TITLE
Technical Tower WorkshopSacofa, Celcom, Digi & Maxis
Macro Common Antenna System (Macro CAS)
12 March 2015
an axiata company
Existing installation issue
COMPANY CONFIDENTIAL 2
Type Antenna weight
RRU Weight
Total Weight
SB 7.9 25 32.9
DB 19.5 25 44.5
TB 34 25 59
QB 56 25 81
• Constraints– Different telcos with different
configuration and installation method.
– Weight incurred (depend on number of system installed)
– Table – weight per sector
an axiata company
COMPANY CONFIDENTIAL 3
SUMMARY
Proposal
Basic Antenna Specification for Macro CASLoading Weight for Macro CASAdvantages & Disadvantages for all OptionsAntenna System Configuration
Option – Supply of antenna, jumper, feeder Artification
an axiata company
Proposal• There are 3 options were identified for Macro Common Antenna Systems
(Macro-CAS).- Quadband- Triband- Dualband
• RF Planning Matter (Azimuth, Tilting & RF Antenna Height)– PM has the right to determine the Azimuth, Tilting and RF Antenna
height which subject to planning requirements.– Others telcos are not allowed to adjust any azimuth and antenna tilting
without consent from PM.– Structure height should be defined by PM.
• Antenna Location– RF Antenna (mobile) on most upper level of the structure– Microwave on lower level of the structure
• RRU Location– RRU located on ground level– Sacofa to provide boom for RRU Mounting and securities for all telcos
equipments, such as caging
COMPANY CONFIDENTIAL 4
an axiata company
COMPANY CONFIDENTIAL 5
Basic Antenna Specification for Macro CAS
Option Antenna Type Band Low High High High
1 QuadbandL H H H
Freq 900 1800 2100 2600
Gain 17 18 18 18
High Gain NA 21 21 21
2 TribandL H H
Freq 900 1800 to 2100 1800 to 2600
Gain 17 18 18
High Gain NA 21 21
3Dualband
L H(with Ultra Broadband)
Freq 900 1800 to 2600
Gain 17 18
High Gain NA 21
an axiata company
COMPANY CONFIDENTIAL 6
Loading Weight for Macro CAS
Note : This figure for 3 sectors basis Feeder Weight estimation = 0.5kg/m x 30 m x total feeder runs
Option Antenna TypeAntenna Weight
Feeder RunFeeder Weight
1Quadband
L H H H56kg x 3 8 x 3 360kg
2TribandL H H
34kg x 3 6 x 3 270kg
3Dualband
L H(with Ultra Broadband
20kg x 3 4 x 3 180kg
an axiata company
COMPANY CONFIDENTIAL 7
Advantages & Disadvantages for all Options
• All options have advantages and disadvantages• The best option from RF Planning point of view is Option 1• The best option from structure loading point of view is Option 3 but could
not accommodate all Telcos interest• The moderate option is suitable solution
Option Antenna TypeAntenna
SizeAntenna Weight
Feeder Cable Weight
Config*Loss
(Combiner+Insertion)
1Quadband
L H H HBulky High High Simple Low
2TribandL H H
Moderate Moderate Moderate Moderate Moderate
3Dualband
L H(with Ultra Broadband
Small Low Low Complex Moderate
an axiata company
Antenna System Configuration
COMPANY CONFIDENTIAL 8
Option 1
900 21001800 2600 900 21001800 2600
Note : *With Ultra Broadband
900 21001800 2600
DiplexerTriplexer
Quadband Antenna
Dualband Antenna
Triband Antenna
Option 3 Option 2
Combiner Combiner
an axiata company
Option – Supply of antenna, jumper, feeder
• Option
– Sacofa should supply the antenna, jumper and feeder for common antenna sites.
– Sacofa to provide the VSWR test acceptance. – In the event that Sacofa unable to deliver the above material
as per required date, PM have the right to provide those material and handover to Sacofa upon completion.
– Sacofa will be responsible for the maintenance, vandalism and etc related to the antenna, jumper and feeder.
– Rental substitution in contra for material supplied by PM to be further discuss for commercial concern.
COMPANY CONFIDENTIAL 9
an axiata company
Artificial
• Artificial View
Painting feeder according to the structure color. Camouflage antenna (subject to degradation of signal strength)
COMPANY CONFIDENTIAL 10
Special note to sesco, we appreciate this collaboration between telcos and sesco in this workshop. As much as we face challenges in delivering with our customer needs, we believe the same could be true for sesco. We hope En. Rosli representatives from Sesco could make a difference to closing the gap on progress update on power application.
an axiata company
• Team member– Syed Taha Syed Mansur [email protected]– Michelle Siew Ee Hanya [email protected]– Zulkarnain Shah [email protected]– Nik Ashraf Nik Mahmood [email protected]– Ku Syamsul Izwan Ku Yahya [email protected]– Alex Lee [email protected]– Mohd Hazwan Bin Md Tahir [email protected]– Zamhari Salleh [email protected]