Tall Buildings, Deep Foundations - Middle East

87
Coffey Geotechnics TALL BUILDINGS, DEEP FOUNDATIONS; MIDDLE EAST EXPERIENCES The 2009 Terzaghi Oration Harry Poulos Coffey Geotechnics

description

Description of foundation systems

Transcript of Tall Buildings, Deep Foundations - Middle East

  • Coffey Geotechnics

    TALL BUILDINGS, DEEP FOUNDATIONS; MIDDLE EAST EXPERIENCES

    The 2009 Terzaghi Oration

    Harry PoulosCoffey Geotechnics

  • OUTLINE

    Design Process for High-Rise Buildings Emirates Twin Towers Project

    Investigations Design Load tests Tower foundation performance

    Burj Dubai Foundation design Load tests Foundation performance

    Gold Coast Building

  • Henry David Thoreau Walden (1854)

    If you have built castles in the air,Your work need not be lost;That is where they should be.Now put the foundations under them.

  • FOUNDATION DESIGN PROCESS

    Site characterization Geology Stratigraphy Quantification of relevant geotechnical parameters.

    Based on: In-situ testing Laboratory testing Load testing

  • FOUNDATION DESIGN PROCESS

    Foundation Type & Layout. Usually piles or piled raft

    Based on: Foundation loadings Design criteria Construction issues Material availability

  • FOUNDATION DESIGN PROCESS

    Design Issues1. Ultimate capacity2. Settlement3. Differential settlement & tilt4. Dynamic behaviour5. Earthquake response6. Structural strength of foundation elements7. Durability

  • LOCATION OF DUBAI PROJECTS

  • Emirates Site - 1996

  • SITE PLAN & BOREHOLES

  • INVESTIGATION PROGRAM

    23 boreholes, up to about 80m depth (maximum) Trial pits SPT in upper layers Undisturbed sampling Water samples Permeability tests Pressuremeter tests Vertical seismic shear wave profiling Uniformity borehole testing

  • LABORATORY TESTING

    Conventional laboratory & field tests Specialized testing

    Site uniformity testing (geophysical) Cyclic triaxial testing

    Effects of repetitive wind loading Stress path triaxial testing

    Deformation parameters CNS testing

    Ultimate shaft friction Resonant column testing

    Dynamic shear modulus & damping

  • GEOTECHNICAL PROFILE & MODEL FOR EMIRATES SITE

    Eu MPa E' MPa fs kPa fb MPa pu MPa

    Silty Sand 40 30 18 0.2 0.1Silty Sand 125 100 73 1.5 1.5

    Calcareous Sandstone 700 500 200 2.3 2.3

    Silty Sand 125 100 150 1.9 1.9

    Calcisiltite 500 400 450 2.7 2.7

    " 90 80 200 2.0 2.0

    " 700 600 450 2.7 2.7

  • FOUNDATION TYPES

    Towers Piled raft foundations

    Podium Piles, pile groups

  • LOAD TEST PROGRAM

    Below each tower:

    Compression test to 3000t, L=40m, d=0.9m Static tension test: L=25m, d=0.6m or 0.7m Cyclic tension test Lateral load test

    Class A predictions made using assessed design parameters

  • PREDICTION METHODS

    Axial Response Non-Linear boundary element analysis PIES program

    Lateral Response Non-Linear boundary element analysis ERCAP program

    Cyclic Tension Test Non-Linear boundary element analysis SCARP program

  • THE EMIRATES PROJECT, DUBAI

  • SETUP FOR COMPRESSION PILE TESTS

    (-2.00)

    (-0.50)(-1.50)

    (-5.00)

    (-10.0)

    (-16.0)

    (-20.0)

    (-25.0)

    (-30.0)

    (-36.0)

    (-40.0)

    Working platform

    Unit 1 - Silty sand

    Unit 2 - Calcareous sandstone

    Unit 4 - Calcisiltite

    Unit 3 - Silty sand

    20301285

    900

    Ground anchors

    Reference beams

    Footprint of the ground anchorsat the ground level

    No. 1 Extensometer

    No. 4 Strain gauges

    22 Nos of ground anchors

  • 3000t LOAD TEST WITH REACTION ANCHORS

    Emirates Project, Dubai

  • LOAD-SETTLEMENT CURVES FOR PILE P3(H)

    0 10 20 30 400

    5000

    10000

    15000

    20000

    25000

    30000

    Appl

    ied L

    oad

    (kN)

    Settlement (mm)

    PredictedMeasured

  • PREDICTED & MEASURED AXIAL LOAD DISTRIBUTIONS

    0 5000 10000 15000 20000 25000 30000

    -40-38-36-34-32-30-28-26-24-22-20-18-16-14-12-10

    -8-6-4-202

    Leve

    l DM

    D (m

    )

    Measured (15000 kN)Measured (23000 kN)Predicted

    Load (kN)

  • LOAD-MOVEMENT CURVES FOR UPLIFT TEST

    -35 -30 -25 -20 -15 -10 -5 00

    1000

    2000

    3000

    4000

    5000

    6000

    Appl

    ied L

    oad

    (kN)

    MeasuredPredicted

    Uplift (mm)

  • ULTIMATE SHAFT FRICTION FROM TESTS

    0 100 200 300 400 500 600 700

    50

    40

    30

    20

    10

    0

    Dept

    h (m

    )

    Ultimate Skin Friction kPa

    Design valuesDeduced from P3 (hotel) pile test (compression)Deduced from P1 (hotel) pile test (tension)Deduced from P3 (office) pile test (compression)Deduced from P1 (office) pile test (tension)

  • MEASURED & PREDICTED LATERAL LOAD-DEFLECTION CURVES

    -10 -5 0 5 10 15 20 25

    Appl

    ied L

    oad

    (kN)

    0

    25

    50

    75

    100

    125

    150

    175

    200

    Displacement (mm)

    PredictedMeasuredMeasured

  • MEASURED & PREDICTED LATERAL DEFLECTION vs DEPTH

    -24

    -22

    -20

    -18

    -16

    -14

    -12

    -10

    -8

    -6

    -4

    -2

    0

    2

    Leve

    l DM

    D (m

    )

    -1.0 0 2.0 4.0 6.0 8.0 10.0 12.0

    MeasuredPredicted (Load= 150 kN)

    Deflection (mm)

  • ASSESSMENT OF PREDICTIONS

    Class A predictions were in fair agreement Cyclic loading effects not well-predicted Assisted by:

    Comprehensive investigation data Modern methods of lab & field testing Straight-forward mechanisms of behavior

  • EMIRATES TOWERS-FOUNDATION SYSTEMS

    1.5m thick raft

    102 piles for office

    91 piles for hotel

    1.2 & 1.5 m piles to 40-45 m

  • DESIGN METHODOLOGY

    Limit State Approach Ultimate Limit State:

    Static loads Repetitive wind loads

    Serviceability Limit State: Settlements : max. 150mm Angular rotation: max. 1/350 long-term

  • TOWER FOUNDATION ANALYSES

    GARP program for piled rafts Ultimate Limit State:

    Used both factored & unfactored pile capacities Many load combinations

    Serviceability Limit State Long-term settlements - GARP Short-term movements (wind) DEFPIG for axial & lateral

    stiffness of individual piles in group Passed on to structural engineer for overall analysis

  • LOAD COMBINATIONS

    Ultimate Limit State: 1.25G + 1.5Q 1.2G + 0.4Q + Wu 0.8G = Wu

    Serviceability Limit State: G + 0.4QTotal of 18 load cases per tower

  • PILE INTERACTION DIAGRAM :OFFICE TOWER

  • DYNAMIC FOUNDATION RESPONSE

    Required for seismic & wind response

    Dynamic stiffness & damping from dynamic pile group analysis via Gazetas approach

    MATLAB program developed for evaluation

  • SEISMIC EFFECTS

    Liquefaction: Low very low risk

    Ground Amplification of seismic motions: Category B assessed modest amplification

    Potential for Site Settlements: Assessed to be low, 5-10mm under design

    earthquake, unlikely to cause excessive downdrag loads on piles.

  • PREDICTED SETTLEMENT CONTOURS FOR OFFICE TOWER

    0 5 10 15 20 25 30 35 40 45 500

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50

    y ax

    is (m

    )

    x axis (m)100 110

    110

    110

    120

    120

    120

    120

    130

    130

    130

    110

    110

    55

    100

    Predicted Max.

    Settlement = 134 mm

  • PREDICTED SETTLEMENT CONTOURS FOR HOTEL TOWER

    0 5 10 15 20 25 30 35 40 45 500

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50y

    axis

    (m)

    x axis (m)

    11 0

    55

    105

    115

    115

    115

    115

    115

    125

    12512

    5

    105

    105

    105

    105

    105

    Predicted Max.Settlement = 138 mm

  • THE EMIRATES PROJECT, DUBAI

  • THE EMIRATES PROJECT, DUBAI

  • MEASURED & PREDICTED TIME-SETTLEMENT BEHAVIOR OFFICE TOWER

    0 1 2 3 4 5 6 7 8 9 10 11 12

    50

    40

    30

    20

    10

    0

    Settl

    emen

    t (m

    m)

    Predicted

    T112T111

    1998Time (months)

  • MEASURED & PREDICTED TIME-SETTLEMENT BEHAVIOR HOTEL TOWER

    0 1 2 3 4 5 6 7 8 9 10 11 12

    50

    40

    30

    20

    10

    0Se

    ttlem

    ent (

    mm

    )

    Predicted

    T4

    T15

    1998Time (months)

    Measured

  • MEASURED SETTLEMENT CONTOURS HOTEL TOWER

    T1

    T2

    T3

    T4 T5

    T6 T7

    T8

    T9

    T10

    T11

    T12

    T13

    T14

    T15

    T16

    T17

    T18

    T19

    T20-8.0

    -7.5

    -8.3

    -6.3

    -6.0

    -8.7

    -7.9

    -8.2

    -8.3

    -7.2

    -6.5

    -5.8

    -6.9

    -6.2

    -7.3

    -6.5

    -7.4

    -5.3

    -7.4

    -7.0

    -6

    -7

    -7

    -7

    -7

    -7

    -7

    -8

    -6

    -8 -8

  • SENSITIVITY OF INTERACTION FACTORS TO ANALYSIS ASSUMPTIONS

    1 2 5 10 20 50 100

    0.1

    0

    0.2

    0.3

    0.4

    Inter

    actio

    n Fac

    tor

    s/d

    1

    2

    53

    4

    Curve No.Modulus ofLayer below

    MPa

    Modulus of Soilbetween Piles

    to Near-Pile Values

    9090200700700

    1.05.05.05.01.0

    12345

    Allowances made for:Stiffer soil between pilesStiffer soil below pile tips

    Interaction is generally reducedMarkedly.

    Assumptions have a MAJORinfluence on computedinteraction effects.

  • EFFECT OF ANALYSIS ASSUMPTIONS ON COMPUTED SETTLEMENT

    0

    20

    40

    60

    80

    100

    120

    140

    160

    ORIGINAL CASE 2 CASE 3 CASE 4 CASE 5

    Settl

    emen

    t m

    m

    Hotel Tower

  • THE EMIRATES PROJECT, DUBAI

  • SOME COMMENTS

    Major efforts to obtain good site characterization

    Design values of skin friction higher than previously used in UAE

    CNS direct shear testing proved very useful Test pile behaviour reasonably well-predicted Foundation behaviour not well-predicted, but at

    least conservative

  • TALLEST BUILDINGS (2000)

  • Dubai - 2006

  • BURJ DUBAI TOWER

  • Site Photograph September 2003

  • EARLY CONSTRUCTION July 2005

  • GEOTECHNICAL PEER REVIEW - SCOPE

    Review geotechnical information Develop geotechnical model independently Independent review of Hyder foundation design Independent calculations for foundation stability,

    settlement, differential settlement Assessment of pile load test data and final design

    parameters.Close cooperation between Coffey & Hyder maintained.Site visits, examination of site and borehole cores.

  • SITE CHARACTERIZATION

    30 boreholes SPT 60 PMT tests in 5 boreholes 6 standpipe piezometers Geophysics cross-hole tomography

  • SIMPLIFIED PROFILE4 Silty Sand

    6 Calcarenite

    17 Calcareous Sandstone

    4.5 Gypsiferous Sandstone

    40 Conglomeritic Calcisiltite

    22.5 Calcareous/Conglomeritic

    >47 Claystone/Siltstone

    Base of Tower Raft

    Base of Tower Piles

  • Typical Cores 66m depth

  • Typical Cores 88m depth

  • LABORATORY TESTING

    Conventional tests:

    Classification (various) UCS Point Load Index Modulus Chemical

  • LABORATORY TESTING

    Advanced tests:

    Stress path triaxial Resonant column Cyclic undrained triaxial Cyclic simple shear CNS

  • HYDER PILE DESIGN PARAMETER ASSESSMENT

    Skin friction via UCS correlations & CNS test data

    Modulus value for settlement prediction via correlations with SPT & UCS, pressuremeter, shear wave velocity (with allowance for strain levels)

    Non-linear behaviour via stress path tests Judgement employed

  • INITIAL PILE DESIGN

    Tower: 196 piles, 1.5m diameter, 47.5m long

    Podium: 750 0.9m diameter piles, 30m long

    Raft: 3.7m thick (tower)

  • HYDER SETTLEMENT PREDICTIONS

    REPUTE linear

    PIGLET - linear

    VDISP - linear & non-linear

    ABAQUS non-linear 3D FEA

  • PREDICTED LOAD-SETTLEMENT CURVES

    50m long 1.5m diam. pile

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    0 10 20 30 40 50 60 70 80 90

    Settlement mm

    Load

    MN

    Hyder

    Coffey

  • HYDER - INITIAL TOWER SETTLEMENT PREDICTIONS

    Analysis Settlement mm(Flexible cap)

    Settlement mm(Rigid cap)

    REPUTE 66 56

    PIGLET - 45

    VDISP - 62

    ABAQUS 72 46

  • COFFEY INITIAL TOWER SETTLEMENT ESTIMATES

    FLAC (Axisymmetric) 73 mm

    (maximum)

    PIGS 74 mm (maximum)

  • LOAD TEST PROGRAM

    3 static compression tests (1.5m dia.) Various toe levels (35-55m long)

    1 static compression test (0.9m dia.) Shaft grouted

    1 cyclic compression test (0.9m dia.) 1 static tension test (0.9m dia.) 1 lateral load test

  • LOAD TEST PROGRAM-OUTCOMES

    1.5m piles loaded to 2 times WL0.9m piles to 3.5 times WL No piles appeared to be approaching failure Skin friction values in excess of design assumptions Shaft grouting effective, but not necessary End bearing resistance not fully mobilized Axial stiffness greater than predicted Cyclic axial loading had little effect Lateral stiffness greater than predicted

  • COMPARISONS SKIN FRICTION

    -120

    -100

    -80

    -60

    -40

    -20

    0

    20

    0 100 200 300 400 500 600 700 800 900

    Skin Friction kPa

    RL

    (DM

    D) Original Design

    Msd. Low er Bound

    Msd. Upper Bound

    Recommended (Hyder)

  • MEASURED & PREDICTED PILE HEAD STIFFNESSES

    0

    1000

    2000

    3000

    4000

    5000

    6000

    TP1 TP2 TP3 TP4 TP5 TP6

    Stiffness MN/m

    Test

    Pile

    Num

    ber

    At Working Load

    At Maximum Load

    Calc. At Working Load

  • MEASURED & PREDICTED PILE HEAD STIFFNESSES

    Possible reasons for stiffer than expected behaviour:

    Use of polymer drilling fluid. Interaction between test pile & reaction piles:

    Analysis estimated that this interaction could cause a reduction in test pile settlement of about 30%

    With this allowance, axial stiffness more consistent with Emirates experience

  • TOWER PILE LAYOUT

  • PREDICTED SETTLEMENT PROFILE

  • PREDICTED SETTLEMENT CONTOURS PIGS ANALYSIS

  • LOAD TESTS ON WORKS PILES

    Load tests carried out on some works piles

    Behaviour (axial) even better than test piles

    Predicted settlements could be conservative, although group settlement depends on stiffness of underlying layers

  • Measured Time-Settlement Wing A

  • Measured Time-Settlement-Wing B

  • Measured Time-Settlement Wing C

  • Measured Settlement Contours -August 2006

  • Comparison with Predictions

    Assuming 40% DL and LL = 20% of DL, in August 2006, applied load is about 33% of design load

    For linear behaviour, maximum predicted settlement is: Hyder 22 mm Coffey 25 mm

    Measured 16 mm

  • Comparison with Predictions

    Latest measurements:

    Maximum measured settlement towards the end of construction is about 40mm

  • COMPLETED RAFT

  • CONSTRUCTION PROGRESS

    Early 2006 Early 2007 September 2007

  • Gold Coast Project - Artique

    A 28 storey building on the Gold Coast

    Structural Engineer designed a fully piled to rock foundation system

    Piling contractor engaged Coffey to assess feasibility of piled raft

    Based on results of feasibility, piling contractor engaged Coffey to optimize piled raft design

  • Analysis of Piled Raft

    Feasibility Detailed Design Serviceability Optimization Detailed Design Strength

  • Original Design

    Contiguous bored pile wall

    136 piles founded on rock

    Shear joint between core and podium

    Slab 0.7m thick

  • PEATY CLAY(SOME SAND)

    F-St

    SANDD

    SANDY CLAY (H) /CLAYEY SAND

    MD

    SAND WITHSOME GRAVEL

    MD

    SANDY GRAVEL

    METASILTSTONESW

    0

    -5

    -10

    -15

    -20

    -25

    -30

    -35

    -40

    DESCRIPTION Av.SPT kPa (RAFT)MPa

    SuEs sE

    (PILES)MPa

    up(RAFT)

    MPa kPaf s bf

    MPa

    ASSUMEDBASE OF RAFT

    60 - 90 5.4 120 100 9.9

    10 80 8 0.5 20 22 0.7

    60 - 90 5.4 120 100 9.9

    14 250 25 1.5 40 60 2.0

    25 - 37.5 2.25 50 48 4.1

    100 - 150 9.0 200 100 10.0

    - - 2000 - 2000 - 10.0

    RL (m

    )

    SANDD-VDGeotechnical

    Model

  • Feasibility Results

    Indicated that a raft foundation alone would have a factor of safety of approximately 10 for ultimate loading

    Settlements would govern. Estimated to be of the order of 35mm to 60mm

    The number of piles would be of the order of 140 as per the foundation design supplied by contractor. However, piles only 18m long not 35m

  • Serviceability Case 123 piles (13

    less) Maximum raft

    settlement of 44mm

    Maximum differential settlement of 10mm (1/400)

  • Outcomes

    Number of piles reduced by 10% (13 piles) Pile length reduced from 35m to 18m Total pile length reduced by 2767m Settlement criteria (both total and

    differential) satisfied Potential variations in pile stiffness

    compensated for by raft

  • CONCLUSIONS

    Ground conditions in Dubai are challenging for very tall buildings

    Modern methods are being employed for: In-situ testing Laboratory testing Analysis & design methods

    Simpler methods essential for checks on advanced numerical analyses

    Use of piled rafts can lead to foundation economy With benefit of experience, predictive capabilities are

    improving BUT, reluctance remains to measure foundation performance

  • ACKNOWLEDGEMENTS Artique Project

    Paran Moyes Frances Badelow John Small

    Emirates Project: Patrick Wong Jeff Forse Paul Gildea Bob Lumsdaine Strath Clarke Leanne Petersen

    Burj Dubai: Frances Badelow Muliadi Merry Patrick Wong

    TALL BUILDINGS, DEEP FOUNDATIONS; MIDDLE EAST EXPERIENCESOUTLINEHenry David Thoreau Walden (1854)FOUNDATION DESIGN PROCESSFOUNDATION DESIGN PROCESSFOUNDATION DESIGN PROCESSLOCATION OF DUBAI PROJECTSEmirates Site - 1996SITE PLAN & BOREHOLESINVESTIGATION PROGRAMLABORATORY TESTINGGEOTECHNICAL PROFILE & MODEL FOR EMIRATES SITEFOUNDATION TYPESLOAD TEST PROGRAMPREDICTION METHODSTHE EMIRATES PROJECT, DUBAISETUP FOR COMPRESSION PILE TESTS3000t LOAD TEST WITH REACTION ANCHORSLOAD-SETTLEMENT CURVES FOR PILE P3(H)PREDICTED & MEASURED AXIAL LOAD DISTRIBUTIONSLOAD-MOVEMENT CURVES FOR UPLIFT TESTULTIMATE SHAFT FRICTION FROM TESTSMEASURED & PREDICTED LATERAL LOAD-DEFLECTION CURVESMEASURED & PREDICTED LATERAL DEFLECTION vs DEPTHASSESSMENT OF PREDICTIONSEMIRATES TOWERS-FOUNDATION SYSTEMSDESIGN METHODOLOGYTOWER FOUNDATION ANALYSESLOAD COMBINATIONSPILE INTERACTION DIAGRAM :OFFICE TOWERDYNAMIC FOUNDATION RESPONSESEISMIC EFFECTSPREDICTED SETTLEMENT CONTOURS FOR OFFICE TOWERPREDICTED SETTLEMENT CONTOURS FOR HOTEL TOWERTHE EMIRATES PROJECT, DUBAITHE EMIRATES PROJECT, DUBAIMEASURED & PREDICTED TIME-SETTLEMENT BEHAVIOR OFFICE TOWERMEASURED & PREDICTED TIME-SETTLEMENT BEHAVIOR HOTEL TOWERMEASURED SETTLEMENT CONTOURS HOTEL TOWERSENSITIVITY OF INTERACTION FACTORS TO ANALYSIS ASSUMPTIONSEFFECT OF ANALYSIS ASSUMPTIONS ON COMPUTED SETTLEMENTTHE EMIRATES PROJECT, DUBAISOME COMMENTSTALLEST BUILDINGS (2000)Dubai - 2006BURJ DUBAI TOWERSite Photograph September 2003EARLY CONSTRUCTION July 2005GEOTECHNICAL PEER REVIEW - SCOPESITE CHARACTERIZATIONSIMPLIFIED PROFILETypical Cores 66m depthTypical Cores 88m depthLABORATORY TESTINGLABORATORY TESTINGHYDER PILE DESIGN PARAMETER ASSESSMENTINITIAL PILE DESIGNHYDER SETTLEMENT PREDICTIONSPREDICTED LOAD-SETTLEMENT CURVESHYDER - INITIAL TOWER SETTLEMENT PREDICTIONSCOFFEY INITIAL TOWER SETTLEMENT ESTIMATESLOAD TEST PROGRAMLOAD TEST PROGRAM-OUTCOMESCOMPARISONS SKIN FRICTIONMEASURED & PREDICTED PILE HEAD STIFFNESSESMEASURED & PREDICTED PILE HEAD STIFFNESSESTOWER PILE LAYOUTPREDICTED SETTLEMENT PROFILEPREDICTED SETTLEMENT CONTOURS PIGS ANALYSISLOAD TESTS ON WORKS PILESMeasured Time-Settlement Wing AMeasured Time-Settlement-Wing BMeasured Time-Settlement Wing CMeasured Settlement Contours - August 2006Comparison with PredictionsComparison with PredictionsCOMPLETED RAFTCONSTRUCTION PROGRESSGold Coast Project - ArtiqueAnalysis of Piled RaftOriginal DesignSlide Number 82Feasibility ResultsServiceability CaseOutcomesCONCLUSIONSACKNOWLEDGEMENTS