System Vendor testing kick-off Fredrik Södö 5.3.2019

Transcript of System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will...

Page 1: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

System Vendor

testing

kick-off

Fredrik Södö

5.3.2019

Page 2: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Fredrik SödöFingrid Datahub Oy

5.3.2019Fredrik Södö

Expert

Stakeholder testing and certification

2

Page 3: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Agenda

• 09:00 – 10:00

• Approach to System Vendor testing

• Deployment plan and interface version management

• Support service

• Next steps

• 10:00 – 10:30

• Datahub B2B interface demo

Page 4: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Approach to System Vendor testing

Page 5: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Purpose

• To support System Vendors integrating their solutions to the datahub system

• To ensure the quality of datahub's external functions

5.3.2019Fredrik Södö5

Page 6: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Early testing

The datahub system is not ready when

System vendor testing starts!

all specified functionality will not be available

there will be bugs and malfunctions

the interface specification will change

business logic will change

We do our best to ensure sufficient quality

before deploying new versions

5.3.2019Fredrik Södö6

Page 7: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Enabling testing

• System Vendors are welcome to use the datahub test

environment in parallel with own development

• the solution does not have to be ready when the testing starts

• Fingrid will provide test scenarios before each Stage

• the scenarios are evaluated in workshops before each Stage

• a subset of the scenarios will form the target scope of the Stage

testing

• a subset of the target scope will form the baseline for official

datahub certification later on

• System Vendors are welcome to execute own

scenarios

• Fingrid will define intermediate targets on process level

for monitoring purposes

5.3.2019Fredrik Södö7

Page 8: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Monitoring• Fingrid will monitor progress for each Stage in relation to the

defined scope and intermediate targets

• System Vendors will be asked to report on the target scope

• The target is to achieve visibility of the real status of the System

Vendor readiness

Page 9: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

5.3.2019Fredrik Södö9

• For Stage 1 Fingrid and CGI will provide the following structural data

separately for each vendor

• Fictive market parties (DSO's and Balance Suppliers identified by GLN codes)

• Fictive Metering Grid Areas (identified by EIC codes)

• Fictive products that can be used in agreements

(the system does not yet provide an interface for managing product information)

• Users

• CMS users based on data provided by the vendors

• system users for B2B communication

• A GSRN number has to be used as accounting point identification

• A technically correct Personal identity code has to be used as

customer identification

Test data

Page 10: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

• The System Vendor testing will be performed in a cloud

environment maintained by CGI

• The environment will contain datahub user information, no

other personal data!

• Use of authentic personal data in System Vendor testing

is strictly prohibited

• Testers should also not use their own personal data

Privacy

Fredrik Södö 5.3.20199

Page 11: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Deployment plan and interface version

management

Page 12: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Overall principles for deployment

5.3.2019Fredrik Södö12

• The datahub system is developed according to an incremental model

• the target is to fix bugs and findings in the next version and to avoid the need of maintaining old versions

• a new version of the datahub system including interface version will be delivered in the beginning of each

Stage testing phase

• Interface version management

• The interface specification that applies for the next version will be published about 1,5 months prior to update

• System Vendors have to adopt to the new interface specification, the datahub project doesn't plan to

maintain several test environments for system vendors operating different interface versions

• new interface versions are not necessary backwards compatible with previous ones

Page 13: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

2019

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

testing prep.

System Vendor testing activities 2019

5.3.2019Fredrik Södö13

Vendor testing

Con Stage 1 Stage 1-2 Stage 1-3 Stage 1-4

Stage 1 scenarios

- draft, review, workshops

Stage 2 scenarios

- draft, review, workshops

Stage 3 scenarios

- draft, review, workshops

Stage 4 scenarios

- draft, review, workshops

Contact info, general

planning, on-line meeting

Datahub delivery

Stage 1 dev & test Stage 2 dev & test

Stage 2 AT

Stage 3 dev & test

Stage 3 AT

Stage 4 dev & test

Stage 4 AT

Stage 5 dev & test

testing prep.

Summer vacation

Stage 1 AT testing prep. testing prep. testing prep.

Page 14: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

DH-500

DH-600DH-200

DH-800

DH-900

Data interface (DH-1000)

DH-320

DH-330

DH-340

DH-700

DH-110

DH-130

DH-420

DH-810

B2B external interface

DH-120

DH-310

DH-410

Implementation plan for business process

support

05/03/2019Fredrik Södö14

Stage 1 Stage 2

Preparations

M

2018 2020

Nov Dec AugJulJunJan Feb Mar Apr May JanDecNovOctSep Feb Mar

2019

Stage 3 Stage 4 Stage 5

Vendor testing

Support for business processes will be implemented incrementally in five (5) stages according to the

following preliminary plan.

Fingrid will communicate eventual changes as the project proceeds.

Page 15: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Checkpoints 2019

5.3.2019Fredrik Södö15

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Stage 1

interface

spec

Kick-off

meeting

Instructions

for connection

to test env.

Connections

established

Stage 1

scenarios

draft

Stage 2

scenarios

draft

DH-410

DH-120

DH-310

Stage 1

approved

for SV test

Stage 2

interface

spec

Stage 2

approved

for SV test

Stage 3

interface

spec

Stage 3

scenarios

draft

Stage 3

approved

for SV test

Stage 4

scenarios

draft

Stage 4

interface

spec

Stage 5

scenarios

draft

Stage 4

approved

for SV test

DH-110

DH-130

DH-420

DH-810

DH-700DH-320

DH-330

DH-340

Stage 2

updateStage 1

updateStage 3

update

Stage 4

update

Page 16: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Support service

Page 17: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Support and communication

5.3.2019Fredrik Södö17

• Slack will be used for instant messaging

• Fingrid's personnel will follow the testing channel and

respond to questions

• Other members of the System vendor forum are also

welcome to attend the discussion

• A ServiceNow based portal will be established

for incident management and service requests

• defects that are found in the datahub-system

• service requests for technical assistance, e.g. in relation to

connectivity problems and protocol level issues

Page 18: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Next steps

Page 19: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Vendor testing March - April 2019

5.3.2019Fredrik Södö19

Date Activity Description

5.3.2019 Demonstration of the B2B interface Demonstration of the B2B interface (SoapUI). On-line meeting..

21.3.2019 Stage 1 Test scenario workshop 1 The test scenarios are evaluated in physical workshops with System Vendors

XX.3.2019 Stage 1 Test scenario workshop 2 Test scenario evaluation continues (if needed)

21.3.2019 Instructions for connectivity testing Instructions for connectivity testing delivered to System Vendors

Week 13 Agreement of connectivity tests Connectivity tests are agreed on beforehand to ensure a smooth process

Week 14 Connectivity tests Connectivity tests performed with each System Vendor that plans to start testing in April

(continues in weeks 15 and 16 if needed)

Week 15 CMS training + quick guide On-line training in the use of CMS GUI for System Vendors that start testing in April

Week 16 Stage 2 test scenarios published in System Vendor

Forum

Test scenarios on heading level

Week 16 Publication of the message specification for Stage 2 xsd and event-document for Stage 2

Page 20: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Vendor testing program, May – June 2019

5.3.2019Fredrik Södö20

Date Activity Description

8.5.2019 Stage 2 Test scenario workshop 1 The test scenarios are evaluated in physical workshops with System Vendors

XX.5.2019 Stage 2 Test scenario workshop 2 Test scenario evaluation continues (if needed)

Week 19 Target for DH-120 testing

Week 20 Target for DH-410 testing

Week 22 Target for DH-310 testing

Week 24 Stage 3 test scenarios published in System Vendor

Forum

Test scenarios on heading level

Week 26 Publication of the message specification for Stage 3 xsd and event-document for Stage 3

Week 26 Target for DH-110 testing

Week 27 Target for DH-130 testing

Page 21: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö

Demo

Page 22: System Vendor testing kick-off - EDIEL · System Vendor testing kick-off ... Fingrid will communicate eventual changes as the project proceeds. Checkpoints 2019 15 Fredrik Södö