Technical Assistance Consultant’s Report€¦ · Achham, Banke, Chitwan, and Pachthar Districts...
Transcript of Technical Assistance Consultant’s Report€¦ · Achham, Banke, Chitwan, and Pachthar Districts...
Technical Assistance Consultant’s Report
This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents. (For project preparatory technical assistance: All the views expressed herein may not be incorporated into the proposed project’s design.
Project Number: 44168-012 Capacity Development Technical Assistance (CDTA) October 2013
Nepal: Mainstreaming Climate Change Risk
Management in Development
(Financed by the Strategic Climate Fund)
District Baseline Reports: Department of Roads (DOR) Achham, Banke, Chitwan, and Pachthar Districts Prepared by ICEM – International Centre for Environmental Management
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
i
TA – 7984 NEP
October, 2013
Mainstreaming Climate Change Risk Management in
Development
1 Main Consultancy Package (44768-012)
ACHHAM DISTRICT BASELINE: DEPARTMENT OF ROADS
(DOR)
Prepared by ICEM – International Centre for Environmental Management
METCON Consultants
APTEC Consulting
Prepared for Ministry of Science, Technology and Environment, Government of Nepal
Environment Natural Resources and Agriculture Department, South Asia
Department, Asian Development Bank
Version B
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
ii
TABLE OF CONTENTS
1 ACHHAM DISTRICT ........................................................................................................... 1
1.1 District Sector Master Plan ............................................................................................. 1
1.2 Sector budgeting and staff .............................................................................................. 1
1.3 Sector trends and issues ................................................................................................. 1
1.3.1 Trends ....................................................................................................................................... 1 1.3.2 Issues ........................................................................................................................................ 1
1.4 Asset inventory ............................................................................................................... 2
1.5 Past extremes in the district ........................................................................................... 2
1.6 Linkages to other sectors ................................................................................................ 2
1.7 Priority infrastructure in Dolakha District ....................................................................... 2
1.7.1 Prioritisation process ................................................................................................................ 2
2 ACHHAM DISTRICT: ASSET BASELINE ................................................................................ 3
2.1 Asset1:Sanfebagar – Martadi Road ................................................................................ 3
2.1.1 Asset Description ...................................................................................................................... 4 2.1.2 Adaptation audit ...................................................................................................................... 5
ANNEX A – MAP OF ACHHAM DISTRICT ........................................................................................ 1
ANNEX B: YEARLY IMPLEMENTATION CALENDAR .......................................................................... 1
ANNEX C: ANNUAL BUDGET ......................................................................................................... 4
ANNEX D: NAMES & POSITIONS OF DISTRICT OFFICERS ................................................................. 5
ANNEX E: PAST EXTREME EVENTS ................................................................................................. 6
ANNEX F: ASSET INVENTORY - ACHHAM ....................................................................................... 8
ANNEX G: PHOTOGRAPHS ASSET 1 ............................................................................................... 9
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
1
1 ACHHAM DISTRICT
1.1 District Sector Master Plan
The strategic roads in Achham District fall under the jurisdiction of Doti Division. Doti division is one
of the division offices of the DoR and is responsible for all types of maintenance works in Doti,
Dadeldhura, Achham and Bajura Districts. All the 25 divisions are required to prepare Annual Road
Maintenance Plan (ARMP) of and submit to the DoR head office. GoN allocated the budget after the
only after the approval of the ARMP. The division does, in general, does not prepare long term
master plan.
1.2 Sector budgeting and staff
Budgeting
A su ar of the Divisio ’s Budget is give i A e C
Staff
The names and positions of district officers are given in Annex D
1.3 Sector trends and issues
1.3.1 Trends
The current trend of the division is as follows
Planning
As mentioned above ARMP is the main tool for planning of maintenance/construction activities of
strategic roads in the district.
Design & Construction
Assessment of needs, planning, design and estimation for all type of maintenance works are carried
out by the division staffs. However design works of new roads and bridges in general are carried out
by local consultants.
All the construction and maintenance works of roads and bridges are done by using local
contractors. The present trend in the construction has shifted from manual to machines. For
example at present construction equipment such as excavator, paver, dozer, roller are being used
more frequently.
Doti Division beside maintenance of roads and bridges, also executes medium scale road and bridge
projects.
Supervision of works is mainly done by division staffs.
1.3.2 Issues
Major issues/difficulties faced by the divisions are as follows:
1. Budget is not sufficient and is not released timely
2. Programs are not approved in time
3. Very low bid by the contractors
4. Contractors receive mobilization advance but do not start and complete the work in time.
5. Several projects but limited technical manpower
6. In Doti district local contractor are not well experienced in the contractual works and hence
they tend to delay the works and sometimes even leave the works without completing
them.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
2
7. The tipper trucks, loaders Dozers provided by the heavy equipment division (HED) of DoR
are old and their repair cost is very high.
8. In RBN funded maintenance and other works the contractors have tendency to start the
work after monsoon only. This has brought a serious problem specially in cyclic works
because they assume that they will suffer by late payment because of other lagging
contractors, even if they complete the works in time.
1.4 Asset inventory
The asset inventory is given in Annex F
1.5 Past extremes in the district
A table of past extreme events is given in Annex E
1.6 Linkages to other sectors
Cooperation with other sectors
The DoR at present is cooperating with the following agencies for implementation of RIWs:
DoLIDAR, DoI, DWSS, DWIDP, NT, NEA, Department of Transport (DoT)
Major Organization working in the District:
WB is providing 10% of the maintenance to the division.
1.7 Priority infrastructure in Dolakha District
1.7.1 Prioritisation process
The key criteria for prioritisation include:
Infrastructure of national strategic importance
Infrastructure of district strategic importance
Infrastructure that has been impacted by past extreme events
Infrastructure located in areas prone to past extreme events
At least one planned infrastructure
The consultant in consultation with the division chief prepared final lists of the priority structures of
the district. The list was prepared following the criteria provided in District Office Report. The
priority list is given in the following table.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
3
2 ACHHAM DISTRICT : ASSET BASELINE
2.1 Asset1:Sanfebagar – Martadi Road
Overall view of the road section from Sanfebagar side. As seen in the picture, a long section of the
road is being hit by the Budhiganga River.
ID Name Infrastructure
type
Reason/s for inclusion
1 Sanfebagar-Martadi Road at
km 12.
Road On Asadh 20 (June 4, 2013) heavy flood
Budhiganga River severely damaged about
60m long section of the road at km 12.
The flood is also threatening 200m long
road section at the same location. If the
road will be washed away, the road link of
Bajura District with National Road
Networks will be cut off.
2 Landslide at km 9+920 along
Sanfebagar –Mangalsen Road
Big landslide causing frequent blockage of
traffic.
3 Lanslide at km 14+500 along
Sanfebagar-Martadi Road
It is the biggest landslide in Achham
District along above road. The lanslided
causes frequent blockage of the vehicular
traffic.
4 Motorable Bridge across
Budhiganga River
Bridge Due to extensive erosion, the
reinforcements of the lower portion of
one pier of the bridge are exposed. If the
problem is not corrected timely, the repair
cost will be very high.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
4
Sketch Plan of Site
Sanfebagar to Mangalsen road (classified as Feeder Road) is one of the most important roads in the
far Western Development Region because it provides a motorable link to the eastern part of
Achham District and the whole of Bajura District.
The total length of the Sanfebagar-Martadi Road is 57 km of which 14 km lies in Achham District.
The road section lying in Achham is black topped.
Majority of the road section in Achham District is located very near to the Budhiganga River which is
the largest river in the district. The river is a big threat to the road as it frequently damages it. Hence
DoR has constructed gabion protection walls to protect the road from river erosion at many
locations.
Due to heavy flood, the river shifted its course towards the road and damaged about 200m long
road section on June 4, 2013. Out of 200m road section, the condition of the condition of 60m long
section is very vulnerable because the gabion walls which were constructed for protection are
already damaged and the road section can be washed away at any time if adequate
protection/remedial measures are not carried out.
2.1.1 Asset Description
Watershed context
The road section lies in the watershed location is Budhiganga River which is a major river in the
whole district. The watershed of the river is covered by cultivated land, bushes and forests. Part of
the Khaptad National Park lies in the watershed of this river.
Asset location
The road section lies at km 12 from Sanfebagar. The road is located very near to the Budhiganga
River (see photo). There are not any manmade features near the road.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
5
The road passes throug the and fragile slope. Hence landslides are common throughout the whole
road section.
Vegetation near the asset mainly consists of bushes, shrubs and trees. Due to steep and fragile
slope, very few areas at the mountain side are culrivated.
The soil type at the hill slope consists of highly weathered rock with loose boulders and loose soils.
Hence the landslides are common along the whole road stretch.
There are not any major water bodies near the asset except small creeks.
The road section is very vulnerable to landslides as well as river erosion.
Asset condition
The stability of the road is very critical and it can be washed away any time during flood if
appropriate measures are adopted. However, there are no major problems with the road surface.
Similarly, the side drains and minor slides along the road are cleaned on regular basis.
Asset design
The road is designed following the standards of feeder road. There are not any shortcomings on the
geometric design aspects (horizontal and vertical curves, longitudinal gradient, visibility etc) of the
road. As the road follows the river alignment and passes through very fragile area it is suffering from
landslides as well as river erosion. DoR has constructed a long gabion wall to protect the road. The
section of gabion walls are adopted from standard design drawings of DoR.
Past extreme events and impacts
Landslides and bank erosion are common along the majority of the road section and cause road
closure for few hours. There was heavy flood on June 4, 2013 and the river shifted its course towards
the right bank and damaged about 200m long road section.
According to local people there were no extreme events in the past especially after black topping of
the road.
Past adaptation responses
DoR has constructed breast walls at the hill side and retaining walls at the river side. Although the
breast walls are functioning properly, the retaining walls have started to fall.
Design appropriateness
The design of road, breast walls and drainage structures seem appropriate. However the design of
gabion walls which were constructed to protect the roads from river erosion have following
shortcomings:
There are no proper launching apron at the river side to protect the road from scouring;
The quality of gabion walls is poor; the stones in the boxes are not properly packed (in loose
state) and the boxes are not properly tied with each other.
2.1.2 Adaptation audit
Adaptation location
See Baseline report above
Adaptation condition
See Baseline report above
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
6
Threat description
There are two types of threat to the asset caused by increasing rainfall and rainfall intensity (200m
long section of the road). They are landslides at hill slope and bank erosion at river side. The field
observation showed that the threat due to landslide is relatively less because if such incident occurs,
the traffic can be resumed within few hours or few days. But if the road is washed away by the flood,
it may take several days or even month to reconstruct the damaged section
Past extreme events and impacts
See Baseline report above
Adaptation design
See Baseline report above
Adaptation success
See Baseline report above
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
1
ANNEX A – MAP OF ACHHAM DISTRICT
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
2
ANNEX B: YEARLY IMPLEMENTATIO N CALENDAR
Recurrent & Specific Maintenance Program
S.N. 2.1.2.1.1 Name of Road Km
Proposed Budget
Recurrent
Minor Specific Total
1
H14: Mahakali Rajmarg
H1405:Faltude-Budar
H1406:Budar-Gairah
H1407:Gairah-Syaule
H1408: Syaule-Anarkholi
11.38
22.08
29.74
22.38
402818.00
1650841.56
877459.20
653181.60
1566180.00
1566180.00
1328880.00
4746000.00
1968998.00
3217021.56
2206339.20
5399181.60
2
H15: Seti Rajmarg
H1501: Syaule-Korayal
H1502: korayal-Samuhagad
H1503U: Samuhagad-
Junc.Sanfe road
24.96
24.73
16.27
661516.80
2044313.37
1388093.27
17560200.00
11865000.00
11556510.00
18221716.80
13909313.37
12944603.27
3
F51:Silgadhi-Sanfe Road
F5101Silgadhi-Choukhutte.
F5102 Choukhutte.-Sanfe
41.00
16.00
728640.00
1481982.00
20559007.56
4740067.50
21287647.56
6222049.50
4
Sanfebagar-Martadi Road
F14601 Sanfebagar-Rakse
F14602 Rakse-Martadi
14.00
13.00
487899.00
455020.50
474600.00
949200.00
962499.00
1404220.50
5 SanfeBagar Mangalsen Road
H1825 35.00 1046560.00 474600.00 1521160.00
Total
11878320.00
77386425.06
89264745.06
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
3
Periodic Maintenance Cost Estimate
Name of Road: Seti Rajmarga (Korayal-Samuhagad) Road Link:
H1502
km:
24.70
S.N Item Unit Quantity NRs./unit Total
1 Providing and laying average
20mm thick premix for pothole
including rolling and compaction all
complete
Sq.m 1975.00 750.00 1481250.00
2 Providing and laying Bitumen
Slurry Seal for crack seal Sq.m. 1220.00 145.00 176900.00
3 Providing and laying SBSD Sq.m. 123500.00 309.00 38161500.00
Total 39819650.00
VAT 13% 5176554.50
Contingencies 5% 1990982.50
Grand total 46987187.00
Name of Road: Seti Rajmarg (Samuhagad-Jn. Sanfe Road) Road Link:
H1406
km:
16.27
S.N Item Unit Quantity NRs./unit Total
1 Providing and laying average
20mm thick premix for pothole
including rolling and
compaction all complete
Sq.m. 1300.00 750.00
975000.00
2 Providing and laying Bitumen
Slurry Seal for crack seal
Sq.m. 910.00 145.00 131950.00
3 Providing and laying SBSD Sq.m. 81200.00 309.00 25090800.00
Total 26197750.00
VAT 13% 3405707.50
Contingencies 5% 1309887.50
Grand total 30913345.00
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
4
ANNEX C: ANNUAL BUDGET
Activity
Allocation for current fiscal year
2011/12
Proposed for next fiscal year
20012/13
Administration 49,82,000.00 59,59,900.00
Routine Maintenance 1,82,45,450.00 1,96,49,130.00
Recurrent Maintenance
Minor
98,57,000.00 1,18,78,320.00
Specific Maintenance 90,00,000.00 7,73,86,425.06
Periodic Maintenance 11,47,00,000.00
Rehabilitation
Reconstruction
Bridge Construction 2,70,00,000.00 7,00,00,000.00
Bridge Maintenance 1,50,00,000.00 2,59,01,295.00
Other works 2,00,000.00 10,20,000.00
Emergency Maintenance 15,00,000.00 25,01,000.00
Road Safety Works 2,00,000.00 12,00,000.00
Total 85,984,450.00 330,196,080.06
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
5
ANNEX D: NAMES & POSITIONS OF DISTRICT
OFFICERS
SN Name Position
1 Mr. Bijaya Kumar Mahato Sr. Divisional Engineer
2 Mr. Nati Babu Khdka Engineer
3 Mr. Sunil Babu Panta Engineer
4 Mr. Man Signh Dhami Engineer
5 Mr. Dhruba Bahadur Chand Engineer
6 Mr. Krishna Brasad Adhikari Accountant
7 Mr Ram Datta Panta Administrative Officer
8 Mr. Surya Prasad Ojha Nayab Subba
9 Mr. Moti Singh Rawal Accountant
10 Mr. Bhupendra Singh Badal Sub-Engineer
11 Mr. Sanjaya Kumar Yadav Sub-Engineer
12 Ms. Chanda Bhandari Kharidar
13 Mr. Dharma Bahdur Chaudhari Kharidar
14 Mr. Tej Bahadur Mahato Office Assistant
15 Mr. Mr. Devi Luhar Office Assistant
16 Mr. Mr. Indra Bahdur Medhasi Office Assistant
17 Mr. Mr. Nara Bahdur Saud Office Assistant
18 Mr. Bhakta Raj Ojha Office Assistant
19 Mr. Megh Bahdur Saud Office Assistant
20 Mr. Sher Bahdur Bhattaai Office Assistant
21 Mr. Gore Bhul Office Assistant
22 Mr. Dan Bahdur Saud Office Assistant
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
6
ANNEX E: PAST EXTREME EVENTS
VDC/
Municipality &
Ward No.
Date
Type of
Disaster
People Affected
Family
Animal
Loss
House
Destroyed
Shed
Destroyed
Land Loss Public
Property
Estimated
Loss
(Rs.) Dead Missing Injured Total Partly No. Unit
2066 (2009/2010)
Nada-8 2066/03/17 Flood 1
Kalekada 2066/04/04 Flood 1 2 2
Khaptad 7, 8 2066/04/16 Flood 50
Khaptad 7, 8 2066/04/25 Flood 50
Patalkot-9 2066/06/20 Landslide 10 60 4
Sidheshwor 2066/06/20 Flood 4
Bindabasini-1 2066/06/20 Flood 1 2 1
Marku-7 2066/06/21 Flood 3 2
Sokal-9 2066/06/21 Flood 9 9
Lungra-4 2066/06/20 Flood 22
Muli 2066/06/20 Flood 5
2067 (2010/2011)
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
7
Sanphebagar,
diff. VDCs
2067/04/04 Flood 2 22 15 60 ropani 920,000
Kulka-8, Boba
VDCs 2
2067/05/09 Flood 2 1
2068 (2011/2012)
Malatikot-7 2011/07/02 Flood 3 1
Shidheshwor 2011/07/25 Flood 1
Kalagaon 2011/07/02 Landslide 3
Budarkot-2 2011/09/14 Landslide 1 2
2069 (2012/2013)
Raniban-2 2012/06/01 Storm 1 12
Budhakot-4 2012/09/06 Rainfall 2 1
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
8
ANNEX F: ASSET INVENTORY - ACHHAM
List of Strategic Roads
List of Bridges
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
9
ANNEX G: PHOTOGRAPHS ASSET 1
Closer view of the damaged section. The gabion protection wall has already collapsed.
Same as picture above
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
10
The river, at present, is shifting its course from right side to left side. As a consequence it is
depositing riverbed materials at left bank and is eroding the right bank (where the road is
located). This is also one of the main reasons for the damage.
i
TA – 7984 NEP
October, 2013
Mainstreaming Climate Change Risk Management in
Development
1 Main Consultancy Package (44768-012)
BANKE DISTRICT BASELINE: DEPARTMENT OF ROADS (DOR)
Prepared by ICEM – International Centre for Environmental Management
METCON Consultants
APTEC Consulting
Prepared for Ministry of Science, Technology and Environment, Government of Nepal
Environment Natural Resources and Agriculture Department, South Asia
Department, Asian Development Bank
Version B
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
ii
TABLE OF CONTENTS
1 BANKE DISTRICT .............................................................................................................. 1
1.1 District Sector Master Plan ............................................................................................. 1
1.2 Sector budgeting and staff .............................................................................................. 1
1.3 Sector trends and issues ................................................................................................. 1
1.3.1 Trends ....................................................................................................................................... 1 1.3.2 Issues ........................................................................................................................................ 2
1.4 Asset inventory ............................................................................................................... 2
1.5 Past extremes in the district ........................................................................................... 2
1.6 Linkages to other sectors ................................................................................................ 2
1.7 Priority infrastructure in Dolakha District ....................................................................... 2
1.7.1 Prioritisation process ................................................................................................................ 2
2 BANKE DISTRICT: ASSET BASELINE .................................................................................... 3
2.1 Asset1: MRM (Mahendra Raj Marg) Agaiya Bazar (km 39+800 – 40+300) ................... 3
2.1.1 Asset Description ...................................................................................................................... 3 2.1.2 Adaptation audit ...................................................................................................................... 4
2.2 Asset 2: Nepalgunj – Baghouda Road (Approach Road to Rapti Bridge) ........................ 5
2.2.1 Asset Description ...................................................................................................................... 6 2.2.1 Adaptation audit ...................................................................................................................... 7
2.3 Asset 3: Culvert on Nepalgunj – Guleria Road ................................................................ 8
2.3.1 Asset Description ...................................................................................................................... 8 2.3.2 Adaptation audit ...................................................................................................................... 9
2.4 Asset 4:Bridge across Aurahi River on Mahendra Raj Marg ......................................... 10
2.4.1 Asset Description .................................................................................................................... 10 2.4.2 Adaptation audit .................................................................................................................... 11
2.5 Asset 5:Bridge across the Rapti River on Nepalgunj – Baghouda Road at km 11+100 . 12
2.5.1 Asset Description .................................................................................................................... 12 2.5.2 Adaptation audit .................................................................................................................... 13
ANNEX A – MAP OF BANKE DISTRICT ............................................................................................ 1
ANNEX B: ANNUAL BUDGET ......................................................................................................... 2
ANNEX C: NAMES & POSITIONS OF DISTRICT OFFICERS ................................................................. 3
ANNEX D: PAST EXTREME EVENTS ................................................................................................ 4
ANNEX E: PHOTOGRAPHS ASSET 1 .............................................................................................. 10
ANNEX F: PHOTOGRAPHS ASSET 2 .............................................................................................. 12
ANNEX G: PHOTOGRAPHS ASSET 3 ............................................................................................. 14
ANNEX H: PHOTOGRAPHS ASSET 4 ............................................................................................. 16
ANNEX I: PHOTOGRAPHS ASSET 5............................................................................................... 17
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
1
1 BANKE DISTRICT
1.1 District Sector Master Plan
All the 25 division offices of the DoR are required to prepare Annual Road Maintenance Plan (ARMP).
The summary sheet of plan is presented in Annex B. The division has not prepared a long term plan.
1.2 Sector budgeting and staff
Budgeting
The Budget for the Financial Year 2011/2012 is given in Annex C
Staff
The names and positions of district officers is given in Annex D
1.3 Sector trends and issues
Nepalgunj Division is one of the 25 divisions of DoR and covers several districts including Banke.
Although the main task of the division is to maintain the roads (routine, periodic, emergency,
recurrent etc.) it also executes small to medium road and bridge projects.
1.3.1 Trends
The current trends of the division are as follows:
Planning
Planning of works is done by the respective divisions. The division is required to prepare annual road
maintenance plan (ARMP) for each year. After approval of the plan by Ministry/DoR, yearly budget is
provided to divisions. Without ARMP, the division will not be liable to receive the yearly budget.
Design
Design works of construction roads and bridges in general are carried out by local consultants. For
some big donor funded projects (WB, ADB etc.) foreign consultants are also hired.
Construction
All the construction and maintenance works of roads and bridges are done through local
contractors. The present trend in the construction has shifted from manual to machines and at
present construction equipment such as excavator, paver, dozer, roller are being used more
frequently.
Supervision of Works
1. For small works, division staffs carryout supervision works;
2. For medium scale works the division hires local consultants;
3. For large contracts, especially for donor funded contracts foreign consultants are also hired.
Monitoring
Monitoring is done on the following aspects:
1. Programme
2. Cost
3. Quality
4. Progress
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
2
1.3.2 Issues
Major issues/difficulties faced by the divisions are as follows:
1. Insufficient manpower, equipment and budget
2. Difficulty in extracting natural occurring construction materials such as gravels, sands, stones
etc. due to Banke and Bardiya National Parks;
3. Very low bid by the contractors
1.4 Asset inventory
Asset inventory of Banke District is presented in Annex E.
1.5 Past extremes in the district
The record of past extreme events in the district is presented in Annex G.
1.6 Linkages to other sectors
The division office cooperates with DoLIDAR, DoI, DWSS, DWIDP, NT, NEA, Department of Transport
(DoT) etc. in the district.
Major Organization working in the District:
ADB is funding for ongoing 3 bridge projects;
WB is providing 10% of total amount for resealing (periodic maintenance) works for 5 years
period.
1.7 Priority infrastructure in Dolakha District
1.7.1 Prioritisation process
The key criteria for prioritisation include:
Infrastructure of national strategic importance
Infrastructure of district strategic importance
Infrastructure that has been impacted by past extreme events
Infrastructure located in areas prone to past extreme events
At least one planned infrastructure
The consultant in consultation with the division chief prepared final lists of the priority structures of
the district. The list was prepared following the criteria provided in District Office Report. The
priority list is given below
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
3
2 BANKE DISTRICT: ASSET BASELINE
2.1 Asset1: MRM (Mahendra Raj Marg) Agaiya Bazar (km 39+800 – 40+300)
2.1.1 Asset Description
MRM is one of the most important National Highways of the country. Its total length is 1027.67 km
out of which 147 Km lies in Banke District. MRM crosses Rapti River at Bhalubng in Dang District and
runs parallel to Rapti River up to Samshergunj.
Agaiya is a small settlement developed at the road side after the construction of MRM. Rapti River is
very near to MRM at this location. DoI recently constructed an intake at Rapti River at Agaiya for
Sikta Irrigation Project. This is the largest irrigation project in the district. Due to intake, the flow of
ID Name Infrastructure
type
Reason/s for inclusion
1 Structures to protect MRM (NH
1)from river erosion
Dykes Dyke constructed for road protection
which is unique.
2 Ongoing rehabilitation works
along Nepalgunj-Baghouda Road
Miscellaneous Severely damaged road due to Rapti River
3 Crossing structure along
Nepalgunj-Guleria Road
Culvert Poor condition due to lack of maintenance
4 Crossing structure along MRM RCC Bridge Bridge was constructed as the existing
causeway was not sufficient to pass the
river discharge.
5 Crossing structure along
Nepalgunj-Dondra Road
Steel Bridge Damage to surrounding areas of the
bridge. To show example of conventional
protection works.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
4
the Rapti River is obstructed and the level of Rapti becomes higher. In order to protect the road from
Rapti River GoN Constructed long dykes along the road about 5 years ago. This asset is shortlisted as
this is a very a very unique structure in the Nepali context.
Watershed context
The asset is located at the mid eastern part of the district. It lies in the watershed of the Rapti River,
which is the This river originates in the hilly part of the Mid Western Development Region crosses
MRM at Bhalubang (Dang District) and runs parallel to MRM upto the project site. The main problem
in the watershed area is the flooding of the Rapti River damaging several structures along it.
Asset location
. MRM is located very near to the Rapti River (about 30m from the bank) at the study area. The asset
was safe from the River before the construction of intake structure of Sikta Irrigation Project. After
the construction of the intake, the asset was found vulnerable to flooding due to obstruction of flow
by the intake. Hence, DoR constructed a dyke to protect the asset from flooding.
Asset condition
The condition of the asset (road) as well as the dyke is good (see photo). The field visit showed that
there is not imminent danger to the structures at present.
Asset design
In this case, the asset is considered both the road and the protection works.
MRM is a double lane road with 7m wide pavement. It is surfaced with asphalt concrete and its
condition near the site is good.
The dyke (protection works) is an earthen one with protection works and launching apron of
gabions. The top width of the dyke is 4m.
Past extreme events and impacts
As mentioned above, Rapti is the largest River in the district. About 10 years ago, the river washed
away the left abutment of the bridge near Lamahi. Similarly, there are several instances of damage
to the properties and loss of lives in the past due to flooding of the river.
Past adaptation responses
The adaptation measure to protect the road is appropriate and it is functioning very good.
Design appropriateness
The adaptation measure seems quite appropriate and the adopted measure is serving its purpose
quite satisfactorily.
2.1.2 Adaptation audit
Adaptation location
The adaptation, consisting of a dyke and slope protection works, is situated upstream of the intake
works for the Sikta Irrigation Schme which caused river levels to rise and thus threaten the MRM.
Adaptation condition
The adaptation is is good condition
Threat description
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
5
The threat to the asset is from increased river levels due to greater flows caused by
increased rainfall.
Past extreme events and impacts
There is no record of past extreme events at this location in the recent past.
Adaptation design
The design of the adaptation is appropriate to present day conditions
Adaptation success
The adaptation has been successful in protecting the MRM and surrounding areas from flooding.
2.2 Asset 2: Nepalgunj – Baghouda Road (Approach Road to Rapti Bridge)
Rapti River has washed away a road section of left approach road. The washed away section is
about 200m from the bridge towards Baghouda side. DoR has planned to construct a 20 m long
Bailey Bridge at this location. The steel truss bridge across Rapti River can also be seen on photo.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
6
2.2.1 Asset Description
After crossing the Rapti River at Bhalubang, MRM runs parallel to the the river along right bank. Up
to Samsherganj, the direction of road and river is towards the west. From Samshergunj, the river
changes its direction and proceeds towards south. Because of this phenomenon, several VDCs at the
south of the Rapti River from Bhalubang to Samshegunj were deprived of vehicular access as there
was no bridge and the people of that area used to travel through India to visit Nepalgunj and other
parts of the country. In order to connect these southern villages, DoR constructed Nepalgunj-
Bagaudha Road and a bridge across the Rapti River at 11 km east of Nepalgunj. In 2012, there was a
big flood near the bridge site area. The flood washed away a long section of left approach road. The
flood also damaged cultivated land, houses and other properties.
Watershed context
The asset lies in the watershed of the Rapti River. The river originates in the hilly part of the Mid
Western Development Region crosses MRM at Bhalubang (Dang District) and runs parallel to MRM
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
7
upto the project site. The main problem in the watershed area is the flooding of the Rapti River
damaging several structures along it.
Asset location
The Nepalgunj-Baghouda is still in the process of construction/upgradation. Initial sections of this
road is blacktopped and graveled wheras the majority of the road is still eartnen. DoR has
constructed a steel truss bridge at km 11+100. The location of the study area is beyond km11+100.
Asset condition
The condition of road at the study area is very poor. About 20m of this road is washed away and DoR
intends to construct a 15m long Bailey Bridge. After the 2012 flood, DoR is constructing concrete
causeway and other crossing drainage structures to protect the road from flooding. It is still
uncertain whether these structures will be able to protect the road from damage during another big
flood
Asset design
DoR is constructing different type of cross drainage structures such as Bailey Bridge, causeway, PCs
etc. Their drawings were not available.
Past extreme events and impacts
In 2012, several portion of the road onwards from the bridge was damaged due to flood. The flood
also destroyed houses and lands. However, there was no human casualty.
Past adaptation responses
Two pipe culverts (one with 3Nos 900mm dia pipes & one with 2Nos pipes) were constructed to act
as cross drainage for flood water from the Rapti River.
Design appropriateness
The cross drainage installed was inadequate and as a result there were several locations where the
road embankment was breached during a flood 2012.
2.2.1 Adaptation audit
Adaptation location
A 20 metre span Bailey Bridge is planned at one washed out section about 200m. from the Rapti
Bridge.
A 50m. concrete causeway is planned at another washed out section 250m. from Rapti Bridge
A 900mm diameter pipe culverty is planned 270m from Rapti Bridge.
Adaptation condition
None of the proposed adaptations are yet completed.
Threat description
The main threat to the asset the probability of severe damage due to flood. It is to be noted that the
existing problem will not be solved completely until the siltation problem in the Rapti River is
properly addressed..
Past Extreme Events and impacts
In 2012, several portion of the road onwards from the bridge was damaged due to flood. The flood
also destroyed houses and lands. However, there was no human casualty.
Adaptation Design
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
8
It is not possible to determine if the proposed adaptations design is adequate
Adaptation Success
The original adaptation of two pipe culverts was unsuccessful. It is not possible to determine if the
proposed adaptations will be successful.
2.3 Asset 3: Culvert on Nepalgunj – Guleria Road
Photo of culvert from downstream. There is no water at the stream at present. Boulders are laid at
the river bed near the culvert to protect the structure from bed scouring
2.3.1 Asset Description
The structure is double cell slab culvert across Kedari Khola with a total length of 13.30m. It is
located at km 8+050 along Nepalgunj Guleria Road. The structure was built about 20 years ago. The
deck slab of the culvert is RCC and the abutments and pier is constructed of brick masonry. The
culvert is structurally sound as it has lasted for about 20 years without any major structural defects
although several heavily loaded vehicles pass through it every day. However, there are sign of
distress due to aging and lack of maintenance.
The length of the culvert seems adequate and there is no substantial damage to the structure due to
flood except some bed scouring.
Watershed context
Kedari Khola (where the culvert is constructed) lies in the watershed of Man River . The khola was
found dry during the field survey.
There was not any major event at the study area in the past
Asset location
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
9
The culvert is located at km 8+050 along Nepalgunj Guleria Road. The area near/around the bridge is
flat and most of the land is cultivated. As the structure is located on flat area, there is no problem of
ground instability
Asset condition
The condition of the asset is satisfactory although it was constructed about 20 years ago. The major
problems of the structure are:
o Bulging and deterioration of brick masonry sub-structures (abutments and pier) due to aging
as well as poor maintenance.
o Scouring of river bed near the culvert due to high gradient.
Asset design
The culvert is designed with two equal spans and its total length is 13.3m. It has RCC deck slab and
abutments and pier of brick masonry. The design of asset matches to the size of the river and the
existing site condition
Past extreme events and impacts
There was no extreme events in the past which endangering the stability of the structure.
Past adaptation responses
DoR has placed dry stone soling at the bed to protect the bridge from scouring. It is functioning
satisfactorily.
Design appropriateness
The structure is sufficient to accommodate the discharge during high flood also. It is also structurally
sound as it has withstood heavy loads for the several year years in the past. The abutments and pier
of the culvert is constructed of brick masonry which is available locally. In short it can be concluded
that the design of the culvert is appropriate.
2.3.2 Adaptation audit
Adaptation location
There have been no adaptations carried out to date
Adaptation condition
NA
Threat description
The threat to the culvert is from increased future flows caused by higher rainfall or flash floods
brought about through climate change
Past Extreme Events and impacts
There are no records of past extreme events at this location
Adaptation Design
NA
Adaptation Success
NA
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
10
2.4 Asset 4:Bridge across Aurahi River on Mahendra Raj Marg
View of the bridge from upstream. It is a three span bridge and the length of the bridge is
adequate for this site.
2.4.1 Asset Description
This asset is a RCC bridge of 77 m length with three equal spans of 25.5m each. Design of this
structure was carried out by a local consulting firm. The construction was done by Tundi/Kumar
Shrestha JV and this structure was completed one year ago.
A RCC causeway was constructed across this river before the construction of this bridge. As the
movement of vehicles were frequently obstructed during high discharge, GoN decided to replace the
causeway with the existing bridge.
Watershed context
The Auri Khola where the bridge is constructed lies in the watershed of Babai River. There was very
little water during the field survey.
The road was frequently obstructed by flood before the construction of the bridge.
Asset location
The bridge is located at a distance of 20 km west of Man River along MRM. The bridge site area is
covered by bushes and cultivated land and lies in the rolling terrain. The river bed materials at the
bridge site consist of sand, gravels and boulders. There is not any ground instability near the asset.
Asset condition
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
11
The asset was constructed one year ago and its construction quality is good. There was not any sign
of damage/problems at the bridge and other ancillary works..
Asset design
This is a double lane RCC bridge with three equal spans of 25.5m each. Both abutments and piers of
the bridge are constructed of RCC.
Past extreme events and impacts
There was no extreme events in the past which endangering the stability of the structure.
Past adaptation responses
Before the construction of the bridge, there existed a RCC causeway. During high flood, there was
frequent obstruction to traffic during high flood. Hence DoR decided to replace the culvert with the
bridge. This response seems appropriate as the traffic along the MRM has increased significantly.
Design appropriateness
The design of the asset is appropriate for the given site condition. There is no probability of
obstruction to river as the bridge length is not less than the river width. The quality of construction
is also good.
2.4.2 Adaptation audit
Adaptation location
The bridge is located at a distance of 20 km west of Man River along MRM. The bridge site area is
covered by bushes and cultivated land and lies in the rolling terrain. The river bed materials at the
bridge site consist of sand, gravels and boulders.
Adaptation condition
The condition of the bridge is good.
Threat description
The threat to the bridge is the increase in river flow caused by increased rainfall associated with
climate change. The recently designed and constructed bridge will not have been designed using the
latest predictions for future flood levels.
Past Extreme Events and impacts
There are no reported past extreme events
Adaptation Design
The design is appropriate for present conditions
Adaptation Success
The provision of a new bridge as an adaptation to the old concrete causeway is a success
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
12
2.5 Asset 5:Bridge across the Rapti River on Nepalgunj – Baghouda Road at km
11+100
View of the bridge from upstream.
2.5.1 Asset Description
This is a steel truss bridge located at km 11+100 of Nepalgunj-Baghouda Road. The bridge has seven
spans and its total length is 342 meter. It has RCC deck and the abutments and piers are constructed
of RCC.
This bridge was constructed more than 5 years ago to provide vehicular link to several VDCs lying
south of the Rapti River. Until now, there is no problem associated with the stability of the structure.
However, there is a serious problem of changing of course by Rapti River due to heavy saltation (see
Asset 2). If DoR does not take measures to regulate the course, the river may flow through left
approach road. Washing away of left approach road by 2012 flood is the indication of the problem.
Watershed context
Rapti is one of the big rivers of the country. The catchment area of the river is more than two
thousand square kilometers. The initial section of the river passes through hill areas covered with
forests. The river gradient at such area is higher. After crossing the MRM at Bhalubang, the river
flows through flat area up to the study area. The catchment area of the river at the flat area (after
Bhalubang) is covered with flat land and forest.
Asset location
The bridge is located at km 11+100 of Nepalgunj Dondra Road. The area near/around the bridge is
flat and most of the land is cultivated. The land near the culvert is flat and there is no problem of
ground instabilities. The asset is located at the southern part of the district near the border with
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
13
India. The area near/around the bridge is flat and cultivated. There is no problem of ground
instability.
Asset condition
The asset was constructed five years ago and its construction quality is good. However, the river is
eroding the left bank. Several structures (PC, SC, bank protection works) are constructed/ under
construction to protect the bank. Although, the bridge itself seems structurally sound, there is a big
question mark on its function in the long term due to hydrological problems.
Asset design
The bridge has seven spans and its total length is 342 meter. It has RCC deck and the abutments and
piers are constructed of RCC.
Past extreme events and impacts
Rapti is the largest river in Banke district. Several people of the Banke District have died in past due
to Rapti floods. Similarly the river also damaged land, properties, houses and structures along it. In
2012, the river washed away the left approach road and caused damage to the land and properties
of the people living in that area. Due to lack of systematic record keeping practice of the district, DoR
and other agencies, it is very difficult to describe about all the past events.
Past adaptation responses
As stated earlier, flooding at the Rapti River is common. It has caused loss to human lives and
properties at several locations in the past at frequent interval. To minimize the damage by the flood,
GoN as well as local people have constructed bank protection works at several locations. These
protection works are functioning satisfactorily although some of them are already damaged.
Design appropriateness
The type of structure seems appropriate. The length of the bridge is almost equal to the existing
waterway. But there is a serious problem due to heavy silting at upstream. Due to siltation, the
difference between the river level and the top level of the bank was found very low even during dry
period. As a consequence the river overtops the bank and damages the surrounding areas during
high flood. GoN should seriously think to minimize the siltation process. Similarly, it is also
recommended to construct bank protection works at left side up to a considerable distance at
upstream from the bridge.
2.5.2 Adaptation audit
Adaptation location
Some adaptation in the form of different types of slope and embankment protection have been
carried out on the upstream banks of the river
Adaptation condition
The condition of these adaptations is not good
Threat description
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
14
The threat is to the areas of land either side of the river and to the bridge approach roads due to
over topping of the banks during high floods. This threat will grow as the increase in rainfall and
flood levels due to climate change becomes more severe with the added threat of sedimentation in
the river bed raising the flood levels even higher.
Past Extreme Events and impacts
In 2012 a high flood overtopped the river banks and caused considerable damage to life and
property including the bridge approach roads.
Adaptation Design
The design of the river bank protection is unlikely to be appropriate in the event of a future high
flood
Adaptation Success
The adaptations are unlikely to be successful In protecting the property and infrastructure on the
Rapti flood plain.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
1
ANNEX A – MAP OF BANKE DISTRICT
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
2
ANNEX B: ANNUAL BUDGET
Budget for the FY 2011/12
Budget
Head Maintenance Type Budget for FY 2011/2012
Proposed
Budget for
fiscal year
2012/2013
337014-3 Administration 8,800
10,000
337165-4 Routine Maintenance 13,500
17,767
337165-4 Recurrent Maintenance 16,100
19,681.00
337165-4 Specific Maintenance 17,500
55,600.00
337165-4 Periodic Maintenance 80,000
51,750.00
337165-4 Traffic Engineering 3,000
520.00
337165-4 Bio Engineering 200
400.00
337165-4 Emergency Maintenance 100
700.00
337165-4 Rehabilitation
56,000.00
337165-4 Karnali Bridge Security 2,200
2,200.00
337158-4 Bridge Maintenance 15,000
20,900.00
Grand Total 156,400.00
235,518.00
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
3
ANNEX C: NAMES & POSITIONS OF DISTRICT
OFFICERS
Names and positions of district officers
SN Name Position
General
1 Manoj Shrestha
Technical
2 Wakil Jha Engineer
3 Nabaraj K.C. Engineer
4 Anand Karna Engineer
5 Khagendra Shahi Engineer
6 Turunt Mandal Engineer
7 Prem Prasad Chuwai Engineer
8 Chetan Kumar Mandal Sub- Engineer
9 Karma Tamang Sub- Engineer
10 Govind Gaire Sub- Engineer
11 Santosh Bhandari Sub- Engineer
12 Padam Bahadur Madai Sub- Engineer
13 Pramod Chaudhary Sub- Engineer
14 Pramod Chaudhary Sub- Engineer
15 Mahavir Chaudhari Lab. Boy
16 Mahendra Kumar Gautam Lab. Boy
17 Saraswati Sharma Gautam Wireless Operator
18 Saroj Bohara Giri Wireless Operator
Account
19 Badri raj arya Under Secretary (Account )
20 Harisharan Bad Accountant
Administration
21 Dil Bahadur Karki Section Officer
22 Bas Bahadur Rana Typist Na. Su.
23 Kul Raj Upadhyaya Na. Su.
24 Dharma Raj Acharya Typist, Na.Su.
25 Chandra Bahadur Malla Adm. Non-Gazetted II
26 Other support staffs 16 nos.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
4
ANNEX D: PAST EXTREME EVENTS
S.
No.
VDC/Municipality
& ward No.
Date Type of
Disaster
People Affected
Family
Animal
loss
House destroyed Shed
Destroyed
Land loss Public
Property
Estimated
Loss (Rs.)
Death Missing Injured Completely Partly No. Unit
2065 (2008/2009)
1. Titihariya 2065/2/31 Fire 1 1 200000
2066 (2009/2010)
1. Different VDCs 2066/04/13 Flood
2. Rapti Nadi 2066/04/23 Flood
2067 (2010/2011)
1. Nepalgunj 2011/01/09 Fire 2 4 300000
2. Puraina-1 2011/01/21 Fire 200000
3. Nauwasta-7 2011/02/27 Fire 2 3 160000
4. Katakuiyaea-8 2011/02/28 Fire 1 25000
5. Gangapur-6 2011/02/28 Fire 25
6. Bilauna-4 2011/03/01 Fire 2
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
5
7. Raniyapur-8 2011/03 Fire 1 2 8
8. Khaskusma-7 2011/03/05 Fire 700000
9. Puraina-2 2011/03/14 Fire
10. Nepalgunj-2 2011/03/15 Fire 200000
11. Nepalgunj-16 2011/03/16 Fire 100000
12. Nepalgunj-8 2011/03/22 Fire 180000
13. Nepalgunj 2011/04/07 Fire 1 1 230000
14. Kohalpur-3 2011/04/08 Fire 3 3 535000
15. Rajhena-3 2011/04/08 Fire 3 3 500000
16. Bankatuwa-9 2011/04/11 Fire 1 4 1
17. Kohalpur-4 2011/04/11 Fire 1 50000
18. Nepalgunj 2067/04/13 Epidemic 6 105
19. Rapti Basin
different VDCs
2067/04/03 Epidemic
20. Different VDCs,
Holiya VDC
2067/04/09 Epidemic 300 Irrigation
canal
75000000
21. Nepalgunj 2011/01/04 Cold
wave
1
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
6
S. No.
VDC/Municipality & ward No.
Date Type of Disaster
People Affected Family
Animal loss
House destroyed Shed Destroyed
Land loss Public Propert
y
Estimated Loss (Rs.)
Death Missing Injured Completely
Partly No. Unit
2068 (2011/2012)
1. Hirmuniya-7 2011/04/07 Fire 2 300000
2. Hirmuniya-7 2011/04/08 Fire 300000
3. Mahadevpuri-8 2011/04/22 Fire 2 1 195000
4. Mahadevpuri-8 2011/04/22 Fire 1 80000
5. Udharpur-5 2011/04/23 Fire 250000
6. Butharapur-2 2011/04/23 Fire 60000
7. Udharpur-6 2011/04/23 Fire 170000
8. Manikapur-3 2011/04/24 Fire 1 30000
9. Pipraha-9 2011/05/03 Fire 130000
10. Paraspur-2 2011/05/14 Fire 1 750000
11. Pipraha-4 2011/05/24 Fire 1 15000
12. Jayasapur 2011/06/06 Fire 150000
13. Khaskushma 2011/07/18 Fire 250000
14. Kohalpur-d3 2011/11/11 Fire 1 250000
15. Piparahawa-6 2011/11/26 Fire 7 60000
16. Manapur-2 2011/12/31 Fire 1500000
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
7
17. Mataiya-2 2012/01/10 Fire 1 25000
18. Sitapur-5 2012/01/17 Fire 40000
19. Kanchanpur-7 2012/01/19 Fire 327000
20. Nepalgunj-5 2012/02/03 Fire 1 150000
21. Sitapur-4 2012/02/06 Fire 1 260000
22. Nepalgunj-1 2012/02/15 Fire 1 100000
23. Fattehpur-8 2012/02/24 Fire 3 3
24. Chisapane-5 2012/02/26 Fire 3 1
25. Huliya-2 2012/03/01 Fire 1 9 400000
26. Kamadi-4 2012/03/09 Fire 26 1.2E+07
27. Patanapur-7 2012/03/17 Fire 1
28. Gaganpur-9 2012/03/31 Fire 2
29. Titahariya-5 2011/07/11 Flood 1
30. Bankatuwa-9 2011/07/23 Flood 1 6
31. Nepalgunj-8 2011/08/16 Flood
32. Nepalgunj-5 2011/09/10 Flood 1
33. Kanchanpur-6 2011/09/13 Flood 1
34. Bageshwori 2011/04/25 Storm 1
35. Kohalpur-3 2012/05/17 Storm 3
36. Baibaijapur-6 2012/07/13 Thunderbolt
1
37. Ganapur-2 2011/07/21 Thunderbolt
1 3
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
8
S.
No.
VDC/Municipality
& ward No.
Date Type of
Disaster
People Affected
Family
Animal
loss
House destroyed Shed
Destroyed
Land loss Public
Property
Estimated
Loss (Rs.)
Death Missing Injured Completely Partly No. Unit
2069 (2012/2013)
1. Kalaefante-5 2012/04/16 Fire 1 100 100 50000000
2. Manikapur-8 2012/04/28 Fire 2 2 450000
3. Fattepur-3 2012/04/28 Fire 400000
4. Kanchanpur-7 2012/05/03 Fire 7 7 1200000
5. Nepalgunj-1 2012/05/08 Fire 800000
6. Narainpur-5 2012/05/13 Fire 1 1 100000
7. Indrapur-7 2012/05/15 Fire 7 7 1900000
8. Nepalgunj-2 2012/05/17 Fire
9. Ganapur-8 2012/05/18 Fire 3 3 500000
10. Kohalpur-9 2012/05/22 Fire
11. Holiya-9 2012/05/23 Fire 1 45 45
12. Narainapur-3 2012/05/23 Fire 1 11 11 2500000
13. Nepalgunj-7 2012/06/01 Fire 1 1 200000
14. Titihiriya-5 2012/06/10 Fire 1 150000
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
9
15. Manikapur-6 2012/06/10 Fire 1 300000
16. Mataehiya-8 2012/06/11 Fire 142
17. Nepalgunj-1 2012/06/12 Fire 45000
18. Indrapur-8 2012/06/15 Fire 1 2 42 7 10000000
19. Mataiya-8 2012/06/15 Fire 57 6000000
20. Pandepurwa 2012/06/15 Fire 42
21. Ganapur 2012/06/25 Fire 300000
22. Dhamboji 2012/07/05 Fire 350000
23. Bageshwori-7 2012/07/31 Fire 1 1 27000
24. Betahani-4,6 2012/08/02 Flood
25. Phattepur-8 2012/08/04 Flood 58
26. Betahani-9 2012/08/04 Flood 1
27. Karkando-5 2012/08/21 Fire 1
28. Narainapur-8 2012/09/03 Epidemic 1
29. Nepalgunj-1 2012/10/01 Fire 1 1600000
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
10
ANNEX E: PHOTOGRAPHS ASSET 1
Photo of dyke. It is an earthen dyke of about 4-5 m height. The top width of the dyke is 3 m wide.
At the river side (left side) the slope is protected by gabion mattress at the lower portion and by
stone rip rap at the top. Gabion mattress is provided at the bed for protection against scouring.
MRM lies at about 25m right from the dyke.
View of MRM from the top of the dyke. The road is about 25 m from the dyke at this location. It
seems that the dyke is functioning properly as there is no damage to the road.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
11
View of intake from dyke. The intake is constructed throughout the river width.
View of the dyke from intake. The road lies behind the dyke.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
12
ANNEX F : PHOTOGRAPHS ASSET 2
Photo of washed away road section from upstream side. The washed away section is very
near to triple cell pipe culvert.
This is another washed away road section. It is located at about 250m from the bridge or 50 m
proposed location of the Bailey Bridge towards Baghouda side. DoR has started constructing 50m
concrete causeway at this location.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
13
Triple cell and double cell PC were constructed to discharge the overflow from Rapti River. As seen
above, these structures are not sufficient to drain the water during high flood.
Single cell PC of dia 90 cm is laid but the headwalls are still not constructed. The location of the PC
is about 270 m from the bridge.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
14
ANNEX G: PHOTOGRAPHS ASSET 3
Closer view of the scouring of the pier. To protect the pier from further scouring, bolders are laid
at the bed.
Bulging of wing wall and widening of gaps at the joint due to earth pressure. The existing
condition shows that the wing wall should be reconstructed.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
15
Cracks at wing wall which occurred due to lack of maintenance (weep holes are blocked, no
attention during small cracks etc.). If the structure is not repaired timely, it will collapse within few
years.
Upstream view of khola. In general the width of the stream is about 8m. Due to adequate length
of the culvert, there is no major damage due to flooding except minor scouring of the pier.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
16
ANNEX H: PHOTOGRAPHS ASSET 4
Remains of the previously constructed concrete causeway. As seen on the photo, the length of the
causeway was much less than the river width causing problems to the vehicles during high flood.
Carriageway of the bridge. As seen on photo the finishing works of the bridge is good.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
17
ANNEX I : PHOTOGRAPHS ASSET 5
Carriageway of the bridge. As seen on photo, the finishing of the works is good.
The local community is constructing gabion launching apron at the left bank, upstream. It is to be
noted that this structure will not very useful as the main problem is not the bank erosion but the
flooding which is caused mainly due to silting of bed at upstream.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
18
Protection works made of bamboos at the left bank. This is a local technology and is working well
for the given site condition. This technology can be replicated for protection works at other
locations also.
Upstream view of Rapti River from the bridge. As observed in the field the height of left bank is
not more than 2-3m which is very little for the large river like Rapti. The bank height has
decreased in the past due to siltation. As a result the river overtops the bank and flows through
the field during high flood
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
1
TA – 7984 NEP
October, 2013
Mainstreaming Climate Change Risk Management in
Development
1 Main Consultancy Package (44768-012)
CHITWAN DISTRICT BASELINES: DEPARTMENT OF ROADS
(DOR)
Prepared by ICEM – International Centre for Environmental Management
METCON Consultants
APTEC Consulting
Prepared for Ministry of Science, Technology and Environment, Government of Nepal
Environment Natural Resources and Agriculture Department, South Asia
Department, Asian Development Bank
Version B
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
ii
TABLE OF CONTENTS
1 CHITWAN DISTRICT .......................................................................................................... 1
1.1 District Sector Master Plan ............................................................................................. 1
1.2 Sector budgeting and staff .............................................................................................. 1
1.3 Sector trends and issues ................................................................................................. 1
1.3.1 Trends ....................................................................................................................................... 1 1.3.2 Issues ........................................................................................................................................ 2
1.4 Asset inventory ............................................................................................................... 2
1.5 Past extremes in the district ........................................................................................... 2
1.6 Linkages to other sectors ................................................................................................ 2
1.7 Priority infrastructure in Dolakha District ....................................................................... 3
1.7.1 Prioritisation process ................................................................................................................ 3
2 CHITWAN DISTRICT: ASSET BASELINE ............................................................................... 4
2.1 Asset1: Lothar Bridge on MRM ....................................................................................... 4
2.1.1 Asset Description ...................................................................................................................... 5 2.1.2 Adaptation audit ...................................................................................................................... 6
ANNEX A – MAP OF CHITWAN DISTRICT ....................................................................................... 1
ANNEX B: NAMES & POSITIONS OF DISTRICT OFFICERS ................................................................. 2
ANNEX C: PAST EXTREME EVENTS ................................................................................................ 3
ANNEX D: ASSET INVENTORY – CHITWAN ..................................................................................... 4
ANNEX E: PHOTOGRAPHS ASSET 1 ................................................................................................ 8
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
1
1 CHITWAN DISTRICT
1.1 District Sector Master Plan
The Annual Road Management Plan for 2070/71 has been published but is too large to be included
in this report
1.2 Sector budgeting and staff
Budgeting
Budget Head FY 2011/12 FY 2012/13 Remarks
General Administration 8818900 -
106-Road Board 26,125,000 27,500,000
107-City Road 101,745,000 107,100,000
148- District Road 34,532,500 36,350,000
123-Regional Road 23,465,00 24,700,000
302-Tourism 10,830,000 11,400,000
199-Chepang Marga 55,404,000 58,320,000
157-Bridge Construction 66,785,000 70,300,000
158-Bridge Maintenance 6,650,000 7,000,000
Total 334,355,400 342,670,000
Staff
The names and positions of district officer is given in Annex B
1.3 Sector trends and issues
Bharatpur Division is one of the 25 divisions of DoR and covers several districts including Chitwan
District. Although the main task of the division is to maintain the roads (routine, periodic,
emergency, recurrent etc.) it also executes small to medium road and bridge projects
1.3.1 Trends
The current trend of the divisions are as follows:
Planning
Planning of works is done by the respective divisions. The division is required to prepare annual road
maintenance plan (ARMP) for each year. After approval of the plan by Ministry/DoR, yearly budget is
provided to divisions. Without ARMP, the division will not be liable to receive the yearly budget.
Design
Design works of construction roads and bridges in general are carried out by local consultants. For
big projects, especially for donor (WB, ADB etc.) funded ones DoR hires foreign consultants.
Construction
All the construction and maintenance works of roads and bridges are done by using local
contractors. The present trend in the construction has shifted from manual to machines. For
example at present construction equipment such as excavator, paver, dozer, roller are being used
more frequently.
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
2
Although Chitwan Division is meant for maintenance of roads, it is carrying out construction works of
roads and bridges also. For example it is involved in construction of 180 m long motorable bridge
and Chepang Marga.
Supervision of Works
1. For small and medium works, division staffs carryout supervision works;
2. For large contracts, especially for donor funded contracts foreign consultants are also hired.
Monitoring
Monitoring is done on the following aspects:
1. Programme
2. Cost
3. Quality
4. Progress
1.3.2 Issues
Planning for the asset management in the road sector has improved the quality of maintenance in
DoR. However, following initiative will help to overcome the shortfall in the maintenance
activities of division.
a. Timely release of the maintenance budget.
b. Close monitoring of the activities both at division and central levels.
Training, working environment and motivation to the division staffs.
The number of length workers deputed in hilly reason during rainy season is not sufficient
due to high importance of the highways.
Old and worn out bridges in PRM needs timely attention.
Criticality of Krishna Bheer should not be overlooked.
Rutting problem of ascending loaded lane in TRP and PRM should be addressed with
reference to new technology.
ROW encroachment, sand quarrying in the road corridor, and access road from highway by
local bodies are other threats to SRN
1.4 Asset inventory
The list of rural roads and bridges in the district is presented in Annex C
1.5 Past extremes in the district
Past extreme events in the district are given in Annex D
1.6 Linkages to other sectors
The DoR at present is cooperating with the following agencies for implementation of RIWs:
DoLIDAR, DoI, DWSS, DWIDP, NT, NEA, Department of Transport (DoT)
Major Organization working in the District:
1. WB is providing 10% of the maintenance to the divisions.
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
3
2. SDC is providing support for construction of dyke
1.7 Priority infrastructure in Dolakha District
1.7.1 Prioritisation process
. The key criteria for prioritisation include:
Infrastructure of national strategic importance
Infrastructure of district strategic importance
Infrastructure that has been impacted by past extreme events
Infrastructure located in areas prone to past extreme events
At least one planned infrastructure
The consultant in consultation with the division chief prepared final lists of the priority structures of
the district. The list was prepared following the criteria provided in District Office Report. The
priority list is given in the following table.
ID Name Infrastructure
type
Reason/s for inclusion
1 Lothar Bridge
Bridge To show an example of exceptionally
heavy siltation at/around the bridge. At
present the vertical clearance is 2.5m
which was 8m in 1977 (during
construction).
2 Riu Khola Bridges
Bridge The river is damaging surrounding areas
even after the construction of two bridges.
3 Approach Road of Sauraha
Bridge
Road Flood washed away approach road and
houses at left bank in 2003.
4 Landslide Protection works
along Narayanghat-Mugling
Road
Road Several check dams are constructed at
upstream to protect road and bridges
from debris, which is unique and
successful.
5 Slab bridge across
Badarmudhe Khola in Madi
(damaged bridge)
Slab Bridge To show the example of change of
hydrological regime within short period
and an example of poor design and
construction.
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
4
2 CHITWAN DISTRICT: ASSET BASELINE
2.1 Asset1: Lothar Bridge on MRM
Extensive siltation near/at the bridge site. Difference between bed level and bridge has been
reduced to 2.5 m which was 8m in 1977. This shows bed level has risen by 5.5 m within the span of
35 years. If the situation is not controlled the bridge will be washed away in future
Sketch Plan of Site
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
5
2.1.1 Asset Description
The bridge is located along MRM at the border of Chitwan and Makwanpur Districts. The bridge was
designed by ND Lea and Associates and was completed in 1977. It has five spans and its total length
is 150m.
The abutments and piers of the bridge are RCC whereas the superstructure is prestressed concrete.
Although the bridge was constructed more than 35 years ago, the structural components of the
bridge are still in very good condition and any major maintenance works are still not required.
While the bridge was completed the clear vertical clearance was about 8m. However, due to
substantial debris deposition in the last several years, the vertical clearance has reduced to 2.5m.
Due to heavy siltation, the bed level of the river is higher than the ground level of the village located
at downstream right bank. To protect the village, about 2 km long earthen dyke is constructed.
As per local people the river overtopped the bridge in 1993 and 2003. It did not damage the bridge
structure but it eroded both banks and damaged to land and properties of the village lying at the
right bank. But there is a high risk of washing away of the bridge during heavy flood in the future.
Watershed context
The bridge lies inside the watershed of Lothar River. This river joins Rapti River at a distance of 5
kilometer downstream from the bridge site. Almost all the watershed of this river lies in Chure
range which is highly susceptible to landslides.
According to the local people, there were big floods in 1993 and 2002 and these floods transported
large amount of debris and deposited at/near the bridge site.
There is a high vulnerability of washing away of bridges during high flood.
Asset location
The bridge lies along MRM of Narayanghat-Hetuada Section. Lothar Khola is the border of
Makwanpur and Chitwan Districts. Geographically the bridge lies at the foothill of Chure Hills. The
watershed of the river is mainly covered by forests and some land areas are cultivated. There was
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
6
rapid deforestation at the watershed in 1990-2000. This was the main cause of landslides at upper
area and heavy siltation at downstream.
The bridge is located at the foot hill. Due to very steep slope, the river transport debris from the hills
and deposits near the bridge site.
The area near the bridge site consists of cultivated land and shrubs and bushes.
The soils of the Chure are composed of sands, gravels and boulders and lacks sufficient clayey
materials. As a consequence they are easily eroded during monsoon rains. As mentioned earlier
there is heavy siltation at the bridge site area and if this continues further, the bridge may collapse in
future.
There are no water bodies near the bridge site.
The bridge lies at the flat area and there are no ground instabilities at its proximity.
Asset condition
The structural components of the bridge such as abutments, piers and superstructures are in good
condition.
The condition of gabion bank protection works and dyke at downstream right bank is good.
There is heavy siltation near the bridge site and is endangering the structure.
Asset design
It is a double lane bridge with 5 spans and its total length is 150 meter. The bridge was designed by
ND Lea and Associates (Canada). The substructures of the bridge are RCC and its superstructure is
constructed with prestressed concrete girder. The horizontal alignment of the main bridge lies in
curve. Design and construction of such curved bridge is rare in Nepal.
Past extreme events and impacts
According to the local people, there were big floods in 1993 and 2002 and these floods overtopped
the bridge and deposited large amount of debris at/near the bridge site.
Past adaptation responses
As previously mentioned there is a heavy siltation at the bridge site. In order to control the siltation,
DWIDP is constructing check dams at upstream and discouraging deforestation. Similarly, DDC has
contracted to extract river bed materials from the bridge site. However, these measures are not
sufficient to control the silting.
DoR/DDC/INGOs have constructed gabion walls and earthen dyke to protect the villages from the
flood. These structures are functioning properly.
Design appropriateness
The design of the bridge is appropriate for the given site condition. The length of the bridge is almost
equal to the river width and there is no obstruction to water way. Due to proper design the bridge
components are in good condition even after 35 years after its construction. At present the vertical
clearance of the bridge is 2.5m and is very less. However the bridge was designed with a provision of
8m vertical clearance and was adequate for that period (before heavy siltation).
2.1.2 Adaptation audit
Adaptation location
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
7
DWIDP is constructing gabion check dams upstream of the bridge and the DDC is extacting river bed
material from areas adjacent to the bridge
Adaptation condition
The check dams are in under construction
Threat description
Due to heavy siltation, the vertical clearance is about 2.5 only and the river overtopped the bridge in
1993 and 2003. The bridge is at high risk of its washing away during heavy flood in future. Hence, the
concerned authority (DoR), should take immediate steps to remove the debris as soon as possible
Past extreme events and impacts
High debris flows in the past have raised the bed level considerably and continued deposition under
higher flow conditions in the future will threaten the integrity of the bridge superstructure
Adaptation design
The design for the check dams is not known
Adaptation success
The success of the various interventions is not yet known.
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
1
ANNEX A – MAP OF CHITWAN DISTRICT
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
2
ANNEX B: NAMES & POSITIONS OF DISTRICT
OFFICERS
Names and positions of district officers
SN Name Position
1 Mr. Birendra Mahaseth Division Chief
2 Mr. Sourav Bajracharya Engineer
3 Mr. Ganga Bahadur Maharjan Engineer
4 Mr. Basant Yadav Engineer
5 Mr. Birendra Kumar Mandal Engineer
6 Mr. Nanda Kumar Gupta Engineer
7 Mr. Dal Bahadur Gurung Engineer
8 Mr. Yadav Prakash lamichhane Engineer
9 Mr. Himalaya Prasad Parajuli Account Officer
10 Mr. Roshan Dev Sub-Engineer
11 Mr. Sachendra Mishra Sub-Engineer
12 Mr. Raghunath Subedi Nayab Subba
13 Mr. Shiva Sharma Nayab Subba
14 Support Staffs (42 nos) Drivers, Supervisors, Peons etc.
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
3
ANNEX C: PAST EXTREME EVENTS
VDC/
Municipality &
Ward No.
Date
Type of
Disaster
People Affected
Family
Animal
Loss
House
Destroyed
Shed
Destroyed
Land Loss Public
Property
Estimated
Loss
(Rs.) Dead Missin
g
Injured Total Partly No. Unit
2065 (2008/2009)
Kawilas-6 2065/02/31
Flood
Landslide 7 7
815000
2066 (2009/2010)
Jagatpur Lothar 2066/04/23 Flood 5
2067 (2010/2011)
2068 (2011/2012)
Mangalpur-5 2012/07/01 Flood 70
Meghauli-1,2 2012/07/01 Flood 250
2069 (2012/2013)
Kabilas-9 2012/06/4 Storm 1 0
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
4
ANNEX D: ASSET INVENTORY – CHITWAN
List of Roads in Chitwan
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
5
List of Bridges
SN Name of
Roads
RIVER/
STREAM
Chainage
Km
Length
(m)
Width, m Span
No
Type Loading
Capacity
Remarks Maintenance
Division
Region
Road
way
Carriage
way
Sup. Str Foundation
1 PRM Mowa 66+610 22.00 8.00 6.00 1 Steel Plate
Girder
Spread CH-
15/CH-
80
Bharatpur Central
2 PRM Dahki 73+090 33.00 8.00 6.00 1 Steel Plate
Girder
Spread CH-
15/CH-
80
Bharatpur
3 PRM Barbang 74+050 26.40 6.90 6.00 3 RCC Slab Spread CH-
15/CH-
80
4 PRM Nagdi 81+040 37.15 6.94 6.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
5 PRM Trishuli 83+990 122.60 8.80 6.00 3 Suspension
(Steel Truss)
Open CH-
15/CH-
80
Damauli Western
6 MRM Mardar 444+670 45.00 10.50 7.70 2 RCC T-Beam 20-44 Bharatapur Central
7 MRM Pampha 449+570 45.00 10.50 7.70 2 RCC T-Beam - HS 20-
44
Bharatapur Central
8 MRM Budhi Rapti 455+760 62.00 10.50 7.70 3 RCC T-Beam - HS 20-
44
Bharatapur Central
9 MRM Budhi Khola 456+760 15.30 10.50 7.70 3 RCC Slab - HS 20-
44
Bharatapur Central
10 MRM Kair 458+410 61.60 10.50 7.70 3 RCC T-Beam - HS 20-
44
Bharatapur Central
11 MRM Khageri II 462+940 66.00 10.50 7.70 4 RCC T-Beam - HS 20-
44
Bharatapur Central
12 MRM Khageri I 463+060 39.00 10.50 7.70 2 RCC T-Beam Spread HS 20-
44
Bharatapur Central
13 MRM Narayani 473+610 420.00 11.00 7.70 14 PSC Pile HS 20-
44
At bordere
with
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
6
Nawalparasi
14 NMRM Kharre 11+300 36.50 7.00 6.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
15 NMRM Dash Dhunga 12+600 12.00 7.60 7.10 2 RCC Slab Spread CH-
15/CH-
80
Bharatpur Central
16 NMRM Phohor Khola 12+850 38.50 7.00 6.00 1 RCC Arch - CH-
15/CH-
80
Bharatpur Central
17 NMRM Lamobaluwa 16+380 28.40 7.00 6.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
18 NMRM Khani 16+850 28.00 7.00 6.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
19 NMRM Bhorle 19+500 56.80 7.00 6.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
20 NMRM Mauri 21+700 26.30 7.00 6.50 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
21 NMRM Dumre 22+030 32.40 8.00 7.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
22 NMRM Simaltal 24+250 37.20 7.00 6.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
23 NMRM Rigdi 25+570 50.25 7.00 6.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
24 NMRM Jalbire 29+210 25.66 10.00 9.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
7
25 NMRM Nyanse 32+670 31.00 7.00 6.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
26 NMRM Tope 32+860 23.00 8.50 7.50 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
27 NMRM Kali 33+350 60.00 7.00 6.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
28 NMRM Gairi 34+660 60.00 7.00 6.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
29 NMRM Chinsenji 35+120 41.15 7.00 6.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
30 NMRM Khahare 35+490 65.60 7.00 6.00 1 RCC Arch Spread CH-
15/CH-
80
Bharatpur Central
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
8
ANNEX E: PHOTOGRAPHS ASSET 1
View of the bridge from the dyke at downstream. The elevation of the adjoining village at the left
bank is less than that of river bed level (see the level of the temple). DoR has constructed a long
dyke to protect the village.
General view of the dyke. Its top width is about 4m and it protected by gabion mattress at river
side.
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
9
Left bank at upstream side of the river. DoR had planned construct dyke at this location also.
However, it could not be constructed because the local people objected this idea demanding a
complete package of protection works.
Photo showing excavaton of river bed materials at downstream. DDC contracted to a private
company to extract the river bed from the bridge site to lower the river bed level. However, the
extracted volume is very small in compariosn to the total deposition.
MOSTE | Mainstreaming climate change risk management in development | DoR district baseline
10
The river bed materials are also being excavated from upstream side also.
i
TA – 7984 NEP
October, 2013
Mainstreaming Climate Change Risk Management in
Development
1 Main Consultancy Package (44768-012)
PANCHTHAR DISTRICT BASELINE: DEPARTMENT OF ROADS
(DOR)
Prepared by ICEM – International Centre for Environmental Management
METCON Consultants
APTEC Consulting
Prepared for Ministry of Science, Technology and Environment, Government of Nepal
Environment Natural Resources and Agriculture Department, South Asia
Department, Asian Development Bank
Version B
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
ii
TABLE OF CONTENTS
1 PANCHTHAR DISTRICT...................................................................................................... 1
1.1 District Sector Master Plan ............................................................................................. 1
1.2 Sector budgeting and staff .............................................................................................. 1
1.3 Sector trends and issues ................................................................................................. 1
1.3.1 Trends ....................................................................................................................................... 1 1.3.2 Issues ........................................................................................................................................ 1
1.4 Asset inventory ............................................................................................................... 2
1.5 Linkages to other sectors ................................................................................................ 2
1.6 Priority infrastructure in Dolakha District ....................................................................... 2
1.6.1 Prioritisation process ................................................................................................................ 2
2 PANCHTHAR DISTRICT: ASSET BASELINE ........................................................................... 4
2.1 Asset1: Barpa Landslide on Phidim to Taplejung Road ................................................... 4
2.1.1 Asset Description ...................................................................................................................... 5 2.1.2 Adaptation audit ...................................................................................................................... 6
ANNEX A: MAP OF PANCHTHAR DISTRICT ..................................................................................... 1
ANNEX B: ANNUAL BUDGET ......................................................................................................... 2
ANNEX C: NAMES & POSITIONS OF DISTRICT OFFICERS ................................................................. 3
ANNEX D: ASSET INVENTORY - PANCHTHAR ................................................................................. 4
ANNEX E: PHOTOGRAPHS ASSET 1 ................................................................................................ 5
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
1
1 PANCHTHAR DISTRICT
1.1 District Sector Master Plan
The ARMP has not yet been drawn up
1.2 Sector budgeting and staff
Budgeting
The annual budgets for 2011/2012 and 2012/2013 is given in Annex B
Staff
The names and positions of the district officers is given in Annex C
1.3 Sector trends and issues
Bharatpur Division is one of the 25 divisions of DoR and covers several districts including Chitwan
District. Although the main task of the division is to maintain the roads (routine, periodic,
emergency, recurrent etc.) it also executes small to medium road and bridge projects.
1.3.1 Trends
The current trend of the divisions are as follows:
Planning
Planning of works is done by the respective divisions. The division is required to prepare annual road
maintenance plan (ARMP) for each year. After approval of the plan by Ministry/DoR, yearly budget is
provided to divisions. Without ARMP, the division will not be liable to receive the yearly budget.
Design
Design works of construction roads and bridges in general are carried out by local consultants. For
big projects, especially for donor (WB, ADB etc.) funded ones DoR hires foreign consultants.
Construction
All the construction and maintenance works of roads and bridges are done by using local
contractors. The present trend in the construction has shifted from manual to machines. For
example at present construction equipment such as excavator, paver, dozer, roller are being used
more frequently.
Although Chitwan Division is meant for maintenance of roads, it is carrying out construction works of
roads and bridges also.. For example it is involved in construction of 180 m long motrable bridge
and Chepang Marga..
Monitoring
Monitoring is done on the following aspects:
1. Programme
2. Cost
3. Quality
4. Progress
1.3.2 Issues
Planning for the asset management in the road sector has improved the quality of maintenance in
DoR. However, following initiative will help to overcome the shortfall in the maintenance
activities of DRO.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
2
* Timely release of the maintenance budget.
* Close monitoring of the activities both at Division and central levels.
* Training, working environment and motivation to the Division staff.
The number of length workers deputed in hilly reason during rainy season is not sufficient due to
high importance of the highways. Old and worn out bridges in PRM needs timely attention.
1.4 Asset inventory
The list of District roads and bridges is given in Annex E
1.5 Linkages to other sectors
Cooperation with other sectors
The DoR at present is cooperating with the following agencies for implementation of RIWs:
DoLIDAR, DoI, DWSS, DWIDP, NT, NEA, Department of Transport (DoT)
Major Organization working in the District:
WB is providing 10% of the maintenance to the divisions.
1.6 Priority infrastructure in Dolakha District
1.6.1 Prioritisation process
. The key criteria for prioritisation include:
Infrastructure of national strategic importance
Infrastructure of district strategic importance
Infrastructure that has been impacted by past extreme events
Infrastructure located in areas prone to past extreme events
At least one planned infrastructure
The consultant in consultation with the division chief prepared final lists of the priority structures of
the district. The list was prepared following the criteria provided in District Office Report. The
priority list is given in the following table.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
3
ID Name Infrastructure
type
Reason/s for inclusion
1 Barpa Landslide Road One of the most problematic site of
Panchthar-Phidim Road Section. At
present it is almost stabilized after
construction of breast walls and bio-
engineering works. To provide an example
of successful adaptation measure.
2 Jorkulo Landslide
Road During pavement construction, the
contractor excavated roadside hill slope
for gravels and crushed stones. After
excavation, the hill slope started to slide
and closed the road several times. To
show an example of man made problem.
3 Kabeli Bridge Bridge Selection of bridge site and its type is
appropriately done. Example of properly
designed bridge.
4 Hewa Khola Bridge
Bridge The gradient of the river at the bridge site
is high. There is high vulnerability to
damage of the bridge by transported
boulders during very high flood. To show
bad consequences of providing pier across
fast flowing rivers.
5 Tamor Bridge Bridge Newly constructed bridge at the boarder
between Panchthar and Dhankuta
Districts. It is the longest bridge of the
district and is very new.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
4
2 PANCHTHAR DISTRICT: ASSET BASELINE
2.1 Asset1: Barpa Landslide on Phidim to Taplejung Road
View of road and landslide area from Taplejung side. The whole landslide area, at present is
covered by bio-engineering and is almost stable.
Sketch Plan of Site
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
5
2.1.1 Asset Description
The landslide is located at a distance of 18 kilometer from Phidim (towards Taplejung side). It is huge
landslide with an average size of 60m X 70m (along road) and it is the most problematic site along
Phidim-Taplejung road section.
The landslide was developed before the construction of the road. After road construction the
landslide became more active and frequent and obstructed vehicular traffic on several occasions
especially during monsoon.
In order to minimize the effect of landslide, DoR took the following actions:
Realigned the road through the upper portion of the landslide
Constructed breast wall throughout the landslide area;
Applied bio-engineering measures on the whole landslide area;
Provided larger side drain along landslide stretch.
The incidence of landslide has decreased significantly in the last 2 years after adopting the above
measures.
The landslide stabilization works were carried out in piecemeal and hence its construction and
maintenance costs are not known.
There were not any extreme events except closure of vehicular traffic.
The information on IEE/EIA of the area was not available.
Watershed context
The asset lies inside the watershed of Hewa Khola which is located at an aerial distance of less than
on kilometer. There are not any major water sources flowing through/near the asset. Only one small
rivulet exists at the mid of the landslide. A pipe culvert is constructed for draining the water at
rivulet location. This rivulet becomes dry throughout the year except during monsoon season.
Asset location
The landslide is located at a distance of 18 kilometer from Phidim (towards Taplejung side). The hill
slope where the asset is located is steep (about 250).
The area near the bridge site consists of cultivated land and shrubs and bushes and trees. Although
there are not any major water bodies at the surface, it seems that there is considerable sub-surface
water movement.
The name (Barpa Bhir) of the location indicates that it used to be landslide prone area even before
the road was constructed. The landslide became more active after the road construction. There used
to be frequent road closure up to two years ago (or after 15 years of road construction). However,
there has not been any major event in the recent time and it seems that the landslide has stabilized.
Asset condition
The whole asset can be divided into following components/adaptation measures:
a) Road (surface); the road surface is maintained satisfactorily. However, it is still not black
topped. The DoR staffs stated that they will black top the section after the landslides are
stabilized.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
6
b) Breast walls; these structures are constructed throughout the landslide section and its
condition is good. There are not any problems such as breaking of gabion wires, bulging of
walls etc.
c) Side drains; DoR has constructed a bigger size side drains at the landslide section. The drain
was cleaned and any major damage was not observed.
d) Vegetations on the slope planted as bio-engineering measures for slope stabilization; the
vegetations are green, thick and have fully covered the slope minimizing the probability of
surface erosion.
Asset design
The road is designed as per feeder road standard. Although there used to be landslide problem in
the past, the area is stable at present. It is to be noted that avoidance of landslide area in the design
phase was not possible as the whole area was moving.
Past extreme events and impacts
The road has frequently been closed due to landslides especially during rainy season.
Past adaptation responses
The adaptation responses to prevent the landslide are:
a) Breast walls
b) Surface water management
c) Bio-engineering works
These adaptation responses of the above measures are found functioning properly.
Design appropriateness
The hill slopes geology of whole country in general is fragile. Due to this, majority of the hill roads
suffer from landslides. DoR have adopted several measures to protect the hill roads from landslides.
In majority cases, DoR is successful and in few cases the landslides are still not stabilized and causing
problems. Barpa Bhir is one of the few examples where the DoR has been successful in stabilizing
the landslide problem to a great extent.
2.1.2 Adaptation audit
Adaptation location
As set out in baseline report above
Watershed context
As set out in baseline report above
Adaptation condition
The adaptation works are generally in good condition
Threat description
The threat is that increased rainfall and intensity of rainfall duet o climate change will increase the
moisture in the landslip areas and therefore increase the instability of the hillside.
Past extreme events and impacts
As mentioned above in baseline report
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
7
Adaptation design
The design of the adaptations is as described in the baseline report above
Adaptation success
The adaptations have been successful to date
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
1
ANNEX A: MAP OF PANCHTHAR DISTRICT
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
2
ANNEX B: ANNUAL BUDGET
Budget Head FY 2011/12 FY 2012/13 Remarks
General Administration 8818900 -
106-Road Board 26,125,000 27,500,000
107-City Road 101,745,000 107,100,000
148- District Road 34,532,500 36,350,000
123-Regional Road 23,465,00 24,700,000
302-Tourism 10,830,000 11,400,000
199-Chepang Marga 55,404,000 58,320,000
157-Bridge Construction 66,785,000 70,300,000
158-Bridge Maintenance 6,650,000 7,000,000
Total 334,355,400 342,670,000
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
3
ANNEX C: NAMES & POSITIONS OF DISTRICT
OFFICERS
SN Name Position
1 Mr. Birendra Mahaseth Division Chief
2 Mr. Sourav Bajracharya Engineer
3 Mr. Ganga Bahadur Maharjan Engineer
4 Mr. Basant Yadav Engineer
5 Mr. Birendra Kumar Mandal Engineer
6 Mr. Nanda Kumar Gupta Engineer
7 Mr. Dal Bahadur Gurung Engineer
8 Mr. Yadav Prakash lamichhane Engineer
9 Mr. Himalaya Prasad Parajuli Account Officer
10 Mr. Roshan Dev Sub-Engineer
11 Mr. Sachendra Mishra Sub-Engineer
12 Mr. Raghunath Subedi Nayab Subba
13 Mr. Shiva Sharma Nayab Subba
14 Support Staffs (42 nos) Drivers, Supervisors, Peons etc.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
4
ANNEX D: ASSET INVENTORY - PANCHTHAR
LIST OF ROADS
LIST OF BRIDGES
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
5
ANNEX E: PHOTOGRAPHS ASSET 1
Gabion wall of 2 m height is provided throughout the lanslide stretch. The condition of the wall is
good.
Lined side drain is provided throughout the landslide stretch. Its base width is 70 cm which is
bigger than usual.
MOSTE | Mainstreaming climate change risk management in development | DoR District Baseline
6
Types of vegetations applied for bio-engineering works. Similar type of vegetations is applied on
the whole area.
There is a smaller landslide area toward Phidim side. A rivulet lies between them. At this section
also 2m high gabion breast wall is constructed.