System Design and Deployment Status
description
Transcript of System Design and Deployment Status
![Page 1: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/1.jpg)
System Design and Deployment Status
PDS Management Council Face-to-FaceUCLA, Los Angeles, California
November 28-29, 2012
Sean Hardman
![Page 2: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/2.jpg)
Topics
• Status- Overall
- Build 3a
• Deployment
• Search Service Status
• Report Service Status
• Build 3b and Beyond
• Next Steps
November 28-29, 2012 System Design and Deployment Update 2
![Page 3: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/3.jpg)
Overall Status
• Validate software in place supporting validation of PDS4 labels using XML Schema and Schematron files.
• Initial data access and transform software in place for working with PDS4 data.
• Harvest and Registry software in place to support EN and Node registration of PDS3 and PDS4 data.
• Search software in place supporting catalog-level search.
• Report software in place waiting to be populated with web logs.
November 28-29, 2012 System Design and Deployment Update 3
![Page 4: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/4.jpg)
Build 3a Status
• Upgraded the Data Search interface to remove the dependence on the PDS3 catalog database.
• Refactored the Search Service to better support PDS4.
• Kept up with Information Model changes.• Added support for PDAP search protocol.• Initial support for PDS4 data transformation.• Correct issues discovered during Build 2c
testing.
November 28-29, 2012 System Design and Deployment Update 4
![Page 5: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/5.jpg)
Build 3a StatusDeployment
• Engineering Node- Deployment of the core components replacing the
central catalog.• Running side-by-side with PDS3 system for six months.
- Existing search interfaces reworked to utilize the PDS4 infrastructure.
• Discipline Nodes- Phased deployment of the core components at the
Nodes is in process.- Once deployment is complete, Nodes may begin
local registration of their PDS4 test bundles.- PDS3 data sets/products may be registered as well.
November 28-29, 2012 System Design and Deployment Update 5
![Page 6: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/6.jpg)
Build 3a DeploymentEngineering Node
November 28-29, 2012 System Design and Deployment Update 6
![Page 7: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/7.jpg)
Build 3a DeploymentDiscipline Node
November 28-29, 2012 System Design and Deployment Update 7
![Page 8: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/8.jpg)
Node Deployment Status
• A couple of early adopters have tackled the installation.- Have received procedure/documentation suggestions and
some RFAs.
• Actively working with Atmospheres to install the software at their Node.
• The other Nodes have been contacted to arrange installation.- Most were waiting for an updated RDD.
• The RDD now includes the Node installation procedure.- http://pds-engineering.jpl.nasa.gov/pds2010/developmen
t/3.0.0/release/index-3.0.0.html
November 28-29, 2012 System Design and Deployment Update 8
![Page 9: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/9.jpg)
Build 3a DeploymentPDS3/PDS4 Product Registration
November 28-29, 2012 System Design and Deployment Update 9
![Page 10: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/10.jpg)
Search Service Status
• PDS4 core infrastructure running at the PDS Engineering Node.
• Working with the IPDA to register ESA data sets in search via PDAP protocol.- Working on some metadata quality issues before
integration with operational search.
• Worked with Atmospheres to register archive information web sites for Cassini and Phoenix data access.
• Use demonstration process to affirm the architecture and then expand.
November 28-29, 2012 System Design and Deployment Update 10
![Page 11: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/11.jpg)
System Design and Deployment Update 11
Search Deployment
November 28-29, 2012
ArchivePages
Facet-BasedSearch
LinkableResultsPage
![Page 12: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/12.jpg)
Report Service Status
• Sawmill software installed at the EN.- Upgraded to the latest version from the vendor.
• Ready to pull log files from the Nodes and setting up a mechanism for push capability.
• Planned operational phases:- Initiate population of the service and initial report
configuration (December 2012).
- Generate PDS-wide web log reports. (March 2013)
- Generate registry-based reports. (October 2013)
November 28-29, 2012 System Design and Deployment Update 12
![Page 13: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/13.jpg)
Build 3b and Beyond
• Continue to support Information Model changes.• Add support for content validation.• Tune the Search Service index.• Add support for product-level search.• Develop initial Transport Service.• Add support for additional transformations.• Add support for package generation.• Integrate distribution and transformation
capabilities.• Upgrade PDS web presence.
November 28-29, 2012 System Design and Deployment Update 13
![Page 14: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/14.jpg)
Next Steps
• Work with the Nodes on Report Service population.
• Continue working with the Nodes to deploy Build 3a software locally.
• Continue Build 3b development.- Align tool development with the tool plan
November 28-29, 2012 System Design and Deployment Update 14
![Page 15: System Design and Deployment Status](https://reader036.fdocuments.us/reader036/viewer/2022081516/56813998550346895da13041/html5/thumbnails/15.jpg)
Questions/Comments