T2K ND280 Time Projection Chambers - …karlen/talks/t2k/tpcreview200712.pdf · T2K ND280 Time...

49
T2K ND280 Time Projection Chambers NSERC Review December 16, 2007 D. Karlen / U. Victoria & TRIUMF representing the T2K ND280 TPC group

Transcript of T2K ND280 Time Projection Chambers - …karlen/talks/t2k/tpcreview200712.pdf · T2K ND280 Time...

T2K ND280 Time Projection Chambers

NSERC ReviewDecember 16, 2007

D. Karlen / U. Victoria & TRIUMFrepresenting the T2K ND280 TPC group

December 16, 2007 T2K TPC project 2

OutlinePhysics requirements and mechanical designPrototype studies: updateFull size module construction statusGas system statusTPC integration issuesMicromegas modulesReadout electronicsSummary

December 16, 2007 T2K TPC project 3

Physics requirementsThe ND280 tracker is designed to

measure the νμ and νe spectra and fluxes prior to oscillationmeasure neutrino interaction cross sections and kinematics

The TPC modules are designed toprovide excellent pattern recognition to allow high purity event samples for different types of neutrino interactions in the FGDmeasure momenta and charge of charged particlesdistinguish electrons and muons/pions and protons

December 16, 2007 T2K TPC project 4

Design considerationsThe 3D tracking capability of TPCs provide excellent pattern recognitionNeutrino energy estimate is affected by Fermi motion. This sets the scale for p precision needed by the TPC to be < 10% at 1 GeV/cdE/dx for electrons is ~ 50% greater than for muons over the momentum range of interest. This sets the scale for dE/dx precision needed by the TPC to be < 10%These goals can be achieved with B=0.2 T for

sampling length ~ 60-70 cmthe pad size ~ 70 mm2

Micromegas technology was selected to provide the gas amplification for readout

December 16, 2007 T2K TPC project 5

TPC Workpackages, contributors, WP leaders

• Oversight by TPC convenors (D. Karlen and M. Zito)

1. TPC mechanical – Canada (Chris Hearty)2. gas system – Canada (Issei Kato)3. ND280 integration – Canada (Roy Langstaff) 4. micromegas modules – Europe (Alain Delbart)5. micromegas mechanical – Europe (Eric Perrin)6. readout electronics – Europe (Denis Calvet)7. online – Europe (Jacques Dumarchez)8. offline software – Europe & Canada (Federico Sanchez)9. calibration – Europe & Canada (Anselmo Cervera)

December 16, 2007 T2K TPC project 6

Mechanical designThree TPCs measure charged particles exiting and entering the two FGD modulesEach TPC has a double box structure:

inner box walls make up the field cageouter box walls at groundgas insulator between themall walls are composite with~1 cm rohacell cores

2.5 m

2.5

m

December 16, 2007 T2K TPC project 7

Mechanical designThe tracker is supported by a basket within the UA1 magnet:

December 16, 2007 T2K TPC project 8

Prototype studies: updateA prototype with 2 readout modules, full drift distance was completed in Jan 2006

proved concept was soundresolution goals achieved

December 16, 2007 T2K TPC project 9

Prototype: Example cosmic eventcoloured accordingto arrival time coloured according

to amplitude

December 16, 2007 T2K TPC project 10

Prototype update: attenuationsaw reduction of signal with drift distance

interpreted this to be due to electron attachment, electron lifetime of about 200 μs lifetime– using relatively slow gas (Ar CO2 90:10, 100 μs drift time)recently we realized that an apparent attenuation is a result of the short shaping time of the ALTRO electronics, c.f. the width of the arrival time distribution of electrons(depends on dip angle and drift distance)

difficult to model and to correctnot a problem forfinal electronics

December 16, 2007 T2K TPC project 11

Prototype update: new baseline gasAs requested by review committee we operated prototype with new baseline gas (Ar CF4 isobutane – 95:3:2)

no “attachment” observed – faster gas, so that the arrival time distribution of electrons shorter than shaping timeallows for amplification systems to operate at lower voltages for the same gain

December 16, 2007 T2K TPC project 12

Prototype: photoelectron calibrationA UV pulsed laser was finally acquired in May 2007 – used to flash the central cathode with diffuse light: producing photoelectrons from aluminum strips

worked very welldrift velocityto 0.01% infew minutes

December 16, 2007 T2K TPC project 13

photoelectron calibration - distortions

Distortion measurements:compare reconstructed locations with designed locations of strips

small displacements, but an apparent rotation

true x0 coordinate (mm)

-150 -100 -50 0 50 100 150

x di

spla

cem

ent f

rom

spe

cific

atio

n (m

m)

-1.5

-1.0

-0.5

0.0

0.5

1.0

1.5

upper module stripslower module stripsmiddle strips

true x0 coordinate (mm)

-150 -100 -50 0 50 100 150

rota

tion

wrt

spec

ifica

tions

(mra

d)

-8

-6

-4

-2

0

2

4

6

8

upper module stripslower module stripsmiddle strips

December 16, 2007 T2K TPC project 14

Photoelectron calibration plansFor full size TPCs, use dots to determine actual displacements – and correct for them

projection of pattern and observedelectrons on single readout module

observed displacements – magnifiedby factor of 10

December 16, 2007 T2K TPC project 15

Full size prototype moduleAs a test of the TPC design and construction, a full size prototype was planned (module 0)

December 16, 2007 T2K TPC project 16

Module-0 constructionA new large bed router at TRIUMF was acquired through CFI – primary use is for TPC and FGD machining

December 16, 2007 T2K TPC project 17

Module-0 constructionAt the time of the last review, we had hoped to have completed module-0 by this timeIn 2007 we suffered many setbacks due to:

router startup problems (installation)continuing router calibration/firmware problems

was challenging to operate at specified tolerances (0.1 mm over distances of ~2 m)

delays in bringing up two shifts on routernow we are back to one shift – job ad out for TRIUMF machinist replacement

December 16, 2007 T2K TPC project 18

Router issuesmoving work off router, to reduce bottleneck

using external company to make rough cuts of G10 materials (oversized) using water jet cutters

performance of router has improvedcompensation tables successfully incorporated backlash reduced by tightening rack and pinionoptical survey determined bow in gantry (0.25 mm)

BEFORE AFTER

December 16, 2007 T2K TPC project 19

Status of module-0 constructionouter panels: complete

inner panels: under construction

outer endplates: completed

module frame: just started

central cathode: under construction

service spacer: under construction

service covers: completed

December 16, 2007 T2K TPC project 20

Module-0 parts

outer box panels (now complete)

inner box panels (under construction)

test of groove cuts for inner panel

December 16, 2007 T2K TPC project 21

Module-0 partsinner box upper panel – strips cut

December 16, 2007 T2K TPC project 22

Module-0 parts

inner box module frame – rough cut

December 16, 2007 T2K TPC project 23

Module-0 parts

Outer box endplates (now complete)

December 16, 2007 T2K TPC project 24

Module-0 partsService spacer –welding completed

December 16, 2007 T2K TPC project 25

Module-0 partsOuter box – dryassembly

December 16, 2007 T2K TPC project 26

Schedule for constructionTimes required for machining parts on the router are much longer than original estimates (factor 2 or more)

serious problem: not only is production schedule longer, but the start of production modules has been delayed

We cannot have an accurate estimate of the total time needed for router, until module-0 parts are complete

expect that subsequent modules will be produced more quickly

December 16, 2007 T2K TPC project 27

Schedule for constructionGiven the progress so far, we believe that module-0 will have machining complete in April 2008 and ready for cosmic+beam tests in MayOver the next several months we will evaluate the production module schedule

a likely strategy:produce production modules in series rather than parallelcomplete module-1 by spring 2009install module-0 and module-1 in ND280 in summer 2009install module-2 in 2010

will explore ways to have 3 TPCs completed in time for 2009 installation – but we must ensure that we have 2

December 16, 2007 T2K TPC project 28

Gas systemGas system is designed to

mix and circulate inner volume gas through filtersbaseline choice: Ar CF4 iC4H10 (95:3:2)

flow CO2 gas through outer volumeflow rates: up to 1 volume change per 5 hours

30 l/min inner, 20 l/min outer (all 3 TPCs)

maintain ΔP between outer volume and atmosphere at less than ~5 mbarmaintain ΔP between inner and outer volumes at about 0.1 mbar

December 16, 2007 T2K TPC project 29

Complete gas system drawing

December 16, 2007 T2K TPC project 30

Mixing system (surface)

December 16, 2007 T2K TPC project 31

Module-0 gas system testOnly one chamber is operated, so flow rate, pump capacity, etc. are downscaled by 1/3Pressure controlled pump loop for recirculationInput and recycling flow controlPressure protection by pressure switches and automatic air valvesBubblers for pressure reliefDid not incorporate mixing system for this test

December 16, 2007 T2K TPC project 32

Module-0 gas system test

December 16, 2007 T2K TPC project 33

Module-0 gas system testSuccessful achievements:

Input and recycling flow controlPressure control in the chamber as required

Achieved ΔP = 0.1 ± 0.01 mbarResponse time for system measuredAutomatic flow shutoff when over/under-pressure occurs

Some problems identified during the testing:Bubbler blows out and the air is sucked into the system when valve is opened to switch the system into operation mode.

A solution identified and was demonstrated by manual operationNext: show that the solution works in automatic operation

December 16, 2007 T2K TPC project 34

Tests of final gas system conceptsdesign goals appears to be achievable

December 16, 2007 T2K TPC project 35

Surface gas buildingIssei Kato has prepared specification

safety review at TRIUMF and KEK

CO2

CF4

Ar

Ar/H2

Isobutane

Room for dry air systemand water heater

Water heater

Gas mixing room

December 16, 2007 T2K TPC project 36

Integration issuesservice routing planning underway

December 16, 2007 T2K TPC project 37

Integration issuesInstallation planning starting

December 16, 2007 T2K TPC project 38

Micromegas modules (Europe)• Bulk micromegas technology used for

gas amplification• 12 modules (34 cm x 36 cm) on each

TPC endplate

Micromegas production to startin early 2008 – 8 per month.Complete 84 by March 2009.

December 16, 2007 T2K TPC project 39

Micromegas modules (Europe)Stiffener frame is bonded to the micromegasPCB to

provide extra strengthattach the module to the TPC endplateform a gas tight seal with the endplate

December 16, 2007 T2K TPC project 40

Readout electronics (Europe)1726 pads readout per module by 6 FECs

FECs based on custom ASIC with SCA (72 x 511)ASIC completed PRR – going into production

72-channel ASIC“AFTER”

Quad-channel ADC

Front-EndMezzanine

card

Optical transceiverFPGA logic

80-pin connector

288-channel Front-End Card 1728-pad Micromegas module

Slow controlnetworkdaisy-chain

Duplex opticalfiber to DCC

Power bar

1 of 72 modules

Low voltageinput(4-5 V)

Technology: Technology: AMS CMOS 0.35AMS CMOS 0.35μμm m Area: Area: 75467546μμm x 7139 m x 7139 μμmmSubmission: Submission: 24 April 200624 April 2006Delivery: Delivery: end of Julyend of JulyPackage: Package: LQFP 160 pins; PlasticLQFP 160 pins; Plasticdimensions: dimensions: 30mm x 30mm 30mm x 30mm thickness: thickness: 1.4mm 1.4mm pitch:pitch: 0.65mm0.65mm# of transistors: # of transistors: 400,000400,000

December 16, 2007 T2K TPC project 41

Front end electronics test

%5.8≈MeanσMicromegas

inserted intoHARP field cage. Readoutby T2K TPC front end cards.

December 16, 2007 T2K TPC project 42

SummaryThe TPC modules are a critical part of the ND280 off axis detectorND280 TPC Group is a large collaboration involving Canada and EuropeProgress made:

full size module under construction (late)gas system designed and tests successfulMicromegas & electronics readout systems verified

Commission ND280 off-axis in fall 2009must work hard to ensure 2 (or 3) TPCs available

Additional material

December 16, 2007 T2K TPC project 44

ND280 TPC group

December 16, 2007 T2K TPC project 45

Attenuation of signals

December 16, 2007 T2K TPC project 46

Shaping time issueAmplitude vs. dip angle for constant drift distance

December 16, 2007 T2K TPC project 47

Gas properties

December 16, 2007 T2K TPC project 48

Gas properties

December 16, 2007 T2K TPC project 49

Bulk micromegas production