OVERVIEW
• Purpose of this project is to deliver Internet connectivity to the VUT main campus residence through fiber cabling and wifi infra-structure.
• You are required to supply, deliver, install and commission the following goods and services.
This tender contains 4 main components:1. The Server Room preparation2. The Fiber cable laying3. The CAT 6 cabling4. Electrical work on Server Room and Drop points
Server Room PreparationPrepping the server room as per on the specificationPaint Work (1 meter wide, 3.5 meters Length and 2.5 meters height)Security doorRelocating the fibre cableElectrical work
The Fiber Cable Length
Red = 755 metersYellow = 900 metersPurple = 205 metersBlue = 30 meters