Synopsis Civil
-
Upload
guman-singh -
Category
Documents
-
view
216 -
download
0
Transcript of Synopsis Civil
-
7/29/2019 Synopsis Civil
1/11
A SYNOPSIS OF PROJECT REPORT
ON
CONSTRUCTION OF NATIONAL HIGHWAY
Under guidance of
SUBMITTED BY
SUBMITTED TO
-
7/29/2019 Synopsis Civil
2/11
INTRODUCTION
In a National Highway-58 project, the engineer has to plan, design and construct either a
network of new roads or road link.
Once a highway is constructed, development takes along the adjoining land and subsequent
changes in alignment in geometric standards become very difficult. A badly aligned highway
is not only a source of potential traffic hazard, but also causes a considerable increase in
transportation cost and strain on the drivers and the passengers. Therefore, proper
investigation and planning are most important in a road project, keeping in view the present
day needs as well as the future development of the region
-
7/29/2019 Synopsis Civil
3/11
NATIONAL HIGHWAY 58 PROJECT
DEFINITIONS
In the contract the following words and expressions shall have the meanings here by assigned
to them, except where the context otherwise requires:
(i) A BOLLARD is a short vertical post typically found where large ships docks. While
originally it only meant a post used on a quick for mooring, the word now also describes a
variety of structure to control or direct road traffic. The term may be related to bole, meaning
the lower trunk of a tree.
(ii) A BYEPASS is a road or highway that avoids or bypasses a built up area, town, or
village, to let through traffic flow without interference from local traffic, to reduce congestion
in the built up area, and to improve road safety.
If there are no strong land use controls, buildings are built a bypass, converting it into an
ordinary town road, and the bypass may eventually become as congested as the local streets it
was intended to avoid.
(iii) A CURB orKERB is the edge where a raised pavement/footpath, road median, or road
shoulder meets an unraised street or other roadway. Typically made from concrete, asphalt, or
long stones, the purpose is twofold: first as a gutter for proper drainage of the roadway, and
second for safety, to keep motorist from driving into the shoulder, median, sidewalk, or
pavement.
(iv)EMPLOYERS means the person named as suchin part II of these conditions and the
legal successors in title to such person. But not any assignee of such person.
-
7/29/2019 Synopsis Civil
4/11
(V)CONTRACTOR means the person whose tender has been accepted by the employer
and the legal successors in title to such person. But not any assignee of such person.
Contract means the conditions, the specification, the drawings, the bill of quantity,the tender, the letter of acceptance; the contract agreement and such further
documents as may be expressly incorporated in Letter of Acceptance or Contract
Agreement.
Specifications means the specification of the work included in the contract and anymodification therefore or addition.
Drawings means all drawings, calculations and technical information of a likenature provided by the Engineer to the contractor under the contract and all drawings,
Calculations, Samples, Pattern, Models, Operations and maintenance, manuals and
other technical information of a like nature submitted by the contractor and approved
by the Engineer.
Bill of Quantities means the priced and completed bill of quantities forming part oftender.
Section means a part of the works specifically identified in the Contract as asection.
Site means the places provided by the Employer where the works are to beexecuted and any other places as may be specifically designated in the Contract as
forming part of the site.
The contractor shall establish working Bench marks tied with the reference BenchMark in the soon after taking possession of the site. The reference Bench Mark for the
area shall be as indicated in the contract document of the values of the same shall be
obtained by the Contractor from the Engineer. The working bench mark shall be at
rate of 4 per km and also at or near all drainage structures, over bridges and under
passes. The working Bench Mark/levels should be got approved from the Engineer.
Check must be based on this Bench Mark once every month and adjustments, if any,got agreed with the Engineer and recorded. An up-to-date record of all Bench Mark
-
7/29/2019 Synopsis Civil
5/11
including approved adjustments, if any, shall be maintained by the contractor and also
a copy supplied to the Engineer for his record.
The lines and levels of formation, side slopes, drainage works, carriageways andshoulders shall be carefully set out and frequently checked, care being taken to ensure
that correct gradients and cross sections are obtained everywhere. In order to facilitate the setting out of the works, the centreline of the highway must
be accurately established by the contractor and approved by the engineer. It must then
be accurately referenced in a manner satisfactory to the engineer, every 50m intervals
in plain and rolling terrains and 20m intervals in highly terrain and in all curve point
as directed by the engineer, with marker pegs and chainage boards sets in or near the
fence line, and schedule of reference dimensions shall be prepared and supplied by the
Contractor to the Engineer. These markers shall be maintained until the works reach
finished formation levels are accepted by the Engineer.
On construction reaching the formation level stage, the centre line again be set out bythe contractor and when approved by the Engineer, shall be accurately referenced in a
manner satisfactory to the Engineer by markers pegs set at the outer limits of the
formation.
No marker pegs or markers shall be moved without the approval of the Engineer andand no earth work shall be commenced until the centre line has been referenced.
The contractor will be the sole responsible party for safeguarding all surveymonuments, bench marks, etc. The Engineer will provide the Contractor necessary for
setting out of the centre line. All dimensions and levels shown on the drawing or
mentioned in documents forming part of the or issued under the contract shall be
verified by the Contractor on the site and he shall immediately inform the engineer of
any apparent error in such dimensions. The Contractor shall in connection with the
staking out of the canter line, survey the terrain along the road and shall submit the
engineer for his approval, a profile along the road centre line and cross section at
intervals as required by the Engineer.
After obtaining approval of the engineer, work on earthwork can commence and theprofile and cross section shall from the basis for measurements and payments.
The work of setting out shall be deemed to be a part of general works preparatory tothe execution of work and no separate payments shall be made for the same..
-
7/29/2019 Synopsis Civil
6/11
TEST ON SUB GRADE SOIL
(I) GRAIN SIZE ANALYSIS
INTRODUCTION:
Most of the method for the soil identification and classification are based on certain physical
properties of the soil. The commonly used properties for the classification are the grain size
distribution liquid limit and plasticity index. These properties have also been used in
empirical design method for flexible pavement; and in deciding the suitable of sub grad soil.
Grain size analysis also known as mechanical analysis of soil is the determination of the
percent of individual grain size present in the sample. The results of the test are of great value
in soil classification. In mechanical stabilization of soil and for designing soil aggregates
mixture the result of gradation test are used .correlation have also made between the grain
size distribution of soil and the general soil behavior as the sub grade material and theperformance such as susceptibility to frost action, pumping of rigid pavement etc.also
permeability characteristics, bearing capacity and some other properties, are approximately
estimated based on grain size distribution of the soil. The soil is generally divided into four
parts on the particle size. The fraction of the soil which is larger than 2.00 mm size is called
gravel, between 2.00 mm and 0.06 mm is sand 0.002mm silt and that is smaller than 0.002
mm size is clay. Two type of sieves are available, one type with square perforation on plate to
sieves course aggregate and gravel, the other type being mesh sieves made of woven wire
mesh to sieves finer particle such fine aggregate and soil fraction consisting of sand silt and
clay. However the sieves opening of the smallest mesh sieves commonly available is about
0.075 mm, which is commonly known as 200 mesh sieves therefore all soil particle
consisting of silt and clay which are smaller than 0.06 mm size will pass through the fine
mesh sieves with 0.075 mm opening. Therefore the grain size analysis of course fraction of
soil is carried out using sieves the principle of sedimentation in water.
The sieves analysis is a simple test consisting of sieving a measured quantity of material
through successively smaller sieves. The weight retain on each sieves. The weight retain on
each sieve is expressed as a percentage of the total sample. The sediment principle has been
used for finding the grain size distribution of fine fraction; two methods are commonly used
pipette method and the hydrometer method.
The grain size distribution of soil particle of size greater than 63 micron is determine by
sieving the soil on set of sieves of decreasing sieve opening placed one below the other and
separating out the different size ranges.
APPARATUS:
Various apparatus set of standard sieves of different sieves size, balance, and rubber covered
pestle mortar, oven, riffle, sieves shaker.
Procedure
-
7/29/2019 Synopsis Civil
7/11
For the fraction retained on 2.0 mm sieves.Sufficient quantity of dry soil retained on 2.0 mm sieves is weighed out. The quantity
of sample taken may be increased when the maximum size of particle is higher. The
sample separated into various fraction by sieving through the set of sieves of size100,
63, 20, 6, 4.75, and 2 mm is sieves. After initial sieves, material retained on eachsieves carefully collected and weighed.
For fraction passing 2.0 mm sieves and retained on 0.63 mm size.The required quantity of soil sample is taken by riffling or quartering method, dried in
oven at 105 to 110 c and is subjected to dry sieves analysis using a set of sieves with
sieves opening 2.0, 0.6, 0.425, 0.15, and 0.075 mm, pan lid. The material collected on
the each sieves and on the pan are separately collected and weighed.
-
7/29/2019 Synopsis Civil
8/11
OBJECTIVES
my objective for this project is to understand and study planning, construction, lab
testing and standards applied for making of Highway .
-
7/29/2019 Synopsis Civil
9/11
RESEARCH METHODOLOGY
For this study I will study construction of national high which will include meeting with
professional engineers and getting consultancy from experience engineers
a) Secondary SourcesSecondary source will play a vital role to play in this report. A good amount data has been
collected from various published articles and reports found in magazines and journals.
Another vital source has been the Internet and particularly the companies own website.
-
7/29/2019 Synopsis Civil
10/11
Scope of the Project
This Project has special significance for further development in making of highway and road
my project is confined to NH-58 only.
-
7/29/2019 Synopsis Civil
11/11
BIBLIOGRAPHY
1.I.S. specification book on highway.2.Highway material testing book by3.S.K.Khanna, C.E.G Justo.4.Organizations Laboratory.5.Organizations Engineers.