TCG G&B Sample Assessment
-
Upload
michael-george -
Category
Documents
-
view
219 -
download
0
Transcript of TCG G&B Sample Assessment
-
8/7/2019 TCG G&B Sample Assessment
1/27
ACOOPERATIVE EFFORT IN GROUNDING &BONDING
Main & West Side Server Room & IDF
TELECOMMUNICATIONS
GROUNDING &BONDING ASSESSMENT
P R E P A R E D F O R
June 8, 2010
Included sites:
San Francisco
The single most cost-effective way to protect your people,
your equipment, and ensure business continuity.
-
8/7/2019 TCG G&B Sample Assessment
2/27
Grounding & Bonding Assessment Sample Report Confidential Information
2
contents
Executive Summary ............................................................................................................................................................ 3
Project Overview ................................................................................................................................................................ 4
Project Objectives ............................................................................................................................................................... 4
Assessment Methodology ................................................................................................................................................... 4
PANDUIT Philosophy .............................................................................................................................................................. 5
Project Team and Contact Information .............................................................................................................................. 6
Current-State Assessment .................................................................................................................................................. 7
Assessment findings summary table ................................................................................................................................... 8
Detailed assessment findings: Telecommunications Rooms.............................................................................................. 9
Detailed assessment findings: Racks and Cabinets .......................................................................................................... 11
Detailed assessment findings: Active Equipment ............................................................................................................ 12
Best Practices ................................................................................................................................................................... 14
Integrated Facilities and Network Infrastructure .............................................................................................................. 14
Purpose of Telecommunications Bonding Systems .......................................................................................................... 14
The Importance of Standards ........................................................................................................................................... 14
Complete System Bonding ................................................................................................................................................ 15
Recommendations ........................................................................................................................................................... 16
Recommendations summary ............................................................................................................................................ 16
Detailed recommendations: Telecommunications Rooms .............................................................................................. 16
Detailed recommendations: Racks and Cabinets ............................................................................................................. 18
Detailed recommendations: Active Equipment ............................................................................................................... 20
Conclusion ........................................................................................................................................................................ 21
Report History and Revisions ............................................................................................................................................ 22
Document Acceptance and Sign-Off ................................................................................................................................. 23
Appendix A: Room-by-Room Analysis .............................................................................................................................. 24
Server Room ..................................................................................................................................................................... 24
Main IDF, Other Server Room........................................................................................................................................ 41
MPOE ................................................................................................................................................................................ 49
Expansion IDF .................................................................................................................................................................... 53
West Side IDF .................................................................................................................................................................... 57
-
8/7/2019 TCG G&B Sample Assessment
3/27
Grounding & Bonding Assessment Sample Report Confidential Information
3
Executive Summary
This report is the result of an assessment of TECHCO Incorporateds telecommunications bonding networks
conducted by PANDUIT Global Professional Services in partnership with TCG Technical Consulting Group on May
1st, 2010.
Telecommunications bonding systems are active, functioning networks designed to create a robust path for strayVoltages and resulting surge currents, allowing them to bypass critical, expensive telecommunications, network, and
computer equipment and safely return to ground. These systems help enterprises maximize network uptime,
maintain system performance, and protect equipment and personnel. Poorly designed or improperly applied
grounding, bonding, and shielding techniques are known to adversely affect network performance and can increase
threats to worker health and safety.
This assessment reports on current state practices found in the SAMPLE facilities, highlights best practices for
implementation of a telecommunications bonding network that is reliable, standards compliant, and professional in
appearance, and suggests areas for improvement at SAMPLEs site. All suggestions and recommendations are
based on industry standards, best practices, and Panduit engineering expertise and are the professional opinions of
PANDUIT Global Professional Services.
Key Findings:A detailed assessment of each site can be found in Section III of the report, Current State Assessment. An
overview of observed telecommunications bonding practices yields the following:
Telecommunications Bonding is minimal to non-existent within the Main, and West Side facilities
Over 62% of evaluated areas and racks have no telecommunications bonding system whatsoever and therefore
are completely out-of-compliance with telecommunications bonding standards
36% of evaluated areas and racks exhibit minimal compliance with telecommunications bonding standards as a
result of improperly deployed telecommunications bonding systems and components
Only 2% of evaluated areas, racks, and equipment exhibit proper compliance to telecommunications bonding
standards and best practices
Recommended Practices:
A detailed recommendation of telecommunications bonding system Best Practices can be found in Section IV of thereport, Recommendations. Based upon on-site assessments and Panduit experience in telecommunications
bonding best practices, the following recommendations are made:
Active Equipment: Bond each piece of active network equipment to a grounding strip or grounding bus bar
installed in compliance with US and International grounding requirements
Racks and Cabinets: Provide a dedicated grounding and bonding system comprised of purpose-built
components (bonded frames, paint-piercing hardware, grounding bards, lugs, ground conductors, etc.) which are
engineered to comply with US and International grounding requirements.
Each site/area: Deploy a telecommunications bonding solution that meets J-STD-607-A, TIA-942, and IEEE Std
1100TM-2005 (The Emerald Book) requirements and utilizes UL-Listed or CSA-Certified products.
It is possible to retrofit and remediate existing installations at the TECCHO sites by deploying telecommunications
bonding backbones (TBBs), telecommunications grounding busbars (TGBs), bonding hardware, equipment jumpers,common bonding network (CBN) jumpers, and other grounding and bonding system components. PANDUIT offers
robust, standards-compliant telecommunications bonding solutions, provides a network of Panduit certified installers
to perform remediation work, and can evaluate the effectiveness of the site upgrade(s).
The PANDUIT team enjoyed the challenge and opportunity presented by TECHCO Incorporated. PANDUIT and TCG
look forward to working closely with TECHCO on subsequent projects and serving an advisory role where appropriate
on other TECHCO Incorporated physical infrastructure deployments and assessments.
-
8/7/2019 TCG G&B Sample Assessment
4/27
Grounding & Bonding Assessment Sample Report Confidential Information
4
Project Overview
This Telecommunications Bonding Assessment is intended to identify current-state conditions and opportunities for
improvement, if needed, in the telecommunications bonding network(s) and common bonding network(s) for
TECHCO Incorporateds Main and West Side facilities located in San Francisco, CA.
Project Objectives
The purpose of the assessment is to determine if the existing telecommunications bonding network(s) conform to
industry standards, best practices, and Panduit recommended deployment methodologies. This assessment includes
an in-depth analysis of each telecommunication area (data center, telecommunications room, or entrance facility) with
a rack-by-rack (or cabinet-by-cabinet) and component-by-component review of the telecommunications bonding
network(s). Panduit will on a best-effort basis take all data communications and telecommunications equipment into
consideration for the assessment. Specifically excluded from the assessment is all Service-Provider (Public Carrier)
equipment, POTS (Plain Old Telephone Service) equipment, and any other non-client owned/operated premises
equipment.
The assessment provides:
Analysis of the current-state of the telecommunications bonding network(s)
Detailed findings for each type of telecommunications room, entrance facility, and data center area site
Site-by-site analysis for every telecommunications bonding deployment
Examination of Telecommunications Bonding standards and best practices
Gap analysis between bonding best practice and current-state infrastructure capabilities
Recommendations for remediation to bring the telecommunications bonding network in-line with best practices
The recommendations presented in this document are based upon standards body documents (TIA, EIA, NEMA,
ANSI, IEEE), industry best-practices, and Panduit engineering expertise. Each section of this document focuses on
specific aspects of the overall Telecommunications Bonding Network deployment.
Assessment Methodology
This assessment is based mainly on the information collected on-site by the Panduit Global Professional Services
consultant through direct examination, measurement, and observation of the telecommunications bonding
infrastructure system deployment.
The assessment methodology is comprised of seven (7) key steps:
1. Determine XYZ Corporation top-of-mind issues and scope overall project requirements
2. Conduct pre-assessment discussions and information gathering
3. Perform telecommunication bonding on-site assessment(s)
4. Capture site layouts, critical data, key measurements, and deployment practices
5. Analyze data based on industry standards, best practices, and Panduit expertise
6. Develop recommendations and conclusions
7. Present final report
-
8/7/2019 TCG G&B Sample Assessment
5/27
Grounding & Bonding Assessment Sample Report Confidential Information
5
Initial pre-assessment discussions and information gathering was done via teleconference on September 28th, 2009.
The on-site assessment was performed on October 1st. The post-assessment analysis and report was completed on
October 26th
, 2009.
The resulting analysis and recommendations are not based upon any detailed application specific information or use
case scenarios but are primarily focused on conformance with industry standards and Panduit best practices.
Implementation of the recommendations provided in this report will require the services of a Panduit certified installer(PCI) to perform the actual remediation work.
Philosophy
Unified Physical Infrastructure: A Guiding Vision for a Smarter, Unified Business Foundation
The growing interdependence of systems and applications, and the increased demands that they place on physical
infrastructures, requires the integration of traditionally disparate and proprietary systems. This trend is dramatically
changing infrastructure design, management strategies and effective synchronization of critical systems, opening the
door for seamless convergence and interoperability of all core business systems. Panduit provides flexible, end-to-
end solutions for the physical infrastructure that drive operational and financial advantages, allowing businesses tominimize risk and heighten agility. Tailored by industry and customized by application, Panduit solutions span the
core systems necessary to transform a business, from data center to facility operations, to next generation intelligent
buildings.
Panduit has developed the industrys most comprehensive and holistic approach to a Unified Physical Infrastructure
and can help enterprises align, converge, and optimize critical systems communication, computing, control, power
and security to build a smarter, unified business foundation. This approach enables the use of an open standards-
based, service-oriented architecture framework and is designed to deliver tangible infrastructure and business
process improvements for increased functionality, interoperability and manageability of mission critical operations
across the enterprise.
Based upon the Unified Physical Infrastructure vision, Panduit Global Professional Services provides a systematic
approach to Assess, Design, and Maintain critical elements within SAMPLE Corporations physical infrastructureincluding the Telecommunications Bonding Network.
Step one is a Bonding Assessment. The bonding assessment evaluates existing or new facilities, collects information
about current or anticipated operations, visually inspects the grounding and bonding deployment practices, and
measures and documents key electrical characteristics. The post-assessment report generates telecommunications
bonding system improvement suggestions to facilitate the equalization of electrical potentials and provide a
supplemental return path for electrical transients.
Step two is Site Remediation. A strategy is formulated for improving the existing telecommunications bonding
network to meet established minimum functionality requirements. Best practice installation advice that meets the
intent of the design standards (J-STD-607-A, TIA-942, and IEEE Std 1100TM-2005) is considered for future
telecommunications bonding systems remediation and expansion. A PANDUIT Certified Installer (PCI) is engaged to
perform the actual site remediation work.
Step three is Lifecycle Management. Periodic health checks or re-commissioning services are performed. These
ensure that moves, adds, and changes (MACs) and additional deployments have been performed in a manner
consistent with industry standards and best practices.
-
8/7/2019 TCG G&B Sample Assessment
6/27
Grounding & Bonding Assessment Sample Report Confidential Information
6
Project Team and Contact Information
This assessment and report would not be possible with the input and contributions of key members of the TECHCO
Incorporateds team, the Remediation team, the TCG team, and Panduit Global Professional Services assessment
team. The list of personnel involved in the project and critical to the success of this assessment includes:
Client team Role/Team Phone e-mail
Joe Smith Facilities Manager* 415-222-9999 [email protected]
Sally Vasquez Project Lead 408-343-4444 [email protected]
Bill George Partner* 415-990-2320 [email protected]
Panduit team Role/Team Phone e-mail
Frank Summers On-site Assessor 744-323-2323 [email protected]
Chris Wilson On-site Assessor 454-222-1234 [email protected]
Carlos Ramirez Project Manager 245-787-4888 [email protected]
Jonathan Peterson Professional Services Sales 333-676-2145 [email protected]
-
8/7/2019 TCG G&B Sample Assessment
7/27
Grounding & Bonding Assessment Sample Report Confidential Information
7
Current State Assessment
This Telecommunications Bonding Assessment surveyed current-state conditions and recorded opportunities for
improvement for the telecommunications bonding network(s) and common bonding network(s) for TECHCO
Incorporateds Main and West Side facilities located in San Francisco, CA.
Overall Findings:
Over 90% of evaluated areas, racks, and equipment have no bonding system whatsoever and therefore are out-
of-compliance with all telecommunications bonding standards
Under 10% of evaluated areas, racks, and equipment are in minimal compliance as a result of improperly
deployed telecommunications bonding systems and components although some effort has been made to comply
with telecommunications bonding standards and best practices
Assessment Findings Summary
This section uses a graphical nomenclature to categorize the assessment of each focus area of theTelecommunications Bonding Assessment. The table below lists each area and highlights the overall findings of the
assessment for the given area based upon the following color scheme:
FullyComplies
Green is assigned when full conformance to industry standards and bestpractices exists and no threat or risk condition is found
PartiallyComplies
Yellow is assigned when partial conformance to industry standards and bestpractices exists and/or a minor threat or lower-level risk condition is found.These areas should be remediated and upgraded to best practice.
Does NotComply
Red is assigned when little or no conformance to industry standards and bestpractices exists. This condition represents a major threat and high-level riskcondition and should be remediated immediately.
Not Assessed Blue is assigned when the particular area was not assessed.
The focus areas are assessed in terms of current-state status and short-term opportunities for improvement (i.e.,
remediation to compliance with industry standards and best practices that can be accomplished with limited efforts,
costs, or rework). Findings that may require more extensive changes, substantial rework, or complete redesign in
order to bring the systems into compliance with industry standards and best practices are considered long -termopportunities and will require additional investigations and remediation recommendations beyond the scope of this
assessment.
-
8/7/2019 TCG G&B Sample Assessment
8/27
Grounding & Bonding Assessment Sample Report Confidential Information
8
SummaryofTelecommunicationsBondingAssessm
ent:
WestSide
IDF
DoesNot
Comply
DoesNot
Comply
Partially
Complies
DoesNot
Comply
DoesNot
Comply
DoesNot
Comply
DoesNot
Comply
DoesNot
Comply
Partially
Complies
WestSide
Exp.IDF
DoesNot
Comply
DoesNot
Comply
Partially
Complies
Partially
Complies
DoesNot
Comply
Partially
Complies
Fully
Complies
DoesNot
Comply
Partially
Complies
MPOE
Partially
Complies
DoesNot
Comply
Partially
Complies
Partially
Complies
DoesNot
Comply
DoesNot
Comply
Partially
Complies
DoesNot
Comply
Partially
Complies
MainIDF
OtherServer
Room
DoesNot
Comply
DoesNot
Comply
Partially
Complies
DoesNot
Comply
DoesNot
Comply
DoesNot
Comply
Partially
Complies
DoesNot
Comply
Partially
Complies
MainServer
Room
DoesNot
Comply
DoesNot
Comply
Partially
Complies
DoesNot
Comply
DoesNot
Comply
DoesNot
Comply
DoesNot
Comply
DoesNot
Comply
Partially
Complies
AssessmentArea
Solidcoppergrou
ndingbusbar(s)present
Busbar(s)drilled
withholesperNEMAstandards
Telecommunicationsequipmentgroundedto
busbarswithinra
cksorcabinets
Telecommunicationsracksandcabinets
groundedtobusb
ars
BusbarsconnectedbybackboneorCommon
BondingNetwork
ofinsulated,solidcoppercable
betweenallclose
ts,rooms,andbusbars
BackboneorCom
monBondingNetwork
connectedtogroundingbusbartoearthground
andstructuralste
el
Bondingconductorcablecoloredgreenor
appropriatelylabeled
ACandDCcurre
ntsatacceptablelevels
DCresistancebe
tweenrackorcabinetand
bondingsatacce
ptablelevels
-
8/7/2019 TCG G&B Sample Assessment
9/27
Grounding & Bonding Assessment Sample Report Confidential Information
9
Detailed Assessment Findings: Telecommunications Rooms
Approximately 98% of TECHCOs rooms, racks, and equipment were non-compliant with basic telecommunications
bonding network requirements.
The Main Server Roomand Main IDF Other Server Room do not have any room-level telecommunications
bonding system or components in place. In these rooms, no telecommunications grounding busbar (TGB) is presentand therefore none of the racks are properly connected to the room-level busbar. In the MPOE Room, the Main Exp.
IDF Room, and the West Side IDF Room, a telecommunications ground busbar (TGB) does exist; however, in the
West Side Exp IDF Room and the West Side IDF Room, this TGB is painted-over, prohibiting proper electrical
contact and thus defeating the purpose of the busbar. The busbar in the MPOE Room is a proper thickness,
unpainted busbar. However, the absence of pre-drilled NEMA standard holes and the use of 1-hole mechanical lugs
with multiple bonding connectors per lug prevent this deployment from being in full compliance.
Figure 1: Telecommunications Grounding Busbar practices at TECHCO Main Server and IDF rooms showing
painted-over busbar (top left, top right), use of one-hole mechanical lugs (top right, bottom), and absence of
pre-drilled mounting holes throughout.
-
8/7/2019 TCG G&B Sample Assessment
10/27
Grounding & Bonding Assessment Sample Report Confidential Information
10
Both the Main and West Side rooms use single-hole mechanical lugs throughout. Where deployed, these 1-hole
mechanical lugs do provide a degree of telecommunications bonding but do not represent best practice installations
as the industry standards TIA-607-A and IEEE Standard 1100 call for two-hole compression-style lugs for all
grounding and bonding terminations.
Best practices are adhered to in the MPOE Room, the West Side Exp. IDF Room, and the Main IDF Room by
using green jacketed copper conductors where these components are deployed. Conversely, foil strips or other non-copper-cable conductors are installed in these rooms to act as bonding or grounding systems. These components
do not conform to any industry standards or best practices and are not capable of carrying the currents and Voltages
found in telecommunications bonding systems. Furthermore, these non-standard conductors can result in a false
sense of security for equipment and personnel protection, giving the appearance of a supplemental bonding system
while being unable to function as such.
In general, the telecommunications bonding network within TECHCOs Main and West Side facilities is not labeled,
tagged, or otherwise clearly marked.
Figure 2: Telecommunications Bonding Network busbar-to-building steel jumpers improperly installed
using single-hole mechanical lugs. Also note that lugs are attached to painted steel, resulting in no
electrical bonding
-
8/7/2019 TCG G&B Sample Assessment
11/27
Grounding & Bonding Assessment Sample Report Confidential Information
11
Detailed Assessment Findings: Racks and Cabinets
Approximately 80% of TECHCOs racks and cabinets are non-compliant with basic telecommunications bonding
network requirements. The remaining racks and cabinets are in partial compliance with industry standards as the
bonding provisions installed do not cover all parts of the rack nor is all equipment in the rack properly bonded to the
rack itself. This effectively allows spurious currents to run across all of the racks, cabinets, and active equipment
instead of isolating the currents and routing them to the bonding network. In situations where the racks themselves
are properly bonding, this measure is often defeated by improper room-level bonding practices, typically by the
absence of a Telecommunications Bonding Busbar (TGB), lack of connection to the busbar, improper termination of
the bonding network jumper (using single-hole mechanical lugs), or the painting-over of bonding system components
so no low-impedance electrical bond could be made. The vast majority of TECHCOs racks and cabinets are not
integrally (self) bonded and therefore will require supplement equipment bonding provision via the use of individual
equipment jumpers, rack-level busbars, and bonding network jumpers.
Figure 3: Rack level Telecommunications Bonding Network installation practices in TECHCO Main and West Side
rooms. Non-compliant practices observed include unused single-hole mechanical lug (top left), cage-nut style
mounting points "floating" in painted equipment rack rails (top right), no thread forming screws used for any
equipment mounting points and unmounted equipment (bottom left) , and adhesive foil strip grounding tape run
on top of rack rail (bottom right)
-
8/7/2019 TCG G&B Sample Assessment
12/27
Grounding & Bonding Assessment Sample Report Confidential Information
12
Detailed Assessment Findings: Active Equipment
Approximately 88% of TECHCOs active equipment (switches, routers, servers, appliances, PBXs, MUXs, UPSs,
etc.) housed in the sites surveyed did not have any form of visible grounding aside from the third conductor on the AC
power supply. Throughout the Main and West Side rooms, the telecommunications and networking equipment is
typically mounted in racks or cabinets that do not have integral self-bonding; therefore, equipment would require a
discrete equipment bonding jumper connecting to a rack-level bonding busbar. These busbars and bonding jumpers
were not present on any of the installed active equipment. Some PBX equipment did have bonding jumpers installed
to the equipment chassis; however, these jumpers remained unterminated and unused.
Figure 4: Active equipmentTelecommunications Bonding installation practices in TECHCO Main and West
Side rooms. Practices observed include not using equipment manufacturer provided system ground
attachment pads (top left), un-bonded, un-racked stacked equipment (top right), and not installingmanufacturer provided equipment bonding jumpers (bottom).
-
8/7/2019 TCG G&B Sample Assessment
13/27
Grounding & Bonding Assessment Sample Report Confidential Information
13
Two pieces of key networking and computing gear a Cisco Systems Catalyst 6513 switch and an HP C7000 blade
center, both located in the Main Server Room are placed directly on the floor. There are no provisions for
grounding or bonding this gear to an appropriate telecommunications bonding network. Additionally, there is no cable
management or cabling pathway for this equipment. This represents a significant operational risk as all data cabling
runs are completely unprotected and run haphazardly on the floor.
Figure 5: Critical networking and computing equipment placed on floor in Main Server Room. Note
Cisco Catalyst 6513 switch (top left) and HP C7000 Blade Center (top right, bottom left) not
mounted in any equipment rack and absence of Telecommunications Bonding Network, proper
cable management, cable pathways, or cable patching organization (bottom right).
-
8/7/2019 TCG G&B Sample Assessment
14/27
Grounding & Bonding Assessment Sample Report Confidential Information
14
Best Practices
The telecommunications bonding system is more than just an insurance policy against a lightning strike or other
surge event. It is an active, functioning system that provides protection for personnel and equipment. The use of
best practices for proper telecommunications bonding deployment is essential for efficient network performance in
telecommunications spaces, computer rooms, and data centers.
Integrated Facilities and Network Infrastructure
Decisions regarding network design and deployment increasingly center on integrating facilities elements with the
networking physical layer. The collective management of these elements, often in the same spaces, allows networks
to meet aggressive uptime goals and scale and expand as required.
A reliable network infrastructure is comprised of sufficient power and cooling capacity, effective telecommunications
bonding and proper grounding of system elements (active and passive), and pathways that route, manage, and
protect electrical and data cabling. Effectively managed cabling also maximizes the accessibility of other facilities
elements by enabling faster moves, adds, and changes (MACs) and by reducing required administration and
maintenance work.
By using robust systems comprised of quality components and materials, deployed according to industry standards
and best practices, network stakeholders can minimize network interruptions and maximize uptime and business
continuity.
Purpose of Telecommunications Bonding Systems
The telecommunications bonding system is an active, functioning network designed to maximize equipment uptime,
maintain system performance, and protect equipment and personnel.
The primary purpose of this system is to create a suitable path for the equalization of stray Voltages and theirresultant surge currents, allowing them to safely return to their source. Lightning, power system fault currents, circuit
switching (motors starting and stopping), activation of surge protection devices, and electrostatic discharges (ESD)
are common causes of transient Voltages and electrical surges.
Poorly designed or improperly implemented grounding, bonding, and shielding techniques often adversely affect the
performance of electronic equipment, from the circuit board level all the way up to and including the overall network
system. IT budgets can be quickly stressed when the additional cost to maintain and replace damaged equipment is
factored in especially so when maintenance and replacement is due to an easily preventable cause such as
improper grounding and bonding. Moreover, personal injury from electric shock due to lack of grounding and bonding
systems or inappropriately deployed grounding and bonding can cause both immeasurable suffering and significant
expense.
The Importance of Standards
Proper grounding and bonding is essential to minimize or eliminate the detrimental effects of transient Voltages and
electrical surges. Industry standards such as J-STD-607-A, TIA-942, and IEEE Std 1100TM-2005 (The Emerald
Book) guide the design and deployment of grounding and bonding systems. Use of UL Listed or CSA Certified
products ensures the long term reliability and safety of those products.
-
8/7/2019 TCG G&B Sample Assessment
15/27
Grounding & Bonding Assessment Sample Report Confidential Information
15
According to these standards, reliable and effective grounding and bonding systems have the following general
characteristics:
1. Intentional design each connection must be engineered and installed to properly handle the
anticipated surge currents.
2. Bonds all metallic components to the grounding system (e.g., equipment, racks, cabinets, access floors,
ladder racks, cable trays, water pipes, electrical conduit, building steel, etc.).3. Visually verifiable and generally arranged for ease of inspection and testing.
4. Provides equalization paths and ports for ESD protection wrist straps.
5. Supports the proper operation of surge protection devices for equipment and power circuits.
6. Promotes electromagnetic compatibility (EMC) with the telecommunications closet, entrance facility, or
data center environment.
7. Adheres to all local electrical codes and utilizes components listed with a nationally recognized test lab
(such as Underwriters Laboratories, Inc., or similar).
Complete System BondingIn addition to the above items, the telecommunications bonding and grounding standards make the following specific
recommendations to ensure that complete system bonding is observed over the entire network:
1. Create electrical continuity throughout the rack or cabinet.
2. Bond equipment and patch panels to the racks or cabinets.
3. Deploy copper telecommunications grounding busbars (TGBs) in each telecommunications room (sized
thick x 2 high x variable length) and copper telecommunications main grounding busbars (TMGBs)
in the telecommunications entrance facility (sized thick x 4 high x variable length).
4. Each busbar is drilled with rows of holes according to J-STD-607-A for attachment of bolted
compression fittings and should be installed with insulated standoffs. All connections to busbars should
be made with two-hole compression lugs mounted with stainless steel hardware and Belleville washers.5. Bond each rack or cabinet to a telecommunications grounding busbar (TGB). This may be done via a
conductor known as a telecommunication equipment bonding conductor (TEBC) typically deployed in a
telecommunications closet of via a mesh common bonding network (MCBN) commonly found in
computer rooms and data centers.
6. Bond each telecommunications grounding busbar (TGB) to the AC service panel serving the active
equipment in the telecommunications space or room. Such bonding promotes equalized ground
potential between the power system(s) serving the equipment and the equipment itself.
7. Connect telecommunications grounding busbars (TBGs) with a backbone of insulated solid copper
cable between all telecommunications space and/or rooms. Minimum size requirement is #6 AWG;
#3/0 AWG is required by J-STD-607-A for distances of 20m or more. Connect this backbone to the
telecommunications main grounding busbar (TMGB) in the telecommunications entrance facility, to an
earth ground in the electrical service entrance facility, and to structural steel on each floor of the facility.
8. Deploy proper grounding and bonding elements (e.g., clear covers, ID labeling, green color-coded
conductors, etc.) to aid in visual verification of the system.
-
8/7/2019 TCG G&B Sample Assessment
16/27
Grounding & Bonding Assessment Sample Report Confidential Information
16
Recommendations Summary
To bring TECHCO Incorporateds Main and West Side, San Francisco, CA, telecommunications bonding networks
into conformance with industry standards and best practices, we recommend each room be retrofitted using UL-
Listed products to meet J-STD-607-A, TIA-942, and IEEE Std 1100TM-2005 requirement. For racks and cabinets,
this translates to providing a dedicated bonding system comprised of dedicated bonding network jumpers, busbars,
and paint-piercing hardware. Each piece of active equipment should then be attached to this bonding system via
equipment bonding jumpers and bonding hardware. More specific recommendations for each of these areas the
telecommunications rooms, racks, and active equipment are detailed below.
Detailed Recommendations: Telecommunications Rooms
Where deployed, the majority of TECHCOs sites currently use single-hole mechanical lugs to make connections with
the telecommunications grounding busbar (TGB). These connectors can easily become loose, leading to faults in the
grounding system. In addition, verification of the integrity of these types of connections requires physically touching
and inspecting them. The single-hole mechanical lugs should be replaced with two-hole compression lugs to ensure
a secure, durable, and low-impedance connection with the telecommunications bonding. All non-compliant
telecommunications grounding busbars (as found in the Main MPOE room, Main Exp. IDF room, and West Side IDF
room) should be replaced with solid copper telecommunications grounding busbars (TGBs) that are 1/4 thick by 2
high uncoated and unpainted copper. Rooms without a telecommunications grounding busbar (Main Server room
and Main IDF other server room) should have a TGB should be installed per industry best practice. These TGBs
must feature rows of holes drilled to NEMA standards. See below illustration for best-practice installation.
Figure 6: Best practice layout and installation for Telecommunications Room bonding network
-
8/7/2019 TCG G&B Sample Assessment
17/27
Grounding & Bonding Assessment Sample Report Confidential Information
17
The bonding system should be connected with suitable wiring that is consistently sized, terminated, and visually
verifiable to ensure safety and ease of management. Industry standards recommend green or green-with-yellow-
stripe cable jacketing. Additionally, all bonding and grounding connections should be labeled and tagged at both
ends for clear identification and network continuity verification (traceability).
All telecommunications grounding busbars (TGBs) should then be grounded to the Telecommunications Main
Grounding Busbar (TMGB). The TMGB itself should be bonded to uncoated and unpainted building steel andgrounded to the electrical service ground according to J-STD-607-A guidelines. Each TGB within each room should
be bonded to uncoated and unpainted building steel and to the electrical panel serving equipment in the room.
The gauge of the connecting ground/earth cable, known as the Telecommunications Bonding Backbone (TBB) should
follow J-STD-607-A guidelines, as outlined in the table below.
Sizing of the Telecommunications Bonding Backbone (TBB)
TBB Length in Linear meters (feet) TBB Size (AWG)
Less than 4m (13 ft) #6 AWG
4m 6m (14 20) #4 AWG
6-8 (21-26) #3 AWG
8-10 (27-33) #2 AWG
10-13 (34-41) #1 AWG
13-16 (42-52) #1/0 AWG
16-20 (53-66) #2/0 AWG
Greater than 20 (66) #3/0 AWG
The Telecommunications Bonding Backbone should be routed to each Telecommunications Grounding Busbar in asstraight a path as possible. The TBB should be installed as a continuous conductor, avoiding splices where possible.
As a final note, any metallic component that is part of the telecommunications space, computer room, or data center,
including all electronic equipment, racks, cabinets, ladder racks, enclosures, and cable trays, etc., must be properly
connected to the telecommunications bonding system.
-
8/7/2019 TCG G&B Sample Assessment
18/27
Grounding & Bonding Assessment Sample Report Confidential Information
18
Detailed Recommendations: Racks and Cabinets
TECHCO Incorporated should install rack-level bonding busbars on all of their equipment racks and ensure that they
are connected directly to the telecommunications bonding network. In addition, they should ensure that all of the
racks are properly bonded using paint-piercing grounding washers. Best practice deployments for cabinet and racktelecommunications bonding networks are shown in Figure 7, below. Site-by-site recommendations for migrating to
best-practice installation of the telecommunications bonding network can be found in Appendix A.
For the Main and West Side rooms, a Retrofit Cabinet Grounding Kit can be used to ensure proper grounding. The
Retrofit Cabinet Grounding Kit includes a copper busbar that acts as the main collection point before connecting to
the Telecommunications Bonding Network. The busbar can be mounted at the top or the bottom of each rack
depending on the location of the room-level Telecommunications Grounding Busbar. All equipment in the rack
should then be grounded to the busbar using equipment-grounding jumpers as described in Detailed
Recommendations: Active Equipment.
The rack-level busbar should then be connected to the telecommunications bonding network utilizing a common
bonding network jumper. PANDUITs retrofit kit includes a #6 AWG cable with one factory installed two-hole
compression lug and hardware to connect to the busbar and one HTAP to connect to the Telecommunications
Bonding Network.
Figure 7: Best practice deployment of telecommunications bonding network for cabinets and open racks
-
8/7/2019 TCG G&B Sample Assessment
19/27
Grounding & Bonding Assessment Sample Report Confidential Information
19
In addition to grounding the racks and cabinets, electrostatic discharge (ESD) ports should be mounted on the back
of every rack and cabinet and also on the front of every cabinet. These ESD ports should be mounted at
approximately 48 inches from the floor on both the front and the back of the racks and cabinets. The ESD ports
should be connected directly to the rack or cabinet rail and should be clearly labeled with protection identification
stickers directly above the ESD ports.
Figure 8: Best practice deployment of Retrofit Cabinet or Rack Grounding Busbar. Note use of two-holecompression lug, mounting holes per NEMA standards, and paint-piercing mounting hardware
Figure 9: Best practice deployment for connecting rack or cabinet common bonding network jumper toTelecommunications Bonding Backbone or Mesh Common Bonding Network via the use of HTAP
-
8/7/2019 TCG G&B Sample Assessment
20/27
Grounding & Bonding Assessment Sample Report Confidential Information
20
Detailed Recommendations: Active Equipment
All active equipment such as switches, routers, servers, etc., should be bonded to the equipment racks per
manufacturers installation instructions. Grounding of the active equipment is critical as stated by the J-STD-607-A
standard:
Grounding through the equipmentAC (alternating current) power cord does not meet the intent of thisstandard. It is intended that the AC power ground path and the telecommunications ground path offer
redundant and specific ground paths for the equipment. While the AC-powered equipment typically has
a power cord that contains a ground wire, the integrity of this path to ground cannot be easily verified.
Rather than relying on the AC power cord ground wire, it is desirable that equipment be grounded in a
verifiable manner as described in this Standard.
The best strategy to meet the intent of this statement is to use a discreet jumper wire that bonds from a lug mounting
pad (if provided by the manufacturer) on the active equipment and terminates via a two-hole compression lug at a
rack-level busbar. The busbar is then used to provide a visually verifiable, all-copper grounding path.
When equipment does not provide a lug mounting pad, the next best option is to bond the equipment mounting
flanges directly to the rack rails. If the equipment mounting flanges are painted or covered in a non-conductive
coating, bonding screws can be used to make this bond (i.e., thread-forming screws with serrations under the head of
the screw will remove coatings from the surface to which they are mounted).
All active equipment in TECHCOs facilities should be retrofitted with grounding jumpers that are connected with
thread forming screws to the rack rail.
Figure 10: Best practice deployment of telecommunications bonding for active equipment. Note use ofequipment bonding jumpers featuring two-hole compression lugs (left image) and paint-piercingequipment mounting screws (right image)
-
8/7/2019 TCG G&B Sample Assessment
21/27
Grounding & Bonding Assessment Sample Report Confidential Information
21
Conclusions
An overview of observed telecommunications bonding systems determined that best practices are minimally in use
within TECHCO Incorporateds Main and West Side facilities and that significant remediation work will be required to
bring all rooms into compliance with industry standards and best practices. 62% of evaluated areas have no bonding
system whatsoever while the remaining 38% of evaluated areas are in partial compliance with telecommunications
bonding standards as a result of either incomplete telecommunications bonding networks or improperly deployed
systems and components.
To bring all of the Main and West Side facilities telecommunications bonding systems into alignment with industry
standards and best practices, the following remediation should be performed:
Each room: Deploy a telecommunications bonding solution that meets J-STD-607-A, TIA-942, and IEEE Std
1100TM-2005 (The Emerald Book) requirements and utilizes UL-Listed or CSA-Certified products.
Equipment Racks: Provide a dedicated grounding and bonding system comprised of purpose-built components
(rack-level bonding busbar, paint-piercing hardware, lugs, ground conductors, etc.) which are engineered to
comply with US and International grounding requirements.
Active Equipment: Bond each piece of active network equipment to a grounding bus bar installed in
compliance with US and International grounding requirements
It is possible to retrofit and remediate existing installations at TECHCO s site by deploying the appropriate
telecommunications bonding network systems and components. To this end, Panduit Global Professional Services
recommends taking the following actions and next steps:
Remediation planning: Develop a detailed remediation plan and inventory of remediation steps and associated
Bill-of-Materials for each site.
Installation: Install and/or retrofit all telecommunications bonding system components as identified in the
Remediation Plan. All installation work should performed by a PANDUIT Certified Installer (PCI).
Validation: Verify proper installation of telecommunications bonding networks and components to ensurequality-of-work and compliance with industry standards and best practices. All verification work should be
performed by personnel certified by Panduit Global Professional Services.
-
8/7/2019 TCG G&B Sample Assessment
22/27
Grounding & Bonding Assessment Sample Report Confidential Information
22
Appendix A: Room-by-Room Analysis Main Server Room
Room Layout
P1 P2
-
8/7/2019 TCG G&B Sample Assessment
23/27
Grounding & Bonding Assessment Sample Report Confidential Information
23
Appendix A: Room-by-Room Analysis Main Server Room
P3 P4
P5 P6
P7 P8
-
8/7/2019 TCG G&B Sample Assessment
24/27
Grounding & Bonding Assessment Sample Report Confidential Information
24
Appendix A: Room-by-Room Analysis Main Server Room
P9 P10
P11 P12
P13 P14
-
8/7/2019 TCG G&B Sample Assessment
25/27
Grounding & Bonding Assessment Sample Report Confidential Information
25
Appendix A: Room-by-Room Analysis Main Server Room
P15 P16
P17 P18
P19
-
8/7/2019 TCG G&B Sample Assessment
26/27
Grounding & Bonding Assessment Sample Report Confidential Information
26
Appendix A: Room-by-Room Analysis Main Server Room
Room Number / Rack Number: Bay 1 Server Room
Room Type / Rack Type: Telco Room
# Initial State Notes
Remediated
State Notes
1 N/A No room-level busbar
present
2 N/A No room-level busbar
present
3 N/A No room-level busbar
present
4 N/A No room-level busbar
present
5 N/A No room-level busbar
present
6 N/A No room-level busbar
present
7 N/A No room-level busbar
present
8 N/A No room-level busbar
present
9 N/A No shielded data cables
in use
Shielded Data Cable related itemsIs the potential bewteen the jack
module and power grounding