SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

12
1 Heat and Power Technology, Stockholm, Sweden SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY STORAGE FOR COMFORT COOLING INTEGRATED IN DISTRICT COOLING NETWORK Justin Ning-Wei Chiu, Dr. Viktoria Martin, and Prof. Fredrik Setterwall Department of Energy Technology Royal Institute of Technology (KTH) Stockholm, Sweden The 11th International Conference on Energy Storage Effstock 2009: Thermal Energy Storage for Efficiency and Sustainability” 14-17 June 2009, Stockholm, Sweden

Transcript of SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

Page 1: SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

1

Heat and Power Technology, Stockholm, Sweden

SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY STORAGE FOR COMFORT

COOLING INTEGRATED IN DISTRICT COOLING NETWORK

Justin Ning-Wei Chiu, Dr. Viktoria Martin, and Prof. Fredrik Setterwall

Department of Energy TechnologyRoyal Institute of Technology (KTH)

Stockholm, Sweden

The 11th International Conference on Energy Storage

“Effstock 2009: Thermal Energy Storage for Efficiency and

Sustainability”

14-17 June 2009, Stockholm, Sweden

Page 2: SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

2

Heat and Power Technology, Stockholm, Sweden

Objectives

• Optimize storage strategy for load shifting to cut down peak hour energy use.

• Perform a case study of an office building load profile optimization located in Stockholm.

• Study economic feasibility of a CTES system upon integration with an existing district cooling network.

• Benchmark against

-stratified chilled water storage

-independent auxiliary chiller based cooling units

Page 3: SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

3

Heat and Power Technology, Stockholm, Sweden

ModelInputs

• Cooling Load:

120-hour load data

peak thermal load 271kW/ average 139kW

• Salt Hydrate PCM, S13:

phase change temperature 13°C

heat capacity 140kJ/kg (208MJ/m³)

130€/kWh

• Heat Exchanger:

extended finned heat exchange model with heat transfer

coefficient of 120 W/m².K

• Tank cost: 350€/m³ to 1460€/m³

• Etc.

Page 4: SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

4

Heat and Power Technology, Stockholm, Sweden

ModelSchematics

Figure 1 Schematics of TES Charging (continuous line) and Discharging (dashed line)

Page 5: SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

5

Heat and Power Technology, Stockholm, Sweden

ModelEfficiency Factors

• Temperature efficiency : penalty on too low temperature returned to the district cooling net.

• Charging/discharging efficiency : heat transfer limitation between the PCM and the HTF.

• PCM cost ratio : “the cost of PCM” that would allow the certain TES size to be cost effective as compared to either SCW or chiller units divided by the current market price.

Page 6: SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

6

Heat and Power Technology, Stockholm, Sweden

ResultsControl Strategy

•The optimum control strategy for alleviating load from district

cooling network where opportunity cannot be taken from

day/night tariff difference was found to be the load leveling

control scheme.

Figure 1 Control Schemes for Office Building: Full Storage (left) and Load Leveling with

Peak Power Reduction of 60kW (right)

0

200

400

600

800

1000

1200

1400

1600

1800

2000

0

50

100

150

200

250

300

350

0 24 48 72 96 120

Sto

rage

Lev

el (

kWh

)

Pow

er (k

W)

Time (h)Demand Work Load Storage Level

2

Page 7: SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

7

Heat and Power Technology, Stockholm, Sweden

ResultsCost Break Down

•At cost breakeven point between SCW TES and PCM TES (13kW)

tank and PCM price on the overall TES economics

impact of space depends on space availability of sites

Figure 1 Cost Distribution of SCW TES (left) and PCM TES (right) at Power Reduction Rate

of 13kW

3

Page 8: SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

8

Heat and Power Technology, Stockholm, Sweden

Figure 1 Profitability Analysis with Low Return Temperature Penalty

0

0.5

1

1.5

2

0 10 20 30 40 50 60

PC

M C

ost

Rat

io

Power Reduction Rate (kW)

SCW

Chiller

ResultsPCM LHTES System Analysis

4

Page 9: SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

9

Heat and Power Technology, Stockholm, Sweden

ResultsPCM LHTES System Analysis

•PCM based TES breaks even with SCW at power reduction rate

of 13kW which corresponds to 5% peak power rate and it is

economically competent against chiller units in the range of 4kW

to 24kW (1% to 9%) peak power reduction.Table 1 Cost Effective Peak Power Reduction

Peak Power Reduction Absolute Value

Peak Power Reduction Percentage

SCW Chiller SCW Chiller

Penalty/ No Cost Reduction <13kW 4kW-24kW

<5%

1%-9%

Penalty/ 50% Cost Reduction <18kW 4kW-39kW

<7%

1%-14%

No Penalty/ No Cost Reduction <24kW 4kW-31kW

<9%

1%-11%

No Penalty/ 50% Cost Reduction <81kW 4kW-59kW

<30%

1%-22%

Page 10: SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

10

Heat and Power Technology, Stockholm, Sweden

Conclusions

Load leveling control scheme is the most appropriate for fixed tariff district cooling network.

Full storage is economically feasible only if off-peak energy cost saving justifies the investment cost.

Breakthroughs are required in material development to further minimize subcooling.

Eliminate of low return temperature penalty.

Lower PCM cost.

22% to 30% peak load power reduction may be

achieved economically.

Page 11: SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

11

Heat and Power Technology, Stockholm, Sweden

Acknowledgement

• The authors of the paper would like to acknowledge Swedish Energy Agency for their financial support

• and Fortum utility company for valuable discussions and for providing district cooling customer load data

• as well as Jeevan and Prof. Palm for their valuable comments.

Page 12: SYSTEM INTEGRATION OF LATENT HEAT THERMAL ENERGY …

12

Heat and Power Technology, Stockholm, Sweden

Thank you