Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value...

40
Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Transcript of Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value...

Page 1: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Target Value Design Workshop 20 February 2020

David Umstot Summer Umstot

Page 2: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

The 5 Biggest Challenges to

Implementing Target Value Design?

© 2020 Umstot Project & Facilities Solutions, LLC

Page 3: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Challenge 1:Failure to Understand the Value Proposition

© 2020 Umstot Project & Facilities Solutions, LLC

Page 4: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Value

What the customer wants from the process. The customer defines value.

The value definition is composed of statements that describe expected outcomes, or “value” that the project will deliver.

© 2020 Umstot Project & Facilities Solutions, LLC

Page 5: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

“Value is in the eye of the beholder.”

© 2020 Umstot Project & Facilities Solutions, LLC

Page 6: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Spaceship 2.0

© 2020 Umstot Project & Facilities Solutions, LLC

Page 7: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Poseidon Desalination Plant – San Diego

© 2020 Umstot Project & Facilities Solutions, LLC

Page 8: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

182,500-square-foot LEED Platinum Energy Systems Integration Facility

National Renewable Energy Lab, Golden, Colorado

© 2020 Umstot Project & Facilities Solutions, LLC

Page 9: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

The Right Cost for the Business Case

© 2020 Umstot Project & Facilities Solutions, LLC

Page 10: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Capital Costs

Operational Costs

Total Cost of Ownership

© 2020 Umstot Project & Facilities Solutions, LLC

Page 11: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Bullitt Center, Seattle

© 2020 Umstot Project & Facilities Solutions, LLC

Page 12: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Business Continuity/Energy Efficiency/Renewable Energy

© 2020 Umstot Project & Facilities Solutions, LLC

Page 13: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Occupant Productivity

© 2020 Umstot Project & Facilities Solutions, LLC

Page 14: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Understanding value through the eyes of the customer yields excellence!

© 2020 Umstot Project & Facilities Solutions, LLC

Page 15: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Challenge 2:Failure to Understand Constraints

© 2020 Umstot Project & Facilities Solutions, LLC

Page 16: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 17: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 18: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 19: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 20: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Challenge 3:Continued Use of Antiquated Estimating Practices

© 2020 Umstot Project & Facilities Solutions, LLC

Page 21: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 22: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 23: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 24: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 25: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 26: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 27: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Challenge 4:Failure to Use Design Thinking

© 2020 Umstot Project & Facilities Solutions, LLC

Page 28: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Empathy Define Ideate Prototype Test Implement

Great design has that “wow” factor that makes products more desirable and services more appealing to users.

Page 29: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 30: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 31: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Mission GoalsDesired outcomes

WorkplanTeam

Data request

ShadowingInterviews

Volumes / ThruputWorkflows

Benchmarks

Big IdeasProcess maps

PrototypesVR

Extreme Schemes

Integrated solutionPhasing

Constructability

inspire implementideateVision Current State Future State Design State

success big questions big ideas the answer

Page 32: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 33: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 34: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 35: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Challenge 5:Failure to Collaborate

© 2020 Umstot Project & Facilities Solutions, LLC

Page 36: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

PROJECT CHARTER

© 2020 Umstot Project & Facilities Solutions, LLC

Page 37: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

Photo Credit: Austin Commercial© 2020 Umstot Project & Facilities Solutions, LLC

Page 38: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

VISUAL MANAGEMENT

© 2020 Umstot Project & Facilities Solutions, LLC

Page 39: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

© 2020 Umstot Project & Facilities Solutions, LLC

Page 40: Target Value Design Workshop - Lean Project Design & Delivery · 2020. 2. 2. · Target Value Design Workshop 20 February 2020 David Umstot Summer Umstot

YOUR TURN!

© 2020 Umstot Project & Facilities Solutions, LLC