SYSTEM RESTART ANCILLARY SERVICES 1 SYSTEM RESTART ANCILLARY SERVICES 17 December 2012 ... •...
Transcript of SYSTEM RESTART ANCILLARY SERVICES 1 SYSTEM RESTART ANCILLARY SERVICES 17 December 2012 ... •...
SLIDE 2
PRESENTATION OBJECTIVES
• Provide an overview of black start • Briefly explain the current system restart ancillary
services (SRAS) arrangements • Explain why AEMO is reviewing the SRAS arrangements • Provide a summary of the options AEMO will consult on
and the proposed timeline • Provide an opportunity for stakeholder feedback
SLIDE 3
WHAT IS BLACK START?
• Black start service supplies electricity for power system restoration to generation in the unlikely event that a significant part or the entire grid loses power
• A black start generator is a generator that is capable of being started without an outside electrical power supply, that is, from the national grid
• AEMO procures SRAS in accordance with the NER and consulted on procedures
SLIDE 4
WHY IS BLACK START NEEDED?
• Black start capability is procured as a “public good” to ensure it is available if it is ever needed
• Where a significant part of the NEM experiences a system black condition, this could have a significant impact on our economy, public health and safety
• It is a control mechanism – intended to reduce the consequence of a black system condition
• SRAS payments are like an “insurance policy” paid to facilitate the restoration of generation and load
• The service level: o should take into account that this type event is unlikely to occur o required is a subjective judgement, as is the acceptability of the
cost
SLIDE 5
WHY IS BLACK START NEEDED?
Political and societal • Economic and
political costs • Reputational
damage, including AEMO
• Health and safety
Economic • Lost production and
perishables • Health and safety
Non-credible contingency
events • Protection failures • Natural disasters
• Terrorism • Cyber attack
Black system (whole or partial)
SLIDE 6
RESTORATION PROCESS
• It is likely that system shutdown will be unique, therefore the restoration plan is a path-based strategy to energise transmission to start up supply to significant generators
• The plan describes individual actions for TNSPs, Market Participants and AEMO – effectiveness is their responsibility
• It works in conjunction with existing emergency procedures • The objective is to re-establish a reliable integrated power
system by restoring the national grid with the available equipment
• The first priority is to restore auxiliary supply to restart significant generation which is used to restore load, sensitive loads indicated by the jurisdictional system security co-ordinators
SLIDE 7
THE CURRENT SERVICE REQUIREMENT
• In each electrical sub-network, AEMO procures to meet the System Restart Standard “the standard” which the Reliability Panel determines
• The standard specifies timeframes to: o Re-supply and energize certain significant generation within 90
minutes o Restore generation and transmission with the aim of supplying 40%
of peak demand within 4 hours o Applies equally across jurisdictions o Requires AEMO to determine the electrical boundaries o Allows AEMO to take into account diversity including: Electrical Technology Location Geography Fuel type
• AEMO procedures (consulted on) provide detail of requirements
SLIDE 8
SETTING THE SERVICE REQUIREMENT
• Clauses 4.2.6 and 4.3.1 of the NER require sufficient black start be available to allow the restoration of the power system
• Currently, AEMO procures a minimum of two black start services in each electrical sub-network – not met in all sub-networks
• These can be a primary or secondary black start service and includes generating units or trip to house load (TTHL)
• To set the requirements to meet the standard AEMO currently assumes: o NEM-wide system shutdown o No infrastructure damage to the transmission network o No generation is available from another electrical sub-network
and the island must be restored from within that electric sub-network
o One black start service is unavailable in the electrical sub-network, hence at least one more is needed
SLIDE 9
THE REVIEW
• The objective – to determine whether improvements should be made to the SRAS arrangements to ensure a more appropriate price and service balance is achieved
• The review will have a broad focus on issues that might affect the System Restart Standard, the NER, AEMO procedures and other changes that are deemed necessary
SLIDE 10
REASONS FOR THE REVIEW
• SRAS costs have trended upwards and services procured have increased, raising concerns about whether under the current SRAS arrangements: o NEM customers have an appropriate service and price
balance o In some electrical sub-networks, there are insufficient
incentives for generators to offer “competitive” prices – too few tenderers
o There are sufficient incentives to encourage a market based response
SLIDE 12
SRAS PAYMENTS BY REGION
$0
$2
$4
$6
$8
$10
$12
$14
$16
$18
$20
$22
$24
Mill
ions
NSW
QLD
SA
TAS
SNOWY
VIC
SLIDE 13
CHANGES IN SRAS PRICES
• The following % change in SRAS prices does not include the increase or decrease in services, the change in service is below
Electrical Sub-network No. of Services (2008-12) No. of Services (2012-17) Change in no. of services 2011-12 ($M) 2012-13 ($M) % Change in price
Queensland - North 2 1 -1 0.97 1.3 34.0
Queensland - Central 2 3 1 2.7 2.6 -3.7
Queensland - South 2 2 0 1.2 2.3 91.7
New South Wales - North 3 3 0 10.2 11.5 12.7
New South Wales - South 3 2 -1 10.6 10.7 0.9
Victoria - Latrobe Valley 1 2 1 1.7 2.5 47.1
Victoria - North and West 0 2 2
South Australia 3 3 0 3.2 3.6 12.5
Tasmania - North 2 2 0 3.9 6.3 61.5
Tasmania - South 1 1 0 1.9 3.1 63.2
SLIDE 16
OPTIONS AEMO WILL CONSULT ON
• What risk level is it appropriate to cover? Should we cover this risk; assume a NEM-wide, region-wide or electrical sub-network black system?
• What is the level of residual risk that beneficiaries should manage? For example: o Encourage generators to “manage” for a higher level of service
than is procured by increasing incentives - encourage a more market based approach
• What level of service is appropriate and how effective will this be? For example: o Re-determining the appropriate number of electrical sub-
networks in some regions and the likely impact • Is it appropriate for SRAS to be recovered on a cost reflective
basis - global vs regional recovery, particularly for Tasmania?
SLIDE 17
OPTIONS AEMO WILL CONSULT ON
• Is the procurement approach appropriate, has it resulted in competitive pricing – competitive tender process (current) vs cost of service?
• Are the terms and conditions of the SRAS arrangements appropriate? For example: o Generator liability concerns o The level of reliability of services o Duration of contract period
• Further actions to improve participation: o Earlier procurement, sufficient time for investment in black
start o More proactive AEMO/generator engagement for
procurement
SLIDE 18
POWER SYSTEM STUDIES
• South Australia – could restart using one black start service and from Victoria, currently three services procured
• Victoria – reduced from two to one electrical sub-network, no black start capability from Tasmania assume available from South Australia and NSW
• NSW – no studies undertaken, however could restart from Snowy (Vic), Qld and Colongra (Central Coast)
• Tasmania – reduced from two to one electrical sub-network, no black start capability from the mainland
• Queensland – reduced from three to two electrical sub-networks, combining Central and North Queensland
SLIDE 19
CONSULTATION - 2013
• Publish Issues and Options Paper – mid January • Submissions close – mid February • Draft Report – late March • Submissions close on the Draft Report – late April • Final Report – June