© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m
Jens C Boemer, Eamonn LannoyeEPRI Grid Operations and Planning
Ning KangArgonne National Lab
T&D Operations & Planning Coordination: TSO/DSO and Tx/DxPlanning Interaction, Processes, and Data ExchangeNERC SPIDER Working Group, January 8-9, 2019, Austin, TX
Work supported by U.S. DOE Office of Electricity, Advanced Grid Research and Development under contract ANL 6F-30562 Mod 2 FE.
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m2
EPRI’s Integrated Grid
A Power System that is Highly Flexible, Resilient and Connected and Optimizes Energy Resources
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m3
Two Parallel EPRI EffortsEuropeU.S.
EPRI European TSO-DSOWhite Paper 2018 - 2019
DOE Project 2017 - 2019
Two Stakeholder Workshops in 2018 attended by> 25 EPRI member companies from transmission
and distribution
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m4
Ongoing InitiativesEuropeU.S.
European Network Codes ENTSO-e + DSO Group Initiatives Germany National Processes Netherlands ETPA SmartNet H2020 multiple partners
FERC orders and proposals New York NYISO roadmap California DR, DER, market integration Texas ERCOT DER integration Hawaii HECO programs
CIGRE IEEE
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m5
Project Overview
Objective: Enable responsible entities to efficiently and effectively conduct their duties in planning & operations across the T&D interface.
Focus/stakeholders: Transmission utilities/TSOs, distribution utilities/DSOs, and balance responsible parties
Approach:– Review vital functions needed to plan & operate a power system with DERs.– Catalog current state and gaps associated with existing processes.
Deliverables:– Specify data exchange needed for grid ops & planning with DERs.– Propose architectural framework and develop guidelines for T&D coordination.
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m6
Long
–Te
rm P
lann
ing
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m7
Ope
ratio
nal P
lann
ing
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m8
Real
Tim
e O
pera
tions
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m9
Preliminary Review of NERC Reliability Standards
121 NERC Standards active or coming into force
Reviewed each to determine whether an active distribution system & significant DER may give rise to:– New methods or approaches to comply with standards– Need for new data exchanges to facilitate standard compliance– Potential for the need to examine a standard’s provisions due to an emerging risk not covered by existing metrics
or requirements
Outcomes: – Unlikely, Potentially, Likely; – If likely: Short-term, Mid-term, Long-term
Candidates include, among others:– Those already on NERC’s radar: TOP-003, IRO-010, MOD-032– Potentially others: BAL-002, BAL-502-RF, IRO-017, IRO-018, MOD-020, MOD-031, PRC-001, PRC-005, PRC-006, PRC-
008, PRC-024, TOP-003
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m10
8
23
20
Long-Term Mid-term Short-term
41
29
51
Unlikely Unclear Likely
NERC Standard Review: First PassPotential revision timeline for “Likely” Stds?Change in standards / compliance approach needed?
WARNING:
More detailed review needed
Total # Stds:121
Total # Stds:51
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m11
Forthcoming Deliverables
US work– Interim report Q1 2019– Final report Q2 2019
European work– Whitepaper Q1 2019
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m12
Together…Shaping the Future of Electricity
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m13
Data Exchange: Main Options Under Consideration
Centralised Data Hub
Key Considerations:– Data Exchange Requirements– Comms. & IT Hardware– Data Protection & Cyber Security
Cascade Data Flow
TSO DSO
DER BRP
TSO
DSO
DER
BRPData Hub
– Business models – Data Types