Team 8: Grand River Rapids

26
Team 8: Grand River Rapids

description

Team 8: Grand River Rapids. Team 8. Aaron Vanderhill. Jim Barron. Jeff Van Laar. Tom Marshall. Outline. Context & Customer Project Overview Design Alternatives Final Design Design Norms Site Planning Dam Modification – HEC-RAS modeling Future Work Questions. Context & Customer. - PowerPoint PPT Presentation

Transcript of Team 8: Grand River Rapids

Page 1: Team 8: Grand River Rapids

Team 8: Grand River Rapids

Page 2: Team 8: Grand River Rapids

Team 8

Aaron Vanderhill Jim Barron Jeff Van Laar Tom Marshall

Page 3: Team 8: Grand River Rapids

Context & Customer Project Overview Design Alternatives Final Design Design Norms Site Planning Dam Modification – HEC-RAS modeling Future Work Questions

Outline

Page 4: Team 8: Grand River Rapids

Kayakers and Canoeists have shown

interest

GRWW

Recreational course not only for

experienced kayakers

Revitalization of Downtown

Context & Customer

Page 5: Team 8: Grand River Rapids

Return the Grand River to a more natural state

Eliminate dangerous hydraulic at 4th street dam

Design entry and exit locations for kayakers

Project Overview

Page 6: Team 8: Grand River Rapids

1. Removal of 5 beautification dams◦ Replace with natural rocks

2. Diversion Channel◦ Go around 4th street dam

3. 4th Street Dam modification

4. Removal of 4th Street Dam

Design Alternatives for River

Page 7: Team 8: Grand River Rapids

Hybrid of alternatives 1 and 3◦ Partial replacement of downstream dams◦ Modification of 4th Street Dam

with stair step Increase entry and exit points Reasons

◦ Meets client’s needs◦ Improves fish habitat◦ Other alternatives not feasible

Sediment behind 4th Street Dam

Would look unnatural Greater costs

Final Design

Page 8: Team 8: Grand River Rapids

Caring◦ Eliminate dangers associated with dams, making

the river safer

Justice◦ Respect rights of fishermen and property owners

Stewardship◦ Naturalize river◦ Improve fish habitat

Design Norms

Page 9: Team 8: Grand River Rapids

Entry & Exit Points

Increase Usability

Site Design

Page 10: Team 8: Grand River Rapids

Special Study•FTC&H•Green Grand Rapids

•18 Sites•Pre-owned by City of Grand Rapids

Page 11: Team 8: Grand River Rapids

Four Entry and Exit Points

Canal Street Park

Fulton Street

Fish Ladder Park

Ford Museum

Page 12: Team 8: Grand River Rapids

Fish Ladder Park

Fish Ladder Park

Page 13: Team 8: Grand River Rapids

Canal Street Park

Canal Street Park

Page 14: Team 8: Grand River Rapids

Ford Museum, Ah-Nab-Awen Park

Ford Museum

Page 15: Team 8: Grand River Rapids

Fulton Street Site

Fulton Street

Page 16: Team 8: Grand River Rapids

Signs◦ Guide, Regulate, and Warn

Lighting Guard Rails

Safety

Page 17: Team 8: Grand River Rapids

Floatable Dock

•Kayak Dock•$1,299 each for Economy Design•Hand ropes on dock

Page 18: Team 8: Grand River Rapids

Project Location

Page 19: Team 8: Grand River Rapids

Flow Rate◦ River used between April and November◦ Low flow = 1,700 cfs◦ High flow = 50,000 cfs (100 year storm)◦ Design flow of 3,200 cfs

Still tested with 100 year storm

Modeling Decisions

Page 20: Team 8: Grand River Rapids

Modeling Accuracy

◦ Rocks & boulders as series of weirs

◦ California Department of Transportation

Modeling Decisions

Page 21: Team 8: Grand River Rapids

4th Street Dam Safety Hazard

Page 22: Team 8: Grand River Rapids

Design Solution – Stairstep

Page 23: Team 8: Grand River Rapids

Downstream Modifications

•Dam modification creates rapids

Page 24: Team 8: Grand River Rapids

Finalize HEC-RAS

Final Report

Prepare for Sr. Design Night◦ Benchtop Model demonstration

Cost Estimation

AutoCAD Drawings

Future Work

Page 25: Team 8: Grand River Rapids

Demonstration

Benchtop Model

Page 26: Team 8: Grand River Rapids

Questions