TDTWG NAESB EDM v1.6 Project Update to RMS Thursday October 16, 2003.
-
Upload
lester-flynn -
Category
Documents
-
view
212 -
download
0
Transcript of TDTWG NAESB EDM v1.6 Project Update to RMS Thursday October 16, 2003.
![Page 1: TDTWG NAESB EDM v1.6 Project Update to RMS Thursday October 16, 2003.](https://reader035.fdocuments.us/reader035/viewer/2022072016/56649ef05503460f94c0050a/html5/thumbnails/1.jpg)
TDTWG
NAESB EDM v1.6
Project Updateto
RMS
Thursday October 16, 2003
![Page 2: TDTWG NAESB EDM v1.6 Project Update to RMS Thursday October 16, 2003.](https://reader035.fdocuments.us/reader035/viewer/2022072016/56649ef05503460f94c0050a/html5/thumbnails/2.jpg)
TDTWGProject History
• GISB EDM v1.4 – July 08, 2002 RMS votes to approve:
• Data transport change from FTP to GISB EDM v1.4• Targeted FTP Retirement date - April 1, 2003• Market participants agreed to migrate to GISB EDM v1.4 via
ERCOT/TDTWG project plan
– Market migration concluded on Q2, 2003
• NAESB EDM v1.6 – July 08, 2002 RMS votes to approve:
• Data transport change from GISB EDM v1.4 to NAESB EDM v1.6 • Target GISB EDM v1.4 Retirement date – Q1, 2004
• TDTWG would create Market Survey necessary for project planning for timing and readiness of project testing and implementation
• Testing and migration would be coordinated with Market Test Flights
![Page 3: TDTWG NAESB EDM v1.6 Project Update to RMS Thursday October 16, 2003.](https://reader035.fdocuments.us/reader035/viewer/2022072016/56649ef05503460f94c0050a/html5/thumbnails/3.jpg)
TDTWGWhere We Are!
Area Task Description Comment
PLANNING
TDTWG Project Charter Project description, Objective, Scope, Deliverables, Project Team and governance of the project
• Published – • Market review and
agreement achieved
Market Survey Survey of Market Readiness for implementation/migration to NAESB EDM v1.6. Identifies contingencies, dependencies, and primary contact information for market coordination. Survey was emailed from ERCOT Client Relations to the Primary Market Participant Registration contacts and TDTWG.
• Completed• Results compiled
and incorporated into detailed project plan
Project Plan / Timeline Project schedule to include development, testing, and migration schedules/timeline for each Market Participant. Market Participant sign-off for key milestone dates will be required.
• Completed• 10/01/03
Vendor SW Available Vendor NAESB EDM V1.6 software available to its users. • Delivered• 08/15/03
Market Implementation Guide
Document for Market Participants to use in support of project implementation. Identifies methodology for implementation, testing/migration requirements, and project contacts.
• Reviewed and received agreement from the Market
Testing Approach Document
Document is to define a detailed, comprehensive plan for controlling and testing the NAESB EDM 1.6 data transport effort by organizing the testing activities. Includes detail test schedules for ERCOT-TDSP, ERCOT-CR, TDSP-CR.
• Published – • Market review and
agreement achieved
EXECUTION
Planning – Execution Market Project Kickoff Conference Calls
Market participant understanding and compliance of the testing and implementation approach for the NAESB EDM v1.6 project. 100 % agreement was achieved on the call.
• Completed• 10/03/03
Market Update Distribute to RMS List Serve
Distributed N AESB EDM v1.6 project update addressing latest project timeline and approach
• Completed• 09/26/03
![Page 4: TDTWG NAESB EDM v1.6 Project Update to RMS Thursday October 16, 2003.](https://reader035.fdocuments.us/reader035/viewer/2022072016/56649ef05503460f94c0050a/html5/thumbnails/4.jpg)
TDTWGTesting Project Approach
ERCOT
TDSPs
CRs
Phase 1: ERCOT and TDSPs1st Phase of testing will be between ERCOT and the TDSPs
3 week duration• 1 week of initial testing• 1 week for rework• 1 week for retest
Phase 2: ERCOT and CRs2nd Phase of testing will be between ERCOT and the CRs
6 week duration• 3 weeks of initial testing• 1 week for rework• 2 weeks for retest
Phase 3: TDSPs and CRs3rd Phase of testing will be between the TDSPs and the CRs
6 week duration• 3 weeks of initial testing• 1 week for rework• 2 weeks for retest
TESTING ENTITY
![Page 5: TDTWG NAESB EDM v1.6 Project Update to RMS Thursday October 16, 2003.](https://reader035.fdocuments.us/reader035/viewer/2022072016/56649ef05503460f94c0050a/html5/thumbnails/5.jpg)
TDTWGNAESB EDM v1.6 Timeline/Milestones
Initiation• Initial strategy
sessions• Draft survey
compiled• Draft guideline
compiled• High-level
time line identified
• Project sourced at ERCOT
Planning• Survey issued;
results gathered• Guideline
approved and published
• Schedules & dependencies identified
• Project Charter approved
• Plan finalized and approved
• Vendor SW available
MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB 03 03 03 03 03 03 03 03 04 03
6/27 Timeline, Survey, & Imp. Guide Review
7/7 Initial Charter & High-level Project Plan developed
7/14 Implementation
Guide Sent to Market for
Review
9/5 Survey Results back from Market
10/01: Signed Charter Docs Returned/ Plan Finalized/ Testing Schedules Approved/ Vendor SW Available
7/31FERC NAESB Standard Decision
8/25 Survey, Guide, and
Project Charter
published to Market
Continued on Next Slide
![Page 6: TDTWG NAESB EDM v1.6 Project Update to RMS Thursday October 16, 2003.](https://reader035.fdocuments.us/reader035/viewer/2022072016/56649ef05503460f94c0050a/html5/thumbnails/6.jpg)
TDTWGNAESB EDM v1.6 Timeline/Milestones
Execution• ERCOT chges
implemented• MP changes
implemented• Cycled Testing• Scheduled
Migrations
Closure• Lessons Learned• Operations
support
OCT NOV DEC JAN FEB MAR APR MAY JUN JUL 03 03 03 04 04 04 04 04 04 04
1/05 Phase 2 Test Start: ERCOT-CR’s
2/13 Phase 2 Test End
2/16 Phase 3 Test Start: TDSP’s-CR’s
3/26 Phase 3 Test End
12/19 Phase 1 Test End
4/05 Migration Start
12/01 Phase 1 Test Start: ERCOT-TDSP’s
4/16 Migration End
4/26 TX SET 2.0 Connectivity Test Start for New MPs
10/01 Market Dev Start
Mid-May: Close Project
4/23 Lessons Learned Mtg
10/27 TCW form sent to Market for Completion
11/14 TCW Forms Ret- urned
![Page 7: TDTWG NAESB EDM v1.6 Project Update to RMS Thursday October 16, 2003.](https://reader035.fdocuments.us/reader035/viewer/2022072016/56649ef05503460f94c0050a/html5/thumbnails/7.jpg)
TDTWGMarket Participant Comments & Concerns
• Market Participant comments and concerns received to date have been addressed
• Comments and concerns have primarily included:– TDTWG NAESB EDM v1.6 Guideline interpretations– Running GISB v1.4 and NAESB v1.6 concurrently, possibly
requiring support for multiple test environments– Overlapping testing timelines – Flight Test (0104 & 0304) vs.
NAESB EDM V1.6– Compliance with NAESB – Required vs. Mutually Agreed– Vendor Software Availability– Resource constraints
![Page 8: TDTWG NAESB EDM v1.6 Project Update to RMS Thursday October 16, 2003.](https://reader035.fdocuments.us/reader035/viewer/2022072016/56649ef05503460f94c0050a/html5/thumbnails/8.jpg)
TDTWGReference Documents
• Documentation supporting the project is available on the ERCOT web-site:
– TDTWG NAESB EDM v1.6 Implementation Guide
– Market Participant Survey
– Project Charter document
– NAESB EDM v1.6 survey results
– Project Timeline document
– Testing Approach document (Identifies Testing Phase I – III Schedules)
http://www.ercot.com/participants/committees/tdtwg_comm.htm
![Page 9: TDTWG NAESB EDM v1.6 Project Update to RMS Thursday October 16, 2003.](https://reader035.fdocuments.us/reader035/viewer/2022072016/56649ef05503460f94c0050a/html5/thumbnails/9.jpg)
TDTWGNext Steps
• RMS Update - 10/16/03• TDTWG Meeting - 10/24/03• Update TDTWG Website with “FAQs”• Scheduled Project Testing Activities
– Phase I - TDSP & ERCOT Testing Readiness Call – 11/22/03
– Phase II - CR & ERCOT Testing Readiness Call – 12/17/03
– Phase III - CR & TDSP Testing Readiness Call – 02/11/04
• Project Team updates will be provided to RMS as needed via the ERCOT – Retail Market Services
• Post April 03, 2004 NAESB EDM v1.6 migration– New Market Participants entering the market must support NAESB EDM v1.6
![Page 10: TDTWG NAESB EDM v1.6 Project Update to RMS Thursday October 16, 2003.](https://reader035.fdocuments.us/reader035/viewer/2022072016/56649ef05503460f94c0050a/html5/thumbnails/10.jpg)
TDTWGProject Support Team
• As the project moves forward, the Project Team will ensure that all communications, questions and concerns will continued to be addressed
– Project Team Support• TDTWG
– Debbie McKeever – Chair
– Susan Tope – Vice Chair
– TDTWG Technical Experts
• ERCOT Team– Rob Connell – IT PM Director
– John Kassell – Business Project Manager
– Jill Prince – IT Project Manager
– Dave Farley – IT Delivery Manager
– Clay Katskee – NAESB EDM v1.6 / Paperfree Analyst
– Nagaraju (Naga) Valasagandla – NAESB EDM v1.6
– Michael Taylor – Paperfree Analyst
– Suzette Wilburn – Retail Market Liaison
![Page 11: TDTWG NAESB EDM v1.6 Project Update to RMS Thursday October 16, 2003.](https://reader035.fdocuments.us/reader035/viewer/2022072016/56649ef05503460f94c0050a/html5/thumbnails/11.jpg)
TDTWGQuestions?