T+3 Market Steering Committee 01 July 2015 · SEP OCT NOV DEC JAN FEB MAR APR MAY JUNE JUL AUG SEP...
Transcript of T+3 Market Steering Committee 01 July 2015 · SEP OCT NOV DEC JAN FEB MAR APR MAY JUNE JUL AUG SEP...
T+3 Market Steering Committee 01 July 2015
Brett Kotze
2
T+3 Project
Market Communication
The aim of the T+3 project
The primary aim of the T+3
project is to shorten the
settlement cycle for equities from
5 to 3 days
3
Phase 1 – Regulatory and Automation
Phase 2 – ECS go-live on T+5 Settlement Cycle
Phase 3 – Market on T3 settlement cycle
Phase Status
1 Implemented successfully - 22 July 2013
2 Implemented successfully – 20 October and 27 October 2014
3 Analysis in progress, commenced with development and iterative testing
May to July 2016 ready for go-live
Overview of the T+3 timeline Overall programme status
4
Functions per phase
Releases
Phase 1 (Regulatory and Automation) Phase 2 (ECS Go-live T+5)
• Split Brokers Prop and Controlled
• Client Pledge (electronic pledge to 3rd parties)
• SLB Automation to CSDP’s
• Corporate Actions Automation to CSDP’s
• ECS (First Phase – replacement of the equities clearing & settlement system)
• Deal Management
• Prime Broking
• Technology Roadmap Upgrade (ECS)
Phase 3 (ECS T+3 Implementation)
• ECS (Second Phase – functional migration to T+3)
• Change from T+5 to T+3 Settlement
• Fails Management Automation
5
T+3 Update Timeline review and overall progress update
Phase 3 Timeline
2015 2016 2014
SEP JUNE MAY APR MAR FEB JAN DEC NOV DEC NOV OCT OCT SEP AUG JUL JUN MAY APR MAR FEB JAN JUL
SIT Cycle 1 Internal
UAT Cycle 1
Regression Cycle
SYT (7 iterations)
ECS Development
SIT Cycle 2 Internal
Scheduled to
start beginning
September
SIT Cycle 3
External
SIT Cycle 4
External
SIT Cycle 5
External
Scheduled to
start end Oct
Strate ready for testing on
new code base
September
4 C
SD
P’s
re
ad
y fo
r in
teg
ratio
n
Au
g –
Se
pte
mb
er
3 C
SD
P’s
re
ad
y fo
r in
teg
ratio
n
en
d O
cto
be
r
1 C
SD
P r
ea
dy fo
r in
teg
ratio
n
Fe
bru
ary
UAT Cycle 2
User Training
Refresher Training
Ready for
go-live May –
July 2016
6
T+3 Update Testing – market involvement
• Timing of phases:
• Required participation per phase:
• Pre-SIT Activities
• Initial reference data set-up
• Test pack review
• Per test cycle:
• Reference data review and health check (two days prior to test execution)
• Test pack refinement
• Test execution
• Results audit (2 days post test execution)
• Environment refresh (2 days prior to the next test phase)
SIT – Cycle 3 Scheduled to start
end Oct 2015
CSDPs (Voluntary)
SIT – Cycle 4 Scheduled to start
mid Nov 2015
CSDPs (Compulsory)
SIT – Cycle 5 Scheduled to start
mid Jan 2016
CSDPs (Compulsory) / Members (Voluntary)
UAT – Cycle 1 Scheduled to start
beginning Feb 2016
CSDPs & Members (Compulsory)
UAT – Cycle 2 Scheduled to start
end Mar 2016
CSDPs & Members (Compulsory)
7
Go-live communication
After a large level of testing has been completed by affected parties a
narrower period for go-live will be announced
This is expected to be announced to the market in November 2015 after
System Integration Testing (SIT) has started and a level of testing
completed
The go-live dates will only be communicated after consultation with –
T+3 Market Steering committee
Clearing and Settlement Advisory Committee (CSAC)
The exact go-live date will be announced after first cycle of User
Acceptance Testing in 2016
8
May
Ap
r
Mar
System Integration Testing Graphical Overview (Dynamic Testing)
FUNCTIONAL / TECHNICAL EXECUTION
2015 2016
Dec
No
v
Oct
Sept
Au
g
Feb
Jan
Ref.
Data
Alignm
ent /
Backu
p
21 - 28
Aug
Cycle 1 Internal (Incl.
Migration) 31 Aug – 22
Sep
Cycle 1 External
(Incl. Migration) 22 Oct – 18
Nov
Cycle 2 External
(Incl. Migration)
19 Nov – 11 Dec
Cycle 3 External
(Excl. Migration) 11 Jan – 03
Feb
Final Benchmarking and reporting 03 Feb – 15 April
LIMITED
TESTING
(b
ased
on
availability)
14
DEC
– 06
JAN
STRATE
23-Sep
Cycle 2 Internal (Incl. Migration) 23 Sep – 21 Oct
System Performance Testing (SPT) 25 Aug – 20 Oct
Integrated Performance Testing (IPT) 25 Nov – 02 Feb
9
09
06
05
04
03
02
System Integration Testing Graphical Task Overview
Integration Testing Cycle 3 (Migration Testing)
November
28
27
26
23
22
30
29
17
16
13
12
11
10
18
October
Development, Support and Training
Revert to backup B 22 – 23 Oct
Communicate Test Scenarios covered in
the cycles to the market
26 – 27 Oct
Settlement Cycle 1 (old)
Settlement Cycle 2 (old)
Settlement Cycle 3 (old)
Settlement Cycle 4 (old)
Settlement Cycle 1 (new)
Settlement Cycle 2 (new)
Settlement Cycle 3 (new)
Settlement Cycle 4 (new)
Settlement Cycle 5 (old)
Settlement Cycle 5 (new)
Settlement Cycle 6 (new)
Convert batch (BCX/JSE)
(Internal JSE action) 03 / 04 Nov
Testing Audit, Market Meeting and cycle 4
adjustments. 17 – 18 Nov
Bug Fixing / Retest 17 – 18 Nov
Perform Health Checks
26 - 27 Oct (CA Events) LDT 02 Nov
(4 events)
(CA Events) LDT = 05 Nov
(4 events)
(CA Events) LDT = 09 Nov
(4 events)
10
07
04
03
02
01
30
System Integration Testing Graphical Task Overview
Integration Testing Cycle 4 (Migration Testing)
December
25
24
23
20
19
27
26
11
10
09
08
November
14
Development, Support and Training
Revert to backup B 19 – 20 Nov
Communicate Test Scenarios covered in
the cycles to the market
23 – 24 Nov
Settlement Cycle 1 (old)
Settlement Cycle 2 (old)
Settlement Cycle 3 (old)
Settlement Cycle 4 (old)
Settlement Cycle 1 (new)
Settlement Cycle 2 (new)
Settlement Cycle 3 (new)
Settlement Cycle 4 (new)
Settlement Cycle 5 (old)
Settlement Cycle 5 (new)
Convert batch (BCX/JSE)
(Internal JSE action) 01 / 02 Nov
Perform Health Checks 23 – 24 Nov
BDA Year-end
11 Dec
(CA Events) LDT = 01 Dec
(4 events)
(CA Events) LDT = 03 Dec
(4 events)
Dummy Public Holiday 02 Dec
Testing Audit, Market Meeting and cycle 5
adjustments. 10 – 11 Dec
11
27
26
25
22
21
20
System Integration Testing (cont.) Graphical Task Overview
Integration Testing cycle 5 (Migration Testing)
February
15
14
13
12
11
19
18
02
01
29
28
January
03
Development, Support and Training
Revert to backup B 11 – 12 Jan
Communicate Test Scenarios covered in
the cycles to the market
13 – 14 Jan
Settlement Cycle 1 (old)
Settlement Cycle 2 (old)
Settlement Cycle 3 (old)
Settlement Cycle 4 (old)
Settlement Cycle 1 (new)
Settlement Cycle 2 (new)
Settlement Cycle 3 (new)
Settlement Cycle 4 (new)
Settlement Cycle 5 (old)
Settlement Cycle 5 (new)
Settlement Cycle 6 (new)
Convert batch (BCX/JSE)
(Internal JSE action) 21 / 22 Feb
BDA Month-end 29 May
Perform Health Checks 13 – 14 Jan
(CA Events) LDT = 20 Jan
(4 events)
(CA Events) LDT = 25 Jan
(4 events)
(CA Events) LDT = 28 Jan
(4 events)
12
Entry and Exit Criteria System Integration Testing
Entry-Criteria
Market documentation reviewed and signed off
Agreed and signed off test packs
Internal and external stakeholders
Market Test Plan completed, reviewed and signed off
Data aligned across applications and all relevant backups are completed
Internal and external stakeholders
Infrastructure verification tests complete (including configuration and connectivity)
Applications and services are operational in the test environment across all applications – Participants to manage internally
No defects with severity of critical or high are open from previous phase
Deviation could occur under the following circumstances
The defect does not affect any key component within your application
The Project team in conjunction with the affected market participant agree to continue with state of defect
13
Entry and Exit Criteria System Integration Testing
Exit-Criteria
All test procedures for a cycle is successfully executed by each market participant
Test results recorded in the agreed test management tool – Participants to manage internally
Screen shots, printouts, actual result, etc. attached to the test case in the test management tool - Participants to manage
internally
Approval for all test cases that are not executed i.e. deferred or not applicable is
quality assured by the Test Manager
All defects with severity of critical and high is fixed and retested during the cycle
Cycle will be extended, if required, to meet the above – Will be agreed by the market
Agreed resolution of all medium and low severity defects
Pass rate is greater than equal to a specified percentage
Pass rate is measured across all applications involved in the cycle
14
Defect Management Process Defect Severity and Priority
Severity – the measure of impact upon the ‘Quality Characteristics’ of the system (e.g. Functionality, Operability etc.)
Priority – the measure of impact upon the test schedule, designates order in which defect
Level Description 1-Critical Impossible to continue testing
Must be corrected immediately The defect results in the failure of the complete software system, or of a subsystem, or of a software unit (program or
module) within the system.
2-High Must be corrected as soon as possible or the schedule will be impacted The defect hampers functionality therefore causes the system to produce incorrect, incomplete, or inconsistent
results. Significant business impact e.g. high financial impact
3-Medium The defect hampers the functionality to a very limited extent, is restricted to a small subset of system functionality,
and has no business impact and there is a work around in place therefore resolving the defect in this release is
negotiable.
4-Low The defect does not hamper the functionality of the system as described in the specification documents, has no impact on the application or business, and can be seen as a nice to have. Examples: different layout of a screen different font/format requested GUI related Correcting is not necessary in this release but may be considered for correcting in this or a subsequent release.
Priority Impacts to Testing 1 Severe impact to plan, cannot continue until fix supplied
2 Significant impact to plan, major areas of test cases awaiting fix to continue
3 Moderate/Low impact to plan, only single test case affected and awaiting fix to continue
4 Minor/No impact to plan, test can continue without fix
15
T+3 Update Proposed training plan - brokers
• The following is the proposed plan for training – details will be confirmed in conjunction with
the T3 Marketing and Education Committee
• Timing - 2 training phases are envisioned:
• 1st phase in Jan 2016 for UAT participants and general market participants
• 2nd phase in Apr / May 2016 for general market participants and refresher training for Phase 1 trainees
• Structure:
• Entire programme lasts 6 hours - split into 2 modules (3 hours each)
• 2 x 3 hour sessions to be run each day (sessions will be alternated to give attendees flexibility)
• 5 total sessions to be run in the week - presentation style (auditorium)
• Planned training agenda:
1. Intro and T3 overview
2. T5 to T3 process changes
3. BDA changes demo
4. ECS changes demo
15
5. Elective Events (Corporate Actions)
6. Fails Management
7. Migration week - Process
16
TWG Sessions
The first of a series of Technical Working Group (TWG) sessions was set up with
brokers on Monday, 29 June 2015 to reconfirm the design of T+3 and impact to
brokers.
Brokers were requested to include their process engineers in the TWG so that they
can start working on the process changes in their back-office
Brokers were invited to request one-on-one sessions with the JSE, to facilitate
direct communication with back-office staff (and potentially traders)
As a proof of concept - the JSE would like to send 2 or 3 staff members into a
brokerage firm to work through and document their process changes. This will
be shared with other brokers – and potentially extended to other brokers
JSE will also extend the invitation for one-on-one sessions to CSDPs – where
JSE will present to the back-office staff on the impact of changes from T+5 to
T+3
17
Design Sessions
Focused on reconfirming design for T+3 on critical areas, taking place in July
and August
Back-to-back links – JSE/Strate/CSDPs
Fails Management - JSE/Strate/CSDPs/brokers
Corporate Actions - JSE/Strate/CSDPs
Migration week – JSE/Strate/CSDPs/brokers
18
Overview of the Phase 3 scope
18
Functions changing / impacted JSE CSDPs JSE Equity Members
Strate Clients
T+5 to T+3 settlement and corporate action cycle (timeline changes)
x x x x x
Scrip Lending and Borrowing / Money Lending and Borrowing
x x
Terminating transactions BDA (Control clients and Brokers Prop)
x x x x x
Terminating transactions CSDP's (non-controlled) x x x x x
Failed Trade Management (ROS and FT) x x x x x
Margining x x
Prime Broking x x
These changes affect a number of systems
19
Reducing the timeframe in which to conduct the existing processes and activities will result in quicker settlement
T+3 settlement cycle
20
T+3 Update User Readiness - Planned comms events (cont.)
• Educational Materials:
• Description: User guides / brochures / manuals explaining the move to T3 and additional concepts contained therein
• Frequency: Multiple drops – July to November
• Purpose: To enhance the knowledge of participants impacted by T3, to enable them to transition to the shorter settlement cycle
• Planned content:
1. T+3 Guide – JSE (July)
2. T+3 FAQs – JSE (July)
3. T+5 to T+3 process timelines – JSE (July)
4. SLB Document – SASLA (July)
5. Corporate Actions Document – Strate (July)
6. Removal Process (Transfer Secs) – JSE (July)
7. SLB Tax Document – SASLA (Aug)
8. SLB Corporate Actions Document – SASLA (Aug)
9. Settlement Obligations Document – JSE (Aug)
10. Migration Document – JSE (Sept)
11. JSE & Strate Rules & Directives – JSE & Strate (Nov)
12. Fails Management Process (to include roles and responsibilities of SASLA & CSDPs) (Nov)
21
T+3 Update User Readiness - Planned comms events (cont.)
• Roadshows / Conferences:
• Description: External presentations to stakeholders (local and foreign) regarding the T3 project
• Frequency: Multiple sessions
• Purpose: To allow impacted stakeholders not based in JHB to attend T3-focussed presentations and engage with project staff
• Planned schedule:
• July 2015 - Buy-side Roadshow (CT) and Namibian Stock Exchange visit
• October 2015 – SIBOS
• November 2015 - Buy-side Visit (CT) / NEMA Africa (LDN) / JSE Roadshow event (LDN)
• February / March 2016 – potential UK/USA roadshow (TBC)
• March / April 2016 – CT visit
22
Current T+3 Committees
T+3 Market and Educational Committee
Purpose: to agree the approach and plan for all market-facing User Readiness activities
Current focus:
Review educational paraphernalia to be circulated to the market
Assist with setting up roadshows and meetings
T+3 Market Steering Committee
Purpose: to review market readiness and updates and agree any future steps
Project Managers
Purpose : to review milestones and updates
Test Managers
Purpose: agree and manage testing requirements
23
External risks and Issues
Risk Risk Description Mitigation Risk Factor
External
External unforeseen (black swan events)
Unforeseen major events – the length of the program, geo political, economic or JSE industry factors – could change the landscape and affect T+3 viability and delivery
• Monitor the external environment for changes • Incorporate outcomes from stress testing and group
economics analysis • Accept residual risk in the event that a black swan
happens. We may be forced to focus senior resources on the resolution of the black swan event instead of T+3
Unanticipated regulatory demand
Any unknown legislative or regulatory changes might dilute focus and compromise market commitment
• Continuous monitoring of legislative and regulatory developments and assessing impacts as and when they arise
• Deferring changes where possible if they impact the T+3 project
Perception that the global precedent is moving
Global markets are moving to T+2, while South Africa is currently only implementing a T+3 cycle
• Continue to reinforce the reason why agreement was reached on a target of T+3 with both the FSB and the market
• Ensure delivery to target timeline to avoid delays (and circumventing further pressure to move directly to T+2)
24
External risks and Issues
Risk Risk Description Mitigation Risk Factor
Market
Competing industry initiatives dilute focus and compromise market commitment
The JSE’s T+3 project is one of many concurrent industry initiatives. While the market has agreed to rank T+3 as the top priority industry initiative, they have warned that a delay in timelines will cause them to re-evaluate priorities and shift delivery focus to other projects.
• Ongoing engagement with market participants to ensure commitment. • High confidence planning to ensure on-time delivery
Market readiness / behavioral changes
There is a concern that the market and participants may not be ready for T+3 (i.e. brokers and fund managers have current processes based on T+5 and may not be prepared for T+3 processes) which will compromise go-live.
• User readiness activities include road shows, communication and educational documentation to be distributed to market participants. • Meetings are frequently being held with various stakeholders from the market to confirm progress on their systems and readiness in line with their planned schedules. • Extensive communication is underway to the market explaining the benefits of the move to T+3. • Early and regular engagement with clients during the course of the project. • Upfront consideration given to the technical impacts on clients.
Offshore market readiness
International investors that arbitrage trade in dual listed stocks on a T+2 cycle in the UK (and a T+5 cycle in SA) might not move shares between registers within the allocated time to meet the new settlement cycle requirements.
• Extensive communication and education about the move to T+3. • Work with transfer secretaries to identify and introduce more efficient processes for the removal of shares between markets. • Increase liquidity for securities lending and borrowing.
25
Margin under T+3
Under T+3 settlement the JSE will margin at EOD T+1 (collect on morning
of T+2 respectively) – 35 to 40% of trades will be margined – figures
depending on how market practice will adjust
Margin will be retained in the case of Fails Management and returned on
final settlement of the transaction -
Rolling of Settlement
Retransactions
Compensation
26
Change in practice
JSE has moved to real-time systems – members may do allocations on a
real-time basis on T and commits to flow on T
Market practice will change – Investors will send instructions and CSDPs
will commit on T or T+1
27
Margining
EOD T+1
Proprietary - uncovered
Controlled Clients – no partials
Non-controlled - uncommitted
EOD T+2
• Proprietary
EOD T+3
• Failed Trades – ROS/FT – marked to market daily
28
Questions