Task Order 2 End States Cleanup Work - Energy.gov...Task Order 2: End States Cleanup Work Subtask #...
Transcript of Task Order 2 End States Cleanup Work - Energy.gov...Task Order 2: End States Cleanup Work Subtask #...
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
i
Task Order 2 – End States Cleanup Work
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
ii
This page intentionally left blank.
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
iii
Table of Contents
Section A – Solicitation/Contract Form .........................................................................................
Section B – Supplies or Services and Prices/Costs ....................................................................... 1
Section C – Performance Work Statement .................................................................................. 2
Section D – Packaging and Marking .......................................................................................... 14
Section E – Inspection and Acceptance ...................................................................................... 14
Section F – Deliveries or Performance ....................................................................................... 14
Section G – Contract Administration Data ................................................................................ 14
Section H – Special Contract Requirements .............................................................................. 14
Section I – Contract Clauses ........................................................................................................ 14
Section J – List of Documents, Exhibits, and Other Attachments ........................................... 15
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
iv
This page intentionally left blank.
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
1
Section B - Supplies or Services and Prices/Costs
This Task Order work shall be performed under Contract Line Item Number (CLIN) 00001 of the
Hanford Central Plateau Cleanup Contract (CPCC) Master Indefinite Delivery/Indefinite Quantity (IDIQ)
Contract (herein referred to as the Master IDIQ Contract). Section B of the Master IDIQ Contract is
incorporated by reference, and is revised for purposes of this Task Order with the information below
specifically identified for this task.
B.1 DOE-B-2012 Supplies/Services Being Procured/Delivery Requirements (Oct 2014)
The Contractor shall furnish all personnel, facilities, equipment, material, supplies, and services
(except as may be expressly set forth in this Task Order as furnished by the Government) and otherwise
do all things necessary for, or incident to, the performance of work as described in Section C,
Performance Work Statement (PWS) under this Task Order.
B.2 DOE-B-2003 Cost-Plus-Incentive-Fee Task Order: Total Estimated Cost and Incentive Fee
(OCT 2014)
(a) This is a Cost-Plus-Incentive-Fee Task Order. In accordance with the Clause at FAR 52.216-10,
Incentive Fee, the target cost, target fee, maximum and minimum fees, and the target fee increase
and decrease ratios for this Contract are shown in Table B-1.
Table B-1. Target Cost and Fee Information
Target Cost [$proposed]
Target Fee [$proposed]
Maximum Fee 15%
Minimum Fee 0%
Target Fee Increase Ratio: 30 Cents/Dollar Less Than Target Cost
Target Fee Decrease Ratio: 30 Cents/Dollar More Than Target Cost
(b) The target cost, target fee, minimum and maximum fee, and target fee increase/decrease ratios are
applicable to the following CLIN. The Target Cost does not include the estimated cost associated
with Usage Based Services (UBS) provided by Other Hanford Contractors (OHC), which is non-fee
bearing.
(c) The Task Order CLIN structure is shown in Table B-2.
Table B-2. Task Order CLIN Structure
CLIN CLIN Title CLIN Type Target Cost + UBS Cost Target Fee Total
00001
End States Cleanup
Work
CPIF [$proposed] [$proposed] [$proposed]
UBS provided by OHCs CR [$proposed] N/A [$proposed]
Total [$Proposed] [$Proposed] [$Proposed]
CLIN = Contract Line Item Number CPIF = Cost Plus Incentive Fee
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
2
(d) CLIN 00001 – End States Cleanup Work:
This CLIN includes the target cost and fee associated with performing the End States identified
within the Task Order PWS.
This CLIN also includes UBSs provided by OHCs, which includes the estimated costs (no fee)
associated with reimbursing OHCs for services provided to CPCC listed within the Master IDIQ
Contract Section J, Attachment J-3, Hanford Site Services and Interface Requirements Matrix.
The costs within this CLIN does not include general administration and management cost for Core
Functions associated with administering this CLIN. The estimated costs for Core Functions to
perform the general administration and management of this CLIN is included within Task
Order 3 – Core Functions.
(e) Payment of target fee shall be made in accordance with the Clause FAR 52.216-10, Incentive Fee,
and the Payments clauses in the Master IDIQ Contract applicable to this Task Order.
The final fee calculation includes a reconciliation of the actual UBSs provided by OHCs at the end of
the Task Order for CLIN 00001, End States Cleanup Work. If there are any differences between the
actual UBS costs in relation to the UBS negotiated cost, an adjustment will be made to the target cost
and fee to reflect the change to services utilized.
B.3 DOE-B-2013 Obligation of Funds (Oct 2014)
(a) Pursuant to the Clause of this Contract in FAR 52.232-22, Limitation of Funds, total funds in the
amount(s) specified below are obligated for the payment of allowable costs and fee. It is estimated
that this amount is sufficient to cover performance through the date(s) shown below.
(b) TBD at Task Order award.
Section C - Performance Work Statement
C.1 Task Order Purpose and Overview
This task is to be performed for the U.S. Department of Energy (DOE) Richland Operations Office (RL)
Central Plateau Cleanup, located on the Hanford Site north of Richland, Washington. The purpose of this
Task Order is to describe the end states-related cleanup work scope to be performed during the period of
performance identified in this Task Order.
C.2 Scope of Work
Table C-1. Listing of Task-Specific Scope
Task Order 2: End States Cleanup Work
Subtask
# Subtask Title
Related Master
IDIQ PWS
Section CWBS Reference
1 Continuation of the characterization and
deactivation of the 105-KW Basin in the 100-K
Area
C.2.2 RL-0041.02;
RL-0041.02.23.21
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
3
Table C-1. Listing of Task-Specific Scope
Task Order 2: End States Cleanup Work
Subtask
# Subtask Title
Related Master
IDIQ PWS
Section CWBS Reference
2 Continued D4 of the 100-K structures and the
remediation of the 100-K soil waste sites
C.2.2 RL-0041.02;
RL-0041.02.23.21
3 Initiate and complete the remote excavation of the
highly contaminated portion of the 300-296 waste
site under the 324 Building in the 300 Area
C.2.3 RL-0041.02.25.21
4 Strategy to Accelerate Completion of Groundwater
Remediation in the River Corridor Groundwater
Operable Units
C.3.2 RL-0030 and all
associated sub-elements
5 Obtain Decision Documents for the River Corridor
operable units
C.5.5 RL-0041.02;
RL-0030.11 and all
associated sub-
elements;
RL-0030.12 and all
associated sub-
elements;
RL-0030.10 and all
associate sub-elements
* The CWBS Reference(s) for the Subtasks can be found in the EMCBC Document Library.
CWBS = Contract Work Breakdown Structure
D4 = Deactivation, Decontamination, Decommission,
and Demolition
EMCBC = Environmental Management Consolidated
Business Center
IDIQ = Indefinite Delivery/Indefinite Quantity
Task: End States Cleanup Work Scope
The following elements of the Task Order (Subtasks 1 through 5) contain work scope that shall be
performed by the Contractor during this Task Order’s period of performance.
Authorized Disposition Activities
In performing the Subtasks 1, 2, and 3 associated with this Task Order, the Contractor shall adhere to the
following associated authorized disposition activities associated with these Subtasks, which are described
below:
The Contractor shall prepare and submit all Operable Unit (OU) regulatory and other documentation
required to cleanup, closeout, and support transition of the associated Implementation Area (IA) to
Long-Term Stewardship.
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
4
In addition, the Contractor shall:
Keep up to date all Remedial Action Work Plans (RAWP), Remedial Design/RAWPs, air monitoring
plans, closure plans, and any other required regulatory documentation and submit revisions for
approval by DOE Richland Operations Office (RL) and its regulators.
Remove Underground Injection Control units associated with or in the vicinity of facilities, document
closure, and submit in accordance with WAC 173-218, Underground Injection Control Program.
Formally submit closure documentation to DOE-RL.
Complete disposition of all mobile offices from within the IA.
Complete miscellaneous restoration, which includes removal of all aboveground utility structures and
components no longer in use, removal of all surplus Conex boxes, fencing and debris, restoration of
the landscape through backfill and grading to match the natural contours of the area, restoration of
positive drainage, and re-establishment of native vegetation.
Prepare documentation and otherwise support DOE in obtaining a Certificate of Completion upon
satisfactory completion of the remedial action phase for a given OU. At the discretion of the lead
regulatory agency, a certificate shall be issued for completion of the remedial action phase for an OU
in accordance with Section 7.3.10 of the Tri-Party Agreement (TPA).
Project Management and Support
The Contractor shall include the project management support work scope activities (these activities are
additional to those in Task Order 3 – Core Functions. Costs in this Task Order shall follow the Offeror’s
management plan and are not duplicate costs in Task Order 3) for each of the cleanup work-related
subtasks in this Task Order including additional project management staff, safety basis, infrastructure, and
equipment required to support the safe and orderly performance of work scope.
Integration with Safe and Compliant Base Operations
In the performance of the subtasks associated with this Task Order, the Contractor shall perform the
activities necessary to manage the integration of this scope with the scope for performing safe and
compliant base operations.
UBS from OHCs and Non-Fee Bearing costs
The Contractor shall include the estimated costs (no fee) associated with reimbursing OHCs for services
provided to CPCC listed within Section J, Attachment J-3, Hanford Site Services and Interface
Requirements Matrix. These costs shall be included in each subtask below (showing quantity and costs),
but not included in the targeted fee calculation. All of the UBSs from OHCs and non-fee bearing costs
will be identified in the proposal and Offeror shall provide the backup of how the targeted fee calculation
was calculated removing these costs. The UBS and non-fee bearing costs apply to the work scope
identified in this Task Order.
C.2.1 SubTask 1 - Continuation of the characterization and deactivation of the 105-KW Basin in
the 100-K Area
The Contractor shall complete the following activities associated with continuing the basin
characterization and deactivation:
Install garnet filter media removal equipment, complete readiness assessment, and complete garnet
filter media removal.
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
5
Train for and complete sand filter media removal equipment installation and operations training.
Train for and initiate underwater debris size reduction and staging.
C.2.2 SubTask 2 - Continued Deactivation, Decontamination, Decommission, and Demolition (D4)
of the remaining 100-K structures and the remediation of the remaining 100-K soil waste sites
The Contractor shall continue completion of the D4 of the remaining 100-K structures and the
remediation of the remaining waste sites in accordance with the existing Interim Action Record of
Decision (ROD) and the Remedial Design/Remedial Action Work Plans (RD/RAWP) for both removal
actions and remedial actions.
The Contractor shall complete the following D4 activity at 100-K Area including removal of associated
aboveground and underground structures and systems:
Complete demolition of the 165KE Power House.
Initiate and complete demolition preparation activities for 165KW Power House.
In addition, the Contractor shall complete the following waste site remediation activities at 100-K Area:
Continue and complete waste site 130-KE-2 (includes 166KE) remediation and close-out
documentation.
Continue and complete remediation and close-out documentation of waste sites 120-KE-8, 100-K-48,
and 100-K-104 (sites adjacent to 130-KE-2).
Complete waste site remediation, to include completion of excavation and closure sampling, for
100-K-55:2, 100-K-56:3 and 100-K-79:6.
C.2.3 SubTask 3 - Initiate and complete the remote excavation of the highly contaminated portion
of the soils in the 300-296 waste site under the 324 Building in the 300 Area
The Contractor shall initiate and complete the remote excavation of the highly contaminated portion of
the soils in the 300-296 waste site, so that in the future, the remainder of the waste site can be remediated
under open air conditions following completion of the 324 Building demolition.
The Contractor shall complete the remote excavation activities as follows:
Remove B-Cell floor.
Complete remote excavation of the high-hazard soils at the 300-296 waste site beneath the
324 Building in accordance with requirements defined in PRC-SRP-00130, Rev. 0, End State Criteria
for Meeting TPA Milestone M-016-85A and Gaining Backfill Concurrence Authorization for B Cell in
Preparation of 324 Facility Demolition and Final Remediation of the 300-296 Waste Site.
C.2.4 SubTask 4 - Strategy to Accelerate Completion of Groundwater Remediation in the River
Corridor Groundwater Operable Units
The Contractor shall develop a treatment strategy that includes a technical approach that achieves
accelerated completion of groundwater remediation, to support initiation of remedy performance
evaluation, for the groundwater operable units in the River Corridor.
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
6
C.2.5 SubTask 5 - Obtain Decision Documents for the River Corridor operable units
The Contractor shall maintain consistency with the information provided in Section C.5 (Resource
Conservation and Recovery Act [RCRA]/Comprehensive Environmental Response, Compensation, and
Liability Act [CERCLA] Decision Documents) in the Master IDIQ Contract. The work to be
accomplished under this subtask is for the Contractor to complete the following documents:
Obtain a final DOE and regulator-approved CERCLA Record of Decision (ROD) for the 100-K Area
Obtain a final DOE and Regulator approved Remedial Investigation/Feasibility Study [RI/FS] and
Proposed Plan for the 100-N Area
Obtain a final DOE and Regulator approved RD/RAWP for the 100-BC Area
C.3 Performance Requirements
Performance Measure – A statement of the outcome or results expected in a specific work area.
Performance Measure Description/Completion Criteria – The critical characteristics or aspects of
achieving the performance measure that will be monitored by the Government and for which the
Government will gather data.
The following performance measures (Table C-2) apply to this End States Cleanup Work Task Order.
Table C-2. Fiscal Year 2020 Performance Measures
SubTask
Number
Performance
Measure Identifier Performance Measure Description/Completion Criteria
1 PM-41-1-20 Complete garnet filter media
removal operations at 105-KW
Basin
Complete removal of all garnet filter
media from garnet filter in the 105-KW
Basin and put into Sludge Transport and
Storage Containers (STSCs). Ship to
T-Plant for storage by September 30,
2020.
2 PM-41-2-20 Complete demolition and
load-out of the 165KE Power
House in the 100 K Area
Complete demolition, load-out, closure
sampling, and close-out in accordance
with and meeting the RAWP
requirements. Complete and submit a
FSCF by September 30, 2020.
3 PM-41-3-20 Complete remote excavation of
the high hazard soils at the
300-296 waste site beneath the
324 Building in the 300 Area
Complete the remote excavation of the
highly contaminated portion of the soils
in the 300-296 waste site, thereby,
completing M-016-85A based on
requirements defined in PRC-SRP-00130,
Rev 0. by September 30, 2020.
4 PM-30-1-20 River Corridor Groundwater
Remediation
Complete the development of the
strategy, including an implementation
schedule, to accelerate groundwater
remediation to support initiation of
remedy performance evaluation in the
River Corridor groundwater operable
units by July 30, 2020.
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
7
Table C-2. Fiscal Year 2020 Performance Measures
SubTask
Number
Performance
Measure Identifier Performance Measure Description/Completion Criteria
5 PM-30-2-20 Obtain Decision Documents for
the River Corridor
Complete final DOE and Regulator
approved RD/RAWP for the 100-BC
Area by March 30, 2020.
Complete final DOE and regulator-
approved CERCLA ROD for 100-K Area
by September 30, 2020.
Complete final DOE and regulator
approved RI/FS Report and Proposed
Plan for the 100-N Area by September
30, 2020.
CERCLA = Comprehensive Environmental Response,
Compensation, and Liability Act
DOE = U.S. Department of Energy
FSCF = Facility Status Change Form
RAWP = Removal Action Work Plan
RD = Remedial Design
RI/FS = Remedial Investigation/Feasibility Study
ROD = Record of Decision
C.4 Additional Supplemental Scope Information
The Supplemental Information in Table C-3 below provides additional required information to be used for
defining the scope of work performed under this Task Order.
Table C-3. Supplemental Information
Subtask Number Work Scope Supplemental Information
1 Install garnet filter media removal
equipment, complete readiness assessment,
and complete garnet filter media removal
1. All equipment fabrication and
procurement for the garnet filter media
removal systems will have been
completed by the incumbent contractor.
2. Sludge removal operations are complete.
3. The training requirements for garnet
filter media removal operations need to
be developed.
4. The garnet filter media removal
equipment installation training will have
been completed by the incumbent
contractor so that equipment will be
ready to install upon sludge removal
completion.
5. The MASF is available for use as a
mockup testing or training facility if
desired.
6. The total volume of garnet filter media
to be removed is 8.8 cubic yards.
Train for and complete sand filter media
removal equipment installation, and
operations training
1. All equipment fabrication and
procurement for the sand filter media
removal systems will have been
completed by the incumbent contractor.
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
8
Table C-3. Supplemental Information
Subtask Number Work Scope Supplemental Information
2. No sand filter media removal operations
are part of this Subtask.
3. The training requirements for the sand
filter media removal system installation
and operations will need to be
developed.
Train and initiate underwater debris size
reduction and staging
1. Characterization and planning for basin
debris removal is complete.
2. There is an estimated 40 tons of debris in
the basin, and not all the debris will be
removed. The amount will depend on the
sum of fractions calculation that will
determine if the grouted basin will meet
ERDF disposal requirements.
3. The work in this Subtask is for size
reduction and staging within the basin
and does not include disposal.
4. All non-TRU will be sent to ERDF.
5. No fuel pieces remain in the basin.
6. No dewatering (i.e. removal and disposal
of the water) will be performed in the
first year.
2 Complete demolition of the 165KE Power
House
1. Demolition preparation activities
complete by the end of FY19.
2. Asbestos abatement is complete.
3. Assume there is not contamination
beneath the building and the building can
be removed to minimum requirements in
the RAWP for 105-KE/ 105-KW Reactor
Facilities and Ancillary Facilities.
Initiate and complete demolition preparation
activities for 165KW Power House
1. Asbestos abatement is complete by the
end of FY19.
2. Demolition preparation activities include:
a. Supervision during Demolition Prep
and Hazards Removal, Asbestos
Removal, Transition to Demolition;
b. Procedure planning and scheduling;
c. Documentation;
d. Deactivate electrical panels and
transformers;
e. Deactivate waterlines;
f. Coordination and supervision of
deactivation;
g. Review of safety issues during
deactivation;
h. Oversight of safety issues during
deactivation;
i. Removal of Asbestos and other
Hazardous materials from building
and equipment; and
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
9
Table C-3. Supplemental Information
Subtask Number Work Scope Supplemental Information
j. Hazmat removal of oil from
equipment.
Continue and complete waste site 130-KE-2
(166KE) remediation and close-out
documentation
1. 130-KE-2 (includes 166KE) the
excavation is complete and liquids are
removed from the tank. The remaining
scope is to remove the tank and any final
excavation required below the tank. Final
sampling, backfill, close-out and
revegetation also remain to be completed.
It is assumed the waste site contamination
did not spread beneath the 165KE and it
can be remediated without impact to the
165KE building walls or floor.
Continue and complete remediation and
close-out documentation of waste sites
120-KE-8, 100-K-48, and 100-K-104
(sites adjacent to 130-KE-2)
1. Excavation is complete and final
sampling, backfill, close-out and
revegetation remain to be completed.
Complete excavation and closure sampling
for 100-K-55:2, 100-K-56:3 and 100-K-79:6
1. The design is complete for all 3 waste
sites.
2. The work to go includes planning and
documentation, excavation, load-out,
backfill, and close-out sampling.
3. This waste remediation work scope has
not started and the Contractor will start
performance from the beginning with no
activities having been accomplished.
3 Remove B-Cell Floor 1. B cell floor scoring started by the end of
FY19 and will be 1% complete.
2. No additional design activity will be
required for completion of the highly
contaminated portion of the 300-296
waste sites remote soil excavation
activity. The Contractor shall use the
existing designs.
3. Equipment installation in 324 Building
REC is complete.
4. Structural modifications are 100%
complete by the end of FY19.
5. Readiness Assessment is complete and
Startup Approval Authority granted
authorization to start soil excavation.
Complete remote excavation of the high
hazard soils at the 300-296 waste site
beneath the 324 Building in accordance with
requirements defined in PRC-SRP-00130,
Rev. 0, End State Criteria for Meeting TPA
Milestone M-016-85A and Gaining Backfill
Concurrence Authorization for B Cell in
Preparation of 324 Facility Demolition and
Final Remediation of the 300-296 Waste
Site
1. No additional design activity will be
required for completion of the highly
contaminated portion of the 300-296
waste sites remote soil excavation
activity.
2. Equipment installation in 324 Building
REC is complete.
3. Structural modifications are complete.
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
10
Table C-3. Supplemental Information
Subtask Number Work Scope Supplemental Information
4. Readiness Assessment is complete and
Startup Approval Authority granted
authorization to start soil excavation.
5. This Subtask includes completing the
backfill of the waste site.
6. The tonnage of waste (includes floor,
liner, and soil) to be removed is 181.8
tons (78.8 BCM), excluding grout to be
added in cells.
7. Waste will be disposed of at ERDF, after
interim placement and grouting in A, C,
and D Cells.
4 Develop a treatment strategy that includes a
technical approach that achieves accelerated
completion of groundwater remediation to
support initiation of remedy performance
evaluation for the groundwater operable
units in the River Corridor
None
5 Obtain a final DOE and regulator-approved
CERCLA ROD for the 100-K Area
1. The 100-K Remedial Investigation and
Feasibility Study are being prepared as
separate documents. At the end of FY
2019, the Remedial Investigation Rev. 0
will be under review by EPA.
2. Assume no work has been performed on
the Feasibility Study by the end of FY19.
3. The Proposed Plan will be started by the
end of FY19 but no formal draft issued.
Obtain a final DOE and Regulator approved
RI/FS and Proposed Plan for the 100-N
Area
1. A draft of the RI/FS Rev. 0 report will be
50% complete by the end of FY19.
Obtain a final DOE and Regulator approved
RD/RAWP for the 100-BC Area
1. 100-BC Area CERCLA ROD issued by
the end of FY19. The Proposed Plan is
complete as part of issuing the ROD.
CERCLA = Comprehensive Environmental Response,
Compensation, and Liability Act
DOE = U.S. Department of Energy
EMCBC = Environmental Management Consolidated
Business Center
ERDF = Environmental Restoration Disposal Facility
FY = Fiscal Year
MASF = Maintenance and Storage Facility
RD/RAWP = Remedial Design/Remedial Action Work Plan
REC = Radiochemical Engineering Cells
RI/FS = Remedial Investigation/Feasibility Study
RH TRU = Remote Handled Transuranic Waste
ROD = Record of Decision
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
11
Table C-4. Building Volume Estimates for Subtask 2
Structure
Title
Above Grade
Construction
Above
Grade
Levels
Above
Grade
Height
(FT)
Below Grade
Construction
Above
Grade
Area
(SQ
FT)
Below
Grade
Levels
Below
Grade
Area
(SQ
FT)
Below
Grade
Depth
(FT)
Tonnage
to ERDF
Piping
Removal
(FT)
Length of
Wall
Removed
(FT)
Backfill
Volume
(CU FT)
165KE -
Power
Control
Building
Concrete
moment frames 1 16
Concrete
moment
frames
26,975 2 34,844 29 7,079 24,400
970
East
basement
wall
remains in
place.
475,200
165KW -
Power
Control
Building
Concrete
moment frames 1 16
Concrete
moment
frames
26,975 2 34,844 29 7,079 24,400
970
East
basement
wall
remains in
place.
475,200
166KE -
Oil
Storage
Vault
Concrete shear
walls 1 8
Concrete
moment
frames
92 1 12,318 27 12,331 50 608 490,875
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
12
Table C-5. Waste Site Volume Estimates for Subtask 2
Structure
Title
Tonnage
to ERDF
Assumed Excavation
Depth (FT) Site Type Area (SQ FT)
Approved
Remedy
Overburden
(CU Yards) Backfill (CU Yards)
130-KE-2
(includes
166KE)
12,331 25’ Storage Tank 19,635
Remove,
treat,
dispose
0 18,180
100-K-48 79 8’ Unplanned
Release 160
Remove,
treat,
dispose
0 47
120-KE-8 478 3’ Unplanned
Release 2,335 Remove, treat,
dispose 0 284
100-K-104 817 16.5’ French Drain 54
Remove,
treat,
dispose
0 605
100-K-55:2 96,871 20’ Radioactive
Process Sewer 170,654
Remove,
treat,
dispose
0 71,744
100-K-56:3 Included in
100-K-55:2
Included in 100-K-
55:2
Radioactive
Process Sewer
Included in 100-
K-55:2
Remove,
treat,
dispose
0 Included in 100-K-
55:2
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
13
100-K-79:6 85,727 40’ Product Piping 182,920
Remove,
treat,
dispose
0 63,490
ERDF = Environmental Restoration Disposal Facility
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
14
Section D - Packaging and Marking
Section D of the Master IDIQ Contract is incorporated by reference.
Section E - Inspection and Acceptance
Section E of the Master IDIQ Contract is incorporated by reference.
Section F - Deliveries or Performance
Section F of the Master IDIQ Contract is incorporated by reference, with the exception of Clause F.1,
which is filled in and provided below.
F.1 Period of Performance
(a) The overall Task Order period of performance shall be for one year from the end of the POP of Task
Order 1 - Transition.
(b) The Contractor shall not be paid for work performed or costs incurred prior to the Task Order
effective date. The Contractor is not authorized to proceed beyond the Task Order period of
performance, nor will the Contractor be paid for any costs incurred beyond that period unless the Task
Order is modified by the CO to extend the period of performance.
Section G - Contract Administration Data
Section G of the Master IDIQ Contract is incorporated by reference.
Section H - Special Contract Requirements
Section H of the Master IDIQ Contract is incorporated by reference.
Section I - Contract Clauses
Section I of the Master IDIQ Contract is incorporated by reference, expect for the following Section I
clause which is filled-in as follows in Table I-1.
Table I-1. Section I Clause Fill-Ins
Clause
No.
FAR/DEAR
Reference Title
Fill-In Information;
See FAR 52.104(d)
I.45 FAR 52.217-8 Option to Extend Services Any time prior to the expiration
of the Task Order
DEAR = Department of Energy Acquisition Regulation FAR = Federal Acquisition Regulation
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
15
Section J - List of Documents, Exhibits, and Other Attachments
Section J of the Master IDIQ Contract is incorporated by reference, as applicable to this Task Order, with
the exception of the following, which are hereby incorporated in this Task Order.
Section J-6 - Separate Small Business Subcontracting Goals
Solicitation Note: The Contractor’s executed Separate Small Business Subcontracting Goals for this Task
Order will be inserted here. See applicable I Clause entitled, FAR 52.219-9, Small Business
Subcontracting Plan, and applicable Section H Clause entitled, Subcontracted Work.
Section J-10 - Contract Deliverables
The following list of End States Cleanup Deliverables is required for this Task Order.
Task Order 2 – End States Cleanup Work Deliverables
Deliverable
Number Deliverable
DOE Deliverable
Due Date
Task Order
Section Action
Response
Time
TO2-0001 Complete and submit a
Facility Status Change Form
for the 165KE Power House
Facility
Approve 30 Days No later than
August 31,
2020
C.2.2, Subtask 2
- Continued D4
of the remaining
100-K structures
and the
remediation of
the remaining
100-K soil waste
sites
TO2-0002 Remaining Sites Verification
Package and Waste Site
Reclassification Form for the
130-KE-2 (166E) waste site
Approve 30 Days No later than
August 31,
2020
C.2.2, Subtask 2
- Continued D4
of the remaining
100-K structures
and the
remediation of
the remaining
100-K soil waste
sites
TO2-0003 Remaining Sites Verification
Package and Waste Site
Reclassification Forms for
120-KE-8, 100-K-48 and
100-K-104 waste sites
Approve 30 Days No later than
August 31,
2020
C.2.2, Subtask 2
- Continued D4
of the remaining
100-K structures
and the
remediation of
the remaining
100-K soil waste
sites
TO2-0004 Verification sampling
showing end state criteria has
been met for 300-296 waste
site
Approve 30 Days No later than
August 31,
2020
C.2.3, Subtask 3
- Initiate and
complete the
remote
excavation of the
highly
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
16
Task Order 2 – End States Cleanup Work Deliverables
Deliverable
Number Deliverable
DOE Deliverable
Due Date
Task Order
Section Action
Response
Time
contaminated
portion of the
soils in the 300-
296 waste site
under the 324
Building in the
300 Area
TO2-0005 Provide decisional draft of
treatment strategy to
accelerate groundwater
remediation for the River
Corridor groundwater
operable units
Review 30 Days January 15,
2020
C.2.4, Subtask 4
- Strategy to
Accelerate
Completion of
Groundwater
Remediation in
the River
Corridor
Groundwater
Operable Units
TO2-0006 Provide final DOE-approved
treatment strategy including
implementation schedule to
accelerate groundwater
remediation for the River
Corridor groundwater
operable units
Approve 60 Days July 30, 2020 C.2.4, Subtask 4
- Strategy to
Accelerate
Completion of
Groundwater
Remediation in
the River
Corridor
Groundwater
Operable Units
TO2-0007 Provide final DOE and
regulator-approved
CERCLA ROD for the 100-
K Area
Approve 30 Days September 30,
2020
C.2.5, Subtask 5
- Obtain
Decision
Documents for
the River
Corridor
operable units
TO2-0008 Provide final DOE and
Regulator approved RI/FS
Report and Proposed Plan for
the 100-N Area
Approve 30 Days September 30,
2020
C.2.5, Subtask 5
- Obtain
Decision
Documents for
the River
Corridor
operable units
TO2-0009 Provide final DOE and
Regulator approved
RD/RAWP for the 100-BC
Area
Approve 30 Days March 30,
2020
C.2.5, Subtask 5
- Obtain
Decision
Documents for
the River
Corridor
operable units
DOE = U.S. Department of Energy
CERCLA = Comprehensive Environmental Response, Compensation, and Liability Act
CENTRAL PLATEAU CLEANUP CONTRACT – FINAL RFP SOLICITATION NO. 89303318REM000008, AMENDMENT 1 – TASK ORDER 2
17
Task Order 2 – End States Cleanup Work Deliverables
Deliverable
Number Deliverable
DOE Deliverable
Due Date
Task Order
Section Action
Response
Time RD/RAWP = Remedial Design/Remedial Action Work Plan
RI/FS = Remedial Investigation/Feasibility Study
ROD = Record of Decision