Team 8: Grand River Rapids
description
Transcript of Team 8: Grand River Rapids
Team 8: Grand River Rapids
Team 8
Aaron Vanderhill Jim Barron Jeff Van Laar Tom Marshall
Context & Customer Project Overview Design Alternatives Final Design Design Norms Site Planning Dam Modification – HEC-RAS modeling Future Work Questions
Outline
Kayakers and Canoeists have shown
interest
GRWW
Recreational course not only for
experienced kayakers
Revitalization of Downtown
Context & Customer
Return the Grand River to a more natural state
Eliminate dangerous hydraulic at 4th street dam
Design entry and exit locations for kayakers
Project Overview
1. Removal of 5 beautification dams◦ Replace with natural rocks
2. Diversion Channel◦ Go around 4th street dam
3. 4th Street Dam modification
4. Removal of 4th Street Dam
Design Alternatives for River
Hybrid of alternatives 1 and 3◦ Partial replacement of downstream dams◦ Modification of 4th Street Dam
with stair step Increase entry and exit points Reasons
◦ Meets client’s needs◦ Improves fish habitat◦ Other alternatives not feasible
Sediment behind 4th Street Dam
Would look unnatural Greater costs
Final Design
Caring◦ Eliminate dangers associated with dams, making
the river safer
Justice◦ Respect rights of fishermen and property owners
Stewardship◦ Naturalize river◦ Improve fish habitat
Design Norms
Entry & Exit Points
Increase Usability
Site Design
Special Study•FTC&H•Green Grand Rapids
•18 Sites•Pre-owned by City of Grand Rapids
Four Entry and Exit Points
Canal Street Park
Fulton Street
Fish Ladder Park
Ford Museum
Fish Ladder Park
Fish Ladder Park
Canal Street Park
Canal Street Park
Ford Museum, Ah-Nab-Awen Park
Ford Museum
Fulton Street Site
Fulton Street
Signs◦ Guide, Regulate, and Warn
Lighting Guard Rails
Safety
Floatable Dock
•Kayak Dock•$1,299 each for Economy Design•Hand ropes on dock
Project Location
Flow Rate◦ River used between April and November◦ Low flow = 1,700 cfs◦ High flow = 50,000 cfs (100 year storm)◦ Design flow of 3,200 cfs
Still tested with 100 year storm
Modeling Decisions
Modeling Accuracy
◦ Rocks & boulders as series of weirs
◦ California Department of Transportation
Modeling Decisions
4th Street Dam Safety Hazard
Design Solution – Stairstep
Downstream Modifications
•Dam modification creates rapids
Finalize HEC-RAS
Final Report
Prepare for Sr. Design Night◦ Benchtop Model demonstration
Cost Estimation
AutoCAD Drawings
Future Work
Demonstration
Benchtop Model
Questions