SWATI Modified

download SWATI Modified

of 25

Transcript of SWATI Modified

  • 8/6/2019 SWATI Modified

    1/25

    FUNCTIONING OF PEM-FINANCE

    BY

    SWATI NAIR

    STAFF NO. 6075975

    EXECUTIVE TRAINEE

    BATCH: 2009-10

    FINANCE

    PROJECT ENGINEERING MANAGEMENT

    BHEL, PEM/PPEI NOIDA

  • 8/6/2019 SWATI Modified

    2/25

    PEM/PPEI Building Page 2Plot No.25, Sector- 16ANoida-201301

    ACKNOWLEDGEMENT

    At this moment, I have hardly enough words to express my gratitude

    towards those who were constantly involved with me during my on the job

    training period at PEM- (FINANCE), BHEL.

    First of all, my heartfelt thanks to Functional Head Mr Shashi Kant Sahni

    who helped me every possible manner. He ensured a proper environment for us

    to work in. For my Department Head Miss. Rita Saxena, it cannot be gone unsaid

    that she put in a sincere effort to make me learn and devoted a lot of her valuable

    time to see that I receive a proper modular training in different areas.

    I express my sincere gratitude to my mentor and guide Mrs. Poonam Lulla, being a

    constant source of inspiration. He ensured that my learning in this department is

    complete and reposed faith in my work by assigning responsibilities and giving

    freedom. Besides, I express my sincere thanks to all the members of Finance

    Deptt. for their friendly and helpful attitude.

    SWATI NAIR

    EXECUTIVE TRAINEE

    STAFF NO. 6075975

    BHEL PEM

  • 8/6/2019 SWATI Modified

    3/25

    PEM/PPEI Building Page 3Plot No.25, Sector- 16ANoida-201301

    CERTIFICATE

    This is to certify that this project report entitled " ON JOB TRAINING

    REPORT by Ms. SWATI NAIR after completion of on-the-job training, is a

    record of bonafide work carried out by her under my supervision and

    guidance. This is as a part of her training programme and being

    submitted to HRDD - Power Sector, Kribhco Bhavan, Noida.

    Ms. Rita Saxena Mrs. Poonam A. Lulla

    DGM Sr. MGR

    BHEL - PEM BHEL - PEM

  • 8/6/2019 SWATI Modified

    4/25

    PEM/PPEI Building Page 4Plot No.25, Sector- 16ANoida-201301

    ABSTRACT

    The purpose of this report is to give a brief idea about the project work

    that has been done during On Job Training to sharpen the skills in

    practical aspects of the job. Project work is carried out in work related

    area. Broadly, the various activities which made a part of our on the job

    training were PEM familiarization, familiarization with work

    particularly in Finance and finally the day to day learning of the

    routine work in the department. It contains introduction about

    organization and PEM is given followed by description of Finance

    department and its functions in PEM. On the whole, this report gives a

    clear picture about my ten months on the job training in BHEL during

    my tenure as Executive Trainee.

  • 8/6/2019 SWATI Modified

    5/25

    PEM/PPEI Building Page 5Plot No.25, Sector- 16ANoida-201301

    INDEX

    Title

    TABLE OF CONTENT

    ACKNOWLEDGEMENT 2

    CERTIFICATE 3

    ABSTRACT 4

    OVERVIEW OF ORGANISATION

    ABOUTTHEORGANIZATION 6-8

    PROJECTENGINEERINGMANAGEMENTDIVISION 9-10

    OVERVIEW OF FIN DEPARTMENT 11-12

    WORK CONTENT OF ON THE JOB TRAINING

    ASSIGNMENTSDURINGON-JOBTRAINING: 12-24

    CONCLUSION 25

  • 8/6/2019 SWATI Modified

    6/25

    PEM/PPEI Building Page 6Plot No.25, Sector- 16ANoida-201301

    1.BHEL: AN OVERVIEW

    1.1 INTRODUCTION

    BHEL is the largest engineering and manufacturing enterprise in India in the energy-

    related/infrastructure sector, today. BHEL was established more than 45 years ago with

    the vision to become a world class engineering enterprises, committed to enhancing

    stakeholders value. The company is striving to give shape to its aspirations and fulfill the

    expectations of the country to become a global player.

    1.2 HIGHLIGHTS

    BHEL sets contributed 74% of the power

    generated in the country in Financial

    Year 2009-10.

    Has earning profit continuously since

    1971-72 and paying dividend since

    1976-77.

    Total order in hand for, at 31st March

    2010, execution in 2010-11 and

    beyond stands about Rs. 143800Crores the highest-ever.

    Caters to the core sector of the Indian

    Economy viz. power generation and

    transmission, industry, transportation,

    renewable energy etc.

    Have a wide network of 14

    manufacturing divisions, 4 power

    sector regional centres, 8 service centres, 18 regional offices and more than 100s of

    projects. Apart from it BHEL has one subsidiary named Bharat Heavy Plates &

    Vessels (BHPV). BHPV is a fully owned subsidiary of BHEL taken over in May, 2008.

    BHEL have multiple portfolios operating at the same point of time. More than 70% of

    the BHELs total business comes from power sector.

    Has made its presence over 60 countries. Foray into a new market Belarus.

  • 8/6/2019 SWATI Modified

    7/25

    PEM/PPEI Building Page 7Plot No.25, Sector- 16ANoida-201301

    Has acquired certification to Quality Management System (ISO 9001), Environmental

    management System (ISO 14001) and Occupational Health and Safety management

    System (OHSAS 18001).

    Manufactures over 180 products under 30 major product groups.

    Capability to deliver 15000 MW of power equipment per annum established and

    further augmentation to 20000 MW per annum by March, 2012.

    For the second time, Business Standard newspaper recognized BHEL as the Star

    Public Sector Company of the year for Financial Year 2009-10.

    1.3 FINANCIAL PERFORMANCE

    BHEL notched up its highest ever turnover of Rs.

    34050* Crore with a PBT of Rs. 6353* in the

    Financial Year 2009-10.

    Net Profit of Rs. 4287* Crore with a EPS of Rs.

    87.60* for the Financial Year 2009-10.

    Total export turnover (Physical + Deemed)

    touched Rs. 14436 Crores.

    Total Net Worth of Rs. 15721* Crores at the end

    of Financial Year 2009-10.

    Expected Performance for the year 2010-11

    Parameters

    Gross Sales (Millions) 380,000

    Gross margin (Million) 81,200

    PBDIT to Total Employment (Million) 1.740

    Gross Margin to Gross Block (%) 92.02

    Gross Profit to Capital Employed (at year

    end) (%)

    45.71

    Net Profit to Net Worth at year end) (%) 25.64

    Added Value to Gross Sales (%) 17.03

  • 8/6/2019 SWATI Modified

    8/25

    PEM/PPEI Building Page 8Plot No.25, Sector- 16ANoida-201301

    Further a stretch Turnover target of Rs. 395,000 Millions has been fixed under Excellent

    rating.

    1.4 STRENGTH

    The greatest strength ofBHEL is its highly skilled & committed employees. Every employee

    is given an equal opportunity to develop himself and grow in his career. Continuous training

    and retraining, career planning, a positive work culture and participative style of

    management, all these have engendered development of a committed and motivated

    workforce leading to productivity, quality & responsiveness.

  • 8/6/2019 SWATI Modified

    9/25

    PEM/PPEI Building Page 9Plot No.25, Sector- 16ANoida-201301

    2. PROJECT ENGINEERING MANAGEMENT (PEM)

    2.1 Introduction of PEM

    Project Engineering Management Division (PEM) is a division within the power

    group of BHEL to provide total Systems Engineering for BHEL equipment, as well as for

    procurement, erection & commissioning of non-BHEL systems & equipment for thermal

    power stations.

    Fig. 2.1 PEM and its Coordination

    Project Engineering

    Management

    Customer/

    Consultants National

    BodiesProject Engg

    Balance Of Plant

    Vendors

    Quality/Inspection

    Agencies

    Project/site

    Management

    Contracting

    Agencies

    BHEL

    Mfg. Units

  • 8/6/2019 SWATI Modified

    10/25

    PEM/PPEI Building Page 10Plot No.25, Sector- 16ANoida-201301

    In 1974, BHEL set up its engineering consultancy wing under the name Consultancy

    Services Division (CSD) to address the market demand for turnkey services in power and

    related areas. In 1977, CSD was re-christened as Projects Engineering Division (PED). Since

    1984, it has been known as Project Engineering Management (PEM).

    Project Engineering Management (PEM) division is BHEL's power plant 'System

    Integrator' providing total engineering solutions for power projects as well as procurement

    and erection & commissioning of non-BHEL systems & equipment for thermal power

    stations, thereby enabling BHEL to offer complete Engineering, Procurement and

    Construction (EPC) services.

    PEM is responsible for the procurement of Balance of Plant (BOP) items, these are the

    items which are not manufactured by BHEL and required for the setting up of the Power

    Plant.

    PEM also provides total engineering solutions for Power Projects as well as procurement

    and erection & commissioning of non-BHEL systems & equipment for power stations,

    thereby enabling BHEL to offer complete Engineering, Procurement and Construction (EPC)

    services.

    Currently PEM is handling more than 125 customer projects.

    2.3. DEPARTMENTS IN PEM

    Mechanical System Engineering(MSE)

    Mechanical Piping Layout(MPL)

    Mechanical Auxiliaries (MAUX)

    Electrical

    Civil

    Control And Instrumentation(C & I)

    QualityProposal Engineering(PE)

    Project Group (PG)

    Finance

    Human Resource.

  • 8/6/2019 SWATI Modified

    11/25

    PEM/PPEI Building Page 11Plot No.25, Sector- 16ANoida-201301

    3. MY DEPARTMENT: FINANCE

    Finance Section of PEM is divided as below;

    A brief of responsibility of the above sections of finance departments are as follows;

    Project Section:

    Routine Accounting of all the power projects.

    Preparation and regular updating of AS-7 (Accounting for construction contracts).

    Making payments to indigenous vendors and foreign vendors (LC payments) for the

    material supplied by them.

    Customer billings, updation of collections, and reconciliation of debtors.

    Getting the Quarterly and Annual audit of Power Projects which is being handled.

    Concurrence Section:

    Granting concurrence to procurement files, which involves vetting of Comparative

    Statements and ordering proposal.

    For the purpose of procurement of material it is necessary to have good vendor base

    for different items, so that advantage of competitive prices could be availed. Hence

    PEM have a dedicated cell which is known by the name of Vendor Development Cell

    which is involved in evaluating and registration of new vendors.

    Ensuring that items are procured at lowest possible for prices, for this concurrence

    cell ensures that Reverse Auction is conducted where ever is required, so that the

    items are procured at the lowest possible prices.

    FINANCE

    PROJECT CONCURRENCE ESTABLISHMENT BOOKS AND

    MIR

    TAXATION

  • 8/6/2019 SWATI Modified

    12/25

    PEM/PPEI Building Page 12Plot No.25, Sector- 16ANoida-201301

    To take part in negotiation with the vendors in order to obtain the best prices for the

    items.

    Establishment:

    Processing of employees salary and other benefits payable to employees, payment of

    advances and processing of employees claims (Like Medical, Tour allowances etc.).

    Taxation Cell:

    Monthly reporting and filling of returns of CST and VAT.

    Timely depositing of TDS and Service tax.

    Issuing C forms to the vendors.

    Dealing with various Nodal Agencies on the issues relating to Central sales tax and

    VAT.

    Books and MIR:

    All the activities relating to budgeting.

    Maintaining the records of all the fixed assets.

    Coordinating statutory, Government, Tax and internal audit.

    Monthly preparation of various MIR`s.

    Controlling the inter unit transactions.

    Vetting of proposals of PE`s.Review of all the balances, including the Debtors.

    Ensuring the proper quarterly and annual closing of accounts.

  • 8/6/2019 SWATI Modified

    13/25

    PEM/PPEI Building Page 13Plot No.25, Sector- 16ANoida-201301

    4.WHERE I STANDS:

    4.1 My work consists of the following;

    Billing to the customers.

    Processing of vendor bills.

    AS 7 sheet preparation and updation.

    Updating cash collection

    Quarterly & Financial Closing.

    Accounting for Inter Unit Transaction.

    4.1.1 BILLING TO THE CUSTOMERS

    Billing advices are submitted by PG to finance department along with invoice, Material

    dispatch clearance certificate(MDCC),Packing list, Lorry Receipt as required by the

    particular contract between BHEL & Customer.

    Items to be billed should be in line with BBU.

    Before making billing invoice to the customer we should ensure that concern liability is

    booked.

    Billing is done as per the terms of payment with customer. For example 10% on advance

    60% on dispatch, 20% on deffered & 10% on MRC billing.

    Billings are of following types types. One is dispatch billing, second is MRC billing third

    is PVC billing, and forth is Freight billing.

  • 8/6/2019 SWATI Modified

    14/25

    PEM/PPEI Building Page 14Plot No.25, Sector- 16ANoida-201301

    4.1.2 PROCESSING OF VENDORBILLS

    Bills are submitted by vendors to the Project Groups

    (PG), upon the checking of by PG this are forwarded

    to Finance for the payment, each payment is allotted

    a unique number which is known as CMP control

    number for keeping the track of payments.

    Item description, quantity and rate are verified with

    the billing schedule.

    Amount and rate of taxes & duties, packing &

    forwarding and freight charges are checked with

    respect to the conditions given in the purchase

    order.

    Calculations are checked and the net amount claimed is verified with respect to the

    terms of payment.

    It is ensured that all necessary documents like Packing List, LR, MDCC, Guarantee

    Certificates, Insurance Intimation, as required in the purchase order, are enclosed

    with the bill.

    It is ensured that the date of LR falls within the contractual delivery date LD amount,

    as per the terms of the PO, is deducted from the net amount claimed.

    It is verified that the bank guarantee (PBG/SDBG), has been received from the

    vendor and the same is valid, as per the terms of the PO.

    For making MRC payment, MRC issued at site is to be accompanied with the bill. Any

    shortage/ damage reported in the MRC is to be taken care of, and necessary

    recovery is made from vendors bill. Bill date should not be earlier than MRC date.

    Freight claims are to be accompanied with MRC and transporters money receipt,

    where ever applicable. Total freight to be restricted to the amount mentioned in the

    PO.

  • 8/6/2019 SWATI Modified

    15/25

    PEM/PPEI Building Page 15Plot No.25, Sector- 16ANoida-201301

    Claim of initial 5% payment, against approval of category I/II drawings, is released

    on declaration of the same by CMP/ Eng.

    In case the payment is through bank and any deduction has been made from the

    vendors bill, a letter from the vendor, advising their bankers to accept the reducedamount, is obtained.

    In case of payment through LC, advance set of documents is to be scrutinized and

    ensured that all the documents, as required under LC terms, have been provided by

    the vendor.

    Check list for passing of vendor bill;

    o Copy of LR & Packing Slip.o Copy of dispatch clearance customer.o Copy of test certificates/inspection reports, CQIR report etc if indicated in the

    SCC/ Project checklist.

    o Copy of vendor invoice.o Insurance intimation letter.o Copy ofGuarantee certificate issued by vendor.o Excise invoice of vendor if indicated in the Project checklist.o Any other document if specified in the Project checklist.

  • 8/6/2019 SWATI Modified

    16/25

  • 8/6/2019 SWATI Modified

    17/25

    PEM/PPEI Building Page 17Plot No.25, Sector- 16ANoida-201301

    Combining and Segmentation of Assets for AS 7.

    Criteria for Segmenting and Combining Segment Combine

    A contract comprises of number of assets

    Separate proposals have beensubmitted for each asset.

    Each asset has been subject toseparate negotiation.

    Contractor / Customer ca accept/reject a part of contract linked to

    that asset. and

    Cost and revenue of each asset canbe separately identified.

    Treat each asset

    as separate

    contract unit.

    Construction of an additional asset at the option

    of the customer or amendment to the original

    contract to construct an additional asset:

    When asset differ significantly in design,technology or function;

    Price of the asset is negotiated withoutregards to the original contract.

    Treat as separate

    contract unit.

    A group of contracts are negotiated as single

    package.

    Contacts are closely interrelated which ineffect can be treated as a single project

    with an overall profit margin.

    Contracts are performed concurrently orin a continuous sequence.

    Treat all such

    contracts as a

    single contract.

    It may so

    happen that

    those contracts

    are with asingle customer

    or several

    customers.

  • 8/6/2019 SWATI Modified

    18/25

    PEM/PPEI Building Page 18Plot No.25, Sector- 16ANoida-201301

    CONTRACT REVENUE AND COST

    CONSTRUCTION CONTRACT

    FIXED PRICE COST PLUS

    REVENUE REVENUE

    Initial Price Agreed Actual Cost Incurred as per

    Add: Agreed Variation or claim agreed cost formula.

    for changes in design, etc. Add: Agreed % on cost

    Add: Agreed Cost Escalation Add: Incentives

    Add: Incentives Less: Penalties

    Less: Penalties

    COST COST

    Direct Cost to Contract Direct Cost to Contract

    Add: Cost that can be allocated to Add: Cost that can be

    Contract. allocated to contract.

    Add: Cost Specifically chargeable Add: Cost Specifically to

    customer. Chargeable to customer.

  • 8/6/2019 SWATI Modified

    19/25

    PEM/PPEI Building Page 19Plot No.25, Sector- 16ANoida-201301

    NOTES:

    1. Claims Arise from delay in supplying the design or specification by the customer oralteration to work which has been done as per approved design. They are included in

    the contract revenue when negotiations have reached an advance stage such that

    the customer will accept the claim and amount can be reliably measured.

    2. Incentives incentives are paid to the contractor when specified standard isachieved or exceeded. Incentive can be recognized as contract revenue when the

    contract is sufficiently advanced to ascertain the degree of standard achieved and

    the amount of incentive to be awarded by the customer can be reliably measured.

    3. It can be noted that in order to recognized the revenue revenue can be

    reliably measured is a must condition.

    4. Direct cost should not be reduced by the sale proceed of surplus material or plant

    and machinery. They are treated as only Other Income. However as per IAS 11

    costs can be reduced by the mentioned sale proceeds.

    5. Again following question may arise;

    For which period cost may be accumulated? What will happen to the cost incurred prior to the date of securing the contract?

    The point wise answer is as follows;

    Cost should be identified from the date of securing the contract to the finalcompletion of contract.

    Cost of obtaining the contract may be included in the contract cost. However if thecost has already been charged to expenses it cant be written back for the purpose of

    inclusion into contract cost. In case cost for obtaining the contract is spent in one

    year and contract is secured in another year, then such cost can be deferred subject

  • 8/6/2019 SWATI Modified

    20/25

    PEM/PPEI Building Page 20Plot No.25, Sector- 16ANoida-201301

    to there is a reasonable certainty that the contract will be obtained. If in the

    subsequent year contract is not obtain then such expenses should be written off.

    6. However the following cost should not charge to contract;

    General Administration Selling Research and development. Depreciation on plant not used in the particular contract.

    RECOGNITION OF REVENUE AND COST.

    When the outcome of a contract can be estimated reliably, contract revenue

    and contract cost associated with the construction contract shall be recognized as

    revenue and expenses respectively by reference to the stage of completion of

    contract activity at the end of the reporting period. An expected loss on the

    construction contract shall be recognized as expenses immediately.

    Since the recognition of revenue and expenses under construction contract isdepend upon reliable estimation of outcome of the contract. How to satisfy

    that outcome can be reliably estimated? It can be clear from the following

    table.

  • 8/6/2019 SWATI Modified

    21/25

    PEM/PPEI Building Page 21Plot No.25, Sector- 16ANoida-201301

    CONSTRUCTION CONTRACT:

    Outcome of the contract can be reliably estimated if

    Fixed Price Contract Cost Plus Contract

    - Total contract revenue can bemeasured reliably.

    - It is probable that economicbenefit attached to the

    contract will flow to the

    enterprises.

    - Stage of completion can bereliably measured.

    - Cost to complete the contractcan be reliably measured.

    - Cost attributable to thecontract can be clearly

    identified and measured

    reliably.

    - Contract cost attributable tothe contract can be clearly

    identified and reliably

    measured.

    - Contract cost may or may notspecifically reimbursable.

    - It is probable that economicbenefit attached to the

    contract will flow to the

    enterprises.

    Secondly how to determine the stage of completion?Stage of completion should reflect the work performed. For this standardspecified three methods as below;

    Ratio of cost incurred to date to estimated total cost. The formula canbe put as below;

    Cost to Date

    % of Completion = ------------------------------------------------------------------

    Cumulative Cost Incurred + Estimated Cost to Complete.

    Survey of work performed. Completion of a physical proportion of the contract work.

  • 8/6/2019 SWATI Modified

    22/25

    PEM/PPEI Building Page 22Plot No.25, Sector- 16ANoida-201301

    Note: The question may arise whether stage of completion be measured

    with reference to progress payment received? The answer is NO; it can

    only be a indicator.

    Revenue when outcome of the contract can be reliably measured.Revenue = Contract Price X Percentage of Completion Revenue Previously

    Recognized

    Cost: Contract costs are usually recognized as an expense in profit and loss

    account in the accounting period in which the work to which they relate

    is performed.

    Finally the billion dollar question comes? What accounting to be done whenoutcome cant be reliably measured.

    Revenue should be recognized only to the extent contract cost areincurred and recovery of which is probable.

    Any expected loss should be recognized as an expense.

    This may happen during the early stage of completion when the outcome of

    the contract cannot be reliably measured. However as soon as the

    uncertainties attached to the reliable estimation of outcome do not exist,

    revenue recognition should be carried out as per percentage completion

    method.

    AS 7 operations in BHEL PEM.

    Overall revenue to be generated from the contract is to be ascertained at theinception, for this purpose Marketing is responsible for dividing the total contract

    price to be received from the customer to various units of BHEL; scope for

    individual unit is also decided by marketing itself.

    On the basis of scope decided by marketing Proposal Engineering provides theestimated cost to be incurred (commonly known as PE estimates) for each of the

    package covered.

    After determination of PE estimates, next is the issue of Indent by the respectiveengineering department for the procurement of particular package. Indent

  • 8/6/2019 SWATI Modified

    23/25

    PEM/PPEI Building Page 23Plot No.25, Sector- 16ANoida-201301

    specifies the technical specification of the packages which are required to be

    procured, along with the estimated cost. At this stage PE estimates are replaced

    with the indent values for the purpose of determination of estimated cost.

    After the indenting of stage, next stage is of placing the order for theprocurement of the item, for this purpose Notice inviting tenders are issued to

    Customer and BHEL approved vendors, on the receipt of tenders statement of

    comparative prices is prepared and the Purchase order is placed to the L1

    vendor.

    Once the purchase order are placed the indent values are replaced with purchaseorder price as the estimated cost.

    For the purpose of determination of contract revenue for a particular period, AS 7factor is worked out by dividing estimated contract revenue by total estimated

    cost and the same is multiplied by the actual cost incurred for the particular

    period.

    In order to match the AS7 revenue as the revenue as per books a adjustmententry is passed, either by debiting or crediting valuation adjustment account.

    Amount to be debited or to be credited to adjustment account is arrived ;{Revenue as per AS7- GDPB- Billing done}

    GDPB; - are the goods which are dispatched by vendor, but the same have notbeen billed on customer because of non-availability of certain documents same is

    treated as good as billing done for a particular period.

    Important Points to be considered for working of AS-7:

    First of all it is important to go through the customer contract, in order toascertain the following:

    The status of project weather it is Mega Power Project or not and weather thecustomer has obtained the necessary clearances from the respective authorities.

    Weather there is any re-imbruement of applicable taxes or duties, like exciseduty, customs duty etc.

    The major terms and conditions for claiming the payment from the customer.

  • 8/6/2019 SWATI Modified

    24/25

    PEM/PPEI Building Page 24Plot No.25, Sector- 16ANoida-201301

    If there is any re-imbruement of applicable taxes or duties same should not betaken into the total estimated cost.

    Total amount of allocated by Marketing should me checked with reference to thecommunication received.

    4.1.4 UPDATING CASH COLLECTION

    Collections are received by the corporate office from the customers & itsintimation is given to project section by the books section.

    Further details of collections like, against which project & which invoice cashis received, are given by Project Group.

    Details of LD deducted or TDS deducted by customer are also given by theProject Group.

    After receiving credit from corporate office finance deptt., debited 4190account which is cash collection from corporate office & credited debtors

    account.

    Project section also updates their sales register with collection received.

    4.1.5 QUARTERLY/FINANCIAL CLOSING

    Booking of all liabilities for the dispatches, taxes & duties freight, testcharges, supervision charges, and engineering consultancy incurred up to the

    date of closing.

    AS-7 Recognition of turnover as per Accounting standard 7.Review theestimated cost to complete and actual cost incurred in respect of each

    contract at the time of each closing

    Passing JVs for inter unit debits. Matching of cost & turnover. Booking ofGDBP (Goods dispatch pending billing): The booking of turnover in

    respect of those goods which are though dispatched to customers site but

    billing is still pending.

  • 8/6/2019 SWATI Modified

    25/25

    PEM/PPEI Building Page 25Plot No.25, Sector- 16ANoida 201301

    Reversal of turnover which has been recognized but remains unbilled as GDBPfor more than six months, to be shown as finished goods stock

    5. CONCLUSION

    PEM is a hub of learning and engineering activity, which enables overall understanding and

    provides a total view of a power plant. This division, being the core engineering division for

    design of power plant is a great platform to start the process of learning about the

    commercial aspect of power plants.

    I got opportunity to interact with all the Engineering Departments also and came to know

    about different activities carried out in PEM.

    I am looking forward to contribute to the best of my capabilities in my department and

    make my career in BHEL to get rewarding and enriching experience.