DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
SWG Program Update
21 February 2013
Lieutenant General Chris Bogdan, USAF
Program Executive Officer
F-35 Lightning II Program
2 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
F-35 Program Status Bottom Line Up Front
• F-35 Program on Realistic Baseline and Stable for past 2.5 years
– Slow but Steady progress being made
• Program Executive Officer Assessment
– Affordability is #1 concern
• Development: No more money, no more time
• Production: Prices coming down slowly
• Operations and Sustainment: MUST reduce life cycle costs
– Schedule
• 90% remaining in Production – Delivery Schedule is stable
• 10% remaining in SDD
– Moderate Confidence we will meet our 2015 capabilities (Block 2B)
– Some risk to delivering 2018 capabilities (Block 3F)
– NO showstoppers for known Technical Issues
• Systems Engineering process/discipline producing better results
• Technical Solutions in Work
• Transparency, Accountability, Discipline
• Too Many Opinions, Not Enough Facts
3 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
F-35 Program Status (PEO Assessment)
• Development
– SDD Cost: $55.2B (TY$) SDD Cost to Go: $5.8B Schedule: No Major Slips since 2011
– Testing: Efficiency: Effectiveness:
– Software:
– Other Technical Issues:
• Production
– A/C Cost: 4% Reduction from LRIP 4 to 5 A/C Schedule: Tracking to Post Strike Plan
– A/C Quality: Improving
– A/C Concurrency: Projected costs reduced ~30%; Actual costs well below projected
– Engine Cost: 4% (CTOVL/CV) / 18% (STOVL) Reduction from LRIP 4 to 5
– Engine Schedule: Average 60 days ahead of need
– Engine Quality: Quality escapes a concern
• Sustainment
– O&S Costs (20 yrs production, 30 yrs sustainment):
2011 OSD Estimate: $617B 2012 Program Office Estimate: $549B
– A/C Availability: Readiness drivers identified with corrective actions
– ALIS: 1.0.3 delivered to Edwards, Eglin, Nellis, Yuma; still too many workarounds
– Site Activations: 4 sites to 17 sites in 5 years
(BY12$)
G
R
Y
Y
Y
Y
4 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
F-35 Basics
CY2012 CY2013 CY2014 CY2015 CY2016 CY2017 CY2018
3i
2A 2B 3F Fleet Release Fleet Release Fleet Release
Fleet Release
Development
Schedule
Delivery
Schedule
Base Stand Up Eglin
Yuma
Nellis
Edwards
Luke
Beaufort
A= 18
B= 16
C= 8
A= 54
B= 13
C= 6
A= 23
B= 6
C= 4
A= 11
B= 17
C= 1
A= 134
B= 29
C= 20
A= 106
B= 19
C= 14
A= 93
B= 16
C= 9
LHA-6
Cherry Point
Ogden
Iwakuni
CVN-72
LHD-8
Hill
Italian AF Main
Operating Base (MOB)
Israeli Main
Operating Base
Misawa JP Grottaglia
LHD-1
LHD-2
Block 1 A/B -Initial Simulated Air-to-Air
-Initial Simulated Air-to-
Ground
-Air Refueling
Block 2 A/B -Initial Warfighting Capability
-Initial Deployment
- Initial Weapons Employment
Block 3 I/F -Exportability
-Full Warfighting Capability
-Internal/External Weapons
Block 4 A/B -Follow-On-Development
-Added Weapons
-Improved Capability
-Enhanced Reliability &
Maintainability
F-35 Weapon System Capabilities:
• Development Schedule: .99 Earned Value “SPI” (Steady)
• Development Cost: .99 Earned Value “CPI” (Steady)
Norway
MOB
5 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
2056
2247
2443
2573
1971
2138
2482
2870
0 500 1000 1500 2000 2500 3000 3500
Mission System
F-35C Flight Science
F-35B Flight Science
F-35A Flight Science
CY 12 Test Efficiency
12/31/2012
Planned Test Points
Actual Test Points
Planned Test Points
Actual Test Points
Planned Test Points
Actual Test Points
Planned Test Points
Actual Test Points
Developmental Flight Test
Efficiency
• Facts About 2012:
– 1,167 Test Flights, 18% more than planned
– 9,319 Test Points, 10% more than planned
• Successes:
– High AoA including first Intentional Departure and Attained 75 deg AoA
– First Airborne Separation of GBU-12, GBU-31, AIM-120, Paveway IV training mode, AIM-120 sim
launch against tracked target
– First Flight with Live Countermeasures
– 100% Complete Clean Wing Flutter
– First Night Refueling
– Air Start Testing Complete
• …But, Issues:
• Weapons Bay Flipper Door
• STOVL Operations Due to
Aux Air Doors
• Spin Chute Modification Delays
• CTOL Air-Refueling Stop
CY2012 Flight Test Efficiency
6 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
Developmental Flight Test
Effectiveness
Durability Test Status
Hours Major Finding Corrective Action
1474 Hours FS496 Bulkhead
Cracking (B Model)
Redesign / Retrofit
Cut In BF24
2117 Hours Fwd Root Rib
(A Model)
Redesign / Retrofit
Cut In AF31
7000 Hours FS472 Bulkhead
Cracking (B Model)
Redesign / Retrofit
Cut In LRIP7
5830 hours Avionics Bay Floor
Cracking (C Model)
Redesign / Retrofit
Cut In TBD
Blk 1B
Blk 2A
Blk 2B
Blk 3F
500 KCAS / 0.9M
39k ft
18 deg AoA / 5.5g
400 KCAS / 0.8M
39k ft
18 deg AoA / 4.5g
550 KCAS / 0.9M
40k ft
18 deg AoA / 5.5g
450 KCAS / 0.9M
40k ft
18 deg AoA / 4.5g
450 KCAS / 0.9M
40k ft
18 deg AoA / 4.5g
700 KCAS / 1.6M
40k ft
50 deg AoA / 7.0g
550 KCAS / 1.2M
40k ft
50 deg AoA / 5.5g
550 KCAS / 1.2M
40k ft
50 deg AoA / 6.0g
700 KCAS / 1.6M
50k ft
50 deg AoA / 9.0g
630 KCAS / 1.6M
50k ft
50 deg AoA / 7.0g
700 KCAS / 1.6M
50k ft
50 deg AoA / 7.5g
Plan: 73%
Act: 68% Plan: 64%
Act: 64%
Plan: 65%
Act: 62%
F-35A
Envelope
F-35B
Envelope
F-35C
Envelope
AIM-120
GBU-12
GBU-31 / GBU-32
AIM-9X
SDB-I
JSOW
Gun
Paveway IV
Flight Science
N/A
Y G Y
7 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
F-35 Technical Issues
Issue Key Accomplishments Next Key Milestone Status /
Trend
BK-1 Fueldraulic Line Failure • All F-35B cleared to fly after mod
• Flights resumed on 14 Feb
Return to production
effort ongoing
Gen II Helmet (Jitter, Green Glow, DAS, Acuity, Schedule,
Export)
• 19 of 38 Test Flights Complete
• Green Glow and DAS Latency DONE
• DoD/Service Review of Suitability 6 March
CDR: 16 Apr 13
F-35C Arresting Hook (Prob of Engagem’t, Loads, Landing Spot - SW)
• Redesign Ongoing
• Ground Test at Lakehurst 4Q2013
• Carrier Qualification 3Q2014
AS Block 3 CDR:
30 April 13
Software (Delivery Timeline, Management of Capability
Content)
• New systems engineering rigor to manage SW
build
• Block 2B Mission Systems SW Build Plan
developed
AS Block 3 CDR:
30 April 13
ALIS Maturity (Unreliable health management, immature ALIS
software)
• New systems engineering rigor
• Incremental software fixes
• End-to-End Testing
AS Block 3 CDR:
30 April 13
Lightning Protection (Can’t operate near thunderstorms)
• Conducted Pre-CDR TIM, 23-24 Jan 13 CDR: 26-28 Feb 13
F-35B STOVL Ops (Clear fleet for vertical takeoff/landing)
• BF-19 mod finished
• FRR completed: 24 Jan 13
Interim Flight
Clearance with
NAVAIR Leadership
Fuel Dump (Airframe wetting)
• Flight test: trade study design
solution review
Design downselect:
Mar 2013
Acronyms:; SW: software; CDR: critical design review; TIM: technical interchange meeting; FRR: flight readiness review
As of 14 Feb 13
G
Y
Y
Y
Y
Y
G
Y
8 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
0.0%
2.0%
4.0%
6.0%
8.0%
10.0%
12.0%
14.0%
16.0%
18.0%
2011 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12
Perc
en
tag
e o
f T
ota
l A
ssem
bly
Ho
urs
LM Ft Worth SRR
Suppliers to LM FW SRR
LMFW
Strike
AF
-06
AF
-07
AF
-08
AF
-09
AF
-10
AF
-11
AF
-12
AF
-13
BF
-06
BF
-07
BF
-08
BF
-09
BF
-10
BF
-11
BF
-12
AF
-14
BF
-13
AF
-15
BF
-14
AF
-16
BK
-01
AF
-17
AF
-18
BK
-02
AF
-19
BF
-15
AF
-20
BF
-16
AN
-01
BF
-17
BF
-18
BF
-19
CF
-05
BF
-20
AF
-21
AF
-22
BF
-21
AF
-23
AF
-24
BF
-22
AF
-25
LRIP 1 LRIP 2 LRIP 3 LRIP 4
Ho
urs
TVE
F-35 Nonconformance Hours by TVE(Excludes Fab)
Data as of: 12-10-12
Delivered Aircraft Quality (60 days after First Flight)
Scrap, Rework, Repair Hours
Hours Expended On Quality Defects
F-35 Production Quality (Thru December 2012)
Aircraft
Ho
urs
D
efe
cts
LMFW
Strike
Aircraft
La
bo
r H
ou
rs
F-35 LM touch Labor Hours
Perc
en
tag
e o
f T
ota
l A
ssem
bly
Ho
urs
0
5
10
15
20
25
30
35
AF
-9
AF
-8
A…
A…
A…
A…
BF
-6
BF
-8
BF
-7
BF
-9
B…
B…
B…
A…
A…
A…
BK
-1
B…
B…
B…
B…
BK
-2
B…
B…
B…
AF-9 AF-8 AF-10 AF-11 AF-12 AF-13 BF-6 BF-8 BF-7 BF-9 BF-10 BF-11 BF-12 AF-14 AF-15 AF-16 BK-1 BF-13 BF-14 BF-15 BF-16 BK-2 BF-19 BF-20 BF-21
OQPL 23 24 24 31 29 18 27 25 22 11 11 7 4 4 6 5 9 9 7 6 1 2 1 3 1
Actual Projected CTOL STOVL CV
9 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
F-35 Production Line Status (As of 14 February 2013)
Mate
Final Finishes
Flight line / Field Ops
Aft Fuselage (BAE)
Roll-out
DD250
Forward Fuselage LM Ft Worth
Weight on
Wheels
Alenia
LM Marietta
LM Ft Worth
Wing
Center Fuselage NGC
Tails (BAE)
Ahead of Schedule
1 day ahead
1 day
behind
16 days behind
7 days behind
2 days ahead
Total Assembly ~1 day behind
Field Ops ~16 days behind
*20 M days margin not included
Ahead of Schedule
Total Assembly: 500 Manufacturing Days
10 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
ContractIncrease
Over Target cost
F-35 LRIP 1 (Cost Plus) 11.8%
F-35 LRIP 2 (Cost Plus) 17.2%
F-35 LRIP 3 (Cost Plus) 22.3%
F-35 LRIP 4 (FPIF) 8.7% (50/50)
F-35 LRIP 5 (FPIF) 45/55 over target share ratio
F-35 LRIP 6 (FPIF) 0/100 over target share ratio
Airframe Production Costs
- Month-end December 2012 CPR
- Production Basic Build Effort Only
UR
F T
Y$M
$220
$171
$141 $131
$123
$215
$159
$127
$110 $106
$122
$50
$100
$150
$200
$250
FY07 LRIP 1 2 CTOL
FY08 LRIP 2 6 CTOL
FY09 LRIP 3 7 CTOL
FY10 LRIP 4
10 CTOL
FY11 LRIP 5
22 CTOL
FY12 LRIP 6
18 CTOL
FY13 LRIP 7
19 CTOL
FY14 LRIP 8
19 CTOL
FY15 LRIP 9
32 CTOL
FY16 LRIP 10 48 CTOL
FY17 LRIP 11 48 CTOL
CTOL SAR 11
CTOL Settlement
CTOL EAC
CTOL
Target
$77
$161
$135 $131 $130
$87
$158
$127
$108 $113
$118
$50
$100
$150
$200
$250
FY07 LRIP 1
FY08 LRIP 2
6 STOVL
FY09 LRIP 3
7 STOVL
FY10 LRIP 4
16 STOVL
FY11 LRIP 5
3 STOVL
FY12 LRIP 6
6 STOVL
FY13 LRIP 7
6 STOVL
FY14 LRIP 8
6 STOVL
FY15 LRIP 9
6 STOVL
FY16 LRIP 10 9 STOVL
FY17 LRIP 11
14 STOVL
STOVL SAR 11
STOVL Settlement
STOVL EAC
UR
F T
Y$M
Target
STOVL
$176
$155
$91
$141 $126
$155
$50
$100
$150
$200
$250
FY07 LRIP 1
FY08 LRIP 2
FY09 LRIP 3
FY10 LRIP 4 4 CV
FY11 LRIP 5 7 CV
FY12 LRIP 6 7 CV
FY13 LRIP 7 4 CV
FY14 LRIP 8 4 CV
FY15 LRIP 9 6 CV
FY16 LRIP 10
9 CV
FY17 LRIP 11 14 CV
CV SAR 11
CV Settlement
CV EAC
UR
F T
Y$M
Target
CV
Cost Performance
11 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
Engine Production Costs
Cost Performance
- Month-end December 2012 CPR, with JPO VACs ($ M)
- Production Effort Only
$25
$22
$20
$20 $19
$18 $15
$12
$10
$15
$20
$25
$30
LRIP 1 FY07
LRIP 2 FY08
LRIP 3 FY09
LRIP 4 FY10
LRIP 5 FY11
LRIP 6 FY12
LRIP 7 FY13
LRIP 8 FY14
LRIP 9 FY15
LRIP 10 FY16
LRIP 11 FY17
U
R
F
T
Y
$
M
CTOL Engine EAC CTOL/CV
Settlement CTOL/CV
$25
$22
$20
$20 $19
$18 $15
$12
$10
$15
$20
$25
$30
LRIP 1 FY07
LRIP 2 FY08
LRIP 3 FY09
LRIP 4 FY10
LRIP 5 FY11
LRIP 6 FY12
LRIP 7 FY13
LRIP 8 FY14
LRIP 9 FY15
LRIP 10 FY16
LRIP 11 FY17
U
R
F
T
Y
$
M
CV Engine EAC CTOL/CV
Settlement CTOL/CV
SAR 12 CTOL/CV
$46
$39
$32
$37
$33 $31 $30
$30
$35
$40
$45
$50
LRIP 1 FY07
LRIP 2 FY08
LRIP 3 FY09
LRIP 4 FY10
LRIP 5 FY11
LRIP 6 FY12
LRIP 7 FY13
LRIP 8 FY14
LRIP 9 FY15
LRIP 10 FY16
LRIP 11 FY17
U
R
F
T
Y
$
M
STOVL Engine EAC STOVL
Settlement STOVL
SAR 12 STOVL
CTOL
STOVL
CV
Target
Target
Target
$25
$22
$20
$20 $19
$18 $15
$12
$10
$15
$20
$25
$30
LRIP 1 FY07
LRIP 2 FY08
LRIP 3 FY09
LRIP 4 FY10
LRIP 5 FY11
LRIP 6 FY12
LRIP 7 FY13
LRIP 8 FY14
LRIP 9 FY15
LRIP 10 FY16
LRIP 11 FY17
U
R
F
T
Y
$
M
CV Engine EAC CTOL/CV
Settlement CTOL/CV
SAR 12 CTOL/CV
ContractIncrease
Over Target cost
F135 LRIP 1 (Cost Plus) 4%
F135 LRIP 2 (Cost Plus) 13%
F135 LRIP 3 (Cost Plus) 11%
F135 LRIP 4 (FPIF) 3% (50/50)
F135 LRIP 5 (FPIF) 0/100 over target share ratio
F135 LRIP 6 (FPIF) 0/100 over target share ratio
12 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
Concurrency
• Concurrency is defined as the overlap of the development, test, production, fielding, operations
and sustainment phases of an acquisition program
• Concurrency introduces risk of discoveries during production – requiring retrofit of delivered a/c
– Fixes rolled into Production line – Timelines decreasing (18 mos to 13 mos)
– Retrofit aircraft already produced – requires modifications (Mod plan created and regularly updated)
– Lockheed Martin sharing in Concurrency costs (LRIP 5 and beyond)
• Concurrency Changes are identified during Flight Test, Qualification Test, Ground Test
Increased Discipline in Estimating & Controlling Concurrency Costs
High-Level Mod Schedule Projected Concurrency Cost by LRIP Lot
• Group 1 Mod Examples:
– Forward Root Rib (STOVL/CTOL)
– Station 3/9 Aft Rib (STOVL/CTOL)
– FS 496 Bulkhead (STOVL)
13 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
F-35 Sustainment
Metric Requirement
By Variant
(CTOL/STOVL/CV)
Current Actual By Variant
(CTOL/STOVL/CV)
Status Against the
Plan By Variant
(CTOL/STOVL/CV)
Reliability & Maintainability
MFHBFDC (Airframe) (6.0/4.0/4.0) (1.66/1.44/1.53)
MFHBFDC (Engine) (290/220/250) (45.1/21.0/22.7)
Prognostic / Health Monitoring
Fault Detection Rate (%) 98 79.80
Electronic Fault Isolation (%) 90 70.00
False Alarms (MFHBFA) 50 .45
Mean Downtime (Supply and Maint)
Maintenance Man-Hours / Flight Hour Unsch. (MMH/FH(U)) (6.0/6.0/6.0) (6.10/4.09/3.77)
Elapsed Maintenance Time (MTTR) (2.5/3.0/2.5) (12.97/11.97/5.21)
MFHBFDC = Maintenance flight hours between failure
14 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
F-35 Sustainment
Non-Mission Capable - Supply Non-Mission Capable - Maintenance
Go
od
Go
od
0%
10%
20%
30%
40%
50% CTOL NMC-S STOVL NMC-S FLEET NMC-S
0%
20%
40%
60%
80%
100% CTOL NMC-M STOVL NMC-M FLEET NMC-M
0%
20%
40%
60%
80%
100% Eglin CTOL AVA Eglin STOVL AVA Eglin FLEET AVA
Go
od
Air Vehicle Availability
15 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
0
200
400
600
800
1000
1200
1400
1600
1800
Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13
F-35 Operational Training ATC Student Throughput
0
20
40
60
80
100
120
140
Apr-
12
May-1
2
Jun-1
2
Jul-
12
Aug-1
2
Sep-1
2
Oct-
12
Nov-1
2
Dec-1
2
Jan-1
3
Feb-1
3
Mar-
13
Apr-
13
May-1
3
Jun-1
3
Jul-
13
Aug-1
3
Sep-1
3
Oct-
13
Nov-1
3
Dec-1
3
Jan-1
4
Feb-1
4
Mar-
14
Ap
r-14
May-1
4
Jun-1
4
Jul-
14
Aug-1
4
Sep-1
4
Oct-
14
Pilots Planned
Pilots Graduated
(End of Month)
(End of Month)
Maintainers
Planned
Maintainers
Graduated
Maintenance Training
Pilot Training
Missed planned target due to: 1) IATO security shutdown in Dec 2011
2) ~60 % Services seat fill rate
16 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
F-35 Sustainment Strategy
• F-35 Program Office will be Product Support Manager
• Product Support Integrator – Not Yet Determined
– LM and P&W have not earned right yet
• Inject Competition where Feasible – Industry Day Results
– Support Equipment
– ALIS Administration
• Improve Reliability and Maintainability of Weapon System
– Repair Contracts
– Robust R&M Team
– Deep Dive of top 20 Air Vehicle Depot Level Reparable (AVDLR) Costs
– R&M Sensitivity analysis of top 50 AVDLR
• Cost per Flying Hour Estimating
• ALIS Improvements
– Global Supply Chain
– Training Center Operations
17 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
F-35 PEO Planning Priorities Year Long Continuing Resolution/Sequestration
• Preserve System Design and Development to the maximum extent possible
• Keep Initial Operational Capability Options open with Block 2B
• Wholeness: Support and sustain all delivered aircraft
• Preserve efficiencies in production to the maximum extent possible. – Reductions will decrease LRIP 7 quantities, increasing unit
recurring flyaway cost
• Maintain production capacity to the maximum extent possible. – Reductions will decrease investments in tooling, redesigns for
obsolete parts, and cost reduction initiatives
18 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
Partner Challenges
• Cost Visibility
– JPO directing LM/PW to adjust Cost Reporting
• Reprogramming Labs
– Partner/FMS Reprogramming Labs late to need; working to recover schedule
• Airworthiness Requirements
– Single Airworthiness Process / Data for all Partners
• Partner unique needs accommodated (funded) on a case-by-case basis
• Transition to pooled training (2013-2014)
– Pooling Implementation Agreements and Contract signatures pending
• Long-Term Training and infrastructure for CONUS-based
international training and basing
– Working with Partners on requests for long-term support and U.S. military
construction projects
19 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
Summary
• Program Making Steady Progress – Realistic Plan
– Driving Stability into the Program
– Schedule/Capabilities Holding Steady
• Affordability is Critical for US and Partners
• Technical Issues are being worked
• New Culture for Industry, Program Office, DoD
Enterprise – Look Forward, Not Back
– Transparency, Accountability, Discipline
– Too many opinions, not enough facts
• F-35 Program MUST deliver on its Promises – Hold ME accountable
20 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
Questions?