Tall Buildings, Deep Foundations - Middle East
-
Upload
draghici-sebastian -
Category
Documents
-
view
27 -
download
7
description
Transcript of Tall Buildings, Deep Foundations - Middle East
-
Coffey Geotechnics
TALL BUILDINGS, DEEP FOUNDATIONS; MIDDLE EAST EXPERIENCES
The 2009 Terzaghi Oration
Harry PoulosCoffey Geotechnics
-
OUTLINE
Design Process for High-Rise Buildings Emirates Twin Towers Project
Investigations Design Load tests Tower foundation performance
Burj Dubai Foundation design Load tests Foundation performance
Gold Coast Building
-
Henry David Thoreau Walden (1854)
If you have built castles in the air,Your work need not be lost;That is where they should be.Now put the foundations under them.
-
FOUNDATION DESIGN PROCESS
Site characterization Geology Stratigraphy Quantification of relevant geotechnical parameters.
Based on: In-situ testing Laboratory testing Load testing
-
FOUNDATION DESIGN PROCESS
Foundation Type & Layout. Usually piles or piled raft
Based on: Foundation loadings Design criteria Construction issues Material availability
-
FOUNDATION DESIGN PROCESS
Design Issues1. Ultimate capacity2. Settlement3. Differential settlement & tilt4. Dynamic behaviour5. Earthquake response6. Structural strength of foundation elements7. Durability
-
LOCATION OF DUBAI PROJECTS
-
Emirates Site - 1996
-
SITE PLAN & BOREHOLES
-
INVESTIGATION PROGRAM
23 boreholes, up to about 80m depth (maximum) Trial pits SPT in upper layers Undisturbed sampling Water samples Permeability tests Pressuremeter tests Vertical seismic shear wave profiling Uniformity borehole testing
-
LABORATORY TESTING
Conventional laboratory & field tests Specialized testing
Site uniformity testing (geophysical) Cyclic triaxial testing
Effects of repetitive wind loading Stress path triaxial testing
Deformation parameters CNS testing
Ultimate shaft friction Resonant column testing
Dynamic shear modulus & damping
-
GEOTECHNICAL PROFILE & MODEL FOR EMIRATES SITE
Eu MPa E' MPa fs kPa fb MPa pu MPa
Silty Sand 40 30 18 0.2 0.1Silty Sand 125 100 73 1.5 1.5
Calcareous Sandstone 700 500 200 2.3 2.3
Silty Sand 125 100 150 1.9 1.9
Calcisiltite 500 400 450 2.7 2.7
" 90 80 200 2.0 2.0
" 700 600 450 2.7 2.7
-
FOUNDATION TYPES
Towers Piled raft foundations
Podium Piles, pile groups
-
LOAD TEST PROGRAM
Below each tower:
Compression test to 3000t, L=40m, d=0.9m Static tension test: L=25m, d=0.6m or 0.7m Cyclic tension test Lateral load test
Class A predictions made using assessed design parameters
-
PREDICTION METHODS
Axial Response Non-Linear boundary element analysis PIES program
Lateral Response Non-Linear boundary element analysis ERCAP program
Cyclic Tension Test Non-Linear boundary element analysis SCARP program
-
THE EMIRATES PROJECT, DUBAI
-
SETUP FOR COMPRESSION PILE TESTS
(-2.00)
(-0.50)(-1.50)
(-5.00)
(-10.0)
(-16.0)
(-20.0)
(-25.0)
(-30.0)
(-36.0)
(-40.0)
Working platform
Unit 1 - Silty sand
Unit 2 - Calcareous sandstone
Unit 4 - Calcisiltite
Unit 3 - Silty sand
20301285
900
Ground anchors
Reference beams
Footprint of the ground anchorsat the ground level
No. 1 Extensometer
No. 4 Strain gauges
22 Nos of ground anchors
-
3000t LOAD TEST WITH REACTION ANCHORS
Emirates Project, Dubai
-
LOAD-SETTLEMENT CURVES FOR PILE P3(H)
0 10 20 30 400
5000
10000
15000
20000
25000
30000
Appl
ied L
oad
(kN)
Settlement (mm)
PredictedMeasured
-
PREDICTED & MEASURED AXIAL LOAD DISTRIBUTIONS
0 5000 10000 15000 20000 25000 30000
-40-38-36-34-32-30-28-26-24-22-20-18-16-14-12-10
-8-6-4-202
Leve
l DM
D (m
)
Measured (15000 kN)Measured (23000 kN)Predicted
Load (kN)
-
LOAD-MOVEMENT CURVES FOR UPLIFT TEST
-35 -30 -25 -20 -15 -10 -5 00
1000
2000
3000
4000
5000
6000
Appl
ied L
oad
(kN)
MeasuredPredicted
Uplift (mm)
-
ULTIMATE SHAFT FRICTION FROM TESTS
0 100 200 300 400 500 600 700
50
40
30
20
10
0
Dept
h (m
)
Ultimate Skin Friction kPa
Design valuesDeduced from P3 (hotel) pile test (compression)Deduced from P1 (hotel) pile test (tension)Deduced from P3 (office) pile test (compression)Deduced from P1 (office) pile test (tension)
-
MEASURED & PREDICTED LATERAL LOAD-DEFLECTION CURVES
-10 -5 0 5 10 15 20 25
Appl
ied L
oad
(kN)
0
25
50
75
100
125
150
175
200
Displacement (mm)
PredictedMeasuredMeasured
-
MEASURED & PREDICTED LATERAL DEFLECTION vs DEPTH
-24
-22
-20
-18
-16
-14
-12
-10
-8
-6
-4
-2
0
2
Leve
l DM
D (m
)
-1.0 0 2.0 4.0 6.0 8.0 10.0 12.0
MeasuredPredicted (Load= 150 kN)
Deflection (mm)
-
ASSESSMENT OF PREDICTIONS
Class A predictions were in fair agreement Cyclic loading effects not well-predicted Assisted by:
Comprehensive investigation data Modern methods of lab & field testing Straight-forward mechanisms of behavior
-
EMIRATES TOWERS-FOUNDATION SYSTEMS
1.5m thick raft
102 piles for office
91 piles for hotel
1.2 & 1.5 m piles to 40-45 m
-
DESIGN METHODOLOGY
Limit State Approach Ultimate Limit State:
Static loads Repetitive wind loads
Serviceability Limit State: Settlements : max. 150mm Angular rotation: max. 1/350 long-term
-
TOWER FOUNDATION ANALYSES
GARP program for piled rafts Ultimate Limit State:
Used both factored & unfactored pile capacities Many load combinations
Serviceability Limit State Long-term settlements - GARP Short-term movements (wind) DEFPIG for axial & lateral
stiffness of individual piles in group Passed on to structural engineer for overall analysis
-
LOAD COMBINATIONS
Ultimate Limit State: 1.25G + 1.5Q 1.2G + 0.4Q + Wu 0.8G = Wu
Serviceability Limit State: G + 0.4QTotal of 18 load cases per tower
-
PILE INTERACTION DIAGRAM :OFFICE TOWER
-
DYNAMIC FOUNDATION RESPONSE
Required for seismic & wind response
Dynamic stiffness & damping from dynamic pile group analysis via Gazetas approach
MATLAB program developed for evaluation
-
SEISMIC EFFECTS
Liquefaction: Low very low risk
Ground Amplification of seismic motions: Category B assessed modest amplification
Potential for Site Settlements: Assessed to be low, 5-10mm under design
earthquake, unlikely to cause excessive downdrag loads on piles.
-
PREDICTED SETTLEMENT CONTOURS FOR OFFICE TOWER
0 5 10 15 20 25 30 35 40 45 500
5
10
15
20
25
30
35
40
45
50
y ax
is (m
)
x axis (m)100 110
110
110
120
120
120
120
130
130
130
110
110
55
100
Predicted Max.
Settlement = 134 mm
-
PREDICTED SETTLEMENT CONTOURS FOR HOTEL TOWER
0 5 10 15 20 25 30 35 40 45 500
5
10
15
20
25
30
35
40
45
50y
axis
(m)
x axis (m)
11 0
55
105
115
115
115
115
115
125
12512
5
105
105
105
105
105
Predicted Max.Settlement = 138 mm
-
THE EMIRATES PROJECT, DUBAI
-
THE EMIRATES PROJECT, DUBAI
-
MEASURED & PREDICTED TIME-SETTLEMENT BEHAVIOR OFFICE TOWER
0 1 2 3 4 5 6 7 8 9 10 11 12
50
40
30
20
10
0
Settl
emen
t (m
m)
Predicted
T112T111
1998Time (months)
-
MEASURED & PREDICTED TIME-SETTLEMENT BEHAVIOR HOTEL TOWER
0 1 2 3 4 5 6 7 8 9 10 11 12
50
40
30
20
10
0Se
ttlem
ent (
mm
)
Predicted
T4
T15
1998Time (months)
Measured
-
MEASURED SETTLEMENT CONTOURS HOTEL TOWER
T1
T2
T3
T4 T5
T6 T7
T8
T9
T10
T11
T12
T13
T14
T15
T16
T17
T18
T19
T20-8.0
-7.5
-8.3
-6.3
-6.0
-8.7
-7.9
-8.2
-8.3
-7.2
-6.5
-5.8
-6.9
-6.2
-7.3
-6.5
-7.4
-5.3
-7.4
-7.0
-6
-7
-7
-7
-7
-7
-7
-8
-6
-8 -8
-
SENSITIVITY OF INTERACTION FACTORS TO ANALYSIS ASSUMPTIONS
1 2 5 10 20 50 100
0.1
0
0.2
0.3
0.4
Inter
actio
n Fac
tor
s/d
1
2
53
4
Curve No.Modulus ofLayer below
MPa
Modulus of Soilbetween Piles
to Near-Pile Values
9090200700700
1.05.05.05.01.0
12345
Allowances made for:Stiffer soil between pilesStiffer soil below pile tips
Interaction is generally reducedMarkedly.
Assumptions have a MAJORinfluence on computedinteraction effects.
-
EFFECT OF ANALYSIS ASSUMPTIONS ON COMPUTED SETTLEMENT
0
20
40
60
80
100
120
140
160
ORIGINAL CASE 2 CASE 3 CASE 4 CASE 5
Settl
emen
t m
m
Hotel Tower
-
THE EMIRATES PROJECT, DUBAI
-
SOME COMMENTS
Major efforts to obtain good site characterization
Design values of skin friction higher than previously used in UAE
CNS direct shear testing proved very useful Test pile behaviour reasonably well-predicted Foundation behaviour not well-predicted, but at
least conservative
-
TALLEST BUILDINGS (2000)
-
Dubai - 2006
-
BURJ DUBAI TOWER
-
Site Photograph September 2003
-
EARLY CONSTRUCTION July 2005
-
GEOTECHNICAL PEER REVIEW - SCOPE
Review geotechnical information Develop geotechnical model independently Independent review of Hyder foundation design Independent calculations for foundation stability,
settlement, differential settlement Assessment of pile load test data and final design
parameters.Close cooperation between Coffey & Hyder maintained.Site visits, examination of site and borehole cores.
-
SITE CHARACTERIZATION
30 boreholes SPT 60 PMT tests in 5 boreholes 6 standpipe piezometers Geophysics cross-hole tomography
-
SIMPLIFIED PROFILE4 Silty Sand
6 Calcarenite
17 Calcareous Sandstone
4.5 Gypsiferous Sandstone
40 Conglomeritic Calcisiltite
22.5 Calcareous/Conglomeritic
>47 Claystone/Siltstone
Base of Tower Raft
Base of Tower Piles
-
Typical Cores 66m depth
-
Typical Cores 88m depth
-
LABORATORY TESTING
Conventional tests:
Classification (various) UCS Point Load Index Modulus Chemical
-
LABORATORY TESTING
Advanced tests:
Stress path triaxial Resonant column Cyclic undrained triaxial Cyclic simple shear CNS
-
HYDER PILE DESIGN PARAMETER ASSESSMENT
Skin friction via UCS correlations & CNS test data
Modulus value for settlement prediction via correlations with SPT & UCS, pressuremeter, shear wave velocity (with allowance for strain levels)
Non-linear behaviour via stress path tests Judgement employed
-
INITIAL PILE DESIGN
Tower: 196 piles, 1.5m diameter, 47.5m long
Podium: 750 0.9m diameter piles, 30m long
Raft: 3.7m thick (tower)
-
HYDER SETTLEMENT PREDICTIONS
REPUTE linear
PIGLET - linear
VDISP - linear & non-linear
ABAQUS non-linear 3D FEA
-
PREDICTED LOAD-SETTLEMENT CURVES
50m long 1.5m diam. pile
0
10
20
30
40
50
60
70
80
90
0 10 20 30 40 50 60 70 80 90
Settlement mm
Load
MN
Hyder
Coffey
-
HYDER - INITIAL TOWER SETTLEMENT PREDICTIONS
Analysis Settlement mm(Flexible cap)
Settlement mm(Rigid cap)
REPUTE 66 56
PIGLET - 45
VDISP - 62
ABAQUS 72 46
-
COFFEY INITIAL TOWER SETTLEMENT ESTIMATES
FLAC (Axisymmetric) 73 mm
(maximum)
PIGS 74 mm (maximum)
-
LOAD TEST PROGRAM
3 static compression tests (1.5m dia.) Various toe levels (35-55m long)
1 static compression test (0.9m dia.) Shaft grouted
1 cyclic compression test (0.9m dia.) 1 static tension test (0.9m dia.) 1 lateral load test
-
LOAD TEST PROGRAM-OUTCOMES
1.5m piles loaded to 2 times WL0.9m piles to 3.5 times WL No piles appeared to be approaching failure Skin friction values in excess of design assumptions Shaft grouting effective, but not necessary End bearing resistance not fully mobilized Axial stiffness greater than predicted Cyclic axial loading had little effect Lateral stiffness greater than predicted
-
COMPARISONS SKIN FRICTION
-120
-100
-80
-60
-40
-20
0
20
0 100 200 300 400 500 600 700 800 900
Skin Friction kPa
RL
(DM
D) Original Design
Msd. Low er Bound
Msd. Upper Bound
Recommended (Hyder)
-
MEASURED & PREDICTED PILE HEAD STIFFNESSES
0
1000
2000
3000
4000
5000
6000
TP1 TP2 TP3 TP4 TP5 TP6
Stiffness MN/m
Test
Pile
Num
ber
At Working Load
At Maximum Load
Calc. At Working Load
-
MEASURED & PREDICTED PILE HEAD STIFFNESSES
Possible reasons for stiffer than expected behaviour:
Use of polymer drilling fluid. Interaction between test pile & reaction piles:
Analysis estimated that this interaction could cause a reduction in test pile settlement of about 30%
With this allowance, axial stiffness more consistent with Emirates experience
-
TOWER PILE LAYOUT
-
PREDICTED SETTLEMENT PROFILE
-
PREDICTED SETTLEMENT CONTOURS PIGS ANALYSIS
-
LOAD TESTS ON WORKS PILES
Load tests carried out on some works piles
Behaviour (axial) even better than test piles
Predicted settlements could be conservative, although group settlement depends on stiffness of underlying layers
-
Measured Time-Settlement Wing A
-
Measured Time-Settlement-Wing B
-
Measured Time-Settlement Wing C
-
Measured Settlement Contours -August 2006
-
Comparison with Predictions
Assuming 40% DL and LL = 20% of DL, in August 2006, applied load is about 33% of design load
For linear behaviour, maximum predicted settlement is: Hyder 22 mm Coffey 25 mm
Measured 16 mm
-
Comparison with Predictions
Latest measurements:
Maximum measured settlement towards the end of construction is about 40mm
-
COMPLETED RAFT
-
CONSTRUCTION PROGRESS
Early 2006 Early 2007 September 2007
-
Gold Coast Project - Artique
A 28 storey building on the Gold Coast
Structural Engineer designed a fully piled to rock foundation system
Piling contractor engaged Coffey to assess feasibility of piled raft
Based on results of feasibility, piling contractor engaged Coffey to optimize piled raft design
-
Analysis of Piled Raft
Feasibility Detailed Design Serviceability Optimization Detailed Design Strength
-
Original Design
Contiguous bored pile wall
136 piles founded on rock
Shear joint between core and podium
Slab 0.7m thick
-
PEATY CLAY(SOME SAND)
F-St
SANDD
SANDY CLAY (H) /CLAYEY SAND
MD
SAND WITHSOME GRAVEL
MD
SANDY GRAVEL
METASILTSTONESW
0
-5
-10
-15
-20
-25
-30
-35
-40
DESCRIPTION Av.SPT kPa (RAFT)MPa
SuEs sE
(PILES)MPa
up(RAFT)
MPa kPaf s bf
MPa
ASSUMEDBASE OF RAFT
60 - 90 5.4 120 100 9.9
10 80 8 0.5 20 22 0.7
60 - 90 5.4 120 100 9.9
14 250 25 1.5 40 60 2.0
25 - 37.5 2.25 50 48 4.1
100 - 150 9.0 200 100 10.0
- - 2000 - 2000 - 10.0
RL (m
)
SANDD-VDGeotechnical
Model
-
Feasibility Results
Indicated that a raft foundation alone would have a factor of safety of approximately 10 for ultimate loading
Settlements would govern. Estimated to be of the order of 35mm to 60mm
The number of piles would be of the order of 140 as per the foundation design supplied by contractor. However, piles only 18m long not 35m
-
Serviceability Case 123 piles (13
less) Maximum raft
settlement of 44mm
Maximum differential settlement of 10mm (1/400)
-
Outcomes
Number of piles reduced by 10% (13 piles) Pile length reduced from 35m to 18m Total pile length reduced by 2767m Settlement criteria (both total and
differential) satisfied Potential variations in pile stiffness
compensated for by raft
-
CONCLUSIONS
Ground conditions in Dubai are challenging for very tall buildings
Modern methods are being employed for: In-situ testing Laboratory testing Analysis & design methods
Simpler methods essential for checks on advanced numerical analyses
Use of piled rafts can lead to foundation economy With benefit of experience, predictive capabilities are
improving BUT, reluctance remains to measure foundation performance
-
ACKNOWLEDGEMENTS Artique Project
Paran Moyes Frances Badelow John Small
Emirates Project: Patrick Wong Jeff Forse Paul Gildea Bob Lumsdaine Strath Clarke Leanne Petersen
Burj Dubai: Frances Badelow Muliadi Merry Patrick Wong
TALL BUILDINGS, DEEP FOUNDATIONS; MIDDLE EAST EXPERIENCESOUTLINEHenry David Thoreau Walden (1854)FOUNDATION DESIGN PROCESSFOUNDATION DESIGN PROCESSFOUNDATION DESIGN PROCESSLOCATION OF DUBAI PROJECTSEmirates Site - 1996SITE PLAN & BOREHOLESINVESTIGATION PROGRAMLABORATORY TESTINGGEOTECHNICAL PROFILE & MODEL FOR EMIRATES SITEFOUNDATION TYPESLOAD TEST PROGRAMPREDICTION METHODSTHE EMIRATES PROJECT, DUBAISETUP FOR COMPRESSION PILE TESTS3000t LOAD TEST WITH REACTION ANCHORSLOAD-SETTLEMENT CURVES FOR PILE P3(H)PREDICTED & MEASURED AXIAL LOAD DISTRIBUTIONSLOAD-MOVEMENT CURVES FOR UPLIFT TESTULTIMATE SHAFT FRICTION FROM TESTSMEASURED & PREDICTED LATERAL LOAD-DEFLECTION CURVESMEASURED & PREDICTED LATERAL DEFLECTION vs DEPTHASSESSMENT OF PREDICTIONSEMIRATES TOWERS-FOUNDATION SYSTEMSDESIGN METHODOLOGYTOWER FOUNDATION ANALYSESLOAD COMBINATIONSPILE INTERACTION DIAGRAM :OFFICE TOWERDYNAMIC FOUNDATION RESPONSESEISMIC EFFECTSPREDICTED SETTLEMENT CONTOURS FOR OFFICE TOWERPREDICTED SETTLEMENT CONTOURS FOR HOTEL TOWERTHE EMIRATES PROJECT, DUBAITHE EMIRATES PROJECT, DUBAIMEASURED & PREDICTED TIME-SETTLEMENT BEHAVIOR OFFICE TOWERMEASURED & PREDICTED TIME-SETTLEMENT BEHAVIOR HOTEL TOWERMEASURED SETTLEMENT CONTOURS HOTEL TOWERSENSITIVITY OF INTERACTION FACTORS TO ANALYSIS ASSUMPTIONSEFFECT OF ANALYSIS ASSUMPTIONS ON COMPUTED SETTLEMENTTHE EMIRATES PROJECT, DUBAISOME COMMENTSTALLEST BUILDINGS (2000)Dubai - 2006BURJ DUBAI TOWERSite Photograph September 2003EARLY CONSTRUCTION July 2005GEOTECHNICAL PEER REVIEW - SCOPESITE CHARACTERIZATIONSIMPLIFIED PROFILETypical Cores 66m depthTypical Cores 88m depthLABORATORY TESTINGLABORATORY TESTINGHYDER PILE DESIGN PARAMETER ASSESSMENTINITIAL PILE DESIGNHYDER SETTLEMENT PREDICTIONSPREDICTED LOAD-SETTLEMENT CURVESHYDER - INITIAL TOWER SETTLEMENT PREDICTIONSCOFFEY INITIAL TOWER SETTLEMENT ESTIMATESLOAD TEST PROGRAMLOAD TEST PROGRAM-OUTCOMESCOMPARISONS SKIN FRICTIONMEASURED & PREDICTED PILE HEAD STIFFNESSESMEASURED & PREDICTED PILE HEAD STIFFNESSESTOWER PILE LAYOUTPREDICTED SETTLEMENT PROFILEPREDICTED SETTLEMENT CONTOURS PIGS ANALYSISLOAD TESTS ON WORKS PILESMeasured Time-Settlement Wing AMeasured Time-Settlement-Wing BMeasured Time-Settlement Wing CMeasured Settlement Contours - August 2006Comparison with PredictionsComparison with PredictionsCOMPLETED RAFTCONSTRUCTION PROGRESSGold Coast Project - ArtiqueAnalysis of Piled RaftOriginal DesignSlide Number 82Feasibility ResultsServiceability CaseOutcomesCONCLUSIONSACKNOWLEDGEMENTS