Task 5 Deliverable: Report on baseline performance for UCSD DER...

67
Task 5 Deliverable: Report on baseline performance for UCSD DER operation under current rates and incentives Submitted August 13, 2012 A California Solar Initiative (CSI) Research, Development, Demonstration, and Deployment Program Grant Supported by the California Public Utilities Commission (CPUC) and managed by Itron, Inc. Grant Title: Innovative Business Models, Rates and Incentives that Promote Integration of High Penetration PV with Real-Time Management of Customer Sited Distributed Energy Resources.

Transcript of Task 5 Deliverable: Report on baseline performance for UCSD DER...

Page 1: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Task 5 Deliverable: Report on baseline performance for UCSD DER operation under current rates and incentives Submitted August 13, 2012 A California Solar Initiative (CSI) Research, Development, Demonstration, and Deployment Program Grant Supported by the California Public Utilities Commission (CPUC) and managed by Itron, Inc. Grant Title: Innovative Business Models, Rates and Incentives that Promote Integration of High Penetration PV with Real-Time Management of Customer Sited Distributed Energy Resources.

Page 2: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Task 5: Establish baseline performance for UCSD DER operation under current rates and incentives A report in partial fulfillment of a California Solar Initiative (CSI) Grant requirement

Eric Cutter, Senior Consultant & CSI Grant Project Manager

Priya Sreedharan, Senior Consultant, PhD, PE Jamil Farbes, Consultant

Andrew DeBenedictis, Senior Associate Gabe Kwok, Associate

Page 3: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Table of contents

Overview of UCSD resources … Slide 4

Baselining methodology … Slide 11

Historical operations … Slide 18

• Campus needs, annual loads, and central plant efficiency … Slide 19

• Understanding daily operations … Slide 25

• Output and efficiency of individual systems … Slide 31

• Summary of historical operations … Slide 39

Understanding campus needs … Slide 40

• Monthly and yearly analysis … Slide 42

• Analysis of day type effects … Slide 50

Preliminary business analysis … Slide 56

Further research and next steps … Slide 63

Page 4: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Glossary

CHP: combined heat and power

CHW: chilled water

CUP: central utility plant

HTW: hot water

HX: heat exchanger

Gens: generators

TES: thermal energy storage

UCSD: University of California, San Diego

WC: denotes a chiller at the Central Utility Plant (either electric or steam)

Page 5: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

OVERVIEW OF UCSD RESOURCES

Page 6: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

UCSD microgrid

With a daily population of over 45,000, UC San Diego is the size and complexity of a small city.

11 million sq. ft. of buildings, $250M/yr of building growth

UC San Diego operates a 42 MW microgrid

UC San Diego grid imports 2007

Self generate ~ 90% of annual demand •30 MW natural gas Cogen plant •2.8 MW of Fuel Cells in operation •1.2 MW of Solar PV installed, additional 2 MW planned •Twice the energy density of commercial buildings

Page 7: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Central plant resources

The central plant is rich with dispatchable resources

• Two 13 MW natural gas generators

• One 3 MW steam generator

• Three Steam driven chillers (~ 10,000 tons capacity)

• Five electric driven chillers (~ 7800 tons capacity)

• 3.8 million gal thermal storage tank

• Backup diesel generation

> 1 MW of solar PV

~ 1.4 MW of DR-ready reducible building load

Visibility at the building level

Chilled water tank at UCSD campus

Page 8: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

UCSD’s cogeneration system

The UCSD cogeneration system has the following

• Natural gas turbines generate electricity for onsite use & steam

• Steam is used to generate hot water, more electricity (steam turbine) and chilled water (steam-driven chillers)

• Cogeneration offsets imported electricity, boiler fuel use for generating hot water & chilled water, and electricity consumption required to generate chilled water

Steam chiller at UCSD campus

Cogeneration is a core component of UCSD’s microgrid

Page 9: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Flexibility of the UCSD resources

UCSD resources can shift load, reduce load and move load between gas and electricity fuels

• Natural gas generators produce electricity and steam; once on, they have a controllable range of up to ~ 6 MW

• Tank can deliver significant portion of campus chilled water needs and can be variably charged/discharged

• Steam from generators can be used to generate hot water, chilled water and additional electricity in varying amounts

• Building load can be reduced ~ 1.4 MW for DR events

Page 10: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

UCSD online energy dashboard

Source: http://energy.ucsd.edu/campus/campus.php

Page 11: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Example of renewables integration using UCSD DER’s

Hypothetical load following scenario using UCSD actual data for 6/7/2011

• Generators are ramped up and down within their acceptable operating range throughout the day

0

5

10

15

20

25

30

35

40

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

MW

Hour

ImportsGenerators' output with load followingCampus total consumptionNormal generators' output

Page 12: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

BASELINING METHODOLOGY

Page 13: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Review of baselining effort

Overall goals for baselining

• Understanding how flexible the resources are and to what extent they can be leveraged to support more solar and renewables

• Understanding thermal & electrical campus needs

• Quantify efficiencies & understand operating strategies

• Identify opportunities for operational improvement

• Validate / calibrate VPower to ensure tool generates plausible operational strategies

Key questions

• How do the campus needs vary by hour, season, month?

• What are the overall system efficiencies (CHP, steam utilization) and equipment-level efficiencies (chillers, generators, etc.)?

• What are the regular modes of operation of each system?

• How much capacity is available for changing operations?

Page 14: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

UCSD data resources

Baselining data obtained from multiple sources:

• MSCADA system: 15-minute power data

• Johnson Control Metasys System: thermal storage tank data

• ‘BOP’ System: steam data for boilers, generators

• ‘Efftrack’ chiller diagnostic system: chiller data

• Daily central plant logs: gas usage

• UCSD expert knowledge (i.e., John Dilliott, Energy Manager)

• Solar data from Prof. Jan Kleissl

Future: disparate data sources have been integrated into a campus-wide data historian

Page 15: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Analytical framework

Inputs Outputs

Nat gas

Diesel

Import kW

Solar PV

Boilers

NG gens

Backup gens

Steam

Steam

KW

St gen

HX’s

Stm chs

Elec chs

Aux eqp

KW

HW

CHW

Heating: space, water, process

Cooling

Non CUP HVAC

Lighting

Plug loads

Non central heating

TES

Baseline data gives input / output relationships, equipment efficiency, capacity factors, seasonal and diurnal patterns of usage, historical costs.

Import + gen

Central Utility Plant End Use

Page 16: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Analytical framework

Inputs Outputs

Nat gas

Diesel

Import kW

Solar PV

Boilers

NG gens

Backup gens

Steam

Steam

KW

St gen

HX’s

Stm chs

Elec chs

Aux eqp

KW

HW

CHW

Heating: space, water, process

Cooling

Non CUP HVAC

Lighting

Plug loads

Non central heating

TES Import + gen

Central Utility Plant End Use Denotes resources scheduled by VPower optimization.

Note: VPower also models JCI interruptible load & hot water strategy.

Services that VPower will treat as constant: CUP CHW, CUP HW, kW net CUP electric chillers

Page 17: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Methodology steps

Collect data

• Electrical data: Imports, central plant generators, chillers, auxiliary, solar

• Thermal data: Chillers, boilers (partial), campus hot water & chilled water needs, thermal storage tank operation, generator fuel

• Up to 3 years of data collected

Assemble data

• To understand system level operation: generate data sets with consistent time stamps to understand inputs/ outputs across the energy flow diagram

• Quantifying individual operating efficiencies and capacities: all individual equipment data can be used

Visualize and analyze data

• Daily, monthly, yearly summaries of main loads

• Calculate equipment level efficiencies

• Calculate system level efficiency (overall inputs to outputs)

• Forecast campus needs based on binning analysis

Page 18: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Data collected and analysis completed

Daily data

• Operator logs (‘Greensheet’) dating back 2005

• Imports, hours of op, CUP gen, gen gas use, some chiller kW

Hourly data

• Chilled water & hot water to campus (dating back 2007)

15 minute interval data

• MSCADA: Imports, CUP gen

• JCI system: TES

• BOP: steam data for boilers, generators

Solar data

• 15 minute inverter & meter data dating back 2009

Historical price info

• Gen & delivery prices dating back 2009 (CAISO day-ahead, NGI; ALTOU, EG and GTNC tariffs)

Efftrack

• Chiller data obtained

• Nameplate capacity and efficiency info

• Historical data dating back to June 2011

Page 19: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

HISTORICAL OPERATIONS

Page 20: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

HISTORICAL CAMPUS NEEDS AND CENTRAL PLANT EFFICIENCY

Campus needs, annual loads and central plant CHP efficiency

Page 21: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Overview of campus needs: monthly values, entire data set

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

0

50,000

100,000

150,000

200,000

250,000

300,000

2008

-120

08-2

2008

-320

08-4

2008

-520

08-6

2008

-720

08-8

2008

-920

08-1

020

08-1

120

08-1

220

09-1

2009

-220

09-3

2009

-420

09-5

2009

-620

09-7

2009

-820

09-9

2009

-10

2009

-11

2009

-12

2010

-120

10-2

2010

-320

10-4

2010

-520

10-6

2010

-720

10-8

2010

-920

10-1

020

10-1

120

10-1

220

11-1

2011

-220

11-3

2011

-420

11-5

2011

-620

11-7

2011

-820

11-9

2011

-10

2011

-11

MW

h

MM

Btu ―

Gen 1 & 2 gas input in MMBtu Hot Water Demand in MMBtuChilled Water Demand in MMBtu Campus Total Consumption Net CUP in MWhChiller Consumption in MWh Output of Gen 1 & 2 in MWh

• Thermal loads (CHW & HTW) are characterized by seasonal variability but also have a strong baseload component.

• Generation satisfies much of campus needs (non-CUP) • Little load growth over the monitoring period

Page 22: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Overview of campus needs: comparison of monthly totals

0

5,000

10,000

15,000

20,000

25,000

0

50,000

100,000

150,000

200,000

250,000

2008-2 2009-2 2010-2 2011-2 2008-8 2009-8 2010-8 2011-8

MW

h - -

-

MM

Btu

Monthly Total Values Gen 1 & 2 Gas input in MMBtu Hot Water Demand in MMBtu Chilled Water Demand in MMBtu

Campus Total Consumption in MWh Output of Gen 1 & 2 in MWh Chiller Consumption in MWh

* Chiller data only available in latter part of 2011

Significant onsite generation across months/years; Little change over 3 years; significant baseload CHW, HTW

February August

Page 23: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Flexibility in providing campus hot water and chilled water

• Campus CHW and HTW needs can be met amply through existing resources • There is flexibility to meet the need through different combinations of electric/steam chilling

for CHW; boiler and cogen operation for HTW • For some hours, need to operate a combination of steam/electric/TES to meet CHW needs

Steam

Elec

Steam & Elec

Steam & TES

0 500 1000 1500 2000 2500 3000 3500 40005

25

45

65

85

105

125

145

165

185

205

225

Hours

MM

Btu/

hr

Histogram of CHW Demand

Nameplate Capacity Values

Boiler 2 Boiler 3

Boiler 4

Calculated Maximum

Potential Cogen Output

All Boilers

0 500 1000 1500 2000 2500 3000 3500 4000 4505

25

45

65

85

105

125

145

165

185

205

225

Hours

Histogram of HTW Demand

Nameplate Capacity Values

Based on ~ 4 years of data

Page 24: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

CHP system energy flows based on daily totals (1)

• Key systems utilizing steam are shown: steam chillers, steam generator, hot water HX • Loading order can be observed: generally steam chillers first, then hot water, then steam turbine • Steam utilization by key systems – steam chillers, hot water HX, steam turbine shown; not 100%

because other systems have ‘baseload’ steam requirements

0

50%

100%

150%

0

1,000

2,000

3,000

4,000

5,000

6,000

Stea

m U

tliza

tion

Daily

MM

Btu

Stm input to Steam chillers Stm input to HTW HX Steam Gen Input NG Gen Steam prod steam utilization by WC's,STG,HX

Both gens out 1 gen out

Page 25: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

CHP system energy flows based on daily totals (2)

0

50%

100%

0

2000

4000

6000

8000

10000

12000

Ove

rall

Effic

ienc

y

Daily

MM

Btu

Gen 1&2 elec out in MMbtu STG MMbtu out CHW from Steam ChillerHTW from Gen's GEN GAS USE Overall CHP Efficiency useful out/ in

• Overall system efficiency shown (roughly 60-70%, median 65%) • Heat rate of natural gas generators shown (roughly 30%, equivalent to ~ 12 MMBtu/MW)

Both gens out 1 gen out

Page 26: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

CHP system efficiency metrics

We characterized the CHP system using these metrics:

Overall efficiency

• Defined as the ratio of useful output to useful input

• Median efficiency of ~ 65% estimated; for context, the CPUC 2010 Impat Evaluation report for the self generation program reported total system efficiencies ranging from ~40-65%

Thermal utilization

• We define as the ratio of steam generated to the heat content of the fuel input net of the power generated

• Median efficiency of ~ 70% estimated

Steam utilization by ‘dispatchable’ variable load systems

• We defined as the fraction of steam generated used by steam chillers, turbine, hot water heat exchanger (other ‘baseload’ systems use a constant amount of steam year-round)

• Median steam utilization by the variable load systems of 75% estimated (due to improvements in baseload steam utilization systems, future utilization of ~ 85% is expected)

Page 27: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Understanding daily operations

Page 28: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Snapshot of electrical loads: hourly/15 min data

Cogen output relatively constant

Imports show expected diurnal pattern: peak during day

CUP consumption shows an ‘inverted’ load profile due to the thermal storage tank

-30

-25

-20

-15

-10

-5

0

5

10

0

5

10

15

20

25

30

35

40

5/22

/201

1

5/23

/201

1

5/24

/201

1

5/25

/201

1

5/26

/201

1

5/27

/201

1

5/28

/201

1

5/29

/201

1

5/30

/201

1

5/31

/201

1

6/1/

2011

6/2/

2011

6/3/

2011

6/4/

2011

MW

h

CUP Generation Imports

Campus Total Consumption Solar Production (right axis)

CUP Plant Consumption (right axis)

Data from 5/22/11

Page 29: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

0

5

10

15

20

25

30

35

0

50

100

150

200

250

300

350

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

MW

- -

-

MM

Btu/

hr ―

Hour

Generator fuel input in MMBtu/hr Hot Water Demand in MMBtu/hr

Chilled Water Demand in MMBtu/hr Campus Total Consumption Net Chillers in MW

Chiller Consumption in MW Campus Plant Generation in MW

Solar in MW Imports in MW

Actual operations: June 7, 2011 example

Load shifting from thermal storage lowers electrical chiller consumption

Thermal and electrical needs vary over the day but contain significant baseload components (high load factor).

Solar PV output ~ 1 MW

Page 30: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Actual operations chilled water system: June 7, 2011

-4000

-2000

0

2000

4000

6000

8000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Tons

Hour

TES Discharge Electric Chiller OutputSteam Chiller output TES ChargeCampus chilled water supply

• Roughly constant steam chiller output across all hours • Electric chiller output is reduced during peak hours (11-6 pm) and greatest when

charging the thermal energy storage (TES) tank • Tank is charged at night and early morning and discharged during peak hours

Page 31: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Observations on daily operation

Generators operated at full capacity & steady state

• Natural gas generators can be operated between ~ 10 and 13 MW without experiencing nitrogen oxide emissions problems

Steam chillers typically operated all hours and at constant output

Electric chillers operated minimally during peak periods and operated mainly to charge the TES

TES is operated conservatively* such that it always maintains capacity to compensate for unexpected steam chiller outage

• *TES is not discharged to the ‘optimal’ rate, assuming perfect foresight on chilled water demand

Solar PV generation peaks at ~ 1 MW (3% of electrical load)

Page 32: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Individual systems

Page 33: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Chiller efficiencies and capacity

Electric chiller (all are centrifugal) efficiency ranges from ~ 0.5 to 0.7 kW/ton (coefficient of performance, COP ~ 5-6*)

Steam driven chiller efficiency ranges from ~ 8000 Btu/hr/ton to 10,500 Btu/hr /ton (COP ~ 1.4-1.7*)

Chiller loading as function of nameplate typically ~ 70-90% (50th & 90th percentiles)

• Exceptions include steam chiller WC1 ~ 40-50% and electric chillers WC 7 & 9 ~ 50-80% (WC1 underwent a refrigerant retrofit, which accounts for its low loading)

* Electric chillers are known to have greater efficiencies than condensing steam-turbine driven chillers; the efficiencies observed here are within range of that expectation.

Page 34: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Chiller loading (5 month period)

WC1 Nameplate

WC2 Nameplate

WC8 Nameplate

All Steam Chillers

0

50

100

150

200

250

300

350

400

0 6 12 18 24 30 36 42 48 54 60 66 72 78 84 90 96 102

108

114

120

Freq

uenc

y (h

ours

)

MMBtu/hr

WC3, WC5 & WC6

Nameplate

WC7 & WC9 Nameplate

All Electric Chillers

0

200

400

600

800

1000

1200

1400

0 6 12 18 24 30 36 42 48 54 60 66 72 78 84 90 96 102

108

114

120

Freq

uenc

y (h

ours

)

MMBtu/hr

WC1 Nameplate WC2 Nameplate

WC8 Nameplate

0

200

400

600

800

1000

1200

0 10 20 30 40 50 60

Freq

uenc

y (h

ours

)

MMBtu/hr

WC1

WC2

WC8

WC3 Nameplate WC5 Nameplate

WC6 Nameplate

WC7 Nameplate

WC9 Nameplate

0100200300400500600700800900

1000

0 5 10 15 20 25

Freq

uenc

y (h

ours

)

MMBtu/hr

WC3

WC5

WC6

WC7

WC9

• Confirms steam chillers meet majority of cooling needs; steam chillers WC2 and WC8 operated the most; • Of electric chillers, WC 7 and 9 operated more; chillers are loaded ~ 70-80% (WC1 has poorest loading)

Steam chillers

Electric chillers

Page 35: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Generator & boiler efficiencies

Two natural gas generators have a median heat rate of ~ 11.5 MMBtu/MWh & have an output of ~ 98% of nameplate capacity

Steam turbine is ~ 15% efficient

Three boilers have median efficiency of ~ 75%

Page 36: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Thermal energy storage tank

Tank capacity ~ 32,000 ton-hr (at 13 °F delta T)

Discharge/charge capacity ~ 3100 ton or ~ 35 MMBtu/hr (5800 gpm and 13 °F delta T)

Thermal storage tank was analyzed: charge, discharge times, rates, losses generated

Quantity 10th % Median 90th % Daily discharge - ton-hr 6,401 16,250 24,504 Charge start time (hr starting) 21 23 1 Charge duration (hr) 8 10 13

Discharge start time (hr starting) 8 9 12 Discharge duration (hr) 10 14 16 Flow rate (gpm) 663 2,491 4,958 Delta T (deg F) 11 13 14 Overall tank efficiency over measurement period Charge ton-hr 6,751,512 Discharge ton-hr 6,454,207 Losses 4.4%

Page 37: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Snapshot: solar PV analysis

• Graph shows average • Installed capacity of solar PV is ~ 1.2 MW • Winter peak production ~ 0.5 MW and summer peak production ~ 0.85 MW

-

100

200

300

400

500

600

700

800

900

1,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Sola

r Met

er O

utpu

t (kW

)

Hour

Average hourly 2011 solar output by month

January February March April May June

July August September October November December

Summer

Winter

Page 38: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Summary of UCSD solar PV output

Max. Solar Meter Output (kW)

2009 2010 2011Birch Aquarium BIRC_1608 9/8/2009 49.2 95% 46.7 44.6 47.0 45.1 Campus Services Complex - Buildings A to E & Trade Shops CSC_1604 9/17/2009 258.4 97% 249.7 249.7 258.9 261.8 Campus Services Complex - Fleet Services Building FLSV_1361 Pre-2009 28.7 96% 27.5 24.4 24.4 24.4 East Campus Central Util ities Plant ECUP_1287 Pre-2009 28.7 96% 27.4 24.5 24.4 24.5 Engineering Building Unit 2 EBU_1362 and EBU_1363 Pre-2009 80.4 95% 76.5 66.6 66.6 66.5 Gilman Parking Structure GILM_1364 Pre-2009 195.0 99% 192.9 138.1 137.8 135.3 Hopkins Parking Structure* HOPK_1365 Pre-2009 338.0 99% 334.3 370.8 373.8 370.8 Price Centers, Buildings 1 to 4* PRIC_1409 Pre-2009 206.6 96% 199.3 199.4 200.8 219.4

Total 1,185.0 1,154.3 855.6 1,075.6 1,071.9 *Solar Meter Output from July 1, 2010 to June 30, 2011 was only provided as a daily average (kWh).

Rated Power (kW AC)

Total Rated Power (kW DC)

First Day of OutputIDSolar Meter Location

Inverter Efficiency

Annual Energy (kWh) Operating Hours Capacity Factor (%)

2009 2010 2011 2009 2010 2011 2009 2010 201116,471 68,389 65,890 2,751 8,756 8,754 12.8% 16.7% 16.1%

87,132 399,739 415,048 2,928 8,760 8,760 11.9% 18.3% 19.0%

50,805 47,928 45,293 8,759 8,759 8,008 21.1% 19.9% 20.6%44,458 47,745 50,470 8,172 8,759 8,759 19.8% 19.9% 21.0%

127,833 122,500 116,428 8,760 8,760 8,760 19.1% 18.3% 17.4%220,738 206,717 202,387 8,759 8,510 7,854 13.1% 12.6% 13.4%536,719 504,082 524,575 8,759 8,759 8,753 18.3% 17.2% 17.9%281,352 292,998 338,367 8,760 8,760 8,760 16.1% 16.8% 19.4%

1,365,409 1,690,041 1,742,042 8,760 8,760 8,760 13.5% 16.7% 17.2%

Birch AquariumCampus Services Complex - Buildings A to E & Trade ShopsCampus Services Complex - Fleet Services BuildingEast Campus Central Util ities PlantEngineering Building Unit 2Gilman Parking StructureHopkins Parking Structure*Price Centers, Buildings 1 to 4*

Total

Solar Meter Location

Page 39: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Summary of historical operations

Page 40: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Overall observations from historical performance

Majority of operating rules and efficiencies have been validated

• Nat gas generators operated steady state at ~ full capacity

• Loading order of steam utilizing systems

Loads have significant baseload component, but there is expected variability by hour, season

• CHW and HTW loads all year, all hours w/ higher CHW load in summer; higher HTW load in winter

• Electrical load factor (net of CUP electric chillers) is relatively high

Flexibility in resources to meet loads confirmed

• Fuel ‘arbitrage’ opportunities: excess capacity between electric/steam chillers; excess boiler capacity

• Load shifting opportunities: chiller operation; thermal energy storage tank operation (optimizing discharge/charge)

Page 41: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

UNDERSTANDING CAMPUS NEEDS

Page 42: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Binning analysis to understand electrical and thermal loads

Goal: Understand the dependence of the main campus load types to influencing factors (e.g., hour, month, day type, year)

Methodology:

• Analyzed chilled water, hot water, campus total power requirements over 3 years

• Conducted a ‘binning’ analysis to understand what variables significantly influence the load

• Binned data according to the hour, month, day type, year and generated time-series hourly plots

• Compared the confidence intervals to identify which variables are key influencing factors

Page 43: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Monthly and yearly analysis

Page 44: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Electrical load by month

0

5

10

15

20

25

30

35

40

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hour

Median Electric Load (MW) from all months, excluding weekend data

January February March April May June

July August September October November December

Total campus electrical load is not very ‘peaky’ (i.e., high load factor throughout the year)

Monthly variation is minimal (~ 5 MW or 10-15%)

Page 45: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Snapshot: variation of electrical loads across months

Variability of the electrical load within an hour is similar across months (shown by the 80% confidence interval)

0

5

10

15

20

25

30

35

40

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24Cam

pus T

otal

Con

sum

ptio

n (M

W)

Hour

January: Weekdays

90th PercentileMedian10th Percentile

0

5

10

15

20

25

30

35

40

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24Cam

pus T

otal

Con

sum

ptio

n (M

W)

Hour

May: Weekdays

90th PercentileMedian10th Percentile

Page 46: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Thermal loads by hour and month

0

20

40

60

80

100

120

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

MM

Btu/

hr

Median chilled water load by month * JanuaryFebruaryMarchAprilMayJuneJulyAugustSeptemberOctoberNovemberDecember

0

20

40

60

80

100

120

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

MM

Btu/

hr

Median hot water load from by month * JanuaryFebruaryMarchAprilMayJuneJulyAugustSeptemberOctoberNovemberDecember

* ~ 3.5 years of data; excludes weekend points

Thermal loads show strong seasonal and hourly dependence

Chilled water loads peak in mid afternoon; hot water in morning

Significant baseload component, although the load factors are greater than for electrical loads

Summer months have higher chilled water loads; winter months have higher hot water loads

Page 47: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Snapshot: variability of thermal loads by hour

0

20

40

60

80

100

120

140

160

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Chill

ed W

ater

Loa

d (M

MBt

u/hr

)

90th PercentileMedian10th Percentile

0

20

40

60

80

100

120

140

160

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Chill

ed W

ater

Loa

d (M

MBt

u/hr

) 90th Percentile

Median

10th Percentile

0

20

40

60

80

100

120

140

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hot W

ater

Loa

d (M

MBt

u/hr

)

Hour

90th PercentileMedian10th Percentile

0

20

40

60

80

100

120

140

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hot W

ater

Loa

d (M

MBt

u/hr

)

Hour

90th PercentileMedian10th Percentile

February: weekdays (~ 3.5 years data) September: weekdays (~ 3.5 years data)

• Variability in thermal loads for a given hour is significant (80% confidence interval ranges from ~ 40% to 70%) and is larger than observed for electrical loads

• Variability in chilled water load is greater during peak periods; more uniformly spread for hot water

Page 48: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Chilled water load: year to year differences

• Year to year variability in chilled water load for a given hour accounts for the wide confidence intervals observed in the previous slide

• Variability by year is likely due to temperature differences

60%

80%

100%

120%0

20

40

60

80

100

120

140

160

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Nor

mal

ized

to 2

008

Chill

ed W

ater

Load

(MM

Btu/

hr))

Hour

August: Weekdays

2008 - Median 2009 - Median 2010 - Median 2011 - Median

Page 49: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Hot water load: year to year differences

80%

100%

120%

140%

0

20

40

60

80

100

120

140

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Nor

amliz

ed to

200

8

Hot W

ater

Loa

d (M

MBt

u/hr

)

Hour

February: Weekdays

2008 - Median 2009 - Median 2010 - Median 2011 - Median

• Similar observations as with chilled water loads: year to year variability in hot water load for a given hour accounts for the wide confidence intervals observed in the previous slide

• Variability by year is likely due to temperature differences

Page 50: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Summary of monthly analysis

Power consumption exhibits the least amount of variability; hourly profiles follow typical shapes with high load factors

Chilled water and hot water loads exhibit significant variability across months and hours

• Variability for a specific hour within the month is mainly due both to year-to-year and day-to-day varying conditions

• Year to year effects likely driven by temperature variability (as opposed to significant differences in electrical and other internal loads)

Page 51: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Analysis of day type effects

Page 52: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Day type influence: electrical loads

10th percentiles are lower for electrical load profiles when the weekend data are included; this is consistent with lower occupancy on weekends. The effect is greatest during the peak periods.

05

1015202530354045

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24Cam

pus T

otal

Con

sum

ptio

n (M

W)

Hour

September: Weekdays

90th PercentileMedian10th Percentile

05

1015202530354045

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24Cam

pus T

otal

Con

sum

ptio

n (M

W)

Hour

September: Weekends

90th PercentileMedian10th Percentile

05

1015202530354045

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24Cam

pus T

otal

Con

sum

ptio

n (M

W)

Hour

February: Weekdays

90th PercentileMedian10th Percentile

05

1015202530354045

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24Cam

pus T

otal

Con

sum

ptio

n (M

W)

Hour

February: Weekends

90th PercentileMedian10th Percentile

Page 53: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Day type influence: hot water loads

0

10

20

30

40

50

60

70

80

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hot W

ater

Loa

d (M

MBt

u/hr

)

Hour

September: Weekdays

90th PercentileMedian10th Percentile

0

20

40

60

80

100

120

140

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hot W

ater

Loa

d (M

MBt

u/hr

)

Hour

February: Weekdays

90th PercentileMedian10th Percentile

Hot water loads reveal a small weekend effect in February which occurs during morning warm-up hours. There is no perceptible weekend effect in September and in other hours.

0

10

20

30

40

50

60

70

80

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hot W

ater

Loa

d (M

MBt

u/hr

)

Hour

September: Weekends

90th PercentileMedian10th Percentile

0

20

40

60

80

100

120

140

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hot W

ater

Loa

d (M

MBt

u/hr

)

Hour

February: Weekends

90th PercentileMedian10th Percentile

Page 54: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Day type influence: chilled water loads

0

10

20

30

40

50

60

70

80

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Chill

ed W

ater

Loa

d (M

MBt

u/hr

)

Hour

February: Weekdays

90th PercentileMedian10th Percentile

Chilled water loads reveal a small weekend effect during peak cooling load hours of ~ 10%; no observable weekend effect exists in other hours.

0

20

40

60

80

100

120

140

160

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Chill

ed W

ater

Loa

d (M

MBt

u/hr

)

Hour

September: Weekdays

90th PercentileMedian10th Percentile

0

20

40

60

80

100

120

140

160

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Chill

ed W

ater

Loa

d (M

MBt

u/hr

)

Hour

September: Weekends

90th PercentileMedian10th Percentile

0

10

20

30

40

50

60

70

80

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Chill

ed W

ater

Loa

d (M

MBt

u/hr

)

Hour

February: Weekends

90th PercentileMedian10th Percentile

Page 55: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Day type summary

Day type impacts all load types but at different levels

All load types (electrical & thermal) are lower on weekends as exhibited by the 10th percentile

Electrical loads are most sensitive to day type

• 10th percentile curve is ~ 10% lower during mid-day hours for plots that include weekend data)

• Weekend effect is greatest during peak periods and less in morning/ evening

Chilled water and hot water loads are mildly sensitive to day type as the lower bound on the confidence intervals are only marginally lower when including weekend data

• For chilled water, 10th percentile curve is ~ 3% lower

• Hot water loads are minimally sensitive to day type

Page 56: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Key insights of binning analysis

Each load exhibits significant baseload across all hours

• Electrical load factors significantly greater than thermal loads

Characteristics of variability:

• Seasonal dependence exists largely for CHW and HTW

• Differences in weekday vs. weekend are more apparent for mid-day hours and for power consumption, as compared to chilled water and hot water loads

• Variability across years exists across all load types but these are not load growth related

• Likely due to temperature effects and other factors

Applying historical loads for future forecast

• Statistical characteristics of loads developed

• These characteristics could be used (along with time series data) to develop dispatch schedules and assess how sensitive these schedules are to uncertainty in future loads

Page 57: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

PRELIMINARY BUSINESS ANALYSIS

Page 58: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Preliminary business analysis

How should UCSD operate its microgrid to maximize its revenues and reduce costs?

• Should it run cogen to maximum capacity?

• How should the tank be operated?

• What should be the loading order of systems utilizing exhaust heat?

Page 59: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Scenarios analyzed

What is the value of the UCSD assets to lowering campus costs?

Spreadsheet model developed to analyze the following scenarios using real UCSD load data

• Scenario 1: full import

• Scenario 2: full import + thermal storage tank

• Scenario 3: cogen (natural gas generators, steam chillers, hot water heat exchanger, steam generator)

• Conducted sensitivities on 1 vs. 2 generator, steam gen

• Scenario 4: cogen + thermal storage tank

• Conducted sensitivities on steam gen

Page 60: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Methodology

Spreadsheet model developed to analyze the cases using real UCSD load data from June-Oct 2011

• Consistent with campus thermal and elec needs

• Loading order consistent with UCSD operations

• Efficiencies & capacities from baseline effort used

Results of preliminary business analysis:

Estimated energy costs between June 1 and October 31 2011 for the idealized scenarios $Millions Electrical Gas Total SavingsFull import 6.8$ 1.3$ 8.2$ 0%Full import w/ gas cooling 6.1$ 2.7$ 8.8$ -8%Full import and thermal storage 6.7$ 1.3$ 8.0$ 2%Cogeneration 1.1$ 5.4$ 6.48$ 21%Cogeneration & thermal storage 0.9$ 5.2$ 6.10$ 25%

Page 61: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Breakdown by month and energy/demand charges

$-

$0.2

$0.4

$0.6

$0.8

$1.0

$1.2

$1.4

$1.6

Totalelectric

Demand Gas Totalelectric

Demand Gas

July October

Cost

s ($M

illio

ns)

Full import

Full import w/ gas cooling

Full import and thermalstorageCogeneration

Cogeneration and thermalstorage

Demand charges significant component of elec charges in both summer/ winter

More significant cost component in the cogeneration cases

Savings from load shifting weighted towards energy savings

Page 62: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Insights and opportunities for further optimization (1)

Preliminary scenario analysis suggests general operating strategy saves campus $

Baseline and preliminary analysis suggest opportunities for enhancement, for example:

• Optimize tank discharge such that more of the tank capacity is utilized during peak hours; charge tank during lowest wholesale energy price periods

• Modify generator output within allowable limits such that low off-peak SP-15 wholesale prices are taken advantage of and thermal utilization is optimized (optimal output may not be constant maximum output)

• Stage the chillers such that they operate at a higher loading factor, such that better efficiency is achieved

Page 63: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Insights and opportunities for further optimization (2)

Limitations of preliminary analysis

• The dispatch schedules of the resources are fixed across all days in the analysis period

• Analysis performs limited number of sensitivities that assumes an operating scenario (rather than solving for it)

• Assumes perfect foresight of campus needs

• To manage the complexity of the problem space, a realtime optimization tool is beneficial

Page 64: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

FURTHER RESEARCH AND NEXT STEPS

Page 65: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Using baselining results

Baselining activity has determined necessary inputs for the business models, such as

• Individual and system level efficiencies (e.g., kW/ton, Btu/kWh, thermal utilization)

• Typical system capacity factors

• Opportunities to move loads among central plant systems

Variability of campus electrical and thermal loads have been characterized & inform inputs to the optimizer

By calibrating the physical model to UCSD operations and loads, the business cases are realistic

Page 66: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Further research: modeling improvements

Develop more detailed models for individual systems to reflect efficiency as a function of output & some inputs, for example

• Chiller efficiency as function of condenser supply and chilled water output temperature, and output

• Generator heat rate curve as function of output

Enhance model such that a loading order for steam utilization is not assumed

Enhance model such that unique hourly dispatch schedules can be developed for all systems

Evaluate business cases against uncertainty in load forecasts (electrical and thermal)

Page 67: Task 5 Deliverable: Report on baseline performance for UCSD DER …calsolarresearch.ca.gov/images/stories/documents/... · 2019. 12. 26. · Task 5 Deliverable: Report on baseline

Further research on supporting solar and renewables

Utilize the model to answer these questions:

• How much additional solar and renewables can UCSD’s resources support?

• How do import prices and tariffs incent or not incent UCSD to utilize its resources to smooth the imported power over a month?

• What business models can create incentives for UCSD to utilize its resources to integrate solar and renewables?