination office:
a. A special unit or team within the ADB Nepal office actively coordinating
Flagship 2.
b. A special unit/section with MOE.
c. A special unit/section with DOE.
d. As an independent “program office” within the overall NRRC framework, funded and sourced through the school DRR program until completion.
Various Ministries
in GON
DR-FP
Development
Partners
DR-FP
UN Agencies
DR-FP
INGOs/ NGOs PABSON
GON
Coordination
Officer
Development
Partner
Coordination
Officer
UN and NGO
Coordination
Officer
Private and
Institutional
Coordination
Officer
Information
Management &
Communication
Officer
School Disaster
Risk Coordinator
(SDRCO)
National &
International Media
Public Events
Technical
Advisory
Committee
Professional Bodies
Academic/Research
Institutes
School Disaster
Risk Steering
Committee
National Disaster
Management Agency ?
*DR-FP Disaster Risk Reduction Focal Point
page 60 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
Figure 3-6: Proposed Organization in Dedicated Coordination Office
3.4 Summary and Conclusions
176. The scale and complexity of the tasks requires the engagement of many
stakeholders carefully aligned with appropriate linkages for a strong and flexible
framework that is necessary for the implementation of the DR strategies at a
national level.
177. Institutional arrangements, roles and responsibilities of the key stakeholders, and
coordination framework is largely reinforced by the collective agreement for the
MOE, through DOE, to take ownership of the entire program as the primary
implementing and coordinating agency. Since the DR of public schools is closely
tied with factors that are under the MOE/DOE’s areas of responsibilities such as the school system management, a close interaction with community, and the
rehabilitation, expansion, maintenance, and up-gradation of the school facilities.
DOE also has a greater presence in all districts and is in a better position to carry
out most of the Linked Strategies and is expected to have a greater national
reach.
178. MOE/DOE’s involvement for the retrofitting works may be substantial in the first phase to prepare all the guidelines, norms, and regulations for the retrofitting of
schools. It is expected that these high level planning details will be accomplished
within three years. MOE/DOE can then transfer the majority of the responsibility to
Department of Urban Development & Building Construction (DUDBC), a
department under the Ministry of Urban Development (MOUD), to continue the
program to its completion.
179. The active engagement of the DUDBC is essential for the overall success of the
program as the main department entrusted to manage the urban development
and building construction. At present, more than 75% of the students in KV are
enrolled in private schools, thus making the role of DUDBC more significant when
compared to DOE in ensuring the safety of children in schools during disasters.
180. DUDBC is encouraged to provide full support to the DOE in terms of technical and
human resources for the DR of public schools and assume direct responsibility for
the DR of private schools, in collaboration with DOE.
181. Frequent and smooth coordination with other ministries: MOHA, MOUD, MOF,
MOFALD, and the Office of the Prime Minister will help ensure that the objectives of
this program are met.
182. Due to the level of community participation that is prevalent in Nepal, it may be
useful to reconsider the roles for community participation to include generating
ownership by the community’s inclusion in basic training programs for response to various hazards and disasters, fund raising, and generating other in-kind resources
and services related to the process, direct intervention (construction) activities at
various levels depending on the size and complexity, and monitoring the works
carried out by other parties, in conjunction with the DEO, VDC, and the
consultants.
183. A separate, dedicated coordination office is proposed for the coordination of the
entire school DRR process. This office will function as a clearing house and
page 61 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
repository of all information generated and needed to smoothly carry out various
aspects of the overall process.
page 62 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
References
1. ACI Committee 318 (2002). Building Code Requirements for Structural Concrete
and Commentary. ACI 318-02.
2. American Society of Civil Engineers (2000). Prestandard and Commentary of the
Seismic Rehabilitation of Buildings. FEMA 356.
3. American Society of Civil Engineers (2006). Seismic Rehabilitation of Existing
Buildings. ASCE 41-06.
4. American Society of Civil Engineers (2003). Seismic Evaluation of Existing Buildings.
ASCE 31-03.
5. Applied Technology Council (1997). NEHRP Commentary on the Guidelines for the
Seismic Rehabilitation of Buildings. FEMA 274.
6. BIA (1996). The Assessment and Improvement of the Structural Performance of
Earthquake Risk Buildings – Draft for General Release. New Zealand National
Society for Earthquake Engineering
7. Bureau of Indian Standards (2002). Criteria of Earthquake Resistant Design of
Structures. IS 1893 (Part 1): 2002.
8. CEB (1997). Fastenings for Seismic Retrofitting. Comite Euro-International Du Beton,
Thomas Telford, London.
9. Department of Education, Ministry of Education, Government of Nepal (2012).
School Sector Reform Program (SSRP), Second Higher Education Project (SHEP),
Education For All Shishu Vikash Karyakram, Community School Capacity
Development Program, Status Report 2012.
10. Department of Education, Ministry of Education, Government of Nepal (2012).
School Earthquake Safety Program (SSP) Action Plan, 2012/2014. Sanothimi,
Bhaktapur.
11. Department of Urban Development and Building Construction (1994). Nepal
National Building Code. NBC 105:1994.
12. Federal Emergency Management Agency (2014). FEMA 395 | Incremental Seismic
Rehabilitation of School Buildings (K-12): Providing Protection to People and
Buildings (2003) http://www.fema.gov/media-library/assets/documents/5154
13. Federal Emergency Management Agency (2014). Hazus.
http://www.fema.gov/hazus
14. Masonry Standards Joint Committee (2002). Building Code Requirements for
Masonry Structures. ACI 530-02/ASCE 5-02/TMS 402-02.
15. National Society for Earthquake Technology-Nepal (NSET) (2011). Developing
Strategy for Improving School Seismic Safety (SSS), prepared for GFDRR.
16. Nepal Risk Reduction Consortium (April 2011). Disaster Risk Reduction in Nepal:
Flagship Programmes.
page 63 of 70
Strategy for Increasing Disaster Resilience for Schools in Nepal
17. National Society for Earthquake Technology (2011). Snapshot Study for School
Safety in Nepal - Report on Snapshot Study for School Safety in Nepal, 2011, a
government report prepared by Nepal (NSET) financed by ADB.
18. Oral Buyukozturk, Oguz Gunes (2003). Advances in Earthquake Risk Assessment
and Hazard Reduction for Lange Inventory of Structures with High Characteristic
Variability. ARI - The Bulletin of the Istanbul Technical University, Volume 53, Number
2, June 2003, Istanbul, Turkey.
19. Rutherford & Chekene (R & C) Consulting Engineers (2006). Techniques for the
Seismic Rehabilitation of Existing Buildings. FEMA 547.
20. SAARC Disaster Management Centre (2014). Nepal Disaster Knowledge Network.
Accessed from: http://www.saarc-sadkn.org/countries/nepal/country_profile.aspx
21. Sugano (1989). Study of the Seismic Behavior of Retrofitted Reinforced Concrete
Buildings.Proc. ASCE ’89 Structures Congress, San Francisco, CA.
22. UN HABITAT (2014). Tools for the Assessment of School and Hospital Safety.
http://www.fukuoka.unhabitat.org/info/misc/20130216.html
23. UNDP/UNIDO (1985). Post-Earthquake Damage Evaluation and Strength
Assessment of Buildings under Seismic Conditions. Volume 4, Vienna
24. UNICEF et al. (March 2013) Comprehensive School Safety.
25. World Bank (2013) Urban Growth and Spatial Transition in Nepal.
http://issuu.com/world.bank.publications/docs/9780821396599
Appendix A
School Data
Strategy for Increasing Disaster Resilience for Schools in Nepal
page 65 of 70
Figure A-1: Seismic Hazards in Nepal based on U.S. Geological Survey (USGC) Map
Figure A-2: Distribution of School Indicators in Various Regions (Public and Private)
Strategy for Increasing Disaster Resilience for Schools in Nepal
page 66 of 70
Figure A-3: Distribution of School-related Indicators in the Kathmandu Valley
Figure A-4: Distribution of DEOs, MOE Resource Centers, and DUDBC Offices
Appendix B
Organization Charts
Strategy for Increasing Disaster Resilience for Schools in Nepal
page 68 of 70
Education Minister
State Minister
SecretaryNepal National Commission
for UNESCO
Administration DivisionHigher Education and
Educational Management Division
Planning DivisionMonitoring, Evaluation
and Observation DivisionSyllabus Development
Center
Office of Examination Controller
Informal Education Center
Educational Manpower
Development Center
Department of School Teacher Records
Nepal National Library
Keshar Library
Department of Education
Regional Education
Directorate
District Education Office
Resource Center
Schools
Educational Training Center
Educational Training Sub Center
Internal Administration and Property
Management Section
Employee Administration and Manpower
Development Section
Financial Administration Branch
Rules and Regulations Advisory Section
Sports and Youth Program Section
University Donors Commission
Universities
Higher Secondary Education Council
Council for Technical Education & Vocational Training (CTEVT)
Higher and Technical Education Section
Scholarship Section
School Education Section
Foreign Aid Co-ordination Section
Policy Analysis & Program Section
Library Co-ordination Section
Monitoring and Evaluation Section
Observation Section
Research & Educational Management and
Information Section
Autonomous Institutions
Dilliraman Kalyani Regmi Memorial
Library
Janak Education Material Center
Ministry of Education
(MOE)
Figure B-1: Overall Roles and Various Divisions in MOE
Minister
Secretary
Administrative Division
Planning, Monitoring & Foreign Aid Division
Drinking Water & Environment Division
Physical Planning & Urban Dev. Division
Building and Accommodation
Division
MunicipalityCoordination Div. Department of
Drinking Water & Sewage Outlet
DUDBCInternal
Management
Section
Finance
Administration
Section
Employee
Administration
Section
Law and Order
Implementation
Section
Monitoring and
Evaluation Section
Foreign Aid and
Investment
Promoting Section
Planning Section
Social Coordination
Section
Environment
Section
Regional Coordination & Capacity Increment
Section
Drinking Water and
Sanitation Section
Town Development
Committee and Small
City Section
Physical Planning and
Urban Infrastructure
Section
Building
Section
Disaster Management
Section
Accommodation
Section
Municipality Financial
Management
Development
Municipality Good
Governance and
Capacity
Ministry of Urban Development
(MOUD)
A
B C
E
D
Figure B-2: Overall Roles and Various Divisions in MOUD
Strategy for Increasing Disaster Resilience for Schools in Nepal
page 69 of 70
Monitoring and Evaluation (A) is very relevant and important for the
development and implementation of the rating and certification system for
private schools, in particular, and public school buildings as well, in consultation
with the DOE/MOE. This section should be engaged from an early stage in the
program.
The section marked (B) should be consulted and informed of the various
capacity and capability activities for school DRR.
Sections marked (C) and (D) involved in DR activities should be informed of the
outcomes of the program and the school building certified for DRR.
Within MoUD, DUDBC is the primary division that should take a major role and
stake in the overall DRR of buildings, including schools.