Date Duration (in min)

Time Place TeamMembers

Issues People

08/05/2008

60 1:00-2:00

University, 4KH, basement

All members

We have further discussed the GUI and the database interface.

Date Duration (in min)

Time Place TeamMembers

Issues People

Page 3: Team Progress Report #5

The problem we have faced last week was the hardware wiring and interfacing. There is no information in the Internet, for that we are going to ask for help from eng.Tariq and eng.Laya and if necessary from Future RFID company.P.S: We received the hardware on the end of the week (thursday).

Page 4: Team Progress Report #5

Task Done byFurther Implemention of functions needed

(Database manager)Abdulaziz

Implimenting the GUI Mohamed and FahadUnderstanding how to connect the hardware All members

Page 5: Team Progress Report #5

For next week: Continue working on the system interface

(the GUI code). Integrate Gui with the database manager Understanding how the hardware work

(wiring and interfacing)..