SWACHH MAHARASHTRA ABHIYAN - e Tenders. Flooring Systems : On the bottom frame 3.2 mm thick GI Sheet...
Transcript of SWACHH MAHARASHTRA ABHIYAN - e Tenders. Flooring Systems : On the bottom frame 3.2 mm thick GI Sheet...
Signature of Tenderer No. of Corrections Signature of NMMC Official
1
SWACHH MAHARASHTRA ABHIYAN
B-1/NMMC/Dy. Comm. (SMA) / 2 (12) / 2016-2017
Tender for the work of
Providing and fixing portable container type Community Toilet with
Bio-Digester Technology at Ishwar Nagar near Mannubhai Maidan
(Female) in Zone No. 4 (North) Digha Ward.
Date of Sale & Upload 20/04/2016 10.00 Hours to 30/04/2016 13.00 Hours
Date of Submission 30/04/2016 15.00 Hours to 04/05/2016 15.00 Hours
Date of Opening 04/05/2016 at 16:00 Hours (If Possible)
Tender Price Rs.1,000/- (Non-Refundable)
Navi Mumbai Municipal Corporation New Head Office Building, Plot No.1, Ground Floor,
Palm Beach Junction, Sector – 15 A,
Belapur C.B.D., Navi Mumbai – 400 614
Signature of Tenderer No. of Corrections Signature of NMMC Official
2
SCHEDULE ‘A’
B-1 /NMMC/Dy. Comm. (SMA)/ 2 ( 12 )/2016-2017
Note :- All the Contractors may note that Enrollment with NMMC is compulsory.
1. Name of Tender Providing and fixing portable container type Community Toilet with Bio-
Digester Technology at Ishwar Nagar near Mannubhai Maidan (Female) in
Zone No. 4 (North) Digha Ward. 2. Estimated cost of
Work Rs.16,94,500/-
3 Persons Responsible Deputy Engineer (SMA), Dy. Commissioner (SMA)
4. Eligibility Criteria and Documents Required to Establish Eligibility
Criteria Required eligibility Documents Required to be attached with
tender or to be uploaded in case of e-
submission to Establish Eligibility
a Registration Class VA & above category with PWD
or equivalent Class with CIDCO Ltd. or Maharashtra Jeevan Pradhikaran (UPTO
Rs. 30 Lacs)
As per Enrollment of NMMC
b Average annual Turn
over for last three
years
Average annual financial during the last
3 years ending 31 st March of the
previous financial year should be at least 30% of the estimate cost. i.e.
Rs.5,08,350/-
c Experience Experience of having successfully
Completed e – toilet/ F.R.P. toilet
/Container Toilet/ RCC Toilet/ RCC Building works during last 7 years
ending last day of month previous to the
one in which bids are invited should be
either of the following
a) Three completed e – toilet/ F.R.P.
toilet /Container Toilet / RCC Toilet / RCC Building works with Govt., semi
Govt., Govt. undertaking, Local Self
Govt. costing not less than the amount
equal to 40% of the estimated cost. i.e.
each work of Rs.6,77,800/-
OR
b) Two completed e – toilet/ F.R.P. toilet /Container Toilet / RCC Toilet /
RCC Building works with Govt., semi
Govt., Govt. undertaking, Local Self
Govt. costing not less than the amount
equal to 50% of the estimated cost. i.e.
each work of Rs.8,47,250/-
Or
c) One completed e – toilet/ F.R.P.
toilet /Container Toilet / RCC Toilet /
RCC Building works with Govt., semi
Govt. Govt. undertaking, Local Self
Govt. costing not less than the amount
equal to 80% of the estimated cost. i.e. each work of
Rs.13,55,600/-
Signature of Tenderer No. of Corrections Signature of NMMC Official
3
d Equipment Available Plant and Machinery – Annexure 3 (The
tenderer needs to upload the document
mentioned in above 2, 3 only when there
is increase in work in hand and plant and
machinery)
e Certification The Company having ISO 9000 (Version
2000) certificate will be preferred.
f Validity period The offer of the Contractor shall remain
valid for 120 days from the date of opening of tender.
g No Relationship with
Corporators
See Clause 12 of Detailed Tender Notice
h Others Undertaking – Annexure 1
5. Earnest Money Rs.17,000/-
6. Security Deposit :
a Initial Security Deposit 3% of the Contract Sum
b Further Security Deposit, to be deducted from Bills 2 % of the Contract Sum
7. Type of Contract Capital work
8. Percentage to be charges as supervision charges for the work got
executed through other means
24.50 %
9. Completion Period 03 Months
10. Defect liability Period One Year
11. The agency will have to furnish an additional deposit equal to the percentage quoted by it below 15% along
with, the security deposit to be paid for the work, in case the agency qualifies for the work, i.e. in case the agency quotes 20% below the cost put to tender, it will have to furnish an additional deposit of 20-15 = 5%
with the designated security deposit amount. Besides this, the agency will have to submit detailed rate
analysis for each and every item in case it quotes below 10% cost put to tender.
12. As per the construction labour welfare Cess Act 1996, a Cess of 1% of contract value towards the welfare of
construction labour will be deducted from the bills.
13. Price variation clause Not applicable.
14. Special Specifications for Container type Community / Public
toilets.
Annexure 10
15.. Special Conditions for Bidders or Collaborators / Group
Companies / MOU Associates etc.
Annexure 11
Signature of Tenderer No. of Corrections Signature of NMMC Official
4
Annexure 10
SPECIAL SPECIFICATIONS Item for Providing, Fixing & Commissioning Container Type 10 seated G.I. Community Toilet Block. Construction details of GI Portable Toilet Cabin of size 6.10 m length x 2.45 m width x 2.60 m height (20 x 8 x 8.5
(feet)) (lift & shift type) : This specifications will apply for new fabricated container type toilet units only.
1. Shell: The shell shall be fabricated from tested quality GI duly welded, comprising of base frame,
peripheral structure, self draining roof, entry doors and of windows (as per requirement). The four
top corners shall be sufficiently strengthened to facilitate transportation, lifting and placing
2. Base Frame : The base frame shall be made of pressed mild steel channel section 125 mm x 70 mm
C Channel and 100 x 50 mm I channel for cross sections.
3. Side and End Walls : The side and end frame shall be made out of pressed sections of suitable
profiles / pillars of sufficient strength. Exterior wall shall be made up of 18 SWG (1.2mm). GI
specially corrugated sheet whereas up to 1.20 M wall will be done by ceramic tiles on interior
walls. The steel sheet shall be treated for corrosion resistant. Panels shall be vertically corrugated,
sheet shall be continuously welded to top side and base structure so as to offer better strength to
weight ratio. All gaps will be sealed at edges and at seams, bottom etc to prevent ingress of
moisture.
4. Corner Post shall be of required full height / length of size 75mm x75mm square pipe with 3.2mm
thickness
5. Flooring Systems : On the bottom frame 3.2 mm thick GI Sheet shall be fixed by welding on 125
mm x70mm and 100 mm x50mm C-channel and I-Channel with entire flooring will be done by
smooth and ceramic tiles will be installed above 3.2 mm G.I. floating plate.
6. Roof : Self draining type roof shall be made out of 18 SWG. GI sheet adequate roof bows are to be
provided. Roof shall be adequately cambered for draining of rain water. Suitable Asbestos sheet /
approved material for heat insulation beneath roofing shall be provided.
7. Paint : Epoxy Zinc Phosphate primer & synthetic Epoxy paint for final 2 coats.
(Corrosion free and fire proof paints)
8. Inner Panelling : Up to 1.20 M Interior wall from floor shall be done by Ceramic Tiles dado and
remaining wall will be 18 SWG GI corrugated sheets. All vertically and horizontal corners shall be
neatly and smoothly finished.
9. Main Entry Door : The door shall ne of external opening type made out of the same material as
wall panels with door closing unit. The construction of the door shall be Double skin steel
construction and the door interior shall be finished with same material matching with that of the
bunk house. The door shall be provided with locking arrangement with appropriate lock bolt. All
door fixtures/fittings shall be made of 310 Grade SS and hinges shall be 3 nos, 150mm of S.S.310
Grade to each door or as directed.
10. Electrical System: The bunk house will be provided with electrical wiring suitable for 250 volt,
50HZ single phase AC power supply. All electrical wiring shall be concealed. Suitable copper
cables shall be used for lighting circuits. The copper cables used will be of 2.5 mm cable for
lighting circuits. ISI mark and concealed in PVC conduits. Insulated copper wire shall be used for
wiring to be done in PVC conduit with small size distribution board with MCB protection and to be
separated with main supply. LED Concealed light with main / solar power supply shall be used as
directed.
11. Sanitary Items: All IWC/EWC shall be made of stainless steel Grade 310 only supplied readymade
by manufactures.
12. Miscellaneous: Each container type toilet shall be provided with 90 cm x 60 cm size GI display
board indicating Swachh Bharat/ Navi Mumbai Mission etc. as directed by the Engineer.
Signature of Tenderer No. of Corrections Signature of NMMC Official
5
Annexure 11
Special Conditions of Qualifying Requirements for Container type
Community / Public toilets in Navi Mumbai Municipal Corporation area.
Qualifying Requirements (QR) for Bidders or Collaborators / Group Companies / MOU Associates:
I Financial & Technical Criteria:
The bidder or Collaborators / Group Companies / MOU Associates should have completed / executed
supply and installation of portable Container type accommodation / cabin. Average Annual Turnover of the
Bidder, in the preceding three (3) financial years as on date of Bid Opening, shall not be less than Rs.335
Lakhs (Indian Rupees Three Hundred and Thirty Five Lakhs Only) for supply and installation of portable
Container type accommodation / cabin or similar works.
Or
II The bidder or / Collaborators / Group Companies / MOU Associates should have completed / executed
supply and installation of portable Container type accommodation / cabin or similar works. During the last
Three (03) years as on date of bid opening for each year as an average in:
(i) Single Contract of value not less than Rs 67.60 Lakhs or
(ii) Two Contracts of value not less than Rs 42.25 Lakhs or
(iii) Three Contracts of value not less than Rs 33.80 Lakhs.
III 1. In support of meeting Qualifying Requirements(QR) agencies have to submit :
a. Audited balance sheet and profit & loss account of last 03 financial years
2012-13, 2013-14, 2014-15.
b. Order copies and completion certificate by the concern Authority issued against relevant order in
support of QR, I & II above.
2. In Clause (I & II) of QR above other income than specified porta cabin or similar type works shall not be
considered for arriving at annual turnover.
3. In Clause (I & II) of QR, if the qualifying work is completed during last Three (03) years as specified
above, even if it has started earlier, the same will be considered as meeting the qualifying requirement.
4. The word executed as mentioned in Qualifying Requirements (QR) means that the bidder should have
achieved the progress specified in QR even if total order is not completed / closed. The same shall be
supported by documentary evidence issued by the concern Authority.
5. In cases where audited results for the last preceding financial year are not available, certification of
financial statements from a practicing Chattered Accountant shall also be considered acceptable.
6. All Relevant documents pertaining to MoU / Collaborators / Group Companies etc. along with
supporting documents as per clause I, II & III (a & b), 2, 3, 4 & 5 above shall be submitted by bidder
while tendering only, failing which the tender quoted will be summarily rejected without assigning any
reasons thereof.
IV
1. Notwithstanding anything stated above, the Navi Mumbai Municipal Corporation reserves the right to access
the capabilities and capacity of the Bidder / his collaborators / associates / subsidiaries / group companies to
perform the contract, should the circumstances warrant such assessment in the overall interest of the Navi
Mumbai Municipal Corporation.
2. Bidder should have MoU with registered DRDO approved dealer for Bio – digester technology provider.
3. Container type Portable Cabin Manufacturer should have proper equipments with MIG welding & machines
at their factory premises & documentary evidence shall be produced while submitting tender.
4. Bidder should submit MDCC (Material Dispatch Clearance Certificate), MTC with the ‘Invoice’ before
dispatch.
5. QAP & Layout has to be got approved by the Navi Mumbai Municipal Corporation before starting the
manufacturing work.
6. All basic material like GI Sheet used for Container Cabin, Structural Steel, Ceramic tiles etc listed in
technical specifications of the tender BOQ documents shall be tested in the approved laboratory before
commencing fabrication of Container as directed by the Engineer in Charge.
Signature of Tenderer No. of Corrections Signature of NMMC Official
6
DETAILED TENDER NOTICE TO CONTRACTOR
1.0 Sealed bids / E-tenders are invited by and on behalf of Commissioner, Navi Mumbai
Municipal Corporation from Eligible bidders for the proposed Work specified in Schedule
‘A’.
2.0 ISSUE OF TENDER
2.1 Tender book will be made available at E-tendering cell, Belapur Bhavan, C.B.D. from date
of publication of Tender Notice on News paper to the Contractors who have enrolled at
N.M.M.C. E-tendering Cell for work of Tender Amount upto Rs.25 lacs. or NMMC
Enrolled Contractor may buy tender book from E-tendering website
www.nmmctenders.com
2.2 For work of tender amount more than Rs.25 lacs tender book will be issued online hrough
E-tendering Website www.nmmctenders.com to the Contractor, who is enrolled with
NMMC.
2.3 Price of Blank Tender form cost must be paid in cash in NMMC’s Account Department
and Receipt of the same should be submitted to E-tendering cell.
2.4 The Tender Document is not transferable. Only the Tenderer who has purchased the tender
form shall be entitled to bid in the Tender.
3.0 LANGUAGE OF TENDER / CONTRACT
The language of the Contract shall be English/Marathi and all correspondence, drawings
etc. shall conform to the English/Marathi language.
4.0 PREBID CONFERENCE
There will be no prebid conference held for the tender. However incase of requirement of
any information applicant may contact responsible person indicated in schedule ‘A’ of the
tender document.
5.0 VALIDITY OF BIDS
The bids will be valid for the period indicated in Schedule ‘A’
6.0 EARNEST MONEY
6.1 The Tenderer shall deposit the amounts indicated in the Tender Notice as Earnest Money
Deposit (EMD)., The Earnest Money shall be deposited in the form of demand draft / pay
order in favour of ‘Navi Mumbai Municipal Corporation’, a fixed deposit with the
Corporation. The failure or omission to deposit the Earnest Money shall disqualify the
Tender and the Corporation shall exclude from its consideration such disqualified
Tender(s). No interest shall be payable by the Corporation in respect of such deposited
Earnest Money.
6.2 The tenderer should refer user’s guide while depositing EMD through the E-tendering
website www.nmmctenders.com.
6.3 The failure or omission to deposit the Earnest Money shall disqualify the tender and the
Corporation shall exclude from its consideration such disqualified tender.
6.4 No interest shall be payable by the Corporation in respect of such deposited Earnest
Money.
6.5 If the Corporation shall accept the Tender the Earnest Money shall be appropriated towards
Security Deposit payable by the Contractor in accordance with Clause No. 7 of the General
Conditions of Contract. Alternatively on payment of the required amount of the Initial
Security Deposit and the execution of the Contract agreement, the Earnest Money shall be
returned to the Tenderer.
Signature of Tenderer No. of Corrections Signature of NMMC Official
7
7.0 FORFEITURE OF EMD
7.1 The Tenderer shall not revoke Tender or vary its terms and conditions without the consent
of the Corporation during the validity period of Tender. If the Tenderer revokes the Tender
or vary its terms or condition contrary to his promise to abide by this condition, the Earnest
Money deposited by him shall stand forfeited to the Corporation without prejudice to its
other rights and remedies and the Tenderer shall be disentitled to submit a tender to the
Corporation for execution of any Work during the next 24 months effective from the date
of such revocation.
7.2 If Successful Tenderer does not pay the Security Deposit in the prescribed time limit or
fails to sign the agreement bond, his Earnest Money Deposit will be forfeited by the
Corporation.
8.0 REFUND OF EARNEST MONEY
The Earnest Money of unsuccessful Tenderers shall be refunded after the successful
Contractor furnishes required Initial Security Deposit to the Corporation and sign the
agreement or within 30 days of the expiry of validity period, whichever is earlier.
9.0 COST OF TENDER
The Tenderer shall bear all costs associated with the preparation and submission of its
Tender. The Corporation shall in no case be responsible or liable for these costs, regardless
of the Conduct or the out come of the Tendering process.
10.0 ELLIGIBLE TENDERERS
Only those Contractors fulfill the Eligibility criteria as mentioned in the Schedule ‘A’ of
the tender notice are eligible to submit their tender for this Work.
11.0 SPARE CAPACITY OF WORK FOR TENDERING
The Tenderers shall be eligible to submit the tender to the Corporation subject to the
essential condition that the price tendered by him together with the value of the
outstanding Works under execution by him for the Corporation or any other employer shall
not be more than four times the value of the average annual turnover of Works executed
during the preceding three financial years ending 31st March.
12.0 RELATION SHIP WITH CORPORATOR (S)
Tenderer shall not be associated presently or in the past with any of the office bearer or
Corporator’s of the Navi Mumbai Municipal Corporation either directly or indirectly as
specified in the section 10(f), (g) of BPMC Act. 1949. The Tenderer shall furnish an
Affidavit on a Non-Judicial stamp paper of Rs.100/- as per Annexure – 9. If any
information so furnished shall be found to be untrue or false, the tender shall be liable to be
disqualified and the Earnest Money accompanying such tender shall stand forfeited to the
Corporation. If the information so furnished shall be found to be untrue or false during the
currency of the contract the Tenderer shall be held to be in-default and the contract if any
awarded to him shall be liable to be terminated with its consequences.
13.0 TIME OF COMPLETION
The period of completion of Works is enumerated under Schedule ‘A’. The time of
completion shall commence from the date of placing the Work Order or date of handing
over the site whichever is earlier. The completion period is for all items of Work in all
parts of Tender Documents.
14.0 SCHEDULE OF RATES AND QUANTITIES 14.1 The Tender has been drafted on the basis of pre-priced schedule of rates and quantities for
different types of items.
Signature of Tenderer No. of Corrections Signature of NMMC Official
8
14.2 All the tender items are priced as mentioned in Schedule "B" of Tender.
14.3 The Contractors are expected to work out their own rates based on the detailed description
of schedule “B” items, the specifications, drawings & conditions and finally arrive at the cost of
the Work. The Contractor shall insert percentage cost over or below the Corporation’s cost to
arrive at the contract value for the Work in Schedule ‘B’.
14.4 In case of Lump Sum Contract, Tenderer should insert his Lump Sum cost as contract
value for the Work in Schedule ‘B’.
15.0 INSPECTION OF SITE AND SUFFICIENCY OF TENDER
15.1 The Contractor shall inspect and examine the site, the utility services and its surrounding
and shall satisfy himself before submitting his Tender as to the nature of the ground and
subsoil (so far as is practicable), the form and nature of the site, the quantities and nature of
the Work and materials necessary for the completion of the Works and means of access to
the site, the accommodation he may require and in general, shall himself obtain all
necessary information as to risk, contingencies and other circumstances which may
influence or affect his Tender.
15.2 The Contractor shall be deemed to have satisfied himself before tendering as to the
correctness and sufficiency of his Tender for the Works and of the rates and prices quoted
in the schedule of Works/items/ quantities or in bill of quantities, which rates and prices
shall, except as otherwise provided, cover all his obligations under the contract and all
matters and things necessary for proper completion and maintenance of the Works.
15.3 No extra charges consequent on any misunderstanding or otherwise shall be allowed.
16.0 MANNER OF SUBMISSION OF TENDER
16.1 The Complete Tenders (having Estimated cost below Rs. 25 lacs) in the manner specified
in the following paragraph will be received in any of the following offices / manner
a) 1st Floor entrance lobby at Belapur Bhavan, sec – 11, CBD, Navi Mumbai.
b) Hon. Commissioner’s office, 1st floor, Belapur Bhavan.
c) Solid waste management Department at 8th Floor, Belapur Bhavan, CBD Navi Mumbai
16.2 The tenders having estimated cost above Rs.25 lacs should be submitted online at
www.nmmctenders.com
16.3 Telex, cable or facsimile offers and offers submitted through tender box in the form of hard
copy for tender having cost above 25.00 Lacs will be rejected.
17.0 LAST DATE FOR SUBMISSION
17.1 Sealed Tender offers shall be received at the address specified above not later than the time
and date specified in the Schedule ‘A’ of the Tender.
17.2 In the event of the specified date for the submission of Tender offers being declared a
holiday, the offers will be received up to the appointed time on the next working day
17.3 The Corporation may, at its discretion, extend this deadline for submission of offers by
amending the Tender Documents, in which case all rights and obligations of the
Corporation and Tenderer will thereafter be subject to the deadline as extended.
17.4 Any Tender offer received by the Corporation after the deadline for submission of Tender
offer prescribed by the Corporation, pursuant to the clause above, will be rejected and / or
returned unopened to the Tenderer.
Signature of Tenderer No. of Corrections Signature of NMMC Official
9
18.0 MODIFICATION AND WITHDRAWAL OF OFFERS
The Bidder may modify or withdraw his offer after its submission, provided that written
notice of the modification or withdrawal is received by the Corporation prior to the closing
date and time prescribed for submission of offers. No offer can be modified by the Bidder,
subsequent to the closing date and time for submission of offers.
19.0 CONTENTS
19.1 Tenders are invited in two-envelope system. Both the envelope shall be placed in another
envelope. The name of Work/Service and Work No. mentioned in the Tender Notice and
the full name and address of the Tenderer shall be clearly written in the bottom left corner
of each envelope.
19.2 The envelope shall contain the following
Envelope No.-1.
1) This should contain all the documents mentioned as below from ‘a’ to ‘q’. This
envelope may contain other documents also such as Technical bids, drawings, any
other as mentioned in the Tender notice.
a) List of all the documents enclosed in the envelope.
b) The Tender price in the form of Demand draft/Pay Order original cash receipt.
(Where it is downloaded from the official website)
c) Form of Bank Guarantee Bond as per Annexure 1.
d) Undertaking in duly signed by a person holding a valid Power Of Attorney as per
Annexure-2
e) Power of Attorney authorising the person to sign the Tender Document (see clause
20(e)).
f) The EMD in the form of Demand draft/ Pay Order (as per clause 6.0 above) or valid
certificate of exemption issued by Navi Mumbai Municipal Corporation.
g) Attested copy of the valid registration certificate (as requested by the eligibility
condition at Schedule ‘A’.
h) Details of forms in Annexure 3.
i) The Tenderer shall furnish a statement showing the type and magnitude of Work
done with last 3 years as per Annexure 4.
j) List of Works in hand as on the date of submission of this Tender in Annexure 5.
k) List of Works tendered as on the date of submission of this Tender in Annexure 6.
l) List of machinery and plant immediately available with the Tenderer for use on this
Work and list of machinery proposed to be utilised on this Work but not immediately
available and the manner in which it is proposed to be procured in Annexure 7.
m) Details of Technical personnel available with the Contractor in Annexure 8.
n) Affidavit on a Non-Judicial Stamp paper of Rs.100/- as per Annexure 9.
o) Affidavit on Rs.100/- stamp paper for preservation of mangroves.
p) Indemnity Bond on Rs.100/- stamp paper as per Annexure c.
q) Eligibility of Registration / turn over \ qualified personnel as per Schedule ‘A’
Envelope No.-2 (Financial bid)
This envelope shall only contain the Commercial Bid in Schedule B only. The Financial
Bid should be written both in words and figures at appropriate places.
OR
Signature of Tenderer No. of Corrections Signature of NMMC Official
10
19.3 The E-Tenderer shall needs to upload the documents mentioned in 19.2(i) & to submit
financial bid both in words and figures in the Schedule B at appropriate places for the
online submission.
20.0 IMPORTANT POINTS TO BE NOTED BY THE TENDERER
a) On receipt of blank Tender form the Tenderer should ensure that no corrections or over
writings or erasures are left to be attested by the competent authority of the
Corporation.
b) The price-bid shall be inclusive of all taxes, Octroi, Local taxes, etc. to be paid by the
Tenderer for the Work and claim for extra payment on any such account shall not be
entertained.
Any change that will be made in the Tender paper by the competent authority after
issue of the Tender will be intimated to the Tenderer in the form of
Corrigendum/Addendum for incorporating the same in the Tender before submitting
the Tender.
c) Price-bid should be written both in words and figures in the Schedule ‘B’, at
appropriate places.
d) No alterations and additions anywhere in the Tender Document are permitted. If any of
these are found, the Tender may be summarily rejected. The Tenderer should get his
doubts cleared during pre-Tender meeting only if provided in the Tender. In case if no
pre-bid meeting is to be held the Tenderer should seek clarification or any doubt in
writing 7 days before the last date for receipt of Tenders.
e) In case of firm, each partner or power of attorney holder shall sign the Tender and the
signatures shall be attested as witness by a reputed person in the space provided for the
purpose. The attested copies of power of attorney of person signing the Tender shall be
enclosed with the Tender. The power of attorney shall be signed by all partners.
In case of private limited/public limited companies, the power of attorney shall be
supported by Board resolutions and appropriate and adequate evidence in support of
the same shall be submitted. Application from joint venture / consortium SHALL NOT
BE ACCEPTABLE
f) All pages and pasted slips should be signed by the Tenderer.
g) No page shall be added or removed from the set of Tender Document.
h) Tenderer shall be deemed to have studied the schedule of Works / Items / Quantities /
Rates, all plans, specifications, terms and conditions, shall inspect and examine the site,
the utility services and its surrounding and shall satisfy himself before submitting his
Tender as to the nature of the ground and subsoil (so far as is practicable), the form and
nature of the site, nature of the Work and materials necessary for the completion of the
Works and means of access to the site, the accommodation he may require and in
general shall himself obtain all necessary information as to risk, contingencies,
obligations under the Contract and all matter and things necessary for proper
completion and maintenance of the Works. No extra charges consequent on any
misunderstanding. A declaration and an undertaking to this effect should be singed by
the Tenderer in the form attached at an Annexure - 2.
i) The Tenderer shall submit the Tender which satisfies each and every condition laid
down in this Tender notice, failing which the Tender will be liable to be rejected
conditional Tenders will be rejected.
Signature of Tenderer No. of Corrections Signature of NMMC Official
11
21.0 CORRUPT OR FRAUDULENT PRACTICES
21.1 The Corporation requires that the bidders/suppliers/ Contractors under this Tender observe
the highest standards of ethics during the procurement and execution of such contracts. In
pursuance of this policy, the Corporation defines for the purposes of this provision, the
terms set forth as follows:
a) “corrupt practice” means the offering, giving, receiving or soliciting of any thing of
value to influence the action of the public official in the procurement process or in contract
execution; and
b) “fraudulent practice” means a misrepresentation of facts in order to influence a
procurement process or a execution of a contract to the detriment of the Corporation, and
includes collusive practice among bidders (prior to or after bid submission) designed to
establish bid prices at artificial non-competitive levels and to deprive the Corporation of
the benefits of the free and open competition;
21.2 The Corporation will reject a proposal for award if it determines that the Bidder
recommended for award has engaged in corrupt or fraudulent practices in competing for
the contract in question; The Corporation will a firm ineligible, either indefinitely or for a
stated period of time, to be awarded a contract if it at any time determines that the firm has
engaged in corrupt and fraudulent practices in competing for, or in executing, a contract.
22.0 MANNER OF OPENING OF TENDER
For the work amounting upto Rs.25 lakhs, the Tender received before the time and date
specified in the Tender Notice will be opened as per the specified program in the office as
mentioned in the Tender Notice (If Possible).
The tenders will be opened in the presence of Tenderers or their authorised representatives
who choose to remain present.
For the Work amounting above Rs.25 lakhs, tender will be opened online in the presence
of Higher Authority of Tender Committee and E-tendering Administrator.
23.0 PROCESS TO BE CONFIDENTIAL
Information relating to the examination, clarification, evaluation and comparison of bids
and the award of a Contract shall not be disclosed to Bidders or any other person not
officially concerned with such process until the award to the successful Bidder has been
announced.
24.0 PRELIMINARY SCRUTINY
24.1 The Corporation will scrutinize the offers to determine whether they are complete, whether
any errors have been made, whether required technical documentation have been
furnished, whether the documents have been properly signed, and whether the offers are
generally in order.
24.2 Prior to the detailed evaluation, the Corporation will determine the substantial
responsiveness of each offer to the Tender Documents. For purposes of these Clauses, a
substantially responsive bid is one that confirms to all the terms and conditions of the
Tender Documents without material deviations. The Corporation’s determination of an
offer’s responsiveness is to be based on the contents of the Tender offer itself without
recourse to extrinsic evidence.
24.3 A Tender offer determined as not substantially responsive will be rejected by the
Corporation and may not subsequently be made responsive by the Bidder by correction of
the nonconformity.
24.4 The Corporation may waive any minor infirmity or irregularity in a Tender offer, which
does not constitute a material deviation. This shall be binding on all Tenderers and the
Corporation reserves the right of such waivers.
Signature of Tenderer No. of Corrections Signature of NMMC Official
12
25.0 CLARIFICATION OF OFFERS
To assist in the scrutiny, evaluation and comparison of offers, the Corporation may, at its
discretion, ask some or all Bidders for technical clarification of their offer. The request for
such clarifications and the response shall be in writing. To speed up the Tender process,
the Corporation, at its discretion, may ask for any technical clarification to be submitted by
means of facsimile by the Tenderer. In such cases, original copy of the document
describing the technical clarifications must be sent to the Corporation by means of courier /
in person.
26.0 REJECTION OF TENDERS
The Tenders are liable to be rejected if the Tenderer
• Does not submit price of Tender in the form of original cash receipt/DD/pay order.
• Does not submit EMD.
• Does not submit undertaking on Rs. 100/- stamp paper. (Annexure -2)
• Does not disclose the full names and address of all his partners in case of a Partnership
Concern;
• Does not submit the information as called for in Annexure (3 to 8)
• Does not submit affidavit on Rs.100/- Stamp Paper. (Annexure - 9)
• Does not submit indemnity Bond on Rs.100/- Stamp Paper. (Annexure –C )
• Fails to initial corrections;
• Fails to fill completely all the proforma provided in the Tender including proforma of
submission of Tender and percentage and amount columns in Schedule - `B';
• Tries to contact the Corporation on any matter relating to its bid, or tries to influence
the
• Corporation in its decision on bid evaluation, bid comparison or Contract award from
the time of the bid opening to the time of contract is awarded.
• Stipulates any condition in the Tender;
• Stipulates the validity period less than what is stated in the form of Tender;
• Does not quote rates inclusive of octroi duty and other terminal or Sales Tax or General
taxes,
• etc.
• Does not sign every page of Tender with seal of company / firm;
• Does not submit document for eligibility criteria mention in Schedule A.
27.0 SHORT – LISTING OF BIDDERS
The Corporation will short-list technically qualifying bidders and commercial offers of
only these bidders will be opened at the date and time to be intimated.
28.0 OPENING OF COMMERCIAL OFFERS
The Corporation shall notify the date of opening of the commercial bids to all the
Tenderers. On such notified date the Envelope No. 2 will be opened and the rates in
Schedule ‘B’ or percentage above / below the Estimate shall then be read out.
For the Work amounting above Rs.25 lakhs, commercial bids will be opened online in the
presence of Higher Authority of Tender Committee and E-tendering Administrator and the
rates in Schedule ‘B’ or percentage above / below the Estimate shall then be read out.
Signature of Tenderer No. of Corrections Signature of NMMC Official
13
29.0 ACCEPTANCE OF TENDER
29.1 Acceptance of Tender on behalf of the Corporation shall be done by an officer(s) to whom
the powers are delegated by the Municipal Commissioner.
29.2 The Corporation is not bound to accept the lowest or any Tender. The Corporation reserves
the right to reject any or all Tenders received without assigning any reason whatsoever.
30.0 INTIMATION TO SUCESSFUL TENDERERS
The acceptance of Tender may be communicated to the successful Tenderer in writing or
otherwise either by the Tender opening Authority or any Authority in the Corporation.
31.0 SECURITY DEPOSIT
The Contractor shall pay a Security Deposit equal to five percent of the contract sum as
security for due fulfillment of the contract, unless otherwise stated in the Tender
Documents The mode of making this deposit is as under.
a) Initial or contract deposit.
A sum, which along with the Earnest Money already paid, amounts to 3% of the contract
sum shall be paid within 10 days after receipt of intimation in writing of acceptance of
Tender. It is optional to the Contractor to make the contract deposit in any one of the
following ways :
i) Wholly in form of National Saving Certificate pledged in favour of the Corporation or
Bank Guarantees / Fixed deposit from Nationalised / Scheduled Banks in the enclosed
format.
ii) Partly in cash and partly in form of National Saving Certificate pledged in favour of the
Corporation or Bank Guarantees / Fixed Deposit from Nationalised / Scheduled Banks
in the
enclosed format.
b) Retention Money :
The remaining amount of the Security Deposit i.e. 2% shall be recovered from the
Contractor’s running bills at the rate of five percent and such retention together with
the contract deposit made as aforesaid shall not exceed in the aggregate five percent of
the contract sum after which such retention will cease.
c) All compensation or other sums of money payable by the Contractor under the terms of
this contract or any other account whatsoever, may be deducted from or paid by the
sale of a sufficient part of this Security Deposit/retention money or from the interest
arising there from or from any sums which may be due or may become due to the
Contractor by the Corporation on any account whatsoever, and in the event of his
Security Deposit/retention money being reduced by reason of any such deduction or
sale as aforesaid, the Contractor shall within 15 days of receipt of notice of demand
from the Engineer make good the deficit.
In the event of the said deposit having been made by the Contractor by delivery to the
Corporation by the Guarantee of the Bankers of the Contractor, and of the Contractor
under any of the provisions of this contract becoming subject to or liable for any
penalty for damages liquidated or unliquidated or of the said deposit becoming
forfeited or any breach or failure or determination of contract, then, and in such case
the amount of any such penalty or damages and the deposit so forfeited is not
previously paid to the Municipal Commissioner, shall immediately on demand be paid
by the said Bankers to Corporation and may be forfeited by the Municipal
Commissioner under and in terms of the said Guarantee.
d) Refund of Security Deposit: - On expiry of defect liability period or payment of the
amount of final bill whichever is later, the Engineer in charge shall on demand from the
contractor, refund to him the Security deposit / retention money, provided that the
Engineer in charge is satisfied that there is no demand outstanding against the
contractor for the respective of work and there is no defectleft in the work by the
contractor.
Signature of Tenderer No. of Corrections Signature of NMMC Official
14
32.0 EXECUTION OF CONTRACT DOCUMENT
The successful Tenderer after furnishing Initial Security Deposit, is required to execute an
Agreement in duplicate in the form attached with the Tender Documents on a stamp paper
of proper value. The proper value at present is Rs. 100/-. The agreement should be signed
within a month from the date of acceptance of the Tender. The Contract will be governed
by the Contract agreement, the General Conditions of the Contract (G.C.C.), and the
Special Conditions of the Contract and other documents as specified in the G.C.C.
33.0 STAMP DUTY, LIGAL AND STATURY CHARGES
It shall be incumbent on the successful Bidder to pay stamp duty for the Contract
agreement, as applicable on the date of the execution.
34. LICENCES
The successful Tenderer should comply statutory instruction of contract labour & will be
required to produce to the satisfaction of the Additional City Engineer a valid contract
labour license issued in his favour under the provision of the Contract Labour License
(Regulation and Abolition) 1970, before starting the Work. On failure to do so, the
acceptance of the Tender is liable to be withdrawn and also the Earnest Money is liable to
be forfeited.
35.0 RIGHTS OF THE CORPORATION
The Corporation reserves the right to suitably increase/reduce the scope of Work put to this
Tender.
36.0 INTERPRETATION OF THE CLAUSES IN THE TENDER DOCUMENT/
CONTRACT DOCUMENT
In case of any ambiguity in the interpretation of any of the clauses in Tender Document or
the Contract Document, interpretation of the clauses by the Corporation shall be final and
binding on all parties.
37.0 NOTICE TO FORM PART OF CONTRACT
Notice of Tender and these instructions shall form part of the contract.
Signature of Tenderer No. of Corrections Signature of NMMC Official
15
Annexure 1
FORM OF BANK GUARANTEE BOND
In consideration of the Navi Mumbai Municipal Corporation (here in after called ‘The NMMC’)
having agreed to exempt _______________________________________________ (hereinafter
called ‘the said Contractor(s)’) from the demand under the terms and conditions of an agreement dated
_______________________________ made between ______________________ and
____________________________ for _______________________________________ (hereinafter
called ‘hereinafter called the said Agreement of security deposit for the die fulfillment by the
Contractors (s) of the terms and conditions contained in the said Agreement, in production of a Dank
Guarantee for Rs._______________________________ (Rupees _______________________ only)
we (hereinafter referred to as the bank) at the request.
Of ___________________________ (Contractor (s) do hereby undertake to pay the NMMC and
amount not exceeding Rs. _____________________ against any loss or demand caused to or suffered
or would be caused to or suffered by the NMMC by reason of any branch by the said Contractors (s)
of any terms or conditions contained in the said Agreement.
2. We _____________________________________________________ so hereby undertake to
pay the amount due and payable under this guarantee without any demur, moorely on a demand from
the NMMC stating that the amount claimed is due by way of loss or damage caused to or would be
caused to or suffered by the NMMC by reason of breach by the said Contractors (s) of any the terms
or conditions contained in the said Agreement or by reason of the contractors (s) failure to perform
the said Agreement any such demand made on the bank shall be conclusive as regard the amount due
and payable by the Bank under this guarantee. However, our liability under this guarantee shall be
restricted to an amount not exceeding Rs. ________________________________
3. We undertake to pay to the NMMC any money so demanded not with standing any dispute or
disputes raised by the contractors (s) / Supplier (s) in any suit or proceeding pending before any Court
or Tribunal – relating thereto our liability under this present being absolute and unequivocal.
4. We _______________________________________ further agree that the Guarantee herein
contained shall remain in full force and effect during the period that would be taken for the
performance of the said Agreement and that contained shall remain in full force and effect during the
period that would be taken for the performance
of the said agreement that it shall continue to be enforceable or till the Dy. Commissioner (SMA) of
NMMC (indicate the name of Administrative Department) certified that the terms and conditions of
the said Agreement have been fully and properly carried out by the said Contractors (s) and
accordingly discharges this guarantee. Unless a demand or claim under this guarantee in made on us
writing on or before the …………………………………………….. We shall no discharge from all
liability under this guarantee thereafter.
Signature of Tenderer No. of Corrections Signature of NMMC Official
16
5. We _______________________________________________ further agree that the NMMC
that the NMMC shall have the fullest liberty without our consent and without affecting in any manner
our obligation hereunder to very any of the terms and conditions of the said Agreement or to extend
time to performance by the said contractor from time to time or to postpone for any time or from time
to time any of the powers exercisable by the NMMC against the said contractor (s) and to forbear or
enforce any of the terms and conditions relating to the said Agreement and we shall not be relievered
from our liability by reason of any such variation, o9r extension being granted, to the said contractor
(S) or for any forbearance, act or commission on the part of the NMMC or any indulgence by the
NMMC to the said contractor or for any such matter or thing whatsoever which under the law relating
sureties would but for this provision, have effect of so relieving us.
6. This guarantee will not be discharged due to the change in the constitution of the Bank or the
Contractor (S) / Supplier (s)
7. We _______________________________________ lastly undertake not to revoke this
guarantee during its currency except with the previous consent of the NMMC in writing.
Dated the ……………day of ……….20
For ………………………..
(Indicate the name of Bank)
Signature of Tenderer No. of Corrections Signature of NMMC Official
17
Annexure 2
UNDERTAKING (ON STAMP PAPER OF Rs. 100/-)
Having examined the tender document including all the annexure, the receipt of which is hereby
duly acknowledge, I/ we the undersigned, state that the specifications, condition, etc of this Tender
have been carefully studied and understood by me/us before submitting this tender. I/We hereby
declare that I/We have made myself/ourselves thoroughly conversant with the conditions of the
tender and I/We have based my/our commercial bid for the tender and offer to undertake the
work/supply/deliver ______________________________ (Description of work/Goods/Services)
in conformity with the said tender documents.
We agree to abide by this tender offer till ______________ and shall remain binding upon us and
may be accepted at any time before the expiration of that period.
A demand draft No. …………………. Dated ………………… from the Nationalised/Scheduled
Bank at. ………………………………….. in respect of the sum of *Rs……………………….. is
herewith forwarded representing the Earnest Money. I/ We agree that the amount of Earnest
Money shall not bear interest and shall be liable to be forfeited to the Corporation, should I/We
fail to (i) Abide by the stipulation to keep the offer open for the period of 120 days from the date
fixed for opening the same and thereafter until it is withdrawn by me/us by notice in writing duly
addressed to the authority opening the tenders. (ii) Security Deposit as specified in the time limit
laid down in the detailed tender notice. The amount of earnest money may be adjusted towards the
security deposit or refunded to me/us if so desired by me/us in writing, unless the same or any
part thereof has been forfeited as aforesaid. Should this tender be accepted I/we hereby agree to
abide by and fulfill all the terms and provisions of the conditions of contract annexed hereto so far
as applicable and in default thereof to forfeited and pay to NMMC the sums of money mentioned
in the said conditions. If our tender offer is accepted we will deposit the specified amount as
security deposit for the due performance of the contract and during the warranty. I/we undertake to
use only the best materials approved by Dy. Commissioner (SMA) of N.M.M.C or his duly
authorized representative, before starting the work and to abide by his decision. Until a formal
contract is prepared and executed, this tender offer, together with your written acceptance thereof
and your notification of award, shall constitute a binding contract between us.
We understand that you are not bond to accept the lowest or any offer you may receive.
The information/documents submitted by us are true to our knowledge and if the information /
documents so furnished shall be found to be untrue or false, the tender shall be liable to be
disqualified and our Earnest Money accompanying the tender will be forfeited.
Date the …………………. Day of ………………….20
Signature of Tenderer
Address …………………………………………………….
Signature of Witness
Address …………………………………………………….
Signature of Tenderer No. of Corrections Signature of NMMC Official
18
Annexure 3
FIRM DETAILS
1. Name of Firm and Class or Registration
with Validity date & Value of Registration
2. Address For Communication & Telephone
No. Email
3. Details of Proprietor / Partners / Director
Name Address Qualification and Experience
4. Annual turnover
Previous Financial Year (Y-1)
2nd
Previous Financial Year (Y-2)
3rd
Previous Financial Year (Y-3)
Certified
Copy of
Profit / Loss
Audited
Balance
Sheet,
statement
Attested
(Yes / No)
5. Detailed of Black Listed & Litigation
6. Remarks
Signature of Proprietor or Authorized Person of the firm
Signature of Tenderer No. of Corrections Signature of NMMC Official
19
ANNEXURE – 4
Details of Works of similar type and magnitude carried out by the Tender (last 3 years)
Name of the Tender:
Sr.
No.
Name of
Work
Type of
Work
Name of
Department
& Address
Cost of
Work
Date of
Starting
Stipulated
date of
completion
Actual date
of
Completion
Remarks
1 2 3 4 5 6 7 8 9
Note : 25% to 50% estimated amount shall be considered based on stipulated period of completion.
The turnover amount should be certified and audited by CA of firm and separate sheet should be
enclosed.
Signature of Tenderer No. of Corrections Signature of NMMC Official
20
ANNEXURE – 5
List of Work in Hand as on the date of submission of this Tender
Sr.
No.
Name of
Work
Name of Deptt.
& Address
Work in Hand Anticipated
date of
completion
Remarks
Tender
Cost
Cost of
Remaining
Work
1 2 3 4 5 6 7
Signature of Tenderer No. of Corrections Signature of NMMC Official
21
ANNEXURE – 6
List of Work in Tendered as on the date of submission of this Tender
Sr.
No.
Name of
Work
Name of Deptt.
& Address
Works tenderd for Remarks
Estimate
Cost
Date when
decisions
expected
Stipulated
date of
period of
completion
1 2 3 4 5 6 7
Note : 25% to 50% estimated amount shall be considered based on stipulated period of completion.
Signature of Tenderer No. of Corrections Signature of NMMC Official
22
ANNEXURE – 7
List of relevant plant and machinery
Sr.
No.
Name of equipment No. of
Units
Kind
and
Make
Capacity Age &
Conditions
Present
Location
Remarks
1 2 3 4 5 6 7 8
A)
B)
Immediately
available
Proposed to be
produced for the
Work
Note : The turnover amount should be certified and audited by CA of the firm and separate sheet
should be enclosed
Signature of Tenderer No. of Corrections Signature of NMMC Official
23
ANNEXURE – 8
Details of Technical Personnel available with the Contractor
Name of the tenderer :
Sr.
No.
Name of
Employee
Technical
Qualification
Whether
Working in
field or in
office
Experience in
execution of
similar works
Period for
which the
person is
working with
tenderer
Remarks
1 2 3 4 5 6 7
Signature of Tenderer No. of Corrections Signature of NMMC Official
24
Annexure 9
AFFIDAVIT
ON STAMP PAPER OF VALUE OF RS.100/-
I / We hereby state that We are aware of the provision of section 10 (1) 10 (f) & (g) of the BMPC Act
1949 which are reproduced below, and solemnly state that we have no partnership or any share of the
any Corporator of this corporation in our company and are not associated presently or in the past with
any of the office bearers of Corporator of the Navi Mumbai Municipal Corporation either directly or
indirectly.
Extract of Sec. 10 of BPMC Act.
10 (d) Subject to the provisions of section 13 and 404, a person shall be disqualified for being elected
and for being a counselor.
10 (f) Subject to the provisions of Sub-section (2) has directly and indirectly, by himself or his partner
any share or interest in any Contract or employment with by or on behalf of the Corporation.
10 (g) Having been elected a councilor is retained or employed in any professional capacity either
personally or in the name of firm in which he is partner or with whom he is engaged in a professional
capacity in connection with any cause or proceeding in which the Corporation or the Commissioner or
the Transport Manager is interested or concerned.
We are aware that the above information if found to be untrue or false, we are liable to be disqualifies
and the Earnest Money accompanying the Tender shall stand forfeited to the Corporation. We are also
aware that if the information produced above if found to be untrue or false during the currency of the
Contract, we shall be held to be default and the contract, if any awarded to us shall be liable to be
terminated with all its concurrences.
Tenderer …………………………………………………..
Address …………………………………………………
…………………………………………………….
Date the ………………………. Day of …………..20 Signature of Tenderer
Witness ………………………………………………..
Address ………………………………………………..
Occupation …………………………………………….. Signature of Witness
Signature of Tenderer No. of Corrections Signature of NMMC Official
25
GENERAL CONDITIONS OF CONTRACT
PART – I
INTERPRETATIONS AND DEFINITIONS
1. Singular and Plural
Where the context so requires, words importing the singular shall also mean the plural and
vice versa.
2. Gender
Words importing the masculine gender shall also include the feminine gender.
3. Definitions
(a) ‘Corporation’ shall mean Navi Mumbai Municipal Corporation as incorporated
under the BPMC Act, 1949.
(b) The ‘Municipal Commissioner’ shall mean the Municipal Commissioner of the
Corporation, for the time being holding that office and also his successor and shall
include any officer authorized by him.
(c) The ‘Engineer’ shall mean the Additional City Engineer appointed for the time
being or any other officers of the Corporation who may be authorized by the
Commissioner to carry out the functions of the Engineer.
(d) (i) ‘Engineer’s Representative’ shall mean Executive Engineer / Deputy
Engineer / Sectional Engineer / Junior Engineer or any other municipal
employee or employee appointed from time to time by the ‘Engineer’ to
perform the duties set forth in Clause No. 66 hereof and generally to assist
the Engineer for the purpose of the contract and whose authority shall be
notified in writing to the contractor by the Engineer.
(ii) Architect / Consultant Architect is a person appointed by Navi Mumbai
Municipal Corporation to assist the Engineer in planning, designing and
supervision of the project. This shall also include his legal representatives,
assignees or successors.
(e) The ‘Contract’ shall mean the tender and acceptance thereof and the formal
agreement if any, executed between the Contractor, and the Corporation together
with the documents referred to therein including these conditions and appendices
and any special conditions, the specification, designs, drawings, price schedules,
bills of quantities and schedule of rates. All these documents taken together shall be
deemed to form one Contract and shall be complementary to one another.
The order of precedence in case of discrepancies shall be as under :
1. Contract Agreements.
2. The letter of Acceptance.
3. Detailed tender notice.
4. Special Conditions of Contract.
5. The General Conditions of Contract.
6. Schedule of Rates & Quantities.
7. The Technical Specifications.
8. The Drawings.
Signature of Tenderer No. of Corrections Signature of NMMC Official
26
9. Schedules & Annexure.
(f) The ‘Contractor’ shall mean the individual or firm or company whether
incorporated or not, undertaking the Works and shall include legal representatives
of such individual or persons composing such firm or unincorporated company or
successors of such firm or company as the case may be and permitted assigns of
such individual or firm or company.
(g) ‘Contract sum’ means the sum named in the letter of acceptance including physical
contingencies subject to such addition thereto or deduction there-from as may be
made under the provision hereinafter contained.
Note : The contract sum shall include the following :
1. (a) In the case of percentage rate contracts, the estimated value of
Works as mentioned in the tender adjusted by the Contractor’s
percentage.
(b) In the case of item rate contracts, the cost of the Work arrived at after
extension of the quantities shown in schedule of items / quantities by the
item rates quoted by the tenderer for various items and summation of the
extended cost of each item.
(c) In case of lump sum contract, the sum for which tender is accepted.
2. Special discount / Rebate / Trade discount offered by the tenderer if any and
accepted by the Corporation.
3. Additions or deletions that are accepted after opening of the tenders.
4. Physical contingencies, if any and accepted by the Corporation.
(h) ‘Excepted risks’ are risks due to riots (otherwise than among Contractors’
employees) and civil commotion (in so far as both these are uninsurable), war
(whether declared or not). Invasion, act of foreign enemies, hostilities, civil war,
rebellion, revolution, insurrection, military or usurped power, any act of
government, damage from aircraft, acts of god, such as earthquake, lighting and
unprecedented floods and other causes over which the Contractor has no control
and accepted as such by the Commissioner.
(i) The ‘Site’ mean the land and other places, more specifically mentioned in the
special conditions of the tender, on, under, in or through which the Works or
temporary Works are to be executed and any other lands and places provided by the
Corporation for working space or any other purpose as may be specifically
designated in the contract as forming part of the site.
(j) ‘Urgent Works’ shall mean any measures which in the opinion of the Engineer
become necessary during the progress of the Work to obviate any risk of accident
or failure or which become necessary for security.
Signature of Tenderer No. of Corrections Signature of NMMC Official
27
(k) The ‘Works’ shall mean the tasks to be executed in accordance with the contract or
part(s) thereof, as the case may be, and shall include all extra or additional, altered
or substituted Works as required for performance of the contract.
(l) ‘Construction Plant’ shall mean all appliances or things of whatever nature required
in or about the execution, completion or maintenance of the Works or temporary
Works (as here in after defined) but shall not include materials or other things
intended to form or forming part of the Works.
(m) ‘Temporary Works’ shall mean all temporary tasks of every kind required in or
about execution, completion or maintenance of the work.
(n) ‘Drawing’ shall mean the drawings referred to in the specification and any
modification of such drawings approved in writing by the Engineer and such
drawings as may from time to time be furnished or approved in writing by the
Engineer.
(o) ‘Approved’ shall mean approved in writing including subsequent confirmation of
previous verbal approval and “Approval” shall mean approval in writing including
as aforesaid.
(p) ‘Specification’ means the specification referred to in the tender and any
modification thereof or addition or deduction thereto as may from time to time be
furnished or approved in writing by the Engineer.
(q) ‘Tender’ means the Contractor’s priced offer to the Corporation for the execution
and completion of the works and the remedying of any defects therein in
accordance with the provision of the Contract, as accepted by the Letter of
Acceptance.
(r) ‘Letter of Acceptance’ means the formal acceptance by the Corporation.
(s) ‘Commencement Date’ means the date upon which the Contractor receives the
notice to commence the work issued by the Engineer pursuant to Clause 80.
(t) ‘Time for Completion’ means the time for completing the execution of and passing
the Tests on Completion of the Works or any Section or part thereof as stated in the
Contract (or as extended under Clause 83 calculate from the Commencement Date.
(u) The ‘Annexure’ referred to in these conditions shall means the relevant annexure
appended to the tender papers issued by the Corporation.
Signature of Tenderer No. of Corrections Signature of NMMC Official
28
PART – II
INSTRUCTIONS TO CONTRACTOR
4. Scope of Work
The Work to be carried out under the Contract shall, except as otherwise provided in these
conditions, include all labour, materials, tools, plant, equipment and transport which may
be required in preparation of an for and in the full and entire Execution and completion of
the Works. The descriptions given in the schedule of Works / items / quantities, and the
Bills of Quantities shall, unless otherwise stated, be held to include waste on materials,
carriage, and cartage, carrying in, return of empties, hoisting, setting, fitting and fixing in
position and all other labour necessary in and for the full and entire execution and
completion as aforesaid in accordance with good practice and recognized principles.
5. Corrupt or Fraudulent Practices
The Corporations requires that the bidders / suppliers / contractors under this tender
observe the highest standards of ethics during the procurement and execution of such
contracts. In pursuance of this policy, the Corporation defines for the purposes of this
provision the terms set forth as follows :
a) “Corrupt Practice” means the offering, giving, receiving or soliciting
of any thing of value to influence the action of the public official in the
procurement process or in contract execution;
b) “Fraudulent Practice” means a misrepresentation of facts in order to influence a
procurement process or an execution of a contract to the detriment of the
Corporation, and includes collusive practice among bidder (prior to or after bid
submission) designed to establish bid prices at artificial non-competitive levels and
to deprive the Corporation of the benefits of the free and open competition:
The Corporation will reject a proposal for award if it determines that the Bidder
recommended for award has engaged in corrupt or fraudulent practices in
competing for the contract in question; The Corporation will a firm ineligible,
either indefinitely or for a stated period of time, to be awarded a contract if it at any
time determines that the firm has engaged in corrupt and fraudulent practices in
competing for, or in executing, a contract.
6. Intimation to Successful Tenderer
The acceptance of tender may be communicated to the Successful Tenderer in writing or
otherwise either by the tender opening authority or any authority in the Corporation.
7. Security Deposit
The Contractor shall pay a security deposit equal to five percent of the contract sum as
security for due fulfillment of the contract, unless otherwise stated in the tender
documents.
The mode of making this deposit is an under.
Initial or contract deposit.
Signature of Tenderer No. of Corrections Signature of NMMC Official
29
A sum, which along with the earnest money already paid, amounts to three percent of the
contract sum shall be paid within 15 days after receipt of intimation in writing of
acceptance of tender. It is optional to the contractor to make the contract deposit in one or
the other of the following ways:
i) Wholly in cash or.
ii) Wholly in form of National saving Certificate pledged in favour of the Corporation
or Bank Guarantees / Fixed deposit from Nationalized / Scheduled Banks in the
enclosed format.
iii) Partly in cash and partly in form of National saving Certificate pledged in favour of
the Corporation or Bank Guarantees / Fixed deposit from Nationalized / Scheduled
Banks in the enclosed format.
Retention Money:
The remaining amount of the security deposit i.e. 2% shall be recovered from the
Contractor’s running bills at the rate of five percent and such retention together with the
contract deposit made as aforesaid shall not exceed in the aggregate five percent of the
estimated cost after which such retention will cease.
8. Forfeiture of Security Deposit
All compensation or other sums of money payable by the contractor under the terms of this
contract or any other account whatsoever, may be deducted from or paid by the sale of a
sufficient part of this security deposit / retention money or from the interest arising there
from or from any sums which may be due or may become due to the Contractor by the
Corporation on any account whatsoever, and in the event of his security deposit / retention
money being reduced by reason of any such deduction or sale as aforesaid, the contractor
shall within 15 days of receipt of notice of demand from the Engineer make good the
deficit. In the event of the said deposit having been made by the contractor by delivery to
the Corporation of the Guarantee of the Bankers of the Contractor, and of the contractor
under any of the provisions of this contract becoming subject to or liable for any penalty or
damages, liquidated or unliquidated or of the said deposit becoming forfeited any breach or
failure or determination of contract, then, an in such case the amount of any such penalty
or damages and the deposit so forfeited is not previously paid to the Municipal
Commissioner, shall immediately on demand be paid by the said Bankers to and may be
forfeited by the Municipal Commissioner under and in terms of the said Guarantee.
9. Execution of Contract Document
The successful tenderer after furnishing Initial Security Deposit, is required to execute an
Agreement in duplicate in the format as per Annexure ‘B’ attached with the tender
documents on a stamp paper of proper value. The proper value at present is Rs. 100/-. The
agreement should be signed within one month from the date of acceptance of the tender.
10. Issue of Work Order
Work Order will be issued after execution of contract document.
Signature of Tenderer No. of Corrections Signature of NMMC Official
30
11. Contract Documents
The Contractor shall be furnished, free of charge, two certified true copies of the contract
documents and all further drawings which may be issued during the progress of the work.
None of these documents shall be used by the Contractor for any purpose other than that of
this contract.
12. Indemnity Bond
The Contractor shall require to execute an Indemnity Bond for satisfactory performance of
the entire project on Stamp Paper of Rs. 100/- in the format as per Annexure ‘C’. This
Indemnity Bond shall remain in force for period mentioned in detailed tender notice as
Defect Liability Period after completion of the project.
13. Licences
The successful tenderer should comply statutory instruction of contract labour & will be
required to produce to the satisfaction of the Engineer a valid contact labour license issued
in his favour under the provision of the Contract Labour Licence (Regulation and
Abolition) 1970, before starting the Work. On failure to do so, the acceptance of the tender
is liable to be withdrawn and also the earnest money is liable to be forfeited.
14. Details to be Confidential
The Contractor shall treat the details of the Contract as private and confidential, save in so
far as may be necessary for the purposes thereof, and shall not publish or disclose the same
or any particulars thereof in any trade or technical paper or elsewhere without the previous
consent in writing of the Engineer. If any dispute arises as to the necessary of any
publication or disclosure for the purpose of the contract the same shall be referred to the
Corporation whose determination shall be final.
15. Official Secrecy
The Contractor shall, whenever required, take necessary steps to ensure that all persons
employed on any Work in connection with this Contract have noticed that the India official
Secrets Act 1923 (XIX of 1923) applied to them and shall continue to apply even after
execution of such Work under the Contract.
16. Assignment
The Contractor shall not assign transfer or attempt to assign, transfer the Contract or any
part thereof, or any benefit or interest therein or there under otherwise than by a charge in
favour of the Contractor’s bankers of any Money due or to become due under this contract,
without the prior written approval of the Commissioner.
Signature of Tenderer No. of Corrections Signature of NMMC Official
31
17. Sub-letting
The Contractor shall not sub-let or attempt to sub-let the whole of the Works. Except
where otherwise provided by the Contract, the Contractor shall not sub-let any part of the
Works without the prior written approval of the Engineer, which shall not be unreasonably
with-held, and such approval, if given, shall not relieve the Contractor from any liability or
obligation under defaults and neglects of any sub-contractor, his agents, servants or
Workmen as fully as if they were the acts, defaults or neglects of the Contractor, his
agents, servants or Workmen. Provided always that the engagement of labour on a piece
work basis or labour with material not to be incorporated in the Work shall not be deemed
to be a sub-letting under this Clause.
The Contractor shall be responsible for observance by his sub-contractors of the foregoing
provisions.
18. Changes in Constitution
Where the contractor is a partnership firm, the prior approval in writing of the
Commissioner shall be obtained before any change is made in the constitution of the firm.
Where the contractor is an individual or Hindu Undivided family business concern such
approval as aforesaid shall likewise be obtained before the contractor enters into any
partnership agreement where under the partnership firm would have the right to carry out
the Work hereby undertaken by the contractor. If prior approval as aforesaid is not
obtained the contract shall be deemed to have been assigned in contravention of the Clause
No. 108 hereof and the same action may be taken and the same consequence shall ensure
as provided for in the said condition.
19. Power of Attorney
The contractor shall not issue any kind of power of attorney in favour of his bankers for
routine payments to the contractor through Bank.
20. Contractors Staff
The Contractor shall employ in and about the execution of Works only such persons as are
skilled and are experienced in their several trades and the Engineer shall be at liberty to
object to and require the Contractor to remove from the Works any person, employed by
the Contractor in or about the execution of the Works, who in the opinion of the Engineer
misconducts himself or is incompetent or negligent in the proper performance of his duties
and such person shall not be again employed upon the works without permission of the
Engineer.
21. Contractors’ Supervision
The Contractor shall himself supervise the execution of Works or shall appoint competent
agent approved by the Engineer to act in this stead. If, in the opinion of the Engineer the
Contractor himself does not have sufficient knowledge and experience to be capable of
receiving instructions or cannot give his full attention to the Works, the Contactor shall at
his own expense, employ as his accredited agent an Engineer or a suitably qualified and
experienced person approved by the Engineer. The name of the agent so appointed, along-
with the qualifications, experience and address shall be communicated to the Engineer. The
agent shall be a responsible person adequately organization by the Contractor to take
decision on site and to spend money if required for procuring material and labour etc. to
carry out Emergency Works in the interest of the work, if so required by the Engineer.
Orders given to Contractor’s agent shall be considered to have the same force as if these
had been given to the Contractor himself.
Signature of Tenderer No. of Corrections Signature of NMMC Official
32
If the Contractor fails to appoint a suitable agent as directed by the Engineer, the Engineer
shall have full powers to suspend the execution of the Works until such date as a suitable
agent is appointed and the Contractor shall be held responsible for the delay so caused to
the Works.
22. Employment of Labour
The Contractor shall employ the labour in sufficient numbers to maintain the required rate
of progress and of quality to ensure workmanship of the degree specified in the Contract
and to the satisfaction of the Engineer. The Contractor shall not employ in connection with
the Work any child who has not completed his 15th
year of age. He shall also not employ
an adolescent who has not completed his 18th
year unless he is certified fit for Work as an
adult as prescribed under clause (b) of sub-section (2) of section 69 of the Factories Act,
1948.
The Contractor shall make his own arrangement for the engagement of all labour local or
otherwise.
The Contractor shall indemnify the Corporation or any agent, servant or employee of
corporation for any lapses on the part of contractors on account of non-compliance of
above referred acts.
23. Compliance with labour Regulation
The contractor shall pay fair and reasonable wages to the Workmen employed by him, for
the contract undertaken by him. In the event of any dispute arising between the contractor
and his Workmen on the grounds that the wages paid are not fair and reasonable, the
dispute shall be referred without delay to the Engineer, who shall decide the same. The
decision of the Engineer shall be conclusive and biding on the contractor but such decision
shall not in any way affect the conditions in the contract regarding the payment to be made
by Corporation at the same sanctioned tender rates.
The employees of the contractor and the sub-contractor in no case shall be treated as the
employees of the Corporation at any point of time.
Signature of Tenderer No. of Corrections Signature of NMMC Official
33
SALIENT FEATURES OF SOME MAJOR LABOUR LAWS APPLIACABLE TO
ESTABLISHMENTS ENGAGED IN BUILDING AND OTHER CONSTRUCTION
WORK.
(i) Workman Compensation Act 1923
The Act provides for compensation in case of injury by accident arising out of and
during the course of employment.
(ii) Payment of Gratuity Act 1972
Gratuity is payable to an employee under the Act on satisfaction of certain
conditions on separation if an employee has completed 5 years service or more or
on death at the rate of 15 days wages for every completed year of service. The Act
is applicable to all establishments employing 10 or more employees.
(iii) Employees PF and Miscellaneous Provision Act. 1952.
The Act provides for monthly contributions by the employer plus Workers @ 10%
or 8.33%. The benefits payable under the Act are
(a) Pension or family pension on retirement or death as the case may be.
(b) Deposit linked insurance on the death in harness of the Worker.
(c) Payment of PF accumulation on retirement / death etc.
(iv) Maternity Benefit Act 1951
Act provides for leave and some other benefits to women employees in case of
confinement or miscarriage etc.
(v) Contract labour (Regulation and Abolition) Act 1970
The Act provides for certain welfare measures to be provided by the contractor to
contract labour and in case the contractor fails to provide, the same are required to
be provided by the Principal Employer by law. The principal employer is required
to take Certificate of Registration and the Contractor is required to take a Licence
from the designated Officer. The Act is applicable to the establishments or
Contractor of principle employer if they employ 20 or more contract labour.
(vi) Minimum Wages Act 1970
The Contractor shall see that the provisions set for under the Minimum
Wages Act and Contract Regulation and Abolition Act 1970 with the Maharashtra
Contract Labour (regulation and abolition) Rules 1971 as amended from time to
time are fully complied with by him and shall maintain necessary registers and
records for payments of wages, overtime, etc. made to his Workmen as required by
the Conciliation Officer (Central), Ministry of Labour, Government of India, or
such other organization person appointed by the Central or State Government.
Signature of Tenderer No. of Corrections Signature of NMMC Official
34
(vii) Payment of Wages Act 1936
It lays down as to by what date the wages are to be paid, when it will be paid and
what deductions can be made from the wages of the Workers.
(viii) Equal Remuneration Act 1979.
The Act provides for payment of equal wages for Work of equal nature to Male &
Female Workers and not for making discrimination against Female employees in
the matters of transfers, training and promotions etc.
(ix) Payment of Bonus Act 1965
The Act is applicable to all establishments employing 20 or more Workmen. The
Act provides for payments of annual bonus subject to a minimum of 8.33% of
wages and maximum of 200% of wages to employees drawing Rs. 3, 500/- P. M. or
less. The bonus to be paid to or employees getting Rs. 2500/- P.M. above upto
3500/- P.M. shall be Worked out by taking wages as Rs. 2500/- P.M. only. The
Act does not apply to certain establishments. The newly set up establishments are
exempted for five years in certain circumstances. Some of the State Governments
have reduced the employments size form 20 to 10 for the purpose of applicability
of the act.
(x) Industrial Disputes Act 1947
The Act lays down the machinery and procedure for resolution of industrial
disputes, in what situations a strike or lockout become illegal and what are the
requirements for laying off or retrenching the employees or closing down the
establishment.
(xi) Industrial Employment (Standing Orders) Act 1946.
It is applicable to all establishments employing 1000 or more Workmen
(employment size reduced by some of the States and Central Government to 50).
The Act provides for laying down rules governing the conditions of employment by
the employer or matters provided in the Act and get the same certified by the
designated Authority.
(xii) Trade Unions Act 1926
The Act lays down the procedure for registration of trade unions of Workmen and
employers. The trade unions registered under the Act have been given certain
immunities from civil and criminal liabilities.
(xiii) Child labour (prohibition and regulation) Act 1986.
The Act prohibits employment of children below 14 years of age in certain
occupation and processes and provides for regulation of employment of children in
all other occupations and processes.
Employment of child labour is prohibited in Building and Construction Industry.
Signature of Tenderer No. of Corrections Signature of NMMC Official
35
(xiv) Inter-State Migrant Workmen’s Regulation of Employment and
Conditions of Service) Act 1979.
The Act is applicable to an establishment which employees 5 or more inter-state
migrant Workmen through an intermediary (who has recruited Workmen in one
state for employment in the establishment situated in another state). The inter-state
migrant Workmen, in an establishment to which this Act becomes applicable, are
required to be provided certain facilities such as housing, medical aid, traveling
expenses from home upto the establishment and back etc.
(xv) The Building & other Construction Workers (Regulation of Employment and
Conditions of Service) Act 1996 and the Cess Act of 1996.
All the establishments who carry on any building or other construction Work and
employs 10 or more Workers are covered under this act. All such establishments
are required to pay cess at rate not exceeding 2% of the cost of construction as may
be notified by the Government. The employer of the establishment is required to
provide safety measures at the Building or Construction Work and other welfare
measures, such as Canteens, First-Aid facilities, Ambulance, Housing
accommodation for Workers near the Workplace etc. The employer to whom the
Act applies has to obtain a registration certification from the Registering Officer
appointed by the Government.
24. Safety Provisions
The Contractor shall at his own expense arrange for the safety provisions indicated in
annexure ‘A’ or as required by the Engineer, in respect of all labour directly or indirectly
employed for performance of the Works and shall provide all facilities in connection
therewith. In case the Contractor fails to make arrangements and provide necessary
facilities as aforesaid, the Engineer shall be entitled to do so and recover the costs thereof
from the Contractor.
25. Provision of First-Aid Box
The contractor shall, at his own cost, provide and maintain at the site of Works a standard
first aid box as directed and approved by the Engineer for the use of his own as well as the
Corporation’s staff on site.
26. Apprentices
The Contractor shall comply with the provision of the Apprentice Act, 1961, and the rules
and orders issued there under from time to time. The contractor shall during the term of
this agreements maintain as a part of his organization a system of apprenticeship for
training craftsmen as may be approved by the Engineer. The apprentices are to be engaged
and trained in the building craft/trades. The number of apprentices to be engaged shall be
decided and got approved from the office of the Director of Technical Education and State
Apprenticeship Advisor, Maharashtra State, Dhobi Talao, Bombay – 400 001. Failure on
the part of the contractor to observe the stipulation of this conditions shall be deemed to be
failure to employ a sufficient number of proper and efficient workmen and all the rights
and remedies of the Commissioner therein provided including the power to determine the
contract shall be applicable in such case. The Contractor shall also be liable for any
pecuniary liability arising on account of any violation by him of the provisions of the Act.
Signature of Tenderer No. of Corrections Signature of NMMC Official
36
27. Personnel
The Contractor shall employ the key personnel named by him in PQ document or other
personnel approved by the Engineer to carry out the functions. The Engineer will approve
any proposed replacement of key personnel only if their qualifications abilities and
relevant experience are substantially equal to or better than those of the personnel listed by
the Contractor.
28. Temporary site Office for the Engineer (For Works Costing Above Rs. 50 Lacks
Only) as specified in special conditions of contract.
The Contractor shall at his own cost and to the satisfaction of the Engineer, provide a site
office of not less than 25 sq. Mtr. With brick walls plastering inside, rough Shahabad
flooring and one writing table with six chairs and large size steel cupboard. He shall also
make necessary arrangements for drinking water and electric connection and locking
arrangement.
Upon completion of the whole work and after clearing the site and upon expiry of defect
liability period, the Contractor shall remove the site office and take possession of the
furniture and cupboards provided by him in the condition it was on the date of receiving
back the same.
29. Contractor’s Office Near Works
The Contractor shall have an office near the Works at which notice from the Engineer may
be served and shall, between the hours of sunrise and sunset on all working days, have a
clerk or some other organization person always present at such office upon whom such
notices may be served and service of any notices left with such clerk or other organization
person or at such office shall be deemed good service upon the Contractor.
30. Permission for Erection & Removal of Office on Completion of Work
The Contractor shall obtain permission for erection of site office, cement godown, store,
etc. on payment of necessary charges as demanded by the concerned authorities as per the
prevailing rules. The cement godown. Watchman cabins, etc. shall be provided as directed
and shall be removed by the Contractor on completion of the work at their cost.
31. Use of Municipal Land
(a) The Contractor shall not be permitted to enter on (other than for inspection
purposes) or take possession of site until instructed to do so by the Engineer in
writing.
The portion of the site to be occupied by the Contractor shall be defined and / or marked
on the site plan, failing which these shall be indicated by the Engineer. The Contractor
shall on no account be allowed to extend his operations beyond these areas. The use of
such portion of the site shall be allowed free of any lease rent during scheduled time period
for the completion of the Work. However at the expiry of the stipulated period of the
Work, as may be extended from time to time. Contractor has to pay charges for these
facilities as per the prevailing rates levied by the Corporation for use of public utility
places.
The Contractor will be allowed to use the land for the purpose of sheds offices thereon for
themselves and for the Engineer and his subordinates and shall remove the same from the
ground on the completion of the Works, or when required to do so, by
Signature of Tenderer No. of Corrections Signature of NMMC Official
37
the Engineer after receiving 7 days notice. He shall make good any damage which may
have been done and restore to good condition any thing which may have been disturbed
during the period of his occupation.
He shall not use or allow to be used any such ground, sheds or officers, or any portion of
the site of the Works, for any other purpose than the carrying out of Works under this
Contract, failing which charges applicable will become payable in the event of there being
on plot or ground or insufficiency of ground belonging to the Corporation available for the
above purpose, the Contractor shall provide other such ground at this own cost.
The Contractor shall in any case pay all taxes which may have to be paid in respect of all
ground, sheds or offices used as above and all the license fees, etc. that may be demanded
for the storage or otherwise of the various articles as per rules in force.
The Contractor shall provide, if necessary or if required on the site all temporary accesses
thereto and shall alter, adopt and maintain the same as required from time to time and shall
take up and clear them away as and when no longer required and make good all damage
done to the site. The contractor has also be allowed at the sole discretion of the corporation
to stack material required for execution of work in corporation land out of the project area
on payment of necessary charges as per corporation rules for use of roads public utility
places.
32. Water Supply for Corporation Work
The Water will not be supplied by the Corporation. The Contractor has to make his own
arrangements for supply of water. However on availability of water it can be supplied to
the organization at Corporation rate and terms and conditions.
33. Electric Supply
No power connection shall be provided. The Contractor shall make at his own cost his own
arrangement for power connection, if required.
34. Contractor to Protect the Work
The contractor shall make his own arrangements for protecting the Work / protection
against obstructions from any anti-social elements by taking at his / their cost police
protection or such other legal methods through law enforcing authorities and that the
Corporation shall not be liable to compensate the contractor on this account. The
Corporation would only forward the application of the contractor to the police Dept.
Without any liability against the Corporation on this account.
35. Fencing, Watching and Lighting
The Contractor shall provide and maintain at his own expense all lights, guards, fencing
and watching when and where necessary or as required by the Engineer for the protection
of the safety and convenience of those employed on the Works or the public. In the event
of failure on the part of the Contractor, the Engineer may with or without notice to the
Contractor put up a fence or improve a fence already put up or provide and / or improve
the lighting or adopt such other measures as he may deem necessary, and all the cost of
such
procedures as may be adopted by the Engineer shall be borne by the Contractor in addition
the Engineer may impose such fines or penalty as the Engineer may deem reasonable,
under Clauses No. 53.
Signature of Tenderer No. of Corrections Signature of NMMC Official
38
36. Contractor’s Liabilities & Insurance (Car Policy)
From commencement to completion of the works, the Contractor shall take full
responsibility for the care thereof and for taking precaution to prevent loss or damage and
to minimize the loss or damage to the greatest extent possible and
shall be liable for any damage or loss that may happen to the Works or any part thereof.
The policy so obtained shall cover entire period of construction (including all extensions)
and also shall cover the Defects Liability period, The policy shall be for the total Contract
Sum.
Before commencing execution of the Work, the Contractors shall without in any way
limiting his obligations and responsibilities under this condition, insure against any
damage loss or injury which may occur to any property (Private, Government and / or
Corporation ) or to any person (including any employee of the Corporation) by or arising
out of the contract.
All insurances (Car Policy) to be affected by the Contractors and / or his sub-contractors
shall be taken out with Directorate of insurance, Maharashtra State only. In case, however,
a particular aspect is not covered under the policy to be obtained from the Directorate of
Insurance, Maharashtra Sate, the Contractor will be allowed to have such insurance from
other insurance company with the prior permission of the Commissioner.
If the Contractor has a blanket insurance policy for all his Works and the policy covers all
the items to be insured under this condition, the said policy shall be assigned by the
Contractor, in favour of the Corporation; provided, however, if any amount is payable
under the policy by the insurers in respect of Works other than the Works under this
Contract, the same may be recovered by the Contractor directly from the insurers. The
amount of claim to the extent payment made by Corporation shall be directly reimbursed
to Corporation by insurer.
PROVIDED always that the Contractor shall not be entitled to payment under the above
previsions in respect of such loss or damage as have been occasioned by any failure on his
part to perform his obligations under the contract or not taking precautions to prevent loss
or damage or minimize the amount of such loss or damage.
Where a Corporation’s Building or part thereof is rented by the Contractor or is allowed to
be used by him, he shall insure the entire building if the building or any part thereof is used
by him for the purpose of storing or using materials of combustible nature as to which the
decision of the Engineer shall be final and binding.
The Contractor shall indemnify and keep indemnified the Corporation against all losses
and claims for injuries or damage to any person or any property whatsoever which may
arise out of or in consequence of the construction and maintenance of the work and against
all claims, demands, proceedings, damages, costs, charges and expenses whatsoever in
respect of or in relation thereto.
PROVIDED always that nothing herein contained shall be deemed to render the Contractor
liable for or in respect of or to the Corporation against any compensation or damage caused
by the Excepted Risks.
Signature of Tenderer No. of Corrections Signature of NMMC Official
39
The Contractor shall at all times indemnify the Corporation against all claims, damages or
compensation under the provision of Payment of Wages Act 1936, Minimum Wages Act
1948, Employers Liability Act 1938, the Workmen’s Compensation Act 1923, industrial
Dispute Act 1947, Indian Factories Act 1948 and Maternity Benefit Act, 1961 or any
modifications thereof and rules made there under from time to time or as a consequence or
any accident or injury to any Workmen or other persons in or about the Works, whether in
the employment of the Contractor or not, save and except where such accident or injury
have resulted from any act of the corporation their agents or servants and also against all
costs charges and expenses of any suit, action or proceedings arising out of such accident
or injury and against all sum or sums which may with the consent of the Contractor be paid
to compromise or compound any such claim without limiting his obligations and liabilities
as above provided. The Contactor shall insure against all claims damages or compensation
payable under the various acts mentioned above or any modifications thereof or any other
law relating thereto.
The aforesaid insurance policies shall provide that they shall not be canceled till the
Commissioner has agreed to their cancellations.
The Contractor shall prove to the Engineer from time to time that he has taken out all the
insurance policies referred to above and has paid the necessary permia for keeping the
policies alive till the expiry of the Defects Liability Period after completion of Work for a
period of not exceeding 12 months as per directives of Directorate of Insurance,
Maharashtra State.
The contractor shall ensure that similar insurance policies are taken out by his sub
Contractors (if any) and shall be responsible for any claims or losses to the Corporation
resulting from their failure to obtain adequate insurance protection in connection thereof.
The Contractor shall produce or cause to be produced by this Sub-Contractor (if any) as the
case may be, the relevant policy or policies and premium receipts as and when required by
the Engineer.
If the Contractor and / or his sub-Contractors (if any) shall fail to effect and keep in force
the insurance referred above for any other insurance which he / they may require to effect
under the terms of Contract then and in any such case the Commissioner may without
being bound to effect and keep in force any such insurance and pay premium or premia as
may be necessary for that purpose and from time to time deduct the amount so paid by the
Corporation plus 20 per cent of premium or premia amount as service charges from any
money due or which may become due to the Contractor or recover the same as debt from
the Contractor.
37. Contractor to Preserve Peace
The Contractor shall at all times during the progress of the Work take all requisite
precaution and use his best endeavors for preventing any riotous or unlawful behavior by
or amongst the Workers and other employed on the Works and for the preservation of
peace and protection of the inhabitants and security of property in the neighborhood of the
Works. He shall also pay the charges of such special police (if any) as the Engineer may
deem necessary.
Signature of Tenderer No. of Corrections Signature of NMMC Official
40
38. Protection of Trees
Trees designated by the Engineer shall be protected from damage during the course of the
Work and earth level within one metre of each such tree shall not be changed. Where
necessary, such trees shall be protected by temporary fencing. All such cost shall be borne
by the Contractor.
39. Maintenance of Under – Ground Utility Services
All the underground utility services such as water pipes, gas pipes, drains, sewers, cables
etc., which may be met up in or about any excavation, shall if the Engineer deem it
practicable, be properly maintained and protected by the Contractor himself or through
other agency by means of shoring, strutting, planking over, padding or otherwise as
directed by the Engineer during the progress of the Work without claiming any extra
charges. Any damage to these underground utility services shall be immediately remedied
by the Contractor or by other agency at his own cost, failing which the Engineer may with
or
without notice adopt such measures as he may deem necessary at the risk and cost of the
Contractor. If on the other hand, the Engineer considers it impracticable for the Contractor
to maintain any such underground utility services and that the exigencies of the work
necessitate, the breaking down, removal or diversion of the said utility services, the cost of
such breaking down, removal or diversion including that of rebuilding, replacing, diverting
and reinstating of any such utility services shall be paid to the Contractor if done by him.
However, the cost of providing pumps, chutes or other appliances as the Engineer may
direct for the raising or temporary passage of the water or sewage and the cost of pumping
out or removing as often as the Engineer may direct, any water or sewage which may
escape from any such underground utility services, shall be borne by the Contractor.
The tenderer shall contact all the public bodies, etc. to know the under-ground services that
may be encountered by him / them during the execution of the work and account for the
consequences of the site restraints while submitting their tenders. No compensation / cost
shall be payable on account of any under-ground services which obstructs the Work and
cause delay.
40. Precautions for Works in Thorough Fares
While the execution of any Work is in progress in any street or thoroughfare the Contractor
at his own cost shall make adequate provision for the passage of traffic, for securing safe
access to all premises approached from such street or thoroughfare, and for any drainage
water supply or means of lighting or any other utility service which may be interrupted by
reason of execution of the Work. Whenever it may be necessary to stop the traffic in any
street or thoroughfare permission must first be obtained from the Engineer and the
Contractor shall then put up such barriers and adopt such other measures or take
precautions as may be necessary or as the Engineer may direct for regulation of traffic. The
work shall in such cases be executed night and day or for as long a period as practicable if
so ordered by the Engineer, and with such speed & vigour as he may require, so that the
traffic may be impeded for as short a time as possible. The Contactor shall remove the
barrier as soon as the necessity for them has ceased. Care shall be taken by the Contractor
to cause the least possible obstruction to traffic during the progress of the work.
Signature of Tenderer No. of Corrections Signature of NMMC Official
41
41. Traffic
The Contractor shall have to make all necessary arrangements for regulating traffic day
and night during the period of construction and to the entire satisfaction of the Engineer.
This includes the construction and maintenance of diversions, if necessary, at no extra cost
to the Corporation. The contractor shall provide necessary caution boards, barricades, flags
and lights, watchmen etc. so as to comply with the latest Motor Vehicle Rules and
Regulation and for traffic safety. The contractor shall be responsible for all claims for the
accidents which may arise due to his negligence whether in regulating traffic or in stacking
materials on the road or by any other reason.
42. Pumping out Water
The Contractor will be required to provide and operate at his own cost all pumps, engines
and machinery requisite to keep the trenches for the sewer, drains or foundations and all
other excavations clear of water whether subsoil water, storm waste or leakage from tanks,
wells, drains, sewers, water-mains, tide water etc. so that there may be no accumulation of
such water and no setting out may be done, no masonry may be laid, no concrete
deposited, no joints made and no measurements taken in water. The pumping shall be
continued so long after the execution of any portion of the work as the Engineer may
consider necessary for the work to set. For the purpose of keeping the excavations as dry as
possible the Work would, if necessary be divided into sections or separate portions as per
best Engineering practices and temporary dams will have to be put up by the Contractor,
sumps for the suction pipes to Work in, will have to be excavated by the Contractor at such
distances apart and to such depths as per best Engineering practices. When the Work
progresses other sumps must, from time to time, be excavated by the Contractor, disused
sumps being filled up by him with dry rubble carefully hand packed to the satisfaction of
the Engineer. The Contractor will not be paid extra for any temporary dams or sumps or
their removal or refilling nor will such Works be taken into measurement in any way,
unless otherwise provided.
The Contractor shall not allow any accumulation of water either from the Discharge of his
dewatering pumps or his water connections on site of his work. The Contractor shall make
proper provision for leading the pumped discharge to the nearest water entrance, storm
water drain, manholes, or water course by means of a wooden or G. I. channel or hose
pipe. Under no circumstances the discharge will be allowed to flow, along a paved surface.
If an accumulation is unavoidable, it shall be treated with insecticides to the
satisfaction of the Engineer. In case of failure to do this on the part of Contractor such
accumulation shall be treated by the Corporation at the risk and cost of the Contractor.
The contractors should note that under no circumstances any payment for pumping out
water finding its way into trenches, hill cutting, excavated pits. Works site etc. from
whatever sources will be permissible unless otherwise specifically mentioned in the tender.
Signature of Tenderer No. of Corrections Signature of NMMC Official
42
43. Storage of Explosives
The Contractor shall obtain the previous permission of the competent authority such as the
Chief of Fire Services for the Site, manner and method of storing explosives near the site
of Work. All handling of explosives, including storage, transport shall be carried out under
the rules approved by the “Explosives Department of the Government”.
44. Facilities to the Other Contractors
The Contractor shall, in accordance with the requirements of the Engineer, afford all
reasonable facilities to other Contractors engaged contemporaneously on separate contracts
in connection with the Works and for departmental labour and labour of any other properly
organization authority or statutory body which may be employed at the Site on execution
of any Work not included in the Contract or of any Contract which the Corporation may
enter into in connection with or ancillary to the work.
45. Prevention of Mosquito Breeding at Construction Site
(i) The Contractor shall on the respective construction site install mosquito proof and
accessible water storage tanks or to cover / protect the present water storage tanks
properly.
(ii) The contractor shall periodically give larvaecidal treatment to water storage
tanks, sites of water stagnation, water collection.
(iii) Any expenditure that may be incurred by the Corporation to unsure that the above
conditions are fulfilled by the contractor will be debatable to contractors account
and will be recovered from the bills of the contractor from time to time.
46. Sanitation
The Contractor shall, at his own cost, make all necessary provisions for health and safety
of his labour / employees. He shall, when required by the Engineer, provide proper latrines
and urinals to the satisfaction of the Engineer in such numbers and in such localities as he
may require, and shall take all steps necessary to compel his labour / employees to resort to
such latrines and
urinals, and shall dismiss from his employment and remove from the Works any one
detected obeying the calls of nature in any place other than the conveniences allotted for
such purposes. The said latrines shall be under the superintendence and orders of the
Engineer or his subordinates.
47. Not to Allow Huts
The Contractor shall, on no account, allow any huts to be erected on Corporation property
unless otherwise permitted by the Engineer in writing, to be inhabited after sunset by
anyone except the watchmen required for the Works, and none of his employees, except
such watchmen as aforesaid, shall sleep at night on any part of the Works. In case of any
offence committed by any of the labour or employees of the Contractor against any of the
provisions of this condition the Contractor shall be liable to a penalty not exceeding
Rupees Hundred for every such offense and the same shall be charged to the account of the
Contractor.
Signature of Tenderer No. of Corrections Signature of NMMC Official
43
48. Treasure Trove Fossils etc.
All fossils, coins, articles of value or antiquity and structural and other remains things of
geological or archaeological interest discovered in or upon the site shall be absolute
property of the Corporation and the Contractor shall duly preserve them and shall take
precautions to prevent his Workmen or any other person from removing or damaging any
such articles or thing and shall immediately upon discovery thereof and before removal
acquaint the Engineer, with such discovery and shall from time to time deliver the same to
such person or persons as the Engineer may from time to time appoint to receive the same
at the expense of the Corporation.
49. Patent’ Right and Royalties
The contractor shall save harmless and indemnify the Corporation from and against all
claims and proceedings for or on account of infringement of any Patent rights, design
trademark or name of other protected right in respect of any constructional plant, machine
Work, or material used for or in connection with the Works or any of them and from and
against all claims, proceedings, damages, costs, charges and expenses whatsoever in
respect thereof or in relation thereto. Except where otherwise specified, the contractor shall
pay all tonnage and other royalties, rent and other payments or compensation, if any, for
getting stone, sand, gravel, clay or other materials required for the Works or any of them.
50. Quarry
i) Quarry for extraction of murum, stone, rubble or any other material shall not
be made available by the corporation the contractor has to make his own arrangements
for quarry at his cost.
ii) The successful tenderer shall submit quarry permit from the competent
authority before starting the Work.
51. Photographs of The Works
No photographs of the Work or any part there of or equipment employed thereon shall be
taken or permitted by the contractor to be taken by any of his employees or any employees
of his sub-contractor without the prior approval of the Engineer in writing and no such
photographs shall be published or otherwise circulated without the approval of the
Engineer in writing.
52. Notices to Local Bodies
(i) The contractor shall comply with and give all notices required under any
Government Authority, Instrument, rule or order made under any Act of
parliament, state laws or any regulation or Bye-Laws of any local authorities
or public utilities concern relating to Works. He shall before making any variation
from the contract drawings necessitated by such compliance give to the
Engineer a notice giving reasons for the proposed variation and obtained
Engineer’s instructions thereon.
(ii) The contractor shall pay and indemnify the Corporation against any liability in
respect of any fees or charges payable under any Act of parliament, state laws or
any Governmental Instrument, rule or order any regulations or bye-laws of any
local authority or public utility concern in respect of the Works.
Signature of Tenderer No. of Corrections Signature of NMMC Official
44
53. Notices
Subject as otherwise provided in this contract all notice to be given on behalf of the
Corporation and all other actions to be taken on its behalf may be given or taken by the
Engineer or any officer for the time being entrusted with functions, duties and powers of
the Engineer.
All instructions, notices and communication etc. under the contract shall be given in
writing and if sent by registered post to the last known place or abode or business of the
Contractor shall be deemed to have been served on the date when in the ordinary course of
post these would have been served on or delivered to him.
54. Use of B.I.S. Specifications
In case where no particular specification is given for any article to be used under the
contract, the relevant specification, where one B.I.S. exists, of the Bureau of Indian
Standards shall apply.
Signature of Tenderer No. of Corrections Signature of NMMC Official
45
PART – III
WORK PROCEDURE
55. Possession of Site and Access Thereto
The corporation will, with the Engineer’s notice to commence the Works, give to the
Contractor possession of the Site.
Such access, as is in accordance with the Contract, is to be provided by the Corporation as
may be required to enable the Contractor to commence and proceed with the execution of
the Works in accordance with the programme referred to in Clause 86 if any, and otherwise
in accordance with such reasonable proposals as the Contractor shall, by notice to the
Engineer make.
The Corporation will, from time to time as the Works proceed, give to the Contractor
possession of such further portions of the Site as may be required to enable the Contractor
to proceed with the execution of the Works with due dispatch in accordance with such
programme or proposal, as the case may be.
56. Failure to Give Possession
The contractor should note that the site for work may be made available by the Corporation
in full or in part and that the contractor shall plan his works to commensurate with the
handing over the site. No claim of compensation on account of delay in making available
the Site shall be payable to the contractor. However, time extension for completing the
Work shall be given to the Contractor in case of such delay.
57. Unforeseeable Physical Obstructions or Conditions
If, however, during the execution of the Works the Contractor encounters physical
obstructions or physical conditions, other than climatic conditions on the site, which
obstructions or conditions were, in his opinion, not foreseeable by an experienced
contractor, the Contractor shall forthwith give notice thereof to the Engineer. On receipt of
such notice, the Engineer shall, if in his opinion such obstructions or conditions could not
have been reasonably foreseen by an experienced contractor, after due consultation with
the Contractor, determine:
Any extension of time to which the Contractor is entitled under Clause 80.
58. Drawings; Custody of Drawings
The drawings shall remain in the sole custody of Engineer, but two copies thereof shall be
furnished to the Contractor free of charge. The Contractor shall provide and make at his
own expense any further copies required by him. At the completion of the Contract, the
Contractor shall return to the Engineer all drawings provided under the Contract.
59. One Copy of Drawing to be Kept on Site
One copy of the drawings, furnished to the Contractors as aforesaid, shall be kept by the
Contractor on the site and the same shall at all reasonable times be available for inspection
and use by the Engineer and the Engineer’s Representative and by any other persons
organization by the Engineer in writing.
Signature of Tenderer No. of Corrections Signature of NMMC Official
46
60. Discrepancies in Drawings or Specifications
The drawings and specifications are to be considered as mutually explanatory of each
other, detailed drawings being followed in preference to small scale drawings and figured
dimensions in preference to scale and special conditions in preference to general
conditions. Special conditions or dimensions given in the specifications shall supersede all
else. Should any discrepancies, however appear, or should any misunderstanding arise as
to the meaning and import of the said specifications or drawings, or as to meaning and as
to the dimensions or the quality of the materials or the due and proper execution of the
Works, or as to the measurement or quality and valuation of the Works executed under this
Contract, or as extra thereupon the same shall be explained by the Engineer be binding
upon the Contractor and Contractor shall execute the Work according to such explanation
(subject as aforesaid) and without extra charge or deduction to or from the contract and
shall also do all such Work and things as may be @ for the proper completion of works as
implied by the Drawings and Specifications, even though such Works and things are not
specifically shown and described in the said Drawing and Specifications. The final
decision of the Commissioner in case a reference be made to him under Clause No. 89 be
binding upon the Contractor and Contractor shall execute the Works according to such
explanation (subject to aforesaid) and shall also do all such explanation (subject to
aforesaid) and shall also do all such Works and required things as may be necessary for the
proper completion of Works as implied by the drawings and specifications, even though
such Works and things are not specifically shown and described in the said drawings and
specifications.
61. Engineer to have Power to issue Further Drawings or Instruction
The Engineer shall have the power and authority from time to time and at all times to make
and issue such further drawings and to give such further instructions and directions as may
appear to him necessary or proper for the guidance of the Contractor and the good
sufficient & execution of the Works according to terms of the specifications and
Contractor shall receive, execute obey and be bound by the same, according to the true
intent and meaning thereof, as fully and effectually as though the same had accompanied
or had been mentioned or referred to in the specification. The Engineer may also alter or
vary the levels or position of any Works contemplated by the specifications, or may order
any of the Works contemplated thereby to be omitted, with or without the substitution of
any other works in lieu thereof or may order any work or any portion of Work executed or
partially executed, to be removed, changed or altered, and if needful, may order that other
Works shall be substituted instead thereof and difference of expense occasioned by any
such diminution or alteration so ordered and directed shall be added to or deducted from
the amount of this Contract as provided under the Clauses No. 101 and 102. No Work
which radically changes the original nature of the contract shall be ordered by the Engineer
and in the event of any deviation being ordered which in the opinion of the Contractor
changes the original nature of Contract he shall nevertheless carry it out and disagreement
as to the nature of the work and the rate to be paid therefore shall be resolved in
accordance with Clause No. 114.
The time for completion of the Works, shall in the event of any deviations resulting in
additional cost over the Contract sum being ordered, be extended or reduced reasonably by
the Engineer. The Engineer’s decision in this case shall be final.
Signature of Tenderer No. of Corrections Signature of NMMC Official
47
62. Levels
All levels referred to in connection with these Works are based on Great Trigonometric
survey (G.T.S.) levels. The Contractor should also keep the leveling instrument in good
Working condition through out the period of construction Work on site.
63. Setting Out the Work
The Engineer shall supply dimensioned drawings, levels and other information necessary
to enable the Contractor to set out the works. The Contractor shall provide all setting out
apparatus at his own cost, such as leveling instruments in good working condition and
appliances, all pegs, ranging rods, long measuring rods, marked metres and organization
and each metre and organization numbered, pots and sight-rails, boning rods, moulds,
templates, etc. together
with any reasonable number of labourers that may be required and set out the work and be
responsible for the accuracy of the same. The Contractor shall amend at his own cost and
to the satisfaction of the Engineer any error found at any stage which may arise through
inaccurate setting out. The Contractor shall protect and preserve all bench marks used in
setting out the work till the end of Defects Liability period unless the Engineer directs its
early removal. The Contractor should also keep leveling instrument in good working
condition throughout the period of construction work on site.
64. Works Closed Between Sunset and Sunrise or on Sundays and Holidays
No work shall be done between sunset and sunrise or on Sunday or Municipal holidays and
except with the special sanction of the Engineer in writing previously obtained and the
withholding of such sanctions shall be no ground of complaint on the part of contractor or
cause for compensation to him, or excuse for not completing the work within the contract
period. The period within which the Work has to be carried out and completed has been
fixed in terms of this clause with the provision that the total number of hours of Work
permissible shall not exceed 48 hours in a week and in no case more than 8 hours on any
Working day, the actual time within which the said hours shall be Worked being subject to
mutual arrangements with the Contractor at the commencement of the Works or from time
to time as may be required and provided that all Works shall be stopped for rest and meals
for one hour at about mid-day exclusive of the permissible hours aforesaid for the Works.
Though sanction may be accorded to the contractor to work on days and at times otherwise
normally non-permissible under this Contract, the Contractor shall be required to bear the
cost for such supervision as in the opinion of the Engineer may be necessary at these times.
It should be distinctly understood that the granting of permission to work extra hours or to
work on Sunday and holiday will be entirely at the discretion of the Engineer and cannot
be claimed by the contractor as a matter of right.
If on the other hand the Engineer requires that the work shall be proceeded with on days
and at times otherwise normally non-permissible under this contract the contractor shall
proceed with the work but he will not be required in such cases to bear the cost of the
Municipal establishment employed at the time.
Signature of Tenderer No. of Corrections Signature of NMMC Official
48
The contractor at all times during the continuance of this contract shall in all his dealings
with local labour for the time being employed on the works contemplated by this contract
have due regard to all local festivals and religious or other customs and all disputes,
matters and questions arising
between the contractor and any of his agent on the one hand and any local labour on the
other hand with respect to any matter or thing in any way connected with this contract shall
be decided by the Commissioner whose decision shall be final and binding on all parties.
65. Work to be in Accordance with contract
The contractor shall execute and complete the works and remedy any defects therein in
strict accordance with the contract to the satisfaction of the Engineer.
66. Duties and Powers of the Engineer’s representative
The duties of the representative of the Engineer are to check, watch and supervise work
and to test and examine any material to be used or workmanship employed in connection
with the works. He shall have no authority to relieve the contractor of any of his duties or
obligations under the contract not to except as expressly provided here under or elsewhere
in the contract to order any work involving delay or any extra payment by the Corporation
or to make any variation of or in the works.
Failure of the representative of the Engineer to disapprove any work or material shall not
prejudice the power of the Engineer thereafter to disapprove such work or material and to
order the pulling down, removal or breaking up thereof.
If the contractor shall be dissatisfied with any decision of the representative of the
Engineer he shall be entitled to refer the matter to the Engineer who shall thereupon
confirm, reverse or vary such decision.
67. Engineer’s Decision
The whole of the work shall be under the direction of the Engineer, whose decision shall
be final, conclusive and binding on all parties to the contract, on all questions relating to
the construction and meaning of plans, working drawings, sections and specifications
connected with the work.
68. Instructions to contractor
The contractor or his agent shall be in attendance at the site(s) during all working hours
and shall supervise the execution of the works with such additional assistance in each trade
as the engineer may consider necessary. Orders given to the Contractor’s agent shall be
considered to have the same force as if they had been given to the Contractor himself.
The Engineer shall communicate or confirm his instruction to the Contractor in respect of
the execution of Work in a “Works site order Book” Maintained in the office of the
Engineer and the Contractor or his authorized representative
shall confirm receipt of such instructions by signing the relevant entries in this book. If
required by the Contractor he shall be furnished a certified true copy of such instruction(s).
If the Contractor fails to comply with the instruction(s) of the Engineer, the Engineer may
impose the daily penalty of Rs. 500 (Rupees Five Hundred) for each of such defaults. This
penalty will not prejudice the right of the Municipal Commissioner or the Engineer to
claim compensation.
Signature of Tenderer No. of Corrections Signature of NMMC Official
49
69. Work Order Book
A Work order book shall be maintained on site and it shall be the property of Corporation
and the Contractor shall promptly sign orders given therein by Engineer or his
representatives and his superior officers and comply with them. The Contractor shall report
the compliance in good time so that it can be checked. The contractor will be allowed to
copy out instruction therein from time to time.
70. Management Meeting
Either the Engineer or the Contractors may require the other to attend Management
meeting. The business of a management meeting shall be to review the plans for remaining
Works.
Engineers shall record the business of management meetings and is to provide copies of
his record to those attending the meeting. The responsibility of the parties for actions to be
taken is to be decided by the Engineer either at the management meetings or after the
management meetings and stated in writing to all who attend the meetings.
71. Materials
(a) Material to be provided by the Contractor:
The Contractor shall, at his own expense, provide all materials required for the Works.
All materials to be provided by the Contractor shall be in conformity with the
specifications laid down in the contract and the Contractor shall, furnish proof to the
satisfaction of the Engineer that the materials so comply, Contractor shall produce proof
viz. challans, bills, vouchers etc. so as to ensure that the material was brought on site and
quantities used as per the norms, specifications etc.
Officers of the Corporation concerned with the work shall be entitled at any time to inspect
and examine any material intended to be used in or on the Works either on the site or at
factory or Workshop or other places where such materials are assembled, fabricated or
manufactured or at any place(s) where
these are laying or from which these are being obtained and the Contractor shall give such
facilities as may be required for such inspection and examination. The materials brought on
site outside Working hours shall be stacked separately till they are inspected by the
Engineer or his representative.
All materials brought to the site shall not be removed off the site without the prior written
approval of the Engineer. But whenever the Works are finally completed the Contractor
shall at his own expense forthwith remove from the site all surplus materials originally
supplied by him.
The Contractor shall, at his own expense and without delay, supply to the Engineer
samples of materials proposed to be used to the Works. The Engineer shall within seven
days of samples or within such further period as he may require and intimated to the
Contractor in writing, inform the Contractor whether the samples are approved by him or
not. If the samples are not approved the Contractor shall forthwith arrange to supply to the
Engineer for approval fresh samples complying with the specifications laid down in the
contract.
Signature of Tenderer No. of Corrections Signature of NMMC Official
50
The Engineer shall have full powers to require removal of any or all of the materials
brought to site by the Contractor which are not in accordance with the contract
specifications or which do not conform in character or quality to the samples approved by
him. In case of default on the part of the Contractor in removing the rejected materials, the
Engineer shall be at liberty to have them removed by other means. The Engineer shall have
full powers to procure other proper materials to be substituted for rejected materials and in
the event of the Contractor refusing to comply, he may cause the same to be supplied by
other means. All costs, which may attend upon such removal and / or substitution shall be
borne by the Contractor.
Subject as hereinafter provided in Clause No. 98 all charges on account of Octroi, terminal
or sales tax, VAT etc. and other duties on material obtained for the Works from any source
shall be borne by the Contractor.
The Engineer shall be entitled to have tests carried out as specified in the contract for any
materials supplied by the Contractor other than those for which as stated above,
satisfactory proof has already been produced, at the cost of the Contractor and the
Contractor shall provide at his expense all facilities which the Engineer may require for the
purpose.
If no tests are specified in the contract, and such tests are required by the Engineer the
Contractor shall provide all facilities required for the purpose and charges for these tests
shall be borne by the Contractor only if the tests disclose that the said materials are not in
accordance with the provision of the contract.
The cost of the materials consumed in test shall be borne by the Contractor in all cases
except when otherwise provided.
For carrying out tests on soil, cement, sand, aggregate, brick and concrete etc. the standard
will be as prescribed in relevant I.S. The Engineer may direct the Contractors to get the
samples of materials tested in CIDCO, PWD, VJTI, IIT, or any approved laboratory out of
those accredited by National Accreditation Board of Laboratories, Govt. of India. The
results of the tests shall be binding on the Contractor and Corporation. In case the
Contractor disputes the results of tests, if is open for him to ask for the re-testing in which
case the cost shall be borne by the Contractor. The decision of the Engineer on
acceptability or re-testing by Corporation or testing again independently in VJTI or IIT
will be binding on both the parties to the contract.
72. Stock of Materials Required.
(a) The Contractor shall at his own expense provide and furnish himself with sheds and
yards in such situations and in such numbers as, in the opinion of the Engineer are
requisite for carrying in out the Works under this contract, and the Contractor shall
keep at each of such sheds and yards a sufficient quantity of materials in stock so as
not to delay the carrying out the Works with due expedition and the Engineer and
his sub-ordinates shall have free access to the said sheds or yards at any time for
the purpose of inspecting the stock of materials so kept in hand any material or
article, which the Engineer may object to, shall not be brought upon or used in
the Work but shall be forthwith removed from the sheds or yards by the Contractor
at his own cost. The Contractor will however be allowed to use for the above
purpose the completed portion of the buildings if available.
Signature of Tenderer No. of Corrections Signature of NMMC Official
51
(b) General :
Cement brought on site by the Contractors shall be stored in waterproof godown
with two locks on each door. The key of one lock of each door shall remain with
the Engineer or his representative and that of the other lock with the Contractor’s
organization agent at site of Works so that cement is removed from the godown
only according to daily requirements with the knowledge of both the parties.
73. Production of Vouchers
The Contractor shall, produce all quotations, invoices vouchers and accounts or receipts
etc. to prove that the materials supplied by him are in conformity with the specifications
laid down in the Contract and the same are brought to the site and utilized on the said
works.
74. Plant and’ Equipment
The Contractor shall arrange at his own expense all tools, plant and equipment required for
execution of Works. If required by the Contractor and if available the Corporation may
supply such of the tools, plant and equipment as are available, to the Contractor at the rates
and terms to be specified by the Engineer. No tools, plant and equipment once brought to
the Work site shall be removed without the written permission or order of the Engineer,
until he has certified the completion of the Work.
If any tools, Plants and equipment brought on site, are in the opinion of the Engineer
inefficient, bad or of inferior quality or are unsuited for the Works then such tools, plant
and equipment shall not be used on the Works but shall be removed by the Contractor at
his own expense within twenty four hours after the service of a written order or notice
from the Engineer to that effect and fresh tools, plant and equipment be substituted in lieu
of that ordered to be removed by the Engineer.
75. Inspection & Approval
All Works embracing more than one process shall be subject to examination and approval
at each stage thereof and the Contractor shall give due notice to the Engineer or his
organization representative when each stage is ready. In default of such notice, the
engineer shall be entitled to appraise the quality and extent thereof.
No work shall be covered up or put out of view without the approval of the Engineer or his
organization representative and the contractor shall afford full opportunity for examination
and measurement of any Work which is about to be covered up or out of view and for
examination of foundation before permanent Work is placed thereon.
The Contractor shall give due notice to the Engineer or his organization representative
whenever any such Work or foundation is ready for examination and the Engineer or his
representative shall without unreasonable delay, unless he considers it necessary and
informs the Contractor in writing accordingly, attend for he purpose of examining and
measuring such Work or examining such foundations. In the event of the failure of the
Contractor to give such notice he shall, if required by the Engineer, uncover such Work at
the Contractor’s expense.
Departmental officers concerned with the Works shall have powers at any time to inspect
examine any part of the Works and the contractor shall give such facilities as may be
required for such inspection & examination.
Signature of Tenderer No. of Corrections Signature of NMMC Official
52
76. Uncovering and Making Good
No part of the Works shall be covered up or put out of view without the approval of the
Engineer. The Contractor shall uncover any part of the Works and /or make opening in or
through the same as the Engineer may from time to time direct for his verification and
shall reinstate and make good such part to the satisfaction of the Engineer, if any such part
has been covered up or put out of view after being approved by the Engineer and is
subsequently found on uncovering to be executed in accordance with the contract, the
expenses of uncovering and/or making openings in or through, reinstating and making
good the same shall be borne by the Corporation. In any other case all such expenses shall
be borne by the Contractor.
77. Contractor to Search
The Contractor shall, if required by the Engineer in writing, search under the direction of
the Engineer for the cause of any defect, imperfection or fault appearing during the
progress of the Work or in the period of maintenance. Unless such defect, imperfection or
fault shall be one for which the Contractor is liable under the contract, the cost of the Work
carried out by the Contractor in searching as aforesaid shall be borne by the Corporation.
If such defect, imperfection or fault shall be one for which Contractor is liable as aforesaid,
the cost of the Work carried out in searching as aforesaid shall be borne by the Contractor
and he shall in such case repair, rectify and make good such defect, imperfection or fault,
at his own expense.
78. Default of Contractor in Compliance
In case of default on the part of the Contractor in carrying out such instruction within the
time specified therein or, if non, within a reasonable time, the Corporation shall be entitled
to employ any other persons to carry out the same and all costs consequent thereon or
incidental thereto shall, after due consultation with the Corporation and the Contractor, be
determined by the Engineer and shall be recoverable from the Contractor by the
Corporation from any monies due or to become due to the Contractor and the Engineer
shall notify the Contractor accordingly.
79. Urgent Works
If any Urgent Work (in respect whereof the decision of the Engineer shall be final and
binding) becomes necessary and the Contractor is unable or unwilling at once to carry it
out, the Engineer may by his own or other Work people, carry it out as he may consider
necessary. If the urgent Work shall be such as the Contractor is liable under the contract to
carry out at his expense all expense incurred on it by the Corporation shall be recoverable
from the Contractor and be adjusted or set off against any sum payable to him.
Signature of Tenderer No. of Corrections Signature of NMMC Official
53
PART – IV
TIME SCHEDULE AND DELAYS
80. Commencement Time
The time allowed for execution for the Works as specified in the contract documents shall
be the essence of the contract. The execution of the Works shall commence from the date
specified by the Engineer in writing. If the Contractor fails or neglects to commence the
execution of the Works as aforesaid, the Corporation shall without prejudice to any other
right or remedy be at liberty to forfeit the security deposit absolutely.
81. Extension of Time for Completion due to Monsoon.
In any case where the time prescribed for completion of any Work is exclusive of monsoon
period. No new trench Work should be started after 15th
May and existing trenches are
required to be reinstated by 31st May every year. The site shall be cleared in all respect
including removal of surplus material on or before 10th
June of every year. The monsoon
period shall be deemed to be from 10th
June to 30th
Sept. of the calendar year.
However, if the Contractor is permitted by the Engineer to Work during any monsoon.
Period, all such period shall be taken into account for the calculating the contract period on
pro-rata basis as under.
Cost of Work done
Effective during Monsoon
Days = ---------------------- x No. of days of contract period
Total cost of
Contract Work
In the event of the Contractor failing to comply with this condition. He shall be liable to
pay as compensation as stated in Clause No. 90.
82. Extension of Time due to Unforeseen events
If the work be delayed by-
a) Force measure such as acts of God, act of public enemy, act of
government, floods, epidemics etc. or
b) Abnormally bad weather, or
I Serious loss or damage by fire or
d) Civil commotion, local combination of workmen, strike or lockout affecting any of
the trades employed on the work, or
e) Delay on the part of other Contractor or tradesmen engaged by the Municipal
Corporation in executing works not forming part of the contract or
f) The reasons stated in condition No 84 and 85.
g) Any other cause, in the absolute discretion of the Engineer.
Signature of Tenderer No. of Corrections Signature of NMMC Official
54
Then upon the happening of any such event causing delay, the Contractor shall
immediately give notice there of in writing to the Engineer but shall nevertheless use
constantly his best endeavors to prevent or make good the delay and shall do all that may
be reasonable required to the satisfaction of the Engineer to proceed with the work.
Request for extension of time, to be eligible for consideration shall be made by the
Contractor in writing within 14 (fourteen) days of the happening of the event causing
delay. The Contractor may also, if practicable indicate in such a request the period for
which extension is desired. In any such case, the engineer may give a fair reasonable
extension of time for completion of individual items or groups of items of work for which
separate periods of completion are specified in the contract or the contact as whole. The
decision of the Engineer in regard to the extension will be communicated to the Contractor
in writing within a reasonable time and the contractor shall also be paid such compensation
that in the opinion of the Engineer is fair and reasonable to cover the delays resulting form
the provisions under the sub clause (e) above.
The time extended for completing the work shall be the essence of the contract for the
period extended.
83. Network Schedule & Monthly Progress Reports
a) On award of the contract, the Contractor shall submit the time schedule for the
Work in the ‘form of PERT Net Works or Bar chart.
b) The schedules shall be prepared in direct relations to the time stated in the contract
documents for completion of items or groups of items of Work and or the contract
as a whole. It shall indicate the dates of commencement and completion of various
activities of the Work. And should contain no activities with a duration greater
than 28 days.
Milestones would be so determined that at least 10 percent of the events are
milestones and no two milestones are more than 3 months apart.
The Engineer may approve the Schedule as submitted or suggest modifications as
he thinks necessary. The Contractor shall modify the chart accordingly and obtain
Engineer’s approval.
c) The finalized Network may be amended from time to time, if felt necessary by
the contractor, with the approval of the Engineer.
d) A fixed sum shall be held in abeyance at the time of the next interim payment
for non-attainment of each milestone in the Network and shall be released only on
completion of the Work after deducting the compensation for delay if there is
Contractor’s fault as per provision in Clause No. 86 and penalty covered under Clause No.
53. The fixed sum shall be:
Rs.10,000/- for all contracts over Rs. 25 Lakhs and upto the value of Rs. 100 Lakhs.
Rs. 20, 000/- for all contracts over Rs. 1 crore and upto the value of Rs. 5 crores.
Rs. 35, 000/- for all contracts over Rs.5 crores and upto the value of Rs. 10 crores.
Rs.50,000/- for all contracts over Rs. 10 crores.
If the attainment of the milestones is delayed for reason not attributable to the Contractors
no moneys will be held in abeyance.
Signature of Tenderer No. of Corrections Signature of NMMC Official
55
84 Disruption of Progress for Lack of Drawings.
The Contractor shall give written notice to the Engineer whenever planning or progress of
the Works is likely to be delayed or disrupted unless any further drawing or order,
including a direction, instruction or approval, is issued by the Engineer within a reasonable
time. The notice shall include details of the drawing or order required and of why and by
when it is required and of any delay or disruption likely to be suffered if it is late.
85. Delays of Drawings
If by reason of any failure or inability of the Engineer to issue within a time reasonable in
all the circumstances any drawing or order requested by the Contractor in accordance with
the clause 84 of this condition the Contractor suffers delay, then the Engineer shall take
such delay into account in determining any extension of time to which the Contractor is
entitled under sub-clause (g) of Clause No. 82 hereof. No. monetary claim will be
entertained on this account.
86. Monthly Report
The Contractors will be required to submit the monthly progress reports by the 2nd
day of
the following month to the Engineer Failure on the part of the Contractor to submit
monthly report in time will attract action as per Clause No. 83.
87. Rate of Progress.
If for reason, which does not entitle the Contractor to an extension of time, the rate of
progress of the Works or any Section is at any time, in the opinion of the Engineer, too
slow to comply with the Time for Completion, the Engineer shall so notify the Contractor
who shall thereupon take such steps as are necessary, subject to the consent of the
Engineer, to expedite progress so as to comply with the Time for Completion. The
Contractor shall not be entitled to any additional payment for taking such steps. If, as a
result of any notice given by the Engineer under this Clause, the Contractor considers that
is is necessary to do any Work at night or on locally recognized days of rest, he shall be
entitled to seek the consent of the Engineer so to do. Provided that if any steps, taken by
the Contractor in meeting his obligations under this Clause, involve the Corporation in
additional supervision costs, such costs shall be determined by the Engineer and shall be
recoverable from the Contractor, and may be deducted by the Corporation from any
monies due or to become due to the Contractor and the Engineer shall notify the
Contractors accordingly.
88. Suspension of Work
(a) The Contractor shall, on receipt of the order in writing of the Engineer, suspend
the progress of the Works or any part thereof for such time and in such manner as the
Engineer may consider necessary for any of the following reasons:-
(i) On account of continued non-compliance of the instructions of
he Engineer of any other default on the part of the Contractor,
or
(ii) For Proper execution of the Works or part thereof for reasons
other than the default of the Contractor, or
Signature of Tenderer No. of Corrections Signature of NMMC Official
56
(iii) For safety of the Works or part thereof.
The Contractor shall, during such suspension, properly protect and secure the
Works to the extent necessary and carry out the instructions given in that behalf by
the Engineer.
(b) If the suspension is ordered for reasons (ii) and (iii) in sub-para
(a) above, the Contractor shall be entitled to an extension of time equal to
the period of every such suspension plus a reasonable time as decided by the
Engineer.
I if the suspension is ordered for reasons of (i) in sub-para (a) above, the Engineer shall
have powers to suspend the payment under the contract. Such suspension of payment may
be continued until default shall have been rectified.
89. Stoppage/Alteration/Restriction of Work.
1) If at any time after the execution the contract documents the Engineer shall for any
reason whatsoever (other than default on the part of Contractor for which the
corporation is entitled to rescind the contract) desires that the whole or any part of
the Work specified in the tender should be suspended for any period or that the
whole or part of the Work should not be carried out, at all he shall give to the
Contractor a notice in writing of such desire and upon the receipt of such notice the
Contractor shall forthwith suspend or stop the Work wholly or in part as required,
after having due regard to the appropriate stage at which the Work should be
stopped or suspended so as not to cause any damage or injury to the Work already
done or endanger the safety there of provided that the decision of the Engineer as to
the stage at which the Work or any part of it could be or could have been safely
stopped or suspended shall be final and conclusive against the Contractor. The
Contractor shall have no claim to any payment or compensation whatsoever by
reason of or in pursuance of any notice as aforesaid, on account of any suspension,
stoppage or curtailment except to the extent specified hereinafter.
2) Where the total suspension of Work ordered as aforesaid continues for a continuous
period exceeding 90 days the Contractor shall be at liberty to withdraw from the
contractual obligations under the contract so far as it pertains to unexecuted part of
the Work by giving a 10 days prior notice in writing to the Engineer, within 30
days of the expiry of the said period of 90 days, of such intention and requiring the
Engineer to record the final measurement of the Work already done and to pay
final bill.
Upon giving such notice the Contractor shall be deemed to have been charged from
his obligations to complete the remaining unexecuted Work under his contract. On
receipt of such notice the Engineer shall proceed to complete measurements and
make such payments as may be finally due to the Contractor within a period of 90
days from the receipt of such notice in respect of the Work already done by the
Contractor. Such payment shall not in any manner prejudice the right of the
Contractor to any further compensation under the remaining provisions of this
clause.
Signature of Tenderer No. of Corrections Signature of NMMC Official
57
3) Where the Engineer required the Contractor to suspend the Work for a period in
excess of 30 days at any time or 60 days in the aggregate, the Contractor shall be
entitled to apply to the engineer within 30 days of the resumption of Work after
such suspension for payment of composition to the extent of pecuniary loss
suffered by him in respect of Working machinery remain idle on the site of on the
account of his having to pay the salary or wages of, labour engaged by him during
the said period of suspension provided always that the Contractor shall not be
entitled to any claim in respect or any such Working machinery, salary or wages for
the first 30 days whether consecutive or in the aggregate such suspension or in
respect or any suspension whatsoever occasioned by unsatisfactory Work or any
other default on his part. The decision of the Engineer in this regard shall be final
and conclusive against the Contractor.
4) In the event of
i) Any total stoppage of Work on notice from Engineer under sub
clause (1) in that behalf.
(ii) Withdrawal by the Contractor from the contractual obligations
to complete the remaining unexecuted Work under sub clause (2) on
account of continued suspension of Work for a period exceeding 90 days.
It shall be open to the Contractor, within 90 days from the service of (i) the notice
of stoppage of Work or (ii) the notice of withdrawal from the Contractual
obligations under the contract on account of the continued suspension of Work (iii)
notice under clause 89 (1) resulting in such curtailment to produce to the Engineer
satisfactory documentary evidence that he had purchased or agreed to purchase
material for use in the contracted Work, before receipt by him of the notice of
stoppage, suspension or curtailment and require Government to take over on
payment such material at the rate determined by the Engineer provided,
however, such rates shall in no case exceed the rates at which the same was
acquired by the Contractor. The corporation shall thereafter take over the materials
so offered, provided the quantities offered, are not in excess of the requirements of
the unexecuted Work as specified in the accepted tender and are of quality and
specifications approved by the Engineer.
90. Liquidated Damages for Delay.
If the Contractor fails to complete the Works and clear the Site on or before the Contract or
extended Date(s)/period(s) of completion, he shall, without prejudice to any other right or
remedy of Corporation on account of such breach, pay as agreed compensation, amount
calculated as stipulated below (or such smaller amount as may be fixed by the Engineer)
on the Contract Value of the whole Work or on the Contract Value of the item or group of
items of Work for which separate period of completion are given in the contract and of
which completion is delayed for every week that the whole of the Work of item or group of
items of Work concerned remains uncompleted, even though the contract as a whole be
completed by the contractor on the extended date of completion. For this purpose the term
“Contract Value” shall be the value of the Work at Contract Rates as ordered including the
value of all deviations ordered:
Signature of Tenderer No. of Corrections Signature of NMMC Official
58
(a) Completion period for (originally stipulated per week or as extended) not
exceeding 6 months @ 1 percent
(b) Completion period for (as originally stipulated per week as extended) exceeding 6
months and not exceeding 2 years @ ½ percent
(c) Completion period as (originally stipulated per week or as extended) exceeding 2
years. @ ¼ percent
The under noted percentage of the Contract Value of the item or group of items of Work
for which a separate period of completion is given.
When the delay is not a full week or in multiple of a week but involves a fraction of a week
the compensation payable for that fraction shall be proportional to the number of days
involved.
Provided always that the total amount of compensation for delay to be paid for this
condition shall not exceed
(a) Completion period (originally stipulated or as extended).
Not exceeding 6 months – 10 percent
(b) Completion period (as originally stipulated or as extended)
Exceeding 6 months and not exceeding 2 years – 7 ½ percent
(c) Completion period (as originally stipulated or as extended)
Exceeding 2 years – 5 percent.
The amount of liquidated damages may be adjusted set off against any sum payable to the
Contractor under this or any other contract with the corporation or from the security
deposit of the Contractor entirely at the discretion of the corporation.
Signature of Tenderer No. of Corrections Signature of NMMC Official
59
PART – V
BILLS AND PAYMENTS
91. Method of Measurements
Except where any general or detailed description of the Work in bills of quantities or
schedule of Works/items/quantities expressly shown to the contrary, bills of quantities
shall be deemed to have been prepared and measurements shall be taken in accordance
with the procedure set forth in the schedule of rates/ specifications notwithstanding any
provision in the relevant standard Method of Measurement or any general or local custom.
In the case of items, which are not covered by the schedule of rates/ specifications,
measurements shall be taken in accordance with the relevant Standard specifications
published by PWD Govt. of Maharashtra and for the works not covered in this publication,
measurements shall be taken as per the codes by Bureau of Indian standards.
92. Records and Measurement:
The Contractor shall submit to the Engineer the monthly statements of the estimated value
of the work completed less than the cumulative amount certified previously. The monthly
statements shall be in the bill form specified by the Engineer and it shall be submitted on
or before the date instructed by the Engineer. These monthly bills shall be supported with
detailed measurements for the gross quantity of the work done duly deducting the gross
quantity paid in the previous bill. The Contractor is permitted to copy down the
corrections in the bills paid as per the Engineers certifications. Upon receipt of the bill and
measurements by the Contractors, the Engineer shall except as otherwise stated ascertain
and determine by measurements the value in accordance with the contract of work done in
accordance therewith.
All items having a financial value shall be entered in measurements Book etc. as
prescribed by the corporation so that a complete record is obtained of all the Works
performed under the contract.
Measurements shall be taken jointly by the Engineer or his organization representative and
by the Contractor or his organization representative. Before taking measurements of any
work the Engineer or the person deputed by him for the purpose shall give a reasonable
notice to the Contractor. If the Contractor fails to attend or send an organization
representative for measurements after such a notice or fails to countersign or the objection
within a week from the date of measurements then in any such event measurements
taken by the Engineer or by the person deputed by him shall be taken to be correct
measurements of the works and shall be binding on the Contractor.
The Contractor shall, without any extra charge, provide assistance with every appliance
and other things necessary for measurements.
Measurements shall be signed and dated by both parties each day (of taking measurements)
on the site on completion of measurements.
Signature of Tenderer No. of Corrections Signature of NMMC Official
60
93. Payments of Bills and Other Claims
The payment of bills and other claims arising out of the contract will be made by account
Payee Cheque drawn in the name of ‘Agency’
94. Full Provisions
The rates inserted by the corporation against various items of Work detailed in various
parts of schedule shall be deemed to include every allowance necessary. Without extra
measurements or charge for meeting the requirement of various components/ parts of the
contract documents (viz particular specifications, PWD of standard specifications,
Maharashtra schedule of rates, MOST specifications, BIS specifications, Special
Conditions, preambles and notes to schedule of items description of schedule items which
shall all be read together and any or of the following unless specifically provided for the
contrary.
a) Compliance with all the conditions of contract including General Conditions of
Contract, schedule of rates and Quantities, Particular Specifications, Drawings
including Notes thereon, Specifications in standard Specifications of PWD of
Maharashtra and MJP relevant Indian Standard Specification wherever applicable.
However, in case of any discrepancy between drawing and tender, the tender item
and specification shall prevail. If there is discrepancy in tender specifications, the
order of preference shall be 1st specification of Maharashtra State PWD, MJP,
MOST and lastly BIS.
b) All labour, materials, tool and plants, equipments and transport which may be
required in preparation for and in the full and entire execution and completion of the
Works including waste of materials, carriage and cartage, carrying in, return of
empties, hoisting, setting, fixtures and fittings in position.
c) Local conditions: Nature of Works, local facilities for supply of labour and
materials accessibility’s to sites and all other matters effecting the execution and
completion of the Works.
d) Duties etc: Payments of any Octroi, Terminal Tax, Sales Tax, Turnover Tax,
Contract Sales Tax, Toll Tax, Ground Rent, Royalty, environmental Cess, Local
Bodies Cess, Taxes or any duties on materials obtained for the Works and any duties in
respect of patent rights.
e) Supervision: Competent Supervision of the Work.
f) Labour: Reasonable terms and conditions of employments, liability to pay
compensation, Wages as per statutory enactment’s temporary accommodation,
sanitation, compliance with contract labour act 1970 (Regulation and Abolition).
g) Water: Provision of all water required including temporary plumbing and
connection.
h) Temporary Work Shops, Stores, Offices, Labour Camps etc. Provisions of
such structures required for efficient execution of the Works and removing and
cleaning up site on completion of Works.
i) Precautions Against Risks: Precautions to prevent loss or damage from all or any
risk, insurance of sheds or any temporary accommodation provided by the
corporation watching and lighting, provisions pertaining to the General
conditions of Contract.
Signature of Tenderer No. of Corrections Signature of NMMC Official
61
j) Notices, fees etc.: Compliance with statutory provisions of regulations and/ or
bye laws of any local authority and/ or any public service company or authority
affected by the Works.
k) Setting the Works including all apparatus required.
l) Site Drainage: Removal of all water that may accumulate due to spring, sub soil
water, flood/tides and any other causes on this site during the progress of the Work.
m) Execution of Work in Workmanlike manner, facilities for inspection etc.
n) Rectification of bad Work: Rectification and / or removal and reconstruction
of any Work which (as decided by the Engineer) has been executed with unsound or
imperfect materials or unskilled Workmanship or of a quality inferior to that
contracted for, whether during construction or reconstruction prior to the expiry of
the Defect Liability period.
o) Responsibility for damages and loss of all construction materials etc., at the
site until handing over to the corporation.
p) Removal of Rubbish: Removal of Rubbish & debris & cleaning of any dirt before
handing over all completion of works.
q) Cleaning site and Works: Removal by the Contractor off the site, of any
tools, plants & materials and sweeping building, washing floors, cleaning joineries &
removal of splashes of asphalt leaving the whole site neat and tidy.
r) Completion: Completing the Work to the satisfaction of the Engineer on or
before stipulated the date of completion.
s) Difficult position: Accessibility or otherwise to site, easy or difficult position
in Works.
t) Errors: Rectification of all defects during construction & defect liability period to
the satisfaction of Engineer.
u) Curved Works etc. Work of any quantity, size or shape whether level, inclined,
curved, battered etc.
v) Maker’s Instruction: Compliance with make’s instructions in the case of
proprietary articles, factory made good of precast items.
w) Waste: All waste laps, seams, joints (rough or fair cutting) straight/raking, circular
and making good.
x) Artificial Lights: To include all lighting / Kerosene or electric power as the case
may be when need arises for use of lighting while carrying out Works.
Construction of approaches to the site of Work. Making arrangements for proper access to
Works in the form of stairs, ladders, lifts etc. as ordered by the Engineer – in – Charge for
proper supervisions, testing and or inspection of Works including material during
construction & defect liability period.
Signature of Tenderer No. of Corrections Signature of NMMC Official
62
95. Interim Payment
Interim bills shall be submitted by the Contractor from time to time (but at an interval of
not less than one month) for the Works executed. The Engineer shall arrange to have the
bills verified by taking or causing to be taken, where necessary, the requisite measurement
of Work. The joint measurements shall not be an excuse for the Contractor to submit
intermediate bills at monthly or intervals not less than a month. All interim bills shall be
first submitted by the Contractor with detailed measurements and thereafter only the
Engineer or his
organization representative shall carry out joint verifications or otherwise on record in the
measurements book before certification of the bills.
Payment on account for amount admissible shall be made on the Engineer certifying the
sum to which the Contractor is considered entitled by way of interim payment for all the
Work executed, after deducting there from the amount already paid, the security
deposit/retention money and such other amounts as may be deductible or recoverable in
terms of the contract.
No interim payment will be admitted until such time the Contractor have fully complied
with the requirement of the Condition 84 concerning submission and approval of Network
Schedule for the Works, as detailed in Condition 83. A fixed sum shall be held in
abeyance at the time of next interim payment for non attainment of each milestone in the
Network and shall be released only on attainment of the said milestone.
96. Modification of Interim Certificate.
An interim certificate given relating to Work done or material delivered may be modified
or corrected by any subsequent interim certificate or by the final certificate. No certificate
of the Engineer supporting an interim payment shall of itself be conclusive evidence that
any Work or materials to which it relates is / are in accordance with the contract.
97. Income Tax
The Contractor shall pay Indian Income Tax on all payments made to him under the
Contract, other than reimbursements made to him by the Corporation to cover payment by
Contractor of minor custom duties etc., or any other payment which the Contractor may
make on the Corporation’s behalf. Under the provisions of sec. 194-C of the Indian
Income Tax Act, the Corporation if required to deduct Tax with surcharge at source at
prevailing rates from the gross amount of each bill submitted. Any expatriate site staff or
staff not normally residents of India, employed by the Contractor shall pay personal
Income Tax on all money earned and paid in India. The Contractor shall perform such
duties in regard to such deductions thereof as may be imposed on him by such laws and
regulations.
Signature of Tenderer No. of Corrections Signature of NMMC Official
63
98. Payment of Taxes
The contractor shall pay all the taxes directly to respective organizations & to the
Government. The corporation shall not take any responsibility for any kind of tax payment
to the Government or semi Government bodies at any point of time.
The prices quoted by the Contractor shall include all customs duties, import duties, excise
duties, business taxes, income and other taxes that may be levied in accordance to the laws
and regulation in-force on the Contractor’s Equipment, materials, supplies (permanent,
temporary and consumables) to be used on or furnished under the contract and on the
services to be performed under the contract nothing in the contract shall relieve the
contractor from his responsibility to pay any tax that may be levied or on profits made by
him in respect of the contract.
The contractor shall perform such duties in regard to such deductions thereof as may be
imposed on him by such laws and regulations.
Charges on account of Octroi, terminal or Sales Tax and other duties on material obtained
for the Works from any source including the tax applicable as per Maharashtra Sales Tax
Act on the transfer of property in the goods involved in the execution of Works contract
(re-enacted) Act, 1991 etc.
shall be borne by the Contractor. Under the provisions of the Maharashtra Sales Tax act,
the Corporation is required to deduct Turnover Tax at source at the rates prevailing at the
time of payments.
The contractor shall submit form – 31 or such other forms as are prescribed under the said
act which is required to be produced by the principle employer in the events of any notice
by the Sales Tax Department within one month of issue of letter of acceptance.
99. Deduction of Contract Sales Tax / Turnover tax
The Contractor are required to produce their registration for contract sales tax/ turnover tax
to the department before releasing the 1st R.A. bill for the Work executed by them, failing
which, no payment shall be released.
100. Provisional Sums
(1) “Provisional sum” means a sum included in the contract and so designated in
the Bill of Quantities for the execution of Work or supply of goods, materials or services
or for contingencies, which sum may be used, in whole or in part, or not at all, at the
direction and discretion of the Engineer. The contract price shall include only such
amounts in respect of the Work, supply or service to which such provisional sum
relate as the Engineer shall approve or determine in accordance with this
clause.
(2) In respect of every provisional sum the Engineer shall have power to order to
execute the Work, including goods, materials or services to be supplied by the
Contractor. The contract price shall include the value of such Work executed
or such goods, material or services supplied determined in accordance with Clause
No. 102.
(3) The Contractor shall produce all quotations, invoices, vouchers and accounts
or receipts in connection with expenditure in respect of provisional sums.
Signature of Tenderer No. of Corrections Signature of NMMC Official
64
101. Rates for Excess in Items
Quantities shown in the tender are approximate and no claim shall be entertained for
quantities of work executed being either more or less than those entered in the tender or
estimate. For purpose of this contract, the variations/deviations in carrying out the items of
work shall not exceed plus or minus 25 percent of contract sum. The deviation/variation in
the quantity of individual items shall not be taken as deviation or variation in the contract.
The difference between the total value of the work done and the Contract sum as
defined above will be only be considered for deviation/variation.
The Contractor shall arrive the rates after carefully preparing the rate analysis taking into
consideration site conditions. For increase upto 25 percent over the quantity shown in the
bill of quantities shall be paid, at the rate mentioned in the bill of quantities. However, if
the quantity increases beyond 25 percent of quantity shown in the bill of quantities the
excess quantity beyond 25 percent shall be priced as under:
The rate shall be worked out based on schedule rate with Contractor’s quoted percentage or
current direct schedule of rates without Contractor’s quoted percentage, which ever is less.
102. Rates for Extra Items:
Rates for such additional altered or, substituted work shall be determined as follows:
i) If rate for additional, altered or substituted item of Work is specified in the bill of
quantities and rats, the Contractor shall carry out the additional, altered or
substituted item at the same rate, subject to 100 above.
ii) If rate for any additional, altered or substituted item of Work is not included in the
bill of quantities and rates, such item of work shall be carried out at the relevant
Corporation’s schedule of rates (Public works Department and M.J.P. schedule of
rates for Thane District) prevailing at the time of execution of extra work (Quoted
percentage will not be applicable)
iii) If the rate for any additional, altered or substituted item of Work cannot be
determined in the manner specified in (i) & (ii) above, or the rate so determined is
found to be unreasonable, then the Contractor will be paid at such fair and
reasonable rates as Worked out by the Engineer on the basis of material, labour and
operations of construction equipment required to execute the item and allowing 10
percent to cover profits and overhead charges.
iv) The Contractor shall submit to the Engineer his detailed rate analysis for carrying
out variation duly supported with supported with quotations and other supporting
documents within 7 days of written instruction to carry out variations. If the
Contractor’s quotation is unreasonable, the Engineer orders the variation and makes
change to the contract price which is based on his own forecast of the variations on
the Contractor’s cost. In case, the rates decided by the Engineer are not acceptable
to the Contractor, he shall continue with the work and maintain contemporary
records of actual expenses on day-to-day basis with joint assessment/verification.
The Contractor is not entitle for payment of actual expenses as per joint records
added with 10% for profit and overheads. Disagreement with the rate fixed by the
Engineer shall be informed by the Contractor before commencing the work of
variations, failing which the rate fixed by the Engineer shall be final and binding on
the parties to contract.
Signature of Tenderer No. of Corrections Signature of NMMC Official
65
103. Overpayment and Underpayment:
Whenever any claim for the payment of a sum to the Corporation rises out of or under this
contract against the Contractor the same may be deducted by the Corporation from any
sum then due or which at any time thereafter may become due to the Contractor under this
contract and failing that under any contract with the Corporation or from any other sum
due to the Contract from the Corporation (which may be available with the Corporation) or
from his security deposit/retention money, or he shall pay the claim on demand.
The Corporation reserves the right to carry out post payment audit the technical
examination of the final bill including all supporting voucher, abstracts etc. The
Corporation further reserves the right to enforce recovery of any over payment when
detected.
It as a result of such audit and technical examination any overpayment is discovered in
respect of any Work done by the Contractor or alleged to have been done by him under the
Contract, it shall be recovered by the Corporation from the Contractor by any or all of the
methods prescribed above or if
underpayment is discovered the amount shall be duly paid to the Contractor by the
Corporation.
Provided that the aforesaid right of the Corporation to adjust overpayment against amount
due to the Contractor under any other contract with Corporation shall not extend beyond
the period of two years form the date of payment of the final bill or in case the final bill is
a “Minus” bill, from the date of the amount payable by the Contractor under the “Minus”
bill is communicated to the Contractor.
Any amount due to the Contractor under this contract for underpayment may be adjusted
against amount then due or which may at any time thereafter become due before payment
is to the Contractor, from him to Corporation on any other contract or account whatsoever.
104. Payment of Final Bill:
Final joint measurement along-with the representatives of the Contractor should be taken
recorded and signed by the Contractors. Contractor should submit the final bill within 1
month of physical completion of the Work.
If the Contractor fails to submit the final bill within 1 months, the Corporation staff will
prepare the final bill based on the joint measurement within next 3 months.
Engineer’s decision shall be final in respect of claims for defect and pending claims against
Contractors.
No further claims should be made by the Contractor after submission of the final bill and
these shall be deemed to have been waived and extinguished. Payment of those items of
the bills in respect of which there is no dispute and of items in dispute, for quantities and
rates as approved by the Commissioner shall be made within a reasonable period as may be
necessary for the purpose of verification etc.
After payment of the final bill as aforesaid has been made, the Contractor may, if he so
desires, reconsider his position in respect of a dispute portion of the final bill and if he fails
to do so within 84 days, his disputed claim shall be dealt with as provided in the contract.
Signature of Tenderer No. of Corrections Signature of NMMC Official
66
105. Receipts to be signed in Firm’s Name by any One of the Partners:
Every receipt for money which may become payable or for any security which may
become transferable to the Contractor under these present shall, if signed in the partnership
name by any one of the partners, be a good and sufficient discharge to the Commissioner
and Corporation in respect of the money or security purporting to be acknowledge thereby,
and in the event of death of any of the partners during the pendency of this contract, it is
hereby expressly agreed that every receipt by any one of the surviving partners shall, if so
signed as aforesaid, be good and sufficient discharge as aforesaid provided that noting in
this clause contained shall be deemed to prejudice or effect any claim which the
Commissioner or the Corporation may hereafter have against the legal representatives of
any partners so doing or in respect of any breach of any of the conditions thereof, provided
also that nothing in this clause contained shall be deemed to prejudice or affect the
respective rights or affect the respective rights or obligations of the Contractor and of the
legal representative of any deceased Contractors interest.
106. Price Variation Clause
Price variation clause shall be applicable as per condition of contract as attached.
Signature of Tenderer No. of Corrections Signature of NMMC Official
67
PART – VI
TERMINATION OF CONTRACT AND SETTLEMENT OF DISPUTES
107. Cancellation of Contract in Full or in Part:
If the Contractor:
(a) At any time makes default in proceeding with the Work with due diligence and
continues to do so after notice in writing of fourteen days from the Engineer; or
(b) Commits default in complying with any of the terms and conditions of contract and
does not remedy it within fourteen days after a notice in writing is given to him in
that behalf by the Engineer, or
(c) Fails to complete the Works or items with individual dates of completion, on or
before the data(s) of completion, and does not complete them within the period
specified in a notice given in written in that behalf by the Engineer, or
(d) Shall offer or give or agree to give to any person in Corporation’s Service or to any
other person on his behalf any gift or consideration of any kind as an inducement or
reward for doing or forbearing to do or for having done or forborne to do any act in
relation to the obtaining or execution of this or any other contract for the
Corporation, or
(e) Shall obtain a contract with the Corporation as a result of ring tendering or other
non-bona-fide methods of competitive tendering or
(f) Being an individual or a firm, any partner thereof, shall at any time be adjudged
insolvent or have a receiving order or order for administration of his estate made
against him or shall take any proceedings for liquidation or composition (other than
voluntary liquidation for the purpose of amalgamation or reconstruction) under any
insolvency act for the time being in force or make any conveyance of assignment of
his effects or composition or arrangement for the benefit of his creditors or purport
so to do, or if any application be made under any insolvency Act for the time being
in force for the sequestration of his estate or if a trust deed be executed by him for
his creditors, or
(g) Being a company, shall pass a resolution or the court shall make an order for the
liquidation of his affairs, or a receiver or a manager on behalf of the debenture
holders shall be appointed or circumstances shall arise which entitle the Court or
debenture holders to appoint a receiver or a Manager, or
Signature of Tenderer No. of Corrections Signature of NMMC Official
68
(h) Shall suffer an execution being levied on his goods and allow it to be continued for
a period of 21 days, or Assigns, transfers, sublets (engagement of labour on a piece
Work basis or labour with materials not to be incorporated in the Work, shall not be
deemed to be sub-letting) or attempts to assign, transfer or sub-let the entire Works
or any portion thereof without the prior written approval of the Commissioner, the
Commissioner may, without prejudice to any other right or remedy which shall
have accrued or shall accrue thereafter to the Corporation by written notice cancel
the contract as a whole or only such items of Work in default from the contract.
(i) In the case of abandonment of the work owing to serious illness or death of
the Contractor.
108. Action when whole of Security Deposit is to be Forfeited:
In the cases mentioned in above clause No. 107 the Engineer, on behalf of the corporation
shall have power to adopt any of the following forces, as he may deem best suited to the
interest of the corporation.
(a) To rescind the contract (for which rescission notice in writing to the Contractor under the
head of Engineer shall be conclusive evidence) and in that case the security deposit of the
Contractor shall stand forfeited and be absolutely at the disposal of Corporation.
(b) To carry out work or any part of the departmentally debiting the Contractor with the cost
of the Work, expenditure incurred on tools and plan and charges on additional supervisory
staff including the cost of Work charge establishment employed for getting the unexecuted
part of the Work completed and crediting him with the value of the work done
departmentally in all respects in the same manner and at the same rates as if it had been
carried out by the Contractor under the terms of his contract. The certificate of the
Engineer as to the costs and other allied expenses so incurred and as to the value of the
work so done departmentally and shall be final and conclusive against the Contractor.
(c) To order that the Work of the Contractor be measured up and to take such part there of as
shall be on executed out of his hands, and to give it to another Contractor to complete, in
which case all expenses incurred on advertisement
for fixing a new contracting agency, additional supervisory staff including the cost of
Work charge establishment and a cost of Work executed by the new contract agency will
be debited to the Contractor and the value of the work done or executed through a new
Contractor shall be credited to the Contractor in all respects and in the same manner and at
the same rates as if it had been carried out by the Contractor under the terms of this
contract. the certificate of the Engineer as to all the cost of the work and other expenses
incurred as aforesaid for or in getting the unexecuted as aforesaid for or in getting the
unexpected work done by the new Contractor and as to the value of the Work so done shall
be final and conclusive against the Contractor.
Signature of Tenderer No. of Corrections Signature of NMMC Official
69
In case the contract shall be rescinded under clause (a) above the Contractor shall not be
entitled to recover or be paid, any sum for any work therefore actually performed by him
under this contract unless and until the Engineer shall have certified in writing the
performance of such work and the amount payable to him in respect their of and he shall
only be entitled to be paid the amount so certified in the event of either to the courses
referred to in clauses (b) or (c) being adopted and the cost of the work executed
departmentally or through a new Contractor and other allied expenses exceeding the value
of such work credited to the Contractor the amount of excess shall be deducted from any
money due to the Contractor, by corporation under the Contractor otherwise howsoever or
from his security deposit or the sale proceeds there of provided, however, that contractor
shall have no claim against corporation even if the certified vale of work done
departmentally or through a new Contractor exceed the certified cost of such work and
allied expenses, provided always that which ever of the three courses mentioned in clauses
(a), (b) or (c) is adopted by the Engineer, the Contractor shall have no claim to
compensation for any loss sustained by him by materials, or entered into any engagements,
or made any advance on account of or with a view to the execution of the work or the
performance of the contract.
109. Action When the Progress of any Particular Portion of the work is Unsatisfactory:
If the progress of any particular portion of the work is unsatisfactory the conditions
mentioned in clause 108(b), be entitled to take action under clause after giving the
Contractor 14 days notice in writing. The Contractor will have no claim for compensation,
for any loss sustained by him owing to such action.
110. Contractor Remains Liable to Pay Compensation if Action not Taken Under Clause
108 and 109:
In any case in which any of the powers conferred upon the Engineer by clause 108 & 109
hereof shall have become exercisable and the same shall not have been exercised the non
exercise there of shall not constitute a waiver of any of the conditions thereof and such
powers shall not withstanding the exercisable in the event of any future case of default by
the Contractor for which under any clause hereof he is declared liable to pay compensation
amounting to the whole of this security deposit and the liability of the Contractor for past
and future compensation shall remain unaffected.
Signature of Tenderer No. of Corrections Signature of NMMC Official
70
111. Power to take possession of or require removal or sell Contractors plant:
In the event of Engineer taking action under sub clause (a) or (c) clause 108, he may if he
so desires, take possession of all / any tools and plant, materials and store in or upon the
Work of the site thereof or belonging to the Contractor, or procured by him and intended to
be used for the execution of the Work or any part thereof paying or allowing for the same
in account at the contract rates or in the case of contract rates not being applicable at
current market rates to be certified by the Engineer whose certificate thereof shall be final.
In the alternative the Engineer may after given notice in writing to the Contractor or his
clerk of the Work, foreman or other authorized agent requires him to remove such tools
and plant, material, or stores from the premises within a time to be specified in such notice
and in the event of the Contractor failing to comply with any such requisition, the Engineer
may remove them at the Contractor’s expense or sell them by auctions or private sale on
account of the Contractor and at his risk in all respect and the certificate of the Engineer as
to the expenses of any such removal and the amount of the proceeds and expenses on any
such sale shall be final and conclusive against the Contractor.
112. No Interest for Delayed Payments Due to Disputes etc.
It is agreed that the Corporation of or its Engineer or officer shall not be liable to pay any
interest or damage with respect to any moneys or balance which may be in its or its
Engineer’s or officer’s hands owing to any dispute or difference or claim or
misunderstanding between the corporation of or its Engineer or officer on the one hand and
the Contractor on the other, or with respect to any delay on the part of the corporation of
Navi Mumbai or its Engineer or officers in making periodical or final payments or in any
other respect whatever.
Payment to the Contractor of the amount due under each of the interim payment certificate
issued by the Engineer shall be made by the Corporation within 45 (Forty Five) days if
such certificate being delivered. If the corporation makes late payment, the contractor is to
be paid interest on the late payment in the next payment. Interest shall be calculated from
the date by which the payment should have been made upto the date when the late payment
is made at 6% per annum. It is a term under this contract that payment of interest in excess
of 6% is barred on any amount payable to the contractor on any account.
Signature of Tenderer No. of Corrections Signature of NMMC Official
71
It is distinctly understood and agreed between the parties hereto that payment for work
already executed by the Contractor is not a condition precedent under this contract for the
execution of the remaining work.
113. Jurisdiction:
In case of any claim, dispute or difference arising in respect of a contract, the cause of
action thereof shall be deemed to have arisen in Navi Mumbai and all legal proceedings in
respect of any such claim, dispute or difference shall be instituted in a competent court in
the City of Navi Mumbai only.
114. Finality of Decision of Non-Arbitrability:
SETTLEMENT OF DISPUTES
If a dispute/disputes of any kind whatsoever arises between the Contractor and Engineers
representative the same shall be referred to the Engineer for his decision with detailed
justification. Such reference shall be stated that it is in pursuance to this clause for review
and giving decision by the Engineers. The Engineer shall give his decision within 14 days
of receipt of notice. If either party is not satisfied with the decision of the Engineer or the
Engineer fails to give the decision within the period of 14 days from the date of receipt of
notice under this clause, such a dispute may be referred to Arbitration as per Clause No.
115.
115. Arbitration:
Except where, otherwise provided for in this contract, all questions and disputes relating to
the meaning of instruction hear in before mentioned or as to any other question, claim,
right, matter of handing whatsoever, if any arising out of or relating to this contract,
specification, estimates, instructions, orders or these conditions or otherwise concerning
the works, or the execution or failure to execute the same where arising during the progress
of the work or after completion or abandonment thereof of any matter directly or indirectly
connected with this agreement shall be referred to the sole Arbitration of the Municipal
Commissioner of Navi Mumbai Corporation, C.B.D., Navi Mumbai and if the Municipal
Commissioner is unable or unwilling to act as such, then the matter in dispute shall be
referred to sole Arbitration or such other person appointed by the Municipal commissioner
who is willing to act as such Arbitrator. In case, the Arbitrator so appointed is unable to act
for any reasons, the Municipal Commissioner in the event of such inability, shall appoint
another person to act as Arbitrator in accordance with the terms of the contract. Such
person shall be entitled to proceed with the reference from the state at which it was left by
his predecessors. It is also a term of this contract that no person other than a person
appointed by the Municipal Commissioner as aforesaid should act as an Arbitrator.
As aforesaid the provisions of the arbitration and conciliation act 1996 or any statutory
modification or Reenactment there of and the rules made there under and for the time
being in force shall apply to the arbitration proceedings under this clause.
116. Laws Governing the Contract:
This contract shall be governed by the Indian Laws for the time being in force.
Signature of Tenderer No. of Corrections Signature of NMMC Official
72
PART- VII
WORK COMPLETION & DEFECT LIABILITY
117. Clearance of Site on Completion:
Upon the issue of any Taking over certificate, the contractor shall clear away and remove
from that part of the site to which such taking over Certificate relates all Contractor’s
equipment, surplus materials, rubbish and temporary works of every kind, and leave such
part of the site and works clean and in a Workmen like condition to the satisfaction of the
Engineer. If the Contractor does not clear the site within 15 days all material will be
confiscated and no compensation shall be paid and the site will be cleared at risk and cost
of the Contractor.
118. Submissions of Final Completion Drawings:
On completion of the Work, the Contractor shall furnish free of cost 1 set of R.T.F. of final
completion drawings and 6 bound sets of copies of drawings, showing all the details
checked and signed by the Engineer within 2 months of completion of Works. The
payment of final bill shall be made to the Contractor after receipt of above sets. In case the
Contractor fails to submit the completion drawings, a compensation at the rate of Rs.
5000/- per drawing shall be recovered from the final bills.
119. Completion Certificate:
(1) As soon as Work is completed, the Contractor shall give notice of such completion to the
Engineer and within 28 (Twenty-eight) days of receipt of such notice the Engineer shall
inspect the works and shall furnish the Contractor with a certificate of completion
indicating (a) the date of completion (b) the defects to be rectified by the Contractor,
and/or (c) items for which payment shall be made at reduced rates.
When separate periods of completion have been specified for items or groups of items, the
Engineer shall issue separate completion certificates for such items or groups of items. No
certificate of completion shall be issued, nor the works be considered to be complete till
the Contractor shall have removed from the premises on which the works has been
executed, all scaffolding, sheds and surplus materials, except such as required for
rectification of defects, rubbish and all huts and sanitary arrangements required for his
workers on the site in connection with the execution of works as shall have been erected by
the Contractor or the Workmen and cleaned all dirt from all parts of building(s) in,
upon or about which the work has been executed or of which he may have had possession
for the purpose execution thereof and cleaned floors, gutters and drains, eased doors and
sashes, oiled and fastenings, labeled the keys clearly and handed them over to the Engineer
or his representative and made the whole premises fit for immediate occupation or use to
the satisfaction of the Engineer. If the Contractor shall fail to comply with any of the
requirements of this Condition as aforesaid, on or before the date of completion of works,
the Engineer may at the expense of the Contractor fulfill such requirements and dispose of
all the surplus material and rubbish etc. as he deems fit and the contractor shall have no
claims in respect of any such materials except for any sum actually realized by the sale
thereof less the cost of fulfilling such requirement is more than the amount realize on such
disposal as aforesaid, the Contractor shall forthwith on demand pay such excess.
Signature of Tenderer No. of Corrections Signature of NMMC Official
73
The Contractor’s notice of completion as aforesaid shall have to be accompanied with one
set of tracings of final completion drawings on RTF and six bound sets of copies of as built
drawings, failing which the notice shall be deemed to have not been issued at all.
(2) It at any time before completion of the entire work, items or groups of items for which
separate periods of completion have been specified, have been completed, the Engineer
with the consent of the Contractor takes possession of any part or parts of the same (any
such part or parts being hereinafter in this condition referred to as “the relevant part”) then
not-withstanding anything expressed or implied elsewhere in this contract.
(a) Within 28 days (Twenty-eight days) of date of completion of such items or a group of item
or possession of the relevant part the Engineer shall issue a completion certificate for the
relevant part provided the Contractor fulfills his obligation for the relevant part as in sub-
para (1) above.
(b) The defects liability period in respect of such items and relevant part shall be deemed to
have commenced from the certified date of completion of such items or relevant part as the
case may be.
(c) For the purpose of ascertaining compensation for delay under Clause No. 88 in respect of
any period during which the Works are not completed the relevant part shall be deemed to
form a separate item or group, with date of completion as given in the contract or as
extended under Clause No. 80 and actual date of completion as certified by the Engineer
under this condition.
(3) If any part of the work shall have been substantially completed and shall have satisfactorily
passed any final test that may be prescribed under the contract, the Engineer may issue a
certificate of completion in respect of that part of the Works before completion of the
whole works and upon the issue of such certificate, the Contractors shall be deemed to
have undertaken to complete any outstanding works in that part of the Works during the
period of maintenance.
120. Taking Over of work:
Corporation will take over the Work at any stage whenever required in the interest of
public by giving 10 days notice to the Contractor.
121. Defects Liability Period:
The Contractor shall be responsible to make good and remedy at his own expenses within
such period as may be stipulated by the Engineer any defects which may developer be
noticed before the expiry of the period mentioned in the Detailed Tender Notice hereto
from certified date of completion and intimation of which has been sent to the Contractor
within 7 days of expiry of the said period by letter sent by hand delivery or by registered
post.
Signature of Tenderer No. of Corrections Signature of NMMC Official
74
122. Liability for Defects or Imperfections and Rectification Thereof:
If it shall appear to the Engineer or to his representative at any time during construction or
reconstruction or during the defects, liability period, that any work has been executed with
unsound, imperfect or unskillful workmanship or that any material or article provided by
the Contractor for execution of thereof the work is unsound or of a quality inferior to that
contracted for, or otherwise, not in accordance with the Contract, or that any defect,
shrinkage or other faults have appeared in the Work arising out of defective or improper
materials or workmanship, the contractor shall, upon receipt of notice in writing in that
behalf from the Engineer forthwith rectify or remove or reconstruct the work so specified
in whole or part, as the case may require or, as the case may be, and/or remove the
materials or articles so specified and provide other proper and suitable materials or articles
at his own expenses notwithstanding that the same may have been inadvertently passed,
certified and paid for, and in the event of his failing to do so within the period to be
specified by the Engineer in his notice aforesaid the Engineer may rectify or remove and
re-execute the work and/or remove and replace with others the materials or articles
complained of, as the case may be, by other means at the risk and cost of the Contractor.
In case of repairs and maintenance Work, splashes and droppings from whitewashing,
painting etc. shall be removed and surfaces cleaned simultaneously with completion of
these items of work in individual rooms, quarters or premises etc. where the work is done,
without waiting for completion of all other items of work in the contract. In case the
Contractor fails to comply with requirement of this condition, the Engineer shall have the
right to get the work done by other means at the risk and cost of the Contractor.
The Engineer shall give three days notice in writing to the Contractor before taking such
action.
The Engineer reserves the right to decide the rates and prices of the works as executed by
other means at the risk and cost of the Contractor.
The Cost and expenses thereby incurred on the works and also such penalty as the
Engineer may impose for such wrongful conduct of the Contractor (which penalty, the
Engineer shall be competent to impose and against the imposition of which or the amount
thereof by the Engineer an appeal shall lie only to the Commissioner within seven days of
the order in that behalf of the Engineer and the decision of the Commissioner shall be final
and binding upon the Contractor) may be deducted from any money due or to become due
to the Contractor, under this or any other contract between the contractor and the
Corporation.
Signature of Tenderer No. of Corrections Signature of NMMC Official
75
123. Maintenance:
The Contractor shall maintain the good condition of the works for a period as specified in
Contract document, after the completion of work without any extra cost to corporation
irrespective of the designs, standards and specification. The Contractor shall get the defects
rectified with required material and maintain the works in good condition throughout the
year. 5 percent amount of the total work done shall be withheld from running account bill
for the period specified in the Contract document from the date of completion of Work as
maintenance charges of maintaining and keeping the Works in good condition This 5
percent amount withheld towards maintenance charges shall be allowed to be replaced with
Bank Guarantee or other recognized forms at intermediate stage, if so, desired in writing.
This maintenance charges shall be in addition to security deposit.
On completion of the work in all respects, necessary certificates will be issued by the
Engineer and the defect liability period will be conducted from the date of issue of such
certificates.
All damage during execution shall be made good by the Contractor at his cost. He will be
responsible for any damage to the Works during construction and guaranteed maintenance
period and no separate payment will be made for restoring such damages.
Defective Work is liable to be rejected at any stage. The Contractor on no account can
refuse to rectify defects merely on reasons that further Work has been carried out. No extra
payments shall be made for such rectification.
124. Defects Liability Certificate:
The Contract shall not be considered as completed until a Defects Liability Certificate shall
have been signed by the Engineer and delivered to the Contractor, stating the date on
which the Contractor shall have completed his obligations to execute and complete the
works and remedy any defects therein to the Engineer’s satisfaction. The defects Liability
Certificate shall be given by the Engineer within 28 days after the expiration of the latest
such period, or as soon thereafter as any works instructed, pursuant to Clause 121 and have
been completed to the satisfaction of the Engineer, Provided that the issue of the Defect
Liability Certificate shall not be a condition precedent to payment to the Contractor of the
Retention Money.
125. Unfulfilled Obligations:
Notwithstanding the issue of the Defects Liability Certificate the Contractor and the
Corporation shall remain liable for the fulfillment of any obligation incurred under the
provisions of the contract prior to the issue of the Defects Liability Certificate is issued
and, for the purposes of determining the nature and extent of any such obligation, the
contract shall be deemed to remain in force between the parties to the Contract.
Notwithstanding the issue of the Defects Liability Certificate the Contractor and the
Corporation shall remain liable for the fulfillment of any obligation incurred under the
provisions of the Contract prior to the issue of the Defects Liability Certificate is issued
and, for the purposes of determining the nature and extent of any such obligation, the
Contract shall be deemed to remain in force between the parties to the Contract.
Signature of Tenderer No. of Corrections Signature of NMMC Official
76
126. Refund of Security Deposit:
The amount of security deposit lodged by a Contractor shall be refunded along with the
payment of the final bill, or after the expiry of the defect liability period which ever is later
unless the Engineer is of the opinion that in order to safeguard against defects and pending
claims against the Contractor it is necessary to retain more amount retained as retention
money.
127. Mobilization Advance:
The Employer will pay mobilization advance to the Contractor if the same is requested by
the Contractor in writing within three months of the date of notice to proceed with the
work, towards costs of mobilization in respect of the Works in a lump sum amount
equivalent to 5 (five) percent of the Contract price. Payment of the advance will be due
after the recommendations of the Engineer’s Representative & Certification by the
Engineer after:
(i) Execution of the form of agreements by the parties thereto
(ii) provision by the Contractor of one or more Bank Guarantees by Nationalized Bank,
State Bank of India or commercial Banks promoted by all India Financial
Institutions including HDFC from the Bank’s branch in Mumbai, in an aggregate
amount equal to the advance loan, such Bank Guarantee / Guarantees to remain
effective until the advance loan, (part of the advance loan in case the Contractor has
submitted more than one Guarantee) has been repaid by the Contractor out of the
current earnings and certified by the Engineer. A form of Bank Guarantee
acceptable to the Employer is indicated in this Tender Document.
The advance loan shall be used by the Contractor exclusively for mobilization in
connection with the Works. Should the Contractor misappropriate any portion of
the advance loan, it shall become due and payable immediately and no further loan
will be made available to the Contractor thereafter.
The mobilization advance shall carry simple interest of 12% per annum subject to
the condition that the progress of the work is as per agreed programme. In case of
Contractor not maintaining the progress of the work as per the agreed programme,
the interest on mobilization advance shall be levied at 15% per annum for the
period in which the progress in not maintained. In case the progress is made good
as per the programme the rate of interest shall be again at 12% per annum.
127a. Additional Mobilization Advance:
The Employer will pay Additional mobilization advance to the Contractor if the same is
requested by the Contractor in writing within three months of the date of notice to proceed
with the work, towards costs of mobilization in respect of the Works in a lump sum
amount equivalent to 5 (five) percent of the Contract price. Payment of the advance will be
due after the recommendations of the Engineer’s Representative & Certification by the
Engineer after:
Signature of Tenderer No. of Corrections Signature of NMMC Official
77
(i) execution of the form of agreements by the parties thereto
(ii) provision by the Contractor of one or more Bank Guarantees by Nationalized Bank,
State Bank of India or commercial Banks promoted by all India Financial
Institutions including HDFC from the Bank’s branch in Mumbai, in an aggregate
amount equal to the advance loan, such Bank Guarantee / Guarantees to remain
effective until the advance loan, (part of the advance loan in case the Contractor has
submitted more than one Guarantee) has been repaid by the Contractor out of the
current earnings and certified by the Engineer. A form of Bank Guarantee
acceptable to the Employer is indicated in this Tender Document.
The advance loan shall be used by the Contractor exclusively for mobilization in
connection with the Works. Should the Contractor misappropriate any portion of
the advance loan, it shall become due and payable immediately and no further loan
will be made available to the Contractor thereafter.
The mobilization advance shall carry simple interest of 12% per annum subject to
the condition that the progress of the work is as per agreed programme. In case of
Contractor not maintaining the progress of the work as per the agreed programme,
the interest on mobilization advance shall be levied at 15% per annum for the
period in which the progress in not maintained. In case the progress is made good
as per the programme the rate of interest shall be again at 12% per annum.
128. Recovery of Advance :
The mobilization advance, the additional mobilization and the accrued interest shall be
repaid with percentage deduction from the interim payments certified by the Engineer
under the Contract. Deductions shall commence in the next interim Payment Certificate
following that in which the total of all such payments to the Contractor has reached 15% of
the Contract Price less Provisional Sums and shall be recovered by the time 90% of the
value of work is completed. The mobilization advance and the interest shall be recovered
in equal installments from interim payments. The amount of such installments shall be
calculated as per the time of taking of such advances and time of completion of 90% of the
work. Failing such repayment the outstanding advance / advances by that date shall be
recovered by encashment of the respective bank guarantee / guarantees mentioned above.
The Contractor may,
at his option, repay the advance loan earlier by increasing the percentage rate of deduction
indicated above. If the Contractor furnishes more than one Bank Guarantee, the guarantees
will be released by the Employer one by one in such a manner that the total amount of
Bank Guarantee left in hand with the Employer will be sufficient to cover the outstanding
amount of advance and likely interest thereon.
Signature of Tenderer No. of Corrections Signature of NMMC Official
78
ANNEXURE ‘A’
(See Condition 24)
SAFETY PROVISIONS
1. Suitable scaffolds shall be provided for workman for all that cannot safety be done from
the ground, or from solid construction except such short period work as can be done safely
from ladders. When a ladder is used an extra mazdoor shall be engaged for holding the
ladder and if the ladder is used for carrying materials as well, suitable footholds and
handholds shall be provided on the ladder and the ladder shall be given an inclination not
steeper than ¼ to 1( ¼ horizontal and 1 vertical).
2. Scaffolding or staging more than 3.25 meters above the ground or floor, swung or
suspended from an overhead support or erected with stationary support, shall have a guard
rail properly attached, belted braced and other wise secured at least 1 meter high above the
floor or platform of such scaffolding or staging and extending along the entire length of the
outside and ends thereof with only such openings as may be necessary for the delivery of
materials. Such scaffolding or staging shall be so fastened as to prevent it from swaying
from the building or structure.
3. Working platform, gangways, and stairways shall be so constructed that they do not sag
unduly or unequally, and if height of a platform or gangway or stairway is more than 3.25
meters above ground level or floor level, it shall be closely boarded, have adequate width
and be suitably fenced as described in 2 above.
4. Every opening in floor of a building or in a working platform shall be provided with
suitable means to prevent fall of persons or materials by providing suitable fencing or
railing with a minimum height of 1 meter.
5. Safe means of access shall be provided to all working platform and other working places.
Every ladder shall be securely fixed. No portable single ladder shall be over 9 meters in
lengths. Width between side rails in a rung ladder shall in no case be less than 30 cm for
ladder upto and including 3 meters in length. For longer ladders this width shall be
increased by at least 6 mm for each additional 30 cm of length. Uniform step spacing shall
not exceed 30cm.
Adequate precaution shall be taken to prevent danger form electrical equipment. No
materials on any of the sites shall be so stacked or places as to cause danger or
inconvenience to any person or the public. The Contractor shall provide all necessary
fencing and lights to protect public from accidents and shall be bound to bear expenses of
defense of every suit, action or other
proceeding at law that may be brought by any person for injury sustained owing to neglect
of the above precautions and to pay any damages and costs which may be awarded in any
such suit, action or proceedings to any such person or which may with the consent of the
Contractor be paid to compromise any claim by any such person.
Signature of Tenderer No. of Corrections Signature of NMMC Official
79
Excavation and Trenching:- All trenches, 1.5 metres or more in depth, shall at all times be
supplied with least one ladder for each 30 meters in length or fraction thereof, ladder shall
be extended from bottom of trench to at least 1 metre above surface of the ground sides of
a trench which is 1.5 meters or more in depth shall be stepped back to give suitable slope,
or securely held by timber bracing, or by other suitable means so as to avoid the danger of
sides collapsing. Excavated material shall not be placed within 1.5 meters of edge of
trench or half or depth of trench, whichever is more. Cutting shall be done from top to
bottom. Under no circumstances shall undermining or under cutting be done.
6. Demolition:
Before any demolition work is commenced and also during the process of the work.
(a) All roads and open areas adjacent to the work site shall either be closed or suitably
protected.
(b) No electric cable or apparatus which is liable to be a source of danger used by
operator shall remain electrically charged.
(c) All practical steps shall be prevent danger to persons employed, from risk of fire or
explosion, or flooding. No floor, roof or other part of a building shall be so
overloaded with debris or materials as to render it unsafe.
7. All necessary personal safety equipment as considered adequate by the Engineer shall be
available for use of persons employed on the site and maintained in a condition suitable for
immediate use, and the Contract shall take adequate steps to ensure proper use of
equipment by those concerned.
(a) Workers employed on mixing asphaltic material, cement and lime mortars/concrete
shall be provided with protective footwear, handgloves and goggles.
(b) Those engaged in handling any material which is injurious to eyes shall be
provided with protective goggles.
(c) Those engaged in welding works shall be provided with welder’s protective eye-
shields.
(d) Stone breakers shall be provide with protective goggles and protective clothing and
seated at sufficiently safe intervals.
(e) When worker are employed in sewers and manholes, which are in use, the
Contractor shall ensure that manhole cover are opened and manholes are ventilated
at least for an hour before workers are allowed to get into them. Manholes so
opened shall be cordoned off with suitable railing and provided with warning
singles or boards to prevent accident to public.
(f) The Contractor shall not employ men below the age of 18 and women on the work
of painting with products containing lead in any form. Whenever men above the
age of 18 are employed on the work of laid painting the following precautions shall
be taken ;
(g) No paint containing lead of lead products shall be used except in the form of paste
or ready made paint.
Signature of Tenderer No. of Corrections Signature of NMMC Official
80
(i) Suitable face masks shall be supplied for use by workers when paint is
applied in the form of spray or surface having lead paint dry rubbed and
scrapped.
(ii) Overalls shall be supplied by the Contractor to workmen and adequate
facilities shall be provided to enable working painter to wash during and on
cessation of work.
8. When work is done near any place where there is risk of drowning, all necessary
equipment shall be provided and kept ready for use and all necessary steps taken for
prompt rescue of any person in danger and adequate provision made for prompt first aid
treatment of all injuries likely to be sustained during the course of the work.
9. Use of hoisting machines and tackles including their attachment, anchorage and supports
shall conform to the following:
(a) (i) These shall be of good mechanical construction, sound material and
adequate strength and free from patent defects and shall be kept in good
repair and in good working order.
(ii) Every rope used in hoisting or lowering materials or as a means of
suspension shall be of durable quality and adequate strength, and free from
patent defects.
(b) Every crane driver or hoisting appliance operator shall be properly qualified and no person
under the age of 21 years shall be in charge of any hoisting machine including any scaffold
winch or give signals to operator.
(c) In case of every hoisting machine and of every chain ring hook, shackle, swivel and pulley
block used in hoisting or lowering or as means of suspension, safe working load shall be
ascertained by adequate means. Every hoisting machine and all gear referred to above shall
be plainly marked with safe working load. In case of hoisting machine having a variable
safe working load, each safe working load and the conditions under which it is applicable
shall be clearly indicated. No part of any machine or of any gear referred to above in this
paragraph shall be loaded beyond safe working load except for the purpose of testing.
(d) In case of departmental machine, safe working load shall be notified by the Engineer, as
regards Contractor’s machine the contractor shall notify safe working load of each machine
to the Engineer whenever he brings it to site of work and get it verified by the Engineer.
10. Motors, gearing, transmission, electric wiring and other dangerous parts of hoisting
appliances shall be provided with efficient safeguard, hoisting appliances shall be provided
with such means as will reduce to the minimum risk of accidental descent of load adequate
precautions shall be taken to reduce to the minimum risk of any part of a suspended load
becoming accidentally displaced. When workers are employed on electrical installations
which are already energized, insulating mats, wearing apparel such as gloves, sleeves and
boots as may be necessary, shall be provided. Workers shall not wear any rings, watches
and carry keys or other materials which are good conductors of electricity.
11. All scaffolds, ladders and other safety devices mentioned or described herein shall be
maintained in a safe condition and no scaffold, ladder or equipment shall be altered or
removed while it is in use Adequate washing facilities shall be provided at or near places
of work.
Signature of Tenderer No. of Corrections Signature of NMMC Official
81
12. These safety provision shall be brought to the notice of all concerned by display on a
notice board at a prominent place at the work spot. Persons responsible for ensuring
compliance with the Safety Provision shall be named therein by the Contractor.
13. To ensure effective enforcement of the rules and regulations relating to safety precautions,
arrangements made by the Contractor shall be open to inspection by the Engineer or his
representative and the inspecting officers.
14. Notwithstanding the above provisions 1 to 13, the Contractor is not exempted from the
operation of any other Act or Rule in force.
Signature of Tenderer No. of Corrections Signature of NMMC Official
82
ANNEXURE ‘B’
""Eò®úÉ®úxÉɨÉÉ''
xÉ´ÉÒ ¨ÉÖƤÉ<Ç ¨É½þÉxÉMÉ®ú{ÉÉʱÉEäòSÉä ´ÉiÉÒxÉä
+ÊiÉÊ®úCiÉ ¶É½þ®ú +ʦɪÉÆiÉÉ,
xÉ´ÉÒ ¨ÉÖƤÉ<Ç ¨É½þÉxÉMÉ®ú{ÉÉʱÉEòÉ.
xÉ´ÉÒ ¨ÉÖƤÉ<Ç.
___________________________
___________________________
___________________________
Eò®úÉ®úxÉɨÉÉ Ê±É½ÚþxÉ
näùhÉÉ®ú
EòÉ®úhÉä Eò®úÉ®úxÉɨÉÉ Ê±É½ÚþxÉ näùiÉÉä EòÒ, xÉ´ÉÒ ¨ÉÖƤÉ<Ç
¨É½þÉxÉMÉ®ú{ÉÉʱÉEòÉ ºlÉɪÉÒ ºÉʨÉiÉÒ `ö®úÉ´É Gò¨ÉÉÆEò _________
/¨ÉÉ.+ɪÉÖCiÉ ªÉÉÆSÉÒ ¨ÉÆVÉÖ®úÒ Ên. / /200 +x´ÉªÉä
_____________________________________________________________________________________
_______________________________ EòɨÉÉSÉÒ ÊxÉÊ´ÉnùÉ ¨ÉÆVÉÚ®ú ZÉɱÉÒ +ɽäþ.
iªÉÉ|ɨÉÉhÉä +ɨ½þÒ ´É®úÒ±É Ê`öEòÉhÉÒ {ÉÖføÒ±É ¶ÉiÉÔ´É®ú
¤ÉÉÆvÉÒ±É +ɽþÉäiÉ.
1. EÆòjÉÉ]õnùÉ®úÉxÉä ¤ÉÄEò MÉì®Æú]õÒSªÉÉ º´É°ü{ÉÉiÉ +xÉɨÉiÉ
Signature of Tenderer No. of Corrections Signature of NMMC Official
83
®úCEò¨É ¨½þhÉÚxÉ EÆòjÉÉ]õ ®úCEò¨ÉäSªÉÉ 2 ]õCEäò ¤ÉÄEäòiÉ
`äö´ÉhÉä +ɴɶªÉEò +ɽäþ. =´ÉÇÊ®úiÉ +xÉɨÉiÉ ®úCEò¨É näùªÉ
ʤɱÉÉiÉÚxÉ 2 ]õCEäò nù®úÉxÉä ´ÉVÉÉ Eò®úhÉäSÉÒ +ɽäþ.
2. VÉxÉ®ú±É ]åõb÷®ú xÉÉä]õÒºÉ "¶ÉÖvnùÒ{ÉjÉɺɽþ'
ÊxÉÊ´ÉnùÉEòÉ®úÉÆxÉÉ ºÉÖSÉxÉÉ ºÉ´ÉÇ +]õÒ ºÉÉvÉÉ®úhÉ +]õÒ,
°ü{É®äú¹ÉÉ iÉ{ɶÉÒ±É,ÊxÉÊ´ÉnùÉ nùºiÉBä´ÉVÉ ´É κ´ÉEÞòiÉÒ {ÉjÉ
xÉÆ. -----------------Ênù. / /200 ½äþ ºÉ´ÉÇ Eò®úÉ®úÉSÉä
EòÉMÉnù{ÉjÉ +ºÉiÉÒ±É.
3. EÆòjÉÉ]õnùÉ®úÉxÉä +É{ɱÉä EòÉ¨É ÊxÉvÉÉÇ®úÒiÉ ´Éä³äýiÉSÉ
Eäò±Éä {ÉÉʽþVÉä.
4. ¨É½þÉ{ÉÉʱÉEòÉ EÆòjÉÉ]õnùÉ®úÉxÉä |ÉiªÉIÉ Eäò±É䱪ÉÉ
EòɨÉÉSÉÒä ®úCEò¨É ¶Éäb÷¬Ú±É ®äú]õ / EòÉä]äõb÷
{ɺÉç]äõVÉ|ɨÉÉhÉä EÆòjÉÉ]õnùÉ®úÉºÉ näù<DZÉ.
Signature of Tenderer No. of Corrections Signature of NMMC Official
84
5. ¨É½þÉ{ÉÉʱÉEäòxÉä VÉ®ú EÆòjÉÉ]õnùÉ®úÉºÉ EòÉähÉiÉÒ½þÒ
ºÉä´ÉÉ Ênù±ªÉÉºÉ iªÉÉSÉÒ ®úCEò¨É EÆòjÉÉ]õnùÉ®úÉxÉä
¨É½þÉ{ÉÉʱÉEäòºÉ näùhÉä MÉ®úVÉäSÉä +ɽäþ.
6. ºÉnù®ú EòɨÉÉSªÉÉ ºÉÆnù¦ÉÉÇiÉ BJÉÉtÉ ´Éä³äýºÉ Ê´É´ÉÉnù
ÊxɨÉÉÇhÉ ZÉɱªÉÉºÉ iÉÉä Ê´É´ÉÉnù `öÉhÉä / ¨ÉÖƤÉ<Ç
xªÉɪÉɱɪÉÉÆSªÉÉ ½þqùÒiÉ iªÉÉSÉÉ ÊxÉ´ÉÉb÷É ½þÉä<DZÉ.
´É®úÒ±É ºÉ´ÉÇ ÊxÉªÉ¨É ´É +]õÒ +ɨ½þÒ EòɳýVÉÒ{ÉÚ´ÉÇEò ´ÉÉSɱªÉÉ
+ºÉÚxÉ iªÉÉ +ɨ½þɱÉÉ {ÉÚhÉÇ{ÉhÉä ¨ÉÉxªÉ ´É ¤ÉÆvÉxÉEòÉ®úEò +ɽäþiÉ. ½þÉ
Eò®úÉ®úxÉɨÉÉ ¨ÉÒ ®úÉVÉÒJÉÖ¶ÉÒxÉä ʱɽÚþxÉ Ênù±ÉÉ +ɽäþ.
Ê`öEòÉhÉ :- ºÉÒ. ¤ÉÒ. b÷Ò., ¤Éä±ÉÉ{ÉÚ®ú, xÉ´ÉÒ ¨ÉÖƤÉ<Ç - 400 614.
ÊnùxÉÉÆEò :- / /2012
Signature of Tenderer No. of Corrections Signature of NMMC Official
85
ºÉÉIÉÒnùÉ®ú Eò®úÉ®úxÉɨÉÉ Ê±É½ÚþxÉ
näùhÉÉ®ú
1. º´ÉÉIÉ®úÒ
xÉÉÆ´É : ________________________ º´ÉÉIÉ®úÒ (EÆòjÉÉ]õnùÉ®ú)
{ÉkÉÉ : ________________________ xÉÉÆ´É : ________________________
: ________________________ {ÉkÉÉ : ________________________
: ________________________ : ________________________
2. º´ÉÉIÉ®úÒ : ________________________
xÉÉÆ´É : ________________________ ®ú¤É®úÒ Ê¶ÉCEòÉ
{ÉkÉÉ : ________________________
: ________________________
: ________________________
¨ÉxÉ{ÉÉ º´ÉÉIÉ®úÒ :-
{ÉnùxÉÉ¨É :-
Signature of Tenderer No. of Corrections Signature of NMMC Official
86
xÉ´ÉÒ ¨ÉÖƤÉ<Ç xÉ´ÉÒ ¨ÉÖƤÉ<Ç xÉ´ÉÒ ¨ÉÖƤÉ<Ç xÉ´ÉÒ ¨ÉÖƤÉ<Ç
¨É½þÉxÉMÉ®ú{ÉÉʱÉEòɨɽþÉxÉMÉ®ú{ÉÉʱÉEòɨɽþÉxÉMÉ®ú{ÉÉʱÉEòɨɽþÉxÉMÉ®ú{ÉÉʱÉEòÉ
ºÉɨÉÉxªÉ ¨ÉÖpùÉ
ºlÉɪÉÒ ºÉʨÉiÉÒSªÉÉ JÉɱÉÒ±É nùÉäxÉ ºÉnùºªÉÉƺɨÉIÉ ºÉɨÉÉxªÉ ¨ÉÖpùÉ
=¨É]õÊ´ÉhªÉÉiÉ +ɱÉÒ +ɽäþ.
xÉÉÆ´É : ________________________ º´ÉÉIÉ®úÒ : _______________________
xÉÉÆ´É : ________________________ º´ÉÉIÉ®úÒ : _______________________
Signature of Tenderer No. of Corrections Signature of NMMC Official
87
-Ö´ÖãÓ´Ö¯ÖÖ -Ö´ÖãÓ´Ö¯ÖÖ -Ö´ÖãÓ´Ö¯ÖÖ -Ö´ÖãÓ´Ö¯ÖÖ ú¸üÖ¸ú¸üÖ¸ú¸üÖ¸ú¸üÖ¸-ÖÖ´Öê -ÖÖë¤ü-ÖÖ´Öê -ÖÖë¤ü-ÖÖ´Öê -ÖÖë¤ü-ÖÖ´Öê -ÖÖë¤ü Öß †Ö×Öß †Ö×Öß †Ö×Öß †Ö× Ö Ö Ö Ö Ã™Ñü¯Ö ›ü¶ã™üß ²ÖÖ²ÖŸÖ.ÙÑü¯Ö ›ü¶ã™üß ²ÖÖ²ÖŸÖ.ÙÑü¯Ö ›ü¶ã™üß ²ÖÖ²ÖŸÖ.ÙÑü¯Ö ›ü¶ã™üß ²ÖÖ²ÖŸÖ.
-Ö¾Öß ´ÖãÓ²Ö‡Ô ´ÖÆüÖ-Ö Ö¸ü¯ÖÖ×»Ö úÖ
-Ö´ÖãÓ´Ö¯ÖÖ/¯ÖÏ¿ÖÖÃÖ-ÖÖ/×¾Ö¬Öß/205/2009,
פü. 08/12/2009
¾ÖÖ“ÖÖ : 1. -Ö´ÖãÓ´Ö¯ÖÖ/¯ÖÏ¿ÖÖÃÖ-Ö/×¾Ö¬Öß/175/2009, פü.15/06/2009
¯Ö׸ü¯Ö¡Ö ú.
2. -ÖÖë¤ü Öß ´ÖÆüÖ×-Ö׸ü Ö ú ¾Ö ´Öã¦üÖÓ ×-ÖµÖÓ¡Ö Ö,
´ÖÆüÖ¸üÖ™Òü ¸üÖ•µÖ ¯Öã Öê µÖÖÓ“Öê
פü-ÖÖÓ ú 20/07/2009 ¸üÖê•Öß“Öê ¯Ö¡Ö
¯Ö׸ü¯¯Ö׸ü¯¯Ö׸ü¯¯Ö׸ü¯Ö¡ÖÖ¡ÖÖ¡ÖÖ¡Ö ú :ú :ú :ú :----
-ÖÖêÓ¤ü-ÖÖêÓ¤ü-ÖÖêÓ¤ü-ÖÖêÓ¤ü Öß (Registwation)Öß (Registwation)Öß (Registwation)Öß (Registwation)
-Ö¾Öß ´ÖãÓ²Ö‡Ô ´ÖÆüÖ-Ö Ö¸ü¯ÖÖ×»Ö êú“µÖÖ¾ÖŸÖß-Öê ú¸ü µÖÖŸÖ
µÖê ÖÖ¸êü ú¸üÖ¸-ÖÖ´Öê ¯ÖÏÖ´Öã µÖÖ-Öê ÃÖÖ±úÃÖ±Ö‡Ô, ¤êü Ö³ÖÖ»Ö-
¤æüºþßÖß, -Ö¾Öß-Ö ²ÖÖÓ¬Ö úÖ´Öê, Ö¸êü¤üß †¿ÖÖ Ã¾Öºþ¯ÖÖ“Öß †ÃÖŸÖÖŸÖ.
†¿ÖÖ ú¸üÖ¸-ÖÖ´µÖÖÓ´Öãôêû ´ÖÆüÖ¯ÖÖ×»Ö êú“µÖÖ Ã£ÖÖ¾Ö¸ü ´ÖÖ»Ö´Ö¢ÖêŸÖ
¤ãüÃÖ·µÖÖ ¯Ö Ö úÖ¸ÖÓ“Öß ÆüŒ ú ¯ÖÏãÖÖ×¯ÖŸÖ ÆüÖêŸÖ -ÖÖÆüß. ŸµÖÖ´Öãôêû
†ÃÖê ú¸üÖ¸-ÖÖ´Öê ¸üוÖÙÒêü¿Ö-Ö †òŒ™ 1908 “µÖÖ Compulsorily Registerbale
µÖÖ ¯ÖÏ úÖ¸ÖŸÖ ´ÖÖê›üŸÖ -ÖÖÆüߟÖ.
Signature of Tenderer No. of Corrections Signature of NMMC Official
88
´ÖÖ¡Ö ´ÖÆüÖ¯ÖÖ×»Ö êú“Öß ´ÖÖ»Ö´Ö¢ÖÖ ³ÖÖ›êü¯Ö™Ëü™ü¶Ö-Öê
¤êü µÖÖ“Öê ÃÖ¾ÖÔ ú¸üÖ¸-ÖÖ´Öê -ÖÖë¤ü Öß éúŸÖ †ÃÖ Öê Ö¸ü•Öê“Öê †ÖÆêü.
´Öã¦üÖÓ´Öã¦üÖÓ´Öã¦üÖÓ´Öã¦üÖÓ ¿Ö㻿Ö㻿Ö㻿Öã» ú (Stamp Dut�)ú (Stamp Dut�)ú (Stamp Dut�)ú (Stamp Dut�)
[A] úÖµÖÔ Óú¡ÖÖ™ü (Work Contract) “µÖÖ ¤üß֋ê¾Ö•ÖÖÃÖ ú¸üÖ¸ÖŸÖß»Ö
¸üŒ ´Ö
(a) ºþ¯ÖµÖê 10 »ÖÖ ÖÖÓ¯ÖµÖÔÓŸÖ †ÃÖê»Ö ŸÖ¸ü ºþ¯ÖµÖê 100/-
(b) ºþ¯ÖµÖê 10 »ÖÖ ÖÖ“Öê ¾Ö¸ü †ÃÖê»Ö ŸÖ¸ü ºþ¯ÖµÖê 100 †×¬Ö ú ºþ¯ÖµÖê
10 »ÖÖ ÖÖ“Öê ¯Öãœüᯙ ¯ÖÏŸµÖê ú ºþ¯ÖµÖê 1 »ÖÖ ÖÖÃÖÖšüß ºþ¯ÖµÖê
100 †×¬Ö ŸÖ´Ö ºþ¯ÖµÖê 5 »ÖÖ Ö ‡ŸÖ êú ´Öã¦üÖÓ ¿Öã» ú ¤êüµÖ
†ÖÆêü.
[B] ×¾Ö úÃÖ-Ö ú¸üÖ¸ :- ÃÖ¤ü¸ü ¯ÖÏ úÖ¸“µÖÖ ¤üß֋ê¾Ö•ÖÖÃÖ ˆŒŸÖ
†×¬Ö×-ÖµÖ´ÖÖ“µÖÖ ¯Ö׸׿Öšü 1 “Öê †-Öã“”êû¤ü 5 ( Ö †) -ÖãÃÖÖ¸ü
×´Öôû úŸÖß“Öê ²ÖÖ•ÖÖ¸ü´Ö㻵ÖÖ¾Ö¸ü Ö¸êü¤üß ÖŸÖÖ¯ÖÏ´ÖÖ Öê ¯Öã ÖÔ
´Öã¦üÖÓ ¿Öã» ú ¤êüµÖ †ÖÆêü.
†ÖµÖ㌟ֆֵÖ㌟ֆֵÖ㌟ֆֵÖ㌟Ö
-Ö¾Öß ´ÖãÓ²Ö‡Ô ´ÖÆüÖ-Ö¾Öß ´ÖãÓ²Ö‡Ô ´ÖÆüÖ-Ö¾Öß ´ÖãÓ²Ö‡Ô ´ÖÆüÖ-Ö¾Öß ´ÖãÓ²Ö‡Ô ´ÖÆüÖ----
-Ö-Ö-Ö-Ö Ö¸üÖ¸üÖ¸üÖ¸ü¯ÖÖ×»Ö¯ÖÖ×»Ö¯ÖÖ×»Ö¯ÖÖ×»Ö úÖúÖúÖúÖ
Signature of Tenderer No. of Corrections Signature of NMMC Official
89
ANNEXURE ‘C’
I N D E M N I T Y B O N D
(on Stamp Paper of value of Rs.100/-)
In consideration of Navi Mumbai Municipal Corporation incorporated under BPMC Act 1949
and having its office at Belapur Bhavan, 1st Floor, C.B.D. Belapur, Navi Mumbai- 400 614.
(hereinafter referred to as the Corporation, which expression, shall unless it be repugnant to the
context or meaning thereof includes its successors or assigns) having awarded to
M/s.___________________________________________ a partnership/ proprietorship/ Pvt. Ltd./
Ltd. Firm carrying in such name and style the business of construction (hereinafter referred to as
the Contractor Which expression shall, unless it be repugnant to the context or meaning thereof,
includes its partner or Partner/Proprietor for the time being or its surviving Partner or his heirs and
executer) for the work of
_______________________________________________________________________________
______________________________________________ at an _________ percent above/ below
estimated cost of Rs. ______________
and in compliance with one of the terms and conditions of the said Contract.
We, M/s._____________________________________________________ being the contractor
do hereby agree and undertake and indemnify and save harmless the corporation in consequence
of the manufacturing defect, patent manufacturing defect and construction defect found in the
constructed work at any time in a defect liability period of ________ years with the grant of
completion certificate by the Corporation to the Contractor in accordance with and subject to the
provision of the said contract.
It is hereby agreed and declared that the Additional City Engineer of the Corporation or any
officer acting as such Additional City Engineer of the Corporation shall be the competent
Authority to decide upon the question as to the defects in the construction of work and the remedy
to be applied by the Contractor for their rectification at his cost and his decision shall be final,
conclusive and binding upon both the Corporation and the Contractor, provided that the
Additional City Engineer shall so decide after giving an opportunity to the Contractor to represent
his case.
We hereby agree and undertake irrevocable and unconditionally to carry out duly each and very
decision, order, direction or instruction as may be issued by the said Additional City Engineer or
as the case may be, the officer of the Corporation in his behalf and to rectify properly and
promptly the defect found by him.
Signature of Tenderer No. of Corrections Signature of NMMC Official
90
FOR AND ON BEHALF OF M/S.
___________________________________________________
___________________________________________________
___________________________________________________
Place:-_____________
Date:- _____________
SEAL
NOTARY, MAHARASHTRA STATE
BEFORE ME
NOTARY
Maharashtra State
Noted and Registered at
________________________________________________
Serial No. _________________________________
For & on Behalf of Corporation
Accepted By,
Signature of Tenderer No. of Corrections Signature of NMMC Official
91
PRICE VARIATION CLAUSE.
Accompaniment to the Government Resolution
Public Works Department No. CAT/06/04/148, dt.16/05/2005.
If during the operative period of the contract as defined in condition (i) below, there shall be any varation in
the consumer price Index (New series) for Industrial workers for Mumbai Center as per the Labour Gazette
published by the Commissioner of Labour, Government of Maharashtra and or in the wholesale price index
for all commodities prepared by the office of Economic Adviser, Ministry of Industry, Government of
India, or in the price of petrol/oil and lubricants and major construction materials like bitumen, cement,
steel various types of metal pipes etc, then subject to the other conditions mentioned below, price
adjustments, on account of
(1) Labour component
(2) Material component
(3) Petrol, Oil and Lubricant components
(4) Bitument Component
(5) HYSD & Mild Steel Component
(6) Cement Component
(7) C.I. and D.I. pipes component.
Calculation as per the formula, hereinafter appearing, shall be made. Apart from these, no other adjustments shall be made to the contract price for any reasons whatsoever, component percentage as given
below are as of the total cost of work put to tender. Total of Labour, Material & POL components shall be
100 and other components shall be as per actuals.
(1) Labour component K1 - 27 %
(2) Material component K2 - 72 % (3) POL components K3 - 1 %
(4) Bitumen Component Actual
(5) T.M.T. Steel Component Actual
(6) Cement Component Actual
(7) C.I. and D.I. pipes component Actual
NOTE :- If cement, steel, Bitumen C.I. & D.I. pipes are supplied on schedule “A” then
respective component shall not be considered. Also if particulars component is
not relevent same shall be deleted.
(1) FORMULA FOR LABOUR COMPONENT :-
V1 = 0.85 Px[ K1 x L1-L0 ]
100 L0
Where :-
V1 = Amount of price variation in rupees to be allowed for labour component..
P = Cost of work done during the quarter under consideration.
Minus
The Cost of cement, T.M.T./H.Y.S.D. and Mild steel, Bitumen C.I. & D.I. pipes calculated at the
basic star rates as applicable for the tender, consumed during the quarter under consideration. (These star rates shall be specified here) The Star Rates shall be Considered as per the Material cost
Considered for the preparation of estimate or at the time of comparison with new D.S.R.
K1 = Percentage of Labour component as indicated above.
L0 = Basic consumer price Index shall be average wholesale price index for the quarter
preceding the month in which to the date prescribed for receipt of tender falls.
L1 = Average consumer price Index for Mumbai Center for the quarter under consideration.
(2) FORMULA FOR MATERIALS COMPONENT :-
V2 = 0.85 P x [ K2 x M1-M0 ]
100 M0
Signature of Tenderer No. of Corrections Signature of NMMC Official
92
Where :-
V2 = Amount of price variation in rupees to be allowed for Material component.
P = Same as worked out for labour component.
K2 = Percentage of Material component as indicated above.
M0 = Basic wholesale price Index shall be average wholesale price index for the
quarter
preceeding the month in which to the last date prescribed for receipt of tender,
falls.
M1 = Average wholesale price Index during the quarter under consideration.
(3) FORMULA FOR PETROL, OIL AND LUBRICANT COMPONENT :-
V3 = 0.85 Px[ K3 x P1-P0 ]
100 P0
Where :-
V3 = Amount of price variation in rupees to be allowed for POL component.
P = Same as worked out for labour component.
K3 = Percentage of petrol, oil and lubricant component.
P0 = Average price of HSD at Mumbai during the quarter preceeding the
month in which the last date prescribed for receipt of tender falls.
P1 = Average price of HSD at Mumbai during the quarter under consideration.
(4) FORMULA FOR BITUMEN COMPONENT :-
V4 = QB (B1-B0)
Where,
V4 = Amount of price variation in rupees to be allowed for Bitumen component.
QB = Quantity of Bitumen (Grade) in metric tonnes used in the permanent works and
approved enabling works during the quarter under consideration.
B1 = Current average ex-refiners price per metric tonne of Bitumen (Grade) under
consideration including taxes (octroi, excise sales tax) during the quarter under
consideration.
B0 = Basic rate of Bitumen in rupees as per metric tonne as considered for working out
value of P or average ex-refinery price in rupees per metric tone including taxes,
(octrol, excise sale tax) of Bitumen for the grade of bitumen under consideration prevailing quarter preceding the month in which the last date prescribed for receipt
of tender falls. whichever is higher,
Signature of Tenderer No. of Corrections Signature of NMMC Official
93
(5) FORMULA FOR HYSD AND TMT STEEL COMPONENT :-
V5 = S0 x [ Sl1-Sl0 ] x T
S10
V5 = Amount of price variation in rupees to be allowed for HYSD/TMT steel
component.
S0 = Basic rate of HYSD/ TMT steel in rupees per metric tonne as considered for
working out value of P.(Under consideration)
Sl1 = Average of steel Index as per RBI Bulletin for the quarter preceding the month in
which the last date prescribed for receipt of tender, falls.
Sl0 = Average of steel Index as per RBI Bulletin for the quarter preceding the month in
hich the last date of prescribed for receipt of tender, falls.
T = Tonnage of steel used in the permanent works for the quarter under consideration.
(6) FORMULA FOR CEMENT COMPONENT :-
V6 = C0 x [ Cl1-Cl0 ] x T
Cl0
V6 = Amount of price escalation in rupees to be allowed for cement component.
C0 = Basic rate of cement in rupees per metric tonne as considered for working out
value of P
Cl1 = Average cement Index published in the RBI bulletin for the quarter under
consideration.
Clo = Average of cement Index published in the RBI Bulletin for the quarter preceding
the month in which to the last date of prescribed for receipt of tender, falls.
T = Tonnage of cement used in the permanent works for the quarter under consideration.
(7) FORMULA FOR C.I/D.I. PIPE COMPONENT :-
V7 = Qd x [ D1 – D0 ]
Where,
V7 = Amount of price escalation in rupees to be allowed for C.I./D.I. pipe component.
D0 = Pig Iron basic price in rupees per tonne considered for working out value of P.
D1 = Average Pig Iron price in rupees per tonne during the quarter under consideration
(published by HSCO)
Qd = Tonnage of C.I./D.I. pipes used in the works during the quarter under
consideration.
Signature of Tenderer No. of Corrections Signature of NMMC Official
94
The following conditions shall prevail :-
(i) The operative period of the contract shall mean the period commencing from the date
of the work order issued to the contractor and ending on the date on which the time
allowed for the completion of the works specified in the contract for work expires,
taking into consideration the extension of time it any for completion of the work
granted by Engineer under the Relevant clause of the conditions of contract in case
other than those where such extension in necessitated on account of default of the
contractor. The decision of the Engineer as regards the operative period of the contract
shall be final and binding on the contractor. Where any compensation for liquidated
damages is levied on the contractor on account of delay in completion of inadequate
progress under the Relevant contract provisions,, for the balance of work from the date
of levy of such compensation the price adjustment amount shall be worked out by
pegging the indices L, M, C, P, B, SI and CI to the levels corresponding to the date
from which such compensation is levied.
(ii) This price variation clauses shall be applicable to all contracts in B-1/B-2 and “C” form
but shall not apply for piece works. The Price variation shall be determined during each
quarter as per formula given above in this clause.
(iii) The price variation under this clause shall not be payable for the extra items required to
be executed during the completion of the work and also on the excess quantities of
items payable under the provision of clause 38/37 of the contract from B-1, B-2
respectively. Since the rates payable for the extra times or the extra quantities under
clause are to be fixed as per the current DSR or as mutually agreed to yearly revision
till completion of such work. In other words, when the completion/execution of extra
items as well as extra quantities under clause 38/37 of the contract from B-1/B-2
extends beyond the operative date of the DSR then the rates payable for the same
beyond that date shall be revised with reference to the current DSR prevalent at that
time on year to year basis or revised in accordance with mutual agreement thereon, as
provided for the contract whichever is less.
(iv) This clause is operative both ways, i.e. if the price variation as calculated above is on
the plus side, payment on account of the price variation shall be allowed to the
contractor and if it is on the negative side, the government shall be entitled to recover
the same from the contractor and the amount shall be deductible from the any amounts
due and payable under the contract.
(v) To the extent that full compensation for any rise or fall in costs to the contractor is not
entirely covered by the provision of this or other clauses in the contract, the unit rate
and prices included in the contract shall be deemed to include amounts to cover the
contingency of such other actual rise of fall in costs.
vi) Basic rates of materials will be consider as per P.W.D.(Thane Circle)for the year 2011-12.
Cement – Rs. 5600/- Per M.T.
T.M.T. Steel – Rs. 42000/- Per M.T.
Structural Steel – Rs. 41000/- Per M.T.
Signature of Tenderer No. of Corrections Signature of NMMC Official
95
DETAIL SPECIFICATION FOR CIVIL WORKS
1.0 SITE INSPECTION
EARTHWORK IN SITE LEVELING
2.1 General
Applicable provisions of conditions of contract shall govern the work under this section.
2.2 Work included
The contractor shall provide materials, labour, plant and equipment to complete the work
indicated or specified herein or both.
2.3 Sequence of Site Levelling
The Contractor shall level the site in accordance with the sequence of earth leveling as
shown on the drawing.
2.4 Cleaning and Grubbing work
All Areas to be excavated for attaining specified levels and for obtaining fill material and
areas where filling has to be done shall be cleared of all vegetation, shrubs, bushes, trees,
roots etc. The Contractor shall break and remove unwanted structures and building,
including foundations, fencing, drains and empty and cleanse all old wells, ponds and
cesspools. All tree stumps shall be removed and roots shall be excavated and removed.
The cleared and grubbed areas shall be maintained free from vegetation and any vegetable
growth during the progress of the work. All materials obtained from cleaning and
grubbing shall be dumped in allotted areas.
2.5 Stripping
The area to be filled shall be stripped of all materials such as vegetation, organic soil, silt
etc. The surface shall be stripped to be depth of 80 mm to 200 mm as may be necessary to
obtain a foundation of satisfactory density and stability all materials that may be soft
yielding or likely to become unstable with saturation or which may interface with the
creation of proper bond between the foundation and filling shall be removed. The material
obtained from stripping should be dumped in allotted areas.
2.6 Excavation of High Areas
All materials required for the fillings shall be taken from high areas which are to be
brought to specialized reduced levels. The earth obtained from specified sections of high
areas shall be placed in specific sections of the zone of filling. The high areas shall be so
worked that the selected materials as required shall be obtainable as close to the point of
utilization as possible and shall not interfere with any permanents structure or disfigure any
part of the work. The depth of the cut form of each high area shall be as shown as on the
drawings. These slopes shall be cleared of all loose drawings. These slopes shall be
cleared of all loose or insecure fragments on blocks which may cause injury or damage by
falling or slipping. The contractor shall take particular care to excavate only to specified
levels. In case any excavation is carried out to levels deeper than specified, no claims for
payment for excavation beyond the specified depth will be admissible. The contractor
shall then have to make good excavation at his own cost and bring the area to the specified
levels.
Signature of Tenderer No. of Corrections Signature of NMMC Official
96
2.7 Earth fill Materials
All suitable material excavated from high areas shall be used for filling the low areas. The
contractor shall maintain at his own cost all haul roads in connection with the work. These
roads shall be graded and well watered from time to time to prevent dust nuisance and to
provide good visibility in the working areas.
2.8 Placing Earth Fill
Roots, sods, wood or other organic matter shall not be placed in the fill. Before a new
layer is laid, existing ruts or other unevenness in the surface of the layer shall be removed
and the surface of the layer shall be scarified and roughened by harrowing and plugging to
obtain bond with the material to be placed. The fill material shall be in continuous
horizontal layers not exceeding 200 mm. Thickness. The fill material shall be kept slightly
sloping from the center to the edges avoid formation of pools during the rains. Dozers
graders shall be used for spreading and leveling the material to uniform thickness.
2.9 Compacting
In filled up areas such as embankments and other c compaction shall be carried out by
sheep’s foot roller capable of giving a bearing pressure of 25 Kg. Per sq.cm. of the foot
area in contact as a given time. The layers of the earth fill placed shall be compacted till
the feet of the sheep’s feet roller commence rising out of the ground. The layers shall be
watered before rolling. If the material laid down for compaction is to wet in the opinion
of the Engineer/Architect, then the Contractor shall allow it to be aerated till the optimum
moisture is reached and then start the process of compaction.
Graders and dozers shall be used to keep the layers uniform so that extreme variations in
depth do not occur. In case of inaccessible places such as ground culvert pipes, headers.
building foundations etc. Technically driven on hand tampers shall be used.
2.10 Blasting
Blasting shall be carried out as specified under Clause 4.0
2.11 Embankments
The finished formation width, side slopes and grade of the embankments shall be true to
line and level as shown on the drawings.
The embankments shall be made up in layers not exceeding s 30 mm thickness over the
whole width between the surface of the side slopes and shall be slightly concave in section
so as to retain the water for water subsidence. All large clods shall be broken up by labour
specially detailed for this work.
When embankments are on side-long ground the whole area of the embankment on slope
shall be benched out or stepped so as to prevent the material from slipping.
Signature of Tenderer No. of Corrections Signature of NMMC Official
97
In construction of embankments over the culverts or pipe drains care shall be taken to
bring the embankments up, equally, ;on both side and over the top of the structure. Earth
embankments shall be compacted as specified in clause 2.9 and in rock embankment, the
rock filling shall be carefully packed for the depths as shown on the drawing.
If embankments are made from borrow pits, the Contractor shall excavate the earth from
borrow pits at the locations indicated on the drawings. The shall be regular in width the
shape and shall be properly graded, drained and finished with neatly trimmed slopes.
2.12 Cuttings
The section of the cutting shall be as shown on the drawings. The sides of all cuttings in
rock shall be cleared out all loose or insecure fragments or blocks which may cause inquiry
or damage by falling.
Where in the sides of rock cuttings inferior stone or soft materials intervene between layers
of hard rock or where the rock after dressing and exposure will not permanently with stand
and effect or weather, such inferior stone or soft material or loose rock shall be excavated
to an approved depth and the resulting space built up with masonry or concrete so as to
ensure a solid uniformly battered face.
Where soft and unsuitable material is encountered in cuttings at formation level or
immediately thereunder it shall be excavated to such levels directed by the
Engineer/Architect. The resultant excavation shall be filled with suitable materials and
compacted as specified in Clause 2.9.
2.13 Water Courses and Drains
Excavations carried out in diversion, enlargements, deepening, or straightening of streams,
water course, or ditches, shall be performed as shown on the drawings. All surplus
suitable material obtained from such excavations shall be used for filling low areas and/or
embankments.
Where water courses have to diverted from the sites of embankments or other works, the
original ;channels shall be cleared of all vegetable growths and soft deposits and filled in
with approved materials and compacted as specified in Clause 2.9 open ditches and catch
water drains from drainage purposes shall be cut to such cross section as shown on the
drawing. The sides shall be dressed fair throughout and the bottoms accurately ;graded so
as to drain the water to the outlet. All suitable material excavated from the ditches and
catch water drains shall be used for filling low areas and/ or embankment.
Signature of Tenderer No. of Corrections Signature of NMMC Official
98
3.0 EAST WORK IN EXCAVATION FOR FOUNDATIONS, BASEMENT DRAINS,
CULVERTS ETC.
3.1 General
Applicable provisions of conditions of contract shall govern work under this section.
3.2 Work included
The Contractor furnish labour, material, plant and equipment to complete excavation,
filling , backfilling , leveling grading and compacting as indicated or specified herein or
both.
3.3 Grub up Old foundations, Drains etc.
The Contractor shall grub up old roots, break up and remove old concrete or brick
foundations, drains or manholes, empty and cleanse all old , wells, cesspools and ponds,
found prior to during progress of excavation, seal up connections where required, remove
all contaminated earth and fill in voids with hard materials and well ram.
3.4 Excavation and Cutting
The Contractor shall excavate to remove materials of any nature or description which may
be encounted and excavate to the depths, widths, and inclinations as shown on the
drawings and/or indicated. The contractor shall not remove trees that are to remain as
directed.
The excavated material shall be classified precautions to prevent ingress of water into
excavated areas, trenches, pits etc. during construction.
3.5 Variation in Excavation
Bad Ground : Should the bottom of any excavation appear to be soft, unsound or
unstable, the contractor shall report the matter to the Engineer/Architect and if the
Engineer/Architect so directs, Shall excavate the same to indicated depths. In case of such
extra excavations the extra depth shall be filled up with concrete or such other materials as
the Engineer/Architect shall direct, such extra excavations and fillings shall be valued and
paid for as an authorized extra.
Excavation the deep : If the Contractor excavates to level lower than those shown drawings
for reason whatsoever, he shall fill it up at his own expense to the proper level with brick
work or concrete as in the case of slips or fails. No payments will be made for excavation
taken down to depths lower than those shown on the drawings.
Slips and Falls : Every precautions shall be taken against slips and falls of earth, clay, sand
or other materials in the excavations, but in the event of any occurring, the contractor shall
at his own expense make good the space affected by the slips or falls, though the affected
area may be outside the dimensions of the work ordered.
The Engineer/Architect will determine in each case whether such affected areas is to be
filled up in whole in part with concrete, brick work or masonry of the quality used in the
adjoining work or where only a part is to be so filled, the materials to be used for this
remaining part.
If in the opinion of the Engineer/Architect there is a possibility of the new constructed
work having been damaged or disturbed by such collapse, the work shall be laid bare at the
expense of the Contractor. Any damage shall be made good by the Contractor at his
expense.
3.6 Shoring, Planking and Strutting
Signature of Tenderer No. of Corrections Signature of NMMC Official
99
The Contractor shall support and maintain adjoining and abutting property and structures
to render work safe to persons and property.
The Contractor shall provide necessary docking, guard, fences, planking and the like to
maintain safe pedestrian and vehicular traffic.
The Contractor shall replace or repair at his own cost and in an approved manner, all work
damaged through removal of such temporary work in improper protective work.
The Contractor shall plant and struct as may be required the sides of all excavations.
3.7 Excavate over Surface
The Contractor shall excavate the surface of the site to remove vegetable soil and carry
such soil to separate spoil heaps on the allotted site within 100m.
3.8 Protection
The contractor shall provide and lay all boards necessary to protect the sides of the
excavations from the effects of inclement weather.
All trenches at all times shall be kept free from water.
The Contractor at his own expense shall pump out or otherwise, remove all water which
may occur during the continuance of the contract.
3.9 Pumping
The Contractor shall provide and operate pumps or other equipments necessary to drain
and keep all excavations, pits, trenches etc. free from water.
3.10 Filling and Rough Grading
For backfilling, the Contractor shall use earth excavated from the foundations, free from
organic and other objectionable matter. The backfilling shall be done in uniform
horizontal layers not exceeding 300 mm. In thickness and rammed and watered as required
to consolidate properly.
Immediately upon the completion of each phase of the work, the contractor shall at his
own expense level the mounds or heaps of earth which may have become surplus in the
execution of thw work within a lead of 10 mkj. And the contractor shall not be paid for
double handling of the spoil.
If sufficient materials are not available on the site to complete all filling to required grades,
they shall be brought to site from outside.
4.0 BLASTING
4.1 General
Applicable provisions of conditions of Contract shall govern work under this section.
4.2 Work included
The Contractor shall furnish labour, materials, plant and tools to complete the work
indicated or specified herein on both. The Contractor shall strictly followed the latest
Government Statutory Laws regarding the safety precautions for storage, use of explosives
and blasting operations.
Signature of Tenderer No. of Corrections Signature of NMMC Official
100
4.3 Storing and Transport
Explosive shall be stored in clean, dry well ventilated magazines to be built for the
purpose. Fuses and detonators shall be stored in separate magazines. Detonators and
explosives shall be transported separately to the blasting site.
4.4 Preparation for Blasting
Explosives shall be kept dry and away from the direct rays of the sun, naked lights, steam
pipes or heated metal etc. Only the quantity of explosive required for a particular amount
of firing to be done shall be brought to the site of work. All surplus explosive loft after
filling the holes shall be removed at lease 400 mm. From the firing point. A wooden
steaming rod shall be used to pushed the cartridge into the shot-hole. Metal rod or rammer
shall not be permitted on the site of the works. The charges shall be pressed firmly into
plane and not rammed or pounded.
The explosive shall be fired by means of an electric detonator placed inside a cartridge and
connected to the firing cable. Due precautions shall be taken to keep the firing circuit
insulated from the ground, bare wires, rails, pipes or any other path of stray currents and
to keep the lead wires short circuited until ready to fire.
4.5 Drilling Rock for Blasting
Holes for changing explosives shall be drilling with pneumatic drills, the drilling pattern
being so planned that rock pieces after blasting will be suitable for handling without
secondary blasting. The rock pieces so blasted shall be neatly stacked at allotted places.
4.6 Blasting Operation
Before any blasting is carried out the contractor shall ensure that all workman vehicle and
equipment on the site are cleared from an area of 300 meteres radius from the firing point,
at least 15 minutes before the firing time by sounding a warning siren. The area shall be
encircled by red flags.
The Contractor shall employ a competent and experienced licensed supervisor in charge of
each set of operation, who shall beheld responsible to ensure that all the safety regulations
are followed.
The firing shall be conducted by supervisor and the number and of shots fired at a time
shall not exceed the permissible limits. In case of misfires the unexploded charges shall be
carefully located after half an hour and shall be exploded by drilling a fresh hole along side
the misfired hole (but not nearer than 600 mm. from it) and by exploding a new charge.
The workman shall not return to the site to firing until at least half an hour after firing.
4.7 Controlled Blasting
When Blasting is conduced in the neighborhood of roads, structures, buildings or any place
which requires controlled blasting, the Contractor shall drill only window shot-holes.
These holes shall be filed with a light charge of explosive and the blast controlled by
placing steel plates loaded with gunny bags filled with sand or earth over the hole and
covering them with wire net fixed to the ground, so as to ensure that the blasted material
do not scatter.
In such cases short delay blasting may be adopted.
Signature of Tenderer No. of Corrections Signature of NMMC Official
101
5.0 EARTH FILLING IN PLINTH AND BACK FILLING AROUND FOUNDATION
PITS
5.1 General
Applicable provisions of Conditions of Contract shall govern work under this section.
5.2 Work included
The Contractors shall supply materials, labour, plants and tools to complete the work
indicated or specified herein on both.
5.3 Workmanship
Before doing the backfilling, The Contractor shall remove all shoring and framework, all
bits of timber, cement bags and all other rubbish.
The filling in plinth shall be of approved earth free from harmful mineral and vegetable
matter. Clays subject to volume changes because of moisture variation such as black
cotton soil, shall not be used for filling.
The backfilling shall be done with selected and approved excavated earth which is free
from large boulders, lumps or similar material, and shall be deposited in layers not
exceeding 200mm in depth. Each layer shall be rammed thoroughly before the next layer is
deposited.
The filling under the floors shall be done in layers not exceeding 150mm in depth. Each
layers shall be thoroughly consolidated by watering and ramming. When filling has
reached the approximate level, the area filled shall be flooded with water and the fill shall
be allowed to settle. When the water has been absorbed in the soil, the whole area shall be
finally rammed and dressed to the required level.
6.0 PLAIN AND REINFORCED CONCRETE WORK
6.1 General
Applicable provisions of conditions of Contract shall govern work under this section.
6.2 Work Included
Supplying all materials, garding aggregates and transporting, handling, protecting and
storing materials for concrete.
Preparing, sampling and testing and concrete mixes.
Mixing, controlling and transporting concrete of all grades and conducting field tests.
Setting, bracing, typing, aligning and checking concrete formwork and constructing
pannels and specials units or providing pre-fabricated unit forms in connects therewith.
Providing and erecting scaffolding.
Providing, fabricating, installing and typing steel reinforcement and dowels.
Fixing anchor bolts and sleeves and settings, typing and aligning for embedments.
Installing and aligning curb angles, pipe sleeves and drains, post, stockets, inserts, furring
anchor devices, hangers, water stops, expansion joint fillers etc. for embedment.
Signature of Tenderer No. of Corrections Signature of NMMC Official
102
Placing concrete3 in building and equipment foundations, footings, piers, walls, slabs and
floors, underpinning, retaining walls, abutments, tunnels, head walls and piping anchor
blocks, storage bins, and track hoppers electrical vaults, conduit beams and trenches,
machinery and equipment foundations, basements, pits and pedestals, cooling tower basing
and substructures etc.
Placing tremie, fast setting, hear and water resistant concrete, open drain and drilled tunnel
timings or other type requiring special procedure.
Placing lean concrete fill in areas where excavations extends below required depths and
where membrane water proofing under floors is indicated.
Applying and joining plies of medmbranes and coal tar water proofing materials with
protective coverings and damp-proofing coats on walls and layers under slabs.
Finishing and protecting floor, slabs, and preparing concrete surfaces for separate
coverings, linings and refractors.
Curing, removing forms, patching and correcting defects, falling from the recesses
cleaning concrete work.
Grouting base, bearing the sole plates, machinery and equipment bed frames as well as
cleaning and grouting constructions joints and preparation for placing additional lifts.
6.3 Materials
Cement :- Ordinary Portland Cement shall conform to IS : 260 and Portland Blast
Furnace Slag cement shall conform to IS : 56.
Reinforcement :- Reinforcement shall M.S. round rods conforming to IS : 432 or IRC
mesh fabric reinforcement conforming to IS : 1666 or mild steel and medium tensile steel
deformed bars conforming to IS : 1139 or cold twisted steel bars conforming to IS : 1786
and shall be free from oil, paint, rust or coatings. The binding wire shall be annealed
approved wire.
Joint Fillers :- Expansion joint fillers shall be approved non extruding, resilient filers as
shown in drawing.
Waterstops :- For expansion and constructions joints waterstops shall be of rubber, PVC
or 20 guage G.I. sheet as indicated in the Bill of Quantities or drawings.
Waterproofing Membrane :- The waterproofing membrane materials and treatment shall
be of a type shown on the drawings.
Water :- Water shall be clean and of potable quality.
6.4 Concrete Mix
The Concrete shall be controlled concrete as defined by IS: 456. The grades of concrete
shall be as indicated on the drawings or as specified and the strength requirements shall be
in accordance with
IS : 456.
The contractor shall grade the aggregate and control the water cement ration as specified in
IS :456 and satisfy the Engineer/Architect by frequent tests at his own cost that the correct
grade of concrete is used. The maximum total quantity of aggregate by weight per 50 kg.
Of cement shall not exceed 450 kg except where otherwise specifically permitted by the
engineer / architect.
Coarse Aggregates Range Where used
40mm to 6mm Mass foundation, heavy
Signature of Tenderer No. of Corrections Signature of NMMC Official
103
ground slabs and where ever
possible. Walls over 250mm and floor
slabs over 150mm.
20mm to 6mm Walls and Slabs thinner
than those mentioned above.
6mm to and below Grouting.
The maximum size of aggregates used shall be as indicated in the drawing and the bill of
quantities.
Where reinforcement is too closely spaced for the maximum size stone in a range, the
largest suitable range will be used with the approval of the Engineer / Architect.
6.5 Mixing
All components of concrete will be proportioned by weight for each grade and preferably a
batch mixing plant shall be used unless volumetricmix is permitted by the Engineer /
Architect. When mixed in a power mixer, it shall be equipped with automatic devices for
control of speed, gauging of water and timing the mixing period, clean potable water only
will be added Batches shall not exceed the capacity which can be mixed efficiently as
determined by mixer efficiently as conform to manufacture’s recommended rate but shall
not vary more than 10 nor exceed 30 m/minute. Net minimum mixing time will begin
when all water is in the mixer and based on mixer size, will be 1 ¾ to 2 minutes for 5/3.5
mixer. Excessive mixing shall be avoided.
When had mixing is permitted, it shall be carried out on a water tight platform and care
shall be taken to ensure that mixing is continued until the mass is uniform in color and
consistency.
Consistency : Consistency will be controlled as per IS : 456 and checked by slump tests in
accordance with IS : 1199. maximum slump for mechanically vibrated concrete shall be as
follows :
Mass construction and pavements : 50mm
Unreinforced foundation walls : 62mm - 75mm
and footings.
Reinforced foundation walls : 75mm – 87mm
and footings.
Reinforced beams, slabs, walls : 100mm
and columns.
Tests : Sampling, making up, curing and testing of specimen will comply with the
IS : 456, IS : 516 and IS : 1199.
Signature of Tenderer No. of Corrections Signature of NMMC Official
104
6.6 Form Work
The form work shall conform to IS : 456. from shall be prefabricated standard or shop built
panels or built – in place units and shall be constructed, stiffened and braced to withstand
the pressure of concrete contingent upon temperature, rate and depth of placing and the
spacing of ties. All forms shall be made up with tight joints to contain the grout. From oil
shall be applied to all panels.
Setting : Panels and units shall be set to true dimensions and alignment and rigidly tied,
waled and braced to prevent distortion and displacement from placing operations, for
surfaces exposed to view, the contact face shall be such that concrete shall present a
smooth, neat appearance. Slip forms where used shall provide smooth even surface true to
dimension and alignment and shall be free of unsightly off – sets, fins and bulges. The
tolerances for wall thickness and general dimensions shall be held to the line consistent
with good construction practice.
Tie Rod : Standard form tips, clamps, bolts and inserts shall be of adequate strength for the
spacing, spreaders, either removable or embedded type shall properly maintain wall
thickness. Tie rod shall be kerfed or notched type to permit removal, so that no end metal
is less than 12mm. back from concrete surfaces. For tie rods of the type which have to be
completely pulled out or to remain embedded, wire shall not be used.
Stripping :- The Period or removal or forms shall conform to IS: 456. Any variation from
code requirements shall be subject to written approval of the Engineer/Architect.
6.7 Reinforcement
Workmanship shall conform to IS:2502. All metal reinforcement shall be freed from loss
mill scale, rust, oil and grease immediately before placing of concrete. Reinforcement
shall not be straightened in a manner that will injure the material. They shall be placed
lapped and maintained in positions and to length. Shown in the drawing. The correct
clearance from the form shall be maintained by provisions of precise concrete Blocks.
All intersections of longitudinal and transverse bars shall be securely tied together with
approved binding wire. The binding wire shall be so placed that it touches all the four
corners of the intersection and the two ends shall be looped with pliers. The cost of
blinding wire and spacer blocks shall be included in the cost of reinforcement.
Welded joints may be used but in all cases of important connections, tests shall be made to
prove that the joints are of the full strength of bars connected. Welding shall be done in
accordance with IS: 2751 and special precautions shall be adopted for cold worked bars.
But welding between the ends of a rod line, whereby stress is transferred across the
section may be adopted only for mild steel bars. For mild steel bars which have had their
strength increased by cold working, the stress at the weld shall be limited to the strength of
mild steel before cold working.
In case of tack welding used for fixing reinforcement in their position, no special
precautions need to be taken.
Signature of Tenderer No. of Corrections Signature of NMMC Official
105
6.8 Embedments
All embedments shall be accurately set and rigidly fastened. Anchor bolts shall be set to
template and firmly secured in vertical and horizontal line at required positions. Water
stops shall be secured against displacement during the placing of concrete. The joints for
G.S. water stops shall be soldered watertight and those of PVC and rubber shall be joined
by cementing and vulcanizing Expansion joint filters shall be for the full depth of slabs or
full width in walls and shall be cemented with a bituminous cement against previously
placed concrete. The ends shall be butted tight and the upper edge set flush with finished
slabs.
6.9 Placing
Transporting Concrete :- Concrete shall be transported from the mixing plant to the forms
as rapidly as possible by means that will prevent segregation or flash set in the concrete
during hot weather. The containers shall be such as to prevent heavy evaporation. At the
time of placing concrete in very hot weather, care shall be taken to see that the temperature
of wet concrete does not exceed 38 degrees centigrade.
Before placing concrete, all framework, emdebments and reinforcement shall be checked
for completeness, location, dimensions, square and plumb. All chips and saw dust or other
foul matter shall be removed from within the forms. The base surface shall be well
moistened and puddles wiped up. Placing equipment and accessories shall be kept clean
and free of partially set grout and concrete and maintained in proper working order.
Placing Aids :- In general, placing shall be direct by transporting buckets. Where it is
necessary to deposit the concrete at level differences of more than 1.5m, short chutes shall
be used. Short chutes and hoppers shall be so designed and installed that segregation will
not take place. In cases where chutes are impracticable due to excessive drop
Construction Joints :- In general construction joints shall be limited to those indicated on
the drawings. In the mass concrete, construction joints may be indicated to the drawings
but shall be made at breaks, offsets or other convenient levels, as controlled by volume,
plant capacity and time factors. Such construction joints shall be so located that they do
not impair the strength of the structure. All construction joints shall be cleaned with were
brush of water to remove all laitance and loose material to expose the aggregate.
Immediately before placing fresh concrete, the surface of previously placed concrete shall
be grouted.
Compaction :- Concrete in general shall be consolidated by vibration using high
frequency mechanically driven vibrators. Concrete shall be placed in layers at least
300mm.deep in walls and approximately 450mm in mass pours. Vibrators shall not
penetrate more than 50mm into the surface of previously placed layers. Care shall be taken
not to over vibrate any concrete and especially those with higher slumps. Spare vibrators
in good operating condition shall be on hand during placing operations.
Special Concreting :- The placing of underwater concrete shall follow IS: 456 in all
respects for the method employed. Special types of concrete shall be placed by methods
most suitable for the particular conditions.
Signature of Tenderer No. of Corrections Signature of NMMC Official
106
Grout :- The base plates of columns and anchor bolts shall be grouted with a mixture
consisting of 1 part of cement and 2 parts of sand with the addition of correct quantity of
water to get the desired consistency. The grout shall be thoroughly worked in and
compacted so that the entire space is filled with dense grout.
Non-shrink grout where indicated, shall be placed in accordance with the method specified
by the manufactures.
6.10 Curing and Protection
Curing of concrete with water shall comply with IS:456. Curing compounds shall be used
subject to approval by the Engineer/Architect. Finished floors shall be protected carefully
until completely set. Protection of concrete against extreme weather conditions shall
comply with the I.S.Sector.
6.11 Repairing and Patching
Pockets of rock formed due to segregation over vibration or other causes shall be
completely removed and the void properly keyed and reinforced if necessary. The face
shall be tightly formed and arranged for providing a head in the concrete. The cavity shall
be filled with the same concrete as used for the structure and thoroughly rodded or
vibrated when vibrated when possible. The filled hopper shall be left in place until
shrinkage has taken place and the concrete sets sufficiently to stay in place. While still
alive, the upper part of form and hopper shall be removed and excess concrete struck off
and finished with wood flat or trowel to match existing concrete. Any fins or unsightly
grout runs or bugles shall be removed from surfaces exposed to view. Form rod holes shall
be pointed up with cement or grouted to match the existing surface as closely as possible.
No cement washes shall be used unless particularly called for on drawings.
7.0 REINFORCED CONCRETE WORK FOR SHELL AND FOLDED PLATE WORK
7.1 General
Applicable provisions of conditions of contract shall govern the work under this section.
7.2 Work Included
The Contractor shall furnish all materials, labour, plant, equipment, tools, to complete the
work indicated or specified herein or both.
Supplying all materials, grading aggregates and transporting, handling, protecting and
storing, materials for concrete.
Preparing, sampling and testing concrete mixes.
Mixing, controlling and transporting concrete of all types and conducing field tests.
Setting, bracing, typing, aligning and checking concrete formwork and constructing panels
and special units or providing prefabricated unit forms in connections therewith.
Providing, fabricating, installing, typing steel reinforcement and dowels.
Fixing anchor bolts and sleeves and setting, typing and aligning for embedment.
Installation and aligning curb angles, pipe sleeves and drains, post sockets, inserts, furring
anchor devices, hinges, water stops, expansion joint fillers etc. embedment.
Signature of Tenderer No. of Corrections Signature of NMMC Official
107
Placing concrete for roofs, slabs and floors,
Applying and jointing plies of membranes and coal tar waterproofing materials with
protective coverings, and damp proofing coats on walls and layers under slabs.
Finishing and protecting floor slabs and preparing concrete surfaces for separate coverings,
linings etc .
Curing, removing forms, patching and correcting defects, filling form tie recesses and
cleaning concrete work.
7.3 Materials
All Material shall be as specified under clause 6.0
7.4 Concrete Mix
The Concrete shall be controlled concrete as defined in IS:456. The grades of concrete
shall be as indicated on the drawings. The water cement ration shall be in accordance with
IS:456 and for attaining greater workability an approved admixture may be provided if
such admixture does not impair the strength of concrete.
The maximum slumps shall be as follows :
Type of work Slumps
Shells (Mech. Vibrated) 25 mm
Folded Plate 40 mm
Shell Folded plate (handtamped) 50 mm
Edge beams 40 mm
The strength of various grades of concrete should be as specified in clause 6.4.
7.5 Mixing
Mixing shall be performed as specified in Clause 6.5
Tests :- Sampling, Making up, curing and testing of specimen shall comply with IS: 456,
IS:516 and IS : 1199.
7.6 Form Work
Formwork shall be as specified in Clause 6.6, subject to the following additional
specification.
7.6.1 Sequence of Operation
The Contractor shall indicate in advance to the Engineer/Architect his sequence of
operation of formwork and concreting and shall obtain prior approval of the same. The
form work shall be erected for the entire shell unit including the edge beams. The
formwork for the edge beams and traverse shall not be connected with the formwork of
the shells/folded plates. The supports required for the edge beams, traverses and
shells/folded plates in one bay shall not be disturbed until the entire concreting in that bay
is completed and the concreted has attained the requisite strength.
Signature of Tenderer No. of Corrections Signature of NMMC Official
108
The following sequence of operation shall be followed :
i) Erection of formwork for edge beams and traverses.
ii) Fabrication and placing of reinforcement and concreting upto construction joints as
indicated on the drawings.
iii) Removal of formwork with retention of requisite support.
iv) Erection of formwork for the entire shell/folded plate.
v) Fabrication and placing of reinforcement and concreting.
vi) Curing and removal of formwork.
vii) Waterproofing.
viii) Finishing.
Approval of the Engineer/Architect shall be obtained regarding design and
sequence of operation of mobile formwork if such formwork is to be used and such
formwork shall be specifically approved by the Engineer/Architect after erection.
7.7 Reinforcement
The Reinforcement work shall be carried out s specified in Clause 6.7, in addition, the
following specification shall apply.
The contractor shall maintain continually of steel between the shells/folded plates and the
edges beams and traverse.
Laps of adequate lengths of welded joints as specified shall be provided. The minimum
number of joints for lengthening of bars shall be used and the joints shall be staggered.
If the joints are but-welded, the welding shall be entrusted only to experience welders and
the welding shall be done with extreme caution in accordance with IS:275, one percent of
of bars welded shall be tested to destruction, at the cost of contractor.
Special reinforcement couplings may be provided in edge beams to avoid congestion of
bars due to laps and hooks.
7.8 Embedment
The work of embedment shall be carried out as specified in Clause 6.8.
7.9 Planning
The placing of concrete shall be carried out as specified in Clause 6.9, in addition the
following specification shall apply.
Edge beams and traverses shall be concreted first. The edge beams and traverses shall be
cast upto a level shown in the drawings.
Concreting of the shell/folded plate shall be done to full thickness and not in layers.
Construction joints shall be positioned as indicated on the drawings or as directed by the
Engineer/Architect.
The portion of an upstand beam, if any, shall be concreted as soon as possible after
concreting of the shell.
Signature of Tenderer No. of Corrections Signature of NMMC Official
109
For casting the shell/folded plate either mechanical compaction with vibrators or hand
tamping may be used. Mechanical compaction shall be done with screed vibrators. The
use of needle vibrators shall be restricted to edge beams, traverses or thickened portions of
shell. Concreting may be done in strips of convenient widths parallel to the curves edge,
each strip shall be started at the lowest level and concreted upwards. Special care shall
be taken in tamping the concrete in deep downstand stiffening beams to ensure adequate
compaction.
The thickness of the shell/folded plates at various points shall be as indicated on the
drawings and in not case shall be thickness be varied from those specified.
The thickness of the shell/folded plate shall be controlled by using cement mortar blocks of
corresponding thickness. As shell/folded plate thickness varies from the edge beams to the
crown. The thickness these two points as indicated by the Engineer/Architect.
Proper arrangement shall be made to avoid displacement of steel during placing of
concrete by providing walkways above the level of the finished concrete and supported at
intervals free from the reinforcement so as to avoid disturbance of the reinforcement. The
surface of the concrete shell/folded plate shall be smoothing with a person with a wooden
flat to the correct curve which shall be set by templates.
7.10 Curing :-
The surface shall be kept wet for a minimum period of 14 days by covering it with sand,
gunny bags, straw or other suitable material and spraying constantly wit water. Embrace
curing if permitted by the Engineer/ Arhcitect, may be adopted as an alternative and
adequate care shall be taken to prevent moisture contained in the concrete from dissipating
through any flaw in the
membrane cover or inefficiently sealed joints and edges.
7.11 Striking of Formwork :-
The process of stripping shall be graduals, without shock and so controlled that the overall
stress pattern in the structure, at any stage of stripping is reasonably similar to the pattern
expected after stripping. The sequence of operations for stripping, the periods between
concreting and the commencement of the stripping (determined as given below) and
between various operations of stripping shall have the prior approval of the
Engineer/Architect. The period between the completion of concreting and the
commencement of stripping will be concreting and the basis of the concrete having
attained 70 to 85 perfect of the 28 days strength.
7.12 Repairing and Patching :-
The work of repairing and patching shall be carriage out on specified clause 6.10
8.0 PRECAST CONTRACT WORK :-
8.1 General :-
Applicable provision of conditions of contract shall given work under this section .
8.2 Work Included :-
The contractor shall furnish materials, labour, plant and tools to completion the work
indicated or specified herein both.
Signature of Tenderer No. of Corrections Signature of NMMC Official
110
8.3 Materials :-
Materials shall be specified in clause 6.3
8.4 Workmanship :-
The workmanship shall be as specified under clause 6.0 of the specification subject to
additional conditions specified below.
8.5 Concrete Proportioning :-
The concrete mix to be adopted shall be indicated on the drawing and the strength
requirements shall confirm to IS : 456.
8.6 Formwork and Moulds :-
The form work and/or moulds for precast concrete members shall be made of metal and
true shape and dimension of the finished product as indicated on the drawings.
The moulds shall be close jointed and perfectly smooth with joints caulked to prevent
leakage of cement slurry. The moulds shall be of rigid constructions to prevent distortion
with the bulging of sides and base. The moulds should be designed with suitable fastenings
to allow them to be struck without to the casting.
The moulds shall generally be vibrated on mechanically operated vibrating table.
8.7 Marking of Units. :-
All precast members shall be marked in a manner approved by the Engineer/Architect in a
conspicuous place, with date of manufacture and marking number. The upper of the
member shall be marked distinctly to ensure proper handling.
9.0 GUNITING WORK
9.1 General :-
Applicable provisions of conditions of contract shall be f\given work under this sections.
9.2 Work Included :-
The Contractor shall provide materials, labour, tools, plant tom completion the work
indicated or specified herein or both.
9.3 Materials :-
Cement :- Cement shall conform IS : 269.
Aggregate : -
Fine aggregate shall be approved river or pit sand shall conform to IS 383
Reinforcement :- Reinforcement shall be electrically welded mesh fabric consisting of 8
guage wire in both directions spaced at 150 mm, centers. Dowels shall be 12 mm, dia MS
rounds 75 mm. Long spaced at 750 mm centers.
9.4 Proportion and Thickness :_
The mix of cement and sand shall be 1 part of cement to 3 parts of sand unless otherwise in
the bill of quantities or on the drawing.
9.5 Preparation s of Surface :-
The surface to be gunited shall be lightly chipped and thoroughly cleaned of any dirt or
grease and all the loose particles shall be removes and the surface shall be fully wetted.
9.6 Fixing Reinforcement :-
Necessary holes shall be drilled on the concrete surface at required intervals. The dowel
bars shall be inserted in these holes and tied to the main reinforcement wherever possible.
Signature of Tenderer No. of Corrections Signature of NMMC Official
111
The dowels shall be grouted and the grout shall be allowed to set at least for one day. After
the grout has set, fabric reinforcement shall be laid on the concrete surface and tied to the
dowel with 18 guage annealed binding wires. The fabrics reinforcement shall have a
minimum lap of 300 mm., and an average cover of 20 mm from the existing concrete
surface.
9.7 Workmanship :-
Water pressure shall be 1.05 kg / cm2 guage. Air pressure shall be 2.46 kg./cm2 gauge for
30 m. length of hose and shall be increase by 0.35 kg/cm2 gauge for every additional 15 m.
length of hose or part thereof. Pressure in the mixing chamber. The quantity of water
added shall be regulated and the water cement ration shall be 0.25 to 0.30 by weight.
The mix shall be shot at right angles to the surface and all rebound materials shall be
removed and shall not be used. Loose sand deposited shall be removed. At the end of the
each day`s work a thin edge shall be left.
Where the thickness of guniting is such it has to be performed in more than one layer, a
minimum of 5 hours shall be allowed between completion of one layer and starting of the
next layer to reduce the undesirable effects of shrinkage.
9.8 Curing :-
Starting about 6 hours after completion of the spraying, the surface shall be cured for a
period of 7 days of methods approved by the Engineer/ Architect.
9.10 Guarantee of Work.
The contactor shall give a guarantee for the gunning work against any leakage, any wear
and tear for a minimum period of six months after the completion of the work. In case any
defects are observed during this period, the contractor shall rectify the same at his own
cost.
10.0 Mortar for Bricks work and plaster work.
10.1 General :-
Applicable provision of condition of contract shall govern work under this section.
10.2 Work Included :-
The contractor shall furnish labour, materials, tools, plant and scaffolding so as to
completion the work indicating or specified herein or both.
10.3 Materials :-
Cement :- Cement used shall conform to IS 26
Sand :- the sand shall be approved river or pit sand and it shall perform to IS 1542 for
plaster and IS 2116 for masonry mortar.
The sand for mortar for masorary work and plaster shall be evenly graded from coarse to
fine, free from loan, clay, dust or organic matter and shall be subject to approval of the
Engineer/Architect. If directed, it shall be washed or screened before use without any extra
cost.
Water :- water shall be clean and of potable quality.
Signature of Tenderer No. of Corrections Signature of NMMC Official
112
10.4 Mortar Proportion :-
The proportion of cement and sand for martar shall be as indicated on the drawing unless
otherwise specified. The proportion of time and sand for mortar shall be as indicated on the
drawings.
10.5 Workmanship :-
The workmanship shall conform to IS 2250 for preparations of masonry and to IS 1661 for
plaster.
The cement and sand shall be thoroughly mixed dry in spefied proportion. Then the water
shall be added by sprinkler just sufficient to make a stiff and workable paste. In case of
mechanical mixing the mortar shall be mixed for at least three minutes and for hand
mixing the mortar shall be mixed back and forth for to the 15 minutes with additions of
water.
10.6 Re-tempering :-
Mortar that stiffened because of evaporation of water from the mortar be re tempered by
adding water as frequently as necessary to restore the requirements of consistency but this
re-tempering shall be permitted only within two hours form the time of additions of
cement. `
11.0 Bricks work :-
11.1 General
Applicable provisions of conditions of contract shall given work under this section.
11.2 Work Included :-
The contractor shall furnish labour, materials, tools, and plant so as to complete the work
indicated or specified herein or both.
11.3 Materials :-
Bricks The bricks used shall conform to IS 1077 Bricks are to be whole sound, well
burnt, free from cracks, square and well shaped, uniform in size and shall emit a clear
ringing sound when struck.
Cement Mortar :- Mortar shall be as specified under clause. 10.0
11.4 Workmanship:-
Bricks Work :- The work of the bricks work shall be carried out y the contractor in uniform
a manner.
All the bricks shall be kept under water till they are completely soaked and used on the
works on their becoming skin dry.
The contractor shall set out builds all bricks work to the dimension, thickness and height,
shown on the drawings, the contractor shall build bricks work in English bond and half
bricks walls and casing to pipe, chases, etc. in stretcher bond. Brickbats shall not be used
expect where require for bond.
Signature of Tenderer No. of Corrections Signature of NMMC Official
113
The contractor shall lay bricks in full mortar beds with shoved joints. The joints are not to
exact 10 mm. In thickness and are to be full or mortar. Close, well finished and neatly
struck. The vertical joints in any course shall not be nearer than a quarter of a bricks length
from those in the course below. All the joints shall be same width except for small
variations to maintain bond. The bricks work shall be laid plumb and trim to line and level.
No portion of bricks work shall be raised more than 1 metre above another at one time. If
the mortar in any course has begun to set, the joints shall be raked out before another
course is said. The top course of bricks work in RC framed structure shall be wedged
against RC surface and joints well filled with mortar.
The contractor work as it progresses shall be thoroughly watered on it faces and top. The
contractor shall keep wet all brickwork for 5 days after laying. The course shall be raked
unless otherwise specified. Net work shall be cleaned and thoroughly watted before joining
new work to it.
Any work in which the mortar perishes shall be dismantled and rebuilt by the contractor at
his own expense.
11.5 Cleaning :-
The contractor shall carry out work in as clean manner as possible and shall remove excess
materials and mortar droppings daily.
Where bricks walls and partitions are to receive plaster, excess materials and mortar
dropping shall be removed and the surface shall be brushed clean.
During cleaning operations, adjacent work shall be protected and any damage resulting
from improper protection shall be made good by the contractor at his own cost.
11.6 Scaffolding :-
Generally scaffolding shall conform to IS 2212 and shall be designed to withstand all
loads and to ensure the completions safety of workman and materials.
The scaffolding must be double i.e. it should have two sets of standards. Where this is not
possible, the inner end of the scaffolding pole shall rest in a hole provided in a head or
course only and only one header for each pole shall be left out. Putlog holes are not to be
allowed in pillar under 2.4 m. width.
12.0 STONE MASONARY (RANDOM RUBLE AND COURSED)
12.1 General :-
Applicable provisions of condition of contract shall given work under this section.
12.2 Work Included :_
The contractor shall furnish labour, material, tools and plant so as to complete the work
indicated or specified herein or both.
Signature of Tenderer No. of Corrections Signature of NMMC Official
114
12.3 Materials
Stone :- Building shall conform to IS 1127 Rubble stone shall be strong, dense, compact,
close grained and uniform in texture and colour with reasonable facility of working. It
should free from cracks, flaws, decay and sandholes and shall be taken from approved
quarries.
A fresh fracture of stone should be bright, clean and shape without loose grains and free
from any dull earthy appearance. The stone shall be properly dressed after quarrying before
they are put to use in the structure. Stone newly quarried containing quarry sap should be
protected from frost until the quarry sap evaporates.
Mortar
The mortar for stone masonry shall normally be of cement sand mortar. The mortar
proportions shall be as indicated on the drawings.
12.4 Workmanship (Random Rubble masonry uncoarsed)
Workmanship for stone masonry shall conform to IS 1597 No stone shall be less than 250
mm in thickness or less than 300 mm. In each horizontal dimension or if the thickness be
more than 300 mm. The lease horizontal dimension must not be less than thickness.
Dressing :- the stones after being fully cleaned and wetted are to be set in the work as
received from quarry and without further dressing of any sort except that of knocking off
weak corners and edges with the mason`s hammer. The stones must be laid on their natural
or quarry bed.
Bond Laying :- The stones shall be carefully laid so as to break joints by at least 75mm
and solidly bedded with close joints. No joints shall exceed 20 mm in thickness. Chip of
stones and spalls shall be wedged into the work wherever necessary so as to avoid thick
beds or joints of mortar. No dry work or hollow spaces shall be allows in the masonry
anywhere. Every stone whether large or small shall be flush in mortar, smaller stones used
in the filling being carefully selected to fit roughly the interstices between the larger ones.
The outside and inside faces of masonry in walls must be carried up in the same plain as
the faces the proceeding length.
Face Stone :- The face stones shall be laid as far as possible without pinning in front and
they shall be selected from the mass of quarry stone for greater size, good beds and
uniform colour. They shall be laid so that they shall not be of greater height than either the
breadth on face of length of tail in the work.
Quoins :- Quoins which must be of the same height as the course in which they occur and
should be formed of header stones from 220 mm. To 450 mm long according to the height
of the course and laid lengthwise alternatively along each face. They should be laid square
on their beds which should be dressed to a depth of at least 100 mm. The corner of each
quoin should have a chisel draft of 25 mm. On each side to facilitate checking the verticals
alignment.
Finishing :- The exposed faces of work shall be cement flush pointed if time mortar is
used unless otherwise specified. If cement mortar is used the joints may be flushed as the
work proceeds. Where stone work is to receive plaster or to be pointed other that flush
pointing, the joints shall be raked to a minimum depth of 12 mm. Provide proper bond.
Any work in which mortar dry, white or powdery through neglect of watering, then the
masonry shall be dismantled and rebuilt by the by the contractor at his own expenses.
Curing :- Curing shall be done for a period of 5 days.
12.5 Workmanship (Random Rubble Masonry Coursed )
Height of Courses :- The stones after being well cleaned and wetted shall be laid in
horizontal courses of equal depth of not less than 150 mm and shall be set full in mortar.
Signature of Tenderer No. of Corrections Signature of NMMC Official
115
Dressing :- the joint between two continuous face stones in the same course must be truly
vertical and the two stones must be hammered of chisel dressed as to be in constant for at
least 75 mm depth from the face of the wall. The beds of face stones also should be
hammer or chisel dressed for at least 75mm depth.
Bond and laying :- the stones shall be laid on their broadcast face in cement mortar and
beaten into position with mallet, care being taken that the mortar is well filled into the
joints. The interior of the wall is to be carefully constructed with proper sized
approximately in every course. The other details shall be followed as detailed forbond or
header stone for random rubble masonry.
Quoins:- The same specifications shall be followed as detailed random masonry for
quoins.
12.7 CLEANINGS
The contractor shall carry out the work in a clean manner and shall remove excess
material, mortar droppings excess materials, mortar droppings shall be removed and the
surfaces shall be brushed clean during cleaning operation, adjacent work shall be protected
and any damage shall be made good at the cost of the contractor resulting from improper
protection.
FINISHING
The exposed surface of the work shall be flush pointed unless otherwise specified. Unless
the interior faces is to be plastered, it shall be the same as the exterior face.
CURING
Curing shall be done for a period of 5 days.
13.0 SOLING AND HARD CORE
13.1 General
Applicable provision of conditions of contract shall govern work under this section.
13.2 Work included
The contractor shall furnish labour, materials tools and plant so as to complete the work
indicated or specified herein or both.
13.3 Materials
Stones:- The boulders for soling shall be granted, trap, basalt, or similar hard stone
approved by the engineer / Architect. Soling stone shall generally be 250mm thick. The
other dimension shall be 300mm to 375mm unless otherwise specified.
Bricks: - The bricks used shall conform to IS 1542
Sand: - The sand used shall be approved river or pit sand and it shall conform to IS:1542
Graveli:- It shall be free from dirt, clay, leaves etc.
Ballast:- The stone ballast shall be of durable tough and close hard texture.
Brick Ballast :- Brick ballast shal be broken from 1st class bricks which are well burnt or
over burnt. The porous or spongy variety shall not be permitted to be used.
13.4 Workmanship
Stone boulder soling : - The sub- grade shall be dressed to correct level and shall be
rammed or rolled to proper consolidation before laying the soling. Stones shall be placed
close to each other. The specified thickness shall be made up in one layer only. The
Signature of Tenderer No. of Corrections Signature of NMMC Official
116
crevices between the stones shall be hand packed first with smaller pieces and hammered
into place so as to completely fill up the voids. No stone after packing shall move or tilt in
any direction when walked over.
Brick flat single layer soling:- The earth shall be filled in layers not exceeding 200mm
thick. The filled layers shall be sprinkled with water and well rammed by head rammers so
as to consolidate it thoroughly. The bricks shall be placed on a thin cushion of sand and
the joints shall be fully filled by dry sand and finally broom.
Bricks flat double layer soling :- The second layer of bricks be placed only after finishing
the first layer and the joints shall be fully filled by dry sand and finally broom.
Rammed gravel or ballast hard core :- Gravel or ballast to be laid over prepared bed shall
be clean free admixture. The ballast shall not be more than 10mm to 40 mm size. The
gravel or ballast shall be laid in layers of up to 75mm to the specified thickness and the
voids shall be filled with sand and rammed by hand rammers dry and wet and preparedly
consolidated.
Broken Bricks hard core :- Broken over burnt bricks aggregate (Jhama) of 30 mm size
shall be laid over prepared bed. The broken bricks aggregate shall be laid in one or more
layers to the specified thickness and well consolidated by hand rammers.
14.0 CAST IN-SITU CEMENT CONCRETE FLOORING:-
14.1 General
Applicable provisions of conditions of concrete shall govern work under this section.
14.2 Work included :- The contractor shall furnish labour, materials, tools and
plant so as to complete the work indicated or specified herein or both.
14.2 Materials :-
Cement :- Ordinary Portland cement, white and coloured, shall conform to IS: 269.
Aggregate :- The aggregate shall conform to IS: 383. the coarse aggregate shall generally
be of the following sizes.
Base concrete - Graded from 40 mm and below.
Cement Concrete topping of - Graded from 16mm and
Thickness 40mm and above - below.
Cement concrete topping of - Graded from 12.5m and
Thickness 25mm - below.
Under layer of cement con - Graded form 12.5 mm and
Crete Topping in 2 layers - below.
Signature of Tenderer No. of Corrections Signature of NMMC Official
117
The fine aggregate shall be either of grading zone 1 or 2 table 2, IS; 2571. Generally 90 %
of the aggregate shall pass thorough IS sieve
4.76mm.
Water :- Water shall be of potable quality.
Glass :- Glass strips used shall be 2mm thick and the depth shall be equal to the overall
thickness of the flooring.
Colour Pigment :- Pigments, synthetic or otherwise, used for coloring shall have
permanent non-fading colour, shall not contain matters deter mental to concrete. The
pigment must be of detrimental to concrete. The pigments must be of approved brand and
tints shall be uniform.
14.4 Workmanship :-
14.4.1 Plain cement Concrete Flooring :-
Generally workmanship shall conform to IS 2571 code of practice for – laying in-situ
concrete floors. If the floor finish is to be laid over consolidated ground or a layer of hard
core, cement concrete of proportion 1:4:8 or 1:5:10 shall be poured as a base layer to the
thickness indicated on the drawings. In the case of structural slabs, the slab itself will form
the required base.
The area requiring finish shall be divided into suitable panels so as to reduce the risk of
cracking. No dimension of a panel shall exceed 4min case of floor finish laid
monolithically with base concrete and 2m in case of floor finish laid separately on a
hardened base length of a panel shall not exceed 1 ½ its breadth.
Paneling shall be done by fixing timber or steel strips of depth equal to the combined
thickness of base concrete and topping. Before being fixed in position these strips shall be
coated with a thickness coat of time wash. Flooring shall be laid in alternative panels, the
intermediate panels being filled in after one of to days. However, if glass or aluminum
strips are specified for effective separation of panels, the base concrete and toping may be
laid simultaneously in all the panels.
Floor finish laid monolithically with base concrete :-
The sub base shall be properly wetted and divided into panels. The base concrete shall be
poured and tamped and screened to levels suitable to accommodate the topping and given
the desired slope. The surface shall be left rough to provide bond with the topping.
On the green surface of the base concrete topping shall be placed in position as soon as the
base has stiffened enough to allow workmen to tread over it by placing planks. The mix for
the topping shall be as shown in drawing and as stiff as possibly consistent with
workability so as to prevent accumulation of excess water on ???? should any water rise to
surface during compaction and screening, it shall be mopped up. The topping shall then the
floated with the wooden float to under the surface.
Floor finish laid separately on hardened concrete base.:-
The sub base shall be properly wetted and the base concrete laid, if possible over the whole
area at a stretch. The surface shall be left rough to provide adequate bond for the topping
by wire brushing two to three hours after its laying.
Before the topping is laid., the surface of the base shall be thoroughly cleaned of loose
materials, dirt and laitance by wire brushing. Where this is not possible, chipping or
hacking shall be done. The surface shall be soaked with water for 12 hours before laying
the topping. The surplus water shall be mopped up, cement slurry spread and then the
concrete for the topping deposited in suitably divided panels. The mix for the topping shall
Signature of Tenderer No. of Corrections Signature of NMMC Official
118
be as indicated in drawing and as stiff as possible consistent with workability so as to
prevent accumulation of excess water laitance. After thorough consolidation the topping
shall be struck off level and surface floated with a wooden float. Is shall be tested with a
straight edge and mason`s spirit level to detect any inequalities and may undulations found
shall be made good immediately.
14.5 Laying toppings in two layers. :-
Where it has been specified that the topping is to be laid in two layers to obtain very
smooth and dense finish, the base concrete and under-layer of topping shall be laid as
above with the exception that the surface of the finished smooth but left rough after
tamping and leveling.
The top 15mm thick wearing of mix1:2 to 3 cement concrete of consistency stiffer than
that of under-layer of concrete shall then immediately laid over the rough but green surface
of under-layer and thoroughly temped, struck off level and the surface floated with the
wooden float. The surface shall then be tested with a straight edge and mason`s spirit level
to detect any undulations. If any these shall be made good and then the surface finished
smooth as under.
14.6 Finishing the surfaces :
After the concrete has slightly hardened it shall be finished by trowelling or floating.
Finishing operations shall start shortly after the compaction of concrete and shall be spread
over a period of one to six hours depending upon temperature and atmospheric conditions.
The surface shall be trowelled three times at intervals so as to produce a uniform and hard
surface. Immediately after laying only just sufficient trowelling shall be done to give a
level surface. Sometime after the first trowelling, the duration being guided by temperature
and rate of setting of cement, the surface shall be retrowelled to close any pores in the
surface and to draw out and mop up any excess water in concrete or laitance. The final
trowelling shall be done well before the concrete has become too hard but at such a time
that considerable pressure is required to make any impression on the surface. Trowelling of
a dry cement mix on the surface shall not be permitted.
14.7 Curing
As soon as the surface has hardened beyond damage, it shall be kept continually moist for
at least 15 days by impounding water on it.
14.8 Polishing
The floor shall be polished with machine eight weeks after laying when the floor is
sufficiently matured by expert trained polishers. The floor shall than be sprinkled with zine
or tin oxide and rubbed hard with rags. The final polish shall be done with wax or with
patent polish.
14.9 Coloured Cement Concrete Flooring
Where coloured finish is finish is indicated, the top shall be finished with coloured cement
as specified. If coloured cement is not available, the pigment shall be mixed in the
proportion, one part of pigment with three parts of cement.
Signature of Tenderer No. of Corrections Signature of NMMC Official
119
The colouring material and cement shall first be mixed dry. Special attention shall be paid
to the mixing of colour, which should be screened twice with a final screen and again
through final muslin before use. All the colour required for one room shall be mixed in one
lot. For red colour the mixture shall consist of one part of iron oxide to three parts of
cement. For green the colour mixture shall consist of one part of chromium oxide to 3 parts
of cement. After dry mixing, the minimum quantity of water required for workability shall
be added gradually until a paste of the required consistency is obtained. Dry colour shall
not be used to finish the surface of coloured concrete floor. Coloured paste shall be applied
with wooden floating boards and English trowels. 0.06 cu.m. of colour mixture shall be
used for 10 sq.m. of surface.
Any cracks, ruts, disfiguration or discolouring of surface shall be made good without extra
charge. The finished portion of the floor shall be kept wet for at least 15 days.
Coloured concrete shall be polished with Nos. 1, 2 and 3 polishing stones. After rubbing
with these stones, the surface shall be sprinkled with zinc or tin oxide and rubbed hard with
rags. The final polish shall be done with wax or with patent polish. For light colours,
celluloid trowels made by fixing a sheet of celluloid on a wooden trowel may be used.
15.0 TERRAZZO FLOORING WITH TILES
15.1 General
Applicable provisions of Conditions of Contract shall govern work under this section.
15.2 Work Included
The Contractor shall furnish labour, materials, tools and plant so as to complete the work
indicated or specified herein or both.
15.3 Materials
Plain or Coloured Terrazzo Cement Tiles : The tiles shall conform to IS : 1237. They shall
be of the type, quality, colour and size as indicated on the drawings or in the Bill of
Quantities and shall be approved Engineer / Architect. The distribution and size of marble
chips shall be as approved by the Engineer / Architect.
Ordinary Portland Cement, White or Coloured Cement
The cement shall conform to IS : 269
Sand : The sand shall be river sand or from approved pits and shall conform to IS : 383.
Aggregate : Aggregate used for mortar for fixing the tiles and in the backing layer of tiles
shall conform to IS : 383. For the wearing layer of tiles, unless otherwise specified, marble
chips, marble powder or a mixture of the two, shall be used.
Pigment : Pigments, synthetic or otherwise shall conform to relevant Indian Standards.
15.4 Preparatory Work
The delivery and storage of tiles shall be so arranged as to minimize handling. Adequate
precautions shall be taken to prevent accidental damage to tiles while unloading.
Clean dry storage space shall be provided at the site for all the materials. The tiles shall be
storage in a room or under such cover as will prevent exposure to damp, sun, rain,
accidental injury or staining.
15.5 Workmanship for laying concrete tiles
Generally workmanship for laying tiles shall conform to IS; 1444 – code of practice for
laying and finishing cement concrete flooring tiles.
Redding : The surface of the sub-floor shall be thoroughly cleaned of dirt, loose particles
and laitance (in case of cement slabs) by scrubbing with a wire brush. The surface shall
then be thoroughly cleaned and well wetted down without forming any water pools on the
Signature of Tenderer No. of Corrections Signature of NMMC Official
120
surface. Screwed pads shall be set up to indicate required levels on the lean damp surface
of the sub – floor in this grout one at a time and gently tapped with a wooden malled to
proper bedding and level of the adjoining tiles. He joints between tiles shall be straight and
shall not exceed 1.5mm in width.
In area adjoining walls, the tiles shall project about 10mm in to the plaster, skirting or dado
as the case may be.
Polishing : After fixing of tiles the flooring shall be allowed to mature undisturbed for
several days. Then the floor shall be polished by machine using carborandum stones of he
following grit :
a) For leveling (where the tiles are supplied
underground ) - 24 to 60
b) For grinding (for removal of filling ) - 120 to 150
c) For final grinding - 220 to 350
sufficient quantity of water shall always be used when polishing with machine to prevent
scratching.
15.6 Skirting and Dado Work
Skirting and dado shall be fixed only after laying the tiles on the floor. Where tiles re to be
fixed on walls, the portion of the wall to be so tiled shall be left unflustered.
Before fixing tiles on brick or concrete wall, the wall surface shall first be wetted with
clean water. Thereafter it shall be evenly and uniformly covered with a coating of lime
mortar about 20mm thick before the cushioning mortar has hardened, the back of each tiles
to be fixed shall be covered with a thin layer of neat cement paste and te tile shall be gently
tapped against the wall with a wooden mallet. The fixing shall be done from the bottom of
the wall upwards. Each tile shall be fixed as close as possible to the one adjoining, and any
difference in the thickness of the tiles shall be evened out in the cushioning mortar or
cement paste so that all he tile faces are set in conformity with one another.
Skirting and ado shall be ground and polished just as for floor work but by machine
suitable for he purpose. Skirting and dado may also be polished by hand by rubbing down
with suitable polishing stone evenly and without scratching the surface.
Upon completion of tiling work, it shall be thoroughly cleaned with water using a
scrubbing brush, coarse cloth or broom. Acids, harsh abrasive cleaning powders or steel
wire shall not be used under normal circumstances.
16.0 IN-SITU TERRAZZO FLOORING
16.1 General:
Application provisions of Conditions of Contract shall govern work under this section.
16.2 The contractor shall furnish labour, material, tools and plant so as to complete the work
indicated or specified herein or both.
Signature of Tenderer No. of Corrections Signature of NMMC Official
121
16.3 Materials
Cement : The cement shall be ordinary Portland conforming to IS : 269 or Portland blast
furnace slag cement conforming to IS :455.White cement of approved quality may be used
for the topping.
Sand : The sand shall be river sand or from approved pits and shall conform IS :383
Aggregate : The aggregates used in the topping shall be of marble aggregate unless
otherwise specified. The size shall be as approved in accordance with clause 5.2 of IS :
2114 – 1962. Marble powder used in the topping shall pass through IS sieve 30.
Aggregates for the under layer and base concrete shall conform to IS: 383.
Pigments : Pigments to be incorporated shall be of permanent colour and shall conform to
Appendix A to IS : 2114.
Dividing Strips : Dividing strips shall be of Aluminium, glass or plastic of thickness not
less than 1.5mm and width not less than 25mm.
Water : Water shall be of potable quality.
16.4 Mix Proportions and Thicknesses :
The base concrete when terrazzo finish is laid over ground shall be lean cement concrete
mix 1:5:10 or lime concrete. The thickness of base concrete shall not be less than 100mm.
The cushioning layer, when terrazzo finish is laid over structural slab shall preferably be of
lime concrete. The thickness of cushioning layers shall not be less than 75mm.
The under layer shall be cement concrete of mix 1:2:4 and the maximum size of aggregate
shall not exceed 1mm. The mix for the topping shall have cement, marble powder and
marble aggregate and water in the proportion as specified in IS : 2114.
If coloured terrazzo finish is indicted, the proportions in which pigments are mixed with
ordinary Portland cement or white cement to obtain different colours shall be as specified
in Table 1 of IS : 2114. The complete quantities of cement and pigment required for one
operation shall be mixed at the beginning of work and stored properly to avoid variation in
colour.
16.5 Workmanship :
The base concrete shall be finished to a reasonably true plain surface and to level which is
lower than the level of the finished floor by the depth specified for the thickness of the
terrazzo flooring. Any slope indicted for the finished floor shall be incorporated in this
base course.
To prevent chances of cracking, the floor shall be divided into suitable panels, not
exceeding 2 sq.m. in area. If dividing strips are indicated, these shall be fixed over the base
concrete to the full depth of he terrazzo finish.
The coloured cement shall be mixed thoroughly in the dry stage with marble powder. The
binder so obtained the chips in the required proportions shall then be mixed dry together.
Water shall then be added in a fine spray while the materials are worked t a consistency
which is plastic but does not flow. The mix shall be used in the work within half an hour of
the addition of water.
Signature of Tenderer No. of Corrections Signature of NMMC Official
122
The base over which flooring is to be laid shall be cleaned of all dirt, laitance and loose
material and then well wetted without forming any water pools on the surface. It shall then
be smeared with cement slurry and immediately thereafter the under layer shall be spread
and leavelled with a screeding board.
Terrazzo topping shall be laid while the underlayer is still plastic, about 20 hours after the
underlayer is laid. A cement slurry. Preferably of the same colour as he topping shall be
brushed on the surface immediately before laying is commenced. The terrazzo mix shall be
placed on the screed bed and compacted thoroughly by tamping and trowelled just
sufficient to give a level surface.
The surface shall then be rammed in order to consolidate the terrazzo, preferably with a
piece of smooth marble stone of size 15cm x 2.5cm. This may be followed by trowelling.
In trowelling pressure rather than rotary action shall be used to achieve a smooth surface.
16.6 Curing
The surface shall be left dry for air – curing for a duration of 12 to 18 hours depending
upon temperature conditions. It shall then be cured by impounding water for at least four
days.
16.7 Grinding
Four days shall be allowed to lapse after completion of laying for grinding to commence
manually. If machine grinding is specified this period shall be seven day. The first grinding
shall be done with carborandum stone of 60 grit size. The surface shall then be washed
clean and grouted with neat cement grout of cream like consistency. It shall then be
allowed to dry for 24 hours and wet cured for four days again. The second grinding shall
be done with 80 grit stone. After another surface grouting, a third grinding with 120 to 150
grit size stone shall be done. The surface shall then be washed clean, allowed to dry for 12
hours and wet cured again for four days. After a last grinding with carborandum stone of
320 to 400 grit size, the surface shall be washed clean and rubbed hard with felt and
slightly moistened oxalic acid powder.
16.8 Terrazzo skirting and dados
For terrazzo finish on vertical surface the underlayer shall consist of a layer of stiff cement
sand mortar 1:3 finished rough to provide keying.
The combined thickness of underlayer and terrazzo shall not be less than 20mm and the
terrazzo topping shall not be less than 6mm.
Other details shall be the same as for in-situ terrazzo flooring except that grinding shall be
manual.
17.0 PVC AND VINYL ASBESTOS FLOORING
17.1 General
Applicable provisions of conditions of contract shall govern work under this section.
17.2 Work Included
The contractor shall furnish labour, materials, tools and appliances so as to complete the
work indicated or specified herein or both.
Signature of Tenderer No. of Corrections Signature of NMMC Official
123
17.3 Materials
PVC (VINYL) asbestos tiles :- shall be plain or mottled, 300mm, or 450mm square, 3m
thick smooth surfaced, homogeneous tiles conforming to IS : 3461. It shall be of a
nonfadeable, uniform colour indicated on drawings and shall comply with all the relevant
requirements associated with tests specified in IS : 3464 “Methods of test for plastic
flooring and wall tiles”.
PVC sheeting and tiles :- shall be homogenous, flexible material of he size specified in the
drawing or Bill of Quantities. It may have a backing of hessain, conforming to IS : 2818,or
other woven fabric. The thickness shall be 3mm ordinarily and 4mm when a backing is
provided.
All characteristics of the material shall conform to IS : 3462 when tested in accordance to
IS : 3464.
Underlay :- Shall be in situ trowelled screeding to the sub –floor.
Adhesives :- Shall of approved make and shall conform recommendations of the flooring
manufacturer. Generally rubber based adhesives shall be used.
17.4 Sampling
The contractor shall submit to the Engineer/ Architect samples of flooring he proposes to
use and all materials in corporated in he work shall be similar to the sample approved by
the Engineer /Architect.
17.5 Workmanship
Workmanship shall generally comply with IS : 5318.
17.5.1 Preparation of the sub – floors
Concrete sub – floors shall be laid in two layers with an effective damp – proof course
located in between. The top of the lower layer shall be finished smooth and when set and
sufficiently hard, painted with two costs of bitumen conforming to IS : 1580 applied at the
rate of 1.5 kg/M2. Alternatively bitumen felt made to IS : 1322 shall be sandwiched
between the two layers. The sub-floor concrete shall be finished using a powder float.
Six weeks time shall be allowed for the water to dry completely form the concrete floor.
Then if power floating has not already been adopted, the finish required for laying PVC
flooring shall be producted with a trowel on a screed applied to the sub-floor concrete.
For old concrete surfaces cleaning and de-greasing shall suffice if the existing floor is even. If
unevenness exists, the surface shall be scrapped free of all foreign materials, swept clean
and wetted for 24 hours by sprinkling water. Then screen topping of 3mm thickness shall
be provided over the concrete.
17.5.2 Setting out
The surface to be floored shall be cleaned with a dry cloth and checked for sufficient
dryness in consonance with Appendix a of IS : 5318. The flooring shall not be laid under
high humidity conditions (70%) as this affects the adhesive strength.
Signature of Tenderer No. of Corrections Signature of NMMC Official
124
The tiles shall be spread on the floor, without any adhesive, from the centre of he room
towards the walls or as specified by the Architect, while placing the tiles, the sides of each
tile shall be cut and finished as necessary to make a uniform setting. The alignment shall
be checked after setting out each row. Cut pieces of tiles, if necessary, shall be set along
the walls.
17.5.3 Fixing
The adhesive shall be applied according to the recommendation of the manufacturer. It
shall be applied uniformly on the back of tiles as well as on the floor. After application
sufficient time (about half an hour ) shall be allowed for he adhesive to become tacky but
not mark the fingers.
The tile shall then be in position on the floor along one edge and rolled out to remove any
entrapped air bubbles. After laying all the tiles, a 5 kg. Wooden roller shall be used to
ensure full contact between tiles and the underlay. Work shall be constantly checked
against guidelines to ensue that all the four edges of adjacent tiles meet accurately.
Any adhesive that may squeeze up between the tiles shall be removed with a wet cloth
before it harness. Hardened adhesive shall be removed with a solvent consisting of one part
of commercial butyl acetate and three parts of turpentine oil.
The floor shall not be out to service within 24 hours of laying. After the tiles are fully
bonded, they shall be cleaned with wet cloth soaked in warm soap solution (two spoons of
soap in 5 liters of warm water).
18.0 GRANOLITHIC FINISH AND FLOOR HARDENER FINISH
18.1 General
Applicable provisions of Conditions of contract shall govern work under this section.
18.2 Work Included
The contractor shall furnish labour, materials, tools and plant so as to complete the work as
indicated or specified herein or both.
18.3 Materials
Cement : Cement shall conform to IS : 269 or IS : 455
or IS : 1489
Aggregates : It shall be approved granite, basalt, trap or
quartzite chippings and the grading shall conform to
Table 1 of IS : 5491.
Sand : The sand shall be approved river sand and
shall conform to IS : 383 The grading shall conform
to Table 2of IS : 5491.
Water : Water shall be of potable quality.
Floor Hardner : It shall be of best quality and of approved make. The
thickness of mix with floor hardner shall be of 20mm
or as shown in the drawings of Bill of Quantities.
Signature of Tenderer No. of Corrections Signature of NMMC Official
125
18.4 Proportion of Mix
The proportion of mix for granolithic flooring shall be 1 part of cement, 1 part of san and 2
parts of granite chippings.
18.5 Workmanship
The floor topping shall be laid in suitable panels. While laying the topping on structural
slab monolithically, no dimension of panel shall exceed 4mand when the topping is laid on
hardened base, no dimension shall exceed 2m. In case of the ground floor the dimensions
of the topping panels shall match those of the base concrete : length of panel shall into
exceed one and a half time its breadth.
18.5.1 Laying granolithic topping monolithically with the base concrete
The topping shall be laid within two to thee hours of laying he base concrete. At the time
of laying the topping he base shall be still green but sufficiently firm to enable the
workman to work over it by placing planks on the surface. The topping shall be laid in
suitable panels ad thoroughly compacted to the finished thickness. The surface shall be
checked for undulation and made even using wooden floats. When the surface has slightly
hardened, it shall be finished smooth.
18.5.2 Laying topping on hardened base and hardened structural slab.
The base concrete shall be thoroughly cleaned of all dirt, loose particles etc. and roughened
by chipping or hacking at close interval. The surface shall then be soaked in water for
several hours and the excess water removed by mopping immediately before laying the
topping. Neat cement slurry shall be brushed on the prepared surface of the base concrete
and the topping laid in suitable panels as described in clause 18.5.1.
19.0 TIMBER DOORS, WINDOWS, WOODWORK AND JOINERY
19.1 General
Applicable provisions of conditions of contract shall govern work under this section.
19.2 Work included
The contractor shall furnish labour, materials, tools and plant to complete the work
indicated or specified herein or both.
19.3 Materials
Timber : Unless otherwise specified, all timber used in the work shall be as specified in IS
: 1003 and shall be of Class I, Grade I only.
Plywood :- Plywood where specified for use in the work shall be of the type indicated in
the Bill of Quantities or the drawings and shall conform to IS : 303.
Flush Door Shutters :- Unless otherwise specified, flush door shutters shall be
manufactured in accordance with IS : 2202 and thickness and type as indicated in the
drawings or in the Bill of Quantities. They shall be solid core as indicated on the drawings
or in the Bill of Quantities.
Hold Fasts :- Unless otherwise specified, hold fasts shall be made of 40mm x 6mm MS
flats 225 m long with a right angle bend at the frame end and 50mm split end at the other.
Builder’s Hardware :- Various articles of hardware shall conform to relevant Indian
Standards. All articles shall be of the quality of samples approved by the Engineer /
Architect.
19.4 Workmanship, Dimensions, Tolerance and Finish :
Unless otherwise specified, construction and workmanship, tolerance, finish and inspection
and test for all doors and windows and ventilators and any other woodwork shall be as
specified in IS : 1003.
Signature of Tenderer No. of Corrections Signature of NMMC Official
126
Timber used shall be free from sapwood, flaws, shakes or cracks and shall have prior
approval of the Engineer/Architect. All pieces after being finished shall hold their full
figured dimensions without patching or plugging of any kind.
Timber buried in ground and the portions of woodwork embedded in or resting on walls
shall be treated with boiling coal tar or other approved protective materials. All steel
works embedded in lime masonry or exposed shall be suitably protected against rust.
All Wood work must be inspected and certified before being put into place. In no case
shall the wood work be painted or otherwise treated before it is inspected.
19.0 TIMBER DOORS, WINDOWS, WOOD WORK AND JOURNEY
19.1 General
Applicable provisions of conditions of contract shall govern work under this section.
19.2 Work included
The contractor shall furnish labour, materials, tools and plant to complete he work
indicated or specified herein or both.
19.3 Materials
Timber :- Unless otherwise specified, all timber used in the work shall be as specified in
IS:1003 and shall be of Class I, Grade I only.
Plywood :- Plywood where specified for use in the work shall be of the type indicated in
the Bill of Quantities of the drawings and shall conform to IS:303.
Flush Door shutters :- Unless otherwise specified, flush door sputters shall be
manufactures in accordance with IS: 2202 and of thickness and type as indicated in the
drawings or in the Bill of Quantities. They shall be solid core as indicated on the drawings
or in the bill of Quantities.
Hold Fasts :- Unless otherwise specified, hold fasts shall be made of 400mm x 6mm MS
flats 225mm long with a right angle bend at the frame end and 50mm split end at the other.
Builder’s Hardware :- Various articles of hardware shall conform to relevant Indian
Standards. All articles shall be of the quality of samples approved by the
Engineer/Architect.
19.4 Workmanship, Dimensions, Tolerance and Finish
Unless otherwise specified, construction and workmanship, tolerance, finish and inspection
and test for all doors and windows and ventilators and any other woodwork shall be as
specified in IS:1003.
Timber used shall be free from sapwood, flaws, shakes or cracks and shall have prior
approval of the Engineer/Architect. All pieces after being finished shall held their full
figured dimensions without patching or plugging of any kind.
Timber buried in ground and the portions of woodwork embedded in or resting on walls
shall be treated with boiling coal tar or other approved protective materials. All steel
works embedded in lime masonry or exposed shall be suitably protected against rust.
All wood work must be inspected and certified before being put into place. In no case
shall the wood work be painted or otherwise treated before it otherwise treated before it is
inspected.
All wood work in building shall, after it has been certified, be treated with a priming coat
of approved pint before being fitted in position. The succeeding coats of paint or other
finish shall be applied after the wood work is fixed in position.
All joints and framing shall be made and fitted in an appropriate manner in position to hold
surface, lines and levels correctly and in accordance with the drawings. All joints shall fit
Signature of Tenderer No. of Corrections Signature of NMMC Official
127
fully and truly without wedging or filling. The finished work shall be flat plumb and true
to shape.
All joiner’s work shall be wrought (planned) perfectly smooth and true and the finished job
shall not bear any sign of guage or setting out markings and shall be perfectly clean.
Unexposed faces need not be wrought, unless specified otherwise. Where so ordered by the
Engineer / Architect, but joints shall be cross tongued, i.e. the tongues to be cut at right
angles or diagonally to the grain of wood. All moldings shall be properly met. Steel bold
fast shall be fixed to the frames with suitable screws before the frames and erected in
position.
Battened, Ledged and Braced Shutters :
Battens shall be not more than 150m in width and shall be put together by tongued and
grooved joints. Each batten except the edge battens shall be nailed to ledges and the nails
clenched. The crossing of batten with ledges and the nails clenched. The length of nails
shall be about 6mm more than the combined thickness of ledges and battens. The edge
battens shall be fixed to the ledges by two W.I. screws in lieu of nails, braces shall run
upward from the hinged side. The edges of braces and ledges shall be chamfered and the
ends of braces bird – mouthed in to the ledges.
If after finishing and erection of wood work any undue shrinkage, cracks, or bad
workmanship is found, the Contractor shall remove the same and supply better approved
materials at his own cost. All shavings, cuttings and other rubbish shall be cleared away as
the work progresses and all precautions taken against fire.
Fixing Builder’s Hardware :
All builder’s hardware shall be fixed to wood work in secure and efficient manner. Special
attention shall be paid to the sizes of screws in countersunk holes to ensure that the head of
screw does not protrude. Location of fittings and accessories shall be as specified in IS :
1003, unless directed otherwise by the Engineer /Architect.
Metal sockets shall be provided to all tower, barrel and drop bolts where the shoots enter
masonry, stone masonry or concrete. These shall be securely fixed flush with the surface
into mortices and cemented. Mortice plates shall be used over holes in wood work. All
locks, bolts, springs and other moving parts shall be properly oiled by the Contractor
before handing over the charge of the building.
Signature of Tenderer No. of Corrections Signature of NMMC Official
128
20.0 METAL DOORS, WINDOWS & MISCELLANEOUS STEEL WORK
20.1 General
Applicable provision of conditions of Contract shall govern work under this section.
20.2 Work Included
The Contractor shall furnish labour, materials, plat and tolls so as to complete the work
indicated of specified herein or both.
20.3 Materials
Steel windows for industrial buildings shall conform to IS : 1361 unless otherwise
specified and shall be of the type and size shown on the drawings.
External doors shall be provided with threshold as shown in IS : 1081 if required by the
Architect and the doors required for internal use shall be provided with an approved size
base tie-bar in lieu of threshold.
Unless otherwise specified, coupling sections shall be of mild steel and handles, peg stays
and pivots of center hug ventilators shall be of leaded tin bronze (gun metal). Hinges for
side hung shutters shall be of projecting non-friction type, unless otherwise specified.
Weather bars shall not be provided unless specifically indicated on the drawings. The type,
size, number and position of fixing lugs shall conform to IS : 1038. The steel doors shall be
painted with one coat of red oxide paint conforming to IS : 102 before they are supplied.
Glazing clips shall be provided where plain sizes exceed 600mm x 300mm and shall be of
shape shown in IS : 1038.
The glazing putty shall conform to IS : 419.
The glass shall weigh 7.5 kg per sq.m. and shall conform to IS : 1038 unless specified
otherwise.
The grill work shall consist of MS flats, squares, rounds and angles as indicated on the
drawings.
20.4 Workmanship
Steel doors, windows and ventilators shall be fixed plumb in line and level. Fixing and
glazing of metal doors, windows and ventilators shall be in accordance with IS : 1081. The
Contractor shall include in his rates for all breakages.
20.5 Rolling Shutter (hand operated, mechanical gear operator and electrically operated)
Rolling shutters shall be fabricated from 18 guage steel and machine rolled with 75mm
rolling centers with effective bridge depth of 12mm 1a the sections, interlocked with each
other and ends loced with malleable cast iron chips to IS : 227, Gr, II.
The guides shall be either rolled or pressed deep channel sections 75mm and 25mm wide
fitted with necessary fittings and fixtures.
The suspension shaft shall be formed from solid drawn seamless tubes 60mm O. D. in 3
segments coupled with 2 pairs C. I. Dog riled flange couplings forming one complete until
restricting deflection in the center to a minimum.
Signature of Tenderer No. of Corrections Signature of NMMC Official
129
The springs shall be approved high tensils flat springs 50/60mm. Width and 1.6/8mm
thickness hardened and tempered. These shall be fitted inside the fabricated housing of
either ends which counter balance the shutter curtain.
The ball bearings shall be double row self – aligning ball bearings fitted inside C. I.
Housing fixed on side brackets holding the suspension shaft at either end.
The suspension of the curtain shall be bolted on specially fabricated cages formed from
M.S. flats ad plates all are-welded.
The hood cover shall be made of 20 guage galvanized sheets with necessary stiffeners and
framework to prevent sag. The bottom lock plate shall be made of 3mm thick M.S. plate
and 95mm wide reinforced with angle/T iron of suitable section with 6mm dia M.S. rivets
interlocked with last stride of curtain.
The locking arrangement shall consist of hasp and staple on the bottom plate lockable from
both sides. Unless otherwise specified, for overall area of rolling setters up to 9 sq. m. full
and push type hand – operated shutters shall be used: for area between 9 and 12 sq.m. pull
and push type shutters shall be provided with ball bearings: for area larger than 12 sq.
mechanical gear type or electrically operated shutters shall be supplied.
20.6 Steel Grills
The grills for windows, verandhas, balconies etc. shall be of mild steel. The design of grills
and shapes and sizes of various components shall be according to he drawings. The edges,
angles and corners shall be clan and true to shape. The joints shall be mechanically
interlocked and overlapping and neatly spot welded in such away that the grill is rigid.
Where moulded grills are specified, the moulded work shall be according to the drawings
and shall have clear, straight and sharply defined profile.
The Contractor shall do necessary cutting, fitting, drilling, tapping, scribing etc. required to
fix grills to adjacent surfaces. The grills shall be fixed plumb, in line and level.
Unless otherwise specified grill shall be painted with one coat of red oxide paint
conforming to IS : 102 before they are fixed.
20.7 Collapsible Gates
Collapsible gates shall be of the size and type shown on the drawings. The gates shall,
unless specified in the drawings or in the Bill of Quantities be manufactured out of M.S.
Channel pickets of size 20mm and flats 20mm x 6mm. The top runner flat shall be at least
50mm x 12mm, in section. The bottom guide shall consist of a channel or two angles of
specified size laid in the flooring to guide the free movement of the gate. The gate shall
move in the guide channel or rollers of adequate size fixed at the top and bottom of the
gate as specified. The gate shall be painted with one coat of red oxide paint conforming to
IS : 102 before fixing in position.
20.8 Subsidiary Gates
The subsidiary gates, unless otherwise specified, shall be made of “A” Grade pipe of
38mm nominal bore and weld mesh fabric 3mm at 50 mm. Centers both ways as indicated
on the drawings and shall be fully welded. The corners shall be square. The gate shall be
additionally reinforced with flats as shown in the drawing.
Signature of Tenderer No. of Corrections Signature of NMMC Official
130
20.9 Wire Fencing
Fencing shall of the type specified in the drawings or in the Bill of Quantities.
Unless specified otherwise, plain fencing wire shall be ply, 14 gage (galvanized ). The
barbed fencing wire shall consist of 2 ply, 12 gage galvanized wire with 4 point thick set
barbs at 75mm Centres. The wires shall be spaced as shown in the drawings.
Fencing posts shall be either of M.S. or reinforced concrete or timber as indicated in the
Bill of Quantities or in he drawings. The post shall be fixed in position in a concrete block
of the size and depth indicated in the drawing. Corner posts shall be suitably strengthened
by structs or ties to resist the forces acting on them.
Wire shall be fully stretched and securely tied to the posts in the manner shown on the
drawings. The fixing shall be done in a workman like manner without leaving any kinds
etc. The wires shall be held tight in position by eye bolts etc.
All steel work shall receive one coat of red oxide zinc chromate paint. Wooden posts shall
be treated with approved fungus resisting paint before fixing. Concrete posts shall be
painted with two coats of cement wash.
20.10 Weldmesh and Expanded Metal Partition
The partitions shall be of the type shown in drawing or in the Bill of Quantities, Weldmesh
shall be of make approved by the Engineer /Architect. Expanded metal shall conform to IS
: 412. The framing shall be of M.S. angles o tees as shown in drawing with additional
stiffening by M.S. flats. The frame shall be of fully welded construction. The connection of
he weldmesh or expanded metal to the frame shall be as shown in drawing.
21.0 PLASTERING (ONE AND TWO OPERATION )
21.1 General
Applicable provisions of conditions of contract shall govern work under this section.
21.2 Work Included
The contractor shall furnish labour, materials, tools and plant so as to complete the work
indicated or specified herein or both.
21.3 Materials
Cement : Cement shall conform to IS : 269.
Sand : Sand shall conform to IS : 1542.
21.4 Workmanship
Unless otherwise specified , all plaster work shall be carried out according to IS : 1661.
The thickness and proportion of cement plaster shall be as shown in drawing or indicated
in Bill of Quantities.
The surface to be plastered shall be cleaned of all extraneous mater and rubbish. In brick
work he joints shall be raked and concrete surface roughened by chipping or backing. Any
shuttering material adhering to the concrete shall be removed. The contractor shall make
plaster pads of the required thickness of plaster for correctness of plumb, line and level.
The surface shall be thoroughly watered and soaked and aerated and all putlog holes shall
be closed before starting plastering operation.
For one coat of plasterwork, the plaster shall be laid slightly thicker than the specified
thickness and the surface then leveled with flat wooden rule to the required thickness. The
plaster shall be well pressed into the joints and the surface finished as specified.
Signature of Tenderer No. of Corrections Signature of NMMC Official
131
Where two coat plaster work is specified, the first coat shall be applied as described above
except that the surface shall be left rough and keys formed for the application of second
coat. The second coat shall correct or mortar ground very fine and shall be laid on with a
wooden rule to a specified thickness, rubbed smooth and leveled and the surface plastered
completely the same day. The leveling shall be continued till the plaster is quite dry and all
moisture which exudes from the plaster shall be wiped off with fine cloth. The surface
shall be kept dry until exudation of moisture cesses, during th processor of rubbing.
21.5 Curing
After the completion of the work, the plaster shall be cured by adequate watering for a
period of seven days.
22. PLASTERING (ROUGH CAST FINISH)
22.1 General
Applicable provisions of Conditions of Contract shall govern work under this section.
22.2 Work Included
The Contractor shall furnish labour, materials, tools and plant so as to complete the work
indicated or specified herein or both.
22.3 Materials
Cement : Cement shall conform to IS : 269
Sand : Sand shall conform to IS : 1542.
Shingle or crushed stone : Size of shingle or crushed stone shall not exceed 10mm in size
and shall be of approved quality.
22.4 Proportion
The first coat shall consist of 1 part of cement and 4 parts of sand unless otherwise
specified.
The proportion of 2nd
coat (rough cast finish) shall be 3 parts of cement, 6 parts of fine
sand and 4 parts of shingle or crushed stone not exceeding 10mm. Size unless otherwise
specified.
22.5 Workmanship
The workmanship shall conform to 2 coat plaster as indicated in IS : 1661 and surface
preparation shall be as specified under Section 21.
The first coat shall be dashed on to the prepared surface with a trowel to fill up all
unevenness in the surface, but the surface shall not be smoothened and the surface shall be
left rough. A wet plastic mix of second coat as specified above shall be thrown on the first
coat by means of a scoop or plasterer’s trowel while the first coat is still soft. The thickness
of the second coat shall not exceed 120mm.
22.6 Curing
The plaster shall be cured by adequate watering for a period of seven (7) days.
Signature of Tenderer No. of Corrections Signature of NMMC Official
132
23.0 PLASTERING (PEBBLE DASH)
23.1 General
Applicable provisions of Conditions of contract shall govern work under this section.
23.2 Work Included
The contractor shall furnish labour, materials, tools and plant so as to complete the work
indicated or specified herein or both.
23.3 Materials
Cement : Cement shall conform to IS : 269.
Sand : Sand shall conform to IS: 1542.
Shingle : Single used for pebble –dash finish shall be from natural deposits and hill
streams and it shall be coarse rounded or waterworn stones. It shall have no injurious
action when it comes in contact with cement. It shall not exceed 10mm in size.
Lime : Lime used shall conform to IS : 712 and IS : 1635
23.4 Proportion :
The first coat of plaster shall consist of 1part of cement and 5 parts of sand unless
otherwise specified.
The second coat upon which single is thrown (i.e. pebble – dash finish) shall consist of 1
part of cement, 1 part of lime and 5 parts of sand unless otherwise specified. The second
Coat shall not exceed 10mm in thickness.
23.5 Workmanship
The workmanship shall conform to 2 coat plaster as indicated in IS : 1651 and the surface
preparation shall be as specified under Section 21.
The first coat of plaster shall be dashed on to the prepared surface to the specified
thickness with a trowel to fill up all unevenness in the surface, but the surface shall not be
smoothened with lime. The first coat shall be allowed to dry and shrink properly before the
second coat is applied. A wet plastic mix of second coat as specified above shall be applied
upon which selected shingle which has been well washed shall be thrown while it is still
soft.
23.6 Curing :
The plaster shall be cured by adequate watering for a period of seven (7) days.
24.0 LIME PUNNING
24.1 General
Application provisions of conditions of contract shall govern work under this section.
24.2 Work Included
The contractor shall furnish labour, material, tools and plant so as to complete the work
indicated or specified herein or both.
Signature of Tenderer No. of Corrections Signature of NMMC Official
133
24.3 Materials
Sand : Sand shall conform to IS 1542.
Lime : Lime shall conform to IS 712 and slaking of lime shall be done in accordance with
IS : 1635.
24.4 Proportion
The proportion of lime punning coat shall be 1 part of lime and 1 part of fine sand unless
otherwise specified.
24.5 Mixing
One part of slaked stone lime and one part of shell lime shall be mixed and tempered by
keeping it under water for at least a week before use. Water shall then he drained off from
the top leaving a paste of lime. The paste shall be well starred to form a homogeny mass
and strained through clean cloth. Lime prepared and fine sand shall be thoroughly mixed in
the proportion specified and water shall be added to make a paste of desired consistency.
24.6 Workmanship
The pastern shall be allowed to dry before he lime putting is applied. The lime plaster
(putty) prepared as above, shall be laid and rubbed and finely trowelled to a fine uniform
smooth finish. All unevenness shall be rubbed down with fine sand paper. Punning shall be
done from top to bottom in one operation to elimination joint marks.
24.7 Curing
The lime punned surface shall be cured by adequate watering for 3 period of seven (7)
days.
25.0 WHITE WASHING, COLOUR WASHING AND DISTEMPERING
25.1 General
Applicable provisions of conditions of contract shall govern work under this section.
25.2 Work Included
The Contractor shall furnish labour, materials, plant and tools to complete the work
indicated or specified herein of both.
25.3 Materials
Lime : White wash shall be prepared from shell lime and fat lime unless otherwise
specified and shell lime shall conform to IS : 712 and IS : 1635. Stacked lime for white
wash shall be screened to pass through a sieve of 49 mashes per Sq.cm.
Colour : Colour used for colour wash shall be as specified or as indicated on the drawings.
Distemper : The type of distemper, its colour and make and brand and number of coats to
be applied shall be as indicated on the drawings or in the Bill or Quantities and shall
conform to IS :427 and IS: 429.
Gum and Blue Pigment : They shall be of best quality and approved make.
25.4 Mixing
The slaked lime shall be dissolved in a tub with sufficient quantity of water and shall be
well mixed to give a thin creamy consistency. It shall then be strained through a clean
coarse cloth and clean gum dissolved in hot water added to it at the rate of 2 Kg for each
cubic meter of lime and ultramarine blue added to the mixture in small proportion just
sufficient to give a very light bluish tint.
Colour wash shall be prepared in the same way as for white washing except that necessary
amount of colouring matter shall be added to lime wash to obtain the colour specified. No.
Signature of Tenderer No. of Corrections Signature of NMMC Official
134
blue shall be added to lime wash in this case. The entire quantity shall be mixed strictly in
accordance with the manufacture’s instructions unless these are varied by the Engineer
/Architect.
Distemper shall not be mixed in a larger quantity than is actually required fo a day’s work
and hot water shall be used in preparing the mixture.
25.5 Preparation of Surface
Before white wash is laid on new wall, the surface of wall shall be well cleaned and
brushed ad all patching must be scraped properly. After cleaning the surface, all holes,
cracks and patches shall be made good with approved materials.
The distemper shall not be approved shall be applied in dry weather, the surface to the
distempered shall be thoroughly cleaned of dust, dirt, grease, oil marks, cement marks,
loose scales etc. and rubbed with sand paper to give a uniform smooth surface.
25.6 Workmanship
White wash shall be applied with brush, each coat consisting of vertical stroke from top
downwards followed by opposite stroke unwards over the first stroke and horizontal stroke
from left to right followed by stroke right to left. Each coat must be allowed to dry before
the next coat is applied. On completion, the surface when dry, shall present a uniform
white appearance. When dry, no coat of white wash shall show any patches, hair cracks or
streaks nor shall it come off when rubbed with hands. While washing shall be done in 3
coats unless otherwise specified. Doors, windows, floors etc. must be protected from white
wash splashes. Any splashes and droppings shall be removed and cleaned.
Colour wash shall be applied in the same manner as specified for white wash. During
application, the solution shall be stirred continuously and wash shall be applied with care
to avoid any cut shade or brush marks on the walls when the work is complete. For all new
work, the surface to be colour washed shall first be treated with a priming coat of lime
wash. Unless otherwise specified, two coats of white wash shall first be applied before
colour wash is applied. Number of coats of colour wash shall be as specified in the
drawings or in the Bill of Quantities. The colour wash, whether applied inside or outside of
a building shall be of uniform tint and shade.
The workmanship for distempering shall conform to IS : 427 and IS : 429 unless specified
otherwise. Distempering shall be done with proper distemper brushes of approved quality.
The finished surface shall be of absolutely uniform shade throughout and free from brush
marks. On drying, the distemper shall not come off on touch and shall not crack.
Distemper shall be applied in two coats over one coat of priming. The priming coat shall
be as specified and the primer shall be in accordance with the recommendation of he
manufacturer. Succeeding coats shall not be applied until the previous coat has been
approved by he Engineer / Architect. The first coat shall always be of a lighter tint and
shall be applied with care. In case the finish be not up to the standards the entire surface
shall be sand papered and a fresh coat or coats of distemper shall be applied without any
extra cost.
All decorative mouldings, cornices, bands etc. shall be finished according to detailed
drawings. All splashes of distemper shall be removed by the Contractor at his own cost.
Signature of Tenderer No. of Corrections Signature of NMMC Official
135
26.0 PAINTING
26.1 General
Applicable provision of Conditions of Contract shall govern work under this section.
26.2 Work Included
Unless otherwise specified, the Contractor shall furnish materials, labour, tools and plant to
complete the painting work specified.
The Contractor shall carry out complete painting and finishing of wood as well as metal
(either unfinished or coated with a priming coat) throughout the exterior or interior of the
Buildings unless otherwise stated.
26.3 Materials
The painting and finishing materials for use in the work shall conform to relevant Indian
Standards Specifications and shall be of best brands and approved make produced for each
kind of work. Ready mixed paints shall be used for the work unless otherwise specified; or
if he Engineer / Architect is satisfied that they are not available they may be prepared at
site.
If paints mixed at site are to be used, they shall be prepared by mixing appropriate
ingredients in approved proportion. The contractor shall submit samples of each material,
for the Engineer / Architects approval. The Contractor shall not construe approval of
samples as acceptance of materials, as these materials shall be tested from time to time
during he progress of the work.
The materials for succeeding coats on any one surface shall be products of the same
manufacturer supplying the first coat for that particular surface.
Pigments : All colours shall be non-fading pigments of approved make.
Primer Coat : Unless otherwise specified, the primer coat for woodwork, steel and iron
work shall be as indicated in the Bill of Quantities.
Brushes :- Paint shall be applied by brushes. Brushes required for painting shall be of type
and size suitable for the work conforming to relevant Indian Standard specifications. Rags,
interior quality brushes or the like shall not be used on the work.
26.4 Workmanship :-
Preparation of Paint :-
Where ready mixed paints are not available and if oil based paints are prepared at site, the
ingredients shall be thoroughly ground and thinned with double boiled linseed oil in
specified proportion to the required consistency. The painting materials, when applied,
shall be spread evenly in a thin coat and flow on smoothly without runs and sags and shall
dry quickly forming a tough durable film without showing any brush marks or cracks.
The coloring pigment shall be thoroughly ground, mixed with oil and added to the
prepared base. The mixture shall be well stunned and strained thorough a piece f cloth.
Preparation of the surface :- The surface of iron and work to be painted shall be cleaned
free and dint, oil, rust, millscale, and shall be thoroughly dried before painting. Cleaning,
removal of grease rust and scales wherever necessary shall be carried out at specified in IS
: 1477 (Part I)
Signature of Tenderer No. of Corrections Signature of NMMC Official
136
The surface of wood work to be painted shall be cleaned and rendered dry, free of dirt, grit
and grease and shall be rubbed smooth with the appropriate quality of sand paper. All
knots pitch streaks and sappy spots shall be touched with shellac varnish.
Painting Iron and Steel Work. :- Painting of iron and steel work shall generally be carried
out as per IS : 1477 (Part II)
The number of coats including the primer coat shall be applied as specified in the bill of
quantities. Each coat shall be allowed to dry sufficiently before the succeeding coat is
applied.
Finish Coat :-
The type of intermediate and finish coat and the number of coats to be applied shall be
specified in the bill of quantities. Intermediate and finish coats may be oil bound.
Bituminous, aluminum or other types of paints. Aluminum paint shall conform to IS 165.
the intermediate and finish coats or structural steel work, sheet metal work and cast iron
work shall be applied as specified in IS : 1477 (Part II).
Painting Wood Work :-
After the primer coat has dried, nail holes, cracks and the like shall be filled up with
approved wood putty and the surface finished smooth.
The type of intermediate and finish coats and the number of coats shall be as specified in
the bill of quantities. The surface shall be rubbed smooth before application of each coat.
Iron work under Water:-
Approved anti-corrosive black enamel paint shall be used for iron works in water such as
cast irons pipes etc., coal tar paint may also be used with the approval of the Engineer /
Architect.
Painting Steel Tanks. :-
Unless otherwise specified steel tanks for the storage of water shall be painted with approved
paint before erecting them in position.
27.0 GLAZING:-
27.1 General :-
Applicable provisions of conditions of contract shall govern work under this section
27.2 Work Included :-
The Contractor shall furnish labour, material, plant and tools to complete the work
indicated or specified herein or both.
Signature of Tenderer No. of Corrections Signature of NMMC Official
137
27.3 Materials :-
Sheet Glass :- All glass used in the work shall be best quality glass, free from specks,
bubbles smokes, wanes, air holes and other defects. Unless otherwise specified, sheet glass
shall be transparent and of weight as indicated in bill of quantities and / or Drawings.
Plate Glass :- where plate glass is specified for the work, it shall be specified
Thickness, with a permissible tolerance of 0.5 to 0.80 mm for polished plate glass. The
transparent type glass shall have polished surface giving clear and non-distorted vision.
Rough Cast wired glass. :- The rough cast wired glass shall be 6mm thick and as approved
by the Engineer/Architect.
Putty :- Putty for use on wooden frames shall conform to IS : 420
Mastic :- the mastic shall be as approved by the Engineer / architect.
27.4 Workmanship :-
All glass shall be cut according to the sizes required as per drawings. Glazing of metal
doors, windows and ventilators shall conform to IS : 1081 and glazing for timber doors,
windows and ventilators shall conform to IS 1003 unless otherwise specified.
For glazed wooden doors and windows, the wooden frame, particulars the rebate, shall be
well oiled to prevent oil form putty being sucked by wood.
The glazing shall be done with specified glaxzing putty and clips. The methos of glazing in
each case shall be according to the details shown on the drawings.
The contractor shall thoroughly clean all glass and replace all putty or glass damaged
during the work.
28.0 VARNISHING & POLISHING :-
28.1 General :-
Application provision of conditions of contract shall govern work under this section.
28.2 Work Included :-
The Contractor shall furnish materials, labour, tools, and plant to complete the work
indicated or specified herein or both.
28.3 Materials :-
Ready prepared varnish shall conform to the relevant Indian Standard specification of
varnishes and shall be of approved make.
Ready prepared French polish conforming to IS : 348 shall be sued for te work.
If the Engineer/Architect is satisfied that ready prepared varnished or polish are not
available only approved ingredients shall be used for its preparations at site. The
Proportions of the materials for the preparations of varnishes at site shall be as follows.
a) For resin Varnish - Resin : Linseed Oil : Spirits
of Turpentine : 2:2:1
b) For Copal Varnish - Copal : Linseed Oil : Oil
of Turpentine 3:2:5
Signature of Tenderer No. of Corrections Signature of NMMC Official
138
28.4 Workmanship :-
Preparation of surface the wood work surface to be varnish shall be thoroughly cleaned and
rubbed smooth sand paper or pumice stone, the rubbing shall not be done across the grain.
All knots in wood work shall be covered or Killed. The surface of wood shall be then be
steeped with hot diluted glue (about 1 lg. Of glue will produce 10 litres) so as to close up
the faces. When dry, the surface shall again be rubbed with sand paper lightly before
varnish is applied.
Wood work is to be polished shall be coated first with a filler composed of about 1.5 kg.
Of whiting mixed in 1 liter of methylate spirit. The surface shall then rubbed sand paper.
Varnishing and Polishing :- Varnishing shall preferably be done in a dry weather. After
the surface is steeped and sand fine haired or approved varnishing evenly in very thin coats
with paint brushes. Successive coats shall be applied after the previous coats are
thoroughly dry. Where additional coats are rubbed down, with fine sand paper before
application of the succeeding coat.
Polish shall be applied on the prepared surface with a pad consisting of absorbent cotton
wool inside a clean white cloth. Polish shall be applied in the number or coats specified
and the surface shall be rubbed with fine sand paper after each coat except the finish coat.
Care shall be taken to renew the cloth should it now signs of warning or else the cotton
will stock to the surface. After the final coat of polish, the surface shall present the desire
and finish.
29. WATERPROOFING WITH BITUMEN FELTS
29.1 General
Applicable provisions of conditions of contract shall govern work under this section.
29.2 Work Included
The Contractor shall furnish labour, materials, plant and tools to complete the work
indicated or specified herein or both.
29.3 Materials
The Materials used for waterproofing with bitumen felts shall be of approved make and
type and as indicated in the bill of Quantities.
Bitumen Material :- It shall consist of blown type bitumen conforming to IS:702 on
residual bitumen conforming to IS: 73 or a mixture thereof.
29.4 Waterproofing Roof Surface
The roof slab shall be cleaned of all dust, dirt , grit etc. and it rough it shall be made
reasonably smooth either by chipping off projections or by applying a thin coat of cement
slurry of cement sand and water.
The roof surface shall be regarded prior to waterproofing either with cement mortar or
lime-surkhi mortar. At the places of drain outlets, projecting pipes, parapet walls and
expansion joint etc. The surface shall be prepared as indicated in IS: 1346.
The workmanship in general shall conform to IS: 1346, unless otherwise specified. Over
the hardened and finished surface of the roof slab, a thin layer of approved bitumen primer
shall be first brushed over the roof surface and allowed to dry.
Signature of Tenderer No. of Corrections Signature of NMMC Official
139
The felt shall be first cut to the required lengths and laid out flat on the roof in position at
right angles to the direction of run off gradient and shall be brushed clean of dusting
materials. Each length of felt thus laid in position shall be rolled up for a distance of half
of its length. Then the bonding material heated to correct temperature shall be poured on
to the roof across the full width of the rolled felt as the latter is steadily rolled out and
pressed down. Excess bonding material shall be squeezed out at the ends and removed as
the laying proceeds. When the first half of the strip of felt has been bonded to the roof, the
other half shall be rolled up and then unrolled on the hot handing material in the same way.
Minimum overlaps of 100m shall be allowed at the end and sides of strips of felt. All
overlaps shall be firmly bonded with hot bitumen. The laying of the second layer of felt
shall be so arranged that the joints are staggered with those of the layer beneath It.
In case of roofs with parapets, a chase 75mm deep shall be cut in the parapet masonry at
about 150mm above the roof level and the felt shall be laid as flashing in widths with a
minimum overlap of 100mm. The lower edge of flashing shall overlap the felt laid on flat
portion of the roof and the upper edge of the flashing shall be tucked into the groove made
in the parapet. After the flashings have been properly bonded. After the flashings have
been properly bonded, the chase shall be cleaned mortar (1:4) flush with the face of the
wall and allowed to set by adequate curing.
In case of drain mountain waterproofing shall be done as specified for the roof excepting
that the treatment shall be carried inside the drain pipes overlapping at least 100 mm.
For gutters, a priming cost shall be first be applied over this, specified number of layers of
felt shall be laid and bonded together with hot bitumen at not less than 1.5 Kg. Sq.mtrs.
The felt layers laid separately in the gutters shall be overlapped with the corresponding
layers on the roof proper. The felt treatment shall be carried down into the outlet pipes to
a minimum depth of 100mm.
After treatment is over, the surface shall be covered by peasized gravel or grit at the rate
of 0.6 cu. Mt. Per 10 sq.m. on flashing and at drain mouths two coats of approved
bituminous primer shall be provided.
29.5 Waterproofing for Underground Structures
Waterproofing for underground structures shall be done in accordance with IS:3067. the
number of layers and the details of protective wall etc. shall be as shown in drawing or
indicated in the Bill of Quantities. No waterproofing treatment shall be applied unless the
site is properly drained and the surface is thoroughly dry.
30.0 LIME TERRACING
30.1 General
Applicable provisions of conditions of contract shall govern work under this section.
30.2 Work Included
The Contractor shall furnish labour, materials, plant and tools to complete the work
indicated or specified herein or both.
Signature of Tenderer No. of Corrections Signature of NMMC Official
140
30.3 Materials
Brick Bats :- Brick bats shall be 25mm gauge from first class brick.
Lime :- Lime used shall be hydraulic lime conforming to IS: 712 and shall be slaked
according to IS: 1635.
Surkhi :- Surkhi used shall be from first class bricks.
Sprinkling Water :- The following proportion of specified materials shall be mixed in 20
litres of water.
Molasses : 1.03 Kg
Katha : 0.26 Kg
Methi : 0.13 Kg
Maskalai dal : 0.52 Kg
This water is to be sprinkled as specified further on 10 sq.m of surface.
30.4 Proportion
Bricks : Lime : Surkhi = 7:2:2 by volume
30.5 Mixing
The brickbats, lime and surkhi mix shall be heaped to a predetermined height depending
upon the amount of material required for particular portion to be treated.
Water shall be added and allowed to remain for 2 days and the materials shall be turned
over several times to ensure a through mix.
30.6 Workmanship
The Surface shall be cleaned of all dirt, rust particles, dust etc. before lime concrete is
placed. The mix shall be gently deposited on the surface and laid to proper beds and cross
falls and leveled to levels indicated on the drawings.
The compaction by hand tampers shall be carried out for 7 days. During the first three
days, the surface shall be sprinkle with water specified above. For the next four days the
compaction shall be carried out and the surface shall be sprinkled with lime water during
compaction.
After this period, a thin coating of lime paste shall be applied and rubbed smooth and the
surface shall be then be covered with straw or sand and water shall be sprinkled for a
further period of 7 days and the flooded up to a height of 75mm to 100mm.
After one month, the surface shall be cleaned and rubbed with inseed oil and water.
If specified, a layer of flat tiles, or broken tile pieces shall be laid in cement mortar of
specified proportion on top of brick bat concrete.
31.0 DAMP PROOF COURSE
31.1 General
Applicable provisions of conditions of contract shall govern work under this section.
Signature of Tenderer No. of Corrections Signature of NMMC Official
141
31.2 Work Included
The Contractor shall furnish labour, material, plan and tools to complete the work
indicated specified herein or both.
31. 3. Materials
Cement :- Cement shall conform to IS : 269
Aggregates :- The aggregates shall conform to IS : 383. fine aggregate shall be river sand
or pit sand from approved pits. Coarse aggregate shall be stone chips of size not exceeding 6mm.
31.4 Proportion :-
The proportion of the above materials and thickness of the coarse shall be as indicated on
the drawing.
31.5 Workmanship
The brick of stone masonry surface shall be leveled, flushed up and prepared as directed to
receive the damp proof course. Damp proof course shall be provided at position shown on
the drawings. In masonry walls of buildings shall normally be placed above the external
ground level. It shall be laid for the full width of the wall. The top surface shall be kept
rough or ribbed for proper adhesion of brick work coming over it. All exposed surfaces of
the damp of proof course shall be finished fair and smooth. After the surface has partially
set, hot bitumen shall be applied in two coats the rate of 1.7 Kg per sq.m per coat and dry
sand spread over it.
32.0 PLUMBING AND SANITARY WORK
32.1 General
Applicable provisions of conditions of contract shall govern work under this section.
All water supply and sanitary work shall be executed by Licensed Plumber and shall be in
accordance with the requirement of relevant bye-laws of Municipal or other Authorities in
whose jurisdiction the work is to be carried out.
For items such as earthwork, excavation, concrete, brick work, stone work, pointing, etc
relevant specification for these shall apply, unless specifications otherwise.
Unless otherwise specifications, all exposed work such as cisterns, brackets etc, shall be
painted with one coat of red oxide paint and two coats of oil paint of approved colour.
The diameter of pipes of fittings wherever mentioned shall mean the internal diameter,
unless otherwise specified.
The rates quoted by the Contractor shall be deemed to include all breakage and wastage of
various materials, fittings and appliances. All materials, fittings and appliances damaged
during the execution of the work or otherwise shall be removed and replaced with
approved materials, fittings and appliances by the contractors at his expenses.
The job shall include the cost of making the necessary holes, etc. in walls, floors etc, and
also making them good on competition of the job. Any damage caused to floors, walls etc
during fixing of sanitary installation, drainage and water supply work shall be made good
by the contractor at his own cost.
Signature of Tenderer No. of Corrections Signature of NMMC Official
142
32.2 Materials, Fittings and Appliances
The materials, fittings and appliances used in the work shall be as specified hereunder.
The type, quality, class, composition, size, finish and make shall be as specified in the Bill
of Quantities. The Contractors shall submit of approval samples of all materials, fittings
and appliances well in advance of starting the work and before being used in the job. All
materials, fittings and appliances used in the work shall conform in the approved samples.
Galvenized iron pipes, fittings, and accessories for water services shall be of tested variety.
All materials, fittings and applicables shall conform to the relevant Indian Standard
Specifications, some of which are listed below :
Asbestos cement building pipes, gutters fittings etc. IS : 16216
Sheet metal rain water pipes, upto 100mm nominal size, gutters,
fittings etc.
IS : 1728
Cast iron rain water pipes, fittings and accessories IS : 1230
Sand cast iron spigot and socket soil, waster and ventilating pipes,
fittings and accessories.
IS : 1729
Sand cast brass screw-down bib tapes and stop taps for water
services.
IS : 781
Self closing taps IS : 1711
Gun Metal gate, Globe and check valves for general services . IS ; 778
Lead-pipe IS : 404
Sluice valves for water works purposes IS : 780
Mixing valves for ablutionary and domestic purposes IS : 1701
Water Meters (domestic type) IS : 779
Rectangular pressed steel tanks IS : 904
Sheet lead for flashing shall be of at least 30 Kg. Weight per sq.m. unless specified
otherwise.
Brass tapes shall be of heavy brass and made particularly smooth on the inside and shall
have all waste and vent connections screwed, unless specified otherwise.
Lead traps shall be of the same weight and thickness as specified for lead pipes.
Signature of Tenderer No. of Corrections Signature of NMMC Official
143
32.3 Water supply
32.3.1 Jointing and laying of water supply pipes.
Jointing of various pipes shall generally conform to IS:1742 unless specified otherwise.
Screwed galvanised iron pipes shall be jointed with screwed socket joints using screwed
fittings of the same materials as that of the pipes. Any burrs remaining on the pipe ends
after the threads are cut shall be removed. An approved jointing compound together with a
grommet of few strands of fine yarn shall be used for jointing pipes and fittings. Any pipe
threads exposed after jointing shall be painted or in the case of underground piping thickly
coated with approved bituminous compound to prevent corrosion.
Teflon tape should be used if specified.
The depth at which the under ground water supply pipe is to be laid shall be as indicated
on the drawings. The service pipe passing into or beneath the building shall be laid at least
200mm. below the ground floor level and accommodated in previously laid sleeve in the
structure –where it enters. The space between the sleeve and the pipe at its entry into and
exit from the building shall be filled with a bituminous material for a minimum length of
150mm at both ends.
Piping shall not be buried on walls or floors as far as possible. However, when
unavoidable, piping shall be buried for the shortest protection provided against damage.
Galvanised iron piping shall be secured by iron or steel clamps when fixed on walls.
All pipe work shall be completely watertight and the joints shall be such that there are no
projections of jointing materials on the like in the interior of pipes. Before the pipe line is
commissioned, all piping and fittings shall be flushed clean.
32.3.2 Storage of Water
All tanks for storage of water shall be of the specified kind and shall be completely
watertight and properly covered with a close fitting and dust, tight and mosquito-proof
cover of approved pattern. The shall be fitted a ball valve of approved type, securely fixed
to the tank independent of the inlet pipe and set in such a position that the body of the
valve always remains above the water line. A mosquito-proof overflow pipe shall be fixed
to the tank with the pipe invert about 25 mm. above the top water line. Approved type of
stop valves or taps shall be provided for every outlet pipe. The outlet pipe shall be
fixed at a level about 75mm. above bottom of tank. The washout or drain or pipe shall be
kept flush with the bottom of the tank at its lowest part.
32.3.4 Testing
After the laying and fixing of all water supply pipes and fittings are completed, the line
shall be slowly and carefully charged with water to a test pressure of 5 Kg. Per sq.cm or
the specified working pressure plus so as may be prescribed by the Engineer/Architect.
This pressure shall be maintained for at least one hour, unless specified otherwise. The
pipes and fittings shall then be inspected for any leakages of water. Defects in pipes and
fittings if detected, shall be remedied by the contractor without extra cost.
Signature of Tenderer No. of Corrections Signature of NMMC Official
144
32.3.5 Internal Plumbing Works
Jointing and Laying Pipes :- Clause 32.3 apply to this wherever applicable.
Lead pipe joint in lead pipe shall be made at wiped solid solder joints when lead pipe have
to be lead through due the join shall be made outside the joint and pipe placed base into
the duct after jointing. All exposed lead pipes, excluding 25mm dia meter shall secured to
walls by iron clips or lead ears. The spacing clips shall not exceed 900mm
32.3.6 Installation of Water Closets
Indian type or European type W.C. pans of the type and make as specified in the Bill of
Quantities shall be carefully fixed in position. Indian W.C. pan shall be built round solid
with masonry or lean concrete to the level of the after all connections are made. Also floor
slope towards the pan.
Unless otherwise specified, each closet shall be provided with standard accessories such as
soil WC connect0or, 40mm lead antisyphonage 32mm flushing pipe 15 liters capacity
flushing of specified type and make , overflow pipe fitted with mosquito-proof strainer at
the end all suitably fixed in position.
32.3.7. Nahani Traps
Nahani Traps shall be of the size and quality indicated in the Bill of Quantities and shall
be embedded flush with the floors. The connec6tion the trap with the waster pipe shall be
through plug bend of the size to suit the wall thickness fitted with an inspection door.
32.3.8 Drainage
Unless otherwise specified, all drainage work for building shall be carried out in
accordance IS:1742.
Handling, laying, bedding, jointing and testing of concrete pipes shall conform to IS: 783.
The method of bedding and jointing of pipes shall be as specified in the bill of quantities.
Manholes gully trap and inspection chambers shall be constructed as shown on the
drawing.
32.3.9. Testing
Unless otherwise specified the drawings system shall be tested in accordance with IS :
1742.
33.0 COST IRON , R.C. AND STONEWARE PIPE WORK
33.1 General
Applicable provisions of Conditions of contract shall govern work under this section.
33.2 Work Included
The contractor shall furnish labour, materials, plant and equipments to complete the work
indicated or specified herein or both.
33.3 Materials
All materials shall be tested variety tested by a recognize test house.
Cost of iron pipes with socket and spigot ends upto 675 mm shall conform to IS 1536 for
centrifugal span pipes. C.I. Pipes with flanged ends shall conform to IS : 1537 for
vertically cast pipes. The class of pipes (whether A. B. or C according to IS) shall be as
specified in the drawings. The sluice valves of various sizes and caulking lead shall
conform to the following standards.
Sluice Valves up to 300mm - IS: 780
Sluice Valves beyond 350mm - IS: 2906
Signature of Tenderer No. of Corrections Signature of NMMC Official
145
Caulking lead for jointing - IS: 782
Other types of fittings such as air valves, reflex valves, hydrants, bends etc. shall be of best
quality and samples shall be approved by the Engineer / Architect.
R.C. Pipes shall conform to IS: 450.
Stoneware pipe, cast iron soil, ventilation and rain water pipes, C.I. manhole covers and
lead pipes shall conform to the following Indian standards specifications.
Salt glazed stoneware and fittings : IS: 651
And other accessories
Cast Iron spigot and socket, soil water and : IS:1729
ventilation pipes fittings and accessories
Cast Iron rain water pipes : IS: 1230
Cast Iron manhole covers and frames : IS: 1726
Lead Pipes : IS: 404
CI pipes for water services shall be of tested variety.
33.4 Joints:
The type of jointing for C. I. Pipes shallbe either socket and spigot with molten lead or lead
wool or flanged type with nuts, bolts and gaskets as indicated on the drawings.
If the joints used are spigot and socket type, the spigot shall be carefully centered in the
socket by one or more laps of clean white hemp spun yarn with about 25mm overlap.
Sufficient yard only shall be forced into the socket to leave a correct depth of lead for
caulking. The pipe shall then be examined again for line and level and the proper depth of
each joint shall be tested before running the molten lead. The pouring of molten lead shall
be done by wrapping a ring of hemp rope covered with damp clay load the pipe at the end
of he socket.
After a section convenient length has been laid, lead shall be caulked sufficiently with a
hand hammer and the joint shall be made neat and clean.
The packing ring or washer for the flanged joint shall be rubber for the full diameter of the
flange with proper pipe hole and bolt holes cut out at both the inner and outer edges. The
packing shall be smeared with graphite paste or a mixture of red lead and while lead and
shall be introduced between the flanges of both the pipes ad nuts lightened in opposite
pairs keeping the longitudinal axes of adjoining pie lines in exactly the same straight line.
Lead washers shall be provided along with bolts to prevent any leakage through bolt holes.
The type of jointing for stoneware pipes shall be socket and spigot as indicated on the
drawings.
Signature of Tenderer No. of Corrections Signature of NMMC Official
146
The inside of the socket shall be first painted with a tin layer of cement mortar 1:2 and a
gasket of yarn dipped in cement slurry shall be inserted in the socket of the pipe with a
wooden caulking tool and wooden mallet in such a way that the gasket shall fully encircle
the spigot with a slight overlap. Where the spigot and receives the gasket, it shall be
wrapped round with two or three turns of treated spun yarn at its end before being inserted
into he socket. The joint shall then be completely fitted with cement and mortar of
proportion 1:1 having very little water and the joint shall be leveled to form a splayed
fillet at a angle 45 degree with the outside pipe. Excess of cement mortar left inside the
pipe joint shall be neatly cleaned off. In jointing stoneware pipes, care shall be taken that
the pipes are kept concentric and the socket, specifically on the underside, shall be
completely filled with cement mortar. Where settlement of earth is envisaged, the joints
shall he made with bitumastic filling or any other material as instructed by the Engineer
/Architect.
33.5 Workmanship
33.5.1 Laying of G.I. Pipes
The laying of the C. I. pipe line shall commence only after the levels at the bottom of he
trench have been done in accordance with the drawing. The sides of the trenches shall be
as nearly vertical as possible. Where joints are made, the trench shall be wide enough to
allow room for caulking joints. Shoring and timbering shall not be used without prior
approval of the Engineer/Architect. The trenches shall be excavated such that there shall be
a minimum cushion of 750mm over the pipes. All pipes, water mains cables etc. met
within the course of excavation shall be carefully protected and supported. All pipes and
fittings shall be sounded wit a light hammer to detect any cracks before laying. The
excavated material shall be thrown on one side of the trench and the pipes stacked on the
other side. The inside of socket and the outside of spigot shall be thoroughly cleaned of all
foreign matter before laying. The pipes shall be laid with their socket ends facing the
directions of flow. The pipes shall be plated in the trenches by any recognized method
which shall be approved by the Engineer / Architect. Then the pipes shall be jointed by
caulking as described previously. After each section of the pipe line has been laid, it shall
be tested for water tightness before filling up the trench. After completing the test, the
trench shall be filled with the excavated material inlayer of 200mm and shall be watered
and rammed. Whether the pipeline cross the railway tracks, roads etc. the trenches shall
have vertical sides with suitable shoring.
33.5.2 Laying of R.C. Pipes : Laying of R.C. pipes shall conform to IS : 783.
33.5.3 Laying of Stoneware pipes: The laying of the stoneware pipelines shall commence only
after the levels at the bottom of the trench at various points have been done as indicated on
the drawings. The center line of he trench shall first be stacked out on he ground and shall
be excavated correct to depth and width at the points. All inverts shall be laid from sight
rails fixed at the rue levels with proper boning roads. The sign rails and boning roads shall
be provided, fixed and maintained by the Contractor at his own expenses. The pipes shall
be carefully laid to the alignment, levels and gradients shown on the plants and sections.
The trench shall be laid truly in straight lines and without any vertical or
Signature of Tenderer No. of Corrections Signature of NMMC Official
147
horizontal undulations. Pipes shall have adequate customs over them and shall be handed
at the bottom with concrete 1:3:6 up to a depth of half the diameter of the pipe. When it
cross under a road, the pipe shall be fully covered in concrete 1:3:6 as shown on drawings.
All pipes and fittings shall be fully examined with a light hammer for soundness before
laying. After each section of he pipeline has been laid, the joints shall be allowed to set
properly and shall be inspected, tested and approved before refilling the trench. After
testing, the trench shall be refilling with finest selected material in layers of 200mm and
shall be watered and thoroughly rammed. All pipes, water main, cables etc. met within the
course of excavation shall be carefully protected and supported.
When the piplelines cross railway tracks, roads etc,.the trenches shall have vertical sides
with suitable shorting. Any subsidence in the line of trenches after refilling shall be
repaired at the Contractors expenses.
33.5.4 Rainwater Pipes : Rainwater pipes inside the building shall be heavy cast iron type as
specified above. They shall be kept away from the finished walls by means of bobbins. The
rainwater pipe shall be connected to the main sewer or to the surface drains as shown on
the drawings.
33.6 Manholes, Gully Trap Chambers, Inspection Chamber.
Those shall be as indicated on the drawings.
33.7 Testing
On completion of the work the Contractor shall conduct at his own cost such tests as the
Engineer will direct. The water supply system shall be tested according to the provisions of
IS. The drainage system shall be tested in accordance with the provisions of IS : 1742. All
defects and deficiencies detected during testing shall be promptly rectified by the
Contractor.
Signature of Tenderer No. of Corrections Signature of NMMC Official
148
LIST OF APPROVED MAKES /BRAND OF VARIOUS BUILDING MATERIALS
Unless orderwise mentioned specifically, any one of approved makes or brands shall be
allowed to us, other makes or brands of he building materials bearing I.S.I. monogram on
the materials itself will also be allowed to be used.
The contractors should distinctly understand that it will not be their prerogative to insist
for using particular makes /brand from the following list. The final selection will have to
be done with the approval of an Engineer – in – charge.
1. CEMENT : Ordinary portland cement 53 grade will be
used for R.C.C structure & OPC 43 grade
can be used for other works of approved
manufacture L&T, Ambuja, A.C.C &
Birla.
2. WHITE CEMENT : Birla White, A.C.C. (Silver Crete)
3. STEEL : TOR & MILD
(MILD STEEL)
: HYSD FE 415 or approved stock yards with
est certificates bar will be used.
4. RUBBLE STONE : Spotless stone available from local sources.
5. METAL NO. 1, 2 & 3 : Conforming to IS – 383 from local sources.
6. BRICKS : Ordinary clay bricks of any brand
conforming to I.S. 1077 minimum crushing
strength of 35Kg/Sq.cm. water absorption
allowed 25% by weigh for bricks used in
panel walls, 20% by weight for bricks used
in load bearing walls when soaked in water
for 24hours.
7. SAND : River Sand conforming to IS 383.
8. MARBLE : Medium quality white marble from :
Makarane, Udaipur, Rajnagar.
9. GRANITE : Approved quality granite.
10. COLOUR /WHITE GLAZED TILES : First quality of Johnson & Johnson , Kajaria
or equivalent approved make .
11. COLOURED CERAMIC TILES : First Quality of Johnson & Johnson ,
Signature of Tenderer No. of Corrections Signature of NMMC Official
149
Kajaria or equivalent approved make .
12. F R P. DOORS : Approved make .
13. TEAK WOOD : Best Quality C. P. / Country teak wood,
well seasoned ad free from all defects,
cracks, knots, decay etc.
14. TREATED TIMBER
(For Frames )
: ‘SAL’ or other similar approved variety
duly treated.
15. GLASS 6MM : Sluce Vallabha / Triveni
16. SHAHABAD, GREEN KOTAH &
OTHER NATURAL STONES
: As available locally /in Mumbai of
approved thickness quality and shade.
17. FITTINGS AND FIXTURES FOR
DOORS AND WINDOWS
: ‘Navabharat’ or as approved
18. ALUMINUM SLIDING WINDOWS : With JUNDAL /AJIT INDIA /GEETA
Heavy sections.
19. ALUMINUM SLIDING WINDOWS : Sentinal, Man Industrial Corporation, Sen-
Harvic, Godrej or any other approved.
20. ROLLING SHUTTERS, ROLLING
GRILLS, SLIDING & FOLDING
GRILL DOORS.
: Swastic, Shaparia Dock, Hercules or any
other approved
21. FLOOR HARDENERS : Carbonate, Fastonate, Kwiksel, purelis,
Ironate, Bestonate.
22. SOFT BOARD & ACCOUNTING
BOARD
: Jolly Board, (Insulues) Sitapur (Sitatex)
23. HARD BOARD & ACCOUNTING
BOARD
: Jolly Board, Sitapur (Sitatex).
Signature of Tenderer No. of Corrections Signature of NMMC Official
150
24. A.C SHEETS
S.R.M.P. SHEETS
: Everest, Ramco, Charminar, R.M.P
(Elephant), Brand TRIPLAST SWASTIK
A.C.Sheets.
25. FIRE GLASS ROOF SHEETS : Paramount
26. FIBRE GLASS SOIL PAN : S.D.Enterprises
27. THERMOLITE CRETE BLOCKS : M/s. Bharat Tiles & Marbles Ltd.
28. BITUMEN FELETE : Shalimar
29. OXYCHLORIDE FLOORING
PARTITION
: M/s. Oxychloride Flooring Products.
M/s. Ajay oxychloride Flooring Company.
30. DOOR CLOSERS : Garnish, Tahilson, Satco.
31. BUILDING HARDWARE : CIEF, Kutyanwala, Tahilsons.
32. FACTORY MADE PANEL DCORS : 1. Shankar Ramchandra Brothers.
2. Beror Wood Industries
M/s. Bechwat of India Ltd.
33. ALUMINIUM DOOR AND
WINDOWS
: M/s. Ajit India Pvt. Ltd.
M/s. Bharat Aluminium Fabricators, godrej
M/s. Aluminium Pvt. Ltd.
34. DECORATE TEXTURE : Vineerntex
35. PRECAST CONCRETE BLOCK FOR
CASTONE
: M/s. Bombay Chemical Pvt. Ltd.
36. PAINT :
A) OIL PAINTS DISTEMPER
& OTHER PAINT
MATERIALS 1ST
QUALITY BRAND
OF ONE OF THE FOLLOWING
MAKES, READY MIX.
: Shalimar, Jenson Nicloson, Good lass
Nerolac, Garware, OMEGA BRIGHT,
Asian or any other approved.
B) PLASTIC EMIULSION AND
SYNTHETIC
: British Paints, Shalimar, MERCURY
PAINTS, Asian, Garware, Jenson,
GOODLESS, NEROLAC , Nicoloson or
any other approved.
C) DRY DISTEMBER : British Paints, Shalimar, GARWARE,
BRIGHT & CO. Jenson, Nicoloson or any
other approved.
D) OIL BOUND DISTEMBER : British paints, Shalimar, ASIAN
GARWARE, Jenson, Nicoloson or any
other approved
Signature of Tenderer No. of Corrections Signature of NMMC Official
151
E) WATER CEMENT PAINTS : Super Snocem or Snocem plus
DVRROCEM, CEMKMOTE,
COLOURCEM, SILVERCEM
F) TEX PAINT : Sandex Matt
G) WOOD PRIMER : Shalimar Asian, Jenson, Nicholoson,
Goodlas Nerolac,(Bombay Paints) Brigh &
Co. Omega Mercury Paints.
H) METAL REDOXIDE PRIMER : Shalimar Asian, Jenson, Nicholoson,
Goodlass Nerolac, (Bombay Paints) Bright
&Co., Omega Mercury Paints.
I) ALUMINIUM PAINTS : Shalimar, Jenson, Nicholoson, Goodlas
Nerolac, (Bombay Paints) bright & Co.,
Omega Mercury Paints.
J) ANTI CORROSIVE : British Paints, Shalimar, Asian, Jenson,
Nicholson (Bombay Paints) Bright & Co.,
Omega Mercury Paints.
K) WOOD PRESERVATIVES : British Paint, Noble Paints, Varshish Co.Pvt
Ltd.
L) FIRE RETARDING PAINTS : Fyretard (M/s. Noble Paints, Varshish Co.
Pvt. Ltd.)
37. WATERPROOFING COMPOUND : ‘Impermow’ ‘Accoprooff’ ‘Sicca’ or any
other approved brand name.
38. ANTI TERMITE TREATMENT : As specified by agency and approved by
E.E. NMMC.
39. BITUMINOUS PAINT : ‘Shalimar Tar Products’
40. LAMINATIONS FOR THE DOORS : Veenar national or as approved by
Executive Engineer, NMMC.
41. FORM WORK SHUTTERING : Plastic coated/marine ply for slabs, beams,
columns steel plates/ply for slabs, beams.
42. READY MIX NEERU : ‘MOOR’ brand of equivalent
43. PLATICISERS : ‘KRISHNA PRODUCTS’ or as approved
by E.E, N.M.M.C.
44. C.P. FITTING : Metro or other approved by Executive
Engineer, NMMC.
45. SOIL TREATMENT AGENCIES : Pest Control Indial Pvt. Ltd.,
Pest Control Corporation\, Pil Pvt.Ltd., B.
Kailkushrao Co.
Signature of Tenderer No. of Corrections Signature of NMMC Official
152
Pest control M.Walsha, Pestoo
Modern Services, Paraggon,
Pesticides, Pest check service
Elite Corporation Asian Pesti
Cides Chema Fume Pvt. Ltd.
Super Pesticides Unique
Pesticides Services.
46. SANITORYWARES
(SOIL PANS, W.H BASIN ETC.)
: Hindustan, II & R.Johnson, Neycer, Patty
ware.
47. PIPES
A) C.I.RAIN WATERSOIL & WATER
PIPES
: T.O. Suleha, I.I.T.C., Kateawal I.S.P
(Confroming to I.S. 123 for rain wallet
pipes and the I.S. 1729 and 3889 for soil
and waster water pipes) P.M. Pvt. Help.
I.S.I.
B) S.W.PIPES : Navroji Vakil, khanapura, Girco Kashmira,
Burn & Co. Perfect Post teris, Orind ,
Sonya.
C) R.C.C PIPES : Indian Hume Pipe Co-primer, Shreeji Spun
Prestress Construction Co., Pipes, N.P.2
Class.
F) G.I. WATER PIPES AND FITTINGS : Ambika Zenith as per I.S.I standard to be
approved by Engineer, N.M.M.C.
Navi Mumbai Municipal Corporation.
Name of Work :- Providing and fixing portable container type Community Toilet with Bio-Digester Technology at Ishwar Nagar near
Mannubhai Maidan (Female) in Zone No. 4 (North) Digha Ward.
Tender Notice No. NMMC/Dy. Comm. (SMA)/ 2 ( 12 ) / 2016-2017
SCHEDULE ‘B’
Quantity Description of Item Specification Rate in Rs. Unit Amount in
Rs.
To be quoted by Tenderer
Percent below /
above the
Estimated rates
entered in col. 4
Amount
quoted by
Tenderer
1. 2. 3. 4. 5. 6. 7. 8.
37.50 Item No. 1 :- Excavation for foundation in Soft
rock including removing the excavated materials
upto a distance of 50 meters beyond the building
area & stacking and spreading as directed
dewatering preparing the bed for the foundation
and necessary back filling, ramming, watering
including shorting and strutting etc. complete. Lift
upto 1.50 meters
Bd.A.1-6, Page
No.13
451.50 Cu. M. 16931.25
26.25 Item No. 2 :- Excavation for foundation in Hard
rock chiseled and wedged or line drilled
including removing the excavated materials upto a
distance of 50 meters beyond the building area &
stacking and spreading as directed dewatering
preparing the bed for the foundation and necessary
back filling, ramming, watering including shorting
and strutting etc. complete.
Lift upto 1.50 meters
Bd.A.1-6, Page
No.13
943.95 Cu. M. 24778.68
22.88 Item No. 3 :- Providing dry trap/ granite/
quartzite/ gneiss, rubble stone soling in 15 cm to
20 cm thick layers including hand packing and
compacting, royalty charges etc. complete
Bd.A.12
Page No. 19
997.50 Cu. M. 22822.80
1. 2. 3. 4. 5. 6. 7. 8.
12.05 Item No. 4 :- Providing and casting in situ cement
concrete 1:2:4 of trap / granite / quartzite / gneiss
metal for foundation & bedding including
centering, formwork, compacting, roughening
them if special finish is to be providing and curing
and finishing if required etc. complete. Without
formwork with SCADA with fully automatic
micro processor based PLC with SCADA enabled
reversible Drum Type mixer.
Bd.E.2, Page
No.288 and B-
7, Page No.70
5276.25 Cu. M. 63578.81
1.00 Item No. 5 :- Providing and installing G.I.
container type 10 seated community toilet block (20’ x
8’ x 8.50’ feet) (size 6.10 m length x 2.45 m width x 2.60
m height) including ceramic tiles dado & flooring with SS 310 grade IWC & EWC as required including
electrification etc. as per special condition and special
specification of the contract as directed by the
Engineer-in-charge etc. complete.
As directed by
Engineer-In-
Charge.
790000.00 No. 790000.00
15.00
Item No. 6 : providing and constructing Brick
Masonry Inspection chamber 90 cm x 45 cm x 90 cm
size including 1:4:8 cement concrete foundation 1:2:4
cement concrete channel half round G.S.W. pipes, Brick Masonry, plastering from inside and airtight
R.C.C. Cover with frame fixing in cement concrete
etc. complete.
Bd.V-43 Page
No. 626 5420.10 No. 81301.50
25.00
Item No. 7 : Providing and supplying in standard lengths
Polyethylene Pipes (H.D.P.E. pipes), confirming to IS 4984 /14151 / 12786 / 13488 with necessary jointing
aterial like mechanical connector i. e. thread / insert
joint / quick release coupler joint / compression fitting
joint or flanged joint, including all local & central
taxes, transportation and fright charges inspection
charges, loading / unloading charges, conveyance to
the departmental stores / site & stacking the same in closed shade duly protecting from sunrays & rains, etc.
complete. PE-100 – 6 Kg./Sq.cm. – 200 mm dia.
As directed by
Engineer-In-
Charge.
916.65 RMT 22916.25
1. 2. 3. 4. 5. 6. 7. 8.
25.00
Item No. 8 :- Lowering, Laying and Jointing H.
D. P. E. pipes by heating to the ends of pipes with
the help of tefflon coated electric mirror / heater to
the required temperature and then pressing the
ends together against each other, to form a
monolithic & leak proof joint by thermosetting
process. The pressing may be required to be done
with Jacks/ Hydraulic Jacks/Butt fusion machine
etc. complete with all materials labours as directed
by Engineer - in - charge, including, given
satisfactory hydraulic test. 200 mm dia.
As directed by
Engineer-in-
charge
111.30 RMT 2782.50
60.00
Item No. 9 :- Providing and laying on
walls/ceiling/floors (Heavy Type) 20 mm
diameter approved Galvanized Iron pipe having
embossed ISI mark on it, Jindal / Rata / Zenith or
equivalent make of required diameter and weight
1.953 Kg per RMT with screwed socket joints
necessary galvanized iron fitting such socked back
nut elbows, bends, tees, reducers, enlargers, plugs,
clamps etc. including removing good to the
demolished portion primer of anticorrosive paint
in two coats complete.
Bd.V.-5 Page
No.596 388.50 RMT 23310.00
1.00
Item No. 10:- Providing and fixing 20 mm dia.
water meter with non-return valve including
strainer, sockets/ union nut including water meter
box making locking arrangement and lock.
[Without chamber]
Bd.V.6 & 7.
Page No.553 2852.85 No. 2852.85
5.70
Item No.11:- Providing Second Class Burnt Brick
masonry with conventional/I.S. type bricks in
cement mortar 1:6 in superstructure, including
striking joints, racking out joints, watering and
scaffolding complete.
Bd.G.5 Page
No.268 5233.20 Cu.M. 29829.24
1. 2. 3. 4. 5. 6. 7. 8.
7.50
Item No. 12 :- Providing Second Class Burnt
Brick masonry with conventional / I.S. type bricks
in cement mortar 1:4 in half brick thick wall
including mild steel longitudinal reinforcement of
2 bars of 6mm diameter / 2 hoop iron strips 25mm
x 1.6 mm painted with anticorrosive paint at every
third course properly bent and bonded at ends,
scaffolding, racking out joints and watering
complete.
Bd.G.7 Page
No.269 708.75 Sq. M. 5315.62
54.44
Item No. 13 :- Providing sand faced plaster
externally cement mortar using approved screened
sand, in all positions, including providing base
coat of 15 mm thick in cement mortar 1:4 mixing
approved water proofing compound at 1 kg per
cement curing the same for not less than 2 days
and keeping the surface of the base coat rough to
receive the sand faced treatment 6to 8 mm thick in
cement mortar 1:4 and finishing the surface by
taking out grains and curing for fourteen days
scaffolding etc. Complete.
Bd.L.7 Page
No.368 431.55 Sq. M. 23493.58
25.16
Item No. 14 :- Providing and laying ceramic tiles
of Somani/RAK/Kajaria / Nitco /Asian or
equivalent make of first quality ,having size 30
cm. x 30 cm. for dado and skirting in required
position with readymade adhesive mortar of
approved quality on plaster of 1:3 cement mortar
including joint filling with white/ colour cement
slurry cleaning curing complete.
BdM-13 Page
No. 389 1012.20 Sq. M. 25466.95
1. 2. 3. 4. 5. 6. 7. 8.
50.00
Item No. 15 :- Providing and laying precast
polished chequered colour cement tiles of size 20
x 32 and 20 mm thick for treads and riser of steps
and staircase with nosing of treads moulded as per
drawing or as directed on bed of 1:4 cement
mortar including neat cement float, filling joints
with cement slurry mixed with approved shade of
pigment to match the colour of tiles, curing,
polishing and cleaning complete.
BdM-33 B
Page No. 397 833.70 Sq. M. 41685.00
4000.00
Item No. 16 :- Providing and fixing H.D.P
container Sintex or equivalent make conforming
to 15. one piece moulded water tank made out of
high density polythyler and built corrugation
including of delivery up to destination hoisting
and fixing of accessories such as inlet, outlet
overflow of all tanks capacity above 1000 to
20,000 liters
As directed by
Engineer-In-
Charge.
9.45 Liter 37800.00
1.00
Item No. 17:- MSEB electrical meter etc.
complete.
As directed by
Engineer-In-
Charge.
4050.00 Job work 4050.00
60.00
Item No. 18 :- Supplying and erecting 2 core 2.5
mm armoured cable etc. complete.
As directed by
Engineer-In-
Charge
145.00 R.M.T. 8700.00
1. 2. 3. 4. 5. 6. 7. 8.
1.00
Item No. 19 :- Providing and fixing DRDO
Approved bio-digester tank including, supplying,
transportation, installation & commissioning along
with necessary fixing polygrass matt of 12mm thik
and 10cm x 8mm size mess of S.S. 310 grade
fasteners of 160mm dia PVC BIS marked
bends/pipes/fitting & fixtures ..etc of specified
size and dimension as per side condition &
construction of brick masonary septic tank in cm
1:4 rendering inside out with cm 1:3 and RCC slab
top covered as per the drawing and as directed by
engineer for 10 seated toilet.etc completed.
As directed by
Engineer-In-
Charge
455481.00 No. 455481.00
34.93
Item No. 20 :- Disposal of excavated materials
upto a lead of 10.00 km.....etc complete
As directed by
Engineer-In-
Charge
326.48 Cu.M. 11403.94
Total Rs : 1694499.97
Says Rs : 16,94,500.00
Total -
(Contractors Quoted percentage (+ / -)-
(In Words -------------------------------------------------------)
Quoted Amount Rs. –
(In Words ------------------------------------------------------
Signature of Tenderer No. of Corrections Signature of Dy. Commissioner (SMA)