Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program...

16
Suttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, [email protected]

Transcript of Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program...

Page 1: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

Suttons Bay Stormwater Project

Sarah U’RenProgram DirectorThe Watershed Center Grand Traverse Bay231-935-1514, [email protected]

Page 2: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

Project Overview:

Process:• Used LID/green infrastructure concept - Reduce runoff before end-of-pipe• Installation completed Fall 2013

Public Beach

Public Beach

Issues:• Three main storm drains outlet to Suttons Bay: Grove, Madison, Broadway Street Drains• Bacterial contamination of nearshore waters (at South Shore Park, possible at Marina Park)• Public health risk

$987,000 grant

Page 3: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

Infiltration TrenchesRain Gardens

Installed System:

Project Engineer:

• High Infiltration Rates:� 12 – 20+ in/hr

• Increase infiltration and reduce amount of runoff making it to pipe outlets:

� Rain Gardens

� Underground Infiltration Trenches

� Combine 2 outfalls and redirect to wetland outlet

• Designed to capture all but 2.5% of storm events (infiltrating 97.5 % percent of storm events)

Page 4: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

BMP System: Rain Gardens

Treatment Steps:1. Runoff enters garden, fills depression,

and infiltrates naturally to ground2. Excess water spills into the storm

system inlet3. Will eventually make its way to

infiltration trench (discussed later)

Southwest corner of Adams St and St.Joseph Ave (M-22)

Southwest corner of St. Mary’s Ave and Broadway Ave

18 installed in residential areas in Village

Page 5: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

Northwest corner St. Mary’s and Broadway Ave

BMP System: Installation of rain gardens (before, during, and after)

Page 6: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

Planned BMP System: Installation of rain gardens (before and after)

Southwest corner Madison Ave and M-22

Page 7: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

Educational sign at corner of M22 and Adams St.

Planned BMP System: Educational Rain Garden Signs

Page 8: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

Where:• Alleys: Broadway-Madison Ave,

Madison-Jefferson Ave• Front Street: Broadway-Jefferson,

Grove-Adams Street

BMP System: Infiltration Trenches

About 3,612 feet of infiltration trench installed

~nearly ¾ mile

Page 9: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

Front Street (between Boone’s Restaurant and Inland Seas Education Association)

BMP System: Installation of Infiltration Trenches

Page 10: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

Planned BMP System: Installation of Infiltration Trenches

Above: Trench Installation – note gravel bed and size of tubesRight: Oil/grit separator

Page 11: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

BMP System: Wetland Treatment• Madison outlet abandoned and redirected to wetland treatment basin between marina

and south docks, overflow to existing wetland• Most flow to Broadway line into infiltration trench, overflow split between current outlet

and wetland basin

X

New drain outlet at the end of Madison adjacent to existing wetland

Page 12: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

Project Costs

EPA GLRI Grant - $987,000

Above: oil/grit separator and infiltration trench installation in alley

Left: Rain garden (Adams/M22) in June 2015

• Engineering - $153,000• Rain Gardens - $86,000 (~ $4,700 ea)• Construction (trenches, wetland outlet) - $703,000• Other (TWC staff, WQ monitoring, Signage, Federal

Audit) - $45,000

Page 13: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

General Observations – First and Second Years

• Rain Gardens� Watch closely the first few weeks, note

where water is coming in and look for erosion

� Mulch will float until a mat forms, some will be transported into pipe

� Clean storm inlets regularly, leaves will clog

� Rocks will be helpful around inlets to rain garden and storm drains

� Spring clean-up necessary –blow/rake out excess sand, grit, and leaves

� Public prefers rain gardens with curbing

� Instituted “Friends of the Rain Gardens” group in 2015 to help take care of gardens over next few years

Above: Note floating mulch, gullies in newly planted gardens

Left: Mulch and leaves blocking overflow inlet to drain system

Page 14: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

Above and Left: Village of Suttons Bay Public Works employees clean out oil/grit separators early Winter (after heavy Fall rains)

• Infiltration Trenches� Oil grit separators must be

cleaned periodically

� Trenches must be power washed and vacuumed out at least yearly

General Observations – First and Second Years

Page 15: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

Grove Street Drain

Visible plume in swimming area at Marina Park Beach caused by outflow from Grove Street Drain Outlet after rain event

The plume is GONE after rain events!!

Page 16: Suttons Bay Stormwater Project - MichiganSuttons Bay Stormwater Project Sarah U’Ren Program Director The Watershed Center Grand Traverse Bay 231-935-1514, suren@gtbay.org

Questions?

Sarah U’RenProgram DirectorThe Watershed Center Grand Traverse Bay231-935-1514, [email protected]