Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located...

13
This report has been prepared by Cedrus Investments Ltd. PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 1 January 30, 2013 Global Equity Research Dr. Thomas Kenny, Chief Emerging Technology Advisor [email protected] Key Points: We believe Cokal Limited (“Cokal”; ASX: CKA) presents an opportunity for potentially substantial upside for longterm investors, as the company looks significantly undervalued. Our target price, AU$0.57 per share, is based on the summation of the discounted cash flow (DCF) valuation of the company’s 60% stake in the Bumi Barito Mineral (BBM) project (AU$207 million as at yearend 2013) and its net cash on hand (AU$25 million as at September 30, 2012). Cokal’s share price of AU$0.195 as of January 29, 2013 close translates into a 66% discount to our valuation. At the moment, our valuation of the BBM project is based entirely on its stage one production schedule. In our view, there could be further upside potential to our valuation should the production schedules of Cokal’s following coking coal projects become clearer: stage two of the BBM project, the Borneo Bara Prima (BBP) project, the Anugerah Alam Katingan (AAK) project, the Anugerah Alam Manuhing (AAM) project, the PT Silangkop Nusa Raya (SNR) project, the Tanzania projects and the Mozambique projects. BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia has the highest probability of producing in the nearterm among Cokal’s projects. In October 2012, Cokal achieved two major milestones, namely, receiving the exploration forestry permit (IPPKH) from the Indonesian government, and completing the initial prefeasibility study. In our view, receiving the IPPKH is a significant achievement, as it allows Cokal to use large capacity equipment and develop a roadway system within BBM. Furthermore, IPPKH is a prerequisite for converting the BBM exploration IUP (mining business license) into a production IUP. For the initial prefeasibility study, Cokal has come up with a detailed development plan. For stage one, production is planned to be commenced in 2Q calendar year (CY) 2014, with a total production for that stage of 18.2 million tonnes (Mt). Production is planned to be at 2 Mt per annum. Total capital expenditure for stage one, US$100 million, would be spent over CY2013CY2014. Average cash operating cost (excluding royalties of 7%) is estimated by Cokal to be US$67.9 per tonne for the first five years of production. We note that the projected average cash operating cost for stage one of BBM is meaningfully lower than its major Indonesian peer, Borneo Lumbung (with an average cash operating cost at US$77.5 per tonne during fiscal year 20112012). In our view, the cost savings could be coming from BBM’s slightly higher strip ratio for the first five years and lower marketing cost. Further exploration upside is possible for BBM. At the moment, the BBM project has a reported coal resources of 77 Mt (7 Mt indicated and 70 Mt inferred; 70% of the resources are coking coal and 30% are PCI coal). However, Cokal has an exploration target of 200 Mt to 350 Mt of coal down to a depth of 200 meters in thirteen seams in the eastern area of the BBM project (approximately 40% of the project area). Macro risks include a drop in the global coking coal demand and a major decline in coking coal prices due to a slowdown in the global economy. We estimate that if coking coal prices increase/decrease by 5%, Cokal’s net estimated profit in FY2016 (first full fiscal year of earnings contribution from the BBM project) could increase/decrease by 11%. Companyspecific risks include: The inability or delay in converting BBM’s exploration IUP into a production IUP; Higherthanexpected cash operating costs and capital expenditure; Lowerthanexpected production volume; Unexpected policy changes regarding exports, mining and/or foreign investments in Indonesia. Cokal Potentially Offers Substantial Upside for Longterm Investors as Its Shares Look Significantly Undervalued Target AU$0.57

Transcript of Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located...

Page 1: Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia

This report has been prepared by Cedrus Investments Ltd.   PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 

1

January 30, 2013 Global Equity Research 

Dr. Thomas Kenny, Chief Emerging Technology Advisor [email protected]

Key Points:                                 

We  believe  Cokal  Limited  (“Cokal”; ASX: CKA)  presents  an  opportunity  for  potentially  substantial  upside  for long‐term  investors,  as  the  company  looks  significantly undervalued. Our  target price, AU$0.57 per  share,  is based on  the  summation of  the discounted  cash  flow  (DCF) valuation of  the  company’s 60%  stake  in  the Bumi Barito Mineral (BBM) project (AU$207 million as at year‐end 2013) and its net cash on hand (AU$25 million as at September 30, 2012). Cokal’s share price of AU$0.195 as of January 29, 2013 close translates into a 66% discount to our valuation.   

At the moment, our valuation of the BBM project is based entirely on its stage one production schedule. In our view,  there  could  be  further  upside  potential  to  our  valuation  should  the  production  schedules  of  Cokal’s following  coking  coal  projects  become  clearer:  stage  two  of  the  BBM  project,  the  Borneo  Bara  Prima  (BBP) project, the Anugerah Alam Katingan (AAK) project, the Anugerah Alam Manuhing (AAM) project, the PT Silangkop Nusa Raya (SNR) project, the Tanzania projects and the Mozambique projects.   

BBM,  a  coking  coal  project  located  immediately  adjacent  to  BHP  Billiton’s  (BHP)  Juloi  tenement  in  Central Kalimantan,  Indonesia  has  the  highest  probability  of  producing  in  the  near‐term  among  Cokal’s  projects.  In October 2012, Cokal  achieved  two major milestones, namely,  receiving  the exploration  forestry permit  (IPPKH) from the Indonesian government, and completing the initial pre‐feasibility study. In our view, receiving the IPPKH is a  significant achievement, as  it allows Cokal  to use  large  capacity equipment and develop a  roadway  system within  BBM.  Furthermore,  IPPKH  is  a  pre‐requisite  for  converting  the  BBM  exploration  IUP  (mining  business license) into a production IUP.   

  For  the  initial  pre‐feasibility  study,  Cokal  has  come  up  with  a  detailed  development  plan.  For  stage  one, 

production  is planned to be commenced  in 2Q calendar year (CY) 2014, with a total production for that stage of 18.2 million tonnes (Mt). Production is planned to be at 2 Mt per annum. Total capital expenditure for stage one, US$100 million, would be spent over CY2013‐CY2014. Average cash operating cost  (excluding royalties of 7%)  is estimated by Cokal  to be US$67.9 per  tonne  for  the  first  five years of production. We note  that  the projected average cash operating cost for stage one of BBM is meaningfully lower than its major Indonesian peer, Borneo Lumbung (with an average cash operating cost at US$77.5 per tonne during fiscal year 2011‐2012). In our view, the cost savings could be coming from BBM’s slightly higher strip ratio for the first five years and lower marketing cost.  

  Further exploration upside is possible for BBM. At the moment, the BBM project has a reported coal resources of 

77 Mt (7 Mt indicated and 70 Mt inferred; 70% of the resources are coking coal and 30% are PCI coal). However, Cokal has an exploration target of 200 Mt to 350 Mt of coal down to a depth of 200 meters in thirteen seams in the eastern area of the BBM project (approximately 40% of the project area).  

  Macro risks  include a drop  in  the global coking coal demand and a major decline  in coking coal prices due  to a 

slowdown  in  the  global  economy. We  estimate  that  if  coking  coal prices  increase/decrease by 5%, Cokal’s net estimated  profit  in  FY2016  (first  full  fiscal  year  of  earnings  contribution  from  the  BBM  project)  could increase/decrease by 11%. Company‐specific risks include: 

The inability or delay in converting BBM’s exploration IUP into a production IUP;  

Higher‐than‐expected cash operating costs and capital expenditure; 

Lower‐than‐expected production volume;  

Unexpected policy changes regarding exports, mining and/or foreign investments in Indonesia. 

Cokal Potentially Offers Substantial Upside for Long‐term Investors as Its Shares Look Significantly Undervalued 

Target 

AU$0.57 

Page 2: Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia

This report has been prepared by Cedrus Investments Ltd.   PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 

2

  Table of Contents 

 

I. Company Description  .................................................................................................................................... 3

II. Financial Information of Cokal ........................................................................................................................ 4

Income Statement  ............................................................................................................................................................... 4 

Balance Sheets ...................................................................................................................................................................... 4 

III.   Competitive Advantages of Indonesian Coal .............................................................................................................. 5 

IV.   Project Economics – Bumi Barito Mineral (BBM) and Other Projects ........................................................................ 5 

V.   Valuation ................................................................................................................................................................... 10 

VI.   Management  ............................................................................................................................................................ 11 

VII.   Risks  ......................................................................................................................................................................... 12 

Important Disclosures  ........................................................................................................................................................ 13 

   

 

                   

Page 3: Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia

This report has been prepared by Cedrus Investments Ltd.   PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 

3

 I.  Company Description 

 Cokal Limited (Cokal)  is an emerging Australian Securities Exchange  (ASX)‐listed coal company (ASX: CKA), with a key focus on metallurgical coal exploration and mining. The company commenced business as Jack Doolan Capital Pty Ltd. (JDC), a private company, formed primarily by the current Board of Directors. In December 2010, JDC was acquired by the then ASX‐listed Altera Resources Limited, with the Board of JDC assuming the control of Altera Resources. Altera Resources was renamed Cokal Limited in February 2011.   Cokal’s vision  is to build a global metallurgical coal business, which delivers valuable results to all  its stakeholders. At the moment, Cokal has acquired stakes in seven Indonesian coal exploration projects, namely 60% stakes in the Bumi Barito Mineral  (BBM) and Borneo Bara Prima  (BBP) projects  located  in Central Kalimantan, 75%  stakes  in Anugerah Alam Katingan (AAK) and Anugerah Alam Manuhing (AAM)  in Central Kalimantan, and a 75%  interest  in PT Silangkop Nusa Raya  (SNR), which owns  three exploration  licenses  in West Kalimantan. The company  is also  involved  in other early‐stage coking coal mining opportunities in Tanzania and Mozambique.   Among the aforementioned coking coal exploration projects, the BBM project has the highest probability of producing in the near term. According to Cokal, production of the BBM project is expected to start in 2Q calendar year (CY) 2014. As such, the focus of this report and our valuation on Cokal is primarily based on the BBM project. We may revise our valuation on Cokal in the future should the production roadmap of the company’s other projects become clearer.     

Cokal’s Coking Coal Projects in Indonesia 

  Source: Cokal 

Page 4: Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia

This report has been prepared by Cedrus Investments Ltd.   PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 

4

 II.  Financial Information of Cokal  

 In this section of the report, an analysis of the key financial data of Cokal is provided, including estimated earnings until fiscal year (FY) 2016 and the potential financing needs by Cokal until the BBM project begins to produce.  

 Income Statement    For  FY2011  and  FY2012  (fiscal  year  ending  June  30),  Cokal’s  net  losses were  AU$2.6 million  (mn)  and  AU$6.3 mn respectively. As Cokal’s coking coal projects have not been producing yet, revenues in FY2011 and FY2012 were mainly coming  from  interest  income. According  to  Cokal,  production  of  the BBM  project  is  expected  to  commence  in  2Q CY2014. As  such, we  are  estimating  that  the BBM project would  start  contributing  earnings  to  Cokal  from  FY2015 onward. We may revise our earnings estimates on Cokal  in the future should there be any changes to the estimated production  schedules  of  the  BBM  project  and  should  the  production  roadmap  for  the  company’s  other  projects become clearer.     

Earnings Estimates for Cokal during FY2013‐FY2016 

(AU$ mn)  FY2013E  FY2014E  FY2015E  FY2016E 

CKA's attributable net profit from BBM  0   0   40   87  

Corporate level net income/(loss)  (7)  (7)  (7)  (7) 

Net profit/(loss)  (7)  (7)  34   81  

              

EPS (AU$)  (0.02)  (0.02)  0.08   0.20  

No. of shares outstanding (mn)  411   411   411   411  

 Source: Cedrus’ estimates  

 Key assumptions of our earnings estimates  include  coking  coal prices, unit production  cost and production volume. While unit production cost and production volume are mainly based on Cokal’s guidance, coking coal price assumptions are based on the  latest contract coking coal prices for 4Q CY2012. We will discuss these variables  in further detail  in section  IV “Project Economics – Bumi Barito Mineral  (BBM) and Other Projects” of this report. We note that Cokal’s earnings are very sensitive  to coking coal price changes;  for example,  if coking coal prices  increase/decrease by 5%, Cokal’s  net  profit  in  FY2016  (first  full  fiscal  year  of  earnings  contribution  from  the  BBM  project)  is  estimated  to increase/decrease by 11%.    

 Balance Sheets  Cokal  is debt  free as at September 30, 2012. To‐date, the company’s operations have been  funded mainly by equity capital raised such as  from the share placements to Passport Capital at AU$0.75 per share  for 16 mn shares  in April 2011  (AU$12 mn)  and AU$0.50  per  share  for  17 mn  shares  in November  2011  (AU$8.5 mn),  and  to  BlackRock  at AU$0.50 per share for 40.2 mn shares in December 2011 (AU$20.1 mn). As at year‐end of FY2012, Cokal had cash and cash equivalents of about AU$29.5 mn. Based on Cokal’s quarterly report, its ending cash balance as at September 30, 2012 was AU$25.3 mn; this  implies a cash outlay rate of AU$4.3 mn for 1Q FY2013, which was about 50% related to exploration and evaluation and 50% related to administration.   Based on the AU$25.3 mn cash on hand as at September 30, 2012, a cash outlay rate of AU$4.3 mn per quarter (based on the cash outlay rate in 1Q FY2013) and an estimated capital expenditure of US$100 mn for the BBM project (before the  project  becomes  operational  in  2Q  CY2014), we  believe  it  is  very  likely  that  Cokal may  need  to  plan  another financing in the next 12‐18 months in order to satisfy its investment needs.   

 

Page 5: Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia

This report has been prepared by Cedrus Investments Ltd.   PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 

5

 III.  Competitive Advantages of Indonesian Coal  

 The key competitive advantage of the Indonesian coal mining industry is that the country is closer to Asia’s major coal markets  than  its major  peer,  Australia.  Therefore,  its  transportation  costs  for  coal  exports  are  significantly  lower. Moreover,  in general,  Indonesia has more flexible and modular  inland transportation systems.   Within  Indonesia, the Kalimantan provinces have the largest coal resources.  

 

Comparison between Major Coal Ports in Australia (Abbot Pt), Indonesia (Balikpapan) and South Africa (Richards Bay) in terms of Proximity (in Nautical Miles) with Asia’s Major Coal Markets  

  Source: Roleva Energy 

 

Indonesia’s Coal Resources by Province, 2009 (Million Tonnes) 

Province  Inferred  Indicated  Measured   Total 

Sumatra  13,949   10,735   7,699   32,383  

Kalimantan  21,029   2,894   13,156   37,079  

Other  96   33   55   184  

Total  35,074   13,662   20,910   69,646  

Source: Indonesian Coal Book 

  

IV.  Project Economics – Bumi Barito Mineral (BBM) and Other Projects 

 Bumi Barito Mineral (BBM)  Cokal has a 60% stake in the Bumi Barito Mineral (BBM) project. The project comprises approximately 19,920 hectares and  is  located  immediately adjacent to BHP Billiton’s Juloi tenement  in Central Kalimantan. On August 6, 2012, Cokal reported  that  the  project  has  77  million  tonnes  (Mt)  of  coal  resources  (7 Mt  indicated  and  70 Mt  inferred)  in accordance with the JORC Code. Approximately 70% of the resources are coking coal and 30% are PCI coal. In addition, the BBM project has an exploration target of 200 Mt to 350 Mt of coal down to a depth of 200 meters (m) in thirteen seams in the eastern area of the BBM project (approximately 40% of the project area).  

Page 6: Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia

This report has been prepared by Cedrus Investments Ltd.   PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 

6

 Initially, premium coking coal from Seam J would be extracted; no coal washing is required from the initial production and all of the coal extracted could be shipped directly, reducing operating expenses and capital expenditure. Borehole cores for Seam B, C and D have been analyzed and produced two coal types within the BBM eastern area, coking coal and PCI coal. The coals are typically low ash (4% to 8%), low sulphur (0.2% to 0.4%) and ultra‐low phosphorus (0% to 0.003%). Coking coal typically has a good swelling index of 8 to 9 and volatile matter in the range of 18% to 20%.  PCI coal has very high carbon content (80% to 85%) due to the low volatile matter (around 10%).   

Resources by Seam and by Depth 

Seam name 

Seam Thickness 

(m) 

Indicated Resources 

(Mt) 

Inferred Resources 

(Mt) 

Total Resources 

(Mt)  

Depth Range (m) 

Indicated Resources 

(Mt) 

Inferred Resources 

(Mt) 

Total Resources 

(Mt) 

J  1.4   7.0   10.0   17.0   0‐50  4.0   8.0   12.0  

D  1.3   ‐  25.0   25.0   51‐100  3.0   13.0   16.0  

C  1.1   ‐  20.0   20.0   101‐150  0.0   12.0   12.0  

B  0.9   ‐  15.0   15.0   151‐200  0.0   11.0   11.0  

Total     7.0   70.0   77.0   201‐300  0.0   26.0   26.0  

Total  7.0   70.0   77.0  

Source: Cokal 

 

Coal Quality of J Seam 

 Source: Cokal 

 

Coal Quality of B, C and D Seams 

 Source: Cokal 

 In October 2012, Cokal achieved two key milestones  for the BBM project, namely, receiving the exploration  forestry permit, Pinjam Pakai (IPPKH), from the Indonesian government, and completing the initial pre‐feasibility study.   IPPKH  is critical  if Cokal wants  to use  large capacity equipment  for  the BBM project;  in particular,  it allows Cokal  to develop a roadway system within BBM. In addition, IPPKH is a crucial pre‐requisite for converting the BBM exploration Izin Usaha Pertambangan (IUP; i.e. Mining Business License) into a production IUP.   For  the  initial pre‐feasibility study, Cokal has come up with a  two‐stage development plan  for  the BBM project. For stage one, production  is planned  to be  commenced  in 2Q CY2014, with  total production  for  that  stage of 18.2 Mt. Annual  targeted production  is at 2 Mt;  the  targeted production  rate  is planned  to be achieved by 4Q CY2014. Total capital expenditure  (capex)  for  stage one would be about US$100 mn, and  it would be  spent over CY2013‐CY2014. 

Product Yield (%)Inherent 

MoistureAsh

Volatile 

Matter

Fixed 

Carbon

Total 

Suphur

Calorific 

Value 

(kcal/kg)

CSNRelative 

DensityPhosphorus

Raw Coal ‐ 0.8 4.6 ‐ 14.3 17.9 71.1 0.40 7,752 9+ 1.35 0.003

Washed Coal  @F1.60 87.95 1.0 5.2 18.3 75.5 0.47 8,237 9+ 1.32 0.002

Seam ProductInherent 

MoistureAsh

Volatile 

Matter

Fixed 

Carbon

Total 

Suphur

Calorific 

Value 

(kcal/kg)

CSNRelative 

DensityPhosphorus

D PCI 0.9 5.1 10.3 83.7 0.43 8,204 1.5 1.36 0.002

D Coking 0.9 5.1 14.4 79.7 0.39 8,287 9.0 1.33 0.002

C PCI 1.0 5.5 9.3 84.3 0.41 8,191 1.0 1.36 0.001

C Coking 0.5 5.5 14.5 79.5 0.24 8,265 8.5 1.33 0.001

B PCI 0.9 14.0 9.5 75.6 0.41 7,676 1.5 1.40 0.004

B Coking 0.5 12.6 13.8 73.1 0.23 7,591 7.5 1.38 0.002

Page 7: Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia

This report has been prepared by Cedrus Investments Ltd.   PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 

7

Average cash operating cost (excluding royalties of 7%) is estimated to be US$67.9 per tonne for the first five years of production.   

Estimated Capital Expenditure and Cash Operating Cost per Tonne (excluding Royalties) 

Development Capital for Stage 1  US$ mn  Cash Operating Cost  US$/ tonne 

Direct ship to start production  50   Average for first 5 years  67.9  

Ramp up to 2 Mt per annum  50   Stand‐alone life of mine  89.6  

Total  100  

Source: Cokal 

 At the moment, there is no clear production schedule for stage two. It is expected that additional capex would have to be spent on expanding the mining, port and  logistics operations. Furthermore, a coal handling and preparation plant would have to be constructed. As such, our analysis and valuation of the BBM project is mainly based on stage one.   Average selling price assumptions  According to Cokal’s October 31, 2012 announcement, the company is assuming a long‐term hard coking coal price of less than US$170 per tonne and a semi‐soft coking coal price of US$122 per tonne. In our view, these assumptions look reasonable as the  latest contract price  for hard coking coal  for 4Q CY2012 was US$163 per tonne.  In our model, we have assumed a long‐term hard coking coal price of US$160 per tonne and a semi‐soft coking coal/PCI price of US$120 per  tonne. While our hard‐coking  coal price  assumption  is based on  the  latest  contract price, our  semi‐soft  coking coal/PCI price assumption  is a  function of  the hard coking coal price assumption; particularly, we have assumed  the long‐term  semi‐soft  coking  coal/PCI  price  to  be  equaled  to  75%  of  the  long‐term  hard  coking  coal  price  based  on Sumitomo’s historical coking coal purchase prices.  

Historical Hard Coking Coal Contract Prices, CY2007‐CY4Q2012 

 Source: Wesfarmers 

 

Sumitomo’s Historical Semi‐soft Coking Coal/PCI Purchase Price as a % of Hard Coking Coal Purchase Price 

 Source: Sumitomo 

 Cash operating cost assumptions  Cokal assumes the average cash operating cost to be US$67.9 per tonne for the first five years and US$89.6 per tonne during the mine’s life. In our view, the average cash operating cost assumption for the first five years looks reasonable as it is in‐line with the company’s Australian peers such as Whitehaven Coal Limited (ASX: WHC) and Wesfarmers (ASX: WES). However, that assumption is significantly lower than its Indonesian peer, Borneo Lumbung. In our view, the cost savings by Cokal over its Indonesian competitor may be coming from BBM’s slightly higher strip ratio for the first five years and  lower marketing  cost  (as Cokal plans  to market BBM’s  coal by  itself versus Borneo  Lumbung, which uses Glencore [805.HK] to market its coal).   

(US$/tonne) CY2007 CY2008 CY2009 CY2Q10 CY3Q10 CY4Q10 CY1Q11 CY2Q11 CY3Q11 CY4Q11 CY1Q12 CY2Q12 CY3Q12 CY4Q12

Hard coking coal  

contract price92 304 124 212 235 209 234 358 322 293 238 212 220 163

Period on period 

changeNA 230% ‐59% 70% 11% ‐11% 12% 53% ‐10% ‐9% ‐19% ‐11% 4% ‐26%

As a % of Hard coking price (CY) 2007 2008 2009 2Q10 3Q10 4Q10 1Q11 2Q11 3Q11 4Q11 1Q12 2Q12 Average

Semi ‐soft coking coa l 66% 80% 64% 84% 76% 68% 80% 78% 72% 63% 76% 69% 73%

PCI  coal 71% 82% 69% 85% 80% 72% 80% 83% 73% 73% 73% 73% 76%

Average 68% 81% 67% 84% 78% 70% 80% 81% 73% 68% 74% 71% 75%

Page 8: Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia

This report has been prepared by Cedrus Investments Ltd.   PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 

8

 

Whitehaven, Wesfarmers and Borneo Lumbung’s Cash Operating Cost per Tonne during FY2011‐FY2012 

(AU$ per tonne)  FY2011  FY2012 

Whitehaven  60.5   69.9  

Wesfarmers  63.8   60.6  

Borneo Lumbung  77.0   78.0  

Source: Whitehaven, Wesfarmers, Borneo Lumbung 

 Of  the US$67.9 cash operating cost per  tonne, US$29  is  transportation cost. While  the proportion of  transportation cost  looks high  (43% of  total) when compared with Borneo  Lumbung’s barging and  logistic  costs  (26% of  total), we believe it is reasonable as coal mined at BBM will be transported some 774 km from the mine site to the Java Sea.  

Proposed Transportation Route for BBM’s Coking Coal 

     Source: Cokal 

 

Page 9: Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia

This report has been prepared by Cedrus Investments Ltd.   PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 

9

 Other projects  Borneo Bara Prima (BBP)  Cokal also has a 60% stake  in the Borneo Bara Prima (BBP) project. The BBP project comprises approximately 13,050 hectares and  is  located adjacent  to BHP Billiton’s Maruwai  tenement  in Central Kalimantan. According to Cokal,  two drilling  rigs  secured  for BBP have  commenced drilling, and  core  samples have been  sent  to Australia  for  laboratory analysis. Initial results indicate some of the coal is suitable for the PCI and anthracite markets. To‐date, the drilling has only tested the outcrops in the southern part of the BBP project; another two locations of mapped outcrops have yet to be tested for coal quality attributes.     Anugerah Alam Katingan (AAK)  Cokal has a 75% stake  in the Anugerah Alam Katingan (AAK) project. The AAK project,  located  in Central Kalimantan, covers approximately 5,000 hectares and has five outcrops (1‐2m in thickness) with bright coal and possible anthracite.  Anugerah Alam Manuhing (AAM)  Cokal  has  a  75%  interest  in  the  Anugerah  Alam  Manuhing  (AAM)  project.  The  AAM  project,  located  in  Central Kalimantan, encompasses approximately 10,000 hectares and has eleven outcrops (1‐2m in thickness) with bright coal. Mapping and preliminary exploration work has been started in AAM to identify the coal potential within the tenement.   PT Silangkop Nusa Raya (SNR)  After  the  conclusion of  a  technical due diligence, which  involved  a Cokal  geological  team  conducting  a preliminary surface mapping exercise, Cokal has completed the acquisition of 75.2% of SNR in FY2012. SNR holds three exploration licenses in West Kalimantan near the Malaysian border. The SNR licenses cover an area of 13,000 hectares.  Recent exploratory work  for metallurgical coal  in  the area has been  limited, although surfaces samples of coal  from surrounding areas had shown good coking coal properties, and there is possibility of opening up a new area. According to Cokal, SNR’s outcrop samples show high volatile, low ash, moderate sulfur and low phosphorus coking coal.   Tanzania  An initial drilling program has been completed in Tanzania, with seven boreholes drilled on the Manda Project (Cokal owns 50%) and one borehole drilled on the adjoining Iwela lease (Cokal owns 60%). However, the drilling results from the Tanzanian  tenements have not yielded any viable coal seams. Cokal will continue  to work with  its  joint venture partner, Tanzoz Resource Company  Limited, a private  company,  to gain access  into other parts of Tanzania  for  the purpose of conducting a coal exploration program.    Mozambique  Cokal  signed  a  co‐operation  agreement with  Empresa Mocambicana de  Exploracao Mineira  (EMEM  – Mozambique Mining Exploration Company)  to explore  tenements  in Mozambique  for coal mining potential and  to  jointly develop mines and associated facilities. EMEM is a state‐owned corporation formed by the Mozambique government in order to participate in mining projects, undertake exploration and mining development as well as promoting value addition to mineral products. Under the terms of the agreement, EMEM will bring tenements to Cokal for review, and if deemed suitable by Cokal, these tenements will be brought into the 80:20 (Cokal:EMEM) joint venture. To‐date, no tenements have been deemed suitable for exploration.     

Page 10: Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia

This report has been prepared by Cedrus Investments Ltd.   PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 

10

 V.  Valuation 

 We are assigning Cokal a target price of AU$0.57 based on the summation of the DCF valuation of the company’s 60% interest  in  the BBM project and Cokal’s  latest net cash on hand as at September 30, 2012.  In our view, Cokal  looks undervalued, as it is trading at a 66% discount to our target price of AU$0.57 based on the company’s closing price as at January 29, 2013. We believe Cokal’s other projects such as the BBP, AAK, AAM, SNR, the Tanzania and Mozambique projects could provide further upside to the company’s valuation should their development schedules become clearer.   

Valuation Estimate for Cokal (assumed AU$0.96 per US$1.00) 

Valuation for Cokal Cokal's Stake 

Valuation Method 

At end  CY2013 (AU$ mn) 

BBM  60%  DCF @ 12%  207  

Add: latest net cash/(debt) [9/30/2012]     Company data  25  

Net asset value (NAV)        233  

NAV per share (AU$)        0.57  

No. of shares outstanding (mn)        411  

Closing price as at January 29, 2013 (AU$)        0.195  

(Discount)/Premium to NAV (%)        ‐66% 

 Source: Cedrus’ estimates 

 

DCF Model for the BBM Project 

 Source: Cedrus’ estimates 

 Note that we have assumed Cokal’s ownership of the BBM project to decline from 60%  in CY2021 to 56%  in CY2022 and to 49% in CY2023. The reason is that under Indonesia’s mining law, the holder of an IUP for the purpose of foreign investment  is obligated  to divest  its  shares gradually  so  that on  the  tenth year of  the operation at  least 51% of  its shares will be held by an Indonesian citizen.   

Required Ownership by an Indonesian Citizen under the Mining Law 

Sixth year   20% 

Seventh year  30% 

Eighth year  37% 

Ninth year  44% 

Tenth year  51% 

Source: Indonesian Ministry of Mining & Energy 

  

Year (US$ mn) ‐ calendar year 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023

Revenues 75 302 302 302 302 302 302 302 302 181

Less : cash operating costs (34) (136) (136) (136) (136) (142) (148) (154) (160) (99)

Less : roya l ties (5) (21) (21) (21) (21) (21) (21) (21) (21) (13)

Cash profit 36 145 145 145 145 139 133 127 121 69

Less : tax (7) (34) (34) (34) (34) (32) (31) (29) (28) (15)

Free cash flow before capex 0 30 111 111 111 111 107 102 98 93 54

CKA's  ownership of BBM 60% 60% 60% 60% 60% 60% 60% 60% 56% 49%

Attributable FCF before capex to CKA 0 18 67 67 67 67 64 61 59 52 27

Less : capex borne  by CKA (25) (75) 0 0 0 0 0 0 0 0 0

Attributable actual FCF to CKA (25) (57) 67 67 67 67 64 61 59 52 27

Page 11: Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia

This report has been prepared by Cedrus Investments Ltd.   PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 

11

 VI.  Management 

 Board of Directors and Company Secretaries 

Board of director  Mr. Peter Lynch  Executive Chairman 

Board of director  Mr. Pat Hanna  Executive Director 

Board of director  Mr. Jim Middleton  Managing Director/CEO 

Board of director  Mr. Domenic Martino  Non‐Executive Director 

Company secretary  Mr. Duncan Cornish  Joint Company Secretary 

Company secretary  Mr. Victor Kuss  Joint Company Secretary/CFO 

Source: Cokal 

 Cokal’s management team has tremendous experience in the coal and finance industries in Australia and overseas: 

Mr. Peter Lynch, Executive Chairman, has held various positions such as mining engineer, project manager, mine  manager,  general  manager  and  managing  director  within  the  coal  industry  in  Australia  since  his graduation with a Mining Engineering degree in the University of New South Wales in 1988. He has a proven track record in coal project evaluation, development and operation. Furthermore, he was responsible for the design  and  construction  of  one  of  Australia’s  best  producing  longwall  projects,  Oaky  North.  Prior  to  his appointment at Cokal, he was the President, CEO and Director of Waratah Coal Inc., a Toronto Stock Exchange (TSX)‐listed company, which was taken over by the Mineralogy Group. Mr. Lynch is a member of Cokal’s Audit Committee.  

Mr.  Pat  Hanna,  Executive  Director,  has  over  30  years  of  experience  as  a  coal  geologist  in  the  areas  of exploration  and  evaluation,  including planning, budgeting  and managing  drilling programs  in Australia  and Indonesia  since his graduation  from  the University of New South Wales  in 1976. When Mr. Hanna was  the Exploration  Manager  for  Riversdale  Mining,  he  was  principally  responsible  for  the  discovery  and documentation of a new coking coal basin  in Mozambique. Furthermore, Mr. Hanna was a member of  the JORC committee, and he has authored and co‐authored numerous coal  industry publications. Mr. Hanna  is a member of Cokal’s Audit Committee.  

Mr.  Jim  Middleton,  Managing  Director  and  Chief  Executive  Officer,  has  held  various  positions  such  as technical, operational, exploration and corporate in the coal industry in Australia, including Coal Allied, Exxon, Glencore, Xstrata and  Illawarra Coal since 1981. He has a reputation  for designing and developing  low‐cost, high‐production,  and  innovative  projects.  For  example, he  designed  and  built  Xstrata’s  highest  ROI United Longwall Project with  a payback period of 12 months. Prior  to his  appointment  at Cokal, he was  the Vice President‐Mining Operations of Illawarra Coal owned by BHP Billiton.     

Mr. Domenic Martino, Non‐Executive Director, is a Chartered Accountant and an experienced director of ASX‐listed  companies  such  as  Pan  Asia  Corporation  Limited  (ASX:  PZC),  Synergy  Plus  Limited  (ASX:  SNR), Australasian  Resources  Limited  (ASX:  ARH)  and  Clean  Global  Energy  Limited  (currently  known  as  Citation Resources Limited  [ASX: CTR]). He has significant experience  in  the development of “micro‐cap” companies and was a key player  in  the re‐birth of a broad grouping of ASX companies  including Sydney Gas, Pan Asia, Clean  Global  Energy  and  NuEnergy  Capital.  As  a  former  CEO  of  Deloitte  Touche  Tohmatsu  Australia, Mr. Martino has strong reputation in the Australian and Chinese capital markets. He has a proven track record in capital raisings across a range of markets and a lengthy track record of closing key energy and resources deals with key local players in Indonesia. Mr. Martino is the Chairman of Cokal’s Audit Committee.  

Mr.  Duncan  Cornish,  Joint  Company  Secretary,  is  an  accomplished  and  highly  regarded  corporate administrator and manager. He has many years of experience in pivotal management roles in capital raisings and stock exchange listings for numerous companies on the Australian Securities Exchange (ASX), AIM Market of the London Stock Exchange and the Toronto Stock Exchange (TSX). Mr. Cornish is highly skilled in the areas 

Page 12: Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia

This report has been prepared by Cedrus Investments Ltd.   PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 

12

of  company  financial  reporting,  company  regulatory,  secretarial  and  governance,  business  acquisition  and disposal due diligence. He has worked with Ernst & Young and PricewaterhouseCoopers both in Australia and the UK. Mr. Cornish is a Chartered Accountant.  

Mr. Victor Kuss, Chief  Financial Officer  and  Joint Company  Secretary, has  tremendous  experience  in M&A activities  and  capital  raising.  He  has  a  strong  track  record  in  the  successful  growth  and  development  of resources  and  resource  related  companies.  Mr.  Kuss  is  a  Chartered  Accountant  and  has  a  Masters  in Economics.    

  

VII.  Risks 

 As coking coal is a key raw material for 70% of the world’s steel industry, a decline in the global steel demand due to a slowdown in the global economy would affect the demand and prices of coking coal. As highlighted previously, Cokal’s earnings are highly sensitive  to changes  in coking coal prices. Therefore, a  further slowdown  in  the global economy could significantly  impact Cokal’s earnings. However,  in the case of a further deceleration  in the global economy, we believe Cokal would be in a better position than most of its global peers, as the cash operating costs of its BBM project it forecasts rank at the low end of the global cost curve. 

In our  view,  company‐specific  risks  for Cokal  include  (a)  the  inability or  delay  in  converting BBM’s  exploration  IUP license into a production IUP license, (b) higher‐than‐expected cash operating costs and capex, (c) lower‐than‐expected production volume, and  (d) unexpected policy changes with respect to exports, mining and/or  foreign  investment  in Indonesia.  

 

 

 Source: Cokal 

 

 

Page 13: Target Cokal Potentially Offers Substantial Upside …...BBM, a coking coal project located immediately adjacent to BHP Billiton’s (BHP) Juloi tenement in Central Kalimantan, Indonesia

This report has been prepared by Cedrus Investments Ltd.   PLEASE SEE IMPORTANT DISCLOSURES BEGINNING ON PAGE 13 

13

 IMPORTANT DISCLOSURES       

STOCK OWNERSHIP AND CONFLICT OF INTEREST DISCLOSURE  

Neither Thomas Kenny nor  the  rest of  the  research  team or  their households  is  an owner of Cokal  Limited common shares. 

Cedrus  Investments  Ltd.  (“Cedrus”)  does  and  seeks  to  do  business  with  companies  covered  in  research  reports distributed by Cedrus, and Cedrus is an investor of the subject company and may have investment banking relationship with the subject company. As a result, investors should be aware that the firm may have a conflict of interest that could affect  the  objectivity  of  this  report.  Cedrus will  identify  such  companies  in  the  reports  of  the  companies  covered. Therefore, investors should consider this report as only a single factor in making their investment decision.  

Cedrus will receive or has received compensation for investment banking services provided within the past 12 months from Cokal Limited. 

Cedrus will receive or has received within the past 12 months compensation from Cokal Limited. 

ANALYST CERTIFICATION 

Thomas Kenny hereby certifies that the views expressed  in this research report accurately reflect his personal views about the subject companies and their securities. He also certifies that he has not been, and will not be, receiving direct or indirect compensation in exchange for expressing the specific recommendations in this report. 

For additional information, please send an e‐mail to [email protected]  

For private circulation only. This  report  is prepared by Cedrus and  is  for  informational purposes only and  is not  intended  to be, nor should  it be construed  to be,  an  advertisement or  an offer or  a  solicitation of  an offer  to buy or  sell  any  securities.  The  information herein, or upon which opinions have been based, has been obtained from sources believed to be reliable, but no representations, express or implied, or guarantees, can be made as to their accuracy, timeliness or completeness. The information and opinions in this report are current as of the date of the report. We do not endeavor to update any changes to the  information and opinions  in this report. Unless otherwise stated, all views expressed herein (including estimates or forecasts) are solely those of our research department and subject to change without notice.  

This report does not take into account the specific investment objectives, financial situation, and the particular needs of any specific company that may  receive  it.  Before  acting  on  any  advice  or  recommendation  in  this  report,  companies  should  consider whether  it  is  suitable  for  their  own particular circumstances. The value of  securities mentioned  in  this  report and  income  from  them may go up or down, and  investors may  realize losses on any  investments. Past performance  is not a guide to future performance. Future terms are not guaranteed, and a  loss of original capital may occur. 

Neither  the  analysts  responsible  for  this  report  nor  any  related  household members  are  officers,  directors,  or  advisory  board members  of  any covered company. No one at a covered  company  is on  the Board of Directors of Cedrus or  its affiliates. The compensation  for  the analysts who prepare  reports  is determined exclusively by senior management. Analyst compensation  is not based on  investment banking  revenues; however, compensation may relate to the revenues of Cedrus as a whole, of which investment banking, sales and trading are a part.   Cedrus does engage in investment banking. Cedrus does trade securities on a principal basis; however, Cedrus’ research analysts are not prohibited from owning securities they cover through Research Reports.  

 

Copyright 2013 Cedrus Investments Ltd.  All rights reserved. Any unauthorized use or disclosure prohibited.