System Formwork

59
06/06/22 1 SYSTEM FORMWORK Larsen and toubro limited Presentation by: Rachna Rajput (1030227)

Transcript of System Formwork

Page 1: System Formwork

04/08/23 1

SYSTEM FORMWORK Larsen and toubro limited

Presentation by:

Rachna Rajput

(1030227)

Page 2: System Formwork

04/08/23 2

LARSEN & TOUBRO LIMITED

ECC DIVISION

LUDHIANA CITY CENTRE

CONSTRUCTION OF RCC BASEMENT STRUCTURE

By : A.K. Mishra

Page 3: System Formwork

04/08/23 3

THE CLIENT: TODAYHOMES AND INFRASTRUCTURE JOINT VENTURE WITH LUDHIANA IMPROVEMENT TRUST

ARCHITECT: CP KUKREJA AND ASSOCIATES

CONTRACTOR : LARSEN AND TOUBRO LIMITED

Page 4: System Formwork

04/08/23 4

LUDHIANA CITY CENTRE

LOCATED IN HEART OF LUDHIANA BUILT ON 25 ACRES OF LAND 4 SIDE OPEN PLOT MAXIMUM NUMBER OF CAR PARKS UNDER

ONE ROOF ONLY DEVELOPMENT OF INDIA WITH 5 STAR

HOTEL,SHOPPING MALL,IT/OFFICE SPACE,HEALTH CARE,LIBRARY,MUESEAM UNDER 1 ROOF

BIGGEST ATRIUM:2 LAKH SQUARE FEET

Page 5: System Formwork

04/08/23 5

LUDHIANA CITY CENTRECONSTRUCTION OF RCC BASEMENT STRUCTURE

Project Highlights

JOB VALUE : 12400 lacs DATE OF LOI: 30:1:2006 DATE OF COMMENCEMENT: 15:02:2006 DATE OF COMPLETION: 14:02:2007 DURATION OF PROJECT : 12 months

Page 6: System Formwork

04/08/23 6

THE WORK

FORMWORK PLANNING AND

DESIGN OF ITS VARIOUS

COMPONENTS

Page 7: System Formwork

04/08/23 7

WHAT IS FORMWORK? FORMWORK IS A MOULD USED TO SHAPE

CONCRETE UNTIL IT ATTAINS SUFFICIENT STRENGTH TO CARRY ITS OWN WEIGHT

CAN BE ASSEMBLED BY UNSKILLED LABOUR

CONSTITUTES 30% OF THE COST AND 60% OF THE TIME IN CONCRETE CONSTRUCTION

GOOD FORMWORK RESULTS IN SPEED,QUALITY,ECONOMY AND SAFETY

Page 8: System Formwork

04/08/23 8

TRADITIONAL APPROACH

BALLIES USED AS SUPPORT FOR SHUTTERING

UNSAFE AND UNRELIABLE

LOW REUSE VALUE

DOES NOT PRODUCE GOOD QUALITY CONCRETE

Page 9: System Formwork

04/08/23 9

CHOICE OF RIGHT TYPE OF FORMWORK

FORMWORK SHOULD BE ABLE TO BE DESHUTTERED AND DISMANTLED FAST

SAFETY TO BE IMPROVED BY SITE PERSONNEL

OVERALL COST SAVINGS GOOD SURFACE FINISH TO BE ACHIEVED OPTIMUM STOCK OF FORMWORK FOR SIZE

OF WORKFORCE AND SPECIFIED TIME SCHEDULE

Page 10: System Formwork

04/08/23 10

SYSTEM FORMWORK-L&T

EARLIER CALLED DOKA FORMWORK

INVERSIBLE FAST ERECTION MORE STABLE SAFE IN USE

Page 11: System Formwork

04/08/23 11

FORMWORK PLANNINGSTEP1.) CONFIRMING HQ ON THE NEW JOBS BAGGED IDENTIFYING TIME AND MATERIALS FOR

CONSTRUCTION PROJECTSTEP2.) FINALIZING FORMWORK MATERIALS

REQUIREMENTS FOR THE PROJECT COLLATE THE REPORTS FROM RUNNING SITES

AND CHECK SEPARABILITY FROM OTHER SITES WITHIN THE REGION

SENDING REQUEST FOR TRANSFER OF RESOURCES IF AVAILIBILIY IS CONFIRMED

Page 12: System Formwork

04/08/23 12

CONTD….

RECEIVING NEW TARGETS ON PRODUCTIVITY FROM HQ

COMPARING THE RUNNING LMP COST FROM THE ACTUAL

IDENTIFYING TRAINING NEEDS OF STAFF

Page 13: System Formwork

04/08/23 13

COMPONENT DETAILING FOUNDATION FORMWORK

HDT TOWER

SLAB/BEAM FORMWORK

WALL/COLUMN FORMWORK

Page 14: System Formwork

04/08/23 14

FOUNDATION FORMWORK

STEEL PANELS OF STANDERED SIZES MINIMIZE MAKING AT SITE

USE OF VERSATILE COMPONENTS LIKE STEEL WALERS(2 ISMC BACK 2BACK) AND ALIGNMENT PROPS

EASY ASSEMBLY WITH DIMENSIONAL ACCURACY

Page 15: System Formwork

04/08/23 15

Page 16: System Formwork

04/08/23 16

FOUNDATION FORMWORK MATERIAL CONTD.

Page 17: System Formwork

04/08/23 17

CONTD…

Page 18: System Formwork

04/08/23 18

CONTD….

Page 19: System Formwork

04/08/23 19

AFTER ERECTION

Steel panel

Pipe waler

Alignment prop

welar

Pipe waler clamp

Page 20: System Formwork

04/08/23 20

HDT TOWER BASIC FRAME HORIZONTAL BRACE DIAGNOL BRACE TAKES LOAD OF 250KN HIEGHT ADJUSTMENTS UPTO 800MM

POSSIBLE TRANSPORT DEVICES CAN BE ATTATCHED

Page 21: System Formwork

04/08/23 21

COMPONENT DETAILING

Page 22: System Formwork

04/08/23 22

CONTD….

Page 23: System Formwork

04/08/23 23

AFTER ERECTION

Coupler and spring lock pin

Foot plate

Tower spindle

Page 24: System Formwork

04/08/23 24

WALL/COLUMN FORMWORK

SHOP MADE SHUTTER

ACCORDING TO THE HIEGHT OF WALL OR COLUMN SPLICING CAN BE DONE

ISMC WALERS ARE USED FOR BEARING

Page 25: System Formwork

04/08/23 25

COMPONENT DETAILING

Page 26: System Formwork

04/08/23 26

CONTD….

Page 27: System Formwork

04/08/23 27

CONTD……

Page 28: System Formwork

04/08/23 28

COLUMN FORMWORK WORKING AT 4.8M HIEGHT

Page 29: System Formwork

04/08/23 29

COLUMN FORMWORK

Page 30: System Formwork

04/08/23 30

WALL FORMWORK 1.8M HIEGHT

Page 31: System Formwork

04/08/23 31

SLAB/BEAM FORMWORK SHEATHING MEMBER

H-BEAM(SECONDARY MEMBER)

WELAR(PRIMARY MEMBER)

HDT TOWER

Page 32: System Formwork

04/08/23 32

AFTER ERECTION

tower

H-beam

Sheathing

welar

Page 33: System Formwork

04/08/23 33

DESIGN OF FORMWORK FORMWORK MUST SUPPORT ALL THE

VERTICAL AND LATERAL LOADS ALL LOADS ARE ASSUMED TO BE

UNIFORMLY DISTRIBUTED BEAMS SUPPORTED OVER 3 OR MORE

SPANS ARE TAKEN AS CONTINUOUS APPROXIMATE FORMULAE ARE USED

Page 34: System Formwork

04/08/23 34

AN IMPORTANT POINT

SHEATHING SPAN DECIDES H-BEAM SPACING

H-BEAM SPAN DECIDES WALER SPACING

WELAR SPAN DECIDES TOWER SPACING

“SPAN” HERE MEANS THE DISTANCE BETWEEN TWO REACTION POINTS

Page 35: System Formwork

04/08/23 35

DESIGN PROCEDUREEXAMPLE

LOADS TO BE TAKEN

DEAD LOAD(1)

(THICKNESS OF MEMBER*DENSITY OF

CONCRETE)

LIVE LOAD(2)

SELF WEIGHT(3)

DESIGN LOAD,W=(1)+(2)+(3)

Page 36: System Formwork

04/08/23 36

DESIGN PROCEDURECHECKS TO BE APPLIED

BENDING MOMENT CONDITION SHEAR FORCE CONDITION DEFLECTION CONDITION THE MINIMUM OF ALL 3 SPANS IS

TAKEN AS SPAN FOR THE MEMBER ACCORDING TO HEIGHT OF WALL OR

COLUMN THE REQUIRED LENGTH OF H-BEAM(AN I SECTION )

HIGH STRENGTH TIE SYSTEM BEAR LARGE CONCRETE PRESSURE

Page 37: System Formwork

04/08/23 37

DESIGN PROCEDURECONTD….

DESIGN DONE FROM TOP TO BOTTOM 1. SHEATHING MEMBER 2.H-BEAM(SECONDARY MEMBER) 3.WELAR(PRIMARY MEMBER) HDT TOWER

Page 38: System Formwork

04/08/23 38

SELF WEIGHT OF CONCRETE WITH REINFORCEMENT=25KN/M^3

SELF WEIGHT OF FORMWORK VARIES BETWEEN 0.5KN/M^2 TO .75KN/M^2

MINIMUM LIVE LOAD =2.5KN/M^2

MINIMUM DESIGN LOAD=5.0 KN/SQM

Page 39: System Formwork

04/08/23 39

SHEATHING MEMBER:

END CONDITION ASSUMED TO BE A PROPPED

CANTILEVER BM=W*L^2/8<=.2KNM/M

SHEAR=5*W*L/8<=6.16KN/M

DEFLECTION=W*L^4/(185*E*I)<=1.852*10^-3M

MINIMUM OF ABOVE THESE 3 SPANS IS TAKEN

AS SPACING BETWEEN H-BEAMS

Page 40: System Formwork

04/08/23 40

SECONDARY MEMBER(H BEAM):

END CONDITION IS ASSUMED TO BE SIMPLY

SUPPORTED LOAD INTENSITY =DESIGN LOAD*SPAN OF

SHEATHING MEMBER BM=W*L^2/8<=3KNM SHEAR=W*L/2<=6KN DEFLECTION=5*W*L^4/(384*E*I)

MINIMUM OF ALL 3 IS TAKEN AS SPAN FOR

H-BEAM

Page 41: System Formwork

04/08/23 41

WELAR (PRIMARY MEMBER)

SIMPLY SUPPORTED END CONDITION IS

ASSUMED NOW WIDTH OF LOADING IS THE SPAN FOR

H-BEAM AND W=DESIGN LOAD*WIDTH OF LOADING

BM=W*L^2/8<=12.67KNM/M SHEAR=W*L/2<=103.4KN/M DEFLECTION=5*W*L^4/(384*E*I)<=6.67*10^-3

MINIMUM OF THESE 3 IS TAKEN AS THE DISTANCE BETWEEN 2 TOWERS

Page 42: System Formwork

04/08/23 42

Page 43: System Formwork

04/08/23 43

DESIGN FOR WALL/COLUMN FORMWORK

CONCRETE EXERTS A FLUID PRESSURE Dh ON THE FORMWORK

Pmax=

D[C1*R^.5-(C2*K*(H-C1*R^.5)^.5) OR

Dh

whichever is smaller

VALUE OF C1

FOR WALLS=1

FOR COLUMNS=1.5

Page 44: System Formwork

04/08/23 44

VALUE OF C2 DEPENDS ON CONSTITUENT MATERIALS OF CONCRETE

D=WEIGHT DENSITY OF CONCRETE H=VERTICAL FORM HIEGHT h=VERTICAL POUR HIEGHT K=TEMPERATURE COEFFICIENT TAKEN AS

(36/T+16)^2 R=RATE OF RISE M/H T=TEMPERATURE OF CONCRETE AT PLACING

(degree celsius)

Page 45: System Formwork

04/08/23 45

PRESSURE DISTRIBUTION DIAGRAM

H

P max

Pmax/D

Page 46: System Formwork

04/08/23 46

DESIGN OF WALER –DESIGNED AS LATERALLY UNSUPPORTED BEAM

SIGMAbc=.66*Fcb*Fy/(Fcb^n+Fy^n)^1/n

Fcb=ELASTIC CRITICAL STRESS(N/MM^2)

Fy= YIELD STRESS OF STEEL IN( N/MM^2)

N=FACTOR TAKEN AS 1.4 Fcb=K1*(X+K2*Y)*C2/C1 PERMISSIBLE SHEAR STRESS=0.4*Fy PERMISSIBLE DEFLECTION=L(SPAN)/325 BENDING STRESS=M/Z SHEAR STRESS=F/Aweb

Page 47: System Formwork

04/08/23 47

STRIPPING TIME FOR FORMWORK

VERTICAL FORMWORK TO COLUMN, WALL AND BEAM :16-24HOURS

SOFFIT FORMWORK TO SLABS(PROPS TO BE

REFIXED AFTER REMOVAL OF FORMWOK) :3DAYS

SOFFIT FORMWORK TO BEAMS :7DAYS

Page 48: System Formwork

04/08/23 48

SAFETY IN FORMWORK BEFORE ERECTION OF STEEL FRAME

STAGING THOROUGH INSPECTION DIAGNOL BRACES SHOULD BE IN PROPER

POSITION ALL CONNECTING DEVICES SHOULD BE IN

PLACE BRACING SHOULD BE PROVIDED IF TOWER

HEIGHT INCREASES 6M AT HIEGHTS SAFETY BELTS SHOULD BE

USED BY WORKMEN

Page 49: System Formwork

04/08/23 49

Ladder Safety

Follow the 4:1 rule when using extension ladders

6 m (20 ft)

1.5 m (5 ft.)

Page 50: System Formwork

04/08/23 50

–Erect First Tower – Adjust and ensure the

top level is same. Connect all pin bracing

Page 51: System Formwork

04/08/23 51

Page 52: System Formwork

04/08/23 52

Page 53: System Formwork

04/08/23 53

Use of lifeline above 2m

Page 54: System Formwork

04/08/23 54

LABOUR PRODUCTIVITY

PRODUCTIVITY IS MAXIMUM OUTPUT FROM MINIMUM INPUT

UNITS ARE SQM/MANDAY

WORKING OF 8 HRS=1MANDAY

PRODUCTIVITY= SHUTTERING AREA ACHIEVED DURING THE

MONTH/MANDAYS

Page 55: System Formwork

04/08/23 55

MATERIAL PRODUCTIVITY

MATERIAL PRODUCTIVITY IS COMPARED WITH STANDERED PRODUCTIVITY

STANDERED PRODUCTIVITY CALCULATED ON THE BASIS OF SHUTTERING AREA COMPLETED AND KG MONTH PER SQM

TOTAL REQUIRED KG=

SHUTTERING AREA *KG MONTH PER SQM

Page 56: System Formwork

04/08/23 56

ACTUAL PRODUCTIVITY IS TAKEN AS AVERAGE STOCK LEFT

PRODUCTIVITY IN %=

(ACTUALPRODUCTIVITY/STANDERED PRODUCTIVITY)*100

Page 57: System Formwork

04/08/23 57

RATE ANALYSIS

ON THE BASIS OF NUMBER OF CARPENTER KHALASI AND HELPER,NUMBER OF HOURS OF WORK AND RATE/HR THE TOTAL AMOUNT IS CALCULATED FOR SHIFTING ,FIXING AND REMOVING

PRODUCTIVITY IN SQM/MANDAYS IS CALCULATED

Page 58: System Formwork

04/08/23 58

BATCHING OF CONCRETE

PAN TYPE BATCHING PLANT CAPACITY OF 60M^3/HR WEIGHED BATCHING MIXING TRANSPORTATION PLACING

Page 59: System Formwork

04/08/23 59

THANK YOU