System Formwork
-
Upload
amurugesan -
Category
Documents
-
view
382 -
download
58
Transcript of System Formwork
04/08/23 1
SYSTEM FORMWORK Larsen and toubro limited
Presentation by:
Rachna Rajput
(1030227)
04/08/23 2
LARSEN & TOUBRO LIMITED
ECC DIVISION
LUDHIANA CITY CENTRE
CONSTRUCTION OF RCC BASEMENT STRUCTURE
By : A.K. Mishra
04/08/23 3
THE CLIENT: TODAYHOMES AND INFRASTRUCTURE JOINT VENTURE WITH LUDHIANA IMPROVEMENT TRUST
ARCHITECT: CP KUKREJA AND ASSOCIATES
CONTRACTOR : LARSEN AND TOUBRO LIMITED
04/08/23 4
LUDHIANA CITY CENTRE
LOCATED IN HEART OF LUDHIANA BUILT ON 25 ACRES OF LAND 4 SIDE OPEN PLOT MAXIMUM NUMBER OF CAR PARKS UNDER
ONE ROOF ONLY DEVELOPMENT OF INDIA WITH 5 STAR
HOTEL,SHOPPING MALL,IT/OFFICE SPACE,HEALTH CARE,LIBRARY,MUESEAM UNDER 1 ROOF
BIGGEST ATRIUM:2 LAKH SQUARE FEET
04/08/23 5
LUDHIANA CITY CENTRECONSTRUCTION OF RCC BASEMENT STRUCTURE
Project Highlights
JOB VALUE : 12400 lacs DATE OF LOI: 30:1:2006 DATE OF COMMENCEMENT: 15:02:2006 DATE OF COMPLETION: 14:02:2007 DURATION OF PROJECT : 12 months
04/08/23 6
THE WORK
FORMWORK PLANNING AND
DESIGN OF ITS VARIOUS
COMPONENTS
04/08/23 7
WHAT IS FORMWORK? FORMWORK IS A MOULD USED TO SHAPE
CONCRETE UNTIL IT ATTAINS SUFFICIENT STRENGTH TO CARRY ITS OWN WEIGHT
CAN BE ASSEMBLED BY UNSKILLED LABOUR
CONSTITUTES 30% OF THE COST AND 60% OF THE TIME IN CONCRETE CONSTRUCTION
GOOD FORMWORK RESULTS IN SPEED,QUALITY,ECONOMY AND SAFETY
04/08/23 8
TRADITIONAL APPROACH
BALLIES USED AS SUPPORT FOR SHUTTERING
UNSAFE AND UNRELIABLE
LOW REUSE VALUE
DOES NOT PRODUCE GOOD QUALITY CONCRETE
04/08/23 9
CHOICE OF RIGHT TYPE OF FORMWORK
FORMWORK SHOULD BE ABLE TO BE DESHUTTERED AND DISMANTLED FAST
SAFETY TO BE IMPROVED BY SITE PERSONNEL
OVERALL COST SAVINGS GOOD SURFACE FINISH TO BE ACHIEVED OPTIMUM STOCK OF FORMWORK FOR SIZE
OF WORKFORCE AND SPECIFIED TIME SCHEDULE
04/08/23 10
SYSTEM FORMWORK-L&T
EARLIER CALLED DOKA FORMWORK
INVERSIBLE FAST ERECTION MORE STABLE SAFE IN USE
04/08/23 11
FORMWORK PLANNINGSTEP1.) CONFIRMING HQ ON THE NEW JOBS BAGGED IDENTIFYING TIME AND MATERIALS FOR
CONSTRUCTION PROJECTSTEP2.) FINALIZING FORMWORK MATERIALS
REQUIREMENTS FOR THE PROJECT COLLATE THE REPORTS FROM RUNNING SITES
AND CHECK SEPARABILITY FROM OTHER SITES WITHIN THE REGION
SENDING REQUEST FOR TRANSFER OF RESOURCES IF AVAILIBILIY IS CONFIRMED
04/08/23 12
CONTD….
RECEIVING NEW TARGETS ON PRODUCTIVITY FROM HQ
COMPARING THE RUNNING LMP COST FROM THE ACTUAL
IDENTIFYING TRAINING NEEDS OF STAFF
04/08/23 13
COMPONENT DETAILING FOUNDATION FORMWORK
HDT TOWER
SLAB/BEAM FORMWORK
WALL/COLUMN FORMWORK
04/08/23 14
FOUNDATION FORMWORK
STEEL PANELS OF STANDERED SIZES MINIMIZE MAKING AT SITE
USE OF VERSATILE COMPONENTS LIKE STEEL WALERS(2 ISMC BACK 2BACK) AND ALIGNMENT PROPS
EASY ASSEMBLY WITH DIMENSIONAL ACCURACY
04/08/23 15
04/08/23 16
FOUNDATION FORMWORK MATERIAL CONTD.
04/08/23 17
CONTD…
04/08/23 18
CONTD….
04/08/23 19
AFTER ERECTION
Steel panel
Pipe waler
Alignment prop
welar
Pipe waler clamp
04/08/23 20
HDT TOWER BASIC FRAME HORIZONTAL BRACE DIAGNOL BRACE TAKES LOAD OF 250KN HIEGHT ADJUSTMENTS UPTO 800MM
POSSIBLE TRANSPORT DEVICES CAN BE ATTATCHED
04/08/23 21
COMPONENT DETAILING
04/08/23 22
CONTD….
04/08/23 23
AFTER ERECTION
Coupler and spring lock pin
Foot plate
Tower spindle
04/08/23 24
WALL/COLUMN FORMWORK
SHOP MADE SHUTTER
ACCORDING TO THE HIEGHT OF WALL OR COLUMN SPLICING CAN BE DONE
ISMC WALERS ARE USED FOR BEARING
04/08/23 25
COMPONENT DETAILING
04/08/23 26
CONTD….
04/08/23 27
CONTD……
04/08/23 28
COLUMN FORMWORK WORKING AT 4.8M HIEGHT
04/08/23 29
COLUMN FORMWORK
04/08/23 30
WALL FORMWORK 1.8M HIEGHT
04/08/23 31
SLAB/BEAM FORMWORK SHEATHING MEMBER
H-BEAM(SECONDARY MEMBER)
WELAR(PRIMARY MEMBER)
HDT TOWER
04/08/23 32
AFTER ERECTION
tower
H-beam
Sheathing
welar
04/08/23 33
DESIGN OF FORMWORK FORMWORK MUST SUPPORT ALL THE
VERTICAL AND LATERAL LOADS ALL LOADS ARE ASSUMED TO BE
UNIFORMLY DISTRIBUTED BEAMS SUPPORTED OVER 3 OR MORE
SPANS ARE TAKEN AS CONTINUOUS APPROXIMATE FORMULAE ARE USED
04/08/23 34
AN IMPORTANT POINT
SHEATHING SPAN DECIDES H-BEAM SPACING
H-BEAM SPAN DECIDES WALER SPACING
WELAR SPAN DECIDES TOWER SPACING
“SPAN” HERE MEANS THE DISTANCE BETWEEN TWO REACTION POINTS
04/08/23 35
DESIGN PROCEDUREEXAMPLE
LOADS TO BE TAKEN
DEAD LOAD(1)
(THICKNESS OF MEMBER*DENSITY OF
CONCRETE)
LIVE LOAD(2)
SELF WEIGHT(3)
DESIGN LOAD,W=(1)+(2)+(3)
04/08/23 36
DESIGN PROCEDURECHECKS TO BE APPLIED
BENDING MOMENT CONDITION SHEAR FORCE CONDITION DEFLECTION CONDITION THE MINIMUM OF ALL 3 SPANS IS
TAKEN AS SPAN FOR THE MEMBER ACCORDING TO HEIGHT OF WALL OR
COLUMN THE REQUIRED LENGTH OF H-BEAM(AN I SECTION )
HIGH STRENGTH TIE SYSTEM BEAR LARGE CONCRETE PRESSURE
04/08/23 37
DESIGN PROCEDURECONTD….
DESIGN DONE FROM TOP TO BOTTOM 1. SHEATHING MEMBER 2.H-BEAM(SECONDARY MEMBER) 3.WELAR(PRIMARY MEMBER) HDT TOWER
04/08/23 38
SELF WEIGHT OF CONCRETE WITH REINFORCEMENT=25KN/M^3
SELF WEIGHT OF FORMWORK VARIES BETWEEN 0.5KN/M^2 TO .75KN/M^2
MINIMUM LIVE LOAD =2.5KN/M^2
MINIMUM DESIGN LOAD=5.0 KN/SQM
04/08/23 39
SHEATHING MEMBER:
END CONDITION ASSUMED TO BE A PROPPED
CANTILEVER BM=W*L^2/8<=.2KNM/M
SHEAR=5*W*L/8<=6.16KN/M
DEFLECTION=W*L^4/(185*E*I)<=1.852*10^-3M
MINIMUM OF ABOVE THESE 3 SPANS IS TAKEN
AS SPACING BETWEEN H-BEAMS
04/08/23 40
SECONDARY MEMBER(H BEAM):
END CONDITION IS ASSUMED TO BE SIMPLY
SUPPORTED LOAD INTENSITY =DESIGN LOAD*SPAN OF
SHEATHING MEMBER BM=W*L^2/8<=3KNM SHEAR=W*L/2<=6KN DEFLECTION=5*W*L^4/(384*E*I)
MINIMUM OF ALL 3 IS TAKEN AS SPAN FOR
H-BEAM
04/08/23 41
WELAR (PRIMARY MEMBER)
SIMPLY SUPPORTED END CONDITION IS
ASSUMED NOW WIDTH OF LOADING IS THE SPAN FOR
H-BEAM AND W=DESIGN LOAD*WIDTH OF LOADING
BM=W*L^2/8<=12.67KNM/M SHEAR=W*L/2<=103.4KN/M DEFLECTION=5*W*L^4/(384*E*I)<=6.67*10^-3
MINIMUM OF THESE 3 IS TAKEN AS THE DISTANCE BETWEEN 2 TOWERS
04/08/23 42
04/08/23 43
DESIGN FOR WALL/COLUMN FORMWORK
CONCRETE EXERTS A FLUID PRESSURE Dh ON THE FORMWORK
Pmax=
D[C1*R^.5-(C2*K*(H-C1*R^.5)^.5) OR
Dh
whichever is smaller
VALUE OF C1
FOR WALLS=1
FOR COLUMNS=1.5
04/08/23 44
VALUE OF C2 DEPENDS ON CONSTITUENT MATERIALS OF CONCRETE
D=WEIGHT DENSITY OF CONCRETE H=VERTICAL FORM HIEGHT h=VERTICAL POUR HIEGHT K=TEMPERATURE COEFFICIENT TAKEN AS
(36/T+16)^2 R=RATE OF RISE M/H T=TEMPERATURE OF CONCRETE AT PLACING
(degree celsius)
04/08/23 45
PRESSURE DISTRIBUTION DIAGRAM
H
P max
Pmax/D
04/08/23 46
DESIGN OF WALER –DESIGNED AS LATERALLY UNSUPPORTED BEAM
SIGMAbc=.66*Fcb*Fy/(Fcb^n+Fy^n)^1/n
Fcb=ELASTIC CRITICAL STRESS(N/MM^2)
Fy= YIELD STRESS OF STEEL IN( N/MM^2)
N=FACTOR TAKEN AS 1.4 Fcb=K1*(X+K2*Y)*C2/C1 PERMISSIBLE SHEAR STRESS=0.4*Fy PERMISSIBLE DEFLECTION=L(SPAN)/325 BENDING STRESS=M/Z SHEAR STRESS=F/Aweb
04/08/23 47
STRIPPING TIME FOR FORMWORK
VERTICAL FORMWORK TO COLUMN, WALL AND BEAM :16-24HOURS
SOFFIT FORMWORK TO SLABS(PROPS TO BE
REFIXED AFTER REMOVAL OF FORMWOK) :3DAYS
SOFFIT FORMWORK TO BEAMS :7DAYS
04/08/23 48
SAFETY IN FORMWORK BEFORE ERECTION OF STEEL FRAME
STAGING THOROUGH INSPECTION DIAGNOL BRACES SHOULD BE IN PROPER
POSITION ALL CONNECTING DEVICES SHOULD BE IN
PLACE BRACING SHOULD BE PROVIDED IF TOWER
HEIGHT INCREASES 6M AT HIEGHTS SAFETY BELTS SHOULD BE
USED BY WORKMEN
04/08/23 49
Ladder Safety
Follow the 4:1 rule when using extension ladders
6 m (20 ft)
1.5 m (5 ft.)
04/08/23 50
–Erect First Tower – Adjust and ensure the
top level is same. Connect all pin bracing
04/08/23 51
04/08/23 52
04/08/23 53
Use of lifeline above 2m
04/08/23 54
LABOUR PRODUCTIVITY
PRODUCTIVITY IS MAXIMUM OUTPUT FROM MINIMUM INPUT
UNITS ARE SQM/MANDAY
WORKING OF 8 HRS=1MANDAY
PRODUCTIVITY= SHUTTERING AREA ACHIEVED DURING THE
MONTH/MANDAYS
04/08/23 55
MATERIAL PRODUCTIVITY
MATERIAL PRODUCTIVITY IS COMPARED WITH STANDERED PRODUCTIVITY
STANDERED PRODUCTIVITY CALCULATED ON THE BASIS OF SHUTTERING AREA COMPLETED AND KG MONTH PER SQM
TOTAL REQUIRED KG=
SHUTTERING AREA *KG MONTH PER SQM
04/08/23 56
ACTUAL PRODUCTIVITY IS TAKEN AS AVERAGE STOCK LEFT
PRODUCTIVITY IN %=
(ACTUALPRODUCTIVITY/STANDERED PRODUCTIVITY)*100
04/08/23 57
RATE ANALYSIS
ON THE BASIS OF NUMBER OF CARPENTER KHALASI AND HELPER,NUMBER OF HOURS OF WORK AND RATE/HR THE TOTAL AMOUNT IS CALCULATED FOR SHIFTING ,FIXING AND REMOVING
PRODUCTIVITY IN SQM/MANDAYS IS CALCULATED
04/08/23 58
BATCHING OF CONCRETE
PAN TYPE BATCHING PLANT CAPACITY OF 60M^3/HR WEIGHED BATCHING MIXING TRANSPORTATION PLACING
04/08/23 59
THANK YOU