Targeting Attrition: Some Familiar Ratemaking Tools
-
Upload
kenneth-gordon -
Category
Documents
-
view
213 -
download
0
Transcript of Targeting Attrition: Some Familiar Ratemaking Tools
Kenneth Gordon is a Special Consultant at NERAand specializes in utility regulation and related
issues. He was previously Chairman of theMassachusetts Department of Public Utilities. Hecame to the Massachusetts Commission from the
Maine Public Utilities Commission, where he alsoheld the office of Chairman. Prior to that, he was anIndustry Economist at the Federal Communications
Commission’s Office of Plans and Policies. Dr.Gordon was an active member of the National
Association of Regulatory Utility Commissioners(NARUC) and served as President of that
organization in 1992. He was also a member ofNARUC’s Executive Committee and Committee on
Communications. In addition, he has served asChairman of the New England Conference of Public
Utilities Commissioners TelecommunicationsCommittee and is a former Chairman of the Power
Planning Committee of the New EnglandGovernors’ Conference.
Wayne P. Olson is a Senior Consultant at NERAand focuses on economic, finance, accounting, and
public policy issues in the electric utility, gasdistribution, oil and gas pipeline, and
telecommunications industries. Prior to joiningNERA, he was Director of Finance of the Maine Public
Utilities Commission, where he was involved inelectric restructuring and telecommunications
activities as well as the full gamut of rate case and otherregulatory issues. He has also served as a Manager at
Palmer Bellevue Corporation, an InternationalBanking Officer at Westpac Banking Corporation, and
a Financial Analyst in the Economics and RatesDepartment of the Illinois Commerce Commission.
Kurt G. Strunk is a Senior Consultant at NERA andhas extensive experience working on strategic,
regulatory, and corporate financial issues in theenergy industry. In the U.S., he has advised utilities on
sector restructuring, contract and asset valuation,origination, hedging and risk management,
regulatory strategy, prudence, cost of capital, affiliatetransactions, and retail market issues. He has been akey member of the NERA team implementing auctions
for the provision of default electric service in NewJersey and Illinois. Mr. Strunk has also advised
governments, regulators, and energy companies onissues relating to industry structure, regulation, and
sector reform in Latin America and Europe. Hecoauthored the white paper outlining structural
reform and partial privatization of the Mexican powersector, which was developed for Mexico’s NationalCongress in 2000. In 2002 and 2003, Mr. Strunkadvised the Commission for Energy Regulation inIreland on the development of a solicitation for the
construction of a 400 MW power generation facilityand associated offtake contract. He has also advised
Mexico’s Comision Federal de Electricidad on thedevelopment of its independent power program and, in1996, was part of the NERA team working on power
sector restructuring in Spain.
10
1040-6190/$–see front matter # 2011 ElseTargeting Attrition:Some Familiar RatemakingTools
Because of their investment in long-lived assets withlittle value in alternative uses, special attention to meetingthe terms of the regulatory compact is appropriate.This need not always take the form of full-blown ratecases—there are more targeted tools as well. Targetedand formula-based approaches can play a role in settingjust and reasonable rates, based on prudently incurredcosts.
Kenneth Gordon, Wayne P. Olson and Kurt G. Strunk
I. Introduction
Public utilities invest in long-
lived, specialized assets. This
‘‘infrastructure’’ supports
economic growth and, as such,
helps to explain why public
utilities are regulated.1 Public
policymakers—at the federal level
and in many states—have made
modernization of the nation’s
electric transmission and
distribution infrastructure a
priority.2 There are a variety of
vier Inc. All rights reserved., doi:/10.1016/j.
policies and practices that can be
considered ‘‘standard’’ public
utility regulatory methods and
that can support investment in
infrastructure.
S tate utility commissions use a
variety of regulatory policies
and practices—variations on a
theme but distinctive enough to
suit the needs of the state. For
utility investors, it is not the tiny
details that matter, but rather
whether there is a credible
commitment to treat both utility
tej.2011.07.005 The Electricity Journal
With any application ofthese regulatorybuilding blocks, thereneeds to be an assurancethat each ratemakingtool can work correctlyand not simply end-runthe regulator.
A
customers and utility investors
fairly, over the short and long
runs. Public utilities are regulated
to protect utility customers from
the consequences of the unfair
exercise of market power.
W hat purpose would
targeted and formula-
based regulatory approaches
serve? The answer to that
question would vary from state to
state and from case to case, but, in
the current economic climate, we
would suggest that there are three
major challenges that many
electric utilities are now facing: (1)
attrition, which is a persistent
inability to recover the real costs
of providing utility services; (2)
the need to invest capital to build
utility infrastructure, some of
which is mandated by the makers
of public policymakers, which can
exacerbate the attrition problem;
and (3) credit ratings that are
above investment grade, but that
remain weak by historical
standards. A utility’s persistent
inability to recover the real costs
of providing utility service would
harm customers. Direct solutions
to the attrition problem may be
difficult to achieve, so the focus of
this article is on investigating new
applications of traditional
regulatory tools, aiming to
provide commissions and utilities
with examples of approaches that
could meet current challenges.
In this article, we review key
regulatory building blocks that
could accommodate regulatory
approaches that result in more
timely recovery of costs.
Examples of regulatory
approaches that are increasingly
ug./Sept. 2011, Vol. 24, Issue 7 1040-6190/$–
being used by state commissions
when setting utility rates include:
� Asset ‘‘trackers’’ for defined
categories of capital expenditures
(‘‘cap ex’’) as they enter rate base.
� Construction work in
progress (CWIP) in rate base with
a cash return.
� Indexing procedures of
various sorts.
� Alternative forms of
regulation, such as broad-based,
formula-rate plans.
� Some form of ‘‘pre-
approval’’ of the regulatory
policies and practices to be used
for a major capital addition, often
generation- or transmission-
related, but that could also apply
to major distribution investments.
Next, we survey and review
specific examples of these
approaches. This article identifies
regulatory building blocks that
are squarely part of standard
regulatory methods, but that,
given the challenges currently
facing the electric utility industry,
may have a greater role to play.
In conclusion, we review some
of the crucial public policy
considerations, e.g., economic
see front matter# 2011 Elsevier Inc. All rights
efficiency and consumer benefits,
which state commissions should
consider. With any application of
these regulatory building blocks,
there needs to be an assurance
that each ratemaking tool can
work correctly and not simply
end-run the regulator. The
approaches described in this
article have the potential to
provide benefits to utility
customers.
II. Industry Challenges
Each state and region has its
own infrastructure needs and
would focus its attention on how
to best meet those needs. Utility
ratepayers would be well served
by a regulatory framework and
company policies that serve the
public interest by minimizing the
overall cost of capital, while
facilitating investments in needed
infrastructure by the regulated
utility industry. There are a
variety of ways to accomplish this
goal.
I n the current economic
climate, we would suggest
that there are three major
challenges that many electric
utilities are now facing:
� Attrition dilemma. Rates that
are adequate for a given ‘‘test
year’’ can fall short in succeeding
periods given growth in rate base
and increasing operating costs,
leading to ‘‘attrition,’’ which is the
erosion of earnings ‘‘caused by
cost of services increasing more
rapidly than revenues.’’3 Figure 1
provides evidence that some
electric utilities have not earned
reserved., doi:/10.1016/j.tej.2011.07.005 11
[(Figure_2)TD$FIG]
32
37
47
55
6360 59
70 6868
0
10
20
30
40
50
60
70
80
2013E2012E2011E2010200920082007200620052004Year
Tot
al C
apita
l ($
Bill
ions
)
Source: Regulatory Research Associates (SNL Energy), Financial Focus Special Report, Capital Expenditures, May 6, 2011
Figure 2: Total Capital Expenditures for 44 Companies (Historical and Forecast-$ Billions)
[(Figure_1)TD$FIG]
8.00
8.50
9.00
9.50
10.00
10.50
11.00
2006 2007 2008 2009 2010
Ret
urn
on E
quity
(%)
Year
Earned ROE Allowed ROE
Figure 1: Allowed ROE vs. Earned ROE (2006–2010)
12
their allowed ROE in recent years.
With few exceptions, all of a
utility’s activities are aimed at
meeting its obligation to serve
customers and, therefore, the
legitimate costs incurred by a
utility as part of its efforts to meet
the needs of its customers would
be recoverable in rates. With
appropriate incentives in place,
there is a strong presumption that
all of a utility’s costs will be
incurred to meet the utility’s
obligation to serve. While there is
no guarantee that a utility will
actually be able to earn its cost of
capital once rates have been set, if
rates are set such that the utility
does not have a realistic
opportunity to recover its costs,
harm to customers will likely
result in the longer run, if not
sooner.
� Capital expenditure challenge.
Infrastructure investment in
generation, transmission, and
distribution plant would be
needed to meet the ambitious
1040-6190/$–see front matter # 2011 Else
goals and major challenges that
face the electric utility industry—
and extensive cap ex construction
programs can exacerbate a
utility’s attrition problem.
Figure 2 shows that the cap ex
plans of utilities are ambitious,
requiring the raising of significant
new capital over the next few
vier Inc. All rights reserved., doi:/10.1016/j.
years. The ability of utilities to
fund capital investment is directly
dependent on their ability to raise
debt and equity in the capital
markets. Moreover, most states
now have renewable portfolio
standards (RPS) or state mandates
in place,4 as shown in Figure 3. To
meet RPS type mandates, many
utilities will need to invest in the
infrastructure needed to make use
of that renewable energy. Given
the nature of these infrastructure
investments, some degree of
regulatory pre-commitment
would likely be appropriate,
along with other regulatory
building blocks, such as asset
trackers and CWIP in rate base
with a cash return.
� Credit quality constraint.
Electric utility credit ratings are
generally above investment
grade, but remain weak by
historical standards. Figure 4
shows the S&P bond ratings for
electric utilities.5 The sharp
tej.2011.07.005 The Electricity Journal
[(Figure_3)TD$FIG]
VA
PA
NC
MI
WVKY
LA
AR
MN
OK
NV
CA
ID
AL
AZ
CO
FL
GA
IA
IL IN
KS MO
MS
MT ND
NE
NM
NY
OH
OR
SC
SD
TN
TX
UT
WA
WIWY
AK
HI
DC
NJ
MD
RI
VT
ME
DE
NHMACT
VA
PA
NC
MI
WVKY
LA
AR
MN
OK
NV
CA
ID
AL
AZ
CO
FL
GA
IA
IL IN
KS MO
MS
MT ND
NE
NM
NY
OH
OR
SC
SD
TN
TX
UT
WA
WIWY
AK
HI
DC
NJ
MD
RI
VT
ME
DE
NHMACT
Source: Energy Information Administration, Renewable Energy Trends in Consumption and Electricity 2008.
Figure 3: States with Renewable Portfolio Standards, 2008
A
decline in electric utility credit
quality (relative to 2001 levels)
begs the question of whether the
industry and its regulators will
together be able to find ways to
implement the nation’s grid
modernization, energy
independence, and
environmental goals in a timely
and efficient manner. Timely rate
[(Figure_4)TD$FIG]
Electric Util196
0%10%20%30%40%50%60%70%80%90%
100%
198519831980197519701965
A- or higher
Sources: Leonard Hyman and EEI.
Figure 4: Electric Utility Bond Ratings (1965–
ug./Sept. 2011, Vol. 24, Issue 7 1040-6190/$–
recovery methods would be a
necessary part of that balanced
approach. The ability of utilities to
fund capital investment is directly
dependent on their ability to raise
debt and equity in the capital
markets. Under current market
conditions, it would be relatively
more difficult for utilities to raise
funds in the debt market, and
ity Bond Ratings5-2009
200920082007200119921990
BBB Below BBB-
2011)
see front matter# 2011 Elsevier Inc. All rights
when they do so, it would be at a
higher cost than it would have
been with a bond rating of ‘‘A-/
A300 or higher.
U tility ratemaking should
not prevent a utility from
earning an adequate return on its
investment in serving the public.
Attrition, which is typically
discussed in the context of the
combined effects of inflation and
large-scale construction programs
on a utility’s opportunity to
actually earn its allowed ROE,
should not lead to a public utility
being prevented from having a
reasonable opportunity to recover
its prudently incurred costs,
including the forward-looking
cost of capital.
Leonard Saul Goodman points
out that‘‘[i]f attrition is an
economic factor truly beyond the
company’s control, and if it is a
proper cost in a transitional
inflationary period, there is
reserved., doi:/10.1016/j.tej.2011.07.005 13
An importantelement in
this demonstrationis being
able to pointto a supportive
regulatoryenvironment.
14
unfairness in placing the entire
burden of the cost on
shareholders.’’6 A close reading of
this comment suggests that:
� Economic factor truly beyond
the company’s control.
Infrastructure costs aimed at
achieving ‘‘energy
independence’’ can be considered
to be a type of mandated cost,
with the initial decision to
construct beyond the control of
the utility. To meet RPS mandates,
utilities will need to invest in
infrastructure and some degree of
‘‘preapproval’’ of the initial
decision to construct can be
justified.
� A proper cost. Note that the
utility would continue to have
control of its execution of the
project and therefore would face
prudence scrutiny with respect to
the mandated investment.
� Unfairness in placing the
burden entirely on shareholders.
With respect to the traditional
regulatory ‘‘balancing act,’’
efforts to ameliorate the economic
effects of attrition by providing
more timely cost recovery can be
beneficial to both utility
customers and investors. This is
because utility customers’ rates
will reflect the weighted cost of
the utility’s debt, preferred stock,
and common equity—and use of
the regulatory building blocks can
potentially reduce these capital
costs.
T he traditional standard to
justify the suitability of a
fuel adjustment mechanism is
whether the cost of the purchased
item is beyond the control of the
utility, large, and volatile.7
1040-6190/$–see front matter # 2011 Else
Applying an analogous
ratemaking approach to
mandated infrastructure
investments can potentially make
sense from a public policy
perspective. After all, the
cumulative effect of numerous
ratemaking adjustments should
not prevent a utility from having
the opportunity to earn a
compensatory return on capital.
Absent imprudence, a public
utility should not face a persistent
inability to recoup its costs of
providing utility service. Put
more positively, a utility should
be given a reasonable opportunity
to realize an adequate rate of
return and thereby be assured of
access to the capital markets at a
reasonable cost—because
customers would benefit.
III. Regulatory BuildingBlocks
The focus of utility regulation
should always be on consumers,
with regulation ensuring that the
rates paid by utility customers are
just and reasonable, based on
vier Inc. All rights reserved., doi:/10.1016/j.
prudently incurred costs. Given
that regulated electric utilities
must be able to raise substantial
amounts of both debt and equity
capital in order to fund
investment in long-lived,
specialized assets, utilities must
be able to demonstrate that they
have the financial standing and
resources needed to raise capital
at a reasonable cost, in good
markets and bad, in both the short
and long terms. An important
element in this demonstration is
being able to point to a supportive
regulatory environment.
T he purpose of this section is
to review key regulatory
building blocks that can
accommodate regulatory
approaches that result in more
timely recovery of costs. These
building blocks include such
regulatory practices as:
� FERC Form 1 accounting
statements. Effective regulation of
any form requires that regulators
define the consistent, durable, and
transparent accounting
procedures to be used by
regulated utilities. The early
history of regulation in the U.S.
was characterized by notorious
accounting abuses, including
overstated expenses, unverifiable
investments in plant and
equipment, a lack of separation
between utility and non-utility
businesses, and
overcapitalization. Such abuses
were ended with the adoption, in
1938, of the Uniform System of
Accounts by the federal
government.8 The goals of good
regulation are frustrated when the
lack of detailed and reliable
tej.2011.07.005 The Electricity Journal
A
accounting data obstructs the
regulator’s ability to periodically
assess the cost of service.9 For
example, the Uniform System of
Accounts rarely leaves U.S. energy
utilities and their regulators in
dispute over basic financial issues
such as profitability, depreciation
expenses, customer contributions,
incurred operating costs, or the
treatment of unregulated affiliates.
Rate cases instead focus on how
these costs should be recovered for
ratemaking purposes.
� Adjustment mechanisms.
Infrastructure recovery
mechanisms, also known as ‘‘asset
trackers’’ or ‘‘riders,’’ are roughly
analogous to the adjustment
mechanisms that are used to pass
through the costs of fuel and
purchased power. Regulatory
Research Associates (RRA)
explains that ‘‘from an investor
standpoint, this is the preferred
treatment, as adjustment clauses
can allow for more timely rate
recognition of incremental
CWIP.’’10 Asset trackers or similar
adjustment mechanisms allow for
more-timely recovery of rate base
additions than would be the case
with traditional rate cases.
Operating and maintenance
expense (O&M) riders or trackers
of various sorts, such as bad debt
riders or regional cost riders, could
also be used. Adjustment
mechanisms have been used by
regulators since the early days of
the industry.11
� CWIP in rate base with a cash
return. As commissions and
utilities grapple with questions of
how best to invest in the utility
infrastructure needed to
ug./Sept. 2011, Vol. 24, Issue 7 1040-6190/$–
accommodate public policy goals,
allowing CWIP in rate base with a
cash return has once again
become a standard part of the
regulatory toolkit. As the industry
proceeds with the ongoing
construction cycle, legislatures
and regulators have begun to
allow CWIP in rate base for a cash
return, sometimes restricted to
only certain designated types of
plant, i.e., transmission or certain
types of generation.12 RRA
reports that 16 states have
permitted a cash return on CWIP
in recent years and that eight of
the states that allow CWIP in rate
base with a cash return also allow
asset trackers to be used.13 Given
that an allowance for funds used
during construction (AFUDC)
need not be recovered in rates,
using this approach reduces the
total cost to customers.
� Inflation adjustments. Attrition
is the persistent inability to recover
the real costs of providing utility
services. To mitigate the impact of
attrition, regulators use inflation
adjustments in a variety of ways
including attrition allowances,
fully forecasted test years,
see front matter# 2011 Elsevier Inc. All rights
projections of cost items, true-up
of projected and actual costs, and
formal price cap plans (inflation
minus an x-factor). Generally,
inflation adjustments can help
maintain rates at levels that
provide a utility with a reasonable
opportunity to recover its costs,
including the cost of capital.
� Cap ex budgeting. All investor-
owned public utilities have some
type of capital expenditure
budgeting process in place to
prioritize the many alternative
infrastructure investments that
could be made. In a few states,
ex ante cap ex budgeting
information is formally provided
to the utility regulator, while, in
other cases, less formal
procedures are used to keep the
regulatory agency informed.
Either way, the cap ex budgeting
process can build a foundation for
recovering utility costs in a timely
manner.
T hese building blocks can aid
in the establishment of
regulatory practices that support
investment in utility
infrastructure, which can, in turn,
aid in meeting RPS requirements
and other state goals.14 The
regulatory process has safeguards
(e.g., prudence reviews) to assure
that tariffed rates remain at a just
and reasonable level. Consistent
with the regulatory compact,
which provides a means of
balancing the competing interests
of utility customers and the
investor–owners of public
utilities, these tools can be used to
respond and adapt to changes in
customer, industry, and market
conditions.
reserved., doi:/10.1016/j.tej.2011.07.005 15
16
IV. Some Solutions tothe Attrition Problem
Utility ratemaking is conducted
on a case-by-case, fact-specific
basis. While the details vary
somewhat from state to state, the
basics of the ratemaking process
are largely the same. For any
given jurisdiction, the
overarching framework of utility
regulation—the ‘‘end result’’15—
is likely what is most important to
investors.16 Under the Hope
standard, ‘‘[i]t is not theory but
the impact of the rate order which
counts.’’17
U tility commissions
necessarily have
discretion, consistent with their
statutory authorization, to revise
regulatory policies and
procedures. Thus, for example,
commissions can typically decide
whether to use a fully forecasted
test year, a partially forecasted
test year, or a fully historic one; a
test year can be adjusted for
attrition and/or known and
measurable changes in costs. The
comprehensive state-level
regulation of electric utilities is
based on a regulatory compact
that provides an economic
framework that supports major
capital investments in assets with
very long useful lives. If utility
price signals are more efficient
when a more cost-reflective test
year is used, for example,
regulatory policies can be
adjusted to accomplish this,
consistent with the commission’s
statutory authority. The purpose
of this section is to review several
regulatory approaches that can be
1040-6190/$–see front matter # 2011 Else
considered ‘‘standard’’ public
utility regulatory methods
and that may be especially well
suited to meeting current
challenges.
A. FERC formula-rate
transmission ratemaking
Formula-based approaches—
and other regulatory building
blocks—can be used to set just
and reasonable rates, based on
prudently incurred costs. The
FERC’s formula rate approach is a
useful example of how to achieve
timely rate recovery, while
maintaining traditional
regulatory oversight of utility rate
levels. The FERC’s approach
relies crucially on applying FERC
Form 1 data in a formula-based
ratemaking approach. Some of
these formula-rate plans use
prior-year FERC Form 1 data to
calculate rates for the upcoming
year, while other plans use
projected rates, which are then
trued up when actual costs are
known, with over-collections
returned to customers with
interest.18
vier Inc. All rights reserved., doi:/10.1016/j.
FERC’s approach has a number
of advantages including:
� Keeping rates at levels that are
close to the cost of service. This
largely avoids the possibility of
‘‘overearning’’ by the utility.
Rates are maintained at cost-
based levels, without the need for
frequent full-blown rate cases.
This is a sharp contrast to the
FERC ratemaking approach for
gas pipelines, where gas pipelines
can ‘‘over-earn’’ for extended
periods of time (paid for by
electric utilities and gas local
distribution company customers,
among others), with the FERC
staff only investigating if the
earned ROE is over 20 percent.19
� Accommodating various types
of incentives. Various types of
incentives can be accommodated
within the FERC’s framework.
Orders 679 and 679-A established
the procedures by which electric
transmission owners can receive
incentive-based rate treatment.20
Under FERC Order 679,
incentives available to
jurisdictional public utilities
include ROE incentives, CWIP in
rate base with a cash return,
hypothetical capital structure,
accelerated depreciation,
recovery of costs of abandoned
facilities, and deferred cost
recovery. FERC’s various
incentive measures typically
garner more attention than does
its formula rate approach.
� Credit quality. Credit quality
is a statutorily required criterion
in FERC’s determination of a
formula-rate plan.21 FERC has,
example, considered Westar’s
‘‘BBB-’’ credit rating when
tej.2011.07.005 The Electricity Journal
A
approving formula rates,22 an
example of a regulatory
commission using its discretion to
support a utility whose credit
rating was on the verge of
dropping below investment
grade.23 The FERC’s formula rate
approach can incorporate
accelerated depreciation for
ratemaking purposes, CWIP in
rate base with a cash return, and
an asset tracker approach, all of
which can support a utility’s
credit standing.
� Inflation adjustments.
Standard ratemaking practice
makes use, in a variety of ways, of
inflation adjustments to actual
costs. Whether it is an attrition
adjustment, use of a fully
forecasted test year, projections of
variable costs, a formal price-cap
(inflation minus an x-factor) plan,
or some other regulatory use of an
inflation adjustment, standard
practice accommodates
ratemaking adjustments based on
anticipated inflation. Adjustment
mechanisms, such as FERC’s
formula-rate approach, can build
in true-ups of projected and actual
costs.
� Administrative efficiency.
FERC has a large and diligent
accounting and auditing staff and
thus can be assured that the FERC
Form 1 data is accurate and
reliable. Thus, FERC’s formula-
rate approach can be
implemented in an
administratively efficient way.
FERC regulates a large number
of transmission entities, and, to
prevent a logjam, needs to have
administratively workable
ratemaking procedures in place.
ug./Sept. 2011, Vol. 24, Issue 7 1040-6190/$–
Nevertheless, the timing and
procedural protocols provide
enough time for interested parties
to review the data filed by the
transmission entity and to submit
information requests.24
S tate commissions regulate a
smaller number of
companies, but the rate-case-
every-few-years paradigm may
currently not work well in all
instances. Among other things,
state commission administrative
resources are constrained in an
era of tight budgets. Most states
commissions have ‘‘annual
report’’ filing requirements, akin
to the FERC Form 1, which would
accommodate the use of a
formula-rate approach.
B. Con Ed distribution rate
settlement
Rate settlements or stipulations
are a standard part of the
procedural repertoire used to
conduct public utility rate
regulation. Settlements are a way
to forge consensus on issues that
would otherwise have to be
decided by the regulator, based
see front matter# 2011 Elsevier Inc. All rights
on a divided record. Thus,
settlements have a useful role to
play.25
Con Ed has, in recent years,
borne a cap ex budget of well over
$1 billion dollars per year, which
is aimed at investing in
distribution infrastructure
needed to meet its obligation to
serve. The Con Ed settlement
‘‘hardwires’’ a three-year cap ex
program of roughly $1.4 billion
per year into a three-year rate
plan, with rate increases of
$540.8 million, $306.5 million, and
$280.2 million, respectively.26 The
New York commission has an ex
ante cap ex review process in
place, which may accommodate
more timely ratemaking
treatment of infrastructure
investment.
W ith settlements, one does
not necessarily know all of
the tradeoffs involved, only the
end result. In some contexts,
settlements can make the
ratemaking process less
transparent because the
commission may not rule, for
example, on what it believes to be a
reasonable capital structure and
cost of equity and thus a
stipulation can become opaque, a
black box. That need not be the
case however and, indeed, is not
the case with Con Ed. Integrating a
three-year cap ex program into the
setting of rates for those years
provides an opportunity to raise
rates in a stable and predictable
way, rather than rely on one-time
adjustments via occasional full-
blown rate cases. Con Ed’s three-
year cap ex rate plan provides a
good ratemaking model, as does
reserved., doi:/10.1016/j.tej.2011.07.005 17
18
the settlement process used to
achieve that outcome.
C. Peoples Gas pipe
replacement tracker
A well-designed and
implemented asset tracker for
qualified infrastructure
investments benefits customers.
The basic idea would be to
recover the costs of ‘‘qualified’’
infrastructure investments
incurred between rate cases
through an asset tracker. The
definition of qualified
investments varies. For example,
the definition for The Peoples Gas
Light and Coke Company
(‘‘Peoples Gas’’) infrastructure
cost recovery charge (ICR charge)
focuses on qualified additions
associated with replacing aged
facilities that have not previously
been included in rate base.27
Under an alternative approach
used in New Jersey,28 job creation
and economic impact are the main
criteria used to target cost
recovery on an expedited basis.29
A definition of ‘‘qualified’’
infrastructure investments might
include capital expenditures that
benefit many customers, are
relatively large in size, and that go
beyond the ordinary expansion of
distribution facilities.
T he Peoples Gas ICR charge
was implemented in the
context of a desire to ensure
timely replacement of aging and
possibly unsafe gas
infrastructure. Further, the tariff
notes that there is a savings of
$6,000 per mile from abandoning
aged cast iron pipe.30 Actual
1040-6190/$–see front matter # 2011 Else
savings are reconciled to this
estimate every three years. Hence,
the program was implemented as
an incentive for what was
considered to be a desirable
investment from safety,
reliability, and economic
perspectives.
An infrastructure recovery
mechanism, or asset tracker, is
attractive from a public policy
perspective for numerous
reasons.
� Accommodate more timely
recovery of new plant costs. By
ensuring timely recovery, a
tracker may make timely
investment in facilities more
feasible. Rates would ordinarily
go up in conjunction with
capital expenditure completion
and commercial operation
but that would be accomplished
in a relatively stable and
predictable fashion given the cap
ex review process. An asset
tracker can be implemented in
conjunction with CWIP in rate
base with a cash return, which
would further accelerate and
smooth rate impacts. In terms of
rate stability, if some AFUDC
vier Inc. All rights reserved., doi:/10.1016/j.
accruals can be avoided or
minimized, that would help keep
rates low.
� Support financial integrity. An
asset tracker can support a public
utility’s ability to raise new
capital, thereby easing the
financing of capital expenditures.
Over time, this would tend to
improve credit quality and benefit
customers via a lower cost of
capital.
� Administrative safeguards.
Procedures could be put in place
to ensure that the commission has
the timely opportunity—and
necessary information—to ensure
that the asset tracker is working as
intended, thereby benefiting
customers. For example, Peoples’
internal auditors must certify
each year that the ICR has been
properly implemented, and there
must be an independent external
review every five years.31
The Peoples asset tracker
mechanism, which places assets
into rates in a timely matter, but
leaves most of the review process
to the reconciliation stage of the
case, provides a reasonable
ratemaking model. Other
approaches can, of course, be
used as well. The Peoples Gas
Rider ICR mitigates regulatory
lag for qualified capital
expenditures. Rather than
spending and then waiting for
commission approval to recover
the costs, the utility is afforded the
opportunity to spend, recover,
and then wait for a retrospective
prudence review.
From a credit quality
standpoint, however, the
regulatory implementation of the
tej.2011.07.005 The Electricity Journal
[(Figure_5)TD$FIG]
0
10
20
30
40
50
60
70
80
20102009200820072006200520042003200220012000Year
Num
ber
of R
ate
Cas
es F
iled
Source: Regulatory Research Associates
Figure 5: Number of Rate Cases Filed, 2000–2010
A
Peoples Gas ICR has a major
drawback. The mechanics of the
Peoples Gas infrastructure tracker
are sound, but the ‘‘quasi-debt’’
rate allowed for Rider ICR assets
may effectively prevent Peoples
Gas from improving its credit
quality, at a time when it must
raise new capital to fund cap ex
programs. Providing only a quasi-
debt return implies that the
‘‘tracked’’ assets require a lower
allowed ROE than non-tracked
assets, but the cost of capital is a
function of the use to which it is
put and is not a function of the
specific rate treatment provided
those assets.32
P roviding only a quasi-debt
return makes it more
difficult for the company to
maintain the coverage ratios
needed to maintain or improve its
credit rating. Peoples Gas had lost
it’s ‘‘A-’’ credit rating from S&P (it
has an ‘‘A3’’ rating from
Moody’s) following its previous
rate case, with those lower ratings
affirmed subsequent to the
February 2010 rate case decision.
In explaining its downgrade, S&P
noted that its assessment was
based, in part, on its ‘‘assessment
of the Illinois regulatory
environment which we place in
the least credit supportive
category.’’33 This rate case did not
put Peoples Gas back on the road
to meriting an ‘‘A-’’ credit rating.
It is a mistake to view an asset
tracker in isolation—credit rating
agencies generally focus on the
regulatory compact in the state
not on relatively narrow aspects
of ratemaking procedure—and
thus this aspect of the February
ug./Sept. 2011, Vol. 24, Issue 7 1040-6190/$–
2010 Peoples Gas rate case order
represents a missed opportunity
to enhance the utility’s ability to
raise debt at a low cost.
V. Traditional RateCases and the RegulatoryBuilding Blocks
While ratemaking procedures
will vary on a state by state, case
by case basis, regulators’ primary
regulatory ‘‘tool’’ for overseeing a
utility’s tariffed rates is the
traditional rate-of-return/cost-of-
service rate case, which provides
the regulator with a forum for
investigating and determining the
justness and reasonableness of the
utility’s rates and the prudence of
its capital and operating costs.
Figure 5 shows that rate case
activity surged during the
middle- to late-2000s following a
period of relative inactivity
during the late 1990s and early
2000s.34 Through June 30, 2011, 39
rate cases have been filed
compared to a total of 60 for
2010.35 Using a ‘‘test year’’
see front matter# 2011 Elsevier Inc. All rights
revenue requirement, the
regulatory agency examines the
reasonableness of the utility’s
sales growth projections, rate
base, operating expenses, cost of
capital, and other cost
components, and then sets rates
that provide the utility a
reasonable opportunity to recover
its prudently incurred costs—this
is the core of the traditional public
utility ratemaking regulatory
bargain.
A regulator’s ability to
disallow imprudently
incurred costs provides crucial
regulatory oversight over the
utility’s management of its
operations. A utility’s costs are
held to a ‘‘reasonableness’’
standard, not an ‘‘ideal’’ standard
of perfection or optimization. In
setting rates that are just and
reasonable, the required
ratemaking approach is to
provide the utility with an
opportunity to recover the
prudently incurred costs
(including a fair rate of return on
capital) of providing utility
services to customers. In
reserved., doi:/10.1016/j.tej.2011.07.005 19
20
examining the prudence of a
utility’s costs, the regulator
considers the costs in relation to a
‘‘reasonable man’’ standard—the
costs must be reasonable in
comparison to the costs that
would result from reasonable
utility practice. Any prudence
determination should be based on
whether the decisions at the time
they were made were reasonable
under the then existing
circumstances. For a utility,
prudence is reflected in the
decision a reasonable utility
management would make at the
time the decision is required, and
must remain free of any
hindsight. If a prudent decision
turns out badly, the bad outcome
does not by itself demonstrate a
lack of prudence.36 Fairness
requires that any imprudence be
demonstrated objectively so that
there will not be uncertainty
about the regulatory decision.
Evidence of failure to act
prudently must be well grounded
in law, economics, and public
policy.
S ome prudently incurred
costs (e.g., charitable
contributions,37 executive
incentive compensation, and
advertising expenses) are
frequently excluded from a
utility’s revenue requirement,
even if they are legitimately
incurred costs. Prof. Alfred E.
Kahn, when he was chairman of
the New York State Public Service
Commission, expressed the view
that ‘‘heated discussions’’ about
advertising ratemaking policy
were a ‘‘tempest in a teapot,’’ both
because the dollars were small
1040-6190/$–see front matter # 2011 Else
and because disallowing
advertising expenditures under
the ‘‘glib assumption that these
costs will then be borne by
stockholders rather than
ratepayers, is something of a
sham.’’38 Prof. Kahn went on to
explain that the:
[E]ssential fraudulence of our
purporting to exclude from rates
expenditures for advertising that
company managements will con-
tinue to feel it necessary to make:
since we made every effort to set
the allowable return on equity at
the minimum cost of capital, and
most of the companies we regulate
are not earning even that, in
principle putting any advertising
expenditures ‘below the line’ can
only mean, if we are honest,
increasing the allowed return on
equity, in order to enable these
companies to raise the capital they
need on reasonable terms.39
This problem could be
addressed directly, by revisiting
commission policies and
precedent on the ratemaking
treatment of these costs.
Unfortunately, however, this
rarely occurs, which makes a
direct solution to the problem
vier Inc. All rights reserved., doi:/10.1016/j.
difficult to achieve. The
regulatory approaches described
in this paper do not solve this
problem, but would provide an
indirect way to deal with the
attrition problem, large cap ex
programs, and bond ratings that
are weak by historical standards.
VI. Conclusion
The standard approaches
described in this article can be
used to meet the challenges that
the electric utility industry
currently faces. While the details
of utility regulation in the state are
no doubt important, there are a
variety of regulatory policies and
mechanisms that can be used to
set utility rates. Regulatory
approaches which might not be
viewed as quite as favorable to
investors, might, in practice, be
well-suited to the specific
situation in a given state and
therefore be considered to be
acceptable. It is the end result that
matters when regulatory
institutions apply the regulatory
compact.
Utilities must have incentives
that lead them to maximize
customer benefits—so that
customers receive efficient, safe,
adequate, and reliable service
both now and in the future. A
utility’s economic incentives will
be better when rates to customers
reflect the utility’s true cost of
providing service.
� Allocative efficiency refers to
the prices that customers face.
Allocatively efficient utility rates
would give customers the
tej.2011.07.005 The Electricity Journal
A
economically correct price signals
to use electricity or gas or not,
depending on the customer’s
choice. Failure to allow
appropriate costs to be included
in the utility revenue requirement
distorts this efficiency, since
customers are receiving an
inaccurate price signal.
� Productive (or technical)
efficiency refers to the incentives
that the utility faces as it decides
how to provide its services. The
utility should have the incentives
to operate in an efficient manner,
while also continuing to provide
safe, adequate, and reliable
service. With appropriate
incentives in place, few if any
costs should be excluded from the
utility’s tariffed rates—the utility
will be focused on fulfilling its
obligations to its customers.
� Investment incentives are the
dynamic aspect of productive
efficiency. The utility must have
the incentive to efficiently invest
in infrastructure. An inability to
recover its costs could distort the
utility’s investment incentives.
Where credit quality concerns
remain a significant deterrent to
utility investment in
infrastructure on behalf of
customers, ratemaking treatments
that provide more timely and
regular recovery of costs may
prove useful.&
Endnotes:
1. Utility regulation may, in part, be a‘‘method of promoting the expansionof infrastructure services.’’ Richard A.Posner, Taxation by Regulation, BELL J.ECON., Spring 1971, at 39–41.
ug./Sept. 2011, Vol. 24, Issue 7 1040-6190/$–
2. Title XIII of the EnergyIndependence and Security Act of2007 (‘‘EISA07’’) declares that ‘‘it is thepolicy of the United States to supportthe modernization of the Nation’selectricity transmission anddistribution system to maintain areliable and secure electricityinfrastructure that can meet futuredemand growth’’ and ‘‘achieve [the 10items], which together characterize aSmart Grid.’’ At 292–293.
3. Robert L. Hahne and Gregory E.Aliff, ACCOUNTING FOR PUBLIC UTILITIES
(Newark, NJ: Matthew Bender, 2001),at 8–3.
4. U.S. Energy InformationAdministration, Renewable PortfolioStandards and State Mandates byState, 2008, Aug. 2010, at http://www.eia.gov/cneaf/solar.renewables/page/trends/table28.html.
5. See Leonard Hyman, AMERICA’S
ELECTRIC UTILITIES: PAST PRESENT AND
FUTURE, 2nd Ed. (Arlington, VA: PUR,1985), at 263. See also Leonard Hyman,A.S. Hyman, and R.C. Hyman,AMERICA’S ELECTRIC UTILITIES: PAST
PRESENT AND FUTURE, 8th Ed. (Vienna,VA: PUR, 2005), at 432. For recent data,see Edison Electric Institute, QuarterlyFinancial Updates, various dates.
6. Leonard Saul Goodman, THE
PROCESS OF RATEMAKING, Vol. I (Vienna,VA: PUR, 1998), at 638.
7. Robert Burns, Mark Eifert and PeterNagler, Current PGA and FAC Practices:Implications for Ratemaking in
see front matter# 2011 Elsevier Inc. All rights
Competitive Markets, NationalRegulatory Research Institute, Nov.1991, at 9.
8. These accounts are firmlyembedded within the practices of theaccounting profession in the U.S. andare not capable of being amended orchanged, as a practical matter, withoutthe scrutiny and approval of the U.S.accounting profession’s standardsboard.
9. Outside the U.S., many regulatoryjurisdictions still lack access to reliableand useful accounting data.
10. RRA, Construction Work inProgress: A State-by-State PolicyOverview, April 7, 2009, at 1–2.
11. Adjustment mechanisms mayhave been unusual in 1918, when thePennsylvania Public ServiceCommission characterized them assuch, but they are not unusual today.See R.S. Trigg, Escalator Clauses inPublic Utility Rate Schedules, UNIV. OF
PENN. LAW REV., May 1958, at 964.
12. RRA goes on to summarize thepolicy rationale for including CWIP inrate base, explaining that: ‘‘[i]nclusionof CWIP in rate base is generallyviewed favorably by investors. Suchtreatment allows the utility to collect acash rate of return on the asset while itis under development. The associatedcash flow may reduce the amount ofutility financing necessary during theconstruction program and enable autility to receive more favorableconsideration from the credit-ratingagencies, thus reducing the utilitiescost-of-capital going forward.Additionally, since including CWIP inrate base effectively ‘phases in’ therelated investment, such treatmentwill reduce the ‘rate shock’ that mightotherwise be experienced by theratepayer when the plant or project iscompleted and placed into service andthen reflected in rates in one step.’’RRA, supra note 10, at 1.
13. Id., at 1–2.
14. For a 50-state survey of RPSstandards, see American BarAssociation, Report of the RenewableEnergy Committee, Section of PublicUtility, Communications andTransportation Law, Spring 2011.
reserved., doi:/10.1016/j.tej.2011.07.005 21
22
15. Per Hope, under the ‘‘just andreasonable’’ standard, ‘‘it is the resultreached not the method employedwhich is controlling.’’ 320 U.S. 591(1944).
16. See Wayne P. Olson, At aCrossroads: Modernizing UtilityInfrastructure in a Tough CreditEnvironment, ELEC. J., Aug./Sept. 2009,at 6–26.
17. Hope, supra note 15.
18. Public Service Electric and GasCompany (PSEG), 123 FERC P 61303,2008 WL 4416764 (FERC), Sept. 30,2008.
19. Of the five most recent FERC rateinvestigations, the lowest earned ROEwas 20.83 percent for Great LakesTransmission. This leads to theconclusion that the effective thresholdto warrant investigation by the FERCwas about 20 percent.
20. Promoting Transmission Investmentthrough Pricing Reform, Order No. 679,FERC Stats. & Regs. � 31,222 (2006)(‘‘Order No. 679’’); order on reh’g,Order No. 679-A, FERC Stats. & Regs.� 31,236 (2006) (‘‘Order No. 679-A’’);order denying reh’g, 119 FERC � 61.062(2007).
21. 16 U.S.C. 824s (2006). Section 219of The Energy Policy Act of 2005, 119Stat. § 594 1241 (2005), amended theFPA. Specifically, § 824s specifies,among other things, that the FERCtransmission infrastructureinvestment rule shall promotereliable transmission and generationby ‘‘promoting capital investment’’in transmission infrastructureand provide an allowed returnon equity that ‘‘attracts newinvestment in transmission facilities.’’See http://www.law.cornell.edu/uscode/16/usc_sec_16_00000824—s000-.html.
22. Westar Energy, Inc., 122 FERC �61,268 (2008), Para. 47.
23. Olson found that ‘‘there isconsiderable evidence that the rateorders for ‘‘BBB-’’ utilities pay carefulattention to credit quality when settingrates.’’ Olson, supra note 16, at 17.
24. PSEG, supra note 18.
1040-6190/$–see front matter # 2011 Else
25. Zhongmin Wang, Settling UtilityRate Cases: An Alternative RatemakingProcedure, J. REGULATORY ECON., 26:2,2004, at 141–163.
26. Before the New York PublicService Commission, Proceeding onthe Motion of the Commission as tothe Rates, Charges, Rules andRegulation of Consolidated EdisonCompany of New York, Inc. forElectric Service, Order EstablishingThree-Year Electric Rate Plan, Case09-E-0428, Mar. 26, 2010, at 3,10–15.
27. Peoples Gas, Rider ICR,Infrastructure Cost Recovery, Ill.C.C.No 28, Fifth Revised Sheet No. 130,Feb. 17, 2010.
28. Before the New Jersey Board ofPublic Utilities, In the Matter of theProceeding for InfrastructureInvestment and a Cost RecoveryMechanism for all Gas andElectric Utilities, Decision and OrderApproving Stipulation, Docket No.EO09010049, April 28, 2009, at 3,10–15.
29. New Jersey’s economic stimulusplan, which sought to moderate theeffects on New Jersey of the worldeconomic downturn that followed the2008 financial crisis, continues inoperation, with companies required tofile quarterly compliance reports. See,for example, South Jersey Gas, CapitalInvestment Recovery TrackerQuarterly Report in Compliance withthe Board’s Order in Docket No.GO09010051, May 2, 2011.
vier Inc. All rights reserved., doi:/10.1016/j.
30. Peoples Gas, supra note 27, at 8.
31. Peoples Gas, supra note 27, at 9.
32. Richard Brealey and StewartMyers, PRINCIPLES OF CORPORATE
FINANCE, 1st Ed. (New York: McGraw-Hill, 1981), at 158.
33. S&P, ‘‘Peoples Gas Light & CokeCo.,’’ Mar. 18, 2009, at 2.
34. During the 1990s, rates werefrozen in a number of jurisdictionsbecause of settlements and litigatedproceedings related to mergers,alternative rate plans, and theintroduction of retail competition. SeeHethie Parmesano and Jeff D.Makholm, The Thaw: The End ofthe Ice Age for American Utility RateCases—Are You Ready? ELEC. J., July2004, at 69.
35. Regulatory Research Associates, athttp://www.snl.com/InteractiveX/RateCaseHistory.aspx.
36. When challenging the prudence ofmanagement on the basis of a badresult, care is needed because theregulatory agency already has onepiece of information that utilitymanagement did not, and couldnot, have at the time the decisionwas made. The evaluation ofprudence must be based on what areasonable utility would have knownat the time the costs were beingincurred, not based on 20/20hindsight, long after the costs wereincurred.
37. The Economist, in a specialsupplement on precisely this issue,points out that ‘‘for strictly selfishreasons, well-run companies willstrive for friendly long-term relationswith employees, suppliers andcustomers. There is no need for selflesssacrifice when it comes tostakeholders. It goes with theterritory.’’ The Good Company,ECONOMIST, Jan. 22–28, 2005, at 11.
38. Prof. Alfred Kahn as quoted inRichard Pierce, Jr., Gary Allison andPatrick Martin et al., ECONOMIC
REGULATION: ENERGY, TRANSPORTATION
AND UTILITIES (New York: Bobbs-Merrill, 1980), at 142.
39. Id.
tej.2011.07.005 The Electricity Journal